Testing Emergency Call Services: 911, Enhanced 911 (E-911 ...
WATER POLLUTION MANAGEMENT FOR SILT DISCHARGE IN LAND TRANSPORT AUTHORITY PROJECT SITES: CASE STUDY...
-
Upload
tth28288969 -
Category
Documents
-
view
14 -
download
0
description
Transcript of WATER POLLUTION MANAGEMENT FOR SILT DISCHARGE IN LAND TRANSPORT AUTHORITY PROJECT SITES: CASE STUDY...
-
WATER POLLUTION MANAGEMENT FOR SILT DISCHARGE
IN LAND TRANSPORT AUTHORITY PROJECT SITES: CASE
STUDY OF DOWNTOWN LINE 2, CONTRACT 911
Jernice Kew Huiling, Executive Engineer (Environmental)
Alex Yip Jui Yong, Deputy Project Manager
Safety Division, Land Transport Authority, Singapore
Downtown Line 2 (Civil Construction Team 1), Land Transport Authority, Singapore
[email protected], [email protected]
ABSTRACT
With the rapid development and transformation of Singapore's urban landscape that boosted the
construction industry over the last decade, water pollution from the construction sites has become a major
concern. Construction projects could cause substantial environmental impacts if effective management
control is not put in place. When top soils are cleared for site preparation works, erosion will occur during
rainy days. The silt bearing runoffs will result in massive sediment pollution in our water catchments such
as the scenic reservoirs and Marina Barrage. Silt turns the waterway turbid, preventing sunlight infiltration
and destroys aquatic life. Not only is marine ecology devastated, the aesthetic beauty of the reservoirs will
be badly affected. Therefore, with the intensive and extensive construction activities currently going on,
effective earth control measures and management are necessary and essential for maintaining the
sustainability of our precious water resources.
Contract 911 (C911) - Design and Construction of Depot for Downtown Line 2 is one of the project with the
largest earthworks and excavation activities. Contract 911 (C911) involved the excavation of about 3.85
millions m3 of earth and with a large site area of 25 ha. It faces greater difficulties in terms of erosion
control as compare to its neighbouring sites along the developing rail transit line. Furthermore, the
existing site terrace (high slope area) stretches from north to south of the entire construction site has also
post greater challenges in controlling effective soil erosion and management. The overall erosion drainage
system, retention ponds, water treatment plants, erosion control measures, etc have to be carefully designed
and assessed. A holistic review of the ECM is thorough and precise. Hence, this paper aims to draw on
C911s unique characteristic as a platform to highlight the importance of controlling silt discharges, foster
greater awareness of our commitment and share our experiences on the challenges faced in the delivery of
our land transport infrastructure projects.
Keywords: Construction; sediment; erosion; land transport; water pollution; silt; water resource
management; road; rail
INTRODUCTION
Singapore, located at the Southern tip of Malaysia
Peninsular, is a country with a total land area of 707.1
m2. Despite being a small island, the Singapore
Government places great emphasis in water resource
management. Via the virtues of early land use
planning, 30% of the land has been allocated as water
catchment areas and the whole island wired up by a
huge network of storm water canals and drains, to
capture as much of its annual 2400mm rainfall as
possible, which eventually is diverted into these
catchment areas or reservoirs for water provision and
portability.
Given the large networks of canals and drains and the
high storm water catchment rate in Singapore, surface
runoffs from the construction sites will find their way
easily to the reservoirs. In addition, with the land
scarcity and large catchment areas, it is no surprise
that sites may be found within 1 or 2 kilometers of
these reservoirs, creating direct impact to the marine
lives and potentially turning water from blue to brown.
For example, Downtown Line 1 and Circle Line, one
of the many railway lines LTA is currently
developing, is located within the basin of one of
Singapores most important and new catchment area
known as the Marina Barrage. Other than the
intention of turning the Barrage into one of
Singapores water sources, there are also plans to
transform the area into a bustling recreational hub for
Proceedings of the World Urban Transit Conference 2010 (WUTC 2010)Copyright 2010 WUTC Organizers :: Published by Research PublishingISBN: 978-981-08-6396-8doi:10.3850/978-981-08-6396-8 P049 149
-
water activities. Economic repercussions will be huge
if the water is allowed to be silted overtime. Hence,
the Land Transport Authority being the largest
developer has a major role to play.
