WATER POLLUTION MANAGEMENT FOR SILT DISCHARGE IN LAND TRANSPORT AUTHORITY PROJECT SITES: CASE STUDY...

7
WATER POLLUTION MANAGEMENT FOR SILT DISCHARGE IN LAND TRANSPORT AUTHORITY PROJECT SITES: CASE STUDY OF DOWNTOWN LINE 2, CONTRACT 911 Jernice Kew Huiling, Executive Engineer (Environmental) Alex Yip Jui Yong, Deputy Project Manager Safety Division, Land Transport Authority, Singapore Downtown Line 2 (Civil Construction Team 1), Land Transport Authority, Singapore Jernice_kew@lta.gov.sg , Jui_yong_yip@lta.gov.sg ABSTRACT With the rapid development and transformation of Singapore's urban landscape that boosted the construction industry over the last decade, water pollution from the construction sites has become a major concern. Construction projects could cause substantial environmental impacts if effective management control is not put in place. When top soils are cleared for site preparation works, erosion will occur during rainy days. The silt bearing runoffs will result in massive sediment pollution in our water catchments such as the scenic reservoirs and Marina Barrage. Silt turns the waterway turbid, preventing sunlight infiltration and destroys aquatic life. Not only is marine ecology devastated, the aesthetic beauty of the reservoirs will be badly affected. Therefore, with the intensive and extensive construction activities currently going on, effective earth control measures and management are necessary and essential for maintaining the sustainability of our precious water resources. Contract 911 (C911) - Design and Construction of Depot for Downtown Line 2 is one of the project with the largest earthworks and excavation activities. Contract 911 (C911) involved the excavation of about 3.85 millions m 3 of earth and with a large site area of 25 ha. It faces greater difficulties in terms of erosion control as compare to its neighbouring sites along the developing rail transit line. Furthermore, the existing site terrace (high slope area) stretches from north to south of the entire construction site has also post greater challenges in controlling effective soil erosion and management. The overall erosion drainage system, retention ponds, water treatment plants, erosion control measures, etc have to be carefully designed and assessed. A holistic review of the ECM is thorough and precise. Hence, this paper aims to draw on C911’s unique characteristic as a platform to highlight the importance of controlling silt discharges, foster greater awareness of our commitment and share our experiences on the challenges faced in the delivery of our land transport infrastructure projects. Keywords: Construction; sediment; erosion; land transport; water pollution; silt; water resource management; road; rail INTRODUCTION Singapore, located at the Southern tip of Malaysia Peninsular, is a country with a total land area of 707.1 m2. Despite being a small island, the Singapore Government places great emphasis in water resource management. Via the virtues of early land use planning, 30% of the land has been allocated as water catchment areas and the whole island wired up by a huge network of storm water canals and drains, to capture as much of its annual 2400mm rainfall as possible, which eventually is diverted into these catchment areas or reservoirs for water provision and portability. Given the large networks of canals and drains and the high storm water catchment rate in Singapore, surface runoffs from the construction sites will find their way easily to the reservoirs. In addition, with the land scarcity and large catchment areas, it is no surprise that sites may be found within 1 or 2 kilometers of these reservoirs, creating direct impact to the marine lives and potentially turning water from blue to brown. For example, Downtown Line 1 and Circle Line, one of the many railway lines LTA is currently developing, is located within the basin of one of Singapore’s most important and new catchment area known as the Marina Barrage. Other than the intention of turning the Barrage into one of Singapore’s water sources, there are also plans to transform the area into a bustling recreational hub for Proceedings of the World Urban Transit Conference 2010 (WUTC 2010) Copyright © 2010 WUTC Organizers :: Published by Research Publishing ISBN: 978-981-08-6396-8 doi:10.3850/978-981-08-6396-8 P049 149

description

This paper is about water pollution management

Transcript of WATER POLLUTION MANAGEMENT FOR SILT DISCHARGE IN LAND TRANSPORT AUTHORITY PROJECT SITES: CASE STUDY...

