Wastewater Asset Management Plan - Palmerston North · Wastewater Asset Management Plan . This...
Transcript of Wastewater Asset Management Plan - Palmerston North · Wastewater Asset Management Plan . This...
Wastewater Asset Management Plan
This Asset Management Plan (AMP) is based on the best information available when it was completed in December 2017. Council decision making both with regard to programmes that are implemented and the timing of the programmes in the context of the 2018-28 10 Year Plan has yet to be finalised. The programmes in this AMP have been used as a planning tool to inform the 10 Year Plan planning process. The actual programme of work that Council plans to implement will be that in the adopted 2018-28 10 Year Plan following formal public consultation.
This document was prepared by Palmerston North City Council, City Networks, Water and Waste Services Division.
Name Signature Date
Prepared by: Phil Burt
Robert van Bentum
Dec 2017
Reviewed by: Phil Walker
Feb 2018
External Peer Review by: AECOM Ltd
March 2018
Approved for Issue by:
Version No. Reason for Amendment Date
D Peer Review Feedback Incorporated April 2018
PNCC Reference No: 8833152
Water & Waste Division Palmerston North City Council l Private Bag 11034 l Palmerston North P: +64 (6) 3568199 l F: +64 (6) 3514489 l www.pncc.govt.nz
Contents Executive Summary................................................................................................................................. i
1 Overview ........................................................................................................................................... 1
1.1 Purpose of this Plan ................................................................................................................... 1
1.2 Relationship with Other Plans .................................................................................................... 1
1.3 AMP review process................................................................................................................... 3
1.4 Changes to AM since 2014 ........................................................................................................ 3
1.5 Navigating the AMP.................................................................................................................... 4
2 The Activity ...................................................................................................................................... 7
2.1 Activity Description ..................................................................................................................... 7
2.1.1 Palmerston North Main Urban Area ................................................................................... 10
2.1.2 Ashhurst .............................................................................................................................. 10
2.1.3 Aokautere............................................................................................................................ 10
2.1.4 Linton (Excluding Army Camp & Prison) ............................................................................ 10
2.1.5 Bunnythorpe ....................................................................................................................... 10
2.1.6 Longburn ............................................................................................................................. 10
2.2 Activity Rationale ...................................................................................................................... 11
2.3 Key Relationships ..................................................................................................................... 12
2.4 LGA Section 17A Review ......................................................................................................... 13
2.5 Significant Negative Effects of the Activity ............................................................................... 13
2.6 Significant Changes to the Activity ........................................................................................... 14
3 Strategic Environment .................................................................................................................. 15
3.1 Internal Strategic Context ......................................................................................................... 15
3.1.1 Council Vision, Goals & Strategic Direction ........................................................................ 15
3.1.2 Infrastructure Strategy ........................................................................................................ 16
3.2 External Strategic Context ....................................................................................................... 17
3.2.1 Horizons Regional Council One Plan ................................................................................. 17
3.3 Statutory and Regulatory Requirements .................................................................................. 17
3.3.1 Key Legislation ................................................................................................................... 17
3.3.2 Local Bylaws ....................................................................................................................... 18
3.3.3 Standards & Specifications ................................................................................................. 18
3.4 Asset Management Policy & Strategy ...................................................................................... 19
3.4.1 Asset Management Policy .................................................................................................. 19
3.4.2 Asset Management Strategy .............................................................................................. 19
4 Levels of Service ........................................................................................................................... 23
4.1 Introduction ............................................................................................................................... 23
4.2 Community Input & Decision Making Process ......................................................................... 24
4.3 Communication of Levels of Service & Performance Measures .............................................. 25
4.4 Current and Future Levels of Service & Performance Measures ............................................ 25
4.4.1 Key Performance Indicators ............................................................................................... 25
4.4.2 Future Changes to Levels of Service .................................................................................. 31
4.4.3 Service Level Gaps ............................................................................................................. 31
5 Growth and Demand ...................................................................................................................... 33
5.1 Future Demand Drivers............................................................................................................. 33
5.2 Growth Projections .................................................................................................................... 33
5.2.1 Population Growth ............................................................................................................... 33
5.2.2 National Policy Statement – Urban Development Capacity ................................................ 34
5.2.3 Household Growth ............................................................................................................... 34
5.2.4 Residential Development Type ........................................................................................... 35
5.3 Residential Growth Strategy ..................................................................................................... 35
5.4 Industrial Growth Strategy ........................................................................................................ 39
5.5 Office and Retailing (Commercial) Land Use Strategy ............................................................. 40
5.6 Rural Residential Strategy ........................................................................................................ 41
5.7 Other Demand / Consumption Projections / Patterns ............................................................... 42
5.7.1 Wastewater Collection Services Demand/Wastewater Production Trends ........................ 42
5.7.2 Changes to Water Use Pattern ........................................................................................... 42
5.7.3 Projected Flows & Loads ..................................................................................................... 44
5.7.4 Wastewater from Private Systems ...................................................................................... 45
5.7.5 Wastewater from Other Sources ......................................................................................... 45
5.7.6 Stormwater Inflow & Infiltration............................................................................................ 45
5.7.7 Regional Council One Plan Standards ................................................................................ 45
5.7.8 National Policy Statement – Freshwater Management ....................................................... 46
5.7.9 Technology Changes .......................................................................................................... 46
5.8 Demand Management .............................................................................................................. 46
5.9 Sensitivity to Demand Changes ................................................................................................ 47
5.10 Climate Change – Impact on Demand...................................................................................... 47
6 Assets & Lifecycle Management .................................................................................................. 49
6.1 Overview of Wastewater Network Assets ................................................................................. 49
6.1.1 Description of Assets ........................................................................................................... 49
6.1.2 Wastewater Supply Asset Components .............................................................................. 51
6.2 The Wastewater Collection Assets ........................................................................................... 51
6.2.1 The Western Trunk Sewer Main Catchment ....................................................................... 52
6.2.2 Featherston/Tremaine Trunk Catchment ............................................................................ 52
6.2.3 Ferguson Street Trunk Catchment ...................................................................................... 52
6.2.4 Eastern Trunk Catchment ................................................................................................... 52
6.2.5 Confluence of Trunks .......................................................................................................... 52
6.2.6 Aokautere Reticulation ........................................................................................................ 53
6.2.7 Linton Reticulation ............................................................................................................... 53
6.2.8 Ashhurst Reticulation .......................................................................................................... 53
6.2.9 Bunnythorpe Reticulation .................................................................................................... 53
6.2.10 Longburn Reticulation ......................................................................................................... 53
6.3 Wastewater Collection Asset Attributes .................................................................................... 53
6.3.1 Wastewater Collection Asset Condition .............................................................................. 55
6.3.2 Wastewater Collection Asset Capacity and Performance .................................................. 57
6.4 Wastewater Pump Station Assets ............................................................................................ 60
6.4.1 Wastewater Pump Station Asset Attributes ........................................................................ 60
6.4.2 Wastewater Pump Station Asset Condition ........................................................................ 63
6.4.3 Wastewater Pump Station Asset Capacity and Performance ............................................ 63
6.5 Wastewater Treatment Assets ................................................................................................. 64
6.5.1 Wastewater Treatment Asset Attributes ............................................................................. 64
6.5.2 Wastewater Treatment Asset Condition ............................................................................. 65
6.5.3 Wastewater Treatment Asset Capacity and Performance ................................................. 67
6.5.4 The Telemetry and SCADA Assets .................................................................................... 69
6.5.5 Description of Assets .......................................................................................................... 69
6.6 Activity Management ................................................................................................................ 70
6.6.1 Support Services ................................................................................................................ 70
6.6.2 Increases in Services (Operating Programmes) ................................................................. 71
6.6.3 Asset Systems Database – Infor Public Sector .................................................................. 72
6.6.4 Network Hydraulic Modelling .............................................................................................. 74
6.7 Water Services Assessment .................................................................................................... 75
6.8 Operation & Maintenance of Assets ......................................................................................... 75
6.8.1 Overview ............................................................................................................................. 75
6.8.2 Operation & Maintenance Strategies .................................................................................. 75
6.8.3 Operation & Maintenance Costs ......................................................................................... 76
6.8.4 Operation of Wastewater Assets ........................................................................................ 76
6.8.5 Maintenance of Wastewater Assets ................................................................................... 77
6.8.6 Operation & Maintenance Delivery ..................................................................................... 77
6.8.7 Delivery of Programme ....................................................................................................... 78
6.9 Renewal of Assets .................................................................................................................... 79
6.9.1 Overview ............................................................................................................................. 79
6.9.2 Renewal Strategies ............................................................................................................. 80
6.9.3 Long Term Renewal Profile ................................................................................................ 80
6.9.4 Renewal Programme .......................................................................................................... 81
6.9.5 Delivery of Programme ....................................................................................................... 85
6.10 Development of Assets ............................................................................................................ 86
6.10.1 Overview ............................................................................................................................. 86
6.10.2 Development Strategies ..................................................................................................... 86
6.10.3 Development Programme ................................................................................................... 87
6.10.4 Delivery of Programme ....................................................................................................... 90
6.10.5 Non Asset Programmes ...................................................................................................... 91
6.10.6 Disposal of Assets .............................................................................................................. 91
6.11 Key AMP Improvement Projects Relating to Asset Lifecycle Management ............................. 91
7 Risks & Resilience ........................................................................................................................ 93
7.1 Corporate Risk Management Framework ................................................................................ 93
7.1.1 Risk Management Policy ..................................................................................................... 93
7.1.2 Strategic Risks .................................................................................................................... 93
7.1.3 Operational Risks ................................................................................................................ 93
7.1.4 Project Risks........................................................................................................................ 96
7.1.5 Risk Management Hierarchy ............................................................................................... 96
7.1.6 Asset Criticality .................................................................................................................... 97
7.1.7 Resilience ............................................................................................................................ 97
7.1.8 Risk Management Process ................................................................................................. 98
7.2 Activity Risk Management ........................................................................................................ 99
7.2.1 Approach for the Activity ..................................................................................................... 99
7.2.2 Role of Activity as a Lifeline Utility ...................................................................................... 99
7.2.3 Critical Assets .................................................................................................................... 100
7.2.4 Resilience .......................................................................................................................... 101
7.2.5 Sources of Risk ................................................................................................................. 101
7.2.6 Reference Documents ....................................................................................................... 102
7.3 Key Risks to the Wastewater Activity ..................................................................................... 102
7.3.1 Operational Failure ............................................................................................................ 102
7.3.2 Asset Failure...................................................................................................................... 103
7.3.3 Project & Planning Risks ................................................................................................... 103
7.3.4 Natural Disasters ............................................................................................................... 103
7.3.5 Events & Incidents ............................................................................................................. 104
7.4 Resilience of Infrastructure to Natural Disaster ...................................................................... 104
7.4.1 Introduction ........................................................................................................................ 104
7.4.2 Seismic Hazard ................................................................................................................. 104
7.4.3 Flooding Hazard ................................................................................................................ 105
7.4.4 Volcanic Hazard ................................................................................................................ 105
7.4.5 Other Natural Hazards ...................................................................................................... 105
7.4.6 Interdependencies ............................................................................................................. 105
7.5 Risk Management Strategy .................................................................................................... 106
7.6 Risk Management Program .................................................................................................... 106
7.7 Civil Defence Preparedness ................................................................................................... 107
7.7.1 Emergency Events ............................................................................................................ 107
7.7.2 Emergency Response Plan ............................................................................................... 107
7.7.3 Business Continuity Plan ................................................................................................... 108
7.7.4 Recovery ........................................................................................................................... 109
7.7.5 Lifeline Utilities Coordination ............................................................................................. 109
7.7.6 Risks and Resilience Improvement Plan ........................................................................... 110
8 Sustainability ................................................................................................................................ 111
8.1 Eco City Strategy .................................................................................................................... 111
8.2 Climate Change ...................................................................................................................... 111
8.3 Approach Taken in This Plan .................................................................................................. 112
9 Financial Projections & Trends.................................................................................................. 113
9.1 Long Term Financial Forecast ............................................................................................... 113
9.1.1 Proposed Operation & Maintenance Expenditure ............................................................ 113
9.1.2 Proposed Renewal Expenditure ....................................................................................... 113
9.1.3 Proposed New Capital Expenditure .................................................................................. 114
9.1.4 Trends in Thirty Year Forecast ......................................................................................... 115
9.2 Asset Valuation ..................................................................................................................... 115
9.3 Confidence levels ................................................................................................................... 116
9.4 Reliability of financial forecasts .............................................................................................. 117
9.4.1 Maintenance and Renewal Forecasts .............................................................................. 117
9.4.2 Development Forecasts .................................................................................................... 117
9.4.3 Potential Effects of Uncertainty ........................................................................................ 117
9.5 Funding policy ........................................................................................................................ 118
9.5.1 Operation and maintenance ............................................................................................. 118
9.5.2 Capital renewal ................................................................................................................. 118
9.5.3 Capital development ......................................................................................................... 118
9.5.4 Development contributions ............................................................................................... 118
10 Assumptions ................................................................................................................................ 119
10.1 Asset Ownership and Provision of Service ............................................................................ 119
10.2 Population Growth .................................................................................................................. 119
10.3 Residential Growth ................................................................................................................. 119
10.4 Industrial Growth .................................................................................................................... 119
10.5 Retail Growth .......................................................................................................................... 120
10.6 Rural-Residential Growth ....................................................................................................... 120
10.7 Levels of Service .................................................................................................................... 120
10.8 Construction Costs ................................................................................................................. 120
10.9 Maintenance & Operational Costs ......................................................................................... 120
10.10 Inflation ................................................................................................................................... 121
10.11 Depreciation ........................................................................................................................... 121
10.12 Vested Assets ........................................................................................................................ 121
10.13 Service Potential .................................................................................................................... 121
10.14 Asset Lives ............................................................................................................................. 121
10.15 Natural Disasters .................................................................................................................... 121
10.16 Council Policy ......................................................................................................................... 122
10.17 Interest Rate ........................................................................................................................... 122
10.18 Treatment Plant Upgrade ....................................................................................................... 122
11 Continuous Improvement ........................................................................................................... 123
11.1 Overview ................................................................................................................................ 123
11.2 Programme Planning and Implementation ............................................................................. 123
11.3 Project Status ......................................................................................................................... 123
11.4 Development Works Planning ................................................................................................ 123
11.4.1 Residential Growth and Industrial Growth Planning (refer to Section 5) .......................... 123
11.4.2 Demand Projections (refer to AMP Section 5) .................................................................. 124
11.4.3 Risk and Resilience (refer to AMP Section 7) ................................................................... 124
11.4.4 Council Strategies (refer to AMP Section 3) ..................................................................... 124
11.5 Renewal Works Planning ........................................................................................................ 124
11.5.1 Condition Data ................................................................................................................... 124
11.6 Operations and Maintenance .................................................................................................. 124
11.6.1 Operations and Maintenance Strategy .............................................................................. 124
11.6.2 Internal Service Level Agreements ................................................................................... 124
11.6.3 Market Comparability Procedure ....................................................................................... 125
11.7 Asset Information .................................................................................................................... 125
11.7.1 Asset Management Plan Improvement ............................................................................. 125
11.8 Asset Management Resources ............................................................................................... 125
11.8.1 Loss of Key AM Knowledge .............................................................................................. 125
11.8.2 Skill Gaps .......................................................................................................................... 125
11.9 Levels of Service Review ........................................................................................................ 125
11.10 AMP Improvement Plan (2017) .............................................................................................. 126
Appendices Glossary Appendix A. Requirements of the LGA 2002 Appendix B. Technical Performance Measures Appendix C. Risk Analysis/ Framework & Register Appendix D. 30 Year Financial Forecasts Appendix E. Resource Consents Appendix F. Asset Grading Definitions Appendix G. Pump Station Asset Data Appendix H.
Data Management Appendix I. 6 Year Asset Renewal Programme Appendix J. Final Peer Review Report Appendix K.
Table of Figures Figure 1: Relationship between Council Planning Processes ................................................................. 2
Figure 2: AMP Structure ........................................................................................................................... 5
Figure 3: Schematic Layout of Wastewater System ................................................................................ 8
Figure 4: Map of Wastewater Collection Areas ........................................................................................ 9
Figure 5: Map showing location of proposed residential development .................................................. 38
Figure 6: Map of NEIZ Infrastructure Roll Out ....................................................................................... 39
Figure 7: Map of Existing Industrial Zone at Longburn .......................................................................... 40
Figure 8: Map of Spatial Extent of the Business Zones ......................................................................... 41
Figure 9: Average Daily Demand of Metered Properties ....................................................................... 43
Figure 10: Historical Metered Non-Domestic Water Demand ............................................................... 43
Figure 11: Breakdown of Average Daily Water Consumption for 2016/17............................................ 44
Figure 12: Wastewater Catchments ...................................................................................................... 50
Figure 13: Wastewater Supply Asset Component Groups .................................................................... 51
Figure 14: Wastewater Pipe Age ........................................................................................................... 54
Figure 15: Wastewater Pipe Material .................................................................................................... 54
Figure 16: Wastewater Pipe Diameters ................................................................................................. 55
Figure 17: Location of CCTV Surveys Completed ................................................................................ 56
Figure 18: Pipe Blockage and Breaks by Pipe Age ............................................................................... 57
Figure 19: Pipe Blockage and Breaks by Pipe Diameter ...................................................................... 58
Figure 20: Pipe Blockage & Breaks Long Term Trends ........................................................................ 58
Figure 21: Catchment Inflow & Infiltration.............................................................................................. 60
Figure 22: Location of Wastewater Pump Stations ............................................................................... 62
Figure 23: Photo of Wastewater PS in Grand Oaks Drive .................................................................... 63
Figure 24: Totara Road Wastewater Treatment Plant Schematic ......................................................... 65
Figure 25: Field Inspector Screen Shot .................................................................................................. 73
Figure 26: IPS Screen Shot ................................................................................................................... 73
Figure 27: Wastewater Treatment Operations & Maintenance Staff ..................................................... 79
Figure 28: Wastewater Pipes Profile Based on Expected Asset Life .................................................... 81
Figure 29: Risk Management Hierarchy ................................................................................................ 97
Figure 30: Risk Management Process (AS/NZS ISO 31000:2009) ...................................................... 98
Figure 31: Thirty Year Operation & Maintenance Expenditure Forecast ............................................ 113
Figure 32: Thirty Year Projected Renewals Expenditure .................................................................... 114
Figure 33: Thirty Year Projected New Capital Expenditure ................................................................. 115
Table of Tables Table 1: Wastewater Assets Quantity by Type ....................................................................................... 7
Table 2: Activity Linkages to City Goals ................................................................................................ 11
Table 3: Wastewater Activity contribution to City Goals ........................................................................ 15
Table 4: AMP Linkages to the Infrastructure Strategy ........................................................................... 16
Table 5: Matters Raised at Councilor LoS Workshop ........................................................................... 25
Table 6: LoS Actions from Strategy Plans ............................................................................................. 25
Table 7: Customer Level of Service, Performance Measures & Targets .............................................. 27
Table 8: Future Changes to LoS ........................................................................................................... 31
Table 9: Population Projection for Palmerston North ............................................................................ 34
Table 10: Household Projection for Palmerston North .......................................................................... 35
Table 11: Residential Development Type.............................................................................................. 35
Table 12: The staging and timing of residential greenfield areas .......................................................... 36
Table 13: Totara Road WWTP Project Flows & Loads .......................................................................... 44
Table 14: Replacement Value of Wastewater Assets ............................................................................ 51
Table 15: Collection System Assets ....................................................................................................... 55
Table 16: Wastewater Pump Station Condition & Performance Ratings ............................................... 61
Table 17: Wastewater Treatment Plant Asset Data ............................................................................... 66
Table 18: Activity Management Program – Five Year Forecast ............................................................ 71
Table 19: Operating Programmes – Forecast Expenditure ................................................................... 71
Table 20: IPS Data Accuracy & Completeness ..................................................................................... 74
Table 21: Operations & Maintenance Forecast Expenditure (Next Five Years) .................................... 76
Table 22: Operations & Maintenance Activity Delivery Expenditure – Five Year Forecast ................... 77
Table 23: Current Operation and Maintenance SLA Costs (2017/18) ................................................... 79
Table 24: Life Expectancy of Wastewater Assets .................................................................................. 80
Table 25: Renewals Programme Expenditure – Five Year Forecast ..................................................... 83
Table 26: Development Programme Expenditure .................................................................................. 87
Table 27: Operational Risks ................................................................................................................... 94
Table 28: Resilience Definitions ............................................................................................................. 98
Table 29: Population Based Criticality Grading ................................................................................... 100
Table 30: Criticality Grading for Wastewater Pipe Assets ................................................................... 100
Table 31: Criticality Grading for Wastewater Pump Station Assets ..................................................... 101
Table 32: Key Operational Risks & Mitigation Measures ..................................................................... 102
Table 33: Key Asset Failure Risks & Mitigation Measures .................................................................. 103
Table 34: Key Project & Planning Risks & Mitigation Measures .......................................................... 103
Table 35: Seismic Resilience ............................................................................................................... 104
Table 36: Utility Services that the Wastewater Activity Depends on for Continuity of Service ............ 106
Table 37: Risk Management Programme ............................................................................................ 106
Table 38: Relevant Eco City Strategy Priorities and Plans .................................................................. 111
Table 39: Asset Valuations 2017 ......................................................................................................... 116
Table 40: Confidence Grading System ................................................................................................ 116
Table 41: Confidence Rating Wastewater Assets ................................................................................ 117
Table 42: Palmerston North City Council 3 Year Asset Management Improvement Programme ....... 127
Executive Summary Asset Management Plan 2017 – Wastewater
i
EXECUTIVE SUMMARY
Purpose of this Plan
The purpose of this plan is to demonstrate how the assets are being managed so as to deliver wastewater services to the community in a sustainable and cost effective way.
This plan details information about:
The strategic outcomes that Council is seeking to achieve related to wastewater infrastructure.
The level of service to be provided. The infrastructure that need to be
maintained, renewed and developed to meet the demands placed on it over the next 30 years.
How these services are to be provided. What funding is required to meet these
demands. The associated risks.
The AMP covers a period from 1 July 2018 to 30 June 2048 with a particular focus on work programmes over the next five years. It informs the Council’s 2018/28 10 Year Plan and 30 Year Infrastructure Strategy and contributes to meeting Council’s identified strategic outcomes.
Activity & Assets
The services that are provided to the community through the assets in this plan are as follows:
Wastewater collection provided throughout the urban environment including collection of wastewater from the outlying areas of Aokautere, Linton, Bunnythorpe, Ashhurst, and Longburn.
Gravity and pumped delivery of the wastewater to the Totara Road wastewater treatment plant.
Treatment at the Totara Road Treatment Plant prior to discharge of the treated effluent to the Manawatu River.
The assets that contribute to providing these services are:
Table A: Asset Component Summary
Asset Component Quantity
Pipelines 404 km
Manholes 5,565
Laterals 27,783
Pump Stations 34
Treatment Plants 1
Oxidations Ponds 2
Valves 35
These assets have a replacement value of $291M.
Asset Condition and Performance
Wastewater Collection Network
The overall condition of the collection network is considered to be good, although there is significant stormwater inflow and infiltration in older parts of the network contributing to high peak wet weather flows. There are also a number of pipe blockages occurring in service laterals and some smaller diameter sewers due to the impact of root intrusion.
The overall performance of the wastewater collection network is considered to be good based on the small number of overflows and pipe blockages that occur.
Wastewater Pump Stations
The majority of the pump station assets are in good to excellent condition. The larger pump stations have been upgraded to meet higher seismic performance levels. Some smaller pump stations are fitted with obsolete electrical and control equipment and are in need to upgrading, which is scheduled early in the next 10 year period.
Totara Wastewater Treatment Plant
The Totara Road plant has been maintained to a high standard with an ongoing maintenance program and timely replacement of mechanical
Executive Summary Asset Management Plan 2017 – Wastewater
ii
and electrical equipment as necessary. Major upgrades to inlet screens, grit traps and pumping are either in progress or programmed to occur early in the next 10 year period.
The wastewater discharge consent requires a new consent to be applied for by June 2022. A Best Practicable Options study is currently underway to determine the most appropriate form of future treatment and disposal of wastewater for the City.
Strategic Environment
Asset management planning is undertaken within both an internal and external strategic environment.
The internal strategic environment is set by the Council’s desired outcomes underpinned by its Vision of ‘Small city benefits, big city ambition’. Council has developed a range of Strategy Plans for each of its 5 strategic goals:
Goal 1: An innovative and growing city. Goal 2: A creative and exciting city. Goal 3: A connected and safe community. Goal 4: An eco-city. Goal 5: A driven and enabling council.
Of particular importance to this AMP are the Infrastructure plan and the Three Waters plan developed under the City Development Strategy and the Eco-City Strategy respectively.
The Infrastructure Plan sets expectations that infrastructure for wastewater will be provided ahead of development demand and will be sufficient to meet on-going urban intensification and high rate growth targets. The Three Waters Plan focusses on managing the effects of growth and climate change on wastewater discharge volumes as well as meeting the higher consenting standards likely to be required through the consent renewal project.
The external strategic environment is also of relevance in that the performance of the wastewater network is governed by legislative obligations and dependent on the management of receiving water courses which fall under the control of the Horizons Regional Council.
The Building Act and Horizons One Plan set legislative and regulatory requirements and controls around development and the level of service from wastewater systems. Critical to the activity in the next 10 year period will be securing a new consent for the wastewater treatment plant. This will require a robust and comprehensive assessment of options and engagement with stakeholders prior to Council’s selection of the preferred option.
AMP Response to the Strategic Context
The approach taken in the AMP is to ensure the safe and reliable collection, treatment and disposal of wastewater to protect community health. Specific issues focussed on for the period 2018-21 and addressed in the plan are:
Reductions in stormwater infiltration and inflow to the wastewater network to provide better control of peak wet weather wastewater flows
Completion of the Best Practicable Options assessment to determine the preferred option for consenting of a new wastewater treatment and disposal solution to secure wastewater services for the city for the next 30 years
Manage flows and loads proactively through implementation of pressure sewer areas and active engagement with major trade waste consent holders
Staged expansion of the wastewater network to meet projected growth
The benefits of addressing these problems and the consequences of not addressing them are outlined in the AMP.
Levels of Service
This plan supports Council providing:
Wastewater collection and treatment systems which protect public health and provide residential, industrial and commercial properties in the City with safe and reliable disposal and treatment of wastewater.
Wastewater infrastructure which meets the expected growth requirements.
Executive Summary Asset Management Plan 2017 – Wastewater
iii
Wastewater services which comply with regulatory and consenting requirements.
Selection of a preferred option for the treatment and disposal of wastewater ready ahead of the preparation and lodging of consents by June 2022
Management of the wastewater activity in a financially sustainable way
LoS measures for the above services are contained in Council’s 10 Year Plan and include a number of regulatory and DIA mandatory performance measures. Key performance indicators include environmental compliance for treatment performance and ensuring wastewater is contained in the network.
The AMP also sets out both customer and technical levels of service in the areas of network performance, wastewater overflows, odour events, as well as responsiveness, consent compliance, fault and complaint occurrence and planning.
Levels of service are expected to change in the following areas:
Higher treatment standards as part of new consenting requirements expected to be in place sometime after June 2022.
Higher levels of network and treatment reliability associated with greater proactive investment in inspection, condition assessment and maintenance.
Specific requirements for the use of low pressure sewer systems in selected new growth areas to limit flows and exclude stormwater
Improvements in per capita wastewater generation associated with a greater focus on water efficiency, inflow and infiltration reduction and trade waste improvement plans.
Higher trade waste standards as part of measures to ensure new consenting and compliance requirements are achieved.
Future Demand
The future demand for wastewater in Palmerston North will be driven by:
Residential and industrial growth in the city. Greater uptake of Low Pressure Sewer
and/or Vacuum Sewer Systems. Changes in Council policy with regard to
rural residential properties. Changes in water consumption and usage
patterns given that most water supplied for domestic, commercial, and industrial purposes is subsequently discharged into the wastewater system.
The extent of stormwater entry to the wastewater system (infiltration and inflow).
Climate change.
The investment in new wastewater reticulation and treatment capacity outlined in this AMP is based on following a specific Palmerston North high population growth scenario for years 1-10 that equates to 1.0% per annum growth and then a medium growth scenario for years 11-30 that gives an overall population growth of 0.6% p.a. over 30 years.
The main areas for residential growth are Whakarongo in the short term and City West in the longer term supported by other smaller developments. Industrial growth will be serviced mainly by the North East Industrial zone extension and land at Longburn.
The demand for services is to be met through a combination of managing existing assets, upgrading of existing assets, providing new assets and demand management.
Lifecycle Management
Policy and Planning
Expenditure on policy and planning is predicted to continue at significant levels with key priorities during the period including:
Completing the city wide wastewater network model to provide an essential planning tool to assess capacity constraints;
Completing policy and regulatory work to sup[port the implementation of pressure sewer areas within the city to better manage flows;
Executive Summary Asset Management Plan 2017 – Wastewater
iv
Undertaking critical asset condition assessment including enhanced condition assessment for critical mechanical and electrical assets; and
Targeting stormwater infiltration and inflow to the wastewater network by way of a dedicated programme of work and proactive follow-up on fault identification.
The programme also includes provision for an enhanced annual programme of CCTV inspection and condition grading for a significant portion of the network with a focus on the catchments with high wet weather flows.
Operations and Maintenance Plan
The operations and maintenance strategy is intended to deliver the required levels of service, mitigate risk and minimise costs by implementing a balanced programme of planned, preventative and reactive works.
Operation and maintenance costs are expected to increase over the planning period due to increased costs associated with meeting higher wastewater treatment and disposal consent requirements. Some minor reductions in costs are anticipated due to increased reliability of equipment.
Renewal of Assets
Renewal or restoration of assets is required to ensure that the service potential of the asset is maintained and that the level of service can continue to be delivered. The renewal programme seeks to provide the optimum mix of treatment options and timing for minimising costs over the life of the asset. The renewal programme is based on:
Knowledge of historical renewal requirements.
Collected asset condition and age data, using a predictive deterioration relationship based on consideration of asset lives and historical rates of condition deterioration.
Actual asset condition assessment programme undertaken on key assets to determine remaining life cycles and prioritisation programme for replacements and maintenance.
Failure history and in some cases, predictive modelling.
Treatment selection and work prioritisation are determined from an economic analysis of options considering all asset life cycle costs.
Total renewal expenditure of $65.M is forecast for the next 30 years for the treatment plant and sewer network as shown in Figure B.
The difference between depreciation and forecast renewal expenditure is due to the relatively young age of some of the wastewater pipe network and the impact of the expected upgrade of the wastewater treatment plant which is expected to result in some assets being superseded.
Development of Assets
Asset development needs to meet demand forecasts and deliver the agreed level of service are identified from an assessment of risks, performance monitoring and demand analysis. All feasible options, including non-asset demand management options, are considered. Project selection and prioritisation is determined from an economic analysis of options considering all asset life cycle costs.
Capital development projects undertaken to meet level of service needs and growth are funded from borrowing and developer contributions respectively.
Expenditure of $128.0M is forecast for the next 30 years for treatment plant development and sewer network upgrades required to accommodate growth with the dominant investment of $110.0M associated with the WWTP Consent Renewal. The capital expenditure associated with the consent renewal will be the single largest expenditure by Council in the planning period.
Financial Summary
The following graphs show the projected operating and capital expenditure associated with the management and development of the assets as set out in the O&M, Renewals and Development Plans. Annual expenditure is
Executive Summary Asset Management Plan 2017 – Wastewater
v
shown annually for the first 10 years and then 5 yearly bands for years 11-30 of the plan. Forecasts are shown as present day costs.
Operation and Maintenance
Figure A depicts projected operation and maintenance expenditure for the 30 year period excluding interest and depreciation.
Figure A: Thirty Year Projected Operations and Maintenance
Renewals
Figure B depicts projected renewal expenditure for the 30 year plan period.
Figure B: 30 Year Projected Renewals Expenditure
Capital Development
The projected 30 year capital development expenditure profile is depicted in Figure C.
Figure C: 30 Year Projected New Capital Expenditure
Financial forecasts are based on generally good asset information although extrapolation of information has been used in some places. Projects in the first few years are more fully scoped than in later years.
Risk & Resilience
Critical assets are those assets which have the highest consequences in terms of disruption in service and financial, environmental and social cost should they fail. For the Wastewater Activity, the assets in this category are:
Large diameter wastewater pipes (criticality assessed as High);
Massey and Maxwell’s Line wastewater pump stations (criticality assessed High); and
Totara wastewater treatment plant. Assets with critical customers
Key risks identified for the activity as a whole are:
Odours from the system; Power failure; Network blockage or breaks; Pump station failure; Wastewater treatment plant failure; Network capacity failure due to lack of
planning; and Major earthquake hazard.
Mitigation measures to address these risks are covered in this plan.
Resilient infrastructure is able to deal with significant disruption and changing circumstances as a result of the occurrence of
$0
$2
$4
$6
$8
$10
Mill
ion
s
Operational ExpenditureWastewater Average Annual in
5 year bandsIIIIIIIII
$0
$1
$2
$3
$4
Mill
ion
s
Renewal ExpenditureWastewater
Average Annual in 5 year bandsIIIIII
$0
$5
$10
$15
$20
$25
$30
$35
$40
$45
Mill
ion
s
Capital New ExpenditureWastewater
Average Annual in 5 year bandsIIII
II
Executive Summary Asset Management Plan 2017 – Wastewater
vi
natural hazards, such as seismic and volcanic events. This AMP is focussed on continuity of wastewater services following a high consequence event.
The greatest threat to the functionality of the wastewater activity is a major seismic event, with the resilience of critical assets especially important for continuation of service delivery. These include the wastewater treatment plant, major pump stations and trunk mains.
Both technical and organisational aspects of resilience have been considered in this plan.
Data Management and
Reliability
The quality and completeness of the wastewater asset data is considered average given it is based on historical capture of asset data at the time of construction and some periodic condition information captured using CCTV. Significant additional CCTV inspection is proposed particularly of the critical large diameter network where there have been a number of unexpected failures. Additional targeted work to try to better manage stormwater inflow and infiltration to the wastewater network is also planned. Other improvements include:
Installation of permanent flow meters with auto-data capture to better monitor flows in the network
Upgrades to wastewater pump stations to provide real time flow measurement to identify leaky catchments with high inflow and infiltration
Implementation of real time flow measurement of all significant trade waste discharge consent holder to better manage their impact on the network
Detailed condition assessment of all major items of plant and equipment at the WWTP
to develop an optimised renewal programme
Continuous Improvement
Asset management processes and practices are continually being assessed and improved in order to provide more cost effective asset management. The priority improvement tasks for the next 3 years are as follows:
Capital renewal and development project planning – further development of processes to take into account a sustainable development approach
Review demand projections on an on-going basis consistent with Council’s Residential Growth Strategy
Continue to develop the wastewater network model and risk based approaches to help prioritise renewal programmes and better manage risks and costs in achieving the desired outcomes
Asset information – on-going development of asset systems and collection and analysis of data to meet all asset management needs.
Resource planning is undertaken to ensure the recruitment, retention and development of sufficient and suitably qualified staff.
Conclusion
This AMP sets out programmes for operating, maintaining, renewal and development of the Wastewater Activity over the next 30 years that will ensure the required level of service is delivered to the community, the service potential of the asset is maintained for future generations, and growth of the City is provided for.
Section 1 – Overview Asset Management Plan 2017 – Wastewater
1
1 Overview
1.1 Purpose of this Plan
This AMP is the basis for the Wastewater activity planning. The objective of asset management is to;
“Deliver the required level of service to existing and future customers in the most cost-effective way.”
In this context the specific objectives for the AMP are:
To define the services to be provided, the target service standards that Council aims to achieve, and the measures used to monitor the performance of the Wastewater activity.
To translate Council’s Strategic Vision and Goals into activity strategies and action plans that aligns to National and Regional policies and strategies. The plan identifies forward works programmes based on strategic outcomes sought and financial forecasts required to meet agreed service levels and cater for growth.
To demonstrate responsible management of the Wastewater activity infrastructure to stakeholders, ensuring that public funds are optimally applied to deliver cost effective services to meet customer expectations.
To document current asset management practices used by PNCC based on clear evidence as part of a sustainable and optimised lifecycle management strategy for the Wastewater infrastructure, and identify actions planned to enhance management performance.
To comply with the requirements of relevant legislation.
The key outputs of this AMP are input into the 2018-28 10 Year Plan process, which will be the subject of a special public consultative procedure.
The intention of this AMP is to set out how Council manages Wastewater assets and services in a way that is appropriate for a readership including elected members of the Council, executive management, interest groups, and business partners associated with the management of the Wastewater activity, along with interested members of the community. It covers the services that are provided from ownership and management of the associated assets.
This AMP covers a period of 30 years commencing 1 July 2018. Operational, maintenance, and renewal programmes for the first 3 years are generally well defined, with reasonable certainty of being implemented to budget as planned. Beyond this period, work programmes are generally based on projected trends and demands, and there is less certainty with respect to scope and timing of the projects. All expenditure forecasts are based on unit costs as at 1 July 2018.
1.2 Relationship with Other Plans
AMPs are a key component of the Council planning process, linking with the following plans and documents:
10 Year Plan (10 Year Plan): A plan required by the Local Government Act (2002) to cover a period of at least 10 years and provide a long-term focus for the decisions and activities of the Council. This AMP contains key information about the Council’s activities, assets, levels of service and cost of providing services. This AMP provides key inputs to the 2018-28 10 Year Plan.
Section 1 – Overview Asset Management Plan 2017 – Wastewater
2
Infrastructure Strategy: A local authority must, as part of its long-term plan, prepare and adopt an infrastructure strategy for a period of at least 30 consecutive financial years. The purpose of this strategy is to: identify significant infrastructure issues for the local authority over the period covered by the
strategy; and identify the principal options for managing those issues and the implications of those options.
Annual Budget: Provides the programmes and funding plan for each year of the 10 Year Plan, including reporting on variances.
District Plan: The District Plan gives effect to four land-use strategies through the City Planning Framework that covers residential, industrial, commercial and rural residential development. The strategies establish the best use of land and direct where private sector investment should occur based on several land use zones. AMPs give support to the strategies and link into the 10 Year Plan for funding of infrastructure.
Contracts and Service Level Agreements: The service levels, strategies and information requirements contained in AMPs are translated into contract specifications, internal service level agreements, and reporting requirements.
Bylaws, standards, and policies: These tools for asset creation and subsequent management are needed to support AM tactics.
Wastewater Services Assessment: This assessment, as required by Section 125 of the Local Government Act 2002, is for territorial authorities to assess the extent to which wastewater (and other water and sanitary services) collection and disposal within the district is being undertaken to adequate standards that meet the current and future community’s needs. This includes areas not currently serviced by Council infrastructure.
The Horizons Regional Council One Plan: A major focus of this plan is the quality of treated wastewater needed to ensure that the water quality of the Manawatū River is improved – particularly with regard to the discharge of nutrients during low flow periods in the river.
Figure 1 depicts the relationship between the various processes and levels of planning within the Council required to deliver on Council’s vision and goals.
Figure 1: Relationship between Council Planning Processes
TACTICAL PLANNING e.g. Asset Management Plans
Co
mm
un
ity
& S
take
ho
lde
r C
on
sult
atio
n
Mo
nit
ori
ng
& R
evie
w
COUNCIL VISION & GOALS
OPERATIONAL PLANNING e.g. Annual Budget
Annual Budget Programme
STRATEGIC PLANNING e.g. Council’s strategic direction &
10 Year Plan
Long term programmes
(5-30yrs)
Medium term programmes
(2-5yrs)
Section 1 – Overview Asset Management Plan 2017 – Wastewater
3
1.3 AMP review process
This AMP review has been a 12 month project undertaken by Council’s asset management (AM) team, led by the Special Projects Manager, covering all Palmerston North City Council (PNCC/Council) AMPs.
Linkages were established early in the process with other Council planning teams including the 2018-28 10 Year Plan team, strategic planning and corporate finance teams to ensure an integrated approach to consistency of information and assumptions across the organisation.
The stages of the review have been as follows:
Assessment of Council’s strategic direction as it has developed over the period February – August 2017 to determine the asset implications of delivering the community outcomes that the Council is seeking and developing programmes accordingly.
Level of service review – to determine what level of service the Council considered affordable and what changes are required. The Councillors were informed about current levels of service and workshopped the issues and options giving consideration to any changes in current levels of service (23 March 2017).
Strategic environment – assessment of growth and demand projections to determine future capacity requirements
Review of critical assets and key risks, assessment of critical asset resilience to natural hazards and interdependencies, review of risk management strategies, and updating of risk management programmes.
Preparation and review of AMP budget forecasts to inform the 10 Year Plan (July - Nov 2017). Internal Peer Review and finalisation of AMPs (December 17 – Jan 18). External peer review (February 2018). Formal reporting of AMPs to the Council.
Any variations between the respective AMPs and the 2018-28 10 Year Plan will be the subject of a report to Council following adoption of the 10 Year Plan in June 2018.
This AMP has been prepared as a team effort by officers dedicated to and trained in AM planning. This team has been supervised and the AMP internally reviewed by professional Council staff having over 10 years’ experience in preparing AMPs. An external peer review has been undertaken by AECOM Ltd.
1.4 Changes to AM since 2014
Asset management is a process of continuous improvement, contiguous with development of and changes to Council’s strategic environment and improved knowledge of asset condition and performance to achieve agreed levels of service.
Key changes to the AMP since 2014 are as follows:
Development of capital new and operational programmes to align with Council’s new Vision Small city benefits, Big city ambitions and associated goals and strategies and the outcomes that the Council is seeking to achieve. (Section 3)
Adjustments to the levels of service to be delivered to the community through level of service review and development of Council’s strategy plans. (Section 4)
Section 1 – Overview Asset Management Plan 2017 – Wastewater
4
Revised schedule of development works for growth for both residential and industrial growth arising out of higher population growth projections - a high growth scenario for years 1-10 and a medium growth scenario for years 11-30. This requires infrastructure for a greater number of households over 30 years than previously planned. (Section 5)
Reassessment of demand for services as a result of higher population and household projections. (Section 5)
Updating of the risk and resilience section. (Section 7) Improvements to asset management processes, particularly the introduction of the Programme
Planning and Implementation process. This is to ensure that the programmes in this plan are supported by robust information.
1.5 Navigating the AMP
This AMP comprises a series of logical steps that sequentially and collectively build the framework for sustainable asset management for the activity it serves. The plan contains three main sections. It first describes what the plan is about and the activity it relates to. The second section is about the drivers that influence and set the direction for asset management. The third section describes out the level of service and strategic outcomes are achieved through managing and developing the assets.
Section 1 – Overview Asset Management Plan 2017 – Wastewater
5
AMP at a Glance(Executive Summary)
Overview (Section 1.0)Purpose of AMP, relationship to other planning documents, AMP review processes &
navigation
The Activity (Section 2.0)Purpose, description & rational of activity, Custemers/Users, Key relationships for
management of activity, significant changes and negative effects associated with activity.
The Strategic Environment (Section 3.0)Strategic context (internal & external) to determine key outcomes sought.
Strategic assessment to identify problems and benefitrs within the overall strategic context & the outcomes desired.
Levels of Service (Section 4.0)The review process followed and the qualities of the service that Council intends to deliver to
the Community
Growth & Demand (Section 5.0)The growth and demand factors impacting on the capacity and levels of service provided by
the assets over 30 years
Assets & Lifecycle Management (Section 6.0)Plans detailing how the assets are to be managed, operated, maintained, renewed and
developed to provide the required level of service over the asset life.
Risk and Resilience (Section 7.0)Risks identified that may affect the ongoing delivery of services from Council’s infrastructure
and resilience to natural disaster
Sustainability (Section 8.0)Identification of key sustainability issues and linkage to Council’s strategies
Financial Projections (Section 9.0)Outlines the long-term (30yr) financial projections for operating, maintaining, renewing and
developing the assets. Asset valuation and reliability of estimates.
Assumptions (Section 10.0)Key assumptions used in developing asset lifecycle programmes and impact of variations from
these assumptions
Improvement Plan (Section 11.0)Initiatives to make improvements to asset management planning over the next 3 years and to
inform the next AMP review
Re
qu
ire
me
nts
Se
ttin
g
Str
ate
gic
Dir
ect
ion
Ass
et
Ma
na
ge
me
nt
an
d S
tra
teg
ic
Re
spo
nse
Wh
at
the
Pla
n is
ab
ou
tS
ett
ing
th
e s
cen
e
Figure 2: AMP Structure
Section 1 – Overview Asset Management Plan 2017 – Wastewater
6
Section 2 – The Activity Asset Management Plan 2017 – Wastewater
7
2 The Activity This section sets out the services provided by the Wastewater Activity including:
A description of the asset used to deliver the activity; The rationale for Council involvement and ownership of assets; The significant negative effects of the activity; and The significant changes in the activity since the last AMP.
2.1 Activity Description
The key function of the Wastewater Activity is to provide for the safe and reliable collection, treatment, and disposal of wastewater (sewage) from residential, industrial, and commercial properties. There are six separate public wastewater collection systems servicing different areas of Palmerston North City. All wastewater collected within the city boundary is treated at the Totara Road Wastewater Plant in Palmerston North and discharged to the Manawatū River.
The broad asset groups and their values as of June 20171 are shown in Table 1.
Table 1: Wastewater Assets Quantity by Type
Asset Component Quantity Replacement Value
Pipelines 418km 138,594,111
Manholes 5679 $30,312,864
Laterals 27,783 $68,948,126
Pump Stations 36 $6,037,242
Treatment Plants 1 $44,816,718
Oxidations Ponds 1 $1,368,890
Valves 109 $570,484
Total $290,648,435
The Wastewater activity comprises the collection of wastewater from private properties and residences, conveyance of the wastewater to a central treatment facility, either by gravity or if necessary by pumping, and treatment of the wastewater to remove harmful pollutants and pathogens before discharge to a receiving environment. A schematic layout of a typical wastewater system is shown in Figure 3 below.
1 Revaluation of Infrastructure Assets June 2017
Section 2 – The Activity Asset Management Plan 2017 – Wastewater
8
Figure 3: Schematic Layout of Wastewater System
The discharge of industrial effluents into the public wastewater system is regulated by the Trade Waste Bylaw 2015. The wastewater system is regulated by the Local Government Act 2002, Health Act 1956, and the Wastewater Bylaw 2017.
City Networks also provides advice to developers on the provision of wastewater reticulation to service new developments.
Although most of the City is urban in nature, there are adjoining rural areas where it is not usually practical to provide a reticulated wastewater service because of the inability to spread the cost of the infrastructure required (pipes, pumps etc.) across a sufficient number of properties. Reticulated wastewater systems may be provided when the land use in these areas changes and they are developed for urban housing.
The point of service for wastewater collection is generally the property boundary. The Council owns and maintains all wastewater pipelines up to and including the point of service. All wastewater drains and plumbing upstream of the point of service are owned by, and are the responsibility of, the property owner.
Sewagepipeline
Sewage treatment plant
Private serviceconnection
Sewagepipeline
Sewage treatment plant
Private serviceconnection
Section 2 – The Activity Asset Management Plan 2017 – Wastewater
9
Figure 4: Map of Wastewater Collection Areas
Section 2 – The Activity Asset Management Plan 2017 – Wastewater
10
2.1.1 Palmerston North Main Urban Area
The Palmerston North wastewater system services a population of approximately 73,662. This includes Ashhurst, Aokautere, Linton (including the Army Camp & Prison), Bunnythorpe, and Longburn. It comprises approximately 418 km of pipelines which operate mainly by gravity drainage to convey wastewater to the Totara Road wastewater treatment plant. There are 36 pumping stations in this system, which pump wastewater to higher elevations from where gravity drainage is not practical. Tertiary treated effluent is discharged to the Manawatū River in accordance with a Resource Consent issued by Horizons Regional Council.
2.1.2 Ashhurst
The Ashhurst wastewater system services a population of approximately 2,634. It comprises approximately 17 km of pipelines, which convey wastewater to the Ashhurst Oxidation Ponds. There are two pump stations in the Ashhurst system: one in Durham Street, and the other located next to the existing oxidation ponds. Wastewater from Ashhurst is partially treated in the existing oxidation ponds before it is pumped to Palmerston North by way of 9 km of 250 mm diameter rising main, where it discharges into the City’s main gravity system at Rosalie Terrace.
2.1.3 Aokautere
This system services a population of approximately 70 people. 600 metres of gravity pipelines convey wastewater to a pumping station in Peterson Road where it is pumped back up Aokautere Drive through 1360 m of 100 mm diameter rising main to where it discharges into the City’s main gravity system at Cashmere Drive.
2.1.4 Linton (Excluding Army Camp & Prison)
This system services 45 individual residential properties which are connected to the Linton Army camp, which is a privately managed system. Wastewater is conveyed to an oxidation pond owned and operated by the Ministry of Defence where it is partially treated before the effluent is pumped across the Manawatū River via a pipeline owned by the NZDF to the Totara Road Waste Water Treatment Plant (WWTP). Wastewater from Linton also includes the discharge from the Linton Army Camp and its associated residential housing area, Manawatū Prison, and New Zealand Pharmaceuticals.
2.1.5 Bunnythorpe
A separate reticulation system services the township of Bunnythorpe, which has a population of approximately 451. Wastewater from Bunnythorpe is now pumped to Palmerston North City for treatment. The Bunnythorpe wastewater system comprises of approximately 8.57 km of pipelines. There are 3 pump stations located within Bunnythorpe, with wastewater pumped to Palmerston North from the Kairanga-Bunnythorpe Road pump station.
2.1.6 Longburn
A separate reticulation system services the township of Longburn, which has a population of approximately 400 (including Longburn College Boarders). The Longburn wastewater system comprises of approximately 9.4 km of pipelines (including rising mains). Wastewater from Longburn is pumped to Palmerston North through 2 pump stations located in Reserve Road and Walkers Road via the 300 mm diameter rising main servicing the Works Road Industrial area.
Section 2 – The Activity Asset Management Plan 2017 – Wastewater
11
2.2 Activity Rationale
Adequate systems for the disposal of wastewater are a fundamental requirement for the health and general wellbeing of the community. In urban areas wastewater is most effectively disposed of by means of reticulated wastewater systems that allow the costs associated with maintaining high standards and efficient infrastructure to be spread over a wide population base, thereby keeping the costs to individual users for wastewater disposal within affordable levels. Sanitary facilities installed to good standards and connected to reticulated wastewater systems require minimal maintenance or intervention for their satisfactory on-going operation and represent a convenient and low risk means of wastewater disposal.
The importance to community wellbeing of effective public wastewater systems is recognised in the Health Act 1956, which requires Local Authorities to provide ‘sanitary works’, the definition of which includes wastewater works and includes all lands, buildings, pipes, and appliances used in connection with any such works, and provide any dwelling house with suitable appliances for the disposal of wastewater and sufficient sanitary conveniences.
The goals for the Wastewater Activity are as follows:
To ensure that all community sanitary wastes are satisfactorily collected, treated, and disposed of in order to protect the health and safety of the public, and to protect and enhance the quality of the natural environment.
To encourage the use of advanced technologies for providing higher quality, reliable, and cost effective treatment, disposal, and reuse options.
The existing wastewater system has been developed and built up over many years as a public system to serve the needs of the community in the collection, treatment and disposal of wastewater. The Local Government Act 2002 requires local government organisations which provide water services (which include wastewater services) to continue to provide these services and maintain their capability to do so.
Recent amendments to the Local Government Act have further clarified the purpose of local government, in particular:
“To meet the current and future needs of communities for good-quality local infrastructure, local public services and performance of regulatory functions in a way that is most cost-effective for households and businesses.”
The services provided by the water activity contribute to the goals adopted by Council for the City as summarised in Table 2.
Table 2: Activity Linkages to City Goals
Priority Activity Contribution
Goal 1 – An innovative and growing city
To ensure that wastewater infrastructure is in place to collect and treat wastewater in advance of new commercial, industrial and residential development.
Goal 2 – A creative and exciting city
Provide reticulated wastewater services which limit negative impacts on public recreational facilities. Effectively manage and mitigate wastewater overflows and provide early and appropriate advice to the community and residents to minimise health impacts.
Goal 3 – A connected and safe community
Ensure the wastewater network functions reliably and is able to contain, transport and treat wastewater with the minimum of risk to community health. Identify and effectively mitigate all dry weather wastewater overflows and limit wet weather overflows.
Section 2 – The Activity Asset Management Plan 2017 – Wastewater
12
Priority Activity Contribution
Goal 4 – An eco city
Reduce the environmental impact of wastewater on the Manawatu river by ensuring current treatment processes comply with resource consents and confirming the preferred option for wastewater treatment and disposal in time for preparation and lodgement of consents by June 2022. Target reductions in carbon emissions by more efficient treatment processes, energy efficient equipment and implementing food waste and organic waste to energy initiatives.
Goal 5 – A driven and enabling council
Adoption of digital transformation technology where appropriate to enable more efficient operation and provide better customer service.
The goal areas most relevant to the Wastewater activity are Goals 1 and 3. These are expanded on in Section 3, The Strategic Environment.
Customers of wastewater services are broken down as follows:
Residential customers Industrial customers Commercial customers
2.3 Key Relationships
PNCC has overall responsibility for public wastewater services in the City. This includes setting policy, service standards, ensuring the required outcomes are achieved as efficiently as possible within Council’s strategic direction, and quality assurance. In providing the wastewater service City Networks works with a number of key business partners including contractors, consulting engineers, regulators, and specialist service providers:
City Enterprises, a unit of the Council, is engaged by City Networks to provide treatment plant operation and reticulation operation, maintenance, and renewals services.
The Ministry of Health has statutory responsibility for public health issues in New Zealand including health related aspects of wastewater services.
Horizons Regional Council (the operating name of the Manawatū-Wanganui Regional Council) has an environmental, regulatory, and monitoring role under the Resource Management Act that includes the regulation of discharge of wastewater to land or receiving waters. Council currently holds consents for each wastewater treatment facility.
Water related issues are of special cultural significance to Maōri. Local iwi are formally represented by Rangitāne. Palmerston North City Council is committed to fostering the relationship with Rangitāne, and developing an active partnership into the future.
Palmerston North adjoins areas administered by Manawatū District, Horowhenua District, and Tararua District Councils. City Networks maintains relationships with wastewater staff of the other Councils through various professional organisations to facilitate the exchange of information, management practices, and to facilitate a joint approach to wastewater issues where this is beneficial.
Other stakeholders in the wastewater activity are: The Palmerston North community, including citizens, ratepayers, and individual users of the
services. Trade waste users. Rangitāne o Manawatū. Community groups. Visitors to Palmerston North.
Section 2 – The Activity Asset Management Plan 2017 – Wastewater
13
2.4 LGA Section 17A Review
Under section 17A of the Local Government Act Local Authorities are required to review the cost effectiveness of their arrangements for meeting the needs of their communities for good quality local infrastructure, public services and regulatory functions. This review requirement includes considering options for the governance, funding and delivery of infrastructure and services.
In June 2016 the Council decided to make the water service exempt from an s17A review prior to 7 August 2017. It decided that a review of this activity before this time was not an effective use of Council resources.
2.5 Significant Negative Effects of the Activity
Potential negative effects associated with the wastewater activity include:
Discharge of treated wastewater effluent from the WWTP to the Manawatū River adversely affecting river quality.
Overflows of untreated wastewater from the wastewater system to the Manawatū River adversely affecting river quality. These may result from: Overloading of the wastewater system during rainfall due to the entry of stormwater runoff
(infiltration and inflow); Structural failure of pipelines; Blockages of wastewater pipelines; or Malfunction of utility installations such as pumping stations or treatment plants.
Odours from wastewater infrastructure such as pumping stations, treatment facilities, and pipeline vents adversely affecting local residents.
The disposal of wastewater treatment by-products, such as bio-solids (stabilised solids extracted from the wastewater during the treatment process), adversely affecting the receiving environment.
All of these potential negative effects are managed as part of the day-to-day operation of the Wastewater Activity.
The quality of effluent discharged to the Manawatū River is regulated by the conditions in the resource consents for these discharges issued by Horizons Regional Council. The consent conditions ensure that negative effects associated with the discharge are managed to acceptable levels.
The Horizons Regional Council initiated a formal review of the discharge consent, with focus on the life supporting capacity of the river. This review was heard in front of four commissioners in 2014 and 2015, following submissions from both PNCC and Horizons Regional Council. The Consent Review Hearing was concluded without a decision. PNCC instead offered to apply for a new discharge Consent in 2022, some 6 years before the original date. In addition, a series of actions were agreed including
Undertake further investigations into the effects of the discharge on the Manawatū river Undertake a robust Best Practical Options review of treatment options prior to the application of
a new consent.
The entry of stormwater to the wastewater system during heavy rainfall can cause overloading of sections of the wastewater system and may lead to overflows. This situation is not confined to Palmerston North, with similar problems being experienced to varying degrees in most urban wastewater systems in New Zealand.
Section 2 – The Activity Asset Management Plan 2017 – Wastewater
14
The range of strategies adopted to overcome wet weather overloading of the wastewater system includes:
Programmes to reduce the entry of stormwater to the wastewater system in private properties (infiltration/inflow programmes).
Renewal of pipelines where there is excessive entry of stormwater and or groundwater through defects in the pipes.
Providing additional capacity in parts of the wastewater system.
There are no reported odour issues associated with the wastewater reticulation system however a small number of odour complaints are received regarding the operation of the WWTP on Totara Rd. Some of the complaints relate to composting activities at the Council composting operations, however in general the odour suppression system in place and careful management of the disposal of wastewater treatment by-products is effective.
2.6 Significant Changes to the Activity
Significant changes to the Wastewater Activity are anticipated to meet increased regulatory requirements from the Horizons Regional Council resource consent discharge conditions.
Both to address concerns around overflows from the Bunnythorpe treatment pond to the Mangaone Stream and to avoid incurring disposal charges from MDC, all Bunnythorpe wastewater flows are now pumped to the Palmerston North network as July 2016.
As outlined the most significant capital works investment will be associated with the upgrade of treatment and/or disposal to meet the requirement of a new consent when the current consent expires in 2022. A provision of some $110M has been made, however the exact level of funding will be determined by the preferred option to be selected by Council at the conclusion of the Best Practicable Options assessment currently underway.
Section 3 – Strategic Environment Asset Management Plan 2017 – Wastewater
15
3 Strategic Environment This section sets out the strategic environment within which the wastewater activity is managed under the following areas of:
Internal Strategic Context Statutory and Regulatory Requirements AM Policy and Strategy
3.1 Internal Strategic Context
3.1.1 Council Vision, Goals & Strategic Direction
The Council Vision for Palmerston North is:
“Small city benefits, Big city ambition.”
Supported by 5 strategic goals:
Goal 1: An innovative and growing city. Goal 2: A creative and exciting city. Goal 3: A connected and safe community. Goal 4: An eco-city. Goal 5: A driven and enabling council.
To achieve the vision and goals, the Council has developed a number of strategies each with specific priorities and associated strategy plans (including actions that link to specific programmes). The Plans most relevant to this AMP are highlighted in Table 3.
Table 3: Wastewater Activity contribution to City Goals
City Goals City Strategies Priorities Strategy Plans
An innovative and growing city
Economic Development Strategy
Create and enable opportunities for employment and growth
Provide the right infrastructure at the right time to enable growth Support an ‘innovative economy’ to underpin growth into the future
Transform the economy to a low carbon economy
Economic Development International Relations Carbon Emissions reduction
City Development Strategy
Create and enable opportunities for employment and growth
Provide the right infrastructure at the right time to enable growth
District plan Housing and future
development Strategic partnerships Urban design Built heritage Infrastructure Strategic Transport Parking
Section 3 – Strategic Environment Asset Management Plan 2017 – Wastewater
16
City Goals City Strategies Priorities Strategy Plans
An eco-city Eco City Strategy
Respect and enhance the mauri of the Manawatū River
Work with the community to reduce carbon emissions
Regenerate native biodiversity Invest in infrastructure that serves to protect,
enhance and preserve our environment Use our legislative powers and policies to ensure
that urban development is sustainable now and into the future
Educate the community, in particular, property owners, on the benefits of investing in sustainable building design and green buildings
Demonstrate leadership and best practice by developing and implementing an environmental sustainability plan for the Council
Biodiversity Three Waters Waste Energy Sustainable practices plan
The Council’s strategic and corporate goals represent the outcomes Council aims to achieve for the City consistent with its vision and in order to promote community well-being, both now and in the future.
Underpinning the city’s vision, goals, strategies, and plans are the following strategic themes that guide the way in which the outcomes and actions are delivered:
Smart city practices – use smart systems, processes and tools. Sustainable practices – embed sustainable design and behaviours. Iwi partnerships – work collaboratively with iwi partners. Strategic Partnerships – work collaboratively with key strategic partners.
3.1.2 Infrastructure Strategy
The Local Government Act 2002 Amendment Act 2014 introduced a requirement for Council to prepare and adopt, as part of its 10 Year Plan, an infrastructure strategy covering a 30 year planning period.
This AMP is an integral document in informing the Infrastructure Strategy. Table 4 describes the linkages between this AMP and the component parts of the Infrastructure Strategy.
Table 4: AMP Linkages to the Infrastructure Strategy
Infrastructure Strategy s.101B LGA 2002 Asset Management Plan
Paragraph No. Description Reference
2a & b Significant infrastructure issues & options Sections 4.0, 5.0, 6.0 & 9.0
3a Renewals and replacements Sections 6.0 & 9.0
3b Growth or decline Sections 5.0, 6.0 & 9.0
3c Changes to LOS Sections 4.0 and 6.0
3d Maintain or improve public health & environmental outcomes or mitigate adverse effects Sections 3.0, 4.0, 6.0, 7.0, 8.0 & 9.0
3e Resilience of infrastructure relating to natural hazards Sections 6.0, 7.0, 9.0 and 11.0
4a Estimates of capital and operating expenditure Section 9.0
4b Significant decisions about capital expenditure Sections 6.0 and 9.0
4c & d Assumptions & uncertainty Section 10.0
Section 3 – Strategic Environment Asset Management Plan 2017 – Wastewater
17
3.2 External Strategic Context
3.2.1 Horizons Regional Council One Plan
This One Plan is about how the natural and physical resources of the region are managed and sets water quality targets for major river catchments, including the Manawatū River. New consents for discharges of treated wastewater will need to meet the objectives, policies and rules of the One Plan.
Rangitāne o Manawatū, as mana whenua, are explicitly recognised in the One Plan, as they have identified the reach of the Manawatū River from upstream of the Manawatū Gorge down to the Foxton Loop, including short reaches of the Pohangina at Ashhurst and the Oroua at Rangiotu, as having a high “density of cultural and historical sites of significance including wāhi tapu and taonga”. “These cultural sites… would be negatively and potentially permanently harmed by some activities and consequently are given a high level of protection” under Policy 6-28 which states:
“Policy 6-28: Activities in sites with a Value of…Sites of Significance – Cultural…
…In sites with a Schedule AB Value of…Sites of Significance - Cultural…activities in, on, under or over the beds of rivers and lakes must be managed in a manner which:
(a) avoids adverse effects on these Values in the first instance; or
(b) for infrastructure and other resources of regional and national importance, or activities that result in an environmental benefit, remedies or mitigates those effects where it is not practicable to avoid them”
3.3 Statutory and Regulatory Requirements
3.3.1 Key Legislation
The key legislation relating to the management of wastewater supply assets are listed below.
The statutory requirements provide Council with a minimum level of service standard and have been reflected in the levels of service shown in Section 4. Council is currently complying with all legislative requirements:
Local Government Act 2002 Amendment Act 2014, which defines the purpose of local government as enabling local decision-making and action by and on behalf of communities and to meet the current and future needs of communities for good-quality local public services and performance of regulatory functions in a way that is most cost effective for households and business.
Resource Management Act 1991, promotes the sustainable management of natural and physical resources. It also requires Councils to take into account the principles of the Treaty of Waitangi in exercising functions and powers under the Act relating to the use, development and protection of natural and physical resources.
