Waimea Community DamTDC Council
25 June 2020
Waimea Water
Waimea Water Ltd25/06/2020 1
-
Agenda
1. Covid-19 impact
2. Funding and expenditure
3. Expenditure and progress
4. Safety
5. Environmental
6. Rockfill: The geology challenge
7. Design update
8. Construction update (video)
9. Questions
Waimea Water Ltd 225/06/2020
-
Meet the WWL Team
Waimea Water Ltd 3
• Designer (PS-1, PS-4) Damwatch Engineering
• Reviewer (PS-2) GHD Engineering
• Engineer to Contract Stantec
• Contractor (PS-3) Fulton Hogan Taylors
• Quantity Surveyor Rawlinsons
• Contract Law Anderson Lloyd
• Programme CCCL
• Safety Impac; Intesafety
• Accountant Findex
• Banker ANZ
• Auditor Audit NZ
25/06/2020
-
COVID-19❖ WWL incurs cost of 5-week Suspension and further delay (no Force Majeure provision in NZ3910)
➢ Further week delay to remobilize and implement facilities
➢ Not covered by insurance
❖ Productivity impacted on resumption with level-3 / level-2 protocols
➢ NZ Construction Industry Standards
❖ Supply chain constrained and likely to slow project: Spares, parts, equipment
➢ Uncertain how international supply chain recovers
❖ Cost of suspension and recovery to yet be determined
➢ Looking to NZ Construction Industry. No precedents
➢ Impact of COVID-19 to be determined during 2020/21 year per Final SOI
Waimea Water Ltd 425/06/2020
-
-
20
40
60
80
100
120
140
Dec-2018 Dec-2019 Dec-2020 Dec-2021
$ m
illio
ns
Budget New forecast (SoI) Actual
Funding and expenditure: 31 May 2020
Waimea Water Ltd 5
Funding and Spend Forecast cost & schedule to complete
$50.2m
Excludes Cost of COVID-19$129.4m
July 2020
August 2021
25/06/2020
-
0% 25% 50% 75% 100%
$
Months
ECI Costs During Construction Construction Variations Remain Original Budget Revised Forecast
$104.4m $129.4m
40mths37mths
Expenditure and progress
Waimea Water Ltd 6
Expenditure
Progress
$50m
16 months
Excludes Cost of COVID-19
25/06/2020
-
Context (SOI)
Waimea Water Ltd 7
Excludes Cost of COVID-19
25/06/2020
-
Programme: + 6 months = +1 season
Waimea Water Ltd 821/04/2020
❖ Currently expect 6 month delay to programme with further risk of slippage
❖ Exploring and pursuing recovery programme (shift work; defer works)
-
Safety: No injuries to date
Celebrating 500 days injury free
Waimea Water Ltd 9
Leading: Contractor Audit and Inspection
0
5
10
15
20
25
30
35
Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20
Lead OFI Low Potential Med Potential High Potential
0
1
0
1
2
3
4
5
Inci
de
nt
Fre
qu
en
cy r
atio
sLT
IFR
/ M
TIFR
/ T
RIF
R
Nu
mb
er
of
inci
de
nts
LTI
MTI
FAI
HPI
MTIFR
TRIFR
Lagging: Accidents, Harm, HPI
25/06/2020
-
Environmental: Full compliance with consent
Waimea Water Ltd 10
Lead: Audit, Inspection and Water Quality monitoring
25/06/2020
0
2
4
6
8
10
12
14
Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20
No
. Au
dit
s p
er m
on
th
TDC Compliance Contractor Weekly Audit Contractor Monthly Audit
FHTJV HO Env Visit Environmental Control Inspection Environmental Follow Up Audit
Southern Skies ESC Inspection SLR Water Quality Visit
#42 River Health Indicator: Quantitative Macroinvertebrate Community Index
• Approved 5 Environmental Management Plans
✓ Verified
• Approved 9 SCEMPs
✓ Verified
All required plans for current works in place, certified, verified and functioning
5
5.5
6
6.5
7
7.5
8
8.5
6/03/2017 22/09/2017 10/04/2018 27/10/2018 15/05/2019 1/12/2019
QM
CI I
nd
ex (
clip
ped
to
sh
ow
d
etai
l)
QMCI Upstream
QMCI Downstream
20% below averagepre-constructionU/S QMCI
During ConstructionPre- Construction
-
Environmental: Full compliance with consent
Waimea Water Ltd 11
#45 River Health Indicator: pH
#44 River Health Indicator: Deposited Fine Sediment
25/06/2020
Independent ecologist verifies river health indicators
0
2
4
6
8
10
12
pH
pH Upstream
pH Downstream
Lower Limit
Upper Limit
0
5
10
15
20
25
30
35
40
45
50
% o
f ri
ver
bed
wit
h f
ine
sed
imen
t d
epo
sits
Upstream
Downstream
Downstream Threshold
-
Rockfill: The Geology Challenge
Waimea Water Ltd 12
▪ Embankment trials late December 2019 and early January 2020 identified Rock degradation
Heavily broken down– Not free drainingLess broken down– Free draining
Expected and Needed Discovered
25/06/2020
-
Rockfill: The Geology Challenge
Waimea Water Ltd 13
▪ Discovering more argillite (mud / siltstone) (~70%) and less greywacke (sandstone) than expected
▪ Greywacke (sandstone) dispersed amongst predominant argillite. Difficult to salvage. (VIDEO)
▪ Fissile argillite showing tendency to break along insipient foliations
➢ Spillway Excavation: “May yield a minimum of 350,000 m3 of rock that will consist of slightly weathered to weathered (Class 1 & 2) greywacke.” (2014). Predominantly fissile argillite
➢ Need to find suitable drainage material from alternative sources (cost)
25/06/2020
-
Design: Rezoning embankment to manage geology❖ Expect less harder class-1 material
❖ Testing in early 2020 identified breakdown on compaction
Increase drainage layers
Alternatively source drainage rock
Waimea Water Ltd 14
Free Draining
Not Free Draining
Drainage
25/06/2020
-
Design: Spillway modified for improved resilience
Waimea Water Ltd 15
2009: 5-92012: 10-142017: 15-17
Design modifications due to recent learnings from international spillway incidents (international standards)
Oroville (right) failure due to poor drainage and anchoring detailing (pressure beneath fn velocity)
Whaley Bridge (UK) no drainage and poor slab detailing combined with poor maintenance
Modifications for resilience (requested by CIIL):
Drainage reviewed and upgraded
Anchoring design reviewed and upgraded
Additional modifications driven by topography and encountered geology.
