Volume 3 - Sec 4

download Volume 3 - Sec 4

of 90

Transcript of Volume 3 - Sec 4

  • 8/6/2019 Volume 3 - Sec 4

    1/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 1 of 91

    January 2009

    SECTION 4

    PAVEMENT CONSTRUCTION

    4.1 AGGREGATES FOR PAVING LAYERS

    4.1.1 All aggregates for use in the construction of the pavement layers shall beobtained only from sources approved by the Engineer.

    4.1.2 The contractor shall have determined the location, suitability and quantityof material available before tendering as well as the cost and the amountof work required to extract, crush, screen and clean the material and thelength of haul to the job site.

    4.1.3 The contractor shall provide the Engineer, within thirty (30) days prior totheschedules beginning of the crushing and screening operations, with a

    complete report on the origin and composition of all stone and/or gravelaggregates to be used in the work (Aggregate Resources Report). Allmaterials shall comply with the specified requirements for the variousaggregates.

    4.1.4 The contractor shall provide petrographic analysis conducted by acompetent independent testing laboratory which shall include reports onthe suitability of the proposed materials for their use in concrete andasphaltic mixes.

    4.1.5 The source and manufacture of the aggregates, which will meet therequirements of the Specification, is the sole responsibility of theContractor. It is also the contractor's sole responsibility to provide such

    aggregates at the rates and in the quantities required to complete thework within the specified Contract Period.

    4.1.6 The approval of the Contractor crushing and screening plant equipmentby the Engineer shall in no way relive the contractor of the responsibilityof producing aggregates which met the Specifications and in thequantities required for the completion of the work within the specifiedContract Period.

    4.1.7 Stock piles of materials produced from each source shall be properlylabeled for clear identification of source and size.

    4.1.8 Delivery of materials produced from commercial manufacturing processshall be accompanied by the manufacturer's certification and test reportsshowing that materials comply with the specification for which it issupplied.

    4.1.9 No aggregate producing equipment shall be put into operation prior to theapproval of the equipment by the Engineer. If after the equipment is putinto operation it fails to perform as proposed the Contractor shall provideadditional equipment or replace the original equipment with more suitableequipment, as may be directed by the Engineer.

  • 8/6/2019 Volume 3 - Sec 4

    2/90

  • 8/6/2019 Volume 3 - Sec 4

    3/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 3 of 91

    January 2009

    4.1.18 The stockpile site shall be prepared by clearing and smoothing and mustbe approved by the Engineer. Prior to any stockpiling of aggregates,cross-sections of the stockpile site shall be taken and control pointsestablished for use in determining the quantity of subsequently stockpiledmaterial.

    4.1.19 The equipment and methods used for stockpiling aggregates and forremoving aggregates from the stockpiles must be approved by theEngineer and shall be such that no segregation of the aggregates willresult and no foreign material will contaminate the aggregate. The stockpile shall be kept flat and the formation of high cone shaped piles shallnot be permitted. The height shall not exceed 5m. For asphalt works,stock piles of aggregate shall be suitably separated by bin walls and shallbe formed on bituminous or concrete floors.

    4.1.20 Material shall be stored in a manner that will ensure preservation of theirspecified quality and fitness for the work. They shall be placed on hard,clean surfaces and, when required by the Engineer they shall be placed

    under cover. Stored materials shall be located in such a manner tofacilitate prompt inspection and control. Private property shall not be usedfor storage purposes without written consent of the owner or lessee andpayment to him, if necessary, at the Contractor's expense.

    4.1.21 The centre of the storage area shall be elevated and sloped to the sidesin order to provide proper drainage of excess moisture. The material shallbe stored in such a way to prevent segregation and to allow propercontrol of moisture. Aggregate stockpiles shall be built up in layers notexceeding one (1) meter. The height of each stockpile shall be limited toa maximum of five (5) meters.

    4.1.22 Sufficient material must be stored in stockpiles to allow for testing and

    approval of such materials prior to use in the works.

    4.1.23 The contractor shall tidy-up the quarry areas on completion and ensurethat side slopes are not steeper than 1 to 2 and in a condition acceptableto the Employer and to the Engineer.

    4.1.24 Following removal of existing asphalt / Interlocking paving blocks, theunder laying materials (sub-base/aggregate road base/wet mixmacadam) shall be retained for their re-use at such places as directed bythe engineer. Any excavated material wasted by the contractor withoutwritten permission of the engineer, shall be replaced by the contractor athis own expenses.

    4.1.25 Excavated material, when required, shall be improved to meet therequirements of the specification by adding borrow material which shallbe quantified by the engineer. In such cases payment shall be made forthe quantity of the extra material borrowed.

    4.2 GRANULAR SUBBASE

    4.2.1 Description

  • 8/6/2019 Volume 3 - Sec 4

    4/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 4 of 91

    January 2009

    Granular sub-base shall consist of furnishing, spreading, and compacting,

    sub-base in accordance with the details shown on drawings and these

    specifications: Granular sub-base used under the carriageway/footpath shall

    consist of hard, durable natural/screened gravel or crushed stone, having

    suitable binding quality and shall be free from dirt, shale, clay balls gypsum

    or other deleterious substances. The material shall lie within the grading

    envelope stated below when tested in accordance with BS 812 Part 103 and

    shall comply with the properties referred under Clause 4.2.5.

    If more than one source is used, the Contractor shall provide a method

    statement to the Engineer indicating the method of mixing, stockpiling and

    delivery of the mixed material to roadbed. Each time the stockpile is made,

    the Engineer shall take samples to check binding quality, homogeneity of the

    mix as well as Grading, MDD, CBR and SE. Mixing of dune sand shall not be

    permitted. Use of salty water for mixing in sub-base under laying bituminous

    mixes shall not be permitted.

    The Contractor shall carryout a site trial of at least 100m outside the

    permanent work to check and confirm the blending quality and homogeneityof the mix material and also to establish the compacting effort required to

    achieve the required degree of compaction.

    4.2.2 Materials

    a) Sub-base Type I

    Granular sub-base material used under footpath shall be well graded and lie

    within the grading envelope stated below when tested in accordance with BS

    812 Part 103 Clause 7.3 and shall comply with the properties of type I as

    referred under Clause 4.2.5.

    b) Sub-base Type II

    Granular sub-base type II used under the carriageway shall lie within thegrading envelope stated below when tested in accordance with BS 812 Part103 Clause 7.3 and shall comply with the properties of type II as referredunder Clause 4.2.5.

    SIEVE SIZE PERCENTAGE PASSING

    Type I Type II

    75mm 100 100

    37.5mm 85-100 85-100

    19mm 62-94 62-82

    9.5mm 40-90 40-70

    4.75mm 25-70 25-45

    0.6mm 8-35 8-22

    0.075mm 0-10 0-10

  • 8/6/2019 Volume 3 - Sec 4

    5/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 5 of 91

    January 2009

    4.2.3 Equipment

    Equipment shall be according to the type and number outlined in theContractor's detailed Programme of Work, as approved by the Engineer.

    4.2.4 Construction

    Road sub-base material shall be delivered to the roadbed as uniform mixture

    and shall be spread in layers. Segregation shall be avoided and the sub-baseshall be free from pockets of coarse or fine materials.

    Each road sub-base layer shall be spread by grader or other approved

    mechanical methods, watered, shaped to a compacted thickness not

    exceeding 150 mm and compacted to the required grade and cross section.

    The compaction procedure and plant shall be to the satisfaction of the

    Engineer. At the time of compaction the moisture content of the laid material

    shall not vary by more than + 2% from the optimum moisture content.

    The granular sub-base shall be compacted to not less than 98% of the

    maximum density determined in accordance with AASHTO T 180 Method - C

    with correction for oversized material Particle size analysis of solid for sieve

    analysis of fine and coarse aggregate shall be carried out in accordance with

    BS 812 part 103 Clause 7.3.

    The surface on completion of compaction shall be well closed, free from

    movement under compaction plant and free from ridges cracks or loose

    material. The finished surfaces of the road sub-base shall not vary at any

    point more than 10 mm above or below the grade established by the

    Engineer. The road sub-base shall be maintained in a condition satisfactory

    to receive any subsequent base or surfacing material. Sub-base, which doesnot conform to the above requirements, shall be reshaped or reworked

    watered and thoroughly re-compacted to conform to the specified

    requirements.

    4.2.5 Relevant Test and Standards

    The following tests should be carried out on each source and the material shall conform tothe requirements stated below:

    STANDARD LIMIT

    TEST Type I Type II

    Sampling AASHTO T2 - -

    Los Angeles Abrasion AASHTO T96 40 % max. 40 % max.

  • 8/6/2019 Volume 3 - Sec 4

    6/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 6 of 91

    January 2009

    Soundness (Magnesium

    Sulphate Solution) (5 Cycles)

    ASTM C88 15 % max. 12 % max.

    Liquid Limit AASHTO T89 35 % max. 35 % max.

    Plasticity Index AASHTO T90 6 % max. 6 % max.

    Compaction Test (Modified

    Proctor) with correction foroversized material

    AASHTO T180 2.0 gram/ cc min. 2.0 gram/ cc

    min.

    C.B.R. at 98% of modified

    Proctor density (96 hours

    soaked)

    ASTM D- 1883 45 % min. 60% min.

    Field Density AASHTO T191 98% min. MDD 98% of MDD

    Linear Shrinkage BS 1377 Part 2

    Method 6.53% max. 3% max.