National Policy Statement for Freshwater Management 2014, Amended 2017. Sets out the objectives and policies for freshwater management under the RMA. It gives specific direction to Local Authorities with respect to Tangata whnua roles and interests.
National Environmental Standard for Sources of Human Drinking Water is intended to reduce the risk of contaminating drinking water sources such as rivers and groundwater.
Section 3 – Strategic Environment Asset Management Plan 2017 – Wastewater
18
Health and Safety at Work Act 2016, which requires the provision of safe work places for all activities by the Person conducting a Business or Undertaking (PCBU) has the Primary Duty of Care and needs to take such precautions as is reasonably practicable for the health, safety and welfare of workers and any other people at risk from any work carried out. Key requirements for local authority staff and any contractors in addition to complying with the act is the maintenance of an audit trail to demonstrate compliance with the Act.
Building Act 2004, which sets minimum standards for buildings and facilities, and requires Councils to produce Project Information Memoranda (PIM’s) and building Warrants of Fitness.
Public Works Act 1981, which prescribes processes to enable the acquisition of land for the completion of construction works by Council.
Public Bodies Contracts Act 1959, which confers on a local authority similar powers to enter contracts as enjoyed by corporate bodies or natural persons.
Construction Contracts Act 2002 sets requirements for payment provisions for construction contracts and dispute resolution.
Local Government Official Information and Meetings Act 1987 sets requirements concerning disclosure of information.
Civil Defence and Emergency Management Act 2002 provides for a coordinated approach to the planning and preparation for emergencies and for response and recovery in the event of an emergency.
Utilities Access Act 2010 requires utility operators and corridor managers to comply with a national code of practice that regulates access to transport corridors and provide for the making and administration of that code.
Health and Safety in Employment Act.
3.3.2 Local Bylaws The following Council By-laws are relevant to the management of Wastewater Activity assets: Palmerston North Trade Waste Bylaw 2015. Palmerston North Wastewater Bylaw 2017. Palmerston North Stormwater Bylaw 2015.
Regulations are in effect for controlling the quantity and composition of industrial wastewater flows to protect wastewater assets, wastewater treatment processes, and wastewater workers (Council staff and contractors). The Wastewater Bylaw is new for Palmerston North and was established to regulates and defines domestic wastewater, the point of supply, and covers matters relating to the acceptance of wastewater discharge, the process for applying for a new connection, working around buried services, and pressure sewer systems, as well as defining the wastewater service areas where connections are allowed.
3.3.3 Standards & Specifications
The standards and specifications for all works to wastewater assets reflect the best current technologies, national standards and legislative requirements. All wastewater assets are operated, maintained and built in accordance with:
PNCC Engineering Standards for Land Development. PNCC Policy for Road Openings and Reinstatement. New Zealand Building Code and Electrical Regulations. NZS 6101 'Classification of Hazardous Areas'.
Section 3 – Strategic Environment Asset Management Plan 2017 – Wastewater
19
CCTV - New Zealand Pipe Inspection Manual. Appropriate industry best practices, technologies and the most recent version of national standards
and legislative requirements. PNCC District Plan. Resource consents issued under the Resource management Act 1991. Horizons One Plan. Wastewater Bylaw 2017.
3.4 Asset Management Policy & Strategy
3.4.1 Asset Management Policy
AM Policy
Asset are managed so as to meet the asset management objectives set out below by applying the AM Strategy.
Objectives
To have a consistent approach across all asset classes within the Council. AMPs reflect the strategic direction of the Council (Including the financial strategy). To manage the assets in a sustainable manner in order to deliver the required level of service to the
present and future generations. Assets are managed cost effectively in accordance with sound risk management, environmental
management practice and statutory and regulatory requirements. That there is continual improvement of asset management practice in the organization. To have up to date AMPs that reflect a multidisciplinary approach across the organization to inform
the 10 Year Plan process. That asset management performance can be demonstrated to the Council and community. That AM Policy and Strategy is approved by Management Team and that AMPs are adopted by the
Council to inform the 10 Year Plan.
3.4.2 Asset Management Strategy
AM Strategy
This Infrastructure Strategy sets out the approach to organising and practicing infrastructure management so as to achieve the asset management objectives for the different Asset Management inputs as set out below.
Planning strategy
30 Year Infrastructure Strategy
A 30 year Infrastructure Strategy will be completed as part of the 10 Year Plan process and will reflect the Council’s vision and strategy and provide a combined view of the asset programmes that are required to achieve this. It will show a clear linkage between the strategies and the programmes required to achieve the strategies. The Strategy will reflect the decisions made by the Council through the 10Yr Plan process.
Section 3 – Strategic Environment Asset Management Plan 2017 – Wastewater
20
Asset Management Plans
AMPs will be reviewed at 3 yearly intervals to align with the 10 Year Plan planning process and cover a 30 year planning period. AMPs will reflect the strategic and financial direction of the Council and be integrated with other Council planning documents. Differences to AMP programmes and those approved in the 10 Year Plan will be reported to the Council together with the asset and service implications. There will be further development of the concept of maintaining the AMP as a ‘living document’ that more accurately reflects the current policies and decisions of the Council.
Levels of Service
A review of the Levels of Service (LoS) that is to be provided will be undertaken in conjunction with the AMP review to reflect any changes that Council may wish to make. The review will be informed by community satisfaction and submissions received over the previous 3 years and Council direction. Engagement with the community on options will be undertaken for specific significant projects as they arise in accordance with the Council’s Community Engagement Strategy. The review will inform the levels of service adopted by the Council.
Capital New Planning
Capital works planning will be based on a sound understanding of the need and timing for the asset based on demand forecasts and implementation of Council’s strategic and financial direction. Documentation will be provided for justification of each programme.
Programme estimating will incorporate full project costs to complete the asset, identify full life cycle costs, and risks associated with the programme. The need for works to accommodate growth will be reviewed on an annual basis to take into account any changes to the anticipated growth rates or other demand drivers.
Capital Renewal Planning
Renewal planning will be based on a sound understanding of the condition and performance of the asset and aim to maintain the current overall service potential of the asset. The renewal programme will also aim to smooth out where possible the financial impact from year to year.
Maintenance and Operational Planning
Maintenance and operational planning will be reviewed on an annual basis but with particular focus at the AMP review as to whether the most cost effective delivery mechanisms are in place. This will also take account of any Council direction arising out of the Local Government Act Section 17A reviews.
Service agreements with contractors will contain performance measures consistent with the AMP and Activity Key Performance Indicators (KPIs) to achieve alignment from the operational level to the 10 Year Plan KPIs.
Demand forecasts
Demand forecasts will take into account population, household and economic growth projections, social and demographic data, technological advances, and other relevant data.
Demand management
Demand management options will also be considered when planning to meet growth, and to ensure projects qualify for any external financial assistance.
Section 3 – Strategic Environment Asset Management Plan 2017 – Wastewater
21
Optimised decision making
ODM techniques will be used for decisions related to significant projects.
Risk & Resilience
Risk exposure will be managed through:
An annual review of the risk management plan and implementing risk mitigation measures where risk exposure is incompatible with corporate risk policy.
Undertaking performance and condition monitoring of critical assets.
Resilience of Council’s critical assets to natural hazards will be assessed and programmes prepared to mitigate risk to an acceptable level.
Information systems
Data collection programmes (condition, asset performance, registers, and service performance) will be closely aligned to the nature and scale of the assets and to tracking achievement of service targets.
AM system functionality will be progressively developed to meet the requirements of advanced AM planning.
Asset Revaluation
Asset revaluation will be undertaken in conjunction with City Corporate staff on a 3 yearly timeframe.
Continuous Improvement
An improvement programme will be included with each AMP review, setting out the areas of improvement required to practices, systems, processes and plans in the following 3 years with identified tasks and budgets. This will be part of the ongoing improvement programme in the City Networks Unit.
Organisational Capacity and Development
Adequate resources will be allocated to asset management to ensure that asset management practices can be undertaken to meet the requirement for robust AMPs and work programmes. AM capabilities will be developed to practice advanced asset management techniques.
Monitoring and reporting on level of service performance measures.
Those level of service measures that are adopted by the Council as KPIs will be reported through quarterly Annual Budget reports. Other LoS performance measures will be reported quarterly to the City Networks Executive Team (CNET).
Section 4 – Levels of Service Asset Management Plan 2017 – Wastewater
23
4 Levels of Service This section defines the level of service or the qualities of the service that the Council intends to deliver and the measures used to monitor this. The adopted levels of service are used to define the programmes to achieve the Council’s strategic goals and are based on user expectations and statutory requirements.
4.1 Introduction
A key objective of this AMP is to match the level of service provided by the asset with the expectations of the users of the service. This requires a clear understanding of user needs and preferences. The levels of service defined in this section will be used:
to inform users of the proposed type and level of service to be offered; as a focus for the AM strategies developed to deliver the required level of service; as a measure of the effectiveness of this AMP; to identify the costs and benefits of the services offered; and to enable users to assess the suitability, affordability, and equity of the services offered.
Levels of service for the Wastewater Activity are based on:
Strategic goals (see Section 3.1.1) - These provide guidelines for the scope of current and future services offered, the manner of service delivery, and the specific levels of service which the organisation seeks to achieve.
Statutory requirements/environmental standards (see Section 3.2.1) - Regulations, Acts, and Council Bylaws that impact on the way assets are managed (i.e. resource consents, building regulations, health and safety legislation). These requirements set the minimum level of service that must be provided.
Community engagement and feedback (see Section 4.2) - Information gained over the last 3 years on LoS from specific consultation, customer service requests, Annual Budget submissions, and community surveys.
The Department of Internal Affairs (DIA) mandatory measures were introduced in 2013 in order to establish a set of baseline data to enable performance to be measured comparatively between all Local Authorities in the country.
The adopted levels of service indicators and measures presented in Appendix C have been grouped into two categories:
Customer performance measures: These are measures of the overall activity, covering the aspects of service that are of most interest to the community and community satisfaction indicators. They include the government mandated non-financial performance measures to be included in the 2018-2028 10 Year Plan. Some of the customer performance measures presented in Section 4 are expected to be included for community consultation in the consultation document and publicly reported against in each Annual Report.
Technical performance measures: These are additional measures adopted to ensure that the customer performance measures are robustly achieved. They are used as a management tool and are measured and reported internally.
Section 4 – Levels of Service Asset Management Plan 2017 – Wastewater
24
4.2 Community Input & Decision Making Process
The levels of service upon which this plan is based have been derived from an on-going process of community consultation and consideration of levels of service options by the Council over a significant period of time.
In 2005, an extensive level of service review was undertaken, which engaged with a broad cross-section of the community to understand how well existing services were meeting user needs, and what improvements were desired for the future. Specifically, the review set out to ascertain views on:
The current levels of service provided by the Council. The desired future levels of service. Aspects of the services by which the quality of the services can be assessed.
At that time, a greater user focus was introduced to the measures. This was reflected by having statements of the service provided to each of the key user groups and performance measures that reflected the user view of the LoS provided.
Subsequently LoS reviews have been undertaken for each AMP review, in which information about LoS received from the community through local, Communitrak surveys, service requests, and Annual Budget submissions, has been presented to the Council in order to inform any changes that it may wish to make to the LoS delivered to the community. Generally, only minor adjustments have been made since 2005.
For this AMP, LoS workshops were held with Councillors over 23-24 March 2017. Information about the current LoS together with community feedback was presented to the Councillors. Councillors were asked to:
Consider whether the current LoS was about right and what changes, if any, were required. Give direction on some specific LoS issues important to the activity.
Generally, the Councillors considered the LoS to be about right. However, the following LoS matters were raised during the workshop and are taken account of in this AMP, as indicated in Table 5.
Section 4 – Levels of Service Asset Management Plan 2017 – Wastewater
25
Table 5: Matters Raised at Councilor LoS Workshop
Matters raised at Councilor LoS workshops 23/24 March 2017 How these are included in this AMP
Increased focus on behaviour change and promotion of sustainable outcomes across all three waters
Additional funding sought to support behaviour change initiatives as part of a three water new operating programme.
Impact of inflow and infiltration on the wastewater network Additional operational programme funding sought for a dedicated programme of work focusing on inflow and infiltration reduction.
Optimised pipeline renewal strategies Enhanced investment in CCTV inspection to determine asset condition and remaining useful life. Use of lining to improve wastewater main life at a significantly lower cost than complete replacement.
As part of the development of Council’s strategic direction a number of Strategy Plans were developed during July and August 2017 (see Section 3). Some of the actions set out in these Strategy Plans have level of service implications for this AMP. These are shown in Table 6.
Table 6: LoS Actions from Strategy Plans
LoS actions arising from Council Strategy Plans July – August 2017
How these are included in this AMP
Reduction of Rainfall induced infiltration Specific additional funding inflow and infiltration operational programme.
Increased investment in pipeline renewals Request for a staged increase in the renewals budget during the first three years of the AMP. Continue to increase the use of relining options to increase the total length of sewer relined per annum.
Reduce Overflow risks and frequency within Network
Specific renewal programmes targeting increased capacity in the network to limit the risk of overflows. Specific focus on looking to identify overflow locations within the network and establish monitoring if possible to measure frequency and volumes if they cannot be eliminated.
4.3 Communication of Levels of Service & Performance Measures Council’s adopted LoS and KPIs will be publicly communicated through the 2018-28 10 Year Plan consultation document.
4.4 Current and Future Levels of Service & Performance Measures
Council’s adopted LoS and KPIs will be publicly communicated through the 2018-28 10 Year Plan consultation document.
Users of wastewater services have been divided between domestic users, commercial users, and industrial users. The services provided for each are set out in Table 7 below.
4.4.1 Key Performance Indicators
Target levels of service for the wastewater activity are shown in Table 7. Performance measures identified as “new” are as a result of mandatory non-financial performance measures specified by the Secretary for Local Government in accordance with Section 261B of the Local Government Act 2002. The new mandatory measures are required to be incorporated in the Council’s 2018-2028 10 Year Plan, and therefore will be reported against in Council’s 2017/18 Annual Report.
Sect
ion
4 –
Leve
ls o
f Ser
vice
As
set M
anag
emen
t Pla
n 20
17 –
Was
tew
ater
27
Tabl
e 7:
Cus
tom
er L
evel
of S
ervi
ce, P
erfo
rman
ce M
easu
res
& T
arge
ts
Key
Serv
ice
Crite
ria
Stak
ehol
ders
and
U
ser G
roup
s
Cus
tom
er L
evel
of
Serv
ice
Cus
tom
er P
erfo
rman
ce
Mea
sure
C
urre
nt
Perf
orm
ance
201
6-17
Perf
orm
ance
Tar
gets
2018
/19
2019
/20
2020
/21
2021
~/22
Qua
lity
and
Hea
lth
All r
esid
ents
and
us
ers.
M
idC
entra
l Hea
lth
The
Cou
ncil
prov
ides
a
safe
(i.e
. no
risk
to p
ublic
he
alth
) was
tew
ater
co
llect
ion
serv
ice.
G
oal 3
G
oal 4
Res
iden
ts a
re s
atis
fied
with
the
qual
ity o
f C
ounc
il’s w
aste
wat
er
serv
ices
.
95%
95
%
95%
95
%
95%
Rel
iabi
lity
All u
sers
Th
e C
ounc
il pr
ovid
es a
re
liabl
e w
aste
wat
er
colle
ctio
n se
rvic
e.
Goa
l 3
Goa
l 5
Odo
ur c
ompl
aint
s pe
r 1,
000
conn
ectio
ns p
er
year
.2
0.39
(1
1 in
tota
l) 1
(28
per y
ear)
1 (2
8 pe
r yea
r) 1
(28
per y
ear)
1 (2
8 pe
r yea
r)
Faul
t com
plai
nts
per 1
000
conn
ectio
ns p
er y
ear.
2.
6 (7
3 in
tota
l)
3 (8
4 pe
r yea
r) 3
(84
per y
ear)
3 (8
4 pe
r yea
r) 1
(84
per y
ear)
Bloc
kage
com
plai
nts
per
1,00
0 co
nnec
tions
per
ye
ar.
0.58
(1
9 to
tal)
1
(28
per
year
))
1 (2
8 pe
r yea
r) 1
(28
per y
ear)
1 (2
8 pe
r yea
r)
Num
ber o
f com
plai
nts
abou
t the
Cou
ncil’s
re
spon
se to
issu
es w
ith
the
was
tew
ater
sys
tem
per
1,
000
conn
ectio
ns p
er
year
0.1
(3 in
tota
l) 1
(28
per y
ear)
1 (2
8 pe
r yea
r) 1
(28
per y
ear)
1 (2
8 pe
r yea
r)
The
Cou
ncil
prov
ides
a
relia
ble
was
tew
ater
co
llect
ion
serv
ice.
G
oal 2
G
oal 3
G
oal 4
The
num
ber o
f dry
w
eath
er w
aste
wat
er
over
flow
s fro
m th
e C
ounc
il’s s
ewer
age
syst
ems
per 1
,000
co
nnec
tions
per
yea
r.3
1.1
38
due
to lo
calis
ed
bloc
kage
s
1 (2
8 pe
r yea
r) 1
(28
per y
ear)
1 (2
8 pe
r yea
r) 1
(28
per y
ear)
The
Cou
ncil
was
tew
ater
sy
stem
is d
esig
ned
to
adeq
uate
sta
ndar
ds a
nd is
op
erat
ed e
ffect
ivel
y G
oal 4
G
oal 5
Med
ian
resp
onse
tim
e fo
r at
tend
ing
to o
verfl
ows
resu
lting
from
blo
ckag
es
or o
ther
faul
ts.
0.4h
rs
<1.5
hr
<1.5
hr
<1.5
hr
<1.5
hr
2 M
anda
tory
mea
sure
from
the
Dep
artm
ent o
f Int
erna
l Affa
irs
3 M
anda
tory
mea
sure
from
the
Dep
artm
ent o
f Int
erna
l Affa
irs
Sect
ion
4 –
Leve
ls o
f Ser
vice
As
set M
anag
emen
t Pla
n 20
17 –
Was
tew
ater
28 Ke
y Se
rvic
e Cr
iteria
St
akeh
olde
rs a
nd
Use
r Gro
ups
C
usto
mer
Lev
el o
f Se
rvic
e C
usto
mer
Per
form
ance
M
easu
re
Cur
rent
Pe
rfor
man
ce 2
016-
17
Perf
orm
ance
Tar
gets
2018
/19
2019
/20
2020
/21
2021
~/22
Res
pons
iven
ess
All u
sers
Th
e C
ounc
il re
spon
ds to
re
ques
ts fo
r ser
vice
in
rela
tion
to o
verfl
ows,
bl
ocka
ges
and
faul
ts in
a
prom
pt a
nd e
ffici
ent w
ay
Goa
l 4
Goa
l 5
Med
ian
resp
onse
tim
e fo
r re
solu
tion
of o
verfl
ows
resu
lting
from
blo
ckag
es
or o
ther
faul
ts.
2.3h
rs
<8hr
(9
.5hr
tota
l) <8
hr
(9.5
hr to
tal)
<8hr
(9
.5hr
tota
l) <8
hr
(9.5
hr to
tal)
Acce
ssib
ility
Res
iden
tial a
nd
com
mer
cial
pro
perty
ow
ners
The
Cou
ncil
prov
ides
w
aste
wat
er s
ervi
ces
to
resi
dent
ial a
nd c
omm
erci
al
area
s of
the
City
G
oal 1
G
oal 5
Prop
ertie
s (w
ithin
the
was
tew
ater
ser
vice
s ar
ea)
are
able
to c
onne
ct to
the
was
tew
ater
ser
vice
.
100%
99
%
99%
99
%
99%
Sust
aina
bilit
y Al
l res
iden
ts.
Hor
izon
s R
egio
nal
Cou
ncil.
R
angi
tāne
M
anaw
atū
Riv
er
Lead
ers
Acco
rd
The
Cou
ncil
disp
oses
of
was
tew
ater
to
envi
ronm
enta
lly
acce
ptab
le s
tand
ards
G
oal 3
G
oal 4
Num
ber o
f aba
tem
ent
notic
es.
No
non-
com
plia
nce
notic
es re
ceiv
ed
0 0
0 0
Sust
aina
bilit
y (C
ontin
ued)
Al
l res
iden
ts.
Hor
izon
s R
egio
nal
Cou
ncil.
R
angi
tāne
M
anaw
atū
Riv
er
Lead
ers
Acco
rd
The
Cou
ncil
disp
oses
of
was
tew
ater
to
envi
ronm
enta
lly
acce
ptab
le s
tand
ards
G
oal 3
G
oal 4
Num
ber o
f inf
ringe
men
t no
tices
. 4 0
0
0 0
0
Num
ber o
f enf
orce
men
t or
ders
. 0
0
0 0
0
Num
ber o
f con
vict
ions
re
ceiv
ed b
y th
e C
ounc
il in
re
latio
n to
reso
urce
co
nsen
ts.
0
0 0
0 0
A 30
-yea
r as
set
man
agem
ent p
lan
is in
pl
ace
for t
he w
aste
wat
er
activ
ity
A 30
yea
r ass
et
man
agem
ent p
lan
prep
ared
, pee
r re
view
ed a
nd
adop
ted
in
Sept
embe
r 201
8
AMP
in
plac
e (k
ey
proj
ects
fro
m A
MP
will
be
outli
ned)
AMP
in
plac
e (k
ey
proj
ects
fro
m A
MP
will
be
outli
ned)
AMP
revi
ewed
(k
ey p
roje
cts
from
AM
P w
ill be
ou
tline
d)
AMP
in p
lace
and
re
view
ed 3
-yea
rly
with
inde
pend
ent
peer
revi
ew (k
ey
proj
ects
from
AM
P w
ill be
out
lined
)
Fina
ncia
l M
anag
emen
t Al
l was
tew
ater
ra
tepa
yers
Th
e C
ounc
il m
anag
es it
s w
aste
wat
er a
ctiv
ity in
a
Was
tew
ater
rate
s ar
e le
ss
than
the
aver
age
of th
e Ac
hiev
ed
Targ
et ra
te $
246
100%
10
0%
100%
10
0%
4 M
anda
tory
mea
sure
from
the
Dep
artm
ent o
f Int
erna
l Affa
irs
Sect
ion
4 –
Leve
ls o
f Ser
vice
As
set M
anag
emen
t Pla
n 20
17 –
Was
tew
ater
29
Key
Serv
ice
Crite
ria
Stak
ehol
ders
and
U
ser G
roup
s
Cus
tom
er L
evel
of
Serv
ice
Cus
tom
er P
erfo
rman
ce
Mea
sure
C
urre
nt
Perf
orm
ance
201
6-17
Perf
orm
ance
Tar
gets
2018
/19
2019
/20
2020
/21
2021
~/22
fin
anci
ally
sus
tain
able
way
G
oal 1
G
oal 5
natio
nal p
eer g
roup
. co
mpa
red
to
natio
nal a
vera
ge
arou
nd $
400
The
Cou
ncil
mai
ntai
ns
and
deve
lops
was
tew
ater
se
rvic
es to
mee
t cur
rent
an
d fu
ture
nee
ds
Goa
l 1
Goa
l 5
Was
tew
ater
Cap
ital
prog
ram
mes
are
del
iver
ed
ahea
d of
dev
elop
men
t de
man
d
Achi
eved
. N
o de
velo
pmen
ts
dela
yed
by la
ck o
f w
aste
wat
er
infra
stru
ctur
e
Achi
eved
Ac
hiev
ed
Achi
eved
Ac
hiev
ed
The
Cou
ncil
man
ages
its
was
tew
ater
act
ivity
in a
fin
anci
ally
sus
tain
able
way
G
oal 5
Was
tew
ater
Ope
ratio
nal
prog
ram
me
is p
rovi
ded
with
in b
udge
t
Achi
eved
if B
PO
Proj
ect E
xclu
ded
Achi
eved
Ac
hiev
ed
Achi
eved
Ac
hiev
ed
Not
e: N
umbe
r of p
rope
rties
ass
umed
to b
e 28
,000
Goa
l 1 –
Ann
inno
vativ
e an
d gr
owin
g ci
ty:
Goa
l 2 –
A c
reat
ive
and
exci
ting
city
: G
oal 3
– A
con
nect
ive
and
safe
com
mun
ity: G
oal 4
– A
n ec
o-ci
ty: G
oal 5
– A
driv
en a
nd e
nabl
ing
Cou
ncil.
Section 4 – Levels of Service Asset Management Plan 2017 – Wastewater
31
4.4.2 Future Changes to Levels of Service
The anticipated changes to the current levels of service over the next thirty years are:
Table 8: Future Changes to LoS
Future Changes to Current Level of Service and Impact on the Community and Costs
Proposed Changes Community Impact Cost Impact
Requirement for the use of pressure sewer systems in designated growth areas
Localised impact Low
Increased standard of WW treatment to meet new consent requirements
All users of public wastewater High
In the next twenty years, Council anticipates changes to the level of service in the following areas:
Changes to resource consent requirements will necessitate improvements to the wastewater treatment systems to improve the quality of the wastewater effluent discharge.
In renewing critical assets, consideration will be given to increasing capacity, or providing duplication of the assets, to improve security of the wastewater collection system.
Designation of specific growth areas within the city North East Industrial Area and City West Residential zone as pressure sewer areas both to limit additional wastewater flows, enable cost effective service provision and provide greater resilience in liquefaction prone areas i.e. City West.
These changes to levels of service have been allowed for in management of the wastewater assets. Capital development programmes to meet projected changes in levels of service are set out and discussed in Section 6.
4.4.3 Service Level Gaps
Generally, the expected level of service is being provided, however, there are a number of areas where the performance of the existing assets needs to be improved and the level of service extended:
Stormwater infiltration and inflow. (Prog 1401 - City Wide Infiltration and Inflow Investigations) Capacity constraints in trunk main network. (Prog 452 – Tremaine / Featherston Trunk Main
Upgrade and Prog 660 – Ferguson Street Trunk Main Upgrade)
Key initiatives proposed to mitigate the negative impacts of the above effects include:
Targeting wastewater pipe renewals in the catchments with the highest peak wet weather flows (Prog 54 – City Wide – Wastewater Pipe Renewal)
Implementing an operational programme to support active CCTV and smoke testing with property level enforcement of improvements to exclude stormwater from the network (Prog 1401 City Wide Infiltration and Inflow Investigations)
Implementation of networked pressure sewer systems in City West and North East Industrial Zone to limit flows, provide storage and exclude stormwater infiltration and inflow (Prog 210 – Urban Growth – Installation of Wastewater Systems for NEIZ and Prog 1055 – Urban Growth City West – Installation of Wastewater Systems)
Section 5 – Growth and Demand Asset Management Plan 2017 – Wastewater
32
The AMP has been prepared on the basis of wastewater collection provision to the area broadly corresponding to the residential and commercial / industrial areas shown in the current District Plan, and service areas outlined in the Wastewater Bylaw 2016.
Generally, the expected level of service is being provided however, there are some areas where the performance of the existing assets will need to be improved to meet the current level of service.
Capital development programs to achieve this, including the associated cost estimates, are set out and discussed in Section 6.
Section 5 – Growth and Demand Asset Management Plan 2017 – Wastewater
33
5 Growth and Demand This section sets out the factors impacting on the management and development of the assets to meet the requirements of growth and other demands place on the wastewater assets as follows:
Future demand drivers; Growth projections; Growth trends; Land-use strategies (residential, industrial, retail and rural-residential); Consumption and use patterns; Demand management strategies; and Climate change impacts on demand.
5.1 Future Demand Drivers
The future demand for reticulated wastewater services in Palmerston North will be driven by:
Residential and, industrial growth in the city. Changes in water consumption and usage patterns. Most water supplied for domestic, commercial,
and industrial purposes is subsequently discharged into the wastewater system. Greater uptake of Low Pressure Sewer particularly in the pressure sewer designated areas. Changes in Council policy with regard to rural residential properties. The extent of stormwater entry to the wastewater system (infiltration and inflow). Future demand for treatment of wastewater driven by technology changes. Regional Council One Plan Standards Climate change.
5.2 Growth Projections
Palmerston North is growing, and the Council has strong aspirations to accelerate growth and prosperity for the city. Council’s strategic priorities are set out in Council’s City Development Strategy, which drives the projects and programmes that the Council intends to implement.
For planning purposes, the Council has decided to assume high growth projections for years 1-10, and a medium growth projection for years 11-30. This is significantly greater than was assumed for the 2014 AMP, which was based on Statistics New Zealand medium growth projections adjusted for the local Palmerston North situation.
The high growth projections for the first ten years gives more weight to the average annual gain from net migration and assumes a general long-term upward trend in inward migration than is accounted for in the Statistics NZ projections. The projections being used by the Council for the first 10 years are similar to the Statistics NZ high growth projections.
5.2.1 Population Growth
The latest population projections for Palmerston North through to 2043 were published by Statistics NZ in December 2016. These suggest a declining rate of population growth over the projection period,
Section 5 – Growth and Demand Asset Management Plan 2017 – Wastewater
34
with a population projection of 102,4005 in 2048 under the medium growth projection. However, because of the high recent rates of inward migration, Council is adopting a higher population projection than the Statistics NZ medium growth projections in the first 10 years. The projection for five year periods through to 2048 is depicted in Table 9.
Table 9: Population Projection for Palmerston North
Population projection for Palmerston North (September 2017)
Average annual change
Period ended Population count Number of people
Rate of change (%)
2013 83,500
2018 88,700 1,040 1.2%
2023 93,700 1,000 1.1%
2028 98,100 880 0.9%
2033 100,704 521 0.5%
2038 102,890 437 0.4%
2043 104,869 396 0.4%
2048 1 106,639 354 0.3%
10-year projection 2018 - 2028 940 1.0%
20-year projection 2018 - 2038 710 0.7%
30-year projection 2018 - 2048 598 0.6%
5.2.2 National Policy Statement – Urban Development Capacity
The National Policy Statement – Urban Development Capacity (NPS-UDC) requires that the Council has 3 years supply of land ready to be developed with existing infrastructure (short term). It must also have 10 years of land zoned with infrastructure in its 10 Year Plan (medium term) and 30 years of land identified for growth with identified infrastructure in its 30 year Infrastructure Strategy (long term).
It must also provide an additional margin of land and infrastructure over and above the projected demand of at least 20% in the short and medium term and 15% in the long term. For planning purposes, these additional margins have been added into the additional household numbers in Table 10. It is assumed that by adopting the high growth scenario for 2018-2028, the additional 20% capacity is provided for. The 20% margin has been added to the 2028-2038 period, and a 15% margin to the 2038-2048 period.
5.2.3 Household Growth
The most recent household projections were published by Statistics NZ in December 2015 and are to 2038. An update to these projections is due to be published in December 2017. Council estimates have been made for changes in the period 2038 and 2048. Projected average annual household growth is not expected to slow to the same extend as the population growth rate because the average size of households is expected to reduce, primarily due to the aging population and an increase in the number of single person households. The numbers of households shown in Table 10 also include the additional margin required for land development in the NPS-UDC, and allow the numbers to be reconciled with the capacity being planned for in growth areas.
5 Based on Statistics NZ 2016 population projection 2013-2043 with estimated projection between 2043 & 2048
Section 5 – Growth and Demand Asset Management Plan 2017 – Wastewater
35
Table 10: Household Projection for Palmerston North
Households projection for Palmerston North (September 2017)
Average annual change
Period ended Households Number of households
Rate of change (%)
2013 31,500
2018 33,000 300 0.9%
2023 35,300 460 1.4%
2028 37,600 460 1.3%
2033 39,198 320 0.8%
2038 40,551 270 0.7%
2043 1 41,611 212 0.5%
2048 1 42,436 165 0.4%
10-year projection 2018 - 2028 460 1.3%
20-year projection 2018 - 2038 378 1.0%
30-year projection 2018 - 2048 315 0.8%
5.2.4 Residential Development Type
Housing preference trends have changed over time since Council began reporting on residential growth in 2004. In 2004 greenfield development made up 61% of development, infill was 27% and rural residential was 12%. Based on recent housing preference trends and experience of preferences during times of high growth distribution of dwelling types is based on the following. The table household numbers include the margin for the requirements of the NPS-UDC.
Table 11: Residential Development Type
Period Household per
annum Greenfield Infill Rural Total
2018 - 2028 460 55% 33% 12% 4,600
2028 - 2038 295 50% 38% 12% 2,950
2038 - 2048 222 50% 38% 12% 1,890
9,440
5.3 Residential Growth Strategy
The Residential Growth Strategy is outlined within the Council’s City Development Strategy.
Council’s main role is to make sure land and infrastructure are available to accommodate growth and provide market choice, while responding to changing demographics. The private sector provides new housing in Palmerston North. Council will work closely with developers to co-create new housing opportunities, such as the proposed Hokowhitu Residential Area at Centennial Drive.
The District Plan has been changed to provide more housing choices. Over the past 20 years, the main forms of housing development have been greenfield, infill subdivision, and lifestyle blocks. Greenfield housing typically occurs at the edge of the city on large sections, with recent development at Kelvin Grove and Aokautere, for example. Infill housing creates new smaller sections among
Section 5 – Growth and Demand Asset Management Plan 2017 – Wastewater
36
existing housing, with recent development in Hokowhitu, and the central city and hospital areas. Lifestyle blocks provide a housing choice in rural areas, with recent development on the foothills of the Tararua Ranges and elevated land north-east of the city.
Other housing choices now allowed under the District Plan include multi-unit developments and minor dwellings. Multi-unit developments are encouraged close to the city and suburban centres, where there is ready pedestrian access to services and facilities. Minor dwellings are aimed at meeting the demand for small, good quality, and affordable rental accommodation.
The planning framework enables apartments in or near the city centre, including as part of a mixed-use development. Council will actively identify opportunities and reduce barriers to city centre living and brownfield development, including transitioning Roxburgh Crescent from industrial to residential.
The demand for infill housing is expected to continue. Lifestyle blocks are directed away from productive land and need to have their own infrastructure. Council wants land for new greenfield housing at Whakarongo brought to the market quickly. PNCC will work closely with landowners and promote Council-owned land at Whakarongo to help meet housing demand.
To release pressure and meet updated growth projections, land at City West identified for medium to long-term greenfield housing will need to be released earlier. The most suitable land for early release is the area bound by the Mangaone Stream, Te Wanaka Road, and Pioneer Highway (the Racecourse land), which will need to be rezoned. The interests of private developers at the outer edge of City West could affect the cost-effective and efficient provision of network infrastructure. Council needs to work with the major landowner in this area to better understand the infrastructure options and timing of the rezoning.
Substantial greenfield housing capacity remains at Aokautere, but plans for developing the remaining residential land are unclear. Council will develop a structure plan with the major landowners to guide future development. There is a need to connect the end of Pacific Drive with existing roads in the Turitea Valley. As well as the Hokowhitu Residential Area, Council will work with landowners at Napier Road and Flygers Line, where small greenfield additions can be made without the need for substantial new infrastructure. A revised plan is needed to develop affordable and first homes at Ashhurst, taking into account detailed flood investigations of land north-west of the village.
The growth areas identified with assumed timescale for greenfield development are shown in Table 12. This shows how the projected demands on greenfield development will be met in the short, medium, and long term. Table 12 also shows the number of lots expected to be provided in each area. The locations are shown spatially on Figure 5.
Table 12: The staging and timing of residential greenfield areas
Greenfield Development Areas
Location Lots Years 1-5 Years 6-10 Years 11-15 Years 16-20 Years 21-30
Zoned Land
Aokautere 759
Ashhurst 88
Kelvin Grove 264
Whakarongo 500
Short to Medium Term Rezoning
Hokowhitu 130
Flygers Line 150
Section 5 – Growth and Demand Asset Management Plan 2017 – Wastewater
37
Greenfield Development Areas
Location Lots Years 1-5 Years 6-10 Years 11-15 Years 16-20 Years 21-30
Napier Road 50
Ashhurst Future 250
Racecourse 220
Aokautere Extensions 400
Pioneer City West 800
Medium to Long Term Rezoning
City West (less Racecourse & Pioneer City West)
1680
The location of these areas is shown on Figure 5.
Section 5 – Growth and Demand Asset Management Plan 2017 – Wastewater
38
Figure 5: Map showing location of proposed residential development
Section 5 – Growth and Demand Asset Management Plan 2017 – Wastewater
39
5.4 Industrial Growth Strategy
The strategy prioritises industrial growth:
In the short to medium term at the North East Industrial Zone (NEIZ), and the recently rezoned Extension Area for large floor plate transport, warehousing, and logistics activities.
Longburn is viewed as a suitable location for wet industry.
North East Industrial Zone
The NEIZ (86 ha) was rezoned in 2004. As at March 2017, 46 ha is developed or purchased for development and not available to the market. Since 2004 the annual uptake of land at the NEIZ is approximately 3.5 ha. It is anticipated that the annual uptake of land in the NEIZ will exceed 3.5 ha in the next 3 years.
NEIZ Extension Area
The 126 ha NEIZ Extension will be sufficient to meet the growth of large floor plate industrial activity over the next 20 to 30 years. Forecasting the market’s timing around sizable investment decisions for large format transport and logistics activity is problematic. Particularly when the nature of investment is lumpy and Council is seeking to forecast the investment profile over a 20 to 30 year time-period.
Infrastructure Roll-Out and Staging
For the purposes of infrastructure roll-out, Figure 6 shows the expected progress of development in the Extension Area. From Council’s perspective, it would be more cost effective to start providing infrastructure in the area shown in Stage 1. It is envisaged the land fronting the Roberts and Richardson’s Line corner / intersection will first to be developed.
Figure 6: Map of NEIZ Infrastructure Roll Out
Section 5 – Growth and Demand Asset Management Plan 2017 – Wastewater
40
Longburn
Longburn remains the preferred option for the development of wet industry given its connection and proximity to the wastewater treatment plant. Council’s infrastructure funding priorities for industrial growth in the short to medium term remain at the NEIZ and Extension Area.
Figure 7 shows the extent of the existing industrial zone at Longburn, which comprises approximately 42 ha of which some 35 ha has yet to be developed or remediated to enable development to occur.
Longburn - Sub-Optimal Infrastructure and Pressure to Rezone Additional Industrial Land
Council is coming under pressure to rezone additional land in the Works Road area of Longburn. Part of the existing Works Road industrial area is serviced by private infrastructure that does not meet Council’s engineering standards and Council is unwilling to approve rezoning of additional industrial land that is reliant on sub-optimal private infrastructure.
Figure 7: Map of Existing Industrial Zone at Longburn
Braeburn Industrial Area
Plan Change 15F rezoned a 33 ha extension to the existing Longburn Dairy Manufacturing Site (LDMS) in 2016. The rezoned land is identified as the Braeburn Industrial Area (BIA).
The purpose of the BIA is to primarily provide for dairy related industrial activities to support the ongoing operational and growth needs of Fonterra’s existing LDMS. It is envisaged the BIA will remain in the single ownership of Fonterra and is not for the purpose of meeting the wider industrial land needs of the City.
5.5 Office and Retailing (Commercial) Land Use Strategy
The Council’s centres based strategy seeks to keep commercial activity centred in the core of the city and to avoid the dispersion of this activity to the periphery of the urban area – particularly in the city’s Industrial Zones. This strategy is given effect to through the District Plan hierarchy of business zones as follows:
Section 5 – Growth and Demand Asset Management Plan 2017 – Wastewater
41
Inner Business Zone (IBZ). Outer Business Zone (OBZ). Fringe Business Zone (FBZ). Local Business Zone (LBZ).
The IBZ is the zone where planning for infrastructure is most critical. The IBZ seeks to provide a high amenity, connected, and pedestrian focused city centre that meets the business, social and cultural needs of the community. IBZ development looks to leverage of public investment and in most cases will utilise public on-street parking.
City Centre Streetscape Plan (CCSP) – Any planned works in the IBZ need to align with the outcomes sought by the CCSP. The Plan sets out the future design direction for the streets and spaces in the city centre. The CCSP is guided by a number of Council strategies, including the Urban Design Strategy, the City Centre Framework, and the Street Design Manual.
Importantly, the scope of the CCSP extends to streetscape upgrades including carriageway, parking, footpaths, hard and soft landscape, as well as Palmerston North's urban and inter-regional bus terminals. To achieve the outcomes sought by the CCSP any infrastructure project will need to be informed by a multi-disciplinary team working in collaboration.
OBZ development is more self-sufficient than IBZ development and is required to provide on-site parking. FBZ development is large format retailing and is also required to provide on-site parking. LBZ development provides local amenities and is expected to provide on-site parking.
All business development other than some LBZ development looks to leverage of existing infrastructure as it is effectively a form of brownfield development.
Figure 8: Map of Spatial Extent of the Business Zones
5.6 Rural Residential Strategy
The District Plan discourages lifestyle blocks and further fragmentation of productive farmland. This land is a scarce resource and represents a significant economic opportunity for future generations, as identified in the regional growth study. It is also a valuable resource for sustainable local food
Section 5 – Growth and Demand Asset Management Plan 2017 – Wastewater
42
production. Substantial capacity for lifestyle blocks is provided on the foothills of the Tararua ranges to ensure they remain a legitimate housing choice in the City.
The provision of urban services, in particular reticulated services, is discouraged in rural areas. The provision of reticulated services in rural areas is an inefficient form of infrastructure investment. It also blurs the lines between rural and urban development and leads to confusion about future development opportunities. Many landowners see the provision of urban services as legitimising further intensification while others see it is undermining the specific rural amenity they sought out. Careful implementation of the new District Plan rural subdivision provisions is essential.
5.7 Other Demand / Consumption Projections / Patterns
5.7.1 Wastewater Collection Services Demand/Wastewater Production Trends
The demand for wastewater collection services is dependent upon the volumes of wastewater produced and the extent of the collection service.
5.7.2 Changes to Water Use Pattern
With the exception of water used for irrigation and unaccounted for water, most water supplied by the Palmerston North City water supply system is subsequently discharged into the wastewater reticulation. Changes in water consumption patterns are therefore likely to be reflected in corresponding changes in discharges to the wastewater system.
Domestic Water Demand
Domestic consumption trends are surveyed from a sample of metered properties that are manually read every two months.
Figure 9 shows the previous five years of demand in terms of average daily demand per property for 51 properties. Whilst this includes irrigation and consumptive water use and is a small sample set it still provides some indication of domestic demand trends. The survey set has recently been increased to some 94 properties in order to better represent domestic demand.
Figure 9 shows the range in water use for each property, including the median and 25th to 75th percentile band. The error bars indicate the properties with the minimum and maximum water demand. Increases in surveyed domestic consumption in the last two years correlate to periods of severe droughts. It appears that peoples’ behaviour responded to the drought in 2013/14 as water restrictions did not have to be instigated until very late in the drought.
Section 5 – Growth and Demand Asset Management Plan 2017 – Wastewater
43
Figure 9: Average Daily Demand of Metered Properties
Also plotted in Figure 9 is the One Plan’s allocation for total domestic use, which equates to 753 L/property/day (derived from an allocation of 300 L/person/day and the average occupancy rate from the 2013 census). The current domestic water use is well within the allocation under the One Plan’s Regional Policy Statement.
Non-Domestic Water Consumption
The majority of significant non-domestic (industrial and commercial) water supply users are metered and charged per cubic metre of water used.
Figure 10: Historical Metered Non-Domestic Water Demand
0
500
1000
1500
2000
2500
3000
3500
40000
500
1000
1500
2000
2500
3000
3500
4000
2009/10 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17
Annual Rainfall
[mm
/yr]
Aver
age
Dai
ly D
eman
d [L
/pro
p/da
y]
25%ile to 75%ile Median Annual Rainfall
0
500
1,000
1,500
2,000
2,500
2003
/04
2004
/05
2005
/06
2006
/07
2007
/08
2008
/09
2009
/10
2010
/11
2011
/12
2012
/13
2013
/14
Annu
al M
eter
ed W
ater
Dem
and
[ML/
yr]
Metered Commercial & Industrial Customers City Council Parks & Facilities
Section 5 – Growth and Demand Asset Management Plan 2017 – Wastewater
44
As shown in Figure 10, the amount of water used by these customers varies greatly from year to year and can partly be attributed to:
Seasonal variation for users that have significant irrigation needs; The economic climate, as seen in the drop around 2008; Several of the top customers moving to new premises; and Improvements in the way the City Council uses water in its parks and facilities.
It is difficult to predict the nature of these customers in the future. For this reason, it is assumed that the future makeup will be similar to the 2016/17 demand summarised in Figure 11 below. The designation of the North East Industrial Zone as a pressure sewer area is designed both to restrict the type of development which can occur but also match wastewater services to the low wastewater flows from the predominantly warehousing and logistics type businesses which have been developing in this area. The change will significantly reduce the wastewater design capacity which must be allowed and help to defer any requirement to upgrade the western trunk sewer which serves that area.
Figure 11: Breakdown of Average Daily Water Consumption for 2016/17
5.7.3 Projected Flows & Loads
Projections of flows and loads arriving at the Totara Road WWTP are summarised below. The projected flows and loads include contributions from the villages and the proposed NEIZ extension and will be reviewed once work on a pressure sewer network in the NEIZ has been designed.
Table 13: Totara Road WWTP Project Flows & Loads
Year Connected Population ADWF [m3/day] PWWF [m3/day] CBOD5 [kg/day] TSS [kg/day] TKN [kg/day]
Current 73,622 27,487 112,000 8,366 9,400 1,467
2014-2022 78,563 35,662 126,557 8,922 10,025 1,565
2022-2032 83,403 37,467 133,993 9,472 10,643 1,661
2032-2043 89,072 39,581 142,680 10,116 11,367 1,774
PN Residential14,936
Ashhurst1,157
Bunnythorpe169
Longburn113
Commercial / Industrial
4,990
Water Loss4,982
Average Daily Water Consumption for 2016/17 [m3/day]
Section 5 – Growth and Demand Asset Management Plan 2017 – Wastewater
45
5.7.4 Wastewater from Private Systems
The two largest private sources of wastewater are from Massey University and the Linton Military Camp. Wastewater from both sites is treated at the Council’s Totara Road WWTP. Previously, an agreement was reached to accept a smaller volume of wastewater from an existing industrial development in Works Rd, Longburn, and to accept a limited volume of waste from the NZ Pharmaceutical’s site, via the Linton connection. Officers are involved in consultation and further assessment work to better define the future flows and loads from the Linton Military Camp, NZP and the Works Road Longburn Industrial Estate.
There is also increasing pressure to install low pressure (pumped) systems into rural residential subdivisions which then connect to Council reticulation. To date one rural subdivision was given approval to connect to Council services, namely the Kingsdale Park subdivision off the Pahiatua Track. Council’s district plan seeks to prohibit the expansion of reticulated water and wastewater services into the rural and rural residential zones. It is not expected that there will be any further servicing developments of this type approved in the future. While the flows from such systems are small and lower than from traditional gravity sewer systems, the cost of assets per property serviced is significantly higher than for the residential zone, resulting in an essential subsidy from existing properties to rural dwellings.
5.7.5 Wastewater from Other Sources
Septage tankers collect waste from septic tanks and other sources, and are only permitted to discharge to the wastewater system at the Totara Road WWTP via a specially constructed receiving facility. Volumes discharged are low and typically comprises 2-4m3/week although the discharges are concentrated with high solids and organics concentrations.
5.7.6 Stormwater Inflow & Infiltration
It is estimated from variations in flows through the Totara Road WWTP that stormwater makes up 20 – 45% of total annual wastewater volumes in Palmerston North, depending on the frequency and intensity of rainfall events. On-going investigations, including CCTV and property inspections, are occurring to attempt to better manage this issue although it is not expected that significant reductions in flows can be achieved. Current wastewater pipe renewal programmes are focused on areas with high inflow and infiltration. Additional funding has been sought to support a dedicated programme to fund a contract position dedicated to investigating and following up on both private property and public stormwater ingress.
In projecting future wastewater volumes, it has been assumed that the inflow and infiltration programmes currently underway will mean that inflow and infiltration will remain at current levels and not increase. Some further analysis of the possible reductions in levels of inflow and infiltration that might be achievable will be undertaken.
5.7.7 Regional Council One Plan Standards
Increased treatment standards and in river targets are expected to be reflected in high treatment standards for wastewater that is to be discharged to the environment and into water ways in particular. This will impact on the extent and capacity of new wastewater treatment systems to be constructed as a result of the new resource consents required at the Totara Rd Treatment Plant.
Section 5 – Growth and Demand Asset Management Plan 2017 – Wastewater
46
Council will continue to work proactively with Horizons Regional Council to identify the best means of achieving improvements in wastewater quality outcomes, in a way which is both practical and cost effective.
5.7.8 National Policy Statement – Freshwater Management
Legislative change through the implementation of National Policy Statements will result in heightened expectation that Council achieves meaningful improvements in wastewater discharge quality.
5.7.9 Technology Changes
Technology changes, such as composting or waterless toilets, are frequently touted as a means of decreasing water consumption and wastewater discharges. However the uptake of these technologies is likely to be very low and health concerns also mitigate against their widespread adoption.
Low Pressure Sewer Systems (LPS) and potentially Vacuum Sewer Systems (VSS) have evolved and become a viable alternative for areas which are low lying, suffer from high groundwater levels and be susceptible to liquefaction in seismic events all factors which make conventional gravity sewer systems less attractive. A key advantage of the LPS systems is their provision of property level storage which provides flow buffer resulting in significantly lower wastewater peaks and the options to hold back flows when the receiving network is at or over capacity. LPS are also very effective at restricting stormwater and ground water infiltration given wastewater can only enter the house or property gravity network which is very limited in extent.
As part of work associated with considering alternatives for Wastewater BPO Project, a comprehensive review will be undertaken of all the technologies which might be adopted to reduce or limit future wastewater flows. The technologies and strategies will be evaluated using local information to determine the extent of any impact on flow under both voluntary and mandatory regimes.
Council’s Trade Waste Bylaw provides a regulatory mechanism for controlling the volume and strength of trade waste discharges. It allows for potentially large discharges to be controlled to reduce or avoid the impact of the discharge on the capacity of Council’s wastewater collection, treatment, and disposal assets. The Trade Waste Bylaw is seen as the preferred mechanism for controlling volumes in different parts of the wastewater network, and in particular, in respect of any new and existing wet industries.
5.8 Demand Management
In response to wet weather overloading of the wastewater system, City Networks has adopted a range of strategies, including:
Programmes to reduce the entry of stormwater to the wastewater system in private properties (infiltration/inflow programmes).
Renewal of pipelines where there is excessive entry of stormwater and / or groundwater through defects in the pipes.
Providing additional capacity in parts of the wastewater system. Proposing the designation of areas where LPS or VSS must be used.
Section 5 – Growth and Demand Asset Management Plan 2017 – Wastewater
47
5.9 Sensitivity to Demand Changes
In projecting the future wastewater demand, it has been assumed that:
The discharge per head of population will reflect water usage patterns and will remain constant, or decrease slightly.
Average dry weather flow increases over the period by approximately 20% to 33,000 m3/day. Current inflow and infiltration levels will not increase. The proportion of major “wet” industries in the City will not increase.
5.10 Climate Change – Impact on Demand
The projected impacts of climate change are likely to become more noticeable towards the end of the planning period of this AMP, and have greatest relevance to water supply, wastewater, and stormwater assets.
The New Zealand Climate Change Office has released a report on the impacts of the changing climate in New Zealand which concludes:
Higher temperatures, more in the North Island than the South (but still likely to be less than the global average).
Rising sea levels. More frequent extreme weather events such as droughts (especially in the east of New Zealand)
and floods. A change in rainfall patterns – higher rainfall in the west and less in the east.
The Ministry for the Environment has predicted impacts of a moderate rate of climate change for the Manawatū-Wanganui region, including changes in average temperature, sea level rise, and rainfall patterns. In general, Manawatū-Wanganui, like much of the west coast of New Zealand, is likely to become warmer and wetter.
Climate scientists estimate that average temperatures in Manawatū-Wanganui could be up to 3°C warmer over the next 70-100 years. This compares to a temperature increase in New Zealand during the last century of about 0.7°C.
Current research and monitoring suggests that the main impacts of climate change on the wastewater activity will be an increase in the frequency and intensity of rainfall events and hence potential increases in inflow & infiltration. This will require Council to continue to adopt an aggressive approach to identifying and reducing I&I if wastewater flows are not to exceed existing network and pump station capacity.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
49
6 Assets & Lifecycle Management This section provides the detail of the key asset components comprising the Wastewater Activity together with individual AM strategies and plans for the maintenance, renewal, and development of these assets.
6.1 Overview of Wastewater Network Assets
6.1.1 Description of Assets
Council owns and operates four distinct gravity wastewater networks from which, wastewater is pumped to the Palmerston North Network or the Totara Road Wastewater Treatment Plant. The networks include:
Palmerston North, including, Linton, and Aokautere; Ashhurst Bunnythorpe and Longburn.
The Palmerston North network collects wastewater from urban areas of the City and from the residential areas of Aokautere, and Linton (including the Army Camp and Manawatū Prison). The wastewater collection network is divided up into catchments which are largely based on the natural topography of the City. The layout of the City’s trunk mains and catchment areas is shown in Figure 12. In Palmerston North City, four trunk mains collect wastewater from individual properties through a reticulation network of pipes and manholes to deliver the wastewater in a general north-east to south-west direction to the Totara Road WWTP in the Awapuni area. A number of low lying areas require wastewater to be pumped into these trunk mains. There are 28 wastewater pump stations in the City wastewater collection network.
Council operates separate wastewater networks for Ashhurst, Longburn, and Bunnythorpe. The wastewater from Ashhurst is pumped to the Palmerston North City reticulation via a pump station located next to the existing oxidation ponds and a 9km rising main, to a discharge point in Rosalie Terrace. The Ashhurst system comprises a collection network, two pump stations, oxidation ponds where the wastewater is partially treated, and a 250 mm diameter rising main.
Longburn has a sewer network with 102 connections and two pump stations. The wastewater is pumped to Palmerston North City via a 300 mm diameter rising main. Bunnythorpe is also served by a separate gravity wastewater system including three pump stations. Since 2016 the wastewater has been pumped to Palmerston North for treatment via a 150 mm rising main in Railway Rd.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
50
Figure 12: Wastewater Catchments
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
51
The broad asset groups and their replacement values as at 30 June 2014 are summarised in Table 14.
Table 14: Replacement Value of Wastewater Assets
Asset Component Quantity Replacement Value
Pipelines 418km 138,594,111
Manholes 5679 $30,312,864
Laterals 27,783 $68,948,126
Pump Stations 36 $6,037,242
Treatment Plants 1 $44,816,718
Oxidations Ponds 1 $1,368,890
Valves 109 $570,484
Total $290,648,435
6.1.2 Wastewater Supply Asset Components
Each wastewater scheme is made up of three different asset groups which link together to make a wastewater system as shown in Figure 13.
Figure 13: Wastewater Supply Asset Component Groups
6.2 The Wastewater Collection Assets
The wastewater collection system comprises:
Sewer laterals. Gravity sewer pipes. Manholes.
Wastewater Collection Network
Pump Stations
Treatment Plant
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
52
Pumped sewer pipes.
The wastewater collection network within Palmerston North is delineated into the following catchments:
6.2.1 The Western Trunk Sewer Main Catchment
The Western trunk sewer main, which was constructed over the period 1959 - 1975, drains the northern perimeter of the City, extending some 15 km from Kelvin Grove in the east to Maxwell’s Line in the west. Recent developments have involved extending this to the intersection of Railway Rd and Roberts Line to collect waste from the NEIZ area. Downstream of Tremaine Avenue, the system has been duplicated, with both lines delivering flow to the Maxwell’s Line Pumping Station. This pump station discharges through a rising main and gravity sewer along Maxwell’s Line, joining the other trunk sewer mains between Otira Place and the WWTP. The bulk of the pipework in this catchment is rubber ring jointed reinforced concrete pipe.
6.2.2 Featherston/Tremaine Trunk Catchment
This trunk sewer main serves the northern part of the main City area, generally between the railway line and Grey Street in the east, and extending as far south as Ferguson Street further west. It interconnects with the Ferguson Street trunk sewer main and the Western trunk sewer main between Rugby Street and the WWTP.
6.2.3 Ferguson Street Trunk Catchment
The Ferguson Street trunk sewer extends from the intersection of James Line and Rosalie Terrace, and receives flows from Ashhurst, the southern part of the City between the Featherston Street catchment to the north, and the Eastern trunk sewer main to the south. The original earthenware pipe was replaced after 1973 by a new 450-1200 mm concrete pipe, with the old pipeline left in some areas to act as a rider line interconnected with the new pipes.
6.2.4 Eastern Trunk Catchment
The Eastern trunk sewer main sewer was completed in 1968 and was designed to handle flows from Aokautere and Massey, and also to relieve the Ferguson Street trunk by taking flows from the south east of the City through pumping stations at College Street and Jickell Street. The trunk is served primarily by these pump stations, with a connection to the Massey pump station by a pipeline across the Manawatū River bridge.
6.2.5 Confluence of Trunks
In the south-western part of the City around Maxwell’s Line, the sewer trunk mains converge on the Totara Road WWTP. The Western trunk sewer main flows are delivered along a rising main in Maxwell’s Line, which gravitates past Racecourse Road and Otira Place, where the flows from the Tremaine/Featherston and Ferguson trunk sewer mains join the system. The College Street trunk and Eastern trunk sewer mains join the other trunks in Totara Road, from where wastewater is transported to the Treatment Plant through parallel 1350 mm and 900 mm pipelines.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
53
6.2.6 Aokautere Reticulation
A separate reticulation system services the Aokautere Village and is connected to the Palmerston North system at Cashmere Drive via a pump station in Peterson Rd and a 100mm diameter rising main.
6.2.7 Linton Reticulation
A separate reticulation system services the Linton area and is connected to the privately owned Linton Army Camp system. The Linton Army Oxidation Pond discharge to the Manawatū River was discontinued in 2006, and a direct pumped connection was made via a private pipeline to the Totara Road WWTP.
6.2.8 Ashhurst Reticulation
A separate reticulation system services the Ashhurst area. Wastewater from Ashhurst is pumped to Palmerston North City via a pump station installed next to the existing oxidation ponds and a 9km rising main discharging into the top end of the Ferguson trunk in Rosalie Terrace. The Ashhurst scheme was installed in the 1980’s, with most of the pipework being either reinforced concrete or PVC.
6.2.9 Bunnythorpe Reticulation
A separate reticulation system services the township of Bunnythorpe. Wastewater from Bunnythorpe is now pumped to Palmerston North for final treatment from the Kairanga-Bunnythorpe Rd pump station upgraded in 2016 to deliver larger flows direct to Palmerston North.
6.2.10 Longburn Reticulation
A separate reticulation system services the township of Longburn. Wastewater from Longburn is pumped to Palmerston North City through two pump stations located in Reserve Rd and Walkers Rd, via the 300mm diameter rising main servicing the Works Rd Industrial subdivision.
6.3 Wastewater Collection Asset Attributes
Data on the collection network is held in the INFOR database. There is reasonably good information about the main sewers and manholes. Data on laterals is incomplete, and the number of laterals is based on the number of properties rated for wastewater, excluding properties where the wastewater pipe is located on the property, and an estimated average lateral length of 9m and an assumed diameter of 100 mm.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
54
Figure 14 shows an age profile of the wastewater pipelines. It indicates that, although the first pipes in the network were installed in 1890, most of the network is relatively young, with 60% of the network installed after 1960.
Figure 14: Wastewater Pipe Age
Figure 15 shows that the network is predominantly constructed of reinforced concrete pipes (55%), with smaller lengths of earthenware (23%) and PVC (22%).
Figure 15: Wastewater Pipe Material
0
10
20
30
40
50
60
70
80
0-9 10-19 20-29 30-39 40-49 50-59 60-69 70-79 80-89 90-99 100-109 110-119 120-129
Leng
th o
f Was
tew
ater
Mai
ns [k
m]
Age Range [years]
0
50
100
150
200
250
Glazed Earthware Concrete Plastic Other
Leng
th o
f Was
tew
ater
Mai
ns [k
m]
Pipe Material Type
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
55
Figure 16 indicates that the network largely consists of small diameter pipes, with 150mm diameter pipes making up 53% of the network.
Figure 16: Wastewater Pipe Diameters
6.3.1 Wastewater Collection Asset Condition
Table 15 summarises the wastewater collection system assets, including the condition and performance grading for each asset type. Condition grading confidence level descriptions are provided in Appendix G. Asset condition is graded on a scale of 1 to 5 (excellent to poor) based on guidelines from the International Infrastructure Management Manual. Details are provided in Appendix G.
Table 15: Collection System Assets
Component Quantity Description Condition Rating
Performance Rating
Public Laterals 242 km Typically 100 mm dia. pipes connecting properties to the public mains from the point of connection.
1 - 5 1 - 5
Gravity Sewer 418km Non pressure pipes sized between 150 to 1350 mm dia. 1 - 4 1 - 4
Manholes 5,679 Access points located at changes in direction or grade and intersections between public mains
1 - 4 1 – 4
Pumped Sewer 29.6km Pressure pipes supplied from associated Pump Stations 1 - 3 1 - 3
The overall condition of the collection network is considered to be good. This assessment has been based on:
The current low level of maintenance problems and premature failures. The relatively young age for the majority of the pipes. Good design and construction standards used to develop the wastewater network. Generally favourable ground conditions in the City. Results of CCTV inspections of a selection of the network.
0
50
100
150
200
250
≤100 150 200-250 300-400 450-525 600-675 750-900 ≥1200
Leng
th o
f Was
tew
ater
Mai
ns [k
m]
Pipe Diameter [mm]
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
56
Additional condition assessments have been based on Closed Circuit TV (CCTV) surveys which provide specific condition data. Since 1988 CCTV inspections have been carried out on approximately 39% of the pipe network which are typically older earthenware or concrete pipes. Surveys were carried out to investigate specific network problems and for condition assessments. Figure 17 shows the areas surveyed as of 2013. CCTV inspections have shown that age of pipe alone is not a good indicator of pipe condition. Other factors influencing condition include:
Circumferential cracking in older earthenware pipes. Corrosion of concrete pipes particularly in the vicinity of major pump stations due to acid attack from
hydrogen sulphide gas exacerbated by turbulent flow conditions. These pipes are to be more closely monitored to enable timely replacement or rehabilitation.
Tree root intrusion – Several of the City's streets suffer significant blockage problems due to tree root entry of the sewer mains. This is also one of the main causes of sewer lateral failure within the road reserve. Many of the earthenware sewer mains laid by the Housing Corporation were located along the rear of the houses in private and these are particularly prone to tree roots intrusion in well planted sections.
Poor pipeline grades – Areas of the City that were built on previous swampy land have settled unevenly so that there are sections with uneven or very flat grades. While this affects sewer laterals more than sewer mains, Council has a proactive mains flushing programme in place to mitigate blockage risks in these sewers.
All CCTV records are catalogued in the INFOR Asset Management System and linked to the GIS. This allows pipelines with a CCTV record to be viewed spatially on any networked PNCC PC. The NEZTEK Data Exchange Utility enables CCTV condition grading information from contractors to be imported into the INFOR AMS. This improves the efficiency and effectiveness of asset planning.
Figure 17: Location of CCTV Surveys Completed
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
57
6.3.2 Wastewater Collection Asset Capacity and Performance
The overall performance of the wastewater collection network is considered to be satisfactory. Performance assessments have been based on:
The number of pipe blockages. The number of sewer overflows. The volume of stormwater inflow and infiltration.
The following Figure 18 and Figure 19 depict the incidence of pipe blockage by age and diameter.
Figure 18: Pipe Blockage and Breaks by Pipe Age
0
50
100
150
200
250
300
0-9 10-19 20-29 30-39 40-49 50-59 60-69 70-79 80-89 90-99 100-109110-119120-129
Num
ber o
f Blo
ckag
e in
Was
tew
ater
Mai
ns S
ince
19
98/9
9
Age Range [years]
Blockage and Breakage at 2014 AMP Blockage and Breakage at 2017 AMP
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
58
Figure 19: Pipe Blockage and Breaks by Pipe Diameter
Figure 20: Pipe Blockage & Breaks Long Term Trends
Blockages
Blockage records held since June 1996 show that the number of blockages per year had remained relatively constant before an up-swing over the period 2008 - 2014, which was primarily related to third party damage from the Ultra-Fast broadband program in the city. It can be assumed that the background level of breaks has remained fairly steady indicating the service potential of the system is being maintained.
