Water Management and Irrigation Assessment and...

170
1 This project is funded by The European Commission A project implemented by HTSPE Limited European Commission Water Management and Irrigation Assessment and Development Final Report Project No. 2013/315545 - Version 1

Transcript of Water Management and Irrigation Assessment and...

Page 1: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

1

This project is funded by The European Commission

A project implemented by HTSPE Limited

European Commission

Water Management and Irrigation Assessment and Development

Final Report

Project No. 2013/315545 - Version 1

Page 2: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

2

HTSPE Limited

Thamesfield House

Boundary Way

Hemel Hempstead

Herts HP2 7SR

United Kingdom

Tel: +44 (0) 1442 202400

Fax: +44 (0) 1442 266438

Email: [email protected]

Web: www.htspe.com

Office for Economic Policy and Regional Development (EPRD) Szkolna 36A Street Kielce 25-604 Poland Tel: +48 41 345 32 71 (to 74) Fax: +48 41 345 25 87 Email: [email protected] Website: www.eprd.pl

This publication has been produced with the assistance of the European Union. The contents of this

publication are the sole responsibility of HTSPE Limited and can in no way be taken to reflect the

views of the European Union.

(5013027)

Page 3: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

3

Trinidad and Tobago European Union

CONSULTANCY SERVICES

FWC BENEFICIARIES 2009 LOT 1: Rural development

Europe Aid/127054/C/SER/multi Contract no. 2013/315545

Final Report

WATER MANAGEMENT AND IRRIGATION ASSESSMENT AND DEVELOPMENT

OF THE FELICITY SITE, CENTRAL TRINIDAD

September 2013

Page 4: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

CONTENTS

1. INTRODUCTION ........................................................................................................... 19

2. OBJECTIVES OF THE PROJECT ................................................................................ 21

3. OVERVIEW OF THE NATIONAL SUGAR ADAPTATION STRATEGY (NAS) ............ 22

3.1 The National Sugar Adaptation Strategy (NAS) ..................................................... 22

3.2 Caroni (1975) Limited ............................................................................................. 22

3.3 Assistance from the EU .......................................................................................... 23

4. RELEVANT PROJECTS AND PROGRAMMES ........................................................... 24

4.1 Caparo River Basin Flood Mitigation and Water Supply Project ............................ 24

4.2 Caroni Green Initiative (CGI) .................................................................................. 25

4.3 Agricultural Incentive Programme (AIP) ................................................................. 25

5. STAKEHOLDERS ......................................................................................................... 26

5.1 Introduction ............................................................................................................. 26

5.2 Recipient Stakeholders ........................................................................................... 26

5.3 Supporting Stakeholders ........................................................................................ 26

5.4 Stakeholder Contact ............................................................................................... 27

6. EXISTING SITUATION IN THE FELICITY AGRICULTURAL AREA ........................... 28

6.1 Caroni (1975) Ltd. Lands ........................................................................................ 28

6.2 Land lying fallow .................................................................................................... 28

6.3 Drainage, Flooding and Irrigation ........................................................................... 28

6.4 Transfer to Non Subsidised Agriculture .................................................................. 29

6.5 Needs Assessment ................................................................................................. 29

6.6 Institutional Arrangements for Water Resources Management .............................. 30

7. CONSULTATIONS WITH FAMERS, FARMERS ASSOCIATIONS ............................. 31

7.1 The Felicity Project Area ........................................................................................ 31

7.2 International Experiences with Water User Associations (WUAs) .......................... 32

8. CHARACTERISTICS OF THE FELICITY PROJECT AREA ........................................ 34

8.1 Introduction ............................................................................................................. 34

8.2 Morphology ............................................................................................................. 34

8.3 Geology .................................................................................................................. 34

8.4 Soils ........................................................................................................................ 34

Page 5: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

8.5 Socio-Economical Aspects ..................................................................................... 35

9. CLIMATE AND CLIMATE CHANGE ............................................................................ 36

9.1 Climate of Trinidad ................................................................................................. 36

9.1.1 Rainfall ............................................................................................................ 36

9.1.2 Evaporation and evapo-transpiration .............................................................. 37

9.1.3 Wind ................................................................................................................ 38

9.2 Climate Change ...................................................................................................... 39

9.2.1 Change in temperature .................................................................................... 39

9.2.2 Change in precipitation .................................................................................... 40

9.2.3 Sea level rise ................................................................................................... 40

9.2.4 Impacts and mitigation measures .................................................................... 40

10. HYDROGEOLOGY .................................................................................................... 42

10.1 Introduction ............................................................................................................. 42

10.2 Aquifers in Central Trinidad .................................................................................... 42

10.3 Potential of Groundwater in the Project Area ......................................................... 42

11. WATER QUALITY ..................................................................................................... 44

11.1 Ground Water Quality ............................................................................................. 44

11.2 Surface Water Quality and Salt Water Intrusion ..................................................... 45

11.3 Test Results on Water from the Felicity Project Area ............................................. 45

11.3.1 Pesticides ........................................................................................................ 45

11.3.2 General chemical/physical parameters ........................................................... 45

11.3.3 Sodium Adsorption Ratio (SAR) Values ........................................................... 46

11.3.4 Conclusions ..................................................................................................... 47

12. ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES .............................. 49

12.1 Introduction ............................................................................................................. 49

12.2 Positive Impact on the Socio-Economic Situation .................................................. 49

12.3 Strategic Environmental Assessment and Environmental Sustainability Plan ........ 49

12.4 Impacts on Water and from Water .......................................................................... 50

12.5 Impacts on Soil ....................................................................................................... 50

12.6 Impacts on Flora and Fauna (biodiversity) ............................................................. 51

12.7 Impacts on Landscape ........................................................................................... 51

12.8 Impacts on Human health ....................................................................................... 51

12.8.1 Pesticides and fertilisers .................................................................................. 51

Page 6: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

12.8.2 Re-use of irrigation water and use of untreated wastewater ........................... 52

12.8.3 Waterborne diseases ...................................................................................... 53

13. IRRIGATION SECTOR STUDY ................................................................................. 54

13.1 Water resources in the former sugar growing areas .............................................. 54

13.2 Current, future and potential agricultural water resource needs ............................. 56

13.2.1 National situation irrigated areas ..................................................................... 56

13.2.2 Former Sugar Growing Areas – potential irrigation demand ........................... 57

13.2.3 Irrigation water requirements – approach ........................................................ 58

13.2.4 Calculated irrigation water needs for the Felicity Pilot Area ............................ 58

13.2.5 Future and potential water needs .................................................................... 60

13.3 Irrigation Sector Study – Concluding Remarks ....................................................... 63

14. OPTIONS FOR IRRIGATION .................................................................................... 66

14.1 Introduction ............................................................................................................. 66

14.2 Possible irrigation water resources ......................................................................... 66

14.3 Irrigation system in the Felicity Area – assumptions .............................................. 73

14.3.1 Irrigation efficiency .......................................................................................... 73

14.3.2 Irrigation ponds ................................................................................................ 73

14.3.3 Water metering ................................................................................................ 76

14.4 Selection of preferred option .................................................................................. 76

15. SELECTED OPTION ................................................................................................. 81

15.1 Selected water resource option .............................................................................. 81

15.2 Recommendations with selected water resource ................................................... 81

15.3 Considerations with selected water resource ......................................................... 82

15.4 Potential Environmental Impacts and Mitigation Measures .................................... 83

16. DESIGN AND FEASIBILITY STUDY. ....................................................................... 84

16.1 Introduction ............................................................................................................. 84

16.2 Water supply options - technical details ................................................................. 84

16.3 Pumps, pipes and ponds ........................................................................................ 86

16.3.1 Lay-out and nomenclature ............................................................................... 86

16.4 Water distribution – organisation and management ............................................... 91

16.4.1 General ............................................................................................................ 91

16.4.2 Irrigation .......................................................................................................... 91

16.4.3 Drainage: (ground) water and salinity control .................................................. 93

Page 7: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

16.5 Design .................................................................................................................... 96

16.5.1 System layout .................................................................................................. 96

16.5.2 Pipe system design ......................................................................................... 96

16.6 Tender documents and contracts ........................................................................... 97

16.7 Operation and maintenance ................................................................................... 97

16.7.1 Cost of operation and maintenance ................................................................ 97

16.8 Recommendations related to design issues ........................................................... 98

16.9 Zoning ..................................................................................................................... 98

16.9.1 Economic Feasibility, Cost for Water, Farmers Involvement ........................... 98

16.9.2 Economic Feasibility ........................................................................................ 98

16.9.3 Cost of Water .................................................................................................. 99

16.9.4 Farmers Involvement ..................................................................................... 100

16.10 Funding of the Implementation of the Felicity Irrigation Project ........................ 100

17. CONCLUSIONS AND RECOMMENDATIONS ....................................................... 101

REFERENCES ................................................................................................................... 103

ANNEXES ........................................................................................................................... 105

LIST OF ANNEXES

ANNEX 1: Map of the Felicity Project Area

ANNEX 2: Activities of supporting stakeholders

ANNEX 3, Farmers consultations, rapid appraisal

ANNEX 4: Drainage and flooding

ANNEX 5: International experiences with water users associations

ANNEX 6: Characteristics of aquifers and well fields in the Central Sands and Limestone

ANNEX 7: Water quality in the Caparo River

ANNEX 8: Test results of water samples from Project Area

ANNEX 9: Guidelines for interpretation of water quality for irrigation

ANNEX 10: Irrigation water requirements

ANNEX 11: Design

ANNEX 12: Assignments of consultants, meetings and fieldwork, persons met

ANNEX 13: Terms of reference

ANNEX 14: Work plan and time frame

Page 8: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

LIST OF FIGURES

Figure 1: Felicity Project Area, Ravine Sable Sand Pits and proposed location of Mamoral

Dam (source: Environmental Impact Assessment Study, Mamoral Dam and Reservoir

Project, NIDCO) .................................................................................................................... 11

Figure 9.1: Piarco Daily High and Low Temperature ............................................................ 37

Figure 9.2: Rainfall distribution over the months, Couva-Tabaquite-Talparo ........................ 38

Figure 9.3: Trinidad Isohyetal Map ....................................................................................... 38

Figure 9.4: Relative Humidity ................................................................................................ 39

Figure 9.5: Wind Speed ........................................................................................................ 40

Figure 13.1: Felicity Scheme Irrigation Requirements, 2013 and 2050 (mm/month) ............ 61

Figure 14.1: Caparo River, daily discharge at Todds Road, 2001 ........................................ 68

Figure 14.2: Ravine Sable Sand Pits .................................................................................... 69

Figure 14.3: Simulation water requirements WASA and Felicity Irrigation at Ravine Sable

Sand Pits, 2013 ..................................................................................................................... 72

Figure 14.4: Simulation water requirements WASA and Felicity Irrigation at Ravine Sable

Sand Pits, 2050 ..................................................................................................................... 72

Figure 14.5: Dynamic water level on-plot pond during the year, situation 2013 ................... 75

Figure 14.6: Dynamic water level on-plot pond during the year, situation 2050 ................... 75

Figure 16.1: Location of the Felicity project area .................................................................. 84

Figure 16.2: Large Buffer Ponds on Caparo River, map ....................................................... 86

Figure 16.3: Large Buffer Ponds on Chandernagore River, map ......................................... 87

Figure 16.4: Simulation water level at Ravine Sable Sand Pits - 2013 ................................. 90

Figure 16.5: Simulation water level at Ravine Sable Sand Pits - 2050 ................................. 90

LIST OF TABLES

Table 1: Climate change, impacts and mitigation measures ................................................ 15

Table 2: Evaluation matrix of options (dry season) for irrigation water resources ................ 17

Table 11.2: Test results of water samples from the Project Area ........................................ 48

Table 11.3: SAR-values of water samples taken in the Project Area ................................... 49

Table 11.4: Water quality matrix related to irrigation for samples taken in the Project Area. 50

Table 13.1: Water Availability per Watershed Based on 1999 WRMS ................................. 56

Table 13.2: Irrigation water volume for Felicity Pilot irrigation scheme, 2013 ....................... 59

Table 13.3: Crop Water Use Parameters - Climate Change adjusted .................................. 61

Table 13.4: Climate Change Adjusted Reference Crop Evapotranspiration for 2050 ........... 62

Table 13.5: Irrigation water volume for Felicity Pilot irrigation scheme – 2050 ..................... 62

Page 9: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

Table 14.1: Irrigation water requirement (including losses) .................................................. 74

Table 14.2: Evaluation matrix of options (dry season) – irrigation water resources ............. 77

Table 15.1: Potential impacts & mitigation measures related to preferred options for source

water and conveyance .......................................................................................................... 83

Table 16.1: Preliminary Make up of Secondary Units. .......................................................... 87

Table 16.2: Capacity LBP and pumps .................................................................................. 87

Table 16.3: Preliminary set-up of supply and distribution systems ....................................... 88

Table 16.4: Filling of On-Farm Ponds ................................................................................... 92

ABBREVIATIONS

AIP Agricultural Incentive Programme CARDI Caribbean Agricultural Research and Development Institute CARICOM Caribbean Community CARIRI Caribbean Industrial Research Unit CACC County Agricultural Consultative Committee CGI Caroni Green Initiative EMA Environmental Management Authority EU European Union FAO Food and Agriculture Organisation GDP Gross Domestic Product GIS Geographic Information System GoRTT Government of the Republic of Trinidad and Tobago MFP Ministry of Food Production MPD Ministry of Planning and Development MPHE Ministry of Planning, Housing, and Environment NAS National Sugar Adaptation Strategy NEP National Environmental Policy N S M G National Strategic Management Group RSSP Ravine Sable Sand Pits SP Sugar Protocol T&T Trinidad and Tobago TTWS Trinidad and Tobago Water Services UWI University of the West Indies VSEP Voluntary Separation of Employment Programme WRA Water Resources Agency WASA Water and Sewerage Authority WRMS Water Resources Management Strategy WTO World Trade Organization a.s.l. above sea level aq. aquifer b.g.l. below ground level EC electrical conductivity igpm imperial galon per minute mg/l milligrams per litre m

3/d cubic metre per day

m3/hr cubic metre per hour

mm millimetre m

3/s cubic metre per second

μs micro-Siemens

Page 10: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

msl mean sea level msy maximum sustained yield s drawdown T-value Transmissivity-value Q yield Q/s Specific Capacity Conversions

1 ft = 0.305 m 1 gallon UK = 4.55 litres

Page 11: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

11

EXECUTIVE SUMMARY

The Felicity Irrigation Project

The EU-financed project ‘Water Management and Irrigation Assessment and Development on the

Felicity Site, Central Trinidad’, also referred as the ‘Felicity Irrigation Project’, is a project initiated in

the context of the National Adaptation Strategy (NAS). The Project has been implemented in

conjunction with the Ministry of Food Production (MFP), and the Water and Sewerage Authority

(WASA/WRA)). The Project Area consists of 1300 acres in the former sugar lands of Caroni Ltd and is

presented in Annex1, and in Figure 1.

For the Project data were collected in the field of irrigation, hydrology, hydrogeology, meteorology,

soils, and water quality. Also environmental, socio-economic, and policy data were incorporated.

Satellite imagery was used, fieldtrips undertaken, water samples taken and analysed, and Lidar data

(derived digital elevation model/DEM) interpreted. The Project has been carried out in the period mid-

May till mid-September 2013.

Figure 1: Felicity Project Area, Ravine Sable Sand Pits and proposed location of Mamoral Dam (source: Environmental Impact Assessment Study, Mamoral Dam and Reservoir Project, NIDCO)

Objectives of the Project

The general objective of the assistance o f t h e E U to the Government of Trinidad and Tobago

i s to mitigate the adverse effects of restructuring their sugar sector. The global objective of the

Project was to identify options for irrigated agriculture for the Felicity Agricultural site in Central

Trinidad. A preferred option was to be recommended and designs for irrigation and drainage

infrastructure prepared, including contract and tender documents.

The irrigation study, presented in current report, will serve as an approach as to the way forward for

other sites identified within these former sugar growing areas. Is the first phase of three phases and

includes a feasibility study with design and tender documents. The second phase will be the

implementation of the proposed option for irrigation, and the third phase will be to duplicate the design

at other former Caroni sugar lands. In other words: the objective is to develop a feasible and viable

Caparo River Ravine Sable Sand Pits

Felicity Project Area

Proposed Mamoral Dam

Page 12: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

12

plan for irrigated agriculture for the Felicity Project site and to use this plan as a model for other areas

in Trinidad.

Stakeholders

The identified primary recipient stakeholders in the project are:

Ex Caroni employees having a lease on 2-acres of land and working their own land. Secondary recipient stakeholders in the Project Area are:

Ex Caroni employees having a lease on 2-acres of land, not working on their land.

Farm labourers, hired to work in the Felicity agricultural area.

Entrepreneurs who deliver agricultural inputs like farm tools, fertilizer and agro-chemicals, but also entrepreneurs who offer mechanised tilling, using their own tractor and equipment and labour for a fee.

Entrepreneur farmers who sublease the agricultural land leases from ex Caroni employees to put together larger scale farming enterprises.

Supporting stakeholders in the Felicity Irrigation Project are the ministries and authorities that have a relation with agriculture and water resources management (chapter 5 in main report).

Needs Assessment, Water User Associations (WUAs)

For the needs assessment concerning the Felicity Project Area information was gathered during

meetings, field visits, and consultations, including the rapid appraisal that was conducted in the

Project Area (chapter 7, Annex 3). The needs in the Felicity Project Area, as expressed by the

stakeholders, including the recipient stakeholders, are as follows:

more water;

irrigation water;

better lease conditions;

better infrastructure

better security;

a famers association;

additional training;

market system;

store houses, cooling facilities.

In many places word wide not all people pay their water bills. The same applies for payment for

irrigation services. In general, and also in the Felicity Project Area, famers indicated their willingness

to pay for a proper irrigation system, but they would like to see first that the service is working well

before starting to pay. Famers associations, or water user associations (WUAs) have not been

established yet in the Felicity Project Area. WUAs are often formed by groups of farmers, who have

shared interests in the demand for and the management of irrigation water. WUAs can be large or

small, and may be formally constituted (as an NGO), or by informal arrangement. Before a farmer’s

association is established certain aspects need to be studied, such as: objectives of the WUAs, areas

of responsibility, and structure of the organisation (chapter 7).

Potential Positive Impact on the Socio-Economic Situation

Turning the former sugar lands of Caroni (1975) Ltd. in cultivated and irrigated farm lands, will have a

positive influence on the regional socio-economic situation. The arrangement to use the property for

agriculture shall generate positive economic returns, resulting in increased rural income and creation

of employment. When the irrigated farm lands prove to be profitable workers will be attracted to these

areas. These farmers will then produce and supply a wide range of fresh agricultural products, which

will most likely adjust prices downward. Consumers may benefit from healthier agricultural products at

lower prices. Also the issue of food security will be enhanced.

Page 13: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

13

Environmental Considerations and Climate Change

Due to irrigation practises several components of the physical and human environment may be

affected, whether this is negative or positive. A strong positive impact is expected from the

introduction of irrigation on the socio-economic situation. Potential negative environmental impacts of

irrigation systems may be caused by agricultural runoff on surrounding rivers and downstream users,

affecting water, soil, flora and fauna (biodiversity), landscape, and human health (pesticides

&fertilisers, re-use of waste water).

In the design of the preferred option for irrigation services in the Felicity Project Area, climate change

as an outside effect, has been taken into account. For Trinidad and Tobago, climate change experts

believe that in the future longer, drier summers, shorter and more intense rainy seasons, and a

potential increase in sea level will occur. Because of expected higher frequency and intensity of

tropical storms, more flooding in low lying areas is expected.

In brief, the Caribbean region global climate change (GCC) is expected to result in:

a more hostile regional climate;

rise of temperature of about 0.2 °C per decade;

higher frequency and intensity of tropical storms and hurricanes;

more severe droughts;

rising sea level. Climate change results in environmental and socio-economic impacts, which partly can be mitigated by specific measures. Major impacts and mitigations measures related to agriculture are presented in Table 1. Table 1: Climate change, impacts and mitigation measures

Climate Change Impacts of climate Change Mitigation Measures

Rise of temperature More intense rainfall, higher frequency and intensity of tropical storms and hurricanes More severe droughts Rising sea levels

Lower crop production Higher frequency of floods; more severe floods Soil erosion, hardening of soils Coastal erosion, salt water intrusion, flooding

Development of crops that can grow under higher temperatures, proper water management Good drainage systems, proper water basin management, reforestation, soil conservation Soil conservation, planting trees, wind breakers, crop rotation, mulching, proper water management Protection of coasts by wetlands, mangrove forests, dikes, producing salt tolerant crops

Possible Irrigation Water Sources

The consultants have identified four possible sources for dry season irrigation water supply:

1. The Caparo River in the project area;

2. Groundwater abstracted in or close to the project area;

3. Upstream reservoirs and conveyance of water to the project area:

a. Large existing, flooded mining pits east of the project area, adjacent to the Caparo River;: the

Ravine Sable Sand Pits (RSSP)

Page 14: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

14

b. The Caparo River dam (Mamoral), formerly only planned for flood protection, now under

consideration as multi-functional reservoir;

c. Abels Clay Pit, now still being mined under a current license.

4. Treated wastewater re-use and drainage water re-use:

a. Conveying treated wastewater from outside the project area directly to the project area;

b. Within the project area, by collecting the outflow /drainage and re-using it by mixing it with the

selected irrigation water source(s) – closed loop

Combinations of more than one of the above water sources can (and have to) be considered.

Evaluation of options for Irrigation Water Sources

To evaluate the options and to come to the most optimal mix of water resources an evaluation matrix

of the different options has been prepared, Table 2. In this table a list of different criteria is set against

the various sources for irrigation water. The matrix provides an overview of advantages and

disadvantages of the different possible water resources. An analysis and evaluation of options, and a

selection of a feasible solution, can only take place based on an overall view of combinations of

resources. It is necessary to use those resources in such a way that the most positive characteristics

are combined in an optimal mix.

Another important consideration that may not be clear from the matrix is that it is recommended to

work as much as possible with the infrastructure that is already in place. Making large changes will be

expensive, and disruptive to farmers who are already working the land, and even partly irrigating the

land. By adapting, improving and adding to their present practices the transition to the new system

can be expected to be much easier, as the acceptance will be much higher. It is imperative to involve

the farmers and other beneficiary stakeholders during all steps of the decision making process.

Page 15: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

15

Table 2: Evaluation matrix of options (dry season) for irrigation water resources

Resource

Criterion

weight

Caparo

River

Ground

water1

Sand

pits,

pipes

Mamoral

Reservoir,

pipes

Sand pits

Caparo,

River

Mamoral

Reservoir,

Caparo

River

Water availability2 2x ++ 0 ++++ ++++ ++++ ++++

Other claimants 1x + + - - - - - - - -

Water quality 1x - - ++ ++ ++ ++

Salt water intrusion 1x o - - ++ ++ ++ ++

Robustness 1x - + o o o o

O&M costs 1x - o - - - -

Environmental

impact 1x - - ++ ++ ++ ++

Conveyance losses

(primary system) 1x + + ++ ++ - - - -

Obstacles for

construction 1x + o - - - - - -

Cost 1x o + - - - - - - - -

Total3 + o +++++ +++++ ++ ++

Key: - - negative; - somewhat negative; o neutral, no effect; + somewhat positive; ++ positive.

Based on the description of the various identified water resources the following can be concluded:

1. Non-viable resources

- Groundwater is not considered a promising source for irrigation water in the Felicity area. The

consultants will not consider groundwater in the mix, for now.

2. Inside the Felicity project area

- Ponds are already constructed on many plots, and are easily and cheaply constructed. The

concept is clear, though the farmers feel that the capacity is too small and the ponds take too

much arable land, especially when they are dry. The study suggests that ponds do have an

essential function in safeguarding irrigation in the Felicity Area, both during the rainy season to

bridge dry spells and as buffers to store and distribute irrigation water during the dry season. The

criticism of the farmers can be countered if a single pond is used for one plot and if the ponds are

replenished from an outside source during the dry season. The land loss, at about 5%, is

acceptable considering the advantages of irrigation and increased water security. The total

capacity of the ponds is 1 Mm3 for the entire Felicity area. The consultants recommend using the

ponds (individual or for groups of plots), and construction of ponds for each of the plots that are

to be irrigated. This is in line with the policy of the Ministry of Food Production.

1 Groundwater has a total score of 0 because it can be neglected. Water availability cannot be

negative. 2 4 ++++ can be awarded as this criterion has twice the weight

3 Total: simply add all +, - and o, valued at 1, -1 and 0.

Page 16: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

16

- Directly linked to the above it follows that an infrastructure needs to be constructed that can

replenish the ponds. A network of rigid (preferably buried) pipes, a network of irrigation channels,

or a combination of the two will be required, to carry the water from the intake location to the

ponds. This system can be operated on a rotational, non continuous basis, given the fact that the

ponds hold a buffer of at least 6 weeks of irrigation water. The consultants prefer a system of

(buried) pipes, especially since this proves to be the preferred method used in other areas.

- A method to measure the amount of irrigation water used by an individual farmer is needed.

Outside the Felicity project area

When considering the above, possible sources of water to supply the ponds are to be identified.

Looking at the matrix of Table 2 there are two viable options, described below.

The Caparo River, but only after rainfall has created enough run-off to flush the accumulated

pollutants and dilute any that are being added to it. For this four things are needed:

1. A weir or weirs are to be constructed in the Caparo River, and possibly basins need to be

constructed to allow pumping. Such basins hold relatively small amounts of water;

2. Large ponds to fill quickly, along the river (buffer of peak flow);

3. A number of large capacity pumps to quickly fill the large ponds when a suitable discharge peak

occurs. The pumps have to be big because the suitable discharge peaks last only a few days at

maximum.

4. This needs a knowledgeable and adequate management, to decide when to operate the pumps.

The operator may get a warning based on rainfall upstream, from one of the rainfall stations in or

near the head of the basin, or through the meteorological services division. An operations

procedure cannot be given as this depends on the actual irrigation water requirement, which will

be different based on actual rainfall and water use.

The drawbacks of using the Caparo River as resource are twofold:

1. The cost of the pumps and the complexity of operation;

2. The residual level of pollution, and the unreliable, irregular and intermittent flow.

A clear advantage is that all needed infrastructure can be built within the project boundaries, so it

is easily controlled and managed by a farmers representative body. Building the infrastructure is

relatively simple and straightforward, but expensive.

The Mamoral reservoir and the Ravine Sable Sand Pits. Both sources would have the same

advantages and disadvantages, and can and even should be operated as one system. At this

moment it is not certain that the Mamoral dam will be built. The Ravine Sable Sand Pits appear to

have enough water for both the Felicity irrigation requirement as well as to cover the WASA demand

for domestic water supply.

For the sake of this discussion it is assumed that water can be made available from the Ravine Sable

Sand Pits. If the Mamoral Dam is built a means to convey the water to the Sand Pits needs to be

decided upon (pipe, or by releasing it in the Caparo River bed). Also, an inlet and cross dam needs to

be constructed in the Caparo River next to the sand pits divert the river water in a controlled manner

into the sand pits. It is assumed that such works will be constructed as a part of the flood control and

mitigation measures currently being studied by the Caparo River Basin project; they will be

considered only in a qualitative manner by the Felicity irrigation project.

While the active storage of the Ravine Sable Sand Pits is not sufficient to cover all the requirements

of the Felicity area, it will also collect runoff during rain in the dry season, increasing the total water

yield. In combination with optimal use of the ponds in the Felicity area the water from the Ravine

Page 17: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

17

Sable Sand Pits is expected to cover the irrigation water requirements for the Felicity area (NIDCO,

2013).

A method to convey the water from the sand pits to the Felicity irrigation intake is needed. There are

two options:

1. Use the Caparo River as conduit by pumping the water from the sand pit back into the river. This

appears to be a very elegant solution: the entire infrastructure to utilise the water of the Caparo

River during the rainy season is the same as for the dry season. However, the cost of pumping

for this option is significant.

2. Build a pipeline, estimated length up to 10km, and use the Ravine Sable Sand Pits as buffer.

Using the Caparo River as conduit:

Advantages

- The entire infrastructure at the Felicity area can be used both in the dry and rainy season,

although the buffer (intake basins) capacity may have to be increased to avoid loss of water

through spillage and a number of large pumps are needed;

- The required ecological flow will add to the irrigation water volume available at the intakes at the

Felicity area.

- Implementation and construction time are relatively short (easily within one dry season).

Disadvantages:

- Cost for pumps, electricity grid, transformers.

- Losses, mostly from legal and illegal abstraction from the Caparo River between the sand pits

and the Felicity inlet, are expected to be higher than for a pipeline

- The water will collect polluted effluent, decreasing the water quality on its way to the Felicity

Area.

- Operation of the pump at the RSSP has to be coordinated with the pumping at the Felicity

intake(s), taking into consideration the travel time through the river

- Leakage beyond the Felicity inlets may occur if not all released water is pumped. However, a

limited ‘ecological flow’ is required anyway.

Building a pipeline as conduit:

Advantages

- Losses are expected to be low.

- Water quality will not be decreased by lateral inflows

- The system will deliver water at pressure to the Felicity area, facilitating easy distribution in the

secondary system. It will be possible to construct a fully pressurised system delivering the water

to the ponds, with relatively small pumps as the system can convey water 24/7 (with ‘smart’

operation and management);

- This system could possibly be implemented without the ponds, though management of a system

without ponds is very complex and the buffer will be cancelled, significantly increasing the

required dry season flow from the RSSP reservoir. Preliminary calculations (NIDCO, 2013) show

that this is not feasible. Management of this system and both investment and O&M costs will be

higher, due to irregular demand. This approach is deemed not viable by the consultants.

Disadvantages:

Page 18: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

18

- Costs are significant, but may in the end be lower than using the Caparo River bed as conduit,

due to the huge difference in required pump capacity. Also, pumps need to be replaced while the

pipeline is probably good for more than 50 years.

- Implementation and construction will be time-consuming. A detailed survey of the right of way is

required, followed by a detailed design. Access to land and the actual right of way has to be

purchased where this is not government owned. A project like this will require tendering

procedures that are much more demanding and time-consuming than for the construction of a

simple pump unit.

Conclusions

The consultants concluded that there are two viable options to provide irrigation water to the Felicity

Pilot area. Both include the individual ponds and a system to replenish these ponds.

Option 1: Source water from the Ravine Sable Sand Pits, possibly in combination with the Mamoral

Dam Reservoir, conveyed to the Felicity Pilot Area using the Caparo River. This will include intake

works and a large number of big pumps on the Caparo River within the project area. During the rainy

season the natural flow of the Caparo River can be utilized to replenish the ponds. During the dry

season water can be released (pumped) from the Ravine Sable Sand Pits into the Caparo River bed.

Option 2: Source water from the Ravine Sable Sand Pits, possibly in combination with the Mamoral

Dam Reservoir, conveyed to the Felicity Pilot Area using a pipeline. This will mean that the intake

works in the Caparo River may not be needed, and water is available at the intake to be distributed to

the ponds under pressure. This option has the advantage of offering 24/7 supply, resulting in relatively

small flow rates (maximum 170-175 l/s) which can be handled with small pumps and a pipe diameter

of about 50 cm (20 inch).

Closed loop system: Adding the closed loop re-use system to either of the above options will reduce

the required amount of ‘fresh’ irrigation water. The effects of applying this interesting concept will have

to be modelled; a rough estimate can probably and possibly be done quickly. Introduction of the

closed loop system has a clear and negative effect on leaching requirements. It is recommended to

implement this only after an additional study into the effects on the soil salinity and the economics.

See also Chapter 16 on salinity and risks of salinisation.

The consultants suggest that Option 1 and Option 2 are considered as Phase 1 and Phase 2. It is

recommended to start with Option 1 for a limited number of plots (100-120) in the Felicity area, and

then start the preparations for building the pipeline. The process of detailed survey, detailed design,

tendering, possibly expropriation and compensation (along the right of way), construction and delivery

can then take place without delaying the introduction in the Felicity Area.

Page 19: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

19

1. INTRODUCTION

Following a World Trade Organisation (WTO) ruling, the EU announced that it would phase out the

Sugar Protocol, under which African, Caribbean and Pacific sugar producing former colonies received

preferential prices. To facilitate this, the EU would provide funds to those Sugar Protocol countries

that choose to diversify away from the sugar business within a structured framework, the EU-

approved National Sugar Adaptation Strategy (NAS, submitted 2007). These developments made

Trinidad and Tobago to initiate in 2003 a strategy to restructure its sugar industry.

The general objective of the assistance of the EU in the sugar sector, is to mitigate adverse effects

caused by the changed situation, based on the decision o f t h e EU Council of Ministers to phase

out the Sugar Protocol (2005). Since 2008 the EU has been supporting the Government of Trinidad

and Tobago (GORTT) with restructuring former sugar lands, focusing on infrastructure, diversification

of agricultural lands, and reintegration of former employees of Caroni (1975) Ltd, the country’s state

owned sugar manufacturing company.

The Felicity Irrigation Project

The EU-financed project ‘Water Management and Irrigation Assessment and Development on the

Felicity Site, Central Trinidad’, often referred to in current report as the ‘Felicity Irrigation Project’, or

‘the Project’, is a project initiated in the context of the National Adaptation Strategy. The Project has

been implemented in conjunction with the Ministry of Food Production (MFP), and the Water and

Sewerage Authority (WASA). The Project area consists of 1300 acres in the former sugar lands of

Caroni Ltd, The location has been indicated as the Felicity Site, and is presented in Annex1, Figure

1.1, and in Photograph 1.1.

In the Inception Report for the Project a 15 steps Approach and Methodology (based on the Terms of

Reference, Annex 13) was presented, on which a Work Plan (Annex 14) was built with 25 activities

that would lead to the fulfilment of the assignment.

For the Project data were collected in the field of irrigation, hydrology, hydrogeology, meteorology,

soils, and water quality. Also environmental, socio-economic, and policy data were incorporated.

Satellite imagery was used, fieldtrips undertaken, water samples taken and analysed, and Lidar data

(derived digital elevation model/DEM) interpreted.

The Project has been carried out in the period mid-May till mid-September 2013 by a HTSPE / EPRD

Consulting Team, comprising of Drs. Frank de Zanger (Team Leader, Water Resources Management

Expert), Ir. Bob Pengel (Water Resources Development Expert), Ir. Frank van Berkom (Hydrologist)

and Mr. Luis Arturo Celis Velasco Msc (Hydrologist).

Page 20: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

20

Photograph 1.1: The Felicity Project Area

Page 21: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

21

2. OBJECTIVES OF THE PROJECT

The general objective of the assistance o f t h e E U to the Government of Trinidad and Tobago

i s to mitigate the adverse effects of restructuring their sugar sector.

The global objective of the Project was to identify options for irrigated agriculture for the Felicity

Agricultural site in Central Trinidad. A preferred option was to be recommend and designs for

irrigation and drainage infrastructure prepared, including contract and tender documents.

The specific objectives of the Project were:

Assess the present situation with respect to irrigation and drainage development at the

Felicity site and assess ongoing water resource projects in the former sugar lands.

Review the existing institutional arrangements for water resources development and

management.

Identify a range of options for the development of sustainable water management (irrigation

and drainage) in the Felicity area, with recommendations for a preferred option.

Prepare design and contract documents for the implementation of the preferred option,

including irrigation, water supply & delivery, wastewater treatment & water reuse (if relevant)

at the Felicity site.

In the ToR the expected results have been formulated as follows: ‘Detailed designs which would allow

for implementation of a communal large scale irrigation system at Felicity, encompassing

approximately 1300 acres, which will serve as an approach as to the way forward for other sites

identified within these former sugar growing areas.’

The irrigation study, presented in current report, is the first phase of three phases and includes a

feasibility study with design and tender documents. The second phase will be the implementation of

the proposed option for irrigation, and the third phase will be to duplicate the design at other former

Caroni sugar lands. In other words: the objective is to develop a feasible and viable plan for irrigated

agriculture for the Felicity Project site and to use this plan as a model for other areas in Trinidad.

Page 22: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

22

3. OVERVIEW OF THE NATIONAL SUGAR ADAPTATION STRATEGY (NAS)

3.1 The National Sugar Adaptation Strategy (NAS)

The Government of the Republic of Trinidad and Tobago (GORTT) has been restructuring the

sugar sector since 2003. On March 5th 2007, the National Sugar Adaptation Strategy ( N A S ) was

submitted to the European Union (EU), as a response to the decision by the EU Council of

Ministers (November 24th, 2005) to end the support to the sugar industry (EU Regulation

266/2006). The NAS is a sector policy document that was developed in the context of Vision 2020, a

wider national development agenda, and was based on the Government’s policy to dissociate

from sugar and to end subsidies to the sugar industry.

In 2006 the European Union facilitated the preparation of the National Sugar Adaptation Strategy.

It was funded under the Accompanying Measures for Sugar Protocol Countries (AMSP). The NAS

was a consequence of the decision and actions of the Government of Trinidad and Tobago t o

reform the sugar sector in 2003. Caroni (1975) Limited, the country’s state owned sugar

manufacturing company closed down farming sugarcane and manufacturing s u g a r i n 2 0 0 3 .

A new entity called the Sugar Manufacturing Company Limited was formed, which continued to

produce raw sugar from cane supplied by private farmers from 2003 until 2007. In 2007 all production

of raw sugar ceased.

The NAS is based on the principle that any future activity in the sector should be private sector

and based on sustainable business models. The NAS outlined three strategic objectives:

options for continued sugarcane farming, which would include the exploration of alternative

uses for sugarcane;

diversification into other food crops;

minimisation of socio-economic and environmental impacts.

The Cabinet of the GORTT has overall responsibility for the implementation of the National Sugar

Adaptation Strategy. A technical sub-committee, coordinated by the Ministry of Agriculture Land and

Marine Resources (MALMR), was established in 2006 for the oversight and coordination of the NAS.

In addition, several government ministries hold direct responsibility for implementing elements of the

NAS, including: The Ministry of Finance, The Ministry of Trade and Industry, The Ministry of

Agriculture, Land and Marine Resources, The Ministry of Energy and Energy Industries, The

Ministry of Public Utilities and the Environment, and The Ministry of Social Development.

While several institutions were responsible to faci l i tate the reform, including support for

agriculture, housing, industrial estates, training & entrepreneurship, there was no common

organization charged with a bid to influence policy decisions on the reform. To solve the institutional

overlap, the National Strategic Management Group ( N S M G ) was created in 2008, acting under

the purview of the Office of the Prime Minister as Project Coordination Unit, and taking up

responsibility for the successful management and implementation of the National Sugar Adaptation

Strategy.

3.2 Caroni (1975) Limited

Caroni (1975) Ltd. is the former state owned sugar company for Trinidad and Tobago, which was

nationalized from the Tate and Lyle Sugar Company. The company had ac t i v i t i es in cane

cutting, cultivation, processing (2 sugar mills, 1 distillery), transportation, administration and non-

sugar operations. Caroni (1975) Ltd. played a major role in the economic and political life of the

country. Caroni’s historical and financial evolution i n f l u e n c e d a large c e n t r a l area in

Trinidad. Several towns and villages relied on the company for growth, nutrition and economic

activities, including the country’s second city of San Fernando and the towns Couva and

Chaguanas. The company provided support to private farmers and diversified into several agricultural

activities, including citrus orchards, rice cultivation, cattle breeding, and aquaculture. Despite

Page 23: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

23

substantial property holdings, Caroni (1975) Ltd. was independently not profitable and the sugar

industry required substantial subsidies from the state. The Government of Trinidad and Tobago

decided to close Caroni (1975) Ltd. in 2003, and developed a National Sugar Adaptation Strategy

(NAS, chapter 3.1), that provided support to displaced workers and provided land for agricultural,

residential, and industrial development.

The impact, caused by the sudden elimination of the sugar industry w a s

c o n s i d e r a b l e . The most significant socio-economic impact of the government’s decision to

reform the sugar industry was the laying of of almost 10,000 employees f r o m the state-owned

sugar enterprise. In 2003, employees of Caroni (1975) Ltd. were offered compensation in the

form of a Comprehensive Voluntary Separation Package (VSEP). This opportunity provided

alternatives for ex Caroni workers by assisting them and their dependents in the transition from

employee to owner, lessee, investor or entrepreneur. Also two acre plots of agricultural land and

residential lots were included in the separation package. In addition, employees were encouraged

to take free training in their area of choice. According to reports to a ministerial committee in

November 2006, 82% of the former employees ( 7,248) accepted the lease of 2-acre agricultural

and housing plots. A Caroni Agricultural Lands Project Team (CALP) has developed infrastructural

works on several estates where these plots were located.

3.3 Assistance from the EU

The general objective of the assistance o f t h e E U in the sugar sector is to mitigate the

adverse effects of the restructuring activities in the former sugar lands. The EU Council of Ministers

decided to phase out the Sugar Protocol starting in 2006, while supporting the GORTT in the

realization of the priorities stated i n the country’s National Development Plan.

In this framework, the EU strategy supports two of the Strategic Objectives of the NAS:

Promoting economic diversification at former sugar dependent areas (exit strategies for sugar

farmers and sugarcane workers, who choose to leave the industry; improving the

environment for economic diversification).

Addressing broader impacts related to social, environmental, community and area-based

issues (maintaining environmental stability; providing sustainable social and economic

support related to the socio-economic effects of transitioning out of the sugar industry).

Since May 2008, an In ter -Min is ter ia l Commit tee, moni tors the implementation of the

National Sugar Adaptation Strategy. Regular reports are submitted to the EU Delegation on the

progress of the implementation of annual financing agreements.

Page 24: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

24

4. RELEVANT PROJECTS AND PROGRAMMES

A project that has definitely implications, and provides possibilities, for the ‘Felicity Irrigation Project’ is

the ongoing ‘Caparo River Basin Flood Mitigation and Water Supply Project’. The ‘Caroni Green

Initiative’ by Caroni (1975) Limited is an important programme that is directly related to the

management of the former Caroni sugar lands and thus of concern for current ‘Felicity Irrigation

Project’. Furthermore, there is the ‘Agricultural Green Initiative’, an incentive programme launched by

the Ministry of Food Production, that in broader context might be of importance for the Felicity former

sugar lands.

4.1 Caparo River Basin Flood Mitigation and Water Supply Project

An important project being carried out east of the Project area is the Feasibility Study and Conceptual

Design for the Caparo River Basin Flood Mitigation and Water Supply Project (Royal Haskoning DHV,

Deltares, Client NIDCO). This Caparo Water Basin Study includes the management of large former

sand mining pits (Ravine Sable Pits), which have filled with water after a heavy flood in the Caparo

River. Although the water level dropped at first for about 5-6 meters, after that the water level

stabilised more or less. The reason for the stabilisation is probably the ‘natural’ lining of the pits by

fine silt and some clay. Of course the idea was born that the pits could be used to catch future floods

of the Caparo River, but also to store water. The water could then be used for water supply, but also

for agriculture, making it an excellent example of an Integrated Water Resources Project. The volume

of water that could be stored in these pits is estimated at 1.6 - 1.7 million m3. In the future a

connection is foreseen between the sand pits and the Caparo River, so that water can be taken in

during rain but in fact as required. Also a dam (Mamoral dam) is planned a few km’s upstream of the

sand pits, which would complement the function of the sand pits (Figure 1.1).

Figure 1.1: Felicity Project Area, Ravine Sable Sand Pits and proposed location of Mamoral Dam (source: Environmental Impact Assessment Study, Mamoral Dam and Reservoir Project, NIDCO)

Ravine Sable Sand Pits

Proposed Mamoral Dam

Dam

Felicity Project Area

Caparo River

Page 25: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

25

Ravine Sable Sand Pits

The Ravine Sable Sand Pits, with their large storage of water of good quality, taken upstream from

the Caparo River, could play a major role in providing irrigation water for the Felicity Site and other

irrigated lands in the former Caroni sugar areas. It’s possible role in one of the options for the

provision of irrigation water is explained in the chapter on preferred options

In fact one large sand pit had filled with water. The pit has a depth of about 27 m below ground level

(b.g.l) and the water level in the beginning of August was approximately 20 m b.g.l. The pit had filled

with about 7 m of water, which level is more or less stable. The ground level around the sand pit –

also the level of Caparo River – is approx. 30 above sea level (a.s.l.), the water level in the pit is about

20 m a.s.l. and the Felicity Project Area has a level of about 8 m a.s.l. If water for irrigation would be

used from the sand pit, then (with levels as described) the water need to be pumped 10 m high and

could be transported from a level of 30 m a.s.l. to 8 m a.s.l. Although the distance from the sand pit to

the Project Area is about 10 km, gravity will help to transport the water.

A fieldtrip was undertaken to the sand mining pits on August 3rd

and discussions were held on site

with the Team Leader of the Caparo River Basin Project, other team members and a representative of

the MFP.

