WEEKLY PROJECT PROGRESS REPORT
PROJECT TITLE :
SUMMARY PHYSICAL PROGRESS REPORT
DescriptionPrevious
09/05/2016 Schedule Progress 30.78%
Actual Progress 19.66%
Ahead / Delay ( % ) -11.13%
Ahead / Delay ( Day ) -45
Date of Completion ( Contract ) 12/18/2016
Estimated Date of Completion 2/1/2017
MANPOWER AT SITE SITE ACTIVITY
Activities
1ST FLOOR
15 Staircase
ROOF
19 Roof Beam
20 RC Flat Roof Slab
21 Roof Column
22 Upper Roof Beam
23 Roof Truss
Building Work
25 Brickwall
26 Metal Beam
27 Timber Door Frame & Alumn. Frame
M & E Services
WEATHER REPORT 29 Electrical Wiring Work
30 Photovoltaic System
31 Security Alarm & CCTV System
32 Smarthome System
33 Air Cond & Mech. Ventilation
34 Central Vacuum System
35 Lift System Installation
FINISHING WORK
49 Plumbing/Sanitary Fittings
50 Sewerage piping, manhole and Rain Water Sy
56 Koi pond / Swimming Pool System Installation
FROM : 09/05/2016 - 16/05/2016
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
5/9/20165/10/20165/11/20165/12/20165/13/20165/14/20165/16/2016
17 17 17
13
8 8 8
Clear; 36%
Cloudy; 21%Slight Rain; 7%
Heavy Rain; 36%
NOTE :
- 1st floor brickworks started at Guest Room, Guest Bath, Bedroom 3, Bath 3, wet kitchen, pantry, Dry Kitchen, Dining Room- All concreting works for structure are completed. The final concreting works done on the 11/05/2016- External fencing work has started.
PREPARED BY : VERIFIED BY :
ABDUL BASIT BIN ABD NASIR
Clear; 36%
Cloudy; 21%Slight Rain; 7%
Heavy Rain; 36%
WEEKLY PROJECT PROGRESS REPORT
FINANCIAL STATEMENT
PROJECT TITLE : Contract Sum RM3,578,347.29
Piling
Variation Order
PC Sum
Revised Contract Sum
SUMMARY PHYSICAL PROGRESS REPORTCurrent
16/05/201633.25%
20.04%
-13.21%
-54
12/18/2016
2/10/2017
SITE ACTIVITYProgress
RemarksActual %Last Week This Week
100% 0% 0% No progress
100% 100% 100% removing sides fwk
100% 100% 100% removing sides fwk
100% 100% 100% removing sides fwk
100% 50% 100% removing sides fwk
100% 0% 0% No progress
100% 55% 55% 1st floor on progress
100% 0% 0% No progress
33% 0% 0% No progress
48% 40% 40% Ducting & conduit
50% 0% 0% No progress
14% 0% 0% No progress
22% 0% 0% No progress
29% 0% 0% No progress
0% 0% 0% No progress
17% 0% 0% No progress
68% 5% 5% No new progress
71% 50% 50% No new progress
33% 0% 0% No progress
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
Scheduled %
- 1st floor brickworks started at Guest Room, Guest Bath, Bedroom 3, Bath 3, wet kitchen, pantry, Dry Kitchen, Dining Room- All concreting works for structure are completed. The final concreting works done on the 11/05/2016
VERIFIED BY :
WEEKLY PROJECT PROGRESS REPORT
FROM : 09/05/2016 - 16/05/2016 PROJECT TITLE :
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
Front Elevation
Side Elevation
Side Elevation
Side Elevation
External Fencing: Cantilever beams construction
WEEKLY PROJECT PROGRESS REPORT
FROM : 09/05/2016 - 16/05/2016 PROJECT TITLE :
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
1st Flr : Dry Kitchen Area1st Flr : Rumpus Room
1st Flr : Guest Room
2nd Flr : Study Room2nd Flr : Pool Side View
1st Flr : External Garden View
2nd Flr : Bedroom 2 ViewRoof Level : Roof Beam & Upper Roof
Beam
WEEKLY PROJECT PROGRESS REPORT
FROM : 09/05/2016 - 16/05/2016 PROJECT TITLE :
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
WEEKLY PROJECT PROGRESS REPORT
FROM : 09/05/2016 - 16/05/2016 PROJECT TITLE :
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO
Front Elevation
Side Elevation
Side Elevation
WEEKLY PROJECT PROGRESS REPORT
FROM : 09/05/2016 - 16/05/2016 PROJECT TITLE :
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO
1st Flr : Dry Kitchen Area
2nd Flr : Study Room
1st Flr : External Garden View
Roof Level : Roof Beam & Upper Roof Beam
WEEKLY PROJECT PROGRESS REPORT
FROM : 09/05/2016 - 16/05/2016 PROJECT TITLE :
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO
Date
5/9/2016 5/9/2016 5/10/2016 5/10/2016 5/11/2016
Clear 1 1 1
Cloudy 1
Slight Rain 1
Heavy Rain
5/9/2016 5/10/2016 5/11/2016 5/12/2016 5/13/2016
Weather Description
Date
5/11/2016 5/12/2016 5/12/2016 5/13/2016 5/13/2016 5/14/2016
1 1
1
1 1 1
5/14/2016 5/15/2016
Clear; 36%
Cloudy; 21%Slight Rain; 7%
Heavy Rain; 36%
DateTotal
5/14/2016 5/16/2016 5/16/2016
5
1 3
1
1 1 5
Clear; 36%
Cloudy; 21%Slight Rain; 7%
Heavy Rain; 36%
Manpower 5/9/2016 5/10/2016 5/11/2016 5/12/2016 5/13/2016
Project Coordinator
Clerk of Work 1 1 1 1 1
Site Engineer
Safety Supervisor
Supervisor 1 1 1 0 0
Surveyor
Operator
Piler
Carpenter 6 6 6 5 5
Concretor
Barbender 1 1 1
General Worker 3 3 3 2 2
Door & Window Frame Inst.
