Water Administration System (WAS PH3) Progress report

49
Water Administration System (WAS PH3) Progress report Nico & Nicolaas Benad´ e (NB Systems Cc) September 2018

Transcript of Water Administration System (WAS PH3) Progress report

Page 1: Water Administration System (WAS PH3) Progress report

Water Administration System(WAS PH3)

Progress report�

Nico & Nicolaas Benade(NB Systems Cc)

September 2018

Page 2: Water Administration System (WAS PH3) Progress report

Key Partners

1. Strategic Water Partners Network (SWPN) – is a Public PrivatePartnership with the Department of Water and Sanitation and variouscorporates including Nestle, Sasol, SAB and Coca-Cola. The mandateof the SWPN is to identify and implement initiatives and projects thatwill assist in addressing the projected 17% gap in water supply anddemand by 2030. SWPN will be responsible for the funding and gov-ernance of the project.

2. Landbank SA - donated funds to purchase and install 28 loggerswhich are used to measure the inflow into the respective schemes whereneeded. They also funded three laptops which are used to run theWAS at three government water schemes that don’t have the requiredhardware.

3. NB Systems Cc – owns the IP for the WAS program which wasdeveloped by Dr Nico Benade. They are responsible for the imple-mentation, maintenance and continued development of the WAS andproject manage the implementation of the Phase 3 implementation.

1

Page 3: Water Administration System (WAS PH3) Progress report

Contents

1 Introduction 41.1 Introduction and background . . . . . . . . . . . . . . . . . . 5

1.1.1 Irrigation water management . . . . . . . . . . . . . . 51.1.2 Current water management system and problems to be

addressed . . . . . . . . . . . . . . . . . . . . . . . . . 51.1.3 The Water Administration System . . . . . . . . . . . 61.1.4 SWPN funding support to WAS . . . . . . . . . . . . 71.1.5 Was Phase 3 . . . . . . . . . . . . . . . . . . . . . . . . 91.1.6 Key data on irrigation schemes where WAS has been

implemented with SWPN Support . . . . . . . . . . . . 10

2 Implementation 122.1 Implementation . . . . . . . . . . . . . . . . . . . . . . . . . . 13

2.1.1 Schemes supported . . . . . . . . . . . . . . . . . . . . 132.1.2 The implementation comprised . . . . . . . . . . . . . 13

2.2 WAS web interface . . . . . . . . . . . . . . . . . . . . . . . . 16

3 Results 223.1 Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

3.1.1 Benefits of WAS demonstrated . . . . . . . . . . . . . . 233.1.2 Baseline water loss & water savings . . . . . . . . . . . 243.1.3 Projected water loss reduction . . . . . . . . . . . . . . 25

A The WAS system 27

B Scheme implementations 30B.1 Boegoeberg WUA . . . . . . . . . . . . . . . . . . . . . . . . . 31B.2 Gamtoos IB . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31B.3 Kakamas WUA . . . . . . . . . . . . . . . . . . . . . . . . . . 32B.4 Kalkfontein WUA . . . . . . . . . . . . . . . . . . . . . . . . . 33B.5 Korente Vette IB . . . . . . . . . . . . . . . . . . . . . . . . . 33

2

Page 4: Water Administration System (WAS PH3) Progress report

B.6 Lindleyspoort GWS . . . . . . . . . . . . . . . . . . . . . . . . 34B.7 Lower Sundays River WUA . . . . . . . . . . . . . . . . . . . 34B.8 Luvuvhu GWS . . . . . . . . . . . . . . . . . . . . . . . . . . 35B.9 Marico Bosveld GWS . . . . . . . . . . . . . . . . . . . . . . . 36B.10 Mooiriver GWS . . . . . . . . . . . . . . . . . . . . . . . . . . 36B.11 Oranje Vaal WUA . . . . . . . . . . . . . . . . . . . . . . . . 37B.12 Schoonspruit GWS . . . . . . . . . . . . . . . . . . . . . . . . 37

C Meetings & Training 39Meetings & Training . . . . . . . . . . . . . . . . . . . . . . . . . . 40