  • WATER POLLUTION MANAGEMENT FOR SILT DISCHARGE

    IN LAND TRANSPORT AUTHORITY PROJECT SITES: CASE

    STUDY OF DOWNTOWN LINE 2, CONTRACT 911

    Jernice Kew Huiling, Executive Engineer (Environmental)

    Alex Yip Jui Yong, Deputy Project Manager

    Safety Division, Land Transport Authority, Singapore

    Downtown Line 2 (Civil Construction Team 1), Land Transport Authority, Singapore

    [email protected], [email protected]

    ABSTRACT

    With the rapid development and transformation of Singapore's urban landscape that boosted the

    construction industry over the last decade, water pollution from the construction sites has become a major

    concern. Construction projects could cause substantial environmental impacts if effective management

    control is not put in place. When top soils are cleared for site preparation works, erosion will occur during

    rainy days. The silt bearing runoffs will result in massive sediment pollution in our water catchments such

    as the scenic reservoirs and Marina Barrage. Silt turns the waterway turbid, preventing sunlight infiltration

    and destroys aquatic life. Not only is marine ecology devastated, the aesthetic beauty of the reservoirs will

    be badly affected. Therefore, with the intensive and extensive construction activities currently going on,

    effective earth control measures and management are necessary and essential for maintaining the

    sustainability of our precious water resources.

    Contract 911 (C911) - Design and Construction of Depot for Downtown Line 2 is one of the project with the

    largest earthworks and excavation activities. Contract 911 (C911) involved the excavation of about 3.85

    millions m3 of earth and with a large site area of 25 ha. It faces greater difficulties in terms of erosion

    control as compare to its neighbouring sites along the developing rail transit line. Furthermore, the

    existing site terrace (high slope area) stretches from north to south of the entire construction site has also

    post greater challenges in controlling effective soil erosion and management. The overall erosion drainage

    system, retention ponds, water treatment plants, erosion control measures, etc have to be carefully designed

    and assessed. A holistic review of the ECM is thorough and precise. Hence, this paper aims to draw on

    C911s unique characteristic as a platform to highlight the importance of controlling silt discharges, foster

    greater awareness of our commitment and share our experiences on the challenges faced in the delivery of

    our land transport infrastructure projects.

    Keywords: Construction; sediment; erosion; land transport; water pollution; silt; water resource

    management; road; rail

    INTRODUCTION

    Singapore, located at the Southern tip of Malaysia

    Peninsular, is a country with a total land area of 707.1

    m2. Despite being a small island, the Singapore

    Government places great emphasis in water resource

    management. Via the virtues of early land use

    planning, 30% of the land has been allocated as water

    catchment areas and the whole island wired up by a

    huge network of storm water canals and drains, to

    capture as much of its annual 2400mm rainfall as

    possible, which eventually is diverted into these

    catchment areas or reservoirs for water provision and

    portability.

    Given the large networks of canals and drains and the

    high storm water catchment rate in Singapore, surface

    runoffs from the construction sites will find their way

    easily to the reservoirs. In addition, with the land

    scarcity and large catchment areas, it is no surprise

    that sites may be found within 1 or 2 kilometers of

    these reservoirs, creating direct impact to the marine

    lives and potentially turning water from blue to brown.

    For example, Downtown Line 1 and Circle Line, one

    of the many railway lines LTA is currently

    developing, is located within the basin of one of

    Singapores most important and new catchment area

    known as the Marina Barrage. Other than the

    intention of turning the Barrage into one of

    Singapores water sources, there are also plans to

    transform the area into a bustling recreational hub for

    Proceedings of the World Urban Transit Conference 2010 (WUTC 2010)Copyright 2010 WUTC Organizers :: Published by Research PublishingISBN: 978-981-08-6396-8doi:10.3850/978-981-08-6396-8 P049 149

  • water activities. Economic repercussions will be huge

    if the water is allowed to be silted overtime. Hence,

    the Land Transport Authority being the largest

    developer has a major role to play.

    Land Transport Authority (LTA)

    LTA is a statutory board under the Ministry of

    Transport that spearheads land transport

    developments in Singapore which includes roads,

    rails (Rail Transit System), pedestrian facilities as

    well as regulating vehicular and traffic matters. LTA

    has till date developed almost 150km length of MRT

    both above and below ground as well as a wide array

    and network of expressways, arterial, collector and

    local access roads which adds up to more than

    3,300km and has currently continued to expand its

    rail network system to include Downtown Line 1 and

    2.

