Waste Guide

download Waste Guide

of 46

Transcript of Waste Guide

  • 7/30/2019 Waste Guide

    1/46

    Planning

    Centralised Building

    Waste ManagementProgrammes in

    Response to Large

    Disasters

  • 7/30/2019 Waste Guide

    2/46

  • 7/30/2019 Waste Guide

    3/46

    1

    IM

    This booklet is a short guide or shelter practitioners with little experience o centralised disasterwaste settings, mainly in response to large disasters. It highlights key issues and priorities odisaster waste management in diferent settings. It provides simple examples o re-use and

    recycling o building waste materials in temporary and permanent shelter programmes. Furtherreading and other sources o more in-depth inormation are provided.

    This project is a collaboration between ProAct Network, Disaster Waste Recovery (DWR) andShelter Centre. It is unded via the Shelter Centre Conict and Humanitarian Fund Programme

    supported by DFID.

    This booklet can be downloaded rom www. proactnetwork.organd www.sheltercentre.org

    ...the re-use of materials salvaged from damaged buildings should bepromoted where feasible, either as primary construction materials (bricks or

    stone masonry, roof timber, roof tiles, etc.) or as secondary material (rubble

    for foundations or levelling roads, etc.).SPHERE Handbook, Shelter and Settlement, Standard 5: Construction, Guidance note 1, 2004

    ...the production and supply of construction material and the building

    process minimises the long-term depletion of natural resources.SPHERE Handbook, Shelter and Settlement Standard 6: Environmental Impact, Key Indicator 3,

    2004

    The eventual discontinuation of [...] temporary settlements should bemanaged to ensure the satisfactory removal and re-use of all material or

    waste that cannot be re-used or that could have an adverse eect on the

    environment.

    SPHERE Handbook, Shelter and Settlement Standard 6, Guidance note 5, 2004

  • 7/30/2019 Waste Guide

    4/46

    2

    CKNOWLEDGEMENTS

    Grateul acknowledgement is made to the ollowing

    people who have provided content, comments and

    support to this publication:

    Joseph Ashmore, Maoya Bassiouni, Martin Bjerregard,

    Tom Corsellis, Igor Fedotov, Heiner Gloor, DaveHodgkin, Orlando Hughes, Ivan Ivanov, Charles Kelly,

    Manoucher Lolachi, Sajjad Malik, Paul Neale, David

    Stone, Karen Walker, Grant Wroe-Street and Jake

    Zarins.

  • 7/30/2019 Waste Guide

    5/46

    3

    CONTENTS

    im 1

    cknowledgements 2

    1. Introduction 4

    2. Nature of Disasters and Scale of Operations 83. Building Waste Generation 10

    4. Composition of Building Waste Materials 12

    5. Priorities 14

    6. Re-use, Recycling and Disposal 16

    7. ccess and Transport 19

    8. Waste Sorting 20

    9. Impacts and Hazards 2410. Community Involvement and Communications 25

    11. Responsibility and Legal Issues 26

    12. Health and Safety 28

    13. Capacity Building and Employement

    Generation 31

    14. Conclusions 32

    ppendix 1 Waste Processing Flowchart 33

    ppendix 2 Re-use and Recycle Potential 34

    ppendix 3 Waste Management Plan 38

    References 41

    Useful websites 42Photo Credits 43

    3

  • 7/30/2019 Waste Guide

    6/46

    4

    Waste created in adisaster poses signicant

    challenges to relief and

    recovery operations and

    a rapid return to a normalsituation.

    1. INTRODUCTION

    Ater a disaster or conict, the rst priority is to meet

    the urgent survival needs o the afected population.Oten this includes the provision o emergency

    ood, water and sanitation, as well as shelter and

    medical care. However, the timely and appropriate

    management o waste generated during a disaster can

    also quickly become a major concern, oten adding to

    problems already aced by afected populations.

    Waste created in a disaster poses signicant challenges

    to relie and recovery operations and a rapid returnto a normal situation. Disaster debris needs to be

    removed rom roads, homes and public acilities

    beore survivors can begin to rebuild their lives and

    livelihoods. Let uncollected and unmanaged, such

    waste can hinder emergency response operations and

    create additional public health and environmental

    risks.

    This booklet outlines the basic principles o centralisedbuilding waste management programmes, including

    some key issues that shelter practitioners may

    encounter. It also identies potential or the re-use

    o certain building waste materials in emergency,

    temporary or permanent shelter construction

    programmes or afected populations.

    The booklet ofers a range o practical, proven

    advice and guidance and outlines possible contentor a waste management plan (Appendix 3) to help

    practitioners respond in the rst instance.

  • 7/30/2019 Waste Guide

    7/46

    5

    Disaster debris is oneof the rst sources of

    emergency shelter and

    energy.

    In most cases, shelterpractitioners will be

    involved in supporting the

    activities of the aected

    populations.

    The composition ofbuilding waste varies

    according to location,

    local building practices,

    context and type of

    disaster.

    1.1 DISSTERS ND WSTE

    Debris created in a large scale disaster poses signicant

    challenges to relie and recovery operations. Lack

    o waste management ater a disaster can have theollowing negative impacts on afected populations

    and the environment:

    hindering access, reconstruction and

    rehabilitation activities;

    encouraging uncontrolled dumping;

    public health risks; and

    hazardous waste risks to peoples health and the

    environment.

    Yet, i in the haste to recover, disaster debris is dis-

    posed o improperly, it will cause uture hardships or

    the disaster-afected population.

    Waste rom demolition, reconstruction and

    rehabilitation o damaged buildings is one o the mostvoluminous types o waste generated by a disaster.

    Building waste, however, has the potential to be a

    valuable resource. Its use in emergency shelter and

    reconstruction eforts can contribute to a reduction

    in natural resource extraction. Labour intensive public

    works clean-up programmes can assist afected

    communities in their post-disaster recovery.

    At the same time, disaster debris is one o the rstsources o emergency shelter and energy. In addition,

    most disaster debris has intrinsic value to the owner

    and considerable use in the recovery efort. Simply

    collecting and disposing o all debris without taking

    these actors into account will make the recovery

    process more costly and more dicult than i the

    debris is transormed into a positive contribution to

    recovery.

  • 7/30/2019 Waste Guide

    8/46

    6

    CSE STUDIES

    Case Study 1Japan, 1995

    The Hanshin-Awaji earthquake on 17

    January 1995 in Kobe destroyed more

    than 192,000 buildings as well as roads

    and railways. The quantity o demolitionwaste generated rom the site clearing

    works was estimated at more than

    15,000,000m3.