Land Transport Authority (LTA)
LTA is a statutory board under the Ministry of
Transport that spearheads land transport
developments in Singapore which includes roads,
rails (Rail Transit System), pedestrian facilities as
well as regulating vehicular and traffic matters. LTA
has till date developed almost 150km length of MRT
both above and below ground as well as a wide array
and network of expressways, arterial, collector and
local access roads which adds up to more than
3,300km and has currently continued to expand its
rail network system to include Downtown Line 1 and
2.
DOWNTOWN LINE 2 - CONTRACT 911
Contract 911 (C911) is managed by LTAs main
contractor: GS Engineering & Construction Hock
Lian Seng Infrastructure Ltd. Joint Venture (GS-JV-
HLS). It comprises the design, construction and
completion of the Depot and its connecting tunnels
between contract boundary C912. C911 is one of the
projects with the largest earthworks and excavation
activities. It has a land area of about 25 ha and an
estimated volume of 3.85 million m3 of earth to be
excavated.
The proposed Depot for Downtown line (DTL) is
located along Woodlands Road and stretch from the
junction of Kranji Expressway (KJE) to Kwong Hou
Sua Teochew Cemetery opposite of Sungei Kadut
Avenue. The proposed Depot as a self contained
operational unit which will be providing maintenance,
operations and support for the operation of
Downtown Line.
The proposed Depot is located at the northern end of
DTL and is designed to maintain an ultimate fleet of
108x3 car electric trains for operation of services
together with supporting service vehicles.
WATER POLLUTION MANAGEMENT AT
C911
Pre-Construction Stage
As required by Singapores Legislation, C911 GS-JV-
HLS had engaged a Qualified Erosion Control
Professional (QECP) to plan and design a system of
earth control measures (ECM). QECPs are registered
Professional Engineers who has satisfactorily
completed specialized professional course in erosion
and sediment control. The submission would have to
include design calculations and specifications such
that the discharge contains less than 50mg/l of total
suspended solids (TSS), the maximum allowable
legal limit stated in the code of practice. Due to its
sheer size, C911 site was segregated into 4 areas and
the ECM plan was initially developed separately for
each of the area before construction works start. As
work in the Depot progressed with increasing
complexity, the team saw that there was a need to
revise and combine all 4 ECM plans to ensure that the
ECM system remains effective and integrated.
Figure 1: Earth Control Plan
On top of the existing legislations, LTA has
developed internal manual and specifications that sets
the standards and system which are required to
establish during the construction phase they are the
Safety, Health & Environmental Management System
(SHEMS) Manual, and the General Specifications
(GS). The SHEMS Manual provides a guide for LTA
project teams to carry out construction work activities
on-site, with due considerations given to
environmental protection. The GS on the other hand,
stipulates contractors responsibilities and provides
details on the provisions that they must provide, with
some of the requirements being stricter than what is
legally required. For example, the Environmental
Control Officers (ECO) engaged by contractors must
have at least 3 years of practical experience relevant
to ECO scope of works and they must attend
professional courses on erosion control so that they
have required knowledge and expertise to manage silt
runoffs on site. Other effective requirements unique
to LTA will be mentioned in the following section.
150 Proceedings of the World Urban Transit Conference 2010 (WUTC 2010)
-
Construction Stage
Challenges
The concurrent massive excavation work post a great
challenge to the erosion control work. The measures
implemented have to be continuously monitored,
improved, enhanced and relocated. The terrains and
landscape of the entire work site is changing from
time to time. As such, the extensive drainage system
in Area 1 to 4 have to be diverted, adjusted or
relocated from stage to stage.
The nature of the excavation work such as large slope
excavation has again challenged the effectiveness of
the erosion control measure implemented. The runoff
is accelerated and has pick up more erosion before it
is channeled or diverted to the controlled drainage
system.
In addition, the natural location as such higher
platform level over the entire work site than to the
adjacent industrial estate has again constituted a
greater challenge. The design and implemented
erosion control system has to be effective, efficient
and flood protected. No over flow from the erosion
control system from the depot site to the Woodlands
Road and the adjacent industrial estate is allowed
Earth Control Measures on Site
C911 first started off with studies looking into the
feasibility of minimizing the formation of bare
surfaces by opening up the land in phases. Taking
into account the balance between economic
constraints and environmental protection, earthworks
are phased into 2 stages Area 3, 4 and 1 and Area
2. Area 2 (of about 10ha) had started 9 months later.
Another strategy that C911 had adopted is to
prioritize permanent turfing and road works so that
these designated bare slopes are quickly cut to the
required angles and shapes and turfed/paved up as
swiftly as possible.