D Confirmation of work 41Boegoeberg confirmation . . . . . . . . . . . . . . . . . . . . . . . . 42Gamtoos confirmation . . . . . . . . . . . . . . . . . . . . . . . . . 42Kakamas confirmation . . . . . . . . . . . . . . . . . . . . . . . . . 43Kalkfontein confirmation . . . . . . . . . . . . . . . . . . . . . . . . 43Korente Vette confirmation . . . . . . . . . . . . . . . . . . . . . . 44Lower Sundays River confirmation . . . . . . . . . . . . . . . . . . 45Luvuvhu confirmation . . . . . . . . . . . . . . . . . . . . . . . . . 45Marico & Lindleyspoort confirmation . . . . . . . . . . . . . . . . . 46Mooi river & Schoonspruit confirmation . . . . . . . . . . . . . . . 47Oranje-Vaal confirmation . . . . . . . . . . . . . . . . . . . . . . . . 48

3

Page 5: Water Administration System (WAS PH3) Progress report

Chapter 1

Introduction

4

Page 6: Water Administration System (WAS PH3) Progress report

1.1 Introduction and background

1.1.1 Irrigation water management

While 12% of South Africa’s land can be used for crop production, only 22%of this is high-potential arable land. However, the greatest limitation is theavailability of water as most of the country has uneven and unreliable rainfall.Around 1.3-million hectares are under irrigation, and around 62% of SouthAfrica’s water is used for agriculture nationally.

Irrigation agriculture is the largest water user in South Africa and withthe increasing competition between existing user sectors, the available watercannot meet the demand under current water use practices and operatingconditions in all water use sectors. It is therefore imperative that the availablewater supplies are used efficiently and effectively to avoid supply shortagesand intermittent water supplies.

1.1.2 Current water management system and prob-lems to be addressed

Currently each irrigation scheme is responsible for the management and mon-itoring of the water resource available to that scheme. For each scheme thereis a Water Use Association, Irrigation Board or Government Water Schemethat will collect all the water orders, calculate water losses (seepage and evap-oration) and then schedule water releases according to the orders received forthat week.

A manual system is often used to manage these processes. In the manualsystem, orders are collected by water bailiffs on a weekly basis for the weekto come. All orders are captured into a spreadsheet for the scheme and inorder to fulfil the water orders, the bailiffs are required to calculate the losses(evaporation and seepage) that will take place over the length of the canal aswell as the lag time for water to reach its destination at the given flow rate.

This inform the water releases required in terms of volumes and times tobe released from the schemes storage dams. Only the obligatory amounts ofwater required by the scheme should be release and the principle of water ondemand ensures that water is used in the most efficient manner. However,if the release of water is not managed properly (i.e. the operator opens thesluices too early or closes them too late), incorrect filling of orders etc. thensignificant volumes of water can be lost due to these operational inefficiencies.The sustainability of the scheme is therefore at risk as well as placing strainon the overall availability of water for the country.

There is often no effective monitoring system in place to measure the

5

Page 7: Water Administration System (WAS PH3) Progress report

actual releases against the orders that are placed when using the manualmethod. Also the current method of using spreadsheets to capture ordersand manage releases introduces the risk of human error and the potentialfor manipulation when reporting to the Department of Water and Sanitation(DWS).

A further risk which has been highlighted by some of the Water UseAssociations is the continuity of the current systems in operation. There areoften only one or two persons who know how the spreadsheets relate to oneanother and how calculations are performed within them. The WUAs aretherefore totally dependent on these individuals, and should they leave orpass away, there is no-one else who knows how to operate the program.

1.1.3 The Water Administration System

A proposed solution to improve monitoring and measurement of releasesin these irrigation schemes is to install the Water Administration System(WAS) with robust logging equipment. The WAS is designed to be a watermanagement tool for irrigation schemes, Water User Associations (WUAs),Catchment Management Agencies (CMAs) and water management officesthat wish to manage their water usage, water distribution and water ac-counts.

The main aim during the development of the WAS program was to min-imise water losses for irrigation schemes that operate on the demand systemand that distribute water through canal networks.

The Water Administration System (WAS) therefore provides a method-ology to improve efficiency and accuracy of water release management andaccounting. WAS is a proprietary, locally developed, integrated irrigation wa-ter management tool used for water distribution management and calculationof canal and dam operation procedures for a given downstream demand, withthe aim of minimising water losses for irrigation schemes that operate on thedemand system and that distribute water through canal networks. Whatmakes the WAS program unique is that it is an integrated system includingthe water allocations, water use, water distribution and billing information.

Annexure 1 describes the WAS functionality and modules in more de-tail. The WAS was born out of public (WRC) funded research with theintention to commercialize it. The WAS system is specifically mentioned inthe National Water Resources Strategy 2013 as follow: ”Create an enablingenvironment to facilitate technology transfer about water use efficiency andproductivity improvement technologies, such as the water accounting system(WAS) developed by the WRC for irrigation schemes”. DWS has indicatedto SWPN that it wishes to have the WAS rolled out to additional schemes.