4.2 Caroni Green Initiative (CGI)

A programme relevant for the agricultural development of the Felicity Irrigation Project is the ‘Caroni

Green Initiative’ (CGI), a business model developed by the GORTT and Caroni (1975) Limited. This

shared value business model for food production will bring former Caroni lands under sustainable and

profitable cultivation. The available land covers a total of 5.800 acres, comprising mainly the 2-acre

agricultural plots leased to former Caroni workers, as part of the Voluntary Separation of Employment

Programme (VSEP). The Caroni Green Initiative promotes to bring the idle Caroni farm lands under

cultivation, with the objective of an increase in the domestic food supply. Herewith is the CGI

supporting T&T’s economic diversification. The CGI is a business framework that is supported by the

Government, but does not rely on specific subsidies. At the national level the Caroni Green Initiative

will assist the GoRTT to achieve its objectives for the agricultural sector. Reference is made to

chapter 7, which deals with farmer involvement in the operation and management of the irrigated

agricultural lands.

4.3 Agricultural Incentive Programme (AIP)

The Ministry of Food Production launched in 2011 the revised ‘Agricultural Incentive Programme’, a

programme designed to support the agricultural sectors in T&T. The intention is to improve the

efficiency and productivity of the agricultural sector and to conserve the environment. The incentives

are meant to support farmers to continue and expand their agricultural production and to encourage

the new generation to enter the agricultural sector. The incentives offered are: financial support for

vehicles, water for agriculture, land preparation, machinery & equipment, soil conservation, crops,

protected agricultural systems, guaranteed prices, integrated pest management, post-harvest &

marketing, livestock, agro processing, new farmers (youth in agriculture), security, soil amelioration,

waste management, marine fisheries, and aquaculture.

Concerning investment, the National Food Production Action Plan 2012-2015 outlines the investment

opportunities in the agricultural sector.

Page 26: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

26

5. STAKEHOLDERS

5.1 Introduction

The involvement of stakeholders is essential in agricultural programmes and projects. Farmers working in the Felicity area are the most important (recipient) stakeholders. If they are to accept ownership of the project, then they have to be heard and be involved. The setting up of farmers/water users associations has been envisaged, as this social engineering phenomenon is critical to the economic viability and sustainability of the project (chapter 7) It is important to clearly define the recipient stakeholder or ‘farmer’ in the Felicity area. Not everybody who has been allotted a 2-acre agricultural plot is a farmer. However, all these persons have a lease. Some will cultivate the land themselves; other lessees would their land be managed by experienced famers or agricultural entrepreneurs. All of these contributors should be regarded as recipient stakeholders. Subsistence farming is clearly not the objective of the GoRTT, and also does not seem to be the intention of the owners / lessees of the agricultural plots. The second important group of stakeholders are the institutions, which are involved in the National Sugar Adaptation Strategy. These ‘supporting stakeholders’ are involved in the transition process of former sugar workers into other work or livelihoods. Most of the supporting stakeholders are government institution or are organisations clearly linked to the Government of T&T.

5.2 Recipient Stakeholders

The primary recipient stakeholders in the project are:

Ex Caroni employees having a lease on 2-acres of land and working their own land. Secondary recipient stakeholders in the project area are:

Ex Caroni employees having a lease on 2-acres of land, not working on their land.

Farm labourers, hired to work in the Felicity agricultural area.

Entrepreneurs who deliver agricultural inputs like farm tools, fertilizer and agro-chemicals, but also entrepreneurs who offer mechanised tilling, using their own tractor and equipment and labour for a fee.

Entrepreneur farmers who sublease the agricultural land leases from ex Caroni employees to put together larger scale farming enterprises.

5.3 Supporting Stakeholders

Supporting stakeholders in the Felicity Irrigation Project are:

Ministry of Food Production (MFP) - Engineering Division and Agricultural Planning Division.

Water Resources Agency (WRA) as a division of the Water and Sewerage Authority (WASA).

Drainage Division of the Ministry of Environment and Water Resources.

Environmental Policy and Planning Division of the Ministry of Environment and Water Resources.

Environmental Management Authority (EMA).

Caroni (1975) Limited

Water and Waste Water Sector Advisory Committee under the Ministry of Science, Technology and Tertiary Education, which has been mandated to develop Occupational Standards for that sector

National Infrastructure Development Company (NIDCO), responsible for executing flood mitigation and water management projects within various watersheds across Trinidad.

While not mentioned in the ToR and not directly involved in the study, the following additional supporting stakeholders are important for creating an environment that is conducive to successful agricultural entrepreneurship in the Felicity Area and in the former sugar lands in general. These organisations support farmer entrepreneurs by supplying information, extension services, contract farming, knowledge transfer, guaranteed minimum prices, and agricultural credit. Incentives (subsidies) on agricultural inputs are available. Additional supporting stakeholders:

Extension Training and Information Service of the Ministry of Food Production (MFP).

Page 27: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

27

National Agricultural Marketing and Development Corporation (NAMDEVCO).

Agricultural Society of Trinidad and Tobago (ASTT)

Trinidad and Tobago AgriBusiness Association (TTABA).

Agricultural Development Bank. The activities of the supporting stakeholders are outlined in Annex 2.

5.4 Stakeholder Contact

Weekly progress meetings were held at the Engineering Division of the Ministry of Food Production in

Centeno, with representatives of the Ministry of Food Production (MFP, Engineering Division &

Agricultural Planning Division), the Water Resources Agency (WRA), the Water and Sewerage

Authority (WASA), and the Drainage Division of the Ministry of Environment and Water Resources.

Farmers in the Felicity Project Area and lessees of the former sugar lands in the Project Area have

been interviewed. Famers were interviewed, working 5-6 km’s East of the Project Area and members

of the last functioning County Agricultural Consultative Committee (CACC) in the region. Also farmers

working in the Felicity Project Area were consulted. A rapid appraisal was carried out, which gave

interesting results. The results are discussed in chapter 7 and presented in Annex 3.

The following institutes and organisations have been visited and consulted:

Extension Training and Information Service Division, Ministry of Food Production, MFP. County Caroni Engineering Division, Chaguanas, Ministry of Food Production, MFP. Environmental Management Authority, EMA. Drainage Division, Ministry of the Environment and Water Resources (NIDCO). Caroni (1975) Limited. Caribbean Agricultural Research and Development Institute, CARDI. Caribbean Industrial Research Institute, CARIRI. Trinidad and Tobago Meteorological Service Division. Town and Country Planning Division, Ministry of Planning and Sustainable Development. Project Office of Royal Haskoning/DHV, concerning Caparo River Basin Study. County Agricultural Consultative Committee, meeting with farmers 5-6 kms East of project

area; Organised by County Caroni Engineering Division, Chaguanas, Ministry of Food Production, MFP.

Meeting and interviews with lessees in the Felicity Project Area.

. A full list of meetings held, fieldwork carried out, and persons met (including details on addresses, tel.

numbers and e-mail addresses) is presented in Annex 12.

Page 28: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

28

6. EXISTING SITUATION IN THE FELICITY AGRICULTURAL AREA

6.1 Caroni (1975) Ltd. Lands

Of the 76,608 acres of available Caroni (1975) Ltd. lands, 27% (20,319 acres) have been allocated for

sub-division into 2-acre lots for ex-Caroni workers, as a part of the Voluntary Separation, Employment

Packages (VSEP). The Felicity Project area consists of 1300 acres in these former sugar lands. The

location has been indicated as the Felicity Project Area, and is presented in Annex1, Figure 1.1, and

in Photograph 1.1. The Site is a low lying flat area, which slopes gently to the coast, where mangrove

swamps protect the area against the sea at the west side. The government has constructed drainage

channels and provided infrastructure like roads and bridges.

6.2 Land lying fallow

Presently, only about 10% of the area is under cultivation. The reason is that many leases have been

given to persons, who worked for the Caroni Ltd, but were no farmers. Several of them have

attempted farming but failed, because of lack of experience, others never started any activity on their

leased lands. More factors have been cited as obstacles to mobilizing the two-acre agricultural plots

into production, like: long distance of the plots from tenant’s residences, legal restrictions imposed on

the use of the land, and lack of interest of land holders in agriculture. Some beneficiaries were

discouraged after learning that the ownership arrangement with the 2-acre plots is leasehold rather

than freehold, as they thought when they were signing the VSEP. A considerable area is lying fallow

at the Felicity site, but an even larger area outside the Project Area is uncultivated, resulting in a huge

loss of production and revenues. Government policy is clearly to increase agricultural production to

obtain food security.

6.3 Drainage, Flooding and Irrigation

Drainage is well managed in the Project Area. A grid of drainage channels has been constructed,

which drain the land under gravity. The land is not water logged in the wet season and there are no

reports of flooding in the Felicity Project Area. Maintenance is sufficient; once per year the MFP is

cleaning the channels. Because of the well-functioning drainage system, there is no high risk for

salinisation of the soil. The low salinity figures in the existing irrigation ponds (chapter 11.3) confirm

this. Annex 4 provides more information on drainage and flooding in the Project Area and the region.

At present there is no proper irrigation and waste water (re-use) system in the Felicity Project Area.

This is one of the reasons that a large percentage of the land is uncultivated. Farmers need sufficient

water also in the dry season to increase crop production. Unfortunately, access to water for

agricultural purposes has to face competition from domestic, industrial and service sectors, especially

during the periods of drought. This is why a major objective of the Project is to identify options for the

development of a sustainable irrigation and drainage system, with recommendations for a preferred

option.

Irrigation is practised in the Project Area during the dry season, but in a rather primitive way. Farmers

block the rivers with wooden planks and let the river water level rise. Then river water is pumped in

drainage channels, which are sometimes blocked as well. From there the water is pumped through

hoses and spray-pipes to irrigate the land. There is no system in place to re-use irrigation water. The

existing irrigation ponds are not functioning properly at present. Famers told (chapters 6.4 and 7) that

the volume is not large enough (20x20x4.5m). Once the pond is full, it is pumped empty in one day.

Filling the ponds occurs by rain and by pumping of river water. However most ponds are not located

near the river and lack proper water inlets. The soils in the area consist of heavy clay. When the

ponds are dry there is no replenishment from groundwater, although the ponds reach into the

groundwater. This also implies that leakage from the ponds, when filled with water, into the

groundwater is minimal. Crops that are grown by the farmers at present in the Felicity Agricultural

Area are: hot pepper, cucumber, eggplant, cassava, eddoes, occra, corn (limited), pumpkin, and

caralli.

Page 29: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

29

6.4 Transfer to Non Subsidised Agriculture

Most vegetables in Trinidad and Tobago are imported. Generally consumers don’t trust local crops,

because in newspapers and magazines is reported that for local produce pesticides and fertilizers are

extensively used and may not be safe to eat. Although in the Felicity Area farmers are practising

Integrated Pest Management, using as much as possible non persistent pesticides, the public is not

aware of it and prefers to buy imported vegetables. It all means a loss of entrepreneurial

opportunities, loss of capacity for national self-sufficiency, and increased vulnerability to food scarcity.

Importation of large amounts of food has increased food prices. This has triggered inflation and is a

burden for the citizens of Trinidad and Tobago in the low income group. However, it also provides

chances for the agricultural sector in T&T, because if food production can be generated in a

sustainable manner and with good marketing, then there is a vast internal market (T&T), profits can

be satisfactory and no subsidies are required..

One of the roles of the Ministry of Food Production (MFP) is to carry out agricultural research, to

develop technology, and to increase agricultural production (MFP Strategic Plan 2010-2015). Vision

2020 states development and modernising farm and agri-food systems to ensure sustained growth

and development in a dynamic environment. The agri-food system must be rapidly transformed into

an efficient and productive sector that is dynamic and competitive and provides food and nutrition

security.

6.5 Needs Assessment

For the needs assessment concerning the Felicity Project Area information was gathered during

meetings, field visits, and consultations, including the rapid appraisal that was conducted in the

project area on August 12th 2013 (chapter 7, Annex 3).

The needs in the Felicity Project Area, as expressed by the stakeholders, including the recipient

stakeholders, are as follows: more water, irrigation water, better lease conditions, better infrastructure,

better security, a famers association, additional training, market system, store houses, and cooling

facilities.

More water

More water is needed for agricultural development in the area. The required volume of additional

water needed could not be revealed. It depends on too many factors. To be able to make a good

living as farmer in the Felicity Area, more water is needed.

Irrigation water

When is expressed that more water is required, it is evident that especially more water is needed in

the dry season. Consequently, irrigation water is needed. It could not be stated how much irrigation

water is required, but in principle the volumes needed to be able to cultivate the land the whole year

round.

Better lease conditions

Lessees clearly expressed that the right to lease the 2-acre plots of the ex-Caroni lands, which is 30

years, is too short. Farmers hope to hand over their cultivated lands to their children or grandchildren

and for that reason would like to have a lease period of 99 years. Preferably, they even would like to

buy the land. A farmer should feel attached to their land; this is a worldwide phenomenon.

Better infrastructure

The government established infrastructure in the Felicity Project Area, like drainage channels, roads

and bridges. However, the famers would like the infrastructure to be improved. Roads need

improvement and proper maintenance; bridges should be repaired (there are holes in it). Drainage

canals are being cleaned each year, but with an irrigation system in place, this might not be sufficient.

Page 30: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

30

Better security

Farmers complained that crops are stolen from their fields. The idea is that a gate system might help.

A famers association

The need is felt for a farmer’s association of local famers with a flat and direct organisation structure,

to manage in cooperation an irrigation system and possible to combine efforts for transportation,

storage and marketing.

Additional training

Especially, there is a request for additional and continued training in Integrated Pest Management

(IPM). Farmers are familiar with IPM and buy as much as possible non persistent ‘safe’ pesticides, but

they realise that IPM is evolving and they would like stay informed.

Market system

If the irrigation system in the Felicity Project Area demonstrates to be successful and the concept is

duplicated to other areas in Central Trinidad, then a large market for crops may emerge. A proper

market system should then be in place to be able to pack and transport the produce in a proper

manner and to sell it for a good and compatible price. Even export should be considered.

Store houses, cooling facilities

Related to a market system for packing, transport, and strategic pricing, are store houses and cooling

facilities, where crops may be stored temporarily. A question to be answered then is where these

store houses and cooling buildings should be constructed; near the farm lands or near harbours or air

fields. Probably, the Extension Training and Information Service of the Ministry of Food Production

could facilitate such training.

6.6 Institutional Arrangements for Water Resources Management

The Water and Sewerage Authority (WASA) was established by an Act of Parliament in 1965 to

manage the water and sewerage sector of Trinidad and Tobago. The Water Resources Agency

(WRA) was appended to WASA as a division in March 1976 and is responsible for the management

and control of the Nation’s water resources, including agriculture. An description of WASA’s and

WRA’s objectives and tasks are presented in Annex 2.

Page 31: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

31

7. CONSULTATIONS WITH FAMERS, FARMERS ASSOCIATIONS

7.1 The Felicity Project Area

Farmers in the Felicity Project Area and nearby in the region have been consulted about their farming

practises and about the existence of and aspirations for farmers/water users associations.

Famers consultation

On July 9th. farmers were visited living 5-6 kms east of the Project Area in a region where formerly

tobacco was grown (Depot Road). These farmers are members of the last functioning farmers

association in the region, the County Agricultural Consultative Committee (CACC). The CACC, in

which a group of farmers is represented, meets monthly. It is a farmer’s forum; not a legal entity, set

up as a means of communication between farmers and the Ministry of Food Production. There were

plans to set up a RACC, or Regional Agricultural Consultative Committee, to act as a ‘layer’ between

the CACC’s and the Ministry. However, this was never implemented. A short report of the consultation

is provided in Annex 3.

Rapid Appraisal

On August 12th the County Caroni Engineering Division (Chaguanas) of the Ministry of Food

Production organised a consultation meeting with eight famers, who work in the Felicity Project Area,

The intention was to obtain through a rapid appraisal insight in what the famers do, what their wishes

are, and what problems they face. A rapid appraisal is a data collection method, aimed at supplying

information in a timely and cost-effective manner. It provides rapid information especially at the

project or program level. It is a quick, low-cost way to gather the views and feedback of beneficiaries

and stakeholders. In Annex 3. the results of the rapid appraisal are presented.

Highlights from the questions and remarks, and from the discussions held with the farmers are

presented below.

Famers Associations

There is a need for a farmer’s association, but it should be an association of directly involved farmers

in the area, and not a ‘distant’ organisation. In the association the famers could make agreements and

decisions concerning the management of an irrigation system, transport, marketing etc.

Willingness to Pay

If a reliable irrigation system would be installed and maintained by the government, then some

farmers are prepared to pay an affordable fee for the investment. But only when all farmers actually

pay. If irrigation water can be delivered at their plot(s) and the system is reliable, then most farmers

are prepared to pay for the water. But only if all farmers pay.

Leases

In the Project Area work both ex-Caroni workers, who have one or more leases on their name, and

farmers who have no lease themselves. One farmer had 4 leases on his name (one himself, 2 of

sons, 1 of deceased family member) and managed 20 leases of 2-acre plots from other lessees. The

farmers who have one or more leases on their name are not interested in subletting the lease,

because they are interested in farming. However, it is known that other persons who have a lease on

their name, and are no farmers, are interested in subletting. The lessees were not satisfied with the

lease conditions, because the leases are only granted for 30 years. They would like to have a lease of

99 years and preferably they would like to buy the land. Both reasons were mentioned also to

safeguard their farming business for their children/family.

Page 32: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

32

Crops

Crops that are grown by the farmers are: hot pepper, cucumber, eggplant, cassava, eddoes, occra,

corn (limited), pumpkin, and caralli. Additional crops that the farmers would like to grow are: sweet

potatoes, tomatoes, water melon.

Attitude to Farming

The eight consulted persons were all farmers, worked all full time as farmer and like to do that. All

farmers have the opinion that they can earn a good living with farming in the Felicity Area. They are

optimistic about the future, especially if they can carry out irrigated farming. There is a fair trust that

prices for crops will be good and stable.

Integrated Pest Management (IPM)

The farmers are familiar with Integrated Pest Management (IPM) and do practise IPM. They buy as

much as possible ‘safe’ pesticides, the pesticides that are not persistent. They want to use IPM also

to market their crops and get the confidence of the consumer.

Irrigation

All famers would like to practise irrigated farming. It is most wanted in the area.

Incentives / Subsidies

Some farmers made use of government incentives (subsidies) to buy equipment and a tractor. Other

famers are not officially registered as a farmer and therefore cannot make use of the offered

incentives. This is felt as a problem.

Assistance Needed

Assistance needed to be a successful farmer: good roads and bridges/infrastructure, irrigation system water security, training (a.o. continued training in Integrated Pest Management), tractor pool. Wishes / Aspirations of Farmers

Wishes and inspirations of farmers: irrigation system, expansion of area to cultivate (there should be a first preference for ex-Caroni workers to lease/buy land that has not been distributed yet), excess roads, good bridges, tractor pool. Problems famers face:

Problems that farmers face are; lack of water, security, crops are stolen, a gate system might help. Complaints

A complaint of the farmers was: there is a lease tax of TTD 200 per year, which is not felt as high, but

not all farmers pay the tax.

Crop Insurance

None of the farmers have crop insurance. The premium is too high.

7.2 International Experiences with Water User Associations (WUAs)

In many places word wide not all people pay their water bills. The same applies for payment for

irrigation services. In general, people are willing to pay for a proper service but they would like to see

the service working efficiently before starting to pay.

Page 33: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

33

Water User Associations (WUAs) are often formed by groups of farmers, who have shared interests in

the demand for and the management of irrigation water. WUAs can be large or small, and may be

formally constituted (as an NGO), or by informal arrangement.

Objectives of WUAs might be:

- To discuss the allocation of scarce water resources between different users (drinking water

supply, industrial, or irrigation) within a given area.

- To raise awareness of the actual water availability and the validity of claims of other water

users, in order to arrive at a just water sharing between different groups of users.

- To advise the organisation in charge of the actual distribution of water.

- To assist the member-farmers in the management of the water sources and the distribution of

available water.

Areas of responsibility:

- WUAs should not be too big, but also not too small; where possible to include a logical local

government level.

- Only to be set up where there is competition for water resources.

- In an area where people/farmers still feel a degree of community.

- Area to be selected, based on existing infrastructure and practical considerations.

Structure of organisation:

- Advisory body.

- Chaired by an elected chairman, not necessarily a government official.

- Members to be selected should represent a certain number of farmers. Irrigated agriculture

members to be elected with votes weight based on land area.

- Meeting regularly.

- Training of new members to be organised on a regular basis.

- Support from the government on technical issues when required.

In Annex 5 some international experiences on Water User Associations are presented from India,

South Africa, Egypt, and Palestine.

Page 34: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

34

8. CHARACTERISTICS OF THE FELICITY PROJECT AREA

8.1 Introduction

In Chapter 8 relevant physical and some socio-economic characteristics of the Felicity Project Area

are presented. Subjects are described like: morphology, geology, soils, and socio-economic aspects.

Hydrogeology, meteorology, and environmental aspects are presented in separate chapters.

8.2 Morphology

The Project Area is located in central west Trinidad along a low-lying coast. The site is rather flat, has

a level of 6-8 m above sea level (a.s.l.) and is sloping gently to the coast. West of the Project Area

there are mangrove swamps, which is presently military area. These mangrove swamps are important

for the Felicity Site and other agricultural areas along the west coast, because they constitute a good

natural barrier against storms and high waters from the sea.

8.3 Geology

Geologically, Trinidad forms the eastward extension of the South American mainland of Venezuela.

Ninety nine percent of the land area consist of sedimentary and metamorphic rocks. The oldest

identifiable rocks are of Jurassic Age. Almost every stage of the Cretaceous and Tertiary Period is

present. More than three quarters of the island is occupied by strata of Tertiary Age, which contain

practically all the known petroleum reserves of the island. These strata are outcropping, or are

covered by a thin layer of Quaternary sediments. The area has been tectonically active since

Oligocene time, resulting in a complex geological framework (de Verteuil et al, 2001). The tectonic

setup of the island consists of three up thrust ranges of mountains and hills, separated by two deep

sedimentary basins.

Relevant to the Project area, located in the central western part of Trinidad, are the Central Sands.

The main aquifers in the Central Sand consist of blanket-sands, and are differentiated in:

Sum Sum Sand;

Mahaica Sand;

Durham Sand.

The Central Sands are located on the southern limb of the Caroni Syncline. They outcrop at irregular

intervals in a band extending diagonally from Claxton Bay in a north-easterly trend towards the

Cumuto area, and dip in a north-westerly direction towards the Gulf of Paria. The entire region is

heavily faulted. The faults tend to be cemented and are relatively impervious. The sands are divided

into a series of isolated pockets, which are generally not hydraulically interconnected.

8.4 Soils

The soils in the project area can be described as brown/reddish and grey clays with a salinity of 0.1-

1% and low acidity. EC-values range from 0.24-2.24 μs Sand percentage is about 45%, silt 5%, and

clay 50% (plots 67,163,194, Soil Laboratory-LWDD, Min. of Agriculture). These soils are mainly heavy

clays, that hold excessive moisture when wet and get very hard when dry. During an interview with

farmers on July 9th, it was explained that in the dry season their soils were kept wet, to avoid getting

the soils hard as concrete. Maintaining sufficient moisture retention, favourable for optimal crop

growth, is a challenge when working with these soils. The use of lime to improve soil fertility is a usual

practise in the Caroni area, but it can be costly since the soils have a tendency to keep high acidity

levels.

A major problem encountered in many irrigation projects is soil salinisation, particularly when drainage

is poor. Salinisation can be defined as a situation of nutrient imbalance (excess of salts), which

causes damage to the soil structure, like crusting and compaction, reducing the infiltration of water.

Also, salts in soil or water may reduce water availability to crops to such extent, that yields are

Page 35: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

35

affected. To prevent soil salinisation good quality irrigation water is to be used and proper drainage is

crucial. Suitable irrigation water contributes to the nutrient balance and stabilises the soil structure.

Farming in the Felicity Project Area will generate a large volume of organic waste, which may be

utilised for the production of organic manure. This may provide abundant supply of alternative

fertilisers for the farms proposed for the Caroni (1975) Limited property. Using organic manure to

remediate soils will improve soil pH and increase fertility, while improving the structure and texture of

the soils. The latter phenomenon will help to reduce soil salinisation. It is a sustainable and

environmentally friendly practice that forms the basis for organic farming.

8.5 Socio-Economical Aspects

It is evident that at present in the Felicity Project Area there are hardly any economic activities. Only

about 10% of the land is being cultivated and thus the market of produce from the area is very small.

This situation could change dramatically if the Felicity Irrigation Project, as proposed in current report,

will be implemented. The area with its clayey soils and with sufficient irrigation water in the dry season

could produce crops during the whole year, thus increasing the farmer’s income.

For locally produced crops there is an image problem in Trinidad and Tobago. From reports in

newspapers and magazines, consumers got the opinion that agricultural produce from T&T would not

be healthy to eat. If this would change for the better, starting with the production of irrigated crops in

the Felicity Area under sustainable agriculture practices, then still a social marketing campaign would

be required to promote the awareness of the availability in T&T of new and healthy crops for an

affordable price.

Further economic aspects related to the implementation of the Felicity Irrigation Project are provided

in the chapter presenting design and feasibility.

Page 36: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

36

9. CLIMATE AND CLIMATE CHANGE

9.1 Climate of Trinidad

The climate of Trinidad is tropical with two major seasons: a dry season from January to May and a

wet season from June to December. During this wet season a short, dryer interim period is often

recognized, called the ‘petit careme4’. The average annual temperature is 26

oC. Diurnal fluctuations

are small. The humidity is high, averaging 50 - 85 percent, especially during periods of high

precipitation. Evapo-transpiration rate is high, and average sunshine is 6-8 hours daily.

Figure 9.1: Piarco Daily High and Low Temperature

Source: TT Meteorological Services Dept. The daily average low (blue) and high (red) temperature

with percentile bands (inner band from 25th to 75th percentile, outer band from 10th to 90th

percentile).

Inter‐annual variability in the Southern Caribbean climate is influenced strongly the El Nino Southern

Oscillation (ENSO). El Niño episodes bring warmer and drier than average conditions between June

and August and La Niña episodes bring colder and wetter conditions at this time. Trinidad and

Tobago lie on the southern margins of the Atlantic Hurricane belt and normally escape the passage of

cyclones and hurricanes, with some notable exceptions (C. McSweeney, 2008).

9.1.1 Rainfall

Precipitation in Trinidad is influenced by the prevailing North East trade winds. Since the mountains

run at an angle with the prevailing winds, this results in a rain shadow effect where rainfall decreases

from the east coast to the west coast and increases with elevation. On average, Trinidad receives

2,200 mm of rainfall annually with 70% to 80% during the wet season, from June to December. This

means that even during the dry season occasional rainfall occurs, see Figure 9.2.

The 75-year mean annual rainfall Isohyetal map (Figure 9.3) shows that the highest rainfall intensity

occurs on the southern slopes of the Northern Range and in the north Caroni Basin with a maximum

4 Typically 14-18 days, end of September – early October (source: TT Meteorological Services Dept.)

Page 37: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

37

depth of 3,800 mm. The west coast of Trinidad is in a rain shadow, resulting in a mean annual rainfall

of less than 1700 mm.

Figure 9.2: Rainfall distribution over the months, Couva-Tabaquite-Talparo5

Source: TT Meteorological Services Dept.

In the Felicity Project Area rainfall is between 1600 to 1800 mm per year (Figure 9.3). This means that

there is a net surplus of rainfall each year. If drainage conditions are indeed adequate this means that

the building up of salt in agricultural areas is not to be expected.

Figure 9.3: Trinidad Isohyetal Map

Source: (WASA, 2008-21).

Typically, the 1:4 year monthly rainfall (dry) is about 75% of the average rainfall (MFPLMA, 2011).

9.1.2 Evaporation and evapo-transpiration

Evaporation is usually high during the dry season, between April and June, due to high temperatures

and relatively low humidity, and it declines from July to December.

Evapo-transpiration is defined as the amount of water that is lost to the air by evaporation from water

bodies and transpiration from plants. The evapo-transpiration rate is high and varies from about 34%

5 Source of data: CRU CL 2.0 which is described in New, M., Lister, D., Hulme, M. and Makin, I., 2002: A high-

resolution data set of surface climate over global land areas. Climate Research 21:1-25 and Aquastat.

Page 38: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

38

of the total rainfall in the wet season to about 70% in the dry season (Smith, 1965). Based on

previous reports the average annual evapo-transpiration for Trinidad ranges from 850 mm to 1000

mm6.

Figure 9.4: Relative Humidity

Source: TT Meteorological Services Dept. The average daily high (blue) and low (brown) relative humidity with

percentile bands (inner bands from 25th to 75th percentile, outer bands from 10th to 90th percentile).

9.1.3 Wind

Over the course of the year typical wind speeds vary from 0 m/s to 7 m/s (calm to moderate breeze),

rarely exceeding 9 m/s (fresh breeze, Figure 9.5).

The highest average wind speed of 4 m/s (gentle breeze) occurs around May 5, at which time the

average daily maximum wind speed is 7 m/s (moderate breeze).

The lowest average wind speed of 2 m/s (light breeze) occurs around August 18, at which time the

average daily maximum wind speed is 5 m/s (gentle breeze).

6 State of the Water Resources, WRA, 2005

Page 39: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

39

Figure 9.5: Wind Speed

Source: TT Meteorological Services Dept. The average daily minimum (red), maximum (green), and average

(black) wind speed with percentile bands (inner band from 25th to 75th percentile, outer band from 10th to 90th

percentile).

9.2 Climate Change

For Trinidad and Tobago, climate change experts believe that in the future longer, drier dry seasons,

shorter and more intense rainy seasons, and a potential increase in sea level will occur. Because of

expected higher frequency and intensity of tropical storms, more flooding in low lying areas is

expected.

In brief, the Caribbean region global climate change (GCC) is expected to result in (CCCC, 2009):

a more hostile regional climate;

rise of temperature of about 0.2 °C per decade;

higher frequency and intensity of tropical storms and hurricanes;

more severe droughts;

rising of sea level. There are several scenarios that predict the climate change for the Caribbean area and Trinidad and

Tobago.

9.2.1 Change in temperature

Temperature observations

Mean annual temperature in Trinidad and Tobago has increased by around 0.6°C since 1960, an

average rate of 0.13°C per decade (period of 48 years). There are insufficient daily data to identify

trends in daily temperature extremes (C. McSweeney, 2008).

According to Vanessa Hyacinth-Ash (Piarco, 2011), the temperature showed an increase of 2.5°C

over a forty year period (period 1971-2010). This means a temperature rise of 0.63°C per decade.

Concerning observations, there is not a good resemblance in temperature rise per decade among

both sources. However, the periods were partly different, resp. 1960-2008 and 1971-2010. The latest

Page 40: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

40

period, 1971-2010 (Vanessa Hyacinth-Ash, 2011) shows the highest rise of mean annual temperature,

namely 0.63°C per decade (2.5°C o v e r a p e r i o d o f f o r t y y e a r s ) .

Temperature projections

Temperature data for Piarco, in the period 1971-2010, suggest average annual temperature rises of

maximum and minimum temperatures of 0.04894°C and 0.04551°C, which would be per decade

respectively 0.49 and 0.46°C (Jones, 2013). The rise of temperature in the region will be about 0.2°C

per decade, according to CGC (Caribbean Global Climate Change).

C. McSweeney (2008) provides a projection for the mean annual temperature for Trinidad and

Tobago. The range of projections by the 2090s, under any one emissions scenario, is around 1‐2°C.

Consequently, a temperature rise of 0.12°C – 0.24°C per decade is expected over a period of 82

years (2008-2090).The projected rate of warming is similar throughout the year.

The range of 0.12°C – 0.24°C per decade, as mean annual temperature rise, is quite large. To select

a figure – as the rise of mean annual temperature till 2050 – for the various scenarios for irrigation

development, the higher figure of 0.24°C has been selected. The reason is, that Hyacinth-Ash (2011)

comes with a evidently higher observation of temperature rise per decade than McSweeney. The

figure of temperature rise of 0.24°C per decade is quite close to the figure of 0.20°C per decade from

CGC.

9.2.2 Change in precipitation

Precipitation observations

There has been a small decline in rainfall and in number of rainy days over a forty years period.

Mean rainfall has decreased fractionally since 1960, but it is not a statistically significant trend. The

largest changes are in the wet season, where, on average, rainfall has decreased by 6.1 mm per

month (2.6%) per decade. For drainage analysis extreme daily rainfall data are required, however,

there are insufficient daily data to identify trends in daily rainfall extremes (C. McSweeney, 2008).

Precipitation projections

Projections of mean annual rainfall from different models are broadly consistent in indicating

decreases in rainfall for Trinidad and Tobago. Annual projections vary between ‐61% and +23% by

the 2090s, with median values of ‐13 to ‐21%. The proportion of total rainfall during heavy showers

decreases in most model projections, changing by ‐20% to +7% (2090s). Maximum 5‐day rainfalls

tend to decrease in model projections, changing by ‐29 to +20mm by (2090s, C. McSweeney, 2008).

Model simulations show wide disagreements in projected changes in the amplitude of future El Niño

events, contributing to uncertainty in future climate variability in projections for the region.

9.2.3 Sea level rise

The Caribbean islands are vulnerable to sea‐level rise. Sea‐level in the region is projected by climate

models to rise by the following levels by the 2090s (relative to 1980‐1999 sea‐level):

0.13 - 0.43 m (SRES B1);

0.16 - 0.53 m (SRES A1B);

0.18 – 0.56 m (SRES A2).

9.2.4 Impacts and mitigation measures

Major climate change phenomena which are relevant for T&T are: rise of temperature, more intense

rainfall, higher frequency and intensity of tropical storms and hurricanes, more severe droughts, and

rising sea levels. These climate change occurrences will have a certain impact. Relevant to

agriculture these impacts may be: lower crop production, more severe floods, higher frequency of

floods, soil erosion, coastal erosion, and salt water intrusion. These impacts of climate change

occurrences can be mitigated to a certain extent by mitigation measures. Several mitigation measures

Page 41: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

41

which are relevant to agriculture, together with the most prominent climate change occurrences and

their impacts, are summarised in Table 9.1.

Table 9.1: Climate change, impacts and mitigation measures

Climate Change Impacts of climate Change Mitigation Measures

Rise of temperature More intense rainfall, higher frequency and intensity of tropical storms and hurricanes More severe droughts Rising sea levels

Lower crop production Higher frequency of floods; more severe floods Soil erosion, hardening of soils Coastal erosion, salt water intrusion, flooding

Development of crops that can grow under higher temperatures, proper water management Good drainage systems, proper water basin management, reforestation, soil conservation Soil conservation, planting trees, wind breakers, crop rotation, mulching, proper water management Protection of coasts by wetlands, mangrove forests, dikes, producing salt tolerant crops

Page 42: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

42

10. HYDROGEOLOGY

10.1 Introduction

In Chapter 10 the hydrogeological aspects of the Felicity Project Area are presented. In Chapter 10

’Irrigation Water Requirements’, the hydrological characteristics of the area are provided, linked with

the subject of irrigation options for the Project Area.

Before 1981 60% of the total municipal water supply was provided by groundwater. After large

surface water plants were constructed, such as the Caroni-Arena Pump Storage Complex and the

North Oropuche Scheme, groundwater has accounted only for about 25% of the total water supply of

Trinidad. Few parameters are known of the aquifers in Trinidad and Tobago. Original pumping test

data of the tests performed were lost during a fire in the WRA office 1973.

Sufficient and accurate aquifer parameters are required to develop a groundwater model for an

aquifer and to obtain reliable output. No groundwater modelling has been applied for the aquifers of

Trinidad and Tobago so far. Methods used to estimate groundwater potentials for Trinidad and

Tobago are:

water balances (water storage/balance equation)

Maximum Sustained Yield (MSY) method.

10.2 Aquifers in Central Trinidad

In Central Trinidad the major aquifers are the Central Sand aquifers, consisting of blanket-sands.

They are differentiated in:

Sum Sum Sand;

Mahaica Sand;

Durham Sand. The Central Sands are located on the southern limb of the Caroni Syncline. They outcrop at irregular

intervals in a band extending diagonally from Claxton Bay in a north-easterly trend towards the

Cumuto area, and dip in a north-westerly direction towards the Gulf of Paria. The entire region is

heavily faulted. The faults tend to be cemented and are relatively impervious. The sands are divided

into a series of isolated pockets, which are generally not hydraulically interconnected. The division

between the Sum Sum and the Mahaica Sands is marked by a large structural shift.

General aquifer characteristics of the Central Sands (Talparo Formation) are:

aquifers consisting of fine to very fine marine sands;

the Sum Sum/Mahaica Sands and Durham Sands are separated by the Caparo clay Member of the Talaro Formation (300 m thick);

Age of Formation: Pleistocene;

aquifers are confined. The major source of recharge is direct infiltration by rainfall into the pervious valley soils, and

streambed infiltration.

10.3 Potential of Groundwater in the Project Area

The project area is situated in the western part of ‘The Central Sands'. The major source of recharge

is direct infiltration by rainfall into the pervious valley soils, and streambed infiltration.

Annex 6 presents the characteristics of the aquifers and the well fields in the region of the Project

Area. Nearest well field is the Carlsen Field Wellfield in the Sum Sum Sands, south-east and

approximately 3 kms from the Project Area. The lithology for the Sum Sum Sands is: fine to very fine

sand, some silts and clays. The average Specific Capacity is 163 m3/day/m, Transmissivity (T) is 225

m2/day, and hydraulic conductivity (K) is 5 m/day, indicating that this aquifer has a rather low

Page 43: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

43

permeability. The data on lithology coincides with data from wells near the Project Area. The Carlsen

Field Wellfield is over pumped and water levels are declining.

There are only a few data available on hydrogeology and groundwater related to the Project Area. On

the Hydrogeological Map of Trinidad (plate 255) is indicated that the area has a ‘marginal well yield

production potential of 20-100 igpm’, which is equal to a yield of 5.5-27.3 m3/hr. From the few

boreholes near the Project Area, only 2 logs provide data on pumping tests. The nearest by borehole

SDH478, just north of the Project Area, is not a production well and there are no pumping test data

available. The description of the lithology at that particular site would be worthwhile, however so far

the log could not be traced, Two boreholes, borehole 1635Cg (north-east, approx. 2.5 km from the

centre of the Project Area) and borehole 1637Cf (Carlsen Field Wellfield, approx. 2 kms from the

centre of the Project Area) provide pumping test data. The pumping tests were carried out for 6-8

hours with airlifting.

Borehole 1635Cg, the most representative production borehole for the Project Area (depth 45.8 m),

was drilled in a sequence of clay and sand. The static water level was 2.10 m b.g.l. and the pumping

level was 7.93 m b.g.l. Discharge was 8.19 m3/hr. The Specific Capacity is: Q/s = 33.6 m

3/day/m. The

lithology for borehole 1637Cf in Carlsen Field Wellfield (depth 33.6 m) is described as ‘reddish yellow

sand’. The static water level was 2.44 m b.g.l and the pumping water level 6.1 m b.g.l. Discharge was

3.54 m3/hr. The calculated Specific Capacity, Q/s = 23.3 m

3/day/m. The low figures of the Specific

Capacities for the 2 boreholes, resp. 33.6 m3/day/m and 23.3 m

3/day/m and the low discharges of the

2 boreholes of 3.54 m3/hr and 8.19 m

3/hr coincide quite well with the potential yield of 5.5-27.3 m

3/hr,

as indicated on the Hydrogeological Map of Trinidad (plate 255).

Another phenomenon, straight from farming practise in the Project Area – and brought forward during

the rapid appraisal (chapter 7) – is that once existing irrigation ponds are pumped empty, they are not

filling up from groundwater. It confirms the low permeability of the clayey soils in the Project Area,

since the irrigation ponds (depth 4.5 m) have been dug into the groundwater.

Conclusion

Realising that the Carlsen Field Wellfield (used for drinking water) just south-east from the Project

Area is over pumped and water levels are declining, and the permeability is generally low in the

Central Sands, the conclusion is that groundwater as a source for irrigation water should not be a first

option. Another reason is that salt water intrusion could be generated, which would be detrimental for

the quality of the groundwater in the Project Area, but could also be a risk for the drinking water

production in Carlsen Field Wellfield. Moreover, test results of a nearby borehole indicated a water

quality that was not adequate for irrigation (chapter 11.1).

Consequently, the potential for groundwater abstraction in the Project Area, in the shallow aquifers, is

low. There are no data on deep boreholes or deep aquifers in the project area, but these would not be

relevant, because abstraction of deep groundwater is expensive and not advised, because of a

serious risk of salt water intrusion. Pumping limited amounts of groundwater for irrigation, as an

additional or back up source for irrigation water might be a possibility, but in that case a proper

hydrogeological investigation should be carried out in the area to identify the fresh-saltwater interface

and the maximum yields that boreholes could be pumped.

Page 44: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

44

11. WATER QUALITY

11.1 Ground Water Quality

Parameters related to agriculture and specifically to irrigation are: pH, TDS, Electrical Conductivity,

Chloride, Ammonium, Phosphate, Sulphate, and the parameters Calcium, Magnesium and Sodium.

Especially levels of Nitrate, Ammonium, Phosphate, Potassium and Sulphate will give an indication

about the effect of fertilizer use on the quality of ground water.

Generally, water from the Sum Sum, Mahaica and Durham Well Fields have a high iron content (Las

Lomas, 11 mg/l) (Water Resources Strategy, 1999). Existing ground water quality data could be

obtained from two production boreholes near the project area, borehole 1635Cg north-east

(approx.2.5 km) of the Project Area, and borehole 1637Cf in Carlsen Field Wellfield south-east

(approx.2km) of the Project Area. The test results of the most representative sample (borehole

1635Cg) is presented in Table 11.1. No existing groundwater quality data are available on pesticides.

Table 11.1: Groundwater quality near the Project Area

Sample

parameter

description units/parameters results

WHO

standard

taken: 26-Jul-2010 Colour Hazen Units 19 < 15

ref: 420/22/00/1007ALES Turbidity N.T.U 5 < 5

Sample location: Aleson Readymix Ltd (well #1) pH

6.2 6.5 - 8.5

Electrical Conductivity μmho/cm 5850

Total Hardness CaCO3 mg/l 2000

Calcium Ca

2+ mg/l 447

Magnesium Mg

2+ mg/l 212

Chloride Cl

- mg/l 1005 < 250

Total Iron Fe

3+ mg/l 20 < 0.3

Source: WRA,#1940Cg/1635Cg

Generally, for irrigation water the following advisory levels for Electrical Conductivity are defined:

< 1,000 μmho/cm: unrestricted use;

1,000 - 2,000 μmho/cm: restrictions on several types of vegetables.

A guideline value of approximately 1,500 μmho/cm is generally used for potable water.

It is evident that the pumped water from borehole 1635Cg would not be suitable for drinking water, but

even for irrigation water – with its high EC-value – the quality is not adequate. The sample was not

compliant with WHO guidelines for potable water for Total Iron, Colour and Chloride and the Total

Coliform count was 500, indicating that the water was bacteriologically unsafe. As expected, the test

results of water from borehole 1637Cf in Carlsen Field Wellfield indicated that the quality of the water

was adequate for potable water (μmho/cm 800; Cl- 100 mg/l, Total Coliform count 3) and thus also for

irrigation water. Electrical Conductivity of tested water from borehole 1635Cg was 5,850 μmho/cm,

which indicates that the water is unsuitable for most vegetables.

An indication of salt water intrusion in groundwater in the Project Area could not be obtained, because

there are no boreholes in the project area itself of which data could be attained. However, the water in

borehole 1635Cg, north-east of the Project Area, has a rather high salt content (EC 5,850 μmho/cm),

which might indicate saltwater intrusion in groundwater. A proper hydrogeological study should reveal

whether the area suffers of saltwater intrusion.

Page 45: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

45

11.2 Surface Water Quality and Salt Water Intrusion

Incoming brackish water from the coastal zone – influenced by the tides with a range of 1.5-2m – west

of the Project Area and carried along in the Caparo River and Chandernagore River, may affect the

quality of surface water and groundwater. To investigate this possible phenomenon, available surface

water quality data from the Caparo River were examined (Annex 7). The time on which the

measurements were taken have not been recorded, so it is not possible to search for a correlation

with tidal fluctuations. The bulk of data is available from October 2005 till September 2008. The

sample location was east of the Felicity Project Area (Todd’s Bridge). No analyses on Chloride

content had been carried out, but amongst other parameters on Total Dissolved Solids (TDS) and

Electrical Conductivity. Two measurements were carried out during dry season (March 1991 and April

2009) and 15 measurements during the wet season (October, November, 2005, 2007, 2008).

Generally, water with TDS-values of 0-1,000 mg/l is regarded as fresh and water with values of 1,000-

10,000 mg/l as brackish. TDS values ranged from 362-533 mg/l, and even the 2 figures from the dry

seasons reached no higher than values of resp. 215 and 320 mg/l. The available lab tests indicate that

the Caparao River water at the sample point was fresh; no indication of salt water intrusion.

Electrical conductivity ranged from 124 to 673 μmho/cm during the wet season and the measurement

on 20-3-1991 gave a value of 470 μmho/cm. The average value during the wet season was 513

μmho/cm. The average for 2005 was 265 μmho/cm (3 measurements), for 2007 563 μmho/cm (12

measurements) and for September 2008 (1 measurement) the value was 410 μmho/cm. From 2005

till 2008 an up-going trend can be seen in Electrical Conductivity.

