Watkins School Modernization Project Update Community Presentation (May 19, 2015)

13
WATKINS ELEMENTARY SCHOOL MAY 19, 2015 Perkins Eastman DC

Transcript of Watkins School Modernization Project Update Community Presentation (May 19, 2015)

Page 1: Watkins School Modernization Project Update Community Presentation (May 19, 2015)

WAT K I N S E L E M E N TA R Y S C H O O L

M A Y 1 9 , 2 0 1 5 Perkins Eastman DC

Page 2: Watkins School Modernization Project Update Community Presentation (May 19, 2015)

Summer 2015 Schedule• Window Delivery – May 30• Installation begins on 4th Floor

• DPR Programs will not occur this summer

Page 3: Watkins School Modernization Project Update Community Presentation (May 19, 2015)

P R O P O S E D S C H E M AT I C P L A N

Page 4: Watkins School Modernization Project Update Community Presentation (May 19, 2015)

Site Plan

P R O P O S E D S C H E M AT I C P L A N

Page 5: Watkins School Modernization Project Update Community Presentation (May 19, 2015)

Basement & First Floor

P R O P O S E D S C H E M AT I C P L A N

Page 6: Watkins School Modernization Project Update Community Presentation (May 19, 2015)

Entry

P R O P O S E D S C H E M AT I C P L A N

ExistingApprox. 200 sf

(includes security desk)

Proposed563 sf Lobby

182 sf Vestibule 97 sf Security

842 sf total

Existing

Page 7: Watkins School Modernization Project Update Community Presentation (May 19, 2015)

Food Prints Garden

P R O P O S E D S C H E M AT I C P L A N

Existing2,580 sf (inside fence)600 sf (outside fence)

3,180 sf totalProposed

2,250 sf (inside fence)750 sf (Outdoor Gathering)

3,000 sf total

Outdoor Gathering @ 750 sf• Parent Gathering

before/after school• Outdoor classroom for

Food Prints

Page 8: Watkins School Modernization Project Update Community Presentation (May 19, 2015)

Gym & Cafetorium

P R O P O S E D S C H E M AT I C P L A N

Page 9: Watkins School Modernization Project Update Community Presentation (May 19, 2015)

Second Floor

P R O P O S E D S C H E M AT I C P L A N

Page 10: Watkins School Modernization Project Update Community Presentation (May 19, 2015)

Second Floor Electives

P R O P O S E D S C H E M AT I C P L A N

Outdoor Classroom @ +/-800 sfCan be easily accessed from

• Visual Arts• Science

• Food Prints• Commons

Page 11: Watkins School Modernization Project Update Community Presentation (May 19, 2015)

Media Center

P R O P O S E D S C H E M AT I C P L A N

Page 12: Watkins School Modernization Project Update Community Presentation (May 19, 2015)

Third Floor

P R O P O S E D S C H E M AT I C P L A N

Page 13: Watkins School Modernization Project Update Community Presentation (May 19, 2015)

Fourth Floor

P R O P O S E D S C H E M AT I C P L A N