Environmental Monitoring Report Quarterly Report (April - June 2014) July 2014 VIE: Greater Mekong Subregion KunmingHai Phong Transport Corridor Noi BaiLao Cai Highway Project Prepared by Getinsa for the Vietnam Expressway Corporation, the Ministry of Transport, the Government of Viet Nam, and the Asian Development Bank

Transcript of VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion...

Page 1: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Environmental Monitoring Report

Quarterly Report (April - June 2014) July 2014

VIE: Greater Mekong Subregion Kunming–Hai

Phong Transport Corridor Noi Bai– Lao Cai

Highway Project

Prepared by Getinsa for the Vietnam Expressway Corporation, the Ministry of Transport, the Government of Viet Nam, and the Asian Development Bank

Page 2: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

CURRENCY EQUIVALENTS (as of 1 July 2014)

Currency unit – dong (D)D1.00 = $0.0000469$1.00 = D21,328

NOTE

In this report, "$" refers to US dollars unless otherwise stated.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project

Hanoi office : 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da District Vinh Phuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Dist, Vinh Phuc Province Madrid Spain head office: C/ Ramón de Aguinaga No 8, 28028 Madrid, Spain/ Web Page: www.getinsa.com

ENVIRONMENTAL, HEALTH AND SAFETY QUARTERLY REPORT

APRIL – JUNE 2014

Page 4: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project

Page 5: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared
Page 6: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor Noi Bai – Lao Cai Highway Project

        1 

Page 7: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

INDEX

0.  SUMMARY 3 

1.  INTRODUCTION. FRAMEWORK OF THE REPORT 6 

1.1  FRAMEWORK OF THE REPORT ...................................................................................... 6 

1.2  DESCRIPTION OF THE PROJECT. DIVISION IN PACKAGES ........................................ 6 

2.  CONSTRUCTION WORKS PROGRESS DURING THE PERIOD 10 

2.1  PACKAGE A1 ................................................................................................................... 10 

2.2  PACKAGE A2 ................................................................................................................... 10 

2.3  PACKAGE A3 ................................................................................................................... 10 

2.4  PACKAGE A4 ................................................................................................................... 11 

2.5  PACKAGE A5 ................................................................................................................... 12 

2.6  PACKAGE A6 ................................................................................................................... 13 

2.7  PACKAGE A7 ................................................................................................................... 14 

2.8  PACKAGE A8 ................................................................................................................... 14 

3.  CARRIED OUT TASKS DURING THE PERIOD 15 

4.  ENVIRONMENTAL MONITORING RESULTS. COMPLEMENTARY MEASURES

TO BE APPLIED 17 

4.1  IMPACT ON AIR QUALITY .............................................................................................. 17 

4.2  IMPACT ON WATER RESOURCES ................................................................................ 22 

4.3  IMPACT ON SOILS QUALITY .......................................................................................... 26 

4.4  NOISE AND VIBRATION LEVELS ................................................................................... 34 

4.5  STREAMS AND RIVERSIDES MAINTENANCE .............................................................. 35 

4.6  EROSION RISKS AND STABILITY IN SLOPES .............................................................. 43 

4.7  HAZARDOUS SUBSTANCES MANAGEMENT ............................................................... 51 

4.8  UNSUITABLE MATERIAL DISPOSALS AND BORROW PITS ....................................... 56 

4.9  WASTE AND CLEANLINESS ON SITE ........................................................................... 63 

4.10  BIODIVERSITY PRESERVATION ................................................................................... 66 

4.11  WORKERS’ CAMPS CONDITIONS ................................................................................. 66 

4.12  LABOUR SAFETY EQUIPMENT ..................................................................................... 69 

4.13  TRAFFIC CONDITIONS AND SIGNPOSTING IN ROADS .............................................. 76 

4.14  SIGNPOSTING IN DANGEROUS SURFACES ............................................................... 81 

4.15  RESTORATION AND LANDSCAPING WORKS .............................................................. 84 

4.16  ACCIDENTS DUE TO THE LACK OF SAFETY MEASURES. RESPONSIBLES ............ 85 

Page 8: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4.17  CONTRACTORS’ ENVIRONMENTAL AND SAFETY SPECIALISTS MOBILIZATION .. 86 

5.  REFERENCE DOCUMENTS RELATIVE TO ENVIRONMENT, HEALTH AND

SAFETY ISSUES 88 

5.1  PACKAGE A1 .................................................................................................................. 88 

5.2  PACKAGE A2 .................................................................................................................. 88 

5.3  PACKAGE A3 .................................................................................................................. 88 

5.4  PACKAGE A4 .................................................................................................................. 89 

5.5  PACKAGE A5 .................................................................................................................. 90 

5.6  PACKAGE A6 .................................................................................................................. 91 

5.7  PACKAGE A7 .................................................................................................................. 92 

5.8  PACKAGE A8 .................................................................................................................. 93 

6.  GRIEVANCE INTAKES. PUBLIC CONSULTATION 95 

7.  ANNEX 1: COMPLAINTS OF LOCAL PEOPLE. SUMMARY TABLE 97 

8.  ANNEX 2: DATA OF ENVIRONMENTAL QUALITY PARAMETERS ANALYSIS 105 

8.1  ANNEX 2.1: AIR QUALITY PARAMETERS .................................................................. 107 

8.2  ANNEX 2.2: WATER QUALITY PARAMETERS ........................................................... 113 

8.3  ANNEX 2.3: NOISE LEVELS ......................................................................................... 119 

9.  ANNEX 3: DOCUMENTATION RECEIVED FROM CONTRACTORS DURING THE

PERIOD 125 

10.  ANNEX 4: STATUS OF THE DOCUMENTATION RELATED TO BORROW PITS,

QUARRIES, SOIL DISPOSALS AND CONCRETE BATCHING PLANTS 129 

11.  ANNEX 5: SUMMARY TABLE OF IMPOSED PENALTIES 189 

12.  ANNEX 9: DOCUMENTATION RELATED TO COMPLAINTS AND

COMPENSATION ACTIVITIES DUE TO SOCIAL IMPACTS 195 

Page 9: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 1

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

ABBREVIATIONS

ADB Asian Development Bank

EIA Environmental Impact Assessment

EPMU Expressway Project Management Unit

EHSMR Environmental, Health and Safety Monthly Report

EHSQR Environmental, Health and Safety Quarterly Report

EHSWIR Environmental, Health and Safety Weekly Inspection Report

MONRE Ministry of Natural Resources and Environment

MOT Ministry of Transport

NB-LC Noi Bai - Lao Cai

NS National Specialist (environmental)

PPE Personal Protection Equipment

PSC Project Supervision Consultant

SMR Safety Monitoring Report

TOR Terms Of Reference

VEC Vietnam Expressway Corporation

Page 10: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 2

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

Page 11: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 3

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

0. SUMMARY

Environmental, Health and Safety Control and Protection: Environmental, Health and

Safety inspections continued being regularly carried out in weekly basis to monitor impacts due

to works and the implementation of mitigation measures. Specific monthly reports, which are

submitted to EPMU, and a quarterly report, which is submitted to the Client and to ADB, were

prepared for all packages concerning the supervision and control of the above mentioned

issues, as regular reporting procedure established by the PSC, increasing the duties specified

in our Contract in order to improve the monitoring and control processes. Also, short weekly

check lists are prepared after each inspection on site in order to maintain the information

constantly updated.

The general main problems and impacts on site along the entire Project in this second quarter

2014 have been very similar to the previous periods, and may be summarized as below:

Cleanliness, healthy conditions

Up to the date, six packages including packages A1, A2, A3, A6, A7 and A8 have been

completed and come into operation and exploitation. All the main construction works of

these packages have been finished and there are some miscellaneous works under

construction such as fencing, slope protection with grass/concrete. During the site

inspection, it’s noted that the construction sites are keep in cleanliness and tidiness

condition, in general; however, at some locations of package A4 and A5 we still

detected the dirtiness status due to lack of housekeeping activity of the Contractor such

as worker’s camps, CBPs or at fueling areas.

Noise & Air Pollution

The dustiness status was noted at some locations of package A4 during carrying out

construction works or transporting material. The Engineer has requested the Contractor

to mobilize the water trucks/wagons to water the surface of transportation roads and at

affected areas in order to minimize the spread of dust. The compliance of the

Contractor with this instruction was recorded during the site inspections.

Soil pollution and erosive processes. Hazardous substances management

Page 12: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 4

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

The status of soil being eroded into cropland or polluted by oil was noted in package

A2, A3, A4 and A5. For the agricultural land which was impacted by erosion, almost all

the land owners have been compensated for damage assets, including restoration cost.

In package A2, the Contractor has prepared the money and made a schedule to

compensate impacted households from July 14th till August 04, 2014.

At the present, for the completed packages, the slope protection work with grass or

concrete is being promptly implemented in order to prevent erosion happening.

Package A1 has finished grassing work; package A2 has reached about 80%; package

A3 has reached 95%; sodding work of package A6 has been completed; package A7

achieved 91% and it’s already finished in package A8.