    Sulphate Content (Acid

    Soluble)

    BS 812 Part 118 0.5% max. 0.5% max.

    Chloride Content (WaterSoluble)

    BS'812 Part 117 1% max. 1% max.

    Sand Equivalent AASHTO T- 176 25% min. 35% min.

    4.2.6 Minimum Test Requirements

    One sample every l,000Cu.m shall be tested for Grading, Plasticity Index,Maximum Dry Density, CBR and Loss by Abrasion, one in-situ Density testshall be made every 500Sq.m of granular sub-base laid but a minimum oftwo tests have to be made for each section prepared.

    4.3 PROTECTION OF SHOULDERS AND SLOPES

    4.3.1 Cement Stabilized Aggregate Capping Layer

    1) Materials Materials shall conform to Section 4.2 Granular SubbaseMaterials (Type I) of the Specifications except that CBR shall not berequired to be determined.

    2) The Sulphate Resisting Cement shall conform to Section 6 of theSpecifications.

    3) Water to conform to Section 6 of the Specifications.

    4) The mix shall have the following properties/proportions:

    i) Cement 6% by weight of the aggregates.

    ii) Water to conform to the Optimum Moisture Contentcorresponding to the Maximum Dry Density determinedaccording to BS 1377 part 4.

  • 8/6/2019 Volume 3 - Sec 4

    7/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 7 of 91

    January 2009

    iii) Capping Layer shall be compacted to 95% of the MDD.

    When tested in accordance with the British Department of TransportationSpecification for Highway Works, Part 3, the minimum compressive strengthat 7 days for an individual cube compacted at OMC should be not less than

    4.5 N/mm

    2

    ; and not less than 7.0 N/mm

    2

    for an average of 5 cubes.

    4.3.2 Testing

    The testing frequencies shall conform to the following:

    a) One sample each for grading, P.I., Sand Equivalent and Loss due toAbrasion per 2000 cu.m of mixed aggregate before the addition ofcement.

    b) MDD determination every 2000 cu.m compacted volume of completemix including cement.

    c) One sample every 2000 cu.m of compacted volume for cementcontent determination according to BS 1924 Part 2 Method 5.1.

    d) One In situ Density determination for every 500 sq.m of laid cappinglayer.

    4.3.3 Method

    1. The approved material is stockpiled next to blending plant.

    2. The required quantity of cement and water shall be added before theaggregate material passed through the mixer. After mixing, thematerial is loaded on trucks ready for site use.

    3. The verge and side slopes shall be prepared to the specified levelsand slopes ready to receive the capping layer material, 50cmrounding to both verge and slope shall be done.

    4. The material is dumped by trucks and is spread by grader to coverthe verge and side slope up to the existing ground, the 50cmrounding is also formed.

    5. The material shall be compacted to 95% of M.D.D.

    a) First by steel roller, starting from the toe and moving up;

    b) then tire roller, starting from the toe and moving up;

    c) and a final pass with steel roller.

  • 8/6/2019 Volume 3 - Sec 4

    8/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 8 of 91

    January 2009

    6. The levels and compaction of the capping layer shall be checked.

    7. Curing for three consecutive days shall be done by spraying sweetwater on the finalized surface to keep it continuously wet.

    4.4 IMPROVED ROCK SUBBASE

    4.4.1 Description

    This work shall consist of the furnishing and placing of courses of approvedgraded coarse and fine aggregates in accordance with clause 4.4.2.1 andconforming to the specifications given below in an approved manner and inconformity with the lines, grades and thickness as shown on the typicalcross-sections or as established by the Engineer.

    4.4.2 Materials

    Improved rock sub-base shall be non plastic crushed rock materials freefrom dirt, organic matter, clay, shale, cemented particles and otherextraneous or deleterious matter and shall be of such a quality that will bindreadily to form a firm stable mass with a sound, smooth, well knit uppersurface free from loose materials.

    At least 80 percent by weight of the materials shall have at least onefractured face materials will be accepted based on the sampling stock piles.However, acceptance of the materials does not constitute acceptance of thecourse in place.

    The materials shall be laid in layers of the types and depths specified inTable 4.1 and shall be spread, rolled and compacted in such a manner that

    the sizes of materials remain distinct. The surface of the Type I or II layer asappropriate shall be blinded with Type III materials to refusal and the wholere-rolled. The whole mass shall not be less than the specified thickness andthe finished surface shall be shaped and compacted to the required levelsand tolerances. Each layer shall be inspected for approval beforecommencing the next layer.

    Table 4.1 - Improved Rock Sub-base layer details

    Layer Type and Thickness

    Bottom Top

    Completed thickness ofimproved rock subbase(mm)

    Type I Type II Type III

    300 180 100 Nominal to complete layer200 180 - Nominal to complete layer

    Where instructed by the Engineer a geo-textile membrane shall be provided,either below or above the rock layer or the whole rock layer shall be wrappedon the top and bottom by the geo-textile membrane. Depending on therequirements of the site the engineer will issue the instructions or it will beindicated on the drawing. A protection layer of Type III materials to a nominalthickness of 50mm shall be placed on top and/ or below the geo-textile

  • 8/6/2019 Volume 3 - Sec 4

    9/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 9 of 91

    January 2009

    membrane prior to placing subsequent layers. Geo-textile fabric shall meetthe requirements as described hereunder:

    Grading

    Gradation of the three types of layer shall be as shown in Table 4.2.Samples for checking compliance with grading requirements of Type I and IImaterials shall be taken at the Engineers instruction from completed layerafter spreading and before compaction.

    Type III material may be naturally occurring in sands and gravels excludingdune sand.

    Table 4.2 - Gradation of Improved Rock Sub-base

    Type I (% Passing)AASHTO SIEVE

    (mm) 300mm 200mm

    Type II

    (% Passing)Type III

    (% Passing)

    6" 100 100 - -

    4" 25- 70 60-90 100 -

    2.5" 5- 20 25- 50 25-60 -

    1.5" - - 0 - 15 -

    1" 0-1 0 10- 25 - -

    3/4" - - 0 - 5 -

    3/8" - 0 - 5 - 100

    3/16" - - - 85 - 100

    No.4 - - - -

    No.8 - - - 60-8 0

    No.40 - - 30 -5 0

    No. 100 - - 8 -20

    No.200 - - 0-10

    Physical Requirements

    Improved Rock Sub-base material shall comply with the following physicalrequirements:

    Loss of Sodium Sulphate Soundness) Type I & II 20% Max.(AASHTO T104), (5 Cycles) Type III 15% Max.

    Loss of magnesium Sulphate(AASHTO T104), (5 Cycles) 25% Max

    Thin and elongated pieces by weight 5% Max.(Thickness less than 1/5 of length)

  • 8/6/2019 Volume 3 - Sec 4

    10/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 10 of 91

    January 2009

    Friable Particles 0.25% Max.

    Dry Density of Particles 250 gm/cc Min.

    Soluble Salts (Type III Material) 5% Max.

    Plasticity Index (Type III Material) 6% Max.

    In the case where qeotextile membrane is provided beneath the improvedrock sub-base layer, a geotextile protection layer to a nominal thickness of50mm and conforming with the requirements of Type III material shall beplaced on top of the geotextile membrane prior to placing rock sub-base toprevent the geotextile membrane from being damaged by the sub-baselayer. Geotextile shall meet the requirements of section 4.5.

    4.4.3 Construction Requirements

    The material shall be laid in two (2) layers of the compacted depths as givenin Table 4.1 or in one layer up to 200mm thick. The material shall be spread /laid even in such a way that there be no voids and no large lumps of materialare concentrated in small areas but shall be distributed in well packed roundwith the finer material and rolled / compacted in such manner that the sizesof material remain distinct.

    The whole mass shall be to specified thickness and the finished surface shallbe shaped compacted to the required levels and tolerances, blinded withspecified blinding material and re-rolled to form a hard smooth and regularsurface.

    The improved Rock Subbase shall be compacted by means of approvedcompaction equipment progressing gradually from the outside towards the

    centre with each succeeding pass uniformly overlapping the previous pass.Rolling shall continue until the entire thickness of each layer is thoroughlyand uniformly compacted to the Contract requirements. The surface of thetop layer shall be finished with sufficient balding and rolling or similar in amanner approved by the Engineer to ensure a smooth surface free from rutsand ridges and having a cross section conforming to the requirements of theContract. The whole shall be carefully blinded to refusal with blindingmaterial and the surface re-rolled to be hard, smooth, free from lean patchesand be suitable for the operation of paving plant for the overlying layer. If thesurface of the rock Subbase becomes loose and dusty following compactionthen the surface layer shall be watered and compacted.

    Compaction trials shall be carried out as specified in the Specification for

    Aggregate Road base using the materials and equipment proposed for theWorks.

    Sampling and testing shall be carried out by excavation at not less than onepit per kilometer of each carriageway to check the compaction andpenetration of the fines (blinding material). After approval the pits shall berefilled and compacted by the Contractor at his own cost and to the approvalof the Engineer.

  • 8/6/2019 Volume 3 - Sec 4

    11/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 11 of 91

    January 2009

    The compacted thickness shall be such that the finished level does not varyby more than 20mm from the required elevation. The variation between twopoints on testing with a 3m straightedge shall not exceed 20mm.

    No further construction shall be laid on the Improved Rock Subbase until thelater has been approved.