Brick Layer 5 5 5 5 0
Roofer
Roof covering
Pre-Caster
Ceiling Work Inst.
Aluminium Inst.
Electrician
Plumber
Plasterer
Skim coating
G.I.Work Inst.
M.S.Work Inst.
Floor Screeder
Tiler
Drain Layer
Painter
Fume Cupboard Installer
Gas installer
Sprinkler System Installer
Airconditioning Workers
Emergency Shower Installer
Total Manpower 17 17 17 13 8
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH
PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
5/14/2016 5/16/2016
1 1
0 0
5 5
2 2
0 0
8 8
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH
PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
3/30/2016 4/13/2016 4/18/2016Scheduled Progress 17.16% 18.14%Actual Progress 15.45% 16.39%
3/30/2016 4/6/2016 4/13/20160.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
35.00%
40.00%
45.00%
50.00%
17.16% 18.14%
15.45% 16.39%
Project Performance From January 2012
Scheduled Progress
Actual Progress
% Progress
3/30/2016 4/6/2016 4/13/20160.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
35.00%
40.00%
45.00%
50.00%
17.16% 18.14%
15.45% 16.39%
Project Performance From January 2012
Scheduled Progress
Actual Progress
% Progress
PROPOSED WORK PROGRAMME (Revision # 5) - 4th May 2016CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 ( PT 32614 ), NO. 15, JALAN PJU 3/12, MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING, NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
COMMENCEMENT DATE : 16/01/2015 COMPLETION DATE : 15/04/2016
Description
May-15 Jun-15
1 8 18 25 1 8 15 22
Preliminaries
Site Mobilization
Site Clearing
Site Survey
Site Office/Store
Signboard & Hoading
Piling & Earthwork
Setting Out
Piling Work
Site Mobilization / Building Material Order
Earthwork
Ground Floor
Footing/Stump
Ground Beam
* Delayed due to Changes Work
Alteration to Existing Ground Beam, Lift Pit
and underground sewerage pipe
Anti Termite
Ground Floor Slab
Ground Floor Column / Lift Shaft Structure / RC wall
Sub-basement Compartment for Genset and Bal. tank
Koi Pond, Balancing Tank & Pump Room
1 st Floor
1sr Floor Beam
1st Floor Slab
1st Floor Column / Lift Shaft Structure
Staircase
Second Floor
Second Floor Beam / Swimming Pool Structure
Second Floor Slab
Second Floor Column / Lift Shaft Structure
Roof
Roof Beam
RC Flat Roof Slab
Roof Column
Upper Roof Beam
Roof Truss
Roof Covering / Sky Light Cover
Building Work
Brickwall
Metal I-beam
Timber Door Frame & Alumn. Frame
Plastering
M&E Services
Electrical Wiring Work
Photovoltaic System
Security Alarm & CCTV System
Smarthome System
Air Cond & Mech. Ventilation
Central Vacuum System
Lift System Installation
Finishing Work
Install Alum. Door, Window Panel and Fix Glass
Internal Wall and Swimming Pool Finishes/Tiles/Stone/Mosaic
Internal Floor Finishes
Internal ceiling Finishes/Roof EaveTimber Ceiling
Internal Skim coat, External and Internal Painting Work
Metal Grille & Screen
Metal Handrail / Glass Handrail Railing
Metal Spiral Staircase
Timber Door Leaf
Timber Skirting and Architrave
External Wall Timber Cladding
Timber Varnishing Work and R.C Feature Coating
Timber Flooring and Staircase Finishes
Plumbing/Sanitary Fittings Installation
Sewage Piping, Manhole and Rain Water System
R.C Ramp, Dry Yard, Fencing Wall, Main and Side Gate
External Wall Finishes
External Floor Finishes and Koi Pond Finishes
Timber Decking Koi Pond and Pump Room
Lighting and Electrical Work Installation
Koi pond / Swimming Pool System Installation
Built-in Furniture and ID Works
Turfing / Lanscape Work
Touch-up and Cleaning
Testing, Commissioning and Hand Over
Note: Otherwise indicated, this revised program is based on the amended Architectural Drawings dated 23 Sept 15, Engineer Drawings dated 16 Oct 15 and Interior Design Drawings dated 2 Nov 15. Any amendment to the above drawings or additional items in future not shows on the drawings are not taking consideration in this program.