Figure 2: Permanent Turf Works started in the early
phases
Whenever possible, bare surfaces are protected from
erosion at source by means of various types of covers.
Such covers include use of erosion control blanket,
LSS, hardcores and canvas sheets. In many
circumstances, there are limited areas where
protective covers can be used due to the many
continual on-going works that is carried out on site.
However, GS-JV-HLS does recognize the importance
of reducing runoffs at source. Hence, bare areas with
no activities at the time being (such as surcharging
areas) are identified and covered with either erosion
control blanket or LSS. Other areas where works are
more frequent are, whenever possible, covered with
canvas sheet.
Figure 3: Various Earth Control Measures on Site
Proceedings of the World Urban Transit Conference 2010 (WUTC 2010) 151
-
Topography of C911 shows that the site generally
slopes towards Woodlands Road. Given the large
amount of on-going construction activities and the
size of the site, effective sediment controls are one of
the key measures in preventing silty water from
flooding Woodlands Road and flowing out into the
stormwater canal. GS-JV-HLS employed the use of
the following measures to contain all runoffs within
the site and to set up a flow system that directs water
to be treated to a level of less than 50mg/l before
discharging:
Perimeter and Internal Drainage System
Pre-cast concrete perimeter drains coupled with
internal concrete-lined drainage system forms the
most important network for an effective sediment
control. This project site has by far one of the most
numbers and length of internal drains that mostly lie
along the bottom of the terraced slopes and
surcharging areas, thus capturing all laden runoffs
before directing them to the sedimentation/retention
ponds. These internal drains are necessary to reduce
potential floodings on the uneven grounds at low-
lying areas of the site and to reduce further erosion at
the bottom of the slope.
Figure 4: ECM plan showing the intricate network of
drainage system
Use of Surcharging Area
Despite the many challenges, C911 had their share of
good fortune. The designated 2m high surcharging
area is located between the slopes and Woodlands
Road, thus providing a much required obstacle to
prevent surface runoffs from discharging out from the
site.
Figure 5: Surcharging area preventing runoffs away
from site
Retention Ponds, Treatment Plants and Monitoring
Devices
A total of 4 giant retention ponds, 1 for each of the 4
areas, have been built to accommodate the maximum
volume of a once in 2 years rainfall. Each pond
measures as follows:
- Area 1 pond = 100m x 21m x 3m
- Area 2 pond = 65m x 20m x 3m
- Area 3 pond = 80m x 12m x 3m
- Area 4 pond = 80m x 15m x 2.5m
A treatment plant of 60m3/h capacity, situated next to
each pond has also been catered for all 4 areas.
Discharges are continuously monitored through
wireless TSS (total suspended solids) monitoring
system where TSS readings can be captured online at
the comfort of ones office. Such device comes with
an additional feature of SMS (short messaging system)
alerts where it sends an SMS to the relevant personnel
when the TSS readings reach above the legal
requirements of 50mg/l.
CCTV camera was also installed at the site of
discharge to monitor the quality of water output.
152 Proceedings of the World Urban Transit Conference 2010 (WUTC 2010)
-
Figure 6: Retention ponds, treatment systems &
monitoring devices on site
Silt Fence and Silt Traps
While most other construction sites uses silt fence to
line the drains so as to reduce the amount of silt
flowing into the drainage system, C911 employs the
use of silt fence in other ways as well. Silt fences
were lined around material stockpiles to ensure that
the material are, as far as possible, retained within the
designated area. Silt trap have also been installed
along the perimeter drains.
Figure 7: Silt fence along perimeter drains
Figure 8: Silt fence surrounding stockpile
Figure 9: Silt Trap
Earth Control Measures Programmes
LTA had been very active in encouraging contractors,
including GS-JV-HLS, to perform above legal and in-
house requirements for environmental matters. Over
the years, a number of schemes and educational
programmes had been launched to ensure Singapores
environment is being protected while meeting the
developmental needs of the society.
