Page 1: Water and Wastewater Facilities Master Plan

Water and Wastewater Facilities Master Plan

Prepared for:

Funded by theBorder Environmental Cooperation Commission

under Contract # CONTA00-010

El Paso County Water Authority M.U.D

Page 2: Water and Wastewater Facilities Master Plan

Project Purpose

Provide EPCWA with definition of facilities needed toexpand their existing wastewater system to serve the StudyArea and improve deficiencies in the water system.

Provide EPCWA with a document that may be usedas supporting documentation in the preparation ofa BECC Step II Form in the BECC Project Certificationprocess for NAD Bank Funding.

Page 3: Water and Wastewater Facilities Master Plan

EPCWA Study Area Boundaries

Page 4: Water and Wastewater Facilities Master Plan

Study Area Population Data

EPCWA connection commitments, 1990 censusand actual 2000 connections.

0

10000

20000

30000

40000

50000

60000

70000

1985 1990 1995 2000 2005 2010 2015 2020

Year

Po

pu

lati

on

Page 5: Water and Wastewater Facilities Master Plan

Existing Water System Information

Existing Groundwater Resources are available in theWheeler Well Field (>1000 TDS) and theDesert Well Field (750 - 1250 TDS)

Maps of the existing system were collected and usedto develop a hydraulic model of the existing system.

Demands from the past 2 years were tabulated to determineaverage, peak day and peak hour flow rates for futurepopulation projections

Reverse Osmosis Plant currently treats Wheeler WellField Water.

Page 6: Water and Wastewater Facilities Master Plan

Groundwater Resources Required

0

20000

40000

60000

80000

100000

120000

140000

1995 2000 2005 2010 2015 2020 2025

Year

Acr

e-ft

of

wat

er

Cumulative Acre-ft Acre-ft per year

Volume (acre-feet) Quality (mg/L TDS)

20 year System Demand 115,305 <1000

Wheeler Well Field 15,400* Approx. 1500

32 and 36 Well Fields 84533 (1) 750 to 1250

* an additional 19,200 acre-feet may recharge the Wheeler Well Field

Page 7: Water and Wastewater Facilities Master Plan

Deficiencies of the Existing System

Running the model with the elevated tanks below themid-level showed the pressures in the Horizon ViewEstates area dropping to between 30 and 35 psi.

Low pressures have been documented with chartrecorders placed in the Horizon View Estates byGray-Jansing & Associates, Inc. and EPCWA.

The cause of this pressure drop is the lack of water linelooping in the area of Horizon View Estates.

Page 8: Water and Wastewater Facilities Master Plan

Immediate Improvements Needed

Approximately 10,000 feet of 12 inch pipe

Page 9: Water and Wastewater Facilities Master Plan

Water System Improvements for Future

Hydraulic Model was adjusted for projected futuredemands including areas of new development.

Pipe sizes were optimized to meet minimum pressurerequirements under peak flow conditions.

Phasing was determined for 2005, 2010, 2015 and 2020 demand conditions.

Page 10: Water and Wastewater Facilities Master Plan

Water System Improvements by Year

Page 11: Water and Wastewater Facilities Master Plan

Phasing of Projects and Cost Opinion

Location $/Unit Qty. Cost of InstallationImmediate Improvements12” Agua Dulce and Horizon View Estates $28.50 10,000’ $285,000Prior to 200512” Desert Breeze Subdivision $28.50 4,250’ $121,12512” Horizon Mesa Subdivision $28.50 3,100’ $88,35012” B&G (Paseo del Este) Subdivision $28.50 1,800’ $51,3002,500 gpm Pump Station Expansion EA. $850,0002 MGD R.O. Expansion EA. $2,000,0001.5 MG Elevated Storage Tank EA. $3,800,000

Total $6,910,7752005 Improvements12” Desert Breeze Subdivision $28.50 2,300’ $65,55012” Horizon Mesa Subdivision $28.50 4,100’ $116,85012” B&G (Paseo del Este) Subdivision $28.50 1,700’ $48,4502,000 gpm Pump Station Expansion EA. $690,0002 MGD R.O. Expansion (New Bldg Req) EA $3,500,0001 MG Elevated Storage Tank EA $2,600,000

Total $6,520,850

Page 12: Water and Wastewater Facilities Master Plan

Phasing of Projects and Cost Opinion

2010 Improvements12” Desert Breeze Subdivision $28.50 2,000’ $57,00012” Horizon Mesa Subdivision $28.50 2,200’ $62,70012” B&G (Paseo del Este) Subdivision $28.50 3,400’ $96,9001,500 gpm Pump Station Expansion EA. $550,0001 MGD R.O. Expansion EA. $1,000,0001 MG Elevated Storage Tank EA. $2,600,000

