Waste management on construction sites
-
Upload
ali-hasan -
Category
Engineering
-
view
162 -
download
6
Transcript of Waste management on construction sites
WASTE MANAGEMENT ON CONSTRUCTION SITES
A ThesisSubmitted to the Department of Building and Construction Engineering at the University of Technology in Partial Fulfillment
of the Requirements for the degree of Master of Science in Building and Construction Engineering
(Project Management)
By
Ali Hasan Hadi Al-Ayem supervised by
Dr. Zeyad S. M. Khaled Dr. Basil S. Al-Shathr Asst. Prof. Asst. Prof.
3/12/2014
INTRODUCTION
Construction waste is a major challenge because of its
tremendous environmental and economic bad effects (Shen,
2004)..
Environmentally: construction waste produces an average of
(32%) of the total annual waste that is disposed to landfills.
Economically: It comprises (10-20%) of the total annual
construction materials used. hence (4-10%) of the project total
cost is wasted.
DEFINITIONS
Material Waste: is defined as any losses produced by activities
that generate direct or indirect costs but do not add any value to
the product (Lauri, 199). It is also defined as the surplus
materials that are generated from construction, renovation and
demolition activities (Formoso, 1999).
Construction Waste Management: is the process of developing
and implementing a strategy or a plan to reduce the generated
waste to the minimum extent possible by three approaches:
Reducing, Reusing, and Recycling.
RESEARCH OBJECTIVES
Finding out waste percentages of ten major construction
materials on local scale.
Employing the waste percentages as early warning indicators
that point out any access in waste percentages at early stages.
Developing a computerized system to be used as a tool for
managing construction waste in the local construction
industry.
RESEARCH JUSTIFICATION
Construction waste in the local construction industry do not receive enough care. There is a serious need to understand the impact of construction waste on the environment and the economic benefits gained through reducing the construction cost.
A successful construction waste management reserves the environment by utilizing the use of natural resources in addition to the economic benefits. For many developed countries the construction waste management is no longer an option but became a necessity.
RESEARCH METHODOLOGY
1. Literature Review
1.1 To explore the issue of construction waste including its
generation, causes, types, management, and treatments.
1.2 To study the facilities of Statistical Package for Social Sciences
(SPSS) and Microsoft Project (MS-Project) programs.
RESEARCH METHODOLOGY
2. Data Acquisition
To determine the average waste percentages of construction
materials at the local construction industry in Karbala:
2.1 Past records of thirty construction projects concerning ten major
types of construction materials are studied carefully and
analyzed. Table (1) shows number of project related to each
Client visited.
(Continued)
Table 1: Allocation of Finished Projects Covered
No. of studied projects Client
10 Directorate of Education in Karbala .
9 General Secretariat of the Husseiniya Shrine.
5 Directorate of Municipality in Karbala .
3 Local Branch of the General Directorate for Roads and Bridges.
2 Directorate of Electric Power Distribution in Karbala .
1 General Secretariat of the Abasia Shrine.
30 Total
Ceram. Marble Tiles Gyps. Stone Brick Steel Cement Gravel Sand Project
- - - 18.07 12.07 - 5.07 5.69 10.18 11.12 Almujtaba Library.
8.39 8.19 - 17.88 - 15.24 4.59 5.41 10.25 11.32 Second Municipal.
10.62 8.28 - 18.17 - 15.31 4.61 5.58 10.33 12.00 Sixth Municipal.
11.54 7.89 - 18.68 - 15.43 4.69 4.84 10.42 12.07 Gardens Dept.
- - - 17.85 11.43 - 4.73 4.76 10.53 12.66 Alwaeli Hospital.
- - 11.70 17.94 - 15.67 4.84 5.18 11.03 11.70 Alsomood school.
- - 11.80 18.33 - 15.78 4.81 5.07 11.32 11.80 Alhindia school.
- - 12.91 17.59 - 15.96 4.94 5.03 11.41 12.91 Almojtaba school.
- - 12.98 18.95 - 16.1 5.13 5.08 11.28 12.98 Alshimokh school.
- - 13.33 17.37 - 16.28 5.27 5.21 10.78 13.33 Altaka school.
- - 11.8 13.91 - 16.38 5.39 5.33 10.62 11.80 Omalhawa school.
- - 13.64 19.21 - 16.41 5.47 5.41 10.86 13.64 Alrafidain school.
- - 14.00 17.20 - 16.5 5.56 5.48 10.91 14.00 Aldobat school.
- - 14.12 14.64 - 16.64 5.64 5.18 11.59 14.12 Alitarat school.
