Wapda Engineering Acadmy Report
-
Upload
syed-muhammad-ali-shah -
Category
Documents
-
view
142 -
download
11
Transcript of Wapda Engineering Acadmy Report
WEA1-BuckHolz Relay
It is installed between conservative tank and main tank. It is purely mechanically operated relay.
In minor fault relay is operated by gas In severe fault relay is operated by pressure of oil Two
"floats" which control the position of magnet and indirectly operate the switches. Upper float for
alarm Lower float for automatic tripping of transformer.
It protects only due to the internal fault of a transformer.
Tap Changer:
There are two types of tap changer
1. On load tap changer (NTDC)
2. Off load tap changer (distribution)
Regulate the voltage
Switch Gear Lab
Grid Station:
Without disturbing the frequency, change voltage level from one value to another.
Bus Bar schemes
1. Single breaker single bus bar:
Line/(earth switch/isolator) line isolator/breaker/CT/Bus bar/ CT/Breaker/ (lightning
arrester+transformer+lightning arrestor)/ incoming breaker/ CT/PT/Bus Bar
2. Single breaker Double Bus bar: ->Two bus bars with two breakers
line/ earth switch/isolator/breaker/CT/PT with each bus bar/ (Double breaker double bus bar)/
CT/Breaker
3. Double breaker double bus bar
4. One and half breaker scheme 3 breakers and 6 isolators on one bay (two bus bars). Each
breaker have two isolators. It is beneficial whenever there are three incoming lines.
CT: over currenr
Differential relay: its zone is between incoming feeder and outgoing feeder. It works on the
basis of difference between two current values.
WEA1-Lec2-Power System
Generation voltage is between 5Kv to 25KV due to limitation.
WarSac generating voltage is 6Kv, with capacity 243MW
Tarbella 13KV and 18 KV with capacity 3500MW on Indus River. We can get 10%
overrated generation with recorded value 3700MW, connected to 500KV with RawAt,
Muhamdi, Gatti, Sheikhupura.
ghazi brotha 1450MW
Dhaso 4320MW
Nelum jehlum 965MW
->Installed Capaciry
1. Thermal 4811MW
Muzaffar Garh
Bin Qasim
Jamshoro Lalpir 362MW
2. Hydal 6461MW
3. IPP's 6365MW
4. Nuclear 462MW
5. WindPower 50MW (6m/s is minimum speed for generation of wind energy)
6. Solar 5200MW (1KW/m2 is trapable energy)
Type of feasabilites
1. Technical feasibility
2. Economic Feasibility
EHV/Primary Transmission benefits
EHV/Primary Transmission, has three benefits
1. Losses reduce
2. Conductor size reduces
3. Power transmission capability increases
P @ ((Vs)(Vr)(Sin&))/XML
P @ (Vs)(Vr)
P@ V2
if voltage is increased by 10 times, power transmission capability increases by
100 times.
Transformer Ratings:
220Kv/132KV is 250-160MVA
132/11KV is 20-26MVA
11/220 is 100KVA
Types of Breaker on Quenching media
1. SF6 breaker
2. Oil breakers
3. Vacuum breakers
4. Blast air breakers
Generators
Generators can give both type of powers
1. Active power
2. Reactive power
Active power and frequency is controlled by Prime mover
Reactive power and voltage is controlled by exciter
Classification of transmission line
Short < 80Km
Medium 80km-240km
Long greater than 240Km
Types of Reactors
1. Series reactor
2. Shunt reactor
Capacitor is installed where power factor is bad. In transmission line, VAR is in excess
so we have to absorb them so we install "Shunt Reactors"
o 500KV 12 grids
o 220Kv 30 grids
o Lag and Lead are basically "time difference".
o Delta: 3 time power capability Harmonic trap
o Star insolation economy (generator's winding is connected in Star)
EA1-Lec3-Analogue Simulator lab
Mimic Diagram:
Drawing dream on control panel is called mimic diagran
Power simulator:
Power simulator is define as, replication of original power system on which various normal and
abnormal conditions can be demonstrated.
Normal conditions:
1. Rated Voltage
2. Rated frequency
3. Balanced Load
4. Maintained stability
5. Power generation greater than demand
Abnormal Conditions:
1. Short circuit (positive sequence, negative sequence, zero sequence)
2. Switching surges (Jerk)
3. Lightning over voltages (LOV)
4. Fehranti effect (no load, line should be atleast medium) We install shunt reactor at
receiving end to overcome this problem.
5. Mall synchronization
Synchronization: Process of connecting two different sources, through sncronizing breaker
meeting conditions ( same voltage, same frequency, same phase angle, phase sequence.
