Waste Guide
-
Upload
pratik-bhagat -
Category
Documents
-
view
224 -
download
0
Transcript of Waste Guide
-
7/30/2019 Waste Guide
1/46
Planning
Centralised Building
Waste ManagementProgrammes in
Response to Large
Disasters
-
7/30/2019 Waste Guide
2/46
-
7/30/2019 Waste Guide
3/46
1
IM
This booklet is a short guide or shelter practitioners with little experience o centralised disasterwaste settings, mainly in response to large disasters. It highlights key issues and priorities odisaster waste management in diferent settings. It provides simple examples o re-use and
recycling o building waste materials in temporary and permanent shelter programmes. Furtherreading and other sources o more in-depth inormation are provided.
This project is a collaboration between ProAct Network, Disaster Waste Recovery (DWR) andShelter Centre. It is unded via the Shelter Centre Conict and Humanitarian Fund Programme
supported by DFID.
This booklet can be downloaded rom www. proactnetwork.organd www.sheltercentre.org
...the re-use of materials salvaged from damaged buildings should bepromoted where feasible, either as primary construction materials (bricks or
stone masonry, roof timber, roof tiles, etc.) or as secondary material (rubble
for foundations or levelling roads, etc.).SPHERE Handbook, Shelter and Settlement, Standard 5: Construction, Guidance note 1, 2004
...the production and supply of construction material and the building
process minimises the long-term depletion of natural resources.SPHERE Handbook, Shelter and Settlement Standard 6: Environmental Impact, Key Indicator 3,
2004
The eventual discontinuation of [...] temporary settlements should bemanaged to ensure the satisfactory removal and re-use of all material or
waste that cannot be re-used or that could have an adverse eect on the
environment.
SPHERE Handbook, Shelter and Settlement Standard 6, Guidance note 5, 2004
-
7/30/2019 Waste Guide
4/46
2
CKNOWLEDGEMENTS
Grateul acknowledgement is made to the ollowing
people who have provided content, comments and
support to this publication:
Joseph Ashmore, Maoya Bassiouni, Martin Bjerregard,
Tom Corsellis, Igor Fedotov, Heiner Gloor, DaveHodgkin, Orlando Hughes, Ivan Ivanov, Charles Kelly,
Manoucher Lolachi, Sajjad Malik, Paul Neale, David
Stone, Karen Walker, Grant Wroe-Street and Jake
Zarins.
-
7/30/2019 Waste Guide
5/46
3
CONTENTS
im 1
cknowledgements 2
1. Introduction 4
2. Nature of Disasters and Scale of Operations 83. Building Waste Generation 10
4. Composition of Building Waste Materials 12
5. Priorities 14
6. Re-use, Recycling and Disposal 16
7. ccess and Transport 19
8. Waste Sorting 20
9. Impacts and Hazards 2410. Community Involvement and Communications 25
11. Responsibility and Legal Issues 26
12. Health and Safety 28
13. Capacity Building and Employement
Generation 31
14. Conclusions 32
ppendix 1 Waste Processing Flowchart 33
ppendix 2 Re-use and Recycle Potential 34
ppendix 3 Waste Management Plan 38
References 41
Useful websites 42Photo Credits 43
3
-
7/30/2019 Waste Guide
6/46
4
Waste created in adisaster poses signicant
challenges to relief and
recovery operations and
a rapid return to a normalsituation.
1. INTRODUCTION
Ater a disaster or conict, the rst priority is to meet
the urgent survival needs o the afected population.Oten this includes the provision o emergency
ood, water and sanitation, as well as shelter and
medical care. However, the timely and appropriate
management o waste generated during a disaster can
also quickly become a major concern, oten adding to
problems already aced by afected populations.
Waste created in a disaster poses signicant challenges
to relie and recovery operations and a rapid returnto a normal situation. Disaster debris needs to be
removed rom roads, homes and public acilities
beore survivors can begin to rebuild their lives and
livelihoods. Let uncollected and unmanaged, such
waste can hinder emergency response operations and
create additional public health and environmental
risks.
This booklet outlines the basic principles o centralisedbuilding waste management programmes, including
some key issues that shelter practitioners may
encounter. It also identies potential or the re-use
o certain building waste materials in emergency,
temporary or permanent shelter construction
programmes or afected populations.
The booklet ofers a range o practical, proven
advice and guidance and outlines possible contentor a waste management plan (Appendix 3) to help
practitioners respond in the rst instance.
-
7/30/2019 Waste Guide
7/46
5
Disaster debris is oneof the rst sources of
emergency shelter and
energy.
In most cases, shelterpractitioners will be
involved in supporting the
activities of the aected
populations.
The composition ofbuilding waste varies
according to location,
local building practices,
context and type of
disaster.
1.1 DISSTERS ND WSTE
Debris created in a large scale disaster poses signicant
challenges to relie and recovery operations. Lack
o waste management ater a disaster can have theollowing negative impacts on afected populations
and the environment:
hindering access, reconstruction and
rehabilitation activities;
encouraging uncontrolled dumping;
public health risks; and
hazardous waste risks to peoples health and the
environment.
Yet, i in the haste to recover, disaster debris is dis-
posed o improperly, it will cause uture hardships or
the disaster-afected population.
Waste rom demolition, reconstruction and
rehabilitation o damaged buildings is one o the mostvoluminous types o waste generated by a disaster.
Building waste, however, has the potential to be a
valuable resource. Its use in emergency shelter and
reconstruction eforts can contribute to a reduction
in natural resource extraction. Labour intensive public
works clean-up programmes can assist afected
communities in their post-disaster recovery.
At the same time, disaster debris is one o the rstsources o emergency shelter and energy. In addition,
most disaster debris has intrinsic value to the owner
and considerable use in the recovery efort. Simply
collecting and disposing o all debris without taking
these actors into account will make the recovery
process more costly and more dicult than i the
debris is transormed into a positive contribution to
recovery.
-
7/30/2019 Waste Guide
8/46
6
CSE STUDIES
Case Study 1Japan, 1995
The Hanshin-Awaji earthquake on 17
January 1995 in Kobe destroyed more
than 192,000 buildings as well as roads
and railways. The quantity o demolitionwaste generated rom the site clearing
works was estimated at more than
15,000,000m3.