Bad management in fueling was noted during inspections package A4 and A5 such as

at Km 105+280 and Km 135+000. The Engineer has requested the Contractor to

comply with fuel control regulations; however, the improvement is inadequate.

Rivers protection, water quality

The serious problem was detected in package A1 from 2011 when the Contractor

carried out the construction work at sections Km 7+660 (Xuan Phuong Bridge) and Km

10+695 (Tan Loi Bridge). Because there was no riverside protection measure applied

during carrying out construction work so the riversides in these areas in downstream

have been seriously undermined and collapsed. Despite the strong penalty of the

Engineer (VND ten billion has been retained), restoration work is being carrying out

very slow at Km 7+660 and there is no action at Km 10+695.

At other locations, in general, the water quality is not seriously impacted. At Km

145+000, the cement laden water from CBP was leaked into small existing drainage;

however, the Contractor has solved this problem already.

Safety conditions

At the sections where is under construction, the lack of PPE status is usually detected.

It is partly unawareness of the worker because of lack the training of the Contractors

and also the Contractor didn’t provide them with enough PPE. The Engineer has many

times requested the Contractor to provide the workers with enough PPE at work as well

Page 13: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 5

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

as implement training for newcomer to ensure the safety onsite; however, the

improvement is unremarkable.

Traffic Protection and Maintenance

It’s noted that almost all the underpass box culverts of package A7 and A7 have not

been completed while the highway has been exploited. This leaded the status of using

the highway for travel by rudimentary vehicles or motorbike, even livestock… of local

people. This is very dangerous. The Engineer has checked and requested the

Contractor to accelerate the progress of frontage roads construction work then

immediately finish the fencing work to ensure the traffic safety.

Page 14: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 6

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

1. INTRODUCTION. FRAMEWORK OF THE REPORT

1.1 FRAMEWORK OF THE REPORT

Within the framework of the Environmental Control Plans proposed by the contractors and the

duties of the Consultant (PSC) in this matter contained in the Consulting Services Contract, the

environmental team of national specialists (NS) in charge of inspecting the environmental

conditions of the works for the new highway, have done weekly inspections along the sites and

surroundings of all the Packages which nowadays are all with construction activities, checking

the environmental measures applied by the constructors and detecting any impacts that could

be generated by the building works during the period of reference of this quarterly report, that

means, April, May and June 2014.

The results were already included in the environmental, health and safety weekly inspection

reports (EHSWIR) and the corresponding monthly reports for each package (EHSMR). The

Weekly Reports have been included in the corresponding Monthly Reports. So, it’s considered

not necessary or useful to include again that information in this document.

As the environmental team, therefore under its responsibility, is also in charge of monitoring

the healthy and safety conditions in site, specialists in site offices also have made weekly

inspections in all packages. Their results have been being included in the mentioned monthly

reports, as nowadays all these issues have been joined in only one report. Therefore these

issues are also included in this quarterly report.

So, this document is defined as Environmental, Health and Safety Monitoring Quarterly Report

(hereinafter called EHSQR). It will be submitted to the Client, Vietnam Expressway Corporation

(VEC), through the Expressway Project Management Unit (EPMU) and following the Terms of

Reference (ToR) of the Consultant’s Contract, also to Asian Development Bank (ADB).

1.2 DESCRIPTION OF THE PROJECT. DIVISION IN PACKAGES

Noi Bai - Lao Cai (NB-LC) Highway is a part of Kunming - Hai Phong Transport Corridor, which

has been studied with a total length of 865 Km passing Yunnan province of China and Lao Cai,

Yen Bai, Phu Tho, Vinh Phuc, Ha Noi, Bac Ninh, Hai Duong, Quang Ninh and Hai Phong

provinces of Vietnam.

Page 15: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 7VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

Vietnam Expressway Corporation, which is a state owner company, is the proposer of this

project. Its executing agency is the Ministry of Transport (MOT), and it’s being financed by

Asian Development Bank (ADB) and the Government of Vietnam.

According to original design, NB - LC Highway has a total length of about 262.4 km, passing

through 72 communes and 18 districts of provinces and cities as Ha Noi, Vinh Phuc, Phu Tho,

Yen Bai and Lao Cai.

The construction of project is divided into two phases, in which the first phase will construct

244 km with 4 lanes from Ha Noi to Yen Bai and 2 lanes from Yen Bai to Lao Cai. The second

phase will be the widen section of the former with 6 lanes from Ha Noi to Yen Bai and 4 lanes

from Yen Bai to Lao Cai (Chinese border, 262 km).

Construction of the whole project, first phase, is divided into 8 packages including A1, A2, A3,

A4, A5, A6, A7 and A8. All of them have already begun their construction activities. The length,

location and the status of works in each package at the end of the period are described in the

following paragraphs and tables.

- Package A1 is about 26.630 km of length with start point at station Km 0+070 and

finishes at station Km 26+700. Package A1 goes through the Soc Son district of

Hanoi City and Vinh Phuc province.

- Package A2 is about 22.120 km of length and goes through the Vinh Phuc province

and a little of Phu Tho province. Package A2 has start point at station Km 26+700

and finishes at station Km 48+820. It must cross over Lo River, with a long bridge.

- Package A3 is about 32.240 km of length with start point at station Km48+360 and

ending point at station Km 80+00. Package A3 goes through the Phu Tho province.

The most significant structure is the bridge to cross over Red River.

- Package A4 has start point at Km 80+000 in Cam Khe district, Phu Tho province

and ending point at Km109+750 in Tran Yen district, Yen Bai province. Its total

length is 29.750 km.

- Package A5 has start point at Km109+750 in Tran Yen district, Yen Bai province

and ending point at Km150+900 in Van Yen district, Yen Bai province. Its total

length is 41.150 km.

Page 16: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 8

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

- Package A6 lengthens from start point Km150+900 of Van Yen district, Yen Bai

province to Km190+420 in Van Ban district, Lao Cai province. Its total length is

39.520 km. Almost alignment goes through high mountains in Yen Bai and Lao Cai

province and crosses over natural streams by 18 bridges. This section also

includes 1 tunnel under range of mountain at Km186+500.

- Package A7 lengthens from start point Km190+420 in Van Ban district to Km

218+040 in Bao Thang district, Lao Cai province. Almost alignment also goes

through high mountains and 18 bridges are needed. Its total length is 27,620 m.

Khe Sang bridge with a length of 287m is the biggest one.

- Package A8 begins at station Km 218+040 in Bao Thang district and finishes at Km

244+155 in Bao Thang district, Lao Cai province. Its total length is 26,115 m. Suoi

Trat bridge with a length of 374.8 m is the biggest one.

Table 1.1: Current status of the works at the end of this quarter (%)

Activity A1 A2 A3 A4

Site clearing 100 100 100 93,41

Earthworks 100 99,19 100 84,56

Drainage 88,99 50,88 62,55 58,40

Structures (1) 100 100 100 91,96

Steel works 100 89,89 53,42 --

Asphalt 99,99 92,94 27,58 --

Grassing 97,28 64,67 94,81 6,32

Overall progress 99,72 93,22 83,54 58,53

Activity A5 A6 A7 A8

Site clearing 100 93,09 100 100

Earthworks 76,34 98,37 99,49 99,27

Drainage 65,91 53,95 90,84 81,60

Structures (1) 84,66 98,80 100 100

Steel works -- 25,53 62,43 100

Asphalt 1,19 22,76 100 90,91

Grassing Unknown 19,39 (2) 91,81 100 (2)

Tunnel Construction 20,2 82,76 -- --

Overall progress 56,63 83,62 97,66 96,13 (1) Concrete works

Page 17: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 9

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

(2) Data provided by the Contractor

(data expressed in percentage of the total planned in the project, related to the contract quantities).

Currently, 2 packages, Package A1 and Package A8, were already opened to traffic, although

some works are still pending. Also, it’s foreseen that on April 1st 2014, Package A7 will be

open to public use. Finally, on April 6th, a forth stretch will be open, Package A2 and first part of

A3 until interchange IC8 to connect with national road.

The environmental monitoring program is carried out in compliance with regulations of Vietnam

Government and ADB safeguard policy in order to control environmental impacts and to

ensure that the environment in the surroundings of the project area is well preserved. The VEC

proponent should perform environmental protection measures stated in the EIA report as well

as requirements written in the approval decision made by MONRE. In accordance with article

23 of the Environmental Protection Law and article 15 of Decree 80/2006/ND-CP, MONRE will

organize, direct, and monitor the environmental protection measures performed by VEC as

stated in the EIA report approved.

At present, this environmental monitoring program is being undertaken by Environmental

specialists of Getinsa hired by Vietnam Expressway Corporation. EPMU, the Project Manager,

with the Consultant’s support, monitors the environmental protection measures applied by the

contractors during the development of their works, incompliance with the environmental control

and protection plans proposed by contractors and already approved by the PSC. Consultant

reports to EPMU-VEC as the main involved authority in the project.

In addition to that, during the monitoring process, the environmental specialists and contractors

will try to find out and mitigate unanticipated environmental impacts arising from the project

construction process.

Page 18: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 10

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

2. CONSTRUCTION WORKS PROGRESS DURING THE PERIOD

In this chapter, they are included all the works already done or in process during the period, in

each package and detailing the section where the works are developed.