6

Page 8: Water Administration System (WAS PH3) Progress report

1.1.4 SWPN funding support to WAS

The SWPN identified the WAS system as a technological solution which canbe implemented in the agricultural sector to assist with addressing the gapbetween water supply and demand in the country, as per its mandate.

The SWPN pilot project focused on the implementation of the waterrelease module of the WAS system, with the main purpose of reducing waterlosses. During the implementation of the first phase of the WAS system, 4large irrigation schemes were supported with the roll out of the WAS systemwater release module (Sand-Vet, Vaalharts, Hartebeespoort (West Canal)and Orange-Riet).

In Phase 2 five further schemes were supported: Impala; Hartbeespoort(East canal); Loskop; Lower Olifant’s River; Nzhelele; and measurementactivities were supported on the Orange-Riet irrigation scheme.

Building on the successes of the WAS Project Phases 1 and 2, SWPN hassupported the upscaling of the roll-out of the WAS to 13 additional irrigationschemes in Phase 3 of the project.

The yearly water savings since 2014 (at the start of phase 1) are reportedin Table 3.1. The estimated water savings for Phase 3 are also shown in thesame table.

7

Page 9: Water Administration System (WAS PH3) Progress report

Figure 1.1: Locality map of the irrigation schemes included in each phase

8

Page 10: Water Administration System (WAS PH3) Progress report

Figure 1.2: Schemes included in each phase as shown on Figure 1.1

1.1.5 Was Phase 3

The primary objective of the project is to reduce water losses and the overallwater demand of selected schemes through the implementation of the WASwater release module.

The specific objectives are:

� To reduce water losses and the overall water demand of selected irriga-tion schemes in order to progressively close the water gap at the localand catchment level.

� To improve scheme financial management and productivity throughmore efficient water use.

� To train and capacitate scheme personnel to utilise the WAS in orderto sustain and build on the efficiency gains realised through the system.

9

Page 11: Water Administration System (WAS PH3) Progress report

� To develop a public platform for access to WAS information as a meansof promoting peer regulation and incentive based monitoring in theagricultural sector.

� To scope the water saving benefits and costs for further roll out of thewater release module in irrigation schemes where the WAS has alreadybeen implemented.

1.1.6 Key data on irrigation schemes where WAS hasbeen implemented with SWPN Support

Figure 1.3: Scheduled areas (* = phase 3)

10

Page 12: Water Administration System (WAS PH3) Progress report

Figure 1.4: Quota allocations (m3/ha) (* = phase 3)

Figure 1.5: Full quota allocations (m3) (* = phase 3)

11

Page 13: Water Administration System (WAS PH3) Progress report

Chapter 2

Implementation

12

Page 14: Water Administration System (WAS PH3) Progress report

2.1 Implementation

2.1.1 Schemes supported

All three phases of the WAS were implemented by NB Systems.

Scheme selection criteria

For the first two phases of the project it was a requirement that the WASmust be installed and up and running at the specific scheme. This criteriawas dropped for phase three and the selection criteria included the following:

� The scheme must deliver water on demand through a canal network.

� The infrastructure must be in place to measure, at least, the inflow intothe system.

� The scheme management must support the implementation of the WASprogram.

� Suitable hardware and access to the Internet must be available to runthe WAS program.

� Skilled personnel must be available to operate the WAS program.

2.1.2 The implementation comprised

� Capturing distribution sheets, water quotas and user information forall schemes.

� Installing measuring stations. The number varied per scheme depend-ing on the layout.

� Capturing water orders, meter readings and downloading of measuringstation data.

� Uploading water use and loss reports to the wateradmin website.

� Generating release volume information for operators.

� Setting up of the required IT capability and platforms.

� Processing data to generate usage and loss statistics.

� Generation of accounts.

13

Page 15: Water Administration System (WAS PH3) Progress report

� Training of scheme operators to use the WAS system to improve oper-ation of the scheme.

Capturing distribution sheet framework of the scheme

The distribution sheet framework of the total canal network was capturedwith details such as the position of abstraction points, measuring structuresand canal capacities. Access to this information was made possible by eachof the schemes.

Measuring Stations

Water flow measurement is the key to effective water distribution manage-ment and the minimization of water losses. The simplest and most effectivemethod to determine the global water loss on an irrigation scheme is by mea-suring the inflow as accurately as possible and subtracting the total wateruse (water orders).

