nromoef.gov.innromoef.gov.in/SMPR/12012016/14.docx · Web viewINFORMATION TV PVT. LTD Sl. No....

47
(A) HALF-YEARLY COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE ENVIRONMENTAL CLEARANCE REF. LETTER NO. SEIAA/HR/2013/1251 DATED 25.11.2013 FOR “COMMERCIAL COLONY” PROJECT IN THE REVENUE ESTATE OF VILLAGE SIHI, SEC-83, GURGAON HARYANA BY M/S INFORMATION TV PVT. LTD Sl. No. Conditions Status of Compliance PART A - SPECIFIC CONDITIONS: Construction Phase:- I “Consent for Establishment” shall be obtained from Haryana State Pollution Control Board Under Air and Water act and a copy shall be submitted to the SEIAA, Haryana before the start of any construction work at site. Agreed. “Consent to Establishment” has been obtained Vide letter no 2821214GUSOCTE569514 Dated 18/02/2014 from the Haryana State Pollution Control Board under Air and Water act. Copy of CTE is enclosed as Annexure –I. II A first aid room as proposed in the project report shall be provided in both during construction and operation phase of the project. Agreed. First aid room will be provided in both during construction and operation phase of the project. III Adequate drinking water and sanitary facilities should be provided for construction workers at the site. Provision should be made for mobile Agreed. Adequate drinking water and sanitary facilities will be provided for construction workers at the site. Provision will be

Transcript of nromoef.gov.innromoef.gov.in/SMPR/12012016/14.docx · Web viewINFORMATION TV PVT. LTD Sl. No....

(A) HALF-YEARLY COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE ENVIRONMENTAL CLEARANCE REF. LETTER NO. SEIAA/HR/2013/1251 DATED 25.11.2013 FOR “COMMERCIAL COLONY” PROJECT IN THE REVENUE ESTATE OF VILLAGE SIHI, SEC-83, GURGAON HARYANA BY M/S INFORMATION TV PVT. LTD

Sl. No. Conditions Status of Compliance

PART A - SPECIFIC CONDITIONS: Construction Phase:-

I “Consent for Establishment” shall be obtained

from Haryana State Pollution Control Board

Under Air and Water act and a copy shall be

submitted to the SEIAA, Haryana before the

start of any construction work at site.

Agreed. “Consent to Establishment” has

been obtained Vide letter no

2821214GUSOCTE569514 Dated

18/02/2014 from the Haryana State

Pollution Control Board under Air and

Water act. Copy of CTE is enclosed as

Annexure –I.

II A first aid room as proposed in the project

report shall be provided in both during

construction and operation phase of the

project.

Agreed. First aid room will be provided

in both during construction and

operation phase of the project.

III Adequate drinking water and sanitary facilities

should be provided for construction workers at

the site. Provision should be made for mobile

toilets. Open defecation by the labors is strictly

prohibited. The safe disposal of waste water

and solid wastes generated during the

construction phase should be ensured.

Agreed. Adequate drinking water and

sanitary facilities will be provided for

construction workers at the site.

Provision will be made for mobile

toilets. The safe disposal of waste water

and solid wastes generated during the

construction phase will be ensured.

IV All the top soil excavated during construction

activities should be stored for use in

horticulture/landscape development within the

project site.

Agreed, Separate stock piles will be

maintain and all the top soil excavated

during construction activities will be

store and utilized in horticulture/

landscape developments within the

project site. The remaining excavated

soil will be utilized in re-filling of

foundation, road works, rising of site

level etc.

V The project proponent shall ensure that the

building material required during construction

phase is properly stored within the project area

and disposal of construction waste should not

create any adverse effect on the neighboring

communities and should be disposed of after

taking necessary precautions for general safety

and health aspects of people, only in approved

sites with the approval of competent authority.

Agreed: The project proponent will

ensure that the building material

required during construction phase is

properly stored within the project area

and disposal of construction waste

should not create any adverse effect on

the neighboring communities and should

be disposed of after taking necessary

precautions for general safety and health

aspects of people, only in approved sites

with the approval of competent

authority.

VI Construction spoils, including bituminous

material and other hazardous materials, must

not be allowed to contaminate watercourses

and the dump sites for such material must be

secured so that they should not leach into the

ground water and any hazardous waste

generated during construction phase, should be

disposed off as per applicable rules and norms

with necessary approval of the Haryana State

Pollution Control Board.

Agreed, Construction spoils including

bituminous material and other hazardous

materials will not allow contaminating

water courses and the dump sites for

such material will be secure so that they

should not leach into the ground water.

Materials are being disposed off as per

applicable rules and norms with

necessary approval of the Haryana State

Pollution Control Board.

VII The diesel generator sets to be used during

construction phase should be ultra-low sulphur

diesel type and should conform to

Environment (Protection) Rules prescribed for

air and noise emission standards.

Agreed. During construction phase DG

sets will be used for office lighting and

site lighting. DG sets will be acoustic

enclosed. It will be running on ultra-low

sulphur diesel only with the provision of

air and noise emission standards as per

EPA Rules, 1986.

Results of the environmental monitoring

carried out at the site are enclosed as

Annexure – II.

VIII The diesel required for operating DG sets shall

be stored in underground tanks and if required,

clearance from Chief Controller of Explosives

shall be taken.

Agreed. The diesel required for

operating DG set will be stored in

HDPE Drums and log books will be

managed adequately.