2.1 PACKAGE A1

Package A1 has been finished.

2.2 PACKAGE A2

Package A2 has been finished.

2.3 PACKAGE A3

April May June

Sec 1: Km 48+360-Km 54+000 Asphalt Finished Finished

Sec 2: Km 54+000-Km 59+600 Asphalt Asphalt Finished

Sec 3: Km 59+600-Km 65+390 Base works;

Asphalt Base works;

Asphalt Finished

Sec 4: Km 65+390-Km 69+070 Base works;

Asphalt Base works;

Asphalt Finished

Sec 5: Km 69+070-Km 73+070 Base works;

Asphalt Base works;

Asphalt Finished

Sec 6: Km 73+070-Km 77+620 Base works;

Asphalt Base works;

Asphalt Finished

Sec 7: Km 77+620-Km 80+000 base works;

Asphalt base works;

Asphalt Finished

TL 325 B Bored piles Structure work Finished

Bai Bang Finished Finished Finished

Cam Phu Finished Finished Finished

Lung Thuong Finished Finished Finished

TL 320 B Finished Finished Finished

HCM IC Finished Finished Finished

XuanThanh Finished Finished Finished

TL 315B Finished Finished Finished

TL 323B Finished Finished Finished

Page 19: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 11

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

Phai Din Finished Finished Finished

TL 320C Finished Finished Finished

RW Flyover Casting pier

column;casting pier head

Structure work Finished

Red River Finished Finished Finished

IC8 Finished Finished Finished

IC10 Finished Finished Finished

CV QL2 Finished Finished Finished

Phong Chau Finished Finished Finished

New Bai Bang (pipe flyover) Finished Finished Finished

2.4 PACKAGE A4

April May June

Sec 1: Km 80+000 – Km 85+000 Earth work;

Subbase Earth work;

Subbase

Earth work; Subbase; base;

asphalt

Sec 2: Km 85+000 – Km 89+600 Earth work;

Subbase Subbase, base Subbase, base

Sec 3: Km 89+600 – Km 96+200 Earth work;

Subbase Earth work;

Subbase; base

Earth work; Subbase; base;

asphalt

Sec 4: Km 96+200 – Km 100+000Earth work;

Subbase Earth work;

Subbase; base Earth work;

Subbase; base

Sec 5: Km 100+000 – Km 105+000

Earth work; Subbase

Earth work; Subbase

Earth work; Subbase

Sec 6: Km 105+000 – Km 109+750

Earth work; Subbase

Earth work; Subbase

Subbase; base; asphalt

Ngoi Lao bridge - Km97+100 Pier Cap working Structure Structure

QL32C bypass bridge - Km107+533

Prepair for Launching PC slab

grider

Finished Finished

Ngoi Van bridge – Km 108+960 Pier Cap working Structure Finished

Dam Nang bridge – Km 108+287 Foundation,

stemwall working Structure Structure

TL321C bridge – Km 84+400 Foundation

working Structure Structure

Ngoi Gianh bridge – Km 88+760 Pier cap, stemwall Structure Structure

Page 20: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 12

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

working

2.5 PACKAGE A5

April May June

Van Phu bridge – Km114+100.05 Structure work Structure work Structure work

Hop Minh My bridge – Km118+920.05

Structure work Structure work Structure work

Ngoi Lau bridge – Km120+615.85 Structure work Structure work Structure work

QL 37 bridge – Km121+433.05 Structure work Structure work Structure work

Ngoi Gua bridge – Km128+665.46 Structure work Structure work Structure work

Ngoi Rao bridge – Km130+916.30 Structure work Structure work Structure work

Ngoi Thu bridge – Km136+108.35 Structure work Structure work Structure work

Ngoi Thap bridge – Km138+447.15

Structure work Structure work Structure work

Ngoi Vien bridge – Km140+788.50

Structure work Structure work Structure work

Xuan Thu bridge – Km141+483.55

Structure work Structure work Structure work

Ngoi Thia bridge – Km145+434.05

Structure work Structure work Structure work

Ngoi Buc bridge – Km 150+704.65

Structure work Structure work Structure work

Sec 1: Km109+750 - Km115+800 Sub base & base work

Sub base & base work

Sub base & base work

Sec 2: Km115+800 - Km120+000 Filling work & sub-base work

Sub base & base work

Sub base & base work

Sec 3: Km120+000 - Km125+000 Filling work & sub-base work

Filling work & sub-base work

Filling work & sub-base work

Sec 4: Km125+000 - Km130+000 Filling work & sub-base work

Filling work & sub-base work

Filling work & sub-base work

Sec 5: Km130+000 - Km136+400 Filling work & sub-base work

Sub base & base work

Sub base & base work

Sec6: Km136+400 - Km142+000 Filling work & sub-base work

Filling work & sub-base work

Filling work & sub-base work

Sec 7: Km142+000 - Km148+000 Sub base & base work

Sub base & base work

Sub base & base work

Sec 8: Km148+000 - Km150+900 Sub base & base work

Sub base & base work

Sub base & base work

Page 21: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 13

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

2.6 PACKAGE A6

April May June

Khe Chuong Bridge - Km153+355 Structure work Structure work Finished

Ngoi That bridge – Km155+971.55

Structure work Structure work Finished

Ngoi Rom bridge- Km157+517.05 Structure work Structure work Finished

Ngoi Cong bridge – Km159+207.85

Structure work Structure work Finished

NgoiGiam I bridge – Km162+896.35

Structure work Structure work Finished

NgoiGiam II bridge – Km163+126.00

Structure work Structure work Finished

Ngoi Hut bridge – Km165+110.50 Structure work Structure work Finished

NgoiChac bridge – Km169+412.00

Structure work Structure work Finished

NgoiPha bridge – Km170+312.50 Structure work Structure work Finished

SuoiQuan bridge – Km173+434.00

Structure work Structure work Finished

NgoiNhuoc bridge – Km176+661.85

Structure work Structure work Finished

Lang Nhay bridge – Km182+164.00

Structure work Structure work Finished

Lang Lau bridge – Km184+057.95 Structure work Structure work Finished

Ngoi Don bridge – Km185+077.75 Structure work Structure work Finished

Dai Viet bridge – Km186+902.05 Structure work Structure work Finished

Van Xuan bridge – Km187+141.55

Structure work Structure work Finished

SuoiNau bridge – Km188+766.00 Structure work Structure work Finished

Lang Nheo flyover – Km173+929 Structure work Structure work Finished

Section 1: Km150+900 - Km156+000

Sub base & base work

Sub base & base work Finished

Section 2: Km156+000 - Km162+000

Sub base & base work

Sub base & base work Finished

Page 22: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 14

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

Section 3: Km162+000 - Km165+000

Sub base & base work

Sub base & base work Finished

Section 4: Km165+000 - Km168+000

Sub base & base work

Sub base & base work Finished

Section 5: Km168+000 - Km172+000

Sub base & base work

Sub base & base work Finished

Section 6: Km172+000 - Km176+713

Sub base & base work

Sub base & base work Finished

Section 7: Km176+713 - Km182+214

Sub base & base work

Sub base & base work Finished

Section 8: Km182+214 - Km186+200

Sub base & base work

Sub base & base work Finished

Section 9: Km186+730 - Km190+420

Sub base & base work

Sub base & base work Finished

Tunnel (Km 186+200 – Km 186+730)

Based and Electric system works

Based and Electric system

works Finished

2.7 PACKAGE A7

Package A7 has been finished.

2.8 PACKAGE A8

Package A8 has been finished.

Page 23: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 15

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

3. CARRIED OUT TASKS DURING THE PERIOD

During the period of reference for this quarterly report, the environmental tasks carried out by the specialists in their site offices and for each

package were the following (see table below).

In some cases, weather conditions difficulted so much the movement along the alignment, therefore may be any week it was not possible the

access to site. In other cases, the progress and distribution of the works in the packages, have conditioned especialists to carry out punctual

inspections instead of general ones.

