Water Treatment Plant DeZurik Replacement€¦ · Installed: 2 Years Cycles: 24 per day No...

1
KINETROL USA www.kinetrolusa.com Water Treatment Plant DeZurik Replacement Field Tested. Application Driven. A Kinetrol USA Midwest Distributor was called out to a local wastewater treatment plant to look at some old DeZurik cylinder actuators that were always in need of repair. Control features and benefits were presented. It took two years to get them on the spec, but since then the Kinetrol actuators were installed and the customer is extremely pleased with their performance. Installed: 2 Years Cycles: 24 per day No Maintenance To Date Kinetrol USA 1085 Ohio Drive Plano Texas 75093 (972) 447-9443 phone (972) 447-9720 fax [email protected]

Transcript of Water Treatment Plant DeZurik Replacement€¦ · Installed: 2 Years Cycles: 24 per day No...

Page 1: Water Treatment Plant DeZurik Replacement€¦ · Installed: 2 Years Cycles: 24 per day No Maintenance To Date Kinetrol USA 1085 Ohio Drive Plano Texas 75093 (972) 447-9443 phone

KINETROL USA www.kinetrolusa.com

Water Treatment Plant DeZurik Replacement Field Tested. Application Driven.

A Kinetrol USA Midwest Distributor was called out to a local wastewater treatment plant to look at some old DeZurik cylinder actuators that were always in need of repair. Control features and benefits were presented. It took two years to get them on the spec, but since then the Kinetrol actuators were installed and the customer is extremely pleased with their performance.

Installed: 2 Years Cycles: 24 per day No Maintenance To Date

Kinetrol USA 1085 Ohio Drive Plano Texas 75093 (972) 447-9443 phone (972) 447-9720 fax [email protected]