Total $3,066,6002015 Improvements12” Desert Breeze Subdivision $28.50 3,450’ $98,32512” Horizon Mesa Subdivision $28.50 3,600’ $102,60012” B&G (Paseo del Este) Subdivision $28.50 4,100’ $116,8502,000 gpm Pump Station Expansion EA $690,0001 MGD R.O. Expansion EA $1,000,0001 MG Elevated Storage Tank EA $2,600,000

Total $4,607,775

Subtotal for all projects $21,391,000Contingency (20%) $4,278,200

Total $25,669,200Engineering & Administration (14%) $3,593,688

Project Total $29,262,888

Page 13: Water and Wastewater Facilities Master Plan

Existing Wastewater System Information

Current WW treatment capacity is 1.0 MGD. 0.5 MGDLagoons and 0.5 MGD activated sludge plant.

Maps of the existing system were collected and usedto develop a hydraulic model of the existing system.

WW flows from the past 2 years were tabulated to determine per capita contributions. 70.62 gpcd

A large portion of the collection system is Vitrified ClayPipe.

Page 14: Water and Wastewater Facilities Master Plan

Projected Wastewater Flows

0

2

4

6

8

10

12

1995 2000 2005 2010 2015 2020 2025

Year

Dai

ly F

low

(M

GD

)

Average 2-Hour Peak

Year PopulationServed

Average Flow Peaking Factor Peak 2-HourFlow

2000 8,174 0.621 MGD 3.349 2.08 MGD2002 18,768 1.33 MGD 2.867 3.80 MGD2005 34,096 2.41 MGD 2.564 6.17 MGD2010 45,000 3.18 MGD 2.434 7.74 MGD2015 53,500 3.78 MGD 2.357 8.90 MGD2020 63,965 4.52 MGD 2.279 10.30 MGD

Page 15: Water and Wastewater Facilities Master Plan

Wastewater Flow Analysis

Lift station and gravity piping was added to model toserve existing un-sewered areas. (Agua Dulce, Lakeway,Burnette Ranchettes, Horizon View Estates and El Paso Hills)

Population and flow projections were added to thewastewater hydraulic model for current day conditions,2005, 2010, 2015 and 2020.

Pipe sizes to handle the projected flows were determinedand checked with velocity and slope criteria.

Page 16: Water and Wastewater Facilities Master Plan

Deficiencies of the Existing System

Sections of piping along Alderwood Manor near theAshford intersection are at capacity.

Existing piping along Horizon Blvd between the WWTP and Darrington is already at or nearing full capacity.

Page 17: Water and Wastewater Facilities Master Plan

Improvements to Serve Un-sewered Areas

Regional Lift station near New R.O. Plant.

Lift stations to pump wastewater from Lakeway, BurnetteRanchettes towards the proposed regional lift station.

Wastewater collection piping within the subdivisions.

Page 18: Water and Wastewater Facilities Master Plan

Location of Improvements for Un-sewered Areas

Page 19: Water and Wastewater Facilities Master Plan

Phasing of Projects and Cost Opinion

Page 20: Water and Wastewater Facilities Master Plan

Phasing of Projects and Cost Opinion

Page 21: Water and Wastewater Facilities Master Plan

Phasing of Projects and Cost Opinion

Page 22: Water and Wastewater Facilities Master Plan

Phasing of Projects and Cost Opinion

Wastewater Collection ProjectsTotal Opinion of Cost: $11,435,500

Page 23: Water and Wastewater Facilities Master Plan

Treatment Capacity and Disposal Area Required

Year Land Area(sq. ft)

WastewaterFlow

App. Rate(gal/sf/day)

Land Area(acres)

Land Area(Sq. Miles)

2005 33,472,222 2,410,000 0.072 768 1.202010 44,166,667 3,180,000 0.072 1,014 1.582015 52,500,000 3,780,000 0.072 1,205 1.882020 62,777,778 4,520,000 0.072 1,441 2.25

*0.23 square miles is current golf course area and 0.25 sq. mi. is current GLO Land with another0.25 sq. mi. of GLO land already committed and permitted for disposal.

Land Disposal of Effluent

Irrigation of Turf Areas

Commercial and Industrial Reuse

Disposal Alternatives

Page 24: Water and Wastewater Facilities Master Plan

Wastewater Treatment Plant Phasing

Description 2002 2005 2010 2015

Construct new 2MGD extend aerationtreatment plant

$5,500,000

Pumping to DisposalArea 2.2 MGDCapacity

$520,000

Construct new 2MGD extend aerationtreatment plant

$5,500,000

Pumping to DisposalArea 0.7 MGDCapacity

$190,000

Pumping to DisposalArea 0.7 MGDCapacity

$190,000

Totals $5,500,000 $520,000 $5,690,000 $190,000