IX Ambient noise levels should conform to

residential standards both during day and

night. Incremental pollution loads on the

ambient air and noise quality should be within

3month period. Latest Corporate Environment

Policy should be submitted to SEIAA within 3

months of issuance of this letter. Closely

monitored during construction phase.

Adequate measures should be taken to reduce

ambient air and noise level during construction

phase, so as to conform to the stipulated

residential standards.

Agreed, ambient noise levels are

being conformed to standards both

during day and night.

The silent type DG set with acoustic

enclosures will be installed at project

site and office.

Low sulphur fuel will be used

Exhaust will be conforming to the

provisions of Environment

(Protection) Rules prescribed for air

and noise emission standards.

All vehicles entering to the site will be

with valid PUC certificate.

All machinery used at the site will be

new and periodic maintenance of the

machinery insured.

Results of the environmental

monitoring carried out at the site are

enclosed as Annexure – II.

Shelter belt will be provided to reduce

the noise level within the site.

X Fly ash should be used as building material in Agreed, Fly ash based material/

the construction as per the provisions of Fly

Ash Notification of September, 1999 and

amended as on 27th August, 2003

products will be used as per the

provisions of fly ash notification of

September, 1999 and as amended on

27th August, 2003.

XI Storm water control and its re-use as per

CGWB and BIS standards for various

applications should be ensured.

Agreed. Storm water control and its

reuse will be maintained as per Central

Ground Water Board and BIS standards

for various applications.

XII Water demand during construction should be

reduced by use of premixed concrete, curing

agents and other best practices .

Water demand during construction will

be reduced by the practice of using

premixed concrete, curing agents and

other best practices.

XIII In view of severe constrains in water supply

augmentation in the region and sustainability

of water resources, the developer will submit

the NOC from CGWA specifying water

extraction quantities and assurance from

HUDA / utility provider indicating source of

water supply and quantity of water with details

of intended use of water potable and non

potable. Assurance is required for both

construction and operation stages separately. It

shall be submitted to the SEIAA/ R.O. MoEF,

Chandigarh before the start of construction.

Ground water will not be extracted for

the purpose of construction as well as

for operation phase of the project.

Application has been filed to HUDA for

fresh water. Acknowledgement copy of

the same is enclosed as Annexure-III

XIV Roof should meet prescriptive requirement as

per Energy Conservation Building Code by

using appropriate thermal insulation material.

Agreed, Roof will meet the prescriptive

requirement as per Energy Conservation

Building Code by using appropriate

thermal insulation material.

XV Opaque wall should meet prescriptive

requirement as per Energy Conservation

Building Code which is proposed to be

Agreed: Opaque wall will meet

prescriptive requirement as per Energy

Conservation Building Code.

mandatory for all air conditioned spaces while

it is desirable for non-air-conditioned spaces

by use of appropriate thermal insulation

material to fulfill requirement.

XVI The approval of the competent authority shall

be obtained for structural safety of the building

on account of earthquake, adequacy of

firefighting equipments, etc. as per National

Building Code including protection measures

from lightening etc. If any forestland is

involved in the proposed site, clearance under

Forest Conservation Act shall be taken from

the competent Authority.

Agreed, The approval of competent

authority will be taken for structural

safety of the building due to earthquake,

adequacy of firefighting equipments etc.

as per National Building Code including

protection measures from lightening etc.

Project site does not fall in Forest area.

NOC from Divisional Forest Officer is

enclosed as Annexure-IV.

XVII Overexploited groundwater and impending

severe shortage of water supply in the region

requires the developer to redraw the water and

energy conservation plan. Developer shall

reduce the overall footprint of the proposed

development. Project proponent shall

incorporate water efficiency / Saving measures

as well as water reuse/ recycling within 3

months before the start of construction to the

SEIAA Haryana and RO, MOEF, GOI,

Chandigarh.

Agreed, No ground water extraction will

take place. However treated water for

construction will be supplied by HUDA.

To reduce the demand in operation

phase treated water from STP will be

used for horticulture, flushing, cooling,

rest will be used in nearby construction

site. As well as efficient fixture will be

used to minimize the water demand for

domestic purpose.

XVIII The project proponent as stated in proposal

shall construct 04 nos rain water harvesting

pits for recharging the ground water within the

project premises. Rain Water harvesting pits

shall be designed to make provisions for silting

chamber and removal of floating matter before

entering harvesting pit. Maintenance budget

Agreed, 13 rain water harvesting pits

will be provided for recharging the

ground water within the project

premises. To remove silt and floating

matter, desilting chamber will be

proposed with rain water harvesting pits.

Care will be taken that contaminated

and persons responsible for maintenance must

be provided. Care shall also be taken that

contaminated water do not enter any RWH pit.

water will not be entered in any of RWH

pits.

XIX The Project Proponent shall provide for

adequate fire safety measures and equipments

as required by Haryana Fire Service Act, 2009

and instructions issued by the local

Authority/Directorate of fire from time to time.

Further the project proponent shall take

necessary permission regarding fire safety

scheme/NOC from competent authority as

required.

Agreed: The Project Proponent will

provide for adequate fire safety

measures and equipments as required by

Haryana Fire Service Act, 2009 and

instructions issued by the local

Authority/Directorate of fire from time

to time. Further the project proponent

will take necessary permission regarding

fire safety scheme/NOC from competent

authority as required.

XX The project proponent shall obtain assurance

from the DHBVN for supply of 3397 KVA of

power supply before the start of construction.

In no case project will be operational solely on

generators without any power supply from any

external power utility.