    4.4.4 STABILISING CRUSHED MATERIAL

    4.4.4.1 In the event the foundation on which the embankment or the subgradematerials will be laid is saturated by water and unstable, the Engineer maydecide to lay crushed granular material to stabilise the foundation. Stabilisingcrushed material shall not be laid directly on ground soil but it shall always belaid on geotextile fabric covering the area to be stabilised as shown on thedrawings or directed by the Engineer.

    4.4.4.2 Such stabilising crushed material when tested in accordance with BS1377:P2 Cl:9.3, 1990 in accordance with Clause 1/12.8 shall have thefollowing gradation:-

    ASTM SIEVE % PASSING2" 1001" 80 - 1001/2" 60 - 85No.4 40 - 70No.10 20 - 50No.20 5 - 25No.40 0 - 10No.80 0 - 2

    4.4.4.3 The stabilising crushed material shall have the following characteristics:-

    Los Angeles Abrasion - Not more than 30% loss(ASTM C-131 or(ASTM C-535)

    BulkSpecific Gravity - Not less than 2.65(ASTM C-127 and C-128)

    Absorbtion - Not more than 2.0%(ASTM C-127 and C-128)

    4.4.4.4 The stabilising crushed material will be laid in layers of 15 cm andcompacted until the foundation is fully stabilised such that the total thickness

    of the stabilising layer shall not be less than 30 cm. Only after inspection andapproval by the Engineer the Contractor may be allowed to continue theconstruction of the embankment with other layers of embankment materialand/or subgrade material. The Engineer may decide, after having taken thelevels of the existing water table in the area, and keeping in considerationthe finished road levels, to excavate portions of the foundation saturated bywater, disposing of the excavated material, and replacing it with stabilisingcrushed material.

    4.4.4.5 Before starting any stabilising of the foundation the Engineer will instruct the

  • 8/6/2019 Volume 3 - Sec 4

    12/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 12 of 91

    January 2009

    Contractor specifying the areas to be stabilised and the final levels to bereached with the stabilising crushed material.

    4.5 GEOTEXTILE FABRIC

    4.5.1 Description

    The Contractor shall furnish and install geotextile fabric at locations and to the

    lines and grades shown on the Drawings or as directed by the Engineer.

    Geotextile fabric shall be supplied, tested or suitably certified, and placed on the

    prepared roadway subgrade and at other locations prepared for its use to restrain

    soil movement, to provide for drainage, and/or to prevent soil erosion.

    4.5.2 Material.

    Geotextile fabric shall be supplied, tested or suitably certified, and placed on

    the prepared base at the locations shown on the drawings or as directed by theEngineer.

    The geotextile fabric shall be a non-woven type produced from long chain

    polymeric filaments or yarns such as polypropylene, polyethylene, polyester,

    polyamide, or polyvinyl-chloride and formed into a stable network such that the

    filaments or yarns retain their relative position to each other when subjected to the

    proposed use within the limits of the physical characteristics required and

    specified herein. In addition, the fabric shall be inert to commonly

    encountered chemicals and shall conform to the requirements of AASHTO

    Designation: M288, Standard Specifications for Geotextiles used for

    Subsurface Drainage Purposes, except as amended and supplemented herein.

    The physical characteristics of the geotextile fabric shall comply with the

    requirements of Table 4.3 when subjected to the tests indicated therein. Prior to

    shipping of any geotextile fabric to the Site, the Contractor shall provide the

    Engineer with certification by the manufacturer of the date and location of its

    manufacture, and a statement that the material has been manufactured and

    tested and found to comply with the requirements of these specifications. A

    copy of such certification, a listing of test results obtained, and date of such

    testings shall be physically attached to each roll by the manufacturer prior to

    shipment. In addition each roll of fabric shall show the date that it has been

    supplied from the manufacturer's plant. At the discretion of the Engineer,

    random samples of fabric from any or all rolls of fabric delivered to the job site

    shall be tested prior to use. Such samples of material shall be tested at a

    laboratory approved by the Engineer for the purpose of verifying the certification

    provided. Any sample of material that fails to pass the specified requirements or

    material that does not fully comply with these specifications shall subject the

    entire roll of fabric to rejection by the Engineer, and such rolls of fabric shall be

    removed from the job site within three (3) calendar days after the date of such

  • 8/6/2019 Volume 3 - Sec 4

    13/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 13 of 91

    January 2009

    notification by the Engineer. To insure proper control of fabric delivered to the

    job site, each roll shall be marked and identified by date of delivery and an alpha-

    numeric designation approved by the Engineer.

    The fabric shall be supplied in rolls wound on a suitable disposable paper

    tube or other non-abrading resilient tube that has an outside diameter of not

    less than 10 cm. The width of fabric supplied on each roll shall be such as to

    minimize the development of longitudinal and transverse overlaps. Where

    longitudinal overlaps are required the width of fabric used shall be not less

    than 4.5 m. A narrower width may be used if the number of longitudinal

    overlaps is the same as would be developed using the minimum fabric width of

    4.5 m. Where transverse overlaps are required, the minimum length of fabric on

    a roll shall be 90m. Shorter lengths of fabric may be employed provided that the

    number of overlaps resulting there from is the same as that developed using the

    specified 90m minimum length rolls.

    Table 4.3 - Physical

    Requirements

    Test Minimum Physical Characteristicsof Fabrics

    Description Method ApplicableUnits

    ProtectedType 1

    UnprotectedType 2

    Fabric Weight ASTM D19IO GM/m2

    100 135

    Tensile Strength ASTMD1682 N 560 900

    Elongation ASTM D 1682 % 20 20

    PunctureStrength

    ASTMD751 N 200 600

    Mullen BurstStrength

    ASTM D3786 kPa 860 2,200

    Tear Strength ASTM Dl 117 N 80 225

    Permeability AASHTO M288* cm/sec 0.01 (Note 1) 0.01 (Note 1)

    E.O.S CW-022 15-77 U.S. STD (Note 2) (Note 2)

    Sieve

    StrengthRetention

    ASTM D 1682 N 560 900

    After AATCC-

    30-74

    Flow Rate AASHTO M288 l/s/m2

    25 25

  • 8/6/2019 Volume 3 - Sec 4

    14/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 14 of 91

    January 2009

    Appendix

    Note 1: Permeability shall not be less than 10 times the permeability of thesoil being drained where the fabric is used to permit drainage of water from the

    soil. A constant head (10 cm) permeability test may be utilized when approved by

    the Engineer.

    Note 2: The E.O.S. value shall be based upon retention of 95% of the size of

    beads used in the test. For soil having less than 50% of its sand fraction

    (minus No. 4 sieve) passing a No. 200 sieve, the fabric shall have a maximum

    E.O.S. of No. 70. Where soil has more than 50% of its sand fraction passing

    a No. 200 sieve, the fabric shall have a maximum E.O.S. of 100.

    4.6 POLYETHYLENE SHEETS

    Where described in the Contact or directed by the Engineer, a protective

    membrane to asphalt pavements shall be alkathene grade min 1500 or

    similar approved and shall comply with the following requirements: -

    a) Tensile Strength - 16.7 MN/Sq.m

    b) Strain at break - 800%

    c) Tear Strength - 125gm/0.001 inch

    d) Bursting Strength - 0.7 MN/Sq.m

    e) Impact Strength - 800gm

    The protective membrane layer shall be laid over the ground at a minimum

    depth of 150 mm below finished subgrade level with a minimum overlap at

    joints of 300 mm. It shall be retained in a manner approved by the Engineer

    until covered by suitable material.

    Before laying the membrane all necessary measures shall be taken to

    ensure all the voids in the ground are filled, the surface of the area is graded

    to a smooth profile and cleared of all debris and material liable to penetrate

    or damage the membrane. Any damage to the membrane shall be rectified

    by overlaying a new layer of protective membrane with a minimum overlap of

    600mm beyond the damaged area.

    The overlaying subgrade material shall be free of large or sharp stones orother injurious materials and shall be of size not greater than 25mmdiameter. It shall be deposited by end tipping and spread evenly over themembrane by tracked plant approved by the Engineer. The tracked plantshall not run on the surface of the membrane. Compaction of the subgradeand formation shall be undertaken in accordance with the requirements ofSection 3 unless otherwise directed by the Engineer.

  • 8/6/2019 Volume 3 - Sec 4

    15/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 15 of 91

    January 2009

    A test area of not less than 300 square metres will be carried out prior toapproval being given by the Engineer. Should approval not be given by theEngineer the test will be repeated until such time as the Engineer is satisfiedwith the Contractor's method of working.

    At overlaps of the polythene membrane, the splice shall be effected by

    means of an approved adhesive tape of adequate width.

    4.7 AGGREGATE ROAD BASE

    4.7.1 Description

    This work shall consist of furnishing and placing one or more courses of

    aggregate including binder soil if required, on a prepared subgrade or sub-

    base in accordance with the Specifications, in conformity with the lines,

    grades, thickness and typical cross-sections shown on the drawings or

    established by the Engineer.

    4.7.2 Material

    4.7.2.1 Material used for aggregate road base shall be free from dirt, shale, gypsumor other deleterious matter and shall be of such quality that it will bind readily

    to form a stable aggregate road base. If more than one source is used thecontractor shall provide a method statement to the Engineer indicating the

    method of mixing, stockpiling and delivery of the mixed material to roadbed.Each time the stockpile is made, the Engineer shall take samples to check

    binding quality, homogeneity of the mix as well as grading, MDD, CBR and

    SE. Mixing of the dune sand shall not be permitted to improve the SE. Use ofsalty water for mixing in sub-base/aggregate road base underlying

    bituminous mixes shall not be permitted. The contractor shall carry out a site

    trial of at least 30 m outside the permanent work to check and confirm thebinding quality and homogeneity of the mixed material and also to establish

    the compacting effort required to achieve the required degree of compaction.The tests shall be carried out on each source of materials and shall confirm

    to the requirements as stated in clause 4.7.2.2.