Synchronizing panel:
1. Dual volt meter
2. Frequency meter
3. Snchronoscope/phase displacement indicator
In field a relay is used called "synchro check relay".Only than
Permeseable ranges:
Difference of voltage for 132KV is +-10%
Difference of voltage for 220KV is +-5%
Difference of voltage for 500KV is +-3%
Difference of frequency is 0.1%
Difference of angle is 30 degree.
Bad effect: Instantaneous voltage difference due to which circulating current will flow and
will damage the insulation.
Every generator has a Generator's capability curve, which tells it will share how many MW and
will deliver how many VAR.
Relay types
First generation electro Mechanical Relay
Solid state relay/Second generation relay
Microprocessor based relay /Third generation relay
Generator's Relay
1. Generator differential relay
2. Over current over load relay
3. Unbalance load relay / negative sequence
4. Under frequency relay
5. Stator earth fault relay
6. Under excitation relay
7. Reverse power relay
8. Rotor earth fault relay
9. Voltage drop relay
10. Voltage rise
Transmission line relay
Impedance/Distance relay
Whenever there is a fault, at that time voltage decreases.
WEA2-Lec1-GSO-Auto Recloser
"The process of automatic closing of a circuit breaker, after that it opens." 3 shoots, after that if
fault persists it locks out, otherwise if fault is temporary, it restore the system.
Circuit:
Two portions,
1. Control box operate on 24V
2. Interruption
Types:
1. Fast auto reclosers
With in 0.3 sec
Single shoot
Used in larger systems, bcz if it remain for a long time, synchronism can be lose, and
system collapses.
Time Designation"
2. Delayed/Low auto reclosers
More than 1 sec
3 shoot First try after 5 sec of fault, second try after 8 sec of fault, third try after
10 sec of fault. There is also a reset timer
Install on 11KV feeder Tranches and also on the beginning of each feeder
Tr CBt Arct Fc-Zero 1st shoot
WEA2-Lec3-BatteryRoom
Battery: ->Two or more cells are called battery. ->Batteries should be connected in series. -
>Weather effects the efficiency of battery, if temperature increases by one degree specific
gravity of a battery decreases by 3 points and vice versa. ->132KV and 66KV grid stations need
the battery of 110V(55 cells) 200KV and 500KV grid stations need a battery of 220V(110 cells).
->Ratio of acid and water in battery is 1:4. ->Over current damages the plates and same effect is
due to excess of acid. ->When voltage is below 1.7V than it should be provided with "Booster"
and when voltage reaches to 2.33V it should be change to "Floating" condition.
Specific gravity criteria: 1.240-1.204 efficient/well charge 1.2002-1.204 well charge Less than
1.2002 poor charge
Important parts: Connecting strips Pilot Cell(poor in voltage and also in specific gravity) Gases
wind plug
Precautions of Battery Room: 1.Analyzer should be used at the time of entrance in the battery
room. (Analyzer senses the gas) 2.Exauat fan should be in running position during 24 hours
3.Walls paint with anti acid paint 4.Rubber/Venyl type mat should be on the floor 5.Apren
should be with the worker 6.Brass brush should be with the worker 7.Glasses and gloves
Availability in Battery: 1.Hydro meter 2.DC volt meter 3.Thermometer 4.Petroleum jelly or
Vasline 5.Distilled water
Purpose: 1.Protection for tripping of the relay (coil) 2.Emergency light in control room
WEA6-LEC1-Insulators
Objective: To determine the flash over voltage test 11KV pin type insulator in case of Dry and
wet conditions.
Flash over: An electrical discharge passing through the air, between connecting part of
insulator(pin, conductor) in the form of spark/arc when high voltage is applied.
Puncture: An electrical discharge passing through the insulator's body itself.
HT insulator: Disc type Pin type
LT insualror: spool type strain type
Apparatus: 1.HV control desh 2.Two, Test transformer S/P 220V/100KV AC 3.V, connecting
(4)K, connecting cup 4.Measuring capacitor 100pf, 100KV Ac 5.Earthing switch 6.CM,
measuring capacitor 100pf, 100KV AC 7. 8.RL charging resistor 10M ohm 9.Connection leads
10.Co axial measuring cable 11.Test object
Reasons of Flash over: 1.Lightning stroke 2.Over voltage 3.Permanent fault (phase to phase,
phase to ground) 4.Transient(switching) surges
Creeping distance: Distance between the pin of insulator and line. As creeping distance
increases, flash over value increases too.