Agreed, The project proponent will

obtain assurance from the DHBVN for

supply of 3397 KVA of power supply

before the start of construction. In no

case project will be operational solely

on generators without any power supply

from any external power utility.

XXI Detail calculation of power load and ultimate

power load of the project shall be submitted to

DHBVN under intimation to SEIAA, Haryana

before the start of construction. Provision shall

be made for electrical infrastructure in the

Project area.

Agreed, Detail calculation of power load

and ultimate power load of the project

has been submitted to DHBVN under

intimation to SEIAA, Haryana before

the start of construction. Provision will

be made for electrical infrastructure in

the Project area.

XXII The Project proponent shall not raise any

construction in the natural land depression/

Nallah/ Water course and shall ensure that the

natural flow from the Nallah/ Water course is

Agreed, the project site does not contain

any natural land depression nallah/

water course as well as no natural flow

will be obstructed by the project.

not obstructed.

XXIII The project proponent shall keep the plinth

level of the building blocks sufficiently above

the level of the approach road as per prescribed

bye laws. Levels of the other areas in the

Projects shall also be kept suitably so as to

avoid flooding.

Agreed, The plinth level of the building

block will be above the level of the

approach road as per the prescribed bye

laws. Levels will be suitably

maintained to avoid flooding.

XXIV Construction shall be carried out so that

density of population does not exceed norms

approved by Director General Town and

Country Department Haryana.

Agreed, population density will be as

per the approved building plan by

Director General Town and Country

Department, Haryana.

XXV The Project proponent shall submit an affidavit

with the declaration that ground water will not

be used for construction and only treated water

should be used for construction.

Agreed, Ground water will not be used

for the construction activity. An

affidavit with the declaration that

ground water will not be used for

construction has already been submitted

to SEIAA, Haryana.

XXVI The project proponent shall not cut any

existing tree and project landscaping plan

should be modified to include those trees in

green area.

There is no need to cut the trees, Only

small bushes clearing will be required

for construction activity.

XXVII The project proponent shall ensure that ECBC

norms for composite climate zone are met. In

Particular building envelope, HVAC service

water heating, pumping, lighting and electrical

infrastructure must meet ECBC norms.

Agreed, ECBC norms for composite

climate zone, water heating, pumping,

lighting and electrical infrastructure will

be followed.

XXVIII The project proponent shall provide 3m high

barricade around the project area, dust screen

for every floor above the ground, proper

sprinkling and covering of stored material to

restrict dust and air pollution during

Agreed: The project proponent will

provide 3m high barricade around the

project area, dust screen for every floor

above the ground, proper sprinkling and

covering of stored material to restrict

construction. dust and air pollution during

construction.

XXIX The project proponent shall construct a

sedimentation basin in the lower level of the

project site to trap pollutant and other wastes

during rains.

Agreed: The project proponent will

construct a sedimentation basin in the

lower level of the project site to trap

pollutant and other wastes during rains.

XXX The project proponent shall provide proper

Rasta of proper width and proper strength for

each project before the start of construction.

Agreed: The project proponent will

provide proper Rasta of proper width

and proper strength for each project

before the start of construction.

XXXI The project proponent shall ensure that the U-

value of the glass is less than 3.177 and

maximum solar heat gain co-efficient is 0.25

for vertical fenestration.

Agreed: The project proponent shall

ensure that the U-value of the glass is

less than 3.177 and maximum solar heat

gain co-efficient is 0.25 for vertical

fenestration.

XXXII The project proponent shall adequately control

construction dusts like silica dust, non-silica

dust, wood dust. Such dusts shall not spread

outside project premises. Project Proponent

shall provide respiratory protective equipment

to all construction workers.

Agreed: The project proponent will

adequately control construction dusts

like silica dust, non-silica dust, and

wood dust. Such dusts will not spread

outside project premises. Project

Proponent will provide respiratory

protective equipment to all construction

workers.

XXXIII The project proponent shall provide one refuse

area till 24 meter as per National Building

Code.

Agreed, one refuse area till 24 meter as

per National Building Code will be

provided.

XXXIV The project proponent shall provide fire

control room and fire officers for building

above 30 meter as per national building Code.

Agreed: The project proponent will

provide fire control room and fire

officers for building above 30 meter as

per national building Code.

XXXV The project proponent shall obtain permission Agreed, Permission from Mines and

of Mines and Geology Department for

excavation of soil before the start of

construction.

Geology Department for excavation of

soil will be obtained for construction.

XXXVI The project proponent shall seek specific prior

approval from concerned local

Authority/HUDA regarding provision of storm

drainage and sewerage system including their

integration with external services of HUDA/

Local authorities beside other required services

before taking up any construction activity.

Agreed: The project proponent will seek

specific prior approval from concerned

local Authority/HUDA regarding

provision of storm drainage and

sewerage system including their

integration with external services of

HUDA/ Local authorities beside other

required services before taking up any

construction activity.

XXXV

III

The site for solid waste management plant be

earmarked on the layout plan and the detailed

project for setting up the solid waste

management plant shall be submitted to the

Authority within one month.

Agreed: The site for solid waste

management plant is earmarked on the

layout plan.

XXXVI

III

Vertical fenestration shall not exceed 40% of

total wall area.

Agreed: Vertical fenestration will not be

exceeding 40% of total wall area.

XXXIX The project proponent shall discharge excess

of treated waste water/storm water in the

public drainage system and shall seek

permission of HUDA before the start of

construction.