Package General Inspection1 Punctual Inspection2 Weekly Report Submission

Letter/Notification Submission

Weekly, Monthly and Specific Meeting

Apr May June Apr May June Apr May June Apr May June Apr May June

A1 01 10, 30 25

A2 2, 14,

29 10, 30 27

A3 3; 10;

24

7, 9, 16, 20,

29

6, 10, 23

20 6 07; 14; 22; 28

12,19, 26

2 12; 22 13, 21,

30 4, 13 05; 12

4, 11, 18, 25

2, 9, 16, 23

A4 02; 09;

23 8, 16, 20, 29

6, 10, 18, 23

27 07; 14; 21; 28

5, 12, 19, 26

2, 9, 16, 23

08; 22, 30

5, 6, 15, 16

13, 20, 26

19; 26

A5 1, 9, 18 7, 20,

30 9, 18

4, 23, 25

13, 26 4, 13,

24 5, 12, 19, 26

10, 17, 24, 31

7, 14, 21, 28

7, 17, 23, 24,

28

14, 15, 16

10, 20, 24, 25

10, 24 8, 22 12, 26

A6 2, 7, 15 5, 19,

28 11, 20 4, 26 14, 23

5, 16, 23

5, 12, 19, 26

10, 17, 24, 31

7, 14, 21, 28

7,10, 20

14, 17 11, 24 10, 24 8, 22 12, 26

Page 24: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 16

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

Package General Inspection1 Punctual Inspection2 Weekly Report Submission

Letter/Notification Submission

Weekly, Monthly and Specific Meeting

Apr May June Apr May June Apr May June Apr May June Apr May June

A7 10, 24 5, 29 3, 24 14, 25 16 16, 30 12, 19,

26 10, 17,

31 7, 21,

28

2, 22, 25, 29,

30

15, 19, 20, 27

4, 16, 19

3, 10 25, 26

A8 10, 23 16, 29 16, 30 7, 14,

25 5, 20 3, 24

12, 19, 26

17, 31 7, 21,

28

2, 16, 25, 29,

30

5, 6, 14, 27

4, 26 3, 11 24

1: Inspections along the whole package or, at least, most of its main stations

2: Inspections in one or few locations, generally because of any specific matter or problem

Page 25: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 17

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4. ENVIRONMENTAL MONITORING RESULTS. COMPLEMENTARY MEASURES TO

BE APPLIED

4.1 IMPACT ON AIR QUALITY

As Annex 2.1 there are included the results of the air quality monitoring carried out during the

period of this quarterly report.

4.1.1 Package A1

At the present, at package A1, the Contractor has finished all construction works.

4.1.2 Package A2

At the present, the Contractor has finished the main construction work of package A2. Miscellaneous works don’t affect air quality.

4.1.3 Package A3

May 09, 2014

Location: TL325B bridge

Site visit: Apr 03, 10, 24; May 7, 9, 16, 20, 29;

Jun 6, 10, 23

Date first observed: 03-Apr-2014

Problems description and cause: Soil is

disposed beside the local road and it was swept

onto surface of this road during the rains and

causes high spread or dust in hot windy days

Recommendation and Action taken by

Engineer: The contactor is requested to clean

the surface of the road and water frequently in

order to minimize spread of dust in this area;

erosion control measures must be applied, too.

Responsible Party: POSCO

Deadline: Immediately

Current status: The Contractor has watered

the surface of the road to minimize the spread

Page 26: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 18

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

Jun 23, 2014

of airborne dust. On June 28, 2014, package

A3 was opened to exploit

4.1.4 Package A4

Mar 6, 2014

Apr 9, 2014

Location: QL32C Bridge

Site visit: Apr 02, 09, 23

Date first observed: Dec 11, 2013

Problems description and cause: There is

much dust on the access road

Recommendation and Action taken by

Engineer: The Engineer has orally requested

the Contractor to clean the surface of the road

and to spray water frequently in order to

minimize the spread of dust

Responsible Party: KEANGNAM

Deadline: Immediately

Current status: The Contractor has not yet

cleaned the dirt on the road as well as sprayed

water to minimize the spread of dust in hot

windy day.

Page 27: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 19

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4.1.5 Package A5

April 18, 2014

May 07, 2014

Location: Embankment sections

Site visit: Apr 09, 18; May 07, 20; June 04,13

Description: The contractor is spraying water on public roads and access roads in order to minimize dust during material transportation.

May 20, 2014

June 13, 2014

4.1.6 Package A6

Location: whole package

Site visit: Apr 07, 15; May 05, 19

Current Status: The contractor is spraying

water on public roads and access roads in

order to minimize spread of airborne dust

during carrying out construction work. The

Page 28: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 20

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

April 7, 2014 (Km 175)

May 19, 2014 (Km 182)

package A6 has been opened to exploit in June

14, 2014

June 16, 2014 (Km18+720)

4.1.7 Package A7

April 25, 2014

Location: Package A7

Site visit: Apr 25; May 05; Jun 23

Current status: At the present, the Contractor has finished the main construction work of package A7. Miscellaneous works don’t affect air quality.

Page 29: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 21

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 05, 2104

June 23, 2014

4.1.8 Package A8

April 20, 2014 (Km 228+000)

April 20, 2014 (Km 241+100)

Location: Package A8

Site visit: Apr 10, 20; May 29; June 04

Current Status: At the present, the main

construction work of package A8 has been

finished, the miscellaneous works don’t pollute

air quality

May 29, 2014 (Km231+800)

Page 30: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 22

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4.2 IMPACT ON WATER RESOURCES

As Annex 2.2 there are included the results of the water quality monitoring carried out during

the period of this quarterly report.

4.2.1 Package A1

At the present, at package A1, the Contractor has finished all construction works.

4.2.2 Package A2

Up to now, the main construction work of package A2 has been finished and the miscellaneous

works are not considered as an impact on water quality.

4.2.3 Package A3

Package A3 has come into operation on June 28, 2014. By observation during site inspections

this period, we didn’t detect any serious problem that affects water quality.

4.2.4 Package A4

Apr 23, 2014

Location: Ngoi Van Bridge

Site visit: Apr 02, 09, 23

May 8, 16, 29

Date first observed: Oct 11, 2012

Problems description and cause: The

Contractor dumped soil into riverbed for the

construction works. But the restoration works

has not been implemented. This is affecting the

water quality in this area

Recommendation and Action taken by

Engineer: The Engineer has orally requested

the Contractor to restore the riverbank and

riverbed by removing accumulated soil from

construction works and stabilize the slope of

river bank. Refer to the letter GET-KEA-A4-153

Page 31: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 23

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 29, 2014

Responsible Party: Keangnam

Deadline: Immediate

Current status: The Contractor has removed

all soil in the riverbed and riverbank to the

approved disposal areas as well as

implemented the restoration works.

May 8, 2014

May 29, 2014

Location: Km 92+600

Site visit: May 8, 20, 29; June 6, 10, 23

Date first observed: 08-May-2014

Problems description and cause:

Construction of frontage road without slope

protection measures resulted leading soil into

the lake due to erosion during the rain

Recommendation and Action taken by

Engineer: The Contractor is requested to

remove the soil that has encroached into the

lake. Implement measures to avoid erosion of

the frontage road into the lake. Refer to the

letter GET-KEA-A4-153

Responsible Party: Keangnam Contractor

Deadline: 15-Jun-2014

Current status: The Contractor has not yet

implemented the requirement of the Engineer

Page 32: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 24

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

June 23, 2014

4.2.5 Package A5

May 7, 2014 (CBP km 145)

May 30, 2014 (CBP km 145)

Location: Concrete Batching Plant (km 145)

Site visit: May 07, 20

Date first observed: 07-May-2014

Problems description and cause: The capacity of the settling ponds is not sufficient to handle wastewater from equipment and truck washing. The entire CBP area is muddy due to overflows from the washing area and due to lack of proper drainage for surface run-off. Cement slurry has reached a nearby agricultural lot. This situation may is cause to impact water quality.

Recommendation and Action taken by Engineer: The Engineer required the Contractor to improve fuel control at this location, at the same time, the Engineer also provided the instruction for this issues.

Responsible Party: Keangnam Contractor

Deadline: Immediate

Current status: The Contractor still have not provided additional settling ponds to properly treat wastewater from equipment and truck washings; however, the Contractor already cleaned up and rearranged this CBP and surrounding area in order to avoid muddy condition as well as prevent impact on surrounding environmental.

Page 33: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 25

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 30, 2014 (CBP km 145)

4.2.6 Package A6

May 5, 2014

May 28, 2014

Location: Asphalt Concrete Batching Plant

(Km 171)

Site visit: May 5, 28; June 11

Date first observed: 05-May-2014

Problems description and cause: Downpour

caused overlowing of settling pond and surface

runoff leaded the mud containing cement to

adjacent area where is close to irrigation canal

and agricultural land

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to remove all the overflowed mud,

rearrange this area, dredge settling pond and

construct a berm which is made of soil to

prevent this situation happening in the future.

Refer to letter GET-DOO-A6-153

Responsible Party: Doosan Contractor

Deadline: 30-May-2014

Current status: Mitigation measure has been

applied

Page 34: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 26

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

June 11, 2014

4.2.7 Package A7

At the present, the main construction work of package A7 has been finished, the

miscellaneous works are not considers as the impact resources affecting water quality.

4.2.8 Package A8

At present, the main construction work of package A8 has been finished; there are only some

miscellaneous works such as fence installation and grassing, these activities don’t impact on

water quality.

4.3 IMPACT ON SOILS QUALITY

4.3.1 Package A1

At the present, at package A1, the Contractor has finished all construction works.

4.3.2 Package A2

Location: Km 42+400 ~ Km 44+900

Site visit: Apr 2, 14, 29; May 30; Jun 27

Date first observed: 05-June-2013

Problems description and cause:

Uncontrolled erosion leaded sediment into

croplands and damaged the crop of local

Page 35: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 27

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

April 02, 2014

May 30, 2014

June 27, 2014

people; restoration work is being carried out

slowly

Recommendation and Action taken by

Engineer: Apply erosion and sediment control

measures; contact local people and authority to

negotiate to compensate for the damaged

assets and restore affected areas. Refer to

letter GET1/POS/A2/2090, 2101, 2176, 2315;

GET/MISC/361, 363; The Engineer also warned

the Project Manager of the Contractor of his

negative attitude in cooperation to deal with

problem; refer to letter GET1/POS/A2/2266;

2362, 2450

Responsible Party: POSCO

Deadline: 30-Jun-2014

Current status: The Contractor already contact

local people (Song Lo DPC and its direction

under CPCs) to deal with this matter. Up to

now, there area some unclear problems such

as flooding period, damaged value… that need

to be verified for compensation and the

Contractor is cooperating with local authorities

in order to ascertain this problem.