    4.7.2.2 The following tests shall be carried out on each source of material and shall

    comply with the requirement stated against each test:-

    Liquid Limit (AASHTO T89)

    25% max

    Plasticity Index (AASHTO 90) 6% max

    Sand Equivalent (AASHTO T176) 40% min

    Loss by Abrasion (AASHTO T96) 35% max

    Flakiness Index (85812 Part 105.1) (Coarse Aggregate) 35% max

    Elongation Index (85812 Part 105.2) (Coarse Aggregate) 35% max.

  • 8/6/2019 Volume 3 - Sec 4

    16/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 16 of 91

    January 2009

    Soundness (ASTM C88) (Magnesium Sulphate) (5 Cycles) 12% max.

    Organic Impurities (BS 1377 Part 3 Method 3) 0.15%

    max.

    Acid Soluble Chlorides (BS 812 Part 117) 1% max

    (Combined Aggregate)

    Dry Density (AASHTO T180 Method C

    (with correction for oversized material) 2.0% gr/ccmin.

    CBR on Remolded Samples after 4 days soaking at 98% of 80% minimumMDD (ASTM D1883)

    4.7.2.3 The gradation limits when tested in accordance with BS 812 Part 103 Clause

    7.3 shall be as follows:

    SIEVE SIZE (BS) PERCENT PASSING

    50mm 100

    37.5mm 70-100

    28mm 55-85

    20mm 50-80

    100mm 40-70

    5mm 30-60

    2.36mm 20-50

    0.425mm 10-30

    0.075mm 5-15

    4.7.2.4 Aggregate road base shall consist of uniform mixtures of gravel and/or

    crushed gravel with sand, silt and clay, conforming to the specified gradationlimits.

    4.7.3 Spreading / Laying

    4.7.3.1 Aggregate road base shall only be machine laid with approved paver and laid

    on subgrade or subbase, which has been approved by the Engineer.

    Aggregate road base, which has been placed on a subgrade or subbase notapproved by the Engineer, shall be removed at the Contractor's expense.

    4.7.3.2 Aggregate road base shall be laid on the approved subgrade in layers not

    exceeding fifteen (15) centimeters in compacted depth.

    4.7.3.3 The material shall be handled in a manner, which avoids segregation.

    Segregated materials shall be remixed until uniform. Suitable precautionsshall be taken to prevent rutting of the subgrade or sub-base during the

    laying of aggregate road base materials. No hauling or placement of material

    will be permitted when, in the judgment of the Engineer, the weather or roadconditions are such that the hauling operations will cause cutting or putting of

    the subgrade or cause contamination of aggregate road base material.

    4.7.4 Compaction

  • 8/6/2019 Volume 3 - Sec 4

    17/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 17 of 91

    January 2009

    4.7.4.1 The moisture content of the aggregate road base material shall be adjustedprior to compaction, by watering with approved sprinkler trucks or by dryingout as directed by the Engineer, to that required to obtain the specifieddensity for aggregate road base. Aggregate road base shall be compacted toninety eight (98) percent of the maximum dry density determined accordingto AASHTO T- 180 Method C with correction for oversized material.

    Variation of moisture content shall be between +2% of the OMC. The fielddensity and actual moisture content shall be determined according toAASHTO T 191-86.

    4.7.4.2 The aggregate road base shall be compacted by means of approvedcompaction equipment progressing gradually from the outside of the roadtowards the centre with each succeeding pass uniformly overlapping theprevious pass. Rolling shall continue until the entire thickness of each layeris thoroughly and uniformly compacted to the specified density. Rolling shallbe accompanied by sufficient blading in a manner approved by the Engineer,to ensure a smooth surface free from ruts ridges and having the propersection and crown.

    4.7.4.3 The surface of the course shall, on completion of compaction, be wellclosed, free from movement under the compaction plant and free fromridges, cracks, or loose material.

    4.7.4.4 Any areas inaccessible to normal compaction equipment shall be compactedby means of mechanical tampers until satisfactory compaction is obtained.

    4.7.4.5 The Contractor shall program his operations to avoid the drying out of thesubbase during construction. If any layer of aggregate road base material orpart thereof, is permitted to dry out after compaction or does not conform tothe required density or finish, the contractor shall, at his own expense,rework, water and recompact the material, as directed by the Engineer, to

    the density specified, before the next layer of aggregate road base orsubsequent pavement layers is placed.

    4.7.5 Compaction trials

    4.7.5.1 If directed by the Engineer, prior to the commencement of the aggregateroad base operations, the Contractor shall construct trial lengths not less

    than 100 metres. The materials used in the trials shall be those approved for

    use as aggregate road base, and the equipment used shall be that accordingto the contractor's approved detailed program of work.

    4.7.5.2 Trial lengths may not form part of the permanent works but may be permitted

    in the construction of temporary detours of sufficient length.

    4.7.5.3 The object of these trials is to determine the adequacy of the Contractor's

    equipment, the loose depth measurements necessary to result in thespecified compact layers depths, the field moisture content, and the

    relationship between the number of compaction passes and the resultingdensity of the material.

    4.7.5.4 The Contractor may proceed with the aggregate road base work, only afterthe methods and procedures, established in the compaction trials have been

  • 8/6/2019 Volume 3 - Sec 4

    18/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 18 of 91

    January 2009

    approved by the Engineer.

    4.7.6 Finishing

    4.7.6.1 Immediately prior to the placing of the first layer of the next pavement courseonto the aggregate road base the final layer of aggregate road bases shall

    be at the specified density and to the required grade and section. In order tomaintain these requirements while placing the next course it may benecessary to water and reshape the surface of the aggregate road base.This work shall be at the contractor's expense.

    4.7.6.2 The surface of the finished aggregate road base will be tested with a three(3) metre straightedge by the Engineer at selected locations. The variationsof the surface from the testing edge of the straightedge between any two (2)Contacts with the surface shall at no point exceed nine (9) millimeters whenplaced on or parallel to the centerline or nine (9) millimeters when placedperpendicular to the centerline of the roadway. The aggregate cross-sectionas shown on the drawings shall not vary by more than nine (9) millimetersfrom the required elevation. All humps and depressions and thickness

    deficiencies exceeding the specified tolerance shall be corrected by removingthe defective work or by adding new material as directed by the Engineer.

    4.7.7 Minimum Test Requirement

    4.7.7.1 One sample every l,000 Cu.m shall be tested for grading, plasticity Index,Sand Equivalent, Maximum Dry Density, C.B.R and loss by abrasion. One in

    situ Density test shall be made every 300Sq.m of aggregate road base laid.

    4.8 Wet Mix Macadam Road Base

    4.8.1 Description

    This work shall consist of furnishing and placing one or more courses of high

    quality crushed aggregate, bound by means of carefully controlled moisture

    content, on the approved subgrade or sub-base in conformity to the line,

    level and thickness shown on the drawings or as directed by the Engineer.

    4.8.2 Material

    4.8.3 The coarse aggregate shall consist of crushed rock (each particle shall have

    a minimum of one crushed face) and the fine aggregate also shall be

    crushed rock. The aggregate shall conform to the following gradation.

    BS SIEVESIZE

    PERCENTPASSING

    50 mm 100

    37.5 mm 95-100

    20 mm 60-80

    10 mm 40-60

  • 8/6/2019 Volume 3 - Sec 4

    19/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 19 of 91

    January 2009

    5 mm 25-40

    2.36 mm 15-30

    0.6 mm 8-22

    0.075 mm 2-8

    The particle size shall be determined in accordance with the requirements ofBS 1377 Part 2 (Method 9.2 and 9.3).

    The gradation shall be adjusted as required or as directed by the Engineer

    within the above limits to ensure the mix has adequate binding properties.

    Wet-mix road-base material shall have physical properties, which do not

    exceed the following values:

    Liquid Limit (AASHTO T 89) 25%

    Linear Shrinkage (BS 1377 Part 2 Method 6.5) 3%

    Plasticity Index (AASHTO T90) 6%

    Aggregate Crushing Value (BS 812 Part 110) 25%

    Water Absorption (ASTM C 128/C127) 2%

    Flakiness Index (BS 812 Part 105.1)30%

    Elongation Index (BS 812 Part 105.2) 30%

    Los Angeles Abrasion Loss (AASHTO T 96) 30%

    (*) Soundness Loss (ASTM C 88) (5 cycles) (Magnesium) 12%Organic Impurities (BS 1377 Part 3 Method 3) 0.1%

    Chloride Content (Acid Soluble) BS 12 Part 117 1% max

    Sulphate Content (Acid Soluble) BS 12 Part 118 0.5% max

    Sand equivalent (AASHTO T 176) 45%

    (*) Soundness requirements shall apply to both course and fine aggregates.

    The moisture content of the wet-mix macadam at the time of laying shall be

    the optimum + 1%. Water required to achieve this moisture content shall be

    added at the mixing plant only.

    The mix shall be produced from mechanical mixing plant.