0
100
200
300
400
500
600
700
800
900
≤100 150 200-250 300-400 450-525 600-675 750-900 ≥1200
Num
ber o
f Blo
ckag
e &
Brea
ks in
Was
tew
ater
Mai
ns
Sinc
e 19
98/9
9
Pipe Diameter [mm]
Blockage Breakage
0
5
10
15
20
25
30
2007/08
2008/09
2009/10
2010/11
2011/12
2012/13
2013/14
2014/15
2015/16
2016/17
2017/18Bloc
kage
per
100
km w
aste
wat
er m
ains
[No.
/100
km
]
Financial Year
Blockage Rate 2017 AMP Technical Performance Measure
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
59
For 2016/17 the number of mains blockages was 19 per 100km of mains, which was below the number of blockage specified in the technical performance measures for levels of service. A target of 1 blockage per 1000 customers has been adopted in accordance with DIA requirements.
The causes of blockages are:
Uneven grade. Tree roots. Offset pipes. Structural collapse. Build-up of fat or gravel. Foreign objects. Third party damage
Overflows
Overflows can occur through a service defect such as pump failure or blockage, or through wet weather flows exceeding the capacity of the pipeline or pump stations. The City does not have a major overflow problem, and only during prolonged periods of heavy rainfall does the network become surcharged sufficiently to cause overflow at a number of known low spots around the City. Part of this problem is thought to be due to the entry of ponded stormwater to the wastewater network in a number of low lying areas in the city, which greatly increases the rate of inflow and infiltration into the wastewater system.
Areas with overflow problems include the low lying areas of the Tremaine/Featherston catchment, and the top end of the Western Trunk. Where practical, properties with known overflow problems have been fitted with reflux (non-return) valves to their connections to prevent backflow.
Stormwater Inflow & Infiltration
Extensive flow monitoring undertaken since 1997 has enabled the assessment of the performance of the various sewer sub-catchments in terms of stormwater inflow and infiltration (I&I) in the wastewater network. Figure 21 depicts the severity of I&I in the wastewater catchments as assessed in 2013. Red areas shown are those with the highest stormwater inflow and infiltration (GHD 2013).6 The R% is the percentage of rainfall volume in any rain event that is estimated as typically entering the wastewater network in each catchment and it is one of a number of indicators of the severity of I&I.
The catchments with the highest assessed I&I have also been the focus for the network renewal programme over the last few years.
6 GHD, NEIZ WW Capacity Assessment, 2013 – DM 1052063
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
60
Figure 21: Catchment Inflow & Infiltration
6.4 Wastewater Pump Station Assets
6.4.1 Wastewater Pump Station Asset Attributes
There are 28 pump stations in Palmerston North: 2 in Longburn, 3 in Bunnythorpe, and 2 in Ashhurst, that lift wastewater from low lying areas into the gravity wastewater collection network. The major pumping stations in the city are Maxwell’s Line (pumping 25% of the City’s wastewater flow), Massey, College St, Jickell Street, and Ashhurst Ponds.
Table 16 summarises the wastewater pump station assets. Complete pump station asset information can be found in Appendix H.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
61
Table 16: Wastewater Pump Station Condition & Performance Ratings
Pump Station Capacity (l/S) No Pumps Year Built Year
Renewal Condition Performance
Rating Rating
Maxwells Line 758 4 1964 1985-2017 1 1 – 2
Admirals Place 10 2 1986 2006 1 – 2 1
Alderson Drive 25 2 2008 N/A 1 1
Aokautere 10 1 2011 N/A 1 1
Ashhurst Ponds 47 2 2014 N/A 1 1
Capri Place 35 2 1975 1986 2 – 3 1 – 3
Cashmere Drive 10 2 2000/08 2008 1 – 2 1 – 2
College St 59 2 1966 2004 2 – 3 1 – 3
Coutts Way 6 2 2016 N/A 1 1
Durham St (Ashhurst) 30 2 1984 1994/2011 1 – 2 1
Food Stuffs – Railway Rd 10 2 2008 2024 1 1
Freedom Drive 35 2 2016 New 1 1
Grand Oaks Dr 10 2 2008 N/A 1 1
Jickell St 100 3 1926 2008-2017 2 – 3 1 – 3
KB Road - Bunnythorpe 13 2 2016 New 1 1
Kensington Mews 18 2 1962 2011 2 1 – 2
Maple St - Bunnythorpe 5 2 1990 2018 Not Rated Not Rated
Massey 139 3 1965 1992-96 2 2
Newton Place 10 2 1986 2002 2 1 – 2
Racecourse Rd 26 2 1975 1994/2006 2 – 3 1 – 3
Railway Road - Bunnythorpe 22 2 1981 2009 Not Rated Not rated
Redwood Grove 20 2 1975 N/A 2 1 – 3
Reserve Rd - Longburn 22 2 1981 2018 2 2
Roy Street 4 2 1993 N/A 2 1 – 3
Ruamahanga Cres 10 2 1986 N/A 1 – 2 1 – 3
Ruapehu Dr 10 2 1999 N/A 1 1
Ryder Cheshire 28 2 1983 N/A 2 – 3 1 – 3
Shirriffs Rd 2.4 2 1994 2002 2 1 – 3
Sutton Place 10 2 1986 2008 1 - 1
Te Awe Awe St 18 2 1955 1990 1 – 3 1 – 3
Te Wanaka Rd 5.2 2 1994 2008 2 1
Tremaine Ave 53 2 1961 1988 2 – 3 1 – 3
Vogel St 4 2 1991 2015 2 – 4 2 – 4
Walkers Rd - Longburn 22 2 1981 2015 2 2
Wikiriwhi Crescent 18 2 1966 2012 1 – 2 1
Condition and performance grading confidence level descriptions are provided in Appendix G .
All pump stations are unmanned with automatic operation of the pumps being controlled by various level sensing devices and pump controllers. The installed pumps operate on an alternate cycle so that
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
62
wear is equalised between the pumps. Pump operation is monitored using Abbey’s Powerlink telemetry system.
To cater for major power outages, standby generators have been installed at three of the biggest pump stations: Maxwell's Line, Jickell St, and Massey. All other pumping stations have a portable generator connection. The portable generators owned by Council are able to power at least one pump in the larger pump stations.
Figure 22: Location of Wastewater Pump Stations
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
63
6.4.2 Wastewater Pump Station Asset Condition
Table 17 contains a summary of the condition for each of the pump station. Additional detail is included in Appendix H. It can be seen that the majority of the pump station assets are in good to excellent condition. The lower condition score pump stations (3 or 4) have been marked down on the basis of the condition of the electrical and control equipment rather than the civil (Concrete) structures.
Figure 23: Photo of Wastewater PS in Grand Oaks Drive
6.4.3 Wastewater Pump Station Asset Capacity and Performance
Pump Capacity
Pump stations are generally designed so that the installed pumping capacity is twice that required to meet wet weather flows. This allows for one pump, in the event of a main pump failure or removal of a pump for servicing, to meet the required level of service.
Studies undertaken in 2011 indicated there were two pump stations with insufficient capacity. These were Massey Pump Station and Maxwell's Line Pump Station. Maxwell’s Line requires all four pumps to run during a prolonged significant wet weather event. In some events, Maxwell's Line Pump Station had not been able to cope with the flows and overflows had occurred at the top end of the Western trunk sewer main. Although an overflow is a rare event, it showed that there was very little spare capacity in the system. Upgrade works were completed in 2013 and 2017 and all four of the existing pumps were replaced with pumps of larger capacity and greater efficiency.
Investigations at Massey pump station showed that all three pumps were operating at significantly less than their theoretical capacity. Further investigations revealed that the constraint was in the capacity of the rising main. The operating regime used at Massey pump station resulted in lower pipe velocities than those necessary to prevent settlement of solids. In addition, the existing pumps had high wear and lower than desirable efficiencies. The pumps at Massey pump station have now been replaced with new, high efficiency pumps, and the operating philosophy changed to ensure regular flushing flows are created to prevent settlement in the rising main.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
64
Wet Well Storage
In the event of complete pump failure (usually from power outage) all pump stations are designed with at least 4 hours storage at inflows of 4 x average dry weather flow. The exceptions to this are Massey pump station, which has approximately 2 hours storage at peak flows before overflow to the Turitea Stream occurs, and Jickell Street which also has only 2 hrs storage at 4 x average dry weather flow.
Studies had indicated that an additional storage volume of 355 m³ is required at the Massey pump station to meet the 4 hour design standard. Unfortunately, there is insufficient space available to construct additional storage. The lack of storage at Massey pump station is mitigated by the presence of a standby generator unit that ensures continuous operation of the pump station in the event of power failure. With respect to Jickell Street, there was again insufficient space available to construct the required storage. This has also been mitigated by the installation of a new standby generator for instances of power failure.
The performance of the pump stations is monitored by telemetry that enables total running hours and other performance indicators to be identified for each pump. This is tracked to detect any deterioration of pump performance. In the past three years there have been several overflows at the Reserve Rd Longburn pump station. In order to improve understanding of flows in the pump station catchments upgrades to provide flow measurement as well as more robust electrical control and telemetry are proposed for a number of stations across the network,
6.5 Wastewater Treatment Assets
6.5.1 Wastewater Treatment Asset Attributes
Palmerston North City – Totara Road Wastewater Treatment Plant
The original conventional primary treatment plant at Totara Road was officially opened on 22 June 1968. The secondary treatment facility (aerated lagoons) were designed and constructed during the early 1980’s, and commissioned in 1985. Tertiary treatment facilities were added in 2006-2008 and included UV irradiation treatment, and a dissolved phosphorus removal plant including clarifier and an associated sludge dewatering plant. To meet cultural objectives, the treated effluent passes through a constructed wetland pond and rock embankments before discharging into the Manawatū River.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
65
Figure 24: Totara Road Wastewater Treatment Plant Schematic
The sludge generated in the primary treatment plant is stabilised through two anaerobic digesters. The anaerobic digesters were upgraded in 2009/10 to enable increased organic loading and increased biogas production.
Ashhurst
Consists of a two stage oxidation pond system with mechanical aeration in the first pond, sited near the bank of the Manawatū River on farmland off the end of Hackett’s Road, and serves a population of approximately 2,634. The first stage pond has a capacity of 19,000 m3 and the second stage pond 7,100 m3. A 4 kW aerator was installed in 1997 to improve the quality of the effluent discharging to the river. Following expiry of the consent to discharge to the river in August 2013, a connection from the Ashhurst system to the city was constructed in June 2014. This comprised a pump station drawing from pond two and 8.6km of rising main discharging to the terminal manhole in Rosalie Terrace. A temporary consent (3 yr expiring in December 2018) in place for the operation of the ponds, subject to the outcome of further investigation in the extent of leakage from the ponds into the surrounding groundwater.
Monitoring of groundwater both upstream and downstream of the assumed zone of influence of ponds over the last 18 months has indicated little if any effect from the discharge. On the basis of the interim results Council is proposing to apply for a long term consent for the two pond system.
6.5.2 Wastewater Treatment Asset Condition
Palmerston North City – Totara Road Wastewater Treatment Plant
Since the WWTP was commissioned in 1968, the plant has been maintained to a high standard, with an ongoing maintenance programme and replacement and upgrade of mechanical and electrical equipment on an as required basis. Historically this has been funded from an annual allocation of funds with final project selection occurring at the start of the budget year. This is being replaced by a more robust 5 year renewals programme informed by condition assessment of all key mechanical and electrical assets. The renewal profile developed will then be used to inform the application for funding.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
66
Elements of the inlet works have previously been investigated to assess performance. The evaluation concluded that the inlet screens were under capacity and had poor performance. In addition, the capacity of the inlet lift pumps will be exceeded by 2022 and will require replacement. The final part of the study investigated the performance of the existing primary sedimentation tanks, and concluded that capacity would be increasingly exceeded as flows increase. The study recommended duplication of the sedimentation tanks in order to treat the projected future inlet flows and loads, and replacement of the pre aeration/grit removal system. The above investigations are set out in detail in the report “Totara Road WWTP Inlet Works and Primary Treatment Capacity, Capacity Review of Inlet Works and Primary Treatment” (Harrison Grierson, June 2014).7
To date the inlet screens and screen conveyor systems are in the process of being replaced, and a new odour control system has been installed. The new screens consist of 3 x 5mm band screens that run continuously and duplicate “nog wash” screen conveyors. The replacement of the pre aeration/grit removal system is also underway, and work on identifying suitable inlet pump replacements has started. The duplication of the primary sedimentation tanks is currently on hold pending the outcome of the upcoming Wastewater Best Practicable Options Assessment (BPO) review.
Previous inspections had revealed that the internal spaces of the floating lids on the two anaerobic digesters were in poor condition. As a result of this, both lids are being repaired, and corroded structural steel replaced over two successive years. Associated equipment is also being replaced, including gas pipework, valves, and pressure relief valves. The internal concrete surfaces are being coated with protective linings.
Ashhurst
The oxidation ponds are in good condition and require little attention, apart from routine maintenance on the mechanical aerator. Some deterioration of the wave band around the ponds has occurred and will require attention in the medium term but it is intended this will be addressed as part of the annual operating programme if required.
Table 17 summarises the wastewater treatment plant assets.
Table 17: Wastewater Treatment Plant Asset Data
Component Description & Purpose Grading
Condition Performance
Totara Road Wastewater Treatment Plant
Sluice Gate A hydraulically operated penstock gate controls the incoming flow automatically so as to limit flow to that which can be handled by the plant.
1 1
Screening Three 5mm band screens and two Nog Wash screen conveyors. Recycled wash water system to keep the screens clean.
1 1
Lift Pumps Four 75KW AC variable speed driven pumps lift all the flow to a suitable level for gravity flow though the treatment processes.
3 3
Pre Aeration and Grit Removal Tank
This tank is for the deposition of grit before the flow passes to the sedimentation tanks.
3 4
Sedimentation Tanks
Three sedimentation tanks allow the solids to sink to the bottom for sludge removal and fat and grease to accumulate on the surface from where it is skimmed off.
3 3
Sludge Digesters Two anaerobic sludge digesters stabilise the sludge for disposal to the sludge lagoons.
2 1
7 Harrison Grierson, Totara Road WWTP Inlet Works and Primary Treatment Capacity, Capacity Review of Inlet Works and Primary Treatment, June 2014 –
DM#1146931
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
67
Component Description & Purpose Grading
Condition Performance
Sludge Lagoons For the accumulation of the digested sludge and further breakdown of the sludge - 3.2 hectares total area.
3-4 3
Aerated Lagoons Two lagoons covering a total area of 3.8 ha are connected in series provide for secondary treatment of the effluent.
2 3
Aerators The first pond utilises four 30 kW floating aerators and two 45 kW floating aerators and the second pond three 30 kW aerators all fitted with variable speed drives to assist with the oxidation process.
2 2
Monitoring SCADA via Wonderware Archestra and Abby Systems Powerlink telemetry.
1 1
Standby Generator(s)
A diesel powered standby 500 KVA generator commissioned in 2013 is installed to provide power for the main building including lift pumps in the event of power failure. A separate 300 KVA diesel powered generator has been installed to power the UV treatment plant and Phosphorus Removal Plant, the lagoon aerators are not supplied with standby power.
1 1
UV Plant Installed and commissioned in 2003 consists of two banks of LP UV lamps 112 kW.
1 1
Phosphorus Reduction Plant
A single 48m diameter clarifier has been installed in association with a sludge dewatering plant in 2007.
1 1
Wetland Pond Constructed in 2003 in conjunction with the UV plant by converting a sludge stabilisation pond.
1 2
Biogas Generator Commissioned in 2010 716 kW dual fuelled generator. 1 1
Digester Sludge Thickener
Andritz rotating drum sludge thickener commissioned in 2012 with associated automated poly batching plant and pumps.
1 1
Digested Sludge Thickener
Teknofaghi Mono Belt Thickener commissioned in 2016. 1 1
Clarifier Sludge Thickener
Westphaila Centrifuge. 1 1
Liquid Waste Reception facilities
Two 30,000L tanks and associated pumps for receiving additional liquid wastes before injection into the digesters commissioned in 2010.
1 1
Ashhurst
Oxidation ponds A two stage oxidation pond system using natural biological process to treat Ashhurst wastewater.
2 2 - 3
Aerator A mechanical device operated to assist aeration in the first pond. 2 2
Condition grading confidence level descriptions are provided in Appendix G.
6.5.3 Wastewater Treatment Asset Capacity and Performance
Palmerston North City – Totara Road Waste Water Treatment Plant
The wastewater treatment plant treats wastewater collected from a population of 73,662. The average dry weather flow is 27,487 m3/day. Flow can increase substantially after rain to as much as 120,000 m3/day due to stormwater inflow and infiltration into the collection system.
Work was undertaken in recent years to increase the capacity of the plant to provide for a population equivalent of 100,000 or 42,000 m3/day dry weather flow. This includes primary settlement tanks bypass channel construction, and improvements that allow for flows to pass directly to the aerated lagoons without primary treatment (1997 and 2005). Upgrades to inlet pumping capacity were completed in 2005 along with improved capacity for flow between the aerated lagoons. The new tertiary treatment works have been designed to meet capacity needs of 100,000 population equivalent.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
68
In recent years, the organic load to the plant has increased, particularly from a number of wet industries in Palmerston North and the Longburn Industrial Area. A further increase in flows has occurred following installation of pumped connections from the satellite towns of Ashhurst, Longburn, and Bunnythorpe. This led to the capacity assessment of the inlet works and primary treatment by Harrison Grierson (June 2014), as discussed in Section 6.5.2.
Primary Treatment Processes
With the projected increase in flows and loads, the capacity of the existing primary plant is constrained. The situation is likely to be exacerbated due to further growth in the future. Moreover, the plant and equipment in the primary treatment plant have been in service for more than 20 years in some cases, and the technology is out dated. As a result, performance had been compromised, with frequent break downs requiring high maintenance.
Some of the key issues were as below:
Inlet Screens – Capacity constrained at current flows, low solids capture rate, and odour issues. Lift Pumps – No redundancy in the system at current wet weather flows, insufficient capacity to
cater for the future flows, Worthington Simpson Pumps which are no longer manufactured. Grit Removal System – Insufficient capacity to cater for the future flows and odour issues. Primary Sedimentation Tanks – Capacity constrained at current flows and unsafe concrete
structure.
Based on a multi criteria analysis, the Harrison Grierson report recommended the following:
Upgrade screens with two 3m Rotary Screens of 1,200 L/s each; Increase pumping capacity with new pumps; and Modify the existing aerated grit chamber to accommodate a PISTA Grit Removal System of 2,468
L/s capacity for projected flows up to 2043, and upgrade PST with the addition of two channels to cater for flows up to 2043.
To date, the inlet screens and screen conveyor have been replaced with 3 x 5 mm band screens rather than 2 rotary screens as originally proposed, and with 2 “nog wash” screen conveyors. At the same time, permanent odour control has been installed. The replacement for the existing aeration/grit removal system has been ordered with installation expected during the summer of 2018/19.
Secondary Treatment Process
After investigations into the performance of the aerated lagoons regarding their performance, an additional two floating aerators were installed into pond one, and the existing aerators relocated. At the same time, additional dissolved oxygen (DO) monitors were installed. This has addressed the shortfall in aeration capacity in pond one and here is now a surplus of aeration capacity in pond two to cater for predicted domestic and commercial growth over the period prior to the upgrade the wastewater treatment plant.
For further details refer to the report “Palmerston North City Council, Totara Road WWTP Aeration, Design Report: Relocation of Aerators” – GHD Consultants, August 2014).8
8 GHD, Palmerston North City Council, Totara Road WWTP Aeration, Design Report: Relocation of Aerators, August 2014 – DM#1177716
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
69
Consent Review
Following on from a non-compliance and abatement notice issued by Horizons Regional Council in 2011, a formal Consent Review of the treatment plant discharge was heard in front of four commissioners in November 2015. The formal Consent Review was withdrawn by Horizons Regional Council before a decision was recorded, after PNCC agreed to apply for a new discharge consent by 2022 rather than in 2028. The revised consent conditions include a requirement that PNCC undertaking a Best Practicable Options assessment of treatment options before applying for the new discharge consent. The revised consent also includes a number of mandated milestones the Council has to achieve and report on. The revised consent is located in Appendix C.
The discharge from Totara Road is covered by RC No.101829 and a copy of the consent is located in Appendix C.
Ashhurst
The Ashhurst ponds were upgraded in 1997, with the addition of a 4 kW aerator to satisfy previous discharge consent requirements. Following expiry of the discharge consent in 2013, a new pumped connection to the Palmerston North network was constructed and commissioned. A temporary three year consent (expiring December 2018) consents the current pond, to allow for intensive ground water monitoring to be undertaken to determine the effects of any leakage from the ponds to the surrounding soils and groundwater. Monitoring to date indicates minimal to no significant leakage to the surrounding soil and so Council proposes to apply for long term consent for the facility. Depending on the outcome of the consent, there is a possibility that the regional council may require the ponds to lining, however at the time of writing this AMP no allowance has been made to fund any works.
Bunnythorpe
Wastewater from Bunnythorpe is now pumped to Palmerston North for treatment. The oxidation pond and pump station that previously supported the pumping of wastewater to Feilding have or are in the process of being decommissioned.
Longburn
Wastewater from Longburn is pumped to Palmerston North for treatment via the 300 mm diameter rising main originating in the Works Rd industrial area.
6.5.4 The Telemetry and SCADA Assets
6.5.5 Description of Assets
In order to collate and store operational data, Council utilises a telemetry service to transmit monitoring data from various sites, typically pump stations throughout the City, to a central database. Council currently uses Abbey Telemetry System. Data is available in real time to operational and City Networks staff to monitor the operations of both the pump stations and the treatment plant. Historical data is also available to analyse trends and patterns.
Data from the sites is transmitted using radio communications. The data monitored includes operational status of the pumps, such as pump run hours, flow rates, well levels, etc. The telemetry system also transmits alarm paging messages to pump maintenance crews whenever it detects faults in pump operations, such as power failure, pump fault, high well level, etc, so that the fault can be
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
70
attended to in a timely manner. Communication with the Telemetry Master Station is by Abbey Secure-Link software using laptops and broadband internet connections.
The Totara Road WWTP uses Wonderware Archestra as the (System Control and Data Acquisition) SCADA system. This monitors, controls, and optimises the various equipment and processes at the plant. The Archestra SCADA software was purchased and installed in 2017. This includes a Historian back-up server that is located at the Main Council Building. The Historian records all data collected from the WWTP, and is available for reporting purposes. The SCADA system also has its own independent alarm paging systems to notify treatment plant operators and supervisors of faults, etc. The Totara Road WWTP can be monitored and managed remotely, as the SCADA system can be accessed via the Council network.
A Disaster Resilience Study & Options Report was completed for PNCC water and waste telemetry system in 2017. The recommended improvements are:
Replacement of aging remote telemetry units. Additional Land Mobile Radio (LMR) Channel to reduce “traffic loading” from the increasing number
of telemetered sites. Setting up of Telemetry Disaster Recovery Master (DRM) at the Arena and the North Range Road
Repeater Site, supported by: High speed Ethernet via two microwave links between North Range Rd Repeater Site with
CAB & Arena. Resilience improvements to North Range Road Telemetry Repeater Site.
6.6 Activity Management
6.6.1 Support Services
Activity management has no direct effect on asset condition, but provides those functions required to support the maintenance, renewal, and development plans. These functions include:
System planning. System monitoring. Systems record management. Policy and strategy development. Effluent quality control. Bylaw development. Regulatory control of stormwater inflow. Resource consents. Public education programmes.
Internal staff resources are mainly utilised in carrying out the functions as outlined above. Specialist external resources are employed for CCTV inspection of pipelines, strategic wastewater flow monitoring, and more sophisticated technical investigations and legal advice. Trade waste investigation and administration is performed by the City Enterprises business unit of the Council.
The support services programme, planning, and policy expenditure forecast for the next five years to implement the strategies above is shown in Table 18.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
71
Table 18: Activity Management Program – Five Year Forecast
Activity 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
City Networks Labour and Overheads $614,525 $936,557 $938,953 $930,648 $930,672 $930,672
Consumables $500,000 $400,000 $400,000 $400,000 $400,000 $400,000
Electricity $364,850 $210,000 $210,000 $210,000 $210,000 $210,000
Insurance $186,180 $191,100 $191,100 $191,100 $191,100 $191,100
Consultancy $220,935 $163,000 $163,000 $163,000 $163,000 $153,000
Rates $76,577 $78,660 $78,810 $78,960 $79,110 $79,110
Miscellaneous $60,057 $61,000 $61,000 $61,000 $61,000 $61,000
Gas $75,000 $30,000 $30,000 $30,000 $30,000 $30,000
Legal $5,942 $5,000 $5,000 $5,000 $5,000 $5,000
Reactive Maintenance $5,214 $5,000 $5,000 $5,000 $5,000 $5,000
Plant Repairs and Maintenance - $10,000 $10,000 $10,000 $10,000 $10,000
Software Licenses $5,000 $5,000 $5,000 $5,000 $5,000 $5,000
Activity Management $2,114,280 $2,095,317 $2,097,863 $2,089,708 $2,089,882 $2,079,882
6.6.2 Increases in Services (Operating Programmes)
Programme 1319 – Totara Road Wastewater Treatment Plant – Consent Renewal Upgrade Options Analysis
This programme which is a multi-year programme continuing from 2017-18 is provided to fund the completion of the optioneering stage of identified the preferred option for an upgraded wastewater treatment and disposal facility. The Best Practicable Options Project (BPO) is scoped to assess all possible options for a future wastewater treatment facility, through effective consultation and engagement with the community and all stakeholders prior to Council confirming their preferred option by June 2021. This will enable an application for the necessary consents to be prepared for lodging by June 2022.
Programme 1401 – City Wide Infiltration and Inflow Investigations
This programme is to fund a focussed programme to identify and address major sources of stormwater infiltration and inflow from both private properties and public spaces to the wastewater network. It has been some time since Council focussed efforts in this area and wet weather flows in the network have increased significantly. The programme is intended to identify the scope and extent of what might be achieved in the run up to applying for new consents for the wastewater treatment plant. It is intended to fund investigation as well as follow-up in catchments with significant inflow and infiltration but also use behaviour change approaches to engage the community in helping to address the issue.
Table 19: Operating Programmes – Forecast Expenditure
Operating Programme 2019/20 2020/21 2021/22 2022/23 2023/24 2024/25
1319-Totara Road Wastewater Treatment Plant - Consent Renewal Upgrade Options Analysis $740,000 $740,000 $990,000 $990,000 $740,000 $740,000
1401-City Wide Infiltration & Inflow Investigations $200,000 $200,000 $200,000 $200,000 $200,000 $200,000
Total $940,000 $940,000 $1,190,000 $1,190,000 $940,000 $940,000
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
72
6.6.3 Asset Systems Database – Infor Public Sector
Council uses an asset management system order to store, collate and analyse asset data. The current Council system is Infor Public Sector (IPS), a product which is supplied by INFOR Global Solutions. The Council has used IPS (formerly Hansen) since 1995. The current version deployed is IPS 8.4.0.
IPS is based on internet technology and is Web-browser-based. It can be customised by asset managers to best reflect AM processes and terminology.
The system is directly linked to the Council’s Geographic Information System (GIS) via the Geo Administrator, an INFOR Global Solutions developed interface. The interface allows new assets to be created in GIS and added to the IPS asset register with a single key stroke. Assets can be selected in GIS and viewed in the IPS window.
The link between IPS and GIS allows assets to be viewed in Geo City, an intranet viewer of Council’s spatial data, which is available to all staff. Council assets can also be viewed through the Geo-Guide on the Council’s public website. Local Contractors are able to use this service to locate Council assets prior to construction activities.
IPS comprises of a number of modules:
Asset Register. Work Orders. Inspections. Valuations. Images.
A Date Exchange Utility (DEU) allows pipe inspection data to be exported from IPS to contractors, and results imported back into IPS.
IPS allows asset managers to produce outputs using the Ad Hoc Reporting function. More complex reports are produced using Crystal Reports.
IPS records the following asset data:
Information: ID, Type, Description. Location: Address, Location Description, Area, Sub Area, District. Structural: Diameter, Material, Length, Manufacturer, Critical Rating. Associated: Install Year, Service Status, Ownership, Drawing No.
Asset data can be assigned a condition rating and a performance rating base on a grading of 1 to 5 (see Appendix G). The ratings, along with criticality ratings, can be used to analyse the asset data and provide renewal profiles and determine maintenance programmes.
Asset maintenance, both planned and reactive on assets, along with inspections, is recorded in IPS. Associated costs can also be recorded in the Work Orders module. Recent work has now provided a mobile platform for undertaking and recording asset maintenance, which utilises off the shelf tablets and proprietary software supplied by IPS.
Work Orders can be processed ‘Live’ in the field using the Infor Field Inspector.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
73
Figure 25: Field Inspector Screen Shot
Assets recorded in the Asset Management System (AMS) have been assigned a replacement value, which is used for insurance purposes, and will be used to estimate renewals programme costs when the condition, performance, and criticality ratings are complete.
Figure 26: IPS Screen Shot
Overall, the quality and extent of data held in IPS is considered to be good. Pipeline data is quite extensive, with the exception of wastewater laterals (service lines). Pump station and treatment plant
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
74
component data records have been improved over the past three years and is now considered to be good.
Table 20 details the extent of the asset data currently held in IPS for the wastewater activity.
Table 20: IPS Data Accuracy & Completeness
Asset Type Sub- Type No of Assets Recorded Asset Register
Valuation Completeness Accuracy
Reticulation
Mains 6588 95% 95% 100%
Manholes 5679 95% 95% 100%
Service Lines 13276 50% 90% 100%
Valves 109 90% 95% 100%
Pump Stations Equipment 609 95% 95% 100%
Treatment Plant Equipment 827 90% 90% 100%
Oxidation Ponds Equipment 31 95% 95% 100%
6.6.4 Network Hydraulic Modelling
Council utilises a computer based hydraulic model to analyse the wastewater network. The model is used to assist in:
Analysis of the capacity of the system to accommodate additional wastewater connections, from a single connection to a multi lot sub-division.
Optimisation of the network to improve operational efficiency. Assessing the effects of inflow and infiltration on the wastewater network. Identifying opportunities to improve network layout prompted by the need for wastewater pipe
renewals. Identifying requirements for pipe upgrades to cater for population growth and new large
developments.
Council uses Mike Urban modelling software, provided by the Danish Hydraulic Institute (DHI). This is a strategic model of the entire Palmerston North Urban wastewater network, and had been calibrated for dry weather and wet weather flows using data collected from a city wide flow monitoring programme undertaken over a number of years. The system was previously limited to the trunk main network. More detailed sub-catchment models have been, although they are yet to be calibrated. The network model has utilised data from a series of flow monitors located at critical locations within the network.
An intensive period of flow monitoring for model calibration purposes was undertaken in 2015, with up to 9 temporary flow monitors installed throughout the network to collect flow data. External consultants were engaged to assist in the model development and calibration work over a period of two years. Additional work was completed to assist in calibrating the model, including surveys of missing manhole inverts and pipe diameters. PNCC now has a fully calibrated wastewater network model that will assist investigations into capacity constraints for current and future flows to inform network renewal and capital upgrade decisions.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
75
6.7 Water Services Assessment
Water Services Assessments, as required by section 125 of the Local Government, were last completed by Maunsells Ltd in 2005. Summaries of the assessments were included in the 2012-22 10 Year Plan.
In the case of wastewater services, the assessments identified that the wastewater services within Palmerston North are adequate to meet public health outcomes and mitigate environmental effects and have sufficient capacity to cater for current demands. The programmes and projects described in this AMP are consistent with the issues and risks previously identified in the 2005 Water Services Assessments. There are no significant variations to disclose.
6.8 Operation & Maintenance of Assets
6.8.1 Overview
The overall goal of operations and maintenance is to ensure that assets will operate as designed and continue to do so reliably when required. With wastewater assets this is particularly important give the public health and environmental impacts of assets which fail, as well as the significantly higher costs associated with undertaking emergency repair to assets that fail. In respect of treatment plant and pump station assets a low risk tolerance threshold is accepted with a focus on pro-active maintenance of all critical components. The provision of duty and stand-by equipment particularly for pumping and monitoring is key to provide an opportunity for repair without loss of service.
With network assets a low risk approach to trunk main assets is taken again because of the high consequence of failure. For less critical assets e.g. property laterals the optimum approach is a balance of both reactive and proactive maintenance. While low levels of reactive maintenance are normally the ideal, high levels indicate inadequate proactive maintenance or significant deferred renewal obligations, both of which are considered undesirable.
6.8.2 Operation & Maintenance Strategies
The pro-active maintenance programme for the treatment plant, pump station and network assets has been developed from operator and staff experience as well as manufacturers’ and supplier recommendations. It comprises a range of routine tasks involving cleaning and flushing of problem network assets to prevent blockage, coupled with regular inspection and cleaning of critical above ground assets such as aerators, motors, pumps and controllers as well as pump station mechanical and electrical assets. Further development of the scheduled maintenance is planned to ensure condition information required to inform renewal programmes is captured.
Critical to effective maintenance of the wastewater network is completion of regular CCTV inspections by CCTV and condition scoring to more robustly confirm the timing and urgency of renewal of the network. The expectation is that the older smaller diameter part of the network will exhibit the poorest condition.
Reactive maintenance includes a wide variety of work ranging from clearing of network blockages, repairs to broken and collapsed pipes, as well as pump, motor and electrical repairs in pump stations and at the treatment plant. A wide variety of mechanical and wearing components at the wastewater treatment plant can fail.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
76
6.8.3 Operation & Maintenance Costs
Wastewater activity operation and maintenance costs are grouped into three areas namely activity management, activity delivery and a range of special operating programmes with specific outcome objectives. Additional charges in the operation and maintenance area include interest and depreciation.
Table 21 depicts the current breakdown of operations and maintenance expenditure within these three areas for the first five years of the plan.
Table 21: Operations & Maintenance Forecast Expenditure (Next Five Years)
Wastewater Activity 2018/19 2019/20 2020/21 2021/22 2022/23
Activity Delivery $2,725,000 $2,799,000 $2,783,000 $2,827,000 $2,827,000
Activity Management $2,095,000 $2,098,000 $2,090,000 $2,090,000 $2,080.000
Operating Programmes $940,000 $940,000 $1,190,000 $1,190,000 $940,000
Total (excl interest and depreciation) $5,760,000 $5,837,000 $6,063,000 $6,107,000 $5,847,000
6.8.4 Operation of Wastewater Assets
The wastewater activity is primarily managed and operated to meet agreed levels of service as set out in section 4 by achieving the following:
Maintain the quality of the service to protect the health of the community. Ensure the service is accessible to the community within the service area. Ensure the service is reliable with minimal service disruptions. Ensure the activity is operated safely to minimise the risks to the public and operational staff. Operate to maximise the sustainability of the activity. Operate to minimise the overall cost of the activity. Other factors that directly influence the operation of the wastewater activity include:
Meeting the requirements specified in Council strategies and specific management plans. Compliance with Horizons Regional Council discharge consent permits. Compliance with national legislation with regard to health and safety and hazardous chemicals.
The day to day operation of the wastewater activity is carried out in accordance with a number of internal Service Level Agreements (SLA’s) covering the operation and maintenance of the treatment plant, wastewater pump stations, and collection network. All work undertaken on the treatment plant and wastewater network is done in accordance with PNCC’s Health & Safety Manual and the site specific Treatment Plant Health & Safety Manual. To ensure that levels of service and regulation requirements are met, Council carries out extensive monitoring of the wastewater network, pump stations, and treatment plant.
Council utilises data automatically collected from flow meters and equipment sensors at all critical wastewater assets, which enables operators to respond immediately to equipment failures or network issues. Council also monitors WWTP equipment and effluent data to ensure reliable on-going operation of the treatment plant. In addition to automated monitoring, operational staff also carry out manual monitoring in the form of visual inspections and manual recording of data.
In order to achieve regulatory compliance, Council is required to take regular samples of the wastewater effluent. Sample results are analysed by an accredited laboratory and are used as appropriate to alter operational settings for efficient operation of the treatment plant.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
77
Council has prepared Business Continuity Plans (BCP) that outlined response and management strategies when key assets or personnel are unavailable. Council is currently completing a review of the BCP plans and developing revised plans. These will set out specific actions required to cope with a 5 day event which impacts on Council and identifies how core services will continue to be provided. Council maintains a suitable level of preparedness for prompt and effective response to disruption events and civil emergencies through suitably trained staff and robust operating procedures.
6.8.5 Maintenance of Wastewater Assets
The wastewater assets maintenance strategy is intended to maintain the current level of service while minimising costs. Day-to day-maintenance activities are carried out to achieve the following:
Maintain operational functionality of the asset. Prevent premature deterioration of the asset.
Council’s maintenance strategy is broadly based on the criticality of the assets:
Assets rated as High Criticality are inspected frequently. A high level of preventative maintenance is carried out, and component renewals are triggered, based on the condition of the asset.
Assets rated as Medium or Low Criticality are inspected less frequently. Preventative maintenance and component renewals are predominantly scheduled on a time basis.
Assets rated as non-critical are rarely inspected and a “run to failure” approach is taken. Assets are repaired or replaced when required.
6.8.6 Operation & Maintenance Delivery
Delivery of the operation and maintenance services for the wastewater assets is carried out by City Enterprises, the operational unit of Council, under contract to City Networks (the asset owner) through a series of internal contracts (known as Service Level Agreements or SLAs). For the wastewater activity there are seven SLA’s in place which cover both operation and planned maintenance tasks and these are summarised in Table 22. These SLAs run annually and are occasionally supplemented by additional SLAs for specific operational or maintenance tasks. In addition to the internal agreements there are also a number of externally contracted organisations engaged to complete specialist maintenance activities including pump station electrical maintenance, maintenance of the biogas engine and calibration and maintenance of various meters, monitors and testing equipment.
In respect of the SLAs work is on-going to shift from lump sum agreements to measure and value agreements still with fixed prices for deliverables but with an enhanced focus on outcomes and outputs reported on monthly. The current level of expenditure on operation and maintenance delivery is outlined in Table 21.
Table 22: Operations & Maintenance Activity Delivery Expenditure – Five Year Forecast
Activity 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
Service Level Agreements $2,400,000 $2,449,000 $2,433,000 $2,477,000 $2,477,000 $2,477,000
External Contracts $325,000 $350,000 $350,000 $350,000 $350,000 $350,000
Total $2,725,000 $2,799,000 $2,783,000 $2,827,000 $2,827,000 $2,827,000
Wastewater Collection Network Maintenance Programme
Work carried out under the wastewater network SLAs involves a mix of scheduled maintenance tasks including inspection and flushing as well as responding to faults that develop in the system including
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
78
blockages, breaks, overflows and odour incidents. Table 21 summarises the anticipated budget cost required over the next five years to ensure delivery of the defined levels of service.
Planned maintenance expenditure includes scheduled flushing, root kill, and inspections. To control the level of stormwater inflow and infiltration into the network, there is an ongoing programme of property drainage inspection in conjunction with smoke-testing of sewer mains. Unplanned maintenance includes clearing of blockages, reactive inspections and repairs to mains, laterals, and manholes. There has been a gradual increase in lateral repairs over the past 3 years, due to a combination of street tree damage and third party damage, primarily resulting from the fibre roll out in the city. The 30 year financial forecast for the collection network is shown in Appendix E.
Pump Stations Maintenance Programme
Work carried out under the pump station maintenance SLA mainly consists of regular inspections, including electrical inspections, well cleaning, and also includes the provision for a 24 hour call out service and receiving and logging of enquiries, complaints, and problems in line with City Networks levels of service requirements. The SLA requires immediate response to pollution overflows and pump station failure, 1 hour response time for high level alarms, and 24 hours for non-urgent complaints. Table 22 above shows anticipated operational costs over the next 5 years to ensure delivery of the defined levels of service. The work needs are consistent with the strategies defined above.
Treatment Facilities Maintenance Programme
Maintenance work at the Totara Road treatment plant includes checking, operation, and maintenance of plant and machinery, setting of gates and controls, sampling of effluent, cleaning, disposal of digested sludge, and operation of the phosphorus removal plant, sludge dewatering plant, sludge booster, liquid waste reception facilities, UV plant, wetland ponds, grounds, and building maintenance.
The oxidation ponds at Ashhurst generally require only weekly inspection. Additional expenses for Ashhurst pond include access track maintenance and running costs for the mechanical aerator.
Table 22 above details anticipated operational costs over the next 5 years to ensure delivery of the defined levels of service.
Biogas Generator Maintenance
The maintenance of the biogas generator located at the treatment plant is contracted out to the original supplier of the generator. The generator is remotely monitored from Australia and there is a local contractor who undertakes minor maintenance and inspections. Major maintenance is undertaken by specialised staff from Australia. PNCC treatment staff also monitor the performance of the generator on site and make the day to day decisions on running times and output.
6.8.7 Delivery of Programme
Operation and maintenance of the wastewater assets is carried out by City Enterprises; the operational unit of Council under specific service level agreements (SLAs). There are seven SLAs in place to cover annual operation and planned maintenance tasks for all the wastewater assets. Table 23 details the these SLAs and their value as agreed in the 2017-18 year. Additional SLAs may be required during the year for one off investigations and are provided for as part of forecast expenditure in Table 23. The SLAs are reviewed and agreed annually.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
79
Table 23: Current Operation and Maintenance SLA Costs (2017/18)
SLA Ref Description Annual SLA Value (2017-18)
5 Totara Road WWTP $1,233,000
6 Ashhurst Pond and Pump Station $29,000
8 Linton Pond Pump Station $3000
9 Wastewater Pump Stations $220,000
87 Wastewater Reticulation Maintenance $425,000
235 Minor Wastewater Reticulation Works $55,000
1109 Cogen No. 2 (Totara Road WWTP) $200,000
1909 Trade Waste Management $153,000
Total $2,318,000
To operate the wastewater activity City Enterprises employs 7.5 FTE (full time equivalent) staff to operate the pump station and treatment plant. This is supplemented by 6 FTE staff to carry out wastewater maintenance. The organisational structure of the City Enterprises team is shown in Figure 27.
Figure 27: Wastewater Treatment Operations & Maintenance Staff
Operations staff are contracted to provide wastewater services on a 24 hours a day, 365 days a year basis, including customer response (Request for Services), and an emergency response capability.
All City Enterprises staff receives an appropriate level of training, including specific Health & safety training and specialised equipment training. For the WWTP staff are trained to a minimum of NZQA level 4 in Wastewater Treatment Plants.
6.9 Renewal of Assets
6.9.1 Overview
Asset renewal is major work which restores, rehabilitates, replaces, or renews an existing asset to extend its economic life and/or restore its service potential. Work over and above restoring an asset to its original capacity is classed as development work.
Renewals may be carried out for two primary reasons:
Maintain the asset service potential – this may be either the quality of service or reliability of service.
Treatment Plant Manager (0.5 FTE)
Senior WWTP Technician
(1 FTE)
WWTP Operators (4 FTE)
Maintenance Fitter
(0.5 FTE)
Trade-waste Officer (1 FTE)
Treatment Plant Project Manager
(0.5 FTE)
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
80
Minimise the whole life cycle cost of the asset.
The decision to renew an asset will be based on:
Criticality (consequence of failure); Condition (and therefore remaining useful life); Performance; and Value.
There are two options for a renewal project:
Rehabilitate or refurbish the asset; or Replace the asset like for like.
Renewal literature often refers to renewals options to upgrade/downgrade or alter the asset to meet other service requirements. For the purpose of this AMP, this is considered development work.
6.9.2 Renewal Strategies
Renewal decisions are made based on criticality, condition, and asset performance. Critical assets should not be allowed to fail, and programmes need to be organized to replace or renew critical asset prior to the expected failure date. Typically assets maintain performance for most of their lifecycle and deteriorate quickly towards the end of their useful life.
Renewal of assets must be carefully considered, as early replacement leaves unused value in the ground, while delayed replacement causes loss of service and costly repairs. Overall performance of the network is carefully monitored to identify areas where renewals are required. Renewals can also be brought forward or delayed in some cases to co-ordinate with the road renewals program.
A Wastewater Pipe Renewal Strategy has been developed to help determine the specific location and timing of pipe renewals moving forward. The strategy has formalised the I&I reduction focus discussed in this document. This document is reviewed annually and progress assessed against targets.
6.9.3 Long Term Renewal Profile
The expected lives used for calculating the replacement year is shown in Table 24.
Table 24: Life Expectancy of Wastewater Assets
Asset Type Expected Asset Life
Wastewater Assets
Wastewater Pipes Standard Manhole
100-175 150
Wastewater Pump Stations
Civil Structures Pipework Mechanical plant e.g. pumps Electrical Equipment
100 80
10-35 15 - 25
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
81
Asset Type Expected Asset Life
Wastewater Treatment Plants
Buildings and civil works Electrical Mechanical Pipework Electronic equipment
100 30 30 50 15
These asset lives have been determined through standard asset lives as set out in the II manual Asset Valuation Guidelines and from our own inspection and condition records.
Figure 28 shows the 50 year renewal profile for the wastewater pipes based on the expected asset life. The renewal profile is based on age and expected asset life, which was reviewed by AECOM as part of the 30 June 2017 re-valuation. It does not currently account for actual asset condition and performance.
Figure 28: Wastewater Pipes Profile Based on Expected Asset Life
6.9.4 Renewal Programme
Council uses a combination of several methods to develop the renewals programme:
Forward projection of historical costs combined with broad estimates of asset depreciation. Predictive modelling based on age. ‘Bottom up’ or ‘unconstrained work bank’ approaches based on available condition information and
operator knowledge.
The current wastewater renewals programme comprises the following on-going renewals programmes:
Wastewater pipes. Wastewater pump stations. Wastewater Treatment Plant minor mechanical/electrical works.
$0
$1
$2
$3
$4
$5
2015
-16
2020
-21
2025
-26
2030
-31
2035
-36
2040
-41
2045
-46
2050
-51
2055
-56
2060
-61
Rep
lace
men
t Val
ue [$
M]
2014 Valuation Pipes Exceded Expected Life
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
82
The value of these programmes has largely been based on historical cost in conjunction with age profiles. Major plant items are also included where known. At this point in time, the age of the pipeline asset has been used as an indicator of remaining useful life, but is otherwise not a significant factor in determining the renewals programme. The renewals programme will be substantially reviewed as a result of the current wastewater network modelling project. Further work will be undertaken to refine the renewal programme to take into account pipe criticality, vulnerability and resilience. These on-going programs are supplemented by specific renewals projects for larger trunk mains. A series of renewals projects have been identified based on asset condition and performance, and targeted investigations.
An on-going CCTV inspection contract has been awarded, in conjunction with a newly developed wastewater main inspection programme which is focused on the critical/larger pipelines in the network but also includes a selection of the smaller less critical pipes. The initial inspection programme is based on age, diameter and criticality. The outcome from these inspections will help define the renewal programme moving forward.
Figure 29: Definition of inspection groups by age, diameter & criticality
Table 25 summarises the proposed renewals program expenditure. Given the age of the Totara Road WWTP there are a significant numbers of plant renewals within the programme, given many of the structures on the site reach the end of their useful life in the coming AMP period. At this stage the renewal requirements for the WWTP will need to be confirmed as part of the planning and options assessment being completed under the wastewater BPO project.
Asset renewal issues relating to each asset group are discussed below.
Tabl
e 25
: R
enew
als
Prog
ram
me
Expe
nditu
re –
Fiv
e Ye
ar F
orec
ast
Prog
ram
me
2018
/19
2019
/20
2020
/21
2021
/22
2022
/23
2023
/24
Ris
k if
Def
erre
d
Colle
ctio
n Ne
twor
k
54-C
ity-w
ide
- Was
tew
ater
Pip
e R
enew
al
$1,6
00,0
0 $1
,800
,000
$2
,000
,000
$2
,000
,000
$2
,000
,000
$2
,000
,000
Fa
ilure
to m
eet l
evel
s of
ser
vice
. St
ruct
ural
failu
re.
65-C
ity-w
ide
- Was
tew
ater
Pum
p St
atio
n R
enew
al
$150
,000
$1
25,0
00
$137
,000
$8
5,00
0 $5
7,00
0 $4
0,00
0 Fa
ilure
to m
eet l
evel
s of
ser
vice
.
1351
-Eas
tern
Tru
nk m
ain
– H
okow
hitu
cam
pus
$2
50,0
00
Failu
re to
mee
t lev
els
of s
ervi
ce.
Stru
ctur
al fa
ilure
.
1378
-Ben
nett
Stre
et 5
25 T
runk
mai
n re
new
al
$170
,000
$1
70,0
00
Failu
re to
mee
t lev
els
of s
ervi
ce.
Stru
ctur
al fa
ilure
.
1379
-Max
wel
l’s L
ine
825
Trun
k m
ain
Ren
ewal
$250
,000
$250
,000
St
ruct
ural
failu
re.
Colle
ctio
n Ne
twor
k Su
b-To
tal
$1,7
50,0
0 $2
,425
,000
$2
,307
,000
$2
,255
,000
$2
,057
,000
$2
,290
,000
Was
tew
ater
Tre
atm
ent
179-
Tota
ra R
d W
WTP
- M
inor
Equ
ipm
ent R
enew
als
$130
,000
$6
0,00
0 $1
00,0
00
$50,
000
$50,
000
$50,
000
Failu
re to
mee
t lev
els
of s
ervi
ce.
1380
-Tot
ara
Rd
WW
TP -
Biog
as G
ener
ator
Maj
or
Ove
rhau
ls
$150
,000
$3
00,0
00
Incr
ease
d ris
k of
sig
nific
ant e
ngin
e fa
ilure
1059
-Tot
ara
Rd
WW
TP -
Rep
lace
men
t of G
rit
Rem
oval
Sys
tem
s 9
$495
,000
Poor
leve
l of s
ervi
ce c
ontin
ues
due
to n
o re
duct
ion
in
wea
r and
tear
in re
st o
f pla
nt
1067
-Tot
ara
Rd
WW
TP -
Rep
lace
men
t of S
ecur
ity
Fenc
e an
d G
ate
$250
,000
Failu
re to
mee
t lev
els
of s
ervi
ce.
1068
-Tot
ara
Rd
WW
TP -
Rep
lace
men
t of I
nlet
Pu
mps
10
$918
,000
$7
80,0
00
Failu
re to
mee
t lev
els
of s
ervi
ce.
Pum
ps u
nabl
e to
co
pe w
ith in
flow
s le
adin
g to
ove
rflow
s in
to th
e en
viro
nmen
t
Was
tew
ater
Tre
atm
ent S
ub-T
otal
$1
,943
,000
$6
0,00
0 $1
00,0
00
$830
,000
$5
0,00
0 $3
50,0
00
TOTA
L $3
,693
,000
$2
,485
,000
$2
,407
,000
$3
,085
,000
$2
,107
,000
$2
,640
,000
9 T
o be
des
igne
d fo
r gr
owth
whi
ch is
est
imat
ed to
be
20%
incr
ease
in c
apac
ity.
Ren
ewal
figu
res
are
80%
of t
otal
pro
gram
me
budg
et.
10 F
irst t
wo
of fo
ur p
umps
. R
emai
ning
two
pum
ps to
be
repl
aced
in 2
021/
22.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
84
Wastewater Collection Network
In the absence of comprehensive network condition assessment, the life cycle predictions were based on asset age and an average expected useful life of 120 years. This is no longer the case following a project undertaken to develop a forward renewal programme based on criticality, resilience, vulnerability and condition assessments amongst other factors. The renewal expenditure is forecast to rise to an average of $2.18 million per year over the next 5 years in order to maintain the service potential of the assets and to meet the higher levels of renewals that fall due during the period 2022 - 28. It is expected that a small percentage of pipes will come to the end of their useful life before their predicted life is reached, due to accelerated corrosion, unforeseen structural loading, or other causes. Likewise, some assets will last longer than their predicted life.
The renewal programme is detailed further in the Wastewater Pipe Renewal Strategy11 and has been refined as more condition assessment information became available from CCTV inspections. The risk associated with the deferral of the renewal works include:
Increased maintenance costs. Unacceptable incidence of wastewater surcharges and overflows during storm events.
To minimise the cost of asset ownership in line with the cost/affordability level of service, full life cycle costs and asset optimisation are considered when assessing options for renewal. The Wastewater Pipe Renewal Strategy recommends integrating pipeline renewal with I&I control efforts to optimise expenditure and minimise the risk. This is to be achieved by targeting renewal initially on older pipe networks in those catchments which have been identified as worst affected by I&I, and where the I&I reduction would provide system capacity most effectively. The targeted catchments are Tremaine Ferguson and College (refer Figure 21).
A study has also been undertaken to assess the impacts of the expanded NEIZ on the downstream network (GHD Consultants, June 2014).12 The recommendation of this study was that I&I reduction work should be undertaken in the Milson and Cloverlea catchments to assist in deferring capacity upgrades in the Western Trunk in order to accommodate additional flows from the NEIZ area. To date, no investigations have been undertaken in these catchments, but they will be included in future I&I works. Separately work to develop design guidance and a network design for a pressure sewer network to service the NEIZ has been commissioned in order to determine the actual flow capacity required. It is expected that the pressure sewer network will allow for deferral of the Western Trunk capacity upgrades.
Indications are that the existing level of service provided is generally satisfactory, and there are no significant assets past the optimum renewal point in their life cycle. Renewal of a pipeline may be brought forward from its predicted useful life if it is considered that this will significantly contribute to reduction in I&I problems. When a major road or underground services upgrade or renewal is planned, the condition and performance of the wastewater network in the affected vicinity is investigated to determine whether its renewal is justified to offset reduced rehabilitation costs. One example of reprioritisation was the advancing of sewer renewal work in The Square (Fitzherbert to Main Street West).
A five year plan of future network renewals has been included in the Wastewater Pipe Renewal Strategy, and this has been added to as further condition assessments have been undertaken. Condition assessment of recently CCTV inspected pipelines revealed that most pipelines are structurally sound. In many cases, the structural condition and performance grading of some pipes can
11 PNCC, Wastewater Pipe Renewal Strategy, July 2014 – DM 845504
12 GHD, North East Industrial Zone Extension, Wastewater Capacity Assessment, June 2014. DM 1147421
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
85
be greatly improved by renewing or rehabilitating a small section of problematic pipeline, rather than a complete replacement from manhole to manhole. This can be a very cost effective way to extend the useful life of a pipeline, and is adopted as one of the renewal strategies where appropriate.
Renewal options include various pipe rehabilitation techniques or replacement with new pipe material, and the use of trenchless technology (pipe relining) where appropriate.
Pump Stations
Renewals have historically been forecast based on asset age, condition, and performance. For this AMP, site specific renewals out to 2048 have been forecast that include works such as major electrical equipment renewals, standby generators, and pumps. Based on the asset lives and historical trends, the long term pump station renewal expenditure averages $50,000 per annum with an increased rate of expenditure forecast in the first 3 years to address some legacy electrical and control system issues.
It is considered that there are currently no deferred pump station renewals. Indications are that the existing level of service provided is generally satisfactory, although additional flow monitoring is now a priority to better understand high inflow catchments and pump stations at risk of overflow in wet weather events. There are no significant assets past the optimum renewal point in their life cycle.
Treatment Facilities
Identified renewal needs are based on end of asset life predictions, condition, performance, and life cycle cost estimates, and have been included as separate programmes where known. The life cycle predictions are based on historical information including asset age, performance, and condition. An additional consideration in developing renewal programmes is asset criticality and the consequence of asset failure in terms of consent compliance and public health.
Based on known condition issues, assessed maximum asset lives and criticality assessments, a 5 year schedule of specific treatment plant has been developed, with budgets required varying between $60,000 and $130,000 depending on the scope of work required. This renewal profile drops away to $20,000 per annum based on the assumption that the majority of the treatment plant will be upgraded or replaced assuming the implementation of new consent requirements from 2023/24.
During the past 3 years a number of major plant items have been or are being renewed or replaced. These include renewal of both digester lids, replacement of the inlet screens and inlet gate, and refurbishment of the existing sedimentation tanks. Indications are that the existing level of service provided is being maintained and there are no significant assets past the optimum renewal point in their life cycle.
6.9.5 Delivery of Programme
The programme will be delivered by either Council’s in-house resources, primarily for the wastewater pipe renewal programme, or by external contractors for more specialised works. The delivery method chosen will depend on the size and complexity of each individual programme. The Project Status reporting programme is used to track the progress of individual projects that make up the overall programme to ensure both the timeliness of delivery and costs. This system also enables delivery of reports to the monthly Works Programming meetings in which the progress of each project is reviewed.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
86
6.10 Development of Assets
6.10.1 Overview
Development includes the creation or acquisition of a new asset that did not previously exist, or works which upgrade or improve an existing asset beyond its existing capacity. Development work may be necessary for the following reasons:
Growth and increase in demand. Changes to Council policy and strategy. Changes to regulations and legislation. Changes to levels of service.
Development of assets may also include disposal of an existing asset that is no longer required.
6.10.2 Development Strategies
The development strategy is to provide for the progressive upgrading of assets to ensure future demand and changing service standards (i.e. resource consents) are achieved.
The selection criteria for the prioritising and programming of development projects will be based on a consideration of risk and benefits, affordability, ranking with other expenditure, existing asset performance with respect to levels of service, and life cycle costs and efficiency.
Proposed projects will be supported by an economic appraisal using cost/benefit analysis techniques which take into account:
Capital costs; Any change in net annual operating costs; Any change in annual maintenance requirements; and Any salvage value of existing assets or components.
All development projects require completion of a Programme Planning and Implementation Plan (PPI) to ensure that reasons for the project, options, costs and risks are considered. Significant projects will also require a Project Execution Plan (PXP) before proceeding.
The design option chosen shall:
Minimise the impact of urbanisation on water quality. Utilise the full capacity of existing infrastructure wherever practicable. Optimise life cycle costs for the assets created.
The risk, costs, and benefits of accepting new privately funded assets constructed in association with property development will be reviewed, and a decision regarding approval will be made on a case-by-case basis by Council staff. When satisfactorily completed in accordance with approvals given, Council will accept such assets into public ownership. Council will not contribute to the cost of such works unless there are exceptional levels of service or equity issues.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
87
When considering disposal options, all relevant costs of disposal will be considered. These may include:
Evaluation of options; Consultation/advertising; Obtaining resource consents; Professional services, including engineering, planning, legal, survey; Demolition/make safe costs; and Site clearing, decontamination, and beautification.
6.10.3 Development Programme
The capital development programme is the upgrade of existing infrastructure or new works that are needed to ensure that the wastewater activity can meet the future needs of the City. The need to upgrade or provide new assets may be due to the following drivers:
Increase the capacity of the assets due to growth in population of the City. This may be due to infill development or for a new sub-division or growth area.
Upgrade assets to meet new regulatory or legislative requirements. This could include areas such as health and safety regulations, changes to resource consent conditions, or changes to national legislation such as National Policy Statements.
Improvements to assets to meet changes in Council policy or strategies, and agreed changes to the level of service.
Development work to cater for population growth may be funded directly by the developer, or may be provided by Council in advance of the development work occurring and then funded through subsequent development contributions.
Development of the collection network over the past five years has largely been further extensions of the network into the current two urban growth areas of Kelvin Grove and towards Aokautere. The majority of these new assets were constructed by developers and then vested to the City Council as a result of new sub-divisional developments.
Other major development works completed recently include:
2007/08 – 475mm trunk main construction in Railway Rd between Setters line and Roberts Line to support industrial growth.
2013/14 – 450mm upgrade of Western trunk between Railway Rd and McGregor Street.
The above works were recommended in the 2001 Sewer Network Management Plan to provide the additional capacity to avoid sewage overflows in the vicinity during storm events.
The future development programme expenditure is summarised in Table 26 below.
Table 26: Development Programme Expenditure
Project Growth % LOS % Expenditure Timing
Collection Network – Reticulation
73 Wastewater Subdivision Contributions 100 - $50-100k pa On-going
210 Urban Growth - Installation of Wastewater Systems for New Industrial Areas - NEI extension area 100 -
$350k $350k
2018-20 2022-28
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
88
Project Growth % LOS % Expenditure Timing
452Tremaine/Featherston - Wastewater Trunk Main Upgrade 20 80
$110K $300K
2028/29 2031/32
624 North East Industrial Zone - Downstream Wastewater Network Upgrade - McGregor Street to Rennie Avenue to Peters Avenue
100 - $1.0M $1.9M
2024/25 2028/29
660 Ferguson Street - Wastewater Trunk Main Upgrade 50 50 $670K 2025/26
1000 Urban Growth - Whakarongo - Installation of Wastewater Systems 100 -
$862K $267k
2018-19/20 2022/23
1043 Totara Road WWTP Inlet Main Duplication 100 - $450k 2018/19 to 2019/20
1055 Urban Growth - City West - Installation of Wastewater Systems 100 - $1.2M 2019/20 to
2023/24
1412-Urban Growth – Ashhurst WW Network Upgrade 100 - $260K 2019/20
Collection Network – Pump Stations
1000 Urban Growth Whakarongo – Installation of Wastewater Systems 100 - $1.1M 2018/19 to
2022/23
Wastewater Treatment
628 Consent Renewal Upgrade 20 80 $110M 2023/24 to 2026/27
1074 Earthquake Strengthening of Civil Structures - 100 $1.1M 2018/19 to 2019/20
1382 Totara Rd Emergency Bypass Upgrades - 100 $100k 2019/20
1383 Emergency Overflow Structure Totara Rd - 100 $150k 2020/21
Projects to Support Growth & Increase in Demand
The following projects are attributed directly to growth as a result of new residential and industrial/commercial developments. Note that wastewater infrastructure to service the proposed growth areas will not proceed until the necessary land use zonings are in place, and investor commitments to the developments have been confirmed.
Residential Rezoning
The Residential Growth Strategy provides for growth through rezoning of the Whakaongo area followed by City West. Typically, the developer will fund and build the wastewater network within its development. However, the Council will need to extend its trunk network to service these developments, which will involve downstream trunk network upgrades and dealing with options for the treatment of their wastewater (refer programmes 624, 452, 1000 and 1055).
Industrial Rezoning
Further provision has been made in this AMP for extension of the NEIZ. It assumes development of approximately 120 ha of land in the vicinity of the existing industrial site. Development of the required utility and road infrastructure is assumed to take place over years three to seven of this AM planning period. It has been assumed and that there will not be any major wet industries for the new zone (refer programmes 210 and 624).
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
89
Pump Stations
Pump stations have been added to the system over the years, mainly to enable low lying areas of the City to be developed. The most recent additions have been the Coutts Way and Freedom Drive wastewater pump stations and these were fully funded by the developers.
It is assumed that most new pump stations will be associated with sub-divisional development, and funded at no cost to Council. There will only be costs to Council if the City wishes to extend the capacity of a developer funded pump station at the time of construction to allow for the needs of an extended area.
The exception to this is the proposed new pump station to be constructed on James Line, at the Napier Road intersection, to service the Whakarongo growth area. A proposed expenditure of $500,000 has been included in 2018/19 to enable construction.
Collection Network
The Wastewater Network Management Plan Review (2001) concluded that the lower sections of the Western, Tremaine, and Featherston Trunk Systems would require some capacity upgrades due to demand growth from developing upper catchment areas, such as Kelvin Grove and NEIZ. The timing of these upgrades has been modified in light of recent studies undertaken (GHD Consultants, June 201413), and in some cases, may even be able to be deferred. There are four separate lengths of trunk main identified for upgrade works as follows:
Western trunk duplication of the 450 mm diameter main from the McGregor Street confluence to Rennie Avenue (length estimated at 1,630 metres);
Western trunk duplication of the 525 mm diameter main downstream of Rennie Avenue to just beyond the end of Peters Avenue (length estimated at 3,290 metres);
Tremaine Ave and Featherston Street upgrade; and And the Ferguson trunk upgrade in 2026.