Measuring stations comprise of a measuring flume, a cabinet or protectivestructure and a data logger. All together 37 measuring stations were installedunder WAS Phases 1 to 3, as shown in Table 2.1. Photo’s of the measuringstations can be viewed in the photo gallery of each scheme on the wateradminwebsite (www.wateradmin.co.za).

The Cello logger that is linked to the Zednet internet interface was foundto be the preferred measuring station for the canal inflow measurements. Adedicated WAS data export function was created on the Zednet platformtogether with an import function in the WAS thereby automating the datatransfer process; saving time and reducing human error.

WAS data flow: capturing water orders, meter readingsand uploading to the server

Weekly water orders are currently captured for all the schemes included inphases 1 to 3 except for Oranje Vaal WUA which is a new scheme and hadto be set-up from scratch. Meter readings are captured or imported from aFTP-site on a monthly basis.

The WAS data flow diagram, as shown in Figure 2.1, displays the differ-ent components that is available for a complete roll-out of the WAS on anirrigation scheme that delivers water on demand.

The description of each component is as follows:

14

Page 16: Water Administration System (WAS PH3) Progress report

1. The WAS-client is a stand-alone application that is used by individualfarmers to capture and maintain their own water orders. The softwarecan upload and download water orders to and from the WAS database.This allows farmers to capture and keep a record of their own waterorders for multiple sluices and synchronise it with the WAS databaseremotely through the internet.

The WAS-client application can be downloaded by a farmer from thewateradmin website.

2. The WAS is a SQL relational database that is used at scheme level forwater distribution and debit accounting management.

3. The www.wateradmin.co.za website is a multi purpose website thatis used for the following:

� Save water orders that was uploaded by farmers using the WAS-client application.

� Save water orders that was uploaded by the WAS.

� Download WAS-client water orders into the WAS.

� Display water orders, water reports and graphs that were uploadedusing the WAS.

� Display water summary reports that were uploaded using the iS-cheme software.

4. The iScheme software is a database that is developed and used by NBSystems Cc to retrieve all the water use information that was uploadedto the wateradmin website using the WAS.

iScheme then generates a water use history summary of all the schemesinto a single report and upload it to the wateradmin website to bedisplayed.

5. Zednet is an Internet platform that is used to archive and display mea-suring station data on the Internet.

The WAS makes use of the Zednet Application Programming Inter-face (API) to import measuring station data directly into the WASdatabase. This functionality makes it possible to generate water usereports automatically in the WAS which in turn are uploaded to thewateradmin website.

15

Page 17: Water Administration System (WAS PH3) Progress report

Figure 2.1: WAS data flow diagram

Generating release volume information for operators

Two methods are available in the WAS to calculate water releases whichinclude:

� Twelve hourly distribution sheet that can be setup and calibrated ac-cording to the user’s requirements. This method is easy to understandand implement which makes it the preferred method among water dis-tribution management personnel.

� Canal network approach that requires a more complicated calibrationprocedure through the use of cross section properties that are not al-ways available.

Only two schemes, which include Orange-Riet WUA and KalkfonteinWUA, make use of the canal network approach. The rest use the distributionsheet method.

2.2 WAS web interface

The URL to access the WAS web interface is www.wateradmin.co.za.Each scheme in phases 1 to 3 has its own set of web pages that can beaccessed through this link.

16

Page 18: Water Administration System (WAS PH3) Progress report

All of the reports and graphs on the wateradmin website are generatedand uploaded using the WAS and iScheme software. An example of thetypical information that is available for each scheme is shown in Figure 2.2.

The WAS system is fully functional. The user interface and usage datacan be viewed on www.wateradmin.co.za.

Lower Olifants River WUA

Week time table

Water distribution sheets

Water use efficiency reports

Weekly Released & Used graph

Weekly average water loss (m3) graph

Weekly average water loss (%) graph

Quota water Used & Available graph

Water Use Efficiency Accounting Report

History: Yearly Water Use/Loss table

History: Yearly Water Loss table

Weather

Vredendal

Clanwilliam

Citrusdal

Cloud coverage South Africa

Map

Photo gallery

Downloads

Contact information

Figure 2.2: Lower Olifants River WUA page

17

Page 19: Water Administration System (WAS PH3) Progress report

Processing data to generate usage and loss statistics

The process to generate water usage, water loss reports and distributionsheets can be summarised in two basic steps.