The majority o the waste was removed
to landll or used or land reclamation in
Osaka bay. Only a minor proportion was
recycled. This resulted in the demolition
waste taking up valuable municipal andhousehold waste landll space, with
resulting negative impacts on the citys
solid waste management systems.
Case Study 2Mexico, 2007
The State o Tabasco, Mexico, was hit by
ooding in October 2007. Over 920,000
people were displaced and over
245,000 homes were afected. A largepercentage o the generated waste was
demolition waste.
Existing waste management services
were not able to deal with the disaster
waste arising rom the ood event and
subsequent recovery phase. A majority
o the waste was removed to uncon-
trolled temporary storage areas causingenvironmental and public health risks.
-
7/30/2019 Waste Guide
9/46
7
Case Study 3The Maldives, 2004
Following the Indian Ocean tsunami
in 2004, approximately 290,000m3 o
demolition waste, combined with an
estimated 50,000m3 o household andother waste, was generated in the Mal-
dives.
The waste was disposed o in uncontrol-
led dump sites and in shallow coastal
waters of beaches. This led to increased
health risks through contact with de-
composing wastes. There was also a risk
o groundwater contamination throughheavy metals leaching through soils.
Case Study 4Kosovo, 1999
During the 1999 war in Kosovo, consi-
derable damage was caused to buil-
dings and structures across the country.
More than 120,000 housing unitswere damaged in 29 municipalities. It
was roughly estimated that the waste
rom damaged buildings and struc-
tures reached a magnitude o 10 million
tonnes.
Through a DANIDA unded environ-
mental programme, the recycling o
building waste was integrated intothe reconstruction work, with recycled
materials being used in new roads and
buildings.
-
7/30/2019 Waste Guide
10/46
8
2. NTURE OF DISSTERSND SCLE OF OPERTIONS
The type and composition o waste varies according to the
location, type and scale o disaster, as illustrated below.
Shelter practitioners may be expected to contribute to
operations on diferent levels. In rare, but welcome, cases they
may be involved in the design o a waste management plan with
government ministries or local and international specialists.
In most cases, however, they will be directly involved in
supporting the activities o the afected populations.
Conict
Post-conict building waste oten contains reduced amounts
o timber, urnishings and personal possessions since the
buildings will oten have been burned. In post-conict situations
there is, however, a risk o unexploded ordnances (UXO), minesand booby traps being present in the building waste. In such
instances, access should be restricted until proessionals have
rst cleared the area.
Banda Aceh
-
7/30/2019 Waste Guide
11/46
9
Pakistan Sri Lanka
Disasters
The nature and scale o waste ollowing a disaster varies
considerably rom one situation to another. In post-tsunami
situations, or instance, the majority o solid building waste
could be washed out to sea by the receding waves. What may
remain, however, is a large volume o mud into which other
materials may be mixed, which may prove dicult or sorting.
In contrast, post-earthquake debris will oten have all o the
materials rom the buildings still present at the ootprint o
the building.
-
7/30/2019 Waste Guide
12/46
10
In a disaster there are our phaseswhere building waste is likely to be
generated.
Disaster
Waste generated by buildings and
inrastructure destroyed by the disaster
itsel.
Search and Rescue
Partial demolition o buildings
to improve access and saety or
emergency response eforts.
Demolition
Demolition o buildings and inrastruc-ture to acilitate reconstruction.
Temporary or PermanentShelter Construction
Waste generated during
reconstruction.
Building waste occurs in every type odisaster and oten represents a large
percentage o the total waste.
The types o waste generated depend
on the nature and location o the disas-
ter, however they can broadly be cate-
gorised as ollows:
vegetation, soils and sediment, ash
and charred wood;
building waste;
domestic waste;
damaged household goods;
hazardous waste;
industrial waste; and
waste rom the emergency res-
ponse, e.g. packaging materials.
3. BUILDING WSTE GENERTION
-
7/30/2019 Waste Guide
13/46
11
Table 1: Major categories o waste in selected events
Hurricane Earthquake Tornado Flood Fire Tsunami ConictCamp
closure
Vegetation a a a a a a
Soil andSediment a a a a
Ash andcharred
wood
a
Buildingwaste a a a a a a a a
Domesticwaste a a a a a a a
Damagedhouseholdgoods
a a a a a a a
Hazardouswaste a a a a a a
Industrialwaste a a a a a a
Relie
waste a a a a a a a a
-
7/30/2019 Waste Guide
14/46
12
4. COMPOSITION OF BUILDINGWSTE MTERILS
The composition o building waste varies according to the location, local building
practices, and the context and type o disaster.
In rural Arica, local construction can be simple, with grass roos, a wood ramework
and mud brick walls.
More complex structures can include breeze blocks, iron sheeting, roong tiles,
rebar and timber.
Cte dIvoire
The Maldives
-
7/30/2019 Waste Guide
15/46
13
In large cities, disaster waste may include a mix o building materials, white goods,
personal belongings and hazardous waste.
It is currently estimated that approximately 50 per cent o the worlds population
live in cities. UN Habitat orecasts that this percentage will increase in the coming
years. This means that a majority o waste rom uture disasters will occur in cities
and will have a typically urban waste composition.
The average composition o building waste in cities in developed countries is shown
below. In developing countries, the percentage o inert materials can reach up to 90
per cent o all building waste.
Estimated average composition o construction and demolition debris in urban settings
Mexico
-
7/30/2019 Waste Guide
16/46
14
5. PRIORITIES
A timely and well planned long-term waste disposal
plan (see Appendix 3 or an example outline) cannot only protect health and saety, but also provide
economic benets through re-use, recycling and/or
sale o materials, according to local needs. It may also:
improve access or immediate relie eforts;
reduce health and environmental risks;
reduce land and landll space taken or dum-
ping;
provide materials or rehabilitation and recons-
truction;
help with income generation through recycling
and re-use;
be a positive action through community recy-
cling; and
reduce the need or double handling o wastes.
