VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity...

29
VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS DOE Peer Review Energy Storage Program Crystal City, VA Nov. 2001 Christopher John GNB Industrial Power Division of Exide Technologies

Transcript of VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity...

Page 1: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

VRLA ENERGY MANAGEMENTSYSTEM ANALYSIS

DOE Peer ReviewEnergy Storage ProgramCrystal City, VA Nov. 2001

Christopher JohnGNB Industrial PowerDivision of Exide Technologies

Page 2: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Battery Energy Storage Systems: Perceptionn It’s Old Newsn Systems Don’t Meet Expectationsn VRLA Technology in Question

Page 3: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Battery Energy Storage Systems: Realityn VRLA Technology Is Being Demonstrated n 7+ Years of Operational Historyn Demanding Utility and Industrial

Applicationsn Ongoing Improvements in VRLA Process

& Product Design (DOE Sponsorship)n Improved Equipment and Controlsn DOE Top 100 Award

Page 4: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Presentation Overviewn Objectives / Backgroundn Battery Operation and Life n Operational Economic Analysisn Future Activities

Page 5: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Objectivesn Demonstrate Performance and Benefits of

GNB ABSOLYTE IIP VRLA Battery Cells for Utility & Industrial Applications.n 1995 Vernon (5-MVA)n 1996 MP&L (1.2-MVA)

n Identify Economic Benefits Using Battery Energy Storage.

Page 6: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Vernon BESS Background

n Lead Smelter:Battery Recycling

n Near Los Angeles, CA

n California Air Resources Board

Page 7: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Vernon BESS Projectn Primary: Critical Load Backup

n Environmental Restrictionsn Load Shedding System

n Secondary: Energy Managementn Demand Cost Reductionn Deferred Energy Costs

Page 8: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Vernon Batteryn First Large, High Voltage VRLA Systemn Absolyte IIP Battery Cell Design

n Valve Regulated Lead Acid (VRLA)n Absorbent Glass Mat (AGM)

n System Capacityn 5 Megawatt Peak Powern 3.5 Megawatt Hoursn Operating Range 600 - 900 VDC

Page 9: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Absolyte IIP VRLA Batteryn Layout

n 2 Parallel Stringsn 378 Modules per

Stringn 3 100A33 Cells in

Parallel per Modulen Horizontal Stacks of

8 modules, Seismic Zone 4

n Cells Built in 1995

Page 10: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Vernon Battery Operationn Primary Function:

Critical Load BackupCarried Load through 6 Outages

Page 11: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Vernon BESS Outage February 27, 1999

-2000

-1500

-1000

-500

0

500

1000

1500

2000

2500

3000

3500

4000

4500

5000

8:40 8:45 8:50 8:55 9:00 9:05 9:10 9:15 9:20 9:25 9:30 9:35 9:40

Time of Day on 2/27/99

Po

wer

(kW

)

30

35

40

45

50

55

60

65

70

75

80

85

90

95

100

Sta

te o

f Cha

rge

(%)

BESS Output supporting Critical Loads, 2400 kW

Power Demanded from Utility, 0 kW

Loss of UtilityBESS Takeover

Utility RestoredBESS Recharging

BESS Battery State of Charge

Page 12: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Vernon Battery Operationn Primary Function:

Critical Load Backup

n Secondary Function:Energy Management

Page 13: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

kW Demands during Peak Shaving Periodon Thursday, July 5, 2000

BESS Trigger Level = 3050 kW

0

500

1000

1500

2000

2500

3000

3500

4000

4500

5000

12:00 PM 1:00 PM 2:00 PM 3:00 PM 4:00 PM 5:00 PM 6:00 PM 7:00 PM 8:00 PM

Time of Day on 7/05/00

Po

wer

, kW

50

55

60

65

70

75

80

85

90

95

100

Sta

te o

f C

har

ge

(%)

State of Charge

BESS Output

Total Plant Demand

Peak Shaving Peak Shaving

Utility Power

Page 14: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Battery Life Expectancy

n BESS OperationsNot Pure FloatNot Pure CycleCombination of Both

n Projected Life Basis Float: Ah of OverchargeCycle: Ah of Throughput

Page 15: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Float Life Calculationbased on a 20-year Lifen Hours of Design Life (175,320 hrs)