The Western trunk duplications can be deferred or possibly dropped altogether if the total flows out of the expanded NEIZ are limited to 20 m3/ha/day or less (GHD, June 2014). I&I reduction works in the Milson and Cloverlea catchments may also help defer upgrades. In addition it is proposed that the expanded NEIZ now be serviced through a pressure sewer system which would be expected to reduce flows from the zone further
Various servicing scenarios were modelled for the proposed City West zone (GHD, June 2014), and a low pressure sewer (LPS) system was recommended for this growth area.
The advantages of an LPS are twofold:
It reduces the level of demand placed on the trunk network by smoothing out the flows and lowering peak flows from the area; and
It is more resilient in high liquefaction zones, such as City West, as they avoid the need to lay wastewater pipes on grade. The PE pipe typically used in LPS systems is also better suited to resisting seismic movements.
The ownership model adopted for any LPS or Vacuum Pressure System (VPS) will need to be approved by Council prior to designation of the area as a pressure sewer area. The preferred approach will be for Council ownership of the on property pump station and connecting pressure connection so
13 GHD, North East Industrial Zone Extension, Wastewater Capacity Assessment, June 2014. DM 1147421
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
90
as to ensure approved equipment and installation and cost effective maintenance (refer programmes 452, 660 and 1043).
Sub-Divisional Contributions
A nominal amount of $100,000 per annum is budgeted for contribution towards building extra infrastructure capacity when a sub-divisional development first takes place to allow for future capacity requirement of subsequent development. This cost will be recovered from future developers by way of development contributions (refer programme 73).
Totara Road WWTP Primary Treatment Duplication
This programme has now been deferred and will be addressed through the WWTP BPO process.
Projects to Support Changes to the Level of Service
Totara Road WWTP Treatment Process Upgrades
The assumption in this AMP is that significant new developments at the Totara Road WWTP will not occur until after new resource consents are granted most probably in 2023-24. The current consents are due to expire in 2028, but the Council has agreed to apply for new consents by June 2022.
It is anticipated that there will be higher environmental and water quality standards to be met, as well as higher expectations from the community when the new consents are applied for. It is inevitable that new treatment processes and upgrades of the treatment facilities will be required to meet those objectives. Resulting from the recent consent review undertaken by Horizons it was also agreed that a more extensive Best Practicable Options investigation would be undertaken with the outcome forming the basis of the new consent application.
Totara Road WWTP Sludge Disposal
Currently all sludge produced from the wastewater process is dewatered and then composted on the neighbouring Awapuni Resource Recovery Park. A sludge disposal options study was undertaken and this will guide the ultimate decision on new technologies that might be used to treat treatment plant sludge’s. It is proposed that the ultimate decision on sludge disposal will be part of the WWTP BPO exercise and subsequent consent renewal upgrade.
Seismic Strengthening to Wastewater Structures
(Refer programmes 630 and 1074).
6.10.4 Delivery of Programme
The programme will be delivered by Council’s in-house staff, or external contractors for more specialised works. The delivery method chosen will depend on the size and complexity of each individual programme. The Project Status reporting programme will be used to track the progress of individual projects that make up the overall programmes to ensure both the timeliness of delivery and costs. This will deliver reports to the monthly Works Programming meetings in which the progress of each project is reviewed.
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
91
6.10.5 Non Asset Programmes
Education initiatives were identified in the level of service workshops with councillors as a means of addressing a number of challenges in the wastewater network including:
blockages due to wet wipes opportunities to reduce nutrient loads e.g. phosphorus by engaging with trade waste dischargers
and reviewing opportunities at the residential scale introduction of a programme to receive hazardous household chemicals and divert them from
discharge to the sewer and stormwater network targeting inflow and infiltration reduction at the property level by establishing a dedicated I&I
reduction programme identifying commercial activities in the residential area that require pre-treatment e.g. grease traps
etc.
6.10.6 Disposal of Assets
Any assets that require disposal will be done so in the most advantageous way. For some assets, this will involve sell by public tender via Tender Link or other publications. For minor or broken/damaged assets, disposal may be by way of direct sale to metal recyclers or similar recycling facilities.
6.11 Key AMP Improvement Projects Relating to Asset Lifecycle Management
For the key AMP improvement projects relating to wastewater Asset Management and Lifecycle Management, refer to the following items in, Section 11 Continuous Improvement:
Item 1, Development works planning (demand/LoS): Document changes to AMP programmes that arise through 10 Year Plan and Annual Budget
process. Item 2, Asset information:
Update detailed asset component and condition information in AM system; Review AM system data quality process and develop data improvement plan: Review condition assessment programme; Review performance data needs; Analyse asset lives using available data; and Assess advanced AM system needs and implement suitable application for predictive modelling Update programme policies and information data.
Item 3, Renewal works planning: Continue to develop predictive modelling; and Develop processes to prioritize risk mitigation options (Section 2 of Improvement Plan).
Item 4, Operations and maintenance: Work on optimising operations and maintenance programmes; and Further develop processes to ensure competitive prices are obtained.
Item 9, Delivery of services: Improve internal service processes (SLA, Market Comparability &CWP).
Section 6 – Assets & Lifecycle Management Asset Management Plan 2017 – Wastewater
92
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
93
7 Risks & Resilience Infrastructure risk management is the process of identifying risks that may affect the ongoing delivery of services from infrastructure.
7.1 Corporate Risk Management Framework
A corporate risk management policy (MT 76, April 2011) has been established to enable risks to be managed in an effective and appropriate manner. From an asset management perspective, the policy helps prevent the Council taking risks that compromise its ability to provide and maintain key infrastructure and services. Progress with mitigation actions is monitored and reported to Council.
7.1.1 Risk Management Policy
The risk management policy covers strategic, operational, and project risks. It applies to all functions performed by the Council and to all staff employed in carrying out its functions.
Strategic risks are defined as those things that prevent the Council from implementing its strategies. They can be caused by misalignment between goals and strategies, or the Council simply not implementing its strategies.
Operational risks are inherent in the processes chosen to implement the Council’s strategies. The benefits of managing operational risks include meeting financial goals, maintaining quality, proactive and effective planning, and preparedness for emergencies.
Project risks are of a specific, normally short-term nature. The benefits of managing these risks include the avoidance of time and cost overruns
7.1.2 Strategic Risks
The key strategic risks to the Council achieving its desired outcomes have been identified as follows:
Poor City image and reputation. Lack of vibrancy in the CBD. Decline in the City economy and jobs. A low level of community trust and engagement with the Council. Council’s financial position is not sustainable.
These risks are mitigated through following the Council strategies set out in Section 3.1 and through quarterly reporting to the Council. Development and management of the Council’s infrastructure is part of this risk mitigation.
7.1.3 Operational Risks
Operational risks identified in the Risk Management Policy, relevant to this activity, are contained in Table 27.
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
94
Table 27: Operational Risks
Operational Risk Corporate Mitigation Strategy Corporate Mitigation Action
Council's infrastructural assets are not managed in accordance with the adopted Asset Management Plans (AMPs) and/or granted Resource Consents
1. Manage infrastructural assets in accordance with AMPs as funded through the 10 Year/Annual Budget
1.1 Review AMPs three yearly, assessing assets over a 30 year period to increase certainty to condition assessments.
1.1.1 Seek continuous improvement of each AMP in terms of quality that matches “best practice” in NZ.
1.1.2 Incorporate consideration of city growth, climate change, urban design and environmental sustainability into each AMP.
1.2 Report to Council where necessary implications of difference in budgets between 10 Year Plan with AMPs, and determine revised asset management actions.
1.2.1 Ensure Infrastructure programmes aligned with the zoning for growth.
1.3 Implement infrastructural programmes (operations and maintenance, renewals and capital new).
1.3.1 Programmes associated with the Totara Road Wastewater Treatment Plant (WWTP) and closed Awapuni Landfill, in respect to their impact on the Manawatū River.
1.3.2 Programmes associated with cycle/pedestrian pathway, in respect to property negotiations and Community stakeholders engagement.
2. Ensure infrastructural asset programmes developed for the AMPs and then presented for consideration in the 10 Year /Annual Budget have adequate justification in terms of assessing options, feasibility, economic, social and environmental factors.
2.1 Develop programme justification for the AMPs to feed into the annual planning process
Council's infrastructural assets are not managed in accordance with the adopted Asset Management Plans (AMPs) and/or granted Resource Consents
3. Operate infrastructural asset activities in compliance with the granted Resource Consents
3.1 Maintain a database of all required Resource Consents
3.2 Monitor compliance against the database
3.3 Attend to Resource Consent renewals before expiry deadlines
4. Operate infrastructural asset activities in a manner that uses the AMP risk register .responses for specific risk situations as and when these may arise
4.1 Report quarterly on infrastructural asset activities against the appropriate AMP Risk Register items in terms of invoking any of the "controls", "treatment" and/or "management options".
Council does not deliver the capital (new and renewal) programmes within approved scope of works, planned timeframes and budget.
1. Set realistic capital revenue and expenditure budgets
1.1 Use City Networks Programme Planning and Implementation Template, identify and update (at least annually) the status of programmes in respect of scope, assumptions, and planning milestones, budget estimates and funding sources.
1.2 Within the City Networks Programme Planning and Implementation Template
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
95
Operational Risk Corporate Mitigation Strategy Corporate Mitigation Action
identify the external factors which must be addressed to advance the programme and establish appropriate milestone dates as to when these factors will be addressed.
1.3 Information in the Programme Summary of the Ozone Corporate Planning module is referenced against an up to date City Networks Programme Planning and Implementation Template.
1.4 Identify as potential “delayed flags” those capital programmes which have constraints beyond management’s control as part of the budget approval process
1.5 At the commencement of the financial year identify those capital programmes where there is confidence of delivery because contracts (& SLAs) are in place.
1.6 At the commencement of the financial year identify those capital programmes where planning is well advanced such that contracts (& SLAs) can be established in the 1st quarter of the financial year
2. Scrutinise all capital revenue and expenditure budgets exceeding $250k.
2.1 Signed off by the relevant General Manager
2.2 Review budget for reasonableness (all individual capital budgets)
3. Obtain Management Team approval on all capital projects that require a Project Execution Plan (PEP) before commencement of the project
3.1 Active management by General Manager
3.2 Report to Chief Executive of all non-compliance instances
4. Assess resources required to deliver the overall capital programmes
4.1 Use the Works Programming Forum both City Networks and City Enterprises identify the internal resources to be allocated to programmes and then determine any shortfall which requires the engagement of external consultant/contractor resources.
5. Manage projects against recognised good practice.
5.1 Deliver projects in accordance with City Networks Asset Management Good Practice Guidelines in relation to Project Management discipline.
5.2 Develop and regularly review Project Execution Plans (PEPs) for significant projects, with specific attention to any change circumstances which may impact on scope of works, timelines and/or budget requirements
6. Monitor progress in the delivery of capital programmes
6.1 Monitor progress through Works Programming Forum
6.2 Monitor progress of work through monthly financial reports, and the Project Status Reporting tool both actual year to date against the current financial budget and against the total project budget spanning more than one financial year.
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
96
Operational Risk Corporate Mitigation Strategy Corporate Mitigation Action
6.3 Identify programmes which cannot be delivered due to changed circumstances giving the reason why.
6.4 Utilise Council's approval of commencing up to 20% renewal works prior to the formal adoption of the new financial year budget
PNCC is not meeting its responsibilities for an emergency or a civil defence emergency event because it is unable to deliver the basic services.
1. Develop and maintain high level PNCC Business Continuity Plan(s) (BCP)
1.1 Prepare and maintain high level PNCC Business Continuity Plans (BCP)
Council's activity preparation in key areas does not align to the 10 Year Plan programmes approval and budget processes and vice versa.
2. Ensure integrated planning occurs across Council’s recreation assets
2.1 Concept and development plans are developed for Council’s recreation facilities and reserves aligned to the Active Recreation Strategy
2.2 10 Year Plan recreation programmes for the first 3 years are informed by soundly-based development plans
3. Implementation of the Street Design Manual
3.1 Programme of work is developed to implement the Street Design Manual
3.2 10 Year Plan levels of service align with changes promoted in the Street Design Manual
3.3 10 Year Plan Programmes advance implementation of the Street Design Manual and for the first 3 years are informed by soundly-based development plans
7.1.4 Project Risks
Project risks associated with significant individual projects (both operational and capital) are normally of a short term nature and are managed through specific project plans approved through the Corporate Management Team. They include acquisitions and investments.
7.1.5 Risk Management Hierarchy
Figure 29 demonstrates the risk management hierarchy from corporate risk management down to activity, project specific, and operational risk management. Risk is managed at these various levels within the Council’s risk management framework. The level of risks included at each layer is appropriate to that layer, but filters down where appropriate with increasing detail.
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
97
Figure 29: Risk Management Hierarchy
Within all the levels of risk management discussed above, consideration is given to the management of both “everyday” risks and the low frequency high impact events such as natural disasters.
When existing assets are being renewed or new works constructed, the potential of those works to affect the resilience and readiness of all lifeline networks is considered. Contingency plans are prepared to ensure, through operational systems and temporary response structures, that appropriate response can be made.
7.1.6 Asset Criticality
Those assets where failure would likely result in a significant disruption in service and financial, environment, and social cost in terms of impact on organisational objectives are considered to be critical assets. The definitions used in this plan for critical assets, customers, and suppliers are as follows:
Critical assets are defined as those assets with the highest consequence of failure, but not necessarily a high probability of failure. In determining consequence of failure, both importance to the city and importance to the service provided are taken into account.
Critical customers are those relying on essential services provided by the Council (e.g. water supply to schools and hospitals).
Critical suppliers are those providing services required for the delivery of the Council’s essential services (e.g. energy supply, communication systems, etc).
The criteria used to assess criticality are set out in Section 7.2.3.
7.1.7 Resilience
The National Infrastructure Unit defines resilient infrastructure as infrastructure that is able to deal with significant disruption and changing circumstances. This may be due to natural hazards and shock events or events which evolve over time such as changing demographics. However, this plan is largely focused on being able to provide essential services following a high consequence event such as a natural disaster. Resilience of critical assets is particularly important for continuation of service delivery. Both technical and organisational aspects of resilience have been considered in this plan.
Operational Risk Management
Civil Defence Management
Activity Risk Management
Group Risk Management
Project Risk Management
Corporate Risk Management
Natural & Technologic
al Risks
Physical/ Asset
Failure Risk
Public Health &
Environmental Risks
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
98
Table 28: Resilience Definitions
Dimension Attribute Definition
Technical Robustness / Resistance
The strength or the ability of elements, systems, and other units of analysis, to withstand a given level of stress or demand without suffering degradation or loss of function.
Redundancy The extent to which elements, systems, or other infrastructure units exist that are substitutable, i.e. capable of satisfying functional requirements in the event of disruption, degradation, or loss of functionality.
Reliability The extent to which the infrastructure components are inherently designed to operate under a range of conditions and hence mitigate damage or loss from an event.
Organisational Preparedness, Response and Recovery
The capacity to mobilise resources when conditions exist that threaten to disrupt some element or system to maintain service and enable a fast and effective response to and recovery from disruptive events.
7.1.8 Risk Management Process
This plan is based on AS/NZS ISO 31000:2009 as the basis of its approach to risk identification and management. The Standard defines risk as the “effect of uncertainty on objectives”. Effective management of risk is important to maintain the performance and functionality of the Wastewater Activity. Risk management is one of the factors used to determine optimum maintenance frequencies and the level and timing of asset renewals. The risk management process considers the following stages:
Risk management context – determining the framework within which Council-wide risks will be managed.
Risk identification – identifying the relevant risks. Risk analysis – scoring or rating each of the risks identified in a way that makes them comparable
across the organisation. Risk treatment – identify the actions to be taken. Monitor and review the risks to ensure mitigation is successful and identify new risks.
This process is summarised in Figure 30 below.
Figure 30: Risk Management Process (AS/NZS ISO 31000:2009)
Further details of the process followed and the risk management register are given in Appendix D.
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
99
7.2 Activity Risk Management
7.2.1 Approach for the Activity
Risk assessments at the activity level focus on risks associated with management of the activity and the enabling infrastructure. Activity risk assessment considers risks identified at both the corporate and the operational level. Risk management planning has been used to identify the potential and actual business risks associated with the provision and management of the Council’s wastewater assets and services. The process has been applied to prioritise mitigation programmes.
The key risk categories adopted for assessing the consequences of identified risks for this activity are:
Legal; Environmental; Corporate Image; Service delivery; Financial; and Community Health and Safety.
A full list of the assessed risks facing this activity, including risks from natural events, is detailed in the Risk Register appendix. The Register also summarises the current mitigation measures and the proposed, or planned, changes to these.
7.2.2 Role of Activity as a Lifeline Utility
The Civil Defence and Emergency Management Act 2002 contains specific requirements in relation to Lifeline Utilities. The term “lifeline utility” is defined as an entity named or described in Part A of Schedule 1, or that carries on a business described in Part B of Schedule 1 of the Act.
The wastewater network is regarded as a lifeline utility. Section 60 of the Act states the duties of lifeline utilities:
“60. Duties of lifeline utilities
Every lifeline utility must—
(a) ensure that it is able to function to the fullest possible extent, even though this may be at a reduced level, during and after an emergency:
(b) make available to the Director in writing, on request, its plan for functioning during and after an emergency:
(c) participate in the development of the national civil defence emergency management strategy and civil defence emergency management plans:
(d) provide, free of charge, any technical advice to any Civil Defence Emergency Management Group or the Director that may be reasonably required by that Group or the Director:
(e) ensure that any information that is disclosed to the lifeline utility is used by the lifeline utility, or disclosed to another person, only for the purposes of this Act.”
The Act also has national and regional requirements, including the roles of Controllers, the establishment of Civil Defence Emergency Management (CDEM) Groups, and the preparation of CDEM Plans.
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
100
7.2.3 Critical Assets
Overview
Critical assets are regarded as those assets which have the highest consequences should they fail. A simple approach has been taken in this plan, applying broad assumptions about the implications of failure, using a number of criteria to make an overall assessment of high, medium, or low criticality. The approach to proactively managing risks is given in section 7.5.
The criteria used for assessing criticality for the Wastewater Activity are as follows:
Numbers of people adversely affected; Significant business activity interrupted; Consequential cost of failure; Critical lifeline/disaster recovery asset; and Other.
Critical assets are defined as those that have a high consequence of failure. By identifying critical assets, it is possible to target inspections, maintenance, and renewals expenditure in the most critical areas.
Criticality is graded as High, Medium, Low, or Non-critical, and is broadly based on the number of people affected by the asset failure. Table 29 contains the population banding used for Palmerston North.
Table 29: Population Based Criticality Grading
Criticality Population Affected
High Above 8,000 persons
Medium Between 6,000 and 8,000 persons
Low Between 4,000 and 6,000 persons
Non Critical Up to 4,000 persons
Wastewater Pipes Criticality Grading
Typically, larger diameter pipes serve larger populations. Using assumptions around a pipe’s capacity, it is possible to broadly categorise criticality of wastewater pipes based on diameter. The criticality grading of wastewater pipes is shown in Table 30.
Table 30: Criticality Grading for Wastewater Pipe Assets
Pipe Diameter [mm] Equivalent Population Criticality
250 2,973 Non Critical
300 4,823 Low
315 5,490 Low
375 8,750 High
450 14,238 High
525 21,488 High
600 30,693 High
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
101
Wastewater Pump Station Criticality Grading
In assessing criticality of pump stations, the sensitivity of the receiving environment to overflows is considered, as well as the population served.
Table 31 shows the criticality grading for the pump station that are categorised as Low criticality or above. Non-critical pump stations are not listed.
Table 31: Criticality Grading for Wastewater Pump Station Assets
Pump Station Capacity [L/s] Equivalent Population Served Criticality
College Street 59 5,098 Medium
Jickell Street 100 6,480 Medium
Massey 139 25,920 High
Maxwells Line 758 30,931 High
Tremaine Avenue 53 4,579 Medium
Ashhurst Pond 47 2,634 low
KB Road Bunnythorpe 13 451 Medium
Wastewater Treatment Critical Assets
Criticality of treatment plant assets is based on the consequence of failure of each component and its role as part of the treatment process overall.
Dependent Customers & Services
For details of customers or services that depend on the Wastewater Activity refer to “Report for Critical Assets - Vulnerability Review - Phase 1” (GHD, March 2011).14
7.2.4 Resilience
The approach taken in this plan is to assess the impact of particular natural hazards on the critical assets of the wastewater activity. This considers the current level and desired level of resilience. Section 7.4 summarises this assessment and Section 7.5 outlines the mitigation strategy adopted in this plan to reduce the risk. The interdependencies of other utility services are identified in Section 7.4.6.
Further work will be undertaken in the next 2-3 years to develop a more comprehensive approach, in which the level of criticality is matched against the desired level of resilience, together with the options available for achieving it. A programme for further work is included in the Improvement Plan.
7.2.5 Sources of Risk
The sources of risk affecting the activity are as follows:
Operational failures. Physical asset risks. Project & planning risks. Natural hazards. Events & Incidents. 14 GHD, Report for Critical Assets - Vulnerability Review - Phase 1, March 2011 (DM#995683)
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
102
Risks arising from these sources are elaborated on in Section 7.3.
7.2.6 Reference Documents
Documents that have informed this plan include:
1994 Hazards Analysis. 2005 Risks & Responsibilities – Lifelines Project Report. 2009 Hazard Risk Assessment for the Manawatū-Wanganui Region. 2011 GHD Critical Assets Phase 1 Report – Three Waters. 2011 GNS Liquefaction Report. 2011 City Infrastructure and Civil Defence Preparedness. 2014 PNCC Engineering Standards Resilience Review. PNCC District Plan Section 22: Natural Hazards – Floods.
7.3 Key Risks to the Wastewater Activity
The five sources of risk impacting on the activity are considered to be operational failure, asset failure, natural disasters, events and incidents, and project and planning risks. The risk register in Appendix D sets out the identified risks arising from these sources. The key risks largely based on criticality are summarised in this section.
It should be noted that from these sources there may be consequences in the following areas:
Legal; Environmental; Corporate Image; Service delivery; Financial; and Community Health and Safety.
These have been considered in identifying the key risks for this activity.
7.3.1 Operational Failure
Operational failures are those events that may prevent service delivery as intended, such as contamination, vandalism, operator error, injury, crash, or contract management issues, but do not involve a physical breakdown of the asset. The operational failure that occurs may also have other consequences, as noted above.
The key operational risks and mitigation measures for this activity are summarised in Table 32.
Table 32: Key Operational Risks & Mitigation Measures
Key Operational Risks Likelihood Mitigation Measures
Odours from the system (WW21) High Odour control devices. Chemical treatment. Tighter Trade Waste Controls.
Power Failure (WW18) Medium Continuous monitoring via telemetry. Standby generators (permanent & mobile).
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
103
7.3.2 Asset Failure
Asset failure can arise from deterioration in condition, leading to structural failure or loss of performance of the asset, which then impacts adversely on the service provided to the community.
The key risks relating to asset failure and mitigation measures have been identified in Table 33.
Table 33: Key Asset Failure Risks & Mitigation Measures
Key Asset Failure Risks Likelihood Mitigation Measures
Network blockage or breaks (WW17) High Ongoing condition assessments/investigations. Inflow & infiltration investigations. Programmed flushing. Public education regarding acceptable disposal practices.
Pump station failure (WW20) Medium Continuous monitoring through telemetry. Staff Training. Regular maintenance.
WWTP failure (WW19) Medium Continuous monitoring through telemetry. Staff training. Regular maintenance.
7.3.3 Project & Planning Risks
Project and planning risks occur when infrastructure is not provided in a timely way, or does not meet the needs of the community, as a result of inadequate project management and planning processes and resources.
The key risks and mitigation measures identified are summarised in Table 34.
Table 34: Key Project & Planning Risks & Mitigation Measures
Key Project & Planning Risks Likelihood Mitigation Measures
WW22 Network capacity failure due to lack of planning
Low Involvement with City Future Planning and Growth development.
7.3.4 Natural Disasters
The impact of natural disaster hazard events on the infrastructure of the Wastewater activity has been considered, with a particular focus on lifelines, critical assets, and interdependencies
The events considered are those used in the Lifelines Hazard Assessment:
Earthquake – an MM9 shaking intensity (return period 1000 years). Flood – equivalent to the 2004 Lower North Island flood event (return period of about a 100 years). Volcanic – an eruption of Mt Ruapehu with a 12 km high column.
There is further discussion in Section 7.4, which describes the hazards and assesses the resulting impacts on critical assets. The initial response will include those measures set out in the CDEM Group Plan and the Business Continuity Plan.
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
104
7.3.5 Events & Incidents
Other events and incidents that could impact on the assets and the services will be managed largely through the measures and procedures set out in the Business Continuity Plan (refer Section 7.7.3).
7.4 Resilience of Infrastructure to Natural Disaster
7.4.1 Introduction
This section considers the impact of seismic, flooding, and volcanic events on critical assets, and the assessed level of resilience to such events. It has been informed by the reports and investigations listed in Section 7.2.6. The Lifelines Project Report 2005 found that the region as a whole is most at risk from seismic hazard – in particular liquefaction could cause significant damage in a severe earthquake.
7.4.2 Seismic Hazard
The wastewater system has between 3 and 6 hours of storage in the event of power failure before overflow occurs. Backup power for most small pump sites is via a mobile generator maintained by City Enterprises, which must be moved from site to site. Permanent backup power is provided at the Massey and Maxwell’s Line pump stations and the Totara Rd WWTP. In the event of pump station failure, overflows occur to water courses. Failure or overloading of the treatment plant will result in overflow to the Manawatū River and/or the Mangaone Stream. The WWTP has backup power generation.
Because most of the sewer network is a gravity system, sewage could, assuming laterals are not damaged, still be received from most customers and disposed of via overflows, even when most pump stations and/or the treatment plant are not operating. However, a functioning gravity pipe network is essential.
A reasonable volume of water is also needed to ‘flush’ a toilet and keep a sewer pipe working – consequently, either the piped water supply system needs to be operational, or residents need ready access to bulk water storage for filling buckets or other containers. By-pass pumping could assist a partially damaged pipe network, although the city has very few pumps suitable for this duty, and these pumps would need to come from further afield.
Approximately 80% of the pipe network is made of brittle materials (reinforced concrete or earthenware) that could be expected to result in fractures and joint pull-outs in a severe earthquake. In addition, in those areas subject to liquefaction, manholes and pumping stations could be displaced.
Table 35 provides a summary of the assessed resilience of the assets to a MM9 earthquake, with a return period of 1,000 years. Where the current level of resilience is less than desired, further work is to be undertaken over the next 2-3 years to determine options for future management and development of the asset.
Table 35: Seismic Resilience
Asset Criticality Current Level of Resilience
Desired Level of Resilience
Totara Road Wastewater Treatment Plant High Moderate Very high
Palmerston North main pump stations (Maxwell’s Line, Massey, Jickell St, College St, Linton Army, Ashhurst)
High Low to moderate Very high
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
105
Asset Criticality Current Level of Resilience
Desired Level of Resilience
Palmerston North wastewater trunk mains High Moderate Very high
Manholes Varies Low to moderate Moderate to High
Reticulation Varies Low to moderate Varies
7.4.3 Flooding Hazard
The WWTP and many of the pump stations are located at near river level and may be subject to flooding. Although the city reach is currently protected against a 1:500 year flood, these assets may be at risk from localised intense rainfalls, or from flooding in excess of this. Flooding would increase flows into the local pump stations and the WWTP, and could lead to overflows within the wastewater network and the treatment plant. Excess flows at the WWTP would require bypassing of the inlet works with direct flow to the Manawatū River, or via the spillway from the aerated lagoons to the Mangaone Stream.
7.4.4 Volcanic Hazard
Volcanic ash is highly abrasive, mildly corrosive, and conductive. Freshly fallen volcanic ash may result in short-term physical and chemical change in water quality, increased wear on wastewater delivery and treatment systems, disruption of electrical power supplies, and high demand for water during clean up. Volcanic Ash may form un-pumpable masses in catchpits and sewer lines which may cause blockages, cause overflows, and damage pumping equipment.
Coarse ash is likely to block inlet screens, cause damage to moving parts and overload mechanical equipment. This ash will also increase the volume of raw sludge. Fine ash may not settle, and low density pumice will float.
Ash deposited directly into open ponds and clarifiers may reduce or halt the oxidation process. Ash is also highly acidic, which may affect bacteriological treatment processes, and fine ash may reduce the effectiveness of UV treatment.
Ash fall may also affect other critical infrastructure, such as electricity supply, water supply, and telecommunications, which compromise the functioning of the treatment plant.
7.4.5 Other Natural Hazards
There are also other natural hazards such as landslides, wind, or lightening that may impact the wastewater treatment. Sufficient assets redundancy will provide better resilience.
7.4.6 Interdependencies
Wastewater critical assets are not stand alone. To operate effectively, wastewater assets are dependent on a variety of other utilities / infrastructure providers. Other utilities also rely on the continued serviceability of the assets of this activity. To effectively manage risk, these interdependencies have been evaluated to identify where the highest levels of dependency exist and the implications of failure.
Table 36 identifies the utility services that this activity depends on, the level of dependence, and the mitigation measures in place.
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
106
Table 36: Utility Services that the Wastewater Activity Depends on for Continuity of Service
Critical Assets
Utility Service the Asset is Dependent on
Implications of Failure of the Asset Depended on
Mitigation Measures
WWTP Power Sewerage overflows Standby power, Alarms
Pump Stations
Power Road Bridge (Fitzherbet Ave)
Sewerage overflows Availability of standby power, alarms
WWTP Water Supply Blocking of equipment Recycling of wastewater
7.5 Risk Management Strategy
The approach to managing the asset to provide for mitigation of risk and increasing the resilience of the assets and networks is as follows:
On-going management and development of the assets according to sound asset management practice. This includes having a good knowledge of the assets and planning appropriately for maintenance, renewal, and development.
Developing the assets to provide for future capacity requirements in a timely way to avoid any loss of service through overloading of the system.
Implementing programs for timely renewal of the assets, particularly critical assets, to reduce the risk of unexpected failure and loss of service.
Prioritising inspection, maintenance, and renewal work to those areas that carry the greatest risk for the Council.
Regular inspections of critical assets in particular large diameter trunk mains. On-going review and refinement of the risk register to provide greater understanding of those asset
components that carry higher risk. Investigating, over the next 2-3 years, options for increasing the resilience of the asset and
developing tools, such as risk based economic analysis, to assist sound decision making. This is to be part of the Improvement Plan.
Including specific programs for strengthening of structures where warranted or required to meet standards.
Incorporating greater resilience when renewing or building new assets through materials selection and application of higher design standards.
Maintaining a readiness for responding to disaster events through having an up to date Business Continuity Plan and participating in the CDEM arrangements.
7.6 Risk Management Program
The programmes that contribute in this plan to mitigate risk and to increase resilience are summarised in Table 37.
Table 37: Risk Management Programme
Programme Impact on Risk & Resilience Cost Year
Maintenance Operation programmes to undertake regular inspections of assets (SLA’s) $400k/yr Ongoing
Renewal Increased pipe renewal expenditure Various renewal programmes at WWTP
$1.65-2 M/yr Ongoing
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
107
Programme Impact on Risk & Resilience Cost Year
Development Duplication of inlet main to WWTP Earthquake strengthening WWTP Seismic strengthening to WW Structures (PS)
$400k $1M
$200k
2017/18 2018/19
2015-2018
Investigation WWTP Investigations into seismic and liquefaction risks Yearly CCTV inspections of WW mains
$100,000 $55k/yr
2017/18 Ongoing
Readiness – BCP etc.
Asset management systems and emergency action plans to mitigate natural disaster risks.
Ongoing
7.7 Civil Defence Preparedness
7.7.1 Emergency Events
The Civil Defence and Emergency Management Act 2002 defines an emergency as a situation that:
is the result of any happening, whether natural or otherwise, including, without limitation, any explosion, earthquake, eruption, tsunami, land movement, flood, storm, tornado, cyclone, serious fire, leakage or spillage of any dangerous gas or substance, technological failure, infestation, plague, epidemic, failure of or disruption to an emergency service or a lifeline utility, or actual or imminent attack or warlike act;
causes or may cause loss of life or injury or illness or distress or in any way endangers the safety of the public or property in New Zealand or any part of New Zealand; or
cannot be dealt with by emergency services, or otherwise requires a significant and co-ordinated response under this Act.
7.7.2 Emergency Response Plan
The Act also requires the establishment of CDEM Groups based on Regional Council boundaries, working in partnership with emergency services, lifeline utilities, and others, to deliver CDEM at the local level. Each Group is required to prepare a plan to describe the Group’s CDEM arrangements that set, out among other things:
Hazards and risks to be managed by the Group. Civil defence emergency management necessary to manage the hazards and risks. Arrangements for declaring a state of emergency in the area. Arrangements for co-operation and co-ordination with other Groups.
The Manawatū-Wanganui Civil Defence Emergency Management Group Plan 2016-2021 covers the CDEM operational arrangements for the assets and services described in this AMP.
The four phases of disaster management outlined in the plan and their applicability to this activity are as follows:
Reduction
Identifying and analysing long-term risks to human life and property from natural or man-made hazards, and taking steps to eliminate these risks where practicable, and where not, reduce the magnitude of their impact and likelihood of their occurring.
For this activity this is achieved through two key initiatives:
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
108
PNCC contribution to the Lifelines Advisory Group which aims to facilitate information exchange and collaboration between the various utility service providers in the region with respect to CDEM. This group is also responsible for maintaining and improving the Regional Lifelines Project Report ‘Risks and Responsibilities’.
Ensuring that the development of infrastructure development is in keeping with PNCC District Plan provisions which, in turn, have been informed by Horizons One Plan with respect to placement of critical infrastructure in areas prone to natural hazard events.
Readiness
Developing operational systems and capabilities before a disaster happens. These include self-help and response programmes for the general public, as well as specific programmes for emergency services.
A significant portion of the CDEM Group’s work is undertaken as readiness initiatives. The group provides co-ordinated planning to ensure an effective response to the affected communities, and for the co-ordination of responding agencies.
This activity provides inputs into these activities.
Response
This relates to response actions taken immediately before an emergency is declared and lasts until the normal systems can accommodate the recovery process. A fundamental principle for this phase is that agencies should respond to an emergency by activating their own plans and co-ordinating with the lead agency.
In the case of this activity, the Business Continuity Plan described in Section 7.7.3 would be activated.
Recovery
This relates to activities beginning after initial impact has been stabilised and extending until the community’s capacity for self-help has been restored. Recovery is a key part of the comprehensive approach to CDEM and, for this reason the Group has a comprehensive Recovery Plan. The impact of a major event can lead to long term recovery needs for the City. For the wastewater activity, this is discussed in Section 7.7.4.
Civil Defence Emergency Management Amendment Act 2016
The changes to the Civil Defence Emergency Management Act strengthen recovery planning. This amendment specifically requires CDEM Groups to amend their plans by 1 June 2018 to include strategic planning for recovery from the hazards and risks in their district. Work on this amendment is currently underway.
7.7.3 Business Continuity Plan
A Business Continuity Action Plan has been prepared for the Water & Waste Services to provide information and strategies, including co-ordination of people and resources, that will enable continued availability of business process and services and recovery from events that interrupt those services.
The Water and Waste Action Plan contains:
The Water & Waste Services call tree.
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
109
Incident Management Team. Water & waste services continuity and recovery strategies:
Accessibility, Resources and Communication; and Wastewater Disposal.
Contact Lists for both internal and external contacts. Response Centre Details - Arena Manawatū.
7.7.4 Recovery
In the event of a major disruption of service, establishing at least a temporary supply to critical customers would be a priority.
Should the event have caused widespread disruption to the water network and recovery over a long term is required, then a recovery programme will need to be put in place. This programme will cover:
Priorities for work done on the asset; Consideration of changes in the way the assets could be configured and materials used if a
significant replacement programme was required; Potential funding needs/issues; and Relationships between the assets and other utilities assets – e.g. co-location in road corridors.
On-going work will be undertaken on these aspects.
7.7.5 Lifeline Utilities Coordination
Protocols and arrangements to facilitate communication and co-ordination with other utilities, in the event of a major event affecting multiple agencies, are set out in the CDEM Group Plan 2016-21. The following organisations are members of the Lifelines Advisory Group:
Horizons Regional Council Palmerston North City Council Ruapehu District Council Wanganui District Council Rangitikei District Council Manawatū District Council Tararua District Council Horowhenua District Council Transpower NZTA Spark NZ Vodafone 2 Degrees Inspire Net
Chorus Electra First Gas Kordia Scanpower Kiwi Rail PowerCo GasNet Palmerston North International Airport Mid Central DHB Teamtalk The Lines Company Foodstuffs
Section 7 – Risks & Resilience Asset Management Plan 2017 – Wastewater
110
7.7.6 Risks and Resilience Improvement Plan
Particular aspects that require further development.
Further assessment of risk and programmes to mitigate risk in the light of further investigation and better information about the impact of natural hazards.
Develop a more advanced approach to identifying critical assets that incorporates rating and other dimensions of criticality.
Further assessment of the current level of resilience. Develop a more comprehensive method of assessing resilience using risk based evaluation and
optimised decision making tools to assist decision making around the desired level of resilience. On-going review of the risk register.
Provision is made in the continuous improvement programme, Section 11, for further work on these aspects over the next three years.
Section 8 – Sustainability Asset Management Plan 2017 – Wastewater
111
8 Sustainability This section sets out how the wastewater activity contributes through the management of its assets to the city having a sustainable future. The practise of asset management is itself based on sustainably delivering services to the community.
8.1 Eco City Strategy
The Eco City Strategy is one of the Council’s main strategies supporting its vision for the City and aims to contribute to the city developing and growing in a way that is sustainable.
This includes having a reduced ecological footprint through effective planning of infrastructure and the protection, maintenance and enhancement of the city’s natural and built environment. The Council is also working towards the city becoming a low carbon economy.
To achieve the desired outcomes the Council has set a number of priorities and developed Strategy Plans under the Eco City Strategy as shown in Table 38.
Table 38: Relevant Eco City Strategy Priorities and Plans
Eco City Strategy Priorities Eco City Strategy Plans
Respect and enhance the mauri of the Manawatu River Work with the community to reduce carbon emissions Regenerate native biodiversity Invest in infrastructure that serves to protect, enhance and preserve our environment Use our legislative powers and policies to ensure that urban development is sustainable now and into the future Educate the community, in particular, property owners, on the benefits of investing in sustainable building design and green buildings Demonstrate leadership and best practice by developing and implementing an environmental sustainability plan for the Council
Biodiversity Water Waste Energy Environmental education Carbon emissions reduction
In addition Sustainable Practices is one of the themes that is to be reflected in all of Council’s strategies and plans.
Key Sustainability Issues Key sustainability issues from these plans for the wastewater activity are as follows.
Minimising the impacts of the wastewater activity on the land and receiving water bodies Embedding energy efficiency and sustainability into all aspects of the wastewater operations by
utilising energy efficient motors when undertaking replacements or upgrades. Incorporating the concept of energy neutrality into future WWTP upgrades. Increasing energy generation at the WWTP through increased waste diversion to the digesters. Developing a sustainable solution for the disposal of sludge.
8.2 Climate Change
Overall, it is anticipated that climate change will have minimal impact on the sustainability of wastewater services. It is predicted that, as a result of climate change, the weather in the region will
Section 8 – Sustainability Asset Management Plan 2017 – Wastewater
112
be warmer and wetter, with more intense rainfall. Depending on the success of the proposed I&I programme this may or may not have impact. This will be monitored over the term of the AMP.
8.3 Approach Taken in This Plan
Sustainability considerations are incorporated into the AMP through the following mechanisms:
The Discharge Consent Permits for Totara Road. Operational Plans for WWTP and Biogas Electricity Generation. Operational Plans for the Wastewater Treatment Plants and Pump Stations. The proposed Sludge Management Plan - application of bio-solids to land through composting or
other processes. Implementation of food waste and organic waste to energy initiatives by utilising surplus digester
capacity to treat organic waste to generate biogas which is then burned in the gas energy to generate electricity to run the wastewater treatment plant site
Participation in peak load shedding events by using standby generators during periods of peak electricity demand.
Section 9 – Financial Projections & Trends Asset Management Plan 2017 – Wastewater
113
9 Financial Projections & Trends This section outlines the long-term financial requirements for operations, maintenance and capital renewal and development for the wastewater activity based on the long-term strategies and tactics described earlier in the AMP.
9.1 Long Term Financial Forecast
9.1.1 Proposed Operation & Maintenance Expenditure
Figure 31 shows the thirty year projected operating expenditure excluding interest and depreciation. The significant increase in operating programme expenditure occurring from 2026/27 onwards is based on the assumed significantly higher cost of a new wastewater treatment and disposal facility. The specific additional costs and their relative proportion will depend on the preferred solution approved by Council and consented through the RMA process. Additional costs are likely to be associated with energy, mechanical and electrical maintenance, staffing, chemical consumables and sludge treatment and disposal. Higher interest costs will also be incurred for the upgraded facility. The reason for the slight reduction in costs in 2024/25 and 2025/26 is the end of the Wastewater BPO Operational Programme 1319.
Figure 31: Thirty Year Operation & Maintenance Expenditure Forecast
9.1.2 Proposed Renewal Expenditure
Figure 32 depicts the thirty year projected renewals expenditure broken down into major asset groups. The majority of the renewal expenditure is associated with network and pump stations. The network renewal profile for the first 10 years reflects a clear programme of renewals based on condition and performance risk and an enhanced level of investment to address legacy condition issues in the network. Beyond 2032/33 the investment in network renewals drops back to an average provision of
$0
$1
$2
$3
$4
$5
$6
$7
$8
$9
$10
2018
/19
2021
/22
2024
/25
2027
/28
2030
/31
2033
/34
2036
/37
2039
/40
2042
/43
2045
/46
Prop
osed
Ren
ewal
Exp
endi
ture
[Mill
ions
]
Management Delivery Operating Programmes
Section 9 – Financial Projections & Trends Asset Management Plan 2017 – Wastewater
114
some $1.9 M per annum. It is expected that the investment in CCTV and optimised modelling will enable a more accurate prediction of network renewals to be developed.
While there is some significant investment in treatment plant renewals over the first 10 years of the AMP this is mostly associated with screening, grit removal and upgrading of inlet pumping. It is assumed that following the proposed upgrade of the treatment and disposal facility currently indicatively timed to occur in 2026/27 there will be no significant renewal investment in the plant for a period of time on the basis that much of the plant will be newly refurbished or upgraded. The spike in renewal investment in 2030-2032 is associated with renewal of the trunk sewer in Tremaine and Featherston as well as upgrades to SCADA and the biogas engine at the wastewater treatment plant.
Renewal investment approaches depreciation levels in the first few years of the plan, given the significant number of assets approaching end of life, however following the investment in the upgraded treatment and disposal facility, depreciation increases significantly. The higher rates of depreciation do not trigger additional renewals given the assets are assumed to be new or recently refurbished and at the early stage in their lifecycle.
.
Figure 32: Thirty Year Projected Renewals Expenditure
9.1.3 Proposed New Capital Expenditure
Figure shows the thirty year projected new capital expenditure, broken down into major asset groups. The capital expenditure profile is dominated by the assumed spending of in excess of $100M over the three years from 2023/24 to 2026/27 to fund the required upgrade in the treatment and disposal facility. The timing and profile of capital funding is indicative only as the preferred option has not yet been selected and the final scope of work is still subject to a consent process.
Apart from the treatment facility, the other capital expenditure is associated with investment in new network and pumping facilities to serve new residential and industrial growth areas. The timing and scale of new network investment is subject to review as the rate and nature of development changes. It is intended that by requiring the use of low pressure sewer systems in several growth areas that capital investment costs will be reduced compared to conventional gravity and network pumping systems.
$0
$1
$2
$3
$4
$5
$6
$7
2018
/19
2021
/22
2024
/25
2027
/28
2030
/31
2033
/34
2036
/37
2039
/40
2042
/43
2045
/46
Prop
osed
Ren
ewal
Exp
endi
ture
[Mill
ions
]
Reticulation & Pumps Treatment 3 Yr Rolling Avg. Depreciation
Section 9 – Financial Projections & Trends Asset Management Plan 2017 – Wastewater
115
Figure 33: Thirty Year Projected New Capital Expenditure
A full breakdown of the thirty year projected costs is given in Appendix E.
9.1.4 Trends in Thirty Year Forecast
Significant trends for the thirty year forecast are:
Operation and Maintenance
Operation and maintenance costs are expected to increase from the major upgrade that will occur at the WWTP. This will be offset to a certain extent by efficiency gains from the new equipment, and anticipated reductions in wastewater flows from I&I.
Renewals and Rehabilitation
The renewal expenditure is higher for the first 15 years (2018/19 to 2031/32) due to renewals of some critical elements at the Totara Road WWTP, including inlet pumps and grit removal and continuing high levels of pipe renewals. Renewal expenditure then drops to a lower level in the second half of the plan. The total expenditure is $125.2M over the next 30 years.
Capital Expenditure
The capital expenditure profile is dominated by the assumed investment in an upgrade of the wastewater treatment and disposal system arising out of the consent renewal process. Expenditure is assumed to occur over the period 2023/24 to 2026/27. Other expenditure is largely associated with providing for growth. The total expenditure is $121.6M over the 30 year period.
9.2 Asset Valuation
Council Wastewater assets were re-valued as at 30 June 2017 in accordance with Financial Reporting Standard (FRS) 3 and the NZ Infrastructure Valuation Guidelines. The results of this valuation were
$0
$5
$10
$15
$20
$25
$30
$35
$40
$45
2018
/19
2021
/22
2024
/25
2027
/28
2030
/31
2033
/34
2036
/37
2039
/40
2042
/43
2045
/46
Prop
osed
Cap
ital E
xpen
ditu
re [M
illio
ns]
Treatment Reticulation & Pumps
Section 9 – Financial Projections & Trends Asset Management Plan 2017 – Wastewater
116
independently audited. The updated valuations at 1 July 2017 are shown in Table 39. The detailed valuation and valuation methodology are contained in the City Networks Valuation Report.
Table 39: Asset Valuations 2017
Asset ORC ODRC Annual Depreciation
Pipelines $138,594,111.65 $72,567,464.80 $1,245,078.71
Manholes $30,312,864.00 $18,492,265.03 $252,559.50
Laterals $68,948,126.36 $29,636,242.96 $755,166.05
Valves $570,484.00 $517,129.23 $11,409.68
Pump Stations $6,037,240.00 $3,609,165.49 $145,166.54
Treatment Plant $44,816,718.34 $29,258,472.71 $795,428.63
Oxidation Ponds $1,368,890.00 $1,202,008.87 $5,574.05
Total $290,648,434.35 $155,282,749.08 $3,210,383.16
9.3 Confidence levels
The confidence in the asset data used as a basis for the financial forecasts has been assessed using the following grading system shown in Table 40, from the NZWWA NZ Guidelines for Infrastructure Asset Grading Standards, final draft, August 1998.
Table 40: Confidence Grading System
Confidence Grade
Description Processes Asset Data
5 Highly reliable/ Audited
Strictly formal process for collecting and analysing data. Process is documented and always followed by all staff. Process is recognised by industry as best method of assessment.
Very high level of data confidence. Data is believed to be 95 to 100% complete and ±5% accurate. Regular data audits verify high level of accuracy in data received.
4 Reliable/ Verified
Strong process to collect data. May not be fully documented but usually undertaken by most staff.
Good level of data confidence. Data is believed to be 80 to 95% complete and ±10 to 15% accurate. Some minor data extrapolation or assumptions has been applied. Occasional data audits verify reasonable level of confidence.
3 Less Reliable Process to collect data established. May not be fully documented but usually undertaken by most staff.
Average level of data confidence. Data is believed to be 50 to 80% complete and ±15 to 20% accurate. Some data extrapolation has been applied based on supported assumptions. Occasional data audits verify reasonable level of confidence.
2 Uncertain Semiformal process usually followed. Poor documentation. Process to collect data followed about half the time.
Not sure of data confidence, or data confidence is good for some data, but most of dataset is based on extrapolation of incomplete data set with unsupported assumptions.
1 Very uncertain
Ad hoc procedures to collect data. Minimal or no process documentation. Process followed occasionally.
Very low data confidence. Data based on very large unsupported assumptions, cursory inspection and analysis. Data may have been developed by extrapolation from small, unverified data sets.
0 No data No process exists to collect data. No data available.
Table 41 summaries the data confidence rating for the various asset groups. Wastewater asset data that is stored in IPS and GIS is routinely updated and generally has reliable physical characteristics for pipeline assets. The confidence level is ‘B’ overall.
Section 9 – Financial Projections & Trends Asset Management Plan 2017 – Wastewater
117
Table 41: Confidence Rating Wastewater Assets
Asset Asset Data Confidence
Condition Data Confidence
Performance Data Confidence
Demand/Growth Forecast Confidence
Pipelines 2 2 3 2
Manholes 2 2 3 2
Laterals 3 3 3 2
Valves 1 3 3 3
Pump Stations 1 2 2 3
Treatment Plant 1 2 2 2
Oxidation Ponds 1 2 2 2
9.4 Reliability of financial forecasts
9.4.1 Maintenance and Renewal Forecasts
These are considered reliable estimates, based on a known quantum and scope of work, and a good historical cost database. There is some increasing uncertainty of forecasts over the long term due to lack of knowledge about real price changes of individual components.
9.4.2 Development Forecasts
Years 1-3 - the scope and pricing of work is considered reliable.
Years 4-10 - increasing uncertainty around scope and detail of work, forecast estimates are considered conservative but are less reliable than years 1-3.
Years 11-20 - rough order costing based on estimated quantum of work, forecasts could change significantly with further investigation.
9.4.3 Potential Effects of Uncertainty
Generally expenditure forecasts are considered conservative. The longer term development budgets will be refined both in scope and costing as these programmes get closer to implementation. Those programmes that are for growth also form the basis for development contributions assessed over a period of thirty years. Periodic revision and adjustment to the schedule of works in the three year rolling programme counters any negative effect of uncertainty of the financial forecasts.
Overall, the continuation of the wastewater level of service to the community is not overly sensitive to changes in particular programmes.
Should the required level of funding not be available, there is a potential risk of deferred maintenance or renewal or development. This would not be noticeable immediately, but could build up over a period of time and result in not meeting agreed levels of service. This is mitigated through an extensive review and revision of asset management requirements that takes place on a three yearly cycle, enabling corrective action to be taken before a substantial backlog is built up.
Significant development projects that have a high level of uncertainty include:
Section 9 – Financial Projections & Trends Asset Management Plan 2017 – Wastewater
118
The timing of urban growth beyond the immediate area, of Whakarongo. This includes the later stages of programme 1055 – Urban Growth – Waste Water Supply for City West from 2024/25 onwards.
The timing of growth in the expanded NEIZ. The Totara Road WWTP Consent Renewal Upgrade.
9.5 Funding policy
The focus of this AMP is on identifying the optimum (lowest lifecycle) cost for wastewater assets necessary to produce the desired level of service. The different types of expenditure are funded as follows:
9.5.1 Operation and maintenance
Funded by trade waste fees and charges and targeted rates, depending on how the benefits of the activity are assessed - as a public or private benefit - or where costs can be attributed to an individual entity.
Trade waste charges are calculated on a flow and load proportional basis in accordance with the Council’s Trade Waste Bylaw.
Targeted rates for the wastewater activity are calculated as a fixed charge per separately used or inhabited part for residential properties, and for all other properties, a fixed charge per rating unit
9.5.2 Capital renewal
Funded from trade waste fees and charges, rates revenue collected to cover renewal costs and loan finance if necessary.
9.5.3 Capital development
Funded from subsidies and grants (where available), user contributions, reserves and, where necessary, from borrowing.
Subsidies and grants relate to Central Government funding contributions towards the cost of wastewater capital upgrades, and research into new innovations involving sustainable treatment of wastewater by-products (e.g. sludge). There is currently no Central Government funding available for wastewater capital renewal works.
9.5.4 Development contributions
Through the application of its Development Contributions Policy, the Council seeks to obtain contributions to fund the infrastructure that is required due to City growth. Programmes that are attributable to growth are shown in this AMP (See TABLE 25 Appendix E). Development contributions for wastewater are area specific.
Section 10 – Assumptions Asset Management Plan 2017 – Wastewater
119
10 Assumptions This section sets out the key assumptions made in developing the asset lifecycle programmes and financial forecasts, and identifies the likelihood and impact of variations from these assumptions.
10.1 Asset Ownership and Provision of Service
Asset ownership and provision of service remains in Council ownership and management.
10.2 Population Growth
The following population projections are assumed:
10-year projection 2018 – 2028, 940 people per annum at 1.0%. 20 year projection 2018 – 2038, 710 people per annum at 0.7%. 30 year projection 2018 – 2048, 598 people per annum at 0.6%.
This is a hybrid growth scenario based on a specific Palmerston North high growth projection for years 1-10, and a Statistics New Zealand medium growth projection for years 11-30.
The AMP is formally reviewed every 3 years, and programmes will be adjusted on an annual basis through the Annual Budget for variances from that assumed. There is a low risk that planning for capital development projects for growth will not match actual needs.
10.3 Residential Growth
The development scenario for residential growth is based on meeting the needs of a growing population, and also includes the additional margins required by the National Policy Statement for Urban Development Capacity. An average household size of 2.5 is assumed.
A future housing preference of 50% for greenfield, 38% for infill and 12% for rural / residential is assumed.
The assumed development scenario is based on greenfield development being centred on Whakarongo, Aokautere, and Kelvin Grove, with a number of other smaller developments in the short to medium term, with City West and further Aoukautere development in the medium to longer term.
Any changes to this scenario will be worked through subsequent AMPs.
10.4 Industrial Growth
It is assumed that the NEIZ and the NEIZ Extension Area will be sufficient to meet the growth in large floor plate industrial activity over the next 20 to 30 Years.
Longburn is viewed as a suitable location for wet industry, although there are infrastructure constraints at the moment to its development due to its private ownership. It is assumed these will be resolved to fully realise its potential.
Section 10 – Assumptions Asset Management Plan 2017 – Wastewater
120
Given that the nature of industrial investment can be lumpy, on-going review of industrial land uptake and needs will be required.
10.5 Retail Growth
A Centre’s based approach is assumed for managing retail and office activity throughout the city. This approach seeks to keep commercial activity centred in the core of the city and to avoid the dispersion of office and retail activity to the periphery of the urban area. This approach is given effect to through the District Plan hierarchy of business zones as follows:
Inner Business Zone (IBZ). Outer Business Zone (OBZ). Fringe Business Zone (FBZ). Local Business Zone (LBZ).
10.6 Rural-Residential Growth
It is assumed that the Council generally will not provide a water or wastewater service to rural-residential and rural properties within the City boundary.
It is assumed rural-residential subdivision will occur in locations which do not require the Council to fund substantial upgrades to the wastewater network in order to facilitate the subdivision.
10.7 Levels of Service
Generally a similar level of service to that currently delivered applies, but with minor adjustments as follows:
Increased education funding. Increased investigations into I&I. Increased wastewater pipe renewals to effect I&I reductions.
Further levels of service changes may occur during this period. Cost implications and updating to the AMP will be made at the time they occur.
10.8 Construction Costs
Financial forecasts are based on projected July 2018 construction costs.
It is likely that the price of some components will change relative to others. Budgets are reassessed each year during the Annual Budget process to mitigate this risk. BERL inflation factors applied to the 10 Year Plan also incorporate an element of price changes in different activity sectors.
10.9 Maintenance & Operational Costs
These are largely based on historical rates and assume similar contract rates throughout the planning period.
Section 10 – Assumptions Asset Management Plan 2017 – Wastewater
121
Inflation factors will be applied at the 10 Year Plan level to reflect forecast price changes in different sectors.
10.10 Inflation
Financial projections are based on July 2018 estimated costs. No inflation factors have been applied.
BERL inflation factors will be applied to the programmes and budgets in the 10 Year Plan. Budgets for successive years of the Annual Budget are based on the corresponding year of the 10 Year Plan.
10.11 Depreciation
Average asset lives at a project level for new works have been used to calculate depreciation.
New works are a small percentage of total depreciation. Differences from actual due to averaging of lives are relatively minor.
10.12 Vested Assets
On average the same level of assets are gifted to the council as a result of subdivision as has occurred over the last 5 years
N.B. The rate of change of development will be taken account of in future revisions of the AMP and subsequent operations and maintenance, and depreciation taken into account.
10.13 Service Potential
Service potential of the asset is maintained by the renewal programme.
There is low risk that the service potential of the asset will not be maintained by implementation of the renewal programme, since this is based on reliable asset and condition information from the asset management system.
10.14 Asset Lives
Asset lives are accurately stated.
The risk that lives are inaccurate is low. Lives are based on generally accepted industry values modified by local knowledge. The asset database gives a good knowledge of asset condition, and an extensive field assessment has recently been undertaken.
10.15 Natural Disasters
There are no major natural disasters requiring additional funds.
Section 10 – Assumptions Asset Management Plan 2017 – Wastewater
122
There is medium risk of a natural disaster occurring during this period, requiring additional funds to repair or reinstate assets. Some further provision for increasing the resilience of the assets has been built into this plan but there is still further work to be undertaken to determine the desired level of resilience and the further asset improvements to achieve this.
10.16 Council Policy
No significant change to Council policy that impacts on assets and services.
Any significant change will require a full review of the AMP and implications identified at the time.
10.17 Interest Rate
An interest rate of 5.7% p.a. is used for debt on new work.
10.18 Treatment Plant Upgrade
That no major expenditure is required for a higher level of wastewater discharge quality other than that already identified by the Council before any upgrade associated with the new consent to be applied for in 2022.
Section 11 – Continuous Improvement Asset Management Plan 2017 – Wastewater
123
11 Continuous Improvement
11.1 Overview
The quality of Council’s AM practice has been enhanced over the past 20 years in line with the objective to match, but not lead, industry 'best practice' in New Zealand. This version of the AMP incorporates the following key improvements and changes undertaken over the last three years:
11.2 Programme Planning and Implementation
A Programme Planning and Implementation Template (PPI) was introduced in 2015 by the City Networks Unit as part of an initiative to improve the quality of information associated with Council infrastructural programmes, including the 30 year programmes in the AMPs
The PPI sheet is completed for every infrastructural programme and includes information about type, timing, and scope of programme, options considered, Council decisions, estimated costs, risks, assumptions and constraints, and approvals required for the programme to be implemented. These files also contain links to other relevant reports. The information is updated annually. As a result the information behind the programmes in this plan is more robust than previously.
11.3 Project Status
A system for monitoring the progress and expenditure of individual programmes through the financial year has been implemented during the last 3 years to aid better monitoring and management of programmes. This allows projects to be tracked against budget and forecasts, and to record the progress being made. An advantage of this is that the information is widely accessible, with a number of different reports available for different audiences.
11.4 Development Works Planning
11.4.1 Residential Growth and Industrial Growth Planning (refer to Section 5)
Council’s Residential Growth Strategy was adopted on 30 September 2010. In October 2011, Council authorised the preparation of a proposed District Plan change to give effect to the Residential Growth Strategy within the District Plan.
Development works included in the 2014 AMP to meet growth were based on the 2010 Residential Growth Strategy adjusted by a 2012 Addendum that identified the Whakarongo area as preceding City West for residential development.
A further modification of this strategy is now included in this plan to incorporate a higher projected growth forecast, and also takes into account the NPS-UDC requirements.
Section 11 – Continuous Improvement Asset Management Plan 2017 – Wastewater
124
11.4.2 Demand Projections (refer to AMP Section 5)
As a result of further analysis of migration trends, the Council has decided to assume high growth projections for years 1-10 and a medium growth projection for years 11-30. This is greater than the growth assumed for the 2014 AMP, which was based on Statistics New Zealand medium growth projections adjusted for the local Palmerston North situation.
11.4.3 Risk and Resilience (refer to AMP Section 7)
The risk and resilience assessment aligns with the new Local Government Act 2002 Amendment Act 2014 requirement for 30 year infrastructure strategies to identify and manage risks relating to natural hazards and to make appropriate financial provision for those risks. Since the 2014 AMP further work has been undertaken with a review of risks facing the assets, a review of Business Continuity plans, and of Lifelines interdependencies.
11.4.4 Council Strategies (refer to AMP Section 3)
As part of the 10 Year Planning process, the Council has reviewed its Vision, Goals, and Strategies to ensure it is achieving the outcomes it desires for the community. The infrastructure elements of the Strategy Plans associated with Council’s goals have been incorporated into these AMPs.
11.5 Renewal Works Planning
11.5.1 Condition Data
Asset age, condition, performance, and risk are the four main determinants of renewals planning. On-going condition and performance assessment of Council’s assets has taken place during the period. The data collected is fundamental to improved renewal programming. Predictive modelling is still in its early stages and provision has been included in this Improvement Plan for development of this aspect of asset management – see Task 2(g).
11.6 Operations and Maintenance
11.6.1 Operations and Maintenance Strategy
The operations and maintenance strategy and processes have been reviewed in conjunction with development of this Plan.
11.6.2 Internal Service Level Agreements
Internal service level agreements between the City Networks Unit and the City Enterprises Unit, the in-house service provider, have continued to be advanced to increase transparency and accountability between funding and service provision. This has been aided by establishing an SLA system looked after by a dedicated officer. This has been supported by a Collaborative Working Practices process between the two Units.
Section 11 – Continuous Improvement Asset Management Plan 2017 – Wastewater
125
11.6.3 Market Comparability Procedure
In conjunction with collaborative working practices, a market comparability procedure is built into the Service Level Agreement process. This is to ensure that the prices being accepted by City Networks reflect the market price. Some improvement has taken place over the past 3 years in this procedure but it still requires further improvement to get the full benefit of this approach. Further work is identified in this Improvement Plan (Task 9(b)).
11.7 Asset Information
11.7.1 Asset Management Plan Improvement
The AMP Policy and Strategy was reviewed in October 2016 and presented to PNCC Management Team in February 2017. This has been incorporated in the 2017 AMPs. A set of AMP guidelines and programme was prepared at the same time to assist the asset managers in the development of the 2017 AMPs. This identified the context and issues that needed to be addressed to enable the AMPs to be completed and aligned with development of the 2018-2028 10 Year Plan.
The programme included a Level of Service review, incorporation of Council Strategies into the AM planning process, development of capital (new and renewal) and operational programmes, and an independent peer review. AMP templates and guidelines were prepared to coordinate the AMP structure and content, and to improve consistency between different AMPs.
The AMP financials were constructed within Council’s corporate 10 Year Planning system to ensure consistency with the 2018 - 28 10 Year Plan projections.
11.8 Asset Management Resources
11.8.1 Loss of Key AM Knowledge
Key systems to preserve asset management knowledge are the Asset Management Systems and the Programme Planning and Implementation template system that keeps track of information connected with particular programmes. These have both been strengthened during this period.
11.8.2 Skill Gaps
Skill gaps are identified through regular performance development interviews of asset management officers. AM skills and knowledge development can be largely addressed through attendance of AM staff at NAMS training courses and other on line courses.
11.9 Levels of Service Review
A review of current levels of service and performance measures was work-shopped with the Council in March 2017. Feedback from the workshop was assessed by senior managers and has been factored into projects and programmes, included in this AMP. Further levels of service information came through from Councillors during the LGA s17A process, and also during the development of Council’s Strategy Plans.
Section 11 – Continuous Improvement Asset Management Plan 2017 – Wastewater
126
11.10 AMP Improvement Plan (2017)
The purpose of the Improvement Plan is to:
Identify and develop implementation of AMP processes. Identify, programme, and resource measures required to complete studies, or measures to confirm
planning assumptions, or to gather information required to improve the reliability / confidence of information used to develop the AMP.
Identify and prioritise ways to cost-effectively improve the quality of the AMP. Identify indicative time-scales, priorities, and human and financial resources required to achieve
AMP objectives.
