VIE: Second Greater Mekong Subregion Corridor Towns ... · cultural and environmental development...
Transcript of VIE: Second Greater Mekong Subregion Corridor Towns ... · cultural and environmental development...
Environmental Monitoring Report
Semi-annual Report
(January - June 2019)
September 2019
VIE: Second Greater Mekong Subregion Corridor Towns
Development Project
Prepared by: PMUs of Bac Giang, Lao Cai and Mong Cai for the Asian Development
Bank (ADB)
Page 1 of 79
CURRENCY EQUIVALENTS
(as of 10 July, 2019)
Currency Unit – Viet Nam Dong (VND)
VND1.00 = $ 0.000043
$1.00 = VND 23,260
WEIGHTS AND MEASURES
dB(A) – Junibel (weighted average)
ha – Hectare
kg/d – kilogram per day
km – Kilometer
km2 – square kilometer
m – Meter
m2 – square meter
m3 – cubic meter
m3/d – cubic meters per day
m3/s – cubic meters per second
mg/m3 – milligrams per cubic meter
mm – Millimeter
NOTE
In this report, "$" refers to US dollars.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
ABBREVIATIONS
ADB - Asian Development Bank
AH - Affected household
BOD - Biological Oxygen Demand
COD - Chemical Oxygen Demand
CEMP - Contractor’s Environmental Management Plan
CPC - Commune People’s Committee
DCST - Department of Communication, Sport and Tourism
DOC - Department of Construction
DOH - Department of Health
DoNRE - Department of Natural Resources and Environment
DOT - Department of Transport
DPI - Department of Planning and Investment
EA - Executing agency
Page 2 of 79
ECC - Environmental Compliance Certificate
EIA - Environmental Initial Assessment
EMP - Environmental Management Plan
EERT - External Emergency Response Team
EO - Environmental Officer
ERT - Emergency Response Team
ERTL - Emergency Response Team Leader
ESU - Environmental Social Unit
IEE - Initial Environmental Evaluation
IA - Implementing Agency
GMS - Greater Mekong Subregion
GOV - Government of Vietnam
NGO - Non-Governmental Organization
O&M - Operation & Maintenance
PIU - Project Implementing Unit
PISC/LISC - Project Implementation Support Consultant
PMU - Project Management Unit
PPC - Provincial People’s Committee
PSC - Project Steering Committee
SO - Safeguard Officer
UXO - Unexploded Ordnance
Page 3 of 79
TABLE OF CONTENT
I. GENERAL INFORMATION OF THE PROJECT ................................................................. 6
II. IMPLEMENTATION PROGRESS ....................................................................................... 7
2.1. Overview ........................................................................................................... 7
2.2. Overall project implementation progress: ........................................................... 7
2.3. Construction activities: ....................................................................................... 7
III. ENVIRONMENTAL MANAGEMENT AND MONITORING FRAMEWORK ...................... 9
3.1. Institutional arrangements for monitoring and implementation of the EMP ............ 9
3.2. Stakeholders’ role and responsibilities in implementing EMP .............................. 10
3.3. Grievance Redress Mechanism GRM (Revised and updated) ............................. 13
3.4. Updated EMPs, Incorporation of EMP requirements into the Construction Contracts
and preparation of the Contractor's Environmental Management Plan (CEMP) .................. 16
IV. EMP IMPLEMENTATION STATUS .............................................................................. 18
4.1. Training and capacity building activities .............................................................. 18
4.2. Compliance with loan terms ................................................................................ 18
4.3. Compliance with GoV regulations........................................................................ 22
4.3.1. Updated EIA .................................................................................................... 22
4.3.2. Licensing for Stone Quarries, Construction Materials Mines and Disposal Sites
23
4.4. Results of environmental compliance monitoring ................................................. 25
4.4.1. Status of EMP implementation ......................................................................... 25
4.4.2. Findings during the site inspections ................................................................. 26
4.4.3. EMP implementation assessment .................................................................... 31
4.5. Environmental Quality Monitoring ....................................................................... 38
4.5.1. In Móng Cái subproject .................................................................................... 38
4.5.2. In Bắc Giang subproject .................................................................................. 39
4.5.3. In Sapa subproject ........................................................................................... 40
V. REMARK ON NON-COMPLIANCES ................................................................................ 42
5.1. Review the implementation of corrective actions from previous report of Jan to June
2018 42
5.2.1. For Mong Cai subproject:................................................................................. 42
5.2.2. For Bac Giang subproject: ............................................................................... 44
5.2.3. For Sapa subproject ........................................................................................ 45
5.2. Key identified issues and requested actions for the period of July to Dec 2018 ... 46
5.2.4. For Mong Cai subproject:................................................................................. 47
5.2.5. For Bac Giang subproject: ............................................................................... 49
Page 4 of 79
5.2.6. For Sapa subproject ........................................................................................ 50
VI. CONCLUSION AND RECOMMENDATIONS ................................................................ 52
APPENDIX 1: MONITORING RESULTS IN BAC GIANG ......................................................... 53
APPENDIX 2: MONITORING RESULTS IN MONG CAI ........................................................... 61
APPENDIX 3: MONITORING RESULTS IN SAPA ................................................................... 69
Page 5 of 79
LIST OF TABLES
Table 1. Status of construction and equipment contracts ......................................................................................8
Table 2. Roles and responsibilities in implementing EMP ..................................................................................... 10
Table 3. Project environmental reporting system assessment .............................................................................. 12
Table 4. Summary of Grievance Cases by Level of GRM........................................................................................ 15
Table 5. Status of compliance with updated EMPs, incorporation EMP requirements and CEMPs ....................... 17
Table 6. Status of compliance with ADB loan terms ............................................................................................. 18
Table 7. Status of compliance with the GoV's Environmental requirements ........................................................ 22
Table 8. Environmental and Safety monitoring activities ..................................................................................... 26
Table 9. Findings during the site inspections ........................................................................................................ 26
Table 10. EMP implementation assessment in Bac Giang subproject ................................................................... 31
Table 11. EMP implementation assessment in Mong Cai subproject .................................................................... 34
Table 12. EMP implementation assessment in Sa Pa subproject .......................................................................... 36
Table 13. Issues for further action on Non-compliance with EMP Requirements from previous report (from 6-
12/2018) – Mong Cai subproject .................................................................................................................. 42
Table 14. Issues for further action on Non-compliance with EMP Requirements from previous report (Last 2018) -
Bac Giang subproject ................................................................................................................................... 44
Table 15. Issues for further action on Non-compliance with EMP Requirements from previous report (December
2018) - Sapa subproject ............................................................................................................................... 46
Table 16. Issues for further action on Non-compliance with EMP Requirements from this report (first 6 months
2019) – Mong Cai subproject ....................................................................................................................... 47
Table 17. Issues for further action on Non-compliance with EMP Requirements from this report (first six months
of 2019) - Bac Giang subproject ................................................................................................................... 49
Table 18. Issues for further action on Non-compliance with EMP Requirements from this report (first six months
of 2019) - Sapa subproject ........................................................................................................................... 50
LIST OF FIGURES
Figure 1: Organization chart for environmental monitoring ...................................................................................9
Page 6 of 79
I. GENERAL INFORMATION OF THE PROJECT
Impact and Outcome: The project’s impact for Bac Giang, Mong Cai and Sa Pa Towns is aligned
with the Government’s Socio-Economic Development Strategy (2011-2020), i.e. economic, socio-
cultural and environmental development in the three towns of Bac Giang, Mong Cai and Sa Pa
improved, contributing to making Viet Nam a modern-oriented, industrial country by 2020. The
project outcome will be improved urban services in Bac Giang, Mong Cai cities and Sapa town.
Outputs: Outputs of the project are: (i) strategic local economic development plans (SLEDPs) and
Sa Pa Green City Action Plan (GCAP) developed; (ii) priority urban infrastructure investments
implemented; (iii) institutional capacities for managing public investments strengthened; and (iv)
community awareness on project activities and environmental sustainability improved.
The project includes: (i) five subprojects in Bac Giang, namely BG1: Tran Quang Khai Road;
BG2: North Eastern Ring Road; BG3: Wastewater Collection and Pond Improvements; BG4:
Stormwater Improvements; BG5: Wastewater Treatment Plant Extension; (ii) three subprojects in
Mong Cai, namely such as MC1: Construction of Wastewater Treatment and Stormwater drainage
system – East; MC2: Construction of Wastewater Treatment and Stormwater drainage system –
West; MC3: River Bank Protection; (iii) three subprojects in Sa Pa, namely such as SP1:
Wastewater and Drainage; SP2: Road 1 – Route 152; SP3: Town Center Enhancement.
Environmental Monitoring Report: Environmental Monitoring for the first 6 months of 2019 is
prepared by the Project Implementation Support Consultant (PISC) for the PMUs. This report
addresses the following issues:
i) Project Implementation Progress
ii) Environmental management and monitoring framework
iii) Implementation status of the Environmental Management Plan
iv) Monitoring of environmental quality
v) Notice of non-compliance
vi) Conclusions and recommendations
Page 7 of 79
II. IMPLEMENTATION PROGRESS1
2.1. Overview
As of June 30, 2019, the value of work completed in the project is estimated at about 39.32% of
the total workload of the whole project. In particular, the rate of completion of the Bac Giang
Subproject is about 22.18%, the Mong Cai Subproject is about 55.71% and the Sa pa Subproject
is about 18.57% compared to the overall progress.
The proportion of the value of workload and actual progress has been achieved for each work item
of the project as follows: (i) Construction and installation of equipment accounts for 80.81% and
the actual progress of this item has been completed at about 26.50%; (ii) Compensation and
clearance works accounted for 5.30% and the actual progress of this item was about 99%; (iii)
PISC consultancy service accounts for 1.46% and actual progress of this item is about 54.83%;
(iv) independent consultant on resettlement accounts for 0.23% and actual progress of this item
being completed at 40%; (v) The Green Sa pa Green Action Plan Consultancy accounts for 1.14%
and the actual progress of this project was 0%; (vi) Other types of consultancy services, project
management and other expenses (using state budget) account for 11.05% and the actual progress
of this item was about 60.16%.
2.2. Overall project implementation progress:
Overall assessment of the progress of the project to date: most of the items of the project basically
meet the requirements of the proposed plan. However, bidding and especially the selection of
contractors is slower than planned so there is a potential risk that affects the overall progress of
the project. Detailed design of the packages has basically been completed. On the other hand, in
the process of construction, there have been some problems that require design changes. These
are: (i) package BG2: additional 1.2km of road surface that needs rehabilitation to ensure
consistency in road infrastructure (ii) Package BG3: the embankment of Banh Keo Lake has been
built up which requires design changes; (iii) package SP2: Additional viaduct at Km7+500 to
Km7+800 to pass over the creeping area in these section; (iv) Packages MC1 and MC2 need to
add SCADA, package MC3 needs to upgrade the existing park upstream of the Eastern
embankment to remain consistent with the new park downstream, and to convert one old
warehouse into parkland to join the 2 parks, in order to maximize the performance and
sustainability of the project.
Construction work in the field to date: (i) In Bac Giang, there are 4 packages BG1, BG2 and BG3,
BG4 under construction with the completed workload of about 25,32%, 88,20%, 26,15% and 13,7
% respectively; (ii) In Mong Cai, 3 packages of MC1, MC2 and MC3 are under construction with
the completed workload of about 53,4%, 66% and 42,00 %, respectively. (iii) In Lao Cai: SP1,
SP2 and SP3 are under construction with a completed workload of about 7,10%, 33,50%, 35,00%
respectively.
2.3. Construction activities:
Construction work in the field to date: (i) In Bac Giang, there are 4 packages BG1, BG2, BG3 and
BG4 under construction with the completed workload of about 25,32%, 88,20%, 26,15% and 13,7
1 Progress Report for Quarter 2, 2019
Page 8 of 79
% respectively; (ii) In Mong Cai, 3 packages of MC1, MC2 and MC3 are under construction with
the completed workload of about 53,40%, 66% và 42,00 %, respectively; (iii) In Lao Cai: SP1,
SP2 and SP3 are under construction with a completed workload of about 7,10%, 33,50%, 25,00 %
respectively.
Table 1. Status of construction and equipment contracts
Contract/Subproject
Expected date
of completion
Implemented
period
(month)
Actual
progress vs
target
(%)
Remarks
Bac Giang city
BG1: Tran Quang Khai road
(NCB)
25 January 2021 17 months 25,32 % constructing bridge piers
and abuttment, applying
surchage load on road
foundation and treating
weak grounds. At the
moment delivering
materials to site is delayed
despite advance payment
and progress payment have
been made in full
BG2: North Eastern Ring Road
(NCB)
26 January 2019 17 months 88,20% work is near complete, the
remaining works are road
marks, signage
BG3: Wastewater Collection and
Pond Improvements (NCB)
01 June 2020 9 months 26,15% Dredging, spoil disposal,
filling of Soc Trang pond
are basically completed,
working on masonry
embankment, Nha Dau
pond is being dredged,
sludge is being dried but
not yet disposed of.
Banh Keo pond: materials
are being gathered, yet
design consultant has not
submitted the revised
design
BG4: Stormwater Improvements
(NCB)
01 February
2021
4 months 13,70% pumping station Van Son
is being constructed. Van
Son drainage canal is
being surveyed
BG5: Wastewater Treatment Plant
Extension: (NCB)
31 December
2020
- - design consultant has
completed the dossier per
the comments of
appraisers. At the moment,
the DoC is carrying out
procedures for PPC’s
approval. Cost estimate is
expected to be submitted
to PPC beore 15/7/2019.
Posting on “Bao Dau
Thau” and ADB’s website
starting 30/7/2019.
Selection of contractor and
work commencement are
expected to complete
before 15/9/2019
Mong Cai city
Page 9 of 79
MC1: Construction of Wastewater
Treatment and Stormwater
drainage system - East (NCB)
06 November
2019
18 months 53,40% stormwater and sewage
sewers, wastewater
pumping stations,
restoration of pavements
and part of WWTPs’
tanks. Manpower and
materials mobilized to site
has not met the planned
schedule.
47/59 equipments have
been approved and ordered
MC2: Construction of Wastewater
Treatment and Stormwater
drainage system - West (NCB)
03 November
2019
18 months 66,00% stormwater and sewage
sewers, restoration of
pavements and part of
WWTPs’ items.
Manpower and materials
mobilized to site has not
met the planned schedule.
34/40 equipment
approved. Of which, 30
have been ordered
MC3: River Bank Protection of
Kalong river (ICB)
April 2020 9 months 42,00% construction of retaining
walls
Sa pa Town
SP1: Construction of Wastewater
treatment system for Sa Pa (ICB)
December 2020 6 months 7,10 % Levelling and spoil
disposal for WWTPs
foundation ongoing, pipe
construction permit being
sought
SP2: Road 1 – Route 152 (NCB) December 2020 18 months 33.50% laying road pavement
temporarily treating
erosions due to flash flood
and ensuring traffic
SP3: Town Center Enhancement December 2020 10 months 25,00 % construction of utilities
and partly restoration of
pavements on several
roads
III. ENVIRONMENTAL MANAGEMENT AND MONITORING FRAMEWORK
3.1. Institutional arrangements for monitoring and implementation of the
EMP
The responsibilities of the Parties for Environmental Monitoring are shown in Figure 1 below.
Figure 1: Organization chart for environmental monitoring
Page 10 of 79
3.2. Stakeholders’ role and responsibilities in implementing EMP
The responsibilities of the Parties for EMP and Environmental Monitoring are shown in Table 2
below.
Table 2. Roles and responsibilities in implementing EMP
Organizations Roles/ Responsibilities
PPC
Overall responsibility for the successful implementation of the EMP, and liaison
with the Lao Cai PMU, Mong Cai PMU in the submission of comprehensive
environmental safeguard reports to ADB. EA will set up a Project Steering
Committee (PSC) to support the implementation of the EMP.
CPC Monitoring the daily implementation of the project including the implementation
of the EMP and reporting to EA.
PPMU
- Ensure that EMP regulations are strictly implemented during different phases of the
project (design / pre-construction, construction and operation) to mitigate
environmental impacts to acceptable levels. Monitor implementation of the EMP
(mitigation and monitoring measures) with the support of the PSC and PCC;
- Ensure that the implementation of the project complies with the principles and
requirements of ADB's Environmental Policy and Safeguard Policy (SPS 2009).);
- Throughout the implementation of the project, commit and maintain a full-time
team of the PPMU consisting of Environmental and Safeguard Officers (ESOs) to
oversee the implementation of the EMP;
- Ensure that environmental protection measures and mitigation measures in the
EMP are incorporated into the detailed design;
- Secure all necessary environmental permits from DONRE prior to awarding
construction contracts;
- Ensure that the Contractor's Environmental Management Plan (CEMP) and
Environmental Management Plan is included in the bid and the contract for the
construction works;
- Establish a mechanism for addressing environmental grievance, as described in the
IEE, to receive and facilitate the settlement of concerns, complaints and grievances
of affected people in terms of the project's environmental performance;
- With the support of the PCC, prepare the semi-annual Environmental Monitoring
Report for submission to ADB;
Page 11 of 79
Organizations Roles/ Responsibilities
- Based on monitoring results of the EMP, identify environmental remedial actions
and prepare corrective action plans if necessary to submit to ADB.
LISC/PISC
- update the EMP to meet the final detail design of subprojects;
- Supervising CEMP preparation of Contractors. Review, clarify and monitor the
implementation of CEMP;
- Provide technical advices and support to PMU / SO to implement EMP; Design
supervision and coordination of PMU-SO's and EO's capacity building and training
programs;
- Implement environmental monitoring in accordance with the environmental
monitoring plan developed in the updated EMP, and implement other plans
approved by ADB and the PMU. Conduct laboratory experiments (EMC) for the
monitoring program specified in this EMP; Prepare monitoring reports for
submission to IA / EA Quarterly;
- Participate in the preparation of monthly and quarterly progress reports for the
subproject (to be submitted to Bac Giang PMU and ADB), and prepare a semi-
annual safeguard policy report (submitted to the EA and ADB);
- Review of possible sites where pollution may occur.
Contractors
- Develop CEMP and submit to Bac Giang PMU (through PISC) for approval before
commencing construction.
- Ensure implementation of the CEMP during construction phase; and
- Prepare and submit a monthly progress report including a report on CEMP
implementation and environmental issues at the construction site.
Detailed Design
Consultant
- Incorporate environmental protection and mitigation measures identified in the
EMP in the design phase of the project; The detailed design stage provides all
necessary information for the PPC to facilitate CEMPs (EMP Management Plans,
Waste Management Plans, Noise and Dust Management, etc.) as described in uIEE
/ EMP.
- During the detailed design phase, inform PCC and LISC of any changes in the
layout or design of the project and provide all necessary information to the PCC to
facilitate any changes, any additional environmental assessment prior to project
development required by the EMP (or additional environmental assessment in the
event of a combined change will result in adverse environmental impacts that do
not fall within the scope of IEE preparation during loan processing, etc.)