Agreed: The project proponent will

discharge excess of treated waste

water/storm water in the public drainage

system and shall seek permission of

HUDA before the start of construction.

XXXX The project proponent shall revise the water

calculation for service apartments @135 lpcd

instead of @111 lpcd and shall also submit

revised water balance diagram before the start

of construction. Sewerage and STP capacity

shall also be revised accordingly.

Agreed: The project proponent has

revised the water calculation for service

apartments and already submitted to the

SEIAA.

PART A- SPECIFIC CONDITIONS : Operation Phase

a “Consent to operate” shall be obtained from

Haryana State Pollution Control Board under

Air and Water Act and a copy shall be

submitted to the SEIAA, Haryana.

Agreed: “Consent to operate” will be

obtained from Haryana State Pollution

Control Board under Air and Water Act

and a copy shall be submitted to the

SEIAA, Haryana.

b The Sewage Treatment Plant (STP) shall be

installed for the treatment of the sewage to the

prescribed standards including odour and

treated effluent will be recycled to achieve

zero exit discharge. The installation of STP

should be certified by an independent expert

and a report in this regard should be submitted

to the SEIAA, Haryana before the project is

commissioned for operation. Tertiary

treatment of waste water is mandatory.

Discharge of treated sewage shall conform to

the norms and standards of HSPCB,

Panchkula. Project proponent shall implement

such STP technology which does not require

filter backwash.

Agreed, The Sewage Treatment Plant

(STP) will be installed for the treatment

of the sewage to be prescribed standards

including odour and treated effluent will

be recycled and used for flushing,

cooling, and rest will be used in nearby

construction site. Report of installation

of STP has been submitted to the

SEIAA, Haryana before the project is

commissioned for operation.

c Separation of the grey and black water should

be done by the use of dual plumbing line.

Treatment of 100% grey water by

decentralized treatment should be done

ensuring that the recirculated water should

have BOD maximum upto 10 mg/litre and the

recycled water will be used for flushing,

gardening and DG set cooling etc.

Agreed, Grey and black water will be

separated by the use of dual plumbing

line. Agreed, recycled water will be used

for flushing, gardening, cooling and rest

will be used for nearby construction site.

water balance diagram is enclosed as

Annexure- V

d For disinfection of the treated waste water

ultra violet radiation or ozonization process

Agreed, for disinfection of the treated

waste water ultra violet radiation process

should be used. will be used.

e Diesel Power generating sets proposed as

source of backup power for lifts, common area

illumination and for domestic use should be of

enclosed type and conform to rules made

under the Environment (Protection) Act, 1986.

The location of the DG sets should be in the

basement as promised by the project

proponent with appropriate stack height i.e.

above the roof level as per the CPCB norms.

The diesel used for DG sets should be of ultra

low sulphur diesel (0.05% sulphur), instead of

low sulphur diesel.

Agreed. DG set will be acoustic

enclosed & conform to rules made under

the Environment (Protection) Act, 1986.

The diesel used for DG sets will be of

ultra-low sulphur contents (maximum up

to 0.05%).

f Ambient Noise Level should be controlled to

ensure that it does not exceed the prescribed

standards both within and at the boundary of

the proposed commercial complex.

Agreed. The Ambient noise level will be

controlled such that it will not exceed

the prescribed standards both within and

at the boundary of the project.

g The project proponent as stated in the proposal

shall maintain at least 31.67% as green cover

area for tree plantation especially all around

the periphery of the project and on the road

sides preferably with local species which can

provide protection against noise and

suspended particulates matter. The open

spaces inside the project should be preferably

landscaped and covered with vegetation/grass,

Herbs& shrubs Only local available plant

species shall be used.

Agreed. The project proponent will

maintaining at least 20% as green cover

area for tree plantation especially all

around the periphery of the project and

on the road sides preferably with local

species so as to provide protection

against particulates and noise. The open

spaces inside the plot will be preferably

landscape and covered with

vegetation/glass. Landscape Plan is

attached as Annexure-.VI

h The project proponent shall strive to

minimize water in irrigation of landscape by

minimizing grass area, using native variety,

Agreed. To reduce the fresh water

demand for landscaping treated water

from STP will be used. Xeriscaping and

xeriscaping and mulching, utilizing efficient

irrigation system, scheduling irrigation only

after checking evapotranspiration data.

mulching technology will be adopted to

reduce the landscaping demand. .

i Rain water harvesting for roof runoff and

surface runoff, as per plan submitted should be

implemented. Before recharging the surface

runoff, pretreatment through sedimentation

tanks must be done to remove suspended

matter, oil and grease. The bore well for rain

water recharging shall be kept at least 5 m

above the highest ground water table. Care

shall be taken that contaminated water do not

enter any RWH pit. The project proponent

shall avoid rain water harvesting of first 10

minutes of rain fall. Roof top of the building

shall be without any toxic material or paint

which can contaminate rain water. Wire mess

and filters should be used wherever required.

Rainwater harvesting as per plan for roof

run-off and surface run-off will be

implemented. Suspended matter, oil and

grease will be removed by treatment

before recharging with surface run-off.

The bore well for recharge will be kept

at least 5 mts. above the highest ground

water table. Rain water Harvesting Plan

is enclosed as Annexure- VII

j The ground water level and its quality should

be monitored regularly in consultation with

Central Ground Water Authority.