A sound and co-ordinated waste management plan
should assess all possible options or each type o
waste. Choose the most viable one on the basis o the
time, practical options, public health, as well as legal,
nancial and environmental considerations.
The management o disaster building waste should
be considered, rom day one, as part o an integraldisaster waste management plan or the afected
area.
The ollowing typical priorities are oten selected
or building waste in a post-disaster situation, with
additional comments with regards the handling o
building waste.
An adequately plannedlong-term waste disposal
plan can provide economic
benets through re-use,
recycling and/or sale ofmaterials, according to
local needs.
Recycling optionsdepend on local
technology and practices
and the market value forthe recycled material.
Direct re-use or resaleof building materials may
happen spontaneously
with local scavengers
salvaging any usable
parts.
-
7/30/2019 Waste Guide
17/46
15
Table 2: Typical priorities or building waste in the post-disaster phases
DESCRIPTION Building Waste Comment
Priority 1
To remove the building waste
(debris) which is impeding
search and rescue operations
as well as the immediate, emer-
gency relie operations (i.e. the
providence o rst aid, ood,
shelter and water).
The site or dumping o the
waste should be selected with
consideration to uture use o
the waste and uture use o
the land on which dumped (i.e.
not to dump building waste on
someones agricultural land).
Priority 2
The removal o damaged buil-
dings and inrastructure which
could cause an immediate
threat to public saety such as
unstable structures and large
piles o unstable rubble in
urban, residential areas.
Handling requires attention to
Health and Saety or the wor-
kers. It also requires attention
to potential legal issues such
as access and ownership o the
waste. Site or dumping o the
building waste as above.
Priority 3
To remove uncontrolled dum-
ped building waste rom urban
areas since i let to lie will o-ten attract dumping o general
wastes (which will reduce the
opportunity to recycle the buil-
ding waste), which in turn can
lead to public health and envi-
ronmental risks.
Handling requires attention to
Health and Saety or the wor-
kers. It also requires attentionto potential legal issues such
as access and ownership o the
waste. Site or dumping o the
building waste as above.
Priority 4
To remove building waste o
damaged buildings rom pri-vate and public plots o land to
enable reconstruction.
Handling requires attention
to Health and Saety or theworkers and there may be an
opportunity to sort the wastes
into recyclables beore trans-
port. It also requires attention
to potential legal issues such
as access and ownership o the
waste. Site or dumping o the
building waste as or Priority 1.
-
7/30/2019 Waste Guide
18/46
16
6. REUSE,RECYLING ND
DISPOSLA successul waste management plan
aims to maximise the re-use o recovered
materials, minimise the volume o waste
requiring ultimate disposal and improve
waste management in the longer term.
Where useul materials are recovered,the volume o the waste requiring
disposal is reduced while the impact o
rebuilding and recovery is diminished
through substituting raw materials with
the recycled materials.
A simplied owchart in Appendix
1 presents the typical steps in han-dling, treating and processing disaster
waste in an urban setting. Appendix 2
highlights some re-use and recycling
options or common materials.
Some options or disaster building
waste are described below.
REUSE
Direct re-use or resale o building
materials is a desirable solution. The
quality o the materials should always
be checked, while options will depend
on local practices and market value.
This oten happens spontaneously.
RECYCLING
Recycling o building waste materials
(or example, crushing concrete to re-
use as gravel) avoids using landll space,
reduces the need to quarry rocks and/orcut trees, can bring economic benets
and is generally good environmental
practice. Recycling options depend on
local technologies and practices and
the market value or recycled materials.
DISPOSL TO LND
Uncontrolled disposal can lead topublic health and environmental risks,
as well as a potential need to move the
waste again once the relie phase has
been completed. Disposing o large
volumes o building waste directly to
landll or dumpsites can use up space
better suited or non-recyclable wastes
and reduce the capacity o existing
municipal solid waste management, isuch a system exists.
REDUCE
Volume reduction o waste at source
is the most desirable long-term option
and should be an integral part o
every waste management plan. For
disaster building wastes, this may
involve reduced packaging or the (re)
construction materials.
-
7/30/2019 Waste Guide
19/46
17
Re-use or recycling o building waste will depend on
the situation, context and demand or materials.
The most common post-disaster operation is the
recycling o concrete and bricks into a gravel or
aggregates material, where these can be used inlow strength concrete, as a sub-base or roads, as
an aggregate or building blocks and as ll under
oundations or on general reconstruction works.
In many cases, this can be an economically and
environmentally viable option ater a disaster as
there may be an increased demand or aggregate in
reconstruction and rehabilitation works.
Many countries have established quality standards orthe recycling o inert building waste into aggregates
or gravel or road base. Check local standards and
specications to ensure that they are met, or reer to
relevant national standards, i they exist.
The value o aggregates and the economic viability o
using recycled concrete, bricks or other building waste
materials depends on local demand, availability and
proximity o natural sources, the availability and costo sorting, crushing and grading recycled materials
and the cost o landll disposal.
The most commonpost-disaster operation is
the recycling of concrete
and bricks into a gravel or
aggregates material.
Recycling of a materialwill only be a feasible
option if it is economically
viable.
6.1 ECONOMICS OF WSTE RECYCLING
Recycling will only be easible i it is economically
viable. This will depend largely on the market value
o the material, once produced. In addition, other
actors may also have an inuence, such as:
enorcement o stopping illegal quarrying since
this would otherwise produce a competitive
material to that produced through recycling;
how easy it is to dump building waste as regards
costs and legality o dumping, i.e. i it is easier
to dump waste and buy cheap quarry materialsthen it may be dicult to support recycling rom
an economic viewpoint;
-
7/30/2019 Waste Guide
20/46
18
Stacked cleaned bricks ready or re-use at the OxamGB re-use/recycling yard in Banda Aceh.
Building blocks or reconstruction purposes whichcan be produced rom recycled building waste,Pakistan.