The following improvement activities have been identified for action over the next 3 years after consideration of priorities identified by the asset management team. Many of these improvements are generic across all asset activities (i.e. water, property, roading, etc.) and will be implemented as coordinated projects across all areas.
Capital renewal and development project planning – further development of processes to take into account a sustainable development approach.
Review demand projections on an on-going basis consistent with Council’s Residential Growth Strategy.
Continue to develop predictive modelling and risk based approaches to help prioritise renewal programmes and better manage risks and costs in achieving the desired outcomes.
Update City-wide asset development plans as growth and actual development necessitates Periodically review risk assessments. Further develop appropriate mitigation strategies for Council’s critical assets in the event of a major
natural hazard, and programmes to improve resilience of critical assets from natural hazards. Operations and maintenance – on-going review of contracting and internal service agreement
strategies to achieve the best balance of risk transfer, cost, and performance. Asset information – on-going development of systems to meet all asset management needs, and
the integration of asset information activities within Council. Internal process improvements for Collaborative Working Practices, Service Procurement
processes, and Market Comparability assessments. Level of service – undertake stakeholder consultation on new, major issues, to update
understanding of community expectations and preferences. Review levels of service with Council every three years.
AM resource planning to ensure the recruitment, retention, and development of sufficient and suitably qualified staff.
Review AM strategy to take account of changes in Council direction and Government policy.
The indicative AM improvement programme is detailed in Table 42.
Sect
ion
11 –
Con
tinuo
us Im
prov
emen
t As
set M
anag
emen
t Pla
n 20
17 –
Was
tew
ater
127
Tabl
e 42
: Pa
lmer
ston
Nor
th C
ity C
ounc
il 3
Year
Ass
et M
anag
emen
t Im
prov
emen
t Pro
gram
me
Re
sour
ces
2017
/18
2018
/19
2019
/20
2020
/21
AM
Cat
egor
y Im
prov
emen
t Act
iviti
es
Timeframe & Responsibility
Est($)
J F
M
A
M
J J
A
S O
N
D
J F
M
A
M
J J
A
S O
N
D
J F
M
A
M
J J
A
S O
N
D
J
1 Dev
elop
men
t w
orks
pl
anni
ng
(dem
and/
Lo
S)
Rev
iew
and
upd
ate
dem
and
proj
ectio
ns c
onsi
derin
g al
l tre
nds
(pop
ulat
ion,
clim
ate,
usa
ge, e
tc.).
U
nder
stan
d fo
reca
st s
cena
rios.
2 weeks
City Networks /City Future
8,000
Rev
iew
impa
ct o
f Cou
ncil's
stra
tegi
es
and
polic
ies
on d
eman
d pr
ojec
tions
.
1 week
Asset Managers
4,000
Rev
iew
dev
elop
men
t pla
ns fo
r ass
ets.
2 weeks
AMP Coordinator
8,000
Rev
iew
pro
ject
prio
ritie
s ba
sed
on
risk/
cost
/ben
efit
anal
ysis
.
2 weeks
Asset Managers
8,000
Rev
iew
miti
gatio
n st
rate
gies
for m
ajor
na
tura
l haz
ard
even
ts.
3 weeks
Asset Managers
20,000
Doc
umen
t cha
nges
to A
MP
prog
ram
mes
that
aris
e th
roug
h 10
Ye
ar P
lan
& AP
pro
cess
es.
2 weeks
Asset Managers
10,000
Sect
ion
11 –
Con
tinuo
us Im
prov
emen
t As
set M
anag
emen
t Pla
n 20
17 –
Was
tew
ater
128
Re
sour
ces
2017
/18
2018
/19
2019
/20
2020
/21
AM
Cat
egor
y Im
prov
emen
t Act
iviti
es
Timeframe & Responsibility
Est($)
J F
M
A
M
J J
A
S O
N
D
J F
M
A
M
J J
A
S O
N
D
J F
M
A
M
J J
A
S O
N
D
J
2 As
set
info
rmat
ion
Rev
iew
AM
sys
tem
dat
a qu
ality
pr
oces
ses
and
impr
ove
as re
quire
d.
Dev
elop
Dat
a Im
prov
emen
t Pla
n.
Link
with
Tas
k 3(
a).
2 weeks
Asset Managers & AM Coord.
10,000
Rev
iew
and
doc
umen
t con
ditio
n as
sess
men
t qua
lity
proc
ess/
pr
ogra
mm
e (to
sup
port
risk
& pr
edic
tive
mod
ellin
g).
2 weeks
Asset Managers
10,000
Rev
iew
per
form
ance
dat
a ne
eds
(repo
rting
& d
ecis
ion-
mak
ing)
and
do
cum
ent d
ata
capt
ure
qual
ity
proc
ess.
2 weeks
Asset Managers
8,000
Anal
yse
asse
t liv
es (u
sing
con
ditio
n/
capa
city
/ per
form
ance
dat
a), a
nd
revi
ew /
addr
ess
data
qua
lity
issu
es.
Ente
r int
o AM
sys
tem
.
1 week
Asset Managers & System
Officers
4,000
Rev
iew
/Iden
tify
criti
cal a
sset
s in
the
regi
ster
.
1 week
Asset Manager
4,000
Rev
iew
fina
ncia
l dat
a ne
eded
to
supp
ort O
DM
and
val
uatio
n-
impl
emen
t pro
cess
.
2 weeks
Asset Managers
8,000
Sect
ion
11 –
Con
tinuo
us Im
prov
emen
t As
set M
anag
emen
t Pla
n 20
17 –
Was
tew
ater
129
Re
sour
ces
2017
/18
2018
/19
2019
/20
2020
/21
AM
Cat
egor
y Im
prov
emen
t Act
iviti
es
Timeframe & Responsibility
Est($)
J F
M
A
M
J J
A
S O
N
D
J F
M
A
M
J J
A
S O
N
D
J F
M
A
M
J J
A
S O
N
D
J
2 As
set
info
rmat
ion
Asse
ss a
dvan
ced
AM s
yste
m n
eeds
, an
d im
plem
ent s
uita
ble
appl
icat
ion
for
pred
ictiv
e m
odel
ling.
2 weeks
Asset System Officer
20,000
Asse
ss fu
ture
opt
ions
for
deve
lopm
ent o
f AM
sys
tem
.
2 weeks
Asset System Officer
8,000
Rev
iew
and
upd
ate
Prog
ram
me
Plan
ning
and
Impl
emen
tatio
n (P
PI)
info
rmat
ion
in c
onju
nctio
n w
ith A
P &
10 Y
ear P
lan
proc
ess.
3 weeks
Asset Managers
20,000
Dev
elop
use
r frie
ndly
dat
abas
e fo
r the
PP
I inf
orm
atio
n.
3 weeks
Asset Group / IT
20,000
3 R
enew
al
wor
ks
plan
ning
Und
erta
ke a
nnua
l ass
essm
ent o
f as
set c
ondi
tion,
age
, and
en
viro
nmen
tal f
acto
rs to
det
erm
ine
resi
dual
ass
et li
ves
(pre
dict
ive
mod
ellin
g).
Annual
Asset Managers
15,000
Com
pile
a re
new
al p
rogr
amm
e (a
ccou
ntin
g fo
r con
ditio
n an
d re
new
al
prof
ile d
epre
ciat
ion)
incl
udin
g co
nseq
uenc
es/ri
sks
of b
udge
t co
nstra
ints
.
4 weeks
Asset Managers
20,000
Sect
ion
11 –
Con
tinuo
us Im
prov
emen
t As
set M
anag
emen
t Pla
n 20
17 –
Was
tew
ater
130
Re
sour
ces
2017
/18
2018
/19
2019
/20
2020
/21
AM
Cat
egor
y Im
prov
emen
t Act
iviti
es
Timeframe & Responsibility
Est($)
J F
M
A
M
J J
A
S O
N
D
J F
M
A
M
J J
A
S O
N
D
J F
M
A
M
J J
A
S O
N
D
J
3 R
enew
al
wor
ks
plan
ning
Dev
elop
and
act
ion
proc
esse
s to
id
entif
y an
d pr
iorit
ise
risk
miti
gatio
n op
tions
(OD
M).
Prep
are
rene
wal
pr
ogra
mm
e.
3 weeks
Asset Managers
10,000
4 O
pera
tions
an
d m
aint
enan
ce
Doc
umen
t O&M
stra
tegy
and
O&M
pr
oces
ses
for o
ptim
isin
g pr
ogra
mm
es
(ben
efit/
cos
t app
roac
h).
1 week
Asset Managers
4,000
Rev
iew
pro
cess
es to
ens
ure
that
co
mpe
titiv
e pr
ices
are
obt
aine
d fo
r se
rvic
es d
eliv
ered
, and
that
ther
e is
th
e co
rrect
bal
ance
bet
wee
n ris
k tra
nsfe
r, pe
rform
ance
orie
ntat
ion
and
cost
s. (S
LA c
ompa
rabi
lity,
cor
e m
arke
t dat
a, s
ched
ules
of p
rices
.)
2 weeks
Asset Managers
8,000
Det
aile
d re
view
of r
esou
rce
inpu
ts to
op
erat
ion
and
mai
nten
ance
act
iviti
es.
3 weeks
Manager
20,000
5 As
set
man
agem
ent
impr
ovem
ent
Esta
blis
h an
Ass
et M
anag
emen
t C
oord
inat
ing
Gro
up to
driv
e im
prov
emen
t pla
n &
next
‘AM
P ov
er
the
next
3yr
s.
AMP Coordinator
3,000
Esta
blis
h an
nual
man
agem
ent r
evie
w
mee
tings
to c
onsi
der A
M p
erfo
rman
ce
AMP Coord/ Activity Manager
Sect
ion
11 –
Con
tinuo
us Im
prov
emen
t As
set M
anag
emen
t Pla
n 20
17 –
Was
tew
ater
131
Re
sour
ces
2017
/18
2018
/19
2019
/20
2020
/21
AM
Cat
egor
y Im
prov
emen
t Act
iviti
es
Timeframe & Responsibility
Est($)
J F
M
A
M
J J
A
S O
N
D
J F
M
A
M
J J
A
S O
N
D
J F
M
A
M
J J
A
S O
N
D
J
Dev
elop
ove
rall
AM s
trate
gy le
adin
g up
to n
ext A
M re
view
and
get
ado
pted
by
MT.
2 weeks
AMP Coordinator
8,000
5 As
set
man
agem
ent
impr
ovem
ent
Dev
elop
a p
roce
ss fo
r reg
ular
revi
ew
of ri
sk.
1 week
AMP Coordinator
5,000
Dev
elop
and
enh
ance
mea
sure
s fo
r re
silie
nce
of c
ritic
al a
sset
s to
nat
ural
ha
zard
s.
3 weeks
AMP Coordinator
5,000
Dev
elop
and
impl
emen
t pro
cess
to
ensu
re th
at th
ere
is b
ette
r int
egra
tion
betw
een
all A
MPs
.
1 week
AMP Coordinator
4,000
Dev
elop
KPI
s to
mon
itor p
rogr
ess
with
the
Impr
ovem
ent P
lan.
2 days
AMP Coordinator
1,000
6 As
set
man
agem
ent
staf
f re
sour
ces
Adop
t suc
cess
ion
plan
ning
pro
cess
to
min
imis
e ris
ks re
latin
g to
loss
of k
ey
staf
f kno
wle
dge.
1 week
Networks MT
4,000
Sect
ion
11 –
Con
tinuo
us Im
prov
emen
t As
set M
anag
emen
t Pla
n 20
17 –
Was
tew
ater
132
Re
sour
ces
2017
/18
2018
/19
2019
/20
2020
/21
AM
Cat
egor
y Im
prov
emen
t Act
iviti
es
Timeframe & Responsibility
Est($)
J F
M
A
M
J J
A
S O
N
D
J F
M
A
M
J J
A
S O
N
D
J F
M
A
M
J J
A
S O
N
D
J
Skill
gap
s in
AM
are
ass
esse
d an
d tra
inin
g pr
ogra
mm
es im
plem
ente
d to
cl
ose
any
iden
tifie
d ga
ps.
1 week
Roading Manager
12,000
6 As
set
man
agem
ent
staf
f re
sour
ces
Prom
ote
orga
nisa
tiona
l und
erst
andi
ng
of A
M p
ract
ices
and
out
com
es.
2 weeks
AMP Coordinator
10,000
7 Le
vel o
f se
rvic
e re
view
Rev
iew
LoS
stra
tegy
and
pro
gram
me.
2 weeks
AMP Coordinator
10,000
Und
erta
ke c
onsu
ltatio
n on
maj
or
issu
es, c
ase
by c
ase.
10 weeks
50,000
Und
erta
ke L
oS R
evie
w w
ith C
ounc
il.
AMP Coordinator /
Asset Managers
30,000
8 U
pdat
e AM
P AM
P M
atur
ity A
sses
smen
t and
id
entif
icat
ion
of k
ey fo
cus
area
s fo
r 20
21 P
lans
.
AMP Coordinator /
Asset Managers
12,000
Sect
ion
11 –
Con
tinuo
us Im
prov
emen
t As
set M
anag
emen
t Pla
n 20
17 –
Was
tew
ater
133
Re
sour
ces
2017
/18
2018
/19
2019
/20
2020
/21
AM
Cat
egor
y Im
prov
emen
t Act
iviti
es
Timeframe & Responsibility
Est($)
J F
M
A
M
J J
A
S O
N
D
J F
M
A
M
J J
A
S O
N
D
J F
M
A
M
J J
A
S O
N
D
J
Prep
are
AMP
usin
g ou
tput
s of
this
im
prov
emen
t pro
gram
me
and
inco
rpor
ate
furth
er re
com
men
datio
ns
from
the
2017
Pee
r Rev
iew
& A
udit
NZ
into
the
Plan
.
16 weeks
Asset Managers
30,000
8 U
pdat
e AM
P U
pdat
e AM
P pr
ogra
mm
e an
d fin
anci
als.
4 weeks
Asset Managers
16,000
Impr
ove
inte
rnal
pro
cess
es o
f CW
P.
SLA
syst
em a
nd M
arke
t C
ompa
rabi
lity
as re
quire
d.
Special Projects Manager
15,000
Section 11 – Continuous Improvement Asset Management Plan 2017 – Wastewater
135
Appendix A – Glossary Asset Management Plan 2017 – Wastewater
137
Glossary Appendix A.
Appendix A – Glossary Asset Management Plan 2017 – Wastewater
139
The following terms and acronyms (in brackets) are used in this Asset Management Plan.
Term / Acronym Definition
Activity An activity is the work undertaken on an asset or group of assets to achieve a desired outcome.
Advanced Asset Management (AAM)
Asset management practice that has evolved to a state that matches business needs. AAM employs predictive modelling, risk management and optimised renewal decision making techniques to establish asset lifecycle treatment options and related long term cashflow predictions. (See Core asset management).
Annual Budget The Annual Budget provides a statement of the direction of Council and ensures consistency and co-ordination in both making policies and decisions concerning the use of Council resources. It is a reference document for monitoring and measuring performance for the community as well as the Council itself.
Asset A physical component of a facility which has value, enables services to be provided and has an economic life of greater than 12 months.
Asset Management (AM)
The combination of management, financial, economic, engineering and other practices applied to physical assets with the objective of providing the required level of service in the most cost effective manner.
Asset Management System (AMS)
A system (usually computerised) for collecting analysing and reporting data on the utilisation, performance, lifecycle management and funding of existing assets.
Asset Management Plan (AMP)
A plan developed for the management of one or more infrastructure assets that combines multi-disciplinary management techniques (including technical and financial) over the lifecycle of the asset in the most cost effective manner to provide a specified level of service. A significant component of the plan is a long term cashflow projection for the activities.
Asset Management Strategy
A strategy for asset management covering, the development and implementation of plans and programmes for asset creation, operation, maintenance, renewal, disposal and performance monitoring to ensure that the desired levels of service and other operational objectives are achieved at optimum cost.
Asset Management Team
The team appointed by an organisation to review and monitor the corporate asset management improvement programme and ensure the development of integrated asset management systems and plans consistent with organisational goals and objectives.
Asset Register A record of asset information considered worthy of separate identification including inventory, historical, financial, condition, construction, technical and financial information about each.
Benefit Cost Ratio (B/C)
The sum of the present values of all benefits (including residual value, if any) over a specified period, or the life cycle of the asset or facility, divided by the sum of the present value of all costs.
Business Plan A plan produced by an organisation (or business units within it) which translate the objectives contained in an Annual Budget into detailed work plans for a particular, or range of, business activities. Activities may include marketing, development, operations, management, personnel, technology and financial planning
Capital Expenditure (CAPEX)
Expenditure used to create new assets or to increase the capacity of existing assets beyond their original design capacity or service potential. CAPEX increases the value of an asset.
Cash Flow The stream of costs and/or benefits over time resulting from a project investment or ownership of an asset.
Components Specific parts of an asset having independent physical or functional identity and having specific attributes such as different life expectancy, maintenance regimes, risk or criticality.
Condition Monitoring
Continuous or periodic inspection, assessment, measurement and interpretation of resulting data, to indicate the condition of a specific component so as to determine the need for some preventive or remedial action
Core Asset Management
Asset management which relies primarily on the use of an asset register, maintenance history, condition assessment, defined levels of service, and simple risk and benefit/ cost assessments in order to establish work priorities and long term cashflow predictions.
Critical Assets Assets for which the financial, business or service level consequences of failure are sufficiently severe to justify proactive inspection and rehabilitation. Critical assets have a lower threshold for action than non-critical assets.
Appendix A – Glossary Asset Management Plan 2017 – Wastewater
140
Term / Acronym Definition
Current Replacement Cost
The cost of replacing the service potential of an existing asset, by reference to some measure of capacity, with an appropriate modern equivalent asset.
Deferred Maintenance
The shortfall in rehabilitation work required to maintain the service potential of an asset.
Demand Management
The active intervention in the market to influence demand for services and assets with forecast consequences, usually to avoid or defer CAPEX expenditure. Demand management is based on the notion that as needs are satisfied expectations rise automatically and almost every action taken to satisfy demand will stimulate further demand.
Depreciated Replacement Cost (DRC)
The replacement cost of an existing asset after deducting an allowance for wear or consumption to reflect the remaining economic life of the existing asset.
Depreciation The wearing out, consumption or other loss of value of an asset whether arising from use, passing of time or obsolescence through technological and market changes. It is accounted for by the allocation of the historical cost (or revalued amount) of the asset less its residual value over its useful life.
Disposal Activities necessary to dispose of decommissioned assets.
Economic Life The period from the acquisition of the asset to the time when the asset, while physically able to provide a service, ceases to be the lowest cost alternative to satisfy a particular level of service. The economic life is at the maximum when equal to the physical life however obsolescence will often ensure that the economic life is less than the physical life.
Facility A complex comprising many assets (e.g. a hospital, water treatment plant, recreation complex, etc.) which represents a single management unit for financial, operational, maintenance or other purposes.
Geographic Information System (GIS)
Software which provides a means of spatially viewing, searching, manipulating, and analysing an electronic data-base.
I&I Infiltration and Inflow.
Infrastructure Assets
Stationary systems forming a network and serving whole communities, where the system as a whole is intended to be maintained indefinitely at a particular level of service potential by the continuing replacement and refurbishment of its components. The network may include normally Recognised ‘ordinary’ assets as components.
Level Of Service The defined service quality for a particular activity (i.e. roading) or service area (i.e. street-lighting) against which service performance may be measured. Service levels usually relate to quality, quantity, reliability, responsiveness, environmental acceptability and cost.
Life A measure of the anticipated life of an asset or component; such as time, number of cycles, distance intervals etc.
Life Cycle Life cycle has two meanings: The cycle of activities that an asset (or facility) goes through while it retains an identify as a particular asset i.e. from planning and design to decommissioning or disposal. The period of time between a selected date and the last year over which the criteria (e.g. costs) relating to a decision or alternative under study will be assessed.
Life Cycle Cost The total cost of an asset throughout its life including planning, design, construction, acquisition, operation, maintenance, rehabilitation and disposal costs.
Maintenance All actions necessary for retaining an asset as near as practicable to its original condition, but excluding rehabilitation or renewal.
Maintenance Plan Collated information, policies and procedures for the optimum maintenance of an asset, or group of assets.
Maintenance Standards
The standards set for the maintenance service, usually contained in preventive maintenance schedules, operation and maintenance manuals, codes of practice, estimating criteria, statutory regulations and mandatory requirements, in accordance with maintenance quality objectives.
Net Present Value (NPV)
The value of an asset to the organisation, derived from the continued use and subsequent disposal in present monetary values. It is the net amount of discounted total cash inflows arising from the continued use and subsequent disposal of the asset after deducting the value of the discounted total cash outflows.
Appendix A – Glossary Asset Management Plan 2017 – Wastewater
141
Term / Acronym Definition
Objective An objective is a general statement of intention relating to a specific output or activity. They are longer term aims and are not necessarily outcomes that managers can control.
Operation The active process of utilising an asset which will consume resources such as manpower, energy, chemicals and materials. Operation costs are part of an assets life cycle costs..
Optimised Renewal Decision Making (ORDM)
An optimisation process for considering and prioritising all options to rectify performance failures of assets. The process encompasses NPV analysis and risk assessment.
Performance Indicator (PI)
A qualitative or quantitative measure of a service or activity used to compare actual performance against a standard or other target. Performance indicators commonly relate to statutory limits, safety, responsiveness, cost, comfort, asset performance, reliability, efficiency, environmental protection and customer satisfaction.
Performance Monitoring
Continuous or periodic quantitative and qualitative assessments of the actual performance compared with specific objectives, targets or standards.
Pipeline Asset Management System
The computerised utilities asset management software system (IPS) supplied by Infor.
Planned Maintenance
Planned maintenance activities fall into 3 categories : Periodic - necessary to ensure the reliability or sustain the design life of an asset. Predictive - condition monitoring activities used to predict failure. Preventive - maintenance that can be initiated without routine or continuous checking (e.g. using information contained in maintenance manuals or manufacturers’ recommendations) and is not condition-based.
Rehabilitation Works to rebuild or replace parts or components of an asset, to restore it to a required functional condition and extend its life, which may incorporate some modification. Generally involves repairing the asset using available techniques and standards to deliver its original level of service (i.e. heavy patching of roads, slip-lining of sewer mains, etc.) without resorting to significant upgrading or replacement.
Renewal Works to upgrade, refurbish, rehabilitate or replace existing facilities with facilities of equivalent capacity or performance capability.
Renewal Accounting
A method of infrastructure asset accounting which recognises that infrastructure assets are maintained at an agreed service level through regular planned maintenance, rehabilitation and renewal programmes contained in an asset management plan. The system as a whole is maintained in perpetuity and therefore does not need to be depreciated. The relevant rehabilitation and renewal costs are treated as operational rather than capital expenditure and any loss in service potential is recognised as deferred maintenance.
Repair Action to restore an item to its previous condition after failure or damage.
Replacement The complete replacement of an asset that has reached the end of its life, so as to provide a similar, or agreed alternative, level of service.
Remaining Economic Life
The time remaining until an asset ceases to provide service level or economic usefulness.
Risk Cost The assessed annual cost or benefit relating to the consequence of an event. Risk cost equals the costs relating to the event multiplied by the probability of the event occurring.
Risk Management The application of a formal process to the range of possible values relating to key factors associated with a risk in order to determine the resultant ranges of outcomes and their probability of occurrence.
Routine Maintenance
Day to day operational activities to keep the asset operating (replacement of light bulbs, cleaning of drains, repairing leaks, etc.) and which form part of the annual operating budget, including preventative maintenance.
Service Potential The total future service capacity of an asset. It is normally determined by reference to the operating capacity and economic life of an asset.
Sewage Water or other liquid, including waste matter in solution or suspension, discharged from a premise.
Sewerage System of pipes, pump stations and pressure mains constructed to transport sewage from each premise to the point of sewage treatment or discharge.
Appendix A – Glossary Asset Management Plan 2017 – Wastewater
142
Term / Acronym Definition
Sewer Piped sewerage asset through which sewage conveyed. Public sewer; the section of sewer downstream of the point of discharge which is owned and maintained by Council. Private sewer / private drain (or lateral); the section of sewer between the customer’s premises and the point of discharge through which sewage is conveyed from the premises. This section of drain is owned and maintained by the customer.
Strategic Plan Strategic planning involves making decisions about the long term goals and strategies of an organisation. Strategic plans have a strong external focus, cover major portions of the organisation and identify major targets, actions and resource allocations relating to the long term survival, value and growth of the organisation.
Trade Waste Discharge is any liquid, with or without matter in suspension of solution, that is or may be discharged from trade premises in the course of any trade or industrial process or operation
Unplanned Maintenance
Corrective work required in the short term to restore an asset to working condition so it can continue to deliver the required service or to maintain its level of security and integrity.
Upgrading The replacement of an asset or addition/ replacement of an asset component which materially improves the original service potential of the asset.
Valuation Estimated asset value which may depend on the purpose for which the valuation is required, i.e. replacement value for determining maintenance levels or market value for life cycle costing.
Appendix B – Requirements of the LGA 2002 Asset Management Plan 2017 – Wastewater
143
Requirements of the LGA 2002 Appendix B.
Appendix B – Requirements of the LGA 2002 Asset Management Plan 2017 – Wastewater
145
Section 101B from the LGA 2002 Amendment Act 2014 and LGA Schedule 10 outline the information to be included in 10 Year Plans. Much of this information is provided through asset management plans.
LGA Section 101B Infrastructure Strategy
“101B Infrastructure strategy
(1) A local authority must, as part of its long-term plan, prepare and adopt an infrastructure strategy for a period of at least 30consecutive financial years.
(2) The purpose of the infrastructure strategy is to—
(a) identify significant infrastructure issues for the local authority over the period covered by the strategy; and
(b) identify the principal options for managing those issues and the implications of those options.
(3) The infrastructure strategy must outline how the local authority intends to manage its infrastructure assets, taking into account the need to—
(a) renew or replace existing assets; and
(b) respond to growth or decline in the demand for services reliant on those assets; and
(c) allow for planned increases or decreases in levels of service provided through those assets; and
(d) maintain or improve public health and environmental outcomes or mitigate adverse effects on them; and
(e) provide for the resilience of infrastructure assets by identifying and managing risks relating to natural hazards and by making appropriate financial provision for those risks.
(4) The infrastructure strategy must outline the most likely scenario for the management of the local authority’s infrastructure assets over the period of the strategy and, in that context, must—
(a) show indicative estimates of the projected capital and operating expenditure associated with the management of those assets—
(i) in each of the first 10 years covered by the strategy; and
(ii) in each subsequent period of 5 years covered by the strategy; and
(b) identify—
(i) the significant decisions about capital expenditure the local authority expects it will be required to make; and
(ii) when the local authority expects those decisions will be required; and
Appendix B – Requirements of the LGA 2002 Asset Management Plan 2017 – Wastewater
146
(iii) for each decision, the principal options the local authority expects to have to consider; and
(iv) the approximate scale or extent of the costs associated with each decision; and
(c) include the following assumptions on which the scenario is based:
(i) the assumptions of the local authority about the life cycle of significant infrastructure assets:
(ii) the assumptions of the local authority about growth or decline in the demand for relevant services:
(iii) the assumptions of the local authority about increases or decreases in relevant levels of service; and
(d) if assumptions referred to in paragraph (c) involve a high level of uncertainty,—
(i) identify the nature of that uncertainty; and
(ii) include an outline of the potential effects of that uncertainty.
(5) A local authority may meet the requirements of section 101A and this section by adopting a single financial and infrastructure strategy document as part of its long-term plan.
(6) In this section, infrastructure assets includes—
(a) existing or proposed assets to be used to provide services by or on behalf of the local authority in relation to the following groups of activities:
(i) water supply:
(ii) sewerage and the treatment and disposal of sewage:
(iii) stormwater drainage:
(iv) flood protection and control works:
(v) the provision of roads and footpaths; and
(b) any other assets that the local authority, in its discretion, wishes to include in the strategy.”
Appendix B – Requirements of the LGA 2002 Asset Management Plan 2017 – Wastewater
147
Extract from LGA Schedule 10
“Part 1
Information to be included in long-term plans
1 Community outcomes
A long-term plan must, to the extent determined appropriate by the local authority, describe the community outcomes for the local authority’s district or region.
2 Groups of activities
(1) A long-term plan must, in relation to each group of activities of the local authority,—
(a) identify the activities within the group of activities:
(b) identify the rationale for delivery of the group of activities (including the community outcomes to which the group of activities primarily contributes):
(c) outline any significant negative effects that any activity within the group of activities may have on the local community:
(d) include the information specified in clauses 4 and 5—
(i) in detail in relation to each of the first 3 financial years covered by the plan; and
(ii) in outline in relation to each of the subsequent financial years covered by the plan.
(2) In this schedule, each of the following activities is a group of activities:
(a) water supply:
(b) sewerage and the treatment and disposal of sewage:
(c) stormwater drainage:
(d) flood protection and control works:
(e) the provision of roads and footpaths.
(3) Despite subclause (2), a local authority may treat any other activities as a group of activities.
3 Capital expenditure for groups of activities
(1) A long-term plan must, in relation to each group of activities of the local authority and for each financial year covered by the plan, include a statement of the amount of capital expenditure that the authority has budgeted to—
(a) meet additional demand for an activity; and
(b) improve the level of service; and
Appendix B – Requirements of the LGA 2002 Asset Management Plan 2017 – Wastewater
148
(c) replace existing assets.
(2) For the purpose of this clause, capital expenditure budgeted for 2 or all of the purposes in subclause (1) may be treated as if it were made solely in relation to the primary purpose of the expenditure.
4 Statement of service provision
A long-term plan must, in relation to each group of activities of the local authority, include a statement of the intended levels of service provision that specifies—
(a) any performance measures specified in a rule made under section 261B for a group of activities described in clause 2(2); and
(b) the performance measures that the local authority considers will enable the public to assess the level of service for major aspects of groups of activities for which performance measures have not been specified under paragraph (a); and
(c) the performance target or targets set by the local authority for each performance measure; and
(d) any intended changes to the level of service that was provided in the year before the first year covered by the plan and the reasons for the changes; and
(e) the reason for any material change to the cost of a service.
5 Funding impact statement for groups of activities
(1) A long-term plan must, in relation to each year covered by the plan, include a funding impact statement in relation to each group of activities of the local authority.
(2) The funding impact statement must be in the prescribed form and must identify—
(a) the sources of funding to be used by the local authority; and
(b) the amount of funds expected to be produced from each source; and
(c) how the funds are to be applied.”
Appendix C – Technical Performance Measures Asset Management Plan 2017 – Wastewater
149
Technical Performance Measures Appendix C.
Appe
ndix
C –
Tec
hnic
al P
erfo
rman
ce M
easu
res
Asse
t Man
agem
ent P
lan
2017
– W
aste
wat
er
151
Tabl
e C1
: Cu
stom
er L
evel
of S
ervi
ce, P
erfo
rman
ce M
easu
res
& Ta
rget
s, &
Per
form
ance
Tar
gets
Key
Serv
ice
Crite
ria
Stak
ehol
ders
and
U
ser G
roup
s
Cus
tom
er L
evel
of
Serv
ice
Cus
tom
er P
erfo
rman
ce
Mea
sure
C
urre
nt
Perf
orm
ance
Pe
rfor
man
ce T
arge
ts
2018
/19
2019
/20
2020
/21
2021
- 28
Qua
lity
and
Hea
lth
All r
esid
ents
and
us
ers.
M
idC
entra
l Hea
lth
The
Cou
ncil
prov
ides
a
safe
(i.e
. no
risk
to p
ublic
he
alth
) was
tew
ater
co
llect
ion
serv
ice.
Res
iden
ts a
re s
atis
fied
with
the
qual
ity o
f C
ounc
il’s w
aste
wat
er
serv
ices
.
95%
95
%
95%
95
%
95%
Res
pons
iven
ess
All u
sers
Th
e C
ounc
il re
spon
ds to
re
ques
ts fo
r ser
vice
in
rela
tion
to o
verfl
ows,
bl
ocka
ges
and
faul
ts in
a
prom
pt a
nd e
ffici
ent w
ay
Med
ian
resp
onse
tim
e fo
r re
solu
tion
of o
verfl
ows
resu
lting
from
blo
ckag
es
or o
ther
faul
ts.
2.3h
rs
<8hr
(9
.5hr
tota
l) <8
hr
(9.5
hr to
tal)
<8hr
(9
.5hr
tota
l) <8
hr
(9.5
hr to
tal)
Acce
ssib
ility
Res
iden
tial a
nd
com
mer
cial
pro
perty
ow
ners
The
Cou
ncil
prov
ides
w
aste
wat
er s
ervi
ces
to
resi
dent
ial a
nd c
omm
erci
al
area
s of
the
City
Prop
ertie
s (w
ithin
the
was
tew
ater
ser
vice
s ar
ea)
are
able
to c
onne
ct to
the
was
tew
ater
ser
vice
.
100%
99
%
99%
99
%
99%
Sust
aina
bilit
y Al
l res
iden
ts.
Hor
izon
s R
egio
nal
Cou
ncil.
R
angi
tāne
M
anaw
atū
Riv
er
Lead
ers
Acco
rd
The
Cou
ncil
disp
oses
of
was
tew
ater
to
envi
ronm
enta
lly
acce
ptab
le s
tand
ards
Num
ber o
f aba
tem
ent
notic
es.
No
non-
com
plia
nce
notic
es re
ceiv
ed
0 0
0 0
Appe
ndix
C –
Tec
hnic
al P
erfo
rman
ce M
easu
res
Asse
t Man
agem
ent P
lan
2017
– W
aste
wat
er
152 Ke
y Se
rvic
e Cr
iteria
St
akeh
olde
rs a
nd
Use
r Gro
ups
C
usto
mer
Lev
el o
f Se
rvic
e C
usto
mer
Per
form
ance
M
easu
re
Cur
rent
Pe
rfor
man
ce
Perf
orm
ance
Tar
gets
2018
/19
2019
/20
2020
/21
2021
- 28
Rel
iabi
lity
All u
sers
Th
e C
ounc
il pr
ovid
es a
re
liabl
e w
aste
wat
er
colle
ctio
n se
rvic
e.
Odo
ur c
ompl
aint
s pe
r 1,
000
conn
ectio
ns p
er
year
.15
0.39
/100
0
(11
in to
tal)
1/10
00
(3 p
er y
ear)
1/10
00
(3 p
er y
ear)
1/10
00
(3 p
er y
ear)
1/10
00
(3 p
er y
ear)
Faul
t com
plai
nts
per 1
000
conn
ectio
ns p
er y
ear.
2.
6/10
00
(73
in to
tal)
3/
1000
(8
4 pe
r yea
r)
3/10
00
(84
per y
ear)
3/10
00
(84
per y
ear)
1/10
00
(84
per y
ear)
Bloc
kage
com
plai
nts
per
1,00
0 co
nnec
tions
per
ye
ar.
0.58
/100
0
(19
tota
l)
10
(280
per
ye
ar))
10
(280
per
ye
ar)
10
(280
per
ye
ar)
10
(280
per
yea
r)
Num
ber o
f com
plai
nts
abou
t the
Cou
ncil’s
re
spon
se to
issu
es w
ith
the
was
tew
ater
sys
tem
per
1,
000
conn
ectio
ns p
er
year
0.1/
1000
(3
in to
tal)
1/10
00
(28
per y
ear)
1 (2
8 pe
r yea
r) 1
(28
per y
ear)
1 (2
8 pe
r yea
r)
The
Cou
ncil
prov
ides
a
relia
ble
was
tew
ater
co
llect
ion
serv
ice.
The
num
ber o
f dry
w
eath
er w
aste
wat
er
over
flow
s fro
m th
e C
ounc
il’s s
ewer
age
syst
ems
per 1
,000
co
nnec
tions
per
yea
r. Err
or!
Book
mar
k no
t def
ined
.
1.1/
1000
38
due
to
loca
lised
blo
ckag
es
1 (3
0 pe
r yea
r) 1
(30
per y
ear)
1 (3
0 pe
r yea
r) 1
(30
per y
ear)
The
Cou
ncil
was
tew
ater
sy
stem
is d
esig
ned
to
adeq
uate
sta
ndar
ds a
nd is
op
erat
ed e
ffect
ivel
y
Med
ian
resp
onse
tim
e fo
r at
tend
ing
to o
verfl
ows
resu
lting
from
blo
ckag
es
or o
ther
faul
ts.
0.4h
rs
<1.5
hr
<1.5
hr
<1.5
hr
<1.5
hr
Sust
aina
bilit
y (C
ontin
ued)
Al
l res
iden
ts.
Hor
izon
s R
egio
nal
Cou
ncil.
R
angi
tāne
The
Cou
ncil
disp
oses
of
was
tew
ater
to
envi
ronm
enta
lly
acce
ptab
le s
tand
ards
Num
ber o
f inf
ringe
men
t no
tices
. 16
0
0 0
0 0
Num
ber o
f enf
orce
men
t or
ders
. 0
0
0 0
0
15 M
anda
tory
mea
sure
from
the
Dep
artm
ent o
f Int
erna
l Affa
irs
16 M
anda
tory
mea
sure
from
the
Dep
artm
ent o
f Int
erna
l Affa
irs
Appe
ndix
B –
Req
uire
men
ts o
f the
LG
A 20
02
Asse
t Man
agem
ent P
lan
2017
– W
aste
wat
er
153
Key
Serv
ice
Crite
ria
Stak
ehol
ders
and
U
ser G
roup
s
Cus
tom
er L
evel
of
Serv
ice
Cus
tom
er P
erfo
rman
ce
Mea
sure
C
urre
nt
Perf
orm
ance
Pe
rfor
man
ce T
arge
ts
2018
/19
2019
/20
2020
/21
2021
- 28
Man
awat
ū R
iver
Le
ader
s Ac
cord
N
umbe
r of c
onvi
ctio
ns
rece
ived
by
the
Cou
ncil
in
rela
tion
to re
sour
ce
cons
ents
.
0
0 0
0 0
A 30
-yea
r as
set
man
agem
ent p
lan
is in
pl
ace
for t
he w
aste
wat
er
activ
ity
A 30
yea
r ass
et
man
agem
ent p
lan
prep
ared
, pee
r re
view
ed a
nd
adop
ted
in
Sept
embe
r 201
8
AMP
in
plac
e (k
ey
proj
ects
fro
m A
MP
will
be
outli
ned)
AMP
in
plac
e (k
ey
proj
ects
fro
m A
MP
will
be
outli
ned)
AMP
revi
ewed
(k
ey p
roje
cts
from
AM
P w
ill be
ou
tline
d)
AMP
in p
lace
and
re
view
ed 3
-yea
rly
with
inde
pend
ent
peer
revi
ew (k
ey
proj
ects
from
AM
P w
ill be
out
lined
)
Fina
ncia
l M
anag
emen
t Al
l was
tew
ater
ra
tepa
yers
Th
e C
ounc
il m
anag
es it
s w
aste
wat
er a
ctiv
ity in
a
finan
cial
ly s
usta
inab
le w
ay
Was
tew
ater
rate
s ar
e le
ss
than
the
aver
age
of th
e na
tiona
l pee
r gro
up.
10
0%
100%
10
0%
100%
The
Cou
ncil
mai
ntai
ns
and
deve
lops
was
tew
ater
se
rvic
es to
mee
t cur
rent
an
d fu
ture
nee
ds
Was
tew
ater
Cap
ital
prog
ram
me
is p
rovi
ded
with
in b
udge
t.
Ac
hiev
ed
Achi
eved
Ac
hiev
ed
Achi
eved
The
Cou
ncil
man
ages
its
was
tew
ater
act
ivity
in a
fin
anci
ally
sus
tain
able
way
Was
tew
ater
Ope
ratio
nal
prog
ram
me
is p
rovi
ded
with
in b
udge
t
Ac
hiev
ed
Achi
eved
Ac
hiev
ed
Achi
eved
Appendix D – Risk Analysis/ Framework & Register Asset Management Plan 2017 – Wastewater
155
Risk Analysis/ Framework & Register Appendix D.
Appendix D – Risk Analysis/ Framework & Register Asset Management Plan 2017 – Wastewater
157
Risk Management Process
The adopted City Networks risk management process is consistent with Australian/New Zealand standard AS/NZ 4360 which defines risk assessment and management.
Risk Management Context
The key risk criteria adopted for City Networks for assessing the consequences of identified risks are:
Environmental and legal compliance. Safety & Health. Third Party Property Damage & Losses. Loss of Service- Extent/ duration. PNCC Business Costs Total Recovery. Corporate image.
Risk Analysis
The likelihood and impact ratings used to determine initial risk ratings are defined in Tables D1 and D2 respectively.
Table D1: Risk Probability Ratings
Code Descriptor Description (Probability)
A Almost Certain The event could occur in most circumstances, e.g. 90% + chance of occurring in the next 12 months (or in 9 out of every 10 years).
B Likely The event will probably occur in most circumstances, e.g. 70% chance of occurring in the next 12 months (or in 7 out of every 10 years).
C Moderate The event should occur at some time, e.g. 50% chance of occurring in the next 12 months (or in 5 out of every 10 years).
D Unlikely The event could occur at some time, e.g. 20-30% chance of occurring in the next 12 months (or in 2-3 out of every 10 years).
E Rare The event may occur only in exceptional circumstances, e.g. up to 10% chance of occurring in the next 12 months (or once in 10 years).
F Extremely Rare The event may occur only in extremely exceptional circumstances, e.g. up to 2% chance of occurring in the next 12 months (or once or less in 50 years).
Appe
ndix
D –
Ris
k An
alys
is/ F
ram
ewor
k &
Reg
iste
r As
set M
anag
emen
t Pla
n 20
17 –
Was
tew
ater
158
Tabl
e D2
: M
easu
res
of C
onse
quen
ces
of F
ailu
re
Area
of
Impa
ct
Fact
or
Extr
eme
Maj
or
Mod
erat
e M
inor
In
sign
ifica
nt
Lega
l Le
gal
Cou
ncil
sued
or f
ined
or
othe
rwis
e lia
ble
for m
ore
than
$2
0M.
Cou
ncil
sued
or f
ined
or
othe
rwis
e lia
ble
for $
5M -
$2
0M.
Cou
ncil
sued
or f
ined
or
othe
rwis
e lia
ble
for $
250K
-
$5M
.
Cou
ncil
sued
or f
ined
or
othe
rwis
e lia
ble
for u
p to
$2
50K.
Cou
ncil
pros
ecut
ed fo
r m
inor
offe
nce.
Cat
astro
phic
env
ironm
enta
l da
mag
e of
nat
iona
l im
porta
nce.
Pro
secu
tion.
Lo
ng te
rm s
tudy
. Im
pact
pe
rman
ent.
Serio
us e
nviro
nmen
tal
dam
age
of n
atio
nal
impo
rtanc
e. P
rose
cutio
n.
Long
term
stu
dy.
Impa
ct n
ot
fully
reve
rsib
le.
Serio
us e
nviro
nmen
tal
dam
age
of n
atio
nal
impo
rtanc
e. P
rose
cutio
n ex
pect
ed.
Impa
ct re
vers
ible
w
ithin
ten
year
s.
Serio
us e
nviro
nmen
tal
dam
age
of lo
cal i
mpo
rtanc
e.
Pros
ecut
ion
prob
able
. Im
pact
fu
lly re
vers
ible
with
in o
ne
year
.
Min
or lo
calis
ed
envi
ronm
enta
l dam
age.
Pr
osec
utio
n po
ssib
le.
Impa
ct fu
lly re
vers
ible
with
in
thre
e m
onth
s.
Cor
pora
te
Imag
e Po
litic
al
Appo
intm
ent o
f a
Com
mis
sion
er.
Dec
isio
n-m
akin
g pr
oces
s br
eaks
dow
n.
Cou
ncil
dela
ys d
ecis
ions
. Br
eakd
own
in th
e re
latio
nshi
p be
twee
n C
ounc
il an
d st
aff.
Imag
e
Nat
iona
l adv
erse
pol
itica
l co
mm
ent f
or o
ne m
onth
plu
s.
Reg
iona
l adv
erse
pol
itica
l co
mm
ent f
or s
ever
al d
ays.
Lo
cal a
dver
se p
oliti
cal
com
men
t for
one
wee
k.
Loca
l adv
erse
pol
itica
l co
mm
ent.
N
egat
ive
natio
nal m
ulti
med
ia
cove
rage
for o
ne m
onth
plu
s.
Neg
ativ
e na
tiona
l mul
ti m
edia
co
vera
ge fo
r sev
eral
day
s.
Neg
ativ
e na
tiona
l m
edia
co
vera
ge fo
r tw
o da
ys.
Neg
ativ
e na
tiona
l m
edia
co
vera
ge.
Neg
ativ
e in
tern
atio
nal m
ulti
med
ia c
over
age
for o
ne
mon
th p
lus.
Neg
ativ
e in
tern
atio
nal m
ulti
med
ia c
over
age.
Cou
ncillo
r/ M
anag
emen
t Ti
me
Unp
lann
ed c
olle
ctiv
e 30
day
s of
Cou
ncillo
rs’ o
r M
anag
emen
ts’ t
ime.
10-1
5 da
ys o
f Man
ager
s’
time.
U
p to
two
days
of M
anag
ers’
tim
e.
Serv
ice
Del
iver
y Se
rvic
e D
eliv
ery
Wat
er s
uppl
y an
d se
wag
e ou
t fo
r city
for s
ever
al d
ays
plus
. W
ater
sup
ply
and
sew
age
out
for t
wo
subu
rbs
for o
ne w
eek.
W
ater
sup
ply
and/
or s
ewag
e ou
t for
city
for o
ne d
ay.
Wat
er s
uppl
y an
d/or
sew
age
out f
or tw
o su
burb
s fo
r one
da
y.
W
ater
sup
ply
cont
amin
ated
.
Perm
anen
t los
s of
sol
id w
aste
fa
cilit
y.
Publ
ic a
men
ity c
lose
d fo
r one
m
onth
or m
ore.
Pu
blic
am
enity
clo
sed
for t
wo
wee
ks o
r mor
e.
Publ
ic a
men
ity c
lose
d fo
r one
w
eek
or m
ore.
Pu
blic
am
enity
clo
sed
for
less
than
one
wee
k.
Sy
stem
atic
cus
tom
er
com
plai
nts,
or c
ompl
aint
s re
latin
g to
mor
e th
an o
ne
occu
rrenc
e.
Isol
ated
cus
tom
er
com
plai
nts.
Appe
ndix
D –
Ris
k An
alys
is/ F
ram
ewor
k &
Reg
iste
r As
set M
anag
emen
t Pla
n 20
17 –
Was
tew
ater
159
Area
of
Impa
ct
Fact
or
Extr
eme
Maj
or
Mod
erat
e M
inor
In
sign
ifica
nt
Serv
ice
Del
iver
y Se
rvic
e D
eliv
ery
R
epea
ted
serv
ice
stan
dard
fa
ilure
or o
ne th
at a
ffect
s m
ultip
le p
eopl
e.
Isol
ated
ser
vice
sta
ndar
d fa
ilure
.
Fina
ncia
l –
PNC
C
Fina
ncia
l U
npla
nned
loss
or c
ost t
o re
inst
ate
of $
3.5M
or g
reat
er
Unp
lann
ed lo
ss o
r cos
t to
rein
stat
e be
twee
n $1
.75M
-$3
.5M
.
Unp
lann
ed lo
ss o
r cos
t to
rein
stat
e be
twee
n $1
.0M
-$1
.75M
.
Unp
lann
ed lo
ss o
r cos
t to
rein
stat
e be
twee
n $5
00K
-$1
.0M
.
Unp
lann
ed lo
ss o
r cos
t to
rein
stat
e le
ss th
an $
500K
.
Ong
oing
loss
of $
400K
pa.
O
ngoi
ng lo
ss $
200K
-$40
0K
pa.
Ong
oing
loss
$10
0K-2
00K
pa.
Fina
ncia
l –
Com
mun
ity
Fina
ncia
l C
atas
troph
ic c
onse
quen
tial
loss
in th
e co
mm
unity
(>
$20M
)
Maj
or c
onse
quen
tial l
oss
in
the
com
mun
ity ($
5M-$
20M
) Si
gnifi
cant
con
sequ
entia
l los
s in
the
com
mun
ity ($
1M-$
5M)
Som
e co
nseq
uent
ial l
oss
in
the
com
mun
ity ($
250K
-1M
) M
inim
al c
onse
quen
tial l
oss
in th
e co
mm
unity
(<$2
50K)
Com
mun
ity
Hea
lth a
nd
Safe
ty
Com
mun
ity
Pe
ople
in s
ever
al s
ubur
bs il
l th
roug
h co
ntam
inat
ed w
ater
or
sim
ilar.
Peop
le in
two-
thre
e su
burb
s ill
thro
ugh
cont
amin
ated
wat
er
or s
imila
r.
Peop
le in
one
sub
urb
ill th
roug
h co
ntam
inat
ed w
ater
or
sim
ilar.
Seve
ral p
eopl
e ill
thro
ugh
cont
amin
ated
wat
er o
r si
mila
r.
Mul
tiple
loss
of l
ife o
r city
-w
ide
epid
emic
. Lo
ss o
f life
or l
ong-
term
ho
spita
lisat
ion
requ
ired.
H
ospi
talis
atio
n re
quire
d.
Med
ical
trea
tmen
t req
uire
d.
D
issa
tisfa
ctio
n of
com
mun
ity
mea
sure
nee
ds to
be
incl
uded
?
Appendix D – Risk Analysis/ Framework & Register Asset Management Plan 2017 – Wastewater
160
Risk Evaluation:
The matrix of likelihood and consequence of failure ratings shown in Table D3 below is used to assess the level of risk, ranking events as low, moderate, significant or high risk.
Table D3: Risks Priority Rating Matrix
Likelihood Consequences
1 2 3 4 5
A H H C C C
B M H H C C
C L M H C C
D L L M H C
E L L M H H
F L L L M M
This allows all asset and corporate risks to be compared and ranked. The risk policy specifies the following broad treatment strategy for the levels of risk:
L = Low Risk: Manage by routine procedures.
M = Moderate Risk: Management responsibility must be specified.
H = High Risk: Risk & management strategy identified in AMP. Failure management plans available.
C = Critical Risk: Risk & management strategy identified in AMP, Failure management plan specifically addressing event in place.
Appendix D – Risk Analysis/ Framework & Register Asset Management Plan 2017 – Wastewater
161
Wastewater Risk Management Framework
Overview
This Wastewater activity specific risk management planning for Palmerston North City Council (PNCC) will provide the basis for future risk analysis and improvement planning.
This section covers the risk management implemented by PNCC and how it applies to current and future wastewater activities. In addition, an overview of risk management theory and practice is provided along with suggested improvements to current practices at the PNCC.
Risk management is a process used to identify the specific business risks, together with any possible risks associated with the provision and management of council’s wastewater services. This can be used to determine the direct and indirect costs associated with these risks, and form a priority-based action plan to address them.
The outcome of this evaluation is to be used to:
Emphasize the importance of continuing to provide Council’s wastewater services and manage inherent risks
Continually identify improvements required to Council wastewater services to avoid risk events, or minimise their impact or to realise identified opportunities.
A Risk is defined in AS/NZS ISO 31000:2009 – Risk management – Principles and guidelines, as:
“Effect of Uncertainty on Objectives”
Effect: Deviation from the expected – positive or negative.
Objectives: Can have different aspects (see Risk Types) and can apply at different levels (see Risk Hierarchy Levels).
Risks: Often characterized by reference to potential events and consequences, and is often expressed in terms of a combination of the consequences of an event and the associated likelihood.
Uncertainty: The state, even partial, of deficiency of information related to, understanding or knowledge of an event, its consequence, or likelihood.
Putting the Risks into Perspective
Council policy and operation cannot influence all the factors contributing to these risk events. However, PNCC has a responsibility to assess the risks faced by the wastewater activity in order to best manage the services with the resources available to avoid and mitigate the effects of any event.
In the following risk analysis, PNCC has highlighted a number of key risk areas across the activity including:
Moderate natural hazards Contract / SLA management Legislative noncompliance Network capacity failure
Appendix D – Risk Analysis/ Framework & Register Asset Management Plan 2017 – Wastewater
162
Network breaks or blockages Treatment plant failure
These are discussed in further detail in the Risk Registers and the overall Action Plan contained in this risk section.
Levels of Risk
The purpose of this risk plan is to identify the risks associated with the provision of wastewater services. This requires approaching the risks from many perspectives including financial, operational, reputational and public health and safety.
These risks are pertinent to both a higher, corporate level, and to a more detailed asset –specific level, but do not substitute for more specific risk analysis at those levels (see Figure D1 below).
The next step beyond this risk analysis is to develop more detailed risk plans where the criticality of specific assets is assessed and an action plan developed as appropriate.
Figure D1: Risk Hierarchy Levels
Risk Types
Risks events derive from, or impact in one or more of the following ways. These are identified against each risk in the risk register as risk types.
Operational
Risks affecting the efficient operation of wastewater system and its’ ability to function effectively.
Corporate Risk
Activity Risk
Asset Specific Risks
Highest level covering risks for the entire organisation
Considers risks from all perspectives affecting the management of the activity and its assets
Specific critical asset/service risks, project risks
Appendix D – Risk Analysis/ Framework & Register Asset Management Plan 2017 – Wastewater
163
Financial/Economic
Risks related to the financial management of PNCC and its’ ability to fund Council services now, and into the future
Risks resulting from an externally imposed economic environment.
Health and Safety
A risk event that adversely impacts on the health and safety of the community or Council staff.
Reputation / Image
Risks that affect the way Council and staff are perceived:
By the community By staff Nationwide and internationally By stakeholders By the media
Legislative
A risk event that results in PNCC either unknowingly or knowingly breaching statutes and regulations, or being exposed to liability.
Environmental
Potential or actual negative environmental or ecological impacts, regardless of whether these are reversible or irreversible in nature.
Current Situation
PNCC’s wastewater activity has not undertaken previous risk assessments on the service, but has carried out an asset level risk exercise for inclusion in the asset management plan.
Corporate Policy
PNCC is seeking to establish a corporate risk policy in place and a Risk and Assurance team, which will have an overview of all risk exposures within the organisation, including corporate, financial, customer, assets. Infrastructure Services staff will contribute regularly to the work of this group.
Each risk identified in this plan will be entered into the corporate risk register.
Risk Management Process
The following sections expand upon the risk management process as identified in the flowchart (Figure overleaf) and detail the key elements of the risk management process. The risk criteria and matrices have been established as the basis for risk evaluation developed in accordance with the AS/NZS ISO 31000:2009 international risk standard.
Appendix D – Risk Analysis/ Framework & Register Asset Management Plan 2017 – Wastewater
164
Identify Risks
All practically possible risks affecting the Council should be identified, entered into the risk register and risk types assigned. The register is used to record and summarise each risk and to outline current mitigation measures and potential future options for management of the risk.
Determine Likelihood and Consequence for Gross Risk Factor
Table and demonstrate the scales used to determine the likelihood and consequence levels, which are then input into the risk matrix to determine the effect of a risk event.
Assessment of the likelihood of occurrence and severity of consequences should be based on as much real data as possible, for example local knowledge or recorded events such as maintenance records, weather events etc. Some analysis may be required to verify the data.
The likelihood scales identify how likely, or often, a particular event is expected to occur and these are shown in Table D4 below. The descriptors are not mandatory, but are presented as a guide to assist ranking the probability of occurrence in line with the nature of each risk. For example, a risk such as a sewer overflow is considered to be ‘rare’ if it occurs once every ten years, whereas a tsunami occurring every ten years would be considered ‘frequent’.
Table D4: Likelihood of Occurrence
Risk - Likelihood of Occurrence
Likelihood Rating Descriptor
Almost Certain A The event could occur in most circumstances, e.g. 90% + chance of occurring in the next 12 months (or in 9 out of every 10 years).
Likely B The event will probably occur in most circumstances, e.g. 70% chance of occurring in the next 12 months (or in 7 out of every 10 years).
Moderate C The event should occur at some time, e.g. 50% chance of occurring in the next 12 months (or in 5 out of every 10 years).
Unlikely D The event could occur at some time, e.g. 20-30% chance of occurring in the next 12 months (or in 2-3 out of every 10 years).
Rare E The event may occur only in exceptional circumstances, e.g. up to 10% chance of occurring in the next 12 months (or once in 10 years).
Extremely Rare F The event may occur only in extremely exceptional circumstances, e.g. up to 2% chance of occurring in the next 12 months (or once or less in 50 years).
Appendix D – Risk Analysis/ Framework & Register Asset Management Plan 2017 – Wastewater
165
Figure D2: Risk Management Process
Identify Possible Risks
Determine likelihood and severity of consequence
Determine Gross Risk factor using a risk register/matrix
(likelihood x consequence)
Identify current processes & systems in place that effectively help to avoid or
minimise the chances & severity of each risk
Determine Net Risk factor using the risk register/matrix
(likelihood x consequence)
Brainstorm possible risk management options to further reduce risk level for
each risk
Prioritise risks based on size of Net Risk and criticality of service, process or asset
Form a practical and achievable Action Plan with priorities aligned with size of
each risk. Set Future Risk
Ensure mechanisms are in place to monitor, measure, report on and review
the Action Plan
New or Varied Risks
Review existing risks only
?
Obtain input from the best available information & perform
analysis as required
Approach from all possible applicable perspectives eg: Operational Financial/Economic Health & Safety
Gross Risk is based on “no measures in place” to prevent or minimise the likelihood or consequence i.e:“How bad would it be if we did nothing?”
Audits /investigations may be required to measure “effectiveness”
Net Risk = Gross Risk minus ‘measures in place’ to avoid or mitigate. This can also be called “Current Actual Risk”.
Use of available techniques to determine various options for risk treatment and cost benefit approach eg: Optimised decision making
Progress action, monitor and report, and repeat the cycle at regular intervals
Future Risk is the risk level expected once management actions are effectively implemented.
Reputation/Image Legislative Environmental
Appe
ndix
D –
Ris
k An
alys
is/ F
ram
ewor
k &
Reg
iste
r As
set M
anag
emen
t Pla
n 20
17 –
Was
tew
ater
166
Tabl
e D5
: Con
sequ
ence
Rat
ing
Area
of
Impa
ct
Fact
or
Extr
eme
Maj
or
Mod
erat
e M
inor
In
sign
ifica
nt
Lega
l Le
gal
Cou
ncil
sued
or f
ined
or
othe
rwis
e lia
ble
for m
ore
than
$2
0M.
Cou
ncil
sued
or f
ined
or
othe
rwis
e lia
ble
for $
5M -
$2
0M.
Cou
ncil
sued
or f
ined
or
othe
rwis
e lia
ble
for $
250K
-
$5M
.
Cou
ncil
sued
or f
ined
or
othe
rwis
e lia
ble
for u
p to
$2
50K.
Cou
ncil
pros
ecut
ed fo
r m
inor
offe
nce.
Cat
astro
phic
env
ironm
enta
l da
mag
e of
nat
iona
l im
porta
nce.
Pro
secu
tion.
Lo
ng te
rm s
tudy
. Im
pact
pe
rman
ent.
Serio
us e
nviro
nmen
tal
dam
age
of n
atio
nal
impo
rtanc
e. P
rose
cutio
n.
Long
term
stu
dy.
Impa
ct n
ot
fully
reve
rsib
le.
Serio
us e
nviro
nmen
tal
dam
age
of n
atio
nal
impo
rtanc
e. P
rose
cutio
n ex
pect
ed.
Impa
ct re
vers
ible
w
ithin
ten
year
s.
Serio
us e
nviro
nmen
tal
dam
age
of lo
cal i
mpo
rtanc
e.
Pros
ecut
ion
prob
able
. Im
pact
fu
lly re
vers
ible
with
in o
ne
year
.
Min
or lo
calis
ed
envi
ronm
enta
l dam
age.
Pr
osec
utio
n po
ssib
le.
Impa
ct fu
lly re
vers
ible
with
in
thre
e m
onth
s.
Cor
pora
te
Imag
e Po
litic
al
Appo
intm
ent o
f a
Com
mis
sion
er.
Dec
isio
n-m
akin
g pr
oces
s br
eaks
dow
n.
Cou
ncil
dela
ys d
ecis
ions
. Br
eakd
own
in th
e re
latio
nshi
p be
twee
n C
ounc
il an
d st
aff.
Imag
e
Nat
iona
l adv
erse
pol
itica
l co
mm
ent f
or o
ne m
onth
plu
s.
Reg
iona
l adv
erse
pol
itica
l co
mm
ent f
or s
ever
al d
ays.
Lo
cal a
dver
se p
oliti
cal
com
men
t for
one
wee
k.
Loca
l adv
erse
pol
itica
l co
mm
ent.
N
egat
ive
natio
nal m
ulti
med
ia
cove
rage
for o
ne m
onth
plu
s.
Neg
ativ
e na
tiona
l mul
ti m
edia
co
vera
ge fo
r sev
eral
day
s.
Neg
ativ
e na
tiona
l m
edia
co
vera
ge fo
r tw
o da
ys.
Neg
ativ
e na
tiona
l m
edia
co
vera
ge.
Neg
ativ
e in
tern
atio
nal m
ulti
med
ia c
over
age
for o
ne
mon
th p
lus.
Neg
ativ
e in
tern
atio
nal m
ulti
med
ia c
over
age.
Cou
ncillo
r/ M
anag
emen
t Ti
me
Unp
lann
ed c
olle
ctiv
e 30
day
s of
Cou
ncillo
rs’ o
r M
anag
emen
ts’ t
ime.
10-1
5 da
ys o
f Man
ager
s’
time.
U
p to
two
days
of M
anag
ers’
tim
e.
Serv
ice
Del
iver
y Se
rvic
e D
eliv
ery
Wat
er s
uppl
y an
d se
wag
e ou
t fo
r city
for s
ever
al d
ays
plus
. W
ater
sup
ply
and
sew
age
out
for t
wo
subu
rbs
for o
ne w
eek.
W
ater
sup
ply
and/
or s
ewag
e ou
t for
city
for o
ne d
ay.
Wat
er s
uppl
y an
d/or
sew
age
out f
or tw
o su
burb
s fo
r one
da
y.
W
ater
sup
ply
cont
amin
ated
.
Perm
anen
t los
s of
sol
id w
aste
fa
cilit
y.
Publ
ic a
men
ity c
lose
d fo
r one
m
onth
or m
ore.
Pu
blic
am
enity
clo
sed
for t
wo
wee
ks o
r mor
e.
Publ
ic a
men
ity c
lose
d fo
r one
w
eek
or m
ore.
Pu
blic
am
enity
clo
sed
for
less
than
one
wee
k.
Appe
ndix
D –
Ris
k An
alys
is/ F
ram
ewor
k &
Reg
iste
r As
set M
anag
emen
t Pla
n 20
17 –
Was
tew
ater
167
Area
of
Impa
ct
Fact
or
Extr
eme
Maj
or
Mod
erat
e M
inor
In
sign
ifica
nt
Sy
stem
atic
cus
tom
er
com
plai
nts,
or c
ompl
aint
s re
latin
g to
mor
e th
an o
ne
occu
rrenc
e.
Isol
ated
cus
tom
er
com
plai
nts.
Serv
ice
Del
iver
y Se
rvic
e D
eliv
ery
R
epea
ted
serv
ice
stan
dard
fa
ilure
or o
ne th
at a
ffect
s m
ultip
le p
eopl
e.
Isol
ated
ser
vice
sta
ndar
d fa
ilure
.
Fina
ncia
l –
PNC
C
Fina
ncia
l U
npla
nned
loss
or c
ost t
o re
inst
ate
of $
3.5M
or g
reat
er
Unp
lann
ed lo
ss o
r cos
t to
rein
stat
e be
twee
n $1
.75M
-$3
.5M
.
Unp
lann
ed lo
ss o
r cos
t to
rein
stat
e be
twee
n $1
.0M
-$1
.75M
.
Unp
lann
ed lo
ss o
r cos
t to
rein
stat
e be
twee
n $5
00K-
$1.0
M.