    The majority o the waste was removed

    to landll or used or land reclamation in

    Osaka bay. Only a minor proportion was

    recycled. This resulted in the demolition

    waste taking up valuable municipal andhousehold waste landll space, with

    resulting negative impacts on the citys

    solid waste management systems.

    Case Study 2Mexico, 2007

    The State o Tabasco, Mexico, was hit by

    ooding in October 2007. Over 920,000

    people were displaced and over

    245,000 homes were afected. A largepercentage o the generated waste was

    demolition waste.

    Existing waste management services

    were not able to deal with the disaster

    waste arising rom the ood event and

    subsequent recovery phase. A majority

    o the waste was removed to uncon-

    trolled temporary storage areas causingenvironmental and public health risks.

  • 7/30/2019 Waste Guide

    9/46

    7

    Case Study 3The Maldives, 2004

    Following the Indian Ocean tsunami

    in 2004, approximately 290,000m3 o

    demolition waste, combined with an

    estimated 50,000m3 o household andother waste, was generated in the Mal-

    dives.

    The waste was disposed o in uncontrol-

    led dump sites and in shallow coastal

    waters of beaches. This led to increased

    health risks through contact with de-

    composing wastes. There was also a risk

    o groundwater contamination throughheavy metals leaching through soils.

    Case Study 4Kosovo, 1999

    During the 1999 war in Kosovo, consi-

    derable damage was caused to buil-

    dings and structures across the country.

    More than 120,000 housing unitswere damaged in 29 municipalities. It

    was roughly estimated that the waste

    rom damaged buildings and struc-

    tures reached a magnitude o 10 million

    tonnes.

    Through a DANIDA unded environ-

    mental programme, the recycling o

    building waste was integrated intothe reconstruction work, with recycled

    materials being used in new roads and

    buildings.

  • 7/30/2019 Waste Guide

    10/46

    8

    2. NTURE OF DISSTERSND SCLE OF OPERTIONS

    The type and composition o waste varies according to the

    location, type and scale o disaster, as illustrated below.

    Shelter practitioners may be expected to contribute to

    operations on diferent levels. In rare, but welcome, cases they

    may be involved in the design o a waste management plan with

    government ministries or local and international specialists.

    In most cases, however, they will be directly involved in

    supporting the activities o the afected populations.

    Conict

    Post-conict building waste oten contains reduced amounts

    o timber, urnishings and personal possessions since the

    buildings will oten have been burned. In post-conict situations

    there is, however, a risk o unexploded ordnances (UXO), minesand booby traps being present in the building waste. In such

    instances, access should be restricted until proessionals have

    rst cleared the area.

    Banda Aceh

  • 7/30/2019 Waste Guide

    11/46

    9

    Pakistan Sri Lanka

    Disasters

    The nature and scale o waste ollowing a disaster varies

    considerably rom one situation to another. In post-tsunami

    situations, or instance, the majority o solid building waste

    could be washed out to sea by the receding waves. What may

    remain, however, is a large volume o mud into which other

    materials may be mixed, which may prove dicult or sorting.

    In contrast, post-earthquake debris will oten have all o the

    materials rom the buildings still present at the ootprint o

    the building.

  • 7/30/2019 Waste Guide

    12/46

    10

    In a disaster there are our phaseswhere building waste is likely to be

    generated.

    Disaster

    Waste generated by buildings and

    inrastructure destroyed by the disaster

    itsel.

    Search and Rescue

    Partial demolition o buildings

    to improve access and saety or

    emergency response eforts.

    Demolition

    Demolition o buildings and inrastruc-ture to acilitate reconstruction.

    Temporary or PermanentShelter Construction

    Waste generated during

    reconstruction.

    Building waste occurs in every type odisaster and oten represents a large

    percentage o the total waste.

    The types o waste generated depend

    on the nature and location o the disas-

    ter, however they can broadly be cate-

    gorised as ollows:

    vegetation, soils and sediment, ash

    and charred wood;

    building waste;

    domestic waste;

    damaged household goods;

    hazardous waste;

    industrial waste; and

    waste rom the emergency res-

    ponse, e.g. packaging materials.

    3. BUILDING WSTE GENERTION

  • 7/30/2019 Waste Guide

    13/46

    11

    Table 1: Major categories o waste in selected events

    Hurricane Earthquake Tornado Flood Fire Tsunami ConictCamp

    closure

    Vegetation a a a a a a

    Soil andSediment a a a a

    Ash andcharred

    wood

    a

    Buildingwaste a a a a a a a a

    Domesticwaste a a a a a a a

    Damagedhouseholdgoods

    a a a a a a a

    Hazardouswaste a a a a a a

    Industrialwaste a a a a a a

    Relie

    waste a a a a a a a a

  • 7/30/2019 Waste Guide

    14/46

    12

    4. COMPOSITION OF BUILDINGWSTE MTERILS

    The composition o building waste varies according to the location, local building

    practices, and the context and type o disaster.

    In rural Arica, local construction can be simple, with grass roos, a wood ramework

    and mud brick walls.

    More complex structures can include breeze blocks, iron sheeting, roong tiles,

    rebar and timber.

    Cte dIvoire

    The Maldives

  • 7/30/2019 Waste Guide

    15/46

    13

    In large cities, disaster waste may include a mix o building materials, white goods,

    personal belongings and hazardous waste.

    It is currently estimated that approximately 50 per cent o the worlds population

    live in cities. UN Habitat orecasts that this percentage will increase in the coming

    years. This means that a majority o waste rom uture disasters will occur in cities

    and will have a typically urban waste composition.

    The average composition o building waste in cities in developed countries is shown

    below. In developing countries, the percentage o inert materials can reach up to 90

    per cent o all building waste.

    Estimated average composition o construction and demolition debris in urban settings

    Mexico

  • 7/30/2019 Waste Guide

    16/46

    14

    5. PRIORITIES

    A timely and well planned long-term waste disposal

    plan (see Appendix 3 or an example outline) cannot only protect health and saety, but also provide

    economic benets through re-use, recycling and/or

    sale o materials, according to local needs. It may also:

    improve access or immediate relie eforts;

    reduce health and environmental risks;

    reduce land and landll space taken or dum-

    ping;

    provide materials or rehabilitation and recons-

    truction;

    help with income generation through recycling

    and re-use;

    be a positive action through community recy-

    cling; and

    reduce the need or double handling o wastes.