    4.8.3.1 Transport and Spreading

  • 8/6/2019 Volume 3 - Sec 4

    20/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 20 of 91

    January 2009

    Transport vehicles carrying the plant mixed material shall have a capacitysuited to the output of the mixing plant and the site conditions and becapable of discharging cleanly. Material when mixed shall be removed atonce from the mixer and transported directly to the point where it is to be laidand protected from the weather both during transit from the mixer to thelaying site and whilst awaiting tipping. No. water shall be added on site.

    The material shall be placed and spread evenly. The material shall be spreadusing a paving machine or spreader box operated with a mechanism whilelevels of the material at an even depth and without delay. Except whereotherwise specified, the material shall be laid and compacted in layers ofmaximum thickness of 150mm.

    4.8.3.2 Compaction Trials

    If directed by the Engineer, prior to the commencement of the Wet -mix

    Macadam Road base operations, the contractor shall construct trial lengths

    not less than 100 metres. The materials used in the trials shall be those

    approved for use as Wet mix Macadam Road base and the equipment used

    shall be that according to the Contractor's method statement.

    Trial lengths may not form part of the permanent works but may be permitted

    in the construction of temporary detours of sufficient length.

    The objective of these trials is to determine the adequacy of the contractor's

    equipment, the loose depth measurements necessary to result in the

    specified compacted layer depths, the field moisture content, and the

    relationship between the number of compaction passes and the resulting

    density of the material.

    The contractor may proceed with the Wet-mix Macadam Rod base work only

    after the methods and procedures established in the compaction trials havebeen approved by the Engineer.

    4.8.3.3 Compaction

    The Material shall be compacted to a field density equal to or greater than

    98% of the maximum dry density value obtained when tested in accordance

    with (AASHTO T-180) method C with correction for oversized material andshall have a minimum CBR of 80% at 98% compaction after 96 hours

    soaking (Test 16, BS 1377). Field Density tests shall be carried out inaccordance with Clause 4.4.2.7.

    Compaction shall be completed as soon as possible after the material has

    been spread.

  • 8/6/2019 Volume 3 - Sec 4

    21/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 21 of 91

    January 2009

    Special care shall be taken to obtain full compaction in the vicinity of bothlongitudinal and transverse joints.

    The surface of any layer of material shall on completion of compaction be

    well closed, free from movement under compaction plant and free fromcompaction planes, ridges, cracks or loose material. All loose, segregated or

    otherwise defective areas shall be made good to the full thickness of layerand re-compacted.

    Where directed by the Engineer a sieve analysis shall be carried out on the

    material recovered from 5 consecutive field density tests. Where this sieve

    analysis shows oversize material content of 10% or greater the area ofconstruction will be removed and the source of the material rejected until

    further tests are carried out to ensure compliance with the specificationrequirements. Where considered necessary other areas of work which were

    carried on using material from the same source shall be tested in a similarmanner.

    4.8.3.4 Finishing

    Immediately prior to the placing of the first layer of the next pavement course

    on to the Wet-mix Macadam Road base the final layer of Wet-mix Macadam

    Road base shall be at the specified density and to the required grade and

    section. In order to maintain these requirements while placing the next

    course it may be necessary to water and reshape the surface of the Wet-mix

    Macadam Road base. This work shall be at the contractor's expense.

    The surface of the finished Wet -mix Macadam Road base will be tested with

    a three (3) metre straight edge by the Engineer at selected locations. The

    variations of the surface from the testing edge between any two (2) contacts

    with the surface shall at no point exceed ten (10) millimeters when placed onor parallel to the centerline, or ten (10) millimeters when placed perpendicular

    to the centerline of the roadway. The Wet-mix Macadam Road base shall be

    compacted to the thickness and cross sections as shown on the drawings

    and shall be compacted to the thickness and cross sections as shown on the

    drawings and shall not vary by more than ten (10) millimeters from the

    required elevation. All humps and depressions and thickness deficiencies

    exceeding the specified tolerance shall be corrected by removing the

    defective work or by adding new material as directed by the Engineer.

    Before placing the next construction layer or applying prime coat, the wet-mixroad base shall be mechanically swept then cleaned with compressed air to

    remove loose material. As soon as possible after cleaning of the surface the

    wet-mix road base shall be sealed by the application of a prime coat as

    specified. Should the surface of the material be allowed to dry out before the

    seal is applied, it shall be lightly watered and re-compacted immediately prior

    to spraying with prime-coat.

  • 8/6/2019 Volume 3 - Sec 4

    22/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 22 of 91

    January 2009

    In the event of a section of Wet-mix Road base failing to comply, either by

    level or degree of compaction, and where the full depth of the layer has been

    allowed to dry out, it shall be removed and replaced at the contractor's

    expense, with fresh material. Watering and re-mixing in place will not be

    permitted.

    4.8.3.5 Minimum Test Requirements

    One sample every l, 000 Cu.m shall be tested for Grading, Plasticity Index,

    Sand Equivalent Value, Maximum Dry Density, C.B.R and loss by Abrasion.

    For compaction and moisture content; one test per 250 sq.m of each layer of

    carriageway and one test per 100 linear metre of shoulder.

    Special care shall be taken to obtain full compaction in the vicinity of both

    longitudinal and transverse joints.

    4.9 BITUMINOUS PAVING COURSES

    4.9.1 Description

    This work shall consist of the construction of the following hot-mix bituminous

    courses which shall be either Asphaltic Concrete or Dense Bitumen Macadam

    as shown on the drawings.

    Bituminous Base Course.

    Bituminous Binder Course

    Bituminous Wearing Course

    Bituminous paving courses shall consist of coarse aggregates, fine

    aggregates, filler material, and bitumen binder. Mixture of two different types of

    rocks e.g. igneous and sedimentary having different specific gravities in a

    single fraction shall not be permitted.

    4.9.2 Coarse Aggregates

    4.9.2.1 Coarse aggregates, which is the material retained on a 4.75mm sieve, shall

    consist of crushed rock or crushed gravel. It shall be clean, hard, tough,

    durable and sound, and shall be of uniform quality and free from decomposed

    stone, shale, clay, lumps and other deleterious substances. Organic matter

    shall not exceed0.05% (BS 1377 Test 3 Method 3) mixing of two different

    types of rocks e.g. igneous and sedimentary having different specific gravities

    in a single proctor shall not be permitted.

  • 8/6/2019 Volume 3 - Sec 4

    23/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 23 of 91

    January 2009

    4.9.2.2 Crushed gravel for use as coarse aggregate shall consist of the product

    obtained by crushing material that has first been screened in such a manner

    4.9.2.3 that not less than ninety (90) percent of the material to be crushed is retained

    on an AASHTO 3/8 inch sieve.

    4.9.2.4 The coarse aggregate shall have an affinity for bitumen such that when coated

    with bitumen it shall pass a stripping test prepared in accordance with

    AASHTO T-182.

    Each particle will have a minimum of one crushed face. In addition each

    stockpile aggregate shall have all faces crushed as indicated below: -

    11/2" - 40% Min.

    1" - 50% Min.

    3/4" - 55% Min.

    3/8" - 65% Min.

    Water absorption of the coarse aggregate as determined by BS 812 shall not

    exceed 2% by weight.

    4.9.2.5 Coarse aggregate shall have properties, which comply with the following

    values:

    Los Angeles Abrasion Loss (AASHTO T96)

    Base Course and Binder Course 30% max

    Wearing Course 25% max;

    Aggregate Crushing Valve (BS 812 part 110)

    Base Course and Binder Course 25%max

    Wearing Course 20% max

    Soundness Loss (ASTM C88) (5 cycles)

    Magnesium Sulphate 10% max

    Flakiness Index (BS 812 part 105.1)

    Base Course and Binder Course 30% max

    Wearing course 25% max

  • 8/6/2019 Volume 3 - Sec 4

    24/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 24 of 91

    January 2009

    Elongation Index (BS 812 part 105.2)

    Base Course and Binder Course 30% max

    Wearing course 25% max

    4.10 FINE AGGREGATE

    4.10.1 Fine Aggregate shall consist of the material passing a 4.75mm sieve.

    4.10.2 Fine aggregate including filler shall be obtained from 100% crushed gravel orcrushed rock pre-screened to exclude natural uncrushed fine material orweathered unsound fines. The use of dune sand shall not be permitted.

    4.10.3 Fine aggregates shall have properties, which comply with the followingvalues:

    Soundness Loss (ASTM C88) (5 cycles)

    Magnesium Sulphate 10 % max

    Plasticity Index (AASHTO T 90) Non Plastic

    Acid Soluble Chlorides

    (BS 812 Part 117) 0.1% max

    Acid Soluble Sulphate 0.5% max

    Water Absorption (BS 812) 2% max.

    4.11 MINERAL FILLER

    4.11.1 When the combined grading of the coarse and fine aggregates is deficient inmaterial passing the AASHTO No. 200 sieve, mineral filler shall be added as

    approved by the Engineer at the Contractor's expense.

    4.11.2 Mineral filler shall consist of finely ground particles of limestone or cement in

    accordance with AASHTO M 17. It shall be thoroughly dry and free from

    organic substances and clay and meet the following grading requirements:

    MINERAL FILLER

    BS SIEVEASTM

    SIEVE SIZEPRECENTAGE BYMASS PASSING

    600 micron No. 30 100

    300 Micron No. 50 95-100

    150 Micron No. 100 90-100

  • 8/6/2019 Volume 3 - Sec 4

    25/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 25 of 91

    January 2009

    70 Micron No. 200 70-100

    4.12 COMBINED AGGREGATE

    4.12.1 The combined mineral aggregate shall meet the following physicalrequirements:

    Sand Equivalent (AASHTO T 176)Determined after all processing

    Except for addition of asphalt binder 65% Minimum

    Plasticity Index (AASHTO T 90) Non Plastic

    4.12.2 When tested according to AASHTO T 11 and AASHTO T 27, the combined

    mineral aggregate shall conform to Table 4.4 for Asphaltic Concrete.