25/06/2020
-
Design Update
✓ Spillway:
▪ Redesigned with vertical walls to mitigate topography / geology risks RHS
▪ Increased drainage per recent standard
▪ Completed and peer reviewed
Waimea Water Ltd 1625/06/2020
-
Design Update: Other items
Mechanical and Electrical
❖ Not designed or priced at commencement of work
Provision Sum challenged
To be priced ~3rd Quarter 2020
▪ Progressing detailed design
Switch to single outlet pipe aiming to realise cost savings
Modifications for future hydropower installation
Waimea Water Ltd 17
2009: 5-92012: 10-142017: 15-17
25/06/2020
-
Power Generation: Opportunity
Enlarge Reservoir / Powergen
▪ Fuse Gate to utilise 2.3m / 5m of flood reservoir
▪ Activate in event of large flood say 1:10,000 yr AEP(55% - 70% of PMF 1094 m3/s)
▪ + 1.5Mm3 storage to ~15Mm3 (15%)
Storage increases powergen utilisation
Increase resilience to droughts / growth / demand
Waimea Water Ltd 1825/06/2020
-
Agenda
1. Covid-19 impact
2. Funding and expenditure
3. Expenditure and progress
4. Safety
5. Environmental
6. Rockfill: The geology challenge
7. Design update
8. Construction update (video)
9. Questions
Waimea Water Ltd 1925/06/2020
-
Construction Update
Waimea Water Ltd 20
LHS Plinth
Culvert
RHS Plinth
Spillway
25/06/2020
-
Diversion Culvert: ~80% complete
Waimea Water Ltd 21
✓ Completed Floor
✓ 12/17 wall & roof sections completed
➢ Expect to complete by Aug and divert river September 2020
25/06/2020
-
Construction Update: Forming LHS Plinth
Waimea Water Ltd 22
✓ Foundation treated and site blinding concrete complete
✓ Commenced forming plinth
25/06/2020
-
Construction Update: Preparing RHS Plinth
Waimea Water Ltd 23
✓ Foundation treatment and treatment underway
25/06/2020
-
Construction Update: Spillway
Waimea Water Ltd 24
▪ Spillway cut underway
➢ Exposed first 20 m section of foundation
❖ Uncovering significantly weathered foundation that will require treatment
▪ Close to cliff edge
✓ Supports change in design to self-supporting vertical walls, rather than a liner
▪ Will evaluate extent of any edge support
25/06/2020
-
Construction Issues: Unexpected Voids
Waimea Water Ltd 2521/04/2020
❖ >1000 m3 concrete
✓ LHS & Culvert done
❖ RHS, Spillway and starter dam to do
-
Closing: By the numbers
Waimea Water Ltd 2625/06/2020
Task Total Quantity Unit
Vegetation Clearance 85 Hectare
Excavation 633,000 m3
Fill 430,000 m3
Cut to Waste 311,000 m3
Material Processing 120,000 m3
Concrete 22,000 m3
Reo Steel (bars) 3,900 t
Reo Steel (mesh) 10,000 m2
Anchors 4,200 No.
Concrete Face 10,000 m2
-
More Information
Waimea Water Ltd 2725/06/2020
https://www.google.com/imgres?imgurl=https%3A%2F%2Fwww.facebook.com%2Fimages%2Ffb_icon_325x325.png&imgrefurl=https%3A%2F%2Fwww.facebook.com%2F&docid=QanOc4elti2_UM&tbnid=eSZWZPUruLZj3M%3A&vet=10ahUKEwjQgNWZ-dblAhUz6XMBHaOLCVMQMwh1KAAwAA..i&w=325&h=325&itg=1&bih=967&biw=1920&q=facebook&ved=0ahUKEwjQgNWZ-dblAhUz6XMBHaOLCVMQMwh1KAAwAA&iact=mrc&uact=8
-
17 Dec 2019: Rezoning embankment to manage geology
❖ Expect less harder class-1 material
❖ Experiencing more fines
Increase drainage layers with
Processed (screened) out fines
Waimea Water Ltd 28
2009: 5-92012: 10-142017: 15-17
02/12/2019
-
Design: Geosynthetic membraneReplace concrete face with Geosynthetic membrane
Improved resilience to settlement and seismic(elasticity), benefit accentuated by softer rock
CO2, Cost and Schedule savings
Easy to repair; performance warranty
Testing demonstrates expected life 50-100 years (robust to UV)
Meets EU and International standards for Health and Environmental impacts
Carpi Ltd: Installed
• 54 New Dams since 1988 (26 larger than Waimea)
• 142 Retrofitted Dams since 1970 (63 since 2010)
• Used on Tekapo Canals (2013 / 2014)
Waimea Water Ltd 29
2009: 5-92012: 10-142017: 15-17
25/06/2020