Viet Nam: Urban Environment and Climate Change Adaptation ...
Transcript of Viet Nam: Urban Environment and Climate Change Adaptation ...
1
Environmental Monitoring Report
Semestral Report Period: January to June 2021 October 2021
Viet Nam: Urban Environment and Climate Change Adaptation Project
Dong Hoi Subproject
Prepared by Dong Hoi City Environment and Climate Change Project Management Unit for
the Asian Development Bank.
2
CURRENCY EQUIVALENTS
(as of August 2021)
Currency Unit - Viet Nam Dong (VND)
VND1.00 = $ 0.00004
$1.00 = VND 22,797.7
ABBREVIATIONS
ADB - Asian Development Bank
AH/AP - Affected Household/ Affected People
BOD5 - Biochemical oxygen demand
CBOs - Community-based organizations
cEMP - Environmental Management Plan of Contractor
COD - Chemical oxygen demand
CPC/PPC - Commune People's Committee/ Provincial People's Committee
CSC - Construction Supervision Consultant
DONRE - Department of Natural Resources and Environment
DOT - Department of Transportation
DPI - Department of Planning and Investment
EHSC - Environment, Health, Safety and officer of the Contractor
EMP - Environmental Management Plan
GoV - Government
IMO - Independent Monitoring Organization
IEE - Initial Environmental Examination
M&E - Monitoring and Evaluation
PMU - Project Management Unit
QCVN - Vietnamese Quality Standard
RP - Resettlement Plan
SEMP - Site Environmental Monitoring Plan
TOR - Terms or References
TSS - Total suspended solids
WEIGHTS AND MEASURES
dB(A) - Decibel (weighted average)
ha - hectare
kg/d - kilogram per day
km - kilometer
km2 - square kilometer
3
m - meter
m2 - square meter
m3 - cubic meter
m3 /d - cubic meters per day
m3 /s - cubic meters per second
mg/m3 - milligrams per cubic meter
mm - millimeter
NOTES
In this report, "$" refers to US dollars.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
4
TABLE OF CONTENTS
I. Introduction 7
A. Project background 7
B. Project Implementation Progress 8
II. Institutional Setup and Responsibilities for EMP Implementation and Supervision 11
A. Institutional setup for Environmental management 11
B. Incorporation of Environmental Requirements into Project Contractual Arrangements 16
III. Compliance with the environmental covenants of the project 17
IV. Environmental impacts mitigation measures implemented in the reporting period 23
A. The compliance status with environmental requirements during the ADB Mission 23
B. Monitoring of the EMP Compliance by PISC1 25
C. Environmental mitigations measures implemented by the contractor 26
V. Environmental impact monitoring 45
A. Monitoring plan and responsibilities 45
B. Environmental monitoring component, number of samplings and monitoring methods 46
C. Monitoring results 49
VI. Public consultation, grievance redress mechanism 57
A. Public consultation and information disclosure 57
B. Grievance redress mechanism 58
VII. Capacity building activities 59
VIII. KEY ENVIRONMENTAL ISSUES 60
A. Key identified environmental issues and corrective actions in the previous reporting period 60
B. Environmental issues should be resolved in the first six months of 2021. 63
IX. Conclusions and recommendations 67
A. Overall Progress of Implementation of Environmental Management Measures 67
B. Proposed actions 68
APPENDIXES
5
LIST OF TABLES
Table 1: Project Implementation Progress ................................................................................ 7
Table 2: Institutional Responsibilities for Environmental Management ..................................... 10
Table 3: List of Personnel for EMP implementation of the Project ............................................ 13
Table 4. Project environmental reporting system assessment ................................................. 14
Table 5. The schedule of updating EMPs ............................................................................... 15
Table 6: Status of Compliance with ADB Loan Covenants ...................................................... 16
Table 7: Environmental issues have been resolved as required by ADB mission ..................... 21
Table 8. Assessment on the EMP Compliance ....................................................................... 25
Table 9: Sampling locations of environmental monitoring ........................................................ 42
Table 10: Results of air quality monitoring .............................................................................. 46
Table 11: Results of surface water quality monitoring ............................................................. 53
Table 12: Key environmental issues in the previous reporting period ....................................... 57
Table 13: Key environmental issues in this reporting period .................................................... 60
LIST OF FIGURES
Figure 1: Organization structure for implementing Environmental management of the Project
Figure 2: Map of sampling locations
Figure 3: Comparison of TPS in March and June 2021 with the background environment in May
2018 and QCVN 05:/2013/BTNMT
Figure 4: Comparison of NO2 in March and June 2021 with the background environment in May
2018 and QCVN 05:/2013/BTNMT
Figure 5: Comparison of SO2 in March and June 2021 with the background environment in May
2018 and QCVN 05:/2013/BTNMT
Figure 7: Comparison of noise in March and June 2021 with background environment in May
2018 and QCVN 05:/2013/BTNMT
Figure 8: Comparison of surface water monitoring results in March and June 2021 with the
background environment
Figure 9: Training on ADB environmental safeguard policy for the PMU staff and contractors
6
I. Introduction
A. Project background
1. Objectives of the Project
The Urban Environment and Climate Change Adaptation Project funded by ADB will construct and upgrade the urban environmental infrastructures, stormwater and wastewater management, and flood control in order to minimize environmental pollution, improve urban environment and climate change adaption for the two coastal cities, namely Dong Hoi (Quang Binh Province) and Hoi An (Quang Nam Province). The objective of the project is to increase people's accessibility to climate change adapting infrastructure. The project was approved by ADB Board on 27 November 2015. The loan agreement, project agreement, and grant agreement were signed on 25 March 2017 and became effective on 17 July 2017.
2. Basic information of Dong Hoi Project
- Project title: Urban Environment and Climate Change Adaptation Project - Dong Hoi City.
- Funding source: Asian Development Bank (ADB).
- Executing agency (EA): People's Committee of Quang Binh province.
- Project Owner/Implementing Agency (IA): People's Committee of Quang Binh province.
- Total investment: 38,800,000 USD (of which 31,739,000 USD of ADB loan and co-
financing by ADB and 7,070,000 USD counterpart funds of the Government of Vietnam).
- Overall project duration: 2017 - 2022.
- Location of the project: Dong Hoi city, Quang Binh province.
3. Components and main packages of the Project
Component 1: Improvement of wastewater management for the city center.
This component focuses on the construction of wastewater system for the center city in Dong Hoi
city, which includes wastewater drainage system, tertiary sewer system, and 01 lift pumping
station. This component includes package DH/W1.
Component 2: Development of climate change resilient infrastructure for Bao Ninh
Peninsula.
This component focuses on the construction of a new Vertical Road No. 3 with 36m in width from
Km0 to Km2,919 and 03 Horizontal roads connecting the new route with the old one (Vo Nguyen
Giap street); construction of rainwater drainage system D1500 and wastewater drainage route;
construction of 03 pumping stations for levelling and 01 pumping station for transferring
wastewater; construction of 02 regulating lakes; construction of medium voltage lines, transformer
stations, and attached control electrical cabinets. This component is divided into four (4) packages
DH/W3, DH/W4, DH/W5, DH/W8.
Particularly, package DH/G1 provides equipment and materials for all pumping stations under the
two above-mentioned components.
Component 3: Management of flood and other infrastructure.
In this component, the implementation of flood management measures and construction of other
infrastructure to cope with climate change adaptation will eliminate economic, social and
environmental damage due to floods, riverbank/ coastal erosion. The component 3 is divided into
two (2) packages DH/W7, DH/C1.
Component 4: Site clearance and Resettlement.
7
The main features of this component include: carry out the graves and architectural objects
relocation to create ground for the construction process and resettlement process for the local
people soon stabilize their life as well as develop the local economy.
Component 5: Project Management and Capacity Building.
This project will improve the capacity of project management, implementation and operation
agencies and raise community awareness of climate change. This component includes three (03)
packages:
- Package DH/PISC1: Project implementation support and capacity development.
- Package DH/PISC2: Independent Auditing Consultant.
- Package DH/PISC3: External Resettlement Monitoring
B. Project Implementation Progress
By June 2021, most of the project’s packages have been in construction process. The Project implementation progress is summarized in table 1 as follows:
Table 1: Project Implementation Progress
No Name of package Date of
contract Construction unit
Project Implementation
Progress
1
Package DH/W1: Improvement of wastewater management for center city
28/05/2020
Vietnam Water and Environment Investment Corporation Joint Stock Company
10,27%
2
Package DH/W3: Bao Ninh wastewater
31/01/2020
Vietnam Water and Environment Investment Corporation Joint Stock Company
41,50%
3
Package DH/W4: Horizontal Road No. 3 (36 M: KM1.387-2.919)
30/7/2019
Joint Venture of Tien Dat Construction Company Limited, Long Thanh Construction Joint Stock Company, 688 Consulting Joint Stock Company
11,2%
4 Package DH/W5: Vertical roads (03 routes) 16/10/2020
Infrastructure Development and Construction Joint Stock Company
14,57%
5 Package DH/W8: Horizontal Road No. 3 (36 M: KM0-1.387)
31/10/2019 471 Joint Stock Company
26,82%
Main construction activities during the reporting period
• DH/W1: The contractor implements the construction of the following items:
- Construction of wastewater drainage route R3 No. T3, T17, T17C in Bac Ly ward; - Reinstatement of the asphalt road pavement on routes No. T1, No. T1A on Hoang Xuan
Han Street; reinstatement of cement concrete road pavement on routes No. T10, T14 on Dao Tan street, Bac Ly ward, route No. T33
8
- Construction of wastewater routes No. T14, T14A, Bac Ly ward.
• DH/W3:
The contractor implements the construction of the following items: - Construction of wastewater drainage route, installation of manholes on Vo Nguyen Giap
street: 3F, route No. 3. - Installation of sewer pipes and manholes for drainage route No. 1, 1B, 1C, 3, 3A, 3E on
Vo Nguyen Giap street;
• DH/W4 The contractor implements the construction of the following items:
- Utility trench No. 4, casting manhole components for rainwater drainage and wastewater drainage, box culvert 2x2m
- Installation of sewer pipes D1500 from T61-T65, construction of ditches - Installation of sewer pipes D1500 from manholes T57-T61, P72-P73, construction of
ditches connecting regulating lake No. 1 and No. 2, construction of the regulating lake No. 1.