Agreed. If required ground water level

and its quality will be monitored

regularly in consultation with Central

Ground Water Authority.

k There should be no traffic congestion near the

entry and exist points from the roads adjoining

the proposed project site. Parking should be

fully internalized and no public space should

be utilized.

Agreed. Parking will be completely

internalized and no public space will be

utilized. Care will be taken to ensure that

there will be no traffic congestion at the

entry and exit points.

l A report on the energy conservation measures

conforming to energy conservation norms

finalize by Bureau of Energy Efficiency

should be prepared incorporating details about

Report on energy conservation measure

conforming to energy conservation

norms finalized by BEE which will

include details of building materials and

building materials & technology; R & U

factors etc. and submit to the SEIAA, Haryana

in three months time.

technology, R & U factors etc has been

submitted to the SEIAA, Haryana within

three months time.

m Energy conservation measures like installation

of LED for lighting the areas outside the

building should be integral part of the project

design and should be in place before project

commissioning. Use of solar panels must be

adapted to the maximum energy conservation.

Agreed. CFL light will be used in

common areas like lift, corridors, and

staircase and service areas. CFLs will be

properly collected and disposed off/sent

for recycling as per the prevailing

guidelines/rules of the regulatory

authority to avoid mercury

contamination. Use of solar panels will

be adapted to the maximum extent

possible for energy conservation.

n The project proponent shall use zero ozone

depleting potential material in insulation,

refrigeration, air-conditioning and adhesive.

Project proponent shall also provide halon free

fire suppression system

Agreed: The project proponent will use

zero ozone depleting potential material

in insulation, refrigeration, air-

conditioning and adhesive. Project

proponent will also provide halon free

fire suppression system

o The solid waste generated should be properly

collected and segregated as per the

requirement of the MSW Rules, 2000 and as

amended from time to time. The bio-

degradable waste should be treated by

appropriate technology at the site ear-marked

within the project area and dry/inert solid

waste should be disposed off to the approved

sites for land filling after recovering recyclable

material.

Agreed: The solid waste generated will

be properly collected and segregated as

per the requirement of the MSW Rules,

2000 and as amended from time to time.

The bio-degradable waste should be

treated by appropriate technology at the

site ear-marked within the project area

and dry/inert solid waste should be

disposed off to the approved. Solid

waste management plan is enclosed as

Annexure-VIII

p The provision of the solar water heating Agreed. Provision of the solar water

system shall be as per norms specified by

HAREDA and shall be made operational in

each building block.

heating system will be as per norms

specified by HAREDA and will be made

operational in open spaces and signages.

q The traffic plan and the parking plan proposed

by the PP should be adhered to meticulously

with further scope of additional parking for

future requirement. There should be no traffic

congestion near the entry and exit points from

the roads adjoining the proposed project site.

Parking should be fully internalized and no

public space should be used.

Agreed. The traffic plan and the parking

plan will be adhered with further scope

of additional parking for future

requirement. Parking will be fully

internalized and no public space will be

used. Traffic circulation plan is

enclosed as Annexure-IX.

r The project shall be operationalized only once

HUDA will provide domestic water supply

system in the area.

Agreed, Project will be operationalized

once HUDA will provide domestic water

supply system in the area.

s Operation and maintenance of STP, solid

waste management and electrical

infrastructure pollution control measures shall

be ensured even after the completion of sale.

Operation and maintenance of STP,

solid waste management and electrical

infrastructure will be maintained by the

Environment Management Cell.

t Different type of wastes should be disposed

off as per provisions of municipal solid waste,

biomedical waste, hazardous waste, e waste,

batteries & plastic rules made under

Environment Protection Act, 1986.particularly

E-waste and battery waste shall be disposed of

as per existing E-waste Management rules

2011 and batteries Management rules 2001.

The project proponent should maintain a

collection center for E-waste and it should be

disposed of to only registered and authorized

dismantler/ recycler.

Agreed: Different type of wastes will be

disposed off as per provisions of

municipal solid waste, biomedical waste,

hazardous waste, e waste, batteries &

plastic rules made under Environment

Protection Act, 1986particularly E-waste

and battery waste will be disposed of as

per existing E-waste Management rules

2011 and batteries Management rules

2001. The project proponent will

maintain a collection Centre for E-waste

and it should be disposed of to only

registered and authorized dismantler/

recycler. Soild waste management plan

has been enclosed as Annexure-VIII

U. Standards for discharge of environment

pollutants as enshrined in various schedule of

rule 3 of Environment Protection Rule 1986

shall be strictly complied with.

Agreed, all the required standard

discharge will be followed for discharge

of environment pollutants as enshrined

in various schedule of rule 3 of

Environment Protection Rule 1986.

v The project proponent shall make provision

for guard pond and other provision for safety

against failure in the operation of wastewater

treatment facilities. The project proponent

shall also identify acceptable outfall for treated

effluents.

Agreed: The project proponent will

make provision for guard pond and other

provision for safety against failure in the

operation of wastewater treatment

facilities. The project proponent shall

also identify acceptable outfall for

treated effluents.

w. The project proponent shall ensure that the

stack height of DG sets is as per the CPCB

prescribed limits. Noise and emission level of

DG sets greater than 800KVA shall be as per

CPCB latestet standards for high capacity DG

sets.

Agreed: The project proponent will

ensure that the stack height of DG sets

is as per the CPCB prescribed limits.

