Waimea Community Dam TDC Council...Construction Update: Spillway Waimea Water Ltd 24 Spillway cut...

29
Waimea Community Dam TDC Council 25 June 2020 Waimea Water Waimea Water Ltd 25/06/2020 1

Transcript of Waimea Community Dam TDC Council...Construction Update: Spillway Waimea Water Ltd 24 Spillway cut...

  • Waimea Community DamTDC Council

    25 June 2020

    Waimea Water

    Waimea Water Ltd25/06/2020 1

  • Agenda

    1. Covid-19 impact

    2. Funding and expenditure

    3. Expenditure and progress

    4. Safety

    5. Environmental

    6. Rockfill: The geology challenge

    7. Design update

    8. Construction update (video)

    9. Questions

    Waimea Water Ltd 225/06/2020

  • Meet the WWL Team

    Waimea Water Ltd 3

    • Designer (PS-1, PS-4) Damwatch Engineering

    • Reviewer (PS-2) GHD Engineering

    • Engineer to Contract Stantec

    • Contractor (PS-3) Fulton Hogan Taylors

    • Quantity Surveyor Rawlinsons

    • Contract Law Anderson Lloyd

    • Programme CCCL

    • Safety Impac; Intesafety

    • Accountant Findex

    • Banker ANZ

    • Auditor Audit NZ

    25/06/2020

  • COVID-19❖ WWL incurs cost of 5-week Suspension and further delay (no Force Majeure provision in NZ3910)

    ➢ Further week delay to remobilize and implement facilities

    ➢ Not covered by insurance

    ❖ Productivity impacted on resumption with level-3 / level-2 protocols

    ➢ NZ Construction Industry Standards

    ❖ Supply chain constrained and likely to slow project: Spares, parts, equipment

    ➢ Uncertain how international supply chain recovers

    ❖ Cost of suspension and recovery to yet be determined

    ➢ Looking to NZ Construction Industry. No precedents

    ➢ Impact of COVID-19 to be determined during 2020/21 year per Final SOI

    Waimea Water Ltd 425/06/2020

  • -

    20

    40

    60

    80

    100

    120

    140

    Dec-2018 Dec-2019 Dec-2020 Dec-2021

    $ m

    illio

    ns

    Budget New forecast (SoI) Actual

    Funding and expenditure: 31 May 2020

    Waimea Water Ltd 5

    Funding and Spend Forecast cost & schedule to complete

    $50.2m

    Excludes Cost of COVID-19$129.4m

    July 2020

    August 2021

    25/06/2020

  • 0% 25% 50% 75% 100%

    $

    Months

    ECI Costs During Construction Construction Variations Remain Original Budget Revised Forecast

    $104.4m $129.4m

    40mths37mths

    Expenditure and progress

    Waimea Water Ltd 6

    Expenditure

    Progress

    $50m

    16 months

    Excludes Cost of COVID-19

    25/06/2020

  • Context (SOI)

    Waimea Water Ltd 7

    Excludes Cost of COVID-19

    25/06/2020

  • Programme: + 6 months = +1 season

    Waimea Water Ltd 821/04/2020

    ❖ Currently expect 6 month delay to programme with further risk of slippage

    ❖ Exploring and pursuing recovery programme (shift work; defer works)

  • Safety: No injuries to date

    Celebrating 500 days injury free

    Waimea Water Ltd 9

    Leading: Contractor Audit and Inspection

    0

    5

    10

    15

    20

    25

    30

    35

    Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20

    Lead OFI Low Potential Med Potential High Potential

    0

    1

    0

    1

    2

    3

    4

    5

    Inci

    de

    nt

    Fre

    qu

    en

    cy r

    atio

    sLT

    IFR

    / M

    TIFR

    / T

    RIF

    R

    Nu

    mb

    er

    of

    inci

    de

    nts

    LTI

    MTI

    FAI

    HPI

    MTIFR

    TRIFR

    Lagging: Accidents, Harm, HPI

    25/06/2020

  • Environmental: Full compliance with consent

    Waimea Water Ltd 10

    Lead: Audit, Inspection and Water Quality monitoring

    25/06/2020

    0

    2

    4

    6

    8

    10

    12

    14

    Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20

    No

    . Au

    dit

    s p

    er m

    on

    th

    TDC Compliance Contractor Weekly Audit Contractor Monthly Audit

    FHTJV HO Env Visit Environmental Control Inspection Environmental Follow Up Audit