    A sound and co-ordinated waste management plan

    should assess all possible options or each type o

    waste. Choose the most viable one on the basis o the

    time, practical options, public health, as well as legal,

    nancial and environmental considerations.

    The management o disaster building waste should

    be considered, rom day one, as part o an integraldisaster waste management plan or the afected

    area.

    The ollowing typical priorities are oten selected

    or building waste in a post-disaster situation, with

    additional comments with regards the handling o

    building waste.

    An adequately plannedlong-term waste disposal

    plan can provide economic

    benets through re-use,

    recycling and/or sale ofmaterials, according to

    local needs.

    Recycling optionsdepend on local

    technology and practices

    and the market value forthe recycled material.

    Direct re-use or resaleof building materials may

    happen spontaneously

    with local scavengers

    salvaging any usable

    parts.

  • 7/30/2019 Waste Guide

    17/46

    15

    Table 2: Typical priorities or building waste in the post-disaster phases

    DESCRIPTION Building Waste Comment

    Priority 1

    To remove the building waste

    (debris) which is impeding

    search and rescue operations

    as well as the immediate, emer-

    gency relie operations (i.e. the

    providence o rst aid, ood,

    shelter and water).

    The site or dumping o the

    waste should be selected with

    consideration to uture use o

    the waste and uture use o

    the land on which dumped (i.e.

    not to dump building waste on

    someones agricultural land).

    Priority 2

    The removal o damaged buil-

    dings and inrastructure which

    could cause an immediate

    threat to public saety such as

    unstable structures and large

    piles o unstable rubble in

    urban, residential areas.

    Handling requires attention to

    Health and Saety or the wor-

    kers. It also requires attention

    to potential legal issues such

    as access and ownership o the

    waste. Site or dumping o the

    building waste as above.

    Priority 3

    To remove uncontrolled dum-

    ped building waste rom urban

    areas since i let to lie will o-ten attract dumping o general

    wastes (which will reduce the

    opportunity to recycle the buil-

    ding waste), which in turn can

    lead to public health and envi-

    ronmental risks.

    Handling requires attention to

    Health and Saety or the wor-

    kers. It also requires attentionto potential legal issues such

    as access and ownership o the

    waste. Site or dumping o the

    building waste as above.

    Priority 4

    To remove building waste o

    damaged buildings rom pri-vate and public plots o land to

    enable reconstruction.

    Handling requires attention

    to Health and Saety or theworkers and there may be an

    opportunity to sort the wastes

    into recyclables beore trans-

    port. It also requires attention

    to potential legal issues such

    as access and ownership o the

    waste. Site or dumping o the

    building waste as or Priority 1.

  • 7/30/2019 Waste Guide

    18/46

    16

    6. REUSE,RECYLING ND

    DISPOSLA successul waste management plan

    aims to maximise the re-use o recovered

    materials, minimise the volume o waste

    requiring ultimate disposal and improve

    waste management in the longer term.

    Where useul materials are recovered,the volume o the waste requiring

    disposal is reduced while the impact o

    rebuilding and recovery is diminished

    through substituting raw materials with

    the recycled materials.

    A simplied owchart in Appendix

    1 presents the typical steps in han-dling, treating and processing disaster

    waste in an urban setting. Appendix 2

    highlights some re-use and recycling

    options or common materials.

    Some options or disaster building

    waste are described below.

    REUSE

    Direct re-use or resale o building

    materials is a desirable solution. The

    quality o the materials should always

    be checked, while options will depend

    on local practices and market value.

    This oten happens spontaneously.

    RECYCLING

    Recycling o building waste materials

    (or example, crushing concrete to re-

    use as gravel) avoids using landll space,

    reduces the need to quarry rocks and/orcut trees, can bring economic benets

    and is generally good environmental

    practice. Recycling options depend on

    local technologies and practices and

    the market value or recycled materials.

    DISPOSL TO LND

    Uncontrolled disposal can lead topublic health and environmental risks,

    as well as a potential need to move the

    waste again once the relie phase has

    been completed. Disposing o large

    volumes o building waste directly to

    landll or dumpsites can use up space

    better suited or non-recyclable wastes

    and reduce the capacity o existing

    municipal solid waste management, isuch a system exists.

    REDUCE

    Volume reduction o waste at source

    is the most desirable long-term option

    and should be an integral part o

    every waste management plan. For

    disaster building wastes, this may

    involve reduced packaging or the (re)

    construction materials.

  • 7/30/2019 Waste Guide

    19/46

    17

    Re-use or recycling o building waste will depend on

    the situation, context and demand or materials.

    The most common post-disaster operation is the

    recycling o concrete and bricks into a gravel or

    aggregates material, where these can be used inlow strength concrete, as a sub-base or roads, as

    an aggregate or building blocks and as ll under

    oundations or on general reconstruction works.

    In many cases, this can be an economically and

    environmentally viable option ater a disaster as

    there may be an increased demand or aggregate in

    reconstruction and rehabilitation works.

    Many countries have established quality standards orthe recycling o inert building waste into aggregates

    or gravel or road base. Check local standards and

    specications to ensure that they are met, or reer to

    relevant national standards, i they exist.

    The value o aggregates and the economic viability o

    using recycled concrete, bricks or other building waste

    materials depends on local demand, availability and

    proximity o natural sources, the availability and costo sorting, crushing and grading recycled materials

    and the cost o landll disposal.

    The most commonpost-disaster operation is

    the recycling of concrete

    and bricks into a gravel or

    aggregates material.

    Recycling of a materialwill only be a feasible

    option if it is economically

    viable.

    6.1 ECONOMICS OF WSTE RECYCLING

    Recycling will only be easible i it is economically

    viable. This will depend largely on the market value

    o the material, once produced. In addition, other

    actors may also have an inuence, such as:

    enorcement o stopping illegal quarrying since

    this would otherwise produce a competitive

    material to that produced through recycling;

    how easy it is to dump building waste as regards

    costs and legality o dumping, i.e. i it is easier

    to dump waste and buy cheap quarry materialsthen it may be dicult to support recycling rom

    an economic viewpoint;

  • 7/30/2019 Waste Guide

    20/46

    18

    Stacked cleaned bricks ready or re-use at the OxamGB re-use/recycling yard in Banda Aceh.

    Building blocks or reconstruction purposes whichcan be produced rom recycled building waste,Pakistan.