- Drainage ditch from pile 13 to TD 2 with the length of 130m; installation of manholes for drainage route No. 2E, 2F
- Tiling work to reinstate the utility trench No. 4
• DH/W5:
The contractor implements the construction of the following items:
- Utility trench of the vertical road No. 2; - Installation of rainwater drainage pipe D800 of vertical route No. 3, rainwater drainage,
wastewater drainage, construction of utility trench route No. 2 - Embankment K95, K98 on the vertical road No. 5, route No. 1,2,3 - Casting culvert base, manhole
• DH/W8:
The contractor implements the construction of the following items:
- Construction and reinstatement of asphalt pavement of route R3 No.5 on Nguyen Thi Dinh street; asphalt coating to reinstate the wastewater drainage route R3 No. 8, 8B
- Construction of route R3 No. 6,7 on Nguyen Thi Dinh street; rainwater drainage route at the section P20-P26, P34-P37, T18-T27; wastewater drainage route No. 2, 2C; route R3 No. 5, 6, 7, 8, 8B, wastewater drainage route R3 No.4A, installation of rainwater drainage pipe on right side of the section Km0.335-Km0.557
- Construction of utility trench Ht22-Ht29; - Casting components - Embankment K98, constructing the base layer of base course at section Km0.759-
Km1.318,
Main construction activities in the next reporting period
• DH/W1: - The contractor continues to implement the construction of drainage routes in Bac Ly, Nam
Ly and Phu Hai wards ▪ In Bac Ly ward: Route No.17A, 17B, 14B, 14C, 14 (Pile 14.6 to Pile 14.13), 12, 12A,
15, 16, 04, 2A, 2B, 2C, 2 with an estimated length of 1,588m ▪ In Nam Ly ward: Construction of the routes No. 15, 15A, 07, 09, 10, 16, 1, 11, 12, 21,
23, 31, 38, 38B, 21A, 01, 01B, 01A, 02 with a total length of about 2,400m ▪ In Phu Hai ward: Construction of a pressurized wastewater collection system,
installation of sewer pipe HDPE D160, PN10 with a total length of about 2,200m, pumping station No. 04.
• DH/W3:
9
Construction of rainwater route No. H13 on the sidewalk of Tran Hung Dao street with a total length of 222m, wastewater drainage routes No. 3, 1B, 1, 1C, 35, 3E, 1A with a total length of 2,356m, pumping stations No. 01, 03, 03.
• DH/W4:
Complete the construction of utility trench on the vertical road No. 4, continue the construction and installation of the surface water drainage system, the wastewater drainage route, the ditch system for the construction of the embankment of the regulating lake No. 1.
• DH/W5:
Construction of the rainwater drainage system, wastewater drainage system, utility trench system on the vertical road No. 1, No. 2, No. 3 and the power system on the vertical road No. 2
• DH/W8:
Construction of aggregate subbase, aggregate base, utility trench, rainwater drainage system, wastewater drainage system at the chainage Km0+330,51÷Km0+557,76, and Km0+759,34 ÷ Km1+387,33.
II. Institutional Setup and Responsibilities for EMP Implementation and Supervision
A. Institutional setup for Environmental management
The Institutional Relations for Environmental Management has been determined since the EMP reporting and shown in Table 2.
Table 2: Institutional Responsibilities for Environmental Management
Name of organization
Institutional Responsibilities for Environmental Management
Status of compliance
PMU - Take responsibilities for supervising the overall project implementation, including the status environmental compliance. The PMU will have the ultimate responsibility for the implementation of the EIA and environmental performance of the project during the construction phase. - Specifically, the PMU will: (i) closely coordinate with local authorities in the participation of communities in project preparation and implementation; (ii) monitor and supervise the implementation of the Environmental-Social Management Plan (ESMP) including the integration of the ESMP into detailed technical designs, bidding documents and contract; (iii) ensure that an environmental management system will be established and operated properly; (iv) report the implementation of the ESMP to DONRE and ADB
Fully complied with
- Ensure that all environmental requirements are considered in the detailed technical design, bidding documents and contracts of contractors;
- Prepare semi-annual environmental reports of the project to submit to ADB for consideration and approval.
- Assigned the environmental officer of PMU to perform relevant tasks
Environmental Officer of PMU
- Assign an environmental officer who resolves environmental issues of the Project, oversees the implementation of the environmental
Fully complied with
- Assigned Ms Dao Ngoc Phuong (environmental
10
Name of organization
Institutional Responsibilities for Environmental Management
Status of compliance
safeguards policy of ADB and Vietnam throughout the Project.
- Assist the PMU leadership in solutions for environmental issues to meet the requirements of ADB environmental safety policies and requirements under Vietnamese regulations
engineer) as the environmental officer.
- Monthly and quarterly assess the EMP compliance of the Project by reviewing and approving labor safety, environmental sanitation reports submitted by PISC1.
Construction Supervision Consultant (CSC) / Environmental Specialist of PISC1 (ES)
- Take responsibility for overseeing construction activities and ensure that the Contractor has fulfilled the contract requirements. Environmental Specialist (ES) of the Construction Supervision Consultants (CSC), is responsible for supervising and monitoring construction activities and ensuring that the Contractor fulfills the requirements stated in the contract with the Project Owner (in the approved EIA and EMP report).
Periodically report the results of environmental monitoring to the PMU.
Fully complied with
- The PISC1 consultant and environmental expert daily supervise the contractor’s EMP compliance during the construction of the package of the Project.
Submit monthly and quarterly reports on labor safety and environmental sanitation to the PMU.
- Assist the PMU to prepare the semi-annual environmental monitoring report to submit to ADB for approval
Contractor/ EHSC
- Prepare the Environmental and Social Management Plan - Commit to sufficiently implement the contents of environmental protection in the approved EIA report. Strictly and fully implement environmental impacts mitigation measures during construction. Under the supervision of the Environmental Monitoring Officer and adjust or strengthen measures when required.
- Actively interact with local people and take actions to avoid disturbance during the construction process.
Complied with
The contractor’s EMP was approved. The contractor assigned an environmental officer to perform this task (list of personnel is presented in table 3).
The contractor is always willing to listening to local people’s opinions or complaints on the environment during the construction of the workers’ camp.
Environmental monitoring unit
- The contract signs a contract with this unit to monitor environmental components and identify emission sources during the construction process of the Project.
Complied with
During this reporting period, the contractor signed a contract with the environmental monitoring unit to carry out environmental monitoring in March and June 2021.
11
Name of organization
Institutional Responsibilities for Environmental Management
Status of compliance
Local community
Community: According to Vietnamese practice, the community has the right and responsibility for regularly monitoring environmental activities during construction to ensure that their rights and safety are sufficiently guaranteed, and mitigation measures are taken effectively by contractor and PMU. If an unexpected incident occurs, they will report it to the supervision consultant and the PMU
Fully complied with
During the reporting period, there have been no complaints of the local community on environment during the construction process.
Provincial People's Committee (PPC), Quang Binh Department of Natural Resources and Environment
(DONRE)
Supervise the Project implementation based on the recommendations of DONRE and PMU to ensure the compliance with the Government policies and regulations.
DONRE is responsible for supervising the compliance with the environmental requirements.
Fully complied with
The EIA of the Project was approved by PPC of Quang Binh according to the Decision No. 2131/QD-UBND dated June 28, 2018.
Organizational structure of environmental management
The current organization structure for implementing Environmental management of the Project is illustrated in Figure 1.
12
Figure 1: Organization structure for implementing Environmental management of the Project
Personnel for Environmental Management
Table 3: List of Personnel for EMP implementation of the Project
Name of organizati
on
Name Educational background
Position Contact
PMU/ ESO
Đào Ngọc Phương Environmental engineer
Environmental management officer of PMU
PISC1/ES Nguyễn Văn Bảy Bachelor of Environment
Environmental specialist
EHSC Lê Minh Thành EHSC of DH/W1 [email protected]
Construction sites
Environmental Safeguards Officer ESO (of the PMU)
Community Supervision
Required mitigation measures/actions
Monitor on environmental
issues
Coordinate Information
Supervision of environmental
issues
Report
Environmental Specialist
ES
Construction Supervision Consultant
CSC
Construction Contractor
Environmental health
and safety consultants
(EHSC)
- MONRE - Quang Binh DONRE - Other relevant agencies
Periodic Monitoring on environmental quality
ENVIRONMENT & CLIMATE CHANGE PMU
ADB
Environmental
monitoring unit
13
Name of organizati
on
Name Educational background
Position Contact
Nguyễn Văn Thắng EHSC of DH/W3 [email protected]
Hoàng Nguyên Lưu EHSC of DH/W4 [email protected]
Bùi Thế Tài EHSC of DH/W5 hoangnhan2211@ gmail.com
Bùi Hữu Hùng EHSC of DH/W8 [email protected]
Environmental Reporting System
In accordance with the approved EMP, monthly monitoring reports on EMP compliance as well as semi-annual environmental monitoring reports must be prepared by relevant stakeholders. The detail status of current reporting is described in Table 4.
Table 4. Project environmental reporting system assessment
Agency Required reports in approved IEE
To Whom Current status
of reportage
Construction contractors
Monthly monitoring report PISC1
Complied with:
The contractors have submitted the monthly health safety and environment report to the PISC1
PISC1 Monthly monitoring report
Dong Hoi PMU
Complied with:
PISC1 consultant have submitted the monthly and quarterly environment, health and safety and semi-annual environmental monitoring reports in 2020 to PMU.
Dong Hoi PMU Semi-annual monitoring report
ADB
Complied with:
The semi-annual environmental monitoring reports in 2020 have been submitted to ADB for review and approval.
B. Incorporation of Environmental Requirements into Project Contractual Arrangements As required by ADB, the original EMP must be updated based on the detail design of each project
package and the updated EMPs should be incorporated in the biding documents instead of the
original EMP. The contractors are responsible for preparing their own CEMP that will include a
COVID 19 risks management plan. The succeeding table showing the schedule of updating uEMP,
preparing CEMP and COVID 19 risks management plan.
Table 5. The schedule of updating EMPs
No Package Status of updating EMPs
Status of preparing CEMPs
Status of preparing COVID 19 risks management plan
14
1 DH/W1 Approved by ADB in March 2019
CEMP was submitted and approved on August 12, 2020.
The contractor is preparing the Covid-19 prevention plan to submit to the PMU for approval.
2 DH/W3 Approved by ADB in January 2019
CEMP was submitted and approved on June 18, 2020.
The contractor is preparing the Covid-19 prevention plan to submit to the PMU for approval.
3 DH/W4 Approved by ADB in September 2018
CEMP was submitted and approved on June 16,2020
The contractor is preparing the Covid-19 prevention plan to submit to the PMU for approval.
4 DH/W5 Approved by ADB in September 2018
CEMP was submitted and approved November 10, 2020
The contractor is preparing the Covid-19 prevention plan to submit to the PMU for approval.
5 DH/W8 Approved by ADB in January 2019
CEMP was submitted and approved on June 16, 2020
The contractor is preparing the Covid-19 prevention plan to submit to the PMU for approval.
