Vol3-Chapter6

download Vol3-Chapter6

of 13

Transcript of Vol3-Chapter6

  • 7/28/2019 Vol3-Chapter6

    1/13

    CHAPTERVI

    Bridge

  • 7/28/2019 Vol3-Chapter6

    2/13

    VI-1

    Introduction

    The Department, in its reportto Congress on the 1997Status of the Nations

    Surface TransportationSystem, found that 11.7percent of the bridges on theNations arterial (includingInterstate) and collectorhighway systems arestructurally deficient and 15.2percent are functionallyobsolete (see Figure VI-1).The estimated annual cost tomaintain current bridgestructural and functionalconditions is $5.6 billion(1995 dollars). This leads tothe question: How muchwould various changes intruck size and weight(TS&W) limits affect currentand future bridge investmentrequirements?

    This study estimates changesin costs to correct structuralbridge deficiencies that couldresult from TS&W policy

    changes. The study does notaddress functionalobsolescence, since factorsthat affect functional

    obsolescence are largelyindependent of truck size andweight limits.

    Basic Principles

    Truck-Bridge Interaction

    The impact of trucks on

    bridges varies primarily bythe weight on each group ofaxles on a truck and thedistances between axlegroups. The number of axlesin each group is lessimportant than the distancebetween adjacent groups.Generally, except for somecontinuous bridges with longspans, the longer the spacing

    between two axle groups, theless the impact. Figure VI-2illustrates the two principaltypes of bridges, simplysupported bridges and

    continuously supportedbridges.

    An increase in vehicle loads

    stretches bridge girders orbeams. However, themaximum stress generally canbe reduced by spreading axlesand axle groups farther apartor, to a much lesser extent, byspreading the load acrossmore axles (see Figure VI-3).

    The relationship between axleloads, axle spacing, and

    bridge stress described aboveholds true for all simplysupported span bridges andmany continuously supportedspans. However, dependingon the length of continuousspans, longer axle spacingscan increase stresses at thebridge inside piers.Continuous span bridges aredesigned to take advantage of

    the interactions that occurwhen axle groups are on theopposite side of the fixed

    There are two types of deficient bridges, structurally deficient (SD) and functionally obsolete(FO). An SD bridge, as defined by the Federal Highway Administration, is one that (1) hasbeen restricted to light vehicles only, (2) is closed, or (3) requires immediate rehabilitation toremain open. An FO bridge is one in which the deck geometry, load carrying capacity(comparison of the original design load to the State legal load), clearance, or approachroadway alignment no longer meets the usual criteria for the highway of which it is an integralpart.

    Figure VI-1. Structurally Deficient versus Functionally Obsolete Bridges

  • 7/28/2019 Vol3-Chapter6

    3/13

    VI-2

    One way to think of a moment is as two forces that tend to rotate a body, such as a bridgebeam. This tendency is one source of stress in a bridge beam (the major one in a long bridgespan) as the material properties and beam connection resist the rotational tendency. Further,this rotational tendency becomes stronger the farther the two forces are spread.

    One of these forces results from an axle load and the other from the support at one end of thebeam. One force acts in the opposite direction of the other giving rise to the rotational

    tendency of the two acting together. As these two forces are moved closer together, theirrotational tendency is reduced. Consequently, when axle or axle groups are spread fartherapart, for any given position of the truck on the bridge, the axle loads are closer to thesupports which reduces the maximum moment induced by the vehicle load and the stresses inthe beam.

    Figure VI-3. Moments

    SimpleOne-Span Bridge

    Continuous

    Two-Span Bridge

    Figure VI-2. Simple and Continuous Span Bridges

    beam connection on thecentral pier. This allows theuse of smaller beams orgirders to reduce bridge costs.However, if the two-axle

    loads are far enough apartand the two spans longenough, the beneficial effectswill be negated.

    The bridge impact analysisfor this study considers bothsimple and continuous spanbridges. The Federal BridgeFormula (FBF), which is

    designed to limit loads andgroups of axles at differentspacings to protect bridgesfrom overloads, was basedonly on consideration ofstresses on simple spanbridges. Consequently, theFBF allows trucks to operatethat could overstress certaincontinuous spans. Likewise,an alternative bridge formula

    developed by the TexasTransportation Institute (TTI)also considered only stresseson simple span bridges.