Generally, for irrigation water the following advisory levels for Electrical Conductivity are set:

< 1,000 μmho/cm: unrestricted use

1,000 - 2,000 μmho/cm: restrictions on several types of vegetables The conclusion can be drawn that the analysed water from the Caparo River would be suitable for

irrigation and would have no restrictions. At the same time the results indicate no saltwater intrusion

from sea in the tested water from the Caparo River at the sample location east of the Project Area.

11.3 Test Results on Water from the Felicity Project Area

To obtain knowledge on water quality in the Project Area 3 water samples were taken from existing

irrigation ponds (nos: 19, 116, and 240; map ‘Felicity Irrigation Ponds, Phases 1 & 2) and 2 water

samples from incoming waters from the Caparo River and the Chandernagore River. The complete

test results of the water samples from the Project Area are presented in Annex 8. Guidelines for the

interpretation of water quality for irrigation is shown in Annex 9 (FAO, 1904).

11.3.1 Pesticides

In the water samples none of the 50 analysed persistent and non-persistent could be detected. No

pesticides were found in the water from the Caparo River and the Chandernagore River and none in

the water samples that were taken in three irrigation ponds in the Project Area.

11.3.2 General chemical/physical parameters

Five samples were analysed on the following chemical/physical parameters: pH, TDS, Electrical

Conductivity, Chloride, Sodium, Calcium, Magnesium, Ammonia, Phosphate, Sulphate, and on a

range of 50 Pesticides. The test results of water samples on the chemical/physical parameters are

presented in Table 11.2.

Page 46: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

46

Table 11.2: Test results of water samples from the Project Area Sample Values

Sample number A1639/13 A1640/13

A1641/13 A1642/13 A1643/13

Parameters Analysed

Caparo River North of Plot 275

Pond on Plot 240 Felicity #2

Chandernagore River

Pond on Plot 116 Felicity 1

Pond on Plot 19 Felicity 2

pH 7.24 6.77 6.44 8.29 7.97

Electrical Conductivity, μS/cm (μmho/cm)

280.00 1072.00 52.40 5890.00 257.00

Total Dissolved Solids, mg/l

735.00 651.50 227.00 4292.50 257.00

Ammoniacal Nitrogen (as NH3-N) mg/l

2.34 0.78 1.38 0.55 0.74

Total Phosphates, mg/l

1.38 0.08 3.73 < 0.05 1.62

Chlorides, mg/l 31.55 0.88 me/l

183.56 5.18 me/l

46.41 1.3 me/l 692.79 19.54

me/l

17.45 0.49

me/l

Sulphates, mg/l 0.12 0.73 0.15 4.82 0.12

Calcium, mg/l 47.34 1.31 me/l

38.13 1.90 me/l

46.04 2.30 me/l

57.80 2.88

me/l

29.95 1.49

me/l

Magnesium, mg/l 11.02 0.91 me/l

25.43 2.09 me/l

10.26 0.84 me/l

211.34 17.38

me/l

10.08 0.83

me/l

Sodium, mg/l 26.19 1.14 me/l

115.14 5.01 me/l

28.63 1.25 me/l

759.27 33.02

me/l

45.09 1.96

me/l

11.3.3 Sodium Adsorption Ratio (SAR) Values

SAR-values were computed to obtain an indication of the suitability of the water in the Project Area for

irrigation purposes. High SAR-values reflect a high concentration of dissolved solids and indicate a

tendency of water to replace adsorbed calcium and magnesium with sodium, which damages soil

structure. The computed SAR-values are presented in Table 11.3.

The water classification for irrigation, based on SAR-values is:

Na SAR = ---------------- milli-equivalents per litre (me/l) (Ca + Mg)/2 < 10 excellent 10-18 good 18-26 fair >26 poor

Page 47: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

47

TABLE 11.3: SAR-VALUES OF WATER SAMPLES TAKEN IN THE PROJECT AREA

Caparo River North of Plot 275

Pond on Plot 240 Felicity #2

Chandernagore River

Pond on Plot 116 Felicity 1

Pond on Plot 19 Felicity 2

Sodium me/l

1.14 5.01 1.25 33.02 1.96

Calcium me/l

1.31 1.90 2.30 2.88 1.49

Magnesium me/l

0.91 2.09 0.84 17.38 0.83

SAR-value 1.0 2.5 0.8 3.3 1.7

11.3.4 Conclusions

Using the guidelines for the interpretation of water quality for irrigation (Annex 9, FAO, 1904), together

with computed SAR-values, and generally accepted values for TDS and Electrical Conductivity,

conclusions could be drawn for the analysed samples.

Table 11.4 presents a matrix of water quality aspects for the water samples taken in the Project Area.

None of the water samples showed detectable concentrations of pesticides (detection limit 0.02 μg/l).

The water from the Chandernagore River has the best quality, followed by the pond on plot 19. The

water from the Caparo River follows next. The irrigation pond on plot 240 has a mediocre water

quality for irrigation and the water quality in the pond on plot 116 scores negative for values of

Electrical Conductivity, Total Dissolved Solids, and Chlorides. Computing SAR-values, taking into

account the concentrations of Sodium (Na+), Calcium (Ca2+

) and Magnesium (Mg2+

), the values for all

samples appear to be good. It is not easy to indicate why the water from the pond on plot 116 has

evidently the lowest quality. Possibly the pond has not been refreshed by pumped irrigation water and

has been under evaporation for a long time, while the other ponds might have been refreshed. All the

ponds can be used to store irrigation water, because they are going to be filled and discharged on a

regular basis. In the future more, regularly, and also in the dry season, water quality tests should be

carried out in the Felicity Project Area; certainly when this irrigated agricultural land serves as a Pilot

Area.

Total Dissolved solids (TDS)

Fresh water: TDS-values of 0-1,000 mg/l

Brackish water : TDS-values 1,000-10,000 mg/l

Electrical Conductivity (EC)

Advisory levels for irrigation water:

< 700 μmho/cm: unrestricted use 700 – 3000 μmho/cm: slight to moderate restriction on use > 3000 μmho/cm: severe restriction on use

Page 48: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

48

TABLE 11.4: WATER QUALITY MATRIX RELATED TO IRRIGATION FOR SAMPLES TAKEN IN

THE PROJECT AREA

, Caparo River North of Plot 275

Pond on Plot 240 Felicity #2

Chandernagore River

Pond on Plot 116 Felicity 1

Pond on Plot 19 Felicity 2

pH + + + + +

Electrical

Conductivity

+ _ + _ _ +

TDS _ _ + _ _ +

Chloride + _ + _ _ +

Sodium + _ + _ _ +

Ammonia + + + + +

Phosphate + + + + +

Sulphate + + + + +

SAR-value + + + + +

Pesticides + + + + +

Page 49: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

49

12. ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

12.1 Introduction

Environmental management in Trinidad and Tobago is controlled by the National Environmental

Policy (NEP), developed and updated under the National Environmental Management Act of 2000.

The Act provides a rational and comprehensive framework for environmental management and

ensures that the natural resources of the country are used for social and economic development,

while protecting human health and supporting sustainable development.

Due to irrigation practises several components of the physical and human environment may be

affected, whether this is negative or positive. A strong positive impact is expected from the

introduction of irrigation on the socio-economic situation. Potential negative environmental impacts of

irrigation systems may be caused by agricultural runoff on surrounding rivers and downstream users,

affecting water, soil, flora and fauna (biodiversity), landscape, and human health (pesticides

&fertilisers, re-use of waste water).

Also from outside there are effects on cultivated land, of which the major impact is climate change.

These aspects are presented and clarified in next chapters. Environmental impacts that are found to

originate from the proposed source for the irrigation scheme are further elaborated on in the chapter

on design of the system. First a brief overview is provided of the Strategic Environmental Assessment

(SEA) of the Implementation of the National Sugar Adaptation Strategy, that was prepared in 2009

(Niras).

12.2 Positive Impact on the Socio-Economic Situation

Turning the former sugar lands of Caroni (1975) Ltd. in cultivated and irrigated farm lands, will have a

positive influence on the regional socio-economic situation. The arrangement to use the property for

agriculture shall generate positive economic returns, resulting in increased rural income and creation

of employment. When the irrigated farm lands prove to be profitable, than workers will be attracted to

these areas. These farmers will then produce and supply a wide range of fresh agricultural products,

which will most likely adjust prices downward. Consumers will benefit from healthier agricultural

products at lower prices. Also the issue of food security will be enhanced.

12.3 Strategic Environmental Assessment and Environmental Sustainability Plan

The objective of the EC supported Strategic Environmental Assessment (SEA) of the National

Adaptation Strategy (NAS) was to examine the environmental, social and economic impacts of

planned activities on the development of the former Caroni Ltd. properties. The SEA addresses

herewith the agricultural diversification from cane production to alternate agricultural uses. The SEA

focuses on the planned use of 76,000 acres, formerly used for cane production. The SEA brought its

recommendations within the existing planning, policy and objectives of the Government of Trinidad

and Tobago (GoRTT), specifically the country-wide strategic initiative Vision 2020. The importance of

the SEA for the Felicity Irrigation Project is the series of plans for Caroni (1975) Ltd. currently under

development. These include development of agricultural activities on 13 mega farms, but also on

14,000 acres of ‘2 acre plot’ leases.

An Environmental Sustainability Plan was development and implemented in 2012 by the GORTT for

lands formerly owned by Caroni (1975) Ltd., which were earmarked for agricultural, residential and

industrial development. The objective of the Environmental Sustainability Plan was the development

of these lands in an environmentally sustainable manner by all stakeholders, ensuring that the needs

of the present are met without compromising the welfare of future generations. It is from this detailed

examination of the planned alternatives for the Caroni lands, that mitigation and enhancement

measures were generated The following were the recommendations:

Page 50: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

50

Recommendations for agricultural development:

Conduct biodiversity surveys of all Caroni Ltd. properties for future baseline references.

Formation of farmer's cooperatives with development of management rules.

Soil remediation and water management schemes implemented in all mega farms and on all

2-acre plots, with at least 40% under organic cultivation.

Development of a joint sustainable agri-business degree program at the University of West

Indies (UWI) and the University of Trinidad and Tobago (UTT).

Increase domestic food production and consumption rate with local branding, with minimal

agro chemical usage.

Implementation of a Social Marketing campaign for local produce.

12.4 Impacts on Water and from Water

Irrigation may have a variety of impacts on water. If irrigation water with a load of fertilisers and

pesticides is discharged on surface water, it may have a negative impact on these waters (disturbing

aquatic systems), but also on areas reached by these surface waters. For example in the greater

Project Area the mangroves west of it, might in such a case be negatively affected. Enclosed

systems, because of limited contact with the surroundings, generally have minor impacts on the

natural environment. Small reservoirs can improve the availability of irrigation water, however they

may also - depending on the subsoil and the quality of the irrigation water - cause contamination of

groundwater. In addition, small reservoirs are liable to deteriorate the quality and the nutrient balance

in irrigation water as a result of warming and eutrophication. It all depends on the actual situation

(Niras 2009, MoP, 1999-6). At present the Caparo River is already heavily polluted by domestic waste

waters, farm chemicals and industrial effluents. In case the preferred options for irrigation are

implemented in the Felicity Project Area, then more water of better quality will be transported to the

Project Area and the environmental situation concerning impacts from incoming waters will improve.

Reservoirs, open water conveyance and distribution systems for irrigation will lead to water losses by

evaporation and will have a slight influence on the microclimate. Because the best option for the water

source for irrigation water in the Project Area is surface water from the Caparo River, the protection of

the Caparo River watershed is important. Closed loop systems, if included in the design of the

irrigation works, will reduce the required amount of ‘fresh’ irrigation water.

Water quality aspects and test results of water samples taken in the Felicity Project Area are

presented in chapter 11.

12.5 Impacts on Soil

Impacts on soils vary in nature, however related to irrigation development there is a specific set of

potential impacts that can be identified. Table 12-1 presents the potential impacts from irrigation

activities on soils and their mitigation measures.

Table 12.1: Potential impacts on soils from irrigation activities, mitigation measures

Potential Impacts Mitigation Measures

Erosion of embankments of channels and reservoirs Sedimentation of channels Damage of soil structure, soil erosion by water and wind Damage to soil fertility and over fertilisation, pollution

Stabilising embankments, ground covering plants with dense root systems Flushing of channels, cleaning Soil conservation, crop rotation, mixed cropping, mulching, improvement of soil structure and nutrition by organic manure and compost Balanced use of fertilisers, Integrated Pest Management

Page 51: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

51

Salinisation Impact of construction activities, spilling of materials (cement, oil), compaction Production of organic waste

Proper drainage Proper environmental management and monitoring Proper waste disposal and composting

12.6 Impacts on Flora and Fauna (biodiversity)

When irrigation is introduced, certain species of flora and fauna may disappear, while its management

may favour other species. A reduction in dry biotopes is set against the replacement by aquatic

biotopes. Increases and decreases in the presence of particular species may have both positive and

negative consequences for man and nature, but because most of the area was, and will be, under

cultivation the impact is negligible. It must be realised that the Project Area is not a nature reserve

and has been under extensive cultivation for sugar cane already for a long time. It is even felt that

prolonged cultivation of the a mono-crop sugarcane – combined with spraying of (at that time)

persistent pesticides – has resulted in extensive loss of biodiversity within the area. There are reports

of the re-appearance of some animals and plant species into the area since the closure of the sugar

lands. The renewed agricultural activities developed on the 2-acre plots should have a positive impact

on biodiversity, if a sustainable approach is maintained.

12.7 Impacts on Landscape

The nature of the landscape in the Project Area will not change significantly and ‘nature’ as such has

never been a characteristic of the Felicity area. It was and is an area under extensive cultivation with

all characteristics of that, like a quite monotone cultivated landscape with little space for trees or wild

plants.

12.8 Impacts on Human health

Irrigation schemes may create health risks. The main health risk is caused by the use of pesticides

and to a lesser degree by overdoses of fertilisers, re-use of irrigation water and use of untreated

waste water, and water borne diseases.

12.8.1 Pesticides and fertilisers

Although irrigated agriculture is not necessarily a type of cultivation that gives higher risks than other

types of farming, the risk of the use of pesticides must be taken into account. Pesticides may have

toxicological, and carcinogenic properties, as well as effects on, and risks for, the balance of nature.

Active ingredients are accordingly assigned to toxicity classes. The FAO Code of Conduct, adopted in

1985, contains recommendations on the registration, distribution and use of pesticides. Numerous

pesticides involving comparatively high risks have been taken off the market and restrictions are

imposed on their use.

Organo-chlorine Pesticides

Heptachlor and Lindane are both broad-spectrum organo-chlorine insecticides. Lindane

slowly degrades by soil micro-organisms.

Heptachlor persists for prolonged periods in the environment. It is converted to the more toxic

heptachlorepoxide in the soil, in plants and in mammals. Heptachlorepoxide undergoes bio-

concentration in many species and accumulates in the food chain. Generally, since 1975 the

use and the production volume of heptachlor have declined, because of a registration

suspension notice by the EPA (1976) for all food crop and home use. However, use of

Page 52: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

52

heptachlor for termite control and non-field crops continues.

DDT and its derivatives are persistent organo-chlorine insecticides. They are stable under

most environmental conditions and are resistant to complete breakdown. In their different

isomeric forms they are rather insoluble in water, but soluble in organic solvents. Its use has

been restricted or prohibited for ecological reasons in many countries, also because of the

increasing resistance of pests to this type of pesticides. DDT is still used in the public health

sector in several tropical countries.

In particular, use of persistent, broad-spectrum agents is internationally banned. Preference should be

given to pesticides with low toxicity, a selective action and low persistence. The ‘dirty dozen’ comprise

the following fifteen active ingredients which should be proscribed in view of the substantial risks

attached to them:

Insecticides: Chlorinated hydrocarbons: aldrin, chlordane, DDT, dieldrin, endrin, HCH-mixed

isomers, heptachlor, lindane, camphechlor; Carbamates: aldicarb (proprietary name: Temik);

Organophosphates: parathion (E 605); Other insecticides: dibromochloropropane (DBCP),

chlordimeform, penta-chlorophenol (PCP).

Herbicides: 2,4,5-T (proprietary name: Weedone)

Another risk of the use of pesticides is the unsound disposal of leftovers and empty packaging

materials. Pesticides should be used within the framework of integrated plant protection methods

(IPM).

Mitigation measures Mitigation measures related to the use of pesticides and fertilisers are:

Use biodegradable substances to control pests and diseases.

Employ cropping systems that encourage low fertilizer usage.

Use natural fertilizers to complement the use of organic manure.

Provide practical alternatives to the use of chemicals.

Adapt integrated farming systems that are designed to control pests and diseases.

Ensure that biological control methods are available, accessible and affordable to farmers.

Train farmers in Integrated Pest Management.

Provide training on water management, quality and conservation awareness.

Use biological control measures and Integrated Pest Management practices.

Reinforce the use of proper protective gear.

Encourage farmers to form cooperatives to obtain easier access to training and support.

12.8.2 Re-use of irrigation water and use of untreated wastewater

The use of wastewater in irrigation water poses risks to both farmers and consumers. However, if a number of rules and guidelines are followed, even untreated wastewater can be used to produce horticulture crops. In general irrigation water is a mix of treated wastewater and surface water, which may in itself be polluted with sewage. For a successful application of irrigation water, which includes a proportion of wastewater, the

following topics need to be addressed:

Often is stated that (treated) wastewater may not be applied in agriculture, however in

practice irrigation water is commonly polluted with sewage in various degrees. A good

approach would be to prepare guidelines which clearly indicate, for each quality class of

irrigation water, which crops can be irrigated and which precautionary measures field workers

need to take. Both to protect themselves and to prevent contamination of crops.

Page 53: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

53

There needs to be agreement on the level of treatment of wastewaters before discharging it

into surface water or directly into an irrigation conveyance system. This is similar to existing

guidelines on wastewater discharge and surface water pollution (Ministry of the Environment).

It is important that consumers have faith in the authorities and in their competence to enforce

standards, ensuring healthy, uncontaminated food. In practice this may be a problem in

Trinidad, as illustrated by the public conviction that food crops contain excessive and harmful

levels of agro-chemicals.

12.8.3 Waterborne diseases

Waterborne diseases, particularly schistosomiasis and onchocercosis, may occur as a health risk in

irrigation systems by stagnant water. Depending on how it is transmitted (via human excretion),

schistosomiasis may well occur in areas being irrigated for the first time. Irrigated farming can also

promote the spread of hookworms and eelworms. Malaria, which often spreads in areas where large

irrigation schemes are being realised, can constitute a problem in small-scale projects using open

reservoirs and water conveyance systems. Because irrigation has so far not widely been introduced in

Trinidad and Tobago, waterborne diseases related to this type of agriculture is not common. It is

advised to monitor a possible spreading of waterborne diseases in areas where irrigation is being

introduced.

Page 54: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

54

13. IRRIGATION SECTOR STUDY

Given the current status of irrigated agriculture in the country where the present irrigated area is small

(approx 5,000 ha7) and the corresponding water allocation to the sector also small (less than 5 % of

the Public Water Supply) the result is that agriculture in Trinidad and Tobago is practised essentially

under rain fed conditions. The implications of a rain fed system of agriculture is that the sector will

continue to be under-developed with the majority of arable land fallow during the first 6 months of the

year and tree crop production at a subsistence level. Provision of sustainable irrigation and drainage

projects would allow for maximum use of the land (reference: ToR).

Generally, the introduction of irrigation provides more reliable yields and incomes, though it also

entails a significant investment and needs ongoing operation and maintenance (O&M). While the

O&M costs are usually translated into fees to be paid by the beneficiaries, e.g. the farmers, the initial

investment is often paid for by the government or by a multi-lateral financing agency. Surprisingly this

is also often the case in developed and rich countries such as the USA or France.

Irrigation generally covers the following components:

- provision of a water supply through storage in reservoirs, use of river water and/or tapping of

groundwater;

- conveyance and distribution of irrigation water by open channels or pipelines;

- field application systems of irrigation water by means of sprinkling, drip irrigation flooding, basins,

border strips, and rills;

- drainage by means of open or concealed systems.

Irrigation is typically thought of as being applied in arid or semi-arid areas, but most of the worlds’

irrigation takes place in areas that have relatively large amounts of rainfall, only the rainfall is

unevenly distributed in place and/or time. This is the case in Trinidad, where irrigation is primarily

applied during the dry season, typically the months from January through May/June. An interesting

conclusion of the calculation of crop water requirements is that even during the rainy season a clear

need for irrigation water exists, which will become more pronounced due to effects of climate change

(see calculations later in this chapter).

In this Chapter an overview of available information and knowledge is presented, providing an

understanding of the irrigation sector for the former sugar growing areas, located on the low areas in

the west of Trinidad. Within the scope of this study, which is limited in time and manpower, the scope

of this overview is necessarily linked to the available time and available data, as it was not possible to

plan more than very limited number of site visits and even the collection of relevant documents and

reports.

13.1 Water resources in the former sugar growing areas

This assessment is done as a desk study and is based on the information made available to the team.

The conclusion based on this information is that not very much can be added to the conclusions

drawn in the (MOP-1999-6) study and the (WASA, 2004-21) Water and Wastewater Master Plan and

Policy. If irrigated agriculture is to be expanded at the rate that was planned in 1999 (e.g. to more

than 100,000 ha for Trinidad) the available surface water resources will not be sufficient to meet the

full potential irrigation requirements. For specific potential irrigation areas the type of crops and

especially the water requirements of these crops need to be matched with available irrigation water

resources, taking into account competing water requirements for domestic water supply and possibly

industry.

7 In other publications areas as small as 3,000 ha are mentioned (MOP-1999-6 and WASA 2004-21)

Page 55: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

55

The calculation for the irrigation water requirements for the Felicity pilot area will show that the

provision of optimal irrigation water supply is only possible for limited parts of the former sugar lands

and has to be linked to specific sources8. Use of individual ponds on the land of the farmers is an

option that does not rely entirely on the availability of surface water in the rivers, but the amount of

water that can be stored without an undue claim on arable area is not sufficient to bridge the entire

dry season. This was rather strongly stated during stakeholder meetings with farmers of the Felicity

Pilot Area (Chapter 7). However, the ponds are an important storage reservoir, if built and used

correctly.

One main source of surface water for both water supply and irrigation in the former sugar growing

areas is the Caroni River. The hydrology of this river has been extensively studied and is again being

studied by the ongoing Caroni River Basin Drainage Study (Royal HaskoningDHV, Deltares, for

NIDCO). Another very relevant study is the Feasibility Study and Conceptual Design for the Caparo

River Basin Flood Mitigation and Water Supply Project (in short: Caparo River Basin Study) by the

same consortium, as this concerns the river that may be used as a source of surface water for the

Felicity pilot site. The results of these studies will be available sometime during the course of next

year (2014). It is recommended to use the final results of these studies to fine-tune the design for the

Felicity pilot area, and to refer to these studies when deciding to implement other irrigation schemes

based on the Felicity pilot design.

Meanwhile a very constructive dialogue and cooperation was established, in which the consultants

could discuss the irrigation water requirements of the Felicity Area with the Caparo River Basin Study

consultants and even at a workshop at Ministry level, to match overall water availability in the Caparo

Basin with demand from various stakeholders (mainly WASA). More details on the (preliminary)

results are given in Chapter 14, Options.

A comprehensive overview of the overall surface water availability, matched with projected irrigated

agricultural demands has been made in the study (MOP-1999-1B). The full annex was not available to

the consultants during the study. Table 13.1 shows the results of that study, indicating that at that time

and with the then used projections it was demonstrated that water resources would be insufficient in a

large proportion of the watersheds, including the Caparo River watershed.

8 The fact that it is very difficult to ensure adequate supply of irrigation water to the Felicity project

area shows that even in a basin with a supposedly relative abundant supply of surface water, irrigation is a challenge. For other areas, both inside and outside the Caparo Basin, the challenges are even larger.

Page 56: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

56

Table 13.1: Water Availability per Watershed Based on 1999 WRMS

Source: (MOP-1999-1B)

13.2 Current, future and potential agricultural water resource needs

13.2.1 National situation irrigated areas

Reference is made to the report “The Development of Water and Waste Water Master Plan and

Policy for Trinidad, Chapter 21: Water Supply and Related Infrastructure Needs (WASA, 2008):

Irrigated agriculture is not presently a major water user in Trinidad or Tobago. The total current area

of irrigated agricultural land in Trinidad is estimated at about 3,050 ha9, with an estimated total water

demand of about 12 MCM10

per year.

Irrigation in Trinidad involves small diversions from creeks and streams with built works by private

individuals. Gravity flow irrigation can be found on a small scale on the Aripo, Guanapo, and San

Juan Rivers, while the larger irrigation systems are on the Caroni and South Oropouche Rivers.

The largest irrigation system is the Caroni system. This system diverts water from the Caroni River to

service the surrounding rice fields. Other irrigation systems are small-scale and are located in St

George, Nariva/Mayaro, St Andrew/St David, Victoria, and St Patrick. The main sources of irrigation

water for the Caroni River Basin are San Juan, St Joseph and Caroni rivers.

Agriculture in Trinidad is mainly rain-fed since there is negligible irrigation infrastructure. Access to

water for agriculture purposes has to face extreme competition from the domestic, industrial and

service sectors, especially during the periods of drought.

Since there is no information available on the existing or proposed national/regional drainage or

irrigation infrastructure from WASA or Drainage Division, GENIVAR had difficulty to analysis the water

available for each farming location and to propose alternative water supply strategies (WASA, 2008-

21).

9 This figure comes up every time, it is also mentioned in the 1999 DHV study for the Ministry of Planning. A new

inventory is obviously needed. Note: hectares, not acres. 10

This translates to about 400 mm per year; it is not clear if this is net requirement and if it is only for the dry season.

Page 57: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

57

13.2.2 Former Sugar Growing Areas – potential irrigation demand

The situation in the former sugar growing areas was well described in the Strategic Environmental

Assessment (SEA) of the Implementation of the National Sugar Adaptation Strategy for Trinidad &

Tobago (NIRAS 2009). Relevant parts of this report are quoted below.

As described in Chapter 3 the Caroni (1975) Ltd. enterprise was liquidated and the lands were to be

distributed and developed. There are three main alternatives for the Caroni (1975) Ltd. properties:

Agricultural, residential and industrial development. For the purpose of this study only the agricultural

lands are considered.

The agricultural lands are to be developed either as mega-farms which are commercial entities, or as

2 acre plots provided to 7000 former Caroni (1975) Ltd. Workers. These are currently underutilized

and are being considered for development as cooperatives in which the title holder would be able to

lease his land to a cooperative in return for a portion of the profits. The cooperative plans for the 2

acre plots are still under development (NIRAS 2009, Chapter 3.2).

Agriculture continues to be a principal development alternative proposed for the former sugarcane

lands at Caroni (1975) Limited. Of the 76,608 acres of available lands, 27% (20,319 acres) are

allocated for sub-division into two acre lots for former sugar workers as a part of their Voluntary

Separation, Employment Packages (VSEP). While estimated at approximately 7000 farmers, Caroni

workers will be recipients of these two-acre plots, and the precise number of beneficiaries remains to

be finalized.

Approximately 2,263 acres of land are allocated for the development of 13 commercial (mega) farms.

The lot sizes for this category of farms range between 100 acres and 267 acres. There are plans to

formalise the occupancy of several informal agricultural land settlers (squatters), who are currently

occupying 6% (4,222 acres), into legal land holders. It is not clear as to what arrangements are in

place to deal with some 11,109 acres (15%) that collectively grow citrus/tree crops, rice, livestock,

pasture and aquaculture under the former Caroni 1975 management structure. The future

arrangements of existing tenants, currently occupying 16 % (11,861 acres) need to be ratified as well.

A total of 16,703 acres (24 %) of the Caroni land are identified as residual lands since the closure of

the sugar industry and could be earmarked for meaningful alternative developmental activities (NIRAS

2009, Chapter 3.2).

To summarise the above: any consideration for irrigated agriculture is to aim at the mega farms (2129

acres) and the 2-acre plots (7305 total developed by 2009 (NIRAS 2009, Chapter 3.2)). As the mega

farms are flexible in the choice of crops it is not simple to estimate possible irrigation water

requirements. However, the methodology presented in this report can be used once the crops and

cropping patterns are known.

For the 14,610 acre in 2-acre plots it is assumed that a mix of vegetable crops will be planted during

the dry season (as well as in the rainy season), but this will depend on the availability of a reliable

source of irrigation water for the specific area. Another assumption that needs to be made is that the

farmers will use the irrigation water in an efficient manner. How this is to be achieved is explained in

Chapter 16, Design.

Irrigated rice is already established (in the lower Caroni basin), and described in (MoP 1999-6). No

evidence of plans for extension of the rice growing area was encountered, as the Ministry seems

acutely aware of the limited availability of water resources for irrigation.

13.2.3 Irrigation water requirements – approach

A comprehensive study into the irrigation water requirements as part of the overall national Water

Resources Management Strategy was carried out by (MOP 1999-6). The method used in this study is

explained in detail in Annex 10, Irrigation Water Requirement; it is based on the normal approach

described in (FAO, 1977) and applied worldwide.

Page 58: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

58

13.2.4 Calculated irrigation water needs for the Felicity Pilot Area

Applying the theory outlined in Annex 10, the following steps are taken to calculate the gross volume

of irrigation water required for the Felicity Pilot irrigation scheme.

1. Determine reference crop evapotranspiration, ETh (Table 18.2) (a)

2. Apply crop coefficient: Vegetable kc of 0.73 to be used for the Felicity Pilot area.(b)

3. Calculate crop evapotranspiration (mm) per month for January-June

4. Calculate effective precipitation (Table 18.4). (c)

5. Estimate the irrigation efficiency at scheme level: 65-70% (75% for tertiary/field application, 90%

for the secondary distribution system) (d)

6. Calculate the net irrigation requirement IR per month (mm)

7. Add leaching requirement or ensure that this is covered in the irrigation losses + rainfall11

8. Calculate net irrigated area (gross area less 5% for infrastructure)

655 2 acre plots = 530 ha – 26 ha (on farm ponds) = 504 ha

9. Calculate the volume of irrigation water requirement per month for the entire area Vscheme

10. Estimate losses for the conveyance from the source of irrigation water to the Felicity Pilot

Scheme intake/distribution works (pipe: 5%; river: range from 10-20% depending on illegal water

abstraction upstream.

11. Calculate the total required volume of irrigation water Vprimary

12. Repeat 3 to 11 for the selected values for climate change scenario 2050 (Table 13.3, Table

13.4).

The results of the calculation for 2013 are shown in Table 13.2. An explanation of the parameters and

the datasets used is given below the table.

Table 13.2: Irrigation water volume for Felicity Pilot irrigation scheme, 2013

Parameters / datasets used for the 2013 scenario

1975-1995 meteorological data from Piarco. Average monthly values, corrected for temperature trend to 2013 based on (MOP 1999-6)

11

For the Felicity area it is assumed that the leaching requirement is met by the rainfall surplus and the losses at tertiary level; this is under the condition that drainage is good / adequate. See also the Chapter on Flooding and Drainage and Chapter 15 (Design).

Month

January 3.9 0.73 2.8 87.7 15.2 72.6 541.7 601.8 570.2

February 4.5 0.73 3.3 91.0 11.6 79.4 592.8 658.6 624.0

March 4.9 0.73 3.6 111.6 6.9 104.7 781.9 868.8 823.1

April 5.1 0.73 3.7 111.5 7.2 104.3 778.9 865.4 819.8

May 4.9 0.73 3.6 109.9 24.9 85.0 634.3 704.7 667.7

June 4.1 0.73 3.0 90.8 61.1 29.7 221.5 246.1 233.1

July 4.2 0.73 3.1 94.2 69.8 24.4 182.4 202.7 192.0

August 4.2 0.73 3.1 93.5 69.6 23.9 178.4 198.2 187.8

September 4.2 0.73 3.1 90.0 52.9 37.1 277.3 308.2 291.9

October 4.0 0.73 2.9 86.6 45.9 40.7 303.8 337.5 319.8

November 3.7 0.73 2.7 76.2 58.3 17.9 133.3 148.2 140.4

December 3.6 0.73 2.6 76.5 32.3 44.2 329.7 366.3 347.1

Dry Season 512 446 3329 3699 3505

Total 1120 456 664 4956 5507 5217

ETh

(mm/d)

kc

ETc

(mm/d)

P e

(month)

IR

(mm/m)

V primary

Pipes

(1000 m3

/ month)

ETc

(month)

V scheme

(1000 m3

/ month)

V primary

Caparo

(1000 m3

/ month)

Page 59: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

59

1971-2010 rainfall data Piarco, 75% monthly rainfall (MFPLMA, 2011); reduced by 10% for Felicity area based on the isohyetal map of Trinidad (WASA, 2008-21); adjusted for climate change outlook (only wet season, 6.1mm decrease monthly average rainfall per decade (Table 18.2)).

Vscheme: efficiency tertiary at 75%, secondary at 90%

Correction T (temperature, max and min): average of 1975-1995 is 1985; difference with 2013 is 28 years. This means that the average of 1975-1995 is to be corrected with: 0.672 °C (28 years x 0.024 °C).

Correction Pe: The midpoint of 1971-2010 is 1990; the difference with 2013 is 23 years. An estimate of the factor between average and 75% rain is 0.74 for June-December. This means that the Pe of 1971-2010 is to be corrected with -10.4 mm for each month of the wet season (here taken as June-December)

12.

Vprimary: efficiency primary conveyance at 95% (pipe) or 90%-80% (Caparo River).

Parameters explained

ETh Reference Evapotranspiration (based on Tmin, Tmax, relative humidity (average), wind, sunshine, all as monthly values, see Table 18.2); mm/day.

kc Crop coefficient: ratio of given crop to ETh, taken as 0.73 for vegetables.

ETp Potential Crop Evapotranspiration kc x ETh, mm/d and mm/month

Pe Effective precipitation, mm/month

IR Irrigation Requirement, mm/month

LR Irrigation Requirement, mm/month

Vscheme Irrigation Volume for net irrigated area of the Felicity Area, including tertiary and secondary efficiency (75% and 90% respectively for spray pipes and piped conveyance)

Vprimary Irrigation Volume for net irrigated area of the Felicity Area including conveyance losses primary system efficiency (95% pipeline, 90%-80% Caparo River)

The resulting irrigation water requirement for the Felicity Area for 2013 is presented in Table 13.2 and

Figure 13.1.

13.2.5 Future and potential water needs

Climate change effects are not taken into account in the calculation presented in Chapter 13.2.4. In

general the parameters that determine ETh are subject to change due to projected climate change,

especially the temperature, and this means that the ETh is expected to become higher in the future.

Likewise it is expected that the rainfall during the dry season will stay the same, while the monthly

average rainfall volumes will decrease. The Pe, the effective rainfall available for the crops will thus

decrease during the rainy season. This effect is considerable, and higher than the effect of rising

temperatures on crop evapotranspiration.

As the GoRTT has not decided on a policy regarding which of the IPCC scenarios and which

downscaling values to use the consultants have selected a likely set of climate change outlooks for

selected parameters.

The consultants advise to use the following figures (Table 13.3) as best figures to work with:

Temperature: increase of on average 0.24°C per decade. Precipitation: decrease only during wet

seasons of on average 6.1 mm per month per decade. The precipitation for the dry season is not

12

This is based on the assumption that the recommended trend based on the selected climate change scenario (see Chapter 9.2) started already in 1971, the start of the rainfall data series used in this study. However, in : MFPLMA, 2011 the trend for average yearly rainfall data appears to be flat. If the correction is not applied this will result in a significant reduction (10%) of the calculated water requirement.

Page 60: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

60

expected to change significantly (McSweeney, 2008). Note that this decrease is a decrease of the

average. No guidance on wind, humidity and sunshine was available, so for the 2050 scenario these

are kept the same (Table 18.2). For more details see Chapter 9, Climate and Climate Change.

The resulting irrigation water requirement for the Felicity Area for 2050 is presented in Table 13.5 and

Figure 13.1.

Figure 13.1: Felicity Scheme Irrigation Requirements, 2013 and 2050 (mm/month)

Table 13.2: Crop Water Use Parameters - Climate Change adjusted

Year

Parameter

2050

Maximum Temperature (oC) +0,24° per decade

Minimum Temp (oC) +0,24° per decade

Mean Rel. Humidity (%) no guidance

Mean Wind velocity (km/day) no guidance

Sunshine hours (h)

Precipitation (mm) dry season

no guidance

no change expected

Precipitation (mm) rainy season 6.1 mm decrease per decade per month

0.0

20.0

40.0

60.0

80.0

100.0

120.0

Sch

em

e Ir

riga

tio

n R

eq

uir

em

en

t (m

m/m

on

th)

2013 irrigation

2050 irrigation

Page 61: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

61

Table 13.3: Climate Change Adjusted Reference Crop Evapotranspiration for 2050

Table 13.4: Irrigation water volume for Felicity Pilot irrigation scheme – 2050

Parameters / datasets used for the 2050 scenario

1975-1995 meteorological data from Piarco. Average monthly values, corrected for temperature trend to 2050 based on (MOP 1999-6) (Table 13.4).

1971-2010 rainfall data Piarco, 75% monthly rainfall (MFPLMA, 2011); reduced by 10% for Felicity area based on the isohyetal map of Trinidad (WASA, 2008-21); adjusted for climate change outlook (only wet season, 6.1mm decrease monthly average rainfall per decade (Table 18.2)).

Vscheme: efficiency tertiary at 75%, secondary at 90%

Maximum

Temp

Minimum

Temp

Sunshine

hours

ETh

(oC) (

oC) (h) (mm/day)

January 31.2 22.0 78.6 112.9 7.7 3.8

February 32.0 22.1 74.4 128.4 8.1 4.4

March 32.8 22.7 70.8 151.1 7.8 4.9

April 33.4 23.4 69.8 150.9 7.7 5.0

May 33.2 24.3 73.4 151.1 7.4 4.8

June 32.3 24.5 78.5 128.8 6.0 4.1

July 32.5 24.4 80.0 108.9 6.5 4.1

August 32.8 24.5 81.8 90.0 6.5 4.1

September 33.3 24.2 79.9 89.5 6.5 4.2

October 33.1 24.2 79.1 86.7 6.3 3.9

November 32.4 23.8 79.7 87.6 6.4 3.6

December 31.7 23.0 76.6 98.2 6.7 3.5

Year 32.5 23.6 76.9 115.3 7.0 1531

Month

Mean Rel.

Humidity

(%)

Mean

Wind

velocity

(km/day)

Month

January 4.0 0.73 2.9 89.8 15.2 74.6 557.1 619.0 586.4

February 4.6 0.73 3.4 93.1 11.6 81.5 608.2 675.8 640.3

March 5.0 0.73 3.7 114.1 6.9 107.2 800.5 889.4 842.6

April 5.2 0.73 3.8 113.9 7.2 106.7 796.7 885.2 838.6

May 5.0 0.73 3.7 112.3 25.0 87.3 651.7 724.1 686.0

June 4.2 0.73 3.1 92.8 44.6 48.2 360.0 400.0 379.0

July 4.3 0.73 3.1 96.3 53.2 43.1 321.5 357.3 338.5

August 4.3 0.73 3.1 95.5 53.1 42.4 316.8 352.0 333.5

September 4.3 0.73 3.1 91.9 36.3 55.6 415.3 461.5 437.2

October 4.1 0.73 3.0 88.4 29.3 59.1 441.1 490.1 464.3

November 3.8 0.73 2.8 78.0 41.8 36.2 270.6 300.6 284.8

December 3.7 0.73 2.7 78.2 15.7 62.5 466.5 518.4 491.1

Dry Season 523 457 3414 3794 3594

Total 1144 340 804 6006 6673 6322

ETh

(mm/d)

kc

ETc

(mm/d)

P e

(month)

IR

(mm/m)

V primary

Pipes

(1000 m3

/ month)

ETc

(month)

V scheme

(1000 m3

/ month)

V primary

Caparo

(1000 m3

/ month)

Page 62: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

62

Correction T (temperature, max and min): average of 1975-1995 is 1985; difference with 2013 is 28 years. This means that the average of 1975-1995 is to be corrected with: 0.672 °C (28 years x 0.024 °C).

Correction Pe: The midpoint of 1971-2010 is 1990; the difference with 2013 is 23 years. An estimate of the factor between average and 75% rain is 0.74 for June-December. This means that the Pe of 1971-2010 is to be corrected with -10.4 mm for each month of the wet season (here taken as June-December).

Vprimary: efficiency primary conveyance at 95% (pipe) or 90%-80% (Caparo River).

Other possible future increases

An extension of the irrigated area will of course mean that more irrigation water is needed. It is

strongly recommended to dimension the main infrastructure that conveys the water to the project area

(primary system) as large as practically and economically feasible. In fact it should be considered to

dimension this infrastructure based on a relatively optimistic estimate of the (future) water resources

available for irrigated agriculture.

Changes in crops: as indicated earlier in this chapter it is assumed that crops will only become more

water-efficient, and it is also assumed that irrigated rice cultivation or aquaculture will not be

introduced. The effect of any change of crops will thus be neutral or mean less consumption of

irrigation water.

13.3 Irrigation Sector Study – Concluding Remarks

1. Alternative preliminary layouts of the scheme are generally prepared, including size and shape of

commanded areas, water level and flow control, and location and size of required engineering

works. This approach has also been followed in the Felicity Pilot area, though the overall plots

and layout of the land was given. Several alternatives for supplying the required irrigation water

were evaluated (Chapter 14, Options).

2. In formulating the project, a thorough study of the engineering alternatives is required in order that

the most appropriate technical, managerial and economical solution is achieved.

3. Land ownership, natural boundaries, land slope and land preparation including land levelling must

be reviewed in relation to the scheme layout. For Felicity it is assumed this has been done

correctly, as the lay-out of roads, plots and drains was in place when the consultants arrived.

Feasibility of land consolidation, where needed, should usually be considered from the legal,

technical, economic and particularly sociological point of view, though in the Felicity case this is

probably not very relevant; only limited legal issues (access to the land for building irrigation

infrastructure) need to be addressed.

4. Accurate evaluation of future project operation and water scheduling (for replication of the pilot

design in other areas of the former sugar growing lands) cannot be made unless pilot projects are

operational. No scheme functions perfectly the day it becomes operational. Allowance should be

made in the planning and design to account for changes in cropping pattern and intensity, at the

same time avoiding any excessive over-dimensioning. Refinements of irrigation scheduling to

match crop irrigation needs should he made after the project has been in operation for some

years.

5. For the estimate of the overall water availability for irrigated agriculture it is not feasible to go

beyond the studies done by DHV in 1999 at this stage. The projected increase in irrigated

agriculture has not been realised; it even appears that the total area under irrigation is lower than

in the 1980’s. It is recommended to reconsider the aim of increasing the area under irrigation to a

realistic target figure set for only 5 years ahead, and to consider options for irrigation on a case by

case basis, matching available water resources with demand for the potential irrigation schemes,

and taking into account the capacity of the agricultural extension service and the availability of

Page 63: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

63

budget for implementation of infrastructure works. Individual schemes need to be identified, which

means that it is not possible to indicate a target area at this stage. Further study is recommended.

6. The need for irrigation water during the wet season means that the natural flow of the rivers

becomes an important factor; infrastructure to utilise water from these streams will have to be

included in the mix of water resources for irrigation.

7. Climate change will increase the dependence on irrigation, slightly during the dry season but

more significantly during the wet season.

8. It is normally recommended to take the social aspects of water management into account when

designing an irrigation scheme layout. The layout will influence and can facilitate the functioning

of water user associations. In the Felicity Pilot area the plot lay-out and main infrastructure is

already given; this limits the freedom for the design.

9. The hydrology of the Caparo River has been extensively studied and is being studied by the

ongoing Feasibility Study and Conceptual Design for the Caparo River Basin Flood Mitigation and

Water Supply Project (in short: Caparo River Basin Study), as this concerns the river that may be

used as source of surface water for the Felicity pilot site. The results of these studies will be

available sometime early next year or during the course of next year (2014). It is recommended to

use the final results of these studies to fine-tune the design for the Felicity pilot area, and to refer

to these studies when deciding to implement other irrigation schemes based on the Felicity pilot

design.

10. For the effective precipitation a decision has to be made on whether to use 1:4, 1:5 or 1:10 year

confidence values, e.g. the expected minimum rainfall in 75%, 80% or 90% of the cases. In the

years that this rainfall limit is not reached crop yield reductions caused by sub-optimal availability

of irrigation water may occur. In this study the available 1:4 or 75% precipitation dataset (1971-

2010, Piarco, monthly values) has been used. Higher confidence values will result in (even)

higher irrigation requirements, and 1:4 or 1:5 are commonly accepted in irrigation design practice.

11. While the subject of this chapter is irrigation, the consultants want to stress irrigation cannot be

seen separately from drainage and leaching. In the long run, if not already from the beginning,

irrigation requires drainage. For Felicity the field application losses that are included in the design

irrigation water requirement together with the (average) rainfall surplus during the rainy season

deliver enough water of reasonable to good quality to remove any accumulated salt from the soil;

however, this flux needs to be evacuated. The risk of salinisation and eventually (hard to reverse)

damage to the soil is certainly present if re-use of drainage water is considered, if too much

irrigation water is applied (over-irrigation, water logging, and often salinisation), or if the (local)

drainage situation is inadequate, but also when under-irrigation is practised (salinity build-up).

