HISTORY OF HOLLOW CORE SLAB BUBBLE DECK TECHNOLOGY SITE INSTALLATION COMPOSITION/THEORY TYPES OF BUBBLE DECK/COMPONENTS EXAMPLES REFERENCES

Page 3: Voided Slab

A concrete block is one of several precast concrete products used in construction. The term precast refers to the fact that the blocks are formed and hardened before they are brought to the job site. In the 1950s, hollow-core slab were invented. The voided or hollow core system was created to reduce the weight of the concrete from the system. this concept removes and replaces concrete from center of the slab, where it is less useful with lighter material in order to decreases the dead wt of concrete floor.however,these hollow cavities significantly decrease the slab resistance to shear and fire, thus reduce its structural integrity.

Page 4: Voided Slab

The first hollow concrete block was designed in 1890 by Harmon S. Palmer in the United States. After 10 years of experimenting, Palmer patented the design in 1900. Palmer's blocks were 8 in (20.3 cm) by 10 in (25.4 cm) by 30 in (76.2 cm), and they were so heavy they had to be lifted into place with a small crane. By 1905, an estimated 1,500 companies were manufacturing concrete blocks in the United States. These early blocks were usually cast by hand, and the average output was about 10 blocks per person per hour. Today, concrete block manufacturing is a highly automated process that can produce up to 2,000 blocks per hour

Page 5: Voided Slab
Page 6: Voided Slab

BUBBLE DECK TECHNOLOGY

Bubble deck slab is the slab in which some amount of the concrete is replaced by the plastic bubbles or ellipsoid which are made by the waste plastic material, which reduces the self weight of the structure. Design of this type of the slab is based on the euro and the British codes.

Page 7: Voided Slab

In the 1990ies, a new system was invented, eliminating the some of the problems. It is used in Dutch:German invented by JORGEN BREUNING. He locks ellipsoids between the top and bottom reinforcement meshes, thereby creating a natural cell structure, acting like a solid slab. The slab is created with the same capabilities as a solid slab, but with considerably less weight due to the elimination of excessive concrete.

Page 8: Voided Slab

Russia

Australia

Brazil

North America

Denmark

New Zealand

uk

Page 9: Voided Slab
Page 10: Voided Slab

Saves 30 to 50 % weight compared to a corresponding solid slab – equal stiffness. 20% concrete reduction in other components. The reduced weight of the slab will typical result in a change in design to longer spans and/or reduced deck thickness. It is also seismic friendly as it lowers the total weight of the building. Reduced concrete usage – 1 kg recycled plastic replaces 100 kg of concrete. The company estimates that building costs are reduced by 8 to 10 %.

Page 11: Voided Slab

SITE INSTALLATION( Type A- Filigree Elements)

• Temporary Support – Propping on parallel beams • Placing Elements – Semi pre-cast elements mechanicallylifted into position• Joint Reinforcement – Insert loose bottom splice barsand tie top mesh across joints between elements• Perimeter shuttering – Fix shuttering to bottom pre-castconcrete layer & tie to top mesh reinforcement• Soffit shuttering – Prop plywood across jointsbetween element bays and between elements & columns

Page 12: Voided Slab

Preparation – Seal joints between elements, clean andmoisten bottom pre-cast concrete layer• Concreting – Pour, vibrate and aggregate in-situ concrete• Temporary works – Remove, typically after 3 – 5 days,according to specific site advice• Finishing – no further work required.

Page 13: Voided Slab

Typical arrangement ofprops and propping beams Loaded

trailersarriving on site

Liftingelementintoposition

Page 14: Voided Slab

Aligning bubbles between elements

Pouring, Vibrating& Floating SiteConcrete

Page 15: Voided Slab

Several methods have been introduced during the last decades, but with very limited success, due to major problems with shear capacity and fire resistance as well as impractical execution. Most attempts have consisted of laying blocks of a less heavy material like expanded polystyrene between the bottom and top reinforcement. But the use will always be very limited due to reduced resistances towards shear, local punching and fire. which is why the use of these systems has never gained acceptance and they are only used in a limited number of projects

Page 16: Voided Slab

The voids are positioned in the middle of the cross section, where concrete has limited effect, while maintaining solid sections in top and bottom where high stresses can exist. Hence, the slab is fully functional with regards to both positive and negative bending.