- In the detailed design stage, provide all necessary information to the PPMU and the
SC and the PSC to facilitate the approval of the DONRE before awarding the
construction contract.
DONRE
- Reviewing and approving environmental assessment reports as required by the
Government.
- Monitor the environmental performance of the project as DoNRE’s function in
accordance with the state management requirements in the field of environment.
Construction
Supervision Consultant
(CSC)
- Continuous supervision of the contractor. Gather information to monitor contract
performance of the EMP and CEMPs
- Assessment of environmental impacts caused by construction works and
equipment.
- Carry out day-to-day monitoring to ensure that environmental management plans
and CEMPs are properly implemented by contractors.
- Guide workers on the implementation of EMP and CEMPs, health and safety
Page 12 of 79
Organizations Roles/ Responsibilities
- Record and answer to the PPMU on occupational accidents, illnesses and incidents
- As part of the regular progress report to the PPMU, preparation of EMP contract
status reports, health and safety.
- Mobilize a national environmental expert to ensure proper implementation of the
above tasks.
- Recruit qualified environmental staff to ensure compliance with environmental and
legal obligations and contractual obligations.
Local Community
- Conducting community supervision of construction activities of the contractor.
- Based on the Grievance Redress Mechanism, promptly notify local authorities and
the PPMU of non-compliance with environmental management measures.
Environmental Reporting System:
In accordance with the approved uEMP, monthly monitoring reports on uEMP compliance as well
as semi-annual environmental monitoring reports must be prepared by relevant stakeholders. The
detail status of current reporting is described below.
Table 3. Project environmental reporting system assessment
Agency Required reports in
approved IEE and uEMPs
To Whom Current status of Reportage
Construction
contractors
Monthly monitoring report
Self-monitoring of
environmental effects of
construction work in terms of
environmental performance
monitoring requirements
identified in uEMPs.
Undertaken on an ongoing
basis throughout construction
works with regular
monitoring frequencies.
CSCs/PMUs Being Complied
After participating the training course on
uEMP monitoring and receiving the
template of environmental monitoring
report with HSE checklist, the Contractors
have prepared monthly environmental
monitoring reports submitting to
CSCs/PMUs since April 2018 in all three
subprojects - Bac Giang; Mong Cai, and Sa
Pa.
The monthly environmental and safety
monitoring report was carried out by CSCs
hired by PMUs since April 2018 in all three
subprojects - Bac Giang; Mong Cai, and Sa
Pa.
PISC Quarterly monitoring
report
Independent -monitoring of
environmental effects of
construction work in terms of
environmental performance
monitoring requirements
identified in uEMPs.
PMUs Being Complied
The quarterly environmental and safety
monitoring report was carried out by PISC
since Quarter 1/2018 in all three
subprojects - Bac Giang; Mong Cai, and Sa
Pa.
PMUs/
Environmental
consultant
Semiannual monitoring
report Monitoring of
Contractor’s compliance
requirements regularly
construction Monitoring
combination of observation
and review of contractor’s
environmental performance
monitoring results
ADB Being Complied
PMUs (the PISC hired by PMUs) prepared
and submitted one semi-annual monitoring
report for the last year of 2017 which got
approved and disclosed both on ADB and
the Project websites.
The semi-annual monitoring report for Jan
to Jun 2018 has been submitted ADB in
Aug 2018 and finalized in Nov 2018.
Page 13 of 79
Agency Required reports in
approved IEE and uEMPs
To Whom Current status of Reportage
The semi-annual monitoring report for
July to Dec 2018 has been submitted ADB
in Jan 2019.
This semi-annual monitoring report for Jan
to Jun 2019 will be submitted ADB in July
2019.
Staff resources for EMP implementation:
Contractors, CSCs and PMUs: Each PMU has 01 full-time staff responsible for safety and
environment; Contractors have mobilized environment and safety staff who is technical engineer
but have been trained in safety and environmental sanitation; The CSCs has assigned staffs in
charge of monitoring of Environmental Safety and Labor Safety for each package in all subproject.
PISC: There is one firm for PISC to help 3 PMUs during project implementation. Each subproject
has 01 part-time staff with a national environmental consultant that has continually been providing
support on environmental and safe issues through site inspections for implementation of the
environmental and safety compliance at site.
3.3. Grievance Redress Mechanism GRM (Revised and updated)
In all Subprojects, the GRM has been introduced to stakeholders and local communities in the
process of public consultation with verbal and visual presentations of the subproject components.
Formal disclosure in local languages of subproject information to affected persons and
stakeholders was undertaken during the preparation of the IEE to constitute the onset of
information disclosure and stakeholders involvement during project implementation. At the very
least, the summary of the IEE was translated into Vietnamese language and distributed to all
affected people. As part of a stakeholder communication strategy established for the IEE, regular
communication with stakeholders is required throughout the implementation of the subproject.
In accordance with ADB's Governmental Communications Policy (2012), the IEE has been
available on PPC website, Provincial People's Committee offices, DoNRE offices, and at project
sites. Similarly, all project reports with specific references to the EMP Implementation of EA / IA
/ PSC has been available simultaneously in office and on site. In addition, the IEE would also be
available on the ADB website. After the commencement of the subprojects, all environmental
reports and EMP reports by the EA / IA Project are available on the ADB website.
A clearly defined grievance redress mechanism has been set up to deal with APs' complaints and
grievances related to environmental issues, land acquisition, resettlement and compensation, in a
timely and satisfactory way. All affected people (APs) are fully aware of their rights, and detailed
procedures for filing a complaint, and appeals process. This has been announced and disseminated
through an effective publicity campaign. The grievance redress mechanism and complaint
procedure would also be explained in a project information booklet (PIB) that would be distributed
to all APs.
APs have the right to complain about any aspect of the affected environment, land acquisition and
resettlement requirements such as noise, pollution, benefits, rates and payments, and procedures
for resettlement and income restoration program. Appeals can be made verbally or in writing. In
the case of verbal complaints, the grievance committee will be responsible for recording minutes
in all meetings with the APs.
A Grievance Board with members experienced in handling environmental and social issues were
organized in the communes, designated for those tasks by the local leadership. Commune officials
Page 14 of 79
have made all efforts to resolve complaints and issues at the commune level through appropriate
community consultation. All meetings have been handled by the Grievance Board and copies
would be provided to APs. A copy of the minute of the meeting and the action taken would be
provided to the PPC, IA, PSC, and ADB on request.
The procedure for settling complaints is presented below. The procedures described below were
applied to both social and environmental issues and in accordance with the legal process for
settling disputes in Vietnam.
Phase 1: First-time APs' complaints will be submitted verbally or in writing to the village head or
cluster leader. Complaints will be discussed with the APs and the Grievance Board or their
members. Because initial environmental issues are likely to be related to construction activities,
the contractor and the PMU should be notified immediately. The Grievance Board shall be settled
within 15 days of receiving the complaint. All meetings will be recorded and a copy of the meeting
minutes will be provided to the affected people.
Phase 2: Without mediation, or response within 15 days of filing the complaint, APs may refer
the matter to the District Grievance Board (DGC). The DGC is required to respond within 15 days
of receiving the AP's appeal.
Phase 3: If the AP is dissatisfied with the decision of the DGC, or if no response is received, APs
may appeal to the Provincial Grievance Committee (PGC). The PGC will review and make a
decision on the appeal within 30 days of receiving the complaint.
Phase 4: If the AP remains dissatisfied with the decision of the PGC or if no response is received
within the prescribed time limit, the AP can eventually take their case to the provincial court. The
court will resolve the complaint in writing and submit a copy to the appropriate authorities
including the PPC, DGC / PGC and APs. However, if the AP remains dissatisfied with the decision
of the Court, the case may be referred to the provincial court. However, if the decision of the
provincial court remains unsatisfactory for the affected person, the AP may file the complaint with
a higher court.
The PPC will be responsible for examining complaints and grievance procedures and resolutions.
PPC supervisors must have expertise and experience in social and environmental issues related to
infrastructure development. PPC may recommend further measures to resolve unresolved
complaints. The environmental consultant will provide necessary training to improve the grievance
procedure and develop capacity building programs for members of the grievance committee when
requested.
In case APs are unable to express in writing or verbally, they are encouraged to seek the help of
local groups, NGOs, family, village head or neighborhood leaders to record their complaints, and
to obtain documentation, surveys or property valuations, to ensure that when disputes occur, the
accuracy of the information provided allows all parties to be treated fairly. Throughout the
grievance process, the responsible Grievance Board will ensure that the affected people are
provided with copies of the grievance, decision or resolution.
If the dispute resolution efforts based on the grievance procedures remain unresolved or
unsatisfactory, the APs have the right to discuss their concerns or issues directly with the ADB
Office in the South-East Asia through ADB resident mission in Vietnam (VRM). If affected people
remain dissatisfied with the VRM feedback, they may contact the ADB Assistance Office directly.
ADB's accountability mechanism/ framework provides a forum where people affected by ADB-
funded projects can talk and find solutions to their problems and report non-compliance with
Page 15 of 79
ADB's policies and procedures. It includes two separate but complementary functions: problem
solving and compliance review. Complaints must be made in writing and sent to the receiving
agency. More information can be found at: (http://www.adb.org/site/accountability-
mechanism/main).
Grievance Redress mechanism: The PISC consultant has assisted the PMUs to set up a GRM
which has been approved by ADB on 26 May 2018.
The grievances redress mechanism has been incorporated into the Contractor's Environmental
Management Plans and has been disseminated to the CPCs of the project communes and the heads
of the villages. Contractors and Construction Supervisors have been trained in this content by the
PISC in each subproject such as:
• In Bac Giang, Bac Giang People's Committee issued the decision on the establishment of
the Complaints Board and the GRM process of the Project in accordance with the Decision
No. 1810 / QD-UBND dated 12/7/2018 and the Decision No. 1811 / QĐ-UBND dated
12/7/2018 of People's Committee of Bac Giang city. A grievance mechanism was
announced by the PMU at meetings with local authorities and affected people in July 2018.
In addition, the Grievance Mechanism was posted by the BG1, BG2 contractors at the site
management office, along with a form to file complaints in June 2018 and in April 2019
for BG3, BG4 contractors.
• In Mong Cai, the preliminary GRM as outlined in the uEMP was announced by the PMU
at meetings with local authorities and affected people in the first quarter of 2018. After the
final draft of the Grievance Mechanism, the contractors have posted it at the site
management office with attached form to file complaint in June 2018.
• In Lao Cai, the preliminary GRM as outlined in the uEMP and then it was integrated into
approved CEMP and disclosed and introduced by PMU/PISC to local authorities
(commune, village head) and affected people in July 2018.
As of this reporting period (from Jan to June 2019), no complaints from people or local authorities
about environmental safeguard issue in Sapa, Bac Giang and Mong Cai has been filed. However,
there are three complaints about the compensation and resettlement in all subprojects:
Table 4. Summary of Grievance Cases by Level of GRM
Location
No. of pending
grievance from
previous
reporting
period
No. of new
grievance cases for
reporting period
Total no. of
cases
received
No. of cases
resolved
No. of cases
progressed to
next level
Bac Giang
(Tran Quang Khai
and Dong Bac ring
roads)
2 0 1 1 1
Mong Cai 1 0 1 1 1
Lao Cai 2 0 2 1 1
Móng Cái subproject: Mr Lam Van Gai has petitioned to LFDC on the compensation rate for the
land that his family has reclaimed. Upto June 2019, this complain has been resolved and his family
has accepted the compensation and allowance
TDA Sa Pa: In the semi-annual report of 2018 there was 1 complain in package SP1 (Mr
NguyenAnh Tuan, Gian Tra hamlet, Sa Pa commune), to date, this complain has been resolved
and his family has accepted the compensation and allowance.
Page 16 of 79
TDA Bắc Giang: In the report of 2018’s 2nd half, there was 1 complain in package BG1 (verbally)
of 22 HHs in Doi Chet area, Huong quarter, Tho Xuong ward on the method to determine the
origin of the land in their area. On 22/6/2019, Bac giang CPC has issued written response on the
petition of Mr Le Kim Lai and other citizens in the quarter, in which the CPC determined that the
acquired land was cemetary, therefore was not entitled to compensation. Local authorities have
sent the response to the AHs. This issue will be further reported in upcoming report if there is new
development (See details on the Semi-annual Report of Resettlement Monitoring for first 6 months
in 2019)
3.4. Updated EMPs, Incorporation of EMP requirements into the
Construction Contracts and preparation of the Contractor's Environmental
Management Plan (CEMP)
The updated EMPs were included in the bidding documents for civil works during the
procurement phase. Bidders are required to consider the requirements of the EMPs when
submitting their bids.
• In Bac Giang: an uEMP (first updated) has been prepared for 4 packages (BG1, BG2,
BG3, BG4) and approved by ADB in May 2017; The first draft of the uEMP for package
BG5 has been submitted to ADB on 12/12/2018 and final version was approved by ADB
at the beginning of March 2019. Besides, package BG2 has proposed to upgrade 1.5 km
of the existing road extended from the Northeast Ring Road to the junction with road 295B
to Ha Bac Nitrogenous Fertilizer Plant, so uEMP (first updated) of the packages BG1,
BG2, BG3 and BG4 were also updated for the second time to submit to ADB in February
2019, this final revision was submitted to ADB in the second half of March 2019.
• In Mong Cai: uEMP (for MC1, MC2, MC3 packages) is included into item 6 chapter VII,
Section 2 of the bidding documents and into the Works contracts.
• In Sa Pa: uEMP has been prepared for all packages (SP02, SP03, SP01) and approved by
ADB in May 2017 and October, 2017 and Febuary 2018 respectively. For the SP 02
“Upgrading of Provincial Route 152 (Section from Sa Pa Town to Ban Den Cross-road),
due to changes of technical design (construct viaducts instead of road), the uEMP of this
component has been updated again in March,, 2019 which have been reviewed by project
owner before submit to ADB for approval. In May, 2019, the uEMP of SP1 have been
finalized and awaiting for No Objection Letter from ADB.
Construction contractors have prepared CEMPs to submit to CSCs and PMUs for approval since
April 2018, such as:
• In Bac Giang: April and May 2018 for BG2 and BG1 packages; in Jan 2019 for BG3
package and in April 2019 for BG4 package.
• In Mong Cai: in April and May 2018 for MC1 and MC2 packages; and MC3 package in
January 2019.
• In Sa Pa: in April and July 2018 for SP2 and SP3 packages and the CEMP of SP01 was
prepared by constructors and revised by PISC in December 2018 and then approved by
PMU Lao Cai in December,2018.
Page 17 of 79
The environmental and safety monitoring tasks included in the contract with the Construction
Supervision Consultant (CSC) require CSCs to regularly monitor environmental compliance and
safety at construction sites.
Table 5. Status of compliance with updated EMPs, incorporation EMP requirements and
CEMPs
Environmental requirements Compliance Remark
Y N P
1. Updated EMPs √ - In Bac Giang: an uEMP (first updated) has
been prepared for 4 packages (BG1, BG2, BG3,
BG4) and approved by ADB in May 2017; The
first draft of the uEMP for package BG5 has
been submitted to ADB on 12/12/2018 and and
final version was approved by ADB at the
beginning of March 2019. Besides, package
BG2 has proposed to upgrade 1.5 km of the
existing road extended from the Northeast Ring
Road to the junction with road 295B to Ha Bac
Nitrogenous Fertilizer Plant, so uEMP (first
updated) of the packages BG1, BG2, BG3 and
BG4 were also updated for the second time to
submit to ADB in February 2019, this final
revision was submitted to ADB in the second
half of March 2019
- In Mong Cai: an uEMP has been prepared for
all packages (MC1, MC2, MC3) and approved
by ADB in Jun 2017.
- In Lao Cai: uEMP has been prepared for all
packages (SP2, SP3, SP1) and approved by
ADB in May 2017 and October, 2017 and
February, 2018 respectively. For the SP 02
“Upgrading of Provincial Route 152 (Section
from Sa Pa Town to Ban Den Cross-road), due
to changes of technical design (construct
viaducts instead of road), the uEMP of this
component has been updated again in March,
2019 and await for No Objection Letter from
ADB
2. Incorporation of EMP requirements
into the Construction Contracts
√
- In Bac Giang: uEMP (for BG1, BG2, BG3,
BG4 packages) is included into item 6 chapter
VII, Section 2 of the bidding document and into
the Works contract (Section IV- the specific
terms of the works contract including items 24,
40, 74).
- In Mong Cai: uEMP (for MC1, MC2, MC3
packages) is included into item 6 chapter VII,
Section 2 of the bidding documents and into the
Works contracts.
- In Lao Cai: article of uEMP (for SP02
packages) is included into article 75, page 36 of
contract.
Page 18 of 79
Environmental requirements Compliance Remark
Y N P
article of uEMP (for SP03 packages) is included
into article 27, page 33 of contract.
article of uEMP (for SP03 packages) is included
into article 26, page 35 of contract
3. Preparation of the CEMPs
√
- In Bac Giang: April and May 2018 for BG2 and
BG1 packages; in Jan 2019 for BG3 package and
in April 2019 for BG4 package.
- In Mong Cai: CEMPs have been submitted and
approved in April (MC1) and May 2018 (MC2).
For CEMP of MC3 has been prepared by the
constructor (JV of Irrigation Construction Joint
Stock Company I and Bac Ninh Construction
JSC), and PMU approved in January, 2019.
- In Lao Cai: CEMPs have been submitted and
approved in April (SP02) and July 2018 (SP03).
For CEMP of SP01 was prepared by constructor
and reviewed by PISC in December, 2018. It was
approved, in late December, 2018.
IV. EMP IMPLEMENTATION STATUS
4.1. Training and capacity building activities
Capacity building activities, training (with main contents such as (i) cleartify Stakeholders’ role
and responsibilities in implementing EMP; (ii) guideline for EMP Requirements (CEMP, monthly
reports for contractor and CSC); (iii) guideline for implementation mitigation measures in the
site, etc) for Environmental Safeguard Officers of PMUs, Contractor, Supervision Consultant had
been conducted at:
- Bắc Giang: for packages BG1 and BG2 on 5/4/2018 and 25/6/2018; for package BG3
on 25/12/2018; and package BG4 on 9/5/2019.
- Móng Cái: for packages: MC1 and MC2 on 29 and 30/3/2018, and MC3 on 05/11/2018.
- Sa Pa: for packages SP02 and SP 03 from 6-7/8/2018; For package SP01 will be
conducted in July, 2019.
4.2. Compliance with loan terms
Table 6. Status of compliance with ADB loan terms
Loan terms Compliance Remark
Y N P
Borrower must ensure that
(i) The project is implemented in accordance with the
Borrower's Law and Environment Regulations, as well as
ADB's 2009 Safeguard Policy (ADS SPS) and that no
significant damage to the natural environment shall be
incurred by the design, construction, operation and
maintenance of the project;
√
All legal documents on
environmental issues comply
with Government and ADB
policies, such as: Initial
Environmental Assessment
(IEE), Environmental
Management Plan (EMP) and
Page 19 of 79
Loan terms Compliance Remark
Y N P
Environmental Impact
Assessment (EIA). prepared
and approved by the relevant
Authority of Vietnam and
ADB.