Climate change, with lower rainfall during the rainy season, will also increase this risk. It is

strongly recommended to establish a 5-yearly audit of the drainage and salinity situation in the

project area, and to establish a monitoring network in the irrigated area. Preventing soil

salinisation is relatively easy and inexpensive; regeneration of a salinised soil is very costly and

time-consuming.

Page 64: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

64

14. OPTIONS FOR IRRIGATION

14.1 Introduction

For successful introduction of irrigation in the Felicity Pilot area a relatively large quantity of irrigation

water is required (Table 14.1, some 700 mm during the dry season, up to 1000 mm over the entire

year for the 2013 situation). The quality of this water has to meet a set of criteria regarding the

presence of (human) sewage and other pollutants, and salinity.

In this Chapter the various options, or water resources, are identified. The description of the various

options is sometimes qualitative, but where possible quantitative. The reader is referred to previous

chapters in this report when relevant.

The process to identify the most promising solution is done in two stages. First the identified potential

irrigation water resources are evaluated against the following criteria:

- suitability for providing sufficient water in the dry season and during the rainy season;

- suitability for appropriate water quality in the dry season and during the rainy season;

- risk of salt water intrusion and soil salinisation (see also Chapter 11.2, 12.5 and 16).

- environmental impact of irrigation water on the project area and downstream.

In the second stage the preferred options are evaluated taking into consideration factors like: Water

availability, other claims on the water, conveyance losses (primary system ), water quality, land loss

for infrastructure, salt water intrusion (groundwater), cost, robustness, O&M costs and environmental

impact (Table 14.2).

Complicating the search for possible water resources is the competition with (domestic) water supply

(WASA), and possibly industrial use. It is recommended to develop and follow a very clear policy

which outlines the distribution of water in times of water scarcity. While under almost all

circumstances the provision of drinking water will always take precedence over agricultural water use,

the domestic supply sector should shoulder a reasonable part of the effort to save water, by reducing

water use (and wastage) and possibly by introducing rationing. Cutting off the entire supply to

agriculture from a shared water supply should only take place under exceptional circumstances.

Management of such shared resources should be aimed at optimising the dual use of the resource.

14.2 Possible irrigation water resources

The consultants have identified four possible sources for dry season irrigation water supply:

1. The Caparo River13

in the project area;

2. Groundwater abstracted in or close to the project area;

3. Upstream reservoirs and conveyance of water to the project area:

a. Large existing, flooded mining pits east of the project area, adjacent to the Caparo River;: the

Ravine Sable Sand Pits (RSSP)

b. The Caparo River dam (Mamoral), formerly only planned for flood protection, now under

consideration as multi-functional reservoir;

c. Abels Clay Pit, now still being mined under a current license.

4. Treated wastewater re-use and drainage water re-use:

a. Conveying treated wastewater from outside the project area directly to the project area;

b. Within the project area, by collecting the outflow /drainage and re-using it by mixing it with the

selected irrigation water source(s) – closed loop

Combinations of more than one of the above water sources can (and have to) be considered.

13

Another river borders the Felicity project area in the south, the Chandarnagore River. However, from information received by the consultants in discussions it is doubtful that this river can contribute in any significant way to the irrigation water requirement. If this option is to be included a further study of the potential discharge of the Chandarnagore River is needed.

Page 65: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

65

1. Caparo River

Rainy season (supplementary irrigation)

During the rainy season there is generally enough water in the Caparo River to cover the irrigation

water requirements. Crop water demand is mostly – but not completely and not dependably14

– met

by rainfall. Because of the relatively large discharge in the Caparo River during the rainy season the

water quality is relatively good as pollutant loads are much diluted. In general it can be stated that the

irrigation water requirement for the Felicity Area can be met using the water in the Caparo River at the

point where it enters the project area. This amount has to be clearly claimed in a water abstraction

license / water abstraction licenses, to prevent later developments upstream from endangering the

irrigation in the Felicity area.

The remaining challenge is to ensure that occasional prolonged dry spells, especially those linked to

the ‘petit careme’, are bridged. The hydrologic records of the Caparo River show that even during the

rainy season the flow can quickly decrease to very low volumes after just a few dry and sunny days,

see Figure 14.1. Some sort of water storage is needed to protect the crops from suffering damage

due to lack of water.

Illustrating the need for access to irrigation water during the rainy season was the observation by the

consultants that the farmers were taking water from the Caparo River in July 2013. They were using

low-lift low pressure pumps and spray-pipes – apparently additional irrigation was still required,

though it may also be that the farmers used the system for efficient fertiliser application.

Dry season (“full” irrigation)

Problems arise when large volumes of irrigation water of adequate quality are required during the dry

season. During this season the discharge of the Caparo River is almost always as low as to be

negligible, the flow is unreliable and the water quality is (very) poor, due to the disposal of (untreated)

domestic and other wastewater into the river. In effect, unless it rains, the entire flow of the Caparo

River can be considered wastewater. This means that the Caparo River under natural flow conditions

is not very suitable as source of irrigation water during the dry season (see Figure 14.1 for an

example of a typical year). Only in the absence of other viable alternatives the Caparo River should

be considered as a source for irrigation; and then only after rainfall has diluted the pollution. Additional

measures to prevent contamination of crops have to be taken.

14

See Chapter 13: Irrigation Sector Study for the former sugar growing area – irrigation water requirement.

Page 66: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

66

Figure 14.1: Caparo River, daily discharge at Todds Road, 2001

(Source: NIDCO, 2013, Royal HaskoningDHV Caparo River Basin Project based on data from Water

Resources Agency, WASA)

2. Groundwater

The availability of groundwater in the project area is limited because of low permeability (quantitative

analysis: see Chapter 10.3 ‘Potential of Groundwater in the Project Area’). Furthermore, there is a risk

for saltwater intrusion in the project area, as it is situated near the brackish wetlands to the west

(Chapter 10.3). To abstract additional water from the nearby Carlsen Field Wells is no option,

because the well field is already overexploited.

Groundwater could be considered as a temporary additional water resource for emergency use.

However, first a hydrogeological study would be required; certainly related to the risk for saltwater

intrusion in the area. This option is not promising.

3. Use of upstream reservoirs

a. Large sand mining pits, (Ravine Sable) adjacent to the Caparo River

About 7 km due east of the project area is a group of large mining pits, known as the Ravine Sable

Sand Pits (RSSP, Figure 14.2). One of these is filled with water since a major flood in 2010 breached

the separation dam (actually an old railway dike) between the Caparo River and the pit. Another pit is

right next to it, connected at high levels, and easily connected at lower levels. Their combined volume

at full capacity is estimated at 3.0 million m3. The possibility to use these pits for flood management

and water supply is studied15

. A connection with a gated structure between the Caparo River and the

pits is being considered, to enable diversion of river water into the pits for storage and flood

management when required.

15

Feasibility Study and Conceptual Design for the Caparo River Basin Flood Mitigation and Water Supply Project, Royal HaskoningDHV, for NIDCO

Page 67: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

67

Figure 14.2: Ravine Sable Sand Pits

(Source: NIDCO 2013)

(Source: GoogleMaps)

A clear advantage of using the RSSP as source for irrigation is the water quality. The source of the

water, the Caparo River, is still upstream of most populated area, the large city of Chaguanas. Also,

the storage will mostly fill during the rainy season when any remaining upstream pollution is diluted to

the maximum level.

There are two options to transport the water from the pits to the project area:

1. Pumping it back into the Caparo River

2. Building a dedicated pipeline

Considerations:

- The sand deposit is in an impermeable or very local aquifer as there is no connection with the two

rivers16

. Ravine Sable to the north-east and Caparo River to the south-west, with both rivers

within just 200 to 500 m from the sand pits. This means that there is probably none or little water

stored in the local aquifer, and that pumping this aquifer is no viable option.

b. The Caparo River (Mamoral) multi-functional dam

In addition to the mining pits a dam is planned on the Caparo River, a few kilometres upstream of the

sand pits17

. The reservoir this dam creates could also be taken into consideration as another potential

irrigation water reservoir. The dam is designed as multi-purpose reservoir, combining flood mitigation

and storage. If the dam is built the operation for water storage needs to be in combination with the

operation and management of the storage capacity of the sand mining pits.

Considerations for the Mamoral multi-functional reservoir and the Ravine Sable Sand Pits:

- The sand pits are considered for both flood mitigation and water supply; however, for effective

flood mitigation the projected Mamoral dam on the Caparo River upstream from the sand pits is

still needed. This would form another large storage reservoir (up to 2.8 Mm3). If this project gets

approval11

the management and allocation of water from both the sand pits and the dam reservoir

will need to be handled by one organisation, as one combined system.

- The combination of flood management (which needs emergency storage capacity) and water

storage for water supply / agriculture are often at odds. Careful management of the water level in

the pits (and possibly the Mamoral dam) is required. Dual use will normally mean that the

reservoirs will not be filled to capacity at the end of the rainy season.

16

Information from discussions with the consultants of the Caparo River Basin Project. 17

At a high-level workshop (attended by the Minister) at the Ministry of Environment on August 27 a consensus was reached that the advantages of building the Mamoral Dam may not offset the disadvantages. Studies also show that the production of the RSSP alone is quite large (estimate August 30: 12.7Mm

3/y) and construction of

the Mamoral Dam may not add much as the reservoirs are in series, not far from each other.

Page 68: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

68

- A minimum base flow in the Caparo River will be required (environment), even though the Caparo

River now often runs dry in the dry season. This will also compete with the other water uses.

c. Abel’s Clay Pit

- Close to the Caparo River, only a few kilometres upstream of the Felicity area, a clay pit is

exploited. This pit could be a very useful reservoir, with a capacity of 1.75 Mm3. (NIDCO, 2013).

As the pit is still mined under a current license this is an option for future consideration.

4. Treated wastewater re-use

a. Directly by bringing treated wastewater from outside the project area

At this moment there are no treatment plants in the area that can deliver treated wastewater to the

Felicity irrigation area. This option needs to be kept open, to be considered for implementation if and

when a large treatment plant will be build, e.g. in Chaguanas Town, which is just upstream from the

project area. The application of treated wastewater should be considered as a source for irrigation

water when a reliable flow becomes available18

.

b. Within the project area, closed loop concept

With introduction of irrigation water, by definition increased drainage losses will result.

Drainage losses from one system may add to the available supplies for other downstream users - or

may be re-used in the same system. Overall efficiencies can thus be higher than efficiencies for

individual irrigation schemes without use of these drainage losses. The return flow is defined as the

percentage of the gross irrigation requirements which will return to the surface water system. For most

schemes a return percentage of 30 per cent is used, for sprinkler irrigation and the relatively efficient

irrigation at the Caroni (1975) Ltd Rice Farm a value of 20 per cent is used. This means that it is

assumed that for the Felicity Area system 20 per cent of the gross irrigation requirement will return to

the system (adapted from DHV-6, 1999).

The re-use drainage water is markedly more saline than the original irrigation water. This is caused by

concentration of the original salt content; the plants do not take up the salt, which is leached away into

the drains. The salt content is thus expected to be multiplied by 5 (1/20%) as all salt is expected to be

leached out. In addition excess fertiliser and excess pesticides will end up in the drainage water.

Introducing the ‘closed loop’ system means that this drainage flow can be collected at the

downstream part of the project area, and pumped back to the irrigation water inlet, to be mixed back

with the ‘fresh’ irrigation water.

This approach has a number of advantages:

1. It reduces the net irrigation water requirement (the ‘fresh’ irrigation water volume);

2. Any fertiliser that was washed out will be re-applied, reducing the need for new fertiliser and

saving money;

3. Pesticides will not spread further downstream of the project area.

Disadvantages are:

1. The infrastructure of the irrigation and drainage system may have to be adjusted, as the

concept of closed loop re-use was not a boundary condition for the design of the present

drainage system. Some kind of reservoir at the downstream end of the drainage system is

required;

18

Due to time constraints the consultants did not consider the option of utilising treated industrial effluent from the facilities at Point Lisas Industrial Estate. This is a concept that can be examined since the Point Fortin Desalination Plant currently supplies approximately 100,000 m³/day to these industries and the effluent released from the operations at the facilities can be considered as a source of irrigation water upon treatment.

Page 69: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

69

2. Pumping means operation and maintenance of a pump or a set of pumps, and the

construction of a pipeline.

3. Pesticides could build up in the soil and possibly the crops by continuous recycling.

4. Due to the increased salinity of the mixed irrigation water an increased irrigation application is

needed, partly negating the advantage of lowering the fresh irrigation water volume (e.g. the

‘leaching requirement’).

5. The soil needs to be closely monitored for signs of salinisation, as the risk of salinisation

increases with application of a more saline mix of irrigation water.

In fact, closed loop re-use is an option that can be applied to any combination of other sources. The

effect of this option will thus be evaluated in combination with the selected option(s). Implementation

of this option can be decided separately, as a ‘module’ to the selected design option, although it will

have effects on the volume of ‘fresh’ irrigation water that is needed; the volume of re-use water cannot

simply be subtracted from the amount of needed ‘fresh’ irrigation water.

A closed loop system cannot reduce the total amount of salt that eventually leaves the project area,

as it is not possible for this salt to accumulate indefinitely. The salt balance should equal zero over a

year or, in exceptional cases, possibly a few years. The main gain in applying the closed loop system

is that it gives the possibility to choose when to discharge / leach the salt and evacuate it out of the

irrigation system. This can be timed to coincide with a period of sustained rainfall and high

discharges, to dilute the pollutant and salt load of the drainage (and eventually river) water.

5. A combination of possible water sources

A total irrigation volume of about 715 mm19

is needed for the dry season months of January up to and

including May. This translates into a volume of 3.6 Mm3. The maximum flow

20 under optimal

management of the on-plot ponds will then be 170-175 l/s. The only source of water for this kind of

volume is the Ravine Sable Sand Pits reservoir.

The estimated average production of this reservoir is about 400 l/s (NIDCO, 2013, Royal

HaskoningDHV). A preliminary optimization shows that the requirements for irrigation at Felicity and

the stated requirements for WASA can be met during the entire year (only 2 days with 5 l/s deficit),

see Figure 14.3 (2013) and Figure 14.4 (2050).

Figure 14.3: Simulation water requirements WASA and Felicity Irrigation at Ravine Sable Sand

Pits, 2013

19

Including all losses in the primary, secondary and tertiary system, including climate change expected for 2050. For 2013 the amounts are 695 mm and 3.6 Mm

3, see Chapter 13 and Annex 10.

20 Taking only 5% losses in the primary system, the conveyance to the Felicity Area.

Page 70: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

70

Figure 14.4: Simulation water requirements WASA and Felicity Irrigation at Ravine Sable Sand

Pits, 2050

For the projected situation in 2050 this is different, though the type of optimization cannot easily be

compared with the design criterion of 1:4 year21

.

Assumptions made for the simulation

The Caparo River flow series received from WRA is only 15 years. This is not a continuous series, it is

1989 to 2007 but 1994, 1996, 1997 and 1999 are excluded due to missing data. The resulting 15 year

series is applied as a continuous series.

The discharge diverted from the Caparo River to the RSSP is variable.

Statistically speaking this analysis cannot be assigned to a certain return period; however, it gives a

very good idea on the overall availability of water for WASA and agriculture / irrigation in the Felicity

area.

Rainfall, evaporation and deep losses into and from the RSSP are included in the calculation, based

on a variable surface area of the RSSP as function of the water level (area-elevation curve).

The maximum level is taken at 30 m +MSL, which is the result of optimisation of the water

requirements. Much higher does not really add to the water availability. From the ‘bottom’ to the 26m

+MSL excellent Elevation-Area-Capacity relations are available (LiDAR based); above that level the

relations are extrapolated, these will be determined more accurately using GIS. The volume can still

be adjusted by further excavation / sand mining.

In addition the Felicity water demand has been allowed to range from 90-100%, because otherwise

deficits would start to add up at the end of the dry season22

.

Flood detention in the RSSP will be in the layer from 30 to 32 m +MSL; this water needs to be

released as quickly as possible after a flood event but this is not important for WASA and the Felicity

21

The optimisation of the operation of the RSSP (preliminary) was done by applying the flow records of the Caparo River for 15 years, and this shows that the 2013 Felicity irrigation requirement and the stated WASA requirement can be met. 22

This means that buffering in the on-plot ponds in the dry season should be actively pursued, and the simulation should be run again with ranges from 90%-110% to allow buffer replenishment.

Page 71: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

71

irrigation area. The flood mitigation analysis, linked with the effects of river channel widening, will be

modelled and simulated later using Sobek (Hydrodynamic model).

While this analysis is preliminary, the consultants of Royal HaskoningDHV are confident that the

results give a good representation of the actual situation.

Please note: the results are preliminary; they have to be reported to and agreed with NIDCO/DrainDiv (planned

for 8 October), and limited adjustments may be made, like the maximum level of the RSSP, or limitations in the

volume of the RSSP when modifications of the RSSP are included in the simulation.

With thanks to NIDCO and the consultants of Royal HaskoningDHV, for an example in inter-project cooperation.

14.3 Irrigation system in the Felicity Area – assumptions

14.3.1 Irrigation efficiency

The evaluation of the options in this chapter is based on the prior assumption that irrigation in the

Felicity Area will be based on low-lift low-pressure pumps, rigid distribution pipes and flexible ‘spray

pipes’. The irrigation efficiency of the secondary system (e.g. to get the water from where it enters the

Felicity area to the farmer plots) is taken at 90%23

, which is based on pipes. The irrigation efficiency at

tertiary level is taken at 75%. By considering 25% primary losses it is assumed that leaching

requirements are met.

14.3.2 Irrigation ponds

Small on-site irrigation ponds have been constructed on a number of plots in the Felicity Area. The

dimensions are 20x20m with a depth of 4.5m, the maximum stored volume24

is about 1700-1800 m3.

This means that a pond takes up 5% of the gross area of one plot18

. If the water of a pond is used for

one plot only, and if the pond is full at the start of the dry season, a total gross irrigation depth of

about 200mm is available. This is not insignificant25, as it will cover four to six weeks of dry season

irrigation water requirement, see Table 14.1.

Unlike the pond used for irrigation and domestic water supply at Depot Road, there is no

inflow/recharge of groundwater in the ponds in the Felicity Area. This means that the supply of water

has to come either from direct rainfall (thus creating a buffer, which is very useful in the rainy season

to bridge dry spells) or from another source. The relatively heavy clays, which prevent direct

contribution from groundwater, have the advantage that they prevent leakage losses. However,

losses from direct evaporation from the pond surface should be considered when calculating the

available irrigation water. Ponds are not a source of irrigation water, although at the start of the dry

season a surplus from rainfall may well have accumulated.

For the ponds to be useful during the dry season there needs to be a system to replenish them from a

water source other than rainfall. Also, a pond has to be constructed at every plot, or larger ponds are

to be constructed that service a number of plots. Construction of larger ponds has the clear

advantage that the system to replenish the ponds can be much simpler. The disadvantage is that

individual farmers cannot control or see exactly who uses how much of the water, possibly leading to

disputes and water wastage (‘tragedy of the commons’). Unless a very clear mechanism to control the

use of pond water can be devised, set up and enforced (metering the outflow?) it is recommended to

build ponds on all individual plots, unless adjacent plots are farmed by one farmer or cooperative.

23

Based on experience, good practice and FAO, 1984 24

From new information received during the last days of the project the dimensions of the on-farm ponds are such that the actual water held is lower, and the land used is more – according to one source up to 9% of the plot area 25

Reports from farmers that a pond holds only enough water for one irrigation should be checked; possibly they overirrigate the crop, or most probably, the water from one pond is used for several plots.

Page 72: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

72

Table 14.1: Irrigation water requirement (including losses)

Vscheme (1000 m3 / month) (mm/month) Flow (litre/s)

Month 2013 2050 2013 2050 2013 2050

January 544.9 560.5 113.1 116.4 170 170

February 596.3 611.9 123.8 127.0 170 170

March 786.6 805.3 163.3 167.2 170 170

April 783.6 801.5 162.7 166.4 170 170

May 638.1 655.7 132.5 136.1 170 170

June 222.8 362.2 46.3 75.2 170/85 170/135

July 183.5 323.5 38.1 67.2 85 135

August 179.5 318.7 37.3 66.2 85 135

September 279.0 417.8 57.9 86.7 110 135

October 305.6 443.8 63.4 92.1 110 170

November 134.1 272.2 27.8 56.5 110 170

December 331.7 469.3 68.9 97.4 110 170

Dry season

3350 3435 695 713

Total 4986 6042 1035 1255

(Source: see Chapter 13 and Annex 10, Irrigation; Flow is at the Ravine Sable Sand Pits)

The ponds are thus essential for buffering irrigation water: to bridge dry spells in the rainy season,

and to ensure that the farmers have an ‘insurance’ if the outside water supply is cut. Figure 14.5 and

Figure 14.6 show examples of how the water levels in the ponds fluctuate during the year. It is clearly

shown how the level is allowed to gradually drop during the dry season, to recover again during the

rainy season. At the end of the rainy season the ponds should all be filled to capacity. Different ponds

will have different filling dates, and may even have different volumes delivered.

Figure 14.5: Dynamic water level on-plot pond during the year, situation 2013

0

500

1000

1500

2000

2500

3000

3500

4000

4500

0 5 10 15 20 25 30 35 40 45 50

Po

nd

leve

l mm

week

Pond level - 2013

depth ponds refill

dry season 6000 mm filltotal 13400 mm fill

Page 73: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

73

Figure 14.6: Dynamic water level on-plot pond during the year, situation 2050

If the Ravine Sable Sand Pit is selected as primary water resource for the Felicity Area and if the full

irrigation water requirement can be sourced from there, it is recommended to install a pressurised

pipe system for distribution of the irrigation water at the secondary level (within the Felicity area).

It would appear that in this case no ponds are needed, freeing up another 5% of irrigable land (for

which irrigation water needs to be brought in). However, the disadvantage is that the management of

this system is much more complex and the robustness is much lower, with less responsibility for the

farmers and much more for the GoRTT. Even more important: the 1 Mm3 of storage within the Felicity

Area is absolutely essential26

. In the opinion of the consultants leaving out the on-farm ponds is not

viable.

14.3.3 Water metering

As the supply of irrigation water is limited, it should be applied correctly. Any wastage should be

avoided. Training and instruction of the farmers is an essential part of any water conservation effort.

However, experience worldwide shows that farmers will start using water economically only if it has a

price, like any other farm input.

This means that some way of metering or measuring the water use of the farmer needs to be

implemented. If water is delivered by a fine network of pipes, water meters can be installed at

individual off-takes. Another method is to check the level of the ponds before filling them, and thus

calculating the water delivered to the farmer. If electrical pump units are used, the electricity use is a

good indicator for the pump hours, which then give a good approximation of the volume of water

used.

Finally, the preferred option: the system of valves to fill the on-farm ponds is operated by a person

who sets the inlet valves at a set time of the day, say 9am, at such a level that 0.5, 1, 1.5 or 2 meter

of additional water is supplied to the pond in 24 hours. This setting, together with the level in the pond

and the electricity meter reading, is recorded (smartphone).

26

Smaller ponds are possible and explored in the Design Annex. This means that a larger area of Large Buffer Ponds is required.

0

500

1000

1500

2000

2500

3000

3500

4000

4500

0 5 10 15 20 25 30 35 40 45 50

Po

nd

leve

l mm

week

Pond level - 2050

depth ponds refill

dry season 6000 mm filltotal 16161 mm fill

Page 74: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

74

14.4 Selection of preferred option

To evaluate the options and to come to the most optimal mix of water resources an evaluation matrix

of the different options is made, Table 14.2. In this table a list of different criteria is tested, and while it

is difficult to assign weight (as importance) to the different criteria, the matrix still gives a good

overview of advantages and disadvantages of the different possible water resources.

Some criteria can be seen as absolute requirements: the fact that only very small volumes appear to

be available from groundwater means that this will still not be a viable proposition. Likewise, the high

scores for the Sand Pit reservoir and the Mamoral Dam Reservoir will be completely useless if no

water from these two sources is allocated to irrigated agriculture, or if the Mamoral Dam is not built.

The Caparo River scores low, while this is the only form of irrigation water presently used by the

farmers in the Felicity area.

An analysis and evaluation of options, and a selection of a feasible solution, can thus only take place

based on an overall view of combinations of resources. It is necessary to use those resources in such

a way that the most positive characteristics are combined in an optimal mix.

Another important consideration that may not be clear from the matrix is that it is recommended to

work as much as possible with the infrastructure that is already in place. Making large changes will be

expensive, and disruptive to farmers who are already working the land, and even irrigating the land.

By adapting, improving and adding to their present practices the transition to the new system can be

expected to be much easier, as the acceptance will be much higher. Still, it is imperative to involve the

farmers and other beneficiary stakeholders during all steps of the decision making process.

Page 75: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

75

Table 14.2: Evaluation matrix of options (dry season) – irrigation water resources

Resource

Criterion

weight

Caparo

River

Ground

water27

Sand pits,

pipes

Mamoral28

Reservoir,

pipes

Sand pits

Caparo,

River

Mamoral22

Reservoir,

Caparo

River

Water availability29

2x ++ 0 ++++ ++++ ++++ ++++

Other claimants 1x + + - - - - - - - -

Water quality 1x - - ++ ++ ++ ++

Salt water intrusion 1x o - - ++ ++ ++ ++

Robustness 1x - + o o o o

O&M costs30

1x - o - - - -

Environmental impact 1x - - ++ ++ ++ ++

Conveyance losses

(primary system31

) 1x + + ++ ++ - - - -

Obstacles for

construction 1x + o - - - - - -

Cost32

1x o + - - - - - - - -

Total33

+ o +++++ +++++ ++ ++

Key: - - negative; - somewhat negative; o neutral, no effect; + somewhat positive; ++ positive.

Based on the description of the various identified water resources the following can be concluded:

3. Non-viable resources

- Groundwater is not considered a promising source for irrigation water in the Felicity area. The

consultants will not consider groundwater in the mix, for now.

4. Inside the Felicity project area

- Ponds are already constructed on many plots, and are easily and cheaply constructed. The

concept is clear, though the farmers feel that the capacity is too small and the ponds take too

much arable land, especially when they are dry. The study suggests that ponds do have an

essential function in safeguarding irrigation in the Felicity Area, both during the rainy season to

bridge dry spells and as buffers to store and distribute irrigation water during the dry season. The

criticism of the farmers can be countered if a single pond is used for one plot and if the ponds are

27

Groundwater has a total score of 0 because it can be neglected. Water availability cannot be negative. 28

It is uncertain if the Mamoral dam will be built; it will certainly not be built within the near future 29

4 ++++ can be awarded as this criterion has twice the weight 30

O&M costs will directly influence user fees, if the O&M is to be paid by the beneficiaries. This is the usual approach in small-scale irrigation projects. 31

The primary system is the infrastructure that takes the water to the Felicity area. The secondary system distributes it to individual farmers or groups of farmers, while the tertiary system is where the farmer or group of farmers apply the water to the crops, including the on-field infrastructure. 32

Using the Caparo River means installing large pumps and the requisite electrical system; this is more expensive than initially expected. 33

Total: simply add all +, - and o, valued at 1, -1 and 0.

Page 76: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

76

replenished from an outside source during the dry season. The land loss, at about 5%, is

acceptable considering the advantages of irrigation and increased water security. The total

capacity of the ponds is 1 Mm3 for the entire Felicity area. The consultants recommend using the

ponds (individual or for groups of plots), and construction of ponds for each of the plots that are

to be irrigated. This is in line with the policy of the Ministry of Food Production34

.

- Directly linked to the above it follows that an infrastructure needs to be constructed that can

replenish the ponds. A network of rigid (preferably buried) pipes, a network of irrigation channels,

or a combination of the two will be required, to carry the water from the intake location to the

ponds. This system can be operated on a rotational, non continuous basis, given the fact that the

ponds hold a buffer of at least 6 weeks of irrigation water. The consultants prefer a system of

(buried) pipes, especially since this proves to be the preferred method used in other areas

(Orange Grove 2-acre plot area).

- A method to measure the amount of irrigation water used by an individual farmer is needed.

5. Outside the Felicity project area

When considering the above, possible sources of water to supply the ponds are to be identified.

Looking at the matrix of Table 14.2 there are two viable options, described below.

The Caparo River, but only after rainfall has created enough run-off to flush the accumulated

pollutants and dilute any that are being added to it. For this four things are needed:

1. A weir or weirs are to be constructed in the Caparo River, and possibly basins need to be

constructed to allow pumping. Such basins hold relatively small amounts of water;

2. Large ponds to fill quickly, along the river (buffer of peak flow);

3. A number of large capacity pumps to quickly fill the large ponds when a suitable discharge peak

occurs. The pumps have to be big because the suitable discharge peaks last only a few days at

maximum.

4. This needs a knowledgeable and adequate management, to decide when to operate the pumps.

The operator may get a warning based on rainfall upstream, from one of the rainfall stations in or

near the head of the basin, or through the meteorological services division. An operations

procedure cannot be given as this depends on the actual irrigation water requirement, which will

be different based on actual rainfall and water use.

The drawbacks of using the Caparo River as resource are twofold:

3. The cost of the pumps and the complexity of operation;

4. The residual level of pollution, and the unreliable, irregular and intermittent flow.

A clear advantage is that all needed infrastructure can be built within the project boundaries, so it

is easily controlled and managed by a farmers representative body (Water User Group?).

Building the infrastructure is relatively simple and straightforward, but expensive.

The Mamoral reservoir and the Ravine Sable Sand Pits. Both sources would have the same

advantages and disadvantages, and can and even should be operated as one system. At this

moment it is not certain that the Mamoral dam will be built. The Ravine Sable Sand Pits appear to

have enough water for both the Felicity irrigation requirement as well as to cover the WASA demand

for domestic water supply (Figure 14.3).

34

In discussions during the last days of the project it emerged that the on-farm ponds may hold less water and take up more land. An alternative with smaller ponds has been investigated; see Design Annex.

Page 77: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

77

For the sake of this discussion it is assumed that water can be made available from the Ravine Sable

Sand Pits. If the Mamoral Dam is built a means to convey the water to the Sand Pits needs to be

decided upon (pipe, or by releasing it in the Caparo River bed). Also, an inlet and cross dam needs to

be constructed in the Caparo River next to the sand pits divert the river water in a controlled manner

into the sand pits. It is assumed that such works will be constructed as a part of the flood control and

mitigation measures currently being studied by the Caparo River Basin project; they will be

considered only in a qualitative manner by the Felicity irrigation project.

While the active storage of the Ravine Sable Sand Pits is not sufficient to cover all the requirements

of the Felicity area, it will also collect runoff during rain in the dry season, increasing the total water

yield. In combination with optimal use of the ponds in the Felicity area the water from the Ravine

Sable Sand Pits is expected to cover the irrigation water requirements for the Felicity area (NIDCO,

2013; Figure 14.3).

A method to convey the water from the sand pits to the Felicity irrigation intake is needed. There are

two options:

3. Use the Caparo River as conduit by pumping the water from the sand pit back into the river. This

appears to be a very elegant solution: the entire infrastructure to utilise the water of the Caparo

River during the rainy season is the same as for the dry season. However, the cost of pumping

for this option is significant.

4. Build a pipeline, estimated length up to 10km, and use the Ravine Sable Sand Pits as buffer.

Using the Caparo River as conduit:

Advantages

- The entire infrastructure at the Felicity area can be used both in the dry and rainy season,

although the buffer (intake basins) capacity may have to be increased to avoid loss of water

through spillage35

and a number of large pumps are needed;

- The required ecological flow will add to the irrigation water volume available at the intakes at the

Felicity area.

- Implementation and construction time are relatively short (easily within one dry season).

Disadvantages:

- Cost for pumps, electricity grid, transformers.

- Losses, mostly from legal and illegal abstraction from the Caparo River between the sand pits

and the Felicity inlet, are expected to be higher than for a pipeline

- The water will collect polluted effluent, decreasing the water quality on its way to the Felicity

Area.

- Operation of the pump at the RSSP has to be coordinated with the pumping at the Felicity

intake(s), taking into consideration the travel time through the river

- Leakage beyond the Felicity inlets may occur if not all released water is pumped29

. However, a

limited ‘ecological flow’ is required anyway.

Building a pipeline as conduit:

Advantages

- Losses are expected to be low.

- Water quality will not be decreased by lateral inflows

35

If the closed-loop system is implemented this water can then be re-used, making spillage less problematic

Page 78: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

78

- The system will deliver water at pressure to the Felicity area, facilitating easy distribution in the

secondary system. It will be possible to construct a fully pressurised system delivering the water

to the ponds, with relatively small pumps as the system can convey water 24/7 (with ‘smart’

operation and management);

- This system could possibly be implemented without the ponds, though management of a system

without ponds is very complex and the buffer will be cancelled, significantly increasing the

required dry season flow from the RSSP reservoir. Preliminary calculations (NIDCO, 2013) show

that this is not feasible. Management of this system and both investment and O&M costs will be

higher, due to irregular demand. This approach is deemed not viable by the consultants.

Disadvantages:

- Costs are significant, but may in the end be lower than using the Caparo River bed as conduit,

due to the huge difference in required pump capacity. Also, pumps need to be replaced while the

pipeline is probably good for more than 50 years.

- Implementation and construction will be time-consuming. A detailed survey of the right of way is

required, followed by a detailed design. Access to land and the actual right of way has to be

purchased where this is not government owned. A project like this will require tendering

procedures that are much more demanding and time-consuming than for the construction of a

simple pump unit.

Page 79: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

79

15. SELECTED OPTION

15.1 Selected water resource option

The consultants concluded that there are two viable options to provide irrigation water to the Felicity

Pilot area. Both include the individual ponds and a system to replenish these ponds.

Option 1: Source water from the Ravine Sable Sand Pits, possibly in combination with the Mamoral

Dam Reservoir, conveyed to the Felicity Pilot Area using the Caparo River. This will include intake

works and a large number of big pumps on the Caparo River within the project area. During the rainy

season the natural flow of the Caparo River can be utilized to replenish the ponds. During the dry

season water can be released (pumped) from the Ravine Sable Sand Pits into the Caparo River bed.

Option 2: Source water from the Ravine Sable Sand Pits, possibly in combination with the Mamoral

Dam Reservoir, conveyed to the Felicity Pilot Area using a pipeline. This will mean that the intake

works in the Caparo River may not be needed, and water is available at the intake to be distributed to

the ponds under pressure. This option has the advantage of offering 24/7 supply, resulting in relatively

small flow rates (maximum 170-175 l/s) which can be handled with small pumps and a pipe diameter

of about 50 cm (20 inch).

Closed loop system: Adding the closed loop re-use system to either of the above options will reduce

the required amount of ‘fresh’ irrigation water. The effects of applying this interesting concept will have

to be modelled; a rough estimate can probably and possibly be done quickly. Introduction of the

closed loop system has a clear and negative effect on leaching requirements. It is recommended to

implement this only after an additional study into the effects on the soil salinity and the economics.

See also Chapter 16 on salinity and risks of salinisation.

The consultants suggest that Option 1 and Option 2 are considered as Phase 1 and Phase 2. It is

recommended to start with Option 1 for a limited number of plots (100-120) in the Felicity area, and

then start the preparations for building the pipeline. The process of detailed survey, detailed design,

tendering, possibly expropriation and compensation (along the right of way), construction and delivery

can then take place without delaying the introduction in the Felicity Area.

15.2 Recommendations with selected water resource

- Ponds need to be constructed for each plot, as a buffer and to bridge protracted dry spells during

the rainy season. An infrastructure to replenish the ponds is required. The ponds need to be

refilled from an external irrigation water source about once six weeks during the dry season, once

every two months during the rainy season. A fee could be collected for the filling, to be organised

through a communal organisation / WUA.

- The water volume available for irrigation or other purposes in the Mamoral Reservoir – Ravine

Sable Sand Pits is not a straightforward function of the active storage. During the dry season

there is still rainfall and thus replenishment of both the reservoir and/or the sand pits. On the other

hand there are losses due to direct open surface evaporation. The Caparo River Basin project

has made preliminary model estimates which indicate that the requirements of both the Felicity

irrigation requirements and WASA for domestic use can (just) be met. The final results of such

modelling should be evaluated and used to adjust (if necessary) the results of the Felicity area

irrigation design.

- The amount of water to be abstracted for the Felicity irrigation area has to be clearly claimed in a

water abstraction license / water abstraction licenses, to prevent later developments upstream

from endangering irrigation in the Felicity area.

- It is recommended to develop and follow a very clear policy which outlines the allocation of water

under circumstances of water scarcity. While under almost all circumstances the provision of

drinking water will always take precedence over agricultural water use, the domestic supply sector

Page 80: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

80

should shoulder a reasonable part of the effort to save water, by reducing water use (and

wastage) and possibly by introducing rationing. Cutting off the entire supply to agriculture from a

shared water supply should only take place under exceptional circumstances. Management of

such shared resources should be aimed at optimising the dual use of the resource.

- At this moment there are no treatment plants in the area that can deliver treated wastewater to

the Felicity irrigation area. If and when a large treatment plant will be build, e.g. in Chaguanas

Town, which is just upstream from the project area, a connection (pipe or otherwise) to convey

this water to the Felicity irrigation area should be considered.

15.3 Considerations with selected water resource

- Ponds take up about 5% of the plots (400 m2 out of 8000 m

2)36

. The land lost is thus not really

excessive. They hold the equivalent of up to 200 mm irrigation, or up to 6 weeks of irrigation water

requirement in the dry season, and enough to bridge a dry spell in the rainy season. If applied to

only one plot and if the water is not wasted, but applied correctly, the ponds are actually very

effective. Disadvantage: the farmers have to use their own (or communally owned) pump.

Advantage: they do not depend totally on an outside source that can be cut by accident, or on

purpose (water allocated for domestic water use). And the farmers maintain and pay for fuel for

their own pump, increasing ‘ownership’ and responsibility and minimising the dependence on the

GoRTT.

- Of the identified external water sources only the Ravine Sable Sand Pits and possibly the

Mamoral Reservoir can supply the required water during the dry season. It is not certain if the

Mamoral reservoir will be built, and the competition for the water will be strong. The total available

water availability for agriculture in the Caparo Basin is expected to just cover the requirements for

Felicity. Implementation of further irrigation schemes in the basin will need additional buffering. In

this case the Large Buffer Ponds (reserved areas in Felicity) need to be constructed and filled

during the rainy season, and Large Buffer Ponds are also needed in the new irrigated area.

Alternatively another cropping pattern can be adopted, for instance by only irrigating half of each

2-acre plot during the dry season.

- Irrigation during the rainy season is also needed, and this need is expected to increase due to

climate change.

- Construction of larger ponds has the clear advantage that the system to replenish the ponds can

be much simpler. The disadvantage is that individual farmers cannot control or see exactly who

uses how much of the water, possibly leading to disputes and water wastage (‘tragedy of the

commons’). Unless a very clear mechanism to control the use of pond water can be devised, set

up and enforced (metering the outflow?) it is recommended to build ponds on all individual plots,

unless adjacent plots are farmed by one farmer or cooperative

15.4 Potential Environmental Impacts and Mitigation Measures

The environmental impacts and mitigation measures concerning the construction & operation of the

works related to the preferred options are presented in Table 15.1. The potential environmental

impacts and mitigation measures related to the irrigation practices themselves in the Felicity Project

Area have been presented and explained in Chapter 12.

36

Discussions in the last days of the project revealed that the land taken by the ponds may be up to 9% of the plots. The option of smaller plots has been studied and adopted for Phase 1 (see Design Annex) at the Design Wrap Up meeting on Monday 9 September 2013.

Page 81: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

81

Table 15.1: Potential impacts & mitigation measures related to preferred options for source water and

conveyance

Preferred options for source water and conveyance

Potential Negative Impacts

Mitigation Measures

Potential Positive Impacts

source: Ravine Sable Sand Pits, conveyance by Caparo River

increased erosion of embankments of the Caparo River

stabilisation of embankments, proper environmental management and monitoring

improved quality of river

water downstream by

discharging water from

sand pits in Caparo River,

better control on required

ecological flow source: Ravine Sable Sand Pits, conveyance by pipeline

temporary impact of activities during the construction phase, spilling of materials (cement, diesel, oil), soil compaction

proper environmental management and monitoring

Page 82: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

82

16. DESIGN AND FEASIBILITY STUDY.

16.1 Introduction

This chapter deals mainly with the civil engineering design of the Felicity irrigation scheme, for the

location see Figure 16.1. In addition the input for the feasibility study is prepared.

The present water supply and irrigation and a summary of the future water supply options and

constraints are presented (see also Chapter 13, 14 and 15) and the technical consequences of the

choices are indicated.

Chapter 16.4, Water distribution – organisation and management will deal with the water balance (see

also Chapter 13) with the emphasis on drainage, salinity, leaching requirement. Also water

management in the field in relation to design is discussed: filling times, rotation schedules and

capacities of ponds, operating times, and guidelines on capacities and energy use of pumps and on

diameters and pressures in pipes and appurtenant installations.

Note: As decisions on design boundary conditions and options were taken up to the last days of the project, and

some relevant information also became available only during the last days, these have been used in the ‘final’

design as detailed in the Design Annex. At relevant locations in the text of this chapter footnotes have been

added.

Figure 16.1: Location of the Felicity project area

16.2 Water supply options - technical details

Typical for irrigation is that water (rainfall, river flow) is at wrong location at the wrong time. It involves

(on-field) storage of water and/or transport of a source (river, reservoir) to an agricultural area.

In the case of Felicity it means that, for the dry season, the nearby Caparo River is now used for

irrigation purposes. A major issue is that most of that water, of reasonable to good quality, passes

through the river in the wet season, whereas in the dry season the flow becomes very peaky, and the

base flow (actually non-existent) is of very low quality. This water has to be captured and stored if it is

to be used efficiently.

On-farm ponds

The original plan for the 2-acre plots assumes storage in the field: each farm plot has a 1600 m3

pond37

to collect (rain) water. When filled it is good for 200 mm irrigation, including field losses, or

about 6 weeks in the dry season. Storage of direct rainfall in the ponds is not enough to fill the ponds,

let alone carry the crop through the dry season. The Caparo River is the next source of water to fill the

37

Possibly smaller, based on discussions during the last days of the project. See Design Annex.

Page 83: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

83

ponds. The ponds allow a scheme wide storage of about 1M m3 when full, well short of the

approximately 3.5M m3 required for the dry season. Three full (re-)fillings would be required to secure

a full crop; this is not possible without additional measures (Chapter 13).

Large buffer ponds

Inter-seasonal storage is needed to provide the required water. Large buffer ponds (LBPs) were

envisaged to store the river water during the wet season and to capture the occasional peak flow in

the dry season, and release the water to the OPs as required. Approximately 68 acres were reserved

for this purpose in the design for Felicity, yielding a storage capacity of 1.1M m3, also with 4.5 m live

storage depth38

. With large pumps the peak flows of the Caparo River in the dry season could be

effectively stored, and a fully irrigated crop can possibly be secured. However, the peaky behaviour of

the flows allows (very) short pump opportunity times (POT), leading to high capacity pumps and pipes

between the river and he LBPs. More pumping intake points and higher weirs at the pump intakes,

thus creating a buffer in the river, may extend the POT, but the effect of this measure is limited.

Ravine Sable Sand Pits

An adequate inter-seasonal buffer is available when making use of the Ravines Sable Sand Pits

(RSSP) (see Chapter 13). Water will be released from the RSSP either through a pipe (a relatively

constant flow) straight into the distribution network of the Felicity irrigation scheme, or through the

Caparo river itself (in short bursts as to limit inefficiencies and opportunity of tampering with the flow)

into LBPs as to minimize the capacity requirement of the secondary distribution network (pumps and

pipes).

The latest (preliminary) modelling results show that in principle all competing claims can be met, with

difficulty probably also for the design situation in 2050 (Chapter 14, 1:4 year).

Using the combination of the Caparo River with LBPs would have the advantage that it can be

implemented quickly, although the water supply from the RSSP would at least partly depend on

(large) pumps. A serious drawback is that for filling the LBPs (1.1M m3) it requires large pumps (and

piping), both at the RSSP and at the Felicity intake. Even if the POT is increased, the pumps required

to fill the LBPs would have a high capacity and would be seriously underused (idle most of the time).

This means that the pipe option with a constant small flow is by far preferred from a technical point of

view. However, the construction of the pipe may prove to be a challenge and it may take several

years before such a pipe will be built, depriving the Felicity irrigation scheme of irrigation during that

time.

It is therefore proposed to adopt a phased strategy: start with a small section of the Felicity scheme at

the head of the project area. For the first 2-3 years 4 LBPs could be constructed at the head of the

distribution system while the pipe project is further developed and then constructed in close

coordination with WASA. The pumps used to take the water from the Caparo River at the temporary

LBPs could then be moved to the RSSP. Some LBPs could also be maintained to ease water

management bottlenecks in the Felicity irrigation scheme. They can also be used and even extended

to support the development of nearby schemes, such as Edinburgh irrigation scheme, or even as fish

ponds with an emergency water supply function. As the reservation for LBPs is still on the map, a full

development of the LBPs, partly to support irrigation in other regions, remains possible. The extension

of the POT would have to be further investigated. A lot of flexibility is created with this phased

approach.

16.3 Pumps, pipes and ponds

16.3.1 Lay-out and nomenclature

38

The design is adjusted based on newer information – see the Design Annex.