Unp
lann
ed lo
ss o
r cos
t to
rein
stat
e le
ss th
an $
500K
.
Ong
oing
loss
of $
400K
pa.
O
ngoi
ng lo
ss $
200K
-$40
0K
pa.
Ong
oing
loss
$10
0K-2
00K
pa.
Fina
ncia
l –
Com
mun
ity
Fina
ncia
l C
atas
troph
ic c
onse
quen
tial
loss
in th
e co
mm
unity
(>
$20M
)
Maj
or c
onse
quen
tial l
oss
in
the
com
mun
ity ($
5M-$
20M
) Si
gnifi
cant
con
sequ
entia
l los
s in
the
com
mun
ity ($
1M-$
5M)
Som
e co
nseq
uent
ial l
oss
in
the
com
mun
ity ($
250K
-1M
) M
inim
al c
onse
quen
tial l
oss
in th
e co
mm
unity
(<$2
50K)
Com
mun
ity
Hea
lth a
nd
Safe
ty
Com
mun
ity
Pe
ople
in s
ever
al s
ubur
bs il
l th
roug
h co
ntam
inat
ed w
ater
or
sim
ilar.
Peop
le in
two-
thre
e su
burb
s ill
thro
ugh
cont
amin
ated
wat
er
or s
imila
r.
Peop
le in
one
sub
urb
ill th
roug
h co
ntam
inat
ed w
ater
or
sim
ilar.
Seve
ral p
eopl
e ill
thro
ugh
cont
amin
ated
wat
er o
r si
mila
r.
Mul
tiple
loss
of l
ife o
r city
-w
ide
epid
emic
. Lo
ss o
f life
or l
ong-
term
ho
spita
lisat
ion
requ
ired.
H
ospi
talis
atio
n re
quire
d.
Med
ical
trea
tmen
t req
uire
d.
D
issa
tisfa
ctio
n of
com
mun
ity
mea
sure
nee
ds to
be
incl
uded
?
Appendix D – Risk Analysis/ Framework & Register Asset Management Plan 2017 – Wastewater
168
After the likelihood and consequence factors have been determined, the level of risk is calculated by multiplying the Likelihood of Occurrence (Table) and Consequence Rating (Table) together.
Risk = the likelihood of an event occurring X the consequence of such an event.
The final outcome is a risk rating. The risk rating enables definition between those risks that are significant and those that are of a lesser nature. Having established the comparative risk level applicable to individual risks, it is possible to rank those risks. Five risk categories have been used: Critical, High, Moderate, Low and Insignificant (see Tables 3 & 4).
Once the impact has been ranked according to the relative risk level it poses, it is then possible to target the treatment of the risk exposure, by beginning with the highest risks and identifying the potential mitigation measures.
Risk Matrix
Likelihood Consequences
Insignificant Minor Moderate Major Extreme
A M M H C C
B L M H H C
C L M M H C
D I L M M H
E I L L M M
F I I L L M
Comparative Levels of Risk
Risk Level Definition Action
I Insignificant Risk Examine where un-needed action can be reduced.
L Low Risk Managed by routine procedures.
M Medium Risk Management responsibility must be specified and risk controls reviewed.
H High Risk Risk and management strategy identified in AMP – Failure management plans available.
C Critical Risk Risk and management strategy identified in AMP – Failure management plan specifically addressing event in place.
Initially, the gross risk needs to be calculated, so likelihood and consequences need to be considered as if there were no measures in place to prevent or mitigate the risk occurrence. Essentially gross risk is an exercise to determine “What is the worst that could happen?” Once the gross risk is determined it is possible to investigate the current systems and processes to identify the net risk and then formulate an action plan to further reduce the likelihood or consequences of identified risks occurring.
Identify Current Systems & Processes, and their Effectiveness
Identifying current systems and processes are identified, and as far as resources allow, their effectiveness measured. It is often practical to identify these processes and systems initially, and rank the effectiveness conservatively until the audits and actual practice prove otherwise. Audits can be identified as part of the improvement process.
Appendix D – Risk Analysis/ Framework & Register Asset Management Plan 2017 – Wastewater
169
Effectiveness of existing systems and processes is expressed in the following categories:
Rating Descriptor
Excellent Fulfils requirements thoroughly, very robust and positive measurable effects
Good Fulfils requirements, robust and measurable, room for improvement
Fair Barely fulfils requirements, effects hard to measure (or haven’t been audited or measured), improvement required
Poor Not fulfilling requirements, little measurement or effect on overall risk
Very poor Totally ineffective in avoiding or mitigating associated risk events
Determine Net Risk
The net risk is the actual risk that exists considering the effective measures implemented. The measures in place reduce either, or both, the consequence and the likelihood of a risk occurrence. The revised factors are input into the same risk matrix to obtain the Net Risk Factor.
Risk Action Plan
The Risk Action Plan is compiled from the Risk Register and highlights the most significant risks faced as determined in the risk register. The main risks are listed in order of severity (primarily gross risk, and secondarily net risk) as assigned in consultation with key Council officers.
Actions that are required to achieve the desired improvements are indicated along with how progress on these actions will be monitored and reported. Where applicable, action tasks will detail timeframes for achievement, and responsibility for these actions.
A priority order of issues to be addressed is obtained by sorting first the gross risk levels and then the net risk levels, and identification of the biggest gaps and opportunities for improvement.
Gaps between gross and net risk indicate the importance of effective current practices to prevent gross risk events. Accordingly, improvement actions should focus on the things that will further assure Council that current practices remain effective.
Gaps between net risk and an acceptable future risk require improvement actions that will reduce current risk levels.
The most suitable risk reduction actions must be determined by considering options and resources available to the Council. Costs and benefits of these actions should be analysed to determine those actions yielding the greatest benefit (risk reduction) for the least cost. The best available techniques should be utilised to analyse the options e.g. optimised decision-making (ODM).
Higher
Risk
Gross Risk Future RiskNet Risk
Lower
RiskActions required to provide assurance
that current practices remain effective
Actions required to reach acceptable risk
levels in future
Current practices and strategies Risk treatments to be applied
Appendix D – Risk Analysis/ Framework & Register Asset Management Plan 2017 – Wastewater
170
Application of ODM applies a ‘value chain’ to the proposed actions rather than just working from the highest risk down regardless of cost. For example:
A high risk may have to remain due to the prohibitive costs associated with avoidance or mitigation
A medium risk event could be easily and cost-effectively avoided within resources available
The options for mitigating risks considered to reduce the cause, probability or impact of failure, are typically:
Rating Descriptor
Accept Risk Accept the Risk, fund and resource any risk impacts.
Strategic Change Implement strategic planning, organisational improvements.
Operational Change Implement technical improvements, procedural changes.
Risk Transfer Outsourcing, Improving contract terms, increased insurance.
Link to Improvement Plans
Actions identified in this Risk Management analysis should be directly linked to actions identified in appropriate improvement plans where they exist e.g. Asset Management Improvement Plan, where resources should be identified, approval of resources noted, and a defined method provided for revisiting and reviewing progress against each action item. Where an equivalent action item is not listed in the Improvement Plan, it should be added.
In all cases, the appropriate risk reference number should be noted in the Improvement Plan, and the Improvement number should be noted in the Risk Action Plan.
Monitor, Measure, Report, Review Plan and Actions
Management options listed in the risk tables have been refined into actions for each risk listed. These are the actions that are required to cost-effectively reduce the net risk by increasing PNCC’s ability to minimise the chances of the risk event occurring, or minimising the consequences should it occur.
Actions should, where possible, align with the overall management objectives of Council, not simply aimed at the minimisation of risk. If possible, proposed actions should align with other initiatives to:
Reduce capital investment costs. Reduce operating and maintenance costs. Reduce business risk exposure (BRE). Increase effective asset life / value. Increase level of service.
The resulting action plan for risk treatment needs to be practical and achievable such that the necessary resources and time frames are realistically met. The actions also need to be able to be monitored and measured.
The monitoring/reporting column of the Risk Action Table specifies:
Responsibility: Nominated person responsible for ensuring the risks are managed and that improvements are carried out in accordance with the programme;
Timeframe: Achievable target date to be monitored and reported against; and
Appendix D – Risk Analysis/ Framework & Register Asset Management Plan 2017 – Wastewater
171
Method and Frequency of Monitoring: This entire Action Table will be monitored by the Risk Management Steering Committee, but there will be certain actions that are being monitored and reported in other forums. These forums are to be specified and the frequency with which these actions will be reviewed.
The actions listed will be reported, monitored and reviewed regularly at the Risk Management Steering Group and various Group forums.
As necessary, this group will need to revise timeframes, responsibility, and even the appropriateness of continuing with the proposed action, or adding new actions.
As actions are complete, the net risk should reduce in most cases. The risk tables will need to be reviewed against these and updated to reflect these improvements.
Review Risks
Most of the time, the risks identified will remain the same and reviews will occur in the context of these risks. However, it will be important to recognise when a new risk arises, or an existing risk changes in nature. In the latter case, the gross risk also needs to be re-evaluated.
Appendix E – 30 Year Financial Forecasts Asset Management Plan 2017 – Wastewater
173
30 Year Financial Forecasts Appendix E.
175
Tabl
e E1
: Th
irty
Year
Ope
ratin
g Bu
dget
OPE
RA
TIN
G E
XPEN
DIT
UR
E ['0
00s]
20
18/1
9 20
19/2
0 20
20/2
1 20
21/2
2 20
22/2
3 20
23/2
4 20
24/2
5 20
25/2
6 20
26/2
7 20
27/2
8 20
28/2
9 20
29/3
0 20
30/3
1 20
31/3
2 20
32/3
3
Act
ivity
Del
iver
y $2
,725
$2
,799
$2
,783
$2
,827
$2
,827
$2
,827
$2
,827
$2
,827
$4
,827
$6
,842
$6
,842
$6
,842
$6
,842
$6
,842
$6
,842
Serv
ice
Leve
l Agr
eem
ents
$2
,400
$2
,449
$2
,433
$2
,477
$2
,477
$2
,477
$2
,477
$2
,477
$4
,477
$6
,492
$6
,492
$6
,492
$6
,492
$6
,492
$6
,492
Exte
rnal
Con
tract
s $3
25
$350
$3
50
$350
$3
50
$350
$3
50
$350
$3
50
$350
$3
50
$350
$3
50
$350
$3
50
Act
ivity
Man
agem
ent
$2,0
95
$2,0
98
$2,0
90
$2,0
90
$2,0
80
$2,0
80
$2,0
80
$2,0
80
$2,0
80
$2,0
80
$2,0
80
$2,0
80
$2,0
80
$2,1
00
$2,1
00
City
Net
wor
ks L
abou
r and
Ove
rhea
ds
$937
$9
39
$931
$9
31
$931
$9
31
$931
$9
31
$931
$9
31
$931
$9
31
$931
$9
31
$931
Con
sum
able
s $4
00
$400
$4
00
$400
$4
00
$400
$4
00
$400
$4
00
$400
$4
00
$400
$4
00
$400
$4
00
Elec
trici
ty
$210
$2
10
$210
$2
10
$210
$2
10
$210
$2
10
$210
$2
10
$210
$2
10
$210
$2
10
$210
Insu
ranc
e $1
91
$191
$1
91
$191
$1
91
$191
$1
91
$191
$1
91
$191
$1
91
$191
$1
91
$191
$1
91
Con
sulta
ncy
$163
$1
63
$163
$1
63
$153
$1
53
$153
$1
53
$153
$1
53
$153
$1
53
$153
$1
73
$173
Rat
es
$79
$79
$79
$79
$79
$79
$79
$79
$79
$79
$79
$79
$79
$79
$79
Mis
cella
neou
s $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1
Gas
$3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0
Lega
l $5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
Rea
ctiv
e M
aint
enan
ce
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
Plan
t Rep
airs
and
Mai
nten
ance
$1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0
Softw
are
Lice
nses
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
Ope
ratin
g Pr
ogra
mm
es
$940
$9
40
$1,1
90
$1,1
90
$940
$9
40
$200
$2
00
$200
$2
00
$200
$2
00
$200
$2
00
$200
1319
-Tot
ara
Roa
d W
aste
wat
er T
reat
men
t Pla
nt -
Con
sent
Ren
ewal
Upg
rade
Opt
ions
Ana
lysi
s $7
40
$740
$9
90
$990
$7
40
$740
-
- -
- -
- -
- -
1401
-City
Wid
e In
filtra
tion
& In
flow
Inve
stig
atio
ns
$200
$2
00
$200
$2
00
$200
$2
00
$200
$2
00
$200
$2
00
$200
$2
00
$200
$2
00
$200
Inte
rest
$6
99
$756
$7
70
$713
$6
66
$1,1
86
$2,8
05
$4,6
50
$5,8
25
$6,0
82
$5,8
19
$5,5
30
$5,1
75
$4,8
17
$4,4
38
Dep
reci
atio
n $4
,145
$4
,183
$4
,221
$4
,230
$4
,239
$4
,253
$4
,262
$5
,494
$6
,100
$6
,500
$6
,507
$6
,523
$6
,523
$6
,523
$6
,523
TOTA
L EX
PEN
DIT
UR
E $1
0,60
4 $1
0,77
6 $1
1,05
4 $1
1,05
1 $1
0,75
2 $1
1,28
6 $1
2,17
4 $1
5,25
1 $1
9,03
1 $2
1,70
3 $2
1,44
8 $2
1,17
5 $2
0,82
0 $2
0,48
2 $2
0,10
4
176
OPE
RA
TIN
G E
XPEN
DIT
UR
E ['0
00s]
20
33/3
4 20
34/3
5 20
35/3
6 20
36/3
7 20
37/3
8 20
38/3
9 20
39/4
0 20
40/4
1 20
41/4
2 20
42/4
3 20
43/4
4 20
44/4
5 20
45/4
6 20
46/4
7 20
47/4
8
Act
ivity
Del
iver
y $6
,842
$6
,842
$6
,842
$6
,842
$6
,842
$6
,842
$6
,842
$6
,842
$6
,842
$6
,842
$6
,842
$6
,842
$6
,837
$6
,837
$6
,837
Serv
ice
Leve
l Agr
eem
ents
$6
,492
$6
,492
$6
,492
$6
,492
$6
,492
$6
,492
$6
,492
$6
,492
$6
,492
$6
,492
$6
,492
$6
,492
$6
,487
$6
,487
$6
,487
Exte
rnal
Con
tract
s $3
50
$350
$3
50
$350
$3
50
$350
$3
50
$350
$3
50
$350
$3
50
$350
$3
50
$350
$3
50
Act
ivity
Man
agem
ent
$2,1
00
$2,0
98
$2,0
98
$2,0
98
$2,0
96
$2,0
96
$2,0
96
$2,0
96
$2,0
96
$2,0
96
$2,0
96
$2,0
96
$2,0
96
$2,0
96
$2,1
00
City
Net
wor
ks L
abou
r and
Ove
rhea
ds
$931
$9
29
$929
$9
29
$927
$9
27
$927
$9
27
$927
$9
27
$927
$9
27
$927
$9
27
$931
Con
sum
able
s $4
00
$400
$4
00
$400
$4
00
$400
$4
00
$400
$4
00
$400
$4
00
$400
$4
00
$400
$4
00
Elec
trici
ty
$210
$2
10
$210
$2
10
$210
$2
10
$210
$2
10
$210
$2
10
$210
$2
10
$210
$2
10
$210
Insu
ranc
e $1
91
$191
$1
91
$191
$1
91
$191
$1
91
$191
$1
91
$191
$1
91
$191
$1
91
$191
$1
91
Con
sulta
ncy
$173
$1
73
$173
$1
73
$173
$1
73
$173
$1
73
$173
$1
73
$173
$1
73
$173
$1
73
$173
Rat
es
$79
$79
$79
$79
$79
$79
$79
$79
$79
$79
$79
$79
$79
$79
$79
Mis
cella
neou
s $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1 $6
1
Gas
$3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0
Lega
l $5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
Rea
ctiv
e M
aint
enan
ce
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
Plan
t Rep
airs
and
Mai
nten
ance
$1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0 $1
0
Softw
are
Lice
nses
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
$5
Ope
ratin
g Pr
ogra
mm
es
$200
$2
00
$200
$2
00
$200
$2
00
$200
$2
00
$200
$2
00
$200
$2
00
$200
$2
00
$200
1319
-Tot
ara
Roa
d W
aste
wat
er T
reat
men
t Pla
nt -
Con
sent
Ren
ewal
Upg
rade
Opt
ions
Ana
lysi
s -
- -
- -
- -
- -
- -
- -
- -
1401
-City
Wid
e In
filtra
tion
& In
flow
Inve
stig
atio
ns
$200
$2
00
$200
$2
00
$200
$2
00
$200
$2
00
$200
$2
00
$200
$2
00
$200
$2
00
$200
Inte
rest
$4
,038
$3
,614
$3
,163
$2
,705
$2
,232
$1
,752
$1
,288
$8
06
$292
-$
241
-$76
1 -$
1,16
7 -$
1,39
4 -$
1,48
9 -$
1,48
5
Dep
reci
atio
n $6
,527
$6
,527
$6
,527
$6
,527
$6
,527
$6
,527
$6
,527
$6
,527
$6
,527
$6
,527
$6
,527
$6
,520
$6
,520
$6
,536
$6
,536
TOTA
L EX
PEN
DIT
UR
E $1
9,70
6 $1
9,28
0 $1
8,83
0 $1
8,37
2 $1
7,89
6 $1
7,41
7 $1
6,95
3 $1
6,47
1 $1
5,95
6 $1
5,42
4 $1
4,90
4 $1
4,49
1 $1
4,25
9 $1
4,18
0 $1
4,18
8
177
Tabl
e E2
: Th
irty
Year
Ren
ewal
Bud
get
REN
EWA
L EX
PEN
DIT
UR
E ['0
00s]
20
18/1
9 20
19/2
0 20
20/2
1 20
21/2
2 20
22/2
3 20
23/2
4 20
24/2
5 20
25/2
6 20
26/2
7 20
27/2
8 20
28/2
9 20
29/3
0 20
30/3
1 20
31/3
2 20
32/3
3
Was
tew
ater
Col
lect
ion
$1,7
50
$2,4
25
$2,3
07
$2,2
55
$2,0
57
$2,2
90
$2,2
90
$2,0
37
$2,0
55
$2,2
85
$2,0
85
$1,8
35
$2,2
85
$2,9
85
$1,8
55
54-C
ity-w
ide
- Was
tew
ater
Pip
e R
enew
al
$1,6
00
$1,8
00
$2,0
00
$2,0
00
$2,0
00
$2,0
00
$2,0
00
$2,0
00
$2,0
00
$2,0
00
$1,8
00
$1,8
00
$1,8
00
$1,8
00
$1,8
00
65-C
ity-w
ide
- Was
tew
ater
Pum
p St
atio
n R
enew
al
$150
$1
25
$137
$8
5 $5
7 $4
0 $4
0 $3
7 $5
5 $3
5 $3
5 $3
5 $3
5 $3
5 $5
5
647-
Trem
aine
/Fea
ther
ston
- W
aste
wat
er T
runk
Mai
n U
pgra
de
(Ren
ewal
Com
pone
nt)
- -
- -
- -
- -
- -
- -
$450
$1
,150
-
1351
-Eas
tern
Tru
nk M
ain
- H
okow
hitu
Cam
pus
Ren
ewal
-
$250
-
- -
- -
- -
- -
- -
- -
1378
-Ben
nett
Stre
et 5
25 T
runk
mai
n R
enew
al
- -
$170
$1
70
- -
$250
-
- $2
50
- -
- -
-
1379
-Max
wel
l's L
ine
825
Was
tew
ater
Tru
nk M
ain
Ren
ewal
-
$250
-
- -
$250
-
- -
- $2
50
- -
- -
Trea
tmen
t and
Dis
posa
l $1
,943
$6
0 $1
00
$830
$5
0 $3
50
$20
$20
$20
$20
$20
$20
$520
$9
5 $2
0
179-
Tota
ra R
oad
Was
tew
ater
Tr
eatm
ent P
lant
- M
inor
Equ
ipm
ent
Ren
ewal
s $1
30
$60
$100
$5
0 $5
0 $5
0 $2
0 $2
0 $2
0 $2
0 $2
0 $2
0 $2
0 $2
0 $2
0
1050
-Tot
ara
Roa
d W
aste
wat
er
Trea
tmen
t Pla
nt -
Rep
lace
men
t of
PLC
s an
d SC
ADA
-
- -
- -
- -
- -
- -
- $1
50
$75
-
1059
-Tot
ara
Roa
d W
aste
wat
er
Trea
tmen
t Pla
nt -
Rep
lace
men
t of
Grit
Rem
oval
Sys
tem
s $4
95
- -
- -
- -
- -
- -
- -
- -
1067
-Tot
ara
Roa
d W
aste
wat
er
Trea
tmen
t Pla
nt -
Rep
lace
men
t of
Secu
rity
Fenc
e an
d G
ate
$250
-
- -
- -
- -
- -
- -
- -
-
1068
-Tot
ara
Roa
d W
aste
wat
er
Trea
tmen
t Pla
nt -
Rep
lace
men
t of
Inle
t Pum
ps
$918
-
- $7
80
- -
- -
- -
- -
- -
-
1380
-Tot
ara
Rd
WW
TP -
Biog
as
Gen
erat
or M
ajor
Ove
rhau
ls
$150
-
- -
- $3
00
- -
- -
- -
$350
-
-
TOTA
L R
ENEW
AL
EXPE
ND
ITU
RE
$3,6
93
$2,4
85
$2,4
07
$3,0
85
$2,1
07
$2,6
40
$2,3
10
$2,0
57
$2,0
75
$2,3
05
$2,1
05
$1,8
55
$2,8
05
$3,0
80
$1,8
75
178
REN
EWA
L EX
PEN
DIT
UR
E ['0
00s]
20
33/3
4 20
34/3
5 20
35/3
6 20
36/3
7 20
37/3
8 20
38/3
9 20
39/4
0 20
40/4
1 20
41/4
2 20
42/4
3 20
43/4
4 20
44/4
5 20
45/4
6 20
46/4
7 20
47/4
8
Was
tew
ater
Col
lect
ion
$1,8
35
$1,8
35
$1,8
35
$1,8
35
$1,8
35
$1,8
55
$1,8
35
$1,8
35
$1,8
35
$1,8
35
$1,8
35
$1,8
35
$1,8
35
$1,8
35
$1,8
35
54-C
ity-w
ide
- Was
tew
ater
Pip
e R
enew
al
$1,8
00
$1,8
00
$1,8
00
$1,8
00
$1,8
00
$1,8
00
$1,8
00
$1,8
00
$1,8
00
$1,8
00
$1,8
00
$1,8
00
$1,8
00
$1,8
00
$1,8
00
65-C
ity-w
ide
- Was
tew
ater
Pum
p St
atio
n R
enew
al
$35
$35
$35
$35
$35
$55
$35
$35
$35
$35
$35
$35
$35
$35
$35
647-
Trem
aine
/Fea
ther
ston
- W
aste
wat
er T
runk
Mai
n U
pgra
de
(Ren
ewal
Com
pone
nt)
- -
- -
- -
- -
- -
- -
- -
-
1351
-Eas
tern
Tru
nk M
ain
- H
okow
hitu
Cam
pus
Ren
ewal
-
- -
- -
- -
- -
- -
- -
- -
1378
-Ben
nett
Stre
et 5
25 T
runk
mai
n R
enew
al
- -
- -
- -
- -
- -
- -
- -
-
1379
-Max
wel
l's L
ine
825
Was
tew
ater
Tru
nk M
ain
Ren
ewal
-
- -
- -
- -
- -
- -
- -
- -
Trea
tmen
t and
Dis
posa
l $2
0 $2
0 $2
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
5 $3
5 $3
5
179-
Tota
ra R
oad
Was
tew
ater
Tr
eatm
ent P
lant
- M
inor
Equ
ipm
ent
Ren
ewal
s $2
0 $2
0 $2
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
0 $3
5 $3
5 $3
5
1050
-Tot
ara
Roa
d W
aste
wat
er
Trea
tmen
t Pla
nt -
Rep
lace
men
t of
PLC
s an
d SC
ADA
-
- -
- -
- -
- -
- -
- -
- -
1059
-Tot
ara
Roa
d W
aste
wat
er
Trea
tmen
t Pla
nt -
Rep
lace
men
t of
Grit
Rem
oval
Sys
tem
s -
- -
- -
- -
- -
- -
- -
- -
1067
-Tot
ara
Roa
d W
aste
wat
er
Trea
tmen
t Pla
nt -
Rep
lace
men
t of
Secu
rity
Fenc
e an
d G
ate
- -
- -
- -
- -
- -
- -
- -
-
1068
-Tot
ara
Roa
d W
aste
wat
er
Trea
tmen
t Pla
nt -
Rep
lace
men
t of
Inle
t Pum
ps
- -
- -
- -
- -
- -
- -
- -
-
1380
-Tot
ara
Rd
WW
TP -
Biog
as
Gen
erat
or M
ajor
Ove
rhau
ls
- -
- -
- -
- -
- -
- -
- -
-
TOTA
L R
ENEW
AL
EXPE
ND
ITU
RE
$1,8
55
$1,8
55
$1,8
55
$1,8
65
$1,8
65
$1,8
85
$1,8
65
$1,8
65
$1,8
65
$1,8
65
$1,8
65
$1,8
65
$1,8
70
$1,8
70
$1,8
70
179
Tabl
e E3
: Th
irty
Year
Cap
ital N
ew B
udge
t
CAP
ITA
L N
EW E
XPEN
DIT
UR
E ['0
00s]
20
18/1
9 20
19/2
0 20
20/2
1 20
21/2
2 20
22/2
3 20
23/2
4 20
24/2
5 20
25/2
6 20
26/2
7 20
27/2
8 20
28/2
9 20
29/3
0 20
30/3
1 20
31/3
2 20
32/3
3
Was
tew
ater
Col
lect
ion
73-C
ity-w
ide
- Was
tew
ater
Sub
divi
sion
C
ontri
butio
ns
$100
$1
00
$100
$1
00
$100
$1
00
$100
$5
0 $5
0 $5
0 $5
0 $5
0 $5
0 $5
0 $5
0
210-
Urb
an G
row
th -
Inst
alla
tion
of W
aste
wat
er
Sys
tem
s fo
r New
Indu
stria
l Are
as -
NE
IZ
exte
nsio
n ar
ea
$125
$2
25
- -
$125
-
- -
- $2
25
- -
- -
-
452-
Trem
aine
/Fea
ther
ston
- W
aste
wat
er T
runk
M
ain
Upg
rade
(Gro
wth
Com
pone
nt)
- -
- -
- -
- -
- -
$110
-
- $3
00
-
624-
Urb
an G
row
th -
Nor
th E
ast I
ndus
trial
Zon
e -
Dow
nstre
am W
aste
wat
er N
etw
ork
Upg
rade
- M
cGre
gor S
treet
to R
enni
e Av
enue
to P
eter
s Av
enue
-
- -
- -
- $1
,000
-
- -
$1,9
24
- -
- -
660-
Ferg
uson
Stre
et -
Was
tew
ater
Tru
nk M
ain
Upg
rade
-
- -
- -
- -
$670
-
- -
- -
- -
1000
-Urb
an G
row
th -
Wha
karo
ngo
- Ins
talla
tion
of
Was
tew
ater
Sys
tem
s $5
00
$362
-
- $2
67
- -
- -
- -
- -
$30
-
1043
-Tot
ara
Roa
d W
aste
wat
er T
reat
men
t Pla
nt -
Inle
t Mai
n D
uplic
atio
n $5
0 $4
00
- -
- -
- -
- -
- -
- -
-
1055
-Urb
an G
row
th -
City
Wes
t - In
stal
latio
n of
W
aste
wat
er S
yste
ms
$50
- $3
15
- $5
50
$282
-
- -
- -
- -
- -
1307
-C/fw
d - U
rban
Gro
wth
- W
haka
rong
o -
Inst
alla
tion
of W
aste
wat
er S
yste
ms
$300
-
- -
- -
- -
- -
- -
- -
-
1412
-Urb
an G
row
th -
Ashh
urst
- W
aste
wat
er -
Nor
th S
t Net
wor
k U
pgra
de
- $2
60
- -
- -
- -
- -
- -
- -
-
Was
tew
ater
Col
lect
ion
Sub-
Tota
l $1
,125
$1
,347
$4
15
$100
$1
,042
$3
82
$1,1
00
$720
$5
0 $2
75
$2,0
84
$50
$50
$380
$5
0
180
CAP
ITA
L N
EW E
XPEN
DIT
UR
E ['0
00s]
20
18/1
9 20
19/2
0 20
20/2
1 20
21/2
2 20
22/2
3 20
23/2
4 20
24/2
5 20
25/2
6 20
26/2
7 20
27/2
8 20
28/2
9 20
29/3
0 20
30/3
1 20
31/3
2 20
32/3
3
Was
tew
ater
Tre
atm
ent &
Dis
posa
l
572-
Tota
ra R
oad
Was
tew
ater
Tre
atm
ent P
lant
- R
epla
cem
ent o
f Grit
Rem
oval
Sys
tem
s (G
row
th)
$120
-
- -
- -
- -
- -
- -
- -
-
628-
Tota
ra R
oad
Was
tew
ater
Tre
atm
ent P
lant
- C
onse
nt R
enew
al U
pgra
de
- -
- -
- $2
0,00
0 $4
0,00
0 $3
0,00
0 $2
0,00
0 -
- -
- -
-
1074
-Tot
ara
Roa
d W
aste
wat
er T
reat
men
t Pla
nt -
Earth
quak
e St
reng
then
ing
of C
ivil
Stru
ctur
es
$100
$1
,000
-
- -
- -
- -
- -
- -
- -
1381
-Tot
ara
Rd
WW
TP -
Biog
as G
ener
ator
Ex
haus
t Hea
t Rec
over
y $1
75
- -
- -
- -
- -
- -
- -
- -
1382
-Tot
ara
Rd
WW
TP -
Emer
genc
y B
ypas
s U
pgra
des
- $1
00
- -
- -
- -
- -
- -
- -
-
1383
-Tot
ara
Rd
WW
TP -
Emer
genc
y O
verfl
ow
Stru
ctur
e To
tara
Rd
- -
$150
-
- -
- -
- -
- -
- -
-
Was
tew
ater
Tre
atm
ent &
Dis
posa
l Sub
-Tot
al
$395
$1
,100
$1
50
- -
$20,
000
$40,
000
$30,
000
$20,
000
- -
- -
- -
TOTA
L C
APIT
AL N
EW E
XPEN
DIT
UR
E $1
,520
$2
,447
$5
65
$100
$1
,042
$2
0,38
2 $4
1,10
0 $3
0,72
0 $2
0,05
0 $2
75
$2,0
84
$50
$50
$380
$5
0
181
CAP
ITA
L N
EW E
XPEN
DIT
UR
E ['0
00s]
20
33/3
4 20
34/3
5 20
35/3
6 20
36/3
7 20
37/3
8 20
38/3
9 20
39/4
0 20
40/4
1 20
41/4
2 20
42/4
3 20
43/4
4 20
44/4
5 20
45/4
6 20
46/4
7 20
47/4
8
Was
tew
ater
Col
lect
ion
73-C
ity-w
ide
- Was
tew
ater
Sub
divi
sion
C
ontri
butio
ns
$50
$50
$75
$75
$75
$75
$75
$75
$75
$75
$75
$75
$0
$0
$0
210-
Urb
an G
row
th -
Inst
alla
tion
of W
aste
wat
er
Sys
tem
s fo
r New
Indu
stria
l Are
as -
NE
IZ
exte
nsio
n ar
ea
- -
- -
- -
- -
- -
- -
- -
-
452-
Trem
aine
/Fea
ther
ston
- W
aste
wat
er T
runk
M
ain
Upg
rade
(Gro
wth
Com
pone
nt)
- -
- -
- -
- -
- -
- -
- -
-
624-
Urb
an G
row
th -
Nor
th E
ast I
ndus
trial
Zon
e -
Dow
nstre
am W
aste
wat
er N
etw
ork
Upg
rade
- M
cGre
gor S
treet
to R
enni
e Av
enue
to P
eter
s Av
enue
-
- -
- -
- -
- -
- -
- -
- -
660-
Ferg
uson
Stre
et -
Was
tew
ater
Tru
nk M
ain
Upg
rade
-
- -
- -
- -
- -
- -
- -
- -
1000
-Urb
an G
row
th -
Wha
karo
ngo
- Ins
talla
tion
of
Was
tew
ater
Sys
tem
s -
- -
- -
- -
- -
- -
- -
- -
1043
-Tot
ara
Roa
d W
aste
wat
er T
reat
men
t Pla
nt -
Inle
t Mai
n D
uplic
atio
n -
- -
- -
- -
- -
- -
- -
- -
1055
-Urb
an G
row
th -
City
Wes
t - In
stal
latio
n of
W
aste
wat
er S
yste
ms
- -
- -
- -
- -
- -
- -
- -
-
1307
-C/fw
d - U
rban
Gro
wth
- W
haka
rong
o -
Inst
alla
tion
of W
aste
wat
er S
yste
ms
- -
- -
- -
- -
- -
- -
- -
-
1412
-Urb
an G
row
th -
Ashh
urst
- W
aste
wat
er -
Nor
th S
t Net
wor
k U
pgra
de
- -
- -
- -
- -
- -
- -
- -
-
Was
tew
ater
Col
lect
ion
Sub-
Tota
l $5
0 $5
0 $7
5 $7
5 $7
5 $7
5 $7
5 $7
5 $7
5 $7
5 $7
5 $7
5 $0
$0
$0
182
CAP
ITA
L N
EW E
XPEN
DIT
UR
E ['0
00s]
20
33/3
4 20
34/3
5 20
35/3
6 20
36/3
7 20
37/3
8 20
38/3
9 20
39/4
0 20
40/4
1 20
41/4
2 20
42/4
3 20
43/4
4 20
44/4
5 20
45/4
6 20
46/4
7 20
47/4
8
Was
tew
ater
Tre
atm
ent &
Dis
posa
l
572-
Tota
ra R
oad
Was
tew
ater
Tre
atm
ent P
lant
- R
epla
cem
ent o
f Grit
Rem
oval
Sys
tem
s (G
row
th)
- -
- -
- -
- -
- -
- -
- -
-
628-
Tota
ra R
oad
Was
tew
ater
Tre
atm
ent P
lant
- C
onse
nt R
enew
al U
pgra
de
- -
- -
- -
- -
- -
- -
- -
-
1074
-Tot
ara
Roa
d W
aste
wat
er T
reat
men
t Pla
nt -
Earth
quak
e St
reng
then
ing
of C
ivil
Stru
ctur
es
- -
- -
- -
- -
- -
- -
- -
-
1381
-Tot
ara
Rd
WW
TP -
Biog
as G
ener
ator
Ex
haus
t Hea
t Rec
over
y -
- -
- -
- -
- -
- -
- -
- -
1382
-Tot
ara
Rd
WW
TP -
Emer
genc
y B
ypas
s U
pgra
des
- -
- -
- -
- -
- -
- -
- -
-
1383
-Tot
ara
Rd
WW
TP -
Emer
genc
y O
verfl
ow
Stru
ctur
e To
tara
Rd
- -
- -
- -
- -
- -
- -
- -
-
Was
tew
ater
Tre
atm
ent &
Dis
posa
l Sub
-Tot
al
- -
- -
- -
- -
- -
- -
- -
-
TOTA
L C
APIT
AL N
EW E
XPEN
DIT
UR
E $5
0 $5
0 $7
5 $7
5 $7
5 $7
5 $7
5 $7
5 $7
5 $7
5 $7
5 $7
5 $0
$0
$0
Appendix F – Resource Consents Asset Management Plan 2017 – Wastewater
183
Resource Consents Appendix F.
Appendix F – Resource Consents Asset Management Plan 2017 – Wastewater
185
Table F1: Wastewater Resource Consents
Asset Consent No.
Date Granted
Expiry Date
Term [Yrs]
Term Left [Yrs]
Type Consent Subtype Description
Totara Rd WWTP
101829 16 May 03 16 May 28 25 13.7 Discharge
Permit Discharge to Water
To discharge treated wastewater from the Totara Road WWTP via an outfall structure into the Manawatū River.
101830 16 May 03 16 May 28 25 13.7 Discharge
Permit Discharge to Land
To discharge digested sewage sludge into and onto land at the sludge lagoons located at the Totara Road WWTP.
101831 16 May 03 16 May 28 25 13.7 Discharge
Permit Discharge to Land
To discharge treated wastewater to land part of the wetland pond system at the Totara Road WWTP.
101832 16 May 03 16 May 28 25 13.7 Discharge
Permit Discharge to Water
Emergency discharge into the Mangaone stream. To discharge secondary treated wastewater from the Totara Road WWTP aeration ponds via a grassed channel into the Mangaone Stream.
101833 16 May 03 16 May 38 35 23.7 Land Use
Consent Misc.
To excavate and disturb the bed of the Manawatū river and adjacent bank to construct use and maintain an effluent discharge structure within the riverbed and adjacent bank and the associated temporary diversion of the flow of the Manawatū River.
101841 16 May 03 16 May 38 35 23.7 Water
Permit Divert
To excavate and disturb the bed of the Manawatū river and adjacent bank to construct use and maintain an effluent discharge structure within the riverbed and adjacent bank and the associated temporary diversion of the flow of the Manawatū River.
Appendix F – Resource Consents Asset Management Plan 2017 – Wastewater
186
Asset Consent No.
Date Granted
Expiry Date
Term [Yrs]
Term Left [Yrs]
Type Consent Subtype Description
Wastewater Pipe Under Mangaone Stream
104334 14 Dec 07 14 Dec 42 35 28.3 Land Use
Consent Misc.
To disturb the bed of the Mangaone stream to place a sewage pipeline beneath the bed of the Mangaone Stream (expired 14 June 2008) and to use and maintain this pipeline (ongoing)
Longburn Oxidation Ponds 104773 5 Feb 09 31 May
10 1 Current Under s124
Discharge Permit
Discharge to Water
To discharge 250 m3/day of treated sewage effluent from the Longburn oxidation pond to the Manawatū river
Longburn Oxidation Ponds 105246 Application
Lodged
To be withdrawn as Longburn is now connected to Palmerston North wastewater network
Discharge Permit
Discharge to Water
To discharge 250 m3/day of treated sewage effluent from the Longburn oxidation pond to the Manawatū River.
Totara Rd WWTP Water Bore
105443 29 Oct 10 1 Jul 33 23 18.8 Water
Permit Groundwater Take
To take 150 cubic metres per day of water from well number 335025 for the purpose of process water and washwater at the Totara Road WWTP.
Ashhurst Oxidation Ponds
107056 &
107057
Application Lodged TBA TBA TBA Discharge
Permit Discharge to Land
Discharge into land for the purpose of storing human effluent and associated discharge to air.
Appendix G – Asset Grading Definitions Asset Management Plan 2017 – Wastewater
187
Asset Grading Definitions Appendix G.
Appendix G – Asset Grading Definitions Asset Management Plan 2017 – Wastewater
189
Table G1: Condition Grading of Rising Mains
Condition Grade General Meaning
1 Excellent Modern pipe material designed to current standards with no pipe wall or joint failures and no evidence of internal or external degradation.
2 Good As grade 1 but not designed to current standards in respect of pressure ratings, design specification, jointing or corrosion protection. Deterioration causing minimal influence on performance.
3 Moderate Rising mains which are generally sound, although with a few pipewall or joint failures or evidence of some external or internal degradation. Some deterioration beginning to reflect in performance.
4 Poor Rising mains with a significant level of pipe wall or joint failures or evidence of significant external or internal degradation causing, or likely to cause a marked deterioration in performance in the medium term. Some asset replacement or rehabilitation needed within the medium term.
5 Very Poor Unsound rising mains with extensive pipe wall or joint failures, or significant external or internal degradation, which has failed or about to fail in the near future, causing unacceptable performance. No life expectancy, requiring urgent replacement or rehabilitation.
Table G2: Performance Grading of Rising Mains
Performance Grade General Meaning
1 Excellent Smooth bored mains not subject to degradation with sound factory applied linings; no measurable deterioration in pipe bore; no performance problems.
2 Good As grade 1 but with loose deposits that are noticeable under abnormal flow conditions or slight deterioration of internal bore which gives a rough surface but with no significant reduction in cross sectional area; occasional flushing and / or desilting required.
3 Moderate Some problems with loose deposits or deterioration of linings leading to occasional blockages. History of occasional pipe blockage with tuberculation causing up to 20% blockage by encrustation. Regular flushing or air scouring required.
4 Poor Frequent problems causing blockage on more than one occasion under normal operating conditions during the previous 12 months or mains with tuberculation causing up to 20% to 40% blockage by encrustation. Frequent flushing or air scouring required.
5 Very Poor Severe problems causing regular blockage and pumping performance cannot be assured; or tuberculation causing greater than 40% blockage by encrustation. Very frequent flushing or air scouring required.
Table G3: Condition Grading of Sewers
Condition Grade General Meaning
CCTV Grading
Peak Mean Avg.
1 Excellent Modern pipe material designed to current standards with no structural defects and no evidence of internal or external degradation.
2 Good As grade 1 but not designed to current standards in respect of manufacturer’s specification, jointing or corrosion protection. Some deterioration causing minimal influence on performance (e.g. circumferential cracking or minor joint defects).
<10 <0.3 <0.4
3 Moderate 10+ 0.3+ 0.4+
Appendix G – Asset Grading Definitions Asset Management Plan 2017 – Wastewater
190
Condition Grade General Meaning
CCTV Grading
Peak Mean Avg. Drains which are generally sound, although with some defects (e.g. deformation 0% to 5% and cracked or fractured; or longitudinal/ multiple cracking; or occasional fractures; or external pipewall degradation) over not more than 25% of the length. Some deterioration beginning to reflect in performance.
4 Poor Drains with a significant level of defects (for example, deformation 5% to 10% and cracked, fractured, broken, serious loss of level and/ or external pipewall degradation) over not more than 50% of the length causing, or likely to cause a marked deterioration in performance in the medium term. Some asset replacement or rehabilitation needed within the medium term.
<60 <1.5 <2.0
5 Very Poor Unsound drains with a high level of defects (e.g. deformation >10% and cracked and fractured or broken, already collapsed or extensive areas of missing fabric), or uneven grade for over 50% of length causing unacceptable performance. No life expectancy, requiring urgent replacement or rehabilitation.
>60 >1.5 >2.0
Table G4: Performance Grading of Sewers
Performance Grade General Meaning
1 Excellent Sewers designed to acceptable standards with adequate self-cleansing velocity; no problems with deposition; no performance problems.
2 Good As grade 1 but with some slimming or minor deposition causing minor loss of hydraulic capacity but not affecting performance.
3 Moderate Sewers with slimming and deposition requiring occasional cleaning or minor backfalls are causing a reduction in pipe capacity or inadequate design capacity and surcharging of the sewer at high flows, although no surface flooding during design storm.
4 Poor Sewers with significant slimming and deposition requiring regular cleaning or backfalls causing a marked reduction in pipe capacity, risk or blockage or inadequate design capacity causing frequent flooding to gardens and roads or occasional flooding to properties or restricted toilet use during design storm.
5 Fail Sewer with a high level of slimming and deposition requiring a high frequency of cleaning or maintenance or backfalls causing a serious reduction in pipe capacity or serious inadequate design capacity, risk of blockages or hydraulic restrictions causing regular flooding to gardens and highways or frequent flooding to properties or restricted toilet use during design storm.
Table G5: Condition Grading of Manholes & Cleaning Eyes
Condition Grade General Meaning
1 Excellent Sound modern structure well maintained with no problems with the manhole structure, cover and frame, step irons, invert, benching or pipe entries into manholes.
2 Good As for grade 1, but showing minor deterioration and wear and tear. Some indications of structural problems. Some surface damage to the structure but no corrosion staining, cracking or loss of stability.
3 Moderate Functionally sound structure but showing some signs of wear and tear. Some minor cracking, staining or signs of tree root penetration.
4 Poor Structure functioning but with problems due to significant infiltration, loss of stability or deformation. Manhole cover or frame showing signs of corrosion causing difficulties for man entry. Step irons showing signs of corrosion.
5 Very Poor
Appendix G – Asset Grading Definitions Asset Management Plan 2017 – Wastewater
191
Serious structural problems having a detrimental effect on the performance of the manhole structure.
Table G6: Performance Grading of Manholes & Cleaning Eyes
Condition Grade General Meaning
1 Excellent No problems with the manhole structure, cover and frame, step irons, invert, benching or pipe entries into manholes. Fully compliant with safety regulations. No infiltration.
2 Good Some indications of structural problems with no effect on the functional performance of the manhole.
3 Moderate Problems exhibited under high flows that affect the functional performance of the manhole..
4 Poor Significant problems with either man entry or the functional performance of the manhole such as lack of benching.
5 Very Poor Significant infiltration causing increased surcharging within the network. ` Non- compliant safety aspects such as corroded or broken step irons resulting in unsafe man entry. No benching in the invert with significant damage affecting the flow.
Table G7: Condition Grading of Pumping Stations & Treatment Plant Structures
Condition Grade General Meaning
1 Excellent Sound structure designed to current standards, well maintained.
2 Good As grade 1 but not designed to current standards or showing minor wear and tear and minor deterioration of surfaces; some spalling but with no corrosion staining; needs to be inspected in the medium term. Deterioration causing minimal influence on performance.
3 Moderate Functionally sound structure, but appearance affected by minor cracking, staining, and vegetation of minor leakage. Some deterioration beginning to be reflected in performance.
4 Poor Structure functioning but with problems due to significant cracking, spalling, cracking, loss of stability, deformation or corrosion likely to cause a marked deterioration of performance in the medium term. Some asset replacement or rehabilitation needed within the medium term.
5 Very Poor Structure has serious problems and has failed or about to fail in the near future, causing unacceptable performance. No life expectancy, requiring urgent replacement or rehabilitation.
Table G8: Performance Grading of Pumping Stations & Treatment Plant Structures
Condition Grade General Meaning
1 Excellent Meets all design and statutory requirements at all times and in all demand conditions. For example, capacity exceeds maximum design demand or flow, adequate standby plant facilities design demand or flow, adequate standby plant facilities, emergency sewage overflow provided. No known flooding or surcharging upstream as a result of pump station constraints..
2 Good As for grade 1, but with some minor shortcomings in non-critical aspects or under extreme demand or climatic conditions. For example capacity equals maximum design demand or flow, adequate standby plant facilities. No known flooding or surcharging upstream as a result of pump station constraints.
3 Moderate Asset generally meeting design requirements with occasional failures in performance criteria under normal conditions. For example capacity less than maximum demand or flow, adequate standby facilities, some known flooding upstream as a result of pump station constraints, occasional operation of storm overflow, or a few reported complaints of noise or smells, or shortcomings in design (pipework, sump, electrics, etc.).
Appendix G – Asset Grading Definitions Asset Management Plan 2017 – Wastewater
192
Condition Grade General Meaning
4 Poor Asset with frequent failures in performance criteria under normal conditions. For example capacity significantly less than maximum design demand or flow, standby plant facilities not fully adequate, regular known flooding upstream as a result of pump station constraints, frequent operation f storm overflow, or regular reported complaints of noise or smells, or shortcomings in design (pipework, sump, electrics, etc.).
5 Very Poor Asset substantially unable to meet performance criteria with very frequent failures against defined standards. For example capacity significantly less than maximum design demand or flow, standby plant facilities not adequate, frequent known flooding upstream as a result of pump station constraints, frequent operation of storm overflow, or regular reported complaints of noise smells, or shortcomings in design (pipework, sump, electrics, etc.).
Table G8: Condition Grading of Electrical & Mechanical Plant
Condition Grade General Meaning
1 Excellent Sound plant designed to current standards, all operable and well maintained.
2 Good As for grade 1, but not designed to current standards or showing wear and tear. E.g. minor oil leaks, gland wear although protective coatings intact and efficiency undiminished; requires major overhaul within the medium term. Deterioration causing minimal influence on performance.
3 Moderate Functionally sound plant and components, acceptable but showing some signs of wear and tear with minor failures and some diminished efficiency. For example, bearing and gland wear and corrosion of metal parts becoming more evident. Deterioration beginning to be reflected in performance and a higher level of maintenance.
4 Poor Plant and components function but require a high level of maintenance to remain operational. likely to cause a marked deterioration in performance in the medium term. Some asset replacement or rehabilitation needed within the medium term.
5 Very Poor Plant and component effective life exceeded and excessive maintenance costs incurred. High risk of breakdown with a serious impact on performance. No life expectancy, requiring urgent replacement of rehabilitation.
Appendix H – Pump Station Asset Data Asset Management Plan 2017 – Wastewater
193
Pump Station Asset Data Appendix H.
As
set M
anag
emen
t Pla
n 20
17 –
Was
tew
ater
195
Tabl
e H1
: Pu
mp
Stat
ion
Asse
t Dat
a
Pum
p St
atio
n Ye
ar
Bui
lt Nu
mbe
r Of
Pum
ps
Wel
l – P
ump
Mak
e An
d M
odel
Ye
ar
Pum
ps
Inst
alle
d
Der
ived
C
apac
ity
[L/S
]
Ris
ing
Mai
n C
ondi
tion
Gra
ding
* Pe
rfor
man
ce G
radi
ng*
Mat
eria
l D
iam
eter
(M
m)
Leng
th
(M)
Civ
il St
ruct
ure
Pum
ps &
C
ontr
ol
Gea
r C
ivil
Stru
ctur
e Pu
mps
&
Con
trol
G
ear
Max
wel
ls L
ine
1964
4
Dry
Wel
l 2
x Fl
ygt
NT3
202,
& 2
x
ABSX
FJ25
0J
2015
,201
6 &
2017
75
8 R
C
525
629
1 1
2 1
Col
lege
St
1966
2
Dry
wel
l Fly
gt;
CP3
127
2004
59
AC
20
0 10
2 3
2 1
3
Wik
iriw
hi
Cre
scen
t 19
66
2 W
et w
ell F
lygt
; C
P310
0 19
94
18
AC
100
363
2 1
1 1
Trem
aine
Ave
19
61
2 D
ry w
ell A
BS; A
FP7
1988
53
R
C
150
152
3 2
1 3
Mas
sey
1965
3
Dry
wel
l Fly
gt
NT3
153
2015
30
0 H
DPE
50
0 23
6 2
2 2
2
Kens
ingt
on
Mew
s 19
62
2 W
et w
ell A
BS;
AS08
40 S
17/2
D
2012
18
C
LS
100
56
2 2
1 2
Jick
ell S
t 19
26
3 D
ry w
ell
Flyg
t;CP3
217
& Fl
ygt N
P312
7 M
T
1992
200
5 &
2018
75
PV
C
200
51
3 2
1 3
Te A
we
Awe
St
1955
2
Dry
wel
l Fl
ygt;N
T310
2 M
T 20
17
18
CLS
15
0 11
3 3
1 1
3
Rua
mah
anga
C
res
1986
2
Wet
wel
l ABS
; AF
P7
1986
10
AC
10
0 17
2
1 1
3
Cap
ri Pl
ace
1975
2
Wet
wel
l ABS
; AF
P7
1986
35
ST
EEL
100
dire
ct
disc
harg
e 2
3 1
3
Rac
ecou
rse
Rd
1975
2
Wet
wel
l ABS
; AF
P7
1994
26
AC
15
0 20
5 2
3 1
2
Red
woo
d G
rove
19
75
2 W
et w
ell A
BS
XFP1
00E
2012
20
R
C
100
41
2 2
1 3
Adm
irals
Pl
ace
1986
2
Wet
wel
l Gru
ndfo
s SE
V 80
.80.
15
2006
10
PV
C
100
69
2 1
1 1
Ryd
er
Che
shire
19
83
2 W
et w
ell A
BS;
XFP1
00C
20
17
28
PVC
10
0 4
2 3
1 3
New
ton
Plac
e 19
86
2 W
et w
ell F
lygt
M
P308
5 20
02
10
STEE
L 10
0 1
2 2
1 2
196
Pum
p St
atio
n Ye
ar
Bui
lt Nu
mbe
r Of
Pum
ps
Wel
l – P
ump
Mak
e An
d M
odel
Ye
ar
Pum
ps
Inst
alle
d
Der
ived
C
apac
ity
[L/S
]
Ris
ing
Mai
n C
ondi
tion
Gra
ding
* Pe
rfor
man
ce G
radi
ng*
Mat
eria
l D
iam
eter
(M
m)
Leng
th
(M)
Civ
il St
ruct
ure
Pum
ps &
C
ontr
ol
Gea
r C
ivil
Stru
ctur
e Pu
mps
&
Con
trol
G
ear
Sutto
n Pl
ace
1986
2
Wet
wel
l ABS
,S26
-2
2008
10
PV
C
100
260
2 1
1 1
Voge
l St
1991
2
Wet
wel
l AB
S;Pi
ranh
a10-
2 19
91
4 PV
C
32
12
2 4
1 4
Roy
Stre
et
1993
2
Wet
wel
l Fl
ygtN
P308
5 M
T 20
15
4 C
LS
100
31
2 2
1 3
Shirr
iffs
Rd
1994
2
Wet
wel
l Fly
gt
NP3
085
MT
2017
2.
4 M
DPE
63
86
2
1 1
1
Rua
pehu
Dr
1999
2
Wet
wel
l Fly
gt
CP3
127
1999
10
PV
C
100
75
1 1
1 1
Te W
anak
a R
d 19
94
2 W
et w
ell G
rund
fos
SEG
40.4
0.50
B 20
08
2.4
MD
PE
63
1360
2
2 1
1
Cas
hmer
e D
rive
2008
2
Wet
wel
l ABS
–
AFP0
844
7KW
20
00
10
PVC
10
0 51
3 1
2 1
2
Dur
ham
St
1984
2
Wet
wel
l Fly
gt
CP3
085M
T 19
94
30
PVC
80
44
2
1 1
1
Rai
lway
Roa
d 20
08
2 W
etw
ell G
rund
fos
SEV.
80.8
0.22
.4.5
0B
2008
10
PV
C
100
15
1 1
1 1
Gra
nd O
aks
Dr
2008
2
Wet
wel
l Fly
gt
CP3
085
2008
10
M
DPE
10
0 28
1
1 1
1
Aoka
uter
e
2011
1
Dry
wel
l Gor
man
R
upp
VS3
2011
10
M
DPE
10
0 13
53
1 1
1 1
KB R
d Bu
nnyt
horp
e 20
17
2 W
et W
ell
Flyg
t:NP3
171.
181
2017
10
M
DPE
10
0 26
00
1 1
1 1
Rai
lway
Rd
Bunn
ytho
rpe
1981
2
Wet
Wel
l Gru
ndfo
s SE
V 80
.80.
200
2009
10
PV
C
80
162
2 2
2 2
Map
le S
t Bu
nnyt
horp
e 19
90
2 W
et W
ell T
suru
mi
15 E
B2
1990
2
AC
100
85
2 2
2 2
Res
erve
Rd
Long
burn
19
81
2 W
et W
ell G
rund
fos
SEV8
0.80
.40
2009
&
2014
7
AC
100
70
2 2
2 2
Wal
kers
Rd
Long
burn
19
81
2 W
et W
ell G
rund
fos
SEV8
0.80
.40
2003
&
2011
4
MD
PE
100
1372
2
2 2
2
Appe
ndix
G –
Ass
et G
radi
ng D
efin
ition
s As
set M
anag
emen
t Pla
n 20
17 –
Was
tew
ater
197
Pum
p St
atio
n Ye
ar
Bui
lt Nu
mbe
r Of
Pum
ps
Wel
l – P
ump
Mak
e An
d M
odel
Ye
ar
Pum
ps
Inst
alle
d
Der
ived
C
apac
ity
[L/S
]
Ris
ing
Mai
n C
ondi
tion
Gra
ding
* Pe
rfor
man
ce G
radi
ng*
Mat
eria
l D
iam
eter
(M
m)
Leng
th
(M)
Civ
il St
ruct
ure
Pum
ps &
C
ontr
ol
Gea
r C
ivil
Stru
ctur
e Pu
mps
&
Con
trol
G
ear
Cou
tts W
ay
2015
2
Wet
Wel
l Gru
nfos
SE
1.50
.80.
22
2015
6
MD
PE
150
268
1 1
1 1
Free
dom
Dr
2016
2
Wet
Wel
l Fly
gt
NP3
127
2016
5
MD
PE
100
473
1 1
1 1
Ashh
urst
H
acke
tts R
d 20
14
2 D
ry W
ell G
rund
fos
VS 4
A60B
20
14
47
MD
PE
250
8700
1
1 1
1
Appendix I – Data Management Asset Management Plan 2017 – Wastewater
199
Data Management Appendix I.
Appendix I – Data Management Asset Management Plan 2017 – Wastewater
201
Data and Information Management
Asset Management Planning depends on drawing on many sources of data and information to formulate plans that quantify the programmes that are required to maintain the asset and provide the required level of service into the future. This section describes the main sources of information that contribute to the different aspects of asset management planning, setting out the source of that information, what it is used for , the quality of information required and how the data is maintained and kept up to date.
The confidence and reliability of the data that lies behind the AM programmes is indicated in Table K1.
Table I1: High Level Overview of Confidence and Reliability of Data
Asset Management Processes
Source of Data & Information
Use of Information Quality Required for AMPs
Maintenance and Updating of Data & Information
Demand Forecasting
Growth projections – population and household growth projections
The City Future planning unit provides advice about population and household growth based on NZ Statistics Information, other professional advice and analysis of past Council data.
Information is used to formulate a planning scenario for the development of residential and industrial areas. The identification of development of infrastructure is based on spatial projections of both the location and rate of growth provided by Council planners, followed by modelling to determine the additional demand for wastewater services due to that demand. This enables confirmation of downstream network capacity and identification of any network or pumping upgrades.
Broad based information only is required that allows a credible 30yr plan to be drawn up and supports the development contribution calculations. Actual development can also be determined by the market at the time.
The growth projections and planning scenario are revised every 3 years based on the most up to date information from NZ Statistics.
Levels of Service
Customer service data (for past 1-3 yrs)
K-Base customer service request system
Used to inform Council’s LOS decision (identifies areas where LOS is not being met or particular service issues are arising. Key source of information on network performance and for identification of problem areas. Also used to monitor and manage the performance of the service provider and check their compliance with key KPIs in their SLAs
Sufficient resolution to identify the main service issues and trends. Generally the last years information adequate
On-going data being received
Appendix I – Data Management Asset Management Plan 2017 – Wastewater
202
Asset Management Processes
Source of Data & Information
Use of Information Quality Required for AMPs
Maintenance and Updating of Data & Information
Submissions made to various Council processes
Used to inform Council’s LOS decision and as a check that particular service areas have been identified. Used to inform campaigns to improve understanding of the wastewater system, how it operates and its limitations.U.
Part of ongoing Council process
Communitrak Survey undertaken periodically
Used to inform Councillors about trends in customer satisfaction with services being delivered. Assists with Councillor LOS decision
Reputable survey Survey undertaken every 3 years
Performance measurement (KPIs)
Used to monitor the delivery of the agreed level of service
Asset Knowledge
Asset age and physical attributes
Asset Information System (Infor Public Sector)
This is core data that is the basis for building up accurate O&M, Renewal and Development Plans. It is also the basis for valuation of the asset.
It is essential to good AM to know what assets need to be maintained and renewed. Accurate information with regard to the physical attributes is important. A reliable date of construction (at least to within 5 years) is desirable
The AIS is continually being updated by the Asset Systems Officer as new information comes to light and as new assets are being built (As built plans). A dedication officer maintains the system. Checks on integrity & accuracy of info.
Asset condition Information collected from CCTV surveys and physical inspections of all critical assets and a cross-section of non-critical assets.
Used to identify faults and performance issues in critical assets for immediate resolution. Used to develop specific life estimates and projections of the renewal profile for non-critical assets
Sufficient overall resolution of condition to reliably inform a 5 level grading system. Needs to be added to on a continuous basis.
Physical inspection of critical assets to be undertaken on regular cycle e.g. 5 years. CCTV inspection of remaining network scheduled so that the entire network is inspected every 10 to 15 years.
Asset performance
Information from monitoring, customer complaints and scheduled inspections is captured in Asset Management System
Inform further investigation and fault finding to identify defects or performance issues. Where performance is related to capacity use to inform detailed catchment modelling to identify any capacity improvements
Needs to accurately identify the current situation
Data needs to be continuous captured and recorded against the asset to provide an up to date record of issues
Appendix I – Data Management Asset Management Plan 2017 – Wastewater
203
Asset Management Processes
Source of Data & Information
Use of Information Quality Required for AMPs
Maintenance and Updating of Data & Information
Analysis of asset information
From information collected & input into the AMS etc
Modelling of both current situation and future condition allowing for full development and the influence of climate change. Asset information enables robust determination of capital improvements which will deliver sustainable and durable long term improvements in service. Predictive modelling to determine asset renewal profiles under different risk scenarios.
Up to date Data needs to be logging and recorded continuously. Key to this is providing mobile solutions which allow field staff to update asset data and record issues directly they are identified. It is intended to give customers and contractors the ability to report on errors in the asset data and so assist the improvement process. Analysis can be undertaken periodically ahead of key planning milestones e.g. LTP
Service Delivery
Procurement of work so as to provide service through operation and maintenance of the assets
Previous information about the cost and scope of work done or assets built. Information about Internal service delivery stored in SLA system. Data about market prices and comparability of internal service delivery to be migrated to database in Benchmark.
Data is used to prepare engineer’s estimates prior to seeking either internal or external prices. Data is critical for determining the market comparability of internal service delivery and whether external contract procurement is justified. Costs data is also used to value new assets and confirm asset valuations on an annual basis.
Up to date with latest prices and costs captured as soon as possible after work is completed
Needs to be kept up to date given that the costs for constructing new infrastructure change rapidly in response to a range of external factors
Programme Planning
Data about programmes – objectives, scope, timing, cost and risk, previous investigation.
Programme Planning and Implementation Database (currently in Excel spreadsheets).
Used to inform asset programmes for the asset management plan.
The database is based on a comprehensive template covering programme information.
The PPI database for each programme in the AMP is updated annually by the asset manager for each activity.
Appendix I – Data Management Asset Management Plan 2017 – Wastewater
204
Asset Management Processes
Source of Data & Information
Use of Information Quality Required for AMPs
Maintenance and Updating of Data & Information
Specific strategy reports including network renewal strategy.
Identifies specific constraints and servicing challenges and sets out options for investment to mitigate effects. The data is critical to providing options for consideration by Council in respect of different levels of investment to meet different levels of service. Outlines consequences of not proceeding with investment as well as benefits.
High level but with clear detail of assumptions used
Regular updating required at a frequency necessary to inform key planning and funding decision making – e.g. 3 yearly to align with the LTP.
Specific consultants reports:
Wastewater I&I - GHD
Flow Capacity Assessment – H&G
Sewer Renewal Strategy - ProjectMax
Used to identify work programmes required to meet the AMP objectives Assisted with confirming capacity parameters for renewal and major capital upgrade programme at the WWTP. Also provided basis for development of renewal programme for the LTP and 30 year programme.
Snapshot of current and future requirements.
Council’s 10YP Used to inform changes adopted by the Council to previous AMP programmes
High level estimates which are sufficient to deliver the programme of work given the risk profiles for each programme or activity.
Through Council’s annual budget and 10YP process & system
Financial Planning
Long term financial forecasts
30 year Infrastructure Plan
Used to inform Council of future funding profiles, borrowing obligations and renewal funding issues.
High level estimates with significant contingency based on optimised profiling of renewals and realistic assessment of new capital requirements.
Three year updates ahead of Council’s 10YP process
Reliability and Confidence in Programmes
The expenditure and programmes in this AMP Plan are based on the data sources described in Appendix I. Confidence that programme information is reliable depends on the accuracy of the input data sources upon which that programme is based.
The following is an assessment of the overall confidence in the various data streams that input into programmes, including the demand drivers, growth projections, the condition and performance data and the estimating data used for the financial forecasts. Further work on this aspect is planned over the next 3 years with a data improvement plan project being included in the Improvement Plan.