Flash Over voltage Wapda Standard: 1.Pin type 11KV 70KV in case of dry condition 40KV in
case of wet condition 2.Disc type 11KV 80KV in case of dry condition 50KV in case of wet
condition 3.Spool type 25KV in case of dry condition 15KV in case of wet condition 4.Strain
type 35KV in case of dry condition 18KV in case of wet condition
Puncture Voltage Wapda Standard: 1.Pin type 11KV 95KV 2.Disc type 11KV 110KV
Test voltages: Pin type, 65KV for within one minute stand Disc type, 75KV for within one
minute stand
Load on insulator: 1.Electrical load (Voltage) 2.Mechanical load ( weight) 3.Atmospheric
variation transients (summer, winds, blow)
Materials: 1.Porcelain covered by smooth and hard glaze of brown color 2.Pin is made of
galvanized mild steel
WEA6-Lec2- Tools and Plant (T&P)
T&P 1.Proper T&P 2.Assigned work
Parts 1.PPE(personal protective equipment) 2
WEA6-Lec3-Cable
Fault detection: Overhead->we petrol Underground->Pulse reflection instrument
Megger: 1.To check insulation 2.To check continuity
Open circuit: Show max value, and tell us the point and nature of fault Short circuit: Intermittent
type of fault (weak insulation fault): "Burn Down Unit", we apply upto 18KV, in this way,
insulation start to burn at the point of weak insulation.
Types of joint in Underground cable: 1.Termination joint (*indoor termination 2inch Per Kv,
outdoor termination 3 inch per KV) 2.Straight joint (Sleeve) 3.Tee joint (Gfw switches)
Types of HT Cables in underground 1. 3/C and S/C PVC , X.LPE U/G cable 2/0 AWG 110A 2.
3/C and S/C PVC, X.LPE U/G cable 4/0 AWG 215A 3. 3/C and S/C PVC, X.LPE U/G cable
500MCM 380A 4. only S/C PVC X.LPE U/G cable 1000MCM 580A
Methods of jointing: 1.Heat shrinkable method 2.Cold shrinkable method 3.Compound method
4.Tapped method
Types of LT cables in underground 1. 2/C or 4/C PVC insulated cable 7/0.052" and current 32A
2. 4/C PVC insulated cable 19/0.052" and 77A 3. 4/C PVC insulated cable 19/0.83" and 115A 4.
4/C PVC insulated cable 37/0.83" and 177A
Parts of HT cable 500MCM S/C PVC XLPE U/G: 1.Conductor carries current 2.Conductor
strand shielding To fill the air gaps between conductor and in isolation, and also cinfine the
circulating current 3.Insulation (XLPE) prevention from current leakage 4.Semi conducting tape
To distribute the electrical stresses evenly produce, when cable is energized. 5.Cooper shielding
tape Services as a drain to ground 6.Cotton tape To hold the mettalic shielding tape in place
during manufacturing and remove sharp edges of the copper shielding tape 7. Cable jacket To
protect the table against moisture, heat and physical damage.
Objective: To locate the cable fault by means of Pulse Reflection in instrument LMG 4000
Formula: 2D = V*t D = (V/2)* t Under test cable : 7/0.052" Limitation up 20,000 meters or
20Km ->This device has an error of 1m to 3m
"Audio frequency unit for pin point
WEA7-Lec1-Jointing of conductor
Types of joints:
Full tension joint: Span is a distance between two poles. If conductor breaks at the point of
dip(tension point), than we apply tension joint. 1.Splice joint For copper stranded conductor
2.Twisted sleeve joint For copper conductor having one wire 3.Single sleeve joint For Rabbit &
Gopher (ACSR) Wasp, Ant & Gnat (AAC) 4.Double sleeve joint Only for ACSR Dog 5 Repair
sleeve joint All ACSR
Non-Tension joint: Where there are dead ends and no tension in the wire. 1."Line tap
compression connector" for permanent jumpers of various line conductor at various places
2."Parallel groove connector", for temporary jumpering of various line conductor 3."U clamp"
used at each end of LT line (dead end of wasp conductor) 4."Service and line tap connector" for
permanent connection of consumer's service with line
Splice joint: 8, 7, 7, 6, 6, 5 turns on each side
Disadvantages of splice joint 1.Gape remains between strands 2.Sparking, heating effects 3.It
may breakdown again
Information on sleeve: There are three things mentioned: Conductor name Use tool to press MD-
6 Dye number W-249
"Oxide inhabiting compound" in sleeve, which prohibits rusting
Double Sleeve joint: Dog: 13 strands (7 steel, 6 aluminum) Sleeve Dye number: 248 (4 press)
Advantages of Proper joint 1.Have good electric contact 2.Have requires tensile strength 3.Have
no weather effect
WEA7-Lec2-transformer
Transformer in No-Load: Two type of current flows in primary, 1.Inductive current for the
magnetization of coil 2.Resistive load as coil has its own resistance.
Types of Loads: Three types of electrical loads 1.Resistive 2.Inductive 3.Capacitive
Power factor: Power factor is inversely proportional to angle between voltage and current.
Actually we are increasing the power handling capacity of the system, whenever generation
remains the same. We can achieve unity power factor by increasing capacitance in the system(up
to a certain value where capacitance totally nullify the inductance), but cost/benefit ratio is not
economical. So our standard is 0.9 in Wapda.