Page 84: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

84

The layout of the system is determined by the present layout of Felicity irrigation scheme, and follows

to some extent the standard layouts of other developments within the MoFP39

. The most striking

elements are the main, primary supply system and the secondary distribution system. Basically the

secondary distribution system is the same, regardless of the selected primary supply system: all flows

and ponds, pipes and valves will have the same capacities and dimensions.

Large Buffer Ponds are located on the reserved areas and named starting from upstream going

downstream on the Caparo River, with L indicating the left bank and R the right bank. LL are ponds

on the Chandernagore River (Figure 16.2, Figure 16.3).

Figure 16.2: Large Buffer Ponds on Caparo River, map

Figure 16.3: Large Buffer Ponds on Chandernagore River, map

39

The consultants have studied design drawings of the Orange Grove 2-acre area

Page 85: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

85

Table 16.1: Preliminary Make up of Secondary Units.

Table 16.2: Capacity LBP and pumps

Area in plot units (2 acre); V in m3, Qfill in m

3/s)

Table 16.3: Preliminary set-up of supply and distribution systems40

Primary supply

through pipeline

Primary supply

through river

River regime first,

pipe regime later.

Main supply system

Ravine Sable Sand Pits (RSSP) Managed for flood attenuation, agricultural and domestic supply

Flood attenuation Infrastructure for gravity inflow and outflow, see study Royal HaskoningDHV

(NIDCO, 2013b)

40

Following discussions during the last days of the project the design could be more focused as a number of choices have been made. For these details see the Design Annex.

Preliminary make

up secondary units

Nr. of plots

in Unit

Secondary

size (ha)

1L 274 302 29 22.4

1R 126 193 68 52.5

2L 249 273 25 19.3

2R 1 125 125 96.4

3L 194 248 55 42.4

3LL 273 353 81 62.5

3R 1 77 77 59.4

4L 78 161 84 64.8

4LL 162 272 111 85.6

Total 655 505.3

No. of plot (first -

last in SU)

Preliminary

make up

secondary AreaLBP V LBP Qfill

1L 3.0 97,440 0.23

1R 3.5 113,680 0.26

2L 2.0 64,960 0.15

2R 4.5 146,160 0.34

3L 3.0 97,440 0.23

3LL 2.5 81,200 0.19

3R 3.0 97,440 0.23

4L 6.0 194,880 0.45

4LL 5.0 162,400 0.38

Total 32.5 1,055,600 2.44

Tfill (days) 5

Page 86: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

86

Primary supply

through pipeline

Primary supply

through river

River regime first,

pipe regime later.

Pump(s) (for agriculture) Relatively small flow of

212 l/s (=175 + 20%).

Δh in RSSP is variable:

WLhi – WLlo < 15m

(see Figure 16.4 and

Figure 16.5)

Large pumps to

simulate peaky

character of Caparo

River in dry season.

Δh <15 m. Large flows

be better not pumped

when Δh > 7.5 m; this

has impacts for

availability water in dry

season, to be resolved.

Large pumps to

simulate peaky

character in dry season

(for 100 – 250 ha first)

Δh <15 m. Large flows

be better not pumped

when Δh < 7.5 m

Relatively small flow of

212 l/s (=175 + 20%)

WLhi – WLlo < 15m with

sometimes high energy

requirements.

Pipe line 212 l/s (=175 + 20%) NA 212 l/s (=175 + 20%)

River41

No works Limited re-sectioning No works

Pump intakes at Felicity NA 7-10 3, possibly to be

removed later

Peak flow pumps (capture

peaks from river)

NA If POT can be extended

to 5 days, between 0.1

and 0.5 m3/s. If POT

only 1.5 days: between

0.35 and 1.75 m3/s.

Only for first SUs LBP

and pumps to be

installed: 3 pumps with

capacity below 0.3 m3/s

LBP (for peak storage) NA App. 24 ha has been

reserved. With 4.5 m

storage: 1.1 M m3 live

storage, could be filled

several times per year

Only a limited area,

possibly 3-4 ha) at the

head of the Felicity

irrigation scheme to be

established, possibly

later rendered defunct

Buffer pumps (to pump water

from the LBP into the secondary

distribution system)

NA 7- 10 pumps with

capacities

commensurate with SU

requirements

3 pumps with

capacities

commensurate with

relevant SU

requirements

Distribution system

Pipe lines (SU) Σ QSU = 200 l/s (167 + 20%).

Valves One on each SU (up to 125 ha); approximately 10 secondary pipelines. To

be securly built in manholes where they can be locked.

Pipe lines (TU) Σ QTU = 187 l/s (156 + 20%).

Valves One on each TU (up to 18 ha); approximately 35 tertiary pipelines. To be

securly built in manholes where they can be locked.

41

Inlet works at the RSSP to be constructed following the Caparo River Basin Study recommendations for flood mitigation and water supply – not considered here.

Page 87: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

87

Primary supply

through pipeline

Primary supply

through river

River regime first,

pipe regime later.

On Farm Ponds Total V = 655 @ 1600 – 1800 = max 1.2 Mm3.

Standard pond filling is 2000 mm (800 m3)/turn. Assume a filling time of 12

hrs: 800/12 = 67 m3/hr = 18.5 l/s; longer filling times are possible: 48 hrs

would require 4.6 l/s. Larger fillings can be allowed but require more time

(and more supervision: spilling should be prevented).

Valves One on each pond (except where plots/ponds are consolidated, possibly

fewer valves can be installed). Max 655 units, possibly as few as 100. These

valves are stepwise adjustable (seeXX) and lockable, yet accessible for O&M

staff.

Private pumps and on-field

irrigation systems

Under farmers control and responsibility.

Miscellaneous items

Electricity for pumps

Main system It is assumed that for the electrification for the pumps at RSSP a co-

operation with WASA can be arranged. High voltage.

Alternatively diesel pumps can also be considered42

.

Secondary system For possibly a booster

pump in network, a

(high voltage) electricity

connection may be

necessary (to be

investigated)

For numerous buffer

pumps a (high voltage)

electricity network to be

installed.

Dependent on

development path:

temporarily (high

voltage) network, or a

permanent electricity

network, for expansion

of irrigation to other

schemes (to be

investigated).

On-farm ponds For hundreds of small pumps, low voltage (110 – 230 V) an electricity

distribution network needs to be built.

Water meters On a number of strategic locations (e.g. at each tertiary pipeline) water

meters to be placed.

In Figure 16.4 and Figure 16.5 the simulated water levels for the RSSP over a 15 year period are

presented under the combined purposes of flood attenuation, domestic water abstraction (3.3M m3)

and irrigation for the Felicity irrigation scheme (4M to 6M m3). Water level is shown to vary from 30 m

+MSL (above the low water level of the Caparo River) to 15 m +MSL43

below the low water level of

the Caparo River. This posed a serious challenge for pumping for irrigation: the cost of pumping goes

up at such lift heights.

42

Diesel pumps at relatively high capacity are available with the Ministry; see also the Design Annex. 43 Note: the water level is actually in mm above MSL – the maximum level is at 30 m above MSL. Source:

Caparo River Basin Study, Royal HaskoningDHV – preliminary findings. As the source is not available the y-axis

legend cannot be corrected.

Page 88: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

88

Figure 16.4: Simulation water level at Ravine Sable Sand Pits - 2013

Note: the water level is actually in mm above MSL – the maximum level is at 30 m above MSL. Source: Caparo

River Basin Study, Royal HaskoningDHV – preliminary findings.

Figure 16.5: Simulation water level at Ravine Sable Sand Pits - 2050

Note: the water level is actually in mm above MSL – the maximum level is at 30 m above MSL. Source: Caparo

River Basin Study, Royal HaskoningDHV – preliminary findings.

In Table 16.3 a maximum primary conveyance (design) capacity of 212 l/s is proposed; in Figure 16.4

and Figure 16.5 lower flows (maximum of 165 l/s) have been used in the simulation44

. In 3 out of 4

years more water is available. The proposed pumps can accommodate larger flows, furthermore there

is water over and above the maximum filling level of RSSP (for flood attenuation), which was not

regarded in the simulation. These flows can be accommodated by the spare capacity in the pipeline

and the ponds (LBP’s), and can be used to further increase the water security in the Felicity area.

44

Reference: email exchange with acting team leader of Caparo River Basin Project

Page 89: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

89

16.4 Water distribution – organisation and management

16.4.1 General

Irrigation systems should be designed in such a way as to make the organisation and management as

well as the operation and maintenance as simple and as straightforward as possible. A very good

term for this is ‘robustness’. A robust system can work under many different circumstances and will

not be sensitive to mistakes in operation. Robustness of a system is a function of both the technical

design and the way it is operated – and these two aspects need to be considered in parallel.

Other considerations are:

1. where does the responsibility of the irrigation organisation stop and the responsibility of the

farmer start

2. how to avoid losses due to characteristics of the distribution network

3. what happens when a part of the system is out of order for some reason

4. how to avoid water wastage

By preserving the concept of on-farm ponds the first three considerations are clearly addressed; the

ponds are the responsibility of the farmer, filling the ponds is relatively straightforward and if somehow

the system to replenish the ponds fails for several days or even a few weeks the ponds hold enough

water to bridge this period.

For consideration 4 a clear way of measuring and then pricing water is needed. Filling the ponds with

set discharges during set times means that the delivered volume of water for each farmer is known.

While the price for the normal amount of irrigation water can be part of the lease payment, any excess

water use should be priced at a level that will deter wastage.

16.4.2 Irrigation

Scheduling – filling of on-farm ponds

Irrigation scheduling usually takes place at the field (soil) level, by shifting the flow of irrigation from

one farmer to the next. In the Felicity irrigation scheme the scheduling point is the on-farm pond. The

consultants propose to install filling pipes to the ponds, equipped with valves which allow for set

volumes of fill: 2 meter water level (800 m3), 1 meter (400 m

3) or 0.5 meter (200 m

3). The setting of

the valves should be done by someone appointed as manager of the secondary distribution system.

Every day at a set time he/she sets the valves of a specific number of ponds to the levels that he/she

determines, based on the conditions in the field. In this manner all ponds are filled on a rotation basis.

For setting of valve, time and flow see Table 16.4. Depending on the setting of the valves more or

fewer ponds can be serviced. The calculated flow at the tertiary level, to fill the pond, is 150 l/s. This

translates into 32.5 meter over 24 hours, expressed in meters pond level45

.

Example: If the valves are set every 24 hour, on a certain day all ponds will receive 2 meter, 16 ponds

can be filled by opening 16 valves at the 2 meter setting (plus one at the 0.5 m setting). Alternatively,

32 ponds can be filled with 1 m (plus one at 0.5 m). And of course any combination is possible as long

as the total adds up to 32.5 meter over 24 hours. The manager has to have a good idea on the level

of the ponds in different areas of the scheme, and should prepare a schedule for all valve settings for

that day.

Details for the pond filling have to be determined once the design is final.

If operation is difficult on a certain day the valves can be set for 48 hours, but at half the level setting.

45

For smaller ponds different flows and times are needed.

Page 90: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

90

Table 16.4: Filling of On-Farm Ponds

0.5 m 1.0 m 2.0 m Depth (m) Volume (m3)

48 h

4.6 0.5 200

24 h

4.6 9.3 1.0 400

12 h 4.6 9.3 18.5 2.0 800

For equal distribution of the water the manager should open valves in at least two different branch

pipes, and preferably more. If all water demand is concentrated along one branch the pressure

distribution among the valves will vary significantly more resulting in uneven distribution of water.

Should a farmer need water before his/her turn a request can be filed with the manager and his/her

pond can be scheduled with the next shift. The manager should ensure that the water is evenly

distributed, as the total amount for Felicity is limited. Giving too much water to too many farmers early

in the dry season may mean that some farmers may not get enough later in the dry season, when

ponds are drawn down too fast.

Having a manager to set the valves has additional advantages. The manager can record the water

levels in the ponds (staff gauges are required) and the electricity consumption of the farmer’s

irrigation pump. The manager can also read the water meters that are installed at selected valves, for

calibration and cross-checking. The consultants recommend the use of a smartphone or tablet to

enter the data on the spot and to take photographs for later verification, especially in order to resolve

disputes. All valves, electricity meters and staff gauges need to be clearly labelled with the plot

number.

Large Buffer Ponds

A limited number of Large Buffer Ponds may have to be incorporated into the final irrigation system

for Felicity, to facilitate overflow and possibly to buffer water made available over and above the

normal allowance for Felicity – this may happen during peak flows and after the RSSP has buffered a

flood peak. Extra flow may also be routed directly into the system, by increasing the number of ponds

/ total daily ‘pond depth’ to be distributed. However, it is recommended to use LBPs to even out large

imbalances in water availability, e.g. if enough water is available during the rainy season it can be

buffered in the LBPs and then applied to help bridge an unusually dry period of the dry season.

Operation of the LBPs adds a layer of complexity to the task of the irrigation manager. An operation

procedure or manual is needed to facilitate the decision to use the LBPs, and how much of the stored

buffer to add to the system. The infrastructure to use the LBPs needs to be included in the design

(pumps to pump the water from the LBP into the secondary distribution system, overflow valve and fill

valve to fill the LBP when excess water is available at the RSSP.

16.4.3 Drainage: (ground) water and salinity control

The main objective of drainage is to evacuate excess water from the land to ensure maximum

production on the field:

prevention of waterlogging: puddles on the field (hamper farm operations, may also cause

damage to crops) and water levels that are too high (hamper optimum crop production

because roots are not well aerated);

prevention of (secondary) salinisation, which is the addition of salt to the field/system salt

balance because of capillary rise from excessively high ground water levels, after (over)

irrigation with (almost always) saline water.

Page 91: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

91

Drainage has two flows to be considered: surface run-off, particularly under heavy rain showers, on

heavy soils, like in Felicity, and sub-surface drainage, in case of high ground water levels,

exacerbated by (over-)irrigation and, in (semi-)arid areas, with the threat of salinisation. Generally

surface run-off needs to be evacuated rapidly, as many crops cannot stand wet feet. With the help of

a drainage module the drainage system can be designed. In irrigated areas with heavy rain showers

and on heavy soils the drainage module may be quite high (well in excess of 2 l/s/ha). For the Felicity

area the drainage module is yet to be determined.

The other flow, sub-surface drainage, aims more at ground water level control, and indirectly at

salinity control. Drain spacing is an important parameter in sub-surface drainage. In Felicity the

present drain distance is about 250 m. For heavy soils such as in Felicity this may be on the high

side. This needs to be investigated.

Present status

Little is known about the actual drainage status of the Felicity irrigation scheme. However, there does

not seem to be a water logging problem, but under more vulnerable crops with increased irrigation

this might just become an issue. There do not seem to be floods that damage the crops but changed

agricultural practices with more vulnerable crops may change that. Salinity is a problem that occurs

mainly in (semi-) arid climates (which Trinidad is not), especially when the land is irrigated (which the

Felicity irrigation scheme is not yet). In the Felicity irrigation scheme it appears that there is a

drainage surplus (in the wet season and over the year on average), though the salinity found during

testing seems to indicate salt accumulated in the deeper subsoil. Further investigations are required.

Increase in ground water level

In irrigation schemes there is almost always the risk of rising ground water levels; only in those cases

where the drainage basis remains low and a new equilibrium can be formed with a ground water level

well below the root zone, one could consider to ignore drainage. Considering the proximity of swamps

downstream and the structure of the soil (relatively heavy clay) high ground water levels are a

concern.

Salinity in the future

Salinisation is a problem that occurs mainly in (semi-) arid climates, especially when the land is

irrigated. Even without (hazardously) increased ground water levels salinisation remains a threat.

Irrigation water always carries salts and if there is no proper mechanism of evacuation of these salts

through drainage water (percolation and possibly additional leaching water) these salts will build up in

the soil. If low quality water is used (re-use of drainage water – closed loop system) and/or if under-

irrigation is conducted, salinity problems may occur.

For a salt balance in equilibrium there must always be a net flux out of the root zone, more importantly

so if low quality water is used for irrigation. Over the year(s) there must be equilibrium, but dynamic

salt management, with varying levels of soil (water) salinity over the seasons, or even over the years,

is possible. One could think of leaching mainly in the rainy season, or of some form of “rotational”

leaching over a number of years.

In the Felicity irrigation scheme there appears to be a drainage surplus, and only in the dry season

there might be a risk of temporary salinity. This depends on factors such as the fraction of surface

run-off, actual infiltration (effective rainfall), and crop evapotranspiration. The very long time of

sugarcane cultivation may have caused an accumulation of salt in the deeper subsoil. This needs to

be investigated in much more detail.

In the long term conditions may change and salinity may become a concern; at the same time in 40

years from now desalination of (irrigation) water will have become cheaper, crops have been

developed (or found) to withstand higher salinity levels, greenhouses have replaced open field

agriculture, etc., and many of the problems we face now may have become manageable.

Page 92: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

92

In Annex 11 the physical relationships between water quality, water quantity, soil salinity and leaching

requirement will be quantified and boundary values will be presented: at this moment there are,

however, insufficient data on soil texture and water quality (salinity) available and it will remain a

theoretical exercise.

Use of water from blocked drains

At the moment some farmers tend to (support the idea to) block drains in the dry season. This would

avoid the need for a pond in-field, land which the farmers would rather use for crops. There are three

topics that require consideration: water quality and water quantity, and hampered drainage.

- Water quality. Part of this water is not drainage water as such, but surface run-off: rain water (at

the end of the wet season) and possibly irrigation water. Even some sub-surface flow may be

captured, although this is bound to be minimal: the drain water level has (temporarily) become the

local drainage basis and there is little head left in the field to drive the flow: there is a risk of water

logging in the field. The water must be of reasonable quality, certainly at the beginning of the dry

season (=end of wet season). Over the season it may deteriorate, and can perhaps only be used

after mixing: however the salt concentration may be lowered, preventing local damage to a crop,

the salt load is not reduced and the salinisation (in the dry season) continues. The risks are (still)

low, and dynamic salt management might control this process.

- Water quantity. For the store to be effective the drain has to be “full” for as long as possible and

refills are necessary; in some locations drainage inflow from higher fields may help, but the extent

of such inflows is unsure. In all fields the side where the drain is located is the short side (60-70 m

long). The average drain has a width of reportedly 6-10 m (top width) with a depth of 2 m (in

heavy clay, 3 m will more likely) and side slopes of 1:1, hence the bed width is 4 m. This means

that the volume of a drain reach is 6*2*60 between 700 – 1000 m3 assuming water level equal to

field level (at the lowest point), an unwanted situation: certainly in the vicinity of the drain

waterlogging conditions will prevail. This volume has to be shared by two farmers: < 500 m3/drain

reach. Drains upstream are smaller than drainage down-stream, so upstream farmers would have

less storage than downstream farmers. In all it is not a very promising prospect.

- Hampered drainage. The principle of a drain is to evacuate water: blocking it is counterintuitive.

Yet water level control in drains is widely practised in delta areas around the world. The (short

term) full ponding of drains described here goes further than water level control. In the vicinity of

the drain water logging conditions may prevail for prolonged periods. Furthermore it is always

unclear when a blockade has to be installed (preferably before the last rain of the wet season) or

lifted (preferably before the occasional rain shower in/at the end of the dry season. As year round

cropping is practised, there will always be different conditions on different fields, different

interests, it will be difficult to please all the stakeholders. Some form of (dry season) water level

control is possible, but it requires well designed and organisation-sanctioned infrastructure and

should be incorporated in the O&M plans of the Felicity irrigation scheme.

Re-use of drainage water – closed loop system

Another water saving measure is he re-use of water from an otherwise unhampered drainage system.

This would amount to pumping the drainage water from the main drains, back to the head of the

system and mix it with fresh irrigation water: the salt concentration gets reduced, the salt load not. If

this would be implemented full time (also in the wet season) it might lead to salinisation even in the

tropical circumstances prevailing in Trinidad as the scheme (soil and ground water) would act as a

cul-de-sac (some ground water flow out of the area will reduce the salt load of the system, but too

slow). However, temporary (dry season) closed loop re-use seems possible from a water and salt

balance perspective, provided that in the wet season the salt balance is indeed restored to zero;

considering the current solid drainage surplus this should not be a problem. A consistent monitoring of

drainage water salinity and soil water salinity is essential: over the years the dry season will probably

Page 93: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

93

get longer and the drainage surplus smaller: by 2050 the conditions in West – Central Trinidad may

be more like a semi-arid climate (with salinity risks) (Design Annex) than the present topical conditions

(without salinity risk). At some point in time the re-use of water may become risky and unwanted.

There are however technical complications. Drainage water is well below the ground level and has to

be pumped all the way back to the head of the system, this requires infrastructure and energy. The

most likely choice of the supply system is a pressurised pipe, and mixing the effluent will be

technically highly difficult, read expensive. It is probably a better idea to pass the water on to

Edinburgh and other downstream areas and re-use the water from drains with some water level

control (see above). Of course in the system pumping may also be allowed at checks structures. Also

here a good monitoring system is essential: the further downstream the water gets the more salts and

other particles it carries and, considering the climate shift, more critical water management conditions

may arise.

16.5 Design

16.5.1 System layout

From a hydraulic point of view it would best if the ponds that receive water (between 17 and 20 at a

time) would be evenly distributed over the pipe network. This would enable the designer to precisely

design a system, through varying dimensions of main, secondary and tertiary pipes, with minimal

pressure differences between extreme locations so that all ponds would receive 2 m (or any other

predefined filling, see 16.4.2) per filling, and at the same time minimise the outlay for infrastructure

and energy requirements. It is not wise to design with such a rigid condition; a more imbalanced water

distribution will most certainly occur. This means that higher pressures will be required in major parts

of the system than strictly necessary. To minimise variations pressure regulators will be incorporated

in the system, at yet to be determined places. In case LBPs are used the pressure in the (sub-

)systems can be better controlled. However, as argued earlier, the use of LBPs will introduce other

technical challenges.

The main supply (the primary system), the pipeline between RSSP and Felicity, will be placed parallel

to the Caparo River, probably on the right bank of the river (and/or in the Caparo River itself). The

pipe will have a capacity of 212 l/s, and will have a Ø 500 mm. The lower order secondary pipes will

carry flows of up to 100 l/s (less if agreeable) at Ø 300 mm. The filler / tertiary pipelines carry equal or

somewhat smaller flows, also at Ø 300 mm. The objective is to keep differential pressures within 0.5

atm. (5 m of water pressure) on a tertiary/filler pipeline, and within 1.0 atm on a secondary supply pipe

line.

Apart from pipes for irrigation there is also a need for drainage and for transport infrastructure. The

field/tertiary drains are already indicated on the pre design map, but the secondary and outfall drains

are not. Presumably the outfall is the Caparo River itself, and the secondary drains will be parallel to

the secondary roads in the system. Furthermore roads are planned in between the fields (tertiary

roads). These roads will be unsurfaced, with a minimum width of 4 m, with a shoulder of 0.5 m on

each side. The secondary roads will be (semi-)surfaced. Along the secondary roads the larger

secondary drains will be located.

16.5.2 Pipe system design

The supply and distribution system is completely based on pipes. Even in the event of the use of

LBPs, the distribution network will be based on pressurised pipes.

The flow formulae used in the design are explained in Annex 11. May it suffice to state that flow is

turbulent, and that the standard flow formulae are used.

The pipes in the system will be of PVC and will be buried. Some sections of the main supply pipeline

may be of other material, if so required: one could think of vulnerable crossings, uncovered sections

with valves and other special installations.

Page 94: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

94

For all the pumps in the supply (main) system, between one and three, and the distribution

(secondary) system, possible a booster pump and a number of (temporary) LBP pumps, the design

criteria and the actual design criterions will be explained.

Special infrastructure like pressure regulators, buffer tanks against water hammer, maintenance

valves and air valves will be specified.

All coefficients used in the design that control inflow and outflow losses, acceleration losses and

pressure losses over pipelines will be presented in Annex 11. Of one typical filler line (tertiary) and of

one distributor (secondary) a complete design will be presented.

16.6 Tender documents and contracts

These has to be discussed and based on workshops with the client.

16.7 Operation and maintenance

At this stage only guidelines for O&M can be prepared. For all infrastructure elements precise

operational rules will be devised (like for the valves described in 16.4.2).

For pumps and other electro-mechanical infrastructure the original manuals will be part of the O&M

documentation (stored at the respective pump houses and other work sites of the O&M engineering

staff). To ensure the project objectives are met specific instructions aimed at a correct distribution will

be part of the O&M manual. In principle a pressurised system like proposed in Felicity is “simple” to

operate: it is a modular flow system and whenever a valve is opened water comes out. However, it is

not a domestic water distribution system, it has a smaller over-capacity than such systems, and fewer

‘customers’, potentially concentrating demand in localised parts of the system. This means that some

central control is required to allow the large volumes required in an agricultural environment to arrive

at the destination without upsetting other parts of the system.

Specific care is required to ensure a trouble free operation of the system, water hammer being one of

the specific issues in a pressurised system.

A complete list of infrastructure elements will be part of Annex 11.

16.7.1 Cost of operation and maintenance

In the cost estimate of O&M the standard maintenance costs of equipment will be the basis of the

calculations. For electro-mechanical equipment generally 1% of the investment costs is used; for

concrete structures 0.5% of the investment cost. Earthworks require 1% of the investment cost.

However, in a pumped system there is also a high cost for energy; this will be estimated in Annex 11.

Careful operation can save a lot on energy (e.g. limiting pumping when the water levels in the RSSP

are low and pumping as much as possible when the Caparo River – RSSP are high. The differential

head between RSSP and the Felicity, approximately 20 m, reduces the energy bill considerably. The

use of the on-farm ponds has a huge positive impact on investments and pumping charges. The use

of (all) LBPs would have an equally large but negative impact on the O&M costs.

All in all the O&M costs will be considerable.

16.8 Recommendations related to design issues

Drainage requires additional investigations:

- with the help of rainfall data and water balance data at field level the drainage module for surface

drainage can be established;

- for sub-surface drainage the drain spacing (related to drain depth) deserves more attention. Soil

parameters like hydraulic conductivity, thickness of soil layers, and chemical make-up of the soil

(CEC, clay type) are important.

Page 95: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

95

16.9 Zoning

A visit to the Town and Country Planning Division of the Ministry of Planning and Sustainable

Development on August 20th brought light on the question whether zoning regulations are applicable

for irrigation projects. It appears that there are no specific regulations for zoning related to agricultural

projects, including irrigation development. For construction activities there is for example a margin to

be followed if a building is planned near a river side, but for agriculture there are in that respect no

regulations. However, there is controlling regulation, namely the Town and Country Planning Act

3501. This Act is being followed up by the Planning and Facilitation of Development Bill, which is now

in parliament. The Bill requires for irrigation developments (which normally includes infrastructure) a

plan to be submitted for verification to the Town and Country Planning Division. The Planning Division

will then react in writing whether there are objections or not to the plan and will refer to WRA, the

Drainage Division and the MFP. If the Felicity Irrigation (Pilot) Project is being duplicated to other

areas in the former sugar lands, then new sites need again verification by the Town and Country

Planning Division.

16.9.1 Economic Feasibility, Cost for Water, Farmers Involvement

16.9.2 Economic Feasibility

If the Irrigation Project, as proposed in current report, will be implemented, the Felicity Area with its

clayey soils – and with sufficient irrigation water in the dry season – could produce crops in all

seasons. It is highest on the wish-list of the farmers in the region: more water and sufficient water in

the dry season, so that the former sugar lands can produce crops the whole year round. For the

farmers is applicable the statement: ‘water availability is income security’.

In the scope of this compact Felicity Irrigation Project, with all its aspects from social to technical, it

would not be possible to present a full economic analysis of the introduction of irrigation practises in

the former Caroni sugar lands. However, there are several economical statements to bring forward,

as well as information on the usefulness of famers associations, and the introduction of cost for water.

Most vegetables for sale in Trinidad and Tobago are imported from Venezuela and the USA against

high prices and consequently vegetables in T&T in supermarkets and groceries are expensive. If the

Felicity Project Area would produce vegetables, grown on a sustainable basis – using non persistent

pesticides and only fertilisers if required – and selling for a price just lower than imported crops, then a

big agricultural market might develop. If the Felicity Irrigation Project is successful and being

duplicated to other former sugar lands, then a vast internal market for vegetables could develop. If the

production is large enough then even export might be an option.

Besides the famers themselves, also the Government of Trinidad and Tobago could assist in

developing the agricultural sector and obtaining the food security that is at present high on the political

agenda.

Possibilities of assistance from the government side are:

- Implementing fiscal and other incentives to allow farmers and the private sector to invest in

agriculture and food production in the region

- Develop infrastructure and logistics to support post-harvest handling, transportation, distribution

and marketing of food, based on the needs of a local market as well as of an international market

(export).

- Develop and implement measures to promote investment in the processing of agricultural

products, to add value and variety.

The benefits of implementing the Felicity Irrigation Project would be considerable: - Improved consumption and demand for local produce.

Page 96: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

96

- Increased status of the agricultural sector.

- Increased food security.

- Decreased carbon footprint for imported foods.

- Increased environmental sustainability and possibly demand for organic foods.

- Increased economic diversification.

Funding of the initial investment for the Felicity Irrigation Project, as a pilot project, seems to be

secured. Recurring operation and maintenance (O&M) costs should be borne by the famers as

agricultural entrepreneurs.

16.9.3 Cost of Water

Sooner or later a price has to be paid for water, whether this is for drinking water, industrial water or

irrigation water. This is a worldwide phenomenon that is required to obtain sustainability. So far no

fees are paid for irrigation water by farmers in T&T. Initiating and promoting irrigated agriculture in

Trinidad and Tobago, it would not be wise to introduce payment for irrigation water at present. Still, in

the future a strategy has to be developed to introduce payment for irrigation water in T&T. The

willingness to pay by famers in the Project Area was brought forward during the rapid appraisal

session (chapter 7). The outcome was that the famers are prepared to pay for irrigation water, if first

there would be proof of a proper functioning irrigation system and increased income as a result of the

irrigation system.

The question then is how cost for water could be organised. A flat rate is an option and if all

connections would have water meters real cost could be charged. Another option – as a flat rate –

would be to include the cost for water in the fee for the lease. A separate study on the willingness to

pay in the Trinidadian context should be carried out before an introduction of ‘cost for water’ would be

introduced.

16.9.4 Farmers Involvement

An important aspect in operating irrigation schemes is that of training and management. Introduction

of irrigation systems usually comes with technically more sophisticated farming practices. To make it

all possible farmers should be well organised. They have to run their irrigation system, they have to

farm their lands, they have to organise packaging and transport and they have to find the market.

Also, it might be required to introduce more temperature tolerant varieties of crops, if the projected

rise of temperature in coming decades will occur. Famers associations would help to carry out these

activities efficiently and would offer the benefit from economies of scale. It also would create an

environment that is helpful for farmers to add value to certain commodities.

16.10 Funding of the Implementation of the Felicity Irrigation Project

The European Union is granting the republic of Trinidad and Tobago a fund for the National

Adaptation Strategy for Sugar (NAS) through the Accompanying Measures for Sugar Protocol

Countries. This occurs under the Multiannual Indicative Programmes 2007-2010 and 2011-2013. The

grant funding in total for these two programmes was approximately 75m Euros. The Multiannual

Indicative Programme 2007-2010 has been completed now and the funds have been spent. The

grants under the 2011- 2013 Programme (approx. 31.7m Euros) are being disbursed directly to the

treasury of the government of Trinidad and Tobago. The implementation of the Felicity Irrigation

Project is sought to be financed from the 2011-2013 Multiannual Indicative Programme by a request

from the Ministry of Food Production, via the Public Sector Investment Programme (PSIP), from the

treasury.

Page 97: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

97

17. CONCLUSIONS AND RECOMMENDATIONS

Positive Impact on the socio-economic situation

Turning the former sugar lands of Caroni (1975) Ltd. in cultivated and irrigated farm lands, will have a

positive influence on the regional socio-economic situation. The arrangement to use the property for

agriculture shall generate positive economic returns, resulting in increased rural income and creation

of employment. When the irrigated farm lands prove to be profitable, than workers will be attracted to

these areas. Farmers will produce a wide range of fresh agricultural products, which most likely will

adjust prices downward. Consumers will benefit from healthier agricultural products at lower prices.

Also the issue of food security will be enhanced.

Negative environmental impacts & mitigation measures

Potential negative environmental impacts of irrigation systems may be caused by agricultural runoff

on surrounding rivers and downstream users, affecting water, soil, flora and fauna (biodiversity),

landscape, and human health (pesticides &fertilisers, re-use of waste water). In the design of the

preferred option for irrigation services in the Felicity Project Area, climate change as an outside effect,

has been taken into account. For Trinidad and Tobago it is expected that in the future longer, drier

summers, shorter and more intense rainy seasons, and a potential increase in sea level will occur.

Because of expected higher frequency and intensity of tropical storms, more flooding in low lying

areas is foreseen. Most negative environmental impacts can be diminished by specific mitigation

measures.

Options for irrigation water

Four sources: The consultants have identified four possible sources for dry season irrigation water

supply:

1. The Caparo River in the project area.

2. Groundwater abstracted in or close to the project area.

3. Upstream reservoirs and conveyance of water to the Project Area:

Large existing, flooded mining pits east of the Project Area, adjacent to the Caparo

River, the Ravine Sable Sand Pits (RSSP).

The Caparo River dam (Mamoral), formerly only planned for flood protection, now

under consideration as multi-functional reservoir.

Abels Clay Pit, now still being mined under a current license.

4. Treated wastewater re-use and drainage water re-use:

Conveying treated wastewater from outside the project area directly to the project

area.

Within the project area, by collecting the outflow /drainage and re-using it by mixing it

with the selected irrigation water source(s) – closed loop.

Combinations of more than one of the above water sources can (and have to) be considered.

The consultants concluded that there are two viable options to provide irrigation water to the Felicity

Pilot area. Both include the individual ponds and a system to replenish these ponds.

Option 1: Source water from the Ravine Sable Sand Pits, possibly in combination with the Mamoral

Dam Reservoir, conveyed to the Felicity Pilot Area using the Caparo River. This will include intake

works and a large number of big pumps on the Caparo River within the project area. During the rainy

season the natural flow of the Caparo River can be utilized to replenish the ponds. During the dry

season water can be released (pumped) from the Ravine Sable Sand Pits into the Caparo River bed.

Option 2: Source water from the Ravine Sable Sand Pits, possibly in combination with the Mamoral

Dam Reservoir, conveyed to the Felicity Pilot Area using a pipeline. This will mean that the intake

Page 98: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

98

works in the Caparo River may not be needed, and water is available at the intake to be distributed to

the ponds under pressure. This option has the advantage of offering 24/7 supply, resulting in relatively

small flow rates (maximum 170-175 l/s) which can be handled with small pumps and a pipe diameter

of about 50 cm (20 inch).

Closed loop system: Adding the closed loop re-use system to either of the above options will reduce

the required amount of ‘fresh’ irrigation water. The effects of applying this interesting concept will have

to be modelled; a rough estimate can probably and possibly be done quickly. Introduction of the

closed loop system has a clear and negative effect on leaching requirements. It is recommended to

implement this only after an additional study into the effects on the soil salinity and the economics.

Phases: The consultants suggest that Option 1 and Option 2 are considered as Phase 1 and Phase

2. It is recommended to start with Option 1 for a limited number of plots (100-120) in the Felicity area,

and then start the preparations for building the pipeline. The process of detailed survey, detailed

design, tendering, possibly expropriation and compensation (along the right of way), construction and

delivery can then take place without delaying the introduction in the Felicity Area.

Recommendations

The following recommendations can be made:

Develop and follow a clear policy which outlines the allocation of water under circumstances

of water scarcity. Cutting off the entire supply to agriculture from a shared water supply

should only take place under exceptional circumstances. Management of shared resources

should be aimed at optimising the dual use of the resource.

Construct a conveyance system for water to the Felicity irrigation area if and when a

treatment plant will be build (e.g. in Chaguanas Town), which is upstream from the Project

Area.

Carry out a study on introduction of farmers associations and willingness to pay for irrigation

water.

Provide organic manure, as alternative fertilisers, to the Caroni (1975) Ltd. farms from the

large volumes of organic waste to be generated in the Felicity area when under irrigation.

Conduct a sensitivity analysis of crop water requirements under the projected climate change.

Carry out an economic analysis and market study for the future Felicity irrigation area.

Page 99: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

99

REFERENCES

NIRAS, 2009 Strategic Environmental Assessment (SEA) of the Implementation of the National Sugar Adaptation Strategy for Trinidad & Tobago, EU Ref. No. 110860/C/SV/Multi

Caroni, 2012 Environmental Sustainability Plan for Caroni (1975) Ltd, Caroni (1975) Ltd. May 9th

2012 MoP, 1999 Water Resources Management Strategy for Trinidad and Tobago, Main Report, DHV

Consultants, Delft Hydraulics, Lee Young & Partners, GoRTT, Ministry of Planning,1999

MoP, 1999-6 Water Resources Management Strategy for Trinidad and Tobago, Annex 6 Irrigation, DHV Consultants, Delft Hydraulics, Lee Young & Partners, GoRTT, Ministry of Planning,1999

MoP, 1999-3 Water Resources Management Strategy for Trinidad and Tobago, Annex 3 Groundwater, DHV Consultants, Delft Hydraulics, Lee Young & Partners, GoRTT, Ministry of Planning,1999

WASA, 2008-21

The Development of Water and Waste Water Master Plan and Policy for Trinidad, Chapter 21: Water Supply and Related Infrastructure Needs. WASA, 2008

FAO, 1977 Crop Water Requirements. FAO Irrigation and Drainage Paper 24, Rome, Italy MFPLMA, 2011

A Study of the Last Forty Years of Daily Rainfall Data in Trinidad to Examine Any Indications of Climate Change and its Repercussions for the Farming Population in Trinidad and Tobago. Vanessa Hyacinth-Ash, Ministry of Food Production, Land and Marine Affairs, May, 2011

Bos et al, 1996

Bos, M.G., J. Vos and R.A. Veddes. 1996. CRIWAR 2.0, a simulation model on Crop Water Requirements. ILRI publication 46. ILRI, Wageningen, The Netherlands

NIDCO, 2013 Royal HaskoningDHV, Solution Identification and Impact Assessment Report for

Caparo River Basin Study – draft 30 July 2013.

NIDCO,

2013b

Royal HaskoningDHV, October 2013. Formulation and Analysis of Alternatives

Report, Caparo River Basin Drainage Study”, Draft Report.

MFPLMA, 2011

Strategic Plan 2011-2015, Ministry of Food Production, Land and Marine Affairs (MFPLMA), March 2011

A.R.S. Progetti, 2010

Socio-economic Baseline of the Sugar Related Areas in the framework of the National Sugar Adaptation Strategy, EU Delegation Trinidad, A.R.S. Progetti S.r.l., April 2010

Koninklijke

PBNA, 1989

Polytechnisch Zakboekje, polytechnical handbook, 1989, ISBN 90-6228-087-0

ILACO, 1981 ILACO bv – International Land Development Consultants, Arnhem, commissioned by

the Ministry of Agriculture and Fisheries, The Hague, The Netherlands. Elsevier,

1981

Smedema,

1983

L.K. Smedema and D.W. Rycroft. Land Drainage, planning and design of agricultural

drainage systems. Batsford Academic and Educational Ltd, London, 1983.

Baars, 1976 Dr. Ir. C. Baars. Design of Trickle Irrigation Systems, Dept of Irrigation and Civil

Engineering, Agricultural University Wageningen, The Netherlands. 1976

Baars, 1978 Dr. Ir. C. Baars. Ontwerpen van regeninstallaties, Dept of Irrigation and Civil

Engineering, Agricultural University Wageningen, The Netherlands. Revision 1978

FAO, 1985 R.S. Ayers and D.W. Westcot. Water Quality for Agriculture. FAO Irrigation and

Drainage paper 29 rev.1, Food and Agricultural Organisation of the United Nations,

Rome, 1985

Vision 2020 GoRRT

Vision 2020, Draft National Strategic Plan, GoRRT

WASA, 2008 The Development of Water and Waste Water Master Plan and Policy for Trinidad, WASA, 2008

MFPLMA, 2013

Status of the Performance Indicators established under the National Adaptation Strategy on Sugar for Trinidad and Tobago: Multiannual Indicative Programme 2011-2013,Progress Report No.1, Ministry of Food Production, April 2013

GoRTT Caroni Green Initiative, Caroni (1975) Limited, GoRTT MFPLMA A Study of the Last Forty Years of Daily Rainfall Data in Trinidad to Examine Any

Indications of Climate Change and its Repercussions for the Farming Population in Trinidad and Tobago, Ministry of Food

Page 100: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

100

V. H. Ash, 2011

Production, Land and Marine Affairs, Piarco, Trinidad and Tobago, Vanessa Hyacinth-Ash, May 9, 2011

R.S. Ayers, D.W. Westcot, 1989/1994,

Water Quality For Agriculture, FAO Irrigation and Drainage Paper, 29 Rev.1, R.S. Ayers, D.W. Westcot, 1989/1994

C. McSweeney, 2008

GCM Projections of Future Climate, C. McSweeney, 2008

C. McSweeney, 2008

Additional Regional Climate Change Information, C. McSweeney, 2008

C. McSweeney, 2008

UNDP Climate Change Country Profiles - Trinidad and Tobago. UNDP; School of Geography and Environment, University of Oxford; Tyndall Centre for Climate Change Research. C. McSweeney, 2008

F. L, Jones, F.B. Lauckner, M. Jones, 2013

An examination of temperature and rainfall trends in Trinidad and Tobago from 1970 to 2011, Caribbean Agricultural Research and Development Institute, CARDI Review, issue 13, Jones, F. L, F.B. Lauckner and M. Jones, April 2013

Junichi Kitamura, 1975

Reports on irrigation, drainage and hydrology in Trinidad and Tobago, West Indies (March 1967-May 1969), JICA, Junichi Kitamura, April 1975

WRA, 2000 Groundwater Master Plan 1999/2000, Water Resources Agency, 2000 CCCCC, 2009 Climate Change and the Caribbean: A Regional Framework for Achieving

Development Resilient to Climate Change (2009-2015), Caribbean Community Climate Change Centre (CCCCC),July 2009

CCCCC, 2011

Delivering Transformational Change 2011-2021, Implementing the CARICOM ‘Regional Framework for Achieving Development Resilient to Climate Change’, Caribbean Community Climate Change Centre, UKAid, Climate & Development Knowledge Network, June 2011

SPCR, 2012 Caribbean Regional Strategic Program for Climate Resilience (SPCR), prepared for the Pilot Program for Climate Resilience, April, 2012

McSweeney, M. New, G. Lizcano, 2010

UNDP Climate Change Country Profiles, Trinidad and Tobago, School of Geography and Environment, University of Oxford. Tyndall Centre for Climate Change Research, 2010 C. McSweeney, M. New, G. Lizcano

GoRTT, 2007 The Environmental Management Act 2000, The Water Pollution Rules 2001, Legal Supplement Part B, Vol. 40, No. 203, 24

th October 2001; Amendment 2006: Vol. 46,

No. 7, 17th January 2007

DHV, 1995 National Minor Irrigation Development, Baseline Survey Water Quality, Bangladesh, DHV Consultants, 1995

Page 101: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

101

ANNEXES

Page 102: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

102

ANNEX 1 MAP OF FELICITY PROJECT AREA

Page 103: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

103

ANNEX 2: ACTIVITIES OF SUPPORTING STAKEHOLDERS

17.1.1 The Water and Sewerage Authority (WASA)

The Water and Sewerage Authority (WASA) was established by an Act of Parliament in 1965 to

manage the water and sewerage sector of Trinidad and Tobago. An essential component of WASA’s

mandate is the delivery of a safe, reliable and efficient water supply to satisfy the demand of all

sectors of the economy, including agriculture.

The vision of WASA can be described as follows:

Being a customer service business.

Delivering consistent, reliable, water of good quality, and wastewater services.

Achieving sustainable financial self-sufficiency.

Enabling employees to be motivated and well trained, providing a platform for future growth.

Improving the organization's impact on the environment and pursue water security for T&T.

Water Pollution Rules 2001 (amended 2006) WASA facilities the water and wastewater treatment plants to discharge effluents into the

environment, and as such apply for source registration of these facilities and permits. To date, the

Water and Sewerage Authority has identified 66 facilities that require source registration and has

submitted all applications for these facilities.

The Water Pollution Rules were enacted in March 2007 and was designed to protect the freshwater

systems. It prohibits any person or organization from releasing water pollutants that exceed the

permissible level and that may cause harm to human health and the environment. Any person or

organization involved in any activity that releases a water pollutant into the environment must register

as a Source and subsequently apply for a Permit to discharge into the environment. Exceptions

include: releases from normal operation of motor vehicles used for transportation, releases from

domestic households such as laundry, kitchen, shower etc., and discharges of sewage into sewerage

facilities.

17.1.2 Water Resources Agency (WRA)

The Water Resources Agency (WRA) was appended to WASA as a division in March 1976 and is

responsible for the management and control of the Nation’s water resources, including agriculture.