During this reporting period, all of packages are developing Covid-19 prevention plans to submit to the PMU for approval. Besides, during the construction process, the contractors also seriously take measures to prevent Covid-19 epidemic including wearing masks when working, washing hands with hand sanitizer, checking the temperature daily for workers, keeping a safe distance on the construction site as recommended by the Government, the Ministry of Health and local authorities. Contractors should post the Covid-19 prevention posters at the workers’ camp and construction sites. PISC1 supervises the contractors' compliance with Covid-19 prevention measures and promptly reports any non-compliance cases to PMU. PISC1 Consultant and PMU also strictly implement the local Covid-19 prevention recommendations such as providing hand sanitizer, checking temperature daily for the staff, officers, and guests to the office, wearing facemasks and arranging staff to work from home…. As of the end of this reporting period, there have been no cases of COVID-19 infection in the project units.
III. Compliance with the environmental covenants of the project The status of compliance with Environmental Covenants of the Project is presented in the table
below.
Table 6: Status of Compliance with ADB Loan Covenants
Para. Content Status of compliance
11 Environment The Borrower shall ensure and shall cause the Project Executive Agencies and the Project
Complied with
15
Para. Content Status of compliance
Implementing Agencies to ensure that the preparation, design, construction, implementation, operation and decommissioning of the Project and all Project facilities comply with: (a) all applicable laws and regulations of the Borrower relating to environment, health and safety; (b) the Environmental Safeguards; and;
(c) all measures and requirements set forth in the IEEs, the EMPs, and any corrective or preventative actions set forth (i) in a Safeguards Monitoring Report or (ii) which are subsequently agreed between ADB and each Project Executing Agency (on behalf of itself and the Borrower)
a. The EIA of the project was approved by Quang Binh PPC in Decision No. 2131/QD-UBND dated June 28, 2018. The contractor is required to comply with all applicable labor laws and core labor standards during construction. b.
The preparation and approval of uEMP is in compliance with the requirements. The EIA report of the project was approved according to Decision No. 1231/QD-UBND dated June 28, 2018; uEMPs of package DH/W4 and DH/W5 were prepared and approved in September 2018; uEMPs of package DH/W3 and DH/W8 were approved in January 2019; uEMP of package DH/W1 was approved in March 2019. The uEMPs have been included in the bidding documents and the contract with the contractors. Contractors prepare the Environmental Management Plan and submit it to the the PISC1 consultant and the PMU for approval prior to the commencement of construction. c. The Monthly Safeguard Monitoring Reports of contractors are submitted to the PISC1 consultant. The consultant prepares a Quarterly Safeguard Monitoring Reports for the PMU and assists the PMU in preparing the Semi-annual Safeguard Monitoring Reports to submit to ADB. Corrective actions at the request of the PISC1 consultant, PMU or ADB have been implemented.
16
Safeguards – Related Provisions in Bidding Documents and Works Contracts: The Borrower shall cause the Project Executing Agencies and the Project Implementing Agencies to ensure that all bidding documents and contracts for Works contain provisions that require contractors to: (a) comply with the measures relevant to the contractor set forth in the IEE, the EMP and the RPs (to the extent they concern impacts on the
Fully complied with
The requirements (a, b, c, d, e) are clearly presented in the bidding documents as well as the civil contract of the contractor. (a) the requirement (a) was provided in SCC 74 (b) the requirement (b) was provided in SCC 74 (c) the requirement (c) was provided in SCC 40.1
16
Para. Content Status of compliance
respective affected people under the Environmental Safeguards and the Involuntary Resettlement Safeguards during construction), and (i) any corrective or preventative actions set forth in a Safeguards Monitoring Report; or (ii) which are subsequently agreed between ADB and each Project Executive Agency (on behalf of itself and the Borrower); (b) make available a budget for all such environmental and social measures; (c) provide the Borrower, the Project Executing Agencies, and ADB with a written notice of any unanticipated environmental, resettlement or indigenous peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEEs, the EMPs and the RPs; (d) adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction; and
(e) reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction.
(d) the requirement (d) was provided in SCC 22.1 (e) the requirement (e) was provided in SCC 63.1.
17
Safeguards Monitoring and Reporting The Borrower shall cause the relevant Project Executing Agency to: (a) submit Safeguards Monitoring Reports to ADB (i) in respect of implementation of and compliance with Environmental Safeguards and the EMPs, semi-annually during the construction and the implementation of the Project and the EMPs, and thereafter annually during operation, until the issuance of ADB’s Project completion report unless a longer period is agreed in the EMPs; and (ii) in respect of implementation of and compliance with Involuntary Resettlement Safeguards and of the RPs, semi-annually during the implementation of the Project, and the RPs until the issuance of ADB’s Project completion report unless a longer period is agreed in the RPs; and disclose relevant information from such reports to the respective affected people under the Environmental Safeguards, and the Involuntary Resettlement Safeguards promptly upon submission;
Fully complied with a. SEMR for the last six months of 2019 and SEMRs of 2020 have been submitted to ADB and approved b. Reported the current status and impacts of Covid-19 epidemic to ADB. The Covid-19 prevention plan of the contractors is being implemented to submit for approval. c. Presented in the Chapter IV of this report
17
Para. Content Status of compliance
(b) if any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the Project that were not considered in the IEEs, the EMPs, and the RPs, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan. c) report any actual or potential breach of compliance with the measures and requirements set forth in the EMPs or the RPs promptly after becoming aware of the breach
19
Grievance Redress Mechanism The Borrower shall ensure that separate safeguards grievance redress mechanisms acceptable to ADB are established in accordance with the provisions of the IEEs and the RPs at the PMUs and within the timeframes specified in the relevant IEEs and the RPs to consider safeguards complaints. The Borrower shall further ensure that within three months of the Effective Date, a grievance redress mechanism, acceptable to ADB, is established and a task force is functioning effectively to review and document eligible complaints of Project stakeholders related to the Project, any of the service providers, any person responsible for carrying out the Project, complaints on misuse of funds and other irregularities as well as gender issues. The grievance redress mechanism and the task force shall (i) proactively address grievances; (ii) provide the complainants with notice of the chosen mechanism/action; and
(iii) prepare periodic reports to summarize (1) the number of complaints received and resolved; (2) selected actions; and (3) final outcomes of the grievances and make these reports available to ADB upon request
Fully complied with - The Grievance Redress Mechanism of the Project presented in IEE and uEMP was approved by ADB.
- The Grievance Redress Committee was established to perform the tasks (i, ii, iii) - (1, 2, 3) is presented in Chapter VI. B of this report.
23
Health risks and Covid-19 epidemic In coordination with the local health center, the Borrower shall cause the Project Executing Agencies and the Project Implementing Agencies to ensure that: (a) training for construction workers and local communities on HIV/AIDS prevention and control methods is carried out;
Partly complied with a. As of this reporting period, the contractor has not conducted trainings for HIV/AIDS prevention and control measures for workers and local community. b, c. Currently, the Covid-19 pandemic has negatively affected the human health. At all construction sites, there have been
18
Para. Content Status of compliance
(b) the Works contractors disseminate information and conduct awareness training on the risks and preventive measures of HIV/AIDS and other communicable diseases to their employees, temporary laborers and family members, and subcontractors during Project implementation;
(c) measures to prevent other communicable diseases are implemented, within the construction sites, as specified in the IEEs; and (d) the requirements of sub-clauses (b) and (c) are included in the Works contracts, monitored and reported quarterly to ADB.
posters on Covid-19, some activities including daily temperature checking, sanitizer handwash, wearing facemask are being seriously implemented in this reporting period. d. The requirements (a, b, c) are clarified in DKCT 24.2.
24
Labor standards The Borrower shall, and shall cause the Project Executing Agencies and the Project Implementing Agencies to ensure that the construction contractors: (a) provide timely payment of wages and safe working conditions to all workers; (b) pay equal wages to female and male employees for equivalent labor; (c) provide safe and healthy working conditions for both male and female workers; (d) do not employ child labor as required by the relevant laws and regulations of the Borrower; (e) maximize the employment of local people, particularly women and ethnic minorities, who meet the job and efficiency requirements for Project construction, operation and maintenance; and
(f) provide such workers with adequate on-the- job training and safety training
Complied with
a. The contractors have timely provided payment of wages for workers. b. The contractors have pay equal wages to female and male employees for equivalent labor c. The personal protective equipment including clothes, shoes, hats, gloves, masks, antiseptic handwash are sufficiently provided for workers. d. All contractors do not employ child labor, the PMU and PISC1 have strictly monitored the contractor's labor contract with the workers to ensure that the contractors comply with this one. e. The Contractors mainly hire local labor, there are some suitable jobs that hire women to do
f. The contractor has implemented training on labor safety for the workers.
IV. Environmental impacts mitigation measures implemented in the reporting period
A. The compliance status with environmental requirements during the ADB Mission
During the review in December 2020, ADB identified a number of environmental issues that should be resolved. PMU and PISC1 consultant have requested contractors to implement these measures and have been recognized by ADB during the monitoring period in May 2021. Besides, some assessments of the ADB mission team in May 2021 have also been taken into consideration and adjusted by PMU and PISC. The detailed measures are presented in the following Table.
Table 7: Environmental issues have been resolved as required by ADB mission
No. Issues during ADB mission in
December 2020
Corrective actions Photos at the site
19
1 All packages lack the diary of environment, health and labor safety.
PISC1 Consultant have provided the new form of the diary including the environmental implementation and Covid-19 management.
The contractors have written the construction daily diary.
Daily site diary of the contractors
2 The camps and construction sites of the packages have not been well implemented measures to prevent the Covid-19 epidemic, including lack of posters Covid-19 prevention, daily temperature checking for staff and workers, hand sanitizer, as well as medical masks
Contractors have posted COVID-19 prevention posters, provided hand sanitizer and masks, and checked daily workers' temperatures.
PISC1 regularly supervise and inspect contractors' implementation of COVID-19 prevention
Poster about 5K, facemask, hand sanitizer at the workers’ camp
20
Daily temperature monitoring dairy for workers
Fire prevention and fighting signs
3 The information board is insufficiently updated, particularly the contact address of the PMU, contractor and the PISC1 supervision consultant.
The contractors have updated the information board including contact address of the PMU, contractor and the PISC1 supervision consultant.
The information board is now sufficiently updated.
4 The contractor of DH/W8 has removed the temporary excavated sand on the route to avoid the air pollution that affects the households living near the river.
The contractor of DH/W8 has removed the temporary excavated sand on the route; as a result, the phenomenon of sand flying causing air pollution has been mitigated.