    For short bridge spans, axleweights (live loads) and theweight of the spancomponents (dead loads) areimportant. For longer spans,

  • 7/28/2019 Vol3-Chapter6

    4/13

    VI-3

    axle spacing becomesimportant in addition to theaxle loads (see Figure VI-4).

    For spans longer than theoverall length of the truck, thegross weight of the truck andits length are important alongwith the dead load of thespan. For very long spans, theweight of the traffic is muchless significant than theweight of the bridge spanitself (that is, the dead load).

    Bridge Impact Criteria

    Previous TS&W studies haveused bridge ratings as thebasis for estimating whether

    bridges were structurallyadequate to handle heaviertruck loads expected underalternative truck size andweight scenarios (see FigureVI-6). Two ratingstraditionally have been usedby bridge engineers to ratethe structural capacity ofbridges, the operatingrating which is set at 75percent of the yield stress,and the inventory rating,which is set at 55 percent ofthe yield stress. There areseveral methods to ratebridges. In the past theWorking Stress Design orAllowable stress ratingmethods were used. In recent

    years bridge engineers havedeveloped new bridge ratingtechniques based on loadfactor design and load andresistance factor design

    principles. The ratingtechnique used by a State inreporting its bridge ratings isnot directly relevant to thisanalyses conducted for thisstudy since analyses are basedon comparison of momentsproduced by scenariovehicles to those produced bythe rating vehicle, regardlessof how the latter were

    determined.

    This study, with somemodifications, uses theoverstress criteriaunderlying Bridge Formula B-- 30 percent overstress forH-15 bridge designs and 5percent overstress for HS-20bridge designs. Theoverstress terms are defined

    in Figure VI-6. Also, seeFigure VI-5, H-15 and HS-20 Bridge Loading. Thestudy used the FBF overstresscriteria because they reflectcurrent truck weightregulation policy.

    If a truck (given its weight,number of axles, and the

    spacing of these axles) con-forms to the FBF, it is not

    considered overweight undercurrent weight regulations,nor does it result in anexpedited program to replaceH-15 bridges.

    Figure VI-4. Interaction of Bridge Span Length and

    Spacing of Truck Axle Groups

  • 7/28/2019 Vol3-Chapter6

    5/13

    VI-4

    Developing an alternativebridge formula was beyondthe scope of this study. Asnoted above, TTI, in researchsupported by the Federal

    Highway Administration,developed an alternativebridge formula in the late1980s that was based only onthe gross weight and length ofthe vehicle. The AmericanAssociation of State Highwayand Transportation Officialsconsidered this new bridgeformula, but did not accept itover the current FBF. The

    TRB recommended avariation of the TTI bridgeformula in its Special Report225.

    Analytical Approach

    The Bridge Analysis andStructural Improvement Cost(BASIC) model was used toestimate bridge impacts. Thismodel was specifically

    designed to evaluatealternative national TS&Wpolicy options. Accordingly,it was designed to analyzequickly tens of thousands ofbridges using readilyavailable data from theNational Bridge Inventory(NBI). BASIC is not abridge rating program thatrequires detailed sectionproperties and other datanormally only available fromthe as built construction

    drawings. The program usesonly data available in the NBIand a table of live load/deadload ratios for different typesof bridges. It determines

    which bridges areoverstressed by comparingthe computed moment of thescenario vehicles to thecomputed moment of therating vehicle. If anyscenario vehicle produces amoment greater than the ratingvehicle times the overstresscriterion, the bridge isassumed to require

    replacement. Once itdetermines the bridges thatrequire replacement, BASICestimates the replacementcost based on reported unitbridge costs for each Sate. Italso applies a queuing theory-based construction zonemodel to estimate delay andrelated dollar costs incurredby users while bridges arebeing replaced.

    Bridge structural impact is afunction of a particular bridgeloading condition and not anaccumulation of loads as isthe case for pavements.Bridge deck deteriorationmay be related to axle loadrepetitions similar topavements, but there wasinsufficient data to analyzepotential nationwide impactsof the illustrative truck sizeand weight scenarios onbridge deck costs.

