V.Montabonnet - Safety during Hardware Commissioning 18 October 2007 1 Contents Electrical circuits...
-
Upload
jonah-carroll -
Category
Documents
-
view
214 -
download
0
Transcript of V.Montabonnet - Safety during Hardware Commissioning 18 October 2007 1 Contents Electrical circuits...
V.M
on
tab
on
net
- S
afe
ty d
uri
ng
Hard
ware
Com
mis
sion
ing
18
Oct
ob
er
20
07
1
Contents
Contents
Electrical circuits in the LHC context Electrical Hazards Preventions Safety Training Habilitation Consignation Flowchart for LHC work
V.M
on
tab
on
net
- S
afe
ty d
uri
ng
Hard
ware
Com
mis
sion
ing
18
Oct
ob
er
20
07
2
LHC Electrical Circuit
DFB
EE system
AC
DC
AC
DC
QHPS18kV
18kV / 400V
400V
400V [UPS]
Water
EE system
QHPS
Power Converter
Power Converter
Power converters supply: Cold circuits: UA, RR, UJ [High Current] Warm Circuits: SR [High Voltage]
Cold Circuits
V.M
on
tab
on
net
- S
afe
ty d
uri
ng
Hard
ware
Com
mis
sion
ing
18
Oct
ob
er
20
07
3
Electrical Hazards
Electrical shock due to contact with energized piece AC side
18kV for the Main Dipole and Warm Magnet converters 400V for all the other converter types 400V UPS for the Electronics of the high current
converters (> 2kA)
DC side (Differential Voltage) Up to 950V for the warm magnets 180V for the Main Dipole Converter during a ramp < 20V for all the other converters
AC
DC
Power Converter
V.M
on
tab
on
net
- S
afe
ty d
uri
ng
Hard
ware
Com
mis
sion
ing
18
Oct
ob
er
20
07
4
Electrical Hazards
Electrical shock due to contact with energized piece
DC side (Common Mode Voltage) Common mode of 10V in normal operation Voltage / Earth could be high during Energy Extraction with additional resistor
EE system700 mOhms
AC
DC
Power Converter
10V
550A
385V
395V
385V
V.M
on
tab
on
net
- S
afe
ty d
uri
ng
Hard
ware
Com
mis
sion
ing
18
Oct
ob
er
20
07
5
Burn due to short-circuit or opening of the load with current Huge amount of energy stored in the superconducting
magnets
Main Dipole: 15.7 Henrys – 11.85kA = 1.1 GJ
BE CAREFUL !!! Zero Voltage doesn’t mean Zero Current Converter OFF but still current in the circuit
Very long time constant: 4 hours for Main Dipole
Electrical Hazards
AC
DC
Power Converter
-0.2V
11.85kA
Example: 1Q converters after FASTPA, OFF
V.M
on
tab
on
net
- S
afe
ty d
uri
ng
Hard
ware
Com
mis
sion
ing
18
Oct
ob
er
20
07
6
Preventions
Prevention against accidental contact
Signalization
Grills added for the protection of the converter DC outputs
Converter rack protection Doors, panels added Rack closed for the main dipole
transformer
V.M
on
tab
on
net
- S
afe
ty d
uri
ng
Hard
ware
Com
mis
sion
ing
18
Oct
ob
er
20
07
7
Voltage Range / UTE C 18-510
Very Low Voltage
Low Voltage High Voltage
TBTS,P,F BTA BTB HTA HTB
DC side
0 120V 750V 1500V 75kV
0 50V 500V 1000V 50kV
AC side
TBTF: Très Basse Tension Fonctionnelle
Most of converters
TBT
- Dipole- Circuits with Extraction Energy Resistor- Warm MagnetsBTA
- Warm Magnets
BTB
BTA Most of converters HTA - Dipole- Warm Magnets
V.M
on
tab
on
net
- S
afe
ty d
uri
ng
Hard
ware
Com
mis
sion
ing
18
Oct
ob
er
20
07
8
Energized piece
Voltage Range / UTE C 18-510
Conclusion / UTE C 18-510:
BT domain even for DC output with low voltage (<10V)
Rules to apply BT: Minimal distance from energized pieces >30cm if
not contain in IP2X envelope
Ø 12mm
Envelope
IP2X Definition
V.M
on
tab
on
net
- S
afe
ty d
uri
ng
Hard
ware
Com
mis
sion
ing
18
Oct
ob
er
20
07
9
LHC Safety Training
LHC Machine Not considered as a “Local Electrique” / UTE C 18-510 Safety Training “Level 4” mandatory: http://
sir.cern.ch/
BUT, not all the equipments are IP2X at the moment“ Keep away from electrical
installations. Minimum distance is 50 cm.”
LHC machine safety training (level 4)
RR Tunnel: DFB, Current Lead
V.M
on
tab
on
net
- S
afe
ty d
uri
ng
Hard
ware
Com
mis
sion
ing
18
Oct
ob
er
20
07
10
Habilitation: for who ?
Electrical Work ?
Near energized electrical piece ?
Under the supervision of
trained person ?