Noise and emission level of DG sets

greater than 800KVA shall be as per

CPCB latest standards for high capacity

DG sets.

x All electric supply exceeding 100amp, 3 phase

shall maintain the power factor between 0.98

lag to 1 at the point of connection

Agreed: All electric supply exceeding

100amp, 3 phase will maintain the

power factor between 0.98 lag to 1 at the

point of connection

y The project proponent shall minimize heat

island effect through shading and reflective or

pervious surface instead of hard surface.

Agreed: The project proponent will

minimize heat island effect through

shading and reflective or pervious

surface instead of hard surface.

z The project proponent shall use only treated

water instead of fresh water for HVAC and

Agreed:

DG cooling. The project proponent shall also

use evaporative cooling technology and

double stage cooling system for HVAC in

order to reduce water consumption . further

temperature, relative humidity during summer

and winter seasons should be kept at optimal

level. Variable speed drive, best C0-efficient

of Performance, as well as optimal integrated

point load value and minimum outside fresh

air supply may be resorted for conservation of

power and water. Coil type cooling Dg Sets

shall be used for saving cooling water

consumption for water cooled Dg sets.

aa The project proponent shall ensure that the

transformer is constructed with high quality

grain oriented, low loss silicon steel and virgin

electrolyte grade copper.

The project proponent shall obtain

manufacturer’s certificate also for that.

Agreed: The project proponent will

ensure that the transformer is

constructed with high quality grain

oriented, low loss silicon steel and virgin

electrolyte grade copper.

The project proponent shall obtain

manufacturer’s certificate also for that.

ab Water supply shall be metered among different

users of utilities.

Agreed: Water supply will be metered

among different users of utilities.

ac The project proponent shall ensure that exit

velocity from the stack should be sufficiently

high. Stack shall be designed in such a way

that there is no stack down-water under any

meteorological conditions.

Agreed: The project proponent will

ensure that exit velocity from the stack

should be sufficiently high. Stack will be

designed in such a way that there is no

stack down-water under any

meteorological conditions.

ad The project proponent shall provide water

sprinkling system in the project area to

suppress the dust in addition to the already

Agreed: The project proponent will

provide water sprinkling system in the

project area to suppress the dust in

suggested mitigation measures in the Air

Environment Chapter of EMP

addition to the already suggested

mitigation measures in the Air

Environment Chapter of EMP.

Environment management Plan is

enclosed as Annexure-X.

PART-B GENERAL CONDITIONS

I The Project proponent shall ensure the

commitments made in Form-1, Form-1A,

EIA/EMP and other documents submitted to

the SEIAA for the protection of environment

and proposed environmental safeguards are

complied with in letter and spirit. In case of

contradiction between two or more documents

on any points, the most environmentally

friendly commitment on the point shall be

taken as commitment by project proponent.

Agreed: All safeguards mentioned in the

application will be implemented during

the construction phase and will be

implemented to the maximum possible

extent.

II Six monthly compliance reports should be

submitted to the Haryana State Pollution

Control Board and Regional Office, MOEF,

GOI, Northern Region, Chandigarh and a copy

to the SEIAA, Haryana

Agreed. Six monthly compliance reports

is being submitted to Haryana State

Pollution Control Board and Regional

Office, MOEF, GOI, Northern Region,

Chandigarh and a copy to the Regulatory

Authority of Haryana.

II STP outlet after stabilization and stack

emission shall be monitored monthly. Other

environmental parameters and green belt shall

be monitored on quarterly basis. After every

3(three) months, the project proponent shall

conduct environmental audit and shall take

corrective measures, if required, without any

delay.

Agreed: STP outlet after stabilization

and stack emission shall be monitored

monthly. Other environmental

parameters and green belt shall be

monitored on quarterly basis. After

every 3(three) months, the project

proponent shall conduct environmental

audit and shall take corrective measures,

if required, without any delay.

IV The SEIAA, Haryana reserves the right to add

additional safeguard measure subsequently, if

found necessary. Environmental Clearance

granted will be revoked if it is found that false

information has been given for getting

approval of this project. SEIAA reserves the

right to revoke the clearance if conditions

stipulated are not implemented to the 10

satisfaction of SEIAA/MoEF.

Agreed, The SEIAA Haryana reserves

the right to add additional safeguard

measure subsequently, if found

necessary.

V The Project proponent shall not violate any

judicial orders/ pronouncements issued by any

Court/Tribunal.

Agreed: There will be no violation of

any judicial order/ pronouncements

issued by the Hon’ble Supreme

Court/High Courts.

VI All other statutory clearances such as the

approvals for storage of diesel from Chief

Controller of Explosives, Fire Department,

Civil Aviation Department, Forest

Conservation Act, 1980 and Wildlife

(Protection) Act, 1972, PLPA, 1900, Forest

Act, 1927 etc. shall be obtained, as applicable

by project proponents from the respective

authorities prior to construction of the project

Agreed, all the required applicable

clearance will be taken from the

respective authority.

VII The project proponent should inform the

public that the project has been accorded

Environment Clearance by the SEIAA and

copies of the clearance letter are available with

the Haryana State Pollution Control Board &

SEIAA. This should be advertised within 7

days from the date of issue of the clearance

letter at least in two local newspaper that are

Agreed:

widely circulated in the region and the copy of

the same should be forwarded to SEIAA,

Haryana. A copy of Environment Clearance

conditions shall also be put on project

proponent web site for public awareness.

VIII Under the provision of Environment

(Protection) Act, 1986 legal action shall be

initiated against the project proponent if it was

found that construction of the project has been

started before obtaining prior environment

clearance.