    Southern Skies ESC Inspection SLR Water Quality Visit

    #42 River Health Indicator: Quantitative Macroinvertebrate Community Index

    • Approved 5 Environmental Management Plans

    ✓ Verified

    • Approved 9 SCEMPs

    ✓ Verified

    All required plans for current works in place, certified, verified and functioning

    5

    5.5

    6

    6.5

    7

    7.5

    8

    8.5

    6/03/2017 22/09/2017 10/04/2018 27/10/2018 15/05/2019 1/12/2019

    QM

    CI I

    nd

    ex (

    clip

    ped

    to

    sh

    ow

    d

    etai

    l)

    QMCI Upstream

    QMCI Downstream

    20% below averagepre-constructionU/S QMCI

    During ConstructionPre- Construction

  • Environmental: Full compliance with consent

    Waimea Water Ltd 11

    #45 River Health Indicator: pH

    #44 River Health Indicator: Deposited Fine Sediment

    25/06/2020

    Independent ecologist verifies river health indicators

    0

    2

    4

    6

    8

    10

    12

    pH

    pH Upstream

    pH Downstream

    Lower Limit

    Upper Limit

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    50

    % o

    f ri

    ver

    bed

    wit

    h f

    ine

    sed

    imen

    t d

    epo

    sits

    Upstream

    Downstream

    Downstream Threshold

  • Rockfill: The Geology Challenge

    Waimea Water Ltd 12

    ▪ Embankment trials late December 2019 and early January 2020 identified Rock degradation

    Heavily broken down– Not free drainingLess broken down– Free draining

    Expected and Needed Discovered

    25/06/2020

  • Rockfill: The Geology Challenge

    Waimea Water Ltd 13

    ▪ Discovering more argillite (mud / siltstone) (~70%) and less greywacke (sandstone) than expected

    ▪ Greywacke (sandstone) dispersed amongst predominant argillite. Difficult to salvage. (VIDEO)

    ▪ Fissile argillite showing tendency to break along insipient foliations

    ➢ Spillway Excavation: “May yield a minimum of 350,000 m3 of rock that will consist of slightly weathered to weathered (Class 1 & 2) greywacke.” (2014). Predominantly fissile argillite

    ➢ Need to find suitable drainage material from alternative sources (cost)

    25/06/2020

  • Design: Rezoning embankment to manage geology❖ Expect less harder class-1 material

    ❖ Testing in early 2020 identified breakdown on compaction

    Increase drainage layers

    Alternatively source drainage rock

    Waimea Water Ltd 14

    Free Draining

    Not Free Draining

    Drainage

    25/06/2020

  • Design: Spillway modified for improved resilience

    Waimea Water Ltd 15

    2009: 5-92012: 10-142017: 15-17

    Design modifications due to recent learnings from international spillway incidents (international standards)

    Oroville (right) failure due to poor drainage and anchoring detailing (pressure beneath fn velocity)

    Whaley Bridge (UK) no drainage and poor slab detailing combined with poor maintenance

    Modifications for resilience (requested by CIIL):

    Drainage reviewed and upgraded

    Anchoring design reviewed and upgraded

    Additional modifications driven by topography and encountered geology.

    25/06/2020

  • Design Update

    ✓ Spillway:

    ▪ Redesigned with vertical walls to mitigate topography / geology risks RHS

    ▪ Increased drainage per recent standard

    ▪ Completed and peer reviewed

    Waimea Water Ltd 1625/06/2020

  • Design Update: Other items

    Mechanical and Electrical

    ❖ Not designed or priced at commencement of work

    Provision Sum challenged

    To be priced ~3rd Quarter 2020

    ▪ Progressing detailed design

    Switch to single outlet pipe aiming to realise cost savings

    Modifications for future hydropower installation

    Waimea Water Ltd 17

    2009: 5-92012: 10-142017: 15-17

    25/06/2020

  • Power Generation: Opportunity

    Enlarge Reservoir / Powergen

    ▪ Fuse Gate to utilise 2.3m / 5m of flood reservoir

    ▪ Activate in event of large flood say 1:10,000 yr AEP(55% - 70% of PMF 1094 m3/s)