1. Capture water orders and meter readings

2. Import measuring station data

Once this information is captured or imported into the WAS database,the following reports and graphs are automatically generated and can beuploaded to the wateradmin website where needed:

� Water usage reports per user, group of users and for the scheme as awhole

� Water distribution sheets

� Water use efficiency accounting reports and graphs

The integration between WAS and the wateradmin website is opera-tional for all of the schemes included in phases 1, 2 and 3. The number ofreports and graphs available on the wateradmin website will be differentfor each scheme depending on their specific needs.

Generation of accounts

Monthly invoices are automatically generated by the WAS and e-mailed ina pdf-format. The debit accounting module in the WAS is not used by theGovernment owned schemes which are using their own accounting system.To date accounts are being generated for users on ten schemes which includea number of sub-schemes.

Training of scheme operators to use WAS system toimprove operation of the scheme

Formal training sessions have been given to personnel on all the schemesincluded in phase 3 of the project as shown in Table 2.2. Training includesthe following:

� Training courses

� Workshops

18

Page 20: Water Administration System (WAS PH3) Progress report

� Remote training sessions using Team Viewer

� Telephonic support

More training courses and workshops will be held until the end of theproject.

19

Page 21: Water Administration System (WAS PH3) Progress report

Table 2.1: Measuring stations Phases 1 to 3

20

Page 22: Water Administration System (WAS PH3) Progress report

Table 2.2: Implementation phase 3

21

Page 23: Water Administration System (WAS PH3) Progress report

Chapter 3

Results

22

Page 24: Water Administration System (WAS PH3) Progress report

3.1 Results

The objective of the WAS is to reduce water losses due to inefficient operationof the releases. As at September 2018 no measures have yet been introducedto improve efficiency as the project is still at the stage of establishing base-line measures. Measures to improve efficiency will follow once a baseline isestablished.

The implementation of the water release module requires an independentdetermination of the baseline water loss in order to evaluate the successof implementation. The determination of the baseline water loss dependson accurate historical release data from a reliable measuring station at theinflow into the scheme and a complete set of water ordered data for thecorresponding period.

The water losses and savings, as shown in Table 3.1, has been calculatedthrough the use of the Water Use Efficiency Accounting Report (WUEAR)in the WAS. The volumetric water losses are the critical indicator for wa-ter distribution managers and the DWS particularly when determining thepotential for water loss reduction.

3.1.1 Benefits of WAS demonstrated

The benefits recorded to date with the installation of the WAS are:

� Demonstrated water savings of 927 891 m3 per week in Phase 1

� Improved monitoring of actual releases and in certain cases, monitoringis now in place where there was previously no data recorded

� Reduced the risk of only a handful of people understanding the complexrelease calculations

� A single, standard platform using the DWS methodology for reporting– saving significant time for the Irrigation Schemes when submittingreports to the DWS

� The use of the Cello loggers and Zednet Platform as a robust platformto monitor and capture live data that is imported into WAS

� Recently developed website, where all schemes and DWS can track realtime water releases and improvements in water management

23

Page 25: Water Administration System (WAS PH3) Progress report

Table 3.1: Water savings & estimated savings for Phase 3 (m3)

3.1.2 Baseline water loss & water savings

The DWS method to calculate and report on the percentage of water lost isas follows:

Water loss(%) =(A−B)

A× 100

whereA = Released volume (m3)B = Ordered volume (m3)

The baseline water loss for phases 1 & 2, as shown in Table 3.1, has beencalculated through the use of the Water Use Efficiency Accounting Report(WUEAR) in the WAS. The percentage water loss is calculated relative to

24

Page 26: Water Administration System (WAS PH3) Progress report

the total of water released as has been the practice by the DWS over theyears.

The water loss values in Table 3.1 has been converted from the corre-sponding water years for each scheme to calendar years. Each value repre-sents a yearly water loss in x1000 m3 and %.

The water savings per year are the difference between the water loss forthe current year minus the water loss for the previous year. The total watersavings per scheme are the cumulative savings for consecutive calendar years.

Figure 3.1: Yearly Ordered & Released Phases 1 & 2

3.1.3 Projected water loss reduction

The projected water loss reduction of 66 Mm3 for phase 3 is shown in Table3.1 and in Figure 3.3. The estimate for the savings in phase 3 is based on a10% reduction of the full water quota allocations combined.

This is a conservative estimate compared to the 15% savings that wererealised in phases 1 & 2.