    Changes to the vehicle fleet

    may also cause changes inlevels of fatigue damage to thebridge superstructure anddamage to bridge decks.Once a critical stress range is

    exceeded, the added fatiguedamage due to the scenariovehicles relative to the currenttruck fleet is not significant,because fatigue damage is afunction of both repetitionsand axle loads, not grossweights. Most scenariovehicles do not have greateraxle loads than vehicles of thecurrent fleet. Also, although

    fatigue damage can besignificant, most damage tobridge components isinexpensively corrected. Afurther consideration is theimpact of truck size andweight scenarios on bridgedeck costs. If total truck VMTdecreases and axle loads donot increase as the result ofTS&W limit changes, bridgedeck deterioration may bereduced somewhat. No directrelationships currently existbetween truck traffic, axleloads, and bridge deckdeterioration, but researchcurrently is underway todevelop such relationships.

  • 7/28/2019 Vol3-Chapter6

    6/13

    VI-5

    Overview

    The bridge analysis for thisstudy examines impacts ofTS&W scenarios on allbridges in a sample of Statesfrom different regions of thecountry. For each bridge,BASIC requires data on thebridge type, bridge length,length of the main span, andthe inventory rating. The

    inventory rating provides thesafe-load carrying capacity ofthe bridge (see Figure VI-6).For each bridge, BASICcomputes the bending momentfor the rating vehicle, the basecase vehicles, and thescenario vehicles. Thebending moment calculationsare based on both the live anddead loads for the bridge.

    Dead load refers to theweight of the bridge spancomponents; the live loadrefers to the weight of thetraffic on the span. Seven oreight truck configurations are

    analyzed for each scenario.

    Based on the allowableoverstress levels, bridgesrequiring replacement areidentified. If the criterion forthe bridge design type isexceeded, the bridge isassumed to requirereplacement. The cost ofreplacing each bridge isestimated and summed toestimate total bridge

    replacement costs. The usercosts associated withreplacing the deficientbridges are also calculated.

    Like previous TRB studies,this study assumes that alldeficient bridges would bereplaced rather than beingposted to limit maximumloads (thereby excluding

    some of the scenariovehicles) or strengthened. Inpractice it may be possible tostrengthen some bridges,especially ones not expectedto carry large volumes of the

    vehicles overstressing thebridge. There was no basis

    for estimating on a nationwidebasis how many bridges mightbe strengthened rather thanbeing replaced or what thecost to strengthen varioustypes of bridges might be, soit was assumed that allbridges would have to bereplaced. However, becausein practice States might beable to strengthen somebridges rather than replacingthem, cost estimates in thisanalysis may overestimateactual bridge costs associatedwith each illustrativescenario.

    Most bridges in the United States were designed to accommodate either an H-15 or HS-20loading. An H-15 loading is represented by a two-axle single unit truck weighing 30,000

    pounds (15 tons) with 6,000 pounds on its steering axle and 24,000 pounds on its drive axle.An HS-20 loading is represented by a three-axle semitrailer combination weighing 72,000pounds with 8,000 pounds on its steering axle and 32,000 pounds on its drive axle and32,000 pounds on the semitrailer axle. The 20 in HS-20 stands for 20 tons (4 tons on thesteering axle and 16 tons on the drive axle). The S stands for semitrailer combinationwhich adds in the additional 16 tons for the third axle to give a total of 36 tons or 72,000pounds.

    Figure VI-5. H-15 and HS-20 Bridge Loadings

  • 7/28/2019 Vol3-Chapter6

    7/13

    VI-6

    40 50 60 70 80 90 100

    Design Safety Factor

    30 Percent Overstress

    5 Percent

    Overstress

    Bridge

    Operating

    Rating

    Design

    Stress

    Level

    Bridge

    Inventory

    Rating

    55 57.75 71.50 75

    Percent of Yield Stress

    Yield

    Occurs

    The terms overstress criteria, design stress, inventory rating, and operating rating are oftenused when discussing or evaluating impacts of TS&W options on bridges. These terms relate to thepoint at which a structural member (a load-carrying component) of a bridge undergoes permanentdeformation, that is, the bridge member does not return to its original size or shape after the load isremoved. The level of stress at which this permanent deformation occurs is called the yield stress.Each of the related terms can be expressed as a percentage of this stress level. It is useful to do this toobserve how each of the terms relate to each other as well as to the yield stress. Also, it is importantto observe that, depending on the type of steel, a bridge member ruptures after considerable

    deformation relative to that which occurs at its initial point of yielding.