Table 3: Waste Percentages Determined From Past Records
Ceram. Marble Tiles Gyps. Stone Brick Steel Cement Gravel Sand Project
9.75 - 10.64 17.68 13.51 14.23 6.03 5.72 8.92 10.64 Alkawther Mall.
6.81 - 12.07 14.94 13.79 - 6.21 5.91 8.75 12.07 Almustafa Mall.
- 7.27 - 17.58 13.97 - 6.46 6.22 8.61 12.04 Zain Hospital.
- 7.38 - 17.47 17.02 - 6.90 6.43 8.83 12.13 Alkafel Hospital.
- - - 15.43 - 13.91 4.54 4.98 9.47 10.63 Alataba Plantation.
9.88 6.54 - 20.31 - 13.64 4.48 4.83 9.56 12.50 Medinat Al-Zairin1.
12.65 9.47 - 17.39 - 13.00 4.31 4.76 13.19 11.24 Medinat Al-Zairin2.
7.81 9.67 - 15.77 - 12.74 4.18 4.62 11.73 14.55 Medinat Al-Zairin3.
8.83 9.81 - 17.18 - - 4.01 4.53 12.19 12.66 Mukhaim Toilets1.
7.25 10.09 - 16.97 - 12.00 2.98 4.48 12.96 14.56 Mukhaim Toilets2.
- - - - - - 3.29 4.23 12.43 13.00 Aldariba Bridge.
- - - - - 16.91 3.48 4.08 12.69 13.30 Towayrige Bridge.
- - - - - - 3.54 3.89 11.73 13.34 Algaire Bridge.
13.39 - 13.34 16.28 - 17.46 3.72 3.71 11.84 14.45 Friha E. Station.
10.56 - 13.66 16.17 - 17.91 3.96 3.46 10.18 13.66 Alkhairat E. Station.
Table 3: Waste Percentages Determined From Past Records(Continued)
Table 2: Allocation of Under Construction Projects Visited
No. of studied projects Client
2 Directorate of Education in Karbala.
2 General Secretariat of the Husseiniya Shrine.
1 Karbala Investment Commission.
1 Directorate of Health in Karbala.
6 Total
2.2 Field investigation included live observations of materials flow
and waste generation in six under construction projects. Table
(2) shows number of project related to each client visited .
RESEARCH METHODOLOGY(Continued)
Retrospective study is conducted to extract data from materials
ordering sheets of thirty finished projects shown in Table (3).
Then net quantities are estimated from related drawings.
Waste percentages are calculated using equation (1).
W% = ........... (1)
PAST DATA DETERMINED
Observational method is employed to measure the required data in
six under construction projects by the aid of the worksheet shown
in Fig. (1). Materials movement stream line once it is delivered to
the work site until being used and built in its final position is
intensively tracked and measured. Several factors that usually
cause construction materials waste in local construction industry
are studied in order to discover their influences. The construction
materials streamline flowchart is illustrated in Fig. (2).
FIELD MEASUREMENTS
FIGURE 2: CONSTRUCTION MATERIALS FLOW CHART
Hauling
Residual materials
Non-reusableReusable
Off-site Recycling, Reclamation or Landfill
Pre-
cons
truc
tion
phas
eStorage
Processing
Supply
Ordering
Con
stru
ctio
n ph
ase
Estimating
Waste percentages are measured in various activities, of different
architectural design, at several elevations, for various work
gangs. Nevertheless, all of them are carried out at the same
storage conditions, with the same way of unloading and
handling, and at the same work conditions using the same
specifications and equipment available at the local industry.
Records of related quantities for thirty finished projects are
collected and analyzed as shown in Table (4).
FIELD MEASUREMENTS (Continued)
Table 4: Observed Waste Percentages
Ceram. Marble Tiles Gyps. Stone Brick Steel Cement Gravel Sand Project
9.67 - 10.17 17.84 11.62 14.50 4.81 5.38 10.33 12.00 Durrat Housing.
- - - - - 15.32 4.34 5.03 10.72 11.92 Khatem Hospital.
- - - - - - 4.64 5.29 11.01 13.01 Orphans School.
10.75 8.93 - - - 15 5.27 4.72 11.44 12.04 Turkish Hospital.
8.81 - - 17.41 - 15.11 4.61 4.90 10.09 12.66 Alsalam school.
9.08 - - 16.71 - 14.66 5.19 5.11 10.23 11.91 Almilad school.
10.27 9.19 9.45 17.25 12.77 15.23 4.81 5.03 10.76 12.47 Norm rates *
* Normal rates are average waste percentages determined from past record.