There is no longer excavated sand on the route
Besides, the ADB mission expressed concern about the quality of two semi-annual environmental monitoring reports in 2020. The mission requested the PMU to work with PISC1 Consultant to mobilize qualified consultants in order to complete the reports and resubmit to ADB by May 31, 2021. PMU coordinated with PISC1 Consultant on the revision of the reports. In May 2021, the two above reports were updated and submitted to ADB for approval.
B. Monitoring of the EMP Compliance by PISC1
PISC1 daily supervises the contractors' compliance with EPM on site as well as the monthly environmental reports. In terms of the environmental and labor safety issues that fail to meet the requirements, PISC1 will issue the official letter to request for resolution. In this reporting period, PISC1 has issued official letter No. RHDHV/PICS1/210630.1 dated June 30, 2021 requesting the contractor of package DH/W1, DH/W3 to take measures to ensure traffic safety. The letter is attached in Appendix 1 of the report.
21
The contractors frequently report the status of compliance with EMP and environmental impacts mitigation measures to the PMU in monthly, quarterly, and semi-annual environmental reports.
In the context of social distancing due to the COVID-19 epidemic, technical staffs, environmental experts of CSC/PISC1, and PMU staff carry out site supervision in compliance with regulations of the local government.
From January to June 2021, Quang Binh province applies the Government's CT15 directive, so the contractors still work on the construction site and implement epidemic prevention measures as required by the local government. The PMU has mobilized the environmental expert of PISC1 consultant, who is living in Dong Hoi city, to supervise the implementation of environmental impact mitigation measures at the sites of the packages DH/W1, DH/W3 DH/W4, DH/W5, DH/W8. The environmental specialist of PISC1 was mobilized for a total of about 1 month to do site supervision during this reporting period. Specifically, the environmental specialist carried out site supervision 4 days in March from 23th to 26th, 5 intermittent days in April from 1st to 7th, 5 intermittent days in May, on 6th , 17th – 18th and 24th - 25th, and 3 intermittent days in June, on 4th, 21th and 30th .
Besides, because PISC1 Consultants does not have a position of safety engineer, monitoring activities on occupational safety, traffic safety, COVID-19 prevention, etc. are further supported by the site inspectors of PISC1. These site inspectors still work normally when Quang Binh province applies Directive 15 in the first 6 months of 2021. The officer who is in charge of the environmental and social safety policies of the PMU also performs supervision as usual. Both the staff of the PMU and PISC1 Consultant comply with the requirements of epidemic prevention in accordance with the requirements of the locality.
The contractor's COVID prevention measures are outlined in Table 8 below..
C. Environmental mitigations measures implemented by the contractor During the construction of site office of package DH/W1, DH/W3, DH/W4, DH/W5, DH/W8, the
contractor has implemented the environmental impacts mitigation measures as committed in
EMP. The implementation of environmental impacts mitigation measures of the contractors is
summarized in Table 8.
Table 8. Assessment on the EMP Compliance
Package EMP requirements
Status of the EMP compliance
DH/W1, DH/W3, DH/W4, DH/W5, DH/W8
1. Launch of EMP and sub-plans
All packages including DH/W1, DH/W3, DH/W4, DH/W5, DH/W8 partly complied with this requirement.
The contractors’ EMP, labor safety plan, fire prevention plan, HIV training plan, solid waste management plan has been approved.
The contractors are preparing the Covid-19 prevention plan to submit to PMU for approval, and they also apply the prevention measures during the construction process.
DH/W1, DH/W3, DH/W4, DH/W5, DH/W8
Training and capacity building
All packages including DH/W1, DH/W3, DH/W4, DH/W5, DH/W8 have not complied with this requirement yet.
22
Contractors cannot carry out training activities on capacity capacity, as it is difficult to organize a mass gathering in the context of the COVID-19 epidemic.
DH/W1 Health and safety for workers
Partly complied with
The issues have been complied during the reporting period
- The workers are provided the personal protective equipment
- Workers' camps are equipped with fire extinguishers and medicine cabinet. - Periodical health checkup plan has been prepared for workers. The workers are provided facemask, sanitizer hand wash to prevent the Covid-19, but it is still insufficient, they have not had their daily temperature checked. The workers’ camp has a rest room, a kitchen, a bathroom, and a toilet that meets their demands.
The issues have not been fully complied with during the reporting period
The workers have not been trained on HIV, labor safety and environmental sanitation yet.
DH/W3 Partly complied with
The issues have been complied during the reporting period
- The workers are provided the personal protective equipment
- Workers' camps are equipped with fire extinguishers and medicine cabinet. - Periodical health checkup plan has been prepared for workers. - The workers are provided facemask, sanitizer hand wash to prevent the Covid-19, but it is still insufficient, they have not had their daily temperature checked. - The workers’ camp has a rest room, a kitchen, a bathroom, and a toilet that meets their demands.
The issues have not been fully complied with during the reporting period
The workers have not been trained on HIV, labor safety and environmental sanitation yet.
DH/W4 Partly complied with
The issues have been complied during the reporting period
- Periodical health checkup plan has been prepared for workers.
23
- The workers are provided facemask, sanitizer hand wash to prevent the Covid-19, but it is still insufficient.
- Workers' camps are equipped with fire extinguishers and medicine cabinet.
- The workers’ camp has a rest room, a kitchen, a bathroom, and a toilet that meets their demands.
The issues have not been fully complied with during the reporting period
- The workers have not been trained on HIV, labor safety and environmental sanitation yet.
- The contractor has not mobilized labor safety and environmental safety personnel; has not provided the personal protective equipment for workers sufficiently.
DH/W5 Partly complied with
The issues have been complied during the reporting period
- Periodical health checkup plan has been prepared for workers.
- The workers are provided facemask, sanitizer hand wash to prevent the Covid-19
- Workers' camps are equipped with fire extinguishers and medicine cabinet.
- The workers’ camp has a rest room, a kitchen, a bathroom, and a toilet that meets their demands.
The issues have not been fully complied with during the reporting period
- The workers have not been trained on HIV, labor safety and environmental sanitation yet.
- The contractor has not mobilized labor safety and environmental safety personnel; has not provided the personal protective equipment for workers sufficiently.
DH/W8 Partly complied with
The issues have been complied during the reporting period
- The workers are provided the personal protective equipment
- Periodical health checkup plan has been prepared for workers. - The workers are provided facemask, sanitizer hand wash to prevent the Covid-19 - Workers' camps are equipped with fire extinguishers and medicine cabinet.
24
- The workers’ camp has a rest room, a kitchen, a bathroom, and a toilet that meets their demands.
The issue has not been fully complied with during the reporting period
- The workers have not been trained on HIV, labor safety and environmental sanitation yet.
- The contractor has not mobilized labor safety and environmental safety personnel.
DH/W1 Waste management
Partly complied with
- Before the construction, the contractor has prepared a solid waste management plan and prepared to sign a contract with the waste treatment unit. - At the construction area of workers’ camp, the contractor arranged trash cans. The contractor also arranged a construction waste collection area. - Before being collected and disposed by a licensed waste carrier, solid waste is temporarily stored at the site in a prescribed area approved by the CSC and local authorities. - Waste packaging is protected against corrosion. - There is no fire at the burial or landfill of solid waste.
- Reusable materials such as wooden planks for trenching, steel, scaffolding materials, packing materials, etc. will be collected and separated from other waste sources for reuse as filler or for sale.
The issue has not been fully complied with during the reporting period
- Up to now, the contractor has not yet signed a contract with a functional unit to treat hazardous waste generated during the construction process.
DH/W3 Partly complied with
- At the construction area of workers’ camp, the contractor arranged trash cans. The contractor also arranged a construction waste collection area. - Before being collected and disposed by a licensed waste carrier, solid waste is temporarily stored at the site in a prescribed area approved by the CSC and local authorities. - Waste packaging is protected against corrosion. - There is no fire at the burial or landfill of solid waste.
- Reusable materials such as wooden planks for trenching, steel, scaffolding materials, packing materials, etc. will be collected and separated from other waste sources for reuse as filler or for sale.
25
The issue has not been fully complied with during the reporting period
- Up to now, the contractor has not yet signed a contract with a functional unit to treat hazardous waste generated during the construction process.
DH/W4 Partly complied with
- Before the construction, the contractor has prepared a solid waste management plan and prepared to sign a contract with the waste treatment unit. - At the construction area of workers’ camp, the contractor arranged trash cans. The contractor also arranged a construction waste collection area. - Before being collected and disposed by a licensed waste carrier, solid waste is temporarily stored at the site in a prescribed area approved by the CSC and local authorities. - Waste packaging is protected against corrosion. - There is no fire at the burial or landfill of solid waste.
- Reusable materials such as wooden planks for trenching, steel, scaffolding materials, packing materials, etc. will be collected and separated from other waste sources for reuse as filler or for sale.
The issue has not been complied with during the reporting period
- Up to now, the contractor has not yet signed a contract with a functional unit to treat hazardous waste generated during the construction process.
DH/W5 Partly complied with
- Before the construction, the contractor has prepared a solid waste management plan and prepared to sign a contract with the waste treatment unit. - At the construction area of workers’ camp, the contractor arranged trash cans. The contractor also arranged a construction waste collection area. - Before being collected and disposed by a licensed waste carrier, solid waste is temporarily stored at the site in a prescribed area approved by the CSC and local authorities. - Waste packaging is protected against corrosion. - There is no fire at the burial or landfill of solid waste.
- Reusable materials such as wooden planks for trenching, steel, scaffolding materials, packing materials, etc. will be collected and separated from other waste sources for reuse as filler or for sale.
The issue has not been complied with during the reporting period
26
- Up to now, the contractor has not yet signed a contract with a functional unit to treat hazardous waste generated during the construction process.
DH/W8 Partly complied with
- Before the construction, the contractor has prepared a solid waste management plan and prepared to sign a contract with the waste treatment unit. - At the construction area of workers’ camp, the contractor arranged trash cans. The contractor also arranged a construction waste collection area. - Before being collected and disposed by a licensed waste carrier, solid waste is temporarily stored at the site in a prescribed area approved by the CSC and local authorities. - Waste packaging is protected against corrosion. - There is no fire at the burial or landfill of solid waste.
- Reusable materials such as wooden planks for trenching, steel, scaffolding materials, packing materials, etc. will be collected and separated from other waste sources for reuse as filler or for sale.
The issue has not been complied with during the reporting period
- Up to now, the contractor has not yet signed a contract with a functional unit to treat hazardous waste generated during the construction process.
DH/W1 Mitigation of impacts on traffic activities
Partly complied with
- The contractor has set up barriers, warning signs, traffic signs at construction routes.
The issue has not been complied with during the reporting period
- The concrete slabs at some manholes on routes T3, T6, T17C were broken or not installed yet, this negatively affected the traffic safety, the PISC1 consultant have issued Document No. RHDHV/PICS1/210630.1 dated June 30, 2021 to request the contractor to resolve the problems.
