Water Supply Operations enterprise/operational... · SMWSA closed their valve from the ECCV line....

8
Page 1/8 TECHNICAL MEMORANDUM To: Eagle Bend Metro District (EBMD)-Board of Directors From: Mitchell Weldon and Justin Korkus, PE Date: December 11, 2019 Subject: Water Operations Summary for October 2019 CC: Larry Moore-President-EBMD, Denise Denslow-District Manager CliftonLarsonAllen, LLC. Project No.: 0416019.01 This Technical Memorandum provides a summary of the EBMD water operations for the month of October 2019. Water Supply Operations South Well: During the month of October, the South Well operated for 256 hours (10.7 days). The South Well average flow rate in October was 257 gpm A total of 4.01 million gallons (MG) or 4,010 kilogallons (kgal) was delivered to the Heritage Eagle Bend (HEB) golf course irrigation pond. Water levels recovered from 122 to 301 feet above the transducer setting depth, or approximately 179 feet. No unexpected down time was logged. Figure 1 – South Well Drawdown and Recovery (October 2019) 0.0 50.0 100.0 150.0 200.0 250.0 300.0 350.0 Water Above Transducer (ft) South Well Level (Feet)

Transcript of Water Supply Operations enterprise/operational... · SMWSA closed their valve from the ECCV line....

Page 1: Water Supply Operations enterprise/operational... · SMWSA closed their valve from the ECCV line. Aurora opened the meter vault and closed both gate valves. Aurora operators took

Page 1/8

TECHNICAL MEMORANDUM

To: Eagle Bend Metro District (EBMD)-Board of Directors

From: Mitchell Weldon and Justin Korkus, PE

Date: December 11, 2019

Subject: Water Operations Summary for October 2019

CC: Larry Moore-President-EBMD, Denise Denslow-District Manager CliftonLarsonAllen, LLC.

Project No.: 0416019.01

This Technical Memorandum provides a summary of the EBMD water operations for the month of October 2019.

Water Supply Operations

South Well:

During the month of October, the South Well operated for 256 hours (10.7 days).

The South Well average flow rate in October was 257 gpm

A total of 4.01 million gallons (MG) or 4,010 kilogallons (kgal) was delivered to the Heritage Eagle Bend (HEB) golf

course irrigation pond.

Water levels recovered from 122 to 301 feet above the transducer setting depth, or approximately 179 feet.

No unexpected down time was logged.

Figure 1 – South Well Drawdown and Recovery (October 2019)

0.0

50.0

100.0

150.0

200.0

250.0

300.0

350.0

Wa

ter

Ab

ove

Tra

nsd

uce

r (f

t)

South Well Level (Feet)

Page 2: Water Supply Operations enterprise/operational... · SMWSA closed their valve from the ECCV line. Aurora opened the meter vault and closed both gate valves. Aurora operators took

Page 2/8

Figure 2 – South Well Water Production (October 2019)

North Well:

During the month of October, the North Well operated for 251 hours (10.5 days).

The North Well average flow rate in October was 143 gpm.

A total of 2.164 MG or 2,164 kgal was delivered to the Heritage Eagle Bend (HEB) golf course irrigation pond.

Water levels recovered from 115 to 290 feet above the transducer setting depth, or approximately 175 feet.

No unexpected down time was logged.

Figure 3 – North Well Drawdown and Recovery (October 2019)

-50.0

0.0

50.0

100.0

150.0

200.0

250.0

300.0

Flo

wra

te (

GP

M)

South Well Flow Rate (GPM)

0.0

50.0

100.0

150.0

200.0

250.0

300.0

350.0

Wa

ter

Ab

ove

Tra

nsd

uce

r (f

t)

North Well Level (Feet)

Page 3: Water Supply Operations enterprise/operational... · SMWSA closed their valve from the ECCV line. Aurora opened the meter vault and closed both gate valves. Aurora operators took

Page 3/8

Figure 4 – North Well Water Production (October 2019)

ECCV/WISE Waterline:

The ECCV/WISE line was not used to supplement the wells for the irrigation pond this month.

The ECCV Line was winterized on October 9, 2019.

Buchanan Tap:

The Buchanan Tap was not used to supplement the wells for the irrigation pond this month.

The Buchanan Tap was winterized on October 9, 2019.

Field Operations

Date Activity Description

10/2/19 Lamp Rynearson (Justin Korkus and Mitchell Weldon) met on-site for an operations transition

meeting with Denise Denslow, Larry Moore, and Roe Sherbert.

At 3 AM, the pond level transducer showed a large (5-ft) decrease in water level, suggesting a

transducer malfunction.

Lamp Rynearson coordinated with Roe Sherbert to leave the pumps on overnight, and to shut off

the well pumps manually the next morning if the pond was approaching capacity prior to

overflowing.