Resistive load on transformer: Resistive load improves the power factor Resistive load creates
voltage drop Resistive load increases losses Losses: losses@ I2
Inductive load on transformer: Current increases Voltage drop increases losses increases Power
factor gets poor
Capacitive load on transformer: current decreases power factor improves
Formula to find value of Capacitor for desired power factor:
KVAR(C) = P(KW)*(tan@1 - tan@2) where, P(KW) is rated load @1 is current angle from
current power factor @2 is required angle from required power factor
WEA-Lec3-Dielectric strength of transformer oil (IEC
296)
Oil name: Hydro Carbon Mineral oil Dicholoro difluoro ethyl benzene
Purpose: 1.Insolation 2.Cooling 3.Flash point (140'C)
Wapda standard for 11KV: ->30KV for one minute with the gape of electrode 2.5mm ->Raising
the voltage at the rate of 2KV/sec
Samples from transformer oil: 1.Top (water vapours) 2.Mid (light impurities, cotton tape small
wooden piece, varnish, wire enamel, paint) 3.Bottom ( Carbon)
Air bubbles: Air dielectric strength is less than transformed oil, so first remove air bubbles than
apply test
If result is less than standard: (Oil is sent to "Reclamation workshop", which is actually a
transformer workshop. There is a "Dehydration plant" over there, in which transformed oil gets
clean.
Vector group(nameplate): If we need to connect two transformers in parallel, than there vector
group should be same. Wapda standard is DY11. By changing internal connection, vector group
changes
WEA8-Lec1
Core Winding
Eddy current in core (hysterisis loss) load current in winding
Losses should be within specified limits (standards defined by IEC or BSS or ANSI or VDE ) .
Wapda follows IEC. If these losses are beyond limit, than transformed would not be purchased.
IEC : International Electric Commission BSS: British Standard ANSI: VDE:
Tests: Core losses/Iron loss/ No load loss: Open circuit test Copper losses: Short circuit test
****Open circuit test*****: This test is used to measure "core losses" HT side open LT side is
excited and is connected with ammeter, voltmeter and wattmeter No load current is flowing in
LT winding which produces magnetic field and heating effect. 1.Reactive component of current
produce magnetic field 2.Active component of current produce Heat Due to sinusoidal current
alternating magnetic field produces which contracts and expands with time. So, this changing
magnetic field produces Emf.
Eddy losses: The same magnetic field links with the core and an emf hence a current known as
"eddy current" flows, which produce losses. This loss can be minimized by using insulating
sheets.
Hysterisis loss: Due to polarity change in core (reversal of magnetism). Our frequency is 50Hz
but change in polarity of domains is 100Hz. Due to this fast changing, their remains some
magnetization in the core and also a sound ( magnetostriction) is produce in the transformer due
to this phenomenon.
Material of core: Silicon steel (Its area under the curve of current-magnetization curve is less, so
hysterisis losses are less)
Why we are exciting LT not HT in No load test: 1. Less voltage is require for excitation instead
11KV main power supply would be required 2.Problem in measurement of high voltage
3.Protection in handling
No load current in Three phases: Three currents in three phase of three phase transformer would
not be equal. Central phase current would be less than side phases, this is because of the
symmetry of three coils in a transformer.
Standard readings: 10KVA 15KVA 25KVA 50KVA
WEA8-Lec2-Tying/Binding of Conductor
Aluminium Annelead tie wire Size= 4mm dia
Types: 1.Top tie 2.Side tie 3.L.T tie
Conductor Top Tie Side Tie Panther 13'. 12' Osprey 12'. 11' Dog 8'. 7' Rabbit 7' 6' Gopher 6' 5'
Wasp 7' Ant 6' Gnat 5'
Top Tie= 2+3+2+1+1+1+2=12 Side Tie= 2+3+1+1+1+2=10 L.T Tie = 2+3+1+1+1+2=10
HT insulator: Pin type Disc type (dead end)
LT insulator: Spool/shackle type Strain type (dead end)
(Armour rod was used before, for the protection of conductor) ->Transformer earthing resistance
is less than 5 ohm ->Consumer meter resistance is 10 ohm
WEA8-Lec3-Energy Meters
Meter records electrical energy in KWh.