    Recycled aggregate rom crushed building waste inKosovo, as used or road construction or low strength

    concrete oundations.

    the ease with which the material can be recycled,

    i.e. has it been mixed with household waste and

    would the removal o non-recyclables be too

    expensive and high risk to complete; and

    the level o acceptance or the recycled materialinto the (re)construction market, i.e. will engi-

    neers accept to use recycled materials compared

    with natural quarry materials that they may be

    more amiliar with?

    Post-disaster reconstruction work normally places a

    huge demand on quarry materials so there are typi-

    cally good economic grounds or recycling buildingwaste. An exception might be in rural areas with good

    access to unlimited quarries.

    A long-term waste management plan (see Appendix

    3) arising rom the post-disaster waste management

    work may include a ocus on developing a market or

    recycled materials where it does not exist. This can

    be developed over time in collaboration with the

    relevant authorities.

  • 7/30/2019 Waste Guide

    21/46

    19

    Transportation ofthe building waste can

    be done by a range of

    methods, from wooden

    carts pulled by animalsto heavy duty excavators,

    trucks and skips.

    In many cases it ispreferable to avoid the use

    of heavy machinery.

    7. CCESS NDTRNSPORT

    Transporting waste is an important economic and

    logistical actor to be considered, given the large

    volumes that may need to be dealt with (see also

    Section 11). Following a disaster, there is commonly a

    shortage o vehicles and the road inrastructure may

    have been damaged. This will have a considerable

    impact on the selection o temporary waste storage

    sites.

    There are two main mechanisms or moving building

    waste rom its source to the treatment site or

    recycling, re-use or disposal:

    push which entails paying an organisation i.e.

    contractor or through cash-or-work to bring

    the building waste to the treatment site; or

    pullwhich entails paying a xed sum o money

    or every load o building waste brought to thetreatment site, e.g. US$1 per wheelbarrow o

    bricks.

    One positive advantage o the pull mechanism is that

    it allows or the local community to participate in the

    building waste clean-up work and thus spreads the

    economic benets o building waste work deeper

    into the community.

    An example o this was the Oxam GB re-use yard in

    Banda Aceh ollowing the 2004 Indian Ocean tsunami

    where the yard paid a set rate per type o building

    waste delivered. The building waste was subsequently

    cleaned and re-used/recycled in a variety o products.

  • 7/30/2019 Waste Guide

    22/46

    20

    Islamic Relie project or the clearing andcleaning o building wastes (including

    rough cut stones) and subsequent re-useor new oundations .

    8. WSTE SORTING

    The ollowing sub-sections present some typical

    orms o handling and processing building waste mainly in connection with centralised waste

    management programmes rom its location at

    source to nal end-use or disposal.

    The use o mechanical clearance should be avoided,

    or careully controlled, in order to respect peoples

    property and possessions and the act that human

    corpses might be in the waste. A possible exception

    to this might be the clearance o roads or emergencyaccess.

    The main emphasis o recycling inert building waste

    is to remove non-recyclable materials such as plastic,

    timber, and household urnishings beore processing

    begins. This results in a quality product which can

    be used in road construction and or low strength

    concrete.

    Building waste will oten be mixed, or example

    recyclable concrete and bricks may be mixed with

    urnishings and other non-recyclable materials. In

    order to realise the maximum value rom building

    waste in terms o items or re-use and recycling, it

    is typically necessary to sort through the waste to

    extract the non-recyclables.

    This can be done in a variety o ways, rom basic

    manual sorting to mechanical means, the latter being

    more appropriate or larger volumes.

    Manual Sorting

    Building waste can be strewn out on the ground and

    manual labour used to pick out the non-recyclablesand other items. Remaining material such as concrete

    and bricks can then be collected or processing.

  • 7/30/2019 Waste Guide

    23/46

    21

    A mechanical grizzly to the let sorts ner materials rom theoversized concrete and bricks, ater which large items can beplaced on a picking station (to the right) or manual separation.

    Typical conveyors with adjustable belt speed or use as a pickingstation.

    A primary screening eedstock or the removal o soil raction andpossible contaminants plastics, paper, non-recyclables beorecrushing.

    Primary Mechanical Sorting

    Alternatively, a basic plant can be constructed

    locally for the mechanical sorting of building

    waste. This provides a higher throughputwith fewer personnel.

    A mobile setup is also possible which allows

    the equipment to be moved from one site to

    another for on-site separation.

    Picking stations are useful since they can be

    linked to a slow moving conveyor belt from

    which waste can be removed manually.These units vary in size from mobile picking

    stations to larger central locations with a

    large, stationary setup. Such belts enable up

    to six people to safely work at the unit, three

    on either side. The belt is normally used in a

    raised position to allow the operators to work

    at waist height.

    Primary Screening Unit

    Should a larger throughput be required, then

    a more sophisticated primary screening unit

    can be used to remove the ner soil fractions

    from the building waste. These units are

    highly mobile and only require a single axle

    truck to move around the site.

  • 7/30/2019 Waste Guide

    24/46

    22

    Locally manuactured mobile crusher in a Pakistan quarry.

    Crushing o building waste in Pakistan ollowing the 2005earthquake, using a small, mobile hand-ed crusher on tracks.

    Crushing o building waste in Kosovo using a medium-sizedmobile crusher (yellow machine to the let) and a screeningunit or separation o the crushed material into three sizeractions (green plant to the right).

    WSTE CRUSHING

    Crushers can generally crush glass,

    porcelain, granite, bricks, blocks, asphalt

    and re-inorced concrete. Dependingon the location and context, a variety o

    crushers are available, each suitable or

    difering purposes and end-products.

    They can range in size rom on-site

    mobile crushers capable o processing

    rom 45-400 tonnes per day to ull-scale

    plants that can handle up to 500 tonnes

    per hour.

    Some commonly used crusher models

    appropriate or post-disaster work

    are described below. Note that or all

    options there is also a solid second-

    hand market or crushers and screeners.

    One does, however, need to ensure that

    the plant is delivered with adequate

    guarantees, warranties and service

    arrangements.

    Locally Manufactured

    Crushers

    Many countries have an active quarry

    industry so there may already be some

    pre-existing facilities and services that

    might be used to deal with certain typesof waste stream. It is also possible to have

    locally manufactured small-scale crushers

    produced to specication and used in

    the post-disaster clean-up and recycling.

    Discussions with manufacturers should

    include consideration for the handling of re-

    inforcement bars when crushing concrete,

    as this often requires a larger aperture for

    the outlet of the feed hopper.