Lamp Rynearson coordinated with Browns Hill Engineering and Controls (Charles Page) to arrive

October 3, 2019 at 9am to diagnose the issue.

10/3/19 Lamp Rynearson met with Browns Hill (Charles Page) to investigate pond level transducer issues. A

previously disconnected backup transducer was reconnected and switched to be the primary

transducer in control of pump operations. The main transducer within the PVC stilling pipe is

suspected to have malfunctioned.

10/9/19 Lamp Rynearson met with South Metro Water Supply Authority (Matt Grunder) and two Aurora

Water technicians at the ECCV vaults for winterization.

-50.0

0.0

50.0

100.0

150.0

200.0

Flo

w G

PM

Channel: 2 Flow Meter (GPM)

Page 4: Water Supply Operations enterprise/operational... · SMWSA closed their valve from the ECCV line. Aurora opened the meter vault and closed both gate valves. Aurora operators took

Page 4/8

SMWSA closed their valve from the ECCV line. Aurora opened the meter vault and closed both gate

valves. Aurora operators took a final reading (017280) and opened drain valve downstream of both

gate valves. SMWSA left site and opened butterfly valve (BFV) at irrigation pond remotely to drain

ECCV line.

Lamp Rynearson and Aurora proceeded to Buchanan tap. Aurora closed inlet isolation valve to vault

(in street) and took final reading (03435). Heritage Eagle Bend Golf Club (Hector) arrived and

explained that the outlet gate valve from the meter vault was closed and HEB staff had previously

blown out line between this valve and the pond.

Lamp Rynearson inspected the butterfly valve at the ECCV line and called Matt Grunder to close the

valve once the line had drained.

10/18/19 Visited ECCV vaults to meet with Antonio Ramirez, Superintendent on Aurora Raw Water line

project for T. Lowell Construction, in response to 811 locate request. Discussed project schedule

and coordination needs with District.

Pending Activities

November The wells will be shut down for winter.

Diversified Underground to provide locate of ECCV raw water line near the ECCV vaults.

Utility Locates

Lamp Rynearson monitors utility locate requests on behalf of the District for buried utilities owned and operated by

the District. Notifications sent by the Utility Notification Center of Colorado (UNCC) to Lamp Rynearson, are

reviewed, and responded to. During the month of October, Lamp Rynearson responded to 25 utility locate tickets.

No field locates were performed during October. At request of T. Lowell Construction, Diversified Underground will

locate the ECCV raw water line near the ECCV vaults in early November.

Water Production Summary

EBMD’s historical water delivery summary is provided in Table 1 from 2010 through present, and graphically in Figure 5 -

Cumulative Annual Water Deliveries by Month, and Figure 6 - Monthly Water Deliveries (2010-2019). For monthly water

production and billing for 2019, refer to Table 2.

Page 5: Water Supply Operations enterprise/operational... · SMWSA closed their valve from the ECCV line. Aurora opened the meter vault and closed both gate valves. Aurora operators took

Page 5/8

Table 1 – Annual Water Production

Year North Well South Well Buchanan Tap ECCV Line, Aurora Pkwy Tap Total

kgal % kgal % kgal % kgal % kgal

2010

2011

26,564

29,408

33

37

43,702

38,888

54

48

0

0

0

0

10,259

12,273

13

15

80,525

80,569

2012 25,416 28 55,493 61 0 0 10,368 11 91,277

2013 26,223 38 38,791 55 0 0 4,982 7 69,996

2014 18,472 33 33,808 60 0 0 4,036 7 56,316

2015 20,510 30 37,999 57 0 0 8,650 13 67,159

2016 21,569 25 55,478 63 0 0 10,824 12 87,871

2017 21,277 31 33,884 49 0 0 14,097 20 69,258

2018 22,971 28 50,100 62 5,400 7 2,747 3 81,218

2019 22,265 29 45,311 60 3,654 5 4,449 6 75,679

Average

(2010-2018) 23,231 31 43,055 57 5,400 7 8,497 11 75,458

Page 6: Water Supply Operations enterprise/operational... · SMWSA closed their valve from the ECCV line. Aurora opened the meter vault and closed both gate valves. Aurora operators took

Page 6/8

Table 2 – Monthly water production and billing for Eagle Bend Metro District (2019)

Page 7: Water Supply Operations enterprise/operational... · SMWSA closed their valve from the ECCV line. Aurora opened the meter vault and closed both gate valves. Aurora operators took

Page 7/8

Figure 5 – Cumulative Annual Water Deliveries by Month (2010 – 2019)

Page 8: Water Supply Operations enterprise/operational... · SMWSA closed their valve from the ECCV line. Aurora opened the meter vault and closed both gate valves. Aurora operators took

Page 8/8

Figure 6 –Historic Monthly Water Deliveries (2010 – 2019)