PROPOSED WORK PROGRAMME (Revision # 5) - 4th May 2016CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 ( PT 32614 ), NO. 15, JALAN PJU 3/12, MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING, NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
COMMENCEMENT DATE : 16/01/2015 COMPLETION DATE : 15/04/2016
Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15
29 6 13 20 27 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16
CHANGES ON DESIGN (FROM RC TO STEEL STRUCTURE)
Note: Otherwise indicated, this revised program is based on the amended Architectural Drawings dated 23 Sept 15, Engineer Drawings dated 16 Oct 15 and Interior Design Drawings dated 2 Nov 15. Any amendment to the above drawings or additional items in future not shows on the drawings are not taking consideration in this program.
PROPOSED WORK PROGRAMME (Revision # 5) - 4th May 2016CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 ( PT 32614 ), NO. 15, JALAN PJU 3/12, MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING, NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
COMMENCEMENT DATE : 16/01/2015 COMPLETION DATE : 15/04/2016 REVISED COMMENCEMENT DATE: 18/05/15 REVISED COMPLETION DATE: 10/12/16
Nov-15 Dec-15 Jan-16 Feb-16
23 30 7 14 21 28 4 11 18 25 1 8 15 22 29
16.67% 33.33% 50.0%
CHANGES ON DESIGN (FROM RC TO STEEL STRUCTURE)
20.00% 40.0% 60.0% 80.0%
33.33%
Change of skirting design and construction method
Note: Otherwise indicated, this revised program is based on the amended Architectural Drawings dated 23 Sept 15, Engineer Drawings dated 16 Oct 15 and Interior Design Drawings dated 2 Nov 15. Any amendment to the above drawings or additional items in future not shows on the drawings are not taking consideration in this program.
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 ( PT 32614 ), NO. 15, JALAN PJU 3/12, MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING, NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
REVISED COMMENCEMENT DATE: 18/05/15 REVISED COMPLETION DATE: 10/12/16
Mar-16 Apr-16 May-16
7 14 21 28 4 11 18 25 2 9 16
66.67% 83.33% 100.00%
100.0%
66.7% 100.0%
50.00% 100.0%
50.00% 100.0%
50.00% 100.0%
50.00% 100.0%
50.00% 100.0%
25.00% 50.0% 75.0% 100.0%
11.11% 22.2% 33.3%
11.11% 22.2% 33.3% 44.4% 55.6% 66.7% 77.8% 88.9% 100.0%
20.00% 40.0% 60.0% 80.0% 100.0%
16.67% 33.3%
Change of skirting design and construction method
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 ( PT 32614 ), NO. 15, JALAN PJU 3/12, MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING, NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
May-16 Schedule Actual Ahead/(Behind) Overall week Week Lapsed Over All %23 30
100% 100% 0% 2 2 0.49% 0.49%
100% 100% 0% 3 3 0.74% 0.74%
100% 100% 0% 3 3 0.74% 0.74%
100% 100% 0% 4 9 0.99% 0.99%
100% 100% 0% 3 2 0.74% 0.74%
100% 100% 0% 1 1 0.25% 0.25%
100% 100% 0% 2 3 0.49% 0.49%
100% 100% 0% 3 3 0.74% 0.74%
100% 100% 0% 5 5 1.23% 1.23%
100% 100% 0% 3 3 0.74% 0.74%
100% 100% 0% 4 4 0.99% 0.99%
100% 100% 0% 2 3 0.49% 0.49%
100% 100% 0% 3 2 0.74% 0.74%
0% 0% 0% 6 0 1.48% 0.00%
100% 100% 0% 5 6 1.23% 1.23%
100% 100% 0% 3 4 0.74% 0.74%
100% 100% 0% 2 2 0.49% 0.49%
100% 90% -10% 2 4 0.49% 0.49%
100% 90% -10% 2 2 0.49% 0.49%
100% 50% -50% 2 1 0.49% 0.49%
Schedule (Overall)
100% 50% -50% 2 1 0.49% 0.49%
25% 0% -25% 4 0 0.99% 0.25%
44.4% 55.6% 0% 0% 0% 9 0 2.22% 0.00%