DH/W3 Partly complied with
The contractor has provided barricade, warning sign, road sign on roads being under construction process
The issue has not been complied with during the reporting period
- The incomplete construction at route 3 on Nguyen Thi Dinh Street negatively affects traffic safety, PISC1 consultant have issued Document No. RHDHV/PICS1/210621.2 dated June 21, 2021 and
27
Document No. RHDHV /PICS1/210630.1 dated June 30, 2021, to request the contractor to resolve the problem.
DH/W4 Complied with
The contractor has provided barricade, warning sign, road sign on roads being under construction process
DH/W5 Complied with
The contractor has provided barricade, warning sign, road sign on roads being under construction process
DH/W8 Complied with
The contractor has provided barricade, warning sign, road sign on roads being under construction process
DH/W1 Management of Air Quality, Dust and
Noise
Fully complied with
- During the construction process, on hot days, the contractor uses watering trucks to minimize dust emission (4 times/day) and the trucks carrying construction materials are covered to prevent spillage of materials during transportation.
- The workers are provided with facemask to avoid dust.
- All the equipment must be obtained "Regulation on quality inspection, technical safety and environmental protection" according to Decision No. 35/2005/QD-BGTVT.
- The construction area is frequently cleaned to avoid dusts in the surrounding area.
- Machine is frequently maintained to prevent noise and vibration during transportation and construction.
DH/W3 Fully complied with
- During the construction process, on hot days, the contractor uses watering trucks to minimize dust emission (4 times/day) and the trucks carrying construction materials are covered to prevent spillage of materials during transportation.
- The workers are provided with facemask to avoid dust.
- All the equipment must be obtained "Regulation on quality inspection, technical safety and environmental protection" according to Decision No. 35/2005/QD-BGTVT.
- The construction area is frequently cleaned to avoid dusts in the surrounding area.
28
- Machine is frequently maintained to prevent noise and vibration during transportation and construction.
DH/W4 Fully complied with
- During the construction process, on hot days, the contractor uses watering trucks to minimize dust emission (4 times/day) and the trucks carrying construction materials are covered to prevent spillage of materials during transportation.
- The workers are provided with facemask to avoid dust.
- All the equipment must be obtained "Regulation on quality inspection, technical safety and environmental protection" according to Decision No. 35/2005/QD-BGTVT.
- The construction area is frequently cleaned to avoid dusts in the surrounding area.
- Machine is frequently maintained to prevent noise and vibration during transportation and construction.
DH/W5 Partly complied with
- The trucks carrying construction materials are covered to prevent spillage of materials during transportation.
- The workers are provided with facemask to avoid dust.
- All the equipment must be obtained "Regulation on quality inspection, technical safety and environmental protection" according to Decision No. 35/2005/QD-BGTVT.
- The construction area is frequently cleaned to avoid dusts in the surrounding area.
- Machine is frequently maintained to prevent noise and vibration during transportation and construction.
The issue has not been fully complied with during the reporting period:
- The contractor should increase watering on vertical roads No. 2, No. 3, especially on hot and dry days (4-6 times/day).
DH/W8 Partly complied with
- The trucks carrying construction materials are covered to prevent spillage of materials during transportation.
- The workers are provided with facemask to avoid dust.
29
- All the equipment must be obtained "Regulation on quality inspection, technical safety and environmental protection" according to Decision No. 35/2005/QD-BGTVT.
- The construction area is frequently cleaned to avoid dusts in the surrounding area.
- Machine is frequently maintained to prevent noise and vibration during transportation and construction.
The issue has not been fully complied with during the reporting period:
- The contractor should increase watering, about 4-6 times/day at the section of Km0.330-Km0.557 and the adjacent roads that the material transport vehicles often pass through.
DH/W1 Mitigation of the impacts of domestic wastewater
Fully complied with
- The worker’s camp area has a septic toilet, domestic wastewater is collected into a septic tank for treatment.
- The contractor and workers have complied with the regulations on environmental sanitation and maintained general sanitation.
- Mobile toilets have been built on the construction site for workers.
DH/W3 Fully complied with
- The contractor mainly employs local workers and assigns one guard at night, so domestic wastewater is inconsiderable.
DH/W4 Fully complied with
- The contractor and workers have complied with the regulations on environmental sanitation and maintained general sanitation.
- The worker’s camp area has a septic toilet, domestic wastewater is collected into a septic tank for treatment.
- Mobile toilets have been built on the construction site for workers.
DH/W5 Fully complied with
- The contractor and workers have complied with the regulations on environmental sanitation and maintained general sanitation.
- Mobile toilets have been built on the construction site for workers.
- The worker’s camp area has a septic toilet, domestic wastewater is collected into a septic tank for treatment.
30
DH/W8 Fully complied with
- The contractor and workers have complied with the regulations on environmental sanitation and maintained general sanitation.
- Mobile toilets have been built on the construction site for workers.
- The worker’s camp area has a septic toilet, domestic wastewater is collected into a septic tank for treatment.
DH/W1, DH/W3, DH/W4, DH/W5, DH/W8
Protection of cultural resources
- This issue is not applied for all packages including DH/W1, DH/W3, DH/W4, DH/W5, DH/W8
- The road construction does not affect to any cultural resources.
DH/W1 Purchase, transportation and storage of materials
Fully complied with
- Materials are transported to the construction site based on the construction plan, so there is no excess material on the construction site.
- Materials that are easily affected by weather such as cement and steel are carefully covered.
DH/W3 Fully complied with
- Materials that are easily dispersed such as sand and gravel are daily cleaned after construction
- Materials are transported to the construction site based on the construction plan, so there is no excess material on the construction site.
- Materials that are easily affected by weather such as cement and steel are carefully covered.
DH/W4 Fully complied with
- Materials are transported to the construction site based on the construction plan, so there is no excess material on the construction site.
- Materials that are easily affected by weather such as cement and steel are carefully covered.
- Materials that are easily dispersed such as sand and gravel are daily cleaned after construction
DH/W5 Fully complied with
- Materials are transported to the construction site based on the construction plan, so there is no excess material on the construction site.
- Materials that are easily dispersed such as sand and gravel are daily cleaned after construction
31
- Materials that are easily affected by weather such as cement and steel are carefully covered.
DH/W8 Fully complied with
- Materials are transported to the construction site based on the construction plan, so there is no excess material on the construction site.
- Materials that are easily dispersed such as sand and gravel are daily cleaned after construction
- Materials that are easily affected by weather such as cement and steel are carefully covered.
DH/W1 Control of erosion and landslide
Fully complied with
- The contractor applies the successive construction method to avoid prolonging excavation of open ditches and result in landslides.
- The embankment is carried out during the dry season.
- The deep ditches at the soft soil location are reinforced by piles to avoid landslides.
DH/W3 Fully complied with
- The contractor applies the successive construction method to avoid prolonging excavation of open ditches and result in landslides
- The embankment is carried out during the dry season
- The deep ditches at the soft soil location are reinforced by piles to avoid landslides.
DH/W4 Fully complied with
- The embankment is carried out during the dry season
- The contractor applies the successive construction method to avoid prolonging excavation of open ditches and result in landslides.
- The deep ditches at the soft soil locations are reinforced by piles to avoid landslides.
DH/W5 Fully complied with
- The contractor applies the successive construction method to avoid prolonging excavation of open ditches and result in landslides.
- The embankment is carried out during the dry season
- The deep ditches at the soft soil locations are reinforced by piles to avoid landslides.
DH/W8 Fully complied with
32
- The contractor applies the successive construction method to avoid prolonging excavation of open ditches and result in landslides.
- The embankment is carried out during the dry season
DH/W1 Impacts on community services and facilities
Complied with
During the reporting period, no utility services were affected due to the contractor's activities.
DH/W3 Complied with
During the reporting period, no utility services were affected due to the contractor's activities.
DH/W4 Complied with
During the reporting period, no utility services were affected due to the contractor's activities.
DH/W5 Complied with
During the construction process, if there are any underground construction works, the contractor should announce the local people and coordinate with the stakeholders to resolve.
In this reporting period, route No. 1 and 2 still have problems with substations and power poles that have not been relocated.
DH/W8 Complied with
During the construction process, if there are any underground construction works, the contractor should announce the local people and coordinate with the stakeholders to resolve.
DH/W1 Public health and safety
Complied with
- The contractor has set up the barriers, warning sign around the construction site
- The speed of construction and materials transport vehicles is limited in accordance with regulations when passing through roads
DH/W3 Complied with
- The contractor has set up the barriers, warning sign around the construction site
- The speed of construction and materials transport vehicles is limited in accordance with regulations when passing through roads
DH/W4 Complied with
33
- The contractor has set up the barriers, warning sign around the construction site
- The speed of construction and materials transport vehicles is limited in accordance with regulations when passing through roads
DH/W5 Complied with
- The contractor has set up the barriers, warning sign around the construction site
- The speed of construction and materials transport vehicles is limited in accordance with regulations when passing through roads
DH/W8 Complied with
- The contractor has set up the barriers, warning sign around the construction site
- The speed of construction and materials transport vehicles is limited in accordance with regulations when passing through roads
DH/W1, DH/W3, DH/W4, DH/W5, DH/W8
Covid-19 prevention
All packages DH/W1, DH/W3, DH/W4, DH/W5, DH/W8 complied with this issue.
Contractors have posted COVID-19 management posters, provided hand sanitizer and masks, and checked workers' temperatures.
During the Covid-19 outbreaks, the Contractor have requested workers to daily declare their personal diseases, travel schedules, wash their hands with antibacterial hand sanitizer before and after finishing work, suspended construction or performed work rotation, mobilized fewer than 10 workers at the construction site.
PISC1 regularly monitor and inspect contractors' implementation of COVID-19 prevention
Some photos of the compliance with environmental safety measures of the packages in the reporting period
34
The barrier on Nguyen Thi Dinh street – DH/W3
The barrier at the construction area of pumping station No. 3 – DH/W3
Regulations on labor safety and fire prevention
Regulations on labor safety and fire prevention
Portable toilet for workers at construction site
Medicine cabinet at the worker's camp
35
Transportation of sewer pipes to ensure traffic safety– DH/W5
The workers do not wear the personal protective equipment sufficiently – DH/W5
Trash cans at the construction site
Hazardous waste is collected
36
Construction site warning sign
Construction and traffic warning signs
Hand sanitizer for workers at the workers’ camp
Workers wear personal protective equipment sufficiently
V. Environmental impact monitoring
A. Monitoring plan and responsibilities
PISC1 Consultant take responsibilities for environmental monitoring. The environmental monitoring program is implemented quarterly. The environmental parameters include air quality, surface water quality, noise and vibration. The three air quality monitoring parameters include: Noise, Dust, CO, SO2, NO2, and surface water quality monitoring parameters include: pH, Suspended Solids, BOD5, COD, Ammonium, Chloride, Iron, Lead, Total grease. During this reporting period, environmental monitoring activities have been carried out in March and June 2021.