Recycled aggregate rom crushed building waste inKosovo, as used or road construction or low strength
concrete oundations.
the ease with which the material can be recycled,
i.e. has it been mixed with household waste and
would the removal o non-recyclables be too
expensive and high risk to complete; and
the level o acceptance or the recycled materialinto the (re)construction market, i.e. will engi-
neers accept to use recycled materials compared
with natural quarry materials that they may be
more amiliar with?
Post-disaster reconstruction work normally places a
huge demand on quarry materials so there are typi-
cally good economic grounds or recycling buildingwaste. An exception might be in rural areas with good
access to unlimited quarries.
A long-term waste management plan (see Appendix
3) arising rom the post-disaster waste management
work may include a ocus on developing a market or
recycled materials where it does not exist. This can
be developed over time in collaboration with the
relevant authorities.
-
7/30/2019 Waste Guide
21/46
19
Transportation ofthe building waste can
be done by a range of
methods, from wooden
carts pulled by animalsto heavy duty excavators,
trucks and skips.
In many cases it ispreferable to avoid the use
of heavy machinery.
7. CCESS NDTRNSPORT
Transporting waste is an important economic and
logistical actor to be considered, given the large
volumes that may need to be dealt with (see also
Section 11). Following a disaster, there is commonly a
shortage o vehicles and the road inrastructure may
have been damaged. This will have a considerable
impact on the selection o temporary waste storage
sites.
There are two main mechanisms or moving building
waste rom its source to the treatment site or
recycling, re-use or disposal:
push which entails paying an organisation i.e.
contractor or through cash-or-work to bring
the building waste to the treatment site; or
pullwhich entails paying a xed sum o money
or every load o building waste brought to thetreatment site, e.g. US$1 per wheelbarrow o
bricks.
One positive advantage o the pull mechanism is that
it allows or the local community to participate in the
building waste clean-up work and thus spreads the
economic benets o building waste work deeper
into the community.
An example o this was the Oxam GB re-use yard in
Banda Aceh ollowing the 2004 Indian Ocean tsunami
where the yard paid a set rate per type o building
waste delivered. The building waste was subsequently
cleaned and re-used/recycled in a variety o products.
-
7/30/2019 Waste Guide
22/46
20
Islamic Relie project or the clearing andcleaning o building wastes (including
rough cut stones) and subsequent re-useor new oundations .
8. WSTE SORTING
The ollowing sub-sections present some typical
orms o handling and processing building waste mainly in connection with centralised waste
management programmes rom its location at
source to nal end-use or disposal.
The use o mechanical clearance should be avoided,
or careully controlled, in order to respect peoples
property and possessions and the act that human
corpses might be in the waste. A possible exception
to this might be the clearance o roads or emergencyaccess.
The main emphasis o recycling inert building waste
is to remove non-recyclable materials such as plastic,
timber, and household urnishings beore processing
begins. This results in a quality product which can
be used in road construction and or low strength
concrete.
Building waste will oten be mixed, or example
recyclable concrete and bricks may be mixed with
urnishings and other non-recyclable materials. In
order to realise the maximum value rom building
waste in terms o items or re-use and recycling, it
is typically necessary to sort through the waste to
extract the non-recyclables.
This can be done in a variety o ways, rom basic
manual sorting to mechanical means, the latter being
more appropriate or larger volumes.
Manual Sorting
Building waste can be strewn out on the ground and
manual labour used to pick out the non-recyclablesand other items. Remaining material such as concrete
and bricks can then be collected or processing.
-
7/30/2019 Waste Guide
23/46
21
A mechanical grizzly to the let sorts ner materials rom theoversized concrete and bricks, ater which large items can beplaced on a picking station (to the right) or manual separation.
Typical conveyors with adjustable belt speed or use as a pickingstation.
A primary screening eedstock or the removal o soil raction andpossible contaminants plastics, paper, non-recyclables beorecrushing.
Primary Mechanical Sorting
Alternatively, a basic plant can be constructed
locally for the mechanical sorting of building
waste. This provides a higher throughputwith fewer personnel.
A mobile setup is also possible which allows
the equipment to be moved from one site to
another for on-site separation.
Picking stations are useful since they can be
linked to a slow moving conveyor belt from
which waste can be removed manually.These units vary in size from mobile picking
stations to larger central locations with a
large, stationary setup. Such belts enable up
to six people to safely work at the unit, three
on either side. The belt is normally used in a
raised position to allow the operators to work
at waist height.
Primary Screening Unit
Should a larger throughput be required, then
a more sophisticated primary screening unit
can be used to remove the ner soil fractions
from the building waste. These units are
highly mobile and only require a single axle
truck to move around the site.
-
7/30/2019 Waste Guide
24/46
22
Locally manuactured mobile crusher in a Pakistan quarry.
Crushing o building waste in Pakistan ollowing the 2005earthquake, using a small, mobile hand-ed crusher on tracks.
Crushing o building waste in Kosovo using a medium-sizedmobile crusher (yellow machine to the let) and a screeningunit or separation o the crushed material into three sizeractions (green plant to the right).
WSTE CRUSHING
Crushers can generally crush glass,
porcelain, granite, bricks, blocks, asphalt
and re-inorced concrete. Dependingon the location and context, a variety o
crushers are available, each suitable or
difering purposes and end-products.
They can range in size rom on-site
mobile crushers capable o processing
rom 45-400 tonnes per day to ull-scale
plants that can handle up to 500 tonnes
per hour.
Some commonly used crusher models
appropriate or post-disaster work
are described below. Note that or all
options there is also a solid second-
hand market or crushers and screeners.
One does, however, need to ensure that
the plant is delivered with adequate
guarantees, warranties and service
arrangements.
Locally Manufactured
Crushers
Many countries have an active quarry
industry so there may already be some
pre-existing facilities and services that
might be used to deal with certain typesof waste stream. It is also possible to have
locally manufactured small-scale crushers
produced to specication and used in
the post-disaster clean-up and recycling.
Discussions with manufacturers should
include consideration for the handling of re-
inforcement bars when crushing concrete,
as this often requires a larger aperture for
the outlet of the feed hopper.
-
7/30/2019 Waste Guide
25/46
23
Small Mobile Crushers
Should locally manuactured crushers
not be available, there are several
options or the purchase o small,
mobile crushers which can be used inurban and rural areas.