  • 7/30/2019 Waste Guide

    25/46

    23

    Small Mobile Crushers

    Should locally manuactured crushers

    not be available, there are several

    options or the purchase o small,

    mobile crushers which can be used inurban and rural areas.

    These smaller crushers can be

    transported by typical 4x4 vehicles

    and are operated by remote control,

    thus allowing access to even the

    most rural areas o a disaster-afected

    community. The output crushed

    material is not suitable or engineered

    roads or low strength concrete but can

    be used or access road rehabilitation

    or as general ll.

    Medium Mobile Crushers

    For larger quantities o building

    waste, a medium-sized mobile plantcan be used, which would normally

    eed straight into a screening unit or

    the separation o the crushed material

    into two or more size ractions. The

    nal product size will depend on the

    required use o the recycled material.

    Medium-sized crushers or recycling

    building waste will require anoverband magnet or the separation

    o the re-inorcement bars rom the

    crushed material.

    Large Stationary Crushers

    Although not typically used in post-

    disaster work since the spread o

    building waste in a geographic area

    makes a mobile crushing solutionmore cost-efective rom a logistics

    view, a stationary crushing unit can be

    implemented i the quantity in an urban

    area is signicant, i.e. more than one

    million tonnes o building waste.

    Stationary crushers and screening units

    have a higher throughput than any othe mobile solutions. They do, however,

    require a larger acility inrastructure or

    recycling and stockpiling, or example,

    and are more costly.

    TIMBER ND OTHER WSTE

    For timber and vegetal debris withinbuilding waste, grinders and shredders

    can be used to reduce the volume o this

    waste stream. It can then, or example,

    be used as mulch in landscaping or or

    compost.

    For other waste streams not typically

    directly recyclable or re-usable, the

    norm is or these materials to bedisposed o at an authorised dumpsite

    or landll. In some cases it may be

    prudent to allow local communities

    access to this waste stream under

    careul working conditions to extract

    any materials which they may nd o

    use. One such example is plastic which

    can be used to make products such asbags or sale in the local market.

  • 7/30/2019 Waste Guide

    26/46

    24

    9. IMPCTS ND

    HZRDS

    Lack o waste management ater a disaster can have

    the ollowing negative impacts on the afected

    populations, and the environment. It may:

    hinder access, reconstruction and rehabilitation

    activities;

    encourage uncontrolled dumping;

    represent a continued and increased hazard and

    public health risk; cause hazardous waste risks to health and the

    environment; and

    be detrimental to uture, normal waste opera-

    tions.

    The use o mechanised clearance should be avoided

    or very careully controlled because o plot bounda-

    ries, bodies in rubble and personal possessions. It is,

    however, commonly used to re-open roads to allow

    emergency access.

    Uncleared waste may continue to represent a hazard

    risk. Atershocks, or example, can urther destroy

    buildings that have not been secured, while high

    winds might lit uncleared debris such as iron shee-

    ting into the air, which could be a potential threat to

    people.

    Uncleared waste or clearance operations themselves

    can also impact on surace water drainage or sewage

    and utilities inrastructure.

    The use of mechanisedclearance should be

    carefully controlled.

    Uncleared waste canpresent continued or

    increased hazard risks.

  • 7/30/2019 Waste Guide

    27/46

    25

    Steel, bricks, timberand tiles are likely to

    oer possibilities for

    transitional shelter and

    might be the startingpoint for reconstruction

    or some form of revenue

    generation.

    Take steps to ensurethat debris items with

    value remain accessible tothe original owner.

    10. COMMUNITY

    INVOLVEMENT ND

    COMMUNICTIONSAs in all other areas, ater a disaster it is vital to

    work with the afected population, local authorities,

    competent authorities and local contractors on waste

    management.

    The rst people on the scene o a disaster are the a-

    ected population. Most communities will have someorm o committee in place. Involving the community

    will help identiy what normal practice is, develop pre-

    erred options or waste collection, and develop pu-

    blic health and other messages associated with waste

    management. Strategies or disseminating public in-

    ormation can include signs, posters, yers, and media

    such as newspaper articles, radio announcements or

    TV announcements, as well as public meetings.

    Where the community is involved, waste sorting at

    source will happen almost automatically. Key points

    have been highlighted above.

    Where there is no pre-existing disaster waste

    management plan, the rst step is to establish a large-

    scale public inormation plan on how to deal with the

    large quantities o waste generated by the disaster.

  • 7/30/2019 Waste Guide

    28/46

    26

    The rst people on thescene of a disaster are the

    aected population.

    Where the community isinvolved, waste sorting at

    source will happen almost

    automatically.

    11. RESPONSIBILITY

    ND LEGL ISSUES

    Three sets o legal issues usually arise in disaster

    debris management: value and ownership, access

    and safety.

    Value and ownership: Destroyed inrastructure is oten

    the only resource let to afected amilies ollowing a

    disaster, not only peoples personal possessions such

    as urniture but also steel, bricks, timber and tiles. For

    many, these ofer distinct possibilities or transitionalshelter and might even be the starting point or

    reconstruction or some orm o revenue generation.

    Special consideration might need to be given to

    multiple owners in multi-storey buildings.

    All disaster debris had some value beore the disaster,

    some o which might still remain ater the event has

    taken place. For instance, the owner o a damaged

    building may want to retain ownership o the bricksbecause o their value in ofsetting a need to purchase

    bricks with which to rebuild. It is not appropriate or

    debris management operations to deprive an owner

    o items which, while damaged by a disaster, are still

    o some value. Special consideration might need to

    be given to multiple owners in multi-storey buildings.

    Debris management eforts should thereore take

    steps to ensure that debris items with value remainaccessible to the original owner. I people are not

    able to return to their ormer homes, then the owner

    should be compensated at air market values

    or the items which are taken and used or another

    purpose, or example, bricks rom damaged buildings

    being used or road sub-surace.

    Addressing ownership and value issues needs to

    be planned in advance o debris removal. Disastersurvivors will need to be consulted to the degree

    possible.

  • 7/30/2019 Waste Guide

    29/46

    27

    Legal actions by government authorities are also

    needed to avoid disputes over ownership. This is

    particularly the case where previous owners o di-

    saster debris may have been killed during the di-

    saster, or where clearance activities uncover objects

    o economic possibly cash, gold or jewellery or

    example or sentimental value.

    The need to preserve plot boundaries as a starting

    point or determining land rights and subsequent

    reconstruction will require specic attention.