  • 8/6/2019 Volume 3 - Sec 4

    26/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 26 of 91

    January 2009

    TABLE 4.4 AGGRERATE GRADING FOR ASPHALTIC CONCRETE

    SIEVE SIZE (SQUARE OPENINGS) PERCENT PASSING (BY WEIGHT)

    Base Binder Wearing

    ASTM Course Course Course37.5mm 100 _ _

    25mm 80-100 100 100

    19mm 62-92 80-100 86-100

    12.5mm - 63-85 69-87

    9.5mm45-75 57-77 58-78

    4.75mm 30-55 40-60 40-60

    2.36mm 20-40 25-45 25-45

    0.85mm 15-30 15-30 15-30

    0.425mm 10-22 10-22 10-22

    0.18mm 6-15 6-15 6-15

    0.075mm 2-8 2-8 2-8

    4.12.2.1 The coarse aggregate shall show no detrimental amount of stripping when

    tested in accordance with AASHTO T 182. The minimum value of non strippedarea shall be 95%. If stripping occurs, the aggregate shall be rejected and anapproved method of treatment specified to change the material from ahydrophilic to a hydrophobic state as directed by the Engineer, or an approvedadditive shall be used with the bituminous binder

    4.12.2.2 When necessary to improve the coating of aggregate by bitumen, additives ofapproved type will be added to the bituminous material in such percentage asrequired to obtain satisfactory results in the affinity, with bitumen testperformed in accordance with ASTM D 1664. The approved additive will beused in accordance with Technical Specifications issued by the manufacturerand approved by the Engineer after appropriate testing,

    4.12.2.3 No extra payment will be made for required anti stripping additives.

    4.13 BITUMEN BINDER

    4.13.1 Bitumen Binder for the Bituminous paving Courses shall be Bitumen Binder

    penetration grade 60-70 unless otherwise specified as 40-50. Generally,

    penetration grade 40-50 will be used for Type "H" mixes.

  • 8/6/2019 Volume 3 - Sec 4

    27/90

  • 8/6/2019 Volume 3 - Sec 4

    28/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 28 of 91

    January 2009

    TABLE 4.6 - BITUMEN CONTENT FOR ASPHALTIC CONCRETE

    PAVEMENT

    COURSE

    BITUMEN PERCENTAGE BY WEIGHT OF MIX

    INCLUSIVE OF TOLERANCES

    Base 3.2 to 4.4

    Binder 3.4 to 4.4

    Wearing 3.4 to 4.4

    4.13.7 Each consignment of bituminous material delivered to asphalt plant site shallbe accompanied by a delivery note and test certificates indicating name of therefinery, country of origin and results in support of the material's compliancewith the specification. Samples for compliance test shall be taken by the

    Engineer as and when deemed necessary.

    4.14 JOB MIX

    4.14.1 The mix approved for use in the works shall be designed by Marshall method

    as per MS-2 and field trials with the following recommendations taken into

    account.

    a) For base course the aggregates for Marshall specimen shall be

    modified by substituting all aggregate size over 25 mm with an equal

    weight of aggregate sizes in the next lower grading size.

    b) The combined aggregate gradation should be adjusted within the

    allowable limits to achieve maximum stability whilst not going below the

    minimum requirement for void content.

    c) The minimum bitumen binder content according to the results of the

    Marshall Method of Mix Design as recommended by MS-2 should be

    used provided that it will still satisfy the durability, the stability and the

    void content requirements.

    d) Prior to final approval, the proposed job mix, but with a bituminous

    content at the upper percentage limits shall be compacted to refusal,

    (400, 500 and 600 blows) and the resulting voids in the mix shall not be

    less than 2% for asphaltic concrete.

    e) The final job mix must display the marshal characteristics specified in

    Table 4.8 for Asphaltic Concrete.

    f) Height of the Marshall specimens outside the limit specified in AASHTO

    T-245 shall be discarded but a minimum of 3 specimens shall be

    averaged.

  • 8/6/2019 Volume 3 - Sec 4

    29/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 29 of 91

    January 2009

    4.14.2 The mix formula must take into consideration the absorption of bitumen in to

    the aggregates. Thus, for calculations for air voids in the mix (VIM) the

    maximum theoretical specific gravity as prescribed by ASTM D 2041 (Rice

    Method) shall be used. For calculation of voids in the mineral aggregate (VMA)

    the equations as mentioned in Asphalt Institute Manual MS-2 shall be used.

    VFB shall be calculated using the following equation:-

    VFB = {VMA VIM} X 100VMA

    4.14.3 The Contractor shall be responsible for the design and performance of all

    bituminous mixes. The Contractor shall submit, for the Engineer's approval, a

    proposed "Laboratory Design Mixture" together with all applicable design data

    atleast 30 days prior to commencement of the relevant asphalt works. The

    Engineer will take samples of materials proposed for use in the mix in order to

    check their quality and to cross check the proposed mix design for which the

    Contractor shall repeat the laboratory design exercise in the site laboratory

    under the supervision of Engineer to confirm the Marshall properties submittedby the Contractor.

    After receiving the approval of aggregate and bitumen from the Engineer, theContractor shall make a written request for the approval of the job mix formulaprepared by the Contractor under the supervision of the Engineer in thelaboratory.

    The approved Laboratory Design Mixture shall be used for agreeing theapproved Job Standard Mixture.

    4.14.4 The laboratory job mix formula shall fix a single definite percentage of

    aggregate

    passing each required sieve size, a single definite percentage of bitumenbinder to be added to the aggregate, a single definite temperature at which the

    mix is to be emptied from the mixer, and a single definite temperature at which

    the mix is to be delivered to the works site.

    4.14.5 The laboratory job mix formula shall be used for the basis of approval of the

    Job standard mixture.

    4.14.6 Trial areas having lengths of at least 100m and to the specified layer thickness

    shall be laid outside the area of the permanent work by the Contractor. At least

    two samples of non compacted material from the trial area shall be taken in

    accordance with AASHTO T 168, and shall be analyzed in the presence of the

    Engineer to determine the aggregate grading, binder content, stability, flow,Marshall density and voids. The results shall be submitted to the Engineer and

    shall be approved by him before further mixing or laying is carried out.

    4.14.7 Trial areas may from part of a temporary traffic detour subject to the approval

    of the Engineer. The compaction trials should be performed on the trial mixes.

  • 8/6/2019 Volume 3 - Sec 4

    30/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 30 of 91

    January 2009

    If the trial areas form a part of the temporary traffic detour they shall not be

    paid for under the relevant bill item.

    4.14.8 Should the laboratory job mix formula after passing the mixing plant and laid

    and compacted with approved plant fail to produce a satisfactory trial area, the

    mix proportions may be modified by agreement with the Engineer, as

    necessary and within the requirements of Tables 4.7 and 4.8 as applicable to

    produce a mix of satisfactory workability and acceptable surface finish. After

    approval of the trial area by the Engineer this mix shall be designated the job

    standard Mix and shall there after be the approved mix. A copy of the

    approved job Standard Mixture signed by the Contractor and Consultant have

    to be submitted to the road section, Al Ain Municipality.

    4.14.9 All mixes produced shall conform to the job Standard Mix approved by the

    Engineer, within the ranges of tolerance specified in Table 4.7, (within) the

    limits of Tables 4.4, 4.6 and 4.8 for asphaltic concrete. Each day the Engineer

    shall take as many samples of the materials and mix as he considers

    necessary and minimum of one sample for every 200 tons laid or part thereof

    for checking their required characteristics. When unsatisfactory results or

    changed conditions make it necessary, the Engineer shall instruct the

    Contractor to establish a new job standard.

    4.14.10 Should a change in a material be encountered or should a change in a source

    of material be made a new job-Standard Mix shall be submitted by the

    Contractor and approved by the Engineer before the mix containing the new

    material is delivered. Job materials will be rejected if they are found not to

    have the characteristics required by the approved job Standard Mix.