25

Page 27: Water Administration System (WAS PH3) Progress report

Figure 3.2: Water loss trend Phases 1 & 2

Figure 3.3: Projected loss reduction Phase 3

26

Page 28: Water Administration System (WAS PH3) Progress report

Appendix A

The WAS system

27

Page 29: Water Administration System (WAS PH3) Progress report

The WAS database can handle any number of abstraction points andmeasuring stations on canal networks, pipelines and rivers from a small wa-ter office up to CMA level where thousands of abstractions and measuringstations are managed.

What makes the WAS program unique is that it is an integrated systemincluding the water allocations, water use, water distribution and billinginformation. WAS will generate monthly invoices automatically using waterusage or scheduled areas information captured in the database. Different usernames and passwords can be used to control access to certain information inthe database.

WAS makes use of nine modules, as shown in Figure A.1, which are fullyintegrated, making it possible to cross-reference relevant data and informa-tion. These modules can be implemented partially or as a whole, dependingon the requirements of the user.

Figure A.1: WAS modules

Water Release Module

The roll out of the WAS under the SWPN has focussed on the module whichcan be installed to monitor the water releases. The Water release module isused to:

� Minimise water distribution losses in canal networks and river systems.

� Calculate water releases for the main canal, including all branches al-lowing for lag times and water losses.

� Determine operational procedures for a dam with varying downstreaminflows and abstractions in a river allowing for lag times, accruals andwater losses.

28

Page 30: Water Administration System (WAS PH3) Progress report

� Graphical output of all inflows and outflows.

� Water release graphs, which can be superimposed for comparison pur-poses.

� Handles any type of cross-section.

The diagram below describes the process followed by the WAS waterrelease module to calculate the required releases and measure the total waterlosses for each scheme.

Figure A.2: WAS release calculation

29

Page 31: Water Administration System (WAS PH3) Progress report

Appendix B

Scheme implementations

30

Page 32: Water Administration System (WAS PH3) Progress report

B.1 Boegoeberg WUA

Boegoeberg WUA has a total scheduled area of 7 693 ha and an allocationof 15 000 m3/ha. Their full quota is 115 395 000 m3 with a total of 1 505abstraction points. They receive their water from Boegoeberg dam.

Boegoeberg WUA: Implementation report

A number of meetings and training sessions were held with Boegoeberg WUA.A two day training and data capturing workshop was held to get the WASup and running.

One measuring station was installed at the inflow of their main canal.There was unfortunately no cellphone signal and the arrangement is thatthey will extract their release data manually.

They are currently capturing their water orders successfully and are inthe process of finalising their distribution sheet to calculate the water releaseschedules.

Figure B.1: Boegoeberg WUA: Meetings & training

B.2 Gamtoos IB

Gamtoos IB has a total scheduled area of 7 408 ha and an allocation of 6 000m3/ha. Their full quota is 44 448 000 m3 with a total 808 abstraction points.They receive their water from Kouga dam which was basically empty for thelast couple of months.

Implementation report

A meeting and training session were held with Gamtoos IB. They have beenusing the WAS for a number of years. Two measuring stations were installed,

31

Page 33: Water Administration System (WAS PH3) Progress report

one at the inflow and one at the tail-end of their main canal. Both measur-ing stations are working fine and data are uploaded to the Zednet platformsuccessfully.

All the abstractions at Gamtoos IB are done through meter readingswhich are captured on a monthly basis to quantify their water losses throughthe use of the water use efficiency accounting report in the WAS.

Figure B.2: Gamtoos IB: Meetings & training

B.3 Kakamas WUA

Kakamas WUA has a total scheduled area of 4 303 ha and an allocation of 15000 m3/ha. Their full quota is 64 545 000 m3 with a total of 537 abstractionpoints. They receive their water from the Orange river.

Implementation report

A number of meetings and training sessions were held with Kakamas WUA.Three measuring stations were installed, one at the left bank canal, one atthe right bank canal and one at the inflow to the Augrabies canal. All threemeasuring stations are working fine and data are uploaded to the Zednetplatform successfully.

They are currently capturing their water orders successfully and are inthe process of finalising their distribution sheet to calculate the water releaseschedules. They have also implemented the WAS-client program to capturetheir water orders remotely.

Figure B.3: Kakamas WUA: Meetings & training

32

Page 34: Water Administration System (WAS PH3) Progress report

B.4 Kalkfontein WUA

Kalkfontein WUA has a total scheduled area of 4 393 ha and an allocation of7 700 m3/ha. Their full quota is 33 829 103 m3 with a total of 94 abstractionpoints. They receive their water from the Kalkfontein dam.