    DOWNTOWN LINE 2 - CONTRACT 911

    Contract 911 (C911) is managed by LTAs main

    contractor: GS Engineering & Construction Hock

    Lian Seng Infrastructure Ltd. Joint Venture (GS-JV-

    HLS). It comprises the design, construction and

    completion of the Depot and its connecting tunnels

    between contract boundary C912. C911 is one of the

    projects with the largest earthworks and excavation

    activities. It has a land area of about 25 ha and an

    estimated volume of 3.85 million m3 of earth to be

    excavated.

    The proposed Depot for Downtown line (DTL) is

    located along Woodlands Road and stretch from the

    junction of Kranji Expressway (KJE) to Kwong Hou

    Sua Teochew Cemetery opposite of Sungei Kadut

    Avenue. The proposed Depot as a self contained

    operational unit which will be providing maintenance,

    operations and support for the operation of

    Downtown Line.

    The proposed Depot is located at the northern end of

    DTL and is designed to maintain an ultimate fleet of

    108x3 car electric trains for operation of services

    together with supporting service vehicles.

    WATER POLLUTION MANAGEMENT AT

    C911

    Pre-Construction Stage

    As required by Singapores Legislation, C911 GS-JV-

    HLS had engaged a Qualified Erosion Control

    Professional (QECP) to plan and design a system of

    earth control measures (ECM). QECPs are registered

    Professional Engineers who has satisfactorily

    completed specialized professional course in erosion

    and sediment control. The submission would have to

    include design calculations and specifications such

    that the discharge contains less than 50mg/l of total

    suspended solids (TSS), the maximum allowable

    legal limit stated in the code of practice. Due to its

    sheer size, C911 site was segregated into 4 areas and

    the ECM plan was initially developed separately for

    each of the area before construction works start. As

    work in the Depot progressed with increasing

    complexity, the team saw that there was a need to

    revise and combine all 4 ECM plans to ensure that the

    ECM system remains effective and integrated.

    Figure 1: Earth Control Plan

    On top of the existing legislations, LTA has

    developed internal manual and specifications that sets

    the standards and system which are required to

    establish during the construction phase they are the

    Safety, Health & Environmental Management System

    (SHEMS) Manual, and the General Specifications

    (GS). The SHEMS Manual provides a guide for LTA

    project teams to carry out construction work activities

    on-site, with due considerations given to

    environmental protection. The GS on the other hand,

    stipulates contractors responsibilities and provides

    details on the provisions that they must provide, with

    some of the requirements being stricter than what is

    legally required. For example, the Environmental

    Control Officers (ECO) engaged by contractors must

    have at least 3 years of practical experience relevant

    to ECO scope of works and they must attend

    professional courses on erosion control so that they

    have required knowledge and expertise to manage silt

    runoffs on site. Other effective requirements unique

    to LTA will be mentioned in the following section.

    150 Proceedings of the World Urban Transit Conference 2010 (WUTC 2010)

  • Construction Stage

    Challenges

    The concurrent massive excavation work post a great

    challenge to the erosion control work. The measures

    implemented have to be continuously monitored,

    improved, enhanced and relocated. The terrains and

    landscape of the entire work site is changing from

    time to time. As such, the extensive drainage system

    in Area 1 to 4 have to be diverted, adjusted or

    relocated from stage to stage.

    The nature of the excavation work such as large slope

    excavation has again challenged the effectiveness of

    the erosion control measure implemented. The runoff

    is accelerated and has pick up more erosion before it

    is channeled or diverted to the controlled drainage

    system.

    In addition, the natural location as such higher

    platform level over the entire work site than to the

    adjacent industrial estate has again constituted a

    greater challenge. The design and implemented

    erosion control system has to be effective, efficient

    and flood protected. No over flow from the erosion

    control system from the depot site to the Woodlands

    Road and the adjacent industrial estate is allowed

    Earth Control Measures on Site

    C911 first started off with studies looking into the

    feasibility of minimizing the formation of bare

    surfaces by opening up the land in phases. Taking

    into account the balance between economic

    constraints and environmental protection, earthworks

    are phased into 2 stages Area 3, 4 and 1 and Area

    2. Area 2 (of about 10ha) had started 9 months later.

    Another strategy that C911 had adopted is to

    prioritize permanent turfing and road works so that

    these designated bare slopes are quickly cut to the

    required angles and shapes and turfed/paved up as

    swiftly as possible.

    Figure 2: Permanent Turf Works started in the early

    phases

    Whenever possible, bare surfaces are protected from

    erosion at source by means of various types of covers.