70% 30% -40% 9 7 2.22% 1.55%
0% 0% 0% 5 0 1.23% 0.00%
50.0% 66.7% 0% 0% 0% 6 0 1.48% 0.00%
0% 0% 0% 10 0 2.46% 0.00%
38% 38% 0% 27 11 6.65% 2.53%
0% 0% 0% 6 0 1.48% 0.00%
0% 0% 0% 14 0 3.45% 0.00%
0% 0% 0% 9 0 2.22% 0.00%
0% 0% 0% 7 0 1.72% 0.00%
0% 0% 0% 4 0 0.99% 0.00%
0% 0% 0% 6 0 1.48% 0.00%
0% 0% 0% 8 0 1.97% 0.00%
0% 0% 0% 11 0 2.71% 0.00%
0% 0% 0% 10 0 2.46% 0.00%
0% 0% 0% 11 0 2.71% 0.00%
0% 0% 0% 17 0 4.19% 0.00%
0% 0% 0% 8 0 1.97% 0.00%
0% 0% 0% 16 0 3.94% 0.00%
0% 0% 0% 5 0 1.23% 0.00%
0% 0% 0% 4 0 0.99% 0.00%
0% 0% 0% 3 0 0.74% 0.00%
0% 0% 0% 6 0 1.48% 0.00%
0% 0% 0% 11 0 2.71% 0.00%
0% 0% 0% 9 0 2.22% 0.00%
45% 5% -40% 22 1 5.42% 2.44%
60% 50% -10% 17 7 4.19% 2.51%
0% 0% 0% 11 0 2.71% 0.00%
0% 0% 0% 10 0 2.46% 0.00%
0% 0% 0% 6 0 1.48% 0.00%
0% 0% 0% 5 0 1.23% 0.00%
0% 0% 0% 5 0 1.23% 0.00%
0% 0% 0% 9 0 2.22% 0.00%
0% 0% 0% 15 0 3.69% 0.00%
0% 0% 0% 4 0 0.99% 0.00%
0% 0% 0% 3 0 0.74% 0.00%
0% 0% 0% 2 0 0.49% 0.00%
406 89 100.00% 23.07%
Proposed
Actual
Ahead / Behi
Actual W/Done
0.49%
0.74%
0.74%
0.99%
0.74%
0.25%
0.49%
0.74%
1.23%
0.74%
0.99%
0.49%
0.74%
0.00%
1.23%
0.74%
0.49%
0.44%
0.44%
0.25%
0.25%
0.00%
0.00%
0.67%
0.00%
0.00%
0.00%
2.53%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.27%
2.09%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
18.76%
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
WORK PROGRAM AS PER REVISED ON 18 APRIL 2016
No. Description May-15 Jun-15
1 8 18 25 1 8 15
Preliminaries
A Site Mobilization
B Site Clearing
C Site Survey
D Site Office/Store
E Signboard & Hoading
Piling & Earthwork
F Setting Out
G Piling Work
1 Site Mobilization / Building Material Order
2 Earthwork
Ground Floor
3 Footing/Stump
4 Ground Beam
* Delayed due to Changes Work
5 Alteration to Existing Ground Beam, Lift Pit
and underground sewerage pipe
6 Anti Termite
7 Ground Floor Slab
8 Ground Floor Column / Lift Shaft Structure / RC wall
10 Sub-basement Compartment for Genset and Bal. tank
11 Koi Pond, Balancing Tank & Pump Room
1 st Floor
12 1sr Floor Beam
13 1st Floor Slab
14 1st Floor Column / Lift Shaft Structure
15 Staircase
Second Floor
16 Second Floor Beam / Swimming Pool Structure
17 Second Floor Slab
18 Second Floor Column / Lift Shaft Structure
Roof
19 Roof Beam
20 RC Flat Roof Slab
21 Roof Column
22 Upper Roof Beam
No. Description May-15 Jun-15
1 8 18 25 1 8 15
23 Roof Truss
24 Roof Covering / Sky Light Cover
Building Work
25 Brickwall
26 Metal I-beam
27 Timber Door Frame & Alumn. Frame
28 Plastering
M&E Services
29 Electrical Wiring Work
30 Photovoltaic System
31 Security Alarm & CCTV System
32 Smarthome System
33 Air Cond & Mech. Ventilation
34 Central Vacuum System
35 Lift System Installation
Finishing Work
36 Install Alum. Door, Window Panel and Fix Glass
37 Internal Wall and Swimming Pool Finishes/Tiles/Stone/Mosaic
38 Internal Floor Finishes
39 Internal ceiling Finishes/Roof EaveTimber Ceiling
40 Internal Skim coat, External and Internal Painting Work
41 Metal Grille & Screen
42 Metal Handrail / Glass Handrail Railing
43 Metal Spiral Staircase
44 Timber Door Leaf
45 Timber Skirting and Architrave
46 External Wall Timber Cladding
47 Timber Varnishing Work and R.C Feature Coating
48 Timber Flooring and Staircase Finishes
49 Plumbing/Sanitary Fittings Installation
No. Description May-15 Jun-15
1 8 18 25 1 8 15
50 Sewage Piping, Manhole and Rain Water System