* Normal Float Current (2.16 A)= 378,691 Design Ah of Overcharge

n Actual Overcharge (136,520 Ah)÷ Design Life (378,691 Ah)= 36% of Total Life Consumed

n Actual Years of Operation (6 years)÷ % of Total Life Consumed (36%) = 16.6 Years of Total Projected Life

Page 16: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Cycle Life Calculation based on 1200 cycles at 80% Depth of Dischargen Cycles (1200) * Depth of Disch (0.80)

* C/6 Capacity (4500 Ah)= Design Ah Throughput (4.32 MAh)

n Actual Throughput (769,823 Ah)÷ Design Throughput (4.32 MAh)= 18% of Total Life Consumed

n Actual Years of Operation (6 years)÷ % of Total Life Consumed (18%)= 33.7 Years Total Projected Life

Page 17: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Vernon vs. Metlakatla Power & LightOperatingParameters

Vernon MP&L

SOC 100% 80%

Ah Overcharge 136,000 0

Equiv. 100% DODCycles/Mo

2.4 5.8

GoverningFailure Mode

Overcharge Throughput

Page 18: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Battery Life Projectionsn Ah Overcharge

n Vernon ~16 yearsn MP&L (Partial SOC, No Overcharge)

n Ah Throughputn Vernon ~34 years (Overcharge Will Limit)n MP&L ~14 years

Page 19: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Battery Life Projection Verificationn Need to Verify Life Projections

n Postmortems for Data Correlationn Vernon 0 points, MP&L 1 point

n Need to Develop End of Life Predictor

Page 20: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Economic Analysisn Energy Management

n Demand Reduction Aspect

Page 21: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Vernon Smelter Electricity Costsn Annual Expenditure

$1.2 -> $1.4 Millionn 30% of Cost from Peak kW Demandn Opportunity for Cost Reduction

Page 22: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Economic AnalysisNet Cost Avoidance =

Avoided On Peak kW Demand Cost+ Avoided On Peak kWh Cost- Additional Mid Peak kW Recharge Cost- Additional Mid/Off Peak kWh Cost

Page 23: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Example Economics : Summer-High Demand Monthly Cost Reduction

kW Avoidance $6486

kWh Avoidance $2339

kWh Cost$2640

kW Cost$2415

Net Cost Avoidance

$3770

Page 24: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Results of Economic Analysis3.5 Megawatt Hour Systemn Primary Function = Critical System Backup

Achievedn Measured Individual Month

$4,000 - $7,000 Cost Avoidancen FY2000 $31,000 Cost Avoidancen 10 year Payback for Energy Management

Capability (1 Battery String) given Current Rate Structure (Low Cost Vernon)

n One Lost Day Can Reduce Cost Avoidance

Page 25: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Effect of Rate Structure on Payback Period

0

2

4

6

8

10

12

0 10 20 30 40 50

$/kW

Pay

bac

k: Y

ears

City of Vernon

Page 26: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Conclusionsn Critical Loads Protectedn Demand Reduction Provides Cost

Avoidancen Absolyte IIP VRLA Chemistry Works in

Energy Management Systemsn Demonstrated in Utility and Industrial

Applicationsn Battery Life Meeting Expectations

Page 27: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Future Activitiesn Continue Battery Field Data Collectionn Battery Inspections, Testing, and

Postmortems: Additional Data Pointsn R&D to Improve Performance and Lifen Optimize Software Control to Reduce

Battery Recharge Costs

Page 28: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Future Activitiesn Utilize Intelligent Monitoring System to

Develop Operational Databasen Refine System Data Analysis Toolsn Energy Storage Workshop to Heighten

Understanding and Visibilityn Intelligent Energy Management Controlsn New Site for Next Generation BESS

Page 29: VRLA ENERGY MANAGEMENT SYSTEM ANALYSIS · nObjectives / Background ... Vernon Smelter Electricity Costs nAnnual Expenditure ... Payback Period 0 2 4 6 8 10 12 0 10 20 30 40 50 $/kW

Acknowledgementsn DOE Sponsorshipn Sandia National Laboratories

n Rudy Jungst Project Manager

n GNB Teamn George Huntn Joe Szymborskin Christopher John ([email protected])