(refer to Table 6)
(ii) If there is a difference between the Borrower's laws and
regulations, and the ADB's SPS, then the ADB policy will
apply;
√
Some discrepancies such as:
ADB requires that project
information sheets are
expressed also in Ethnic
languages.
Package SP02 has achieved
this.
Thanks to the location of the
project, where many Hmong
people reside and benefit, the
GRM has been translated into
Hmong language.
(iii) ADB's environmental policies and requirements are
applied and implemented for all project components
regardless of financial sources;
√
Environmental management plan
does not address financial
sources for environmental
monitoring, but when
negotiating and implementing
the contract, the PMUs still
require the Contractors to
allocate funds to meet
environmental requirements and
work safety.
This content is included in the
Works contract
(refer to Table 6)
(iv) Contracts for construction of works under the Project
include specific measures to minimize negative
environmental impacts caused by construction activities in
accordance with the requirements of the Environmental
Management Plan the preparation for the Project and the
EMP will be included in the bid and the contract requires the
contractor to comply with all terms;
√
- In Sapa subproject: uEMP
conditions are included in
bidding documents and contract
of construction of 3 packages
SP01, SP02 and SP03 in Sapa.
- In Bac Giang subproject: the
uEMP (first updated) has been
implemented for packages
BG1, BG2, BG3, BG4. The
final uEMP for package BG5
has been aproved by ADB at
the end of March 2019.
Besides, package BG2 has
proposed to upgrade 1.5 km of
the existing road extended from
the Northeast Ring Road to the
junction with road 295B to Ha
Bac Nitrogenous Fertilizer
Page 20 of 79
Loan terms Compliance Remark
Y N P
Plant, so uEMP (first updated)
of the packages BG1, BG2,
BG3 and BG4 were also
updated for the second time to
submit to ADB in February
2019, this final revision was
submitted to ADB in the second
half of March 2019
- In Mong Cai, the uEMP has
been prepared for packages
MC1, MC2 and MC3.
all updated EMPs approved by
ADB were included in the
bidding documents for civil
works during the procurement
phase. Bidders are required to
consider the requirements of the
EMPs when submitting their
bids
(refer to Table 6)
(v) budget and human resources allocated to the
implementation of the EMP;
√
The budget for implementing
CEMP is included in the
corresponding contract costs.
PMUs, PCCs and CSCs have
regularly assigned officers to
inspect the implementation of
CEMPs by contractors.
(refer to Table 6)
(vii) environmental approval as requested by the Borrower is
to be collected promptly and copies of such approvals will be
submitted to ADB upon issuance;
√
- In Bac Giang, the EIA report
for all component has been
approved by Bac Giang PPC
according to Decision No. 1784 /
QĐ-UBND of Bac Giang
People's Committee dated
28/9/2015. By the updating the
design detail for package BG5,
Bac Giang PMU (with supported
by PISC) has submitted these
changes and supplements on EIA
report for Bac Giang subproject
to Bac Giang DONRE and has
been approved by the Decision
No. 1990 / QD-UBND dated
December 21, 2018 by Bac
Giang Provincial People's
Committee.
- In Mong Cai, the EIA report
for all component has been
approved by Quang Ninh PPC
Page 21 of 79
Loan terms Compliance Remark
Y N P
according to Decision No. 1352 /
QĐ-UBND of Quang Ninh
People's Committee dated
23/10/2015.
- In Lao Cai, the EIA report for
all component has been
approved by Lao Cai PPC
according to Decision No. 3163 /
QĐ-UBND of Lao Cai People's
Committee dated 17/9/2015.
(ix) construction works performed by the contractor are
adequately monitored to ensure compliance with the EMP; √
Continuous monitoring is
carried out by the CSC’s ESs
and is routinely monitored by
the PMUs and PISC
(x) The new or additional environmental assessment report
shall be prepared in accordance with the ADB's SPS if any
additional items or changes in the Project, such as location
and design, would result in negative impact on the
environment and not within the scope of the ADB approved
environmental evaluation report; These documents will be
submitted to ADB for clearance prior to the implementation
of additional components or major changes and must be
approved by the relevant approval body (s);
√
EMPs were updated prior to the
construction phase. There is no
significant change during the
construction phase that
guarantees update of the EMP.
Particularly, in SP02 package in
Sapa, due to a change in design,
the new EMP was updated in
March, 2019 and now await for
No Objection Letter from ADB.
In Bac Giang, the final uEMP
for package BG5 has been
aproved by ADB at the end of
March 2019.
(refer to Table 6)
(xi) if any apparent unforeseeable environmental impacts
arise during the implementation of the project, corrective
action plans must be prepared and submitted to ADB for
approval and implementation of the corrective action plan is
mandatory
There were no unexpected
environmental impacts during
this reporting period.
(xii) establish an environmental grievance redress mechanism
satisfactory to ADB to receive and address concerns,
complaints and grievances of the people on the performance
of the project; and √
GRM has been prepared and
approved on 26/5/2018
GRM has been communicated
to CSC’s and contractor's
environmental staffs, and
disseminated to communes and
village heads in the project areas
(refer to Section 3 above)
(xiii) a six-month report on the implementation of the EMP
submitted to ADB.
√
The first SEMR for the last 6
months of 2017 (completed)
submitted to ADB for approval
in April 2018;
The second SEMR for Jan to
June 2018 has been submitted
Page 22 of 79
Loan terms Compliance Remark
Y N P
ADB in Aug 2018 and finalized
in Nov 2018.
The semi-annual monitoring
report for July to Dec 2018 has
been submitted ADB in Jan
2019.
This semi-annual monitoring
report for Jan to Jun 2019 will
be submitted ADB in July
2019.
4.3. Compliance with GoV regulations
4.3.1. Updated EIA
During the project preparation phase, the PMUs have complied with the Vietnamese Government's
Environmental Regulations. EIA reports for each subproject have been appraised and approved by
the PPCs, as follows:
Table 7. Status of compliance with the GoV's Environmental requirements
Environmental requirements Compliance Remark
Y N P
Approved EIA
(Comply with the Law on
Environmental Protection in 2014 and
relevant regulations of the GoV)
√
- In Bac Giang, the EIA report for all component
has been approved by Bac Giang PPC according
to Decision No. 1784 / QĐ-UBND of Bac Giang
People's Committee dated 28/9/2015. By the
updating the design detail for package BG5, Bac
Giang PMU (with supported by PISC) has
submitted these changes and supplements on
EIA report for Bac Giang subproject to Bac
Giang DONRE and has been approved by the
Decision No. 1990 / QD-UBND dated December
21, 2018 by Bac Giang Provincial People's
Committee.
- In Mong Cai: the EIA report for all component
has been approved by Quang Ninh PPC
according to Decision No. 1352 / QĐ-UBND of
Quang Ninh People's Committee dated
23/10/2015
- In Lao Cai, the EIA report for all component
has been approved by Lao Cai PPC according
to Decision No. 3163 / QĐ-UBND of Lao Cai
People's Committee dated 17/9/2015.
During the detail design phase, there is no change in design, scale, location and programme of
the project, thus updating the EIA is not necessary expectation to Bac Giang subproject. Due to
the change in wastewater treatment technology and the addition of the existing wastewater
treatment plant (package BG5), Bac Giang PMU (with supported by PISC) has submitted these
changes and supplements on EIA report for Bac Giang subproject to Bac Giang DONRE and has
Page 23 of 79
been approved by the Decision No. 1990 / QD-UBND dated December 21, 2018 by Bac Giang
Provincial People's Committee.
Besides, package BG2 has proposed to upgrade 1.5 km of the existing road extended from the
Northeast Ring Road to the junction with road 295B to Ha Bac Nitrogenous Fertilizer Plant, so
uEMP (first updated) of the packages BG1, BG2, BG3 and BG4 were also updated for the second
time to submit to ADB in February 2019, this final revision was submitted to ADB in the second
half of March 2019 Bac Giang PMU (with supported by PISC) has submitted these changes and
supplements on EIA report to Bac Giang DONRE for approval in April 2019, however, there isn't
still the decision to approval for this report by Bac Giang PPC until now. It is expecting to
approval this report in August 2019.
4.3.2. Licensing for Stone Quarries, Construction Materials Mines and
Disposal Sites
a. In Móng Cái
The permits required for the quarries, mines of the MC1 and MC2 subprojects under the Mong
Cai subproject are largely collected by the PPMU during the project preparation phase. The status
of licenses for mining, mines and disposal sites can be summarized as follows:
- Sources of construction materials: The supplier is Tri Duc Construction Investment and
Development JSC, located at Hoa Binh Boulevard - Upper Trung - Ninh Duong Ward -
Mong Cai. This company supplies sand and stone for two packages MC1 and MC2 and they
have full legal documentation for this supply. Information on sand and stone supply units
was verified by the CSC in Official Letter No. 05.17 / TVGS-GMS2 sent to the PMU on 18
November 2017. Fresh concrete for MC3 is supplied by Quang Thao Construction JS
Company (address: Zone 7 km2, Hai Yen ward, Mong Cai city, Quang Ninh). The whole
soil from excavation is re-used for leveling.
- Source of filling material: Demand for backfill for both sub-projects is 66,700 m3 and the
readily available sources (from the hills located in the area of West Ka Long WWTP and a
small part from the construction of drainage lines) is 17,700 m3 respectively. Currently, the
subproject is still using readily available resources. For additional resources, during the
project preparation phase, the selected field is within Hong garden, Hamlet 5, Quang Nghia
commune, Mong Cai city (about 25 km from the center of the city). However, the licensing
of soil mining in the Mong Cai area is difficult due to licensing procedures and due to
adjustments in the provincial planning. The PMU and its contractors are working to
accelerate the licensing process and take into account land use plans at licensed mines
outside Mong Cai to avoid delays. Up to now (Q4/2018), there still is a shortage of filling
material for WWTP of MC1 (the contractor is still applying for environmental license for
the current mine, but there are other viable alternatives). Project owner and CSC have issued
warnings for contractor.
- Disposal sites: Construction spoil includes soil dredged from the construction site of the
Eastern WTP and a part of the spoil is dredged from the drainage ditch (approx. 500-600
m3, mainly sandy soil and sediment), which will be temporarily transported to Ngoc Ha
Construction Joint Stock Company’s disposal site (a sub-project subcontractor) in Hai Hoa
Page 24 of 79
ward (about 8 km from Mong Cai center). At present, most of the construction spoil is fertile
soil (in Eastern WTP) that can be recycled for farming. The whole soil from excavation is
re-used to level in MC3 concstruction site.
b. In Bắc Giang
The licenses required for the quarries, mines of the BG1, BG2 subprojects in the Bac Giang
subproject are largely collected by the PPMU during the detailed design phase. Licensing status
for mining and disposal sites can be found in the uEMPs.
Sources of construction materials:
The construction materials such as cement, iron, steel, bentonite, stone ... from suppliers in Bac
Giang province and surrounding areas to serve two packages (BG1, BG2) which have been
submitted by the contractor and approved by CSC, PPMU before and during construction.
Source of filling material:
- Package BG1: The contractor has proposed the supply of source of filling material and has
been approved by CSC and PPMU from the soil mine in Deo Rung hill of Bao Loc 1 village,
Bao Son commune, Luc Nam district, Bac Giang province.
- Package BG2: The contractor has proposed the supply source of filling material and has been
approved by CSC and PPMU from 2 soil mines including (i) soil mine in Nui hill – Nam Le
village – Xuong Lam commune – Lang Giang district – Bac Giang province and soil mine in
Minh Son commune - Huu Lung district - Lang Son province. The supply source of stone for
construction is the stone mine Vo Noi village - Ho Dung commune - Huu Lung district - Lang
Son province.
Disposal sites: Particularly for spoils of specific packages as follow
- Package BG1: The contractor has signed a contract with Bac Giang Urban Public Works Joint
Stock Company to collect, transport and dispose of excavated soil in Song Mai commune,
Bac Giang city, to make use of vacant land in the project area. There is a need to level instead
of transport to the Da Mai landfill site 6km away from the project area.
- Package BG2: The contractor has signed a contract with Hoan Chinh Construction Materials
and Trading Company Limited to collect, transport and dispose of waste in Dong Bong, Nam
Ngan Village, Quang Chau Commune, Viet Yen District, Bac Giang Province to fill subsided
areas (eg, lagoons, riversides).
- Package BG3: the contractor has been approved the disposal site for dredged material of
ponds. The disposal of dredged material area is approved that is Da Mai landfill, in
accordance with the approved uEMP, it is far from about 6km to the project area.
During construction and transportation phases, the use of quarries, mines, and environmental
protection will be regularly monitored at the disposal sites and on major transport routes.
c. In Sapa
Fill mines: Road fill is taken from the excavated volume, the remaining will be excavated from
(I) Mine 1: Km5 + 700 on the left of the village road of Lao village, Lao Chai commune, (ii) Mine
2: Km11+100 on the left side of the village road of Su Pan.
Page 25 of 79
Sand mine: Sand Mine No.1 (Bao Nhai Sand Mine): Located at the beginning of the route at Km
5 + 00 TL153 on the right side of Bac Ngam - Bac Ha, Bao Tan 2 village, Bao Nhai commune,
Bac Ha district. The mine has been licensed and under the management of mining cooperative Anh
Tu. Quality: coarse sand with little gravel, good quality sand and in stable, favorable conditions
for transportation.
Construction sand mine 2 (Bến Đền sand mine): Located at the beginning of the route at Km
26 + 600 Highway 4E, about 0.5 km left in Gia Phu commune, Bao Thang district. The mine has
been licensed and is under the management of production and trading company Gia Phu Building
Materials. Quality: coarse sand with little gravel, good quality sand and in stable, favorable
conditions for transportation.
Construction sand mine 3 (Cốc San sand mine): Located at the beginning of the route at km
133 + 300 QL4D about 1.3 km turn left of the route, following the Road to Canh San hydropower
scheme in Luong Do village, Coc San commune, Bat Xat district. The mine is licensed and under
the management and operation of the Commune People's Committee. Quality: coarse sand with
little gravel, good quality sand and and in stable, favorable conditions for transportation.
The quarry at Trung Chai field is located at the end of the route, on the left of the road Km 99 +
500 QL4D, belonging to the group 12 Sa Pa town, Sa Pa district. The quarry has been licensed and
under the management and harvest of Kim Tuyen One Member Limited Company. Quality: This
is sedimentary rock, medium intensity, gray color, blue gray, block structure. Road to the mine is
convenient, from the mine to the beginning of the route is about 5km. Current production is about
1000m3 / day.
Other materials: timber collected in Sa Pa center, Iron and steel in Thai Nguyen, concrete in the
center of Lao Cai city, Plastic in Hai Phong.
Disposal sites
Design consultants, investors and local authorities have agreed on the selection of reasonable
disposal sites. These sites are planned by Sapa DPC for disposal sites. These are the existing sites
of district. The detailed as follows:
(i) Site 1: at Km1+00 – Km1+250 on the right of Provincial Road 152, Sapa town, Sapa district.
(ii) Site 2: at Km11+400 – Km11+600 on the right of Provincial Road 152, Su Pan commune,
Sapa district.
(iii) Site 3: Km14+500 – Km14+700 on the right of Thanh Kim- Bản Phùng route, Ban Ho
commune.
4.4. Results of environmental compliance monitoring
4.4.1. Status of EMP implementation
The inspection methodology involved reviewing project document and CSC reports, field
observations of the work areas and relevant site supplemented with photographic documentation
and formal and informal interviews with workers, residents, stakeholders and affected persons
(APs).
The site inspections for EMP compliance are conducted daily by CSCs, joint meetings among
CSCs and Contractors shall be organized whenever the environmental and safety issues are
Page 26 of 79
identified and corrective actions are requested. The monitoring activities relating to environment
and safety are shown in Table below.
Table 8. Environmental and Safety monitoring activities
Mission/Task Date Location of site visits Conducted by Whom
Monitoring on
Contractor’s EMP
compliance
Daily sites of the packages that are
being executed.
Staffs of CSCs
Monitoring on EMP
implementation and
compliance for
Semiannual
environmental repor
Bac Giang: 25/3;
9&20/5; and
24&25/6/2019
Bac Giang: BG1, BG22, BG3
and BG4 packages
Joint site inspections
of PPMU’s
EO, CSC’s EO and PISC
environmental specialists.
Mong Cai:
22-25/2/2019
12-13/3/2019
22-23/4/2019
9-12/5/2019
Mong Cai: MC1, MC2 and
MC3
Sa Pa: 27-29/3/2019;
From 6-9/5/2019
And From 25-
29/6/2019
Sa Pa: SP02 and SP03
packages and SP01
4.4.2. Findings during the site inspections
In the first half of 2019, site inspections were conducted by the PISC environmental specialists to
validate and monitor the implementation of EMP for construction packages in Bac Giang, Mong
Cai and Sa Pa. The site visits were conducted together with the PPMUs, the CSCs and the relevant
contractors in the three provinces. The site-visits suggested that the construction works in three
provinces are mostly minor that did not generate significant adverse environmental impacts. There
are some minor environmental and safety issues that the contractors have not complied with to
follow approved EMPs, as indicated in Table below.
Table 9. Findings during the site inspections
Issues/Concerns/Findings Pictures
Bac Giang - BG1 Package
2 The main construction items of package BG2 were completed in April 2019 (except for about 100 meters of road at the gate of Methadone-
Treatment Center, which is pending for permission of the Ministry of Public Security), so that the site inspection was not conducted by PISC in
this period.
Page 27 of 79
Issues/Concerns/Findings Pictures
Issue: Risk of waterway's safety.
Description: Risk of boats crashing into BG1's
river infrastructure at night because there are no
becons
Location: on the construction site of Ben
Huong bridge.
Issue: Risks of worker safety
Description: lack of additional life jackets for
workers when executing works on Thuong river
according to regulations.
Location: on the construction site of Ben
Huong bridge.
Bac Giang -BG3 Package
Issue: Odor, exhaust mitigation
Description: Odor generated from dredged
materials of ponds that can affect community's
health.
Location: on the construction site of Soc Trang
pond.
Bac Giang -BG4 Package
Page 28 of 79
Issues/Concerns/Findings Pictures
Issue: Dust emission
Description: Dust generated from construction
activities in BG4 site, especially on the dyke-
road of Thuong river.
Location: on the construction site of Van Son
pumping station
Issue: Risk of worker's safety
Description: Safety risks in BG4 due to (i) lack
of safety measures and insufficient protective
equipment, especially for workers who work in
high places, (ii) No medical equipment for
emergency first aid.
Location: on the construction site of Van Son
pumping station
Issue: Risk of flooding
Description: The risk of flooding when rain in
BG4 due to excavated spoil in BG4 is deposited
in the drainage canal, blocking the existing Van
Son channel
Location: on the construction site of Van Son
pumping station.
Mong Cai -MC1 Package
Issue: Waste management
Description: Domestic waste is not collected
into containers or a right place.
Location: WWTP construction site
Issue: Lack of toilet in workers’ camp
Description: There are no toilets in workers’s
camp, and the workers temporarily use pit
latrines.