51 R.C Ramp, Dry Yard, Fencing Wall, Main and Side Gate
52 External Wall Finishes
53 External Floor Finishes and Koi Pond Finishes
54 Timber Decking Koi Pond and Pump Room
55 Lighting and Electrical Work Installation
56 Koi pond / Swimming Pool System Installation
57 Built-in Furniture and ID Works
58 Turfing / Lanscape Work
59 Touch-up and Cleaning
60 Testing, Commissioning and Hand Over
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
WORK PROGRAM AS PER REVISED ON 18 APRIL 2016
Jun-15 Jul-15 Aug-15 Sep-15
22 29 6 13 20 27 3 10 17 24 31 7
Jun-15 Jul-15 Aug-15 Sep-15
22 29 6 13 20 27 3 10 17 24 31 7
3.7% 7.4%
Jun-15 Jul-15 Aug-15 Sep-15
22 29 6 13 20 27 3 10 17 24 31 7
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
WORK PROGRAM AS PER REVISED ON 18 APRIL 2016
Sep-15 Oct-15 Nov-15
14 21 28 5 12 19 26 2 9 16 23 30
Sep-15 Oct-15 Nov-15
14 21 28 5 12 19 26 2 9 16 23 30
4.5% 9.1% 13.6% 18.2%
Sep-15 Oct-15 Nov-15
14 21 28 5 12 19 26 2 9 16 23 30
5.9% 11.8%
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
WORK PROGRAM AS PER REVISED ON 18 APRIL 2016
Dec-15 Jan-16 Feb-16
7 14 21 28 4 11 18 25 1 8 15 22
16.7% 33.3%
CHANGES ON DESIGN (FROM RC TO STEEL STRUCTURE)
20.0% 40.0% 60.0%
Dec-15 Jan-16 Feb-16
7 14 21 28 4 11 18 25 1 8 15 22
11.1% 14.8% 18.5% 22.2%
Change of skirting design and construction method
22.7% 27.3%
Dec-15 Jan-16 Feb-16
7 14 21 28 4 11 18 25 1 8 15 22
17.6% 23.5% 29.4% 35.3% 41.2% 47.1% 52.9%
11.1% 22.2%
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
WORK PROGRAM AS PER REVISED ON 18 APRIL 2016
Feb-16 Mar-16 Apr-16 May-16
29 7 14 21 28 4 11 18 25 2 9 16
50.0% 66.7% 83.3% 100.0%
80.0% 100.0%
33.3% 66.7% 100.0%
50.0% 100.0%
50.0% 100.0%
50.0% 100.0%
50.0% 100.0%
50.0% 100.0%
Feb-16 Mar-16 Apr-16 May-16
29 7 14 21 28 4 11 18 25 2 9 16
25.0% 50.0% 75.0% 100.0%
11.1% 22.2% 33.3%
11.1% 22.2% 33.3% 44.4% 55.6% 66.7% 77.8% 88.9% 100.0%
20.0% 40.0% 60.0% 80.0% 100.0%
16.7% 33.3%
25.9% 29.6% 33.3% 37.0% 40.7% 44.4% 48.1%
16.7% 33.3% 50.0%
7.1% 14.3%
11.1% 22.2%
14.3% 28.6%
25.0% 50.0%
16.7%
Change of skirting design and construction method
31.8% 36.4% 40.9% 45.5% 50.0% 54.5% 59.1% 63.6% 68.2%
Feb-16 Mar-16 Apr-16 May-16
29 7 14 21 28 4 11 18 25 2 9 16
58.8% 64.7% 70.6%
33.3%
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
WORK PROGRAM AS PER REVISED ON 18 APRIL 2016
May-16 Jun-16 Jul-16 Aug-16
23 30 6 13 20 27 4 11 18 25 1 8
May-16 Jun-16 Jul-16 Aug-16
23 30 6 13 20 27 4 11 18 25 1 8
44.4% 55.6% 66.7% 77.8% 88.9% 100.0%
50.0% 66.7% 83.3% 100.0% Timber Door Frame confirmed on 14/4/16, 3 weeks required for manufacture, Alumn no confirmation yet
10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0% Plastering cannot proceed due to concealed smarthome/alarm wiring not confirmed
51.9% 55.6% 59.3% 63.0% 66.7% 70.4% 74.1% 77.8%
21.4% 28.6% No confirmation 35.7% 42.9% 50.0%
33.3% 44.4% 55.6% No confirmation
42.9% 57.1% No confirmation
33.3% 50.0%
12.5% 25.0% 37.5% 50.0% 62.5%
9.1% 18.2% 27.3% 36.4% 45.5% 54.5% 63.6%
10.0% 20.0% 30.0%
9.1% 18.2%
5.9% 11.8% 17.6% 23.5% 29.4% 35.3%
6.3% 12.5% 18.8% 25.0% 31.3% 37.5%
20.0% 40.0% 60.0% 80.0% 100.0%
16.7% 33.3% 50.0% 66.7% 83.3%
9.1% 18.2% 27.3% 36.4% 45.5%
72.7% 77.3% 81.8%
May-16 Jun-16 Jul-16 Aug-16
23 30 6 13 20 27 4 11 18 25 1 8
76.5% 82.4% 88.2%
10.0% 20.0% 30.0%
44.4%
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