Integrated Water Resources Management, requires collaboration with a range of stakeholders to be

able to make decisions in a sustainability manner. Key stakeholders of WRA are: Environmental

Management Authority (EMA), Ministry of Works and Transport Drainage Division, Ministry of Food

Production, Land and Marine Resources (MFPLMA), Ministry of Public Utilities, Office of Disaster

Preparedness and Management (ODPM), and the Meteorological Services of Trinidad and Tobago

(MET).

WRA’s mission is to manage the country’s water resources effectively and promote conservation of

these resources in a cost effective and integrated manner to support socio economic growth.

WRA’s functions are to manage the country’s water resources in a sustainable manner, using the

Integrated Water Resources Management (IWRM) approach. To promote development, conservation

and protection of water resources.

WRA’s objectives are:

Undertake water resources monitoring and assessment with respect to quantity and quality.

Undertake water allocation, regulation and licensing of water abstraction.

Undertake water resources planning, investigations and development.

Promote and coordinate the implementation of IWRM.

Page 104: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

104

Develop and maintain a National Water Resources database and information system.

Monitoring and Assessment

The Agency’s data collection system comprises a monitoring network of gauges, which measures and reports rainfall, stream flow, groundwater, evaporation and water quality at strategically located sites throughout Trinidad and Tobago. The data provide information on trends in the quality and quantity of surface and groundwater resources and are required for social and economic development and protection of the environmental.

For planning and management purposes, such as industrial development and agricultural projects,

the collection of reliable data is a basic activity conducted by the WRA. Both mechanical and real-time

automated equipment are utilized for data capture. The use of telemetry has allowed WRA to provide

organizations such as, the Meteorological Services of Trinidad and Tobago (MET) and the Office of

Disaster Preparedness and Management (ODPM), with early warning information on extreme events.

Abstraction licenses

WRA issues water abstraction licenses, which are legal contracts granting a water use right, which is

a right to use water abstracted from a surface or groundwater source. This license does not confer

ownership of the water, nor does it guarantee the quality of the water or the required volume of water

to be abstracted. It provides for re-allocation of water in circumstances of emergency, at times of

scarcity, and in cases of competing applications. Also, it assures that no license will be granted that

may reduce the volume of previous allocations. The license to permit abstraction of surface and

groundwater consists of the following requirements and restrictions:

Limits the volume of water to be abstracted on a monthly basis.

Limits the use to which water can be produced.

Limits the duration and validity of the permit.

Specifies the method for measurement of volumes of water to be abstracted.

Restricts the source(s) from which abstractions may be made.

Expires at the end of year in which it is granted.

Requires renewal at the end of a calendar year.

Requires compliance with the terms and conditions under which the license is issued.

Specifies that violation of the terms and conditions of a license gives rise to an offence.

Requires approval of the Ministry of Works, Drainage Division for the construction of any

proposed structure in or on the banks of rivers for the diversion of flows.

Above restrictions and requirements are relevant for the development of irrigation schemes.

Extension Training & Information Services (ETIS/MFP)

The Extension, Training and Information Services Division (ETIS) is an arm of the Ministry of Food

Production with the mandate to provide information in aspects of agriculture and related issues, with

the aim of assisting farmers in increasing efficiency in production and hence increasing profitability.

The Division continues to seek ways to improve the delivery of service to their clientele who are

spread throughout the various counties on the island.

Vision

To be the premier learning agency for agricultural development and growth.

Mission

To promote the empowerment of our clients through an extension service, which is client oriented and

responsive to changing needs and circumstances.

Page 105: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

105

Function

To provide farmers, potential farmers, communities, youth and other interested persons, with

information on aspects of agriculture and related issues. To support the regional based extension

service by providing multimedia learning resources and conducting staff training. The eventual aim is

to increase efficiency of agricultural production, leading to increased profitability of enterprises and

improved livelihoods of clients. Staff also participates in exhibitions, field days and other activities as

requested.

Services

On-farm demonstration, trials, farmer field schools.

Provision of audio, visual, publications and printed materials.

Training courses at the Ministry's Offices and within communities.

National Agricultural Marketing and Development Corporation (NAMDEVCO)

The National Agricultural Marketing and Development Corporation (NAMDEVCO) is a statutory body

created by Act of Parliament No. 16 of 1991, with a mandate ‘to create, facilitate and maintain an

environment conducive to the efficient marketing of agricultural produce and food products through

the provision of marketing services and the stimulation of business investment in the agro-industrial

sector of Trinidad and Tobago’.

Vision

Leading Trinidad and Tobago in agricultural marketing and agribusiness solutions, that will contribute

to the social and economic well-being of all our stakeholders.

Mission

Committed to the growth and sustainability of Trinidad and Tobago’s agricultural sector by offering

agribusiness and marketing solutions, through commercial partnerships and linkages with key

stakeholders, in order to produce high quality and value-added food products at fair and competitive

prices, to targeted markets.

Agricultural Society of Trinidad and Tobago (ASTT)

Founded in 1839, the Agricultural Society of Trinidad and Tobago (ASTT) is the only national

organisation representing farmers. As a Statutory Body within the Ministry of Food Production, Land

and Marine Affairs, the ASTT represents every sector of Agriculture.

The ASTT is managed by a committee comprising representatives of all spheres of agriculture,

elected at an Annual General Meeting. Its mandate is not only functioning as an advocacy body, but

also to assist and encourage the development and advancement of all sectors of agriculture.

Over the years, the ASTT has formed alliances with other agencies and organizations, both nationally

and internationally with the main objective of strengthening the agricultural sector.

Vision

To position the ASTT as the flagship for agricultural development in Trinidad and Tobago.

To reposition the agriculture sector as the engine of growth in the national economy.

To achieve food security for all our people by making local foods available and affordable.

Mission

To represent and advocate the interest of all branches in the agricultural sector and to consider,

encourage and advance the growth and development of agriculture in Trinidad and Tobago.

Trinidad and Tobago Agri-Business Association (TTABA)

Page 106: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

106

The Trinidad and Tobago Agri-Business Association (TTABA) was established in May 2006 by private

sector agri-business stakeholders with government support, to accelerate national economic and

social development through the sustainable expansion of the agri-business sector.

As a ‘for development not for profit company’ TTABA is not owned by private shareholders, but by its

current 33 member associations, drawn from every level of the agri-business sector. TTABA cannot

disburse dividends or profits to individual members, but must reinvest its profits to further its objective

of leading the development and expansion of the agri-business sector in Trinidad and Tobago.

Vision

To be the acknowledged leader of an innovative, competitive, sustainable and social expanding agri-

business sector and one of the main drivers of economic and social development in Trinidad and

Tobago

Mission

To lead the sustainable expansion of the agribusiness sector in Trinidad and Tobago, through the

development of strategic agricultural industries and the provision of innovative agribusiness services

along the value-chain.

Services

The core business is the provision of technical services for the development of selected agricultural

commodity/industry value-chains, and the provision of high quality agro-processing services.

The strategy is to develop agro-industry value-chains and provide agro-processing services to support

3 critical pillars of national development: health/nutrition/security, bio-energy security, and

environmental security.

Agricultural Development Bank

The Agricultural Development Bank has had its roots firmly entrenched in the annals of the history of

Trinidad and Tobago. The Bank’s history dates back to the 1800s when the ‘Agricultural Bank’ was

established as a mortgage lending institution in the wake of a disastrous hurricane. Its immediate

objective was to assist plantation owners to replant their estates. Thereafter, it continued to operate

on a small scale due to restricted legislation and limited financial resources.

Today, the Agricultural Development Bank has truly come of age. It has developed from an agency of

colonial administration into undoubtedly a national institution, providing the major source of funding for

the agricultural, agro-industrial and rural sectors in Trinidad and Tobago. It has developed into a very

important Development Financial Institution (DFI), with a major role to play in the growth of the

national economy.

Vision

To be the first choice for complete financial and support solutions to transform agriculture into a

dynamic, sustainable and competitive sector, which promotes socio-economic development.

Mission

To facilitate sustainable socio-economic development of the agribusiness and rural sectors through

strategic partnerships with our stakeholders, delivering cutting-edge financial products and services to

satisfy our internal and external customers, utilizing a team and customer-focused approach.

Page 107: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

107

ANNEX 3: Farmers consultations, rapid appraisal,

Consultation with farmers, living 5-6 kms east of the Project Area, in a region where formerly

tobacco was grown (Depot Road), July 9th

2013

At Depot Road an area of 72 acres is served by a water pumping station that extracts its water from a

pond. Most farmers own 3 acres, some have an area of 5 acres. In the nineties the farmers ceased to

grow tobacco, because it was not profitable anymore. The FAO stepped in in 2010 with a project to

facilitate the change from tobacco to crops. The shift to crops and vegetables had not been a major

problem. At present sweet potatoes, hot peppers, sorrel and corn are grown. The farmers can

continue crowing crops in the dry season, because the pond never falls dry. This pond, which in fact

is a small reservoir of about 1 ½ acres, has a dam and has a spring as its source. It was constructed

for tobacco production, using pipes to distribute the water to the land. The MFP provided 3 pumps for

the reservoir, which are operated by the famers. The famers do not pay for the water distribution and

even not for the diesel for the pumps. Some farmers were prepared to pay for diesel but others not,

with the result that after a while nobody contributed anymore. The pumps are operated in the dry

season, but also in the wet season during dry intervals. The water is also used as a source of drinking

and household water. One of the reasons to irrigate is to prevent the soil to harden. Farmers said that

the soil could become hard as concrete. The present system used for irrigation is drip irrigation

through plastic hoses (‘spray pipes’). The price of this material is 180 TTD for about 90 m of hose,

which is considered acceptable by the farmers. In this area farmers do not operate wells or use

groundwater. The farmers hire labourers to plough their land, which costs about TTD 200 per acre.

They expressed the will to get subsidised (‘incentives’) for that by the government and found it more

important than the incentives for vehicles. The farmers told that there is a lack of agricultural workers

in the region. Young people tend to leave for the towns and prefer to work in other kind of businesses.

RAPID APPRAISAL

Consultation with farmers working in the Felicity Project Area, August 12th

2013

On August 12th the County Caroni Extension Office (Chaguanas) of the Ministry of Food Production

organised a consultation meeting with 8 famers who work in the Felicity Project Area. The intention

was to obtain insight in what the famers do, what their wishes are, and what problems they face.

The information was gathered with the help of the followings questions and remarks, which were

brought forward to the farmers:

Are you an ex Caroni worker?

Are you a farmer?

Full-time farmer?

Are you interested in subletting the lease?

What crops do you grow?

What crops would you like to grow?

Do you think you could earn good money with your crops?

Are you happy with the lease conditions?

Do you need assistance to be a successful farmer?

What type of assistance would you like to get?

Do you know about IPM: Integrated Pest Management?

Do you practise IPM?

Do you make use of Incentives (subsidies)?

Do you need assistance in registering as a farmer to get incentives?

Do you have crop insurance?

Would you like to make use of an irrigation system?

Would you pay for the investment?

Page 108: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

108

Would you pay for irrigation water?

What are the problem that you face?

Do you have wishes?

Results

The following information could be gathered from the questions and remarks, and from the

discussions held with the farmers:

In the Project Area work both ex-Caroni workers, who have one or more leases on their name, and

farmers who have no lease themselves. One farmer had 4 leases on his name (one himself, 2 of

sons, 1 of deceased family member) and managed several leases of 2-acre plots from other lessees.

The 8 consulted persons were all farmers, worked all full time as farmer and like to do that.

The farmers who have one or more leases on their name are not interested in subletting the lease,

because they are interested in farming. However, it is known that other persons who have a lease on

their name, and are no farmers, are interested in subletting.

Crops that are grown by the farmers are: hot pepper, cucumber, egg plant, cassava, eddoes, occra,

corn (limited), pumpkin, and caralli.

Additional crops that the farmers would like to grow are: sweet potatoes, tomatoes, water melon.

All farmers have the opinion that they can earn a good living with farming in the Felicity Area. They

are optimistic about the future, especially if they can carry out irrigated farming. There is a fair trust

that prices for crops will be good and stable.

The lessees were not satisfied with the lease conditions, because the leases are only granted for 30

years. They would like to have a lease of 99 years and preferably they would like to buy the land.

Both reasons were mentioned also to safeguard their farming business for their children/family.

Assistance to be a successful farmer was felt necessary for:

Good roads and bridges / infrastructure

Irrigation system

Water security

Training, a.o. in continued training in Integrated Pest Management

Tractor pool

The farmers are familiar about Integrated Pest Management (IPM) and do practise IPM. They buy as

much as possible ‘safe’ pesticides, the pesticides that are not persistent. They want to use IPM also

to market their crops and get the confidence of the consumer.

Some farmers made use of government incentives (subsidies) to buy equipment and a tractor. Other

famers are not officially registered as a farmer and therefore cannot make use of the offered

incentives. This is felt as a problem.

None of the farmers have a crop insurance. The premium is too high.

All the famers would like to practise irrigated farming. It is most wanted in the area.

If a reliable irrigation system would be installed and maintained by the government, then some

farmers are prepared to pay an affordable fee for the investment. But only when all farmers actually

pay.

If irrigation water can be delivered at their plot(s) and the system is reliable, then most farmers are

prepared to pay for the water. But only if all farmers pay.

Page 109: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

109

There is a need for a farmers association, but it should be an association of directly involved farmers

in the area, and not a ‘distant’ organisation. In the association the famers could make agreements and

decisions concerning the management of an irrigation system, transport, marketing etc.

Problems that the famers face are:

A lack of water

Security, crops are stolen, a gate system might help

Complaint of the farmers: there is a lease tax of TTD 200 per year, which is not felt as high, but not all

farmers pay the tax.

Wishes of the farmers are:

Irrigation system

Expansion of area to cultivate; there should be a first preference for ex-Caroni workers to

lease/buy land which has not been distributed yet

Excess roads, good bridges

Tractor pool

There was one senior farmer who has clear ideas about the setting up of an irrigation system in the

Project Area. He would like to discuss such a system with irrigation engineers and is prepared to

make drawings to explain his views.

Page 110: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

110

ANNEX 4: INTERNATIONAL EXPERIENCES WITH WATER USER ASSOCIATIONS

SOUTH AFRICA

After: Empowerment of the poor through agricultural water user associations. Draft Policy Document, Department of Water Affairs and Forestry for the Management of Water Resources, Pretoria, South Africa, 13-02-2002.

Water User Associations and Cooperative Governance

Poverty often goes hand in hand with a range of problems that prevent the poor from contacting those

government officials who could provide much needed support. One aspect of these problems is the

complexity of the support structures that government provides. There are a variety of government

departments, each with their own mandates, which have a range of support programmes for the poor.

To the uninitiated, it may not always be clear that support is available, how support can be accessed,

or how various programmes work together to provide support from a range of angles. In some cases,

despite the best intentions, support systems may be contradictory or difficult to implement in an

integrated fashion. In addition, it may often be the case that support from one department is

ineffective unless it is tied to support from another department. The use of effective systems of

cooperative governance is therefore a key element in poverty alleviation. As a result, it is important to

address this issue within the context of WUA policy.

The first question that needs to be resolved in this regard is the question how WUAs can access the

support of a range of government departments at once, generating a ‘virtuous circle’ of development.

Users may decide to allow their WUA to perform a range of different functions, not all of which are

necessarily related to the management of water. This means that the activities of a WUA may be

relevant to more than one government department. Also, the success of a WUA may require support

from a range of different government departments. For example, a WUA that has been established for

irrigation purposes could require the following kinds of assistance:

from the Department of Water Affairs and Forestry for the management of water resources

from the Department Land Affairs to increase the security of land tenure amongst farmers;

from the Department of Agriculture for the provision of extension support and advice in increasing production;

from the Land Bank for a production loan;

from the National Agricultural Marketing Council to receive advice on products and marketing;

from the Department of Public Works for the establishment of community assets such as storage facilities;

from the Department of Trade and Industry for training in managing a business ad facilitating market access.

It can be seen from this example that WUAs hold a lot of potential with regard to the pursuit of

cooperative governance. However, it is important that the mechanisms for cooperation among

government departments be clear and unambiguous if the system is to serve WUA members

adequately. Currently a policy proposal has been submitted to Cabinet that suggests that henceforth,

all proposals that relate to agricultural water use be submitted to the Provincial Irrigation Action

Committees (IACs) for approval. It also suggests that the membership of IACs be broadened to

include all government departments that initiate projects that are related to agricultural water use.

This includes the Department of Public Works and the Department of Health.

Alongside IACs, increasing emphasis is currently being placed on the role of local government in

integrating the deliverables of the various line departments into local development plans. In terms of

the Integrated Sustainable Rural Development Strategy (ISRDS), it is expected that any services

required of government departments by community institutions will be obtained through the mediation

Page 111: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

111

of district councils. Thus District Councils are available to WUAs and other localized water

management institutions for the submission of development proposals.

Where there is lack of clarity with respect to the institutional vehicles for cooperation, it is likely that

the relevant Catchment Management Agency will, through the implementation of its catchment

management strategy, facilitate liaison between departments on project proposals.

A second question relating to cooperative governance relates to the fact that WUAs are not the only

institutions that manage water for the benefit of their members. As a result of the initiatives of a range

of government departments aimed at the provision of specific support at community level,

communities have the choice between a range of institutions through which they can achieve their

aims. Examples of these are Communal Property Associations, Community Production Centres,

Trusts, Sect. 21 companies and the Water User Associations treated in this document. In line with the

principles of cooperative governance each ministry needs to ensure that no one institutional format

excludes a community from the provision of support by another line department. What is required to

facilitate this is the development of a memorandum of understanding between relevant government

departments that enables each community structure to access support from all government

departments if the activities of that community structure fall within the mandate of the department in

question.

This also requires a policy decision to be made within the Department of Water Affairs and Forestry in

relation to the conditions under which it is prepared to provide its grants and subsidies to local level

community organisations other than WUAs. It could be argued that if an organisation other than a

WUA is using water for the benefit of its members, it should be treated as a WUA in principle, as it

could have opted to register as a WUA under the National Water Act.

A third matter falling under the broad heading of cooperative governance is the opportunity presented

by WUAs to contribute to the reconstruction of communities that were fragmented and divided by

apartheid. If well established, WUAs are likely to achieve the purpose of the Act such as redressing

imbalances created in the past , promoting equitable access to water and facilitating social and

economic development (section 2, NWA). All these are a means to reconstruction and development.

Not only is promoting social cohesion a fundamental goal of the Integrated Sustainable Rural

Development Strategy, it is also mentioned by community facilitators as a precondition for sustainable

institutional development in poor rural areas. The creation of strong local level institutions such as

WUAs which can bring different groups together in a common vision therefore presents a social

challenge that goes beyond the strict confines of water management and contributes to rural

integration in a broad sense. The establishment of strong WUAs is a function of the quality of the

public consultation process that has brought the WUA into being.

Lastly, WUAs are an important institution through which the National and Provincial Departments of

Agriculture can implement their programme of irrigation management transfer (IMT) which transfers

the management of government initiated irrigation schemes to the users. Close cooperation is

required between the two departments to ensure the achievement of agricultural and water related

objectives, as well as the smooth transition to user-managed institutions.

Functions of WUAs This section is intended to clarify the functions of a WUA. In doing so, it also intends to provide some

clarity on the question how WUAs should be delineated from and link in to umbrella structures of

water resource management.

A number of issues are important in considering the differences between various tiers of water

management, namely:

1. The function that the institution has been established to perform. Four key functions of water institutions can be identified, namely:

Page 112: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

112

Operational functions, related to the management of a service;

Bulk supply functions, related to the management of a bulk water supply system

Resource management functions, related to the management of the resource;

Representation functions, related to the representation of stakeholder needs at higher institutions of water management

2. The functions mentioned above each require a certain nature and frequency of the communication between members or sub-aggregate units.

3. The commonality of vision and purpose amongst members or sub-aggregate units.

Of these, the key issue in distinguishing between various tiers of water management institution is the

functions that they are intended to perform. However, this is also strongly related to the commonality

of vision of members of base WUAs. Thus WUAs may for instance be formed as a result of an

attempt to overcome poverty. Cultural bonds may equally foster mutual ties out of which such an

institution can be built, and such natural social cohesion forms a strong basis upon which to form an

institution. The social fragmentation generated by the past may act to destabilise institutions if

communities which do not see eye to eye are forced to cooperate within the context of one institution.

The pursuit of social cohesion, it is argued, belongs to a long term rather than a short term strategy. In

terms of WUA policy this means that while base-level institutions may be formed on the basis of a

self-defined group, one task of umbrella bodies will be to foster cooperation among these base

institutions over the long term.

A natural unit for base-level WUAs is an institution that has been established to manage a water

service. In addition, individuals who can interact with each other on a day to day basis may form a

more natural unit for a base-level WUA than structures in which communication is limited by

geographical reach. This is because they can reach each other on foot and can communicate verbally

to each other. Furthermore, a WUA has natural strength if there is a commonality of vision based on

the shared views of its members.

A natural unit for umbrella structure is an institution devoted to the management of macro-

infrastructure common to numerous smaller WUAs, or to the allocation of the resource along a stretch

of river. Policy already exists which makes provision for such a structure in the form of the envisaged

catchment management committee. In other words, an umbrella structure manages a common

resource. At this higher level of operation, daily communication is usually no longer possible. This will

in most cases, be compensated by regular meetings between groups making use of a system.

This argument suggests that there is a natural distinction between the functions of ‘base’ water user

associations operating at a local level and that of a catchment management committee which should

operate at a somewhat higher level. The catchment management committee is made up of elected

members from all the water user associations in their area of jurisdiction. CMC act as conduits for

issues from the local level to the CMA. The differentiation between the two levels is based on the

nature of the functions that need to be carried out at each level. As a statutory body, the catchment

management committee may enter into legal transactions when the need arises. Thus representation

becomes a key ancillary function of this first aggregate level of water management institution.

Furthermore, by virtue of their management of the resource, catchment management committees

have the ability to intervene in a system in the interests of equity - for instance on behalf of tail end

users. This provides a point of entry for the Department of Water Affairs and Forestry - or the CMA -

with respect to the promotion of equitable access to water both during the establishment and during

the operation of primary WUAs. This would be done within the context of each local catchment

management strategy, which should also spell out the roles and relationships of the different

institutions in the water management area. Ideally, catchment management strategies should have

developmental chapters setting out the overall equity goals of the water management area.

Another unanswered question is how WUAs will link into the Integrated Sustainable Rural

Development Strategy (ISRDS), which operates from District offices in response to requests

Page 113: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

113

submitted by local authorities on the basis of community development visioning processes. Given that

the ISRDS seeks to integrate the rural upliftment strategies of a range of government programmes for

poverty alleviation, it impacts on the establishment of those WUAs which will contribute to the

empowerment of small scale farmers.

INDIA

After: Water Users Association for Sustainable Water Management, Experiences from the Irrigation Sector, Tamil Nadu, India. C. Chandrasekaran, P.T. Umashankar, V. Duraiswaminathan, R. Jayakumar, UNESCO New New Delhi Office, 2002.

Strategy

The strategy for organising farmers was drawn from thc cxperience gained by CWR in organising W A

Sin four tanks under a project assisted by the Ford Foundation, India. The approach gavc importance

to working directly with farmers and gave priority to their concerns rather than implcmcnting a

preconceived action plan. Farmers were asked to identify their own priorities and concerns, which

were an integral part of the implementation process. After about two months of intensive village

contacts, the first farmers’ meeting was organised. Fifty scvcn farmers attended the meeting as

representatives of the ten villages. The farmers resolved to form a WUA for thc entire command and

to accept turnover as the ultimate aim of the association. As a first major step towards the formation

of the NK channel WUA, an advisory committee was to be constituted with at least two (not more than

four members) from each of the ten villages. There after farmers in each village met to select their

representatives and the advisory committee was formed. The committee divided itself into several

adhoc committees for such purposes as mobilising resources, organising farmers support, and

women’s participation. Farmers were involved in motivating others to join the WUA through regular

visits and meetings in every village and hamlet.

The advisory committee was treated as a general body in order to select the office bearers of the EC

of the WUA. The office bearers consist of a president, two vice presidents, a secretary, two joint

secretaries, and a treasurer. Additionally, the general body unanimously selected twelve EC

members. Women have 30 percent representation in the EC. The channel level WUA helped organise

village level or branch WUAs. They are called the Branch WUAs on the channel. The latter ensure full

participation from each village. They help in the collection of subscriptions, development of leadership

and quick administrative response. Apart from these, women farmers formed a separate WUA. The

entire branch WAS, as well as women WAS, are affiliated with NK Channel WUA.

One advantage of the NK Channel command is the existence of a strong tail-end WUA, the

Vagaikulam Land Holder Association, which has been hnctioning since 1945. Being among the most

deprived, the tail-end farmers of Vagaikulam as elsewhere are keen to get water. The Vagaikulam

WUA developed the capability to work collectively to ensure the availability of water. It supported any

organisation that could bring order to the entire system and become the approach as well as the

principal motivator for the creation of a functional WUA for the NK Channel as a whole. Women in

WAS. A notable feature o f the NK Channel experiment i s the importance given to the role of women

in agriculture and irrigation. Women play a vital role in all phases of irrigated farming, as marginal and

small farmers constitute the majority of the farming community. The initial impetus for women’s

participation came from the Vagaikulam Farmers Association, which had women members in the

WUA. In order to motivate women, weekly meetings were organised using women leaders and

women’s groups. Even male farmers, particularly key farmers, were persuaded to commit themselves

to including women in the WAS. A committee of four women and one man wasspecifically constituted

for women development and for integrating women into the turnover process.

Page 114: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

114

Advantages of the WUA formation to solve environmental issuesThe formation of WUAs has brought

down some of the environmental problems. For example, the water logging and salinity problems

were experienced during pre-WUA period in 40 percent of the surveyed schemes. These problems

were more pronounced in both tank and canal irrigation schemes. The p o s t - W A period showed

improved situation due to (a) controlled and regulated supply of water in the canal due to the

application of effective water distribution system and (b) canal improvement works. Nearly 50% o f the

schemes have experienced slightly poor quality of groundwater below theiayacuts (command area).

Four out of six schemes that have yielded below normal level of crop productivity during pre-WUA

period have indicated just normal yields during the post-WUA period, Same number o f schemes has

shown above normal level of yield from normal level of yield after WUA formation. Farmers perception

i s that it happened due to (a) application of right quantity of water at right time, the consequence of

proper distribution pattern, (b) reduced water logging condition, (c) awareness about soil, water and

crop management aspects. Their awareness was judged by asking them about the requirement of

training on the above aspects. 83%, 90% and 93% of the farmers do not want training on water, crop

and soil management respectively. However 85% of the farmers want training on WUA management

especially on how to raise the resources and how to deal with the Government departments

EGYPT

After: The role of water users’ associations in reforming irrigation. Nile Water Sector, MWRI, Ministry of Water Resources and Irrigation, case # 110, Abdelfattah Metawie, 2002.

Water resources Egypt’s water resources are severely constrained, at less than 1000m3 per person. This calls for

increasing the water use efficiency by improving irrigation management practice, as the agriculture

sector is the main user of water resources. Much of the irrigation infrastructure is elderly and in need

of rehabilitation. The irrigation improvement program (IIP) is one of the large-scale projects to help

Egypt in the 21st century in order to sustain its ambitious development plan. The program involves a

combination of technical changes and infrastructure investment, together with institutional and

organisational changes in the way irrigation water is managed. Of key importance, Water Users’

Associations playing a major role in decision making and the operation and maintenance of the

pumps and mesqas by themselves, with minimal assistance from the Irrigation Advisory Service (IAS)

staff. The fundamental change introduced by the irrigation improvement is to replace individual farmer

pumping at multiple points along the mesqa (irrigation ditches) by collective single point pumping. In

addition to the above primary aims, there are many other aspects to the project, including intensive

training for water users, the IAS, and all levels of personnel involved to the top of the ministry; special

studies and seminars, workshops to help the execution of such a program.

Lessons learned

− The new programme has been built of the experience if earlier irrigation programmes; there is a

body of knowledge that has been tested and piloted which provides underlying strength to the new

reforms.

− In order to increase the efficiency as well as the performance of the system, users’ participation in

the management is a must since their decisions and ideas have a great impact on the operators and

the modernization process of the systems would assure the sustainability of the system.

− Increased crop production and achievement of real water savings in the system is dependent on the

awareness and understanding of both users, and operators and managers of the system.

− Increasing the capacity of users, operators and managers require intensive training. Now in Egypt

the new generation has accepted the concept of users’ participation in the management and the

MWRI has legalized the formation of water users’ association.

Page 115: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

115

Water users associations (WUA) The idea of water users association is broadly accepted now in many of the areas where the Irrigation

Improvement Project (IIP) is to be implemented. The idea needs understanding and support from both

sides of the equation of the supply and the demand whether they are decision-makers, planners,

managers and operators in the supply side and users in the demand side. Developing mechanisms

for reaching agreements should occur through dialogue. The experience of forming WUAs has helped

to create a new generation of engineers, technicians, and users, who have become experts in

building the trust between both parties. The on-going challenge is to ensure the continuation of mutual

understanding on all levels of the irrigation system, so that areas where meeting the demands of

users for reaching the potential production as well as defining areas where real water saving could

become reality with less cost can be located.

Investment in people as well as in infrastructure Changes in the software of the system where the rules and roles of operation can be modified are

harder than changes in the hardware of the system such as adding structures. But the impact of

changing the rules and roles is greater where it involves investments in the people by increasing their

awareness of their system, their capacity to run the system within its constraints and limitations.

Acceptance as well as appreciation of the users is greatly dependent on the performance of the

management in meeting the demands of the users with the least costs involved in operating the

system as well as keeping in right shape through maintenance. A seven-phase process has been

developed in the IIP areas for building sustainable Water Users Associations. The seven phases for

building sustainable water user associations are presented at regular intervals in almost all

documents and reports pertaining to IIP. Most descriptions of the seven-phase process (7PP) state

the targeted goals and the way these goals have to be achieved (how it is done), and the steps are

summarised in Table 1. The ultimate goal of the process is to increase total farm income by saving

labour, time spent on irrigation, to ensure good water control for increased production possibilities,

and more equitable distribution of water. Monitoring and evaluation should of course be a continuous

effort and be part of each phase. Apart from special evaluations on the project’s impact, which could

be done in a separate phase, there should be continuous regular monitoring of WUAs and mesqa

progress to feed back into the learning process.

Conditions for effective WUAs One of the most important activities in building sustainable WUAs is system of process documentation

for learning from experience how to improve the process. There are a number of conditions which

help develop effective WUAs. Clear policy guidelines and continuous strong, Egypt: the role of Water

Users’ Associations in reforming irrigation Case #110 9,support from the MWRI and senior officials in

implementation of the new legislation and, developing the appropriate organizational mechanisms for

the IAS Irrigation Improvement, Projects is essential. Other conditions include strong IAS leadership,

and regular meetings, contacts and special training of WUA leaders. The time involved should be

recognised: communication and training support focused on creating understanding and building

linkages with stakeholders should begin in new project areas several weeks before, Phase I activities

and communication support should continue throughout the seven phases. Building strong linkages

and working relationships with district engineers, staff of the MOA, local banks, cooperatives, schools

and influential local legal begins with phase I, "entry" and must continue through all phases into the

future. The investment in time and effort means that it is essential that the benefits of the new

technology and the WUA organization must continue exceed the costs involved if strong and

sustainable WUAs are to be.

After: Assessment Indicators for Water Users’ Associations in Egypt. E-Water, Official Publication of the European Water Association (EWA), Abdel Hakim M. Hassabou, Inas K. El-Gafy, 2007.

Page 116: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

116

The analysis, Institutional Aspects • Meetings are not registered and there are no organized files for the WUAs in Kemry canal. WUAs of Mantout and Bustan canals register meetings and keep records for all the activities of the associations in organized files. • Board members are elected. One or all of them can be replaced if their performance is not successful. • In the old land, they have good relation with the IAS officers. In the new land, there is no IAS in the area. The agricultural extension agent meets regularly the IAS officers and also the officers of the Bustan Development Project.

Management and Financial • Managing the activities of the WUA is the responsibility of the board members, sometimes with the help of other members. • Members are informed with all the activities of the board. • In the old and new lands, the woman has the right to participate as a member in the WUA, if she owns the holding. In the old land, she appoints her father, husband or son to replace her in the activities of the association. In the new lands, a woman member appoints another member of the WUU to replace her in the meetings and voting.

Maintenance • The pump breaks down 2-3 times a year except in Mohamed Refat Villag. The pump breaks down 2-3 times a month because the spare parts are not the originals and they do not have a special mechanic for maintenance. They often do the maintenance. • In most cases the average time needed to fix breakout is 2-3 days.

Water use and the Environment • There is a continuous flow of water in the canals and mesqas in Mantout and Bustan canals and a rotation system in Kemry canal. In the new lands water is not available in the mesqas one day a week. • In the old land, traditional system of irrigation is followed, while in the new lands modern systems of irrigation are applied. • Underground water is used if there is a shortage in the Nile water. The problem is the low quality of this water, which causes the salinity of the soil and the decrease in yield.

Socio-Economic Impacts • The costs of O& M of the mesqa and the lifting pump are paid by the members of the WUAs either per hour or per feddan. In WUUs each member pays LE 5-10 per feddan a year, according to the rules of the union and each group of 4 holders is responsible for O&M of their own pump. Usually, farmers pay their (shares) spare parts in the costs. In the new lands each holder pays LE 85/ feddan/ year for the electricity consumption. • Each WUA or WUU has a bank account and a fund for emergency cases except in Sharkia associations. • The cost and the time of the irrigation period have decreased after the improvement of the mesqas and the establishment of water user associations. • All type of farmers in the old and new lands were not accepting the idea of joining a WUA or a WUU, until they visited successful WUAs or WUUs in other areas and after having had a lot of discussions with mesqa improvement agents. • In general, the crop yield has been increased, except in Ahmed Ramy village. In Ahmed Ramy village they cannot say that crops' yields have increased because of the shortage in water during the critical time of plant growth. • Conflicts between members are solved by discussions and convincing.

Page 117: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

117

PALESTINE

After: Emergency Capacity Building Project to the Palestinian Water Authority. Technical, Planning and Advisory Team in the Water and Sanitation Sector (TPAT) of the

Water Sector Reform Agenda for Palestine, B. Pengel,17-06-2013.

Water User Associations in Palestine

are primarily seen as within the responsibility of the Ministry of Agriculture (MoA). WUAs are often

formed by groups of farmers who have a shared interest in irrigation supplies for cost and water

sharing, and to coordinate demand with the irrigation water supplier. WUAs can be large or small, and

may be formally constituted (as an NGO) or by informal arrangement. In Gaza for example, many

small informal groups of cooperating farmers exist due to the sharing of wells, where cost-sharing is

not uncommon to avoid disadvantaging farmers further from the well. This approach would be

appropriate for re-use water supplies where a group of farmers may share an off-take, organise the

water distribution and cooperate over the division of costs. These groups could provide focal points

for the operator of the re-use water conveyance system on issues covering water demand and

scheduling, billing, complaints, etc. The PWA has limited experience through a project in Gaza; a

Memorandum of Understanding on the application of treated wastewater has been signed. The MoU

describes the cooperation between the involved ministries and agencies in Gaza to facilitate the

Austrian Project, which is carrying out a pilot on treated wastewater re-use in Gaza. This MoU also

mentions the establishment of Water User Organisations as an important requirement. The PWA in

Ramallah has contacts with the MoA on possible pilots in the Jordan Valley (source: Ahmed Hindi).

While the original TPAT planning mentioned ‘the establishment of Water User Organisations’ the

study up to now showed that this is far too ambitious; the objective has been adjusted to developing

and discussing an overall institutional framework including stakeholder representatives at several

levels, from farmer cooperatives to possibly governorate level water user councils. The experience up

to now also indicated that not just water user associations at farmer level (for joint management of

agricultural inputs including groundwater or re-use water) are needed, but that higher level

organisations at district / governorate level are to represent other water users (industry, domestic,

municipal etc.), with the explicit objective to be a competent partner for the PWA when discussing and

implementing water allocation issues between different uses. While actual influence of these higher

level water user organisations on the water allocation may be limited, they can act as a conduit for

two-way communication on water resources management issues and information.

Page 118: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

118

ANNEX 5: DRAINAGE AND FLOODING

1 Drainage and Flooding

In this Chapter an overview of available information and knowledge is presented, providing an

overview of the drainage and flooding situation for the former sugar growing areas, located on the low

areas in the west of Trinidad. Within the scope of this study, which was very limited in time and

manpower, the output is necessarily linked to the available time and available data, as there was no

scope for more than very limited site visits and even the collection of relevant documents and reports.

17.2 Flooding

Flooding was kept at a minimum at Caroni (1975) Limited; there was a permanent crew of workers

which was actively engaged in cleaning the drains, especially after harvesting of the sugarcane. Each

worker had to patrol sugarcane fields looking for pollutants. With the closure of the sugar industry the

routine patrols have stopped and some areas have become a dumping ground, which has contributed

to an increase in the incidence of flooding as drainage channels are blocked (NIRAS 2009, Chapter

5).

After floods in the early years of this century, which caused serious problems in Chaguanas, part of

the flow from the Caparo River now is diverted through the Honda River bifurcation, significantly

reducing or even completely preventing flooding in Chaguanas. The Honda River joins the Caparo

River again just upstream of the Felicity Pilot area.

According to several resource persons the risk of flooding in the Felicity pilot area is limited; if in the

future problems arise another link from the Honda River to a river further to the south (the

Chandernagore River) is also possible, using an existing channel, which will need to be widened.

Figure 1: Flood prone areas in Trinidad and Tobago

Source: MoP 1999

Page 119: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

119

While the Terms of Reference for the Felicity Project ask for a study of flooding in the former sugar

growing areas, a full study is well outside the scope of this relatively small project. Meanwhile the

Caparo River Basin Project and the Caroni River Basin Project are being carried out by Royal

Haskoning DHV for NIDCO. These studies presently mobilize much larger resources. It is

recommended to wait for the results of these studies. Also, the main subject for the Caparo River

Basin Project is to devise a flood management and mitigation strategy for the Caparo Basin.

Assuming that this is successful, flooding in the Felicity area should be something of the past.

17.3 Drainage

17.3.1 Leaching and salt accumulation

Drainage is essential for successful irrigation; without proper drainage rapidly rising groundwater

levels may lead to waterlogging and eventually to soil salinisation. In the early years of a scheme,

when ground water levels and salinity build-up in the soil(-water) are still low, drainage could be

ignored but, unless a stable permanent natural drainage pattern develops, artificial drainage is

required.

To avoid salt accumulation in the root zone and related crop damage, a leaching requirement must be

determined. Even if the field application losses of irrigation initially suffice to off-set the salinization

risk, in the long term salinity may still develop. In particular when low quality water is used or

(temporary) under-irrigation occurs additional water will have to be added to the irrigation gift.

Dynamic salt management, leaching during off-peak water use periods or non-cropping periods, is

another viable option and has an added benefit: it reduces peak water demand and design capacity of

the distribution system. Natural rainfall will also contribute to leaching, as the leaching requirement

consists of a yearly total amount of water and a maximum allowable level of soil salinity. Timing and

depth of leaching will depend mainly on type of crop, soil, climate, irrigation practices, rainfall and

rainfall distribution and irrigation water quality.

17.3.2 Salt water intrusion

In general the elevation of the Felicity pilot area is high enough above the mean sea level and even

above the mean flood level to prevent any salinisation of the groundwater. Salt water intrusion in the

groundwater is not to be expected as the groundwater flow is towards the sea due to the clear rainfall

surplus, and there is no well abstraction in the area. The permeability of the subsoil is also rather

limited. The abstractions at the Carlsson well field, about 3-5 km to the east of the project area, might

in theory cause such deep coning that seawater could start flowing into the groundwater aquifers;

large scale abstraction for irrigation obviously increases such risk, but is not now considered. It is

recommended to study the groundwater flow processes in more detail, and to install measurement

wells on the seaward side of the project area, to monitor groundwater level and groundwater quality.

This could possibly be done with automatic loggers.

Salt water intrusion through the main rivers and drainage channels may present a possible problem.

This is certainly the case for the Caroni and Canupia rivers, which have been dredged to a level

where a salt tongue can reach up to the highway at times when discharge is low. For the Felicity area

this may possibly be a problem in limited seaward part of the area, when taking water from drains and

rivers for irrigation. The risk is expected to be very small, though. A weir under the last bridge over the

Caparo River will effectively block seawater intrusion.

17.3.3 Soil drainage

Internal drainage in the Felicity area may be a challenge. A surface drainage system is in place, but

the soils are heavy and in some places the groundwater is relatively close to the surface. Over-

irrigation may cause groundwater to rise to close to the surface, leading to water-logging, and into the

zone of capillary rise, where subsequent evaporation will result in the deposit of salt, damaging the

crops. Care should be taken to limit the irrigation water application to the amount needed for the crop

Page 120: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

120

and for adequate leaching: over-irrigation is in the long run as serious a threat as under-irrigation,

unless additional (and in fact unnecessary) drainage capacity is installed. The groundwater level

should be monitored on a regular basis - at least yearly, after the dry season irrigation period. If there

are any indications of rising groundwater or salinisation due to capillary rise to the surface, the

drainage situation needs to be improved, possibly by installing sub-surface drainage.

Page 121: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

121

ANNEX 6: CHARACTERISTICS OF AQUIFERS AND WELL FIELDS IN THE CENTRAL SANDS AND LIMESTONE

Annex 6a: Aquifers characteristics of the Central Sands and Limestone

aquifer

unconfined/confined

lithology recharge

area

(ha)

total

thickness

(m)/ total

permeable

zone (m)

specific

capacity

(m3/day/m)

average

specific

capacity

(m3/day/m)

transmissivity

(T)(m2/day)

(estimated)

hydraulic

conductivity(K)

(m/day)

Sum Sum Sand: confined (sub-

aquifers S1-S5):

Unseparated Sum Sum

Upper Sum Sum

Lower Sum Sum (pump test carried out in

Carlsen Well Field)

fine to very fine sand,

some silts and clays

S1 & S2:

375

S3: 132

S4: 445

S5: 182

30-100/30-

100

25-70/25-70

10-90/10-90

55/130/275/2

0/336

163 225

970 (lit.12)

5

22 (similar to

Sum Sum-

Mahaica

Sands)

Sum Sum - Mahaica Sand:

confined (sub-aquifers M1, M2)

(pump test carried out in Las

Lomas Well Field)

fine to very fine

sands, some silts

and clays

M1: 728

(incl.sub-

crops)

M2: 1012

40/40

90(max)/90

60/396/185/

335/17/26-

389 (lit.23)

199 275

1,290 (lit.12)

7

22 (storage

coefficient

0.0003; lit.12)

Durham Sand: confined

(sub-aquifers D1-D7)

fine to very fine

sands, some silts

and clays

D1 & D2: 55

D3: 26

D4: 210

D5-D7: 625

15-75/15-75

15-125/15-

125

20-160/20-

160

20-160/20-

160

124/81 103 140

3

Guaracara Limestone limestone - - - - - -

Page 122: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

122

(fossilerous)

Source: Water Resources Management Strategy, 1999

Annex 6b: Characteristics of well fields in the Central Sands and Limestone

aquifer

well field numbe

r of

wells

yield 1995

(m3/year)

yield

1995

(m3/day)

long term

water level trend

bal. yield

per aquifer

De Verteuil

1968(m3/yr

)

safe yield

per aquifer

Dillon

1969(m3/yr

)

safe yield

per

aquifer

WRA

1994

(m3/yr)

Sum Sum Sand:

unseparated Sum Sum

Upper Sum Sum

Lower Sum Sum

1. Carlsen Field

2. Freeport/California (1)

Private wells:

Sub-total:

5

4

10

19

3.98x106

*2.64x106

1.71x106

8.33x106

10,904

*7,229

4,680

22,813

declining:1986-91

upward:1991-94

declining:1994-95

equal: 1986-91

upward: 1991-93

declining:1993-95

**

6.64x106 3.65x10

6

Sum Sum-Mahaica Sand

1. Las Lomas

upper aquifer

lower aquifer 2. Waller Field

Private wells:

Sub-total:

5

-

3

8

3.12x106

*0.53x106

0.02x106

3.67x106

8,548

*1,451

54

10,053

equal: 1991-95

equal: 1991-95

**

11.62x106 4.38x10

6

Durham Sand

Freeport Todd’s

2

*2.19x106

*6,000

equal: 1986-91

upward: 1991-91

6.47x106 2.01x10

6

Page 123: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

123

Private wells:

Sub-total:

3

5

0.04x106

2.19x106

12

6,012

declining:1993-95 **

Caroni Surface gravels Private wells 3 0.14x106 370 ** - -

Central Shallow Gravels Private wells 3 0.01x106 32 ** - -

Guaracara Limestone Guaracara; Private wells: 1 0.01x106 35 ** - -

Sub-totals public wells (WASA)

Private wells

16

23

12.40x106

1.89x106

34,132

5,315

TOTAL 39 14.30x106 39,315 (10.0x10

6)

Source: Water Resources Management Strategy, 1999

Page 124: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

124

ANNEX 7: WATER QUALITY IN THE CAPARO RIVER Water and Sewerage Authority , Water Resources Agency, water quality, river Caparo, location: north 1,158,770, east 681,735

Period Specific

Conductivity pH

Colour (Hazen Units)

Temperature (OC)

Phosphate (mg/l)

Free Ammonia

(mg/l)

Organic Nitrogen

(mg/l)

Nitrate (mg/l)

TDS (mg/l)

DO (mg/l)

Iron (mg/l)

Sulphate (mg/l)

Turbidity

20-03-1991 470 7.8 70

0.02 0.26

320

1.5 71 15

13-10-2005 123.8 7.4

2.9

1

4.83 0.83 46 15-11-2005 270 7.3

0.89

5.86 2.68

378

09-10-2005 402 7.5

5.8

190

27-10-2007 624 7.7 150 25.3

0.35

533 6.34 4 109 30

27-10-2007 533 7.6 400 25.3

0.33

430 5.83 3.9 85 48

27-10-2007 441 7.5 500 25.1

0.33

362 5.62 6.4 77 57

15-11-2007 640 7.7 60 26.1

0.22

502 6.13 2.9 85 16

15-11-2007 577 7.9 70 27.4

0.23

434 6.18 3.8 84 27

15-11-2007

7.8 50

0.23

440

3.3 83 35

20-11-2007

7.9 60 24.5

0.25

513

3.57 99 26

20-11-2007 567 7.9 100 25.7

0.21

460 5.67 4.3 87 38

20-11-2007 567 7.9 500 25.8

0.46

457 5.67 17.45 86 592

22-11-2007 673 7.9 50 25

0.09

516 6.39 0.6 100 9

22-11-2007 618 7.9 60 26.4

0.09

463 6.14 1.34 83 18

22-11-2007 605 7.7 500 26.4

0.04

462 4.51 13.6 86 116

26-11-2007 490 7.8 400 26.4

0.11

380 6.04 12.84 75 101

27-11-2007

7.6 150

0.18

380

6.95 71 44

27-11-2007 419.8 7.6 500 29

0.17

353 5.01 5.11 67 226

09-09-2008 410 8

32 1.17

4.86 0.04 46 94.9

30-04-2009

7.6

27 1.11 0.3 5.85 2.05 215 1.7 0.49 0.01

Page 125: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

125

ANNEX 8: Test results of water samples from project area

Annex 8 Test results of water samples from project area.pdf

Page 126: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

126

ANNEX 9: GUIDELINES FOR INTERPRETATION OF WATER QUALITY FOR

IRRIGATION

Guidelines for Interpretations of Water Quality for Irrigation1

Potential Irrigation Problem Units

Degree of Restriction on Use

None Slight to Moderate

Severe

Salinity(affects crop water availability)2

ECw dS/m < 0.7 0.7 – 3.0 > 3.0

(or)

TDS mg/l < 450

450 – 2000 > 2000

Infiltration(affects infiltration rate of water into the soil. Evaluate using ECw and SAR together)3

SAR = 0 – 3 and ECw = > 0.7 0.7 – 0.2 < 0.2

= 3 – 6 = > 1.2 1.2 – 0.3 < 0.3

= 6 – 12 = > 1.9 1.9 – 0.5 < 0.5

= 12 – 20 = > 2.9 2.9 – 1.3 < 1.3

= 20 – 40 = > 5.0 5.0 – 2.9 < 2.9

Specific Ion Toxicity (affects sensitive crops)

Sodium (Na)4

surface irrigation SAR < 3 3 – 9 > 9

sprinkler irrigation me/l < 3 > 3

Chloride (Cl)4

surface irrigation me/l < 4 4 – 10 > 10

sprinkler irrigation me/l < 3 > 3

Boron (B)5 mg/l < 0.7 0.7 – 3.0 > 3.0

Trace Elements (see Table 21)

Miscellaneous Effects (affects susceptible crops)

Nitrogen (NO3 - N)6 mg/l < 5 5 – 30 > 30

Bicarbonate (HCO3)

(overhead sprinkling only) me/l < 1.5 1.5 – 8.5 > 8.5

pH Normal Range 6.5 – 8.4

Source:.S. Ayers, D.W. Westcot, 1989/1994, 29 Rev.1, Water Quality For Agriculture, FAO Irrigation and Drainage Paper.