    ▪ + 1.5Mm3 storage to ~15Mm3 (15%)

    Storage increases powergen utilisation

    Increase resilience to droughts / growth / demand

    Waimea Water Ltd 1825/06/2020

  • Agenda

    1. Covid-19 impact

    2. Funding and expenditure

    3. Expenditure and progress

    4. Safety

    5. Environmental

    6. Rockfill: The geology challenge

    7. Design update

    8. Construction update (video)

    9. Questions

    Waimea Water Ltd 1925/06/2020

  • Construction Update

    Waimea Water Ltd 20

    LHS Plinth

    Culvert

    RHS Plinth

    Spillway

    25/06/2020

  • Diversion Culvert: ~80% complete

    Waimea Water Ltd 21

    ✓ Completed Floor

    ✓ 12/17 wall & roof sections completed

    ➢ Expect to complete by Aug and divert river September 2020

    25/06/2020

  • Construction Update: Forming LHS Plinth

    Waimea Water Ltd 22

    ✓ Foundation treated and site blinding concrete complete

    ✓ Commenced forming plinth

    25/06/2020

  • Construction Update: Preparing RHS Plinth

    Waimea Water Ltd 23

    ✓ Foundation treatment and treatment underway

    25/06/2020

  • Construction Update: Spillway

    Waimea Water Ltd 24

    ▪ Spillway cut underway

    ➢ Exposed first 20 m section of foundation

    ❖ Uncovering significantly weathered foundation that will require treatment

    ▪ Close to cliff edge

    ✓ Supports change in design to self-supporting vertical walls, rather than a liner

    ▪ Will evaluate extent of any edge support

    25/06/2020

  • Construction Issues: Unexpected Voids

    Waimea Water Ltd 2521/04/2020

    ❖ >1000 m3 concrete

    ✓ LHS & Culvert done

    ❖ RHS, Spillway and starter dam to do

  • Closing: By the numbers

    Waimea Water Ltd 2625/06/2020

    Task Total Quantity Unit

    Vegetation Clearance 85 Hectare

    Excavation 633,000 m3

    Fill 430,000 m3

    Cut to Waste 311,000 m3

    Material Processing 120,000 m3

    Concrete 22,000 m3

    Reo Steel (bars) 3,900 t

    Reo Steel (mesh) 10,000 m2

    Anchors 4,200 No.

    Concrete Face 10,000 m2

  • More Information

    Waimea Water Ltd 2725/06/2020

    https://www.google.com/imgres?imgurl=https%3A%2F%2Fwww.facebook.com%2Fimages%2Ffb_icon_325x325.png&imgrefurl=https%3A%2F%2Fwww.facebook.com%2F&docid=QanOc4elti2_UM&tbnid=eSZWZPUruLZj3M%3A&vet=10ahUKEwjQgNWZ-dblAhUz6XMBHaOLCVMQMwh1KAAwAA..i&w=325&h=325&itg=1&bih=967&biw=1920&q=facebook&ved=0ahUKEwjQgNWZ-dblAhUz6XMBHaOLCVMQMwh1KAAwAA&iact=mrc&uact=8

  • 17 Dec 2019: Rezoning embankment to manage geology

    ❖ Expect less harder class-1 material

    ❖ Experiencing more fines

    Increase drainage layers with

    Processed (screened) out fines

    Waimea Water Ltd 28

    2009: 5-92012: 10-142017: 15-17

    02/12/2019

  • Design: Geosynthetic membraneReplace concrete face with Geosynthetic membrane

    Improved resilience to settlement and seismic(elasticity), benefit accentuated by softer rock

    CO2, Cost and Schedule savings

    Easy to repair; performance warranty

    Testing demonstrates expected life 50-100 years (robust to UV)

    Meets EU and International standards for Health and Environmental impacts

    Carpi Ltd: Installed

    • 54 New Dams since 1988 (26 larger than Waimea)

    • 142 Retrofitted Dams since 1970 (63 since 2010)

    • Used on Tekapo Canals (2013 / 2014)

    Waimea Water Ltd 29

    2009: 5-92012: 10-142017: 15-17

    25/06/2020