Week 8 28_march_2011.v3
-
Upload
teamhd -
Category
Technology
-
view
721 -
download
0
Transcript of Week 8 28_march_2011.v3
Killer Application For NBN (Team HD)
Week 13
Gautam Koul 3067031Renuka Umbarkar 3061872Nadia Almualem 3045389Komal Jondhra 3056416
Modes of Thinking
Nadia
GautamRenukaKomal
Renuka : Project ManagerCo-ordinator -Monitor & Driver
Gautam :Research Manager resource investigator
Nadia : Project Coordinator Implementer & specialist
Komal : Risk managerSupporter & Finisher
Outputs & Outcomes
OUTPUTS
Power journal
Web conferencing-Video conferencing -VoIP
Remote access
Remote support
Application and file sharing
Social Networking
Real time Feeds
OUTCOMES
Provide the ability of working remotely
Reduce travel time & Cost
Statistics
• Total Population - 22,599,875 (2011 estimation)
• Total Population - 19,855,288 (2006 census)
• Employed – 11,433,000
• Unemployed – 604,000
• Ready for Teleworking – 2,270,000
Social Issues Resisting Teleworking
Isolation
Direct monitoringOverall performance
Video conferencing-Leisure talks, status updates -Schedule conference calls-Attending employee meetings
Extensive reports- Weekly report- Number of hours worked tasks completed- Websites visited, Applications used &
Telephone calls made- Performance comparison with peer group
Power Journal-Journal entry addressing work done, questions, arrangements, & updates ETC.
Almost certain
Likely
Unlikely
Low Medium High
Major Project Risks
Competition
Consumer Uptake
Scope
Risk Analysis MatrixLikelihood & Consequence approach
likelihood
Consequence
Cost
WBS ItemNumber
of resources
Duration (Days) Hrs/day Hourly rate
or Cost/UnitWBS Level 1
Total % of Total
Initiation and planning 2 20 8 80 25600 6.59%
Development & Testing 34 45 8 Various 156880 40.44%
Project management 2 67 8 115 123280 31.78%
Hardware 35 500 17500 4.51%
Reserves (20% of total estimate) 64652 16.66%
Total 387912
Note : - Total cost = (323260+64652) = 387912
Time
ClosureFinalise
Idea
Development & Testing M1
ApprovalInitiation
& Planning
Development & Testing M2
Development & Testing M3
Development & Testing M4
Development & Testing M5
Development & Testing M6
Development & Testing M7
A1 = 63B = 6
C= 20
D = 20
E = 20
F = 20
G = 20
H = 20
I= 30
J= 30
K= 25
L= 35
M= 45
N= 45
Note: All the durations are in days. A0 =35 means activity A0 has duration of 35 days Critical path – A0- A-B-G-M and A0-A-B-H-N
Start Discussing different
ideas
A0 = 35