WORK PROGRAM AS PER REVISED ON 18 APRIL 2016
Aug-16 Sep-16 Oct-16
15 22 29 5 12 19 26 3 10 17 24 31
Aug-16 Sep-16 Oct-16
15 22 29 5 12 19 26 3 10 17 24 31
Timber Door Frame confirmed on 14/4/16, 3 weeks required for manufacture, Alumn no confirmation yet
Plastering cannot proceed due to concealed smarthome/alarm wiring not confirmed
81.5% 85.2% 88.9% 92.6% 96.3% 100.0%
57.1% 64.3% 71.4%
75.00% 100.0%
75.0% 87.5% 100.0%
72.7% 81.8% 90.9% 100.0%
40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0%
27.3% 36.4% 45.5% 54.5% 63.6% 72.7% 81.8% 90.9% 100.0%
41.2% 47.1% 52.9% 58.8% 64.7% 70.6% 76.5% 82.4% 88.2%
12.5% 25.0% 37.5% 50.0% 62.5% 75.0% 87.5% 100.0%
43.8% 50.0% 56.3% 62.5% 68.8% 75.0% 81.3% 87.5%
25.0% 50.0% 75.0% 100.0%
100.0%
54.5% 63.6% 72.7%
11.1% 22.2% 33.3% 44.4% 55.6% 66.7%
Aug-16 Sep-16 Oct-16
15 22 29 5 12 19 26 3 10 17 24 31
9.1% 18.2% 27.3% 36.4% 45.5% 54.5% 63.6%
40.0% 50.0% 60.0% 70.0% 80.0%
16.7%
20.0% 40.0% 60.0% 80.0%
20.0% 40.0% 60.0%
55.6% 66.7%
6.7% 13.3% 20.0% 26.7% 33.3% 40.0% 46.7% 53.3% 60.0% 66.7% 73.3%
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
WORK PROGRAM AS PER REVISED ON 18 APRIL 2016
Nov-16 Dec-16 Jan-17
7 14 21 28 5 12 19 26 2 9 16 23
Nov-16 Dec-16 Jan-17
7 14 21 28 5 12 19 26 2 9 16 23
66.7% 83.3% 100.0%
78.6% 85.7% 92.9% 100.0%
66.7% 77.8% 88.9% 100.0%
71.4% 85.7% 100.0%
66.67% 83.3% 100.0%
94.1% 100.0%
93.8% 100.0%
81.8% 90.9% 100.0%
77.8% 88.9% 100.0%
86.4% 90.9% 95.5% 100.0%
Nov-16 Dec-16 Jan-17
7 14 21 28 5 12 19 26 2 9 16 23
94.1% 100.0%
72.7% 81.8% 90.9% 100.0%
90.0% 100.0%
33.3% 50.0% 66.7% 83.3% 100.0%
100.0%
80.0% 100.0%
77.8% 88.9% 100.0%
80.0% 86.7% 93.3% 100.0%
25.0% 50.0% 75.0% 100.0%
33.3% 66.7% 100.0%
50.0% 100.0%
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
WORK PROGRAM AS PER REVISED ON 18 APRIL 2016
Jan-17 Schedule Actual Ahead/(Behind) Overall week Week Lapsed Over All %30
0% 0% 0% 0 0.00%
0% 0% 0% 0 0.00%
0% 0% 0% 0 0.00%
0% 0% 0% 0 0.00%
0% 0% 0% 0 0.00%
0% 0% 0% 0 0.00%
0% 0% 0% 0 0.00%
100% 100% 0% 2 2 0.66%
100% 100% 0% 3 3 0.99%
100% 100% 0% 3 3 0.99%
100% 95% -5% 9 5 2.98%
0% 0% 0% 1 0 0.33%
0% 0% 0% 2 0 0.66%
0% 0% 0% 2 0 0.66%
0% 0% 0% 8 0 2.65%
0% 0% 0% 4 0 1.32%
0% 0% 0% 2 0 0.66%
0% 0% 0% 2 0 0.66%
0% 0% 0% 1 0 0.33%
0% 0% 0% 5 0 1.66%
0% 0% 0% 3 0 0.99%
0% 0% 0% 2 0 0.66%
0% 0% 0% 2 0 0.66%
0% 0% 0% 2 0 0.66%
0% 0% 0% 2 0 0.66%
0% 0% 0% 2 0 0.66%
Jan-17 Schedule Actual Ahead/(Behind) Overall week Week Lapsed Over All %30
0% 0% 0% 4 0 1.32%
0% 0% 0% 6 0 1.99%
0% 0% 0% 2 0 0.66%
0% 0% 0% 5 0 1.66%
0% 0% 0% 6 0 1.99%
0% 0% 0% 6 0 1.99%
0% 0% 0% 29 0 9.60%
0% 0% 0% 6 0 1.99%
0% 0% 0% 6 0 1.99%
0% 0% 0% 6 0 1.99%
0% 0% 0% 6 0 1.99%
0% 0% 0% 4 0 1.32%
0% 0% 0% 4 0 1.32%
0% 0% 0% 5 0 1.66%
0% 0% 0% 12 0 3.97%
0% 0% 0% 7 0 2.32%
0% 0% 0% 11 0 3.64%
0% 0% 0% 5 0 1.66%
0% 0% 0% 6 0 1.99%
0% 0% 0% 10 0 3.31%
0% 0% 0% 24 0 7.95%
0% 0% 0% 5 0 1.66%
0% 0% 0% 3 0 0.99%
0% 0% 0% 15 0 4.97%
Jan-17 Schedule Actual Ahead/(Behind) Overall week Week Lapsed Over All %30
0% 0% 0% 6 0 1.99%
0% 0% 0% 6 0 1.99%
0% 0% 0% 6 0 1.99%
0% 0% 0% 11 0 3.64%
0% 0% 0% 3 0 0.99%
0% 0% 0% 11 0 3.64%
0% 0% 0% 5 0 1.66%
0% 0% 0% 4 0 1.32%
302 13 100.00%
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
WORK PROGRAM AS PER REVISED ON 18 APRIL 2016
Propose Schedule Actual
0.00% ###
0.00% ###
0.00% ###
0.00% ###
0.00% ###
0.00% ###