Principle: Electromagnetic induction
Parts of Meter: 1.Potential coil 2.Current coil 3.Spindle Jeweel Disc 4.Permanent magnet 5.Dial
Truch 6.Name plate 7.Terminal block 8.Base plate 9.Glass window 10.Meter cover
Mechanism: 1.Driving mechanism 2.Braking mechanism 3.Recording mechanism
Testing method: 1.Long period test 2.Short period test
Long period test/ Energy Comparison method: In the long period test energy recorded by
"observation meter" and energy recorded by "Correct method". Compare the both recorded
energies and the %age error is find by the following formula: %error= ((Eo - Ec)/Ec)*100 Eo=
Energy recorded by observation method Ec= Energy recorded by correct method
2.Short Period Test %age error calculated by the following formula: %age error = ((Tc -
To)/To)*100) Tc = Time calculate To = Time observed
Tc= (3600*rev)/(Load KW*meter factor) if meter is CT operated, then
Etc=((3600*rev)/(load*M.C))*M.F
M.F= Ct ratio/ meter current ratio
Check: 1.if Tc>To then meter is fast 2.if To>Tc then meter is slow
Wapda standard tolerance: +-2.5% to +-3%
TOU meter: The TOU static meter is the first of a new generation of electronic meter that is
designed by advance Computer and electromagnetic Compatibility Technology. Meter is fully
static without any moving parts. And its performances are conformity with Wapda specification
and relevant international standards. 3-phase multi rate / multi function (TOU/TOD) meter
designed to meet the high accuracy and multi tarrif requirements.
Parts of meter: 1.Vs = voltage sensor 2.Cs = Current sensor 3. DSP=digital signal processing
4.MCU=micro computer unit 5.IC's 6.CT's
Salient characteristics of an Electromagnetic meter: 1.High functionality 2.High accuracy 3.No
tilt error 4.Susceptibility to extreme environments 5.Susceptible to Electromagnetic
compatibility / interference issues 6.Max expected life of 15 years
S/P static meter LCD display: ->serial number ->Total energy (kWh) –
WEA9-Lec1-Providing Temporary Earthing to the Line
Need: 1.For the safety of working staff/to avoid mishap 2.To avoid undue/wrong operation of
any equipment 3.To do the job efficient being safe/to achieve better workmanship
Source of Re-Energized of any Dead line: 1.Back supply a) operation of Generator of any
consumer b) Double feeder supply c) Ring man system (RMS/RMU) 2Due to induction of any
other line passing over 3.Due to lightening 4.Break down of any other feeder passing over 5 Due
to tree branches hanging between two feeders.
Where tempo earthing: Both side of working zone
PTW is issued to lineman, than same person have to cancel it. 11KV earth tester to check the
status of line Source side(grid) has to earth first, than Load side(working side) has to earth After
work T&P is removed PTW is cancelled
WEA9-Lec2-Induction motor, power factor improvement
Stator is provided with three phase ac Rotor is short circuited
Power factor: Power factor at no load is very poor 0.1-0.2 At normal load Power factor is 0.5-0.6
At max load power factor is 0.8-0.86
Why not to run on no load? Because at that point rated current is flowing and if due to some
reason voltage drops to some value than at same value motor will draw more current
Normal load: 60% to 80% At this load power factor is 0.5-0.6
Power factor: ->Cosine of the angle between voltage and current waveform. Angle depends upon
nature of load. ->Ratio of active power and apparent power ->Ratio of resistance and impedence
When we apply the voltage at no load, than the voltage is only used for magnetization, it means
there is some kind of inductive load, (no resistive), so the system power factor at no load is poor.
Motor is drawing two types of current, 1.Working current 2.Magnetization current
Equipment use for pf improvement: 1.Capacitors 2.Synchronous condenser: Basically its
synchronous motor, running in overexcited mode with no load. 3.Phasor bansers
Delta and star: Capacitor required in star is three times capacitor required in delta. C(star) =
3*C(delta) But, In distribution side it is beneficial to use in Delta In HT side(feeder) it is
beneficial to use in Star(Less in isolation is required, because voltage in star is less than voltage
in delta)
Fuses required: Up to 5horse power direct starting is used and fused are required for double
rating
Greater than 5horse power motor "star delta starting" method is used, and fuses size need to be
1.5 times of motor rating.
Shuttling of KVAR: Capacitor stores KVAR from the source and then provide it to the system
whenever polarity changes. These KVAR are stored in the form of electric field. Same shuttling
phenomenon occurs in inductor, and KVAR are stored in magnetic field.
WEA9-Lec3- Transformer turn ratio
When applying "D" some of the turns get shorted. The D of that coil drops again and again when
some turn of transformer coil get short, the other two coils (D's) remain stand by.