• “Electrical Worker” for measurement maintenance reparation modification
• “Chargé de Travaux”• “Chargé d’Intervention”
• “Chargé de Consignation”
No Habilitation
Habilitation forNon Electrical Worker
B0
Habilitation forElectrical WorkerB1, B2, BR, BC
YesNo
No
No
Yes
Yes
BT <30cm
V.M
on
tab
on
net
- S
afe
ty d
uri
ng
Hard
ware
Com
mis
sion
ing
18
Oct
ob
er
20
07
11
Habilitation: Actors
B2
B1 B0
BC
BR
“Chargé de Travaux” B2“Chargé d’ Interventions” BR
Supervise on the field - the work planned Ex: extension, modification - the “intervention” Ex: reparation, measurements
Ensure his own safety and the safety of people under his supervision
“Exécutant électricien” B1
Execute electrical work Responsible for his own safety
“Exécutant non électricien” B0
Execute or supervise non electrical work Habilitation not mandatory if all electrical hazards have been removed
“Chargé de Consignation” BC
Execute or get execute the consignation or part of it
AT
AT
AC
AC
V.M
on
tab
on
net
- S
afe
ty d
uri
ng
Hard
ware
Com
mis
sion
ing
18
Oct
ob
er
20
07
12
1) Separate the equipment from its electrical sources2) Lock in open position the separation devices
3) Identify the equipment 4) Check that the voltage is zero Earth and short-circuit (not mandatory in BT)
Consignation: Principle
1ère étape de consignation
On the work area
2nde étape de consignation
V.M
on
tab
on
net
- S
afe
ty d
uri
ng
Hard
ware
Com
mis
sion
ing
18
Oct
ob
er
20
07
13
Procedure: Première Etape de Consignation related to Power
Converters http://www.edms.cern.ch/853633
Procedure for any work of disconnection of warm parts of the superconductive circuits of LHC: Safety Aspects
https://edms.cern.ch/document/762293
Consignation in 2 steps
Request Consigne RPHE.UA83.RQD.A78 converter& Measure I=0 on DFBAO.7L8
Chargé de Travaux
1ère étape de consignation
Separate the converter from AC sources
Chargé de Consignation C.C.[AB-PO for power converter]
Lock in open position
On the field
2ième étape de consignation
Identify the converter: To be sure that the work will be done on the correct equipment
Chargé Travaux
I=0 @ working point Chargé Travaux
Chargé Consignat. [AB-PO]
V=0, Earthing & Short-circuit Chargé Travaux
Work can start under the responsability of the « Chargé de Travaux » under safe conditions
AC
AC
V.M
on
tab
on
net
- S
afe
ty d
uri
ng
Hard
ware
Com
mis
sion
ing
18
Oct
ob
er
20
07
14
Work Flowchart in LHC Context
ChargéTravaux
I HAVE A JOB TO ORGANIZE ON POTENTIALLY DANGEROUS INSTALLATION.I AM RESPONSIBLE FOR MY TEAM SAFETY
C.T.
JOB WAS DONE IN SAFE CONDITIONS.FOLLOW STEPS EASIER & SAFER
ANALYSEHAZARDS:
ELECTRICAL&
OTHERS
~~~~~~~~~~~~~~~~~~~….
~~~~~~~~~~~~~~~~~~~….
~~~~~~~~~~~~~~~~~~~….
~~~~~~~~~~~~~~~~~~~….
AB/PO
~~~~~~~~~~~~~~~~~~~….
~~~~~~~~~~~~~~~~~~~….
~~~~~~~~~~~~~~~~~~~….
~~~~~~~~~~~~~~~~~~~….
AT/MEL
WhereWhat ?
Mr Circuit
C.T.
E.I.C Pt Owner
01
C.T.
OK! PLAN WITH
POINT OWNERAND / OR
E.I.C C.T.
©
OK!
E.I.CPt Owner
When ? 02
REQUEST1ère
ETAPE DECONSIGNATION C.T.
AT/MEL ©
AB/PO
© 03
CONSIGNE1ère
ETAPE AB/PO
©
04
DELIVERATTESTATION
BACK TOC.T. AB/PO
©©©
©©©
©©©
C.T.
©©©
05
DOINTERVENTION
IN SAFECONDITIONS
OK! Work!
El.Ex. Non El.Ex.C.T.
©©©©©©
07
REMOVEMISE A LA
TERREC.T.
©©©©©©
08
DECONSIGNE&
INFORMEIC & P.OWNER
AB/PO
E.I.C
Pt Owner
Done !
AB/PO
©©© ©©
10
GIVE BACK YELLOW
FORM
Job Done.
C.T.
©©© ©
AB/PO
©©© ©©
09
CONSIGNE2ème
ETAPE
V=0V I=0A
VAT VAI MALT
IDs
C.T.
©©©©©©
06
AB/PO
V.M
on
tab
on
net
- S
afe
ty d
uri
ng
Hard
ware
Com
mis
sion
ing
18
Oct
ob
er
20
07
15
Documents
Documents:
Attestation de 1ère Etape de Consignation
Autorisation de Travail AT
AT
AC
AC