One such effective scheme developed, and used in
C911 as well, is the Environmental, Safety and
Security (ESS) assessment. The purpose of such
scheme is to monitor the contractors EHS
performance on a monthly basis throughout the
contract duration. The assessment consists of a main
ESS form and an annex of ESS form. The annex
assessment form details areas, encompassing ECM,
solid waste management, noise control, water
pollution control, air pollution control and mosquito
control, to be assessed for comprehensive assessment
on Environmental Management. ECM and water
pollution control holds a high weightage of 27 out of
the total 80 marks. The score given in the annex will
be pro-rated to 5% of the main ESS form which
consist of mainly safety management and practices.
The LTA person-in-charge of contract, tasked as the
assessor, has to evaluate the contractors ECM and
Proceedings of the World Urban Transit Conference 2010 (WUTC 2010) 153
-
water pollution control performance on the following
items:
Environmental Management
Items Max
Score
Actual
Score
Adequate protection of exposed earth
& material 5
Adequate & effective provision/
maintenance of silt traps, silt fence,
wash bays & perimeter cut-off drains
5
Concentration of total suspended
solids in discharge not greater than
50mg/L
5
Earth
Control
Measures
Prevention of earth or construction
wastes littering from construction
vehicles
2
No sign of oil leakages 5 Water
Pollution
Control No sign of chemical leakages 5
Figure 10: ESS Assessment on Earth Control
Measures and Water Pollution Control
The ESS assessment is made more effective by the
Safety Performance Scheme (SPS), a contractually
binding carrot-and-stick (with monetary reward and
penalty) scheme to motivate contractors to achieve
excellent EHS performance on their projects.
Contractors have to allocate 1.5% of the lump sum
stated in the Letter of Award for the provision of ESS
facilities and they are subjected to a total bonus or
penalty of 0.5% subjected to a cap of $1million as
shown in the figure below.
Figure 11: Safety Performance Scheme
Based on the ESS Assessment form where
environmental management accounts for 5% of the
total score, if the contractor achieves a score of 65, he
will be considered as performing up to the minimal
expectations and will not be awarded nor penalized. If
he achieves a score higher than 65, he will be paid an
increased adjustment as according to the graph. On
the other hand if he achieves a score of lower than 65,
the adjustments will be deducted up to 0.5% as
labeled under the poor performer category.
Other programmes LTA has in place includes
publicity materials and promotional events. Since
2006, a series publication have been release year after
year posters promoting effective water pollution,
erosion and sediment controls on site; LTA Safety
Newsletters with articles written on ECM on LTA
Sites and Technical Aspects of Earth Control;
pocket calendars that provides essential information;
and a guidebook on Best Environmental Practices:
Earth Control Measures.
This guidebook provides a good coverage (with
pictorial illustrations) of the relevant legislations, and
the planning and controls that should be in place
during the pre-construction and construction stages. It
also imparts a scoring assessment list to judge the
sites level of ECM implementation. The table below
provides a portion of the items in the list and the
recommended maximum scores. If the site achieved a
total score of less than 50, it indicates poor ECM on
site and further improvements are required. If the site
scores between 50 and 85, it indicates an average
implementation of ECM and there are rooms for
improvements. Achieving a score of above 85 would
indicate excellent ECM on site. LTA contractors are
strongly encouraged to make use of this detailed
assessment list to evaluate their level of ECM
implementation and to identify the area for
improvements.
154 Proceedings of the World Urban Transit Conference 2010 (WUTC 2010)
-
Figure 12: ECM guidebook and recommended list of
Assessment Criteria
While materials such as the guidebook and
newsletters are meant for Supervisor levels and above,
other items were developed to ensure that the
message was brought across even to the construction
workers on site. For instance, the pocket calendar was
designed to be handy and easy to carry around in
construction sites by workers. It contains information
such as a simple colour comparison chart for
wastewater discharges which can be used to do an on-
site verification on the TSS discharge quality.
LTA also appreciates and recognizes individuals and
contractors who have demonstrated the most pro-
active attitude and has been successful in managing
and promoting environmental protection on their
worksite. Annual promotional and award events were
organized to serve as a platform for acknowledging
their exemplary efforts and for stakeholders to share
their best practices and experiences.