WEA10-FESCO Transformer Workshop
Categories of repairing: 1.Major 2.minor Transformer came from SDO or Exion 3.Major
repairing from FESCO store
Dehydration: for 72 hours 1.Oil is sent to dehydration plant through pumps Oven: Winding is
kept in oven, to remove moisture
Washing section: Tank is sent to this section to clean it, there may be blockage of carbon in
pipes. Castic soda 90'C to 110'C 72 hours
Dehydration plant: 1.Oil gets clean 2.Dielectric strength recovers
Oil test: 1.Dielectric strength 30KV with one minute stand maintaining 2.5mm 60KV for new oil
2.Moisture test Absent 3.Specific gravity 0.895 4.Flash point 140'C 5.Viscosity 40 CST (Centi
Stroke) 6.Delta Tan test For power transformer
Winding section:
Paint section: Smoke gray for outer side Red oxide for inner side
Transformer test: 1.Winding resistance R=? 2.No load test Iron loss test 3.Full load test
converted at 75'C Copper loss 4.Induce voltage insulation test 5.Desperate source over voltage
with stand high voltage test 6.Turn ratio test voltage ratio 7.Air pressure test leakage test 8.Bird
protection test prevent birdage 9.Tin coating & other allied test on connector 10.Visual and
dimentional 11.Oil test of transformer oil quality
Winding section: After design testing 12 transformer g For insolation we use, Press pan paper
Press ply sheet
WEA11-Lec1-Steam Power plant
Advantages of simulator:
Response according to actual plant
Check the response 10 times faster than actual time
Back train provision from 1 mint to 5 mint
Snapshots, from where we want to start training we can start from that point
Synchronization of plant is the issue in actual plant, so here we can get trained easily
Mall function faults (95 in number)
Our simulator specifications:
Balanced drop furnace
Tandem compound turbine
Water tube boiler
37-40% efficiency
Components:
Boiler
Steam Turbine
Generator
Panels:
Fuel
air section
Water steam panel
*****Boiler*****
Color scheme:
Dark green color for "pure water"
Light green for "Raw water"
Dark red for "dry steam"
Light red, for "wet steam"
It is also called "steam generator”.
Riser tubes
Steam is generated in "Riser tubes" and is stored in Steam drum.
Down covers tube
"Down covers tube" just outside the body. Natural circulation of water in riser tubes and down
covers"
Types:
Fire tube boiler
Fire in the pipes, water outside
Water tube boiler Water inside the pipes, fire outside
Fuel:
Propane Just for ignition of main boiler, as a pilot flame
Crude oil (Bunker C)
Light oil
Burners:
16 burners
4 elevations (4 burner on each elevation)
Corner firing
Types of furnaces:
1. Pressurized furnace
2. Balanced drop furnace
Fans:
Forced dot fan(2)
Induced dot fan(2 fans)
Up to 50% load one FD fan is enough Pressure inside burner is balanced, minus 1mili bar
vacuum.
Flue gases (200'C) Rotary type air heater to heat up the gases.
Burner position:
Changing the position of boiler is called "tilting". If temperature is not rising than do not change
the fuel injection but apply tilting
*****Turbine*****
Types:
1. Impulse turbine
2. Reaction turbine
Portion of Turbine:
1. High pressure turbine (HP)
2. Intermediate pressure turbine (IP)
3. Low pressure turbine (LP)
(These all have same speed, mounted on the same shaft)
Quality of steam to run turbine:
Temperature not less than 320'C (minimum)
50 bar pressure (minimum)
165 bar (normal)
540'C (normal)
WEA11-Lec2-Steam power plant
How we get feedback that load is greater than generation??
Voltage dips Frequency falls
Frequency is controlled by hydal plants not by thermal plants.
Hydal:
Thermal:
Two types of it,
Steam turbine
Boiler
Turbine
Generator
Gas turbine
In thermal plants we cannot control frequency, because in short time we cannot inject
more heat, so if we do so, than steam gets from dry steam to wet steam, on which we
have a protection, so unit trips.
*****Steam Turbine*****
Quality of water:
Demy water/Demineralized water.We install chemical plant. Get water from canal or tube well
(high conductivity). Chemical dosing by sulphuric acid dosing and got demy water. If we are
running the plant for the first time, we take water from "feed water tank". Feed pump 15-20 feet
high. Boiler drum is filled by it
Deaerator:
Showering from one side and heat from other side, so that components remove from it.
Hydrazine, phosphate used for dozing.
Starting of boiler:
Not immediate flaming in order to avoid explosion due to the storage of gases.
Purging System:
A system to remove gases in the boiler. For this two type of fans 1.Forced draft fan Suction is
from Hot reservoir or hall 2.Induced draft fan Produce vacuum in the furnace Air fuel ratio is
maintained in ratio 1:10
After forcing boiler is fire up. Now we have to provide heat so that 1' rise in temperature in one
minute in order to avoid "hammering"
Type of Boiler start:
1. Cold start (Less than 150'C)
2. Warm start (150'C to 250'C)
3. Hot start (greater than 250'C)
Waste water temperature:
Its temperature should be 7'C.
Auxiliary steam:
We heat up the turbine before feeding steam to it. In turbine the upper and lower part shouldn't
have its temperature greater than 50'C.
Turbine drain system:
All heat that is condensate is sent to "Hot well".