Location: WWTP construction site
Page 29 of 79
Issues/Concerns/Findings Pictures
Issue: Risks of community safety and traffic
Description: There are risks of transport safety
for people going through the construction site.
The risks caused by (i) site has not been fully
restored after laying of pipeline, (ii) warning
sign boards do not meet requirements and (iii)
materials are not gathered in the right place.
Location: on the construction site at Hai Xuan
service road
Issue: Risk of worker's safety
Description: Workers do not wear PPEs while
working althought they all were fully provided
with adequate PPEs.
Location: Treatment wastewater plant
Mong Cai -MC2 Package
Issue: Risks of community safety and traffic
Description: There are risks of transport safety
for people going through the construction site.
The risks are caused by (i) no fence installed for
isolation of construction activities, (ii) not
enough warning sign boards installed, (iii) site
has not been fully restored after laying of
pipeline.
Location: on the construction site of Hai Yen
service road
Page 30 of 79
Issues/Concerns/Findings Pictures
Issue: Waste management
Description: No dust bin in worker camp and
domestic waste is not collected into containers
or a right place.
Location: WWTP construction site
Issue: Risk of worker's safety
Description: Workers do not wear PPEs while
working althought they all were fully provided
with adequate PPEs.
Location: WWTP construction site
Mong Cai -MC3 Package
Issue: Waste management
Description: Construction waste has not been
collected into containers or a right place.
Location: Sitecamp in Huu Nghi street
Issue: Risk of worker's safety
Description: Workers do not wear PPEs while
working althought they all were fully provided
with adequate PPEs
Location: MC3 construction site (Ka Long
river)
Sa Pa -SP2 Package
Page 31 of 79
Issues/Concerns/Findings Pictures
Issues: Contractors have installed fences around
the site and warning signs. However, there are
some places having no signposts/guides or signs
or poor quality of sign or the fence are not
qualified.
Location: Construction site of SP2
Issues: Worker do not fully use personal
protection equipment
Location: At some construction sites
4.4.3. EMP implementation assessment
Table 10. EMP implementation assessment in Bac Giang subproject
EMP
requirement
Assessment on Compliance with EMP in Bac Giang subproject
Package BG1 Package BG3 Package BG4
Dust
suppression
Being Complied
- Watering is carried out well
at the site.
- Material trucks are covered
with plastic sheets.
- Material yards are covered
by plastic sheets.
Being Complied
- Watering is carried out well
at the site.
- Material trucks are covered
with plastic sheets.
- Material yards are covered
by plastic sheets.
Partly Complied
- Watering is not carried out
fully at the site. The
contractor must increase
watering at the site,
especially on dyke-road of
Thuong river.
- Material trucks are covered
with plastic sheets.
Page 32 of 79
EMP
requirement
Assessment on Compliance with EMP in Bac Giang subproject
Package BG1 Package BG3 Package BG4
- Material yards are covered
by plastic sheets.
Noise limitation Being Complied
.- Restrict working loud
activities as pile driving in
Ben Huong bridge's site after
10pm and before 5am.
- Check licenses required by
Vietnamese regulations for
each type of
vehicle/equipments before
constructing.
- Maintain equipment in
proper working order.
Being Complied
- Restrict working loud
activities as
sediments/materials digging
in Soc Trang pond's site after
10pm and before 5am.
- Check licenses required by
Vietnamese regulations for
each type of
vehicle/equipments before
constructing.
- Maintain equipment in
proper working order.
Being Complied
- Restrict working loud
activities as basement
foundation digging for Van
Son pumping station after
10pm and before 5am.
- Check licenses required by
Vietnamese regulations for
each type of
vehicle/equipments before
constructing.
- Maintain equipment in
proper working order.
Water quality
protection
Being Complied
- There is no activity of
discharging domestic
wastewater from workers
into Thuong River because
the contractor has used
available toilets in the renting
houses of local people.
- The Contractor has installed
sheet piles to reinforce
Thuong River bank to
mitigate the risk of
erosion/landslide during the
bridge abutment
construction;
- The Contractor has
prepared the emergency
flood response plan before
the wet season.
- Construct temporary drain
to prevent localized flooding.
Being Complied
- There is no vehicle washing
station at sites.
- There is no activity of
discharging domestic
wastewater from workers
into Soc Trang pond because
the contractor has used
available toilets in the renting
houses of local people.
- The Contractor has
prepared the emergency
flood response plan before
the wet season.
- Construct temporary drain
to prevent localized flooding.
Partly Complied
- The contractor has
constructed the septic-tank
toilet in the temporary camp
before discharging into Van
Son channel. .
- Erosion (such as road bed,
river bank): At present, there
are no construction activities
in the weak areas.
- The Contractor has
prepared the emergency
flood response plan before
the wet season.
- Risk of flooding due to rain
in BG4. Excavated soil in
BG4 is deposited in the
drainage canal, blocking the
existing Van Son channel.
Occupational
and Community
health and
safety plan
Partly Complied
- Place warning signs /
instructions at the site and
intersections with the current
road. But,
+ Lack of additional life
jackets for workers when
executing works on Thuong
river.
+ There are risks of boats
crash into BG1's river
infrastructure at night
because there are no lights.
- Material trucks are covered
with plastic sheets on the
local roads.
Being Complied
- Place warning signs /
instructions at the site and
intersections with the current
road.
- Material trucks are covered
with plastic sheets on the
local roads.
- Regulations and training for
workers on regulations,
community communication.
- The regulation prohibiting
drinking, gambling for
worker: The contractor has
reminded workers; these
contents have been displayed
as rules at sites/ rented
houses.
Partly Complied
- Place warning signs /
instructions at the site and
intersections with the current
road.
- Material trucks are covered
with plastic sheets on the
local roads.
- Regulations and training for
workers on regulations,
community communication.
- Camp regulation
prohibiting drinking,
gambling: The contractor has
reminded workers; these
contents have been displayed
as rules at sites/ camps.
Page 33 of 79
EMP
requirement
Assessment on Compliance with EMP in Bac Giang subproject
Package BG1 Package BG3 Package BG4
- Regulations and training for
workers on regulations,
community communication.
- The regulation prohibiting
drinking, gambling for
workers: The contractor has
reminded workers and these
rules have been displayed at
sites/ rented houses.
- Provide the first-aid kit at
camps or site office.
- Daily cleaning of
construction area after work.
- Fire protection: The
contractor has reminded
workers. The contractors
have provided fire
extinguisher in the kitchen/
storage.
- Provide the first-aid kit at
camps or site office.
- Fire protection: The
contractor has reminded
workers and provided fire
extinguisher in the kitchen/
storage.
- Safety risks in BG4 due to
(i) lack of safety measures
and insufficient protective
equipment, especially for
workers who work in high
places, (ii) No medical
equipment for emergency
first aid.
- Daily cleaning of
construction area after work.
- Fire protection: The
contractor has reminded
workers and provided fire
extinguisher in the kitchen/
storage.
Excavated soils,
erosion control,
and construction
waste
management
Being Complied
- Workers' daily solid waste
has been collected locally. -
Fully equipped with
specialized garbage bins for
collection and classification
of domestic and hazardous
solid waste on the sites and
rented houses.
- Treatment of excavation for
leveling or backfill, roadside:
+ Re-use part of excavation
volume that ensures the
standards for roadside and
backfill.
+ The remaining excavation
volume, the contractor signs
the contract with the service
unit for collection, transport,
and treatment at the disposal
site in accordance with
regulations.
(The contractor has signed a
contract with Bac Giang
Urban Public Works Joint
Stock Company to collect,
transport and dispose of
excavated soil in Song Mai
commune, Bac Giang city, to
make use of vacant land in
the project area).
Being Complied
- Workers' daily solid waste
has been collected locally. -
Fully equipped with
specialized garbage bins for
collection and classification
of domestic and hazardous
solid waste on the sites and
rented houses.
- The contractor signs the
contract with the service unit
for collection, transport, and
treatment at the aproved
disposal site (at Da Mai
landfill).
Party Complied
- Workers' daily solid waste
has been collected locally. -
Fully equipped with
specialized garbage bins for
collection and classification
of domestic and hazardous
solid waste on the sites and
camps.
- Treatment of excavation for
leveling or backfill: Re-use
part of excavation volume
that ensures the standards for
backfill.
- However, there is still a
potential risk of flooding
when rain in BG4 due to
excavated soil in BG4 is
deposited in drainage canal,
blocking Van Son canal.
Domestic and
hazardous waste
management
Being Complied
- Contractor has equipped
collection and segregated
bins for hazardous waste in
accordance with regulations.
Being Complied
- Contractor has equipped
collection and segregated
bins for hazardous waste in
accordance with regulations.
Being Complied
- Contractor has equipped
collection and segregated
bins for hazardous waste in
accordance with regulations.
Page 34 of 79
EMP
requirement
Assessment on Compliance with EMP in Bac Giang subproject
Package BG1 Package BG3 Package BG4
HWs generation in this phase
is insignificant.
HWs generation in this phase
is insignificant.
HWs generation in this phase
is insignificant.
Table 11. EMP implementation assessment in Mong Cai subproject
EMP
requirement Assessment on Compliance with EMP in Mong Cai subproject
Package MC1 Package MC2 Package MC3
Dust
suppression
Being Complied
Watering is carried out
regularly
Material trucks are covered
with plastic sheets.
Material yards are covered
by plastic sheets.
Partly Complied
Watering is not carried out
regularly
Material trucks are covered
with plastic sheets.
Material are not covered by
plastic sheets
Being Complied
Watering is carried out
regularly
Material trucks are covered
with plastic sheets.
Material yards are covered
by plastic sheets.
Noise limitation Being Complied
Restrict working loud
activities after 10pm and
before 5am.
To equip personal protective
equipment (PPEs) for
workers (such as workwear,
helmet, ear muffs, etc).
Being Complied
Restrict working loud
activities after 10pm and
before 5am.
To equip personal protective
equipment (PPEs) for
workers (such as workwear,
helmet, ear muffs, etc).).
Being Complied
Restrict working loud
activities as basement
digging or concrete pour in
Ka Long bank (Huu Nghi)
after 10pm and before 5am.
Loud activities after 10pm
and before 5am.
To equip personal protective
equipment (PPEs) for
workers (such as workwear,
helmet, ear muffs, etc).
Water quality
protection
Partly Complied
There is no vehicle washing
station at site
Use available toilets in the
rented houses as camps for
workers working in
collection pipeline
construction sites (Tran Phu,
Dao Phuc Loc, Hoang Quoc
Viet streets). However, there
are no septic toilets in
Eastern WWTP construction
site.
Erosion: At the present time,
construction activities are
being carried out far from the
Ka Long River bank so it
does not affect the quality of
river water.
The Contractor has prepared
the emergency flood
response plan before the wet
season.
Construct temporary drain to
prevent localized flooding.
Being Complied
There is no vehicle washing
station at site
Use available septic toilets at
site (WWTP construction
site).
Erosion: At the present time,
construction activities are
being carried out far from the
Khe Re stream but it does not
affect the quality of river
water.
The Contractor has prepared
the emergency flood
response plan before the wet
season.
Construct temporary drain to
prevent localized flooding.
Being Complied
There is no vehicle washing
station at site
There are septic toilets in
camps/sites.
Erosion: At the present time,
new construction activities
are being carried at the banks
of Ka Long river, and it does
not affect the quality of river
water due to reasonable
construction methods.
The Contractor has prepared
the emergency flood
response plan before the wet
season.
Construct temporary drain to
prevent localized flooding.
Page 35 of 79
EMP
requirement Assessment on Compliance with EMP in Mong Cai subproject
Package MC1 Package MC2 Package MC3
Occupational
and Community
health and
safety plan
Partly Complied
Place warning signs /
instructions are installed at
the main sites (pump station,
drainage, WTTP construction
sites). However, there is still
a lack of fence for isolation
of construction activities in
Hai Xuan commune.
Material trucks are covered
with plastic sheets on the
local roads.
Regulations and training for
workers on regulations,
community communication.
Camp regulation prohibiting
drinking, gambling: The
contractor has reminded
workers. However, these
contents have not been
displayed as rules at sites/
camps.
Provide the first-aid kit at
camps or site office.
Daily cleaning of
construction area is
implemented after work but
sometimes this procedure is
not operated.
Fire protection: The
contractor has reminded
workers and provided fire
extinguisher in the worker
camp.
There are not toilets in
workers’s camp and workers
temporarily use poor
sanitation toilet.
Partly Complied
Place warning signs /
instructions at the site
including pump station,
WTTP construction sites but
excluding drainage
construction sites (Hai Yen
commune). However, there is
still a lack of fence for
isolation of construction
activities in Hai Yen
commune.
Material trucks are covered
with plastic sheets on the
local roads but construction
materials are not covered or
enclosed by fences at
drainage site at Hai Yen
commune’s road.
Regulations and training for
workers on regulations,
community communication.
Camp regulation prohibiting
drinking, gambling: The
contractor has reminded
workers. However, these
contents still have not been
displayed as rules at sites/
camps.
Provide the first-aid kit at
camps or site office.
Irregularly cleaning of
construction area after work.
Fire protection: The
contractor has reminded
workers and provided fire
extinguisher in the worker
camp.
Partly Complied
Place warning signs /
instructions are installed at
the sites
Material trucks are covered
with plastic sheets on the
local roads.
Construction materials are
covered or enclosed by
fences.
Regulations and training for
workers on regulations,
community communication.
Camp regulation prohibiting
drinking, gambling: The
contractor has reminded
workers. However, these
contents have not been
displayed as rules at sites/
camps.
Camp regulation prohibiting
drinking, gambling: The
contractor has reminded
workers. However, these
contents stil have not been
displayed as rules at sites/
camps.
Provide the first-aid kit at
camps or site office.
Regularly cleaning of
construction area after work.
Fire protection: The
contractor has reminded
workers and provided fire
extinguisher in the worker
camp.
Excavated soils, erosion control, and construction
waste
management
Being Complied
Construction spoil includes
soil dredged from the
construction site of the
Eastern WTP and a part of
the spoil is dredged from the
drainage ditch (approx. 500-
600 m3, mainly sandy soil
and sediment), which will be
temporarily transported to
Ngoc Ha Construction Joint
Stock Company’s disposal
site (a sub-project
subcontractor) in Hai Hoa
ward (about 8 km from
Mong Cai center). At
present, most of the
Being Complied
There is not soil generated
from excavation because
demand for backfill for this
package is about 66,700 m3.
Construction waste is
transported to the disposal
site, which is located at Km
26, Quang Nghia commune,
Mong Cai City, 25 km far
from the central of Mong Cai
City. Mong Cai CPC
approved this landfill
according to letter number
1505/CV-UBND dated on
August 19, 2015.
Being Complied
Soil generated from
excavation is re-used for
filling.
Construction waste and the
rest of excavated soil are
transported to the disposal
site, which is located at Km
26, Quang Nghia commune,
Mong Cai City, 25 km far
from the central of Mong Cai
City. Mong Cai CPC
approved this landfill
according to letter number
1505/CV-UBND dated on
August 19, 2015.
Page 36 of 79
EMP
requirement Assessment on Compliance with EMP in Mong Cai subproject
Package MC1 Package MC2 Package MC3
construction spoil is fertile
soil (in Eastern WTP) that
can be recycled for farming.
The other construction waste
is transported to the disposal
site, which is located at Km
26, Quang Nghia commune,
Mong Cai City, 25 km far
from the central of Mong Cai
City. Mong Cai CPC
approved this landfill
according to letter number
1505/CV-UBND dated on
August 19, 2015.
Domestic and
hazardous waste
management
Partly complied
There is a lack of containers
for collection and
classification of HWs arising
in the future (at this time,
almost no hazardous waste
has been generated)
There is not a principal
contract with the licensed
company to collect and treat
hazardous wastes. However,
it is acceptable because the
amount of hazardous waste
generated is very small, and
it is very difficult to make an
agreement with the HWs
collection and treatment
supllier. So, the contractor
must collect HWs into
containters in accordance
with requirements of
36/2015/TT-BTNMT issued
by MONRE.
Partly complied
Workers' daily solid waste
has been collected locally.
Garbage containers are
rudimentary, such as plastic
bags, plastic containers/
baskets without lids.
There is a lack of containers
for collection and
classification of HWs arising
in the future (at this time,
almost no hazardous waste
has been generated)
There is not a principal
contract with the licensed
company to collect and treat
hazardous wastes. However,
it is acceptable because the
amount of hazardous waste
generated is very small, and
it is very difficult to make an
agreement with the HWs
collection and treatment
supllier. So, the contractor
must collect HWs into
containters in accordance
with requirements of
36/2015/TT-BTNMT issued
by MONRE..
Partly complied
There is not a principal
contract with the licensed
company to collect and treat
hazardous wastes. However,
it is acceptable because the
amount of hazardous waste
generated is very small, and
it is very difficult to make an
agreement with the HWs
collection and treatment
supllier. So, the contractor
must collect HWs into
containters in accordance
with requirements of
36/2015/TT-BTNMT issued
by MONRE...
Table 12. EMP implementation assessment in Sa Pa subproject
EMP
requirement
Assessment on Compliance with EMP in Sa Pa subproject
Package SP2 Package SP3 Package SP1
Dust
suppression
Partly Complied
There is almost no dust on
construction site because it
is foggy and high humidity
or drizzle almost the time.
The whether changed every
few hours that make the
constructors meet dificulty
Being Complied
There is almost no dust on
construction site because it is
foggy and high humidity or
drizzle almost the time. The
whether changed every few
hours that make the
constructors meet dificulty in
Partly Complied
There is almost no dust on
construction site because it is
foggy and high humidity or
drizzle almost the time. Thee
construction site for Water
treatment plant is located in
isolated area and did not
Page 37 of 79
EMP
requirement
Assessment on Compliance with EMP in Sa Pa subproject
Package SP2 Package SP3 Package SP1
in watering the road. In fact,
they watered the road but
not all the section of road
In addition, vehicles
carrying materials also
covered
However, the fact that there
are many tourist cars and
vehicles transporting
materials of local people
also caused dust
watering the road. In fact, they
watered the road but not all
the section of road
At the material gathering
place, the contractor installs
the water pump to wash the
car before leaving the
construction site
Material trucks are covered
with plastic sheets.
Material yards are covered by
plastic sheets.
cause significant dust to
surrounding. In fact, they
watered the management
road (road for transporting
construction materials) but
not all the section of road
In addition, vehicles carrying
materials also covered
Noise
limitation
Being Complied
There are no
houses/resedent live near the
construction site at the
reporting time
No activities after 10pm and
before 5am.
equip personal protective
equipment (PPEs) for
workers (such as workwear,
helmet, ear muffs, etc).
Partly Complied
There are no houses/resedent
live near the construction site
at the reporting time
No activities after 10pm and
before 5am.
The contractor has fully
equipped PPEs. However,
there are still some workers
who are not fully clothed in
PPEs.
