Virtual Server Implementation

21
Virtual Server Implementation Presented by HYUN

description

Virtual Server Implementation. Presented by HYUN. The Project objects. Power saving server environment Server resource utilization. Virtual Server. d. Virtual Networking implementation. Electricity power calculation. A fluorescent light power consumption. 30 – 40 W. - PowerPoint PPT Presentation

Transcript of Virtual Server Implementation

Page 1: Virtual Server Implementation

Virtual Server Implementation

Presented by HYUN

Page 2: Virtual Server Implementation

The Project objects

• Power saving server environment

• Server resource utilization

Page 3: Virtual Server Implementation

Virtual Server

• d

Page 4: Virtual Server Implementation

Virtual Networking implementation

Page 5: Virtual Server Implementation

Electricity power calculation

• A fluorescent light power consumption

30 – 40 W

Page 6: Virtual Server Implementation

Electricity power calculation

• General desktop/server’s power consumption

• CPU : 100W• RAM : 8W• Graphic card : 30W• Mother board : 20W• CD-ROM : 20W• HDD : 13W• Monitor : 40W

-------------------------------------------------------------------Total = 230W

Page 7: Virtual Server Implementation

Electricity power calculation

• General server power consumption(per day)

230W x 24(hours) = 5,520 Wh = 5.5 KWh

5.5kWh $ ?

Page 8: Virtual Server Implementation

Electricity power calculation

• A fluorescent light power consumption30 – 40 W

230W / 35W ≒ 6.5

=

Page 9: Virtual Server Implementation

Power consumption comparison

VS

5 Physical Virtual Server servers

Page 10: Virtual Server Implementation

Power consumption comparison

230Wx5x

24h=

27.6kwh + a

230Wx

24h

=5.5kwh + a

Page 11: Virtual Server Implementation

Virtual Server Advantages

• Power saving over multiple physical servers

• Simplify system administration by integrating all servers into one physical machine

• Server hardware resource optimization

Page 12: Virtual Server Implementation

Virtual Server disadvantages

• When host server machine crash, all virtual servers embedded in the server crash too.

Page 13: Virtual Server Implementation

Extra considerations for power saving

• General SATA HDD

13W

• NAND flash memory – SSD

1W

Page 14: Virtual Server Implementation

Extra considerations for power saving

• External USB HDD

3W – 5W

Page 15: Virtual Server Implementation

Extra considerations for power saving

• Power saving application

– Turning off the monitor– Turning off the HDD– CPU power control etc.

Full load Saving Mode

230W 150W

Page 16: Virtual Server Implementation

Design Overview

e

Page 17: Virtual Server Implementation

Hardware ListTiming Equipment needed

Quantity

Description Unit cost Total cost

1 Standalone Server(HP Prolian ML 370 G5)CPU: Quad Core

Processor 2 GHzRAM: 2G

$6,000 $6,000

2 External HDD 320G(USB) $100 $2001 SSD Flash

memory(64GB)$1,875 $1,875

1 Halogen light(USB) $15 $151 17” LCD Monitor $200 $2001 HP T1500 XR UPS G2 $700 $700

Total equipment cost for the project $8,990

Page 18: Virtual Server Implementation

Software ListTiming Software needed

Quantity

Description Unit cost Total cost

1 VMware GSX $3,400 $3,400

1 Windows2000 Advanced Server(5CAL)

$570 $570

1 Ubuntu Server $0 $0

1 Windows Server 2003(5CAL)

$1,583 $1,583

1 Recording power consumption software

$0 $0

1 Power saving application $38 $38

Total software cost for the project $5,591

Page 19: Virtual Server Implementation

MS ProjectID Task_Name Duration

Initiate 0.5 days

1 Project Charter 0.3 days

2 Feasibility study 0.2 days

Planning 1.7 days

3 WBS 0.5 days

4 MS Project 0.1 days

5 Sketch 0.2 days

6 Hardware 0.3 days

7 Software 0.3 days

8 Service 0.3 days

Executing 2.5 days?

9 Installation 1 day?

10 Test 0.5 days

11 Training 1 day?

Control 0.8 days

12 Change Control 0.5 days

13 Sketch of Change 0.3 days

Closing 1.5 days?

14 Closeout Report 0.5 days

15 Audit 1day?

Total 7DAY

Page 20: Virtual Server Implementation

Budget

Expenditures

Internal Staff Labor $3,000

Software Tools $5,600

Hardware $8,990

Total $17,590

Page 21: Virtual Server Implementation

THANK YOU