Rolling of turbine:
Before rolling check the following conditions, Turbine heating Lubrication system Hydrogen
cooling Seal oil system
Turbine speed limits:
500rpm for 30 minutes 1000rpm for
WEA11-Lec3-Steam Power
Tandem compound turbine:
Turbine having more than one cylinders
*****Water Cycle*****
Water should be clear up to 1ppm (pound per million) 1100 ton per hour water is
required, so we recycle the same water.
Steam is condensed in "condensator" having temperature 50'C to 80'C 1 or 2% water can
be lost, so regular compensation is needed.
When plant is not running, and we have to run the plant, than the cycle is as:
Water is filled in "Hot-well" which is for the storage of condensate water, where water
level is 200mili meter.
"Condensate pump" A and B, one would work other will be in standby.
"Polisher" checks whether the water is pure or not, if not, it removes impurities.
"Gland steam condenser", in which there is a heater, which warms the water, and is the
first step of per heating.
"Deaerator pump" which pumps the water.
"LP Heater" which again rises the temperature, here steam is used for heating purpose
which is called steam bleeding/steam extraction.
"Deaerator" which removes air from the water, because air creates hammering in the
pipes. Steam is injected at certain angle and keep away the air with it.
"Deaerator storage tank", in which level of water is 2m.
Three "Boiler feedback pump" with pressure 200 bars, one runs at 50% load, second
started work at full load, these two have motors, other which is in standby is run by mini
turbine.
"HP heater" which further heats up the water.
((5 steam lines, two are from LP turbine, two are from IP turbine, and one from cold
reheat line. Two are used in LT heater, Two are used in HP heater, one is used in boiler
heat pump (mini turbine pump)))"
Regulating valves, (low load valve, full load valve), 250'C.
After that water goes to economizer gaining temperature 280'C and then to Boiler drum.
Now this is warm water and easily converted to steam.
Down comer tubes:
Just outside the boiler, from which water comes from boiler drum into the boiler.
Riser tubes: Steam is made in Riser tubes.
Note: 7 stages of preheating of water before going to drum
WEA12-Lec1-Combine cycle
It has following parts, 1.Gas turbine 2.Heat recovery steam generator 3.Steam turbine
*****Gas Turbine*****
Fuel:
HSD oil/diesel
Furnace oil/crude oil
Natural Gas
Components:
1. Compressor
2. Turbine/Combustion chamber
3. Generator
Compressor:
To compress the natural air, which rises the temperature of compressed air. Air is cleared
through filters because Dust and moisture have to remove, which can accumulate on blades,
results in unbalance of weight causes vibration.
Two types of blades use in turbine,
Rotatory blades
Stationary blades
Fit in diapharam in the form of segments.
Three stage gas turbine Four stage gas turbine
Barings:
Two type of Barings,
1. General barring
2. General thrust barring
Barings are lubricated from below, because in static condition shaft can touch the white
metal. Lubrication oil has the function of "cooling, reduce friction, center the shaft".
General:
A part of shaft which rotates within the barring is called General.
White metal:
If anytime lube oil system fails, than white metal is a protection of the shaft. Shaft is made of
hard metal and barring is made of soft metal, so if shaft hits against the white metal, it is saved
from damaging.
Gas turbine is designed on 30'C and its Exhaust temperature is 500'C. Lower the ambient
temperature lower the exhaust temperature, and hence it can take more load. To control the
temperature, eight "Thermocouple" are installed. If temperature rises, the machine left the load
and if temperature is not controlled machine gets trip. If temperature is below 15'C than
efficiency reduces. In normal days we have ambient temperature of 45'C so an inter-cooling
system "Evaporator cooling system" is introduced.
*****Heat recovery Steam Generator*****
Types:
1. Horizontal
2. Vertical
Parts:
Economizer
Evaporator
Super heater
Economizer->Boiler drum->Evaporator->Boiler drum->Super heater
In steam drum there are "steam separators" which desperate steam from water.
Source:
1. Direct from waste heat
2. Supplementary
WEA12-Lec2-Boiler and turbine terms
*****Boiler*****
1600'C is the temperature of boiler 300'C is the temperature of steam
Balanced Draft furnace
Pressure is not too high not too low
Furnace Probe:
Its function is of temperature measurement. It should be in before start, so that we get the
knowledge whether or not there is any fire in the furnace before
Super Heater:
Three super heaters. It has so many tubes which increase the surface also wet steam to be there
for some period. They convert wet steam to Dry steam.
D-Super heater:
It is connected with the coils of super heater and give the control to control temperature. These
have interlocking and don't open until pressure is 70bars. It has the disadvantage that if there is
any leakage than injection of pure water will be there and temperature reduces without our
requirement.
Economizer:
Its for preheating of water going into drum. Efficiency of the plant increases.
Steam type air per heater:
Initially air is warmed with the help of steam.
Rotary Type Air preheater:
Flu Gas recirculation fan:
They recirculate the flue gases in the furnace. They suck gases from the exhaust end and
discharge that warm air just above the burners, so fuel reduces.