SOME VISITED CONSTRUCTION SITES
PAST DATA ANALYSIS
The past data obtained are tested against statistical measures.
Normal distribution curves are fitted to verify the credibility of
the determined statistical society of past records for each
material using the Statistical Package for Social Sciences
(SPSS) as shown in Fig (3).
Figure 3:MATERIALS WASTE PAST DATA DISTRIBUTIONS
The distribution of each statistical society of past records is
submitted to the test of "Goodness of fit" to verify its
characteristic under (99%) level of confidence. The results of this
test for all materials wastes are summarized in Table (5) which
reveals that the statistical society of all materials wastes conform
to the normal distribution.
PAST DATA VERIFICATION
Table 5: Results of the test of goodness of fit for past records
*Degree of Freedom. ** Two tailed test.
Asymp. Sig.** Df * Chi-Square Materials
0.045 26 17.103 Sand0.153 28 13.651 Gravel0.194 26 2.406 Cement
0.081 29 2.087 Reinforcement Steel Bars
0.09 29 3.12 Bricks0.163 28 10.71 Thermo-stone0.294 29 4.333 Gypsum0.067 28 26.059 Terrazzo Tiles0.509 28 3.933 Marble0.019 29 8.083 Ceramics
OBSERVED DATA VERIFICATION
Reliability of the method adopted to determine the waste
percentages of materials are verified against the data
measured from field investigation of six under construction
projects. "t- Test" for six different iterations of each material
at (99%) level of confidence is conducted as shown in Table
(6).
Table 6: Results of the test of hypotheses for observed data
Conf. Interval ***MeanDif. Sig.** Df * t Waste
%
Material
Upper Lower
1.1208 -0.795 0.5206 0.023 29 2.391 12
Sand
1.2008 0.0005 0.6006 0.01 29 2.759 11.920.1208 -1.079 -0.4793 0.036 29 -2.202 13.011.0808 -0.1195 0.4806 0.035 29 2.208 12.040.4608 -0.7395 -0.1393 0.527 29 -0.64 12.661.2108 0.0105 0.6167 0.009 29 2.805 11.911.0968 -0.1815 0.4576 0.058 29 19.74 10.33
Gravel
0.7068 -0.5715 0.0676 0.773 29 0.292 10.720.4168 -0.8615 -0.2223 0.346 29 -0.959 11.01-0.013 -1.2915 -0.6523 0.009 29 -2.813 11.441.3368 0.0585 0.6976 0.005 29 3.009 10.091.1968 -0.815 0.5576 0.023 29 2.405 10.23
Material Waste % t Df * Sig.** Mean Dif.Conf. Interval ***Lower Upper
Cement
5.38 -2.778 29 0.009 -0.3573 -0.7118 -0.0035.03 -0.057 29 0.955 -0. 007 -0.3618 0.34725.29 -2.079 29 0.047 -0.2673 -0.6218 0.08724.72 2.353 29 0.026 0.3026 -0.0518 0.65724.9 0.954 29 0.348 0.1226 -0.2318 0.47725.11 -0.679 29 0.502 -0.0873 -0.4418 0.2672
Reinfor-cement Steel
Bars
4.81 0.065 29 0.949 0.0113 -0.4696 0.49234.34 2.759 29 0.01 0.4813 0.0004 0.96234.64 1.039 29 0. 307 0.1813 -0.2996 0.66235.27 0.571 29 0.016 -0.4467 -0.9296 0.03234.61 1.211 29 0.236 0.2113 -0.2696 0.69235.19 2.113 29 0.043 -0.3687 -0.8496 0.1123
Bricks
14.5 2.903 29 0.007 0.801 0.0404 1.561615.32 0.069 29 0.946 -0.019 -0.7796 0.741614.93 1.345 29 0.189 0.371 -0.3896 1.1316
15 1.091 29 0.284 0.301 -0.4596 1.061615.11 0.692 29 0.494 0.191 -0.5696 0.951614.66 2.323 29 0.027 0.641 -0.1196 1.4016
Table 6: Results of the test of hypotheses for observed data (Continued)
Material Waste % t Df * Sig.** Mean Dif.Conf. Interval ***Lower Upper
Thermo-stone
11.62 2. 937 29 0.006 1.1636 0.0715 2.255912.84 0.766 29 0.45 0.3036 -0.7885 1.395913.77 -2.489 29 0.019 -0.9863 -2.0785 0.105913.59 -2.035 29 0.051 -0.8063 -1.8985 0.285912.56 0.564 29 0.577 0.2236 -0.8685 1.315912.07 1.801 29 0.082 0.7136 -0.3785 1.8059
Gypsum