    Such covers include use of erosion control blanket,

    LSS, hardcores and canvas sheets. In many

    circumstances, there are limited areas where

    protective covers can be used due to the many

    continual on-going works that is carried out on site.

    However, GS-JV-HLS does recognize the importance

    of reducing runoffs at source. Hence, bare areas with

    no activities at the time being (such as surcharging

    areas) are identified and covered with either erosion

    control blanket or LSS. Other areas where works are

    more frequent are, whenever possible, covered with

    canvas sheet.

    Figure 3: Various Earth Control Measures on Site

    Proceedings of the World Urban Transit Conference 2010 (WUTC 2010) 151

  • Topography of C911 shows that the site generally

    slopes towards Woodlands Road. Given the large

    amount of on-going construction activities and the

    size of the site, effective sediment controls are one of

    the key measures in preventing silty water from

    flooding Woodlands Road and flowing out into the

    stormwater canal. GS-JV-HLS employed the use of

    the following measures to contain all runoffs within

    the site and to set up a flow system that directs water

    to be treated to a level of less than 50mg/l before

    discharging:

    Perimeter and Internal Drainage System

    Pre-cast concrete perimeter drains coupled with

    internal concrete-lined drainage system forms the

    most important network for an effective sediment

    control. This project site has by far one of the most

    numbers and length of internal drains that mostly lie

    along the bottom of the terraced slopes and

    surcharging areas, thus capturing all laden runoffs

    before directing them to the sedimentation/retention

    ponds. These internal drains are necessary to reduce

    potential floodings on the uneven grounds at low-

    lying areas of the site and to reduce further erosion at

    the bottom of the slope.

    Figure 4: ECM plan showing the intricate network of

    drainage system

    Use of Surcharging Area

    Despite the many challenges, C911 had their share of

    good fortune. The designated 2m high surcharging

    area is located between the slopes and Woodlands

    Road, thus providing a much required obstacle to

    prevent surface runoffs from discharging out from the

    site.

    Figure 5: Surcharging area preventing runoffs away

    from site

    Retention Ponds, Treatment Plants and Monitoring

    Devices

    A total of 4 giant retention ponds, 1 for each of the 4

    areas, have been built to accommodate the maximum

    volume of a once in 2 years rainfall. Each pond

    measures as follows:

    - Area 1 pond = 100m x 21m x 3m

    - Area 2 pond = 65m x 20m x 3m

    - Area 3 pond = 80m x 12m x 3m

    - Area 4 pond = 80m x 15m x 2.5m

    A treatment plant of 60m3/h capacity, situated next to

    each pond has also been catered for all 4 areas.

    Discharges are continuously monitored through

    wireless TSS (total suspended solids) monitoring

    system where TSS readings can be captured online at

    the comfort of ones office. Such device comes with

    an additional feature of SMS (short messaging system)

    alerts where it sends an SMS to the relevant personnel

    when the TSS readings reach above the legal

    requirements of 50mg/l.

    CCTV camera was also installed at the site of

    discharge to monitor the quality of water output.

    152 Proceedings of the World Urban Transit Conference 2010 (WUTC 2010)

  • Figure 6: Retention ponds, treatment systems &

    monitoring devices on site

    Silt Fence and Silt Traps

    While most other construction sites uses silt fence to

    line the drains so as to reduce the amount of silt

    flowing into the drainage system, C911 employs the

    use of silt fence in other ways as well. Silt fences

    were lined around material stockpiles to ensure that

    the material are, as far as possible, retained within the

    designated area. Silt trap have also been installed

    along the perimeter drains.

    Figure 7: Silt fence along perimeter drains

    Figure 8: Silt fence surrounding stockpile

    Figure 9: Silt Trap

    Earth Control Measures Programmes

    LTA had been very active in encouraging contractors,

    including GS-JV-HLS, to perform above legal and in-

    house requirements for environmental matters. Over

    the years, a number of schemes and educational

    programmes had been launched to ensure Singapores

    environment is being protected while meeting the

    developmental needs of the society.

    One such effective scheme developed, and used in

    C911 as well, is the Environmental, Safety and

    Security (ESS) assessment. The purpose of such

    scheme is to monitor the contractors EHS

    performance on a monthly basis throughout the

    contract duration. The assessment consists of a main

    ESS form and an annex of ESS form. The annex

    assessment form details areas, encompassing ECM,

    solid waste management, noise control, water

    pollution control, air pollution control and mosquito

    control, to be assessed for comprehensive assessment

    on Environmental Management. ECM and water

    pollution control holds a high weightage of 27 out of

    the total 80 marks. The score given in the annex will

    be pro-rated to 5% of the main ESS form which

    consist of mainly safety management and practices.