Implementation report

Kalkfontein WUA has been using the WAS since 1994. One measuring sta-tion was installed at the inflow of their main canal. The measuring stationsis working fine and data are uploaded to the Zednet platform successfully.

They are currently capturing their water orders successfully and theircanal network has been set-up and calibrated. They are using the canalnetwork approach to calculate the water release schedules. No additionaltraining was needed to get them up and running.

B.5 Korente Vette IB

Korente Vette IB has a total scheduled area of 852 ha and an allocation of 7000 m3/ha. Their full quota is 5 964 000 m3 with a total of 121 abstractionpoints. They receive their water from the Korentepoort dam.

Implementation report

An inception meeting and a training session were held with Korente Vette IB.Three measuring stations were installed, one at the left bank canal, one atthe right bank canal and one at the inflow of the Nofo canal. All three mea-suring stations are working and are uploading data to the Zednet platformsuccessfully.

They are currently capturing their water orders successfully and are inthe process of finalising their distribution sheet to calculate the water releaseschedules.

Figure B.4: Korente Vette: Meetings & training

33

Page 35: Water Administration System (WAS PH3) Progress report

B.6 Lindleyspoort GWS

Lindleyspoort GWS has a total scheduled area of 1 705 ha and an allocation of5 300 m3/ha. Their full quota is 9 036 500 m3 with a total of 121 abstractionpoints. They receive their water from the Lindleyspoort dam.

Implementation report

Personnel from Lindleyspoort GWS scheme attended two training coursesheld in Pretoria in September 2018. They are one of the schemes that receiveda laptop that is dedicated to the use of the WAS.

Their base data has been captured and they are currently in the processof finalising their distribution sheet to calculate the water release schedules.

One measuring station was installed at the inflow into their main canalat Lindleyspoort dam. There is unfortunately no cellphone signal and thearrangement is that they will extract their release data manually. An effortwill be made to install an antennae that will hopefully solve the problem.

B.7 Lower Sundays River WUA

Lower Sundays River WUA has a total scheduled area of 19 366 ha andan allocation of 9 000 m3/ha. Their full quota is 174 295 800 m3 with atotal of 1 070 abstraction points. They receive their water from Gariep dam,Darlington dam, Scheepersvlakte dam and Korhaans weir.

Implementation report

The WAS is fully implemented and operational, water orders are capturedon a daily basis and monthly invoices are e-mailed to farmers. However,Lower Sundays River WUA is the only scheme that orders water using a flowrate and duration approach. They also use a unique distribution sheet tocalculate their water release schedules.

The flow rate and duration capturing form has been added to the WASand it is working perfectly. The distribution sheet has also been added tothe WAS and it is in its final testing phase. It is foreseen that a number ofthe other schemes will also take advantage of this new distribution sheet.

Two measuring stations were installed, one at Korhaansdrift and one atKirkwood. Both measuring stations are fully operational and are uploadingdata to the Zednet platform.

34

Page 36: Water Administration System (WAS PH3) Progress report

One of the challenges at Lower Sundays River WUA is a discharge tablethat is in dispute between them and the DWS. This has an effect on thewater use and loss volumes calculated on the water use efficiency accountingreports. An effort will be made to rectify this.

Figure B.5: Lower Sundays River WUA: Meetings & training

B.8 Luvuvhu GWS

Luvuvhu GWS has a total scheduled area of 2 410 ha and an allocation of 8400 m3/ha. Their full quota is 20 244 000 m3 with a total of 145 abstractionpoints. They receive their water from the Albasini dam.

Implementation report

Personnel from Luvuvhu GWS scheme attended a training course held inPretoria in September 2018. They are one of the schemes that received alaptop that is dedicated to the use of the WAS.

Two measuring stations were installed, one at the inflow into the Luvuvhucanal and one at the inflow into the Latonyanda canal. Both measuringstations are fully operational and are uploading data to the Zednet platform.

They are in the process of verifying their base data and setting up theirdistribution sheets to calculate the water release schedules.

Figure B.6: Luvuvhu GWS: Meetings & training

35

Page 37: Water Administration System (WAS PH3) Progress report

B.9 Marico Bosveld GWS

Marico Bosveld GWS has a total scheduled area of 2 523 ha and an allocationof 5 300 m3/ha. Their full quota is 13 371 900 m3 with a total of 309abstraction points. They receive their water from the Marico Bosveld damand Kromellenboog dam.