17.84 -2.159 29 0.039 -0.5777 -1.3153 0.159917.31 -0.178 29 0.86 -0.0477 -0.7853 0.689916.96 1.1301 29 0.268 0.3023 -0.4353 1.039918.01 -2.794 29 0.009 -0.74767 -1.4853 -0.01017.41 -0.552 29 0.585 -0.14767 -0.8853 0.589916.71 2.064 29 0.048 0.55233 -0.1853 1.2899
Terrazzo Tiles
10.17 -2.545 29 0.016 -0.73733 -1.5358 0.06119 1.494 29 0.146 0.43267 -0.3658 1.2311
9.81 -1.303 29 0.203 -0.37733 -1.1758 0.42118.63 2.771 29 0.01 0. 80267 0.0042 1.60119.38 0.182 29 0.857 0.05267 -0.7458 0.8511
10.31 -3.029 29 0.005 -0.87733 -1.6758 -0.079
Table 6: Results of the test of hypotheses for observed data (Continued)
Marble
9.52 -1.265 29 0.216 -0.34133 -1.0853 0.4027
10 -3.043 29 0.005 -0.82133 -1.5653 -0.077
8.44 2.737 29 0.01 0.73867 -0.053 1.4827
8.93 0.921 29 0.365 0.24867 -0.4953 0.9927
9.71 -1.968 29 0.059 -0.53133 -1.2753 0.2127
9.07 0.403 29 0.69 0.10867 -0.6353 0.8527
Ceramic
9.67 1.724 29 0.095 0.68733 -0.4114 1.7861
9.38 2.452 29 0.02 0.97733 -0.1214 2.0761
10.17 0.47 29 0.642 0.18733 -0.9114 1.2861
10.75 -0.985 29 0.333 -0.39267 -1.4914 0.7061
9.13 3.079 29 0.005 1.22733 0.1286 2.3261
10.08 0.696 29 0.492 0.27733 -0.8214 1.3761
Table 6: Results of the test of hypotheses for observed data (Continued)
The descriptive statistics; mean, median, standard deviation, range,
variance, and others of all materials wastes are determined using
SPSS. The results are summarized in Table (7) and they confirm
that the waste of materials at the local construction industry in
Karbala is relatively higher than the limits set by the Iraqi Ministry
of Housing and Construction (MOHC) but it is predictable and
avoidable which coincides with the research hypothesis.
STATISTICAL ANALYSIS RESULTS
Table 7: Statistics of ten construction materials waste percentages
MOHC Range Variance St. Dev. Median Mean Material
10 4.55 1.219 1.104 12.315 12.477 Sand9 4.58 1.378 1.174 10.75 10.76 Gravel4 2.97 0.42 0.648 5.05 5.03 Cement
6 3.92 0.775 0.88 4.77 4.81 Reinf. Steel
15 5.91 1.926 1.387 15.275 15.23 Bricks15 8.81 4.044 2.01 12.7 12.77 Thermo-stone18 6.4 1.785 1.328 17.4 17.25 Gypsum10 6.25 2.151 1.466 9.265 9.45 Terrazzo tiles7 5.48 1.859 1.363 9.015 9.19 Marble7 8.26 4.034 2.008 9.965 10.27 Ceramics
CONSTRUCTION WASTE MANAGEMENT SYSTEM
Open vs. close systems
The construction industry is usually considered as an open loop
system that consists of input, processing, and output. An
attempt to achieve higher efficiency in materials usage is
made by adding a feedback flow of waste materials which
convert the open loop system to a close one as shown in Fig.
(4) (Poon, 2004).
Figure 4: Open and close loop systems
Input
Processing Output + WasteInput
Output + Waste
Open Loop System
Waste feedback
Close Loop System
Processing
CONSTRUCTION WASTE MANAGEMENT SYSTEM (Continued)
A system is developed in an attempt to convert the traditional open
loop system to a close one. It is developed to serve as a tool to be
used by construction engineers during the execution phase.
CONSTRUCTION WASTE MANAGEMENT SYSTEM (Continued)
Easy to install and operate.
Do not need excessive input data.
Capable to comprise all necessary information in its database.
Provides understandable and useful reports.
Flexible and capable to handle wide range of applications.
Compatible with other systems that are used in the same field.
PRINCIPLES OF THE SYSTEM
Reducing waste: The developed system employs the principles of ‘supply chain method’ (SCM) or ‘just-in-time’ delivery concept (JIT) to supply the construction materials to sites.