    Local government authorities and disaster survivors

    should be consulted on the necessary legal and so-

    cial steps required to permit access to private pro-perty. These procedures should be in place beore

    debris clearance begins, and include how to handle

    valuables and personal possessions.

    Access is also an issue when establishing tempo-

    rary processing areas or permanent disposal sites.

    For the latter, some level o environmental review

    should rst occur ahead o the land being legalised

    through the normal but expedited adminis-trative process. In the case o the ormer, tempo-

    rary authorisation should be received rom the site

    owner, which should speciy the condition o the

    site beore use as well as what condition it should

    be in when returned to the owner.

    Saety issues are dealt with in the ollowing section.

    Local governmentauthorities and disaster

    survivors should be

    consulted on the necessary

    legal and social stepsrequired to permit access

    to private property.

  • 7/30/2019 Waste Guide

    30/46

    28

    12. HELTH ND

    SFETY

    Building waste generated by disasters can include

    materials and wastes that are hazardous to human

    health as well as the surrounding environment. These

    require identication and special handling.

    The need to preserve plot boundaries as a starting

    point or determining land rights and subsequent

    reconstruction will require specic attention.

    Additional hazardous wastes such as oils, chemicals

    and heavy metal containing items should be identied

    and removed rom the waste.

    In addition to actual waste materials, in post-conict

    situations there is also the risk o UXO and mines

    being present in the building waste. Co-ordination is

    required with relevant and specialist organisations in

    the eld to ensure that building waste is clear o such

    ordnance and sae to handle.

    Protective clothing should always be provided when

    dealing with waste, particularly mixed waste streams.

    This includes adapted ootwear hard boots to pre-

    vent spikes entering the sole and minimise the risk

    o harm rom heavy materials dropping onto eet

    gloves, overalls and masks. Equipment such as sho-

    vels, buckets, carts and skips should also be provided.

    Where possible, people working with waste should

    have access to changing and washing acilities.

  • 7/30/2019 Waste Guide

    31/46

    29

    Case Study 5

    Indian Ocean Tsunami

    Ater the 2004 Indian Ocean tsunami, UNDP and its partners considered a numbero livelihood restoration and creation projects in waste management, as well as

    opportunities or viable recycling business start-up. Projects included the ollowing:

    composting projects to make organic ertiliser or rice padi and park

    rehabilitation;

    plastic processing acilities to make and sell plastic chips to recyclers;

    provision o restored tsunami wood to urniture manuacturers;

    wood-red brick kiln rehabilitation projects to make red bricks using tsunami

    wood;

    wood-red limestone kiln rehabilitation projects to make lime using tsunami

    wood;

    charcoal manuacture rom tsunami timber; and

    provision o stone crushers to make secondary aggregate or use in brick

    projects, concrete preparation and/or as a road base.

    Those employed under a cash or work scheme were either pre-existing scavengers,people recruited or the project or those employed directly rom camps housing

    some o the displaced people. The scheme tried to ensure that the most vulnerable

    people rom within the communities were considered. Employment o women was

    particularly encouraged. In rubble clearance and recycling activities, the programme

    promoted gender-sensitive approaches in work and wage distribution. The

    programme also sought to strengthen the long-term capacity o local government

    on waste management through working with district sanitation departments.

    Source: Tsunami Recovery Waste Management Plan

  • 7/30/2019 Waste Guide

    32/46

    30

    Case Study 6

    Sri Lanka

    In a shelter programme or returnees in eastern Sri Lanka, the Norwegian ReugeeCouncil (NRC) encouraged beneciaries to re-use bricks and blocks or shelter

    reconstruction.

    Houses had been destroyed in the ghting and NRC was providing a small core

    shelter that provided a 9m2 ull masonry room with an additional 9m2 o open, but

    rooed, area which had oundations. Beneciaries provided inll or the raised oor

    using rubble rom old houses. They could also use salvaged bricks/block to ll in the

    walls or the open section o the house.

  • 7/30/2019 Waste Guide

    33/46

    31

    13. CPCITY BUILDINGND EMPLOYMENT

    GENERTIONAside rom voluntary participation within the

    community, well-designed employment and cash or

    work programmes can help support the overall clean-

    up efort as well as provide income to vulnerable

    populations who may have lost their employment as

    a result o the disaster.

    Immediate employment activities can be designed

    to rehabilitate and improve access to public acilities,

    inject cash into displaced populations who have lost

    sources o income, and to reduce trauma among

    victims through the provision o work.

    Implementation o waste recycling and recovery

    projects can restore livelihoods. Much o the waste

    is recoverable and recyclable or use in rehabilitation

    and reconstruction. Re-use o recycled timber,

    concrete and bricks will reduce the need to cut trees

    or new timber and quarry rock or use in concrete,

    drainage, roads and ll.

    Local non-governmental organisations (NGOs) and

    local companies involved in recycling and waste dis-

    posal beore a disaster can be valuable collaborators

    in the post-disaster management o debris. Using lo-

    cal partners will acilitate operations and strengthen

    local capacity to manage waste and debris in the

    uture.

    Well-designedemployment and cash

    for work programmes

    can help support the

    overall clean-up eort aswell as provide income to

    vulnerable populations

    who have lost their

    employment as a result

    of the disaster.

    Using local partnerswill facilitate operations

    and strengthen local

    capacity to manage

    waste and debris in the

    future.

  • 7/30/2019 Waste Guide

    34/46

    32

    14. CONCLUSIONS

    This guide does not attempt to address all aspects o this large

    and complex topic. It is intended to highlight some key issues thatshelter specialists may encounter during diferent levels o disaster

    and post-disaster operations.

    Although building waste management may not seem like an

    immediate concern during and ater a disaster, the large quantities

    o waste oten generated at such times means that this issue needs

    careul consideration.

    To maximise the re-use o recovered materials, it can be useul

    to minimise the volume o waste requiring ultimate disposal. It is

    important that waste management is properly planned, organised

    and monitored, Complex issues such as land rights, legal aspects,

    saety concerns and the livelihoods o afected populations need to

    be considered.

    Further reerences and links are provided at the end o this document

    or more in-depth inormation.

  • 7/30/2019 Waste Guide

    35/46

    33

    PPENDIX 1

    WSTE PROCESSING FLOWCHRT

    This simplied owchart presents some o the typical steps in handling, treating

    and processing disaster waste. It is based on the assumption that a centralised

    waste disposal plan is in place. Each step can be carried out at the source, e.g. a

    damaged building, or at an of-site processing or disposal site.