The compensation is going to be implemented

from July 16 till August 04, 2014. For

unrestorable sections, the EPMU will acquire

that land and hands over to local authorities for

management or change the use purpose of

land.

4.3.3 Package A3

Location: Km 57+300; Km 56+400 – Km

56+800

Site visit: May 07, 09, 16, 20

Page 36: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 28

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 7, 2014 (Km 57+300)

May 9, 2014 (Km 57+300)

May 7, 2014 (Km 56+400 ~ Km 56+800)

Date first observed:

Problems description and cause: Soil slides

on agricultural lands and irrigation canals. This

can reduce the crop production and quality of

agriculture land

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to restore the ariculture areas

affected and apply the erosion control

measures to prevent this problem happening in

the future. Refer to the letter Ref GET-POS-A3-

264, GET2-POS-A3-2360

Responsible Party: Posco Contractor

Deadline: Immediate

Current status: The compensation has been

paid to some of the affected persons whose

farmlands have been damaged due to erosion

and landslides from road embankment but the

others refuses to receive payment. The

Contractor continues solving this problem.

However, the Contractor still does not

implement the suitable measures (e.g., slope

stabilization, installation of adequate drainage,

etc) to ensure that such impacts will be avoided

in the near future.

4.3.4 Package A4

Location: Km 82+000

Site visit: May 8, 20, 29

Page 37: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 29

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

April 20, 2014

May 08, 2014

Date first observed: 26-Apr-2013

Problems description and cause: Agricultural

lands have been damaged due to erosion and

landslides from road embankments.

Recommendation and Action taken by

Engineer: Closely coordinate with affected

households and local authorities to expedite

compensation for damages caused by

construction activities. Dig adequately sized

side drainage/ditch at erosion prone areas to

direct surface run-off away from agricultural

land. Implement slope stabilization measures

to minimize erosion. Provide drainage/ditch

reinforcements (e.g., sandbags and/or other

appropriate measures) to avoid spill-over of

surface run-off onto surrounding agricultural

lands. Refer to the letters GET2-KEA-A4-1283,

GET2-KEA-A4-1293, GET2-KEA-A4-1378;

GET2-KEA-A4-1460, GET2-KEA-A4-1509.

Responsible Party: Keangnam Contractor

Deadline: 05-Apr-2014

Current status: The Engineer has not yet

received any document to confirm that whether

the compensation has been paid to the affected

households. The Contractor also has not

restored these areas or implement

countermeasures (e.g., slope stabilization,

installation of adequate drainage, etc) to

prevent this issue keeping happening.

Location: Km 81+700

Site visit: May 8, 20, 29

Page 38: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 30

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 8, 2014

May 8, 2014

June 23, 2014

Date first observed:

Problems description and cause: Road

embankment erosion buried portions of rice

fields owned by 4 households. The incident

occurred in December 2012 and compensation

for the affected crops has been paid by the

contractor in 2013. The contractor also

disclosed that the affected HH preferred to

remove the soil by themselves with

corresponding payments from the contractor.

To date, although the households have

received payment, they have not removed the

soil.

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to implement the suitable measures

(e.g., side ditch to direct the discharge of the

culvert away from the rice fields, etc.). Refer to

the letter GET-KEA-A4-153

Responsible Party: Keangnam

Deadline: 15-Jun-2014

Current status: The Contractor has not

implemented the Consultant‘s instructions

4.3.5 Package A5

Location: Ngoi Thu bridge’s construction site

Site visit: Apr 09, 25

Page 39: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 31

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

April 9, 2014 (Ngoi Thu bridge)

April 25, 2014 (Ngoi Thu bridge)

Date first observed: 09-Apr-2014

Problems description and cause: Fuel control is not well performed; fuel tanks were put directly on the ground. This situation caused the leak of oil and soil pollution.

Recommendation and Action taken by Engineer: The Engineer required the Contractor to improve fuel control at this location (Refer to the letter No. GET3-KEANGNAM-14-A5-117 dated on 17th April, 2014 regarding to require the Contractor to improve fuel control onsite).

Responsible Party: Keangnam Contractor

Deadline: 24-Apr-2014

Current status: Through site checking and supervision, the Engineer dectects that Sub-contractor has already removed all fuel tanks at this location, besides sub-contractor also cleaned this location.

May 7, 2014 (ACBP Km136)

Location: Asphalt Batching Plant (Km 136)

Site visit: May 07, 30

Date first observed: 07-May-2014

Problems description and cause: Leaks and spills from fuel oil tanks and bitumen burning equipment were noted. Puddles of contaminated water were also noted in the said areas. This situation may is cause to impact soils quality. Recommendation and Action taken by Engineer: The Engineer required the Contractor to improve fuel control at this location (Referring to the letter No. GET-KEA-A5-145 dated on 15th May, 2014)

Responsible Party: Keangnam Contractor

Deadline: Immediate

Page 40: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 32

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 30, 2014 (CBP Km136)

Current status: The Contractor cleaned up this location, but he did not apply suitable measures in order to prevent fuel leaking, therefore the Engineer still found that fuel leaks on the ground.

May 07, 2014

May 30, 2014

Location: Km 148+600

Site visit: May 07, 30; Jun 04

Date first observed: 07-May-2014

Problems description and cause: Although a fuel storage area with roof and concrete flooring is provided at the site, toppled drums were left outside and are exposed to the elements. Leaks and spills are also evident. This situation may is cause to impact soils quality.

Recommendation and Action taken by Engineer: The Engineer required the Contractor to improve fuel control at this location (Referring to the letter No. GET-KEA-A5-145 dated on 15th May, 2014)

Responsible Party: Keangnam Contractor

Deadline: Immediate

Current status: Mitigation measures have not been implemented

Page 41: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 33

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

June 04, 2014

4.3.6 Package A6

May 05, 2014

May 28, 2014

Location: Asphalt Concrete Batching Plant

(Km 171)

Site visit: May 5, 28

Date first observed: 05-May-2014

Problems description and cause: Downpour

caused overlowing of settling pond and surface

runoff leaded the mud containing cement to

adjacent area where is close to irrigation canal

and agricultural land

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to remove all the overflowed mud,

rearrange this area, dredge settling pond and

construct a berm which is made of soil to

prevent this situation happening in the future.

Refer to letter GET-DOO-A6-153

Responsible Party: Doosan Contractor

Deadline: 30-May-2014

Current status: Mitigation measure has been

implemented

Page 42: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 34

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

June 11, 2014

June 11, 2014

4.3.7 Package A7

The main construction work of package A7 has been finished at the end of March, 2014; the

Contractor is now carrying out the miscellaneous works such as installing fence, signboard and

sodding. These works don’t impact on soil quality at surrounding areas.

4.3.8 Package A8

Package A8 has come to operation in March 02, 2014; it means the main construction work

has been finished and during the site inspections in this quarter we didn’t detect the problem

that is due to construction work to impact on surrounding soil quality.

4.4 NOISE AND VIBRATION LEVELS

As Annex 2.3 there are included the results of the noise and vibration levels monitored during

the period of this quarterly report.

4.4.1 Package A1

All the construction work of package A1 has been finished by January 2014.

4.4.2 Package A2

The main construction work of package A2 has been finished, and there is no noise or

vibration impacting on the sensitive areas. Up to now, the Contractor is still carrying out the

compensation the local people for the damages which were due to vibration during

implementing construction work.

Page 43: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 35

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4.4.3 Package A3

The main works of remaining section of package A3 in this peiod are asphalt concrete

pavement; road marking, fencing and landscaping. These works didn’t cause the vibration that

affects the sensitive areas and the noise didn’t excess the standard.

4.4.4 Package A4

By monitoring onsite, it’s noted that the noise arising from construction work didn’t exceed the

standard.

4.4.5 Package A5

By monitoring onsite, it’s noted that the noise arising from construction work didn’t exceed the

standard.

4.4.6 Package A6

It’s noted that almost all the main construction works of package A6 has been finished and the

Contractor is completing the road marking and landscaping works; these works don’t cause

serious noise and vibration that affect sensitive areas.

4.4.7 Package A7

The main construction work of package A7 has been finished, and there is no noise or

vibration impacting on the sensitive areas.

4.4.8 Package A8

Four months ago, the package A8 has come to operation; therefore, there is no noise or

vibration which is due to construction work impacting on the sensitive areas.

