Week 9 PCIBDM 9.1 Shear
-
Upload
tam-captain -
Category
Documents
-
view
220 -
download
0
Transcript of Week 9 PCIBDM 9.1 Shear
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
1/21
Example 9.1
PCI Bridge Design Manual
Noncomposite Adjacent Box Girder
Simple SpanStandard Specifications
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
2/21
Connection of Beams
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
3/21
Shear
Key
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
4/21
9.1.2 Material Properties (1)
Concrete
f'ci = 4,000 psi = 4.0 ksi
f'c = 5,000 psi = 5.0 ksi
wc = 150 pcf = 0.150 kcf
The AASHTO Standard Specifications require a
pretensioned member to be designed at 5000 psi (6000 psi
at the discretion of the engineer).
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
5/21
9.1.2 Material Properties (2)
Strand
0.5-in., seven wire low relaxation;
fpu = 270 ksi; fpi = 0.75fpu = 202.5 ksi
Es = 28,500 ksiNonprestressed Steel
fsy = 60 ksi
Es = 29,000 ksi
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
6/21
9.1.3 Cross-Section Properties (1)
A = 813 in.2 I = 168,367 in.4
yb = 19.29 in. Sb = 8,728 in.3
yt = 19.71 in. St = 8,542 in.3
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
7/21
9.1.3 Cross-Section Properties (2)
At release
Eci = 33,000 (0.150)1.5 (4.0)1/2
= 3,834 ksi
At 28 days
Ec = 33,000 (0.150)1.5 (5.0)1/2
= 4,287 ksi
Modulus of elasticity is needed for various calculations:
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
8/21
9.1.4.1.1 Dead Loads per Girder
Beam self weight = 0.847 kip/ft
Diaphragm weight = 0.73 kip/diaphragm at pts)
Barrier weight = 0.086 kip/ft
Wearing surface = 0.134 kip/ft
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
9/21
Shear and Moment at h/2
Compute Vci: Vci=0.6(fc)1/2bd+Vd+(ViMcr)/Mmax
Vd = 50.0 kips = shear due to dead loads
VLL+I = 32.7 kips = shear due to live loads
Md = 82.8 ft-kips = moment due to dead loads
MLL+I = 53.2 ft-kips = moment due to live load
Vu = 136.0 kips = factored shear force
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
10/21
Strand Pattern-Midspan (Fig 9.1.5.4-1)
Whats with the 2 at the top?? Discussed later!
Pattern is symmetrical must be or beam bends sideways!
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
11/21
Strand Pattern-Beam End (Fig. 9.1.8.2-1)Debond 7 strands in bottom row for 5 ft.
PATTERN STAYS SYMMETRICAL
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
12/21
DEBONDEDSTRAND
Strand is
covered
with teflonto prevent
bonding.
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
13/21
9.1.11 Shear Design
Members should be designed such thatVu < f(Vc + Vs)
Critical section is h/2 from face of support
Shear forces at this section are given in
Table 9.1.4.2.4-1
In reinforced concrete, ACI and AASHTO use d
from face of support, but in prestressed concrete,d often varies due to debonding and/or harping.
Thus, h/2 is used.
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
14/21
9.1.11 Shear Design
Compute Vci: Vci=0.6(fc)1/2bd+Vd+(ViMcr)/Mmax
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
15/21
9.1.11 Shear Design
Mu = 223.1 ft-kips factored moment
Vmu = 136.0 kips factored shear forceoccurring with the factored moment
Mmax = 140.3 ft-kips = Mu - Md
Vi = 86.0 kips = Vmu - Vd
fpe = Pse/A + (Pseec)/Sbe = eccentricity at h/2 = 13.96 in.
Pse = 24(0.153)(171.6) = 630.1 kips
fpe = 1.783 ksi
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
16/21
fd = Md/Sb = (82.8(12))/8,728 = 0.114 ksi
Mcr= (6(fc)1/2+fpe-fd)Sb =
(((6(5000)1/2)/1000)+1.783-0.114) (8,728/12) =
1,522.5 ft-kips
9.1.11 Shear Design
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
17/21
9.1.11 Shear Design (4)
d = 39.0-5.33 = 33.67 in. > 0.8(h) = 31.20 in.,
therefore d = 33.67 in.
Vci = 0.6(5000)1/2(10)(33.67)+50.0+((86.0(1,522.5))
1000 140.3= 997.5 kips
Is Vci
> minimum Vci
?
minimum Vci= 1.7(fc)1/2bd
= (1.7(5000)1/2)/1000)(10)(33.67) = 40.5 kips
< Vci = 997.5 kips OK
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
18/21
9.1.11 Shear Design
Compute Vcw
Vcw= (3.5(fc)1/2+0.3fpc)bd+Vpfpc = Pse/A = 630.1/813 = 0.775 ksi
Vp = 0 for straight strands
Vcw = (((3.5(5000)1/2
)/1000)+0.3(0.775))(10)(33.67)+0 = 161.6 kips
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
19/21
9.1.11 Shear Design (5)
Vc = 161.6 kips (lesser of Vci and Vcw)
Vu = 136.0 < fVc = 0.9(161.6) = 145.4 kipsSince Vc>Vu the concrete resists the total
shear and shear steel is not required to assist in
resisting Vu. Therefore provide min. reinforcement.
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
20/21
Graph of Vu and concrete shear strengths
0
100
200
300
0 10 20 30 40Length (ft.)
Sheark
phi Vcw
phi Vci
Vu
-
7/29/2019 Week 9 PCIBDM 9.1 Shear
21/21
9.1.11 Shear Design (6)
Minimum shear reinforcement
Av-min= (50bs)/fy = minimum area of webreinforcement
Set s = 12 in.
Av-min = 50(10)(12)60,000
= 0.10 in.2 (per foot)
Maximum spacing = 0.75h = 0.75(39) = 29.25 in.
use 24.0 in.Use #4 at 24 in. spacing in each web
(Av = 0.20 in.2/ft)