  • 7/30/2019 Waste Guide

    36/46

    34

    PPENDIX 2

    REUSE ND RECYCLE POTENTIL OFSTNDRD BUILDING MTERILS

    MTERIL REUSE RECYCLE

    Plastics Check local practices and demandor recycled plastic.

    Check local practices and demandor recycled plastic.

    WOOD

    Timber Wood can be re-used or a varietyo diferent purposes, rangingrom low-quality, temporary

    work like survey pegs and boxingor concreting to high-quality,permanent uses like oor boards,

    beams and other architecturaleatures i the recovered material isin a suitable condition.

    Depending on the type o disaster,

    rotting, humidity, splitting, presenceo nails or screws can afect the

    potential or re-use.

    Untreated timber of-cuts can bechipped into mulch and used inlandscaping, animal bedding or

    used as uel. Depending on thecontext, wood rom constructionand demolition waste competes

    with orestry and manuacturingwood waste as an input orindustrial urnaces and boilers,

    particularly in pulp and paper mills.

    Bamboo Bamboo is requently used inlow-cost construction such ashuts and encing. During camp

    closure, bamboo structures can bedismantled and transported or re-use or sale at a local market.

    It can be afected by ungus indamp climates and attacked by

    insects. Check the quality beorere-using or reselling.

    Other uses include compost or chip,dry and use as uel.

  • 7/30/2019 Waste Guide

    37/46

    35

    MTERIL REUSE RECYCLE

    INERT MTERILS

    Bricks / Blocks Bricks and blocks can be cleanedand re-used i their quality is

    acceptable. They can be resold tothe community and / or re-used inreconstruction programmes. Thepresence o cement mortar or glues

    can hinder re-use as they are unableto be cleaned of.

    Diferent orms o brick can berecycled or re-use in reconstruction

    programmes.Mud bricks degrade easily and canbe broken up by hand and used as

    inll or latrines and trenches. Theycan also be crushed by hand andspread across the land.

    Bricks can be crushed to a suitablesize and recycled as aggregate tobe used in concrete. They can be

    broken to use as hardcore as sub-bases to concrete work. They canalso be broken or crushed as inll in

    landscaping applications.

    Concrete Damaged concrete cannot be

    directly re-used.

    During land rehabilitation ater

    camp closure, concrete can becrushed by manual labour andre-used as ller or abandoned

    latrine pits, drainage trenches andother surace irregularities. This alsoprovides local income.

    Concrete can be crushed and

    recycled as aggregate or hardcoreor building and road base materialor oundations

    Concrete can be crushed manually;with a mobile crushing unit or

    transported to a specialisedconcrete crushing plant. Location,volume o concrete waste, localdemand or aggregates and

    availability o other types oaggregates are determining actorsin the choice o crushing method.

    The presence o local quarries orriverbeds providing gravel couldmean that recycled aggregate is

    not viable.Steel rebar may block crushing

    machines i they are not designedto separate the steel rom theconcrete. Proper assessment must

    take place to ensure no asbestos ispresent prior to crushing.

  • 7/30/2019 Waste Guide

    38/46

    36

    MTERIL REUSE RECYCLE

    sphalt Asphalt cannot be re-used withoutprocessing.

    Asphalt is requently recycledduring normal road resuracing in

    developing countries.

    Commonly used asphalt recyclingequipment includes eed systemsadded onto a large xed asphaltproduction plant or small mobile

    pieces o equipment or asphaltreheating.

    Plasterboard Plasterboard is likely to be damagedduring a disaster and thereore

    unsuitable or re-use.

    Gypsum makes up approximately90% o the weight o a piece o

    plasterboard. Gypsum can berecovered and used : in the manuacture o new

    drywall; as an ingredient in the production

    o cement;

    or application to soils and cropsto improve soil drainage andplant growth;

    an ingredient in the production oertiliser products;

    an additive to compostingoperations.

    However, this is unlikely in mostemergency responses.

    ROOFING MTERILS

    Roof thatching The type and quality o thatching

    material can vary. It is prone todecay in damp conditions and canbe ruined by vermin. Thatched roos

    are also very ammable. Thatching

    is usually replaced once a year andis unlikely to be re-used or sold.

    Thatching can be composted where

    composting acilities are available.In the case o IDP or reugee campclosure, it can be spread on the

    ground or ploughed into the soil

    and let to decompose naturally.

    Roong tiles I in reasonable condition, roongtiles can be re-used.

    Recovered tiles can be crushed andused as aggregate, landscaping or

    inll purposes. Check local marketor demand and prices.

    Corrugated iron

    sheets

    I in reasonable condition, thesheets can be re-used. Howevercorrugated iron sheets can easily

    corrode.

    Scrap metal is a lucrative businessin most countries. Corrugated ironsheets can be sold and exported

    to iron smelting plants. Check local

    market or demand and prices.

  • 7/30/2019 Waste Guide

    39/46

    37PPENDIX 2: WSTE PROCESSING FLOWCHRT

    MTERIL REUSE RECYCLE

    OTHER

    Metals Demand or resale and recyclingo scrap metals is high in most

    countries. Iron and steel are themost recycled materials worldwide.Steel is unique among majorconstruction materials in that it

    always contains recycled content;it is completely recyclable at theend o its product lie and may berecycled without loss o quality. It

    can be smelted and recycled.Check local demand and prices,which can vary according to

    location.Steel rebar Rebar cannot be re-used or

    structural purposes as it will havelost its main properties

    In low cost shelter, rebar is oten

    stripped by the resident populationand sold on local markets. Checklocal markets or demand and

    prices.

    The presence o rebar can

    complicate the crushing oconcrete. Some specialisedcrushing machines have magnets

    to automatically separate the steelrom the concrete. Others requireprior sorting.

    Hazardous waste Hazardous materials shouldbe identied at source andimmediately separated rom the

    rest o the waste stream to avoidcontamination.

    Hospital waste, agriculture

    related wastes (e.g. pesticides andertilisers), oil and oil contaminated

    wastes should be identied assoon as possible and collected anddisposed o by trained personnel.

    The recycling o hazardousmaterials should only beundertaken by trained proessionals

    with appropriate protective gear.

    The presence o asbestos should

    be identied as soon as possible.

    It should be separated rom othertypes o waste and collected and

    disposed o by trained specialists.

    Miscellaneous Electronic debris should beseparated rom other wastes. They

    should be disposed o in speciallandlls, i available. Check localpractices.