These smaller crushers can be
transported by typical 4x4 vehicles
and are operated by remote control,
thus allowing access to even the
most rural areas o a disaster-afected
community. The output crushed
material is not suitable or engineered
roads or low strength concrete but can
be used or access road rehabilitation
or as general ll.
Medium Mobile Crushers
For larger quantities o building
waste, a medium-sized mobile plantcan be used, which would normally
eed straight into a screening unit or
the separation o the crushed material
into two or more size ractions. The
nal product size will depend on the
required use o the recycled material.
Medium-sized crushers or recycling
building waste will require anoverband magnet or the separation
o the re-inorcement bars rom the
crushed material.
Large Stationary Crushers
Although not typically used in post-
disaster work since the spread o
building waste in a geographic area
makes a mobile crushing solutionmore cost-efective rom a logistics
view, a stationary crushing unit can be
implemented i the quantity in an urban
area is signicant, i.e. more than one
million tonnes o building waste.
Stationary crushers and screening units
have a higher throughput than any othe mobile solutions. They do, however,
require a larger acility inrastructure or
recycling and stockpiling, or example,
and are more costly.
TIMBER ND OTHER WSTE
For timber and vegetal debris withinbuilding waste, grinders and shredders
can be used to reduce the volume o this
waste stream. It can then, or example,
be used as mulch in landscaping or or
compost.
For other waste streams not typically
directly recyclable or re-usable, the
norm is or these materials to bedisposed o at an authorised dumpsite
or landll. In some cases it may be
prudent to allow local communities
access to this waste stream under
careul working conditions to extract
any materials which they may nd o
use. One such example is plastic which
can be used to make products such asbags or sale in the local market.
-
7/30/2019 Waste Guide
26/46
24
9. IMPCTS ND
HZRDS
Lack o waste management ater a disaster can have
the ollowing negative impacts on the afected
populations, and the environment. It may:
hinder access, reconstruction and rehabilitation
activities;
encourage uncontrolled dumping;
represent a continued and increased hazard and
public health risk; cause hazardous waste risks to health and the
environment; and
be detrimental to uture, normal waste opera-
tions.
The use o mechanised clearance should be avoided
or very careully controlled because o plot bounda-
ries, bodies in rubble and personal possessions. It is,
however, commonly used to re-open roads to allow
emergency access.
Uncleared waste may continue to represent a hazard
risk. Atershocks, or example, can urther destroy
buildings that have not been secured, while high
winds might lit uncleared debris such as iron shee-
ting into the air, which could be a potential threat to
people.
Uncleared waste or clearance operations themselves
can also impact on surace water drainage or sewage
and utilities inrastructure.
The use of mechanisedclearance should be
carefully controlled.
Uncleared waste canpresent continued or
increased hazard risks.
-
7/30/2019 Waste Guide
27/46
25
Steel, bricks, timberand tiles are likely to
oer possibilities for
transitional shelter and
might be the startingpoint for reconstruction
or some form of revenue
generation.
Take steps to ensurethat debris items with
value remain accessible tothe original owner.
10. COMMUNITY
INVOLVEMENT ND
COMMUNICTIONSAs in all other areas, ater a disaster it is vital to
work with the afected population, local authorities,
competent authorities and local contractors on waste
management.
The rst people on the scene o a disaster are the a-
ected population. Most communities will have someorm o committee in place. Involving the community
will help identiy what normal practice is, develop pre-
erred options or waste collection, and develop pu-
blic health and other messages associated with waste
management. Strategies or disseminating public in-
ormation can include signs, posters, yers, and media
such as newspaper articles, radio announcements or
TV announcements, as well as public meetings.
Where the community is involved, waste sorting at
source will happen almost automatically. Key points
have been highlighted above.
Where there is no pre-existing disaster waste
management plan, the rst step is to establish a large-
scale public inormation plan on how to deal with the
large quantities o waste generated by the disaster.
-
7/30/2019 Waste Guide
28/46
26
The rst people on thescene of a disaster are the
aected population.
Where the community isinvolved, waste sorting at
source will happen almost
automatically.
11. RESPONSIBILITY
ND LEGL ISSUES
Three sets o legal issues usually arise in disaster
debris management: value and ownership, access
and safety.
Value and ownership: Destroyed inrastructure is oten
the only resource let to afected amilies ollowing a
disaster, not only peoples personal possessions such
as urniture but also steel, bricks, timber and tiles. For
many, these ofer distinct possibilities or transitionalshelter and might even be the starting point or
reconstruction or some orm o revenue generation.
Special consideration might need to be given to
multiple owners in multi-storey buildings.
All disaster debris had some value beore the disaster,
some o which might still remain ater the event has
taken place. For instance, the owner o a damaged
building may want to retain ownership o the bricksbecause o their value in ofsetting a need to purchase
bricks with which to rebuild. It is not appropriate or
debris management operations to deprive an owner
o items which, while damaged by a disaster, are still
o some value. Special consideration might need to
be given to multiple owners in multi-storey buildings.
Debris management eforts should thereore take
steps to ensure that debris items with value remainaccessible to the original owner. I people are not
able to return to their ormer homes, then the owner
should be compensated at air market values
or the items which are taken and used or another
purpose, or example, bricks rom damaged buildings
being used or road sub-surace.
Addressing ownership and value issues needs to
be planned in advance o debris removal. Disastersurvivors will need to be consulted to the degree
possible.
-
7/30/2019 Waste Guide
29/46
27
Legal actions by government authorities are also
needed to avoid disputes over ownership. This is
particularly the case where previous owners o di-
saster debris may have been killed during the di-
saster, or where clearance activities uncover objects
o economic possibly cash, gold or jewellery or
example or sentimental value.
The need to preserve plot boundaries as a starting
point or determining land rights and subsequent
reconstruction will require specic attention.
Local government authorities and disaster survivors
should be consulted on the necessary legal and so-
cial steps required to permit access to private pro-perty. These procedures should be in place beore
debris clearance begins, and include how to handle
valuables and personal possessions.