B. Environmental monitoring component, number of samplings and monitoring methods
Sampling locations for environmental quality monitoring of the packages are determined in uEMP, air quality is monitored at 15 locations of the packages DH/W1, DH/W3, DH/W4, DH/W5
37
and DH/W8, surface water quality is collected at 1 location on Nhat Le river (in the South of Nhat Le 1 bridge). Sampling locations have been kept unchanged in March and June 2021.
The specific sampling locations of each package are presented in the table 9 as below:
Table 9: Sampling locations of environmental monitoring
Location Parameter Package
Air quality monitoring
K1: At the intersection Tran Hung Dao and Quach Xuan Ky streets;
Noise level, Dust, CO, SO2, NO2
This location is outside the scope of the packages (the nearest package is DH/W3)
K2: At the intersection of Tran Hung Dao and Vo Nguyen Giap road;
Noise level, Dust, CO, SO2, NO2 DH/W3
K3: At junction between Nhat Le 2 Bridge and National Highway 1A;
Noise level, Dust, CO, SO2, NO2 DH/W1
K4: On Vo Nguyen Giap road, in front of Hai Dang guest house;
Noise level, Dust, CO, SO2, NO2
DH/W3
K5: At junction between Vo Nguyen Giap road and the end of Horizontal road 1, at Km 0 + 263.19;
Noise level, Dust, CO, SO2, NO2 DH/W3 and DH/W5
K6: At junction between Vo Nguyen Giap road and the end of Horizontal road 2, at Km 0 + 381.01;
Noise level, Dust, CO, SO2, NO2
DH/W3 and DH/W5
K7: At junction between Vo Nguyen Giap and the end of Horizontal road 3, at Km 0 + 544.13;
Noise level, Dust, CO, SO2, NO2
DH/W3 and DH/W5
K8: At junction with the road passing Nhat Le Bridge 1 and Nguyen Thi Dinh Street;
Noise level, Dust, CO, SO2, NO2 DH/W3
K9: At the beginning of the road along the Nhat Le river (on the right of the bridge);
Noise level, Dust, CO, SO2, NO2 DH/W3.
38
Location Parameter Package
K10: In front gate of Secondary School No.2 Bac Ly, TK11, Bac Ly Ward;
Noise level, Dust, CO, SO2, NO2 DH/W1
K11: On Quang Trung Street, in front of Bao Minh Trading Limited Company;
Noise level, Dust, CO, SO2, NO2 DH/W1
K12: On Truong Chinh street, turn to the new market Bac Ly;
Noise level, Dust, CO, SO2, NO2
DH/W1
K13: At junction between Huu Nghi Street and the road to Vietnam-Cuba Hospital;
Noise level, Dust, CO, SO2, NO2 DH/W1
K14: At the intersection of Tran Hung Dao Street and Ton That Thuyet Street (one side of Dong Phu Market);
Noise level, Dust, CO, SO2, NO2
DH/W1
K15: On National Highway 1A, at the short bridge.
Noise level, Dust, CO, SO2, NO2
DH/W1
Surface water monitoring
Nhat Le river (in the South of Nhat Le 1 bridge)
pH, Suspended Solids, BOD5, COD, Ammonium, Cl, Steel, Pb, Total Grease.
DH/W3
Specific sampling locations on the map are presented in the below figure
39
Figure 2: Map of sampling locations
Note that Surface water monitoring sampling location is adjacent sampling location of K9 on the map
40
C. Monitoring results
1. Results of air quality monitoring
Details of the results of the two monitoring periods are shown in the following table:
Table 10: Results of air quality monitoring
No. Location
March 2021 June 2021
TPS μg/m3
SO2
μg/m3
NO2
μg/m3
CO μg/m3
Noise dBA
TPS μg/m3
SO2 μg/m3
NO2 μg/m3
CO μg/m3
Noise dBA
1 K1: At the intersection Tran Hung Dao and Quach Xuan Ky streets;
200 32 41 4560 69,2 180 26 35 3675 66,7
2 K2: At the intersection of Tran Hung Dao and Vo Nguyen Giap road;
90 29 56 4215 63,7 70 19 28 3210 60,2
3 K3: At junction between Nhat Le 2 Bridge and National Highway 1A;
180 48 63 5230 73,5 150 36 47 3970 70,8
4 K4: On Vo Nguyen Giap road, in front of Hai Dang guest house;
80 26 32 3265 61,2 70 <10 <10 <3000 62,4
5
K5: At junction between Vo Nguyen Giap road and the end of Horizontal road 1, at Km 0 + 263.19;
90 35 40 3415 61,8 110
<10 <10 <3000 58,6
6
K6: At junction between Vo Nguyen Giap road and the end of Horizontal road 2, at Km 0 + 381.01;
130 42 51 3875 62,4 170
29 41 3455 63,7
7
K7: At junction between Vo Nguyen Giap and the end of Horizontal road 3, at Km 0 + 544.13;
70 29 38 3250 58,2 190
38 52 3570 61,1
41
No. Location
March 2021 June 2021
TPS μg/m3
SO2
μg/m3
NO2
μg/m3
CO μg/m3
Noise dBA
TPS μg/m3
SO2 μg/m3
NO2 μg/m3
CO μg/m3
Noise dBA
8 K8: At junction with the road passing Nhat Le Bridge 1 and Nguyen Thi Dinh Street;
140 41 59 5630 68,3 160 22 35 3300 65,9
9 K9: At the beginning of the road along the Nhat Le river (on the right of the bridge);
60 38 46 3920 57,9 60 <10 <10 <3000 58,9
10 K10: In front gate of Secondary School No.2 Bac Ly, group 11, Bac Ly Ward;
120 44 58 4360 68,0 90 <10 <10 <3000 60,5
11 K11: On Quang Trung Street, in front of Bao Minh Trading Limited Company;
130 32 41 4975 68,7 150
40 56 3890 70,8
12 K12: On Truong Chinh street, turn to the new market Bac Ly;
90 43 65 5390 72,5 100 26 39 3325 60,4
13 K13: At junction between Huu Nghi Street and the road to Vietnam-Cuba Hospital;
80 34 48 4265 74,1 140
30 51 4010 73,3
14
K14: At the intersection of Tran Hung Dao Street and Ton That Thuyet Street (one side of Dong Phu Market);
110 39 45 4360 75,6 130
34 49 4245 72,6
15 K15: On National Highway 1A, at the short bridge.
170 42 61 4610 73,1 140 37 52 3960 68,6
QCVN 05:2013/BTNMT
300 350 200 30.000 70 300 350 200 30.000 70*
(*): QCVN 26:2010/BTNMT (8h): National Technical Regulation on Noise
QCVN 05:2013/BTNMT: National Technical Regulation on Ambient Air Quality
The results of ambient air quality monitoring in this reporting period show that all parameters are within the permissible limits of the standards according to QCVN 05:2013/BTNMT, except for noise at locations K3. , K12, K13, K14, K15 in the monitoring period in March 2021 and the
42
location at K11, K13, K14 in the monitoring period in June 2021 are higher than the permissible limits. The reason for this issue is the participation of many other means of transport at the time of monitoring.
Comparing the monitoring results in March and June 2021 with the background environmental monitoring results sampled and analyzed during the preparation phase of the EIA report in May 2018 (The background environment results are included in Appendix 3 of the report), it shows that the monitoring parameters fluctuate as follows:
- TPS: The results at the sampling locations in March 2021 and June 2021 are higher than the background environment results in May 2018. However, all values of the TPS parameters are below the permissible limits.
- NO2: The results at 14/15 sampling locations in June 2021 are lower than the background environmental results in May 2022, while the results in March 2021 had 9/15 locations which are lower than the background environmental results, but all locations are within the permissible limits.
Figure 3: Comparison of TPS in March and June 2021 with the background environment in May 2018 and QCVN 05:/2013/BTNMT
Figure 4: Comparison of NO2 in March and June 2021 with the background environment in May 2018 and QCVN
05:/2013/BTNMT
0 50 100 150 200 250 300 350
K1
K3
K5
K7
K9
K11
K13
K15
TPS μg/m3
TPS μg/m3 Mar-21 TPS μg/m3 May-18 TPS μg/m3 Jun-21
0 50 100 150 200 250
K1
K3
K5
K7
K9
K11
K13
K15
NO2 μg/m3
NO2 μg/m3 Jun-21 NO2 μg/m3 Mar-21 NO2 μg/m3 May-18
43
- SO2: The results of all sampling locations in March and June 2021 are lower than the background environment in May 2018 and lower than the permissible limits.
Figure 5: Comparison of SO2 in March and June 2021 with the background environment in May 2018 and QCVN 05:/2013/BTNMT
- CO: In March 2021, the results of 5/15 sampling locations are lower than the background environment while in June 2021, the results of 10/15 locations are lower than the background environment. In general, all results of the 2 monitoring periods are within limits of QCVN 05:/2013/BTNMT
0
50
100
150
200
250
300
350
400
SO2 μg/m3
SO2 μg/m3 Jun-21 SO2 μg/m3 May-18 SO2 μg/m3 Mar-21
44
Figure 6: Comparison of CO in March and June 2021 with the background environment in May 2018 and QCVN 05:/2013/BTNMT
Noise: Most of the monitoring results in March and June 2021 are lower than the background environment in May 2018 because most of the results in May 2018 are above the permissible limits. During the monitoring period in March 2021, the results of noise at 5 locations K3, K12, K13, K14, K15 and 3 locations K11, K13, K14 in the monitoring period in June 2021 were higher than the permissibe limits of QCVN 26:2010/BTNMT. Many means of transport at the intersections at the monitoring time is considered to be the primary reason for the noise problem at these monitoring locations. Mitigation measures of contractors have been mentioned above.
0
5000
10000
15000
20000
25000
30000
35000
CO μg/m3
CO μg/m3 May-18 CO μg/m3 Mar-21 CO μg/m3 Jun-21
45
Figure 7: Comparison of noise in March and June 2021 with background environment in May 2018 and QCVN 05:/2013/BTNMT
0
10
20
30
40
50
60
70
80
90
Noise dBA
Noise dBA Mar-21 Noise dBA May-18 Noise dBA Jun-21
46
2. Results of surface water quality monitoring:
Surface water is monitored at a location of the package DH/W3 with 9 parameters. Monitoring results in 2 sampling periods in March and June 2021 are presented in the table 11 below.