    White goods, such as rerigerators,stoves, washers and dryers should

    be segregated and recycled, ipossible. Check local practices.

  • 7/30/2019 Waste Guide

    40/46

    38

    PPENDIX 3

    MIN ELEMENTS OF WSTEMNGEMENT PLN

    The ollowing points summarise some key considerations in planning a debris

    management programme. The planning should be done, where possible in

    collaboration and agreement with other international organisations involved in

    disaster response, the Emergency Shelter and/or WASH Cluster i applicable, local

    authorities, local waste management service companies or organisations, local

    NGOs and community-based organisations (CBOs).

    1) ssess the post-disaster debris situation with relevantpartners and determine:

    existing waste handling capacity;

    types o debris;

    presence o hazardous materials;

    quantities (volumes) o materials;

    whether or not there is an existing waste management plan; and

    location o diferent types o materials houses, actories, public spaces and

    so orth.

    2) Understand the scope of debris management eorts whodoes what by:

    consulting with clusters such as Emergency Shelter and WASH, i in place.

    3) Determine legal requirements and social norms related toassessing private property and collecting debris:

    who owns the waste?

    who has liability?

    are there any disaster exemptions?

    site ownership issues.

  • 7/30/2019 Waste Guide

    41/46

    39

    4) Determine whether waste processing will take place on-siteor whether it will be transported to a central processing site.

    On-site processing should be used i most o the debris will be let or use by

    the owner.

    5) Determine whether processing will be done throughlabour-intensive methods, machine intensive methods or acombination of both.

    Machine intensive methods are usually done of-site.

    6) Consult with local authorities and disaster survivors oncompensation issues and how much and how compensationwill be paid.

    7) Establish a protocol for handling valuables and personaleects collected.

    8) Establish personnel and equipment requirements for debrisprocessing.

    9) Dene management and reporting requirements for debriscollection and processing activities.

    10) Identify specialists services if available procedures andlocations for handling and disposal of hazardous waste.

    11) Develop a training plan for personnel involved in theoperation including:

    handling o hazardous materials;

    valuables and personal possessions; and

    saety and any other skills required.

  • 7/30/2019 Waste Guide

    42/46

    40

    12) Develop a budget covering:

    labour;

    equipment and machinery;

    transport;

    management tasks;

    compensation requirements; and

    saety requirements.

    13) Develop a schedule covering the debris disposal operation.

    14) Develop an exit strategy that includes:

    realistic and veriable targets;

    a transition to existing authorities, private sector waste management

    organisations or local or international NGOs, depending on available capacities;

    and

    consideration o alternative approaches such as the establishment o a CBO

    with project management responsibilities early in the project process.

    15) Begin implementation.

  • 7/30/2019 Waste Guide

    43/46

    41

    REFERENCES

    Basnayake B., Chiemchaisri C., Visvanathan C. (2006) Clearing up ater the Tsunami

    in Sri Lanka and Thailand.

    Baycan, F and Petersen, M. (2002) Disaster Waste Management Paper at ISWA 2002

    Annual Congress, Istanbul.

    Corsellis, T. and Vitale, A. (2005) Transitional Settlement: Displaced Populations.

    DWR / UNEP (2008) Disaster Waste Management Assessment Tskhinvali, South

    Ossetia, Republic o Georgia.

    GEIDE (2007) Dchets post-catastrophe - risques sanitaires et environnementaux.

    NRC (2009) Camp Management Toolkit.

    The SPHERE Project (2004) Humanitarian Charter and Minimum Standards in

    Disaster Response.

    SRSA / DWR / PROACT (2008) Disaster Waste Management Assessment Tabasco,

    Republic o Mexico.

    UNDP (2005) Tsunami Recovery Waste Management Programme.

    UNEP (2006) Environmental Considerations o Human Displacement in Liberia. A

    Guide or Decision Makers and Practitioners.

    UNEP/ ISWA/ DWR (2006) Pakistan Earthquake Disaster Waste Management Plan.

    UNEP (2005) Maldives Post-Tsunami Environmental Assessment.

    UNEP (1993) Sustainable building and construction: Facts and gures.

    UNHCR (2005) Environmental Guidelines.

    UNHCR (2007) Handbook or Emergencies.

    UNOCHA / IFRC / CARE International (2009) Timber as a Construction Material in

    Humanitarian Operations.

    US EPA (1995) Planning or Disaster Debris.

  • 7/30/2019 Waste Guide

    44/46

    42

    USEFUL WEBSITES

    Aggregain Online Guide to Sustainable Aggregates: www.aggregain.org

    Construction Waste Management in Sri Lanka: www.cowam-project.org

    Disaster Waste Recovery homepage: www.disasterwaste.org

    Groupe dExpertise et dIntervention Dchets Post-Catastrophe:

    www.robindesbois.org/geide

    International Society or the Environmental and Technical Implications o

    Construction with Alternative Materials: www.iscowa.org/

    International Solid Waste Association: www.iswa.org/web/guest/home

    Online Guide to Drywall Recycling: www.drywallrecycling.com/

    Recycling Construction Debris article: www.architectureweek.com/2001/0926/

    environment_1-2.html

    Shelter Centre website: www.sheltercentre.org

    Swiss Resource Centre and Consultancies or Development: www.skat.ch/

    Training Manual: Debris Management in Disaster Recovery: www.stopwaste.org/

    docs/disaster_debris_management_training_manual.pd

    UNEP Publications: www.unep.org/publications

    Waste & Resources Action Programme. Tips and Suggestions or Uses o Recycled

    Materials in Construction: www.wrap.org.uk/construction/index.html

  • 7/30/2019 Waste Guide

    45/46

    43

    PHOTO CREDITS

    Danish International Development Agency 7

    Disaster Waste Recovery 8, 18, 22, 23Golder Associates 8, 18, 23

    Islamic Relie Pakistan 21, 23

    NRC (J. Zarins) 31

    Oxam 18

    Portall 22

    ProAct Network (K.Walker, J. Godson) 6, 12, 13

    UNDP 8, 23

    UNEP 6, 7

  • 7/30/2019 Waste Guide

    46/46

    Rue de Cornavin 111201 Geneva

    Switzerland

    Tel: +41 22 755 3777

    Fax: +41 22 755 3779Email: [email protected] page: www.sheltercentre.org

    Les Deux CedresAvenue Alred-Cortot 7D

    CH - 1260 NyonSwitzerland

    Tel: + 41 22 362 53 84Fax: +41 22 362 53 85Email: [email protected] page: www.proactnetwork.org