Agreed, already environment clearance

vide letter no. SEIAA/HR/2012/492 has

been obtained. Copy of the same is

attached as Annexure-XI.

IX Any appeal against this Environment

Clearance shall lie with the National Green

Tribunal, if preferred, within a period of 30

days as prescribed under Section 16 of the

National Green Tribunal Act, 2010.

Not applicable.

X The project proponent shall put in place

Corporate Environment Policy as mentioned

in MoEF, GOI OM No. J-11013/41/2006-IA II

(I) dated 26.4.2012 within 3 month periods.

Latest Corporate Environment Policy should

be submitted to SEIAA within 3months of

issuance of this letter.

Agreed, Corporate Environment Responsibility as mentioned in MOEF, GOI OM No. J-11013/41/2006-IA II (I) dated 26.4.2012 will be justified.

That the safe and hygienic working

conditions will provide for the workers

during construction.

That the drinking water and sanitary

facilities of the type of mobile sulabh

shauchalayas has been provided during

construction phase.

First aid facilities will be maintained at

readily accessible place where necessary

appliances including sterilized cotton,

wool, etc. have been available.

Routine inspection, cleaning and

maintenance of the site will be occurred.

The corporate social responsibility is

enclosed as Annexure-XI

XI The fund ear marked for environment

protection measures should be kept in separate

account and should not be diverted for other

purposes and year wise expenditure shall be

reported to the SEIAA/ RO MoEF GoI under

rules prescribed for Environment Audit.

Agreed, The fund earmarked for

environment protection measures will be

kept in separate account and will not be

diverted for other purposes and year

wise expenditure will be reported to the

SEIAA/ RO MoEF GoI under rules

prescribed for Environment Audit.

XII The project proponent shall ensure the

compliance of Forest Department, Haryana

Notification no. S.O.121/PA2/1900/S.4/97

dated 28.11.1997.

Agreed: The project proponent will

ensure the compliance of Forest

Department, Haryana Notification no.

S.O.121/PA2/1900/S.4/97 dated

28.11.1997.

XIII The project proponent shall ensure that no

vehicle during construction/operation phase

enter the project premises without valid

‘Pollution Under Control’ certificate from

competent Authority.

Agreed: The project proponent will

ensure that no vehicle during

construction/operation phase enter the

project premises without valid ‘Pollution

Under Control’ certificate from

competent Authority.

XIV The project proponent shall seek prior

clearance from the forest department for

access to the commercial complex from

Highway.

Agreed: The project proponent will seek

prior clearance from the forest

department for access to the commercial

complex from Highway.

XV The project proponent is responsible for

compliance of all conditions on Environmental

Clearance letter and project proponent cannot

absolve himself/herself of the responsibility by

shifting it to any contractor engaged by project

Agreed: The project proponent is

responsible for compliance of all

conditions on Environmental Clearance

letter and project proponent cannot

absolve himself/herself of the

proponent. responsibility by shifting it to any

contractor engaged by project proponent.

XVI The project proponent shall seek fresh

Environmental clearance if at any stage there

is change in the planning of the proposed

project.

Agreed: The project proponent will seek

fresh Environmental clearance if at any

stage there is change in the planning of

the project.

XVII Besides the developer/applicant, the

responsibility to ensure the compliance of

Environmental Safeguards/ conditions

imposed in the Environmental Clearance letter

shall also lie on the licensee/licenses in whose

name/names the license/CLU has been granted

by the Town & Country Planning Department,

Haryana.

Agreed: Besides the developer/applicant,

the responsibility to ensure the

compliance of Environmental

Safeguards/ conditions imposed in the

Environmental Clearance letter shall

also lie on the licensee/licenses in whose

name/names the license/CLU has been

granted by the Town & Country

Planning Department, Haryana.

(B) COMPLIANCE TO ENVIRONMENTAL IMPACT ASSESSMENT GUIDANCE MANUAL 2010 OF MoEF

S. No. Points as per EIA Guidance Manual Status of Compliance

A. Air Environment

1. Wind erosion is a serious problem in areas

where the ground is virtually bare and devoid

of vegetation. Vegetation methods are found to

be most effective in the form of windbreaks

and shelterbelts.

Windbreaks and shelterbelts will be

provided to reduce wind erosion during

the construction phase.

2. Sprinkling of water and fine spray from

nozzles to suppress the dust.

Water sprinkling will be provided during

the construction phase.

S. No. Points as per EIA Guidance Manual Status of Compliance

3. On-Road-Inspection should be done for black

smoke generating machinery.

All the machineries will be use at site

having highest standard and of reputed

make and will comply with emission &

noise standards.

4. Promotion of use of cleaner fuel should be

done.

Ultra low sulphur diesel (ULSD) (sulphur

content less than 0.05%) will be used for

running of DG sets, vehicles and

construction machineries.

5. All DG sets should comply emission norms

notified by MoEF.

The DG sets will be installed such a way

that it will comply with the emission

norms notified by MoEF.

6. Vehicles having pollution under control

certificate may be allowed to ply.

It is ensured that all the vehicles used for

construction activities will have valid

Pollution under Check (PUC) certificates.

The vehicles without valid Pollution under

Check (PUC) certificate will be permit at

project site.

7. Use of covering sheet to prevent dust

dispersion at buildings and infrastructure sites,

which are being constructed.

Covering sheet will be use to prevent dust

dispersion during the construction phase.

8. Use of covering sheets should be done for

trucks to prevent dust dispersion from the

trucks, implemented by district offices.