    TABLE 4.7 - JOB MIX TOLERANCE

    TABLE 4.8 - PROPERTIES OF MIX FOR ASPHALTIC CONCRETE

    Aggregate retained on 4.75mm sieve or large 5%

    Aggregate passing 4.75mm sieve and retained on0.85mm sieve

    4%

    Aggregate passing 0.85mm sieve and retained on0.075mm sieve

    2%

    Aggregate passing 0.075mm sieve 1%

    Bitumen Binder 0.2%

    Temperature of mixing and placing 10 C

  • 8/6/2019 Volume 3 - Sec 4

    31/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 31 of 91

    January 2009

    PROPERTIES BITUMINOUSBASECOURSE

    BITUMIOUSBINDERCOURSE

    BITUMINOUSWEARINGCOURSE

    Number of Compactionblow at each end ofspecimen

    75 75 75

    Stability ( Marshall )Minimum Kg. F

    1200 1400 1500

    Flow (Marshal) mm 2 - 4 2 - 4 2 - 4

    Stiffness minimum Kg.F/mm

    500 500 550

    Percent air voids (VIM) 4 - 8 4 - 8 4-8

    Percent voids in

    Mineral Aggregate (VMA)

    1 3 1 4 15

    Percent voids filledwith Bitumen (VFB)

    50 -6 5 50 -7 0 50-75

    Loss of Marshall stabilityby submerging specimensin water at 60deg. C fortwenty four (24) hourscompared to stabilitymeasured aftersubmersion in water at 60deg. C for thirty (30)

    minutes

    Max. 25% Max. 25% Max. 25%

    Filler / Bitumen Ratio 0 . 6 - 1 . 5 0 . 6 - 1 . 5 0 . 6 - 1

    4.14.11 Samples of the mixed materials shall be taken from the first two hundred tones

    and from every two hundred tones thereafter to determine aggregate grading

    and binder content. Samples of loose asphaltic concrete mix shall be taken

    behind the paver before compaction and shall be obtained in accordance with,

    ASTM D 979.Samples of compacted asphaltic concrete shall be obtained by

    coring in accordance with Method B of AASHTO T-230.

    Determination of bitumen content and extraction gradation may be performedon either loose or compacted samples in accordance with AASHTO T-164 and

    AASHTO T-30 except that the mass of mineral matter in the total volume of

    the extract shall be determined by using a bitumen meter or other equipment

    and procedures which give equally satisfactory results. The specific gravity of

    compacted asphalt course shall be measured in accordance with AASHTO T -

    230. Gmm as per ASTM D2041shall be checked on daily bases and used for

    calculating air voids.

  • 8/6/2019 Volume 3 - Sec 4

    32/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 32 of 91

    January 2009

    If any of these tests show results which are not in accordance with approved

    job standard mix within permissible variations the material shall be rejected

    and suitable adjustments shall immediately be made to ensure compliance

    therewith. Samples of the mixed material shall be taken at least twice a day or

    as determined by the Engineer for making Marshall specimens to determine

    stability, flow and unit weight. For the taking of daily Marshall specimens themixing pug mill temperature shall be set to the mixing temperature as specified

    in AASHTO T-245 and the compaction temperature of the moulds shall also

    be in accordance with AASHTO T-245. Should for practical reasons the pug

    mill temperature be different from that used in AASHTO T-245 then the

    Engineer shall set the compaction temperatures for the moulds to so

    compensate. All approved sampling and testing required under the sub-clause

    of this clause shall be undertaken by the Engineer. Sampling and testing by

    the Engineer in no way relives the Contractor of his responsibility for regular

    quality control testing in order to ensure compliance with the Specifications.

    4.14.12 The density of the compacted mixes shall be related to the daily Marshall

    Density, which shall be determined by making four standard Marshallspecimens from samples of the mix taken from the mixing plant or paver. The

    density of each sample shall be determined and compared with the mean

    value. Any individual result which varies from the mean by more than 0.015

    gm /cc shall be rejected. Marshall tests shall be repeated on a daily basis to

    establish the daily Marshal Density for that particular day's production. The

    daily Marshall Density shall not vary from the job mix Design Density by more

    than + 0.75%. If it does, the Job Standard Density shall be applied to satisfy

    the requirements of in-situ compaction.

    4.14.13 The Job Standard Mixture Reference Density shall be obtained by making six

    standard Marshall Specimens from samples of the approved Job Standard

    Mixture determining the relative density or each and comparing them with themean values of the six. Any individual result which differs from the mean by

    more than 0.015 gm/cc shall be rejected and provided not more than two

    results are so rejected the mean of the remaining results shall be designated

    the Job Standard Mixture Reference Density.

    4.14.14 The assistance of the Engineer in the preparation of the job standard mix in no

    way relieves the Contractor of the responsibility of producing a bituminous mix

    meeting the requirements of the Specifications.

    4.15 EQUIPMENT FOR BITUMENS PAVING OPERATIONS

    The Method statement and equipment list shall be according to the type and numberoutlined in the Contractor's detailed programme of work, as approved by theEngineer.

    In addition to the above requirements, trucks used for hauling bituminous mixshall have tight, clean, smooth metal beds which have been thinly coated witha minimal amount of paraffin oil, lime solution, or other approved material toprevent the mix from adhering to the beds. When required by the Engineer,

  • 8/6/2019 Volume 3 - Sec 4

    33/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 33 of 91

    January 2009

    each vehicle shall be equipped with a canvas cover or other suitable materialof such size as to protect the mix from the weather.

    Rolling equipment shall be self-propelled. The wheels on the rollers shall beequipped with adjustable scrapers and the rollers shall have water tanks andsprinkling apparatus, which shall be used to keep the wheel wet and prevent

    the surface material from sticking.

    4.16 PREPARATION OF BITUMEN BINDER

    The heating of the bitumen binder for mixing and compacting shall be in

    accordance with AASHTO T-245.

    4.17 PREPARATION OF MINERAL AGGREGATE FOR BITUMINOUS MIX

    4.17.1 Coarse and fine aggregate shall be stored at the asphalt plant in such a

    manner that the separate stockpiles will not become intermixed. The

    stockpiles shall be of sufficient size to provide a minimum quantity of one week

    continuous production of asphalt mix. Aggregates brought to the asphalt plant

    to supplement stocks should be tested and approved prior to placing in the

    existing approved stockpiles.

    The cold bins shall be calibrated with the materials to be used and the settings

    shall be such as to produce a combined gradation in accordance with the job

    mix. The proportioning shall be such that surpluses and shortages in the hot

    bins will not cause breaks in the continuous operation. All the above shall be

    as approved by the Engineer.

    The materials shall be thoroughly dried and heated so that their temperature

    is within 8 deg. C of the temperature needed to satisfy the viscosity

    requirements of the asphalt cement. The moisture content of the heated and

    dried materials shall not exceed 0.5 per cent. The quantity of materials fed

    through the drier shall in all cases be held to an amount, which can be

    thoroughly dried and heated within the limits specified.

    4.17.2 Immediately after heating, the aggregate or aggregates shall be screened into

    at least five (5) sizes and conveyed in to separate bins ready for batching and

    mixing with bituminous material. When the aggregates supplied are of such

    size and grading that separating into five (5) bins is impractical, the number of

    required separations may be reduced to four (4) or to three (3) with the

    approval of the Engineer. The efficiency of the screening operations shall be

    sufficient to produce, at plant operating capacity, gradations in each of the

    sizes of heated and dried aggregates which are reasonably uniform and result

    in the production of a mix complying with the limits specified for the aggregate

    gradation.

    4.18 REPARATION OF BITUMINOUS MIX

    4.18.1 Dried aggregate as specified and prepared as prescribed above shall be

    combined in the plant conforming to ASTM D 995 in the approved

  • 8/6/2019 Volume 3 - Sec 4

    34/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 34 of 91

    January 2009

    proportions. The bitumen binder shall be introduced into the mix in the

    proportion specified by the job-mix formula.

    4.18.2 The initial mixing time will be designated by the Engineer. Mixing time may be

    increased by the Engineer if additional time is necessary to obtain a

    homogeneous mix and satisfactory coating.

    4.18.3 The batch plants timing shall begin at the start of the introduction of the

    bitumen

    into the pug mill.

    4.18.4 The length of mixing time for continuous plants will be determined by the

    following formula or other approved methods: -

    Mixing time in seconds = Pug mill dead load capacity in kgPug mill output in kg / second

    4.18.5 The temperature of the aggregate immediately prior to mixing shall be within +

    10 deg. C of the temperature of the asphalt cement and the temperature of theaggregate and asphalt prior to mixing shall be approximately that of the

    completed mix as defined in the job mix formula approved by the Engineer.

    The mix temperature shall be within the limits set out in the job mix formula

    when emptied from the mixer.

    4.19 SURFACE PREPARATION

    4.19.1 When the Bituminous mix is placed on a prepared road base and whether or

    not a prime coat is designated on the Drawings, the Granular Road base shall

    be even and firm and within the construction tolerances specified for the road

    base to the satisfaction of the Engineer.

    4.19.2 When the paving layer is constructed on an existing bituminous surface, the

    surface shall be cleaned of all foreign material and broomed free of dust, In

    addition any loose, broken or shattered bituminous material along the edge of

    the existing surface shall be removed, and the exposed subgrade and

    sufficient width of the shoulder adjacent to the edge of the existing surface to

    receive the new bituminous mix shall be shaped, bladed, compacted and

    broomed and primed to provide a uniform firm sub grade of the new surface

    course.

    4.19.3 The existing bituminous surface, base, or sub grade shall be removed if

    broken, shattered, or unstable. The areas shall be excavated to a depth as

    directed by the Engineer, and refilled with the bituminous mix according to thespecifications.

    4.19.4 Prior to the placing of the mix, when designated on the Drawings or as directed

    by the Engineer, a prime coat or tack coat shall be applied to the road base or

    surface in accordance with the specification for prime coat or Tack coat.

    4.20 PLACING OF THE MIX

  • 8/6/2019 Volume 3 - Sec 4

    35/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 35 of 91

    January 2009

    4.20.1 All bituminous mixes shall be introduced to the paver at a temperature not less

    than 135 deg. C and not more than 163 deg. C. Mixes outside this temperature

    range shall be discarded. Temperature along the edge of the longitudinal joint,

    prior to rolling, shall not fall below 120 deg. C.