Fuels:
1. Propane (yellow color)
2. Bunker C (Brown)
3. Light oil (orange)
When plant is just going to start, start it with "light oil", if bunker C is just ready and we
cannot use it until drum pressure is 40 bars.
Bunker C has heating quality (Btu per pound) greater than light oil, so we cannot slow
heat with bunker C.
Why slow heating of boiler is essential??
Because sudden heating causes "Thermal Stresses" of metal tubes, than cracks in the next stage
and ultimately damage the tubes.
If a fuel is in liquid form than before burning we have to "atomize" it. In atomized form
fuel is almost in gaseous form, than "pilot burner" will burn the fuel.
Methods of atomization:
1. Mechanical atomization
High pressure pumps discharge the fuel from the nozzles. Bunker C is atomize in this
way.
2. Air atomization
WEA12-Lec3-Steam cycle
Cycle:
Drum to primary super heater
Primary super heater to D-Super heater
D-Super heater to Secondary super heater
Secondary super heater to D-Super Heater
D-Super Heater to tertiary super heater/ final super heater, where it is converted from
Wet steam to Dry steam/super-heated steam/ live steam, having temperature 540'C and
165 bars
HP turbine 320'C pressure 35 bars, than it again goes to furnace for re heating
Furnace has "Primary re heater" than it goes to "Secondary re heater" than it goes to "IP turbine"
than to "LP turbine"
Main steam drain:
Main Steam safety valve (mechanically operated):
Operated at 182bar
Electrometric release valve:
178bar
HP turbine bypass line:
If pressure is beyond 170 bar, than steam is bypassed and sent to condenser.
Main steam isolation valve:
Close up to 40 bars, because initially pressure of steak is low, so we block the steam until its
pressure rises.
Governing valve:
On the inlet of HP turbine, these are to regulate the steam according to load demand.
Boiler master:
To watch the line and regulate the fuel and air to maintain Temperature.
If temperature is still not under control than tilting of burners
Tilting of burner:
To change the position of burner.
If still temperature is not controllable, than we inject water directly from D-Super heater, this is
the last option.
Re circulation cycle:
It is the pipe, which collect warm exhaust having unburnt particles in it, to feed again into the
furnace. This would increase efficiency. Secondly it uniformly heats the boiler when the plant is
run initially.
Fuels:
1. Diesel
2. Bunker C/ Crude oil/ Furnace oil
Usually it is very thick and cannot be pumped easily. So we warm it to 110'C and then
there are pumps which rises the pressure to 70 bars. At this temperature and pressure, it would
behave like diesel (in sense of pumping)
Temperature Pressure Ranges:
HP turbine:
Inlet 540'C 165 bars,
Outlet 320'C 35 bar
IP turbine:
Inlet 540'C 32 bars
Condenser: 0.06bar vacuum
Turning Gear: When plant is shut down
WEA13-Lec1-Gas Turbine
Kepco unit 1 and 2
Model V93.2 70MW unit Quick start unit, within minutes its on full load but its cost per unit is
higher. Its not self start, we need some media to start it.
Components:
Burning chamber Turbine Generator
Hot gases directly hit wit blades of turbine. Exhaust temperature is 500'C 70% power is used by
compressor itself, and in remaining 30% some of it is used to run auxiliary. So, the efficiency is
18%. So we install CCP(Combined cycle power plant)
To start it we install 1.induction motor, 2.Diesel engine 3.Start generator as motor
When generator start as motor, it will be synchronous motor, it has same problem of self starting,
so we gave low frequency to it, by turning gear having frequency 100rpm with the help of
Hydraulic pressure. 1.6Hz frequency.
Now slowly increase the frequency so speed of the generator(which is now working as
synchronous motor) will increase correspondingly.
Electrical circuit Control oil circuit Fuel circuit
********Electrical Circuit****** If unit is running plant supply power to the system. If unit is
shut down, power is supplied from system to the plant.
5 circuits are taken from the 6KV bus bar
1. 6Kv/540V than convert it to DC for excitation
2.Heavy oil heater 6kv/400V to heat the oil
3.Emergency circuit A small "black start generator" for emergency 4.SFC (Static Frequency
converter) circuits: It is the circuit from where frequency is regulated in order for starting. First
AC to DC, than DC to AC of our desired frequency 5.Circuit for fan and pumps
Up to 2100rpm it remains as motor.
****Lube Oil and Control oil Circuit** Air bleeding: 5th and 10 stage of the compressor 2 lines
are taken, so that from here, when plant is just started air is compressing but is not having
utilization, than Release compressed air in the exhaust so that it will not back pumped. Same is
for, when plant is shutting down.
Pilot fame: 480'C
600rpm main flame is on, but it has not enough power so that turbine can share power with the
motor.