Implementation report

Personnel from Marico Bosveld GWS scheme attended a training course heldin Pretoria in September 2018. They are one of the schemes that received alaptop that is dedicated to the use of the WAS.

Two measuring stations were installed, one at the inflow into the canal atMarico Bosveld dam and one at the inflow into the canal at Kromellenboogdam. The measuring station at Kromellenboog is fully operational and isuploading data to the Zednet platform. There was unfortunately no cellphonesignal at the Marico Bosveld measuring station and the arrangement is thatthey will extract their release data manually. An effort will be made to installan antennae that will hopefully solve the problem.

They are currently capturing their water orders successfully and are inthe process of finalising their distribution sheet to calculate the water releaseschedules.

B.10 Mooiriver GWS

Mooiriver GWS has a total scheduled area of 4 517 ha and an allocation of 7700 m3/ha. Their full quota is 34 783 980 m3 with a total of 491 abstractionpoints. They receive their water from the Lakeside, Boskop and Klerkskraaldams.

Implementation report

A number of meetings and training sessions were held with personnel fromMooiriver GWS scheme.

Three measuring stations were installed, one at the inflow into the canalat Lakeside dam, one at the inflow into the canal at Boskop dam and one atthe inflow into the canal at Klerkskraal dam. All the measuring stations arefully operational and are uploading data to the Zednet platform.

36

Page 38: Water Administration System (WAS PH3) Progress report

They are currently capturing their water orders successfully and are usingtheir distribution sheets to calculate the water release schedules.

Figure B.7: Mooiriver GWS: Meetings & training

B.11 Oranje Vaal WUA

Oranje Vaal WUA has a total scheduled area of 11 258 ha and an allocationof 11 500 m3/ha. Their full quota is 129 468 610 m3. They receive theirwater from the Orange and Vaal rivers.

Implementation report

Personnel from Oranje Vaal WUA scheme attended a training course heldin Pretoria in September 2018. They are the only scheme as part of phase 3that started completely from scratch.

Two measuring stations were installed, one at the inflow into their maincanal and one at the inflow into the Buclands canal. Both measuring stationsare fully operational and are uploading data to the Zednet platform.

NB Systems is currently assisting them with the capturing of their basedata and setting up their distribution sheet to calculate the water releaseschedules.

Figure B.8: Oranje Vaal WUA: Meetings & training

B.12 Schoonspruit GWS

Schoonspruit GWS has a total scheduled area of 1 940 ha and an allocation of7 700 m3/ha. Their full quota is 14 938 000 m3 with a total of 258 abstraction

37

Page 39: Water Administration System (WAS PH3) Progress report

points. They receive their water from the Rietspruit and Elandskuil dams.

Implementation report

A number of meetings and training sessions were held with personnel fromSchoonspruit GWS scheme.

Two measuring stations were installed, one at the inflow into the canalat Rietspruit dam and one at the inflow into the canal at Elandskuil dam.Both measuring stations are fully operational and are uploading data to theZednet platform.

They are currently capturing their water orders successfully and are usingtheir distribution sheets to calculate the water release schedules.

Figure B.9: Schoonspruit GWS: Meetings & training

38

Page 40: Water Administration System (WAS PH3) Progress report

Appendix C

Meetings & Training

39

Page 41: Water Administration System (WAS PH3) Progress report

Table C.1: Inception meetings & Training sessions

40

Page 42: Water Administration System (WAS PH3) Progress report

Appendix D

Confirmation of work

41

Page 43: Water Administration System (WAS PH3) Progress report

Figure D.1: Boegoeberg confirmation

Figure D.2: Gamtoos confirmation

42

Page 44: Water Administration System (WAS PH3) Progress report

Figure D.3: Kakamas confirmation

Figure D.4: Kalkfontein confirmation

43

Page 45: Water Administration System (WAS PH3) Progress report

Figure D.5: Korente Vette confirmation

44

Page 46: Water Administration System (WAS PH3) Progress report

Figure D.6: Lower Sundays River confirmation

Figure D.7: Luvuvhu confirmation

45

Page 47: Water Administration System (WAS PH3) Progress report

Figure D.8: Marico & Lindleyspoort confirmation

46

Page 48: Water Administration System (WAS PH3) Progress report

Figure D.9: Mooi river & Schoonspruit confirmation

47

Page 49: Water Administration System (WAS PH3) Progress report

Figure D.10: Oranje-Vaal confirmation

48