0.00% ###
0.66% ### 100% 100% 0% 0.49% 0.49%
0.99% ### 100% 100% 0% 0.74% 0.74%
0.99% ### 100% 100% 0% 0.74% 0.74%
1.66% ### 100% 100% 0% 0.99% 0.99%
100% 100% 0% 0.74% 0.74%
0.00% ### 100% 100% 0% 0.25% 0.25%
0.00% ### 100% 100% 0% 0.49% 0.49%
0.00% ### 100% 100% 0% 0.74% 0.74%
100% 100% 0% 1.23% 1.23%
0.00% ### 100% 100% 0% 0.74% 0.74%
0.00% ### 100% 100% 0% 0.99% 0.99%
0.00% ### 100% 100% 0% 0.49% 0.49%
0.00% ### 100% 100% 0% 0.74% 0.74%
0.00% ### 100% 0% -100% 1.48% 0.00%
0.00% ### 100% 100% 0% 1.23% 1.23%
0.00% ### 100% 100% 0% 0.74% 0.74%
0.00% ### 100% 100% 0% 0.49% 0.49%
0.00% ### 100% 100% 0% 0.49% 0.49%
0.00% ### 100% 100% 0% 0.49% 0.49%
0.00% ### 100% 100% 0% 0.49% 0.49%
0.00% ### 100% 50% -50% 0.49% 0.25%
Actual W/Done
Ahead/Behind
Schedule (Overall)
Actual W/Done
Propose Schedule Actual
Actual W/Done
Ahead/Behind
Schedule (Overall)
Actual W/Done
0.00% ### 75% 0% -75% 0.74% 0.00%
0.00% ### 11% 0% -11% 0.25% 0.00%
0.00% ### 100% 55% -45% 2.22% 1.22%
0.00% ### 60% 0% -60% 0.74% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 48% 38% -10% 3.20% 2.53%
0.00% ### 50% 0% -50% 0.74% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 50% 0% -50% 0.49% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0% 0% 0% 0.00% 0.00%
0% 0% 0% 0.00% 0.00%
0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 64% 5% -59% 3.45% 0.27%
Propose Schedule Actual
Actual W/Done
Ahead/Behind
Schedule (Overall)
Actual W/Done
71% 50% -21% 2.96% 2.09%
0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 33% 0% -33% 0.74% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
0.00% ### 0% 0% 0% 0.00% 0.00%
4.30% ### 30.78% 19.66%
No. Description
May-16 Schedule Actual16
Preliminaries
A Site Mobilization
B Site Clearing
C Site Survey
D Site Office/Store
E Signboard & Hoading
Piling & Earthwork
F Setting Out
G Piling Work
1 Site Mobilization / Building Material Order 100% 100% 0%
2 Earthwork 100% 100% 0%
Ground Floor
3 Footing/Stump 100% 100% 0%
4 Ground Beam 100% 100% 0%
* Delayed due to Changes Work
5 Alteration to Existing Ground Beam, Lift Pit 100% 100% 0%
and underground sewerage pipe
6 Anti Termite 100% 100% 0%
7 Ground Floor Slab 100% 100% 0%
8 Ground Floor Column / Lift Shaft Structure / RC wall 100% 100% 0%
10 Sub-basement Compartment for Genset and Bal. tank 100% 100% 0%
11 Koi Pond, Balancing Tank & Pump Room 100% 100% 0%
1 st Floor
12 1sr Floor Beam 100% 100% 0%
13 1st Floor Slab 100% 100% 0%
14 1st Floor Column / Lift Shaft Structure 100% 100% 0%
15 Staircase 100% 0% -100%
Second Floor
16 Second Floor Beam / Swimming Pool Structure 100% 100% 0%
17 Second Floor Slab 100% 100% 0%
18 Second Floor Column / Lift Shaft Structure 100% 100% 0%
Roof
19 Roof Beam 100% 100% 0%
20 RC Flat Roof Slab 100% 100% 0%
21 Roof Column 100% 100% 0%
22 Upper Roof Beam 100% 100% 0%
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 ( PT 32614 ), NO. 15, JALAN PJU 3/12, MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING, NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING
YEW TONG
Ahead/(Behind)
No. Description
May-16 Schedule Actual16
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 ( PT 32614 ), NO. 15, JALAN PJU 3/12, MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING, NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING
YEW TONG
Ahead/(Behind)
23 Roof Truss 100% 0% -100%