    Figure VI-6. Relationship of Overstress Criteria to Design Stress and Bridge Ratings

  • 7/28/2019 Vol3-Chapter6

    8/13

    VI-7

    It can be noted in the sketch that the standard stress level for the design of bridge members is 55percent of the stress at which yield occurs. This safety factor provides a contingency for weaknessesin materials, poor quality of construction, noncompliance with vehicle weight laws, and futureincreases in bridge loads.

    Bridges are rated by the States at either of two yield stress levels: the inventory rating, which is 55percent of the yield stress (the same as the design stress) or the operating rating, which is 75 percent ofthe yield stress. These ratings are used to post bridges and for inventory purposes.

    Past truck size and weight (TS&W) studies have used either of these two ratings to determine when abridge should be replaced, given alternative TS&W policy options. A 1991 study of TS&W policyimpacts on bridges used a 65-percent criterion to identify bridges needing replacement. It can be seenthat bridge replacement needs would vary considerably depending on which rating was used.

    The Federal Bridge Formula (FBF) is based on stress levels (overstress criteria) related to the designstress. When the FBF was formulated, a decision was made to allow loads to stress bridges designedfor an H-15 loading at levels up to 30 percent over the design stress. This type of design was usedfor bridges prior to the Interstate Highway Program, and these bridges are primarily located on lowerfunctional class highways. Their early replacement was anticipated such that some shortening ofbridge life could be tolerated. Bridges expected to have heavy truck traffic were designed with anHS-20 loading. The decision to allow loads no more than 5 percent over the design stress wasintended to ensure that these bridges would function satisfactorily for their expected service life, 50 ormore years, without the need for replacement.

    This study used the FBF overstress criteria, rather than either the inventory or operating rating used in

    past studies, to indicate the need for bridge replacement, but with two exceptions. First, the criteriawere applied to the rating stress level, and second the loads were permitted to exceed the inventorystress levels on H-17.5 (or higher H rating) bridges by only 15 percent versus the FBFs 30 percent.In terms of the yield stress, the 30 percent overstress is 71.5 percent, the 15 percent overstress is63.5 percent, and the 5 percent overstress is 57.75 percent of the yield stress (see sketch). Thesecriteria fall between the two bridge rating stress levels, and further they replicate the FBF criteria,which today allow a truck to exceed a bridges inventory rating and not be considered overweight, thatis, be found illegal or required to obtain an overweight permit. Whereas most bridges were designedusing the HS-20, H-15 and H-20 design vehicles, recently several States have chosen to use the HS-25design vehicle. Nonetheless, the bridge ratings in the NBI, as reported by the States, should generallynot be the same as the original design ratings. The rating process should account for deterioration,strengthening, and the like. Also, a bridge may have been designed using an older Working Stress or

    Allowable Stress Design method, but now is rated by the Load Resistance Design rating method.Whereas bridge design and bridge rating is very dependent on which design method is used, it is notrelevant to the concept of overstress as used in this study.

    Relationship of Overstress Criteria to Design Stress and Bridge Ratings (Cont.)

  • 7/28/2019 Vol3-Chapter6

    9/13

    VI-8

    Bridge Replacement

    Model Inputs

    To assess which bridgeswould be structurallyinadequate to carry vehicleweights and dimensionsassumed in each scenario, an11-State sample of bridgeswas drawn from the NationalBridge Inventory (NBI) (see

    Figure VI-7). The States,which were selected fromvarious regions of the country,were Alabama, California,Colorado, Connecticut,Missouri, North Dakota,South Carolina, Texas,Virginia, Washington, andWisconsin. Analytical resultsfor the sample bridges, whichinclude almost 30 percent of

    all bridges in the NBI, wereexpanded to reflect bridges inall States based on the deckarea of the bridges in thesample States and the deckarea of the bridges in the

    remaining States.

    Questions were raisedconcerning whether bridgesin States chosen to reflecteach region of the countrywere truly representative ofall bridges in those regions.No statistical analysis wasconducted to verify thatbridges were indeedrepresentative, but because ofthe large overall sample size

    and the fact that no results arereported below the nationallevel, the estimates ofnationwide bridge costs inthis analysis are not believedto be significantly affected bythe choice of States in thesample.