Figure 13: Environmental Excellence Award and
LTA Pocket Calendar
CONCLUSION
Over the years, LTA had developed numerous
national road and rail projects, and from time to time,
distinctive sites such as C911 would emerge and
provide upmost challenges to LTA. For this case, the
unique combination of its vast area of construction,
sloping terrains, high volume of earthworks and large
amount of rainfalls in the recent months, has made
managing the silty discharges from site an uphill task.
However, with an effective environmental
management system in place, continual supervision
by the LTA project teams together with a responsible
and diligent contractor, C911 has now became one of
the sites with the most extensive earth control
measures in place.
ACKNOWLEDGEMENT
Special thanks to LTA C911 Project Team and GS
Engineering & Construction Hock Lian Seng
Infrastructure Ltd. Joint Venture (GS-JV-HLS) for
their contribution and support in developing and
maintaining an environmentally friendly site.
REFERENCES
1. Best Environmental Practices: Earth Control Measures, Land Transport Authority,
Singapore
2. Code of Practice on Surface Water Drainage, Public Utilities Board, 5
th Edition,
March 2000 with amendments under
Addendum No.4 September 2006
3. Environmental Protection and Management Act, Chapter 94A, Singapore
4. Guidebook on Erosion and Sediment Control at Construction Sites, The Singapore
Contractors Association Ltd and Public
Utilities Board, 3rd
Edition, September 2006
5. http://www.singeo.com.sg/singeo/maps/mrtdtlmap.html
6. LTMaster Plan: A People-Centred Land Transport System, Land Transport Authority,
Singapore
7. Sewerage and Drainage Act, Chapter 294, Singapore
8. Singapore Land Transport Statistics in Brief 2008, Land Transport Authority, Singapore
9. Tan Yong Soon with Lee Tung Jean and Karen Tan, Clean, Green and Blue: Singapores
Journey Towards Environmental and Water
Sustainability, Singapore 2009
10. www.pub.gov.sg
11. www.lta.gov.sg
Proceedings of the World Urban Transit Conference 2010 (WUTC 2010) 155
/ColorImageDict > /JPEG2000ColorACSImageDict > /JPEG2000ColorImageDict > /AntiAliasGrayImages false /CropGrayImages true /GrayImageMinResolution 300 /GrayImageMinResolutionPolicy /OK /DownsampleGrayImages true /GrayImageDownsampleType /Bicubic /GrayImageResolution 300 /GrayImageDepth -1 /GrayImageMinDownsampleDepth 2 /GrayImageDownsampleThreshold 1.50000 /EncodeGrayImages true /GrayImageFilter /DCTEncode /AutoFilterGrayImages true /GrayImageAutoFilterStrategy /JPEG /GrayACSImageDict > /GrayImageDict > /JPEG2000GrayACSImageDict > /JPEG2000GrayImageDict > /AntiAliasMonoImages false /CropMonoImages true /MonoImageMinResolution 1200 /MonoImageMinResolutionPolicy /OK /DownsampleMonoImages true /MonoImageDownsampleType /Bicubic /MonoImageResolution 1200 /MonoImageDepth -1 /MonoImageDownsampleThreshold 1.50000 /EncodeMonoImages true /MonoImageFilter /CCITTFaxEncode /MonoImageDict > /AllowPSXObjects false /CheckCompliance [ /None ] /PDFX1aCheck false /PDFX3Check false /PDFXCompliantPDFOnly false /PDFXNoTrimBoxError true /PDFXTrimBoxToMediaBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ] /PDFXSetBleedBoxToMediaBox true /PDFXBleedBoxToTrimBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ] /PDFXOutputIntentProfile () /PDFXOutputConditionIdentifier () /PDFXOutputCondition () /PDFXRegistryName () /PDFXTrapped /False
/Description > /Namespace [ (Adobe) (Common) (1.0) ] /OtherNamespaces [ > /FormElements false /GenerateStructure true /IncludeBookmarks false /IncludeHyperlinks false /IncludeInteractive false /IncludeLayers false /IncludeProfiles true /MultimediaHandling /UseObjectSettings /Namespace [ (Adobe) (CreativeSuite) (2.0) ] /PDFXOutputIntentProfileSelector /NA /PreserveEditing true /UntaggedCMYKHandling /LeaveUntagged /UntaggedRGBHandling /LeaveUntagged /UseDocumentBleed false >> ]>> setdistillerparams> setpagedevice