Access is also an issue when establishing tempo-
rary processing areas or permanent disposal sites.
For the latter, some level o environmental review
should rst occur ahead o the land being legalised
through the normal but expedited adminis-trative process. In the case o the ormer, tempo-
rary authorisation should be received rom the site
owner, which should speciy the condition o the
site beore use as well as what condition it should
be in when returned to the owner.
Saety issues are dealt with in the ollowing section.
Local governmentauthorities and disaster
survivors should be
consulted on the necessary
legal and social stepsrequired to permit access
to private property.
-
7/30/2019 Waste Guide
30/46
28
12. HELTH ND
SFETY
Building waste generated by disasters can include
materials and wastes that are hazardous to human
health as well as the surrounding environment. These
require identication and special handling.
The need to preserve plot boundaries as a starting
point or determining land rights and subsequent
reconstruction will require specic attention.
Additional hazardous wastes such as oils, chemicals
and heavy metal containing items should be identied
and removed rom the waste.
In addition to actual waste materials, in post-conict
situations there is also the risk o UXO and mines
being present in the building waste. Co-ordination is
required with relevant and specialist organisations in
the eld to ensure that building waste is clear o such
ordnance and sae to handle.
Protective clothing should always be provided when
dealing with waste, particularly mixed waste streams.
This includes adapted ootwear hard boots to pre-
vent spikes entering the sole and minimise the risk
o harm rom heavy materials dropping onto eet
gloves, overalls and masks. Equipment such as sho-
vels, buckets, carts and skips should also be provided.
Where possible, people working with waste should
have access to changing and washing acilities.
-
7/30/2019 Waste Guide
31/46
29
Case Study 5
Indian Ocean Tsunami
Ater the 2004 Indian Ocean tsunami, UNDP and its partners considered a numbero livelihood restoration and creation projects in waste management, as well as
opportunities or viable recycling business start-up. Projects included the ollowing:
composting projects to make organic ertiliser or rice padi and park
rehabilitation;
plastic processing acilities to make and sell plastic chips to recyclers;
provision o restored tsunami wood to urniture manuacturers;
wood-red brick kiln rehabilitation projects to make red bricks using tsunami
wood;
wood-red limestone kiln rehabilitation projects to make lime using tsunami
wood;
charcoal manuacture rom tsunami timber; and
provision o stone crushers to make secondary aggregate or use in brick
projects, concrete preparation and/or as a road base.
Those employed under a cash or work scheme were either pre-existing scavengers,people recruited or the project or those employed directly rom camps housing
some o the displaced people. The scheme tried to ensure that the most vulnerable
people rom within the communities were considered. Employment o women was
particularly encouraged. In rubble clearance and recycling activities, the programme
promoted gender-sensitive approaches in work and wage distribution. The
programme also sought to strengthen the long-term capacity o local government
on waste management through working with district sanitation departments.
Source: Tsunami Recovery Waste Management Plan
-
7/30/2019 Waste Guide
32/46
30
Case Study 6
Sri Lanka
In a shelter programme or returnees in eastern Sri Lanka, the Norwegian ReugeeCouncil (NRC) encouraged beneciaries to re-use bricks and blocks or shelter
reconstruction.
Houses had been destroyed in the ghting and NRC was providing a small core
shelter that provided a 9m2 ull masonry room with an additional 9m2 o open, but
rooed, area which had oundations. Beneciaries provided inll or the raised oor
using rubble rom old houses. They could also use salvaged bricks/block to ll in the
walls or the open section o the house.
-
7/30/2019 Waste Guide
33/46
31
13. CPCITY BUILDINGND EMPLOYMENT
GENERTIONAside rom voluntary participation within the
community, well-designed employment and cash or
work programmes can help support the overall clean-
up efort as well as provide income to vulnerable
populations who may have lost their employment as
a result o the disaster.
Immediate employment activities can be designed
to rehabilitate and improve access to public acilities,
inject cash into displaced populations who have lost
sources o income, and to reduce trauma among
victims through the provision o work.
Implementation o waste recycling and recovery
projects can restore livelihoods. Much o the waste
is recoverable and recyclable or use in rehabilitation
and reconstruction. Re-use o recycled timber,
concrete and bricks will reduce the need to cut trees
or new timber and quarry rock or use in concrete,
drainage, roads and ll.
Local non-governmental organisations (NGOs) and
local companies involved in recycling and waste dis-
posal beore a disaster can be valuable collaborators
in the post-disaster management o debris. Using lo-
cal partners will acilitate operations and strengthen
local capacity to manage waste and debris in the
uture.
Well-designedemployment and cash
for work programmes
can help support the
overall clean-up eort aswell as provide income to
vulnerable populations
who have lost their
employment as a result
of the disaster.
Using local partnerswill facilitate operations
and strengthen local
capacity to manage
waste and debris in the
future.
-
7/30/2019 Waste Guide
34/46
32
14. CONCLUSIONS
This guide does not attempt to address all aspects o this large
and complex topic. It is intended to highlight some key issues thatshelter specialists may encounter during diferent levels o disaster
and post-disaster operations.
Although building waste management may not seem like an
immediate concern during and ater a disaster, the large quantities
o waste oten generated at such times means that this issue needs
careul consideration.
To maximise the re-use o recovered materials, it can be useul
to minimise the volume o waste requiring ultimate disposal. It is
important that waste management is properly planned, organised
and monitored, Complex issues such as land rights, legal aspects,
saety concerns and the livelihoods o afected populations need to
be considered.
Further reerences and links are provided at the end o this document
or more in-depth inormation.
-
7/30/2019 Waste Guide
35/46
33
PPENDIX 1
WSTE PROCESSING FLOWCHRT
This simplied owchart presents some o the typical steps in handling, treating
and processing disaster waste. It is based on the assumption that a centralised
waste disposal plan is in place. Each step can be carried out at the source, e.g. a
damaged building, or at an of-site processing or disposal site.
-
7/30/2019 Waste Guide
36/46
34
PPENDIX 2
REUSE ND RECYCLE POTENTIL OFSTNDRD BUILDING MTERILS
MTERIL REUSE RECYCLE
Plastics Check local practices and demandor recycled plastic.