Being Complied
There are no houses/resedent
live near the construction site
at the reporting time
No activities after 10pm and
before 5am.
equip personal protective
equipment (PPEs) for
workers (such as workwear,
helmet, ear muffs, etc).
In the first 6 months of 2019,
the construction activities are
mainly leveling, construct the
transporting route so it does
not cause big vibration.
Water quality
protection
Being Complied
To construct toilets in
camps.
Construct temporary drain to
prevent localized flooding.
Being Complied
To construct toilets in camps.
Construct temporary drain to
prevent localized flooding.
Being Complied
To construct toilets in camps.
Construct temporary drain to
prevent localized flooding.
Occupational
and
Community
health and
safety plan
Partly Complied
- Organize and maintain
instructions and warnings or
install the fence at
construction sites.
However, this work is not
regular and needs
improvement.
- There are regulations, and
training for workers about
regulations and
communication with the
community
- Equipped with first aid kit /
medicine cabinet at the
construction site to provide
first aid if incidents of labor
accidents / traffic occur.
- Build rules for workers,
such as time, do not drink,
or gambling
Partly Complied
- Construction at the streets is
affecting the travel of the
people even though the
contractor has sent officials to
instruct traveler and to gather
and clean up materials.
- Organize and maintain
instructions and warnings at
construction sites. It was
performed in good manner
- There are regulations, and
training for workers about
regulations and
communication with the
community
- Equipped with first aid kit /
medicine cabinet at the
construction site to provide
first aid if incidents of labor
accidents / traffic occur.
Complied
- Organize and maintain
instructions and warnings at
construction sites.
- There are regulations, and
training for workers about
regulations and
communication with the
community
- Equipped with first aid kit /
medicine cabinet at the
construction site to provide
first aid if incidents of labor
accidents / traffic occur.
- Build rules for workers, such
as time, do not drink, or
gambling.
- Equipping firefighting
equipment for storage of
materials / kitchen / office.
Page 38 of 79
EMP
requirement
Assessment on Compliance with EMP in Sa Pa subproject
Package SP2 Package SP3 Package SP1
- Equipping firefighting
equipment for storage of
materials / kitchen / office.
- Set up regulations, and
training for workers about
regulations and
communication with the
community
-
- Build rules for workers, such
as time, do not drink,
gambling.
- Equipping firefighting
equipment for storage of
materials / kitchen / office.
- Set up regulations, and
training for workers about
regulations and
communication with the
community
- Set up regulations, and
training for workers about
regulations and
communication with the
community
- All these measures were
complied.
Excavated soils
and
construction
waste
management
Partly Complied
Workers' daily solid waste
has been collected locally.
Garbage bins are
rudimentary, such as plastic
bags, plastic containers /
baskets without lids.
Treatment of excavation for
leveling or backfill, roadside:
- Re-use part of excavation
volume that ensures the
standards for roadside and
backfill.
- The remaining excavation
volume, the contractor signs
the contract with the service
unit for collection, transport,
and treatment at the disposal
site in accordance with
regulations.
Partly Complied
- Waste of daily activities of
workers has been cleared.
- Excavated rock have been
reused. The abundant has been
gathered and cleared,
however, it still affects
people's travel activities
Partly Complied
Workers' daily solid waste
has been collected locally.
Garbage bins are
rudimentary, such as plastic
bags, plastic containers /
baskets without lids.
Treatment of excavation for
leveling or backfill, the
transportation route
-.In the first 6 months of the
year 2019, there are no
redundancy excavated soils.
In case of redundancy, the
contractor will sign a contract
with a transport unit to
transfer to the district's
disposal site as committed in
the CEMP.
Domestic and
hazardous
waste
management
Partly Complied
Appropriate hazardous
waste bins. However, these
are unlabeled and warning
sign for waste oil tank
Partly Complied
Appropriate hazardous waste
bins. However, these are
unlabeled and warning sign
for waste oil tank;
Partly Complied
Appropriate hazardous waste
bins. However, these are
unlabeled and warning sign
for waste oil tank
4.5. Environmental Quality Monitoring 3
4.5.1. In Móng Cái subproject
Environmental Quality in construction phase
Monitoring of environmental quality has been carried out in all construction packages in 3
subprojects. A total of 6 construction packages have been monitored for environmental quality (BG
has 2 packages, MC has 3 packages and SP has 1 package). The following results:
On February 22 – 25 and May 09 – 12, 2019, PISC consultant conducted environmental monitoring
during the construction phase for 3 packages MC1, MC2 and MC3.
3 According to 2018 2nd Quarterly Environmental Report of PISC
Page 39 of 79
The purpose of this environmental monitoring sampling program is to monitor the air quality,
noise, vibration and surface water quality during construction of 3 packages as the basis for
assessment of the impact of construction activities on the East, West of Ka Long and Ka Long river
(MC3). Analysis results show
Air quality, Noise, Vibration in MC1, MC2 and MC3
Results showed that concentration of pollutants is less than or equal to the permitted levels
specified in related QCVN. However, noise levels in the measurement exceed the WHO noise
guideline.
Surface Water quality
The results show that most of the indicators are within the allowable limits of QCVN 08-MT: 2015
/ BTNMT-B2- “National Technical Regulation on surface water quality - B2- Waterborne traffic
and other purposes with low quality water requirements”. Particularly nitrite content at all sampling
points are slightly over the limit.
Results of environmental quality monitoring in Mong Cai subproject are shown in Appendix 2
4.5.2. In Bắc Giang subproject
Quarterly, on March 25th and June 25th, 2019, the environmental monitoring is conducted by PISC
on the construction period for 3 packages of BG1, BG24 and BG3.
The purpose of this environmental monitoring is the assessment of quality of air, noise, vibration
and surface water during BG1, BG2 and BG3 packages construction which is the basis for the
evaluation of impact on surrounding air, surface water quality during construction of Tran Quang
Khai road (BG1), North East Ring Road (BG2), Upgrading ponds (BG3). Analysis results show
that:
Environmental quality monitoring results in package BG1:
Air Quality, Noise, Vibration:
The results show that concentrations of pollutants in ambient air samples are all lower than the
maximum allowable levels under QCVN 05:2013/ BTNMT - National Technical Standard on
Ambient Air Quality; noise are all lower than the maximum allowable levels under QCVN
26:2010/BTNMT - National Technical Standard on noise (normal areas: from 6 am-9 pm).Surface
Water Quality:
- The concentration of all pollutants in Thuong River at project area (BG-SW0.1, BG-SW0.2
adn BG-SW0.3 measurement points) are within the specified threshold in QCVN 08: 2015-
B1 / BTNMT - National Technical Standard on Surface Water Quality, column B1 on this
period. In fact, construction activities In package BG1 discharge no wastewater to the Thuong
River. However, the results of baseline environmental survey at the above positions, the
ammonium content exceeds the allowed limit. This suggests that the quality of the Thuong
River is affected by many industrial enterprises located on both sides of the river, especially
the Ha Bac Fertilizer and Chemicals Plant, one of the largest producers of fertilizer in
Vietnam - often discharges at least 10,000 m3 of wastewater per day.
4 The main construction items of package BG2 were completed in Apirl 2019 (except for about 100 meters of road at
the gate of Methadone-Treatment Center, which is pending for permission of the Ministry of Public Security), so it
was not conducted the air quality monitoring for package BG2 in June 2019.
Page 40 of 79
- Surface water quality in surrounding small pond/lagoon (BG-SW0.4, BG-SW0.5
measurement points): The results show that most of the contaminants in surface water in
small surrounding ponds / lagoons all meet the standard in QCVN 08: 2015-B1 / BTNMT:
National technical regulation on surface water quality - column B1, except to some
parameters that exceeded the standard at the measurement point BG-SW0.4 such as: DO
(exceeded 2.5 times), BOD (exceeded 1.6 times), COD (exceeded 1.5 times) and at the
measurement point BG-SW0.5 is DO (exceeded 1.9 times), BOD (exceeded 1.13 times),
COD (exceeded 1.03 times) in the dry season. Based on the observation, there is no activity
of discharging waste water from the construction sites, this is a small pond/ lagoon with
activities to breed ducks and poultry, so there is a currently potential risk of organic pollution
on the small pond / lagoon.
Results of environmental monitoring in package BG2:
Air Quality, Noise, Vibration: On March 25th, 2019, the environmental air, noise, vibration
monitoring is conducted for BG2 package. The results show that concentrations of pollutants in
ambient air samples are all lower than the maximum allowable levels under QCVN 05:2013/
BTNMT - National Technical Standard on Ambient Air Quality; noise are almost lower than the
maximum allowable levels under QCVN 26:2010/BTNMT - National Technical Standard on noise
(normal areas: from 6 am-9 pm), except for BG-A0.3 sampling point (exceeded 1.01 times) because
of there is high density of vehicles at the juntion of current NH.1A road.
For Packages BG3 (upgrading ponds):
Air Quality, Noise, Vibration: The results show that the concentration of pollutants in ambient
air samples is lower than the maximum allowed under QCVN 05: 2013 / BTNMT: National
Technical Regulation on ambient air quality. In general, the quality of the air environment,
vibration, noise is quite good while the construction of BG3 package.
Results of environmental quality monitoring in Bac Giang subproject are shown in Appendix 1.
4.5.3. In Sapa subproject
According to the terms of reference approved by ADB, three packages in Sapa have to carry out
baseline monitoring and quarterly monitoring, 3 of which have been carried out.
a. Timing of monitoring
Periodic environmental monitoring has been carried out on quaterly basic which in accordance
with Government regulations and requirements in the project's environmental management plan.
As of July 2019, a total of 12 quarterly monitoring times were held at 03 bidding packages. The
latest environmental monitoring of 3 packages in Sapa were in 28 June, 2019.The sample as
followed: SP02: 6 air samples; 3 surface water samples and 2 soil samples; SP02: 10 air samples
and 4 soil samples; SP01: 3 air samples; 2 surface water samples and 2 soil samples
b. Location: As in ADB approved ToRs.
c. Results
For package SP01
Air environment: Air quality is within the permitted standard according to QCVN 05:
2013/BTNMT: National technical regulation on ambient air quality (average 1 hour) of
Ministry of Natural Resources and Environment.
Page 41 of 79
Water Environment: Results of monitoring and analyzing surface water samples show that:
The concentration of analytical indicators is within the allowable limits according to QCVN
08: 2015/BTNMT - National technical regulation on surface water quality.
Soil environment: The content of heavy metals in the soil environment of the project is within
the allowable limits according to QCVN 03-MT: 2015 / BTNMT: National technical regulation
on permissible limits of some metals heavy in the soil (Agricultural land), does not affect
cultivation and production activities.
For package SP02
Ambient Air: Measurement and analysis parameters in the project are up to standards, the
concentration of pollutants is not higher than that of QCVN 05: 2013 / BTNMT: National
Technical Regulation on ambient air quality (average 1 hour); Therefore, the construction and
installation work in the project does not pollute the surrounding air environment.
In this package, there are 3 construction contractors. In July, there are not many construction
activities, only some locations are leveling and casting concrete structures. The main sources
of air pollution in this time are mainly transportation of materials on the road and ground
leveling and construction.
Surface water: The concentration of the parameters is compared against QCVN 08-MT: 2015
/ BTNMT: National Technical Regulation on surface water quality, showing that the surface
water is not polluted, ensuring the life of aquatic plants as well as other human activities.
Soil: The project activities do not pollute the soil. The concentration of indicators is within the
limits of regulation QCVN 03-MT: 2015 / BTNMT: National technical regulation on limits of
some heavy metals in soil (agricultural land).
For package SP03:
Air: Measurement and analysis parameters in the project area before the construction are up
to standards, the concentration of pollutants not exceeding the level specified in QCVN 05:
2013 / BTNMT: Technical regulations National Quality of surrounding air quality (average 1
hour);
Soil: Unpolluted soil. The concentration of indicators is within the regulation of QCVN 03-
MT: 2015 / BTNMT: National technical regulation on limits of some heavy metals in soil
(agricultural land).
Results of environmental quality monitoring in Sa Pa subproject are shown in Appendix 3
Page 42 of 79
V. REMARK ON NON-COMPLIANCES
5.1. Review the implementation of corrective actions from previous report of
January to June 2019
The non-compliance with EMP requirements and further action for each sub-project from
previous report of January to June 2019 are presented below.
5.2.1. For Mong Cai subproject:
Table 13. Issues for further action on Non-compliance with EMP Requirements from
previous report (from 6-12/2018) – Mong Cai subproject
Issues Required Action Responsibility and
Timing
Resolution
1. For Package MC1
There is a lack of containers for
collection and classification of
HWs arising in the future.
Equip collection and
segregated bins for
hazardous waste
Contractor;
CSC to inspect and
supervise the
Contractor.
By the end of the first
quarter 1 of 2019.
Contractor has equipped
collection and segregated
bins for hazardous waste
in accordance with
regulations.
There is not a principal contract
with the licensed company to
collect and treat hazardous
wastes.
Sign the contract with
licensed units
Contractor;
CSC to inspect and
supervise the
Contractor.
Not completed yet
There is not a principal
contract with the licensed
company to collect and
treat hazardous wastes.
However, it is acceptable
because the amount of
hazardous waste
generated is very small,
and it is very difficult to
make an agreement with
the HWs collection and
treatment supllier. So, the
contractor collects HWs
into containters in
accordance with
requirements of
36/2015/TT-BTNMT
issued by MONRE.
There are risks of transport
safety for people travelling on
the access road and dyke road
going through the construction
work caused by (i) no fence
installed for isolation of
construction activities, (ii) not
enough warning sign boards
installed
Mong Cai PMU to
work with CSC and
contractor to (i) install
fences for isolation of
construction activities;
(ii) install enough sign
boards to warn the risks
of transport accidence
and to inform project
activities including
contact person; and (iii)
assign traffic safety
person/s providing
guidance for traffic
flow and safety during
high construction
works.
The contractor take
action immediately
and complies
throughout the
construction process.
CSC supervises
contractor's actions
Not completed yet.
The contractor has not (i)
installed fences for
isolation of construction
activities; (ii) installed
enough sign boards to
warn the risks of transport
accidence and to inform
project activities
including contact person;
2. For Package MC2
Page 43 of 79
The Contractor does not spray
water into the internal road to
maintain ground moisture, and
this makes dust generate into
the ambient air.
The watering should be
done 3 times or more
per day, especially in
dry season
Contractor;
CSC to inspect and
supervise the
Contractor.
Not completed
The Contractor does not
regularly spray water into
the internal road to
maintain ground
moisture, and this makes
dust generate into the
ambient air.
There are risks of transport
safety for people travelling on
the access road and dyke road
going through the construction
work caused by (i) no fence
installed for isolation of
construction activities, (ii) not
enough warning sign boards
installed, (iii) no instructor
assigned to provide guidance
for traffic flow and preventing
accidence, and (iv) No plastic
sheet cover or fence for
materials.
Mong Cai PMU to
work with CSC and
contractor to (i) install
fences for isolation of
construction activities;
(ii) install enough sign
boards to warn the risks
of transport accidence
and to inform project
activities including
contact person; and (iii)
assign traffic safety
person/s providing
guidance for traffic
flow and safety during
high construction
works.
The contractor take
action immediately
and complies
throughout the
construction process.
CSC supervises
contractor's actions
Not completed yet.
The contractor has not (i)
install fences for isolation
of construction activities;
(ii) install enough sign
boards to warn the risks
of transport accidence
and to inform project
activities including
contact person;
Workers' daily solid waste has
been collected locally. Garbage
containers are rudimentary,
such as plastic bags, plastic
containers/ baskets without
lids.
Equip appropriate bins
(with lid and sufficient
capacity)
Contractor;
CSC inspected and
supervise the
Contractor.
Not Completed yets.
Contractor still has not
equipped appropriate bins
with lid and sufficient
capacity.
There is not a principal contract
with the licensed company to
collect and treat hazardous
wastes.
Sign the contract with
licensed units
Contractor;
CSC to inspect and
supervise the
Contractor.
Not completed yet
There is not a principal
contract with the licensed
company to collect and
treat hazardous wastes.
However, it is acceptable
because the amount of
hazardous waste
generated is very small,
and it is very difficult to
make an agreement with
the HWs collection and
treatment supllier. So, the
contractor collects HWs
into containters in
accordance with
requirements of
36/2015/TT-BTNMT
issued by MONRE.
1. For Package MC3
There is not a principal contract
with the licensed company to
collect and treat hazardous
wastes.
Sign the contract with
licensed units
Contractor;
CSC to inspect and
supervise the
Contractor.
Not completed yet
There is not a principal
contract with the licensed
company to collect and
treat hazardous wastes.
However, it is acceptable
because the amount of
hazardous waste
generated is very small,
and it is very difficult to
make an agreement with
Page 44 of 79
the HWs collection and
treatment supllier. So, the
contractor collects HWs
in containters in
accordance with
requirements of
36/2015/TT-BTNMT
issued by MONRE.
As for HWs, because it is very difficult to make an agreement with the HWs collection and
treatment supllier to transport a small amout of HWs, the contractors of three packages contiune
to store HWs in containters in accordance with requirements of 36/2015/TT-BTNMT issued by
MONRE and intend to sign an unique contract to transport and treat the whole HWs after
completion of the sub-project.
5.2.2. For Bac Giang subproject:
Table 14. Issues for further action on Non-compliance with EMP Requirements from
previous report (Last 2018) - Bac Giang subproject
Issues Required Action Responsibility
and Timing Resolution
1. For Package BG1
Risk on Thuong River bank by
erosion/landslide during the bridge
abutment construction on the
construction site of Ben Huong
bridge.
Reinforce Thuong river
bank with steel piles;
Cover the excavated soil
gathering points when
stopping construction and
rainy.
Contractors;
By the end of Jan
2019.
The contractor has
reinforced Thuong river
bank with steel piles to
ensure there is no bank
erosion at the
construction site;
Used tarpaulin to cover
temporary points of
excavation.
Lack of adequate safety signs for
waterways and additional life
jackets for workers when executing
works on Thuong river according
to regulations.
To install adequate safety
signs for waterways and
additional life jackets for
workers when executing
works on Thuong river
according to regulations
Contractors;
By the end of Nov
2018.
The contractor has
installed the adequate
safety signs for
waterways and
additional life jackets for
workers when executing
works on Thuong river
according to regulations
in Nov 2018.
There are risks of transport safety
for people travelling on the access
road and dyke road going through
the construction work of Tran
Quang Khai road and Ben Huong
bridge caused by (i) no fence
installed for isolation of
construction activities, (ii) not
enough warning sign boards
installed and (iii) no instructor
assigned to provide guidance for
traffic flow and preventing
accidence.
Bac Giang PMU to work
with CSC and contractor
to (i) install fences for
isolation of construction
activities; (ii) install
enough sign boards to
warn the risks of transport
accidence and to inform
project activities
including contact person;
and (iii) assign traffic
safety person/s providing
guidance for traffic flow
and safety during high
construction works.
Contractors;
(i), (ii) on the dyke
road by 15
November 2018;
(iii) from 15
November 2018.