    4.20.2 The bituminous mix shall be spread and finished to crown and grade by

    automatically controlled bituminous paver. Bituminous mix may be spread and

    finished by hand methods only where machine methods are impractical as

    determined by the Engineer.

    4.20.3 The automatically controlled paver shall lay the bituminous mix without tearing

    the surface and shall strike a finish that is smooth, true to cross-section,

    uniform in density and texture, free from hollows, transverse corrugations and

    other irregularities.

    All paving machines, prior to using on site shall be checked to ensure proper

    functioning and expected surface finish. Texture of the paved asphalt behind

    the paver shall be smooth, uniform close textured, free from segregation drag

    or other unacceptable surface finish. Extension of the paver with extra screeds

    shall be subject to extension of the auger as well as proper functioning of the

    inbuilt tamping mechanism of the screeds and the paved surface being similar

    to the remaining section without any sign of drag or any other surface defects.

    Defective pavers shall not be used on site unless they are rectified to the

    satisfaction of the Engineer.

    4.20.4 The paver shall be operated at a speed which will give the best results for the

    type of paver being used and which co-ordinates satisfactorily with the rate of

    delivery of the mix to the paver, to provide a uniform rate of placement without

    intermittent operations of the paver.

    4.20.5 The mix shall be delivered to the paver in time to permit completion of

    spreading, finishing and compaction of the mix during daylight hours.

    4.20.6 The longitudinal joints in successive layers shall be offset not less than fifteen

    (15) centimeter. The width of surface or top course placements shall conform

    to trafficlane edges as shown on the Drawings.

    4.20.7 The leading half of half road way paving shall not get ahead of the trailing half

    of the pavement by more than one (1) average full-day of paving and, in no

    case, shall the leading half be more than one half (1/2) kilometers ahead of the

    trailing half without the written permission of the Engineer. If the Contractor

    fails to comply with this requirement, the Engineer may suspend paving on the

    leading half until such time, as the Contractor shall pave the trailing half to a

    point approximately even with the leading half.

    4.20.8 Unless otherwise directed by the Engineer, where successive layers are to be

    placed, the surface of the existing layer shall be swept clean with a power

    broom, or by other means as approved by the Engineer, and tack coat applied.

    Tack coat may not be required where the delay between courses laying is less

    than 48 hours and when the surface is fresh and clean and at the discretion of

    the Engineers

  • 8/6/2019 Volume 3 - Sec 4

    36/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 36 of 91

    January 2009

    4.20.9 After the approval of the "job standard mixture" (JSM) the trial area as

    specified in Clause 4.14.6 of the specifications shall be used to establish the

    rolling/compaction method required to produce the specified relative density.

    Three pairs of course shall be taken from the compacted trial area and the

    mean density of each pair shall be not less than 98% of the "Job Standard

    Mixture density (JSMD). If the required field density is not obtained the rolling

    procedure shall be adjusted and further trial areas shall be laid and tested until

    satisfactory results are obtained. These procedures shall be reported to the

    Engineer and the rolling method agreed before mixing or laying of the

    pavement works is commenced. Agreed procedures shall not subsequently be

    varied without the Engineer's written approval.

    4.21 RELIMINARY SURVEY AND REFERENCE STRING LINE

    4.21.1 The contractor shall make the necessary survey required for the referencegrade. When the survey is approved by the Engineer the Contractor shall erect

    and maintain an approved reference string line and operate the paver to

    conform to the reference string line for the initial layer and /or any other layersas directed. Elevation control point stakes for the first layer of bituminous

    paving course shall be set at a maximum spacing of twenty (20) metres. Forsubsequent layers, control points shall be set at ten (10) metres maximum

    spacing. The contractor shall furnish and maintain an approved mobile string

    line for all layers not laid with the erected string line. The string line shall be

    erected parallel to the reference grade, and the bituminous mix shall be spreadat a constant elevation above, below or at the string line elevations as directed.

    4.21.2 The use of the automatically controlled bituminous paver, to provide bothlongitudinal and traverse control, shall include the furnishing and maintaining of

    a string line, fixed or mobile, by the Contractor. The longitudinal and traversecontrols shall operate independently of each other to the extent that the

    surface of the bituminous mix will conform to the string line and will be uniformin cross -section and crown.

    4.21.3 The Contractor shall establish the centre -line points and shall maintain the

    location of the points until the completion of the surfacing or as directed. When

    directed by the Engineer, the contractor shall erect a string line, to be used asa guide for the furnishing machine, in order to maintain a uniform edge

    alignment. If any other method is proposed by the Contractor it shall first beapproved by the Engineer.

    4.22 BITUMINOUS LEVELING AND WIDENING OF EXISTING PAVEMENT

    4.22.1 A levelling course, consisting of a layer of bituminous material of variablethickness may be used to eliminate irregularities in existing surfaces or bases

    and to vary existing cross -section elements of roadways.

    4.22.2 In areas where levelling courses are required as shown in the drawings

    determined by the Engineer, the Contractor shall make a survey of the existing

    surface or base. When the survey is approved, the Engineer will determine

    and inform the Contractor of the precise locations and thickness of leveling

    course to obtain the smoothest possible riding surface. Upon receipt of the

  • 8/6/2019 Volume 3 - Sec 4

    37/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 37 of 91

    January 2009

    location and thickness from the Engineer, the Contractor shall proceed with

    the placement of the levelling course.

    4.22.3 Where the existing carriageway is to be widened, the sides shall be trimmed in

    accordance with the drawings or as required by the Engineer. The bituminous

    courses shall be cut back to a clean vertical face which shall be completely

    coated with a grade of hot bitumen suitable for the purpose immediately

    before laying new bituminous material adjacent to it.

    4.22.4 The material for regulating shall be as shown on the drawings and shall be

    made and laid in accordance with the appropriate clauses of the Specification.

    4.22.5 Unless stated to the contrary, any thickness of material described means the

    finished or fully compacted thickness.

    4.22.6 Where the existing carriageway requires regulating to accommodate the new

    pavement overlay the following methods may be adopted.

    a) Cold Planning

    Cold planning is the recommended method for removing large quantities of

    bituminous material. Trial sections are to be carried out, under the supervision

    and direction of the Engineer to establish the degree of cold planning required

    along each individual section as indicated on the drawings or instructed by the

    Engineer.

    b) Heating and Planning

    Heating and planning may only be used as an alternative to cold planning with

    the Engineer's permission. Should this method be adopted there shall be a

    minimum period two weeks before the pavement overlay is applied. Trial

    sections shall be carried out under the Engineer's supervision and direction to

    determine the degree of planning required along each individual section as

    indicated on the drawings. A tack coat shall be applied to the planed surface in

    accordance with Section 4.36 at the discretion of the Engineer.

    4.22.7 The material removed from the existing carriageway shall be disposed off as

    instructed by the Engineer.

    4.22.8 Scarifying of the existing pavement shall be used to prepare the surface of the

    existing pavement to provide a key for the subsequent layers of asphalt. The

    scarification shall comprise forming a grooved surface to the existing asphalt

    with an average depth of groove being 5mm from the existing surface with an

    average spacing between grooves of 50mm or as otherwise approved by the

    Engineer.

    4.23 THICKNESS CORES

    4.23.1 The depth of each bituminous paving course shall be measured by cores

    samples.

  • 8/6/2019 Volume 3 - Sec 4

    38/90

    Roads and Infrastructure Works forShiab Al Ashkar NeighbourhoodGeneral Specifications

    RD4672/D-004 Rev.1 Page 38 of 91

    January 2009

    The Contractor shall furnish and operate an approved core drill for cutting

    samples from the compacted mix on the road. The equipment shall be capable

    of cutting the mix without shattering the edges of the specimen or otherwise

    disturbing the density of the specimen. Cored samples shall be ten (10)

    centimeters in diameter for binder course and wearing course and fifteen (15)

    centimeters in diameter for base course and road base.

    Cores extracted for thickness measurement may be used for density

    determination and density samples may be used for thickness measurements.

    4.24 COMPACTION OF BITUMINOUS LAYERS

    4.24.1 After spreading and strike off, and as soon as the mix conditions permit the

    rolling to be performed without excessive shoving or tearing, the mixture shall

    be thoroughly and uniformly compacted. Rolling will not be prolonged to an

    extent that cracks appear.

    4.24.2 Rollers shall be of the steel-wheel and pneumatic tyre type and shall be in

    good condition, capable of reversing without backlash, and shall be operated at

    speeds slow enough to avoid displacement of the bituminous mix. The number

    and weight of rollers shall be sufficient to compact the mix to the required

    density while it is still in a workable condition. The use of equipment which

    results in excessive crushing of the aggregate will not be permitted. A

    minimum of three (3) rollers, one (1) steel-wheel and two (2) pneumatic -tyre

    type, shall be used with each spreading operation for each lane.

    4.24.3 The Contractor shall provide adequate back-up equipment for use in the event

    of mechanical failure, all to the satisfaction of the Engineer.

    4.24.4 Initial or breakdown rolling shall be done by means of either a tandem power

    steel roller or three-wheel roller followed by a pneumatic-tyre roller or as

    agreed by the Engineer. Rolling shall be longitudinal, beginning at the low side

    of the spread of material and proceeding toward the high side, overlapping on

    successive passes by at least one half (1/2) the width of the near wheels,

    alternate passes of the roller shall be of slightly different lengths.

    4.24.5 The motion of the roller shall at all times be slow enough to avoid displacement

    of the mix. To prevent adhesion of the mix to the rollers,