24 Roof Covering / Sky Light Cover 33% 33% 0% -33%
Building Work
25 Brickwall 100% 55% -45%
26 Metal I-beam 100% 100% 0% -100%
27 Timber Door Frame & Alumn. Frame 33% 33% 0% -33%
28 Plastering 0% 0% 0%
M&E Services
29 Electrical Wiring Work 48% 40% -8%
30 Photovoltaic System 0% 0% 0%
31 Security Alarm & CCTV System 14% 14% 0% -14%
32 Smarthome System 22% 22% 0% -22%
33 Air Cond & Mech. Ventilation 29% 29% 0% -29%
34 Central Vacuum System 0% 0% 0%
35 Lift System Installation 17% 17% 0% -17%
Finishing Work
36 Install Alum. Door, Window Panel and Fix Glass 0% 0% 0%
37 Internal Wall and Swimming Pool Finishes/Tiles/Stone/Mosaic 0% 0% 0%
38 Internal Floor Finishes 0% 0% 0%
39 Internal ceiling Finishes/Roof EaveTimber Ceiling 0% 0% 0%
40 Internal Skim coat, External and Internal Painting Work 0% 0% 0%
41 Metal Grille & Screen 0% 0% 0%
42 Metal Handrail / Glass Handrail Railing 0% 0% 0%
43 Metal Spiral Staircase 0% 0% 0%
44 Timber Door Leaf 0% 0% 0%
45 Timber Skirting and Architrave 0% 0% 0%
46 External Wall Timber Cladding 0% 0% 0%
47 Timber Varnishing Work and R.C Feature Coating 0% 0% 0%
48 Timber Flooring and Staircase Finishes 0% 0% 0%
No. Description
May-16 Schedule Actual16
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 ( PT 32614 ), NO. 15, JALAN PJU 3/12, MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING, NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING
YEW TONG
Ahead/(Behind)
49 Plumbing/Sanitary Fittings Installation 68% 68% 5% -63%
50 Sewage Piping, Manhole and Rain Water System 71% 50% -21%
51 R.C Ramp, Dry Yard, Fencing Wall, Main and Side Gate 0% 0% 0%
52 External Wall Finishes 0% 0% 0%
53 External Floor Finishes and Koi Pond Finishes 0% 0% 0%
54 Timber Decking Koi Pond and Pump Room 0% 0% 0%
55 Lighting and Electrical Work Installation 0% 0% 0%
56 Koi pond / Swimming Pool System Installation 33% 0% -33%
57 Built-in Furniture and ID Works 0% 0% 0%
58 Turfing / Lanscape Work 0% 0% 0%
59 Touch-up and Cleaning 0% 0% 0%
60 Testing, Commissioning and Hand Over 0% 0% 0%
* : Delayed items
Actual W/Done
0.49% 0.49%
0.74% 0.74%
0.74% 0.74%
0.99% 0.99%
0.74% 0.74%
0.25% 0.25%
0.49% 0.49%
0.74% 0.74%
1.23% 1.23%
0.74% 0.74%
0.99% 0.99%
0.49% 0.49%
0.74% 0.74%
1.48% 0.00%
1.23% 1.23%
0.74% 0.74%
0.49% 0.49%
0.49% 0.49%
0.49% 0.49%
0.49% 0.49%
0.49% 0.49%
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 ( PT 32614 ), NO. 15, JALAN PJU 3/12, MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING, NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING
Overall Scheduled
Actual W/Done
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 ( PT 32614 ), NO. 15, JALAN PJU 3/12, MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING, NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING
Overall Scheduled
0.99% 0.00%
0.74% 0.00%
2.22% 1.22%
1.23% 0.00%
0.49% 0.00%
0.00% 0.00%
3.20% 2.66%
0.00% 0.00%
0.49% 0.00%
0.49% 0.00%
0.49% 0.00%
0.00% 0.00%
0.25% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
Actual W/Done
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 ( PT 32614 ), NO. 15, JALAN PJU 3/12, MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING, NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING
Overall Scheduled
3.69% 0.27%
2.96% 2.09%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.74% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
33.25% 20.04%