Page 17: Voided Slab

In principle, Bubble Deck slabs acts like solid slabs. Designing is consequently like for solid slabs, just with less load corresponding to the reduced amount of concrete. Thorough investigations according to Euro codes are made at universities in Germany, Netherlands and Denmark, concluding that a Bubble Deck slab acts like as a solid slab.

Page 18: Voided Slab

Only top compressive portion and bottom reinforcing steel of a solid concrete slab contribute to flexure stiffness in bending.

Bubble deck removes concrete from the center of the flexural slab and replaces with hollow HDPE spheres. It is having equal bending stiffness as solid slab.

But technical university of Denmark also carried out test on stiffness of bubble deck slab. they verified the result and they found out, for same strength, bubble deck has 87% of bending stiffness of similar solid slab but only 66% concrete volume due to HDPE spheres.

Page 19: Voided Slab

As a result, deflection was higher in bubble deck.

However, significant lower dead weight compensated for the slightly reduced stiffness and therefore bubble deck gave higher carrying capacity.

As, reduced permanent load positively affects long term response in the serviceability limit state design, which governs crack propagation.

It has been concluded that adding a minimum amount of extra reinforcing steel would satisfy the criteria.

Page 20: Voided Slab

The main difference between a solid slab and a voided, voided slab refers to shear resistance. Due to the reduced concrete volume, the shear resistance will also be reduced.

For a BubbleDeck slab the shear resistance is proportional to the amount of concrete, as the special geometry shaped by the ellipsoidal voids acts like ,hence enabling all concrete to be effective.

The reduced shear resistance will not lead to problems, as balls are simply left out where the shear is high, at columns and walls

Page 21: Voided Slab

In calculations, a reduction factor of 0.6 is used on the shear capacity for all bubble deck slab.

This guarantees a large safety margin. Areas with high shear loads need therefore a special attention, e.g. around columns. That is solved by omitting a few balls in the critical area around the columns, therefore giving full shear capacity.

Page 22: Voided Slab

The simple Bubble Deck is castover the pre-fabricated “bubble lattice”on traditional formwork.(cast in situ)

In the filigree-element Bubble Deck the bottom side of the ‘bubble-lattice’ unit is furnished with a pre-cast concrete layer which on the building site replaces the horizontal part ofthe formwork.(semi pre cast)

Page 23: Voided Slab

The simple Bubble Deck may alsobe delivered to the building site aspre-cast factory-made slabs.(pre cast)

Page 24: Voided Slab

COMPONENTS

Page 25: Voided Slab

-Grade of steel: Generally Fe 500,550.

-Rebar size depends on the thickness of the slab and span.

-spacing: Max 1 m. or maximum 3 balls between two girder.Two types: (a). Self supporting (b). Trussed type.

Page 26: Voided Slab

- Main bar 10mm minimum – for 200 to 300 mm slab thickness.

- 12mm- for size ≥300 mm

Page 27: Voided Slab

Plastic balls or ellipsoids are made up of the plastic waste.

Diameter: always 0.9 of the slab size.

Material of balls: 1.polyethin. 2.pvp- poly vinyl propylene. 3.pvc- poly vinyl chloride.

Page 28: Voided Slab

Concrete

Type: self compacting concrete Grade: Any grade of concrete can be used, generally M 20, 30 grade is use.

Page 29: Voided Slab

The largest Bubble Deck structure so far erected in Great Britain. The structure comprises 7,800 m2 of Bubble Deck floor slabs between 3 and 6 stories high supported on in-situ reinforced concrete columns. Over £400,000 of savings were realized as a direct result of incorporating Bubble Deck into this project, amounting to a 3% saving off the total project cost.

1.LeCoieHousing:

Page 30: Voided Slab
Page 31: Voided Slab

Sogn Arena, Oslo in Norway

Page 32: Voided Slab

City Hall and Offices, in Denmark

Page 33: Voided Slab

Bubble deck-advanced structure engineering by Paul harding,managing director bubble deck C.I.ltd.Bubble deck structure solution (UNITED KINGDOM)Structural Behavior of bubble deck slab by Massachusetts institute of Technology