4.5 STREAMS AND RIVERSIDES MAINTENANCE

4.5.1 Package A1

Location: Tan Loi Bridge, Xuan Phuong Bridge

Site visit: Apr 01; May 16, 30; June 25

Date first observed:

Page 44: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 36

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

Apr 01, 2014 (Xuan Phuong Bridge)

May 30, 2014 (Xuan Phuong Bridge)

Jun 25, 2014 (Xuan Phuong Bridge)

Problems description and cause: landslide

happened on riversides because the Contractor

didn’t comply with Engineer’s instructions on

riverside protection during carrying out

construction work in these areas; besides, the

water flows in these sections are being blocked

due to temporary stream crossing. Up to now,

the main construction works in these areas

already finished; however, the Contractor has

not began the restoration work yet

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to submit the detail restoration

schedule as well as the working method

statement basing on the approved restoration

plans. Refer to letter GET1/POS/A1/2269

Due to the Contractor doesn’t comply with

requirements of the Engineer in order to restore

affected areas so the Engineer is going to retain

VND 10,000,000,000 (VND ten billion) until he

finishes restoration work. Refer to letter

GET1/POS/A1/2306, 2314, 2317

Responsible Party: POSCO

Deadline: 30-Jul-2014

Current status: The Contractor begun the

restoration work at Xuan Phuong Bridge (Km

7+660); however, the construction work

progress is slow. At Tan Loi Bridge (Km

10+695), it’s noted that there is no action of the

Contractor to restore affected area.

Page 45: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 37

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

Apr 01, 2014 (Tan Loi Bridge)

May 30, 2014 (Tan Loi Bridge)

Jun 25, 2014 (Tan Loi Bridge)

4.5.2 Package A2

The main construction work of package A2 has been finished and the miscellaneous works do

not affect streams and riversides.

4.5.3 Package A3

By observation during this quarter, it’s noted that there is not any serious problems regarding

to stream and riverside maintenance detected.

4.5.4 Package A4

Location: Ngoi Van Bridge

Site visit: Apr 02, 09, 23; May 8, 16, 29

Page 46: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 38

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

Nov 20, 2013

Apr 23, 2014

May 29, 2014

Date first observed: 11-Oct-2012

Problems description and cause: The

Contractor dumped soil into riverbed for the

construction works. But the restoration works

has not been implemented. This problem is

blocking water flow in this area

Recommendation and Action taken by

Engineer: The Engineer has orally requested

the Contractor to restore the riverbank and

riverbed by removing accumulated soil from

construction works and stabilize the slope of

river bank.

Responsible Party: Keangnam

Deadline: Immediate

Current status: Mitigation measures have

been implemented

4.5.5 Package A5

Location: Ngoi Thia Bridge

Site visit: May 07, 30; June 11

Date first observed: 07-May-2014

Page 47: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 39

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 7, 2014

May 30, 2014

Problems description and cause: Although

the temporary access road across the river is

no longer needed for the remaining bridge

works, the contractor has yet to remove the

said obstruction causing high velocity flow

downstream. This condition will likely cause

scouring/erosion of the river embankment

Recommendation and Action taken by

Engineer: The Engineer requested the

Contractor to undertake complete removal of

the temporary access road and restoration of

affected riverbed (Referring to the letter No.

GET-KEA-A5-145 dated on 15th May, 2014)

Responsible Party: Keangnam Contractor

Deadline: 30-Jun-2014

Current status: The water flow is being

blocked due to the Contractor has not carried

out the restoration work

June 11, 2014

4.5.6 Package A6

Location: Suoi Quan bridge’s construction site

Site visit: May 05; Jun 05

Date first observed: 05-May-2014

Page 48: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 40

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 5, 2014 (Suoi Quan bridge)

June 5, 2014 (Suoi Quan bridge)

Problems description and cause: Spoils have

completely buried a short section of the stream

Recommendation and Action taken by

Engineer: The Engineer requested the

Contractor to clean the stream of spoils and

implements slope stabilization measures to

ensure that the stream will not be blocked even

during heavy downpours

Responsible Party: Doosan Contractor

Deadline: Immediate

Current status: The Contractor cleaned up

stream and applied slope stabilization

measures

May 5, 2014 (Dai Viet bridge)

Location: Dai Viet bridge’s construction site

Site visit: May 05, 28

Date first observed: 05-May-2014

Problems description and cause: The flow of a small stream (which discharges to Red River) at the Dai Viet Bridge site is totally blocked since the pipe culvert under the local road has not been reinstalled yet

Recommendation and Action taken by Engineer: The Engineer requested the Contractor to implement the tasks as follows:

1. Install adequately sized culvert(s) to restore stream flow.

2. Undertake regular clearing of the channel

Page 49: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 41

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 28, 2014 (Dai Viet bridge)

section affected by construction;

(Ref. GET-DOO-A6-153 dated to on 14th May, 2014)

Responsible Party: Doosan Contractor

Deadline: 30-May-2014

Current status: The Contractor still have not yet installed culvert at this location.

The Contractor is combining with local authorities and Yen Bai province People’s committee in order to install culverts at province road No.166 this month.

May 5, 2014 (Ngoi Rom bridge)

May 28, 2014 (Ngoi Rom bridge)

Location: Ngoi Rom bridge’s construction site

Site visit: May 05, 28

Date first observed: 05-May-2014

Problems description and cause: Although the temporary access roads across the rivers/streams are no longer needed for the remaining bridge works, the contractor has yet to remove the said obstruction

Recommendation and Action taken by Engineer: The Engineer requested the Contractor to undertake complete removal of the temporary access road, restoration of riverbed and river width, as well as stabilization of affected slopes.

(Ref. GET-DOO-A6-153 dated to on 14th May, 2014)

Responsible Party: Doosan Contractor

Deadline: 30-Jun-2014

Current status: The Contractor has alerady removed temporary access road at this bridge to ensure the water flow

Page 50: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 42

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4.5.7 Package A7

April 14, 2014

May 29, 2014

Location: Km 209+329

Site visit: Apr 14; May 29; June 23

Date first observed: 25-Feb-2014

Problems description and cause: The water

flow is being blocked by disposal material

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to restore the natural flow of stream

and apply the slope protection measure to

avoid this problem happening in the future by

letter No: Ref. Get4-GRBCC-1045

Deadline: 15-Mar-2014 (immediate)

Current status: Mitigation measures have not

been implemented

June 23, 2014

4.5.8 Package A8

Location: Son Ha Bridge Km224+369

Site visit: Apr 10, 14, 23; May 16; Jun 04

Date first observed: 22-May-2013

Page 51: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 43

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

April 14, 2014

May 16, 2014

Problems description and cause: The canal

was blocked due to soil and stone falling during

carrying out construction works

Recommendation and Action taken by

Engineer: The contractor has been requested

to remove all soil and stone from canal to

ensure the water flow. Refer to letter Get4-

Vinaconex-912

Deadline: 30-Mar-2014

Current status: The Contractor is carrying out

the restoration work but it’s very slow

June 04, 2014

4.6 EROSION RISKS AND STABILITY IN SLOPES

4.6.1 Package A1

At the present, at package A1, the Contractor has finished all construction works.

4.6.2 Package A2

At the present, the main construction work of package A2 has been finished and the

Contractor is preparing the slope at section from Km 39+580 to Km 47+660 to complete the

grassing work.

Page 52: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 44

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4.6.3 Package A3

May 7, 2014 (Km 57+300)

May 9, 2014 (Km 57+300)

May 7, 2014 (Km 56+400 ~ Km 56+800)

Location: Km 57+300; Km 56+400 – Km

56+800

Site visit: May 07, 09, 16, 20

Date first observed:

Problems description and cause: Erosion

lead the soil from embankment and slope into

cropland because of unprotected slopes during

the rains

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to restore the ariculture areas

affected and apply the erosion control

measures to prevent this problem happening in

the future. Refer to the letter Ref GET-POS-A3-

264, GET2-POS-A3-2360

Responsible Party: Posco Contractor

Deadline: Immediate

Current status: The compensation has been

paid to some of the affected persons whose

farmlands have been damaged due to erosion

and landslides from road embankment but the

others refuses to receive payment. The

Contractor continues solving this problem.

However, the Contractor still does not

implement the suitable measures (e.g., slope

stabilization, installation of adequate drainage,

etc) to ensure that such impacts will be avoided

in the near future.

Page 53: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 45

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4.6.4 Package A4

Apr 20, 2014

May 08, 2014

Location: Km 82+000

Site visit: Apr 02, 09, 23

Date first observed: 26-Apr-2013

May 8, 20, 29

Problems description and cause: Agricultural

lands have been damaged due to erosion and

landslides from road embankments.

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to contact local people and authority

to verify the damaged status, restore the

affected areas and compensate for the

damaged assets. The erosion control measures

are also required to apply in order to prevent

this matter happening in the future. Refer to the

letters GET2-KEA-A4-1283, GET2-KEA-A4-

1293, GET2-KEA-A4-1378; GET2-KEA-A4-

1460, GET2-KEA-A4-1509.

Responsible Party: Keangnam Contractor

Deadline: 05-Apr-2014

Current status: The Contractor has not

reported to the Engineer the compensation

status; the restoration work and

countermeasures have not been implemented

Location: Km 81+700

Site visit: May 8, 20, 29; Jun 6, 10, 23

Date first observed:

Problems description and cause: Road

Page 54: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 46

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 08, 2014

May 08, 2014

June 23, 2014

embankment erosion buried portions of rice

fields owned by 4 households. The incident

occurred in December 2012 and compensation

for the affected crops has been paid by the

contractor in 2013. The contractor also

disclosed that the affected HH preferred to

remove the soil by themselves with

corresponding payments from the contractor.