Covering sheets will be used on trucks to

prevent dust dispersion from the trucks.

9. Paving is a more permanent solution to dust

control, suitable for longer duration projects.

High cost is the major drawback to paving.

During construction, access roads will be

covered with gravels to prevent dust

emission.

S. No. Points as per EIA Guidance Manual Status of Compliance

10. Reducing the speed of a vehicle to 20 kmph

can reduce emissions by a large extent. Speed

bumps are commonly used to ensure speed

reduction. In cases where speed reduction

cannot effectively reduce fugitive dust, it may

be necessary to divert traffic to nearby paved

areas.

Speed of the vehicles will be restricted by

erecting speed bumps at regular intervals

at project site and proper signage will be

provided for guided vehicular movement

and speed restrictions.

11. Material storages/ warehouses-Care should be

taken to keep all material storages adequately

covered and contained so that they are not

exposed to situations where winds on site

could lead to dust/ particulate emissions.

Fabrics and plastics for covering piles of soils

and debris is an effective means to reduce

fugitive dust.

Construction material will be stored in

storage yard.

B. Noise Environment

Setting up the barriers: National Building Code

2005 suggests that design solutions such as

barrier blocks should be used to reduce

external LA10 noise levels to at least 60-

70dB(A) at any point 1.0 m from any inward

looking façade.

The site will be enclosed with barricade

wall around the project boundary.

The DG will be installed within factory

made acoustic enclosure which conforms

to the permissible noise standards notified

by MOEF.

C. Water Environment

1. Curing water should be sprayed on concrete

structures; free flow of water should not be

allowed for curing.

STP treated water will be sprayed on

concrete structures.

S. No. Points as per EIA Guidance Manual Status of Compliance

2. After liberal curing on the first day, all

concrete structures should be painted with

curing chemical to save water. This will stop

daily water curing hence save water.

STP treated water will be used for curing.

3. Concrete structures should be covered with

thick cloth/gunny bags and then water should

be sprayed on them. This would avoid water

rebound and will ensure sustained and

complete curing.

Water will be sprayed on concrete

structures which will be covered with

thick cloth/gunny bags.

4. Ponds should be made using cement and sand

mortar to avoid water flowing away from the

flat surface while curing

Ponds will be made using cement and

sand mortar to avoid water flowing away

from the flat surface while curing.

5. Water ponding should be done on all sunken

slabs; this would also highlight the importance

of having an impervious formwork.

Agreed. Water ponding will be done on

all sunken slabs; this would also highlight

the importance of having an impervious

formwork.

(C) COMPLIANCE TO NGT ORDER DATED 10.04.2015 RELATED TO

CONSTRUCTION

S. No. NGT Order dated 10.04.2015 Status of Compliance

1. Every builder or owner shall put tarpaulin on

scaffolding around the area of construction and

the building. No person including builder,

owner can be permitted to store any

construction material particularly sand on any

part of the street, roads in any colony.

Tarpaulin covers will be provided around

the area of construction, wherever

required. No construction materials such

as cement, sand and aggregates will be

stored at site.

S. No. NGT Order dated 10.04.2015 Status of Compliance

2. The construction material of any kind that is

stored in the site will be fully covered in all

respects so that it does not disperse in the Air

in any form.

Construction material on site will be fully

covered.

3. All the construction material and debris shall

be carried in the trucks or other vehicles which

are fully covered and protected so as to ensure

that the construction debris or the construction

material does not get dispersed into the air or

atmosphere, in any form whatsoever.

The trucks carrying construction materials

and debris will be suitably covered by

tarpaulin and plastic sheets.

4. The dust emissions from the construction site

should be completely controlled and all

precautions taken in that behalf.

All necessary precautions will be adopted

to control the dust emissions. Water

sprinkling at site has been done.

5. The vehicles carrying construction material

and construction debris of any kind should be

cleaned before it is permitted to ply on the road

after unloading of such material.

Vehicles carrying construction material

and construction debris will be cleaned

before it will be permitted to ply on the

road after unloading of such material.

6. Every worker working on the construction site

and involved in loading, unloading and

carriage of construction material and

construction debris shall be provided with

mask to prevent inhalation of dust particles.

All safety measures will be taken.

7. Every owner and or builder shall be under

obligation to provide all medical help,

investigation and treatment to the workers

involved in the construction of building and

carry of construction material and debris

relatable to dust emission.

First aid facility will be provided at the

construction site.

S. No. NGT Order dated 10.04.2015 Status of Compliance

8. It shall be the responsibility of every builder to

transport construction material and debris

waste to construction site, dumping site or any

other place in accordance with rules and in

terms of this order.

Construction material and debris waste

will be disposed off to construction site,

dumping site or any other place in

accordance with rules and in terms of this

order.

9. All to take appropriate measures and to ensure

that the terms and conditions of the earlier

order and these orders should strictly comply

with by fixing sprinklers, creations of green air

barriers.

Regular sprinkling of water will be carried

out at site.

10. Compulsory use of wet jet in grinding and

stone cutting.

Wet jet in grinding and stone cutting will

be used.

11. Wind breaking walls around construction site. Wind breaking walls will be provided

around the construction site.

12. All the builders who are building commercial,

residential complexes which are covered under

the EIA Notification of 2006 shall provide

green belt around the building that they

construct. All Authorities shall ensure that such

green belts are in existence prior to issuance of

occupancy certificate.

Green area will be developed as per

approved building plan.