Check local practices and demandor recycled plastic.
WOOD
Timber Wood can be re-used or a varietyo diferent purposes, rangingrom low-quality, temporary
work like survey pegs and boxingor concreting to high-quality,permanent uses like oor boards,
beams and other architecturaleatures i the recovered material isin a suitable condition.
Depending on the type o disaster,
rotting, humidity, splitting, presenceo nails or screws can afect the
potential or re-use.
Untreated timber of-cuts can bechipped into mulch and used inlandscaping, animal bedding or
used as uel. Depending on thecontext, wood rom constructionand demolition waste competes
with orestry and manuacturingwood waste as an input orindustrial urnaces and boilers,
particularly in pulp and paper mills.
Bamboo Bamboo is requently used inlow-cost construction such ashuts and encing. During camp
closure, bamboo structures can bedismantled and transported or re-use or sale at a local market.
It can be afected by ungus indamp climates and attacked by
insects. Check the quality beorere-using or reselling.
Other uses include compost or chip,dry and use as uel.
-
7/30/2019 Waste Guide
37/46
35
MTERIL REUSE RECYCLE
INERT MTERILS
Bricks / Blocks Bricks and blocks can be cleanedand re-used i their quality is
acceptable. They can be resold tothe community and / or re-used inreconstruction programmes. Thepresence o cement mortar or glues
can hinder re-use as they are unableto be cleaned of.
Diferent orms o brick can berecycled or re-use in reconstruction
programmes.Mud bricks degrade easily and canbe broken up by hand and used as
inll or latrines and trenches. Theycan also be crushed by hand andspread across the land.
Bricks can be crushed to a suitablesize and recycled as aggregate tobe used in concrete. They can be
broken to use as hardcore as sub-bases to concrete work. They canalso be broken or crushed as inll in
landscaping applications.
Concrete Damaged concrete cannot be
directly re-used.
During land rehabilitation ater
camp closure, concrete can becrushed by manual labour andre-used as ller or abandoned
latrine pits, drainage trenches andother surace irregularities. This alsoprovides local income.
Concrete can be crushed and
recycled as aggregate or hardcoreor building and road base materialor oundations
Concrete can be crushed manually;with a mobile crushing unit or
transported to a specialisedconcrete crushing plant. Location,volume o concrete waste, localdemand or aggregates and
availability o other types oaggregates are determining actorsin the choice o crushing method.
The presence o local quarries orriverbeds providing gravel couldmean that recycled aggregate is
not viable.Steel rebar may block crushing
machines i they are not designedto separate the steel rom theconcrete. Proper assessment must
take place to ensure no asbestos ispresent prior to crushing.
-
7/30/2019 Waste Guide
38/46
36
MTERIL REUSE RECYCLE
sphalt Asphalt cannot be re-used withoutprocessing.
Asphalt is requently recycledduring normal road resuracing in
developing countries.
Commonly used asphalt recyclingequipment includes eed systemsadded onto a large xed asphaltproduction plant or small mobile
pieces o equipment or asphaltreheating.
Plasterboard Plasterboard is likely to be damagedduring a disaster and thereore
unsuitable or re-use.
Gypsum makes up approximately90% o the weight o a piece o
plasterboard. Gypsum can berecovered and used : in the manuacture o new
drywall; as an ingredient in the production
o cement;
or application to soils and cropsto improve soil drainage andplant growth;
an ingredient in the production oertiliser products;
an additive to compostingoperations.
However, this is unlikely in mostemergency responses.
ROOFING MTERILS
Roof thatching The type and quality o thatching
material can vary. It is prone todecay in damp conditions and canbe ruined by vermin. Thatched roos
are also very ammable. Thatching
is usually replaced once a year andis unlikely to be re-used or sold.
Thatching can be composted where
composting acilities are available.In the case o IDP or reugee campclosure, it can be spread on the
ground or ploughed into the soil
and let to decompose naturally.
Roong tiles I in reasonable condition, roongtiles can be re-used.
Recovered tiles can be crushed andused as aggregate, landscaping or
inll purposes. Check local marketor demand and prices.
Corrugated iron
sheets
I in reasonable condition, thesheets can be re-used. Howevercorrugated iron sheets can easily
corrode.
Scrap metal is a lucrative businessin most countries. Corrugated ironsheets can be sold and exported
to iron smelting plants. Check local
market or demand and prices.
-
7/30/2019 Waste Guide
39/46
37PPENDIX 2: WSTE PROCESSING FLOWCHRT
MTERIL REUSE RECYCLE
OTHER
Metals Demand or resale and recyclingo scrap metals is high in most
countries. Iron and steel are themost recycled materials worldwide.Steel is unique among majorconstruction materials in that it
always contains recycled content;it is completely recyclable at theend o its product lie and may berecycled without loss o quality. It
can be smelted and recycled.Check local demand and prices,which can vary according to
location.Steel rebar Rebar cannot be re-used or
structural purposes as it will havelost its main properties
In low cost shelter, rebar is oten
stripped by the resident populationand sold on local markets. Checklocal markets or demand and
prices.
The presence o rebar can
complicate the crushing oconcrete. Some specialisedcrushing machines have magnets
to automatically separate the steelrom the concrete. Others requireprior sorting.
Hazardous waste Hazardous materials shouldbe identied at source andimmediately separated rom the
rest o the waste stream to avoidcontamination.
Hospital waste, agriculture
related wastes (e.g. pesticides andertilisers), oil and oil contaminated
wastes should be identied assoon as possible and collected anddisposed o by trained personnel.
The recycling o hazardousmaterials should only beundertaken by trained proessionals
with appropriate protective gear.
The presence o asbestos should
be identied as soon as possible.
It should be separated rom othertypes o waste and collected and
disposed o by trained specialists.
Miscellaneous Electronic debris should beseparated rom other wastes. They
should be disposed o in speciallandlls, i available. Check localpractices.
White goods, such as rerigerators,stoves, washers and dryers should
be segregated and recycled, ipossible. Check local practices.