Reusing waste: The developed system offers possible ways to reuse waste materials in the same project through functioning as an expert system.
Recycling waste: The developed system provides possible options (if any) for recycling construction materials waste that cannot be reused.
SCOPE OF THE SYSTEM
1. Inter basic information of the project.
2. Import the time table of the project from MS-Project program.
3. Determine quantities needed in progress for each material.
4. Optimize the available space of material storage.
5. Determine optimal demand dates.
6. Prepare a daily report about each material with e-mail possibility.
7. Alarm an early warning in case of excessive waste.
8. Offer all possible ways to reuse waste in the coming activities.
9. Offer opportunities of recycling materials that cannot be reused.
The framework of the developed system and its programming interlinks are summarized in Fig (5).
FUNCTIONS OF THE SYSTEM
SYSTEM INTERFACES
Running the system does not need any special training above
minimal computer skills for the system is designed to be user-
friendly and self-exploratory in which the interfaces enable the
user to run the system easily. The followings are the interfaces of
system:
Main Interface
SYSTEM INTERFACES (Continued)
New Project Interface
SYSTEM INTERFACES (Continued)
Work Items Interface
SYSTEM INTERFACES (Continued)
Follow-up Interface
SYSTEM INTERFACES (Continued)
Orders due Interface
SYSTEM INTERFACES(Continued)
Daily Report Output
SYSTEM INTERFACES (Continued)
Waste management Interface
SYSTEM INTERFACES (Continued)
List of actions Output
SYSTEM INTERFACES (Continued)
Waste Report Output
SYSTEM INTERFACES (Continued)
Recycling Output
SYSTEM INTERFACES (Continued)
SYSTEM EVALUATION
The developed system is implemented in six under-construction
projects in Karbala in order to:
verify its flexibility, accuracy, effectiveness, and suitability
for application.
find out application difficulties, and
explore any additional arguments of the users.
Direct interviews are also conducted with each project
associated staff including (the representative of the
consultant firm, the resident engineer, the site engineer, the
quantity surveyor, and the store keeper). Interviews are
documented by a Questionnaire Form for specific ranked
system characteristics as shown in Table (8).
SYSTEM EVALUATION (Continued)
(Ranked Questions)
MeanScore
Obtained frequency System characteristics Q.
Excel. V. G. Good Poor V. P.6.6 5 14 11 - - Installation 1
6.73 11 4 15 - - Data input 28.13 17 13 - - - Output display 36.2 3 14 11 2 - User interaction 4
5.26 - 8 18 4 - Accuracy of results 5
8 16 12 2 - - MS-project Integration 6
6.73 7 12 11 - - Storage management 77 5 19 6 - - Waste early warning 8
7.06 7 17 6 - - Reducing the waste 95.4 - 10 16 4 - Applicability 10
TABLE 8: EVALUATION OF SYSTEM CHARACTERISTICS
It can be noticed from the ranked answers that:1. Installing the system is easy.2. Data input is smooth.3. Output is reliable.4. Interaction between the user and the system is efficient.5. Results are accurate.6. Integration between the system and MS-project is effective.7. Early warning of waste excess is active.8. Employing the system in the local construction industry is
possible.
SYSTEM EVALUATION (Continued)
CONCLUSIONS
1.The actual waste percentages of construction materials exceed the limits set by (MOHC) listed in Table (7). 2.Local contracting companies do not seem to be concerned about material waste.3.High variation in wastage is found for different construction materials at the same project itself . 4.There is a considerable variance between waste percentages of the same material from site to site.5.A serious absence of the appropriate knowledge of construction materials waste management is found.6.Most of the generated waste can be avoided by implementing few preventive measures.
RECOMMENDATIONS
1. The Ministry of Planning is invited to develop the contract conditions in order to compel contractors to apply construction waste control clauses at the construction phase.2.The Ministry of Construction and Housing is invited to issue instructions to enable construction firms to use feasible approaches for construction waste management.3.The Ministry of Environment is invited to conduct studies to determine the environmental and economical effect of construction waste.4.The Iraqi Engineers Syndicate is invited to hold symposiums to raise the awareness of the professional teams concerning construction waste.5.The Union of Iraqi Contractors is invited to conduct symposiums to raise contractors' awareness concerning construction waste.
FUTURE STUDIES
1.Investigation of alternative waste disposal methods.
2.Develop a Waste Disposal Data System because there is acute
demerit in the construction waste data base at local scale.
3.Develop more general waste management system for the Iraqi
construction environment as a whole.
Finally, it is recommended to use the system developed through this research.
THANK YOU