Appendix I – Data Management Asset Management Plan 2017 – Wastewater
205
Definition of Data Confidence Rating Table I2: Confidence Grading Description
Confidence Grade
Description Processes Asset Data
5 Highly reliable/ Audited
Strictly formal process for collecting and analysing data. Process is documented and always followed by all staff. Process is recognised by industry as best method of assessment.
Very high level of data confidence. Data is believed to be 95 to 100% complete and ±5% accurate. Regular data audits verify high level of accuracy in data received.
4 Reliable/ Verified Strong process to collect data. May not be fully documented but usually undertaken by most staff.
Good level of data confidence. Data is believed to be 80 to 95% complete and ±10 to 15% accurate. Some minor data extrapolation or assumptions has been applied. Occasional data audits verify reasonable level of confidence.
3 Less Reliable Process to collect data established. May not be fully documented but usually undertaken by most staff.
Average level of data confidence. Data is believed to be 50 to 80% complete and ±15 to 20% accurate. Some data extrapolation has been applied based on supported assumptions. Occasional data audits verify reasonable level of confidence.
2 Uncertain Semiformal process usually followed. Poor documentation. Process to collect data followed about half the time.
Not sure of data confidence, or data confidence is good for some data, but most of dataset is based on extrapolation of incomplete data set with unsupported assumptions.
1 Very uncertain Ad hoc procedures to collect data. Minimal or no process documentation. Process followed occasionally.
Very low data confidence. Data based on very large unsupported assumptions, cursory inspection and analysis. Data may have been developed by extrapolation from small, unverified data sets.
0 No data No process exists to collect data. No data available.
Appendix I – Data Management Asset Management Plan 2017 – Wastewater
206
Assessment of Confidence in Key data Inputs to AMP Table K3: Confidence Grading Description
Data Confidence Assessment
Comment
Demand drivers
4 Demand drivers in respect of wastewater services include:
Changes associated with new consents targeting improvements in effects in the Manawatu River
Changes to the pattern and intensity of rainfall across the city impacting on the frequency and severity of wet weather flows due to stormwater infiltration and inflow
Higher expectations in the community that negative effects from wastewater should be mitigated including avoidance of overflows, removal of 100% of heavy metals, emerging contaminants and non-organic compounds e.g. micro-plastics
Expectations that there should be no impediment to growth from either residential or industrial such that the wastewater system should be able to accommodate all future growth in flows and loads
Growth projections
4 The growth projections are neither predictions nor forecasts. They are built on assumptions about future changes in population based on demographic trends and patterns and other factors. Variations in the economic cycle mean that it is inevitable that the actual rate of growth will be above or below the projected rate at different times in the economic cycle. Projections are reassessed every 3 years in the light of the information available at that time at which point the programmes based on the projections will be reassessed.
Asset useful lives
2 The current useful lives for wastewater assets are based on the asset lives detailed in the IIMI guidelines. For some asset types where condition assessments indicate the lives differ from the mean, these have been reduced or increased. It is clear that there are some pipeline assets which require immediate renewal, not because they have failed but because they let unacceptable quantities of stormwater. This reduced life assessment is not reflected in the asset register.
Asset values 4 Asset values are based on the latest information for renewal and capital construction costs for work undertaken in the last two years by Council. Where no work has been done estimates for work undertaken by local Councils within the region have been used.
Condition of asset
3 Asset condition assumptions are based on the results of historical CCTV inspections for a portion of the network. These inspections are somewhat dated and of average quality. Work is now underway to significantly increase the investment in inspection and condition scoring to develop a more robust assessment of condition.
Performance of Network
3 The development of an integrated model of the sewer network has highlighted system capacity constraints under wet weather conditions. The modelling has confirmed the anecdotal evidence of capacity constraints in some parts of the network during wet weather events. While dry weather performance is good, during wet weather events the key large pumping stations, trunk sewers and WWTP inlet works are all operating at or close to capacity. Further refinement of the model will improve confidence around understanding of the network performance.
Operational forecasts
3 Forecasts of operational costs are uncertain due in large measure to the unknown impact of the pending upgrade to the wastewater treatment and disposal facility. There is also uncertainty around the cost of addressing a growing number of lateral and mains blockages. There is evidence of significant legacy issues associated with the laying of flat sewers or poorly constructed sewers which is contributing to maintenance costs.
Renewal forecasts
2 While additional funding has been requested for next 7 years of the AMP to address legacy renewals, much of this is to renew earthen ware pipes in catchments with significant stormwater infiltration and inflow. Given the limited extent of recent CCTV inspection data there is limited confidence in the renewal forecasts. It is expected that with more condition information, additional investment in renewals may be required to address legacy condition issues within the older parts of the network.
Appendix I – Data Management Asset Management Plan 2017 – Wastewater
207
Data Confidence Assessment
Comment
Development forecasts
3 Current planning forecasts are considered robust and potentially overestimate the demand and the rate of uptake for both residential and commercial property particularly in greenfield areas. The key uncertainty is in the impact of infill growth on wastewater flows in the existing network. Without effective control of stormwater infiltration and inflow there is the possibility of significant capacity constraints during wet weather events. The implementation of low pressure sewer systems is designed to help mitigate this.
Reliability of Financial Forecasts
Information for programmes in this plan are derived from the information that is input into the Programme Planning and Implementation database. This database provides for the estimating accuracy to be made of each programme together with the estimating rates on which the estimate is based. The types of estimates with their definition are as follows:
Ballpark
This is an order of magnitude estimate made in the early stages of a project based on high level comparative information
Rough Order
This applies in the early stages of feasibility using a top down approach but with better breakdown of the major components of work.
Preliminary
Work is reasonably well defined with more detailed knowledge of quantities and scope of work. Based on historic rates for construction
Firm – Engineers Estimate
This is based on detailed design specification and drawings. Costing is based on market rate information.
In this plan an assessment is made of the reliability of the financial forecasts based on the reliability of physical asset data, asset condition data, asset performance data and growth projections in Section 9.
Appendix J – 6 Year Asset Renewal Programme Asset Management Plan 2017 – Wastewater
209
6 Year Asset Renewal Programme Appendix J.
Appendix J – 6 Year Asset Renewal Programme Asset Management Plan 2017 – Wastewater
211
Table J1: Programme and Renewal Project List
Programme and Renewal Project List 2018/19 [$] 2019/20 [$] 2020/21 [$] 2021/22 [$] 2022/23 [$] 2023/24 [$]
1059-Totara Road Wastewater Treatment
Plant - Replacement of Grit Removal Systems
$494,764
Grit System $494,764
1067-Totara Road Wastewater Treatment
Plant - Replacement of Security Fence and
Gate
$250,000
Security Fence and Gate $250,000
1068-Totara Road Wastewater Treatment
Plant - Replacement of Inlet Pumps
$918,000 - - $780,000
Upgrade two lift pumps $918,000 $780,000
1351-Eastern Trunk Main - Hokowhitu
Campus Renewal
$250,000
Hokowhitu Campus $250,000
1378-Bennett Street 525 Trunkmain Renewal $170,000 $170,000
Bennett Street 525 Trunk Main Renewal $170,000 $170,000
1379-Maxwell's Line 825 Wastewater Trunk
Main Renewal
$250,000 - - - $250,000
Maxwell's Line 825 Wastewater Trunk Main
Renewal
$250,000 $250,000
1380-Totara Rd WWTP - Biogas Generator
Major Overhauls
$150,000 - - - - $300,000
E50 12,000 hr service of Engine $150,000
E60 24,000 hr service of Engine $300,000
179-Totara Road Wastewater Treatment
Plant - Minor Equipment Renewals
$130,000 $60,000 $100,000 $50,000 $50,000 $50,000
Cross collector gear box 1 $5,000
Digester heat exchange 2 $70,000
Cross collector gear box $10,000
Digester Sludge circulation pump 1 $15,000
Air compressor main building $15,000
Digester Sludge circulation pump 2 $15,000
Hot water cylinder $5,000
Gallery water pipelines $25,000
Appendix I – Data Management Asset Management Plan 2017 – Wastewater
212
Programme and Renewal Project List 2018/19 [$] 2019/20 [$] 2020/21 [$] 2021/22 [$] 2022/23 [$] 2023/24 [$]
Main air supply fan $15,000
DO probes in second oxidation pond $15,000
1200mm outlet mag flow meter $50,000
Potable water booster set $40,000
Wave bands $10,000
Minor and Reactive Works $50,000 $50,000 $50,000
54-City-wide - Wastewater Pipe Renewal $1,600,000 $1,800,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000
Minor and Reactive Works $55,587 $38,948 $188,850 $42,576 $266,158 $58,442
Renewal Dia - Street
600mm -Moray Pl $50,376
750mm -Rugby St $89,645
600mm -Nottingham Ave $194,904
600mm -Alexander St $2,824
600mm -Totara Rd $3,046
600mm -Marriner St $212,745
750mm -Alexander St $196,724
750mm -College St $115,721
600mm -Maxwells Line $299,952
750mm -Glen Pl $69,643
600mm -Botanical Rd $65,285
750mm -Maxwells Line $243,549
450mm -Shamrock St $54,599
450mm -College St $723,797
450mm -Ferguson St $24,809
375mm -Featherston St $42,942
450mm -Kaimanawa St $27,959
375mm -Hobson Pl $45,190
450mm -Mihaere Dr $129,106
375mm -Clausen St $231,194
450mm -Pitt St $43,805
450mm -Botanical Rd $150,130
375mm -Botanical Rd $238,875
375mm -Ferguson St $3,755
450mm -Vogel St $44,891
300mm -Cuba St $31,055
300mm -College St $2,410
Appendix I – Data Management Asset Management Plan 2017 – Wastewater
213
Programme and Renewal Project List 2018/19 [$] 2019/20 [$] 2020/21 [$] 2021/22 [$] 2022/23 [$] 2023/24 [$]
375mm -Wood St $205,242
300mm -Crewe Cres $202,862
300mm -Centennial Dr $218,420
300mm -Ferguson St $302,602
300mm -Burns Ave $50,753
375mm -Pioneer Hwy $122,141
300mm -Churchill Ave $134,160
375mm -Tremaine Ave $541,505
225mm -Browning Pl $12,801
225mm -Balmoral Dr $66,209
300mm -Stirling Cres $82,545
225mm -Albert St $311,836
300mm -Te Awe Awe St $147,116
300mm -Fitzherbert Ave $251,787
300mm -The Square $112,060
300mm -Maxwells Line $4,362
300mm -Tremaine Ave $401,008
250mm -North St $261,604
300mm -Wood St $52,175
300mm -Mcgiffert St $31,680
300mm -Woodstock Pl $38,290
300mm -Main St $152,863
225mm -Alton Pl $31,087
225mm -Bryant St $59,747
225mm -Cuba St $215,310
225mm -Joseph St $125,967
225mm -Fitzroy St $44,340
225mm -Church St $64,520
225mm -Grey St $445,906
225mm -College St $45,615
225mm -Guy Ave $87,897
225mm -Crewe Cres $26,742
225mm -Hardie St $83,799
225mm -Cleland St $44,054
225mm -Heretaunga St $4,675
225mm -Centennial Dr $14,269
225mm -Ihaka St $146,169
Appendix I – Data Management Asset Management Plan 2017 – Wastewater
214
Programme and Renewal Project List 2018/19 [$] 2019/20 [$] 2020/21 [$] 2021/22 [$] 2022/23 [$] 2023/24 [$]
225mm -Cook St $196,065
225mm -Jickell St $128,767
225mm -Shamrock St $34,612
225mm -Main St $518,335
225mm-Matipo St $88,557
225mm -St Johns Ave $111,926
225mm -Pahiatua St $303,036
225mm -Roy St $177,079
225mm -Parkland Cres $85,414
225mm -Snelson St $27,967
225mm -Princess St $125,069
225mm -Ruahine St $105,902
225mm -Rangitikei St $143,744
225mm -Rongopai St $80,154
225mm -Rata St $139,762
65-City-wide - Wastewater Pump Station
Renewal
$150,000 $125,000 $137,000 $85,000 $56,500 $40,000
Minor and Reactive Works $1,000 $11,500 $28,500 $56,500 $40,000
New antena pole and 3rd repeater plus 10
individual RTU's
$90,000
Capri Pl WW PS Pumps $9,000
Jickel ST WW PS Pump Controls $25,000
Te Wanaka Rd WW PS Electrical Incl.
Telemetry
$15,000
Roy St WW PS Electrical $10,000
RTUs $65,000 $53,500
Ruamahanga Cr WW PS Pumps $13,500
Tremaine Ave WW PS Electrical $20,000
Capri Pl WW PS Electrical $15,000
Maple St WW PS $17,500
Maxwells Ln WW PS Electrical $66,000
Racecourse Rd Electrical $16,500
Massey Pump Controls $40,000
Appendix K – Final Peer Review Report Asset Management Plan 2017 – Wastewater
215
Final Peer Review Report Appendix K.Peer review comments to be added here
16-Apr-2018 Prepared for – Palmerston North City Council – Co No.: N/A
PNCC Asset Management Review
Palmerston North City Council
16-Apr-2018
Asset Management Review - 2017 AMP's
AECOM
PNCC Asset Management Review
Asset Management Review - 2017 AMP's
16-Apr-2018 Prepared for – Palmerston North City Council – Co No.: N/A
Quality Information
Document Asset Management Review - 2017 AMP's
Ref
60544471
p:\605x\60544471\8. issued docs\8.1 reports\pncc 2017 amp review final.docx
Date 16-Apr-2018
Prepared by Stephen Garlick
Reviewed by Ian Martin
Revision History
Rev Revision Date Details
Authorised
Name/Position Signature
Draft A 21-Mar-2018 For Comment Ian Martin Regional Manager, Wellington
Final 16-Apr-2018 Final Issue Ian Martin Regional Manager, Wellington
AECOM
PNCC Asset Management Review
Asset Management Review - 2017 AMP's
16-Apr-2018 Prepared for – Palmerston North City Council – Co No.: N/A
Appendix F
Wastewater AMP
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-1
Ap
pen
dix
F
Waste
wa
ter
AM
P
PN
CC
AM
Ass
ess
me
nts
20
18
AM
P
20
17
Wa
ste
wa
ter
AM
P
Ass
ess
me
nt
Ite
m 1
A
lig
nm
en
t
Sco
re
2-3
Wh
y i
s th
is i
mp
ort
an
t?
O
ur
Fin
din
gs
Th
e p
urp
ose
of
org
an
isa
tio
ns
is t
o a
chie
ve o
rga
nis
ati
on
al
ob
ject
ive
s.
In t
he
ca
se o
f lo
cal a
uth
ori
tie
s th
ese
are
ge
ne
rally
exp
ress
ed
as
Co
mm
un
ity
Ou
tco
me
s (r
eq
uir
ed
by
an
d L
GA
20
02
)
an
d in
so
me
ca
ses
sep
ara
te o
rga
nis
ati
on
al o
bje
ctiv
es
sitt
ing
be
low
the
Co
mm
un
ity
Ou
tco
me
s.
It is
imp
ort
an
t th
at
the
ma
na
ge
me
nt
of
ass
et
ba
sed
loca
l au
tho
rity
act
ivit
ies
(as
set
ou
t in
AM
Ps)
is c
lea
rly
alig
ne
d w
ith
an
d
con
trib
ute
s to
th
e a
chie
vem
en
t o
f o
rga
nis
ati
on
al o
bje
ctiv
es.
AM
Ps
sho
uld
als
o r
efl
ect
th
e o
rga
nis
ati
on
’s a
sse
t m
an
ag
em
en
t
po
licy
an
d s
tra
teg
y (i
f th
ere
th
e o
rga
nis
ati
on
ha
s th
ese
) a
nd
wit
h
the
In
fra
stru
ctu
re S
tra
teg
y.
Ro
ad
ing
AM
Ps
(an
d in
pa
rtic
ula
r a
ny
wo
rks
tha
t re
ceiv
e
go
vern
me
nt
sub
sid
y) s
ho
uld
be
co
nsi
ste
nt
wit
h a
nd
su
pp
ort
th
e
Go
vern
me
nt
Po
licy
Sta
tem
en
t o
n L
an
d T
ran
spo
rt a
nd
th
e t
hre
e
stra
teg
ic p
rio
riti
es
form
ing
pa
rt o
f th
e N
ati
on
al P
olic
y St
ate
me
nt
Ta
ble
3 s
ets
ou
t h
ow
th
e W
ast
ew
ate
r A
ctiv
ity
con
trib
ute
s to
th
e f
ollo
win
g 2
(o
f 5
) C
ity
Go
als
·
An
inn
ova
tive
an
d g
row
ing
cit
y
·
An
eco
-cit
y.
It is
un
de
rsto
od
th
at
the
5 C
ity
Go
als
sta
ted
in
th
e A
MP
are
th
e p
rop
ose
d P
alm
ers
ton
No
rth
Cit
y C
om
mu
nit
y O
utc
om
es
for
the
20
18
-20
28
LTP
.
Th
e c
on
trib
uti
on
of
the
Wa
ste
wa
ter
Act
ivit
y to
Cit
y G
oa
ls i
s e
xpre
sse
d i
n T
ab
le 3
as
Pri
ori
tie
s.
Th
ese
re
ad
mo
re li
ke
str
ate
gie
s th
an
sta
tem
en
ts o
f h
ow
th
e W
ast
ew
ate
r A
ctiv
ity
con
trib
ute
s to
Cit
y G
oa
ls e
.g.
“Re
ge
ne
rate
na
tive
bio
div
ers
ity”
sou
nd
s m
ore
lik
e a
str
ate
gy
tha
n
a c
on
trib
uti
on
of
the
Wa
ste
wa
ter
Act
ivit
y co
ntr
ibu
tes
to C
ity
Go
als
.
AM
Ps
are
fo
un
de
d o
n t
he
se
rvic
es
to b
e p
rovi
de
d a
nd
th
e s
tan
da
rds
to b
e a
chie
ved
in
th
e p
rov
isio
n o
f th
ese
se
rvic
es
(Le
vels
of
Serv
ice
).
Th
ese
Le
vels
of
Se
rvic
e s
ho
uld
th
ere
fore
be
cle
arl
y a
lign
ed
wit
h a
nd
co
ntr
ibu
te t
o t
he
ach
ieve
me
nt
of
the
Co
mm
un
ity
Ou
tco
me
s. T
his
is a
n
issu
e A
ud
it N
Z h
ave
ra
ise
d i
n a
ud
its
of
oth
er
org
an
isa
tio
ns.
Th
e L
eve
ls o
f Se
rvic
e f
or
the
Wa
ste
wa
ter
Act
ivit
y se
t o
ut
in T
ab
le 7
co
ver:
·
Qu
alit
y a
nd
He
alt
h
·
Re
liab
ility
·
Re
spo
nsi
ven
ess
·
Acc
ess
ibili
ty
·
Sust
ain
ab
ilit
y
·
Fin
an
cia
l M
an
ag
em
en
t.
Ho
w t
he
se S
erv
ice
Cri
teri
a a
lign
wit
h a
nd
co
ntr
ibu
te t
o C
ity
Go
als
co
uld
be
mo
re e
xplic
it.
De
tail
s o
f th
is a
lig
nm
en
t a
re p
rob
ab
ly b
est
ap
pe
nd
ed
.
Th
e a
sse
t m
an
ag
em
en
t p
roce
ss a
nd
alig
nm
en
t b
etw
ee
n t
he
pri
nci
pa
l ele
me
nts
of
ass
et
ma
na
ge
me
nt
can
be
illu
stra
ted
by
the
fo
llow
ing
dia
gra
m.
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-2
Clo
sin
g t
he
loo
p o
n t
he
ass
et
ma
na
ge
me
nt
pro
cess
invo
lve
s m
ea
suri
ng
pe
rfo
rma
nce
re
lati
ve t
o w
ha
t w
e s
et
ou
t to
ach
ieve
an
d u
sin
g t
his
pe
rfo
rma
nce
(p
erf
orm
an
ce g
ap
s) a
s a
ba
sis
for
con
tin
ua
l im
pro
vem
en
t. 2
01
6/2
01
7 p
erf
orm
an
ce i
s sh
ow
n r
ela
tive
to
pe
rfo
rma
nce
ta
rge
ts
in t
he
le
vels
of
serv
ice
/ke
y p
erf
orm
an
ce in
dic
ato
rs T
ab
le 7
in S
ect
ion
4.4
.1 o
f th
e A
MP
.
It is
no
ted
th
at
the
on
ly K
PI
wh
ere
th
e t
arg
et
leve
l of
pe
rfo
rma
nce
wa
s n
ot
fully
ach
ieve
d w
as:
·
Th
e n
um
be
r o
f d
ry w
ea
the
r w
ast
ew
ate
r o
ve
rflo
ws
fro
m t
he
Co
un
cil’
s se
we
rag
e s
yst
em
s p
er
1,0
00
co
nn
ect
ion
s p
er
ye
ar.
Sect
ion
4.4
.3 c
ove
rs S
erv
ice
Le
vel
Ga
ps.
It
wo
uld
be
exp
ect
ed
th
at
this
fa
ilu
re t
o a
chie
ve t
he
ta
rge
t le
vel o
f p
erf
orm
an
ce w
ou
ld b
e
refl
ect
ed
in
th
e a
na
lysi
s o
f se
rvic
e le
vel g
ap
s w
hic
h i
n t
urn
fe
ed
in
to c
ap
ita
l pro
gra
mm
es.
In
ste
ad
se
rvic
e le
ve
l ga
ps
dis
cuss
ed
in
se
ctio
n
4.4
.3 r
ela
te t
o:
·
Sto
rmw
ate
r in
filt
rati
on
an
d i
nfl
ow
.
·
Ca
pa
city
co
nst
rain
ts in
tru
nk
ma
in n
etw
ork
It is
dif
ficu
lt t
o id
en
tify
th
e s
erv
ice
leve
ls in
Ta
ble
7 t
ha
t th
ese
Se
rvic
e L
eve
l Ga
ps
rela
te t
o.
Sect
ion
3.4
of
the
AM
P s
ets
ou
t th
e A
sse
t M
an
ag
em
en
t P
olic
y a
nd
Str
ate
gy
for
Pa
lme
rsto
n N
ort
h C
ity
Co
un
cil.
T
he
Wa
ste
wa
ter
AM
P
refl
ect
s th
is P
olic
y a
nd
Str
ate
gy.
Ide
ally
, th
e f
ina
nci
als
in t
he
AM
P w
ou
ld b
e p
rese
nte
d in
a w
ay
such
th
at
pri
nci
pa
l bo
tto
m li
ne
s ca
n b
e r
ea
dily
re
con
cile
d w
ith
th
e f
ina
nci
al
sta
tem
en
ts i
n t
he
Co
un
cil L
on
g T
erm
Pla
n.
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-3
Th
is is
imp
ort
an
t a
s A
ud
it N
Z h
av
e t
he
ve
ry r
ea
son
ab
le e
xpe
cta
tio
n t
ha
t th
e A
MP
s w
ill c
lea
rly
pro
vid
e t
he
ba
sis
an
d j
ust
ific
ati
on
fo
r th
e
fin
an
cia
l sta
tem
en
ts in
th
e L
TP
.
Th
e f
ollo
win
g e
xpe
nd
itu
re f
ore
cast
s a
re t
ak
en
fro
m t
he
20
17
Wa
ste
wa
ter
AM
P –
Lif
ecy
cle
Pro
gra
mm
es
Th
ese
are
th
en
su
mm
ari
sed
in
th
e F
ina
nci
al F
ore
cast
s in
Ap
pe
nd
ix E
.
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-4
Th
ere
ap
pe
ars
to
be
a m
ism
atc
h b
etw
ee
n t
he
fin
an
cia
ls s
et
ou
t in
th
e li
fecy
cle
pro
gra
mm
es
an
d t
he
fin
an
cia
ls i
n A
pp
en
dix
E.
Fo
r e
xam
ple
the
bu
dg
ete
d r
en
ew
al e
xpe
nd
itu
re f
or
20
18
/20
19
in T
ab
le 2
3 i
s $
3,6
93
,00
0 w
he
rea
s in
Ta
ble
E2
, b
ud
ge
ted
re
ne
wa
l exp
en
dit
ure
fo
r
20
18
/20
19
is $
2,1
27
,00
0.
Fo
r 2
01
9/2
02
0,
the
fig
ure
s in
th
e t
wo
ta
ble
s a
re $
2,4
85
,00
0 a
nd
$1
,59
5,0
00
re
spe
ctiv
ely
. I
n t
he
20
15
/20
25
LT
P
the
re
ne
wa
l fig
ure
s a
re $
3,7
89
,00
0 f
or
20
18
/20
19
an
d $
1,8
18
,00
0 f
or
20
19
/20
20
.
Th
e d
raft
20
18
/20
28
LT
P is
no
t cu
rre
ntl
y a
vaila
ble
. T
he
re a
pp
ea
red
to
be
a s
urp
risi
ng
leve
l of
vari
an
ce b
etw
ee
n t
he
fin
an
cia
ls in
th
e 2
01
7
AM
P a
nd
th
ose
in t
he
20
15
/20
25
LT
P,
eve
n a
llow
ing
fo
r th
e f
act
th
at
the
20
15
/20
25
LT
P is
in t
he
pro
cess
of
be
ing
su
pe
rse
de
d.
. I
t h
as
be
en
ass
um
ed
th
at
such
dis
cre
pa
nci
es
do
no
t a
pp
ea
r w
he
n c
om
pa
rin
g w
ith
th
e 2
01
8/2
02
8 d
raft
LT
P.
It is
ext
rem
ely
imp
ort
an
t th
at
the
re is
a c
lea
r li
ne
of
sig
ht
fro
m t
he
bu
dg
et
fig
ure
s in
th
e L
TP
ba
ck t
o t
he
co
nso
lida
ted
fin
an
cia
l pro
ject
ion
s
in t
he
AM
P a
nd
fro
m t
he
re b
ack
to
th
e b
ud
ge
ts in
ea
ch o
f th
e li
fecy
cle
pro
gra
mm
es.
Au
dit
Ne
w Z
ea
lan
d h
ave
th
e v
ery
re
aso
na
ble
exp
ect
ati
on
th
at
the
AM
P w
ill b
e t
he
so
urc
es
of
fin
an
cia
l fo
reca
sts
in t
he
LT
P a
nd
th
at
this
ca
n b
e r
ea
dily
ve
rifi
ed
by
com
pa
rin
g b
oth
do
cum
en
ts.
In
ab
ility
to
de
mo
nst
rate
th
is c
lea
r li
ne
of
sig
ht
will
un
de
rmin
e t
he
cre
dib
ilit
y o
f b
oth
th
e A
MP
an
d o
f th
e L
TP
.
O
pp
ort
un
itie
s fo
r Im
pro
ve
me
nt
1
. Sh
ow
mo
re c
lea
rly
the
ali
gn
me
nt
be
twe
en
th
e L
eve
ls o
f Se
rvic
es
set
ou
t in
Se
ctio
n 4
of
the
AM
P,
the
Act
ivit
y C
on
trib
uti
on
to
Cit
y G
oa
ls
an
d t
he
refo
re t
he
Cit
y G
oa
ls.
Th
e d
iag
ram
be
low
pro
vid
es
on
e e
xam
ple
of
ho
w t
his
alig
nm
en
t m
igh
t b
e d
em
on
stra
ted
.
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-5
2.
Imp
rove
th
e a
lig
nm
en
t b
etw
ee
n s
erv
ice
ga
ps
ari
sin
g f
rom
th
e c
om
pa
riso
n o
f 2
01
6/2
01
7 p
erf
orm
an
ce w
ith
th
e c
urr
en
t ta
rge
t in
Ta
ble
7 in
th
e A
MP
, th
e d
iscu
ssio
n o
f se
rvic
e le
vel g
ap
s in
Se
ctio
n 4
.4.3
an
d t
he
ca
pit
al d
eve
lop
me
nt
pro
gra
mm
e r
eco
gn
isin
g t
ha
t cu
rre
nt
an
d e
xpe
cte
d s
erv
ice
ga
ps
are
th
e d
rive
r fo
r n
ew
ca
pit
al i
nv
est
me
nt.
3.
En
sure
th
ere
is a
cle
ar
lin
e o
f si
gh
t fr
om
th
e F
ina
nci
al P
roje
ctio
ns
on
th
e L
TP
ba
ck t
o t
he
co
nso
lida
ted
fin
an
cia
l p
roje
ctio
ns
in t
he
AM
P
an
d f
rom
th
ere
ba
ck t
o t
he
bu
dg
ets
in e
ach
of
the
life
cycl
e p
rog
ram
me
s
0 -
In
no
cen
t 1
- A
wa
re
2 -
De
ve
lop
ing
3 -
Fu
lly
me
ets
re
qu
ire
me
nts
4
- E
xce
ed
s re
qu
ire
me
nts
Th
e A
MP
do
es
no
t d
em
on
stra
te a
ny
aw
are
ne
ss o
f th
is r
eq
uir
em
en
t
Th
e A
MP
do
es
no
t cu
rre
ntl
y a
dd
ress
this
re
qu
ire
me
nt
(or
cove
rs it
in a
min
ima
l wa
y) b
ut
de
mo
nst
rate
s a
n
inte
nt
to p
rog
ress
it
Th
e A
MP
pa
rtly
co
mp
lie
s w
ith
go
od
ind
ust
ry p
ract
ice
an
d d
em
on
stra
tes
an
inte
nt
to a
chie
ve f
ull
co
mp
lian
ce w
ith
go
od
ind
ust
ry p
ract
ice
Th
e A
MP
co
mp
lies
wit
h g
oo
d in
du
stry
pra
ctic
e
Th
e A
MP
exc
ee
ds
com
plia
nce
wit
h g
oo
d
ind
ust
ry p
ract
ice
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-6
Ass
ess
me
nt
Ite
m 2
S
erv
ice
sta
tem
en
ts a
nd
Le
ve
ls o
f S
erv
ice
Sco
re
3
Wh
y i
s th
is i
mp
ort
an
t?
O
ur
Fin
din
gs
AM
Ps
sho
uld
be
fo
un
de
d o
n a
sta
tem
en
t o
f w
ha
t th
e p
lan
s a
re
inte
nd
ed
to
ach
ieve
. T
his
is
ge
ne
rally
a s
tate
me
nt
of
the
se
rvic
es
to b
e p
rovi
de
d t
hro
ug
h t
he
pla
n,
the
sta
nd
ard
s to
be
ach
ieve
d a
nd
the
lev
el o
f p
erf
orm
an
ce t
ha
t is
ta
rge
ted
. T
his
sh
ou
ld i
nco
rpo
rate
the
ma
nd
ato
ry p
erf
orm
an
ce m
ea
sure
s re
qu
ire
d u
nd
er
the
No
n-
Fin
an
cia
l Pe
rfo
rma
nce
Me
asu
res
Ru
les
20
13
. R
oa
din
g A
MP
s sh
ou
ld
inco
rpo
rate
On
e N
etw
ork
Ro
ad
Cla
ssif
ica
tio
n p
erf
orm
an
ce
me
asu
res
as
ap
pro
pri
ate
.
Th
e j
ust
ific
ati
on
fo
r th
e t
arg
et
lev
els
of
serv
ice
sh
ou
ld b
e p
rovi
de
d.
Ide
ally
th
is w
ou
ld i
ncl
ud
e c
on
sid
era
tio
n o
f b
en
efi
ts a
nd
co
sts
of
dif
fere
nt
leve
ls o
f se
rvic
e.
Serv
ice
sta
tem
en
ts r
ep
rese
nt
the
ob
ject
ive
s th
at
the
AM
P a
ims
to
ach
ieve
. I
t is
imp
ort
an
t th
at
the
se o
bje
ctiv
es
are
cle
arl
y a
lig
ne
d
wit
h o
rga
nis
ati
on
al o
bje
ctiv
es
(ali
gn
me
nt
sho
uld
be
de
mo
nst
rate
d
in t
he
AM
P).
Ide
ally
th
e A
MP
wo
uld
pro
vid
e a
cle
ar
sta
tem
en
t o
f th
e s
erv
ice
s th
at
will
be
pro
vid
ed
to
ea
ch o
f th
e m
ain
cu
sto
me
r se
gm
en
ts.
Th
is,
tog
eth
er
wit
h s
tan
da
rds
to w
hic
h t
he
se s
erv
ice
s w
ill b
e p
rovi
de
d f
orm
th
e f
ou
nd
ati
on
of
the
AM
P.
Sect
ion
2.2
of
the
AM
P p
rovi
de
s th
e f
ollo
win
g s
eg
me
nta
tio
n o
f cu
sto
me
rs:
“Cu
sto
me
rs o
f w
ast
ew
ate
r se
rvic
es
are
bro
ke
n d
ow
n a
s fo
llo
ws:
·
Re
sid
en
tia
l cu
sto
me
rs
·
Ind
ust
ria
l cu
sto
me
rs
·
Co
mm
erc
ial
cust
om
ers
”.
Ide
ally
an
y cu
sto
me
r re
ad
ing
th
e A
MP
sh
ou
ld b
e a
ble
to
re
ad
ily id
en
tify
th
e c
ust
om
er
seg
me
nt
(or
seg
me
nts
) w
ith
in w
hic
h t
he
y fi
t a
nd
th
e
ass
oci
ate
d s
erv
ice
s th
ey
can
exp
ect
to
re
ceiv
e f
rom
th
e C
ou
nci
l. T
his
is t
ypic
ally
pre
sen
ted
as
follo
ws.
Th
e A
MP
do
es
no
t a
pp
ea
r to
ide
nti
fy t
he
po
int
of
serv
ice
fo
r w
ast
ew
ate
r se
rvic
es
pro
vid
ed
by
the
Co
un
cil.
(D
iffe
ren
t cu
sto
me
rs s
ho
uld
be
ab
le t
o c
lea
rly
un
de
rsta
nd
th
e p
oin
t o
f d
em
arc
ati
on
be
twe
en
th
e C
ou
nci
l re
spo
nsi
bil
itie
s a
nd
th
eir
re
spo
nsi
bili
tie
s)
Th
e C
ust
om
er
Leve
ls o
f Se
rvic
e f
or
Wa
ste
wa
ter
set
ou
t in
Ta
ble
7 o
f th
e A
MP
co
ver
the
fo
llow
ing
se
rvic
e d
ime
nsi
on
s:
·
Qu
alit
y a
nd
He
alt
h
·
Re
liab
ility
·
Re
spo
nsi
ven
ess
·
Acc
ess
ibili
ty
·
Sust
ain
ab
ilit
y
·
Fin
an
cia
l M
an
ag
em
en
t.
Th
ere
is a
go
od
ra
ng
e o
f C
ust
om
er
Pe
rfo
rma
nce
Me
asu
res
for
the
se s
erv
ice
dim
en
sio
ns.
Te
chn
ica
l Le
vels
of
Serv
ice
are
ap
pe
nd
ed
in
Ta
ble
C1
alt
ho
ug
h t
he
se a
pp
ea
r to
be
th
e s
am
e a
s th
e C
ust
om
er
Leve
ls o
f S
erv
ice
.
Ta
ble
s 5
an
d C
1 i
nco
rpo
rate
th
e L
oca
l Go
vern
me
nt
Ma
nd
ato
ry P
erf
orm
an
ce M
ea
sure
s se
t o
ut
in t
he
No
n-F
ina
nci
al P
erf
orm
an
ce M
ea
sure
s
Ru
les
20
13
.
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-7
Wh
ere
th
ere
is
a s
ign
ific
an
t va
ria
tio
n b
etw
ee
n a
ctu
al a
nd
ta
rge
t le
vel o
f p
erf
orm
an
ce s
om
e f
orm
of
com
me
nta
ry s
ho
uld
be
pro
vid
ed
as
this
ma
y in
dic
ate
a n
ee
d f
or
som
e f
orm
of
inte
rve
nti
on
.
For
exa
mp
le t
he
nu
mb
er
of
blo
cka
ge
co
mp
lain
ts is
ap
pro
xim
ate
ly 1
6 t
ime
s lo
we
r
tha
n t
he
ta
rge
t w
hic
h is
go
od
bu
t w
hic
h b
eg
s th
e q
ue
stio
n “
Is t
he
ta
rge
t to
o h
igh
?”
A
co
mm
en
tary
on
un
usu
al l
oo
kin
g r
esu
lts
wo
uld
ad
dre
ss p
ote
nti
al q
ue
stio
ns
Pe
rfo
rma
nce
ta
rge
ts f
or
ea
ch L
OS
are
sta
ted
fo
r a
10
ye
ar
ho
rizo
n.
It
is u
ncl
ea
r h
ow
th
ese
pe
rfo
rma
nce
ta
rge
ts w
ere
se
t a
nd
wh
eth
er
an
y
an
aly
sis
of
the
be
ne
fits
an
d c
ost
s o
f d
iffe
ren
t p
erf
orm
an
ce t
arg
ets
ha
s b
ee
n c
arr
ied
ou
t. A
nti
cip
ate
d c
ha
ng
es
in t
arg
et
leve
ls o
f se
rvic
e a
re
sta
ted
an
d t
he
re i
s a
dis
cuss
ion
of
serv
ice
ga
ps.
O
pp
ort
un
itie
s fo
r Im
pro
ve
me
nt
4
. Id
en
tify
th
e c
ust
om
er
seg
me
nts
fo
r w
ast
ew
ate
r se
rvic
es
the
ass
oci
ate
d s
erv
ice
s th
ese
se
gm
en
ts c
an
exp
ect
to
re
ceiv
e f
rom
th
e
Co
un
cil.
5.
De
fin
e t
he
“p
oin
t o
f se
rvic
e”
for
wa
ste
wa
ter
serv
ice
s
6.
Pro
vid
e a
co
mm
en
tary
wh
ere
th
ere
is a
sig
nif
ica
nt
vari
an
ce b
etw
ee
n A
ctu
al P
erf
orm
an
ce a
chie
ved
an
d t
he
Pe
rfo
rma
nce
Ta
rge
ts
7.
Pro
vid
e a
co
mm
en
tary
on
ho
w t
he
ta
rge
t le
vels
of
serv
ice
we
re s
et.
Id
ea
lly t
his
wo
uld
in
clu
de
co
nsi
de
rati
on
of
cost
imp
lica
tio
ns
of
dif
fere
nt
leve
ls o
f se
rvic
e a
lth
ou
gh
a f
ull
be
ne
fit/
cost
an
aly
sis
of
dif
fere
nt
leve
ls o
f se
rvic
e m
ay
no
t b
e j
ust
ifie
d.
0 -
In
no
cen
t 1
- A
wa
re
2 -
De
ve
lop
ing
3
- F
ull
y m
ee
ts r
eq
uir
em
en
ts
4 -
Ex
cee
ds
req
uir
em
en
ts
Th
e A
MP
do
es
no
t d
em
on
stra
te a
ny
aw
are
ne
ss o
f th
is r
eq
uir
em
en
t
Th
e A
MP
do
es
no
t cu
rre
ntl
y a
dd
ress
this
re
qu
ire
me
nt
(or
cove
rs i
t in
a
min
ima
l wa
y) b
ut
de
mo
nst
rate
s a
n
inte
nt
to p
rog
ress
it
Th
e A
MP
pa
rtly
co
mp
lie
s w
ith
go
od
ind
ust
ry p
ract
ice
an
d d
em
on
stra
tes
an
inte
nt
to a
chie
ve f
ull
co
mp
lian
ce w
ith
go
od
ind
ust
ry p
ract
ice
Th
e A
MP
co
mp
lies
wit
h g
oo
d in
du
stry
pra
ctic
e
Th
e A
MP
exc
ee
ds
com
plia
nce
wit
h g
oo
d
ind
ust
ry p
ract
ice
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-8
Ass
ess
me
nt
Ite
m 3
F
utu
re d
em
an
d
S
core
3
Wh
y i
s th
is i
mp
ort
an
t?
O
ur
Fin
din
gs
AM
Ps
are
str
ate
gic
do
cum
en
ts w
hic
h t
ake
a lo
ng
te
rm v
iew
. I
t is
imp
ort
an
t to
ide
nti
fy t
he
pri
nci
pa
l ch
an
ge
s w
hic
h a
re l
ike
ly t
o
imp
act
on
th
e p
lan
ove
r th
e t
erm
of
the
pla
n a
nd
ta
ke a
cco
un
t o
f
the
se c
ha
ng
es
in t
he
pla
n.
Th
is i
nvo
lve
s id
en
tify
ing
th
e p
rin
cip
al
dri
vers
of
cha
ng
e,
ass
ess
ing
ho
w t
he
se d
rive
rs a
re l
ike
ly t
o c
ha
ng
e
ove
r th
e t
erm
of
the
pla
n a
nd
th
e o
vera
ll im
pa
ct o
n t
he
pla
n.
Th
e A
MP
ide
nti
fie
s 8
pri
nci
pa
l d
rive
rs o
f d
em
an
d.
·
Re
sid
en
tia
l an
d,
ind
ust
ria
l gro
wth
in t
he
cit
y.
·
Ch
an
ge
s in
wa
ter
con
sum
pti
on
an
d u
sag
e p
att
ern
s. M
ost
wa
ter
sup
pli
ed
fo
r d
om
est
ic,
com
me
rcia
l, a
nd
ind
ust
ria
l pu
rpo
ses
is
sub
seq
ue
ntl
y d
isch
arg
ed
into
th
e w
ast
ew
ate
r sy
ste
m.
·
Gre
ate
r u
pta
ke
of
Low
Pre
ssu
re S
ew
er
pa
rtic
ula
rly
in t
he
pre
ssu
re s
ew
er
de
sig
na
ted
are
as.
·
Ch
an
ge
s in
Co
un
cil p
olic
y w
ith
re
ga
rd t
o r
ura
l re
sid
en
tia
l pro
pe
rtie
s.
·
Th
e e
xte
nt
of
sto
rmw
ate
r e
ntr
y to
th
e w
ast
ew
ate
r sy
ste
m (
infi
ltra
tio
n a
nd
in
flo
w).
·
Futu
re d
em
an
d f
or
tre
atm
en
t o
f w
ast
ew
ate
r d
rive
n b
y te
chn
olo
gy
ch
an
ge
s.
·
Re
gio
na
l Co
un
cil O
ne
Pla
n S
tan
da
rds
·
Clim
ate
ch
an
ge
.
Th
ere
is a
dis
cuss
ion
ab
ou
t h
ow
ea
ch o
f th
ese
fa
cto
rs is
exp
ect
ed
to
ch
an
ge
ove
r ti
me
. T
he
wa
y th
e d
iscu
ssio
n a
bo
ut
the
se f
act
ors
is
pre
sen
ted
co
uld
be
imp
rove
d t
o m
irro
r m
ore
clo
sely
th
e 5
dri
vers
of
de
ma
nd
as
ind
ica
ted
be
low
.
Th
ese
dri
vers
of
de
ma
nd
fe
ed
in
to a
de
ma
nd
pro
ject
ion
in
Ta
ble
13
co
veri
ng
a 3
0 y
ea
r h
ori
zon
. A
s w
ell
as
sho
win
g p
roje
cte
d f
low
s th
is
als
o p
roje
cts
the
dif
fere
nt
loa
din
gs
(BO
D,
SS e
tc.)
in t
he
wa
ste
wa
ter
tha
t im
pa
ct o
n t
rea
tme
nt
pro
cess
es.
Th
ere
is m
eri
t in
se
gm
en
tin
g t
he
de
ma
nd
pro
ject
ion
by
the
dri
vers
of
de
ma
nd
an
d s
ho
win
g t
his
gra
ph
ica
lly.
Th
is h
igh
ligh
ts w
ha
t is
pri
ma
rily
dri
vin
g f
utu
re d
em
an
d a
nd
th
e a
rea
s w
he
re e
ffo
rts
sho
uld
be
fo
cuss
ed
to
re
du
ce d
em
an
d.
Ide
ally
th
ere
wo
uld
be
an
in
dic
ati
on
giv
en
of
con
fid
en
ce i
n t
he
de
ma
nd
pro
ject
ion
. T
his
co
uld
be
do
ne
by
pro
vid
ing
hig
h,
me
diu
m a
nd
low
pro
ject
ion
s o
f d
em
an
d.
O
pp
ort
un
itie
s fo
r Im
pro
ve
me
nt
8
. P
rovi
de
an
ind
ica
tio
n o
f th
e le
ve
l o
f co
nfi
de
nce
in d
em
an
d p
roje
ctio
ns
0 -
In
no
cen
t 1
- A
wa
re
2 -
De
ve
lop
ing
3
- F
ull
y m
ee
ts r
eq
uir
em
en
ts
4 -
Ex
cee
ds
req
uir
em
en
ts
Th
e A
MP
do
es
no
t d
em
on
stra
te a
ny
aw
are
ne
ss o
f th
is r
eq
uir
em
en
t
Th
e A
MP
do
es
no
t cu
rre
ntl
y a
dd
ress
this
re
qu
ire
me
nt
(or
cove
rs it
in a
min
ima
l wa
y) b
ut
de
mo
nst
rate
s a
n
inte
nt
to p
rog
ress
it
Th
e A
MP
pa
rtly
co
mp
lie
s w
ith
go
od
ind
ust
ry p
ract
ice
an
d d
em
on
stra
tes
an
inte
nt
to a
chie
ve f
ull
co
mp
lian
ce w
ith
go
od
ind
ust
ry p
ract
ice
Th
e A
MP
co
mp
lies
wit
h g
oo
d in
du
stry
pra
ctic
e
Th
e A
MP
exc
ee
ds
com
plia
nce
wit
h g
oo
d
ind
ust
ry p
ract
ice
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-9
Ass
ess
me
nt
Ite
m 4
R
isk
Sco
re
2-3
Wh
y i
s th
is i
mp
ort
an
t?
O
ur
Fin
din
gs
AM
Ps
set
ou
t h
ow
org
an
isa
tio
ns
inte
nd
to
wo
rk t
o a
chie
ve a
ctiv
ity
spe
cifi
c a
sse
t m
an
ag
em
en
t o
bje
ctiv
es.
It
is im
po
rta
nt
to a
lso
ide
nti
fy r
isk
s to
th
e a
chie
vem
en
t o
f th
ese
ob
ject
ive
s, e
nsu
re
tra
nsp
are
ncy
of
the
se r
isk
s a
nd
ma
na
ge
th
ese
ris
ks w
ith
in t
he
ris
k
ap
pe
tite
of
the
org
an
isa
tio
n.
Ris
k sh
ou
ld b
e a
n i
np
ut
to d
eci
sio
n
ma
kin
g.
Th
ere
is c
om
pre
he
nsi
ve c
ove
rag
e o
f ri
sk in
th
e A
pp
en
dix
D o
f th
e A
MP
wit
h a
su
mm
ary
of
the
ap
pro
ach
se
t o
ut
in S
ect
ion
7.
Ris
ks
are
ma
na
ge
d i
n a
cco
rda
nce
wit
h a
Co
rpo
rate
Ris
k M
an
ag
em
en
t P
olic
y w
hic
h s
up
po
rts
a c
on
sist
en
t a
pp
roa
ch t
o r
isk
ma
na
ge
me
nt
acr
oss
th
e
org
an
isa
tio
n.
Th
is p
olic
y co
vers
str
ate
gic
, o
pe
rati
on
al a
nd
pro
ject
ris
ks.
Th
ere
is a
se
pa
rate
se
ctio
n (
7.2
) o
n A
ctiv
ity
Ris
k M
an
ag
em
en
t.
In S
ect
ion
7.2
.1,
it is
sta
ted
th
at
the
co
nse
qu
en
ce o
f ri
sk is
eva
lua
ted
in t
erm
s o
f:
·
Leg
al
·
En
viro
nm
en
tal
·
Co
rpo
rate
Im
ag
e
·
Serv
ice
de
live
ry
·
Fin
an
cia
l
·
Co
mm
un
ity
He
alt
h a
nd
Sa
fety
.
Ta
ble
D2
se
ts o
ut
Me
asu
res
of
Co
nse
qu
en
ces
of
Fail
ure
. I
t is
no
tice
d t
ha
t in
th
is t
ab
le “
En
viro
nm
en
tal”
is n
ot
ide
nti
fie
d a
s a
n a
rea
of
imp
act
wit
h e
nvi
ron
me
nta
l d
am
ag
e b
ein
g i
ncl
ud
ed
in
th
e “
Leg
al”
ca
teg
ory
. I
t is
su
gg
est
ed
th
at
pa
rtic
ula
rly
for
an
act
ivit
y su
ch a
s
wa
ste
wa
ter
wh
ich
ca
n h
ave
sig
nif
ica
nt
en
viro
nm
en
tal e
ffe
cts,
“E
nvi
ron
me
nta
l” s
ho
uld
be
a s
ep
ara
te c
on
seq
ue
nce
ca
teg
ory
.
It is
no
ted
th
at
Ta
ble
D5
: C
on
seq
ue
nce
Ra
tin
g a
pp
ea
rs t
o r
ep
ea
t T
ab
le D
2:
Me
asu
res
of
Co
nse
qu
en
ce o
f Fa
ilure
an
d t
ha
t th
ere
ap
pe
ar
to
be
tw
o d
iffe
ren
t ri
sk m
atr
ice
s sh
ow
n a
s fo
llow
s.
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-1
0
Ob
vio
usl
y d
up
lica
tio
n i
s u
nd
esi
rab
le c
on
sist
en
cy is
ess
en
tia
l.
Alt
ho
ug
h r
efe
ren
ce i
s m
ad
e i
n t
he
AM
P t
o a
ris
k re
gis
ter
in A
pp
en
dix
D,
the
re d
id n
ot
ap
pe
ar
to b
e a
n A
ctiv
ity
Ris
k R
eg
iste
r in
th
e A
MP
.
Fig
ure
D2
se
ts o
ut
a r
isk
ma
na
ge
me
nt
pro
cess
wh
ich
incl
ud
es
the
id
en
tifi
cati
on
of
risk
.
Ris
ks
are
un
cert
ain
fu
ture
eve
nts
th
at
cou
ld i
mp
act
on
an
org
an
isa
tio
n’s
ab
ilit
y t
o a
chie
ve it
s o
bje
ctiv
es.
Th
e A
S/N
ZS
ISO
31
00
0:2
00
9
Sta
nd
ard
de
fin
es
risk
as
the
“e
ffe
ct o
f u
nce
rta
inty
on
ob
ject
ive
s”.
R
isks
sh
ou
ld t
he
refo
re b
e id
en
tifi
ed
in t
erm
s o
f o
bje
ctiv
es
(Im
pa
ct o
n
ob
ject
ive
s is
wh
at
ma
ke
s a
ris
k a
ris
k).
It
is s
ug
ge
ste
d t
ha
t th
is p
roce
ss d
iag
ram
sh
ou
ld a
lso
incl
ud
e r
efe
ren
ce t
o o
bje
ctiv
es
in t
he
ris
k
ide
nti
fica
tio
n p
ha
se.
O
pp
ort
un
itie
s fo
r Im
pro
ve
me
nt
9
. In
clu
de
a r
eg
iste
r o
f A
ctiv
ity
Ris
ks
in t
he
AM
P
10
. A
dd
co
nsi
de
rati
on
of
ob
ject
ive
s to
Fig
ure
D2
- r
isk
ma
na
ge
me
nt
pro
cess
re
cog
nis
ing
th
at
it is
im
pa
ct o
n o
bje
ctiv
es
wh
ich
ma
kes
a r
isk
a r
isk.
11
. E
nsu
re a
co
nsi
ste
nt
ap
pro
ach
is
ad
op
ted
to
th
e a
sse
ssm
en
t o
f ri
sks
(sin
gle
ris
k m
atr
ix)
an
d d
ele
te o
ne
of
the
ris
k co
nse
qu
en
ce t
ab
les.
0 -
In
no
cen
t 1
- A
wa
re
2 -
De
ve
lop
ing
3 -
Fu
lly
me
ets
re
qu
ire
me
nts
4
- E
xce
ed
s re
qu
ire
me
nts
Th
e A
MP
do
es
no
t d
em
on
stra
te a
ny
aw
are
ne
ss o
f th
is r
eq
uir
em
en
t
Th
e A
MP
do
es
no
t cu
rre
ntl
y a
dd
ress
this
re
qu
ire
me
nt
(or
cove
rs it
in a
min
ima
l wa
y) b
ut
de
mo
nst
rate
s a
n
inte
nt
to p
rog
ress
it
Th
e A
MP
pa
rtly
co
mp
lie
s w
ith
go
od
ind
ust
ry p
ract
ice
an
d d
em
on
stra
tes
an
inte
nt
to a
chie
ve f
ull
co
mp
lian
ce w
ith
go
od
ind
ust
ry p
ract
ice
Th
e A
MP
co
mp
lies
wit
h g
oo
d in
du
stry
pra
ctic
e
Th
e A
MP
exc
ee
ds
com
plia
nce
wit
h g
oo
d
ind
ust
ry p
ract
ice
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-1
1
Ass
ess
me
nt
Ite
m 5
C
riti
cal
ass
ets
Sco
re
2-3
Wh
y i
s th
is i
mp
ort
an
t?
O
ur
Fin
din
gs
Cri
tica
l ass
ets
are
th
ose
wit
h a
hig
h c
on
seq
ue
nce
of
failu
re.
It is
imp
ort
an
t th
at
crit
ica
l ass
ets
are
id
en
tifi
ed
usi
ng
a d
efi
ne
d a
nd
con
sist
en
t m
eth
od
olo
gy
an
d t
ha
t a
pp
rop
ria
te in
terv
en
tio
ns
are
pu
t
in p
lace
(su
ch a
s co
nd
itio
n m
on
ito
rin
g,
rep
lace
me
nt
be
fore
fa
ilure
,
con
tin
ge
ncy
pla
nn
ing
, a
ctio
ns
to r
ed
uce
cri
tica
lity)
to
min
imis
e t
he
risk
of
failu
re o
f cr
itic
al a
sse
ts.
Ass
et
Cri
tica
lity
is s
um
ma
rise
d in
7.1
.6 -
Se
ctio
n 7
– R
isk
s a
nd
Re
sili
en
ce a
nd
co
vere
d in
mo
re d
eta
il in
7.2
.3.
In
7.2
.3,
crit
ica
l ass
ets
are
ide
nti
fie
d “
as
tho
se a
sse
ts w
hic
h h
ave
th
e h
igh
est
co
nse
qu
en
ces
sho
uld
th
ey f
ail
”.
Sect
ion
7.2
.3 s
tate
s th
at
“Cri
teri
a f
or
ass
ess
ing
cri
tica
lity
are
:
·
Nu
mb
ers
of
pe
op
le a
dve
rse
ly a
ffe
cte
d;
·
Sig
nif
ica
nt
bu
sin
ess
act
ivit
y i
nte
rru
pte
d;
·
Co
nse
qu
en
tia
l co
st o
f fa
ilu
re;
an
d
·
Cri
tica
l li
feli
ne
/dis
ast
er
reco
very
ass
et”
.
·
Oth
er
Th
e c
riti
calit
y o
f p
um
p s
tati
on
s is
ass
ess
ed
in
te
rms
of
the
se
nsi
tivi
ty o
f th
e r
ece
ivin
g e
nvi
ron
me
nt
to o
verf
low
s is
co
nsi
de
red
, a
s w
ell
as
the
po
pu
lati
on
se
rve
d.
Cri
tica
lity
of
tre
atm
en
t p
lan
t a
sse
ts is
ba
sed
on
th
e c
on
seq
ue
nce
of
failu
re o
f e
ach
co
mp
on
en
t a
nd
its
ro
le a
s p
art
of
the
tre
atm
en
t
pro
cess
ove
rall.
Ris
k a
nd
cri
tica
lity
are
lin
ked
. W
he
rea
s ri
sk i
s a
co
mb
ina
tio
n o
f co
nse
qu
en
ce a
nd
pro
ba
bil
ity,
cri
tica
lity
is a
bo
ut
con
seq
ue
nce
on
ly.
Co
nse
qu
en
ce o
f a
ctiv
ity
risk
is
ass
ess
ed
in
th
e A
MP
in t
erm
s o
f th
e f
ollo
win
g:
·
Leg
al
·
En
viro
nm
en
tal
·
Co
rpo
rate
Im
ag
e
·
Serv
ice
de
live
ry
·
Fin
an
cia
l
·
Co
mm
un
ity
He
alt
h a
nd
Sa
fety
In t
he
in
tere
sts
of
con
sist
en
cy,
the
sa
me
cri
teri
a s
ho
uld
be
use
d t
o a
sse
ss c
riti
calit
y. F
or
exa
mp
le s
ho
uld
an
ass
et
wh
ose
fa
ilu
re w
ou
ld b
e
like
ly t
o le
ad
to
se
vere
en
viro
nm
en
tal d
am
ag
e,
na
tio
na
l h
ea
dli
ne
s a
nd
pro
secu
tio
n o
f th
e C
ou
nci
l be
co
nsi
de
red
a c
riti
cal a
sse
t? I
t
pro
ba
bly
sh
ou
ld.
Als
o a
sse
ts s
erv
ing
cri
tica
l cu
sto
me
rs s
uch
as
ho
spit
als
do
no
t a
pp
ea
r to
ha
ve b
ee
n id
en
tifi
ed
as
crit
ica
l b
y th
e c
urr
en
t
pro
cess
.
Se
ctio
n 6
.8.2
se
ts o
ut
ho
w t
he
Co
un
cil’
s m
ain
ten
an
ce s
tra
teg
y i
s li
nk
ed
to
ass
et
crit
ica
lity
wit
h d
iffe
ren
t in
spe
ctio
n a
nd
ma
inte
na
nce
reg
ime
s fo
r
·
Hig
hly
cri
tica
l ass
ets
·
Me
diu
m a
nd
Lo
w c
riti
calit
y a
sse
ts
·
No
n c
riti
cal a
sse
ts.
Cri
tica
lity
is a
lso
ta
ken
in
to a
cco
un
t in
ma
kin
g r
en
ew
al d
eci
sio
ns.
Ta
ken
ove
rall,
cri
tica
lity
is w
ell
do
ne
in t
he
Wa
ste
wa
ter
AM
P.
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-1
2
O
pp
ort
un
itie
s fo
r Im
pro
ve
me
nt
1
2.
En
sure
ali
gn
me
nt
an
d c
on
sist
en
cy b
etw
ee
n a
sse
ssm
en
ts o
f cr
itic
ali
ty a
nd
ass
ess
me
nts
of
risk
by
ass
ess
ing
co
nse
qu
en
ce o
n t
he
sa
me
ba
sis
for
bo
th r
isk
an
d c
riti
calit
y.
0 -
In
no
cen
t 1
- A
wa
re
2 -
De
ve
lop
ing
3 -
Fu
lly
me
ets
re
qu
ire
me
nts
4
- E
xce
ed
s re
qu
ire
me
nts
Th
e A
MP
do
es
no
t d
em
on
stra
te a
ny
aw
are
ne
ss o
f th
is r
eq
uir
em
en
t
Th
e A
MP
do
es
no
t cu
rre
ntl
y a
dd
ress
this
re
qu
ire
me
nt
(or
cove
rs it
in a
min
ima
l wa
y) b
ut
de
mo
nst
rate
s a
n
inte
nt
to p
rog
ress
it
Th
e A
MP
pa
rtly
co
mp
lie
s w
ith
go
od
ind
ust
ry p
ract
ice
an
d d
em
on
stra
tes
an
inte
nt
to a
chie
ve f
ull
co
mp
lian
ce w
ith
go
od
ind
ust
ry p
ract
ice
Th
e A
MP
co
mp
lies
wit
h g
oo
d in
du
stry
pra
ctic
e
Th
e A
MP
exc
ee
ds
com
plia
nce
wit
h g
oo
d
ind
ust
ry p
ract
ice
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-1
3
Ass
ess
me
nt
Ite
m 6
Ju
stif
ica
tio
n f
or
ma
inte
na
nce
pro
gra
mm
es
S
core
2
-3
Wh
y i
s th
is i
mp
ort
an
t?
O
ur
Fin
din
gs
Ma
inte
na
nce
pro
gra
mm
es
are
re
lie
d u
po
n a
s a
so
urc
e o
f in
pu
ts t
o
the
Co
un
cil’
s lo
ng
te
rm f
ina
nci
al
pla
nn
ing
an
d t
he
Co
un
cil
Lon
g
Te
rm P
lan
. T
he
y sh
ou
ld p
rovi
de
co
nfi
de
nce
th
at
an
ap
pro
pri
ate
leve
l of
ma
inte
na
nce
is b
ein
g c
arr
ied
ou
t a
nd
th
at
the
ab
ility
to
ach
ieve
se
rvic
e o
bje
ctiv
es
an
d t
he
se
rvic
e c
ap
ab
ility
of
the
ass
ets
is
no
t b
ein
g c
om
pro
mis
ed
.
Ma
inte
na
nce
pro
gra
mm
es
sho
uld
be
su
bje
ct t
o s
yst
em
ati
c d
eci
sio
n-
ma
kin
g p
roce
sse
s to
op
tim
ise
th
ese
pro
gra
mm
es
Ro
ad
ing
AM
Ps
sho
uld
in
corp
ora
te t
he
NZ
TA
Bu
sin
ess
Ca
se
Ap
pro
ach
to
en
suri
ng
ap
pro
pri
ate
an
d c
ost
eff
ect
ive
ma
inte
na
nce
pro
gra
mm
es.
Th
ere
sh
ou
ld b
e a
cle
ar
lin
e o
f si
gh
t fr
om
th
e m
ain
ten
an
ce
pro
gra
mm
es
in t
he
AM
P t
o t
he
fin
an
cia
l pro
gra
mm
es
in t
he
LT
P.
Th
e r
ea
son
s a
nd
co
nse
qu
en
ces
of
an
y in
con
sist
en
cie
s b
etw
ee
n t
he
AM
P a
nd
th
e L
TP
sh
ou
ld b
e s
tate
d
Op
era
tio
n &
Ma
inte
na
nce
of
Ass
ets
is s
et
ou
t in
Se
ctio
n 6
.8.
Th
e p
urp
ose
of
ass
et
op
era
tio
n a
nd
ma
inte
na
nce
is
cle
arl
y se
t o
ut.
Th
ere
are
de
fin
ed
ma
inte
na
nce
str
ate
gie
s b
ase
d o
n t
he
cri
tica
lity
of
ass
ets
.
It i
s im
po
rta
nt
tha
t u
tili
tie
s a
re o
pe
rate
d c
orr
ect
ly i
n a
cco
rda
nce
wit
h t
he
de
sig
ne
r’s
inte
nti
on
s. O
pe
rati
on
an
d m
ain
ten
an
ce o
f ke
y
wa
ste
wa
ter
uti
liti
es
sho
uld
be
ca
rrie
d o
ut
in a
cco
rda
nce
wit
h d
efi
ne
d p
roce
du
res
wh
ich
are
do
cum
en
ted
in o
pe
rati
on
s m
an
ua
ls.
It
is
un
cle
ar
wh
eth
er
the
re a
re o
pe
rati
on
s m
an
ua
ls f
or
wa
ste
wa
ter
uti
liti
es.
O
pe
rati
on
s m
an
ua
ls a
lso
pro
vid
e a
ba
sis
for
au
dit
s to
be
ca
rrie
d
ou
t to
en
sure
uti
litie
s a
re b
ein
g o
pe
rate
d a
nd
ma
inta
ine
d c
orr
ect
ly.
Ta
ble
20
pro
vid
es
a 5
ye
ar
fore
cast
of
op
era
tio
ns
an
d m
ain
ten
an
ce c
ost
s.
Th
is a
pp
ea
rs t
o b
e a
t va
ria
nce
wit
h t
he
30
ye
ar
op
era
tio
na
l b
ud
ge
t se
t o
ut
in T
ab
le E
1
Ide
ally
th
e A
MP
wo
uld
pro
vid
e a
dd
itio
na
l co
mm
en
tary
on
th
e b
asi
s o
f th
e j
ust
ific
ati
on
fo
r th
e e
xpe
nd
itu
re f
ore
cast
s in
Ta
ble
21
. T
he
Op
era
tio
n &
Ma
inte
na
nce
of
Ass
ets
se
ctio
n o
f th
e A
MP
sh
ou
ld e
xpla
in “
this
is
wh
at
we
ne
ed
to
do
(a
nd
wh
y)
an
d t
he
se a
re t
he
co
sts
ari
sin
g f
rom
th
at”
.