-
7/30/2019 Waste Guide
40/46
38
PPENDIX 3
MIN ELEMENTS OF WSTEMNGEMENT PLN
The ollowing points summarise some key considerations in planning a debris
management programme. The planning should be done, where possible in
collaboration and agreement with other international organisations involved in
disaster response, the Emergency Shelter and/or WASH Cluster i applicable, local
authorities, local waste management service companies or organisations, local
NGOs and community-based organisations (CBOs).
1) ssess the post-disaster debris situation with relevantpartners and determine:
existing waste handling capacity;
types o debris;
presence o hazardous materials;
quantities (volumes) o materials;
whether or not there is an existing waste management plan; and
location o diferent types o materials houses, actories, public spaces and
so orth.
2) Understand the scope of debris management eorts whodoes what by:
consulting with clusters such as Emergency Shelter and WASH, i in place.
3) Determine legal requirements and social norms related toassessing private property and collecting debris:
who owns the waste?
who has liability?
are there any disaster exemptions?
site ownership issues.
-
7/30/2019 Waste Guide
41/46
39
4) Determine whether waste processing will take place on-siteor whether it will be transported to a central processing site.
On-site processing should be used i most o the debris will be let or use by
the owner.
5) Determine whether processing will be done throughlabour-intensive methods, machine intensive methods or acombination of both.
Machine intensive methods are usually done of-site.
6) Consult with local authorities and disaster survivors oncompensation issues and how much and how compensationwill be paid.
7) Establish a protocol for handling valuables and personaleects collected.
8) Establish personnel and equipment requirements for debrisprocessing.
9) Dene management and reporting requirements for debriscollection and processing activities.
10) Identify specialists services if available procedures andlocations for handling and disposal of hazardous waste.
11) Develop a training plan for personnel involved in theoperation including:
handling o hazardous materials;
valuables and personal possessions; and
saety and any other skills required.
-
7/30/2019 Waste Guide
42/46
40
12) Develop a budget covering:
labour;
equipment and machinery;
transport;
management tasks;
compensation requirements; and
saety requirements.
13) Develop a schedule covering the debris disposal operation.
14) Develop an exit strategy that includes:
realistic and veriable targets;
a transition to existing authorities, private sector waste management
organisations or local or international NGOs, depending on available capacities;
and
consideration o alternative approaches such as the establishment o a CBO
with project management responsibilities early in the project process.
15) Begin implementation.
-
7/30/2019 Waste Guide
43/46
41
REFERENCES
Basnayake B., Chiemchaisri C., Visvanathan C. (2006) Clearing up ater the Tsunami
in Sri Lanka and Thailand.
Baycan, F and Petersen, M. (2002) Disaster Waste Management Paper at ISWA 2002
Annual Congress, Istanbul.
Corsellis, T. and Vitale, A. (2005) Transitional Settlement: Displaced Populations.
DWR / UNEP (2008) Disaster Waste Management Assessment Tskhinvali, South
Ossetia, Republic o Georgia.
GEIDE (2007) Dchets post-catastrophe - risques sanitaires et environnementaux.
NRC (2009) Camp Management Toolkit.
The SPHERE Project (2004) Humanitarian Charter and Minimum Standards in
Disaster Response.
SRSA / DWR / PROACT (2008) Disaster Waste Management Assessment Tabasco,
Republic o Mexico.
UNDP (2005) Tsunami Recovery Waste Management Programme.
UNEP (2006) Environmental Considerations o Human Displacement in Liberia. A
Guide or Decision Makers and Practitioners.
UNEP/ ISWA/ DWR (2006) Pakistan Earthquake Disaster Waste Management Plan.
UNEP (2005) Maldives Post-Tsunami Environmental Assessment.
UNEP (1993) Sustainable building and construction: Facts and gures.
UNHCR (2005) Environmental Guidelines.
UNHCR (2007) Handbook or Emergencies.
UNOCHA / IFRC / CARE International (2009) Timber as a Construction Material in
Humanitarian Operations.
US EPA (1995) Planning or Disaster Debris.
-
7/30/2019 Waste Guide
44/46
42
USEFUL WEBSITES
Aggregain Online Guide to Sustainable Aggregates: www.aggregain.org
Construction Waste Management in Sri Lanka: www.cowam-project.org
Disaster Waste Recovery homepage: www.disasterwaste.org
Groupe dExpertise et dIntervention Dchets Post-Catastrophe:
www.robindesbois.org/geide
International Society or the Environmental and Technical Implications o
Construction with Alternative Materials: www.iscowa.org/
International Solid Waste Association: www.iswa.org/web/guest/home
Online Guide to Drywall Recycling: www.drywallrecycling.com/
Recycling Construction Debris article: www.architectureweek.com/2001/0926/
environment_1-2.html
Shelter Centre website: www.sheltercentre.org
Swiss Resource Centre and Consultancies or Development: www.skat.ch/
Training Manual: Debris Management in Disaster Recovery: www.stopwaste.org/
docs/disaster_debris_management_training_manual.pd
UNEP Publications: www.unep.org/publications
Waste & Resources Action Programme. Tips and Suggestions or Uses o Recycled
Materials in Construction: www.wrap.org.uk/construction/index.html
-
7/30/2019 Waste Guide
45/46
43
PHOTO CREDITS
Danish International Development Agency 7
Disaster Waste Recovery 8, 18, 22, 23Golder Associates 8, 18, 23
Islamic Relie Pakistan 21, 23
NRC (J. Zarins) 31
Oxam 18
Portall 22
ProAct Network (K.Walker, J. Godson) 6, 12, 13
UNDP 8, 23
UNEP 6, 7
-
7/30/2019 Waste Guide
46/46
Rue de Cornavin 111201 Geneva
Switzerland
Tel: +41 22 755 3777
Fax: +41 22 755 3779Email: [email protected] page: www.sheltercentre.org
Les Deux CedresAvenue Alred-Cortot 7D
CH - 1260 NyonSwitzerland
Tel: + 41 22 362 53 84Fax: +41 22 362 53 85Email: [email protected] page: www.proactnetwork.org