The contractor of BG1 is currently installing a soft reflective strip to separate the lanes of the dyke road passing through the construction site of Ben Huong bridge on Tran Quang Khai road; installing additional warning signs and arranging 01 traffic controllers to minimize the risk of traffic accidents at the end of November 2018.
Page 45 of 79
Issues Required Action Responsibility
and Timing Resolution
2. For Package BG2
Ground leveling of the North - East
Ring Road has filled up some small
drainage canals causing flooding
during heavy rain in some small
agriculture farms of Nam Giang
Villages, Xuong Giang Commune.
Bac Giang PMU to work
with CSC and contractor
to conduct a survey to
find out the blogging
canal and clear up the soil
for water flowing to the
main local drainage
system.
Contractor;
by 15 November
2018.
The Northeast Ring
Road (package BG2) has
been provided with
underground ditch to
pass under the road,
connected to the existing
agricultural irrigation
ditch, which has been
cleared of excavated
soil. The excavated soil
is deposited near the
ditch, ensuring the
maintenance of irrigation
and drainage flow for the
fields in the area on Nov
2018.
3. For Package BG3
Odor generated from dredged
materials of ponds that can affect
community's health on the
construction site of Soc Trang
pond.
Lime powder or EM
spray preparations to limit
odors and pathogenic
microorganisms at
temporary dredged
material gathering sites.
Contractors;
By the end of
quarter I/2019
The contractor has
conducted preliminary
treatment of odor,
pathogenic
microorganisms at
temporary dredged
material gathering sites
before transporting to the
final dredged material
disposal.
Lack of safety warning signs and
project signs at construction site of
Nha Dau pond.
Installing safety warning
signs at construction sites
to reduce risks to the
community.
Contractors;
By the end of
quarter I/2019
The contractor has
installed safety signs
according to regulations.
The proposal for disposal sites for
dredged material of ponds
Urgently selection the
proposal for disposal sites
for dredged material of
ponds
Contractors;
By the end of
quarter I/2019
The contractor has been
approved the disposal
site for dredged material
of ponds. Approved
spoil disposal area is Da
Mai landfill in
accordance with the
approved uEMP, about
6km from the project
area
Revise and finalize the CEMP. Urgently Revise and
finalize the CEMP
Contractors;
By the end of Feb
2019
The contractor has
finalized the CEMP and
CSC and PMU have
approved on April 2019.
5.2.3. For Sapa subproject
Page 46 of 79
Table 15. Issues for further action on Non-compliance with EMP Requirements from
previous report (December 2018) - Sapa subproject
Issues Required Action Responsibility
and Timing Resolution
1. For Package SP02
PPEs have been provided to
workers, but there are still
occasional cases of not wearing
or only partilly wearing them
Contractors, CSC should
urge regularly and ask
workers to comply.
Contractor to be
remedy by the 3nd
week of
July,2019;
CSC to inspect
and supervise the
Contractor.
The contractor provides
protective equipment for
workers.
Take into account the
rules of the construction
site and take the form of
reminding and punishing
those who have not
complied when necessary
Contractors have installed
fences around the construction
site and warning signs.
However, there are still some
locations that do not have signs
/ instructions or installed
The contractor should
assign staff/workers and
install barriers in front of
the construction area to
inform the pedestrians.
Supervision consultants
regularly remind and urge
contractors to comply
These issues need to be
addressed in briefings with
stakeholders
Contractors must
act immediately;
CSC to inspect
and supervise the
Contractor.
The constructor took
action to install the barrier
in front of the
construction area. The
safeguard officer also
instructed the travelling
on the road at the
construction site
The fence or warning sign has
implemented but sometimes
inappropriate (eg warning signs
placed in inappropriate
locations or barriers separating
the construction area
temporarily.)
The contractor needs to
install signs in easy-to-
observe locations, clear and
firm signs for easily
identifiable by pedestrians.
Contractors must
act immediately;
CSC to inspect
and supervise the
Contractor.
The contractor installed
warning signs in easy-to-
observe locations
2. For Package SP03
Affecting travelling of people
and construction site is still dirty,
not clean.
The contractor needs to
clean and irrigate clean
water at the construction site
at the end of the day and
assign people to instruct
traffic at the construction
site. The contractor needs to
work with the PMU to
consider appropriate
construction measures to
reduce the times of
excavating road. Measures
to assign workers to instruct
traffic and install signs, wash
and clean up the site should
be done immediately.
The contractor
should work with
the PMU to agree
on the construction
method to reduce
the time of
excavating road in
January 2019.
The constructors have
cleaned the construction
sites with the close
monitored by
construction supervision
consultant
5.2. Key identified issues and requested actions for this period of Jan to June
2019
Tables below are presented the non-compliance with EMP requirements and further action for
each sub-project in this period report of first 6 months in 2019.
Page 47 of 79
5.2.4. For Mong Cai subproject:
Table 16. Issues for further action on Non-compliance with EMP Requirements from this
report (first 6 months 2019) – Mong Cai subproject
Issues Required Action Responsibility and
Timing Resolution
1. For Package MC1
In WWTP construction
site, there are not
toilets in workers’
camp (WWTP
construction site) and
the workers
temporarily use pit
latrines.
Install santiation toilets in
workers’ camp and stop use
poor sanitation toilets that
could adverly impact on
surfacewater.
Contractor;
CSC to inspect and
supervise the
Contractor.
By July /2019
The contractor must install
santiation toilets in workers’
camp and stop use poor
sanitation toilets that could
adverly impact on
surfacewater.
Domestic waste is not
collected into
containers or store a
right place.
Must daily collect wastes in
containers or store a right
place.
Contractor;
CSC to inspect and
supervise the
Contractor.
By July /2019
Must daily collect wastes in
containers or store a right
place. This must be
maintained regularly.
There is not a principal
contract with the
licensed company to
collect and treat
hazardous wastes
Sign the contract with
licensed units to transport
and treat HWs.
Contractor;
CSC to inspect and
supervise the
Contractor.
By July /2019
Sign the contract with
licensed units to transport
and treat HWs.
There are risks of
transport safety for
people travelling on the
access road and dyke
road going through the
construction work
caused by (i) lack of
fence for isolation of
construction activities
in Hai Xuan commune,
(ii) not enough warning
sign boards installed
Mong Cai PMU to work
with CSC and contractor to
(i) install fences for
isolation of construction
activities; (ii) install enough
sign boards to warn the
risks of transport accidence
and to inform project
activities including contact
person; and (iii) assign
traffic safety person/s
providing guidance for
traffic flow and safety
during high construction
works.
The contractor must take
action immediately By
July /2019 and complies
throughout the
construction process.
CSC supervises
contractor's actions
The contractor must (i) install
fences for isolation of
construction activities; (ii)
install enough sign boards to
warn the risks of transport
accidence and to inform
project activities including
contact person;
Workers do not wear
PPEs while working
althought they all are
fully provide with
adequate PPEs
Contractors, CSC should
urge regularly and ask
workers to comply.
The contractor must take
action immediately By
July /2019 and complies
throughout the
construction process.
CSC supervises
contractor's actions
Contractors, CSC should
urge regularly and ask
workers to comply.
Introduce site regulations and
take up actions against those
who do not comply when
necessary
There is a lack of
regulation on
prohibiting drinking,
gambling for workers
at the site/camps.
These contents have
Print and insert the rules on
prohibiting drinking,
gambling for workers at the
site/camps.
The contractor must take
action immediately By
July /2019 and complies
throughout the
construction process.
CSC supervises
contractor's actions
The contractor must print and
insert the rules onto the wall
of site camp.
Page 48 of 79
Issues Required Action Responsibility and
Timing Resolution
not been displayed as
rules at sites/ camps
Daily cleaning of
construction area is
implemented after
work but sometimes
this procedure is not
operated.
Clean site and vicinity after
every day of construction
The contractor must take
action immediately By
July /2019 and complies
throughout the
construction process.
CSC supervises
contractor's actions
The contractor must carry out
daily cleaning of construction
areas.
2. For Package MC2
There are risks of
transport safety for
people travelling on the
access road and dyke
road going through the
construction work
caused by (i) lack of
fence installed for
isolation of
construction activities,
(ii) not enough warning
sign boards installed,
(iii) no instructor
assigned to provide
guidance for traffic
flow and preventing
accidence, and (iv) No
plastic sheet cover or
fence for materials in
Hai Yen commune’s
road.
Mong Cai PMU to work
with CSC and contractor to
(i) install fences for
isolation of construction
activities; (ii) install enough
sign boards to warn the
risks of transport accidence
and to inform project
activities including contact
person; and (iii) assign
traffic safety person/s
providing guidance for
traffic flow and safety
during high construction
works.
The contractor must take
action immediately By
July /2019 and complies
throughout the
construction process.
CSC supervises
contractor's actions
The contractor must (i)
installs fences for isolation
of construction activities; (ii)
installs enough sign boards
to warn the risks of transport
accidence and to inform
project activities including
contact person; and (iii)
assigns traffic safety
person/s providing guidance
for traffic flow and safety
during high construction
works and (iv) use plastic
sheet cover or fence for
materials.
Domestic waste is not
collected into
containers or a right
place.
Must daily collect wastes in
containers or store a right
place.
Contractor;
CSC to inspect and
supervise the
Contractor.
By July /2019
Must daily collect wastes in
containers or store a right
place. This must be
maintained regularly.
There is not a principal
contract with the
licensed company to
collect and treat
hazardous wastes
Sign the contract with
licensed units to transport
and treat HWs.
Contractor;
CSC to inspect and
supervise the
Contractor.
By July /2019
Sign the contract with
licensed units to transport
and treat HWs.
Workers do not wear
PPEs while working
althought they all are
fully provide with
adequate PPEs
Contractors, CSC should
urge regularly and ask
workers to comply.
The contractor must take
action immediately By
July /2019 and complies
throughout the
construction process.
CSC supervises
contractor's actions
Contractors, CSC should
urge regularly and ask
workers to comply.
Introduce site regulations
and take up actions against
those who do not comply
when necessary
Watering is not carried
out regularly
Material trucks are
covered with plastic
sheets.
- Water must be sprayed
regularly especially in dry
season.
- Material trucks must be
covered with plastic sheets.
The contractor must take
action immediately By
July /2019 and complies
throughout the
construction process.
The contractor improves
quantity of watering sensible
locations in dry weather.
Page 49 of 79
Issues Required Action Responsibility and
Timing Resolution
Material are not
covered by plastic
sheets
- Material must be covered
by plastic sheets
CSC supervises
contractor's actions
There is a lack of
regulation on
prohibiting drinking,
gambling for workers
at the site/camps.
These contents have
not been displayed as
rules at sites/ camps
Print and insert the rules on
prohibiting drinking,
gambling for workers at the
site/camps.
The contractor must take
action immediately By
July /2019 and complies
throughout the
construction process.
CSC supervises
contractor's actions
The contractor prints and
inserts the rules onto the wall
of site camp.
1. For Package MC3
Domestic waste is not
collected into
containers or a right
place.
Must daily collect wastes in
containers or store a right
place.
Contractor;
CSC to inspect and
supervise the
Contractor.
By July /2019
Must daily collect wastes in
containers or store a right
place. This must be
maintained regularly.
There is not a principal
contract with the
licensed company to
collect and treat
hazardous wastes
Sign the contract with
licensed units to transport
and treat HWs.
Contractor;
CSC to inspect and
supervise the
Contractor.
By July /2019
Sign the contract with
licensed units to transport
and treat HWs.
Workers do not wear
PPEs while working
althought they all are
fully provide with
adequate PPEs
Contractors, CSC should
urge regularly and ask
workers to comply.
The contractor must take
action immediately By
July /2019 and complies
throughout the
construction process.
CSC supervises
contractor's actions
Contractors, CSC should
urge regularly and ask
workers to comply.
Introduce site regulations
and take up actions against
those who do not comply
when necessary
5.2.5. For Bac Giang subproject:
Table 17. Issues for further action on Non-compliance with EMP Requirements from this
report (first six months of 2019) - Bac Giang subproject
Issues Required Action Responsibility
and Timing Resolution
1. For Package BG1
Risk of waterway's safety: risk of
boats crashing into BG1's river
infrastructure at night because
there are no lights on the
construction site of Ben Huong
bridge
PMU works with
contractor BG1 to install
lights on the river to
control night traffic
Contractors;
By July /2019
The contractor must ensure
waterway's safety for boats
moving on Thuong river.
Risks of worker safety: lack of
additional life jackets for workers
when executing works on Thuong
river
CSC remind workers
using life jackets while
executing works on
Thuong river.
Contractors;
By July /2019
The contractor must ensure
workers using life jackets
while executing works on
Thuong river.
2. For Package BG2
Page 50 of 79
Issues Required Action Responsibility
and Timing Resolution
None
3. For Package BG3
Odor generated from dredged
materials that can affect
community's health on the
construction site of Soc Trang
pond
Lime powder or EM
spray preparations to
limit odors and
pathogenic
microorganisms at
temporary dredged
material gathering sites.
Contractors;
By July /2019
The contractor has
conducted preliminary
treatment of odor,
pathogenic
microorganisms at
temporary dredged
material gathering sites
before transporting to the
final dredged material
disposal.
4. For Package BG4
Dust emission: dust pollution
from BG4 construction activities,
especially on the Thuong River
dike on the construction site of
Van Son pumping station
PMU and PPMU ensure
contractors of BG4
frequently spray the site.
Contractors;
By July /2019.
The contractor needs to
enhance spraying on the
construction site and dyke
of Thuong river in the
construction site.
Safety risks for workers in BG4
due to (i) lack of safety measures
and insufficient protective
equipment, especially for workers
who work in high places, (ii) No
medical equipment for emergency
first aid.
PMU and TV supervise
the contractor of BG4 to
ensure (i) safety measures
(ii) protective equipment
for workers and if
workers do not wear
protective gear they
cannot be allowed to
work (iii) first aid kit at
the construction site
Contractors;
By July /2019
Contractors need to remind
workers to comply with
full labor protection;
Equip a medicine cabinet /
first aid kit at the office of
the construction site /
temporary camp.
The risk of flooding when rain in
BG4 due to excavated soil in BG4
is deposited into the drainage
canal, blocking the existing Van
Son channel.
Bac Giang PMU works
with contractor of BG4 to
remove spoil in the
drainage canal
Contractors;
By July /2019.
The contractor must
reopen Van Son canal to
ensure good drainage
before the rainy season.
5.2.6. For Sapa subproject
Table 18. Issues for further action on Non-compliance with EMP Requirements from this
report (first six months of 2019) - Sapa subproject
Issues Required Action Responsibility and
Timing Resolution
1. For Package SP02
Labor protection equipment
has been equipped for
workers but there is still a
situation where workers do
not use labor protection, or
do not use all labor
protection.
Contractors, CSC need to
urge regularly and ask
workers to comply.
The contractor
performs before the
3rd week of July
2019,
CSC supervises
contractor's actions
The contractor provides
protective equipment for
workers.
Take into account the
rules of the construction
site and take the form of
reminding and punishing
those who have not
complied when necessary
Page 51 of 79
Issues Required Action Responsibility and
Timing Resolution
Contractors have installed
fences around the
construction site and
warning signs
However, there are still
some locations that do not
have properly signs /
instructions
The contractor should
assign worker and install
barriers in front of the
construction area to inform
the pedestrians.
CSC regularly remind and
urge contractors to comply
These issues need to be
addressed in briefings with
stakeholders in the meeting
The contractor take
action immediately by
July /2019 and
complies throughout
the construction
process.
CSC supervises
contractor's actions
Dust suppression
There is almost no dust on
construction site because it is
foggy and high humidity or
drizzle almost the time. The
whether changed every few
hours that make the
constructors meet dificulty
in watering the road. In fact
they watered the road but not
all the section of road
Constructor should spray
water at the dusty section
road when possible
although the dust is not
significal and it was also
caused by many other
tourism car
When ever the road
was dusty by their
construction activities
The contractor must take
action to spray the road
when possible.
CSC supervises
contractor's actions
02. SP01
Dust suppression
There is almost no dust on
construction site because it is
foggy and high humidity or
drizzle almost the time. The
whether changed every few
hours that make the
constructors meet dificulty
in watering the road. In fact
they watered the road but not
all the section of road.
Moreover, only a short
section of the management
road was dustt at some time.
Constructor should spray
water at the dusty section
road when possible
although the dust is not
significal. Moreover, the
construction site are
isolated in there are where
almost no traveller except
worker pass by
When ever the road
was dusty
The contractor must take
action to spray the road
when possible.
CSC supervises
contractor's actions
Medicine cabinet
The constructor have not
provided medicine cabinet in
the camp sites
Madicine cabinet have to
be provided to all camp
site
Befor week 3 of July,
2019
CSC monitor and remind
constructor
03. SP03
Noise limitation
However, there are still
some workers who are not
fully clothed in PPEs.
CSC regularly remind and
urge contractors to comply.
It should be reminded in
the construction logbook
CSC remind
constructor/worker
when ever worker do
not use PPE
CSC monitor and remind
constructor
If this issue repeat, it
should remind in logbook
and minutes/monthly
report
Occupational and
Community health and
safety plan
Clean the construction
material on the road side
At the construction
time
CSC monitor constructor
CSC remind constructor
to comply and
report/raised these issues
Page 52 of 79
Issues Required Action Responsibility and
Timing Resolution
- Construction at the streets is
affecting the travel of the
people even though the
contractor has sent officials
to instruct traveler and to
gather and clean up
materials.
Safeguard officer of
constructor should instruct
travelling at the
construction site
to PMU in the monthly
report
VI. CONCLUSION AND RECOMMENDATIONS
Conclusions:
i) The project has mostly complied with the requirements of ADB and the Government
of Vietnam in the management and monitoring of the environment.
ii) Regarding the Environmental Management Plan. Overall, the subprojects have
complied with the requirements of the approved EMP and CEMP fairly well. Necessary
documentation and arrangement for EMP monitoring work have been completed in all
subprojects.
iii) Environmental Surveys as required by the project have been undertaken.
iv) Nonetheless, some contractors have not fully complied with EMP requirements as
shown in section “Remarks on Non-compliance”. This issue must be improved by
contractors and CSCs in the coming time.
Recommendations:
i) For contractors: complete missing / unrealized environmental protection measures /
structures as mentioned in the report; continue the implementation of environmental
and safety measures in construction sites; remind workers to strictly observe labor
safety regulations.
ii) For CSCs: promptly assign personnel to supervise occupational safety and
environmental aspects; maintain the promised reporting programme; Support PISC
during environmental monitoring.
iii) For PPMUs: urge contractors, CSC, PISC to perform tasks according to assigned tasks
and schedule, ensure environmental compliance during construction process.
Page 53 of 79
APPENDIX 1: MONITORING RESULTS IN BAC GIANG
Quarterly, on March 25th and June 25th, 2019, the environmental monitoring is conducted by PISC on the construction period for 3 packages of
BG1, BG2 and BG3.
The purpose of this environmental monitoring is the assessment of quality of air, noise, vibration and surface water during BG1, BG2 and BG3
packages construction which is the basis for the evaluation of impact on surrounding air, surface water quality during construction of Tran Quang
Khai road (BG1), North East Ring Road (BG2), Upgrading ponds (BG3).