    The LTA person-in-charge of contract, tasked as the

    assessor, has to evaluate the contractors ECM and

    Proceedings of the World Urban Transit Conference 2010 (WUTC 2010) 153

  • water pollution control performance on the following

    items:

    Environmental Management

    Items Max

    Score

    Actual

    Score

    Adequate protection of exposed earth

    & material 5

    Adequate & effective provision/

    maintenance of silt traps, silt fence,

    wash bays & perimeter cut-off drains

    5

    Concentration of total suspended

    solids in discharge not greater than

    50mg/L

    5

    Earth

    Control

    Measures

    Prevention of earth or construction

    wastes littering from construction

    vehicles

    2

    No sign of oil leakages 5 Water

    Pollution

    Control No sign of chemical leakages 5

    Figure 10: ESS Assessment on Earth Control

    Measures and Water Pollution Control

    The ESS assessment is made more effective by the

    Safety Performance Scheme (SPS), a contractually

    binding carrot-and-stick (with monetary reward and

    penalty) scheme to motivate contractors to achieve

    excellent EHS performance on their projects.

    Contractors have to allocate 1.5% of the lump sum

    stated in the Letter of Award for the provision of ESS

    facilities and they are subjected to a total bonus or

    penalty of 0.5% subjected to a cap of $1million as

    shown in the figure below.

    Figure 11: Safety Performance Scheme

    Based on the ESS Assessment form where

    environmental management accounts for 5% of the

    total score, if the contractor achieves a score of 65, he

    will be considered as performing up to the minimal

    expectations and will not be awarded nor penalized. If

    he achieves a score higher than 65, he will be paid an

    increased adjustment as according to the graph. On

    the other hand if he achieves a score of lower than 65,

    the adjustments will be deducted up to 0.5% as

    labeled under the poor performer category.

    Other programmes LTA has in place includes

    publicity materials and promotional events. Since

    2006, a series publication have been release year after

    year posters promoting effective water pollution,

    erosion and sediment controls on site; LTA Safety

    Newsletters with articles written on ECM on LTA

    Sites and Technical Aspects of Earth Control;

    pocket calendars that provides essential information;

    and a guidebook on Best Environmental Practices:

    Earth Control Measures.

    This guidebook provides a good coverage (with

    pictorial illustrations) of the relevant legislations, and

    the planning and controls that should be in place

    during the pre-construction and construction stages. It

    also imparts a scoring assessment list to judge the

    sites level of ECM implementation. The table below

    provides a portion of the items in the list and the

    recommended maximum scores. If the site achieved a

    total score of less than 50, it indicates poor ECM on

    site and further improvements are required. If the site

    scores between 50 and 85, it indicates an average

    implementation of ECM and there are rooms for

    improvements. Achieving a score of above 85 would

    indicate excellent ECM on site. LTA contractors are

    strongly encouraged to make use of this detailed

    assessment list to evaluate their level of ECM

    implementation and to identify the area for

    improvements.

    154 Proceedings of the World Urban Transit Conference 2010 (WUTC 2010)

  • Figure 12: ECM guidebook and recommended list of

    Assessment Criteria

    While materials such as the guidebook and

    newsletters are meant for Supervisor levels and above,

    other items were developed to ensure that the

    message was brought across even to the construction

    workers on site. For instance, the pocket calendar was

    designed to be handy and easy to carry around in

    construction sites by workers. It contains information

    such as a simple colour comparison chart for

    wastewater discharges which can be used to do an on-

    site verification on the TSS discharge quality.

    LTA also appreciates and recognizes individuals and

    contractors who have demonstrated the most pro-

    active attitude and has been successful in managing

    and promoting environmental protection on their

    worksite. Annual promotional and award events were

    organized to serve as a platform for acknowledging

    their exemplary efforts and for stakeholders to share

    their best practices and experiences.