1 Adapted from University of California Committee of Consultants 1974.

2 ECw means electrical conductivity, a measure of the water salinity, reported in deciSiemens per metre at 25°C

(dS/m) or in units millimhos per centimetre (mmho/cm). Both are equiva-lent. TDS means total dissolved solids, reported in milligrams per litre (mg/l). 3 SAR means sodium adsorption ratio. SAR is sometimes reported by the symbol RNa. See Figure1 for the SAR

calculation procedure. At a given SAR, infiltration rate increases as watersalinity increases. Evaluate the potential infiltration problem by SAR as modified by ECw.Adapted from Rhoades 1977, and Oster and Schroer 1979. 4 For surface irrigation, most tree crops and woody plants are sensitive to sodium and chlor-ide; use the values

shown. Most annual crops are not sensitive; use the salinity tolerance tables (Tables 4 and 5). For chloride tolerance of selected fruit crops, see Table 14. With overhead sprinkler irrigation and low humidity (< 30 percent),

Page 127: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

127

sodium and chloride may be absorbed through the leaves of sensitive crops. For crop sensitivity to absorption, see Tables 18, 19 and 20. 5 For boron tolerances, see Tables 16 and 17.

6 NO3 -N means nitrate nitrogen reported in terms of elemental nitrogen (NH4 -N and Organic-N should be

included when wastewater is being tested).

Page 128: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

128

ANNEX 10: IRRIGATION WATER REQUIREMENTS

Irrigation water requirements – approach

A comprehensive study into the irrigation water requirements as part of the overall national

Water Resources Management Strategy was carried out by (MOP 1999-6). The method used

in this study is quoted in detail in the box below; it is the normal approach described in (FAO,

1977) and applied worldwide.

The crop irrigation water requirements consist of the potential crop evapotranspiration, ETp, minus the

effective rainfall, Pe.

The potential crop evapotranspiration, ETp, is the volume of water required to meet the crops’ potential

evapotranspiration during a specific time period, under a given cropping pattern and in a specific

climate. The ETp is based on the reference crop evapotranspiration, which can be calculated

according to the FAO Modified Penman Method or the Penman Monteith approach. Research at the

field station of the University of the West Indies reveals that the Penman Monteith approach performs

better under the local conditions prevailing in Trinidad and Tobago (Simon, 1995). In this report the

Penman Monteith approach will be used for the calculation of the reference crop evapotranspiration,

ETh.

To determine the potential crop evapotranspiration, ETp, the reference crop evapotranspiration value is

multiplied by a crop coefficient, kc. (see Section 4.2.2) Hence ETp = kc ETh.

Subsequently the crop irrigation water requirement is determined by reducing the calculated ETp value

by the effective part of the precipitation, Pe. The effective precipitation is that part of the total

precipitation on the cropped area, during a specific time period, which is available to meet

evapotranspiration in the cropped area.

Finally the Irrigation Water Requirements will be determined based on the efficiency of the irrigation

system. In an ‘average’ irrigation system more water is delivered from the water source than is

consumed (i.e. evapotranspired) by the irrigated crops. Most of the un-consumed part of the delivered

irrigation water returns to the groundwater or to the downstream surface water system.

To calculate the volume of irrigation water required to be delivered to the scheme, the crop irrigation

water requirements, ETp-Pe, is divided by the overall (or project) irrigation water-use ratio or efficiency

which quantifies the fraction of the irrigation water evapotranspired by the crops.

The consultants’ team of DHV used the CRIWAR simulation model to calculate the crop water

requirements (Bos et al, 1996).

In the study (MOP, 1999-6) the objective was to obtain values for national water resources

management evaluation. In this study a lot of interesting and useful work was done. Irrigation

requirements were calculated in the usual manner following the next four steps:

a. Calculate the ETh or reference evapotranspiration using the Penman Monteith formula,

based on average monthly values for temperature, humidity, wind and sunshine /

radiation (Piarco Airport record);

b. Select and apply the crop coefficients kc for the crop or crop mixture in the irrigation

scheme and calculate the crop evapotranspiration or ETp

c. Estimate the effective rainfall based on average monthly rainfall values

d. Estimate the irrigation efficiency

a. Reference Crop Evapotranspiration

Page 129: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

129

Climatic data are measured at meteorological stations which are listed in Table 18.1.

Recordings, made by various departments, are collected by WRA and published in their

yearly Climatic Reports.

Table 18.1: Hydro-meteorological Stations

Name Number Measuring Agency Elevation (m)

Hollis Reservoir 2.3 WASA 152.4

Navet Reservoir 3.8 WASA 121.9

Penal Demonstration 7.7 WASA 12.2

Centeno 9.24 Ministry of Agriculture 15.2

UWI 9.6 UWI

WRA 9.63 Meteorological Department

Piarco Airport 9.32 Meteorological Department 11.0

Crown Point 15.1 Meteorological Department 7.6

Source: WRA Climatic Reports

The Hollis and Navet observation stations are located at the reservoir sites at higher

elevations. Since most of the irrigated areas are in the lowlands, these stations are of less

relevance for the determination of water demands for irrigated agriculture. The data obtained

at the Penal station have too many gaps (for the period 1975-1995 complete data sets are

only available for 7 years). The same counts for the observations at Centeno. The

observation stations at UWI and WRA were just recently started. Only the observation

stations at the Piarco and Crown Point Airports have long- term data available on humidity,

temperature, wind speed and sunshine hours. For this reason the Reference Crop

Evapotranspiration is determined based on the data from Piarco Airport (see Table 18.2).

Table 18.2: Reference Crop Evapotranspiration, data Piarco Airport (1975-1995)

Month Maximum

Temp

(oC)

Minimum

Temp

(oC)

Mean Rel.

Humidity

(%)

Mean Wind

velocity

(km/day)

Sunshine

hours

(h)

ETh

(mm/day)

January 29.6 20.4 78.6 112.9 7.69 3.8

February 30.4 20.5 74.4 128.4 8.08 4.4

March 31.2 21.1 70.8 151.1 7.80 4.9

April 31.8 21.8 69.8 150.9 7.69 5.0

May 31.6 22.7 73.4 151.1 7.43 4.8

June 30.7 22.9 78.5 128.8 5.99 4.1

July 30.9 22.8 80.0 108.9 6.45 4.1

August 31.2 22.9 81.8 90.0 6.49 4.1

September 31.7 22.6 79.9 89.5 6.47 4.2

October 31.5 22.6 79.1 86.7 6.33 3.9

November 30.8 22.2 79.7 87.6 6.42 3.6

December 30.1 21.4 76.6 98.2 6.72 3.5

Year 31.0 22.0 76.9 115.3 6.96 1531

Co-ordinates of Piarco Airport are10.37 N.L; 61.21 W.L

The number of climatic observation stations is small, and it is questionable whether they can

be considered representative of the whole country. Initiatives to address this situation have

already been taken by the Meteorological Department, which has recently installed five

telemetric stations (one at WRA).

Page 130: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

130

b. Crop coefficients for the area

In most of the irrigated areas the main crop is vegetables, compromising a large variety of

vegetables, the main vegetables being cabbage, pumpkin, tomatoes, melongene (eggplant)

and cucumber (see Figure 18.1).

Figure 18.1: Green Vegetables Area cultivated in St George

Source: CSO, 1996

The crop coefficients (kc) are determined for the main stages of crop development (FAO,

1977):

Period 1: Initial growth (nursery);

Period 2: Crop development;

Period 3: Mid season;

Period 4: Late season

In areas without flooding during the wet season, vegetables can be grown on a continuous

basis throughout the year, with different planting dates and harvesting. For this situation an

overall crop coefficient (kc) can be adopted. The determination of the overall crop coefficient

is based on the kc values of the 5 main vegetables (see Table 4.4). If other vegetable crops

are added to this mix the effect on the overall kc will be so small it can be safely ignored.

Table 18.3: Overall Crop Coefficients (kc) for continuous vegetable growing

Stage crop

development

Crop

Period 1

(days)

kc

Period 2

(days)

kc

Period 3

(days)

kc

Period 4

(days)

kc

avg

kc

Cabbage 20 0.4 30 0.68 20 0.95 10 0.8 0.69

Pumpkin 30 0.4 40 0.68 45 0.95 30 0.6 0.69

Tomatoes 30 0.4 40 0.73 45 1.05 30 0.6 0.73

Melongene (eggplant) 30 0.4 45 0.68 40 0.95 20 0.8 0.72

Cucumber 25 0.4 35 0.65 50 0.9 20 0.7 0.71

Sources: MOP 1999-6 (using WS Atkins 1993, Agristudio 1994, FAO 1979, FAO 1977)

0,0

20,0

40,0

60,0

80,0

100,0

120,0

are

a (

ha)

vegetables

dry season

wet season

Page 131: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

131

The average of the 5 weighted average kc values is used as the overall crop coefficient: 0.71;

the maximum is 0.73. While the (MOP 1999-6) study used the average vegetable kc of 0.71,

it is proposed to use the maximum value of 0.73 for the Felicity Pilot area.

If other crops, e.g. tubers, are irrigated, the resulting kc will be significantly different; this is

also true if large areas are used to cultivate one single (vegetable) crop.

c. Effective precipitation

To determine the effective precipitation several approaches can be used and each of these

approaches has its advantages and disadvantages. The (MOP, 1999-6) study used the

CRIWAR model for an approach which is generally applicable.

Effective precipitation is that part of the total precipitation that replaces, or potentially

reduces, a corresponding net quantity of required irrigation water. To calculate the effective

precipitation, the model uses a semi empirical method developed by the U.S. Department of

Agriculture. This method is combined in the model with an improved estimate of the effect of

the net irrigation application depth on effective precipitation.

Three major factors are considered to influence the effectiveness of precipitation:

1. Mean Cumulative Monthly Precipitation. In areas with light precipitation during the

growing season losses to deep percolation to the groundwater and surface run-off will

usually be low. Consequently the effectiveness of precipitation in areas with light

precipitation will be high.

2. Mean Cumulative Evapotranspiration. When the evapotranspiration rate is high, the soil

water will be rapidly depleted. As a consequence, a large amount of water can be stored

in the soil profile again before it reaches field capacity. Thus, the higher the

evapotranspiration rate, the higher the effectiveness of precipitation.

3. Irrigation application depth. For most irrigation areas, the depth of water application per

irrigation turn is assumed to equal the readily available soil water that can be stored in

the root zone. The capacity of the soil profile to store water for crop use depends on the

soil type and the effective rooting depth. A high storage capacity within the root zone

(which is equal to the application depth) indicates a relatively high effectiveness of

precipitation.

In CRIWAR, the effective precipitation is calculated on a monthly basis by an empirical

expression, which reads as follows:

Pe = f ( 1.253 P0.824

- 2.935 ) x 100.001ETp

where

Pe = effective precipitation per month (mm)

P = total precipitation per month (mm)

ETp = total crop evapotranspiration per month (mm)

f = a correction factor which depends on the irrigation application depth per turn

The factor f equals 1.0 if the irrigation water application depth (Da) is 75 mm per turn. For other

application depths, the value of f equals:

f = 0.133 + 0.201 ln Da if Da < 75 mm/turn

and

Page 132: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

132

f = 0.946 + 7.3 x 10-4

x Da if Da > 75 mm/turn

If the use of these equations results in an effective precipitation that exceeds either ETp or P,

CRIWAR reduces the Pe value to the lowest of these two. When the mean total rainfall per

month is less than 12.5 mm, CRIWAR assumes all precipitation to be 100 per cent effective.

In the (MOP 1999-6) study average monthly rainfall data were used to determine the

effective precipitation. These results are useful for long-term water management planning at

the national level.

In the Felicity pilot study the requirement is different. The objective is to determine the crop

water requirements based on the farmers requirement. The farmer will not accept a yield

reduction every other year, which will happen if monthly averages are used to dimension the

system. In fact the farmer would like to see that there is always sufficient water. This may

prove uneconomical, however. A commonly accepted approach is to ensure that only once

every four or five years the water supply will not cover the entire irrigation water need and

crop yield reduction may occur. In other words, in 75%-80% of the cases the supply will be

adequate. This means that step c (calculate effective rainfall) needs to be different from the

approach of (MOP, 1999-6).

In this study a probability of 75% is assumed46; this means that only once every four years

the crop may show yield reduction from a limited supply of water. Rainfall data from

(MFPLMA, 2011) were used, see Table 4.9. The table also shows the rainfall adjusted for

2013, using the selected climate change outlook / trend for rainfall, see 13.2.5. The

difference is in the rainy season months, when the predicted decline in (average, monthly)

rainfall is 6.1 mm per decade.

Adjustment for local conditions

To use the Piarco rainfall data for the Felicity Pilot area a correction on the rainfall statistics is

made; a problem here is that only a yearly rainfall isohyetal map is available (Figure 18.2)

whereas there may be a different statistical relation for the dry season than for the wet

season. Another possible approach is to use the shorter time-series of two rainfall stations

operated by the Water Resources Agency at Flanagin Town and Mamoral. However, these

stations are a distance to the east, inland and on higher ground. For this reason a correction

using the isohyetal map of Trinidad (Figure 18.2) has been selected as the best approach

considering the available datasets, resulting in a 10% lower rainfall figure (2000mm/y vs

1600mm/y) to be applied for the months of the dry season.

The resulting effective rainfall for the Felicity Area is presented in Table 18.4 and Figure

18.3.

46 80% or 90% is also possible, but needs further statistical analysis of the rainfall dataset

Page 133: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

133

Figure 18.2: Trinidad Isohyetal Map

Source: (WASA, 2008-21).

Table 18.4: Precipitation in mm (1971 – 2010)

Series 1971-2010 Adjusted 20133

month average 75% Flc1 Pe

2 75% Flc

1 Pe

January 75.4 31.7 28.5 15.1 31.7 28.5 15.1

February 48.1 24.0 21.6 11.6 24.0 21.6 11.6

March 37.3 14.1 12.7 6.9 14.1 12.7 6.9

April 54.8 14.7 13.2 7.2 14.7 13.2 7.2

May 116.1 51.0 45.9 24.9 51.0 45.9 24.9

June 240.7 177.6 159.8 71.4 167.2 141.1 61.1

July 254.0 201.1 181.0 80.0 190.7 162.3 69.8

August 259.4 201.0 180.9 79.8 190.6 162.2 69.6

September 189.7 154.1 138.7 63.1 143.7 120.0 52.9

October 209.3 135.9 122.3 56.2 125.5 103.6 45.9

November 233.0 176.2 158.6 68.6 165.8 139.9 58.3

December 157.0 101.6 91.4 42.6 91.2 72.7 32.3

Total 1874

Source: MFPLMA, 2011 (average and 75%); own calculations 1 Adjusted for difference between Piarco and Felicity using isohyet map;

2 Calculated using CRIWAS (3.0).

3 Corrected for trend in climate change to 2013 of 6.1 mm decrease per decade (Chapter 9.2). The 75% rainfall is about 74%

lower than the average rainfall, so the rainfall figures for 1971-2010 were adjusted by subtracting 10.4 mm (28 year x 0.61mm

x 74%) from both the 75% rainfall and the 75% effective rainfall monthly figures47

.

47

This is based on the assumption that the recommended trend based on the selected climate change scenario

(see Chapter ....) started already in 1971, the start of the rainfall data series used in this study. However, in :

Page 134: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

134

Figure 18.3: Effective Rainfall Felicity Area for 2013 and 2050

Use of decade data

One more way to improve accuracy is to use decade (10 day) data for both the determination

of the Reference Crop Evapotranspiration and for the effective precipitation. While this is

recommended when designing rotation schedules for irrigation management, this level of

accuracy is not generally used for design purposes. Also, the assumptions related to the

cropping pattern and planting dates need to be known much more accurately. It is not clear if

such levels of irrigation management are required or desirable within the Trinidad context.

d. Irrigation Efficiency

Irrigation efficiency is defined as the ratio between the net and gross irrigation requirements.

Once the crop irrigation water requirements (net) have been determined, the irrigation

requirements (gross) can be obtained by taking into consideration conveyance losses

(including seepage and evaporation), distribution (or operational) losses and field losses

(including losses due to deep percolation through the root zone to groundwater and field

runoff)48.

Return flow, closed loop system

Irrigation efficiencies can be established for various levels, such as the field, system, or

regional (river basin) level. This distinction is important for water resources development

studies, where drainage losses from one system may add to the available supplies for other

downstream users (re-use of drainage water). Regional efficiencies can be much higher than

efficiencies for individual irrigation schemes. An example is the irrigated system of the Nile

Delta in Egypt. The overall system efficiency in the delta is about 90 per cent, although the

efficiency of individual schemes can be as low as 50 per cent. This phenomenon of re-use is

taken into account in the (MOP, 1999-6) study. The return flow is defined as the percentage

of the gross irrigation requirements which will return to the surface water system. For most

MFPLMA, 2011 the trend for average yearly rainfall data appears to be flat. If the correction is not applied this will result in a significant reduction (10%) of the calculated water requirement. 48

A detailed study on irrigation efficiency is recommended to establish the irrigation losses / efficiency based on the local situation and conditions. Another approach is to actually consider the Felicity area as a pilot and to monitor the actual losses; this knowledge can then be adapted and applied to other areas in Trinidad.

0.0

10.0

20.0

30.0

40.0

50.0

60.0

70.0

80.0

90.0

0 1 2 3 4 5 6 7 8 9 10 11 12

eff

ect

ive

rai

nfa

ll (m

m/m

on

th)

month

effective rainfall Pe

Pe 2013

Pe 2050

Page 135: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

135

schemes a return percentage of 30 per cent is used, for sprinkler irrigation and the relatively

efficient irrigation at the former Caroni (1975) Ltd Rice Farm lands a value of 20 per cent is

used. This means that it is assumed that in most of the areas 30 per cent of the gross

irrigation requirement will return to the system.

There is a serious downside to this approach: salinisation. This strongly depends on the

water quality, and although initially it may seem to be a benign problem, in the end it requires

specific measures: e.g. expansive drainage systems have been built in Iraq, Pakistan, Egypt,

and large parts of Central Asia with the sole purpose of salinity control / land reclamation; in

parts of the Unites States drainage is no longer allowed for reasons of saline effluent,

effectively rendering irrigation impossible.

For the design of a single irrigation scheme the return flow cannot be taken into

consideration, unless the return flow is re-used again by pumping it back to the inlet of the

scheme and mixing it with the ‘fresh’ irrigation water supply. This method, also known locally

as ‘closed loop re-use’ and applied on a pilot scale on a farm close to the Felicity pilot area49,

will be considered as an option for the full Felicity area with the selected approach (see

Chapter 14). For now the closed loop re-use is seen as an option to reduce the total

requirement of irrigation water. In the design options it is considered as an alternate,

additional water resource, to be added to reach the overall irrigation water requirement

estimated in this chapter.

Irrigation efficiencies for rice, vegetable cultivation and citrus are discussed below.

Rice

The only irrigated area with double rice cropping is at the Rice Farm managed by Caroni

(1975) Ltd., which is located in the lower part of the Caroni basin. Irrigation water for this

farm is pumped from different streams. The rice is grown on heavy clay soils (with restricted

internal drainage), which can be assumed to have small infiltration losses (low infiltration

rates, low deep percolation losses). Adjacent to the Rice Farm is the Caroni swamp,

percolation losses to the swamp are most probably not high (high groundwater table). Given

this situation an overall irrigation efficiency of 65 per cent is assumed for the Rice Farm:

about 20 % is lost in the conveyance system and another 20 per cent is lost during the field

application (so irrigation efficiency is 0.8 x 0.8).

Vegetables

Vegetables are generally grown on beds. To irrigate the crops ‘spray pipes’ or ‘spray hoses’

are now widely applied, mostly replacing the older ‘furrow-splash’ method. These flexible pvc

pipes are rolled out in the field and stay there until they need to be replaced or until tilling

takes place. The spray pipes deliver water to the crops directly and by filling the furrows in

between, acting as miniature sprinklers. They are connected with rigid pvc pipes through

couplings; the rigid pipe delivers the water to the field. Only low pressure is needed, saving

construction costs and energy. See box below and the pictures in Figure 18.4 and Figure

18.5.

49

The farm, known as Mr. Roop’s Farm, is run on a basis of environmentally friendly and holistic farming. In fact, the term ‘closed loop’ is misleading, in fact this 3-acre plot can better be termed ‘self-contained’. While the full concept will be difficult to replicate on a wider basis, aspects of his approach can be applied. The regulation that tree crops are not allowed in the Felicity Area also precludes successful adoption of main elements of Mr. Roop’s farming system.

Page 136: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

136

Box: commercial supplier praising the advantages of spray pipes

1. It is a water-saving system for spraying irrigation water that requires only low

water pressure, which really helps save electricity and water.

2. It sprays evenly. This helps improve the germination rate of seeds and the

survival rate of seedlings.

3. It has two functions: One is it sprays evenly. The other is to inject the liquid

fertilizer into the tube, mix with the water. This helps establish the evenness of

topdressing.

4. After using solid fertilizer, the spraying irrigation helps dissolve fertilize effectively

seep into the soil and easily reach the root zone without washing out.

5. It helps maintain the looseness of soil (note: important according to Trinidad

farmers).

6. The crops are planted in rows which are extremely suitable for using our spray

tubes which spray can cover a width of 7 meter.

7. It is the most suitable equipment for irrigating sandy soil

8. Spraying irrigation in late afternoon reduces the survival rate of moths and other

harmful insects, and thus reduces the amount of pesticide that is required

In addition: it is readily available in Trinidad, accepted and used by the farmers,

and economical – the price of the tubes were not seen as a problem.

Page 137: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

137

Figure 18.4: Spray pipes / tube – fitting and pipes in vegetable field in Felicity area.

Figure 18.5: Spray pipes / tubes application in a vegetable field (China)

The use of overhead sprinkler systems is discouraged in Trinidad, because of relatively high

water losses. “Evaporation losses from the spray are small and generally below 2 percent.

Losses due to wind drift may be considerable at higher wind speeds and can reach 15% at

5m/s. Strong winds also result in a poor water distribution pattern. Overhead sprinkler

irrigation should not normally be used when wind speeds are higher than 5m/s” (FAO,

1977p64). Farmers in Trinidad also mention the labour intensity of overhead sprinkler

systems as these typically have to be moved every few hours.

In the dry season irrigation is applied every 2-3 days. In some areas water is pumped directly

from the streams, and in other areas a conveyance system (e.g. Aranguez) is used.

Vegetables are usually grown on well drained soils, which suggest that percolation losses

may be higher. On the other hand operational losses might be smaller since the irrigation

technique described above is efficient, and losses will only occur in the furrows around the

beds and in the conveyance system to the fields. The overall efficiency is assessed at 67 per

Page 138: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

138

cent: assuming a field application (tertiary) efficiency of about 75 per cent and a conveyance

(secondary) efficiency of about 90 per cent.

For the Felicity area, assuming that spray pipes will be applied, the overall scheme efficiency

is estimated at 65-70%, while the on-farm application efficiency is estimated at 75%.This is

not taking into account any losses in the conveyance system from the source of the irrigation

water to the Felicity Pilot Scheme intake; these will depend on the conveyance option that is

selected and implemented.

e. Additional considerations

Local rainfall figures are not used because the time series are not long enough. In the future

these local rainfall figures may be used as input.

Local meteorological data are not used. For now the only reliable long-term dataset for non-

rainfall meteorological data is available from the Piarco Airport Meteorological Station only.

As this is not very far (relatively) and at roughly the same elevation as the Felicity Pilot site,

this assumption is considered acceptable.

Wind can vary greatly at short distances, being influenced by the elevation of land and wind

shielding by large crops, trees and bushes, as well as by build-up areas. As detailed

information is not available at the time of this study and as this is mostly useful in determining

localized irrigation schedules, the effect of wind variability is ignored.

Local variability in effective rainfall and evapo-transpiration: these are often caused by local

variations in wind, see above.

Soil differences translate into different rates of infiltration, which can strongly influence field

application efficiencies. As the preferred method of irrigation is the use of spray pipes and as

the soils of the Felicity Pilot area are relatively heavy (50% clay, 50% sand/silt mix), while the

typical irrigation gift is relatively small, it can safely be assumed that deep percolation losses

are limited and soil differences do not translate into large infiltration differences.

Supplemental irrigation: In fact all irrigation in Trinidad can be described as ‘supplemental

irrigation’ as even in the dry season there is a contribution from rainfall. However, the term is

often associated with irrigation during the rainy season. The availability of irrigation water will

give extra security for the farmers to plant at dates that are more optimal, related to expected

harvest dates and prices; it also reduces the probability of crop yield reduction if the ‘petite

careme’ dry interval during the rainy season (end of September, early October, typically 15-

18 days) is particularly dry and pronounced. Interestingly the calculations based on the 75%

effective rainfall show that even in the rainy season there is a clear need for irrigation, a need

that gets more pronounced if climate change outlooks are considered (see 13.2.4 and

13.2.5).

Variability in crop factors: In Table 18.3 crop coefficients are given. In fact the crop

coefficients depend on variety, planting date, local and micro-climate, and also on the

availability of other growth factors such as sunlight, fertility, temperature and soil. Pests and

diseases can radically reduce crop development, lowering ETh. For the calculation of the

irrigation water requirement it is assumed that crop growth is unimpeded and all

circumstances are optimal.

Soil salinity: ETh can be affected by soil salinity since the soil water uptake by the plant can

be drastically reduced due to higher osmotic potential of the saline groundwater. Poor crop

Page 139: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

139

growth may be due to adverse physical characteristics of some saline soils. Some salts

cause toxicity and affect growth. The relative extent to which each of these factors affects

ETh cannot be distinguished (FAO, 1977). For the Felicity Pilot area we will not consider soil

salinity in the calculation of ETh.

In Trinidad and at the Felicity Pilot area location the average yearly rainfall exceeds the

average yearly evaporation. If there is any accumulation of salt during the dry season

irrigation it can be assumed that this is leached out during the rainy season. An adequate

drainage system needs to be in place to ensure the proper evacuation of the leaching and

normal drainage water. The decrease of overall rainfall due to climate change may have to

be considered, and the increase in salinity during (relatively) dry years should be monitored.

Crop yield reduction: while the calculations are done for a crop that is fully supplied with all

inputs and water, the effect of a (temporary) reduction in the availability of water in the root

zone on crop yield is very dependent on the stage of crop growth. Crops are very sensitive to

water stress during specific growth stages, such as germination and establishment, flowering

and seed development. Conversely, during the crop ripening stage and often during the

vegetative stage a temporary lack of water will result in a delay in growth, or in a small

overall yield reduction. For some crops the reduction of the water application in the

harvesting stage has a positive effect on the quality (FA), 1977).

Crop selection / cropping pattern: It is obvious that the actual cropping pattern in the Felicity

Pilot area will determine the crop water requirements. As the cropping pattern is free

(restrictions are on tree crops only) an overall estimate of the ETh is the only practical way to

design the irrigation system. However, with the assumptions made and the use of the highest

of the average vegetable kc values there is enough flexibility to adopt other crops, too. Crops

that require very high amounts of irrigation water, such as rice and aquaculture, may not be

possible (and should be prohibited) in the Felicity Pilot area.

Drought resistant crops: In the Trinidad context, with a relatively short dry season in which

still significant rainfall occurs, the combination of drought resistant crops and irrigation is not

practical or economical. If irrigation water is relatively scarce crops that can withstand brief

periods of water stress without significant yield reduction can be selected. In general the

investment for irrigation infrastructure, both at scheme level and on the field, will only be

justified if relatively high-value crops can be grown. In general drought-resistant crops are

also lower value and lower yielding. Efforts at regional crop research centres to develop high-

yield high value crops that can handle water stress better should be closely watched;

promising crops should be tested in Trinidad and then promoted by the Ministry of Food

Production – extension service.

Page 140: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

140

ANNEX 10: DESIGN

Page 141: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

141

1. SCENARIOS WATER SOURCE FELICITY

Following discussions in the week of 02-06 September between the design team and the

consultants the possible scenario’s had to be revisited, mainly due to better understanding of

costs. The main costs appear to be pumps with high discharges and the pipeline to convey

the water from the RSSP to Felicity.

Unfortunately an estimate of the benefits for the introduction of irrigation at Felicity is not

available due to the limited time available and ambitious planning for the project.

The infrastructure within the Felicity area, to convey the water from the primary source to the

various blocks (laterals / secondary), and the offtakes to the ponds (tertiary) remain the same

regardless of the selected water resource option. This has been elaborated and the costs

have been estimated using the best available unit costs.

The use of on-farm ponds of standard dimensions (20x20 m, 4 m effective depth) was also

part of the standard lay-out. Smaller ponds have been proposed and are now used in the

design50. The dimensions of the smaller ponds are 17.5x17.5, without embankment (or only a

small rise to prevent unwanted drainage and siltation.

1.1 Scenario 1: Pipeline from RSSP to Felicity.

Availability of water is sufficient, at least for now; the RSSP (Ravine Sable Sand Pits) will act

as buffer during both the dry and rainy season. A relatively low maximum flow (200l/s) is

needed.

Requirements:

- Regulator to divert water from Caparo River into RSSP (part of Caparo River Basin Study

recommendations for flood mitigation – not costed in Felicity project)

- Submersible pump at RSSP, head +20m, intake protection – stilling well, pump house,

generator or electrical mains. Capacity /design flow in dry season is 170 l/s. Operation

24/7 (during peak demand). Detailed design will only be possible once a decision on the

implementation of the RSSP is made, which may be several years in the future. A study

should be made on the feasibility of a pump on a floating raft; the intake will then always

be at the optimum level, siltation will not be a problem, and any type of pump can be

used, as suction head is not a problem. The joints to allow free floating of the platform

should be designed with care.

- Pipeline to connect RSSP with Felicity head works. HDPE, Ø600mm, 11.5 km (along old

railway, Caparo River to Honda bifurcation, Honda River, Caparo River

- (Booster) pump to pressurise the secondary pipe system again

50

Based on decisions made during a final Design meeting on 09/09/2013

Page 142: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

142

Figure 1.1: Alignment of the RSSP to Felicity pipeline

Considerations:

- The pipe will be expensive

- A booster pump at the head of the distribution system is needed, or the pump (into the

pipe) has to be dimensioned to facilitate flow over 11.5 km with 20 m + the initial pump

pressure; without these interventions there is not enough to pressure in the Felicity

secondary system.

1.2 Scenario 2: Using the Caparo River from the RSSP to Felicity

This scenario was thought to be second choice for reasons of water loss and water quality

issues, and especially because of expected large pump capacity, to take advantage of very

brief and high peaks in the river. However, as the pipeline option may be rather expensive

the consultants revisited some of the assumptions.

The core of this option is using the Large Buffer Ponds which are reserved in the lay-out of

the Felicity area. These ponds cover an area of 23.6 hectares; net area is perhaps 25% less,

at 18 ha. If a live storage depth of 4 meters is realised, they can hold 0.72 Mm3. This can be

pushed with a live storage of 4.5m (and higher embankments) to 0.81 Mm3. The ponds are to

be interconnected to allow for more flexible and efficient use of the water stored, and to

optimise the combined storage of the ponds. A detailed calculation of volume and

dimensions is given in the discussion on Phase 1, in Table 1.4.

Requirements:

- RSSP for buffering in both the dry and rainy season

- Regulator to divert water from Caparo River into RSSP (part of Caparo River Basin

Study recommendations for flood mitigation – not costed in Felicity project)

- Submersible pump at RSSP, head +20m, intake protection – stilling well, pump house,

generator or electrical mains. Capacity /design flow in dry season is 5x180=900 l/s.

(considering 10% losses and no water theft). Operation during 2 days continuously out

of 10 during peak demand time (week 1-24).

- Pump into the Caparo River at RSSP location

- Divert from Honda River to Chandernagore River (20% of flow); a diversion work is

required;

Page 143: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

143

- Pump at Chandernagore River (one pump, capacity 1x170 l/s). Pump into the 2 Large

Buffer Ponds (LBPs) LLBP 3 and LLBP 4.

- Pump at Caparo River (four pumps, capacity 1x170 l/s). Pump into the Large Buffer

Ponds (LBPs) R1, R2 and R3 and LBP L1, L2, L3 and L4.

Interconnecting pipes between the LBPs (between L1-L4, and R1-R3, and LLBP3 and 4), to

allow for flow in both ways. Considerations:

- The design of the main pipe distribution system in the Felicity Area should allow

interconnection between the ponds and 5 pumps using large pipes, to minimise head

losses and head differences over the system, regardless of which pump supplies the

main;

- When there is water in the river(s) all pumps should run to fill the ponds, one of them to

fill / pressurise the main pipe system of Felicity. Each of the pumps may be used for this.

- All pumps at the LBPs can be used

o to pump from the river into the Felicity distribution system (Z = 6m, P = 50 m, Δh =

10-15 m))

o to pump from the river into the LBPs (Z = 3 m, Δh = 10-15m)

o to pump from the LBPs into the Felicity distribution system (Z=<1m, Δh = 5-10 m, P

= 50m)

- The pumps should be standardized in order to deliver the required flow and head into

the Felicity distribution system

- Sets of ponds (on both sides of the Caparo River) will be serviced by one pump

- Pumps will be situated on the river, raised (1 meter) to safeguard them from flooding

- An oblique weir will be installed at the pump site, to create a buffer while still allowing

large volumes of water to pass during a flood. The weir will contain connector pipe/pipes

if two ponds on different sides of the river are to be serviced by one pump.

- A standard design for the oblique weir can be adapted to the required dimensions. The

dimensions of the Caparo River are not known to the consultants at this stage. Design

instructions are available in http://content.alterra.wur.nl/Internet/webdocs/ilri-

publicaties/publicaties/Pub20/pub20-h.annex3.pdf.

1.3 Option with Scenario 2

- Setting up / increasing the water level in the Caparo River and creating a larger buffer

- Use earth from the cut of the LBPs to build an embankment along the Caparo River

- Increase the level of the oblique weirs

- Increase the cross-section of the Caparo River to ensure sufficient capacity during floods

- Drain outfalls into the Caparo River need to be fitted with flap / no-return gates

- Ensure that the bridges / roads will not be flooded.

1.4 Closed loop – drainage re-use

While the disadvantages of the closed loop system (as asked for in the Terms of Reference)

are made clear at several locations in this report, the simplest way to realise ‘closed loop re-

use’ is to pump water from the Caparo River at the last bridge of the Felicity Area. A cross-

weir is proposed here to facilitate Phase 1 (see following text). With the pump that fills the

LBPs drainage water can (and will be, in Phase 1) be re-introduced into the system.

If a cleaning/treatment phase is to be included a reed bed is proposed. However, this takes

up land, and the water has to be pumped into the reed bed, and out of it again, into the LBP.

Page 144: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

144

Use of drainage water introduces (increased) risks of soil salinisation. Leaching of the soil

needs to take place at least once each season, preferably during the rainy season, and the

saline drainage water has to be evacuated from the Felicity area.

1.5 Phase 1: Develop 20% of the Felicity site first

Because water availability is a constraint (any work on the RSSP and works to deliver water

from the RSSP to Felicity will take more than one and possibly several years to complete)

the consultants propose to start with a ‘pilot in a pilot’. An area of 20% of the full project area

has been selected based on the following criteria:

- Abutting the Caparo River

- Sufficient area for Large Buffer Ponds

- On-farm ponds already installed in a relatively large proportion of plots

- Access to be relatively easy

Based on the above criteria the north-west corner of the Felicity project area was selected,

encompassing parts of both Felicity 1 (plots 1-77, two plot numbers missing) and Felicity 2

(plots 1-60), for a total of 135 plots, or almost exactly 20% of the 653 plots of the Felicity

project area.

1.5.1 On-farm ponds

On-farm ponds are used in the south of Trinidad to enable limited irrigated agriculture in the

dry season, and have been adopted by the Ministry of Food Production. If implemented

properly they can store a significant amount of water, but not enough to last the full dry

season in the Felicity Area. Considerations on the on-farm ponds:

- Construction appears to be somewhat expensive at TT$ 30,000 each (very roughly

costed at TT$ 20 per m3 cut).

- The buffer function of the on-farm ponds is essential to make the design and operation

flexible. Without the ponds the capacities for the distribution system and the pumps need

to be significantly larger (and more expensive) because of the fluctuations in demand for

water. With the ponds a constant delivery of water can be achieved. Monitoring of water

use is also easier.

- The required size of the ponds is open for discussion; in fact smaller ponds will also work,

as long as they can store at least 2 weeks of water demand in the dry season (ensuring

water availability). In the design we worked with a net volume of 1600 m3. In discussions

we understood that this may be (significantly) lower.

- The design needs to be optimised to store as much water as possible on as small a

footprint as possible. The current design has low embankments around the pond, which

take additional land without increasing the storage by much. A pond without

embankments takes much less land and can also benefit from local drainage into the

pond. Flooding should be prevented by creating an overflow / spill into the drains.

- Smaller sized ponds mean reductions in the tertiary lines, but also mean that the ‘refill’ of

the pond has to be more frequent. 2 weeks return time is considered the practical lower

limit for operation.

- This means that on-farm ponds with a capacity of about 600 m3 may be sufficient. A

different design can be made to accommodate that amount of water. Losses due to

evaporation and leakage will be lower. It is recommended to look at experiences with

storage of water used in greenhouses – intensive horticulture in the Netherlands is

Page 145: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

145

obliged to recycle water and buffer rainwater, and land is very scarce in these areas.

Lining there is done using sturdy geo-textiles/plastics.

- In the design a pond is considered to be constructed in cut only, 4 m deep, to be filled up

to 3.5 meter. Side slopes are assumed at 1:151. The average area of the pond can then

be kept at 172 m2. Overall area will be 17.5x17.5 m or a little below 4% of the plot size52.

- Smaller on-farm ponds mean larger Large Buffer Ponds. With the on-farm ponds reduced

to one-third of the volume (0.39 M m3) a LBP storage of about 0.61 M m3 is required. This

is possible on the reserved land within the Felicity project area and can be fitted in the

proposed design. In this annex calculations are shown which will enable Phase 1; the

calculated storage for Phase 1 is different as the full dry season requirement needs to be

buffered in this pilot phase.

- On-farm ponds take away land, not just in the dry season but also in the rainy season.

This has to be taken into consideration too. If a pond takes away 4% of the land this

means that during the rainy season 4% of the land cannot be used, which otherwise

would yield a crop. Thus the net ‘gain’ of irrigated land during the dry season is only

(100%-7/5*pond area percentage-pond area percentage). For 4% the effective loss is a

little less than 10% of dry season acreage. If the area of the pond is higher this factor is

also higher.

The operation of a system with smaller ponds as described above means that the operation

of the system gets much more intensive. Filling of the ponds will have to be scheduled up to

3 times as often, meaning that up to 3 times as many valves need to be opened on one

single day. Also, the buffering is much less, so flows into the ponds will be higher, as the

drawdown during the dry season in the on-farm ponds is much less. This will be buffered by

extra capacity in the LBPs (Phase 1 design), so the dimensioning of the primary system will

not change. The secondary system needs to be dimensioned to manage these higher

maximum flows (up to 210 l/s for the secondary system). For a simulated operation of a small

on-field pond see Figure 1.2 and Figure 1.2

51

A solution for the reported erosion needs to be found – experience indicated that lining the sides by smearing with mud will reduce leakage and stabilise the sides. This was explained during the field visit to Mr. Roop’s Farm (Mr. Ramgopaul Roop, [email protected]), on 23 August 2013. 52

Actually on average 13.1 m, if square, with an additional 2x2.25m to account for the slope.

Page 146: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

146

Figure 1.2: Simulated operation of a small pond – example - 2013

Figure 1.2: Simulated operation of a small pond – example - 2050

1.5.2 Design of Large Buffer Ponds

To compensate for the flow (at secondary level) of 32.9 l/s over 5 months (20% of 162 l/s), a

volume of 0.427 Mm3 needs to be stored / available; if smaller ponds are implemented the

volume will be 0.557 Mm3.

0

500

1000

1500

2000

2500

3000

3500

4000

0 5 10 15 20 25 30 35 40 45 50

Po

nd

leve

l mm

week

Pond level - 2013

depth ponds refill

dry season 18000 mm filltotal 30519 mm fill

0

500

1000

1500

2000

2500

3000

3500

4000

0 5 10 15 20 25 30 35 40 45 50

Po

nd

leve

l mm

week

Pond level - 2050

depth ponds refill

dry season 19000 mm filltotal 36832 mm fill

Page 147: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

147

Table 1.1: Large Buffer Ponds in Felicity Area – reserved area

Area (ha) perimeter (m) Area (ha) perimeter (m)

LBP L1 2.584 989 LBP R2 2.882 845

LBP L2 1.298 498 LBP R3 1.857 657

LBP L3 2.176 733 LBP LL3 1.912 601

LBP L4 3.676 793 LBP LL4 4.721 1013

LBP R1 2.545 707 total area 23.651 6836

Close to or adjacent to the ‘Felicity Pilot’ there are 4 reservations for Large Buffer / Retention

Ponds. Naming them from upstream to downstream along the Caparo River these are the

ponds indicated in blue in Table 19.1. These ponds will have a total (gross) area of about

10.7 ha.

However, the area that the embankments take in has to be considered. It is proposed to

make the LBPs with cut & fill, to create embankments from part of the cut. A typical

embankment design is shown in Figure 19.2. Considerations are given in Table 19.2.