To date, although the households have

received payment, they have not removed the

soil.

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to implement the suitable

countermeasures (e.g., side ditch to direct the

discharge of the culvert away from the rice

fields, etc.) to prevent this matter keeping

happening. Refer to the letter GET-KEA-A4-153

Responsible Party: Keangnam

Deadline: 15-Jun-2014

Current status: The Contractor has not

implement the requirement of the Engineer

Location: Km 92+600

Site visit: May 8, 20, 29; Jun 6, 10, 18, 23

Date first observed: 08-May-2014

Page 55: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 47

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 8, 2014

May 29, 2014

Problems description and cause:

Construction of frontage road without slope

protection measures resulted leading soil into

the lake due to erosion during the rain

Recommendation and Action taken by

Engineer: The Contractor is requested to

remove the soil that has encroached into the

lake. Implement measures to avoid erosion of

the frontage road into the lake. Refer to the

letter GET-KEA-A4-153

Responsible Party: Keangnam Contractor

Deadline: 15-Jun-2014

Current status: The Contractor has not yet

implemented the requirement of the Engineer

June 23, 2014

4.6.5 Package A5

Location: Package A5

Site visit: Apr 01, 10, 23

May 07, 20, 26, 30

Description: The Contractor is planting grass at cutting slopes and embankment slopes. Besides, the Contractor also built stone wall at cutting slope (material of cutting slope is not good condition), construct top ditch in order to

Page 56: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 48

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

April 1, 2014 (Km119)

April 18, 2014 (Km128)

May 26, 2014 (Km124)

minimize erosion risks and protect slope.

May 26, 2014 (Km137)

June 18, 2014 (Km143)

4.6.6 Package A6

Location: whole package

Page 57: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 49

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

April 2, 2014 (Km171)

April 7, 2014 (Km179)

May 14, 2014 (Km178)

Site visit: Apr 2, 7, 26

May 14, 23, 28

Description: The Contractor is planting grass

at cutting slopes and embankment slopes.

Besides, the Contractor also is spraying

concrete at cutting slope (material of cutting

slope is not good condition), construct top ditch

in order to minimize erosion risks and protect

slope. Package A6 has been opened for traffic

in June 14, 2014

June 20, 2014 (Km154)

June 16, 2014 (Km174)

4.6.7 Package A7

Location: Excavation slope Km 215+200

Page 58: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 50

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

April 14, 2014

May 29, 2014

Site visit: Apr 14; May 29, June 16

Date first observed: 21-May-2013

Problems description and cause: High risk of

erosion and landslide during rainy season due

to unprotected slope

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to apply the slope protection

measure as well as install the warning

signboard to ensure the traffic safety.

Deadline: Immediate

Current status: The Contractor is cutting the

slope to carry out the slope protection measure

June 16, 2013

4.6.8 Package A8

Location: Package A8

Site visit: Apr 10, 14, 23; May 29; June 4, 12,

16, 30

Date first observed:

Problems description and cause: High risk of

landslide happening on slopes due to the

protection measures has not been implemented

Page 59: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 51

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

April 14, 2014

May 29, 2014

Recommendation and Action taken by

Engineer: The Engineer has requested the

contractor to settling the safety fence and

signpost around the landside and erosion

areas, after that apply the erosion control

measure to protect the slope

Responsible Party: Vinaconex

Deadline: As soon as possible

Current status: Mitigation measure is being

applied

June 30, 2014 (Km223+000)

4.7 HAZARDOUS SUBSTANCES MANAGEMENT

4.7.1 Package A1

At the present, at package A1, the Contractor has finished all construction works.

4.7.2 Package A2

During the site inspection in this period, we did not detect any serious problem regarding to

hazardous substance management.

4.7.3 Package A3

By observation during this period, there is no serious problem regarding to hazardous

substance management detected in package A3.

Page 60: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 52

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4.7.4 Package A4

April 02, 2014

May 29, 2014

June 23, 2014

Location: TL321C bridge

Site visit: Apr 02, 09, 23; May 29, Jun 23

Date first observed: 02-Apr- 2014

Problems description and cause: Haphazard

placement of waste oil and oil drums was

observed at this location. This can cause the

spills/leaks of oil on the ground and affect the

soil quality.

Recommendation and Action taken by

Engineer: The Engineer has orally requested

the Contractor to immediately improve the fuel

storage with roof, concrete floor and bund

surrounding to minimize the risk of spills/leaks

of oil.

Responsible Party: Keangnam

Deadline: 07-Apr-2014 (immediate)

Current status: The Contractor has rearranged

the oil storage; however, he has not complied

with instructions of the Engineer in order to

construct an oil storage that meets

requirements above

Location: Km 105+280

Page 61: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 53

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 8, 2014

May 29, 2014

June 18, 2014

Site visit: May 8, 20, 29; June 6, 10, 18, 23

Date first observed: 08-May-2014

Problems description and cause: Haphazard

placement of waste oil and oil drums was

observed at this location. This can cause the

spills/leaks of oil on the ground and affect to the

soil quality.

Recommendation and Action taken by

Engineer: The Engineer has orally requested

the Contractor to immediately improve the fuel

storage with roof, concrete floor and

surrounding bund to minimize the risk of

spills/leaks of oil. Refer to the letter GET-KEA-

A4-153

Responsible Party: Keangnam

Deadline: 30-May-2014 (immediate)

Current status: Mitigation measures have not

been implemented

4.7.5 Package A5

Location: Asphalt Batching Plant (km 135)

Site visit: May 07, 30

Page 62: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 54

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 7, 2014 (ACBP Km136)

May 30, 2014 (ACBP Km136)

Date first observed: 07-May-2014

Problems description and cause: Leaks and

spills from fuel oil tanks and bitumen burning

equipment were noted. Puddles of

contaminated water were also noted in the said

areas.

Recommendation and Action taken by

Engineer: The Engineer required the

Contractor to improve fuel control at this

location (Referring to the letter No. GET-KEA-

A5-145 dated on 15th May, 2014)

Responsible Party: Keangnam Contractor

Deadline: Immediate

Current status: Mitigation measures have not

been implemented

May 7, 2014 (Km 148+600)

Location: Km148+600

Site visit: May 07, 30; June 04

Date first observed: 07-May-2014

Problems description and cause: Although a fuel storage area with roof and concrete flooring is provided at the site, toppled drums were left outside and are exposed to the elements. Leaks and spills are also evident.

Recommendation and Action taken by Engineer: The Engineer required the Contractor to improve fuel control at this location (Referring to the letter No. GET-KEA-A5-145 dated on 15th May, 2014)

Responsible Party: Keangnam Contractor

Page 63: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 55

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

June 4, 2014

Deadline: Immediate

Current status: Mitigation measure has not been implemented

4.7.6 Package A6

April 27, 2013 (Km172)

June 5, 2014 (Km172)

Location: Km172

Site visit: Apr 27; Jun 05

Date first observed: 27-Apr-2014

Problems description and cause: Fuel control

is not well performed; fuel tanks were put

directly on the ground, lack of safety fence and

signboards at fuel storage area.

Recommendation and Action taken by

Engineer: The Engineer required the

Contractor to improve fuel control at this

location, at the same time, the Engineer also

provided the instruction for this issues.

Responsible Party: Doosan Contractor

Deadline: 05-May-2014

Current status: Most item is finish at this

location, the Contractor have already cleaned at

this location.

Page 64: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 56

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4.7.7 Package A7

During the site inspection in this period, we did not detect any serious problem regarding to

hazardous substance management. Package A7 has been opened to exploit.

4.7.8 Package A8

By observation during site inspection this period, we did not find any serious problem regarding

to hazardous substance management.

4.8 UNSUITABLE MATERIAL DISPOSALS AND BORROW PITS

4.8.1 Package A1

At the present, at package A1, the Contractor has finished all construction works.

4.8.2 Package A2

April 02, 2014

May 30, 2014

Location: Km 45+500

Site visit: Apr 2, 14, 29; May 10, 30; June 27

Date first observed: 17-Jan-2014

Problems description and cause: Unsuitable

material is disposed along throughway (this

area is still in right of way)

Recommendation and Action taken by

Engineer: The Contractor is requested to find

out and submit disposal place for this material;

unsuitable material must be removed to

disposal place right after the approval of the

Engineer for disposal area. Refer to letter

GET1/POS/A2/2388

Responsible Party: POSCO

Deadline: 24-Jan-2014 (immediate)

Current status: The Contractor is removing

this material to approved disposal place;

Page 65: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 57

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

Jun 27, 2014

however, the progress of this work is slow

4.8.3 Package A3

Package A3 has been opened on June 28, 2014 and during this quarter there was not any

unauthorized disposal activity detected.