Table 11: Results of surface water quality monitoring
No. Parameter Unit Result MT 08-MT: 2015/BTNMT
March 2021 June 2021
1 pH 8,1 7,9 5,5 - 9
2 TSS mg/l 22 18 ≤100
3 BOD5 mg/l 13,1 16,5 ≤25
4 COD mg/l 29,6 30,4 ≤50
5 NH4+ (based on Nitrogen)
mg/l 0,27 0,21 ≤1
6 Chloride mg/l 6665 6688,92 -
7 Total iron mg/l 0,8 0,1 ≤2
8 Pb mg/l <0,002 <0,002 ≤0,05
9 Oil & grease mg/l <0,3 <0,3 ≤0,3
The results show that all monitoring parameters are within the permissible limits of QCVN 08-MT: 2015/BTNMT – National technical regulation on surface water quality.
Comparing the surface water monitoring results in March and June 2021 with the background environmental results during the preparation phase of the EIA report in May 2018 shows that the pH, TSS, BOD5, COD are higher, but all of the parameters are below the permissible limits.
In terms of the ammonium, iron, and lead, the monitoring results in March and June also show that they are all higher than the background environmental results, except that the Total grease remains unchanged in all three monitoring times.
The results of background environmental are included in Appendix 3 of the report
47
Figure 8: Comparison of surface water monitoring results in March and June 2021 with the background environment
VI. Public consultation, grievance redress mechanism
A. Public consultation and information disclosure The EIA of the Project, the environmental protection plan of DH/W1, DH/W3, DH/W4, DH/W5,
DH/W8 have been published in Bao Ninh commune. Besides, the contractor also provided an
information board about the project including name, package, design consultant, supervision
consultant, construction contractor, and location.
In this reporting period, the DH/PISC1 supervision consultant only conducted the public
consultations in the form of direct interviews with a few households surrounding the construction
site of DH/W1, DH/W3, DH/W4, DH/W5, DH/W8. The results of the interview are as follows:
0
20
40
60
80
100
120
Mar-21 May-18 Jun-21 QCVN 08-MT:2015/BTNMT
Nước mặt (mg/l)
Surface water
pH Chất rắn lơ lửng BOD5 COD
Surface water (mg/l)
TSS
0
0.5
1
1.5
2
2.5
Mar-21 May-18 Jun-21 QCVN 08-MT:2015/BTNMT
Surface water
Amoni (tính theo N) Sắt Chì Tổng dầu mỡIronAmmoniumAmmonium Lead Total gease
48
- All participants were well-aware of the construction and supported the construction. Local
people living around the construction site in Phu Hai ward, Bac Ly junction, Nguyen Thi
Dinh street, Truong Chinh, Nhat Le, Ly Thuong Kiet, Huu Nghi, Hoang Xuan Han street
confirmed that they had not been affected by the construction activities and there had been
no labor accidents or environmental incidents since the commencement of construction of
the packages.
- The list of the interviewees is added in Appendix 4 of the report
B. Grievance redress mechanism Before the construction of DH/W1, DH/W3, DH/W4, DH/W5, DH/W8, the grievance redress
mechanism (GRM) has been established and operated since 2019 in order to address community
concerns and assist the project to maximize environmental and social benefits.
The GRM has been disclosed to APs through the meetings, public consultations with
representatives of the PMU, PISC1, contractors, and local authority & AHs.
When the construction of the packages starts, the contractor will publish information board at the
gate of the construction area or close to the construction area including information about the
project name, package, design consultant, supervision consultant, construction contractor,
location, so that the AHs can know and contact if any complaints occur.
PMU has been setting up a system to monitor and record complaints. This system includes:
- Tracking forms and procedures for grievance redress.
- Processes for informing stakeholders about the status of a case;
- Procedures to retrieve data for reporting purposes, including the periodic reports to the
ADB.
Additionally, the procedure available under the Civil Law and the Land Law No. 45/2013/QH13;
Law on Complaints No. 02/2011/QH13; and Decree No. 47/2014/ND-CP
In the public consultations, the GRM was discussed and all AHs agreed with the proposed GRM.
By the reporting period, the PMU found out that
- Number of new grievances, since the last follow up, if any: 0
- Number of resolved complaints: 0
- Number of unresolved complaints: 0
VII. Capacity building activities The implementation of capacity building activities for the Project is essential and should be
integrated in the project construction process.
In July 2020, with the assistance of the PISC1 Consultant, PMU organized the training on ADB environmental safeguard policy for contractors of package DH/W3, DH/W4, DH/W8 and PMU staff. Contractors were provided with basic information about the environmental management system, environmental compliance requirements according to ADB policies, as well as experience in implementing mitigation measures at the construction site. In addition, the consultant also guided the contractor on how to prepare monthly environmental reports.
49
Figure 9: Training on ADB environmental safeguard policy for the PMU staff and contractors
Plan of capacity building training on environmental safeguards for the remaining contractors DH/W1, DH/W8… was submitted by PISC1 and approved by PMU in June 2021. However, due to the complicated developments of the Covid-19 epidemic and the State's regulations on the Covid-19 prevention (limiting mass gatherings), training sessions on environmental capacity building have not been carried out in this reporting period.
The PISC1 consultant proposes the expected training plan in the near future as follows:
- Training on environmental safety policy for contractors of package DH/W1, DH/W8.
- The training period: 01 day in October 2021 or November 2021, the specific training time will be agreed with the PMU after the COVID19 epidemic is basically under control.
- The training content will introduce ADB safeguard policy, the contractor's compliance with the EMP, mitigation measures at the site, supervision process of the contractor's environmental safety staff, and reporting the environmental compliance. Specific training program and training materials will be submitted to the PMU for consideration and approval.
- Environmental Expert of PISC1 Consultant is responsible for conducting the training. In case the expert cannot conduct offline training in Dong Hoi, an online training plan will be developed and submitted.
VIII. KEY ENVIRONMENTAL ISSUES
A. Key identified environmental issues and corrective actions in the previous reporting period In the previous reporting period, the existing environmental issues and the status of corrective
actions are shown in the following table:
Table 12: Key environmental issues in the previous reporting period
Package Key issues Schedule Status of compliance
DH/W1 - Sign contract with a functional unit for hazardous waste collection and treatment.
4th quarter 2021
The contractor is seeking for a service provider to sign the contract
- Supplement personal protective equipment for workers
January 2021 Complied with
50
- Lack of Covid-19 preventive measures
January 2021 Fully complied with
- The information board is insufficiently updated, particularly the contact address of the PMU, contractor and the PISC1 supervision consultant.
January 2021 Fully complied with
- Lack of documents of environmental, labor health and safety
January 2021 Fully complied with
DH/W3 - Sign contract with a functional unit for hazardous waste collection and treatment.
4th quarter 2021
The contractor is seeking for a service provider to sign the contract
- Supplement personal protective equipment for workers
January 2021 Complied with
- Lack of Covid-19 preventive measures
January 2021 Fully complied with
- The information board is insufficiently updated, particularly the contact address of the PMU, contractor and the PISC1 supervision consultant.
January 2021
Fully complied with
- Lack of documents of environmental, labor health and safety
January 2021
Fully complied with
DH/W4 - Sign contract with a functional unit for hazardous waste collection and treatment.
4th quarter 2021
The contractor is seeking for a service provider to sign the contract
- Supplement personal protective equipment for workers
January 2021 Not fully complied with
- Lack of Covid-19 preventive measures
January 2021 Fully complied with
- The information board is insufficiently updated, particularly the contact address
January 2021
Fully complied with
51
of the PMU, contractor and the PISC1 supervision consultant.
- Lack of documents of environmental, labor health and safety
January 2021
Fully complied with
DH/W5 - Sign contract with a functional unit for hazardous waste collection and treatment.
4th quarter 2021
The contractor is seeking for a service provider to sign the contract
- Supplement personal protective equipment for workers
January 2021 Complied with
- Lack of Covid-19 preventive measures
January 2021 Fully complied with
- The information board is insufficiently updated, particularly the contact address of the PMU, contractor and the PISC1 supervision consultant.
January 2021
Fully complied with
- Lack of documents of environmental, labor health and safety
January 2021
Fully complied with
DH/W8 - Sign contract with a functional unit for hazardous waste collection and treatment.
4th quarter 2021
The contractor is seeking for a service provider to sign the contract
- Supplement personal protective equipment for workers
January 2021 Complied with
- Lack of Covid-19 preventive measures
January 2021 Fully complied with
- The information board is insufficiently updated, particularly the contact address of the PMU, contractor and the PISC1 supervision consultant.
January 2021
Fully complied with
- Lack of documents of environmental, labor health and safety
January 2021
Fully complied with
52
- Excavated sand on the road resulted in the air pollution and negatively affected the households living near the river.
January 2021
Fully complied with
B. Environmental issues should be resolved in the first six months of 2021.
There are several issues that contractors have not carried out since the beginning of the contract, including:
- Organizing training on labor safety for workers
- Signing a contract with a hazardous waste collection unit (waste oil and grease).
- Developing the Covid-19 epidemic prevention and control plan
The prolonged and complicated development of the Covid-19 epidemic is considered the primary reason that has affected the contractors’ performance. PISC1 Consultant have requested the contractors to remind and disseminate safety measures at every weekly meeting, so far there have not been any labor safety incidents occurring in all packages. Waste oil and grease are currently being collected by contractors into boxes and stored at the camp to find a collection and treatment unit. Besides, the contractors are preparing the Covid-19 prevention plan to submit to PMU for approval, and the contractor still applies epidemic prevention measures during the construction process. Specific details of each issue and implementation responsibilities are shown in Table 13 below.
The remaining environmental issues of each package in this reporting period are listed in Table 8, with corrective actions and schedule shown in Table 13.
Table 13: Key environmental issues in this reporting period
Key environmental issues
Corrective actions Schedule Responsibility
The remaining environmental issues in the previous reporting period
- Labor safety training for workers
The contractors prepare the plan for labor safety training for workers
- Organize on-site training in small groups to ensure safety and epidemic prevention
- Report the training implementation in the monthly report
4th quarter 2021
The contractors of package DH/W1, DH/W3, DH/W4, DH/W5, DH/W8
PISC1 supervises the implementation
- Sign contract with a functional unit for hazardous waste collection and treatment. (waste grease).
Contractors review the expected volume of waste oil and grease of all packages, the utilization of waste grease and the remaining volume that should be treated; Propose a proper treatment plan
4th quarter 2021
The contractors of package DH/W1, DH/W3, DH/W4, DH/W5, DH/W8
PISC1 supervises the implementation
53
- Development of Covid-19 prevention plan
Based on the Covid-19 epidemic prevention regulations of Quang Binh province, the contractors develop the plan
The contractors are implementing
(3rd 2021)
The contractors of package DH/W1, DH/W3, DH/W4, DH/W5, DH/W8
PISC1 Consultant reviews and approves
Remaining environmental issues in this reporting period (specified in Table 8)
DH/W1
The concrete slabs at some manholes on routes T3, T6, T17C were broken or not installed yet, this negatively affected the traffic safety.