    Dead loads for the bridgeswere estimated based on

    detailed design informationfor 960 bridges of differenttypes and span lengths.Given the type and spanlength of a bridge of interest,the dead load may be

    estimated from a table lookupfeature in the model. Whiledead loads for specificbridges may vary from thoseestimated in this analysis, the

    methods used for the studysnationwide analysis arebelieved to be satisfactory.

    This is the first nationwideTS&W study to consider bothlive and dead bridge loads.Previous studies haveconsidered only live loads.However, with bridges oflonger span length, the dead

    load becomes increasinglyimportant, and in fact, thesignificance of the live load isreduced. In other words, theportion of total stress in abeam that results from thetraffic load is less importantthan the portion of the stressresulting from the weight ofthe bridge span components.

    Overstress Criteria

    As noted above, this studyassumed that bridgessubjected to stresses that arenot allowed under the FBFwould have to be replaced.Thus bridges rated up toH-17.5 subjected to stressesthat exceed 71.5 percent of theyield stress (1.3 times the

    design stress level of 55percent of yield) are assumedto be structurally deficient toaccommodate scenariovehicles. Bridges with arating greater than H-17.5 are

    The National Bridge Inventory contains records of 581,862bridges. The database is updated continuously and includesdetailed information about all highway bridges in thecountry, on all functional systems. This information is usedin the monitoring and managing of the Highway BridgeReplacement and Rehabilitation Program, as well as toprovide the condition information presented in the biennialStatus of the Nations Surface Transportation Report toCongress.

    Figure VI-7. National Bridge Inventory

  • 7/28/2019 Vol3-Chapter6

    10/13

    VI-9

    assumed to be deficient whenstressed over 63 percent ofyield. Bridges with an HS-20rating that are subjected tostresses by scenario vehicles

    that exceed 57.5 percent oftheir yield stress (1.05 timesthe rating stress level of 55percent of yield) are assumedto be structurally deficient toaccommodate scenariovehicles.

    Analytical Parameters

    Available Routes

    For the Longer CombinationVehicles (LCVs) NationwideScenario, Rocky MountainDoubles (RMDs) andTurnpike Doubles (TPDs)were assumed to be restrictedto a 42,500-mile system; onlybridges on that system weretested to determine whetherthey are structurally adequate,

    based on the criteriadescribed above, to carrythose configurations. Othertruck configurations in thescenario combinations wereevaluated on all bridges in thesample States as they have thepotential to use all the non-posted bridges in the NBI foraccess to terminals, places forloading and unloading, and

    places for food, fuel, rest, andrepairs.

    Specifications

    Table VI-1 presents the

    weights, dimensions, andhighway networks availableto the truck configurationstested and the TS&W policyscenarios in which they are

    included. The GVWs are theweights for which the impactswere estimated. Themaximum weight for noimpact is given to show thedifference in weight betweenthe configurations as testedand the weight at which therewould be no bridge impactsfor each configuration.

    Three-axle single unit trucksevaluated in the UniformityScenario could operate at thescenario weight withoutadditional bridge impacts.Four-axle single unit truckscould operate at near thelower of the two NorthAmerican Trade Scenarioweights without additionalbridge impacts, but the higher

    weight is considerablygreater than the no impactweight. Five-axlesemitrailers and STAAdoubles could operate at theUniformity Scenario weightswith no bridge impacts. Thesix-axle semitrailer couldoperate at the lower of thetwo North American TradeScenario weights without

    causing bridge impacts, butnot at the higher weight. Allof the LCVs would requirebridge improvements, andwith the exception of theseven-axle Rocky Mountain

    Double, the scenario weightsare considerably above the noimpact weight.

    User Costs

    In addition to the capital costto replace bridges, theanalytical approach estimatesdelay and excess vehicleoperating costs accruing tousers from traffic congestionduring bridge replacement.The assumptions foraccommodating traffic throughthe workzone are: (1) for

    twin bridges typically foundon freeways, one

    bridge is taken out of serviceand all traffic uses the other;(2) for multilane bridges, oneor two lanes are closed whiletraffic uses the remaininglanes with perhaps one beingreversible to accommodatethe predominant direction ofthe travel for the time of day;

    and (3) for a bridge with onelane in each direction, theprocedure assumes either thenew bridge is constructedbefore the old one is closed, atemporary bridge is providedwhile the bridge beingreplaced is built, or that thereare adequate bypass

  • 7/28/2019 Vol3-Chapter6

    11/13

  • 7/28/2019 Vol3-Chapter6

    12/13

    VI-11

    opportunities andconsequently no significantchange in user costs.