1. Environmental quality monitoring results in package BG1
On March 25th and June 25th, 2019, the environmental air, noise, vibration and surface water monitoring is conducted for BG1 package on the
construction period. Sampling/monitoring points and parameters to be analyzed for package BG1 - construction of Tran Quang Khai road is
summarized in the Error! Reference source not found. and Error! Reference source not found..
Table 1. List of air sampling points and quality parameters in BG1 package
No. Sampling point Sample code Parameter
A Ambient air, noise and vibration
Total suspended particles
(TSP), CO, SO2, NO2, noise,
vibration)
1 The starting point of Tran Quang Khai road (Hau cluster,
Tho Xuong ward)
BG-A0.1
2 The end of Tran Quang Khai road (Phu Gia hamlet, Song
Mai commune)
BG-A0.2
B Surface water
3 Surface water of Thuong River: Bridge construction site -
500 m
BG-SW0.1 pH, DO, BOD5,
COD, TSS,
ammonium,
nitrite, nitrate, sulphate,
phosphate,
total nitrogen,
total phosphorus,
oil and greases, Total
Coliform
4 Surface water of Thuong River: Bridge construction site BG-SW0.2
5 Surface water of Thuong River: Bridge construction site +
500 m
BG-SW0.3
6 Surface water of a pond nearby the end of Tran Quang Khai
road (position no. 1)
BG-SW0.4
7 Surface water of a pond nearby the end of Tran Quang Khai
road (position no. 2)
BG-SW0.5
Figure 0-1 Map of monitoring points in Package BG1 area
(in Bac Giang city)
Analysis results show that:
Page 54 of 79
a. Noise, vibration, air quality
The results show that concentrations of pollutants in ambient air samples are all lower than the maximum allowable levels under QCVN 05:2013/
BTNMT - National Technical Standard on Ambient Air Quality; noise are all lower than the maximum allowable levels under QCVN
26:2010/BTNMT - National Technical Standard on noise (normal areas: from 6 am-9 pm). These are presented in the following table:
Table 19 Air quality in package BG1 on the construction period
No. Parameters Unit BG-A0.1 BG-A0.2 QCVN
05:2013
/BTNMT
QCVN
26:2010/
BTNMT
QCVN
27:2010/
BTNMT
WHO noise
guidelines
(daytime)
Mar
2019 June 2019
Mar
2019 June 2019
1 TSP µg/m3 116 132 72 95 300 - - -
2 CO µg/m3 < 7,500 < 7,500 < 7,500 < 7,500 30,000 - - -
3 NO2 µg/m3 90 95 85 91 200 - - -
4 SO2 µg/m3 123 131 113 125 350 - - -
5 Noise (LAeq) dBA 53.7 69.1 52.1 65.7 - 70 - 55
6 Vibration (Leq-X) dB 50.1 49.1 50.3 41.2 - - 75 -
7 Vibration (Leq-Y) dB 48.9 48.0 46.2 42.0 - - 75 -
8 Vibration (Leq-Z) dB 47.5 45.2 42.6 39.8 - - 75 -
Remark: - QCVN 05:2013/BTNMT: National Technical Standard on Ambient Air Quality
- QCVN 27:2010/BTNMT: National Technical Standard on vibration (normal site: from 6 am-21 pm)
- QCVN 26:2010/BTNMT: National Technical Standard on noise (normal site: from 6 am-21 pm)
b. Surface Water Quality
The results show that:
- The concentration of all pollutants in Thuong River at project area (BG-SW0.1, BG-SW0.2 adn BG-SW0.3 measurement points) are within
the specified threshold in QCVN 08: 2015-B1 / BTNMT - National Technical Standard on Surface Water Quality, column B1 on this period.
In fact, construction activities In package BG1 discharge no wastewater to the Thuong River. However, the results of baseline environmental
survey at the above positions, the ammonium content exceeds the allowed limit. This suggests that the quality of the Thuong River is affected
Page 55 of 79
by many industrial enterprises located on both sides of the river, especially the Ha Bac Fertilizer and Chemicals Plant, one of the largest
producers of fertilizer in Vietnam - often discharges at least 10,000 m3 of wastewater per day.
- Surface water quality in surrounding small pond/lagoon (BG-SW0.4, BG-SW0.5 measurement points): The results show that most of the
contaminants in surface water in small surrounding ponds / lagoons all meet the standard in QCVN 08: 2015-B1 / BTNMT: National technical
regulation on surface water quality - column B1, except to some parameters that exceeded the standard at the measurement point BG-SW0.4
such as: DO (exceeded 2.5 times), BOD (exceeded 1.6 times), COD (exceeded 1.5 times) and at the measurement point BG-SW0.5 is DO
(exceeded 1.9 times), BOD (exceeded 1.13 times), COD (exceeded 1.03 times) in the dry season. Based on the observation, there is no activity
of discharging waste water from the construction sites, this is a small pond/ lagoon with activities to breed ducks and poultry, so there is a
currently potential risk of organic pollution on the small pond / lagoon.
Table 20 Surface Water Quality in package BG1 area
No Parameters Unit
BG-SW0.1
(Thuong river)
BG-SW0.2
(Thuong river)
BG-SW0.3
(Thuong river)
BG-SW0.4
(pond/lagoon)
BG-SW0.5
(pond/lagoon)
QCVN08-
MT:2015
/BTNMT-
B1 Mar 2019 June 2019 Mar 2019
June
2019 Mar 2019
June
2019 Mar 2019
June
2019 Mar 2019 June 2019
1 pH - 7.17 7.1 7.26 7.14 7.53 7.14 7.78 7.1 7.21 7.19 6-8.5
2 DO mg/L 4.8 4.3 5.0 4.7 5.1 4.5 1.6 4.2 1.9 4.1 ≥ 4
3 BOD5 mg/L 4 12 4 14 5 11 25 13 17 12 15
4 COD mg/L 6 21 7 24 8 19 46 22 31 20 30
5 TSS mg/L 46 17 48 16 43 15 32 21 43 20 50
6 N-NH4+ mg/L 0.11 0.82 0.21 0.76 0.08 0.81 0.51 0.65 0.85 0.72 0.9
7 N-NO2- mg/L < 0.01 < 0.01 < 0.01 < 0.01 < 0.01 0.026 <0.01 0.034 < 0.01 0.025 0.05
8 N-NO3- mg/L 4.9 1.4 4.8 1.4 4.1 0.4 4.61 0.59 2.8 0.8 10
9 T-P mg/L 0.18 0.02 0.21 0.03 0.15 0.045 0.17 < 0.015 < 0.015 < 0.015 -
10 P-PO43- mg/L 0.078 0.016 0.092 0.028 0.081 0.04 0.059 < 0.015 < 0.015 < 0.015 0.3
11 SO42- mg/L 28.0 26.5 32.8 27.4 30.8 28.9 28.0 27.5 32.3 29.1 -
12 T-N mg/L 5.9 3.4 5.4 3.6 5.4 2.1 6.5 2.1 4.5 2.2 -
Page 56 of 79
No Parameters Unit
BG-SW0.1
(Thuong river)
BG-SW0.2
(Thuong river)
BG-SW0.3
(Thuong river)
BG-SW0.4
(pond/lagoon)
BG-SW0.5
(pond/lagoon)
QCVN08-
MT:2015
/BTNMT-
B1 Mar 2019 June 2019 Mar 2019 June
2019 Mar 2019
June
2019 Mar 2019
June
2019 Mar 2019 June 2019
13 Total grease and
oil mg/L <0.3 <0.3 < 0.3 < 0.3 < 0.3 <0.3 0.5 0.6 < 0.3 < 0.3 1
14 Total Coliform MPN/100mL 1500 2100 2100 2300 1200 2000 7,500 2100 4,600 2300 7,500
Remark: QCVN 08:2015-B1/BTNMT: National Technical Standard on Surface Water Quality, Category B1: Applicable for irrigation purposes and purposes with similar
water quality requirements or for listed purpose in category B2.
2. Results of environmental monitoring in package BG2
On March 25th, 2019, the environmental air, noise, vibration monitoring is conducted for BG2 package on the construction period. The main
construction items of package BG2 were completed in April 2019 (except for about 100 meters of road at the gate of Methadone-Treatment Center,
which is pending for permission of the Ministry of Public Security), so it was not conducted the air quality monitoring for package BG2 in June
2019. Sampling/monitoring points and parameters to be analyzed for package BG2 - construction of Dong Bac ring road is summarized in the
Error! Reference source not found. and Error! Reference source not found..
Page 57 of 79
Table 21 List of air sampling points and quality parameters in BG2
package
No. Sampling point Sample
code
Parameter
A Ambient air, noise and vibration
Total suspended
particles (TSP), CO,
SO2, NO2, noise,
vibration)
1 The end of North-Eastern ring road (Dinh Ke
cluster, Dinh Ke ward) BG-A0.3
2 The gate of Methadone-Treatment Centre (under
Bac Giang Centre for HIV/AIDS Prevention) BG-A0.4
3 Residential area near by the starting point of
North-Eastern ring road (Xuong Giang ward) BG-A0.5
Figure 0-2 Map of monitoring points in Package BG2 area
(Bac Giang city)
The results show that concentrations of pollutants in ambient air samples are all lower than the maximum allowable levels under QCVN 05:2013/
BTNMT - National Technical Standard on Ambient Air Quality; noise are almost lower than the maximum allowable levels under QCVN
26:2010/BTNMT - National Technical Standard on noise (normal areas: from 6 am-9 pm), except for BG-A0.3 sampling point (exceeded 1.01
times) because of there is high density of vehicles at the juntion of current NH.1A road. These are presented in the following table:
Page 58 of 79
Table 22 Air quality in package BG2 on the construction period
No.
Parameters Unit BG-A0.3 BG-A0.4 BG-A0.5
QCVN
05:2013
/BTNMT
QCVN
26:2010/
BTNMT
QCVN
27:2010/
BTNMT
WHO noise
guidelines
(daytime)
1 TSP µg/m3 206 78 119 300 - - -
2 CO µg/m3 < 7500 < 7500 < 7500 30,000 - - -
3 NO2 µg/m3 142 56 76 200 - - -
4 SO2 µg/m3 178 111 152 350 - - -
5 Noise (LAeq) dBA 70.8 62.1 58 - 70 - 55
6 Vibration (Leq-X) dB 62.1 60.3 50.2 - - 75 -
7 Vibration (Leq-Y) dB 60.1 59.2 52.2 - - 75 -
8 Vibration (Leq-Z) dB 59.3 58.9 48.1 - - 75 -
Remark: - QCVN 05:2013/BTNMT: National Technical Standard on Ambient Air Quality
- QCVN 27:2010/BTNMT: National Technical Standard on vibration (normal site: from 6 am-21 pm)
- QCVN 26:2010/BTNMT: National Technical Standard on noise (normal site: from 6 am-21 pm)
3. Results of environmental monitoring in package BG3
On March 25th and June 25th, 2019, the environmental air, noise and vibration monitoring is conducted for BG3 package on the construction
period. Sampling/monitoring points and parameters to be analyzed for package BG3 - Upgrading ponds is summarized in the Error!
Reference source not found. and Error! Reference source not found..
Page 59 of 79
Table 23 List of air sampling points and quality
parameters in package BG3
No. Sampling point
Package Sample
code No.
1 At the resident area
surrounding Soc Trang pond BG3
(Wastewater
Collection and
Pond
Improvements)
BG-
A0.6 TSP, CO,
SO2, NO2
noise,
vibration)
2 At the resident area
surrounding Nha Dau pond
BG-
A0.7
3 At the resident area
surrounding Banh Keo pond
BG-
A0.8
Figure 0-3 Map of monitoring points in package BG3
The results show that the concentration of pollutants in ambient air samples is lower than the maximum allowed under QCVN 05: 2013 /
BTNMT: National Technical Regulation on ambient air quality. In general, the quality of the air environment, vibration, noise is quite good
while the construction of BG3 package. These are presented in the following table:
Table 24 Ambient Air Quality in Package BG3 No.
Parameters Unit
BG-A0.6 BG-A0.7 BG-A0.8 QCVN
05:2013
/BTNMT
QCVN
26:2010/
BTNMT
QCVN
27:2010/
BTNMT
WHO noise
guidelines
(daytime) Mar
2019
June
2019
Mar
2019
June
2019
Mar
2019
June
2019
1 TSP µg/m3 101 128 82 91 92 88 300 - - -
2 CO µg/m3 < 7500 < 7500 < 7500 < 7500 < 7500 < 7500 30,000 - - -
3 NO2 µg/m3 70 82 56 72 77 72 200 - - -
4 SO2 µg/m3 128 136 72 104 125 116 350 - - -
5 Noise (LAeq) dBA 54.9 66.3 50.87 62.7 50.9 63.0 - 70 - 55
6 Vibration (Leq-X) dB 50.1 42.1 51.3 48.2 48.2 43.3 - - 75 -
7 Vibration (Leq-Y) dB 48.8 41.9 49.7 47.1 46.3 42.0 - - 75 -
Page 60 of 79
No.
Parameters Unit
BG-A0.6 BG-A0.7 BG-A0.8 QCVN
05:2013
/BTNMT
QCVN
26:2010/
BTNMT
QCVN
27:2010/
BTNMT
WHO noise
guidelines
(daytime) Mar
2019
June
2019
Mar
2019
June
2019
Mar
2019
June
2019
8 Vibration (Leq-Z) dB 46.1 40.2 48.2 45.3 45.3 41.1 - - 75 -
Remark: - QCVN 05:2013/BTNMT: National Technical Standard on Ambient Air Quality
- QCVN 27:2010/BTNMT: National Technical Standard on vibration (normal site: from 6 am-21 pm)
- QCVN 26:2010/BTNMT: National Technical Standard on noise (normal site: from 6 am-21 pm)
Page 61 of 79
APPENDIX 2: MONITORING RESULTS IN MONG CAI
a. Air quality, Noise, Vibration in MC1, MC2 and MC3
Table 25 Pollutants concentration in air samples In Móng Cái
Indicator Monitoring quarter Vibration
(Leq) Noise (LAeq) SO2 NO2 CO TSP
Unit dB dBA µg/m3 µg/m3 µg/m3 µg/m3
MC-A2.1 QI-2019 37.3 54 20.3 18.78 <7000 85
QII-2019 37.3 54 17.46 14.68 <7000 124
MC-A2.2 QI-2019 38.3 56.9 18.32 19.5 <7000 72
QII-2019 38.3 56.9 16.7 15.39 <7000 117
MC-A2.3 QI-2019 38.3 56.9 18.32 19.5 <7000 72
QII-2019 38.3 56.9 16.7 15.39 <7000 117
MC-A0.4 QI-2019 40.8 62.7 25.13 22.82 <7000 103
QII-2019 40.8 62.7 19.4 17.42 <7000 138
MC-A0.5 QI-2019 41.3 64.5 24.38 12.95 <7000 116
QII-2019 45.3 61.9 15.58 17.45 <7000 149
MC-A0.6 QI-2019 43.9 62.5 29.08 17.56 <7000 162
QII-2019 43.3 67.5 18.17 16.78 <7000 204
MC-A0.7 QI-2019 45.6 60.9 26.36 17.52 <7000 175
QII-2019 43.6 68.9 17.87 20.79 <7000 215
QCVN 05:2013/ BTNMT - - 350 200 30,000 300
QCVN 27:2010/ BTNMT
(normal site: 6 am-21 pm)
- 70 - - - -
QCVN 26:2010/BTNMT
(Normal site: 6 am-21 pm)
70 - - - - -
WHO Guidelines (daytime) 55
Page 62 of 79
Sampling code:
Residential area in Hai Yen commune, 500 m from the Western WWTP toward the West. : MC-A2.1
Residential area in Hai Yen commune, 500 m from the Western WWTP toward the East. : MC-A2.2
Residential area next to the Eastern WWTP (Hai Xuan commune) : MC-A2.3
Position No. 1 on Huu Nghi Street (opposite to Tho Xuan market) : MC-A0.4
Position No. 2 on Huu Nghi Street : MC-A0.5
Intersection between Hoa Binh avenue and Tue Tinh street : MC-06
Ka Long bridgehead (Eastern side) : MC-07
Results showed that pollutants are less than or equal to the permitted levels specified in QCVN. However, noise levels in the measurement exceed
the WHO noise guideline.
0
10
20
30
40
MC-A2.1 MC-A2.2 MC-A2.3 MC-A0.4 MC-A0.5 MC-A0.6 MC-A0.7
SO2 content in ambient air analyzed in QI and QIImonitoring courses (ug/m3)
SO2-QI SO2-QII
0
100
200
300
MC-A2.1 MC-A2.2 MC-A2.3 MC-A0.4 MC-A0.5 MC-A0.6 MC-A0.7
TSP content in ambient air analyzed in QI and QII monitoring courses (ug/m3)
TSP-QI TSP-QII
Page 63 of 79
Figure 0-1 Noise level and concentration of pollutants monitored in QI and QII monitoring courses
a. Surface Water quality
Table 26 Surface water quality analysis In Mong Cai
Indicator
pH DO TSS COD BOD5 SO4
2- N-NO3- N-NO2
- N-
NH4+
T-N P-
PO43-
T-P
Total oil
and
grease
Coliform
Unit - mg/L mg/L mg/L mg/L mg/L mg/L mg/L mg/L mg/L mg/L mg/L mg/L MPN/100
mL
MC-SW2.1 QI-2019 6.55 5.89 11.6 26.8 15.8 22.39 0.502 0.053 0.156 1.4 0.059 0.122 <0.3 40
QII-2019 6.89 5.56 16.3 27.1 15.1 20.52 0.526 0.063 0.085 0.95 0.212 0.459 <0.3 200
MC-SW2.3 QI-2019 6.84 5.84 15.2 25.2 15.7 21.97 0.516 0.069 0.133 1.34 0.043 0.109 <0.3 70
QII-2019 6.93 5.58 10.4 24.8 12.7 18.6 0.531 0.069 0.092 1.01 0.228 0.459 <0.3 250
MC-SW2.7 QI-2019 6.83 5.94 17.3 29.8 17.9 33.03 0.573 0.081 0.173 1.74 0.182 0.257 0.357 90
QII-2019 6.92 5.77 21.7 26.3 17.3 29.51 0.577 0.083 0.149 1.12 0.367 0.75 <0.3 700
MC-SW2.9 QI-2019 6.81 5.93 16.7 29.1 15.6 33.86 0.052 0.058 0.188 1.57 0.198 0.287 0.437 150
QII-2019 6.95 5.73 15.9 27.9 16.4 28.91 0.514 0.061 0.13 1.06 0.343 0.68 <0.3 900
MC-SW0.4 QI-2019 7.18 5.75 24.3 19.1 10.8 24.06 0.557 0.077 0.227 2.24 0.125 0.205 <0.3 70
QII-2019 6.99 5.46 30.5 20.1 9.8 14.62 0.572 0.077 0.163 1.4 0.196 0.307 <0.3 200
0
10
20
30
MC-A2.1 MC-A2.2 MC-A2.3 MC-A0.4 MC-A0.5 MC-A0.6 MC-A0.7
NO2 content in ambient air analyzed in QI and QII monitoring courses (ug/m3)
NO2--QI NO2--QII
0
10
20
30
MC-A2.1 MC-A2.2 MC-A2.3 MC-A0.4 MC-A0.5 MC-A0.6 MC-A0.7
NO2 content in ambient air analyzed in QI and QII monitoring courses (ug/m3)
NO2--QI NO2--QII
Page 64 of 79
MC-SW0.5 QI-2019 7.21 5.83 21.2 18.4 9.8 23.85 0.568 0.068 0.165 1.85 0.116 0.169 <0.3 <3
QII-2019 7.05 5.41 23.4 19.4 8.9 12.51 0.569 0.057 0.175 1.57 0.155 0.362 <0.3 150
MC-SW0.6 QI-2019 7.14 5.82 22.3 22.2 11.5 24.37 0.536 0.056 0.13 1.18 0.092 0.213 <0.3 <3
QII-2019 7.02 5.44 27.9 21.3 11.6 16.01 0.511 0.048 0.188 1.74 0.175 0.383 <0.3 90
QCVN 08-MT:2015/
BTNMT-B2
5.5-9 ≥ 2 100 50 25 - 15 0.05 0.9 - 0.5 - 1 10000
Sampling code:
Khe Re stream – effluent receiving point + 200 m (West WWTP) : MC-SW2.1
Khe Re stream – effluent receiving point -200 m(West WWTP : MC-SW2.3
Ka Long river – section receiving effluent of the Eastern WWTP -200 m : MC-SW2.7
Section receiving effluent of the Eastern WWTP + 200 m : MC-SW2.9
Ka Long-embankment construction site : MC-SW0.4
Ka Long-embankment construction site-200 m : MC-SW0.5
Ka Long-embankment construction site+200 m : MC-SW0.6
The results show that most of the indicators are within the allowable limits of QCVN 08-MT: 2015 / BTNMT-B2- “National Technical
Regulation on surface water quality - B2- Waterborne traffic and other purposes with low quality water requirements”. Particularly nitrite content
at all sampling points are slightly over the limit.