    Figure 13: Environmental Excellence Award and

    LTA Pocket Calendar

    CONCLUSION

    Over the years, LTA had developed numerous

    national road and rail projects, and from time to time,

    distinctive sites such as C911 would emerge and

    provide upmost challenges to LTA. For this case, the

    unique combination of its vast area of construction,

    sloping terrains, high volume of earthworks and large

    amount of rainfalls in the recent months, has made

    managing the silty discharges from site an uphill task.

    However, with an effective environmental

    management system in place, continual supervision

    by the LTA project teams together with a responsible

    and diligent contractor, C911 has now became one of

    the sites with the most extensive earth control

    measures in place.

    ACKNOWLEDGEMENT

    Special thanks to LTA C911 Project Team and GS

    Engineering & Construction Hock Lian Seng

    Infrastructure Ltd. Joint Venture (GS-JV-HLS) for

    their contribution and support in developing and

    maintaining an environmentally friendly site.

    REFERENCES

    1. Best Environmental Practices: Earth Control Measures, Land Transport Authority,

    Singapore

    2. Code of Practice on Surface Water Drainage, Public Utilities Board, 5

    th Edition,

    March 2000 with amendments under

    Addendum No.4 September 2006

    3. Environmental Protection and Management Act, Chapter 94A, Singapore

    4. Guidebook on Erosion and Sediment Control at Construction Sites, The Singapore

    Contractors Association Ltd and Public

    Utilities Board, 3rd

    Edition, September 2006

    5. http://www.singeo.com.sg/singeo/maps/mrtdtlmap.html

    6. LTMaster Plan: A People-Centred Land Transport System, Land Transport Authority,

    Singapore

    7. Sewerage and Drainage Act, Chapter 294, Singapore

    8. Singapore Land Transport Statistics in Brief 2008, Land Transport Authority, Singapore

    9. Tan Yong Soon with Lee Tung Jean and Karen Tan, Clean, Green and Blue: Singapores

    Journey Towards Environmental and Water

    Sustainability, Singapore 2009

    10. www.pub.gov.sg

    11. www.lta.gov.sg

    Proceedings of the World Urban Transit Conference 2010 (WUTC 2010) 155

    /ColorImageDict > /JPEG2000ColorACSImageDict > /JPEG2000ColorImageDict > /AntiAliasGrayImages false /CropGrayImages true /GrayImageMinResolution 300 /GrayImageMinResolutionPolicy /OK /DownsampleGrayImages true /GrayImageDownsampleType /Bicubic /GrayImageResolution 300 /GrayImageDepth -1 /GrayImageMinDownsampleDepth 2 /GrayImageDownsampleThreshold 1.50000 /EncodeGrayImages true /GrayImageFilter /DCTEncode /AutoFilterGrayImages true /GrayImageAutoFilterStrategy /JPEG /GrayACSImageDict > /GrayImageDict > /JPEG2000GrayACSImageDict > /JPEG2000GrayImageDict > /AntiAliasMonoImages false /CropMonoImages true /MonoImageMinResolution 1200 /MonoImageMinResolutionPolicy /OK /DownsampleMonoImages true /MonoImageDownsampleType /Bicubic /MonoImageResolution 1200 /MonoImageDepth -1 /MonoImageDownsampleThreshold 1.50000 /EncodeMonoImages true /MonoImageFilter /CCITTFaxEncode /MonoImageDict > /AllowPSXObjects false /CheckCompliance [ /None ] /PDFX1aCheck false /PDFX3Check false /PDFXCompliantPDFOnly false /PDFXNoTrimBoxError true /PDFXTrimBoxToMediaBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ] /PDFXSetBleedBoxToMediaBox true /PDFXBleedBoxToTrimBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ] /PDFXOutputIntentProfile () /PDFXOutputConditionIdentifier () /PDFXOutputCondition () /PDFXRegistryName () /PDFXTrapped /False

    /Description > /Namespace [ (Adobe) (Common) (1.0) ] /OtherNamespaces [ > /FormElements false /GenerateStructure true /IncludeBookmarks false /IncludeHyperlinks false /IncludeInteractive false /IncludeLayers false /IncludeProfiles true /MultimediaHandling /UseObjectSettings /Namespace [ (Adobe) (CreativeSuite) (2.0) ] /PDFXOutputIntentProfileSelector /NA /PreserveEditing true /UntaggedCMYKHandling /LeaveUntagged /UntaggedRGBHandling /LeaveUntagged /UseDocumentBleed false >> ]>> setdistillerparams> setpagedevice