    Assessment of ScenarioImpacts

    The estimated costs, in 1994dollars, for replacing bridgesthat would be stressed atlevels above one of the threeoverstress thresholdsdiscussed earlier and the usercosts during bridge

    reconstruction are given inTable VI-2. Also shown areestimated costs to bringexisting bridges up tostandard to accommodateBase Case vehicles.

    It is important to note thatbridge costs are one timecosts, not annual or recurringcosts. For all scenarios, the

    user costs are at least as highas the capital costs, and forthe scenarios with significantincreases in GVWs, the delaycosts are much higher.

    The scenario analysisassumes that no bridges areposted or otherwiseunavailable for the scenariovehicles. In practice State

    officials would have severaloptions for bridges that mightbe structurally inadequate toaccommodate vehicles thatmight be allowed underrevised truck size and weight

    limits. One option would beto replace the bridgeimmediately if it wasanticipated to carrysubstantial volumes of more

    damaging vehicles. A secondoption would be to postponereplacement if anticipatedoverstress was determined tobe acceptable for a limitedtime. A third option wouldbe to strengthen deficientbridges that would beexpected to carry loads thatcould not safely beaccommodated without

    improvements but which didnot need immediatereplacement. A fourth optionwould be to post bridges thatwere not economicallyimportant or were notrequired to carry largevolumes of larger vehicles.Costs estimated in thisanalysis thus may besomewhat overstated andcertainly not all costs wouldhave to be incurred beforeheavier loads could beallowed to operate. Even ifsome bridges can bestrengthened in the short run,many might have to bereplaced sooner thanotherwise would have beenthe case had there been nochange in truck size andweight limits.

    The Uniformity Scenario (seeTable VI-2) would reducecurrent bridge investmentrequirements (by $20

    billion). Savings result fromthe rollback of State weightlimits that apply to the NO,which includes Interstatehighways, that are higher than

    the Federal limits.

    The bridge impacts of theNorth American TradeScenarios are dominated bythe weight (44,000 poundsand 51,000 pounds) allowedon the tridem-axle for thenoted configurations. Thebridge impacts are $51 billionand $65 billion for capital

    costs and $203 billion and$264 billion for user delaycosts for the scenarios withthe 44,000-pound and 51,000-pound tridem limit,respectively.

    The bridge impact for theLonger Combination VehiclesNationwide Scenario is $53billion in capital costs and

    $266 billion in user delaycosts. It is dominated by thenine-axle TPD at 148,000pounds distributed across alength of 119.3 feet, and theeight-axle B-train double-trailer combination at 131,000pounds distributed over 69.3feet.

    Theoretically, the H.R. 551

    Scenario might increasebridge impacts as the lengthsof some semitrailercombinations would bereduced as semitrailers longerthan 53 feet would be phased

  • 7/28/2019 Vol3-Chapter6

    13/13

    VI-12

    Analytical Case

    Costs($Billion)

    Change from Base Case($Billion)

    Capital User Total Capital User Total

    1994 Base Case 154 175 329 0 0 0

    2000 Base Case 154 175 329 0 0 0

    SCENARIO

    Uniformity 134 133 267 -20 -42 -62

    44,000-pound

    tridem axleNorth American Trade

    51,000-poundtridem axle

    205 378 583 51 203 254

    219 439 658 65 264 329

    LCVs Nationwide 207 441 648 53 266 319

    H.R. 551 154 175 329 0 0 0

    Triples Nationwide 170 276 446 16 101 117

    Table VI-2. Scenario Bridge Impacts

    out of service. Decreasing thelength of a truck at a givenweight increases the stress onbridges. This effect is verysmall for two reasons. First,

    the number of trucks affectedis very small and second, thecommodities carried in extra-long semitrailers aregenerally very light such thatthey have no impact onbridges. Therefore, thisscenario has virtually noimpact on bridges.

    For the Triples Nationwide

    Scenario bridge costs ($16

    billion in capital and $101billion in user costs) resultfrom the use of the seven-axletriple-trailer combination at aGVW of 132,000 pounds

    distributed over a length of97.2 feet.