The contractor has inspected these concrete slabs and supplement new ones.
The PISC1 consultant have issued Document No. RHDHV/PICS1/210630.1 dated June 30, 2021 to request the contractor to resolve the problems.
July - August 2021
Contractor - Vietnam Water and Environment Investment Corporation- JSC
PISC1 Consultant /PMU
DH/W3
The incomplete construction at route 3 on Nguyen Thi Dinh Street negatively affected traffic safety,
Contractors should use soft fences and warning signs to ensure traffic safety. PISC1 consultant have issued Document No. RHDHV/PICS1/210621.2 dated June 21, 2021 and Document No. RHDHV /PICS1/210630.1 dated June 30, 2021, to request the contractor to resolve the problem.
July - August 2021
Contractor - Vietnam Water and Environment Investment Corporation- JSC
PISC1 Consultant /PMU
DH/W4
The contractor has not mobilized labor safety and environmental safety personnel; have not provided enough personal protective equipment for workers
The contractor should implement the following measures:
- Check the insufficient types of personal protective equipment and fully provide for the workers
- Supervise and remind the workers to wear personal protective equipment when
July - August 2021
Joint Venture of Tien Dat Construction Company Limited, Long Thanh Construction Joint Stock Company and 688 Consulting Joint Stock Company
PISC1 Consultant /PMU
54
working on the construction site
- Mobilize labor safety and environmental safety officers to supervise the implementation of environmental impacts mitigation measures on the construction site.
DH/W5
The vertical routes No. 2, No. 3 are dusty due to contractor' construction vehicles
Contractor should increase watering, about 4-6 times/day on these routes on the hot and dry days.
July - August 2021
Infrastructure Development and Construction Joint Stock Company PISC1 Consultant/PMU
The contractor has not mobilized labor safety and environmental safety personnel; has not provided enough personal protective equipment for workers
The contractor should implement the following measures:
- Check the insufficient types of personal protective equipment and fully provide for the workers
- Supervise and remind the workers to wear personal protective equipment when working on the construction site
- Mobilize labor safety and environmental safety officers to supervise the implementation of environmental impacts mitigation measures on the construction site.
July - August 2021
Infrastructure Development and Construction Joint Stock Company PISC1 Consultant/PMU
DH/W8
The contractor has not mobilized labor safety and environmental safety personnel.
PISC1 Consultant requests the contractor to mobilize labor safety and environmental safety officers to supervise the implementation of environmental impacts mitigation measures on the construction site.
July 2021 471 Joint Stock Company
PISC1 Consultant/PMU
55
Contractor's material transport vehicles often pass through and generate dust at the section of Km0.330 - Km0.557 and adjacent roads.
Contractor should increase watering, about 4-6 times/day on these routes.
PISC1 supervises the contractor's implementation
July - August 2021
471 Joint Stock Company
PISC1 Consultant/PMU
IX. Conclusions and recommendations
A. Overall Progress of Implementation of Environmental Management Measures The environmental management system of the project has been established and operated rather
effectively. All environmental requirements from both ADB and the Government have been
implemented.
During the reporting period, the stakeholders namely the Project Management Unit, PISC1 Consultant, the construction supervisor, and the Contractor, have sufficiently performed the required tasks in compliance with the environmental safety policy. Specifically:
PISC1 consultant taking responsibilities for construction supervision and capacity building conducts monitoring of EMP compliance activities of contractors at the construction site, requests immediate corrective actions for unsatisfactory issues. Periodic monitoring in the first 6 months of 2021 has been carried out by PISC1 as planned. Monitoring results of environmental components are updated in this reporting period. The PISC1 consultant will continue to carry out the monitoring in the last 6 months of 2021 as planned. Monitoring results will be updated in the next reporting period. The PISC1 consultant prepares the environmental safety monitoring report for the first 6 months of 2021 for the PMU to consider and approve. The PISC1 consultant complies with the requirements of COVID-19 prevention according to local regulations, and simultaneously, monitors and reminds contractors about this work. During the site monitoring process, the PISC1 consultant also consulted the people around the construction site about the impacts of construction activities, so far, in the current reporting period, there have been no complaints from the local people.
Contractors of packages DH/W1, DH/W3, DH/W4, DH/W5, DH/W8 have taken corrective actions as required from the previous ADB review; complied with COVID-19 prevention measures including the preparation of a COVID19 prevention plan in order to carry out construction under new normal conditions. The contractors are preparing the Covid-19 prevention plan to submit to PMU for approval. During construction, the contractors not only relatively effectively implement the environmental mitigation measures, but also maintain and comply with the report preparation.
The PMU conducts site inspections, discusses and reminds contractors to improve the implementation of environmental measures. The PMU has reviewed the Environmental Safety Monitoring Report for the first 6 months of 2021 prepared by the PISC1 consultant and submitted it to ADB for consideration and comments. The PMU also regularly supervises the opinions of people around the construction site of the packages in order to propose timely measures.
B. Proposed actions The remaining environmental issues of the Project during this reporting period are clearly
presented in section B, part VIII. Relevant agencies are required to mobilize resources to urgently
resolve these issues.
56
In the context of complicated developments of the Covid-19, the contractor is required to
sufficiently comply with the Covid-19 preventive measures during the construction process to
ensure the workers’ health and safety.
The environmental monitoring program should be carried out as planned in the next reporting period. According to the construction progress and the current status of Covid-19, PISC1 Consultant and the sampling unit should arrange a reasonable sampling plan to ensure the safety and comply with the requirements of the Government.
When the Covid-19 epidemic is under control, training courses on labor safety, environmental sanitation and HIV should be promptly implemented.
73
Appendix 3: Background environmental monitoring results according to the EIA report of the Project
Results of measurement of air quality in the project area
No Location
Parameter
Temperatur
e
(0C)
CO
(mg/m3)
NO2
(mg/m3)
SO2
(mg/m3)
Dust
(mg/m3)
Noise
(dBA)
1 K1 30 4,504 0,056 0,08 0,07 74,1
2 K2 31 4,488 0,074 0,10 0,07 80,2
3 K3 31 3,366 0,055 0,08 0,07 72,6
4 K4 32 <3 0,037 0,05 0,06 68,2
5 K5 32 <3 0,055 0,08 0,07 67,5
6 K6 32 <3 0,037 0,05 0,06 68,5
7 K7 32 3,354 0,055 0,08 0,07 67,1
8 K8 33 3,345 0,055 0,08 0,06 70,3
9 K9 32 <3 0,037 0,05 0,06 63,9
10 K10 31 4,488 0,055 0,08 0,07 72,8
11 K11 31 3,366 0,055 0,08 0,07 74,2
12 K12 32 3,354 0,055 0,08 0,07 75,0
13 K13 32 4,472 0,074 0,10 0,07 79,3
14 K14 32 4,472 0,055 0,08 0,08 78,2
15 K15 31 3,366 0,074 0,10 0,07 73,5
Permissible
limits - ≤ 30 ≤ 0,2 ≤ 0,35 ≤ 0,3 ≤ 70
Notes:
- Date of sampling: 02/05/2018;
- Sampling locations as required in the uEMP of the Project.
Results of analysis of surface water quality in the project area
No. Parameter Unit
Result QCVN 08-
MT:2015/BTNMT
(Column B1) M1 M2 M3
1 pH 7,36 7,60 7,65 5,5 - 9
2 Suspended solids mg/l 6 9 8
3 BOD5 mg/l 8,7 9,6 7,6 ≤ 15
4 COD mg/l 14 16 12 ≤ 30
5 Ammonium (in N) mg/l 0,06 0,58 0,10 ≤ 0,9
6 Chloride mg/l 83,8 91 91,4 ≤ 350
74
7 Iron mg/l 0,05 <0,03 0,05 ≤ 1,5
8 Lead mg/l <0,0012 <0,0012 <0,0012 ≤ 0,05
9 Total grease mg/l <0,3 <0,3 <0,3 ≤ 1
Notes:
QCVN 08-MT:2015/BTNMT - National technical regulation on surface water quality
Date of sampling: 02/05/2018.
Sampling locations:
- M1: Nhat Le river, section passing Nhat Le 1 bridge;
- M2: 100m downstream from M1;
- M3: Nhat Le river, section passing Nhat Le 2 bridge;
Appendix 4: List of local people participating in the consultations/exchanging opinions at the construction site
No. Name Address Phone
Number
1 Trần Thị Cách 10A, Hoang Xuan Han, Bac Ly Ward
932375303
2 Nguyễn Thị Hoa Lane 85 - Ly Thuong Kiet
333044162
75
3 Võ Thị Thanh Lane 85 - Ly Thuong Kiet
333425439
4 Nguyễn Thanh Tùng Residential Group 13 - Bac Ly Ward
912912746
5 Ngô Mậu Quân 49 Truong Chinh street 912921672
6 Lê Anh Tuấn 62 Huu Nghi street 978888181
7 Phạm Hải Nam 74 Huu Nghi street 888718678
8 Trần Thị Hải Lý 74 Huu Nghi street 819531352
9 Nguyễn Thị Liên Bac Ly juntions
10 Nguyễn Mạnh Hùng Bac Ly juntions
11 Trương Thị Mùi Bac Ly juntions
912386247
12 Phạm Thị Thu Hoài 57 Huu Nghi street 888968777
13 Phạm Thị Oanh 102 Nguyen Thi Dinh, Bao Ninh commune
14 Lê Thị Loan Nguyen Thi Dinh, Bao Ninh commune
15 Lại Thị Vân Nguyen Thi Dinh, Bao Ninh commune
16 Lại Thị Anh Nguyen Thi Dinh, Bao Ninh commune
17 Nguyễn Thị Thu Huyền Nguyen Thi Dinh, Bao Ninh.
18 Đoàn Văn Năm 203 Nhat Le, Bao Ninh commune
19 Hồ Minh Xuân 125 Nhat Le, Bao Ninh commune
20 Hà Việt Hưng Phu Hai ward
21 Hoàng THám Phu Hai ward
22 Hoàng Giảng Phu Hai ward
23 Trần Thị Hậu Phu Hai ward
24 Phạm Thị Liên Phu Hai ward
25 Võ Văn Nguyên Phu Hai ward
26 Phạm Thị Hoa Phu Hai ward
27 Nguyễn Văn Thái Phu Hai ward
28 Nguyễn Văn Sửu Phu Hai ward
29 Lê Xuân Tiến Phu Hai ward
30 Võ Quốc Phượng Phu Hai ward
31 Lê Thị Tuấn Phu Hai ward