Figure 1.3: Typical Large Buffer Pond embankment / design

Table 1.2: Dimensions of Large Buffer Pond Embankment

width area

top width 1.50 1.50 4.50

height 3.00

outside slope 1: 1.50 4.50 6.75

inside slope 1: 1.00 3.00 4.50

bottom width 9.00 15.75

Calculations show that the area of the embankment takes away a significant amount of land,

which has to be compensated by deepening the pond. A maximum height of the

embankment of 3 meter is assumed, with 0.5 meter of freeboard. At maximum storage the

water will be at 2.5 m above ground level.

Pond losses (sum of rainfall, evaporation and leakage losses, 1:4 year) over the months of

January until and including May (week 22) are 670 mm.

Eight different options have been calculated:

1. No extra area, no compensation for evaporation. It is assumed that the evaporation

during the dry season can be compensated by pumping the scarce flow peaks during

the dry season from the Caparo. The resulting pond area will be cut to the depth that

outside slope 2:3

bottom width 9 m

top width 1.5 m

inside slope 1:1

height 3 m

Page 148: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

148

allows for storage of the volume of irrigation water for the 135 ponds in Phase 1.See

Table 1.9 and Table 1.10.

2. No extra area, compensation for evaporation. In this scenario the evaporation losses

are compensated by increasing the storage depth. The resulting pond area will be cut

to the depth that allows for storage of the volume of irrigation water for the 135 ponds

in Phase 1. See Table 1.5 and Table 1.6.

3. Extra area by adding ponds no. 74, 75 and 76 to LBP R3, no compensation for

evaporation (see Table 19.5). It is assumed that the evaporation during the dry

season can be compensated by pumping the scarce flow peaks during the dry

season from the Caparo. The resulting pond area will be cut to the depth that allows

for storage of the volume of irrigation water for the 135 ponds in Phase 1. Extra area

will be added to decrease the required cut. See Table 1.11 and Table 1.12

4. Extra area by adding ponds no. 74, 75 and 76 to LBP R3, compensation for

evaporation. As 3, but with compensation for pond losses.Table 1.7 and Table 1.8.

For each of these options a further option was considered: using smaller on-field ponds. This

means that a total of 8 possibilities were calculated and evaluated. An overview of the results

of the calculations is shown in Table 1.4.

Table 1.3: Add 3 plots to LBP R3

perimeter Area Phase 1

(m) (ha)

LBP L3 733 2.18

LBP L4 793 3.68

LBP R2 845 2.88

LBP R3 657 1.86

LBP R3 additional 307 2.44

total 7143 13.03

Without more accurate prices for earthworks and compacting it is not possible to do an

accurate estimate. However, as an indication the amount of cut has been calculated and an

indicative price of TT$ 30 per m3 has been applied, to cover all cut / fill and transport of

various volumes.

During a final meeting on 9/9/2013 decisions were made on:

- The application of smaller ponds

- The compensation of pond losses

- The possibility of using additional area (adding plots to the LBP area)

This means that Table 1.8 shows the estimated amounts of earthworks and the estimated

cost for constructing the LBPs for Phase 1.

Table 1.4: overview of different options – estimated cost for earthworks

cost est. (M TT$) depth cut (m)

on-farm ponds 1600 m3 600 m3 1600 m3 600 m3

pond losses not counted no extra plots 6.9 10.9 2.8 4.5

compensate pond losses no extra plots 8.6 12.4 3.5 5.1

pond losses not counted extra plots 5.5 9.3 1.8 3.0

compensate pond losses extra plots 7.4 11.3 2.4 3.7

Page 149: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

149

Table 1.5: Pond losses compensated, no extra plots, ‘normal’ ponds

Table 1.6: Pond losses compensated, no extra plots, small ponds

Table 1.7: Pond losses compensated, extra plots, ‘normal’ ponds

Table 1.8: Pond losses compensated, extra plots, small ponds – PREFERRED OPTION

Calculation embankment width area Unit cost Total

(m) (m) (m2) (TT/m3) (M TT/m3)

top width 1.50 1.50 4.50 cut/fil l 44.9 30 1.3

height 3.00 compacting 44.9 0 0.0

outside slope 1: 1.50 4.50 6.75 cut/remove 220.1 30 6.6

inside slope 1: 1.00 3.00 4.50 topsoil 21.2 30 0.6

bottom width 9.00 15.75 topsoil transport 21.2 0 0.0

topsoil removal 0.20 m realised volume 427.9

depth below level 3.50 m required volume 426.9

LBP R3 additional 0 cost estimate M TT$ 8.6 8.6

Pond losses dry season 0.67 m unit cost 1m3 TT$ 30.0

1=yes 0=no

(1000 m3)

Earthworks volumes

Calculation embankment width area Unit cost Total

(m) (m) (m2) (TT/m3) (M TT/m3)

top width 1.50 1.50 4.50 cut/fil l 44.9 30 1.3

height 3.00 compacting 44.9 0 0.0

outside slope 1: 1.50 4.50 6.75 cut/remove 348.6 30 10.5

inside slope 1: 1.00 3.00 4.50 topsoil 21.2 30 0.6

bottom width 9.00 15.75 topsoil transport 21.2 0 0.0

topsoil removal 0.20 m realised volume 556.3

depth below level 5.10 m required volume 556.9

LBP R3 additional 0 cost estimate M TT$ 12.4 12.4

Pond losses dry season 0.67 m unit cost 1m3 TT$ 30.0

1=yes 0=no

(1000 m3)

Earthworks volumes

Calculation embankment width area Unit cost Total

(m) (m) (m2) (TT/m3) (M TT/m3)

top width 1.50 1.50 4.50 cut/fil l 49.7 30 1.5

height 3.00 compacting 49.7 0 0.0

outside slope 1: 1.50 4.50 6.75 cut/remove 169.4 30 5.1

inside slope 1: 1.00 3.00 4.50 topsoil 26.1 30 0.8

bottom width 9.00 15.75 topsoil transport 26.1 0 0.0

topsoil removal 0.20 m realised volume 425.9

depth below level 2.35 m required volume 426.9

LBP R3 additional 1 cost estimate M TT$ 7.4 7.4

Pond losses dry season 0.67 m unit cost 1m3 TT$ 30.0

1=yes 0=no

(1000 m3)

Earthworks volumes

Calculation embankment width area Unit cost Total

(m) (m) (m2) (TT/m3) (M TT/m3)

top width 1.50 1.50 4.50 cut/fil l 49.7 30 1.5

height 3.00 compacting 49.7 0 0.0

outside slope 1: 1.50 4.50 6.75 cut/remove 306.9 30 9.2

inside slope 1: 1.00 3.00 4.50 topsoil 26.1 30 0.8

bottom width 9.00 15.75 topsoil transport 26.1 0 0.0

topsoil removal 0.20 m realised volume 563.5

depth below level 3.70 m required volume 556.9

LBP R3 additional 1 cost estimate M TT$ 11.5 11.5

Pond losses dry season 0.67 m unit cost 1m3 TT$ 30.0

1=yes 0=no

(1000 m3)

Earthworks volumes

Page 150: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

150

Table 1.9: Pond losses not compensated, no extra plots, ‘normal’ ponds

Table 1.10: Pond losses not compensated, no extra plots, small ponds

Table 1.11: Pond losses not compensated, extra plots, ‘normal’ ponds

Table 1.12: Pond losses not compensated, extra plots, small ponds

An alternative that has not been calculated is: not to increase the area of the LBPs but to

decrease the area of the irrigated land.

Calculation embankment width area Unit cost Total

(m) (m) (m2) (TT/m3) (M TT/m3)

top width 1.50 1.50 4.50 cut/fil l 44.9 30 1.3

height 3.00 compacting 44.9 0 0.0

outside slope 1: 1.50 4.50 6.75 cut/remove 163.9 30 4.9

inside slope 1: 1.00 3.00 4.50 topsoil 21.2 30 0.6

bottom width 9.00 15.75 topsoil transport 21.2 0 0.0

topsoil removal 0.20 m realised volume 425.5

depth below level 2.80 m required volume 426.9

LBP R3 additional 0 cost estimate M TT$ 6.9 6.9

Pond losses dry season 0 m unit cost 1m3 TT$ 30.0

1=yes 0=no

(1000 m3)

Earthworks volumes

Calculation embankment width area Unit cost Total

(m) (m) (m2) (TT/m3) (M TT/m3)

top width 1.50 1.50 4.50 cut/fil l 44.9 30 1.3

height 3.00 compacting 44.9 0 0.0

outside slope 1: 1.50 4.50 6.75 cut/remove 300.4 30 9.0

inside slope 1: 1.00 3.00 4.50 topsoil 21.2 30 0.6

bottom width 9.00 15.75 topsoil transport 21.2 0 0.0

topsoil removal 0.20 m realised volume 561.9

depth below level 4.50 m required volume 556.9

LBP R3 additional 0 cost estimate M TT$ 11.0 11.0

Pond losses dry season 0 m unit cost 1m3 TT$ 30.0

1=yes 0=no

(1000 m3)

Earthworks volumes

Calculation embankment width area Unit cost Total

(m) (m) (m2) (TT/m3) (M TT/m3)

top width 1.50 1.50 4.50 cut/fil l 49.7 30 1.5

height 3.00 compacting 49.7 0 0.0

outside slope 1: 1.50 4.50 6.75 cut/remove 113.3 30 3.4

inside slope 1: 1.00 3.00 4.50 topsoil 26.1 30 0.8

bottom width 9.00 15.75 topsoil transport 26.1 0 0.0

topsoil removal 0.20 m realised volume 438.1

depth below level 1.80 m required volume 426.9

LBP R3 additional 1 cost estimate M TT$ 5.7 5.7

Pond losses dry season 0 m unit cost 1m3 TT$ 30.0

1=yes 0=no

(1000 m3)

Earthworks volumes

Calculation embankment width area Unit cost Total

(m) (m) (m2) (TT/m3) (M TT/m3)

top width 1.50 1.50 4.50 cut/fil l 49.7 30 1.5

height 3.00 compacting 49.7 0 0.0

outside slope 1: 1.50 4.50 6.75 cut/remove 235.6 30 7.1

inside slope 1: 1.00 3.00 4.50 topsoil 26.1 30 0.8

bottom width 9.00 15.75 topsoil transport 26.1 0 0.0

topsoil removal 0.20 m realised volume 560.4

depth below level 3.00 m required volume 556.9

LBP R3 additional 1 cost estimate M TT$ 9.3 9.3

Pond losses dry season 0 m unit cost 1m3 TT$ 30.0

1=yes 0=no

(1000 m3)

Earthworks volumes

Page 151: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

151

The feasibility of adding plots to the LBPS needs to be investigated. Further optimisation by

adding plots to other LBPS can also be considered.

1.5.3 Pumps and cross weirs

For considerations on the pumps and cross weirs see 1.2: (Scenario 2: Using the Caparo

River from the RSSP to Felicity. Detailed design of cross weirs is not possible due to time

constraints and lack of information.

1.5.4 Irrigation management / scheduling

By reducing the maximum flow used to fill the on-farm ponds a significant saving in

investment can be realised (the tertiary pipes can be smaller). The meeting decided that for

Phase 1 separate pipes to the ponds and valve manifolds along the roads are to be

implemented. At a later stage it is possible to install telemetry. It is proposed to run Phase 1

as a pilot for at least three years and evaluate before extending to the full area.

Page 152: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

152

2. SECONDARY SYSTEM

2.1 General

A major concern in the distribution system is the ease of operation and the energy use, of

which the latter is for only a minor part determined by the distribution system. Under all three

options presented here the energy use is the same.

2.2 Lay-out and operation

The secondary system is oriented along the Caparo River, where 7 (out of 9) LBPs are

located, with a connecting balancing pipeline, or the (future) RSSP pipeline. From the

(RSSP) pipe line the laterals branch off, all with the same capacity of 61 l/s (3 full flow shares

to fill a pond53 with 2 m of water in 12 hrs = 55.5/0.90 = 61 l/s per lateral). On any one lateral

there will never be more than three ponds being filled at the same time. Depending on the

design there will be 8-10 laterals taking off of the main pipe, but there will never be more than

10 on-farm ponds taking full flow: the capacity of the main system is 200 l/s:

10* 18.5 /(ep*es) = 185/(0.95 * 0.90) = 195 l/s ≈ 200 l/s

The sub laterals’ and pond supply pipes’ designs depend on the options in the secondary

system (see para 3.3).

Ease of operation is typified by the effort the farmers and the O&M staff have to exert to

operate the system. A (semi-)central operation is proposed for the system so that the

individual farmers cannot tamper with the supply and the system will be used in a

responsible way: a government appointed or, preferably, a WUA appointed operator will

open and close the valves in a predetermined manner. There is flexibility in the system in

terms of flows per pond (100%, 50% 25% of full supply flow), which allows for varying fillings

(0.5, 1.0 and 2.0, m per filling) and over varying delivery periods (T = 6 hrs, 12 hrs, 24 hrs

and 48 hrs, although preliminarily, in phase I, one delivery period is chosen: 6-8hrs per day,

5 days a week; once the entire scheme is implemented this can be easily fitted in into the

then prevailing water scheduling arrangements).

For the distribution system the actual operation concentrates on the opening and closing of

the valves, i.e. setting and locking the valves, safeguarding the valves against tampering,

and ensuring the accessibility of the infrastructure.

The accessibility turned out to be the most pressing issue. All on-farm ponds are located

near the drain: to ensure short spilling lines to the drain in case of overtopping and spilling or

worse; and presumably also to allow for easy supply from the same drain.

The best location for sub-laterals, branching off from the laterals, would be along the

(existing) farm roads, where an operator could easily access all the valves to the ponds. It

would also mean that the supply pipes to the pond would have to be almost 100 m from the

sub-lateral, adding to the vulnerability and cost of the system.

A better option would be to have the sub-laterals along the drains, one on each side;

however there are no good maintenance/access roads along the drains (at most only on one

side) so for the operator it will be cumbersome to operate all the gate valves. Even if a

maintenance road is available that leaves the other side of the drain where an equal number

of gate valves is located, out of reach. A possibility here is to have the connecting pipes

53

Standard size pond; if smaller ponds are adopted more ponds need to be filled at the same time along the same lateral branch.

Page 153: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

153

cross the drain: this increases the vulnerability of the system (pipes would be in the open)

and complicates mechanised maintenance of the drains. Another option is to connect all the

ponds directly to the lateral, and provide each pond with its own supply, adding significantly

to the length of (small diameter) pipes, but making operation very easy: on the main road,

straight on the laterals are the manifolds with all the pond pipes grouped together.

Disadvantage is (like in the case of sub laterals along the roads access, or half the ponds in

case one maintenance track along the drain) that the operator never needs to get near to the

ponds anymore, which deprives the organisation of an important monitoring tool in water use,

efficiency and status of the pond. Regular checks on all ponds need to be scheduled by the

operator, and reporting on levels should be done at least weekly.

The pipes that fill the pump are fitted with a valve with three stops. The pipe downstream of

the valve will extend from the (sub-)lateral and near the pond rise from the soil to a height of

max. water level + 0.5 m.

2.3 Options of secondary system – Works description and BoQ

For three options the design has been detailed and the BoQ has been determined. All pipes

are buried: main pipes, laterals, sub-laterals and pond supply pipes in trenches: Width of the

trench is 3 * Ø (min. 50 cm), Depth is Ø + 1.0 m.

For option 1, the preliminarily selected option, a more detailed BoQ a has been prepared.

Three laterals, Ø300 (12”) B3-1, B3-2 and B3-3, make up the backbone of the Block 3,

selected for the Phase I development. The laterals are placed under the road drains, or on

the field of the farmers where the drain is of a larger order.

Any valves for sub-laterals (options 2 and 3) or manifolds (option 1) are placed on the

farmers land, unless unallocated land is available. All such infrastructure will be protected by

lockable protection boxes, iron wiring, or concrete rings, soundly fixed with concrete steel

and anchors in the soil.

Option 1

Each tank is supplied through its own pipeline. On the laterals are 4 and 6 pipe manifolds

that supply the pond supply lines. The manifolds connect through a Tee to the lateral.

Option 2

Three laterals: Lat 3-1, Lat B3-2 and Lat 3-3. The ponds are connected to sub-laterals on

each side to the drain by a supply pipe of approximately 15 m.

Option 3

As option 2, but with connected laterals to increase robustness; this may reduce pressure

differences in a block, if between blocks (final delineation not yet decided upon) also

connected laterals are implemented this may de stabilise pressure variations: to be further

investigated.

The design assumes pond filling flows of 18.5 l/s; if, as discussed, smaller tanks are placed

in the field smaller flows may be used as well. This may allow smaller pond supply pipes, and

in some cases also smaller laterals. However, many more tanks will need to be filled at any

one time, even though more water is supplied throught the main pipe, the laterals have a

combined capacity more than enough to handle such flows.

Page 154: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

154

Figure 3: Map phase I, option1

Page 155: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

155

Lateral and MF-code

No of supply lines

Distribution of distances and diameters over supply pipes, per manifold Length supply lines (Opt 1) Sub-laterals (Opt 2)

up 100 m: Ø 100 up 250 m: Ø 125 over 250 m: Ø150 Ø 100 (4") Ø 125 (5") Ø150 (6") Ø 100 (4") Ø 125 (5") Ø150 (6")

Lat 3-1 (m) (m) (m) (m) (m) (m) (m) (m) (m) (m) (m) (m) (m) (m)

MF3-1-1 4 20 120 220 320

20 340 320

320

MF3-1-2 6 40 130 200 270 340 410

40 330 1020

410

MF3-1-3 7 20 90 160 230 300 370 440

110 390 1110

440

MF3-1-4 7 20 90 160 230 300 370 440

110 390 740

370

MF3-1-5 4 20 110 200 290

20 310 290

290

MF3-1-6 4 20 110 200 290

20 310 290

290

MF3-1-7 6 20 90 160 230 300 370

110 390 670

370

MF3-1-8 7 20 90 160 230 300 370 440

110 390 1110

440

MF3-1-9 7 20 90 160 230 300 370 440

110 390 1110

440

MF3-1-10 8 20 80 140 130 190 250 320 360 100 710 680

360

Lat 3-2

Ø 100 (4") Ø 125 (5") Ø150 (6") Ø 100 (4") Ø 125 (5") Ø150 (6")

MF3-2-154

7 20 20 90 120 140 210 270

130 470 270

210

MF3-2-2 5 20 50 110 170 220

70 500

220

MF3-2-3 5 20 50 110 170 220

70 500

220

MF3-2-4 5 20 50 110 170 220

70 500 0 220

MF3-2-5 6 30 75 130 105 280 360

105 235 640

360

MF3-2-6 5 30 75 130 105 280

105 235 280

280

MF3-2-7 6 20 2 80 85 120 150

22 285

80

Lat 3-3

Ø 100 (4") Ø 125 (5") Ø150 (6") Ø 100 (4") Ø 125 (5") Ø150 (6")

MF3-3-1 5 20 50 110 170 220

70 500 0 220

MF3-3-2 6 20 50 110 170 220 270

70 500 270

270

MF3-3-3 6 20 50 110 170 220 270

70 500 270

270

MF3-3-4 8 20 20 80 140 200 260 320 380 120 340 960

380

MF3-3-5 8 60 120 180 240 300 360 420 480 60 540 1560

480

13255

Totals (m) 962 5,105 4,320 - 960 2,250

54

extra-long individual supply line under option 2 (and 3) required for plot 77 55

assuming compensation for adjusted ponds

Page 156: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

156

Table 9: Bill of quantities and preliminary cost estimate Phase I – Felicity irrigation project

L P Cost L P Cost L P Cost

Main Supply (Balancing) Pipe (per 19 ft) TT$ (per 19 ft) TT$ (per 19 ft) TT$

Q=185 l/s ; Ø = (400); 1150 2400 476,585 1150 2400 476,585 1150 2400 476,585

Laterals

B3-1, Q=61.05 l /s ; Ø=125 850 550 80,726 850 550 80,726 850 550 80,726

B3-2, Q=61.05 l /s ; Ø=225 (300) 1500 2000 518,027 1500 2000 518,027 1500 2000 518,027

B3-3, Q=61.05 l /s ; Ø=150 650 700 78,567 650 700 78,567 650 700 78,567

ConLatera l B3-1-2, Q=61.05 l /s ; Ø=150 20 550 1,899

ConLatera l B3-2-3, Q=61.05 l /s ; Ø=150 700 550 66,480

Pond supply lines/Sublaterals

Q=18.5 l /s ; L<100 m; Ø=100 1712 400 118,248 1980 400 136,759 1980 400 136,759

Q=18.5 l /s ; 100 m <L <250 100 m; Ø=125 9055 550 859,969 960 550 91,173 960 550 91,173

Q=18.5 l /s ; L > 250 100 m; Ø=150 11960 700 1,445,642 5980 700 722,821 5980 700 722,821

Total pipes 26,877 3,577,765 13,070 2,104,659 13,790 2,173,038

Installation: labour, eng. (50% of purchase price) 1,788,882 1,052,329 1,086,519

Earth works TT$/m3 TT$/m3 TT$/m3

Trenching Main Pipe B = 0.6, D = 1.9 1,150 45.6 52,440 1,150 45.6 52,440 1,150 45.6 52,440

Trenching Latera ls B = 0.6, D = 1.8 3,000 32.4 97,200 3,000 32.4 97,200 3,720 32.4 120,528

Trenching Sub-Latera ls B= .5, D = 1.7 120 25.5 3,060 6,940 25.5 176,970 6,940 25.5 176,970

Trenching Pond Pipes B=0.6, D=1.8 22,727 5.4 122,726 1,980 5.4 10,692 1,980 5.4 10,692

Appendages

Manifolds 300 Y 14 3048 42,665

Elbow 90 28 121 3,381

Pipe 14 4945 69,230

T 150 16 53 846

T100 23 48 1,111

Elbow 90 117 199 23,277

7 300 Total MF 20073 140,510 NA NA

150 Y 30 2032 60,950

Elbow 45 60 81 4,830

Pipe 30 3297 98,900

T 150 45 35 1,587

T100 48 32 1,546

Elbow 90 279 133 37,005

15 150 Total MF 13382 204,817

Valves Supl . Pipes 4" 43 960 41,280 132 960 126,720 132 960 126,720

5" 54 1075 58,050

6" 35 1285 44,975

SubLats 5" 1 1075 1,075 1 1075 1,075 1 1075 1,075

6" 1 1285 1,285 1 1285 1,285 2 1285 2,570

8" 1 1820 1,820 1 1820 1,820 2 1820 3,640

Tees 132 800 105,600 132 800 105,600

Protection boxes MFs 22 2000 44,000

Protecion boxes Valves 132 500 66,000 132 500 66,000

Bends (incl conc. Foudations) 120 300 36,000 264 1000 264,000 264 1000 264,000

Tees (s teel / i ron) 28 1000 28,000 264 1000 264,000 23 1000 23,000

Tees (PVC) 132 250 33,000 132 250 33,000

Pressure regulators (each S-latera l ) 22 2000 44,000 22 2000 44,000 22 2000 44,000

Concrete works

Manholes for Manifolds (Tees) 242 5000 1,210,000 14 2000 28,000 14 2000 28,000

Manholes for Pond va lves 0 2000 - 132 2000 264,000 132 2000 264,000

Total Appendages 2,131,239 1,536,802 1,322,235

Miscellaneous

Buffer tanks against water hammer

Additional Pressure regulators (latera ls ) 10% 749,788.54 469,379.02 458,179.26

Water meters

Grand total Distribution system 8,247,674 5,163,169 5,039,972

Option 1: separate pond supply pipelinesOption 2: sub laterals Option 3: sublaterals, connected lateralsDescription Item

Page 157: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

157

3. WATER QUALITY AND SALINITY

In general salinity issues are limited to (semi-)arid regions; however, in sub-humid regions

salinity can also occur. These are generally related to local salinity sources such as sea

water intrusion, a geological origin, pollution, etc.

In Trinidad there seems to be salinity problem in a wide area in West-Central-Trinidad, and

the origin of the salinity has not been established. A specific case seems to have been

identified in the Felicity irrigation scheme, where water quality samples have been taken from

two rivers (Caparo River and Chandernagore River) and three ponds. The water quality was

fair (see Chapter 11.3), however, one pond showed very different results.

It is unclear how a 4 m deep pond could have turned saline. Possible causes of this low

quality water were not apparent and a number of mechanisms was evaluated.

Concentrating through evaporation

Over the dry season the evaporation is higher than precipitation and salinity levels in a pond

of water may increase. Over the wet season the opposite process takes place and salinity

levels will drop, even some spilling may occur and salts may be flushed out. A (long term)

annual increase of salinity will require an external source of salts.

There are several possible external sources of salt. Salinity through salt intrusion from the

sea, shallow geological deposits and salinity build-up through agricultural practices are all

possible sources.

Sea water intrusion seems unlikely in the case of the Felicity irrigation scheme as the area

has an elevation of 8 to 12 m above MSL, and the ground water is approximately 4 to 8 m

above MSL, with overall a steady drainage flow.

Geological salt at a shallow depth is possible. In a shallow layer it would have been picked

up by rivers a long time ago, cutting through the layer in the erosion process, but at the time

there were no agriculturalists (or engineers) to worry about such a process or even detect it:

water (slightly saline) washed into the sea.

Agricultural practices could also be a source though the process is not very obvious. Under normal

conditions there is a solid surplus of precipitation in Trinidad over drainage. A natural leaching

process is expected. However in C-Trinidad the surplus is not very high. Furthermore in the clayey

soils of C-Trinidad the leaching fraction of precipitation may be relatively small: there is quite some

overland flow under natural conditions and (natural) leaching may not have been as much as thought

likely. As rainfall does not add salt to the soil water mix, a slow, long term leaching process may have

taken place; in the heavy clays of C. Trinidad, however, an unnoticeable process. The long term

cultivation of sugarcane (200 years) may have changed that. More infiltration may have occurred

because of more roughness on the field, and a stronger leaching process might have occurred.

However, sugar cane transpires a lot more than the previous natural vegetation (adapted to the

relatively low infiltration/leaching faction), and drainage-cum-leaching may have slowed down or

even come to a standstill. The application of fertiliser, organic or chemical, may have added to the

salt load in the soil. When drainage-cum-leaching was reduced to a trickle, salinity may have

accumulated in the lower layers of the root zone or just below. An analogous process was described

in detail in Saudi Arabia (a real arid climate) under irrigated date palms over a 30 year period

(Reference: Evaluation and Development Study of the Irrigation Water Distribution System in Al-

Hassa Area”, 2003).

Page 158: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

158

This is still a hypothesis and, together with the shallow geologic saline deposits, deserves

more study. The real issue is to ascertain whether indeed salinity is a widespread problem as

being claimed by certain people in the field, or indeed that the saline pond is a freak incident

with merely local implications.

Salinity in the future

For the long term however agricultural practices may certainly play a role in salinity

development. The precipitation surplus will further reduce, Pe will reduce, if not relatively it

will reduce in absolute numbers, and (irrigation) water quality may deteriorate.

Under normal circumstances there is a fraction of the water that infiltrates into the soil

(precipitation and irrigation water). Irrigation water carries salt, even if only very small

amounts, rainfall is free of salts.

where,

R* = balance of leaching and recharge from ground water

Ii = volume of irrigation water

Pe = effective precipitation (infiltrating precipitation)

An equilibrium, important to stave off salinity damage to crop and soil (SAR), is reached if the

salt balance is zero. This can be achieved when the leaching requirement (LR) is fulfilled.

The LR is described by the following relation:

LREC

EC EC

w

e w

5

LR = leaching requirement

ECw = electric conductivity irrigation water

ECg = (allowable) ECe at an accepted yield loss level

Reference is made to FAO Publications 29 (Water quality for agriculture) and 61 Agricultural

drainage and water management in (semi-) arid areas).

Page 159: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

159

4. METHOD OF PIPE DESIGN

4.1 Operation and design

In the secondary system an important criterion is to limit pressure difference in a pipeline: if

the pressure difference is too high large deviations between the first and last lateral, sub-

lateral of supply line may occur. In the laterals, long or short, the maximum head difference

between first and last branching off sub-lateral, is put at 15 m water pressure (150,000 Pa).

This explains why some laterals have a smaller diameter than other while the discharge is

equal.

In sub-laterals and supply lines the maximum head differential is limited to 5 m water

pressure. In spite of the design it is accepted that larger differences will occur and these will

be compensated at the lateral where the sub-lateral or supply line branches off. Pressure

regulators will be installed at those points. For pressure regulators to work excess pressure

is required and the operating pressure of the system at the head of the lateral is as follows

(Table 1.10).

Table 10: Make up of pressure in laterals

5 m Pressure at nozzle supply pipe at tank

5 m Head loss over supply line or sub lateral

15 m Head loss over lateral

20 m Additional head available for pressure balancing in laterals

45 – 50 m Total head available at head of lateral

15 m Head loss over main pipe / balancing pipe in secondary system

60 – 65 m Total head required at head of main pipe – balancing pipe

The pressure losses have been (preliminarily) determined through applying the general flow

formulae, but for ease of quick reference the head losses as shown in Figure 4 have been

used. Losses in appendages have not been included yet but are of a lower oreder than these

pipe losses; yet these have to be determined. For the balancing pipe, the pipe that allows

different pumps (and ponds) to convey water to different parts of the system, while npt

effecting the pressure distribution over the system too much, the flows and pressure losses

have been compiled in Table 10. In the ideal situation, at each lateral flow is being diverted

from the pipe into a lateral. The worst case is being presented here: full flow from the supply

of the RSSP enters he system, and flow is being diverted at each lateral. The impact of the

use of the smaller pipes (1’ or Ø300 vs. 1’4” or Ø400) is obvious. In the smaller pipe a much

larger head loss will occur (12.5 m) than in the larger pipe (27.5 m). This means that more

energy will be wasted and that the pump will require a larger capacity to allow such a flow.

Careful optimisation will allow lower investment costs and lower energy costs. This requires

further investigation.

Page 160: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

160

Table 11: Head losses in balancing (transport) pipe.

RD (m)

Q Ø400 (1’4”) Ø300 (1’)

(l/s) (m3/hr) (gipm) Δh/100m Δh (m) Δh/100m Δh (m)

0

600 200 720 2632 0.85 5.1 1.95 11.7

1200 180 648 2368 0.60 3.6 1.30 7.8

1800 140 504 1842 0.30 1.8 0.70 4.2

2800 100 360 1316 0.15 1.5 0.35 3.5

3000 60 216 789 0.08 0.2 0.03 0.1

12.2 27.3

Page 161: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

161

Figure 4: Head losses (m water pressure) per 100 m pipe

Page 162: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

162

ANNEX 12: ASSIGNMENTS CONSULTANTS, MEETINGS AND FIELDWORK, PERSONS

MET

Assignments Consultants

Name

Position Period 2013

Frank de Zanger

Team Leader, Water Resources Management Expert

June 9 – September 13

Bob Pengel

Water Resources Development Expert

June 23 – July 13 July 29 – September 13

Frank van Berkom

Hydrologist August 21 – September 10

Luis Celis

Hydrologist June 16 – June 30

Meetings and fieldwork

Date Meetings, Fieldtrips Location & Details

11-6-2013 EU Delegation Level 2, Sagicor Financial Centre, 16 Queen’s Park West, Port of Spain, tel. 622 6628 / 622 0591 / 622 0615

14-6-2013 Environmental Management Authority (EMA)

8 Elizabeth Street, St. Clair, Port of Spain, tel. 628 8042

17-6-2013 County Caroni Extension Office, Chaguanas, Ministry of Food Production (MFP)

LP 525 Old Southern Main Road, Chase Village, Chaguanas, tel. 672-0878, 627 2865; [email protected]

17-6-2013 Fieldtrip

Felicity Project Area

18-6-2013 Extension Training and Information Service Division, Ministry of Food Production (MFP)

Mausica Road, Centeno

18-6-2013 Caroni (1975) Limited Brechin Castle, Couva, tel. 636 2346/9912, 679 2255

20-6-2013 Caribbean Agricultural Research and Development Institute (CARDI)

Frederick Hardy Building, University of the West Indies, St. Augustine Campus, St. Augustine

21-6-2013 Drainage Division, Ministry of the Environment and Water Resources

NIDCO Building, 5th floor, Melbourne Street, Port

of Spain. Tel. 623 3158/379 6996

26-6-2013 Weekly progress meeting. Extension Training and Information Service Division, Ministry of Food Production (MFP)

Mausica Road, Centeno

26-6-2013 Fieldtrip

Felicity Project Area

3-7-2013 Weekly progress meeting. Extension Training and Information Service Division, Ministry of Food Production (MFP)

Mausica Road, Centeno

9-7-2013 Meeting with farmers 5-6 kms east of project area (Depot Road Irrigation Scheme): County Agricultural Consultative Committee. Organised by County Caroni Extension Office, Chaguanas, Ministry of Food Production (MFP)

LP 525 Old Southern Main Road, Chase Village, Chaguanas, tel. 672-0878, 627 2865; [email protected]

Page 163: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

163

10-7-2013 Weekly progress meeting. Extension Training and Information Service Division, Ministry of Food Production (MFP)

Mausica Road, Centeno

10-7-2013 Fieldtrip, guided by Drainage Division of Ministry of Environment and Water Resources

Irrigation / drainage system North of Felicity

Project Area

11-7-2013 Meeting at Project Office of Royal Haskoning/DHV, conc. Caparo River Basin Study

36A Carlton Avenue, St. James, Port of Spain, tel. 868 628 5767

17-7-2013 Weekly progress meeting. Extension Training and Information Service Division, Ministry of Food Production (MFP)

Mausica Road, Centeno

24-7-2013 Weekly progress meeting. Extension Training and Information Service Division, Ministry of Food Production (MFP)

Mausica Road, Centeno

31-7-2013 Weekly progress meeting. Extension Training and Information Service Division, Ministry of Food Production (MFP)

Mausica Road, Centeno

3-8-2013

Field trip to sand mining pits/sinks East of the Felicity Project Area with Mr. Johan Mathijssen, Team Leader of the Caparo Water Basin Study, HaskoningDHV-Deltares.

Field trip to mining pits/sinks East of the Felicity Project Area

7-8-2013 Weekly progress meeting. Extension Training and Information Service Division, Ministry of Food Production (MFP)

Mausica Road, Centeno

7-8-2013 Meeting at the Trinidad and Tobago Meteorological Service Division

Piarco

12-8-2013 Taking water samples in the project area with technicians of CARIRI laboratory and officials from MFP

Felicity Project Area

12-8-2012 Rapid appraisal; consultation with farmers working in the Felicity Project Area

Felicity Project Area

14-8-2013 Weekly progress meeting. Extension Training and Information Service Division, Ministry of Food Production (MFP)

Mausica Road, Centeno

20-8-2013 Meeting at the Town and Country Planning Division, Ministry of Planning and Sustainable Development

Twin Towers, Port of Spain

23-8-2013 Introduction meeting at Agricultural Extension Office, Introducing Mr. Frank van Berkom

Mausica Road, Centeno

23-8-2013 Sugar Cane Feed Lots Pokhar Road, Longdenvill, Chaguanas mob.1-868-365-1103,email: [email protected] [email protected]

23-8-2013 Mr. Roop’s Demonstration Farm Usire Road, Freeport ph. (868) 367-8655, fax: (868) 671-9179 email: [email protected]

27-8-2013 Workshop Caparo River Basin Study (Drainage Division, NIDCO)

Tower D, International Water Front Complex, Wrighton Road, Port of Spain

28-8-2013 Presentation of options for irrigation, progress meeting.

Mausica Road, Centeno

Page 164: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

164

Extension Training and Information Service Division, Ministry of Food Production (MFP)

29-8-2013 Meeting with engineers on design of irrigation scheme

Mausica Road, Centeno

3-9-2013 Meeting with engineers on design of irrigation scheme

Mausica Road, Centeno

6-9-2013 Presentation of the draft Final Report and discussion of the results, comments. Extension Training and Information Service Division, Ministry of Food Production (MFP)

Mausica Road, Centeno

6-9-2013 Meeting with engineers on design of irrigation scheme

Mausica Road, Centeno

9-9-2013 Last meeting on design of irrigation scheme

Mausica Road, Centeno

PERSONS MET

EU Delegation Level 2, Sagicor Financial Centre, 16 Queen’s Park West, Port of Spain, tel. 622 6628 / 622 0591 / 622 0615

Kathrin Renner [email protected] EU Delegation

International Aid Officer / Attaché

Solomon Ioannou

[email protected] EU Delegation

Programme Officer

Environmental Management Authority (EMA) 8 Elizabeth Street, St. Clair, Port of Spain. Tel. 628 8042

Christiaan Harragin 628 8042 /4308 [email protected],tt

EMA Senior Technical Specialist

Xio Mara Chin

EMA

Water Resources Agency, WASA 179-181 Eastern Main Road, Barataria

Anthony Chadee 678 1282 [email protected]

Water Resources Agency, WASA

Deputy General Manager

Sara-Jade Govia 466 7475 [email protected]

Water Resources Agency, WASA

Environmental Specialist

Philmore Williams 686 1899 [email protected]

Water Resources Agency, WASA

Senior Hydrologist

David Samm Water Resources Agency, WASA

Senior Hydrologist

County Caroni Extension Office, Ministry of Food Production (MFP) LP 525 Old Southern Main Road, Chase Village, Chaguanas. Tel. 672-0878, 627 2865; [email protected]

Mala Powdhar [email protected] Engineering Division MFP, Irrigation & Drainage

Agricultural Engineer II

Joel Ramadoo 642 0363, 646 0267 [email protected]

Engineering Division MFP

Engineer I

Garth Roach County Caroni Agriculture Assistant II

Page 165: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

165

Office

Ivan Dadd 487 9824 County Caroni Office

Agriculture Assistant I

Ministry of Food Production (MFP) Extension Training & Information Service Division, Mausica Road, Centeno; Port of Spain

Ann Marie Dardaine

717 4151 [email protected]

Engineering Division MFP

Director

Frankie Balkissoon 472 1707 642 0267 / 0363 [email protected]

Engineering Division MFP, Irrigation & Drainage

Deputy Director

Yvonne Davidson McKenzie

622 1221 ext. 2140/ 622 5953 [email protected]

Agricultural Planning Division (APD) MFP

Planning Officer III

Beena Persad 798 3224 [email protected]

Agricultural Planning Division (APD) MFP

Planning Officer I

Mala Powdhar [email protected] Engineering Division MFP, Irrigation & Drainage

Agricultural Engineer II

Candace Maharaj 714 3272 [email protected]

Fisheries Division MFP Junior Civil Engineer

Candice Gray-Bernard

721 5544 [email protected]

Fisheries Division MFP Senior Civil Engineer

Cavelle Motilal 772 8607 / 642 0267 [email protected]

Engineering Division MFP

Engineer

Caroni (1975) Limited Brechin Castle, Couva. Tel. 636 2346/9912, 679 2255

Deosarran Jagroo 681 4845 Caroni (1975) Ltd. Chief Executive Officer

Johnny Ribiero 789 5097 Caroni (1975) Ltd. Felicity farmer contacts

Michelle Gittens 705 9313 Caroni (1975) Ltd. Project Manager

Russel Boland 794 4358 Caroni (1975) Ltd. Lands Leader / Mgr.

Royal Haskoning / DHV - Deltares 36A Carlton Avenue, St. James, Port of Spain, tel. 868 628 5767 Johan Mathijssen

868 468 2615 [email protected]

Team Leader / Project Manager

Caribbean Agricultural Research and Development Institute, CARDI Frederick Hardy Building, University of the West Indies, St. Augustine Campus, St. Augustine

Norman Gibson 645 1205-7, [email protected] www.cardi.org

CARDI Scientific Officer

Caribbean Industrial Research Institute, CARIRI University of the West Indies, St. Augustine Campus, St. Augustine

Gaitri Jeethan mob. 4915558 [email protected]

CARIRI Chemist Analytical Chemistry

Page 166: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

166

Caribbean Agribusiness Association Department of Agricultural Economics, Rm.l09, University of the West Indies, St. Augustine Campus, St. Augustine

Ramgopaul Roop

mob. 1-868-365-1103, Email: [email protected] [email protected]

Department of Agricultural Economics

Regional Administrator

Dinal Enterprises, Agricultural Consultants & Contractors

Main Road Longdenville, Chaguanas, Trinidad

Roopnarine Siewnarine

Ph. (868) 367-8655 Fax: (868) 671-9179 email: [email protected]

Farmer, consultant

Trinidad and Tobago Meteorological Service Division Piarco, airport area

Kenneth Kerr mob. 4624790 [email protected]

Climatologist

Town and Country Planning Division, Ministry of Planning and Sustainable Development Independence Square, Twin Towers, Port of Spain

Clyde Watche

Town and Country Planning Division

Director

Kerry Pariag

Town and Country Planning Division

Planning Engineer

Drainage Division, Ministry of the Environment and Water Resources NIDCO Building, 5

th floor, Melbourne Street, Port of Spain. Tel. 623 3158/379 6996

Shamshad Mohammed

Drainage Division, Ministry of the Environment and Water Resources

Director

Ramdaht Baboolal 468 0481 [email protected]

Drainage Division, Ministry of the Environment and Water Resources

David Persaud Drainage Division, Environmental Policy and Planning, Ministry of the Environment and Water Resources

Manager

Drainage Division, Ministry of the Environment and Water Resources Chaguanas

Sahedee Ramoutar

Drainage Division, Ministry of the Environment and Water Resources

Work Forman I

Page 167: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

167

ANNEX 13: TERMS OF REFERENCE

Annex 13 Terms of Reference

Page 168: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

168

ANNEX 14: WORK PLAN AND TIME FRAME

Consultants: F: Frank de Zanger B: Bob Pengel L: Luis Celis V: Frank van Berkom

Project Activities, 2013 June July August September

wk1 wk2 wk3 wk4 wk5 wk6 wk7 wk8 wk9 wk10 wk11 wk2 wk13 wk14

On mission F F F F F F F F F F F F F F

On mission B B B B B B B B B B

On mission L L V V V

Reporting F F F F F F F F F F F F F F

Liaison with Delegation of the EU F F F F F F F F F F F F F F

1

Meetings with the EU Delegation and

representatives of GoRTT, WASA, MFLMA and

other identified agencies to obtain feedback

F

FL

FL

2

Data collection on hydrology, meteorology,

irrigation, aerial photography, socio-economy,

legislation, policy, environment

F LF

BFL BF BF

F

F

BF BF

3

Submission of Inception Report with Work

Plan

X

4 Comments on Inception Report X

5

Revision by Consultants

X

FBL

6 Approval of Inception Report X

7

Overview/description of the National Sugar

Adaptation Strategy (NAS) and its institutional

and legislative framework

FL

FB

8

Identification of precise project area. Field visits FL

FBL

9

Identification and description of stakeholders in

the project area. Field visits

FBL

10

Meetings with stakeholders in the project area and

obtaining their feedback. Field visits

FBL BF

11

Study on set up of water users associations. Field

visits

BF

Page 169: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

169

12

Assessment of the existing situation for irrigation

and drainage, including water and wastewater

systems, in the project area. Field visits

FL

BFL

13

Review of existing institutional arrangements for

water resources development and management.

Field visits

BF

14

Needs assessment in the project area. Field visits.

BF

15 Irrigation Sector Study

15a Assessment of drainage and flooding B

15b

Estimation of current, future and potential

agricultural water resource needs

B

15c

Hydrological,watershed study to determine water

availability

BF

F

F

15d

Aerial photographs / satellite image interpretation

15e

Identification of trends and projects proposed on

the short, medium and long-term, taking into

account external factors, including influence of

other sectoral policies

BF

F

F

15f

Potential environmental impacts of irrigation

system (agricultural runoff) on surrounding rivers,

other drainage features, and downstream users

(domestic, industrial, ecosystem water demands)

F

F

F

15g

Formulation of mitigation measures to deal with

changing catchment characteristics

F

F

15h

Identification of various options for the

development of sustainable water management

(irrigation/drainage) in the Felicity area. Field

visits

BF

BF

15i

Defining a preferred option for irrigation and

drainage of agricultural lands in the Felicity area

(1300 acres), serving as a model for the rest of the

country. Field visits

BF

16 Feasibility Study and Preliminary Design

Page 170: Water Management and Irrigation Assessment and …eeas.europa.eu/.../documents/eprd_final_report_trinidad.pdf1 This project is funded by The European Commission A project implemented

170

16a Water supply (abstraction) and delivery BF BF

16b Water storage and head works B B VB VB VB

16c Distribution system to farmers B VB VB VB

16d Drainage works B VB VB VB

16e

Waste water treatment facilities (with closed loop

system) and reuse options, if required

B VB VB VB

16f

Economic analysis providing guidance to the

economic feasibility of the project and potential

for funding by regional/international lending

agencies

BF BF

16g Proposal for cost for water BF

16h Addressing environmental issues F

16i

Farmers involvement in the operation and

management of the project

B

17 Preparation of contract and tender documents V V V

18

Formulation of conclusions and recommendations

FBV FB F

19 Organising a stakeholder workshop FB

20 Revision of draft Final Report FB

21 Submission of Draft Final Report X

22

Comments on Draft Final Report by the EU

Delegation, including comments by

representatives of the GoRTT and other

stakeholders

X

23

Revision by the Consultants

X

FB

X

FB

24

Submission of Final Report

X

25 Approval of Final Report