Agenda

1. Introductions2. Fiber cable deployment progress3. FAP construction progress and

completion schedule4. Connecting to CAI’s5. Undersea cable deployment

progress

STX02DROPS: 100%CAI: 2/27

STX03DROPS: 100%CAI: 0/13

STX04DROPS: 0%CAI: 0/4

STX05DROPS: 0%CAI: 0/11

STX06DROPS: 50%CAI: 0/6

STX16DROPS: 0%CAI: 0/7

STX15DROPS: 76%CAI: 0/17

St. Croix (West)

Backbone Fiber Installed

Backbone Innerduct Placed

STX12DROPS: 0%CAI: 0/1

STX09DROPS: 57%CAI: 0/14

STX13DROPS: 0%CAI: 0/7

STX17DROPS: 0%CAI: 0/22

STX07DROPS: 0%CAI: 0/4

St. Croix (East)

Backbone Fiber Installed

Backbone Innerduct Placed

STT01DROPS: 44%CAI: 0/17

STT02DROPS: 88%CAI: 0/8

STT05DROPS: 0%CAI: 0/7

STT16DROPS: 70%CAI: 0/30

St. Thomas (West)

Backbone Fiber Installed

Backbone Innerduct Placed

STT14DROPS: 95%CAI: 0/43 STT12

DROPS: 84%CAI: 0/19

STT13DROPS: 0%CAI: 0/6

STT10DROPS: 67%CAI: 0/3

STT09DROPS: 38%CAI: 0/8

St. Thomas (East)

Backbone Fiber Installed

Backbone Innerduct Placed

STT11

STT11DROPS: 88%CAI: 0/17

STJ01DROPS: 0%CAI: 0/20

STJ02DROPS: 0%CAI: 0/11

St. John

Backbone Fiber Installed

Backbone Innerduct Placed

Splicing the fiber cables into a complete network

Fusion splicing fibersand training a local tech

Completed spliced fibersin tray

Splice tray enclosure for pole mounting

Fiber/Facility Access Point (FAP) STT10 (Nadir)

Cisco ME 3800 Aggregation Switch (1)

FAP #

Local Name Contractor% Building complete Gen/Power HVAC

Racking & Duct DC Power

% Completed Drops

BB Fiber Terminated     Notes

                       

STX02 Frederiksted Benton/JBC 100        100        

STX03 Boy & Girls Club Benton/JBC 100↑   10/09 10/09   100    .  

STX04 UVI Benton/JBC 100↑   10/11 10/14 10/15 0       

STX05 Villa La Reine AT 100   10/19 10/23 10/24 0        

STX06 Woodson School AT 100   10/23 10/24 10/24 50       

STX07 Dept Education AT 90 ↑   10/28 10/27 10/27 0  

    Working on epoxy flooring and elect trim

STX09 Gov’t House Benton/JBC n/a       75 57       

STX12 Cotton Valley Benton/JBC 100 ↑   10/13 10/18 10/18 0    

 

STX13 DPW Benton/JBC 100         0       

STX15 Juan Luis Hospital Eleven 10   11/02 11/23 11/23 76       

STX16 Roebuck – Ind. Park Benton/JBC 100 ↑   10/07 10/12 10/12         

STX17 WAPA Richmond AT 15   11/07 11/26 11/26         

                         

STT01 Vitema Balbo           44        

STT02 UVI Benton/JBC65↑

  10/29 11/11 11/11 88       

STT03 Bonne Esperance CancelledCancel

                

STT05 Estate Dorothea Benton/JBC5 hold

                

STT09 Eudora Keane Benton/JBC100 ↑

  09/29 10/30 10/30 38       

STT10 Nadir Benton/JBC 100 ↑   10/04 11/02 11/02 67        

STT11 Ft. Mylner Rumina 65 ↑   11/12 11/14 11/14 88        

STT12 Schneider Hospital Benton/JBC 100 ↑  10/11 11/05 11/05 84    

 

STT13 WICO – Havensight Benton/JBC 15 ↑

             

   

STT14 Boy Scouts Apex

Pending reassignment

        100    

   

STT16 Nisky Center Rumina 75 ↑   10/24 11/09 11/09 70        

STJ01 Cruz Bay Custom 100 ↑   10/29 11/17 11/17 0      

STJ02 Myra Keating Custom 100 ↑   11/03 11/20 11/20 0      

Super FAP STX02 (Frederiksted):

Cisco ASR 9006Core Router (1)

Cisco ME 3800Aggregation Switch (2)

Community Anchor Institutions

• Schools……………………... 82• Libraries……………………. 7• Healthcare Providers….. 19• Public Safety……………… 42• Colleges……………………. 4• Government Offices…… 124• Public Broadcast Sys…. 2• Community Centers…… 37 Total 316

viNGN is bringing a 4-fiber cable and interface to each CAI at no cost to them and which is capable of delivering at least 1 gigabit service through an ISP of their choosing!

Athalie McFarlane Petersen Public Library-Frederiksted

Aerial Attachment Building Entry Point

Patch PanelCisco ME 3400Premise Aggregation Switch

…and 100 megabit+service becomes a reality in the USVI!

CAI Connection Schedule

Beach Manhole Installations

Summary and Conclusions

• Construction is proceeding on all aspects of the network.

• As CAI’s are connected and their segment of the network is lit, gigabit service may begin.

• Completion of the network build is expected by year end 2013.