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-1
4
Such
a c
om
me
nta
ry m
igh
t b
e a
lon
g t
he
fo
llo
win
g g
en
era
l lin
es:
“Th
e b
ud
ge
t h
as
be
en
de
rive
d f
rom
his
tori
c co
sts
tha
t h
ave
be
en
est
ab
lish
ed
as
be
ing
su
ffic
ien
t to
ca
rry
ou
t th
e m
ain
ten
an
ce a
nd
op
era
tio
n p
rog
ram
me
an
d w
hic
h h
ave
be
en
am
en
de
d a
s n
ece
ssa
ry t
o a
llo
w f
or
cha
ng
es
in m
an
ag
em
en
t a
ctiv
itie
s a
nd
pra
ctic
es.
Th
e
fore
cast
fo
r e
xpe
nd
itu
re i
s b
ase
d o
n a
ssu
mp
tio
ns
tha
t:
·
Th
e o
ve
rall
co
nd
itio
n o
f th
e n
etw
ork
wil
l n
ot
cha
ng
e s
ign
ific
an
tly o
ve
r th
e n
ext
15
ye
ars
(se
e r
en
ew
al
stra
teg
ies)
.
·
Ext
en
sio
ns
of
the
wa
ste
wa
ter
syst
em
wil
l re
pre
sen
t o
nly
a s
ma
ll p
rop
ort
ion
of
the
en
tire
sy
ste
m (
see
de
ma
nd
pro
ject
ion
s).
·
Th
e l
eve
l o
f m
ain
ten
an
ce r
eq
uir
ed
wil
l n
ot
incr
ea
se (
an
d m
ay d
ecr
ea
se),
re
fle
ctin
g a
n i
ncr
ea
se i
n t
he
ove
rall
co
nd
itio
n o
f th
e
wa
ste
wa
ter
ne
two
rk a
s a
re
sult
of
the
ass
et
ren
ew
al p
rog
ram
me
.
·
Th
ere
wil
l b
e a
sig
nif
ica
nt
incr
ea
se i
n t
he
pri
ce o
f th
e o
pe
rati
on
an
d m
ain
ten
an
ce c
on
tra
ct w
he
n i
t is
co
mp
eti
tive
ly r
e-t
en
de
red
.
(th
is r
efl
ect
s o
ur
ass
ess
me
nt
of
the
ma
rke
t fo
r th
is t
yp
e o
f w
ork
)”.
O
pp
ort
un
itie
s fo
r Im
pro
ve
me
nt
1
3.
En
sure
th
e c
orr
ect
ma
inte
na
nce
an
d o
pe
rati
on
of
all
sig
nif
ica
nt
wa
ste
wa
ter
uti
litie
s is
do
cum
en
ted
in o
pe
rati
on
s m
an
ua
ls
14
. E
nsu
re t
he
re is
a c
lea
r li
ne
of
sig
ht
fro
m t
he
fin
an
cia
l fo
reca
sts
in t
he
op
era
tio
ns
an
d m
ain
ten
an
ce p
rog
ram
me
to
th
e c
on
soli
da
ted
fin
an
cia
l pro
ject
ion
s in
Ap
pe
nd
ix E
to
th
e f
ina
nci
als
in
th
e p
ub
lish
ed
LT
P.
15
. P
rovi
de
ad
dit
ion
al c
om
me
nta
ry j
ust
ifyi
ng
th
e b
ud
ge
ts a
risi
ng
fro
m t
he
ma
inte
na
nce
an
d o
pe
rati
on
s p
rog
ram
me
s.
0 -
In
no
cen
t 1
- A
wa
re
2 -
De
ve
lop
ing
3 -
Fu
lly
me
ets
re
qu
ire
me
nts
4
- E
xce
ed
s re
qu
ire
me
nts
Th
e A
MP
do
es
no
t d
em
on
stra
te a
ny
aw
are
ne
ss o
f th
is r
eq
uir
em
en
t
Th
e A
MP
do
es
no
t cu
rre
ntl
y a
dd
ress
this
re
qu
ire
me
nt
(or
cove
rs it
in a
min
ima
l wa
y) b
ut
de
mo
nst
rate
s a
n
inte
nt
to p
rog
ress
it
Th
e A
MP
pa
rtly
co
mp
lie
s w
ith
go
od
ind
ust
ry p
ract
ice
an
d d
em
on
stra
tes
an
inte
nt
to a
chie
ve f
ull
co
mp
lian
ce w
ith
go
od
ind
ust
ry p
ract
ice
Th
e A
MP
co
mp
lies
wit
h g
oo
d in
du
stry
pra
ctic
e
Th
e A
MP
exc
ee
ds
com
plia
nce
wit
h g
oo
d
ind
ust
ry p
ract
ice
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-1
5
Ass
ess
me
nt
Ite
m 7
Ju
stif
ica
tio
n f
or
ass
et
ren
ew
al
pro
gra
mm
e
S
core
3
Wh
y i
s th
is i
mp
ort
an
t?
O
ur
Fin
din
gs
Ass
et
Re
ne
wa
l Pro
gra
mm
es
are
re
lied
up
on
as
a s
ou
rce
of
inp
uts
to
the
Co
un
cil’
s lo
ng
te
rm f
ina
nci
al
pla
nn
ing
an
d t
he
Co
un
cil
Lon
g
Te
rm P
lan
. T
he
y sh
ou
ld p
rovi
de
co
nfi
de
nce
th
at
an
op
tim
um
le
vel
of
ass
et
ren
ew
al i
s b
ein
g c
arr
ied
ou
t w
hic
h w
ill m
ain
tain
an
acc
ep
tab
le l
eve
l of
serv
ice
ca
pa
bil
ity
of
the
ass
et
syst
em
s, w
hile
ma
xim
isin
g t
he
va
lue
to
be
ob
tain
ed
fro
m in
vest
me
nt
in t
he
ass
ets
,
an
d t
ha
t a
sse
t re
ne
wa
l p
rog
ram
me
s a
re c
ost
eff
ect
ive
.
Re
ne
wa
l pro
gra
mm
es
sho
uld
be
su
bje
ct t
o s
yste
ma
tic
de
cisi
on
-
ma
kin
g p
roce
sse
s (O
DM
) to
op
tim
ise
th
ese
pro
gra
mm
es.
Ro
ad
ing
AM
Ps
sho
uld
in
corp
ora
te t
he
NZ
TA
Bu
sin
ess
Ca
se
Ap
pro
ach
to
en
suri
ng
ap
pro
pri
ate
an
d c
ost
eff
ect
ive
ass
et
ren
ew
al
pro
gra
mm
e.
Th
ere
sh
ou
ld b
e a
cle
ar
lin
e o
f si
gh
t fr
om
th
e a
sse
t re
ne
wa
l
pro
gra
mm
es
in t
he
AM
P t
o t
he
fin
an
cia
l pro
gra
mm
es
in t
he
LT
P.
Th
e r
ea
son
s a
nd
co
nse
qu
en
ces
of
an
y in
con
sist
en
cie
s b
etw
ee
n t
he
AM
P a
nd
th
e L
TP
sh
ou
ld b
e s
tate
d
Th
e r
en
ew
al o
f a
sse
ts is
co
vere
d i
n 6
.9.
Th
e r
en
ew
al p
rog
ram
me
s is
de
term
ine
d f
rom
co
nsi
de
rati
on
of
crit
ica
lity,
co
nd
itio
n,
an
d a
sse
t
pe
rfo
rma
nce
.
Th
ere
is a
ve
ry g
oo
d a
pp
roa
ch t
o p
rio
riti
sin
g a
sse
t re
ne
wa
ls s
et
ou
t in
Fig
ure
29
ba
sed
on
ag
e,
dia
me
ter
an
d c
riti
calit
y.
Fig
ure
28
se
ts o
ut
the
re
ma
inin
g l
ife
pro
file
of
the
wa
ste
wa
ter
pip
e n
etw
ork
. T
his
ap
pe
ars
to
ind
ica
te t
ha
t a
n a
vera
ge
lon
g t
erm
exp
en
dit
ure
on
re
ne
wa
ls o
f th
e o
rde
r o
f a
bo
ut
$1
.5m
an
nu
ally
sh
ou
ld b
e s
uff
icie
nt
to s
ust
ain
th
a n
etw
ork
.
Ta
ble
23
se
ts o
ut
a 5
ye
ar
fore
cast
of
wa
ste
wa
ter
ren
ew
als
.
Th
is a
pp
ea
rs t
o b
e a
t va
ria
nce
wit
h t
he
30
ye
ar
ren
ew
als
bu
dg
et
set
ou
t in
Ta
ble
E2
Fig
ure
32
se
ts o
ut
a 3
0 y
ea
r re
ne
wa
l pro
ject
ion
fo
r th
e p
rin
cip
al a
sse
t g
rou
ps
an
d c
om
pa
res
this
wit
h d
ep
reci
ati
on
. T
his
ap
pe
ars
to
sh
ow
a
clo
ser
reco
nci
liati
on
wit
h T
ab
le 2
3 t
ha
n w
ith
Ta
ble
E2
.
As
wo
uld
be
exp
ect
ed
pro
po
sed
exp
en
dit
ure
on
re
ne
wa
ls is
sig
nif
ica
ntl
y a
t va
ria
nce
wit
h d
ep
reci
ati
on
. W
hile
th
is s
imp
ly r
efl
ect
s th
e
con
dit
ion
an
d r
em
ain
ing
life
pro
file
s o
f th
e a
sse
ts,
som
e a
dd
itio
na
l co
mm
en
tary
ab
ou
t th
is v
ari
an
ce i
s d
esi
rab
le t
o d
isp
el
pe
rce
pti
on
s th
at
an
insu
ffic
ien
t le
vel o
f re
ne
wa
ls i
s p
rop
ose
d.
Th
is i
s a
n is
sue
th
at
ha
s b
ee
n r
ais
ed
by
Au
dit
Ne
w Z
ea
lan
d in
au
dit
s o
f o
the
r te
rrit
ori
al
au
tho
riti
es
an
d s
ho
uld
be
ad
dre
sse
d p
roa
ctiv
ely
in t
he
AM
P
O
pp
ort
un
itie
s fo
r Im
pro
ve
me
nt
1
6.
Pro
vid
e a
dd
itio
na
l co
mm
en
tary
on
th
e v
ari
an
ce b
etw
ee
n d
ep
reci
ati
on
an
d t
he
ass
et
ren
ew
al p
roje
ctio
n t
o p
rovi
de
ass
ura
nce
th
at
an
ap
pro
pri
ate
leve
l of
ren
ew
als
is
pla
nn
ed
wh
ich
will
ma
inta
in t
he
ove
rall
serv
ice
ca
pa
bil
ity
of
the
wa
ste
wa
ter
infr
ast
ruct
ure
.
0 -
In
no
cen
t 1
- A
wa
re
2 -
De
ve
lop
ing
3
- F
ull
y m
ee
ts r
eq
uir
em
en
ts
4 -
Ex
cee
ds
req
uir
em
en
ts
Th
e A
MP
do
es
no
t d
em
on
stra
te a
ny
aw
are
ne
ss o
f th
is r
eq
uir
em
en
t
Th
e A
MP
do
es
no
t cu
rre
ntl
y a
dd
ress
this
re
qu
ire
me
nt
(or
cove
rs it
in a
min
ima
l wa
y) b
ut
de
mo
nst
rate
s a
n
inte
nt
to p
rog
ress
it
Th
e A
MP
pa
rtly
co
mp
lie
s w
ith
go
od
ind
ust
ry p
ract
ice
an
d d
em
on
stra
tes
an
inte
nt
to a
chie
ve f
ull
co
mp
lian
ce w
ith
go
od
ind
ust
ry p
ract
ice
Th
e A
MP
co
mp
lies
wit
h g
oo
d in
du
stry
pra
ctic
e
Th
e A
MP
exc
ee
ds
com
plia
nce
wit
h g
oo
d
ind
ust
ry p
ract
ice
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-1
6
Ass
ess
me
nt
Ite
m 8
Ju
stif
ica
tio
n f
or
ass
et
de
ve
lop
me
nt
pro
gra
mm
e
S
core
2
-3
Wh
y i
s th
is i
mp
ort
an
t?
O
ur
Fin
din
gs
Ass
et
De
velo
pm
en
t P
rog
ram
me
s a
re r
eli
ed
up
on
as
a s
ou
rce
of
inp
uts
to
th
e C
ou
nci
l’s
lon
g t
erm
fin
an
cia
l p
lan
nin
g a
nd
th
e C
ou
nci
l
Lon
g T
erm
Pla
n.
Ass
et
De
velo
pm
en
t P
rog
ram
me
s cl
ose
cu
rre
nt
an
d
pro
ject
ed
se
rvic
e g
ap
s.
Th
ey
sho
uld
pro
vid
e c
on
fid
en
ce t
ha
t a
n
acc
ep
tab
le l
eve
l of
serv
ice
ca
pa
bil
ity
will
be
ma
inta
ine
d i
nto
th
e
futu
re.
Ass
et
de
velo
pm
en
t p
rog
ram
me
s sh
ou
ld b
e s
ub
ject
to
sys
tem
ati
c
de
cisi
on
-ma
kin
g p
roce
sse
s (O
DM
) to
op
tim
ise
th
ese
pro
gra
mm
es.
Alt
ho
ug
h t
he
ra
te o
f cl
osi
ng
se
rvic
e g
ap
s is
a p
olit
ica
l de
cisi
on
an
d i
s
sub
ject
to
co
mp
eti
ng
de
ma
nd
s fo
r C
ou
nci
l fu
nd
ing
, it
sh
ou
ld b
e
no
ted
in t
he
pla
ns.
Ro
ad
ing
AM
Ps
sho
uld
in
corp
ora
te t
he
NZ
TA
Bu
sin
ess
Ca
se
Ap
pro
ach
to
en
suri
ng
ap
pro
pri
ate
an
d c
ost
eff
ect
ive
ass
et
de
velo
pm
en
t p
rog
ram
me
.
Th
ere
sh
ou
ld b
e a
cle
ar
lin
e o
f si
gh
t fr
om
th
e a
sse
t d
ev
elo
pm
en
t
pro
gra
mm
es
in t
he
AM
P t
o t
he
fin
an
cia
l pro
gra
mm
es
in t
he
LT
P.
Th
e r
ea
son
s a
nd
co
nse
qu
en
ces
of
an
y in
con
sist
en
cie
s b
etw
ee
n t
he
AM
P a
nd
th
e L
TP
sh
ou
ld b
e s
tate
d
All
ass
et
de
velo
pm
en
t p
rop
osa
ls s
ho
uld
be
cle
arl
y lin
ke
d t
o a
cu
rre
nt
or
an
tici
pa
ted
se
rvic
e g
ap
. T
his
ma
y b
e a
cu
sto
me
r o
r te
chn
ica
l
serv
ice
ga
p a
nd
sh
ou
ld id
ea
lly r
ela
te t
o a
se
rvic
e s
tan
da
rd t
ha
t is
de
fin
ed
in t
he
AM
P.
Th
e r
ea
son
fo
r th
is is
th
at
the
pu
rpo
se o
f a
sse
t d
eve
lop
me
nt
is t
o i
ncr
ea
se s
erv
ice
ca
pa
bili
ty.
Th
ere
wo
uld
be
no
ne
ed
to
in
cre
ase
se
rvic
e
cap
ab
ility
if t
he
re w
as
no
t (o
r n
ot
exp
ect
ed
to
be
) a
se
rvic
e g
ap
. I
f le
vels
of
serv
ice
are
lin
ked
ba
ck t
o C
om
mu
nit
y O
utc
om
es/
Co
un
cil
Ob
ject
ive
s th
en
by
link
ing
de
velo
pm
en
t p
rop
osa
ls t
o s
erv
ice
ga
ps
it f
ollo
ws
tha
t th
ese
pro
po
sals
wil
l, if
ad
op
ted
co
ntr
ibu
te t
o t
he
ach
ieve
me
nt
of
Co
mm
un
ity
Ou
tco
me
s, w
hic
h is
th
e i
nte
nt
of
the
LG
A 2
00
2.
Th
ere
is a
dis
cuss
ion
on
se
rvic
e g
ap
s in
Se
ctio
n 4
.4.3
of
the
AM
P.
Se
rvic
e g
ap
s a
pp
ea
r to
re
late
to
·
Infi
ltra
tio
n/i
nfl
ow
·
Tru
nk
ma
in c
ap
aci
ty c
on
stra
ints
.
Som
e d
eve
lop
me
nt
pro
ject
s in
6.1
0.3
– D
eve
lop
me
nt
Pro
gra
mm
e r
efl
ect
tru
nk
ma
in c
ap
aci
ty c
on
stra
ints
. T
he
se
rvic
e g
ap
s to
wh
ich
oth
er
pro
ject
s re
late
is u
ncl
ea
r.
Th
e d
eve
lop
me
nt
stra
teg
y d
esc
rib
ed
in
6.1
0.2
is t
o p
rovi
de
fo
r th
e p
rog
ress
ive
up
gra
din
g o
f a
sse
ts t
o e
nsu
re f
utu
re d
em
an
d a
nd
ch
an
gin
g
serv
ice
sta
nd
ard
s a
re a
chie
ved
.
An
eco
no
mic
ap
pra
isa
l of
pro
po
sed
pro
ject
s is
re
qu
ire
d u
sin
g c
ost
/be
ne
fit
an
aly
sis
tech
niq
ue
s w
hic
h t
ake
into
acc
ou
nt:
·
Ca
pit
al c
ost
s
·
An
y ch
an
ge
in n
et
an
nu
al o
pe
rati
ng
co
sts
·
An
y ch
an
ge
in a
nn
ua
l ma
inte
na
nce
re
qu
ire
me
nts
·
An
y sa
lva
ge
va
lue
of
exi
stin
g a
sse
ts o
r co
mp
on
en
ts.
A P
roje
ct E
xecu
tio
n P
lan
fo
r is
re
qu
ire
d f
or
pri
or
ap
pro
val b
y th
e m
an
ag
em
en
t te
am
.
Sch
ed
ule
10
of
the
LG
A 2
00
2 r
eq
uir
es
cap
ita
l de
velo
pm
en
t e
xpe
nd
itu
re t
o b
e i
de
nti
fie
d a
s b
ein
g r
eq
uir
ed
to
se
rvic
e g
ap
s a
risi
ng
fro
m a
ne
ed
to
:
·
me
et
ad
dit
ion
al d
em
an
d f
or
an
act
ivit
y (g
row
th)
·
imp
rove
th
e l
eve
l of
serv
ice
.
Th
e D
eve
lop
me
nt
Pro
gra
mm
e B
ud
ge
t in
ta
ble
24
sh
ow
s th
e p
rop
ose
d l
eve
ls o
f e
xpe
nd
itu
re i
n e
ach
ca
teg
ory
.
O
pp
ort
un
itie
s fo
r Im
pro
ve
me
nt
1
7.
Pro
vid
e a
cle
are
r li
nk
be
twe
en
th
e p
rop
ose
d d
eve
lop
me
nt
pro
gra
mm
e a
nd
cu
rre
nt
an
d p
roje
cte
d g
ap
s b
etw
ee
n t
arg
et
LOS
sho
wn
in
Sect
ion
4 o
f th
e A
MP
an
d c
urr
en
t se
rvic
e c
ap
ab
ilit
y.
0 -
In
no
cen
t 1
- A
wa
re
2 -
De
ve
lop
ing
3 -
Fu
lly
me
ets
re
qu
ire
me
nts
4
- E
xce
ed
s re
qu
ire
me
nts
Th
e A
MP
do
es
no
t d
em
on
stra
te a
ny
aw
are
ne
ss o
f th
is r
eq
uir
em
en
t
Th
e A
MP
do
es
no
t cu
rre
ntl
y a
dd
ress
this
re
qu
ire
me
nt
(or
cove
rs it
in a
min
ima
l wa
y) b
ut
de
mo
nst
rate
s a
n
inte
nt
to p
rog
ress
it
Th
e A
MP
pa
rtly
co
mp
lie
s w
ith
go
od
ind
ust
ry p
ract
ice
an
d d
em
on
stra
tes
an
inte
nt
to a
chie
ve f
ull
co
mp
lian
ce w
ith
go
od
ind
ust
ry p
ract
ice
Th
e A
MP
co
mp
lies
wit
h g
oo
d in
du
stry
pra
ctic
e
Th
e A
MP
exc
ee
ds
com
plia
nce
wit
h g
oo
d
ind
ust
ry p
ract
ice
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-1
7
Ass
ess
me
nt
Ite
m 9
D
ata
Sco
re
2
Wh
y i
s th
is i
mp
ort
an
t?
O
ur
Fin
din
gs
Da
ta s
up
po
rts
fact
ba
sed
de
cisi
on
ma
kin
g,
key
ass
et
ma
na
ge
me
nt
pro
cess
es
an
d p
erf
orm
an
ce m
ea
sure
me
nt.
It
is im
po
rta
nt
tha
t
org
an
isa
tio
ns
ide
nti
fy t
he
da
ta t
he
y re
qu
ire
fo
r th
ese
pu
rpo
ses,
th
e
qu
alit
y o
f d
ata
th
ey
req
uir
e,
wh
ere
th
ey
will
ob
tain
th
e d
ata
, a
nd
ho
w t
he
y w
ill m
an
ag
e a
nd
re
trie
ve
th
e d
ata
as
req
uir
ed
.
Th
ey
sho
uld
als
o id
en
tify
th
e q
ua
lity
of
exi
stin
g d
ata
re
lati
ve t
o w
ha
t is
req
uir
ed
an
d p
ut
in p
lace
a p
rog
ram
me
to
imp
rove
da
ta (
wh
ere
da
ta q
ua
lity
ga
ps
exi
st).
Th
is i
ncl
ud
es
da
ta o
n t
he
ass
ets
, th
eir
con
dit
ion
an
d p
erf
orm
an
ce a
s w
ell
as
oth
er
da
ta n
ee
de
d t
o s
up
po
rt
bu
sin
ess
pro
cess
es
an
d d
eci
sio
n m
aki
ng
.
Th
e q
ua
lity
of
ass
et
ma
na
ge
me
nt
can
on
ly e
ver
be
as
go
od
as
the
qu
alit
y o
f th
e u
nd
erl
yin
g d
ata
.
Da
ta s
up
po
rts
the
en
tire
ass
et
ma
na
ge
me
nt
pro
cess
.
Ide
ally
th
ere
wo
uld
be
an
ass
ess
me
nt
ma
de
of
the
da
ta r
eq
uir
ed
to
su
pp
ort
ke
y a
sse
t m
an
ag
em
en
t a
nd
de
cisi
on
ma
kin
g p
roce
sse
s
(in
clu
din
g m
on
ito
rin
g o
f p
erf
orm
an
ce),
to
ge
the
r w
ith
th
e r
eq
uir
ed
qu
alit
y o
f th
is d
ata
, d
ata
so
urc
es
an
d d
ata
co
llect
ion
me
cha
nis
ms
an
d
arr
an
ge
me
nts
fo
r d
ata
ma
na
ge
me
nt,
re
trie
val
an
d a
na
lysi
s.
An
aly
sis
of
ga
ps
be
twe
en
th
e d
esi
red
an
d c
urr
en
t st
ate
of
ea
ch d
ata
ite
m
wo
uld
th
en
fo
rm b
asi
s o
f d
ata
imp
rove
me
nt
pro
gra
mm
e.
A s
um
ma
ry o
f th
is a
sse
ssm
en
t w
ou
ld b
e i
ncl
ud
ed
in t
he
AM
P.
Sect
ion
9.3
se
ts o
ut
an
ass
ess
me
nt
of
con
fid
en
ce in
ass
et
da
ta u
sed
as
a b
asi
s fo
r th
e f
ina
nci
al f
ore
cast
s. T
his
in
dic
ate
s a
re
lati
ve
ly h
igh
leve
l of
con
fid
en
ce i
n t
his
da
ta (
B-
relia
ble
ove
rall)
.
It is
als
o n
ote
d t
ha
t th
ere
do
es
no
t a
pp
ea
r to
be
an
ass
ess
me
nt
of
con
fid
en
ce in
un
it r
ate
da
ta w
hic
h a
lso
fe
ed
s in
to c
on
fid
en
ce in
th
e
cap
ita
l pro
gra
mm
es.
O
pp
ort
un
itie
s fo
r Im
pro
ve
me
nt
1
8.
Ad
d a
su
bse
ctio
n o
r a
pp
en
dix
on
da
ta m
an
ag
em
en
t w
hic
h i
de
nti
fie
s th
e d
ata
re
qu
ire
d t
o s
up
po
rt k
ey
ass
et
ma
na
ge
me
nt
an
d
de
cisi
on
ma
kin
g p
roce
sse
s, r
eq
uir
ed
da
ta q
ua
lity,
da
ta s
ou
rce
s, d
ata
co
llect
ion
me
cha
nis
ms,
da
ta m
an
ag
em
en
t a
rra
ng
em
en
ts a
nd
wh
ich
inco
rpo
rate
s a
da
ta i
mp
rove
me
nt
pla
n (
if n
ece
ssa
ry)
to c
lose
an
y g
ap
s b
etw
ee
n c
urr
en
t a
nd
ta
rge
t d
ata
ava
ilab
ility
an
d q
ua
lity
.
0 -
In
no
cen
t 1
- A
wa
re
2 -
De
ve
lop
ing
3
- F
ull
y m
ee
ts r
eq
uir
em
en
ts
4 -
Ex
cee
ds
req
uir
em
en
ts
Th
e A
MP
do
es
no
t d
em
on
stra
te a
ny
aw
are
ne
ss o
f th
is r
eq
uir
em
en
t
Th
e A
MP
do
es
no
t cu
rre
ntl
y a
dd
ress
this
re
qu
ire
me
nt
(or
cove
rs it
in a
min
ima
l wa
y) b
ut
de
mo
nst
rate
s a
n
inte
nt
to p
rog
ress
it
Th
e A
MP
pa
rtly
co
mp
lie
s w
ith
go
od
ind
ust
ry p
ract
ice
an
d d
em
on
stra
tes
an
inte
nt
to a
chie
ve f
ull
co
mp
lian
ce w
ith
go
od
ind
ust
ry p
ract
ice
Th
e A
MP
co
mp
lies
wit
h g
oo
d in
du
stry
pra
ctic
e
Th
e A
MP
exc
ee
ds
com
plia
nce
wit
h g
oo
d
ind
ust
ry p
ract
ice
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-1
8
Ass
ess
me
nt
Ite
m 1
0
Co
nfi
de
nce
in
pro
gra
mm
es
S
core
2
-3
Wh
y i
s th
is i
mp
ort
an
t?
O
ur
Fin
din
gs
Pro
gra
mm
es
fro
m A
MP
s a
re in
ten
de
d t
o s
up
po
rt t
he
su
sta
ina
ble
lon
g t
erm
pro
visi
on
of
serv
ice
s.
Th
ese
pro
gra
mm
es
are
re
lied
up
on
as
a s
ou
rce
of
inp
uts
to
th
e C
ou
nci
l’s
lon
g t
erm
fin
an
cia
l p
lan
nin
g
an
d t
he
Co
un
cil L
on
g T
erm
Pla
n.
It
is t
he
refo
re im
po
rta
nt
tha
t a
ny
issu
es
wit
h c
on
fid
en
ce i
n t
he
se p
rog
ram
me
s a
re k
no
wn
an
d
dis
clo
sed
.
Th
is t
ypic
ally
in
volv
es
ide
nti
fyin
g t
he
inp
uts
to
th
e p
rog
ram
me
s a
nd
ma
kin
g a
n a
sse
ssm
en
t o
f th
e a
ccu
racy
of
the
se i
np
uts
as
a b
asi
s fo
r
est
ima
tin
g c
on
fid
en
ce in
th
e p
rog
ram
me
s. T
he
ass
ess
me
nt
sho
uld
be
do
cum
en
ted
.
Sect
ion
9.4
se
ts o
ut
an
ass
ess
me
nt
of
the
Re
liab
ility
of
Fin
an
cia
l Fo
reca
sts.
It
wo
uld
be
exp
ect
ed
th
at
Sect
ion
9.4
wo
uld
be
de
rive
d f
rom
Sect
ion
9.3
– C
on
fid
en
ce L
eve
ls.
T
he
lin
kag
e b
etw
ee
n S
ect
ion
9.4
an
d S
ect
ion
9.3
is u
ncl
ea
r fr
om
th
e A
MP
.
It is
als
o n
ote
d t
ha
t th
ere
do
es
no
t a
pp
ea
r to
be
an
ass
ess
me
nt
of
con
fid
en
ce in
un
it r
ate
da
ta w
hic
h w
ou
ld a
lso
aff
ect
co
nfi
de
nce
in
th
e
cap
ita
l pro
gra
mm
es.
Id
ea
lly t
he
re w
ou
ld a
lso
be
an
ass
ess
me
nt
of
con
fid
en
ce o
f o
the
r ke
y p
roje
ctio
ns
in t
he
AM
P s
uch
as
the
de
ma
nd
pro
ject
ion
.
In S
ect
ion
9.4
“R
eli
ab
ilit
y o
f F
ina
nci
al
Fo
reca
sts”
ass
ess
me
nts
are
ma
de
of
the
re
lia
bil
ity
of
Ma
inte
na
nce
an
d R
en
ew
al F
ore
cast
s a
nd
of
De
velo
pm
en
t Fo
reca
sts.
T
he
co
ncl
usi
on
s a
re t
ha
t sh
ort
to
me
diu
m t
erm
fo
reca
sts
are
ge
ne
rally
co
nsi
de
red
“re
lia
ble
” w
ith
un
cert
ain
ty
incr
ea
sin
g o
ver
the
lon
ge
r te
rm.
It is
un
cle
ar
ho
w t
he
ass
ess
me
nts
of
con
fid
en
ce le
vels
in d
ata
in 9
.3 f
ee
d in
to t
he
ass
ess
me
nts
of
con
fid
en
ce in
fo
reca
sts
in 9
.4 o
r w
ha
t
leve
l of
an
aly
sis
ha
s b
ee
n c
arr
ied
ou
t to
re
ach
th
e c
on
clu
sio
ns
in S
ect
ion
9.4
. T
he
re n
ee
ds
to b
e a
n a
ud
it t
rail
be
hin
d t
he
se a
sse
ssm
en
ts o
f
relia
bil
ity.
It is
use
ful t
o t
rack
act
ua
l va
ria
tio
ns
fro
m p
rog
ram
me
s o
ver
tim
e a
s a
“re
ali
ty c
he
ck”
on
ass
ess
me
nts
of
con
fid
en
ce in
th
e p
rog
ram
me
s.
If
for
exa
mp
le t
he
pro
gra
mm
es
are
co
nsi
ste
ntl
y co
min
g in
wit
hin
+/-
10
% o
f p
lan
th
en
th
is w
ou
ld c
on
firm
th
at
an
ass
ess
me
nt
of
“re
lia
ble
” is
rea
son
ab
le.
O
pp
ort
un
itie
s fo
r Im
pro
ve
me
nt
1
9.
Imp
rove
th
e li
nka
ge
be
twe
en
ass
ess
me
nts
of
con
fid
en
ce i
n d
ata
an
d a
sse
ssm
en
ts o
f re
liab
ilit
y in
pro
gra
mm
es
an
d p
rovi
de
ap
pro
pri
ate
an
aly
sis
to j
ust
ify
the
ass
ess
me
nts
of
con
fid
en
ce i
n p
roje
ctio
ns
an
d p
rog
ram
me
s. (
the
act
ua
l an
aly
sis
cou
ld b
e a
pp
en
de
d
or
he
ld o
uts
ide
th
e p
lan
)
20
. T
rack
his
tori
c va
ria
tio
ns
be
twe
en
pro
gra
mm
es
an
d “
act
ua
ls”
to p
rovi
de
a “
rea
lity
ch
eck
” o
n a
sse
ssm
en
ts o
f co
nfi
de
nce
in
th
e
pro
gra
mm
es
0 -
In
no
cen
t 1
- A
wa
re
2 -
De
ve
lop
ing
3 -
Fu
lly
me
ets
re
qu
ire
me
nts
4
- E
xce
ed
s re
qu
ire
me
nts
Th
e A
MP
do
es
no
t d
em
on
stra
te a
ny
aw
are
ne
ss o
f th
is r
eq
uir
em
en
t
Th
e A
MP
do
es
no
t cu
rre
ntl
y a
dd
ress
this
re
qu
ire
me
nt
(or
cove
rs it
in a
min
ima
l wa
y) b
ut
de
mo
nst
rate
s a
n
inte
nt
to p
rog
ress
it
Th
e A
MP
pa
rtly
co
mp
lie
s w
ith
go
od
ind
ust
ry p
ract
ice
an
d d
em
on
stra
tes
an
inte
nt
to a
chie
ve f
ull
co
mp
lian
ce w
ith
go
od
ind
ust
ry p
ract
ice
Th
e A
MP
co
mp
lies
wit
h g
oo
d in
du
stry
pra
ctic
e
Th
e A
MP
exc
ee
ds
com
plia
nce
wit
h g
oo
d
ind
ust
ry p
ract
ice
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-1
9
Ass
ess
me
nt
Ite
m 1
1
Pe
rfo
rma
nce
Me
asu
rem
en
t
Sco
re
2
Wh
y i
s th
is i
mp
ort
an
t?
O
ur
Fin
din
gs
AM
Ps
set
ou
t h
ow
org
an
isa
tio
ns
will
wo
rk t
o a
chie
ve t
he
ir a
ctiv
ity
spe
cifi
c a
sse
t m
an
ag
em
en
t o
bje
ctiv
es.
It
is
imp
ort
an
t to
“cl
ose
th
e
loo
p”
an
d m
ea
sure
pe
rfo
rma
nce
re
lati
ve
to
th
ese
ob
ject
ive
s. T
his
incl
ud
es
pe
rfo
rma
nce
re
lati
ve t
o m
an
da
tory
pe
rfo
rma
nce
me
asu
res
req
uir
ed
un
de
r th
e N
on
-Fin
an
cia
l P
erf
orm
an
ce M
ea
sure
s R
ule
s
20
13
Mo
nit
ori
ng
pe
rfo
rma
nce
re
lati
ve t
o o
bje
ctiv
es
he
lps
ide
nti
fy a
rea
s
wh
ere
imp
rove
me
nts
ma
y b
e r
eq
uir
ed
an
d a
rea
s w
he
re
org
an
isa
tio
ns
ma
y b
e o
verp
erf
orm
ing
. T
he
re m
ay
be
sco
pe
fo
r co
st
savi
ng
s in
su
ch a
rea
s.
Mo
nit
ori
ng
pe
rfo
rma
nce
he
lps
org
an
isa
tio
ns
com
pa
re t
he
ir p
erf
orm
an
ce w
ith
th
at
of
com
pa
rab
le o
rga
nis
ati
on
s
By
mo
nit
ori
ng
pe
rfo
rma
nce
ove
r ti
me
org
an
isa
tio
ns
are
ab
le t
o
ide
nti
fy t
ren
ds
wh
ich
ma
y in
dic
ate
a n
ee
d f
or
inte
rve
nti
on
.
Cu
rre
nt
(20
16
/20
17
) p
erf
orm
an
ce (
wh
ere
ava
ilab
le)
is m
on
ito
red
fo
r e
ach
of
the
Cu
sto
me
r Le
vels
of
Serv
ice
in T
ab
le 7
(Se
ctio
n 4
Le
ve
ls o
f
Serv
ice
) a
nd
in A
pp
en
dix
C.
Te
chn
ica
l Pe
rfo
rma
nce
Me
asu
res.
P
erf
orm
an
ce t
arg
ets
are
pro
vid
ed
fo
r e
ach
of
the
ye
ars
20
18
/19
to
20
20
/21
an
d f
or
the
pe
rio
d 2
02
1 t
o 2
02
8.
Cu
rre
nt
pe
rfo
rma
nce
pro
vid
es
a s
na
psh
ot
in t
ime
of
pe
rfo
rma
nce
an
d a
pa
ss/f
ail
ind
ica
tio
n o
f w
he
the
r ta
rge
ts a
re b
ein
g a
chie
ve
d (
an
d b
y
ho
w m
uch
). T
his
is o
f lim
ite
d v
alu
e a
s it
do
es
no
t p
rovi
de
an
in
dic
ati
on
of
pe
rfo
rma
nce
tre
nd
s –
wh
eth
er
it i
s im
pro
vin
g,
sta
yin
g c
on
sta
nt
or
de
clin
ing
, e
xpe
cte
d f
utu
re p
erf
orm
an
ce,
or
ho
w p
erf
orm
an
ce c
om
pa
res
wit
h t
ha
t o
f co
mp
ara
ble
org
an
isa
tio
ns.
Ide
ally
, p
erf
orm
an
ce r
esu
lts
wo
uld
be
pre
sen
ted
in g
rap
hic
al f
orm
wh
ich
sh
ow
s h
isto
ric
pe
rfo
rma
nce
tre
nd
s, c
urr
en
t p
erf
orm
an
ce,
exp
ect
ed
fu
ture
pe
rfo
rma
nce
, p
erf
orm
an
ce t
arg
ets
an
d h
ow
th
ese
are
ch
an
gin
g o
ver
tim
e a
nd
an
in
du
stry
be
nch
ma
rk (
wh
ere
ava
ilab
le).
Pre
sen
tin
g p
erf
orm
an
ce r
esu
lts
in t
his
fo
rm e
na
ble
s m
an
ag
ers
to
qu
ickl
y m
ake
in
form
ed
de
cisi
on
s a
bo
ut
the
ne
ed
fo
r in
terv
en
tio
n a
nd
an
tici
pa
te i
ssu
es
tha
t m
ay
be
de
ve
lop
ing
.
Th
e in
dic
ati
ve
gra
ph
s b
elo
w s
ho
w h
ow
pe
rfo
rma
nce
re
sult
s a
re t
ypic
ally
pre
sen
ted
in
th
is w
ay.
O
nce
sys
tem
s a
re s
etu
p,
rep
ort
ing
pe
rfo
rma
nce
in t
his
wa
y is
no
t o
ne
rou
s.
Ide
ally
th
ere
wo
uld
be
a s
ep
ara
te p
erf
orm
an
ce s
ect
ion
in
th
e A
MP
pre
sen
tin
g p
erf
orm
an
ce in
th
is w
ay.
T
his
will
he
lp r
ea
de
rs m
ake
info
rme
d j
ud
ge
me
nts
ab
ou
t h
ow
th
e a
ctiv
ity
is p
erf
orm
ing
.
As
ind
ica
ted
in
Ass
ess
me
nt
Ite
m 2
, w
he
re t
he
re is
a s
ign
ific
an
t va
ria
tio
n b
etw
ee
n a
ctu
al a
nd
ta
rge
t le
vel o
f p
erf
orm
an
ce o
r if
a
pe
rfo
rma
nce
ta
rge
t h
as
no
t b
ee
n a
chie
ved
th
ere
sh
ou
ld b
e s
om
e f
orm
of
com
me
nta
ry p
rovi
de
d a
s th
is m
ay
ind
ica
te a
ne
ed
fo
r so
me
fo
rm
of
inte
rve
nti
on
.
Re
sult
s w
he
re a
co
mm
en
t o
n t
he
pe
rfo
rma
nce
ach
ieve
d m
ay
be
ap
pro
pri
ate
are
in
dic
ate
d in
th
e t
ab
le b
elo
w:
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-2
0
O
pp
ort
un
itie
s fo
r Im
pro
ve
me
nt
2
1.
Pre
sen
t p
erf
orm
an
ce r
ela
tive
to
cu
sto
me
r LO
S in
in g
rap
hic
al f
orm
in t
he
AM
P w
hic
h s
ho
ws
his
tori
c p
erf
orm
an
ce t
ren
ds,
cu
rre
nt
pe
rfo
rma
nce
, e
xpe
cte
d f
utu
re p
erf
orm
an
ce,
pe
rfo
rma
nce
ta
rge
ts a
nd
ho
w t
he
se a
re c
ha
ng
ing
ove
r ti
me
an
d a
n in
du
stry
be
nch
ma
rk
(wh
ere
ava
ilab
le).
22
. C
on
sid
er
ad
din
g a
se
pa
rate
se
ctio
n o
n p
erf
orm
an
ce t
o t
he
AM
P s
ett
ing
ou
t p
erf
orm
an
ce a
s su
gg
est
ed
in O
FI 2
1 a
bo
ve
23
. P
rovi
de
a c
om
me
nta
ry w
he
n a
pe
rfo
rma
nce
ta
rge
t is
no
t a
chie
ve
d o
r w
he
n t
he
re i
s a
sig
nif
ica
nt
vari
an
ce b
etw
ee
n t
arg
et
an
d a
ctu
al
pe
rfo
rma
nce
.
0 -
In
no
cen
t 1
- A
wa
re
2 -
De
ve
lop
ing
3
- F
ull
y m
ee
ts r
eq
uir
em
en
ts
4 -
Ex
cee
ds
req
uir
em
en
ts
Th
e A
MP
do
es
no
t d
em
on
stra
te a
ny
aw
are
ne
ss o
f th
is r
eq
uir
em
en
t
Th
e A
MP
do
es
no
t cu
rre
ntl
y a
dd
ress
this
re
qu
ire
me
nt
(or
cove
rs it
in a
min
ima
l wa
y) b
ut
de
mo
nst
rate
s a
n
inte
nt
to p
rog
ress
it
Th
e A
MP
pa
rtly
co
mp
lie
s w
ith
go
od
ind
ust
ry p
ract
ice
an
d d
em
on
stra
tes
an
inte
nt
to a
chie
ve f
ull
co
mp
lian
ce w
ith
go
od
ind
ust
ry p
ract
ice
Th
e A
MP
co
mp
lies
wit
h g
oo
d in
du
stry
pra
ctic
e
Th
e A
MP
exc
ee
ds
com
plia
nce
wit
h g
oo
d
ind
ust
ry p
ract
ice
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-2
1
Ass
ess
me
nt
Ite
m 1
2
Su
sta
ina
ble
Fu
nd
ing
Sco
re
1-2
Wh
y i
s th
is i
mp
ort
an
t?
O
ur
Fin
din
gs
Lon
g t
erm
exp
en
dit
ure
pro
ject
ion
s a
re a
fu
nd
am
en
tal p
art
of
AM
Ps.
Th
ese
sh
ou
ld b
e m
atc
he
d b
y a
pro
ject
ion
of
the
leve
l of
fun
din
g
tha
t is
re
qu
ire
d t
o s
ust
ain
th
e a
ctiv
ity
ove
r th
e lo
ng
te
rm.
Th
is i
s
ne
ed
ed
to
“cl
ose
th
e l
oo
p”.
Lo
ng
te
rm f
un
din
g p
roje
ctio
ns
sho
uld
incl
ud
e f
un
din
g t
o c
ove
r o
pe
rati
ng
co
sts,
ass
et
rep
lace
me
nt
(if
de
pre
cia
tio
n f
un
din
g is
use
d f
or
this
pu
rpo
se i
t sh
ou
ld b
e s
uff
icie
nt
to c
ove
r lo
ng
te
rm a
sse
t re
ne
wa
ls),
inte
rest
on
de
bt
tha
t w
ill b
e
ne
ed
ed
to
bri
dg
e p
eri
od
s w
he
n a
ccu
mu
late
d e
xpe
nd
itu
re e
xce
ed
s
acc
um
ula
ted
de
pre
cia
tio
n a
nd
fu
nd
ing
to
se
rvic
e d
eb
t a
sso
cia
ted
wit
h a
dd
itio
na
l ass
ets
. T
he
se f
un
din
g p
roje
ctio
ns
in t
he
AM
Ps
sho
uld
be
pre
pa
red
in
co
nsu
lta
tio
n w
ith
th
e f
ina
nce
ma
na
ge
r.
Th
ese
fu
nd
ing
pro
ject
ion
s sh
ou
ld b
e u
pd
ate
d r
eg
ula
rly
to
ta
ke
acc
ou
nt
of
infl
ati
on
an
d b
e b
ase
d o
n r
ea
listi
c a
sse
t va
lua
tio
ns.
It s
ho
uld
be
po
ssib
le t
o r
eco
nci
le t
he
lon
g t
erm
su
sta
ina
ble
fu
nd
ing
pro
ject
ion
s in
th
e A
MP
s w
ith
fu
nd
ing
pro
vid
ed
th
rou
gh
th
e L
TP
an
d
exp
lan
ati
on
s sh
ou
ld b
e p
rovi
de
d f
or
an
y si
gn
ific
an
t va
ria
nce
s
be
twe
en
th
e t
wo
.
Sect
ion
9.5
of
the
AM
P c
ove
rs t
he
Fu
nd
ing
Po
licy.
T
his
se
ctio
n s
ets
ou
t th
e b
asi
s o
f fu
nd
ing
fo
r th
e d
iffe
ren
t ca
teg
ori
es
of
exp
en
dit
ure
:
·
Op
era
tio
n &
Ma
inte
na
nce
·
Ca
pit
al R
en
ew
al
·
Ca
pit
al D
eve
lop
me
nt
It a
lso
su
mm
ari
ses
the
Co
un
cil’
s a
pp
roa
ch t
o d
eve
lop
me
nt
con
trib
uti
on
s.
Ass
et
ma
na
ge
me
nt
is in
ten
de
d t
o s
up
po
rt t
he
su
sta
ina
ble
lon
g t
erm
pro
visi
on
of
serv
ice
s. T
he
re is
no
ind
ica
tio
n g
ive
n i
n t
he
pla
n o
f
wh
eth
er
the
pro
po
sed
le
vel o
f fu
nd
ing
in t
he
AM
P is
su
ffic
ien
t to
su
sta
in t
he
act
ivit
y o
ver
the
lon
g t
erm
, w
he
the
r it
su
pp
ort
s th
e p
rin
cip
le
of
inte
rge
ne
rati
on
al
eq
uit
y a
nd
if s
ign
ific
an
t ch
an
ge
s in
fu
nd
ing
lev
els
(e
xclu
din
g a
dju
stm
en
ts f
or
infl
ati
on
) w
ill b
e r
eq
uir
ed
in
th
e f
utu
re.
Th
e f
ina
nci
al f
ore
cast
s in
Ap
pe
nd
ix E
se
t o
ut
lon
g t
erm
(3
0 y
ea
r) o
pe
rati
ng
an
d c
ap
ita
l exp
en
dit
ure
pro
ject
ion
s.
Th
ey
do
no
t g
ive
an
y
ind
ica
tio
n o
f th
e f
un
din
g t
ha
t w
ill b
e a
pp
lied
to
th
e A
ctiv
ity
(Ap
art
fro
m a
re
lati
vely
sm
all
am
ou
nt
of
op
era
tio
na
l re
ven
ue
sh
ow
n in
Ta
ble
E1
) o
r w
he
the
r th
e lo
ng
te
rm b
ud
ge
t fo
r th
e A
ctiv
ity
is b
ala
nce
d.
Ide
ally
th
e c
ove
rag
e in
th
e p
lan
of
fun
din
g s
ho
uld
go
be
yon
d t
he
fu
nd
ing
po
licy,
it s
ho
uld
sh
ow
th
e l
on
g t
erm
lev
els
of
fun
din
g t
ha
t w
ill b
e
ne
cess
ary
to
su
sta
in t
he
act
ivit
y o
ver
the
lon
g t
erm
. T
his
will
he
lp h
igh
ligh
t p
oss
ible
fu
ture
fu
nd
ing
pro
ble
ms
(su
ch a
s a
bru
pt
cha
ng
es
in
the
lev
el o
f fu
nd
ing
th
at
will
be
re
qu
ire
d a
nd
in
dic
ate
wh
eth
er
the
Act
ivit
y a
s d
esc
rib
ed
in
th
e A
MP
is
sust
ain
ab
le o
ver
the
lo
ng
te
rm.
O
pp
ort
un
itie
s fo
r Im
pro
ve
me
nt
2
4.
Co
nsi
de
r a
dd
ing
lon
g t
erm
fu
nd
ing
pro
ject
ion
s to
th
e p
lan
sh
ow
ing
th
e l
eve
ls o
f fu
nd
ing
th
at
are
exp
ect
ed
to
be
ne
cess
ary
to
su
sta
in
the
act
ivit
y.
0 -
In
no
cen
t 1
- A
wa
re
2
- D
ev
elo
pin
g
3 -
Fu
lly
me
ets
re
qu
ire
me
nts
4
- E
xce
ed
s re
qu
ire
me
nts
Th
e A
MP
do
es
no
t d
em
on
stra
te a
ny
aw
are
ne
ss o
f th
is r
eq
uir
em
en
t
Th
e A
MP
do
es
no
t cu
rre
ntl
y a
dd
ress
this
re
qu
ire
me
nt
(or
cove
rs it
in a
min
ima
l wa
y) b
ut
de
mo
nst
rate
s a
n
inte
nt
to p
rog
ress
it
Th
e A
MP
pa
rtly
co
mp
lie
s w
ith
go
od
ind
ust
ry p
ract
ice
an
d d
em
on
stra
tes
an
inte
nt
to a
chie
ve f
ul l
co
mp
lian
ce w
ith
go
od
ind
ust
ry p
ract
ice
Th
e A
MP
co
mp
lies
wit
h g
oo
d in
du
stry
pra
ctic
e
Th
e A
MP
exc
ee
ds
com
plia
nce
wit
h g
oo
d
ind
ust
ry p
ract
ice
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-2
2
Ass
ess
me
nt
Ite
m 1
3
Re
ad
ab
ilit
y
Wh
y i
s th
is i
mp
ort
an
t?
O
ur
Fin
din
gs
AM
Ps
po
ten
tia
lly h
av
e a
wid
e r
an
ge
of
au
die
nce
s
·
Ass
et
Ma
na
ge
rs –
AM
Ps
sho
uld
act
ive
ly g
uid
e a
sse
t m
an
ag
ers
in t
he
ma
na
ge
me
nt
of
ass
et
ba
sed
se
rvic
es
·
Sen
ior
ma
na
ge
me
nt
– A
MP
s sh
ou
ld b
e r
ea
dily
co
mp
reh
en
sib
le
to s
en
ior
ma
na
ge
me
nt
an
d p
rovi
de
se
nio
r m
an
ag
em
en
t w
ith
a
hig
h l
eve
l u
nd
ers
tan
din
g o
f w
ha
t th
e a
ctiv
ity
invo
lve
s, w
ha
t it
is t
ryin
g t
o a
chie
ve,
an
y si
gn
ific
an
t is
sue
s a
nd
ris
ks
the
act
ivit
y
is f
aci
ng
, h
ow
it is
ma
na
ge
d a
nd
co
sts
of
the
act
ivit
y.
·
Ele
cte
d m
em
be
rs -
– A
MP
s sh
ou
ld b
e r
ea
son
ab
ly
com
pre
he
nsi
ble
to
ele
cte
d m
em
be
rs,
an
d p
rovi
de
ele
cte
d
me
mb
ers
wit
h a
hig
h le
ve
l un
de
rsta
nd
ing
of
wh
at
the
act
ivit
y
invo
lve
s, w
ha
t it
is t
ryin
g t
o a
chie
ve a
nd
wh
y, a
ny
sig
nif
ica
nt
issu
es
an
d r
isk
s th
e a
ctiv
ity
is f
aci
ng
, a
nd
co
sts
of
the
act
ivit
y.
It s
ho
uld
pro
vid
e e
lect
ed
me
mb
ers
wit
h c
on
fid
en
ce t
ha
t th
e
act
ivit
y is
be
ing
we
ll m
an
ag
ed
·
Inte
rest
ed
me
mb
ers
of
the
co
mm
un
ity
- –
AM
Ps
sho
uld
be
rea
son
ab
ly c
om
pre
he
nsi
ble
to
inte
rest
ed
me
mb
ers
of
the
com
mu
nit
y, a
nd
pro
vid
e e
lect
ed
me
mb
ers
wit
h a
hig
h le
ve
l
un
de
rsta
nd
ing
of
wh
at
the
act
ivit
y in
volv
es,
wh
at
it is
try
ing
to
ach
ieve
an
d w
hy,
an
y si
gn
ific
an
t is
sue
s a
nd
ris
ks
the
act
ivit
y is
faci
ng
, a
nd
co
sts
of
the
act
ivit
y.
·
Au
dit
Ne
w Z
ea
lan
d -
– A
MP
s sh
ou
ld p
rovi
de
Au
dit
Ne
w Z
ea
lan
d
wit
h c
on
fid
en
ce t
ha
t th
e a
ctiv
ity
is b
ein
g m
an
ag
ed
ap
pro
pri
ate
ly
It is
th
ere
fore
imp
ort
an
t th
at
AM
Ps
are
re
ad
ab
le a
nd
re
ad
ily
com
pre
he
nsi
ble
It is
sta
ted
in S
ect
ion
1.1
“P
urp
ose
of
this
Pla
n”
tha
t th
e A
MP
is
inte
nd
ed
to
be
“a
pp
rop
ria
te f
or
a r
ea
de
rsh
ip i
ncl
ud
ing
ele
cte
d m
em
be
rs o
f
the
Co
un
cil,
exe
cuti
ve
ma
na
ge
me
nt,
in
tere
st g
rou
ps,
an
d b
usi
ne
ss p
art
ne
rs a
sso
cia
ted
wit
h t
he
ma
na
ge
me
nt
of
the
Wa
ste
wa
ter
act
ivit
y,
alo
ng
wit
h i
nte
rest
ed
me
mb
ers
of
the
co
mm
un
ity.”
AM
Ps
pro
vid
e a
n o
pp
ort
un
ity
for
ass
et
ma
na
ge
rs t
o d
em
on
stra
te t
he
qu
alit
y o
f th
eir
ma
na
ge
me
nt
of
ass
et
ba
sed
se
rvic
es.
Th
ey
sho
uld
pro
vid
e c
on
fid
en
ce t
o in
tere
ste
d p
art
ies
tha
t th
e a
ctiv
ity
cove
red
by
the
AM
P is
be
ing
we
ll m
an
ag
ed
. F
or
mo
st a
ud
ien
ces
this
ne
cess
ita
tes
a r
ea
son
ab
ly c
on
cise
do
cum
en
t.
Th
e W
ast
ew
ate
r A
MP
co
nta
ins
the
info
rma
tio
n t
ha
t w
ou
ld b
e r
eq
uir
ed
by
a d
ive
rse
re
ad
ers
hip
an
d c
on
veys
th
is i
nfo
rma
tio
n in
a lo
gic
al
an
d c
om
pre
he
nsi
ble
ma
nn
er.
It
ha
s co
nti
nu
ally
de
ve
lop
ed
an
d e
volv
ed
ove
r a
nu
mb
er
of
yea
rs.
M
ovi
ng
fo
rwa
rd t
he
re i
s so
me
de
tail
in
the
pla
n w
hic
h c
ou
ld b
e a
pp
en
de
d a
s p
art
of
the
pro
cess
of
on
go
ing
ev
olu
tio
n o
f th
e A
MP
.
O
pp
ort
un
itie
s fo
r Im
pro
ve
me
nt
2
5.
Co
nsi
de
r tr
an
sfe
rrin
g s
om
e o
f th
e m
ore
de
tail
ed
in
form
ati
on
in t
he
AM
P t
o a
pp
en
dic
es
as
pa
rt o
f a
pro
cess
of
evo
luti
on
to
wa
rds
a
hig
he
r le
vel d
ocu
me
nt
(No
te:
no
sco
re is
ass
ign
ed
to
th
is it
em
)
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-2
3
Ge
ne
ral
Ob
serv
ati
on
s
Th
is is
fu
nd
am
en
tally
a g
oo
d A
MP
. I
t is
log
ica
lly s
tru
ctu
red
an
d c
ove
rs a
ll e
lem
en
ts t
ha
t w
ou
ld b
e e
xpe
cte
d in
an
AM
P f
or
an
act
ivit
y su
ch a
s a
co
mm
un
ity
wa
ste
wa
ter
serv
ice
.
Th
e A
MP
de
mo
nst
rate
s o
ng
oin
g d
eve
lop
me
nt
an
d im
pro
vem
en
t o
ver
the
ye
ars
.
It w
as
ple
asi
ng
to
se
e in
Se
ctio
n 2
.2 “
Act
ivit
y R
ati
on
ale
” th
at
the
fu
nd
am
en
tal r
ea
son
PN
CC
pro
vid
es
a w
ast
ew
ate
r n
etw
ork
is t
o s
up
po
rt t
he
he
alt
h a
nd
we
llbe
ing
of
the
com
mu
nit
y a
nd
th
at
leg
isla
tive
re
qu
ire
me
nts
are
on
ly a
n u
nd
erl
yin
g r
ea
son
PN
CC
ma
y w
ish
to
ch
eck
co
mp
lian
ce o
f th
eir
ass
et
ma
na
ge
me
nt
po
licy
(Se
ctio
n 3
.4.1
) a
nd
str
ate
gy
(Se
ctio
n 3
.4.2
) w
ith
th
e r
eq
uir
em
en
ts o
f th
e I
SO 5
50
01
Ass
et
Ma
na
ge
me
nt
Sta
nd
ard
. I
t is
like
ly t
he
re w
ill b
e a
n in
cre
asi
ng
exp
ect
ati
on
th
at
org
an
isa
tio
ns’
ass
et
ma
na
ge
me
nt
pra
ctic
es
are
ge
ne
rall
y c
om
pli
an
t w
ith
th
is S
tan
da
rd (
bu
t p
rob
ab
ly n
ot
of
form
al c
ert
ific
ati
on
to
th
e S
tan
da
rd).
Th
ere
wo
uld
be
me
rit
in in
clu
din
g a
“M
an
ag
em
en
t R
evi
ew
” p
roce
ss a
s p
art
of
Sect
ion
11
“C
on
tin
uo
us
imp
rove
me
nt”
. M
an
ag
em
en
t R
evi
ew
Me
eti
ng
s, t
ypic
ally
he
ld a
t in
terv
als
of
3-6
mo
nth
s, c
on
sid
er
the
pe
rfo
rma
nce
of
the
act
ivit
y, s
ign
ific
an
t is
sue
s th
at
ha
ve a
rise
n,
cust
om
er
fee
db
ack
, a
nd
an
y o
the
r m
att
ers
th
at
are
re
leva
nt
to im
pro
vin
g t
he
ma
na
ge
me
nt
of
the
act
ivit
y.
Th
ey
pro
vid
e a
n o
pp
ort
un
ity
to p
eri
od
ica
lly “
tak
e s
tock
” o
f h
ow
th
ing
s a
re g
oin
g a
nd
ta
ke a
pp
rop
ria
te a
ctio
n a
s m
ay
be
ap
pro
pri
ate
.
Wit
h t
he
pa
ssin
g o
f th
e H
ea
lth
an
d S
afe
ty a
t W
ork
Act
20
15
th
e A
MP
ma
y b
e a
litt
le li
gh
t o
n id
en
tify
ing
an
d m
an
ag
ing
He
alt
h a
nd
Sa
fety
ris
ks a
sso
cia
ted
wit
h t
he
wa
ste
wa
ter
infr
ast
ruct
ure
(a
pa
rt f
rom
illn
ess
ari
sin
g f
rom
co
nta
ct w
ith
wa
ste
wa
ter)
. P
NC
C a
nd
ind
ivid
ua
ls w
ith
in t
he
Co
un
cil m
ay
be
exp
ose
d t
o li
ab
ility
in t
he
eve
nt
of
ha
rm t
o p
ers
on
s
occ
urr
ing
wh
ich
is a
sso
cia
ted
wit
h t
he
wa
ste
wa
ter
infr
ast
ruct
ure
un
less
PN
CC
ha
s id
en
tifi
ed
ris
ks a
sso
cia
ted
wit
h t
ha
t in
fra
stru
ctu
re a
nd
elim
ina
ted
or
min
imis
ed
th
ose
ris
ks s
o
far
as
is r
ea
son
ab
ly p
ract
ica
ble
..
Th
e A
MP
sh
ou
ld id
ea
lly in
clu
de
a p
roje
ctio
n o
f fu
ture
ass
et
valu
es
tha
t w
ill r
esu
lt f
rom
imp
lem
en
tati
on
of
the
pro
gra
mm
es
in t
he
AM
P.
Au
dit
NZ
ha
ve r
ais
ed
th
is in
au
dit
s
els
ew
he
re.
A p
roje
ctio
n o
f fu
ture
ass
et
valu
es
wh
ich
sh
ow
s a
de
clin
ing
tre
nd
in t
he
ove
rall
valu
e o
f th
e n
etw
ork
ma
y (b
ut
will
no
t n
ece
ssa
rily
) in
dic
ate
th
at
the
re is
an
issu
e
bu
ildin
g w
ith
de
ferr
ed
re
ne
wa
ls.
A d
ecl
inin
g v
alu
ati
on
ove
r ti
me
wo
uld
th
ere
fore
ne
ed
to
be
exp
lain
ed
.
Th
e L
GA
20
02
re
qu
ire
s a
ny
sig
nif
ica
nt
ne
ga
tive
eff
ect
s th
at
ma
y b
e a
sso
cia
ted
wit
h a
n a
ctiv
ity
to b
e id
en
tifi
ed
. S
ect
ion
2.5
co
vers
“S
ign
ific
an
t N
eg
ati
ve E
ffe
cts
of
the
Act
ivit
y”
Th
is s
ect
ion
se
ts o
ut
po
ten
tia
l ne
ga
tive
eff
ect
s w
he
rea
s it
is o
nly
ne
cess
ari
ly t
o s
tate
act
ua
l eff
ect
s o
r e
ffe
cts
tha
t a
re l
ike
ly t
o o
ccu
r a
nd
on
ly if
th
ese
are
co
nsi
de
red
sig
nif
ica
nt.
Th
e p
roce
ss t
ha
t ca
n b
e f
ollo
we
d t
o id
en
tify
sig
nif
ica
nt
ne
ga
tive
eff
ect
s is
to
fir
stly
de
fin
e t
he
cri
teri
a b
y w
hic
h s
ign
ific
an
ce w
ill b
e d
ete
rmin
ed
. T
his
is n
orm
ally
th
e s
oci
al
cult
ura
l eco
no
mic
an
d e
nvi
ron
me
nta
l we
llbe
ing
of
the
co
mm
un
ity
(th
is w
as
pre
vio
usl
y sp
eci
fie
d in
th
e L
GA
20
02
bu
t h
as
sin
ce b
ee
n r
em
ove
d).
Po
ssib
le n
eg
ati
ve e
ffe
cts
ari
sin
g
fro
m t
he
wa
ste
wa
ter
act
ivit
y a
re t
he
n a
sse
sse
d (
wit
h c
urr
en
t co
ntr
ols
in p
lace
) re
lati
ve t
o t
he
cri
teri
a t
o d
ete
rmin
e w
hic
h n
eg
ati
ve e
ffe
cts
are
sig
nif
ica
nt.
On
ly n
eg
ati
ve e
ffe
cts
wh
ich
ha
ve b
ee
n id
en
tifi
ed
as
sig
nif
ica
nt
fro
m a
pro
cess
su
ch a
s th
is s
ho
uld
be
re
po
rte
d in
th
e p
lan
. T
he
pro
cess
itse
lf s
ho
uld
be
ap
pe
nd
ed
. A
n e
xam
ple
of
an
ass
ess
me
nt
of
ne
ga
tive
eff
ect
s is
se
t o
ut
be
low
. T
his
is o
nly
on
e o
f a
nu
mb
er
of
po
ssib
le a
pp
roa
che
s.
AE
CO
M
PN
CC
Asset
Man
agem
ent R
evie
w
Asset
Ma
nag
em
en
t R
evie
w -
201
7 A
MP
's
16-A
pr-
20
18
P
rep
are
d f
or
– P
alm
ers
ton N
ort
h C
ity C
oun
cil
– C
o N
o.: N
/A
F-2
4