Page 65 of 79
Figure 0-2 Map of sampling points in Westerm Ka Long area (MC2)
Page 66 of 79
Figure 0-3 Map of sampling points in Eastern Ka Long area (MC1)
Page 67 of 79
Figure 0-4 Map of sampling points in Ka Long river area (MC3)
Page 68 of 79
Figure 0-5 Changes in concentrations of pollutants in water samples taken in QI and QII 2019 environmental monitoring coures.
The variation in the typical pollutants’ content in water samples analyzed during environmental monitoring courses is not significantly
different.. Field observations show that no discharge from the site could affect the quality of Ka Long and Khe Re rivers.
0
5
10
15
20
MC-SW2.1 MC-SW2.3 MC-SW2.7 MC-SW2.9 MC-SW0.4 MC-SW0.5 MC-SW0.6
BOD5 content of surface water samples analyzed in QIand QII monitoring courses (mg/L)
BOD5--QI BOD5-QII
0
0.02
0.04
0.06
0.08
0.1
MC-SW2.1 MC-SW2.3 MC-SW2.7 MC-SW2.9 MC-SW0.4 MC-SW0.5 MC-SW0.6
Nitrite content of surface water samples analyzed in QI and QII monitoring courses (mg/L)
NO2--QI NO2--QII
0
5
10
15
20
MC-SW2.1 MC-SW2.3 MC-SW2.7 MC-SW2.9 MC-SW0.4 MC-SW0.5 MC-SW0.6
BOD5 content of surface water samples analyzed in QIand QII monitoring courses (mg/L)
BOD5--QI BOD5-QII
0
10
20
30
40
MC-SW2.1 MC-SW2.3 MC-SW2.7 MC-SW2.9 MC-SW0.4 MC-SW0.5 MC-SW0.6
COD of surface water samples analyzed in QI and QII monitoring courses (mg/L)
COD--QI COD-QII
Page 69 of 79
APPENDIX 3: MONITORING RESULTS IN SAPA
In Sapa, as of the end of June, 2019, 03 construction packages namely SP1, SP 02 and SP03 are under construction. Below is the results of
monitoring conducted in late June 2019. During the survey on 27/6/2019, weather was quite stable, sunny with light breeze. Results are shown in
detail in the table below:
1. Result of environmental monitoring of SP02
1.1. Ambient Air quality monitoring
Table 1: Ambient Air Quality In Sapa of SP02
Result*
No parameter Unit
Baseline
in 3/2018
6/2019 Baseline
in 3/2018
6/2019 Baseline in
3/2018
6/2019 Baseline in
3/2018
6/2019 Baseline
in 3/2018
6/2019 Baseline in
3/2018
6/2019 QCVN
05:2013/
BTNMT
KXQ1 KXQ2 KXQ3 KXQ4 KXQ5 KXQ6
1 Temperature oC 22,9 28,0 22,6 27,8 23,4 26,8 23,3 27,4 23,8 28,1 23,8 26,7 -
2 Humidity % 64,5 80,0 66,5 78,2 65,8 79,8 67,0 77,5 66,4 77,3 64,6 79,0 -
3 Wind speed m/s 0,7 0,9 0,7 0,9 0,7 0,8 0,8 0,7 0,7 0,7 0,8 0,6 -
4 Noise dBA 61,8 63,2 65,5 66,7 63,4 67,1 60,5 61,6 59,4 60,8 63,3 62,6 70(1)
5 Suspended
solid µg/m3 66 89 59 73 77 76 76 85 79 87 71 81 300
6 CO µg/m3 2.630 <2.500 2.540 <2.500 2.860 <2.500 2.770 <2.500 2.650 <2.500 2.860 <2.500 30.000
7 SO2
µg/m3 62 36 68 42 64 48 71 40 64 51 69 44 350
8 NO2 µg/m3 70 57 75 62 84 72 86 61 69 74 75 68 200
Remark: KXQ= Air
+ QCVN 05:2013/BTNMT: National Technical Standard on ambient air (1h average);
+ (1)QCVN 26:2010/BTNMT: National Technical Standard on noise;
Remark and comment:
Measured and analysed parameters are within allowable limits, and concentrations of pollutants do not exceed specified levels in QCVN 05: 2013
Page 70 of 79
/ BTNMT: National Technical Regulation for Ambient Air Quality (average 1h); Therefore, the construction and installation in the project does
not affect the ambient air environment.
1.2. Surface water monitoring
Sampling time: 15-17 pm on 27/6/2019. Sampling results are shown in table 12 below:
Table 27 Surface water analysis In Sapa
Result*
Stt Parameter Unit
NM1 NM2 NM3 QCVN
08-MT:2015/
BTNMT
(colum B1)
Baseline in
3/2018
6/2019 Baseline in
3/2018
6/2019 Baseline in
3/2018
6/2019
1 pH - 6,84 6,9 6,75 6,83 6,91 6,97 5,5 - 9
2 TSS mg/L 32 38 41 30,2 28 33,6 50
3 DO mg/L 5,45 4,8 5,26 4,6 5,32 4,5 ≥ 4
4 COD mg/L 22,5 27,3 18,4 24,8 15,5 20,7 30
5 BOD5 mg/L 18,3 9,4 12,4 8,9 10,3 7,5 15
6 NH4+ mg/L <2 0,6 2,7 0,71 2,4 0,67 0,9
7 NO3- mg/L 0,35 1,4 0,12 1,042 0,27 0,81 10
8 NO2- mg/L <0,003 0,017 <0,003 0,011 <0,003 0,008 0,05
9 PO43- mg/L 0,08 0,09 0,03 0,04 0,06 0,06 0,3
10 Clorua mg/L 35 16,3 28 9,2 31 8,8 350
11 Tổng dầu, mỡ mg/L <0,3 <0,3 <0,3 <0,3 <0,3 <0,3 1
12 Coliforms MPN/
100mL 2.800 1.600 3.900 1.100 2.300 1.300 7.500
NM: Surface water
Standard: QCVN 08-MT:2015 : National Technical Standard on Surface Water Quality; Category B1 : for irrigation use or other purposes with
similar water quality requirements or for purposes specified in category B2;
Remarks:
Page 71 of 79
Surface Water Quality of the area is detailed in the table above, the concentration of the parameter was compared against QCVN 08-MT: 2015 /
BTNMT: National Technical Standards for surface water quality, which reveals that: Surface water is not contaminated, ensuring conditions for
aquatic plants growth as well as other human activities. 1.3.Soil quality monitoring
The result shows that, the soil quality indicators do not exceed the allowace limitted of the National standard. This mean the project activities do
cause contaminated for soil in the project area. The details of soil quality is shown in table below:
Table 3 Soil sampling results In Sapa
TT Indicator Unit
Result*
Method
QCVN
03-MT:2015/
BTNMT Baseline in
3/2018
6/2019 Baseline in 3/2018 6/2019
Đ1 Đ2
1 Cu mg/kg
dry soil 26,4 25,3 35,1 29,0
US EPA Method 3050B+
SMEWW 3111B:2012 100
2 Pb mg/kg
dry soil 34,7 2,25 42,2 1,95
US EPA Method 3050B+
SMEWW 3113B:2012 70
3 Zn mg/kg
dry soil 87,3 44,4 72,4 36,5
US EPA Method 3050B+
SMEWW 3111B:2012 200
Page 72 of 79
4 As mg/kg
dry soil 12,6 0,27 10,4 0,44
US EPA Method 3050B+
SMEWW 3113B:2012 15
5 Cd mg/kg
dry soil 1,15 0,09 1,35 0,14
US EPA Method 3050B+
SMEWW 3113B:2012 2
6 Cr mg/kg
dry soil 36,4 0,9 37,5 0,73
US EPA Method 3060A+
US EPA Method 7196 A 200
Remark: Đ= Soil
Page 73 of 79
2. Environmental Monitoring results in package SP03
At the monitoring time on 28/6/2019, weather is quite stable, sunny.
2.1. Ambient Air quality monitoring
Table 1 Ambient Air quality monitoring of package SP03
Result
TT Indicator Unit
Baselin
e in
7/2018
6/2019 Baselin
e in
7/2018
6/2019 Baselin
e in
7/2018
6/2019 Baselin
e in
7/2018
6/2019 Baselin
e in
7/2018
6/2019 Baseline
in 7/2018
6/2019 QCVN
05:2013/B
TNMT K1 K2 K3 K4 K5 K6
1 Temperat
ure oC 28,5 31,0 28,6 30,3 28,6 30,8 28,3 30,6 28,6 31,2 28,6 29,8 -
2 Humidity % 78,3 78,7 78,6 78,0 78,4 78,3 78,4 79,2 77,9 78,1 77,5 79,0 -
3 Wind
speed m/s 0,3 0,8 0,3 0,6 0,5 0,8 0,5 0,7 0,8 0,7 0,7 0,8 -
4 Noise dBA 56,3 37,2 53,7 41,1 56,8 38,6 58,1 40,7 62,1 42,7 60,3 35,8 70(1)
5 Suspended
solid µg/m3 91 93 88 87 86 90 90 82 85 85 87 96 300
6 CO µg/m3 2.820 <2.500 2.670 <2.500 2.780 <2.500 2.830 <2.500 2.710 <2.500 2.810 <2.500 30.000
7 SO2 µg/m3 78 41 83 48 74 42 81 53 75 55 79 51 350
8 NO2 µg/m3 86 63 92 70 88 67 90 78 82 84 85 72 200
Page 74 of 79
Table 2 Ambient Air quality monitoring in package SP03 (cont)
No Indicator Unit Result
Vietnamstandard
05:2013/
BTNMT
Indicator K7 K8 K9 K10
Baseline in
7/2018 6/2019 Baseline in
7/2018 6/2019 Baseline in
7/2018 6/2019 Baseline in
7/2018 6/2019
1 Temperature oC 28,5 30,0 28,3 30,9 28,4 30,5 28,4 31,1 -
2 Humidity % 78,3 79,5 78,5 78,2 78,5 79,1 78,3 78,7 -
3 Wind speed m/s 0,7 0,8 0,5 0,9 0,5 0,9 0,3 0,8 -
4 Noise dBA 60,3 61,2 62,1 62,5 58,6 63,1 59,1 62,0 70(1)
5 Suspended
solid µg/m3 91 86 85 80 89 73 83 85 300
6 CO µg/m3 2.810 <2.500 2.770 <2.500 2.820 <2.500 2.850 <2.500 30.000
7 SO2 µg/m3 82 42 76 46 80 50 83 41 350
8 Indicator µg/m3 91 59 90 62 88 68 92 60 200
Remark:
Indicators measures and analyzed in the project area prior to construction are up to standards, the concentration of pollutants not exceeding the
level specified in QCVN 05: 2013 / BTNMT: National Technical Regulation ambient air quality (average 1 hour); The project activities do not
cause the air pollution in the project site.
2.2.Soil quality
Page 75 of 79
Table 3 Ambient soil quality monitoring in package SP03
TT Indicator Unit
Results
Đ1 Đ2 Đ3 Đ4 Vietnam standard 03-
MT:2015/BTNMT
Baseline
in
7/2018
62019 Baseline
in 7/2018
62019 Baseline
in 7/2018
62019 Baseline in
7/2018
62019
1. Cu mg/kg
dry soil 56,8 61,0 61,3 62,7 65,8 59,7 63,6 65,3 100
2. Pb mg/kg dry soil 24,1 18,4 22,5 24,7 23,2 17,1 25,5 22,2 70
3. Zn mg/kg
dry soil 67,4 63,4 62,7 79,8 66,3 71,8 65,2 77,9 200
4. As mg/kg
dry soil 12,1 7,02 11,7 8,18 12,2 9,3 11,3 8,36 15
5. Cd mg/kg
dry soil 1,07 0,74 1,12 0,81 1,10 0,87 1,13 0,90 2
Comment:
Based on the results of the analysis, the indicators showed that the soil was not contaminated. Some indicators exceed the baseline result but not
exceed the allowance limited of National standard. The concentration of indicators is in the regulation of QCVN 03-MT: 2015 / BTNMT:
National technical regulation on limits of some heavy metals in soil (agricultural land).
Page 76 of 79
3. Environmental Monitoring results in package SP01
3.1. Air quality
The result of monitoring of air quality in the projec site of SP1 are presented in the following table in comparation with baseline monitoring and National
standard. The detail below
Table 1: Ambient Air Quality In Sapa
Result*
No Parameter Unit
Baseline in 3/2018 6/2019 Baseline in
3/2018
6/2019 Baseline in
3/2018
6/2019 QCVN
05:2013/
BTNMT KXQ1 KXQ2 KXQ3
Temperature oC 13,1 26,1 13,1 27,1 12,8 25,8 -
Humidity % 77,2 78,2 77,0 77,8 76,6 78,6 -
Wind speed m/s 0,6 0,7 0,3 0,6 0,5 0,7 -
Noise dBA 67,6 75,1 56,7 77,3 58,7 66,5 70(1)
Suspended solid
µg/m3 95,49 0,27 82,2 0,22 91,6 0,17 300
CO µg/m3 <2.500 <2,50 <2.500 <2,50 <2.500 <2,500 30.000
SO2
µg/m3 38 0,033 45 0,04 40 0,044 350
NO2 µg/m3 66 0,055 73 0,063 68 0,069 200
*Remark: KXQ= Air
+ QCVN 05:2013/BTNMT: National Technical Standard on ambient air (1h average);
+ (1)QCVN 26:2010/BTNMT: National Technical Standard on noise;
Remark:
Measured and analysed parameters are within allowable limits, and concentrations of pollutants do not exceed specified levels in QCVN 05: 2013
/ BTNMT: National Technical Regulation for Ambient Air Quality (average 1h); Therefore, the project does not affect the ambient air
environment.
Page 77 of 79
3.2. Surface water monitoring
Sampling time: 15-17 pm on 27/6/2019. Sampling results are shown in table 2 below:
Table 2 Surface water analysis In Sapa
Stt Parameter Unit
Result* QCVN
08-MT:2015/
BTNMT
(colum B1) NM 1 NM2
Baseline in 3/2018 6/2019 Baseline in 3/2018 6/2019
1 pH - 6,68 6,68 7,21 6,83 5,5 - 9
2 TSS mg/L 21,1 31,1 18,3 28,3 50
3 DO mg/L 5,3 4,1 4,8 4,2 ≥ 4
4 COD mg/L 17,3 21,3 20,5 24,5 30
5 BOD5 mg/L 6,5 7,5 7,2 8,2 15
6 NH4+ mg/L 0,34 0,34 0,25 0,25 0,9
7 NO3- mg/L 1,12 1,12 1,86 1,86 10
9 PO43- mg/L 0,076 21,3 0,064 0,064 0,3
10 Clorua mg/L 18,6 21,3 15,7 15,7 350
11 Tổng dầu,
mỡ mg/L <0,3 <0,3 <0,3 <0,3 1
12 Coliforms MPN/
100mL 750
2.700 630
2.900 7.500
NM: Surface water
Benchmarks: QCVN 08-MT:2015 : National Technical Standard on Surface Water Quality; Category B1 : for irrigation use or other purposes
with similar water quality requirements or for purposes specified in category B2;
Remarks:
Surface Water Quality of the area is detailed in the table above, the concentration of the parameter was compared against QCVN 08-MT: 2015 /
BTNMT: National Technical Standards for surface water quality, which reveals that: Surface water is not contaminated, ensuring conditions for
aquatic plants growth as well as other human activities.
3.3. Soil quality monitoring
Soil quality is shown in table below:
Page 78 of 79
Table 4: Soil quality monitoring results of SP1
No Indicator Unit
Result
Method
QCVN
03-MT:2015/
BTNMT D1* D2*
Baseline 6/2019 Baseline 6/2019 Agricultural
land
Forestry
land
Cu mg/kg
dry soil 56,7 48,5 60,8 45,1
US EPA Method 3050B+
SMEWW 3111B:2012 100 150
Pb mg/kg
dry soil 15,4 14,2 21,2 13,1
US EPA Method 3050B+
SMEWW 3113B:2012 70 100
Zn mg/kg
dry soil 65,5 57,2 68,3 52,8
US EPA Method 3050B+
SMEWW 3111B:2012 200 200
As mg/kg
dry soil 2,5 2,1 3,7 2,4
US EPA Method 3050B+
SMEWW 3113B:2012 15 20
Cd mg/kg
dry soil 0,9 0,65 0,6 0,51
US EPA Method 3050B+
SMEWW 3113B:2012 2 3
Cr mg/kg
dry soil 34,5 31,2 30,7 30,3
US EPA Method 3060A+
US EPA Method 7196 A 200 200
*D means soil
Comment:
The above result show that the soils in the sample are not polluted. Concentrations of the indicators are under the allowance limitted of National
standard named QCVN 03-MT: 2015 / BTNMT: National technical regulations on the allowable limits of some heavy metals in the soil
(Agricultural land, forestry land). The project activities does not pollute the soil environment.