4.8.4 Package A4

June 10, 2014

Location: Km 96+000

Site visit: Jun 10, 18, 23

Date first observed: 10-Jun-2014

Problems description and cause: The

Contractor dumped unsuitable materials beside

express-way without the approval of Engineer

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to remove the unsuitable materials

to the approved disposal. Refer to the letter

GET2-KEA-A4-1580

Responsible Party: Keangnam

Deadline: 25-Jun-2014

Current status: The Contractor has not yet

implemented the Consultant ‘s instructions

Page 66: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 58

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

June 18, 2014

4.8.5 Package A5

May 07, 2014

May 30, 2014

Location: Km 136+000

Site visit: May 07, 30; June 09

Date first observed: 07-May-2014

Problems description and cause: It’s noted

that the Contractor disposed unsutable material

on area that is close to a small stream without

permission of local authority and the Consultant

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to remove the spoils to an approved

disposal place and clean the stream of

materials; slope stabilization measures must be

applied to ensure that the stream will not be

blocked even during heavy downpours. Refer to

letter No. GET-KEA-A5-145 dated on 15th May,

2014

Responsible Party: Keangnam Contractor

Deadline: Immediate

Current status: Mitigation measures have not

been implemented

Page 67: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 59

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

June 09, 2014

4.8.6 Package A6

By the site inspections during this quarter, the Engineer didn’t dectect the unsuitable material

disposal activity of the Contractor in unauthorized disposal place. Besides, the Contractor also

didn’t submit any new borrow pit.

4.8.7 Package A7

April 25, 2014

Location: Km 190+420

Site visit: Apr 25; May 05, 29; June 7, 16, 30

Date first observed:

Problems description and cause: The

Contractor disposed unsuitable material under

the bridge and close to riverside without

permission of the Engineer

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to remove the unsuitable material as

much as possible to the approved disposal

place and apply the slope protection as well as

restore the water flow in this area as

requirement of ADB during mission in May,

2014

Page 68: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 60

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 29, 2014

Responsible Party: Guangxi

Deadline: 30-Jul-2014

Current status: The Contractor is being

mobilized the equipment to carry out the work

June 30, 2014

April 29, 2014

Location: Km 195+500

Site visit: Apr 14; May 05, 29; June 16, 30

Date first observed:

Problems description and cause: The

Contractor disposed unsuitable material under

the bridge and close to riverside without

permission of the Engineer

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to remove the unsuitable material as

much as possible to the approved disposal

place and apply the slope protection in this area

as requirement of ADB during mission in May,

2014

Page 69: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 61

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 29, 2014

Responsible Party: Guangxi

Deadline: 30-Jul-2014

Current status: The Contractor is installing the

gabion at the toe of the slope

June 16, 2014

April 14, 2014

Location: Km 208+890

Site visit: Apr 14; May 05, 29; June 12, 16, 30

Date first observed:

Problems description and cause: The

Contractor disposed unsuitable material on

riverside without permission of the Engineer

and the soil encroached riverbed

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to remove the unsuitable material

that encroached riverbed to the approved

disposal place and apply the slope protection in

this area as requirement of ADB during mission

Page 70: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 62

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 29, 2014

in May, 2014

Responsible Party: Guangxi

Deadline: 30-Jul-2014

Current status: Mitigation measures have not

been implemented

June 12, 2014

April 24, 2014

Location: Km 209+800

Site visit: Apr 14; May 05, 29; Jun 16, 30

Date first observed:

Problems description and cause: The

Contractor disposed unsuitable material on

riverside without permission of the Engineer

and the soil encroached riverbed

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to remove the unsuitable material

that encroached riverbed to the approved

Page 71: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 63

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 29, 2014

June 16, 2014

disposal place and apply the slope protection in

this area as requirement of ADB during mission

in May, 2014

Responsible Party: Guangxi

Deadline: 30-Jul-2014

Current status: Mitigation measures have not

been implemented

4.8.8 Package A8

Package A8 has come to operation in early of March this year and there was no disposal

activity noted during site inspections in this quarter.

4.9 WASTE AND CLEANLINESS ON SITE

4.9.1 Package A1

At the present, at package A1, the Contractor has finished all construction works.

4.9.2 Package A2

The main construction work of package A2 has been finished and all the sites are clean.

Page 72: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 64

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4.9.3 Package A3

During the site inspections during this period, there is no serious problem of waste or dirtiness

on site noted in package A3. This package also has been exploited from June 28, 2014.

4.9.4 Package A4

May 8, 2014

June 23, 2014

Location: Ngoi Van Bridge

Site visit: Jun 10, 18, 23

Date first observed:

Problems description and cause: The

Contractor dumped leftover concrete beside

riverbank

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to remove the this material to the

approved disposal. Refer to the letter GET-

KEA-A4-153; GET2-KEA-A4-1580

Responsible Party: Keangnam

Deadline: Immediate

Current status: The Contractor has not yet

implemented the Consultant ‘s instructions

4.9.5 Package A5

Location: whole package

Site visit: Apr 01, 09, 25; May 13, 26; June 13, 24

Description: Construction site is tidy and clean

Page 73: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 65

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

April 1, 2014 (Km135)

May 26, 2014 (Km 136)

June 24, 2014 (Km141)

4.9.6 Package A6

April 4, 2014 (Km154)

Location: whole package

Site visit: Apr 4, 15, 26; May 19; jun 05

Description: Construction site is tidy and

clean. Package A6 has come to operation in

June 14, 2014

Page 74: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 66

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 19, 2014 (Km163)

June 5, 2014 (Km182)

4.9.7 Package A7

During the site inspections during this period, there is no serious problem of waste or dirtiness

on site noted in package A7.

4.9.8 Package A8

The main construction work of package A8 has been finished and all the sites are clean.

4.10 BIODIVERSITY PRESERVATION

In this period, during the site inspections, we did not find any serious impacts, which arise from

construction activities of the project, on biodiversity preservation.

4.11 WORKERS’ CAMPS CONDITIONS

4.11.1 Package A1

At the present, at package A1, the Contractor has finished all construction works.

4.11.2 Package A2

Up to now, the main construction work of package A2 has been finished and the Contractor

already demobilized all worker’s camps onsite.

Page 75: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 67

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4.11.3 Package A3

In package A3, the Contractor is hiring the local people’s houses for the living of workers with

enough sanitary facilities. Thus, there is not any worker’s camp on site.

4.11.4 Package A4

May 29, 2014

June 23, 2014

Location: Workers’ camps at Ngoi Gianh

Bridge

Site visit: Apr 02, 09, 23; May 8, 16, 29; Jun 6, 10, 23

Current status: The toilet is maintained in

clean and hygienic conditions

Location: Km 105+280

Site visit: May 08, 29; Jun 10, 18, 23

Date first observed: 08-May-2014

Problems description and cause: The

Page 76: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 68

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 29, 2014

June 18, 2014

rubbish was not collected regularly. The

Contractor does not supply any rubbish bin for

this workers’ camp

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to supply a trash bin and clean the

worker’s camp in regular basic. Refer to the

letter GET-KEA-A4-153

Responsible Party: Keangnam

Deadline: Immediate

Current status: The Contractor has not yet

implemented the Consultant ‘s instructions

June 23, 2014

4.11.5 Package A5

Location: The worker’s camp at Km135

Site visit: May 07, 30

Date first observed: 07-May-2014

Problems description and cause:

Indiscriminate disposal of solid waste was

noted at the camp sites. There is also stagnant

water within the camp’s premises at km 135.

First aid kit and fire extinguishers are also not

Page 77: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 69

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 07, 2014

May 30, 2014

provided

Recommendation and Action taken by

Engineer: The Engineer requested the

Contractor to improve living and working

condition at this camp (referring to the letter No.

GET-KEA-A5-145 dated on 15th May, 2014)

Responsible Party: Keangnam Contractor

Deadline: 30-May-2014

Current status: The Contractor have already

provided first aid kit and fire-extinguishers for

the worker’s camp

4.11.6 Package A6

In this period, almost all the main construction work of Package A6 was completed and

package A6 has been opened to exploit from June 14, 2014. All the worker’s camps have

been demobilized.

4.11.7 Package A7

Up to now, the Contractor has demobilized all the worker’s camp onsite due to the main

construction work had been finished.

4.11.8 Package A8

Up to now, the Contractor has demobilized all the worker’s camp onsite due to the main

construction work had been finished.

4.12 LABOUR SAFETY EQUIPMENT

4.12.1 Package A1

At the present, at package A1, the Contractor has finished all construction works.

Page 78: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 70

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4.12.2 Package A2

The main construction work of package A2 has been finished and during the site inspections

we didn’t detect the violation of labour safety.

4.12.3 Package A3

April 10, 2014

May 29, 2014

Location: Package A3

Site visit: Apr 03, 10, 24; May 7, 9, 16, 20, 29;

Jun 06

Date first observed: 10-Apr-2014

Problems description and cause: Workers do

not use enough PPEs while working on site

Recommendation and Action taken by

Engineer: The Engineer has orally requested

the Contractor to provide enough PPE for all

the workers and ensure that they use

adequately PPE at work

Responsible Party: Posco

Deadline: Daily

Current status: Workers were provided PPE to

work.

May 7, 2014

Page 79: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 71

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4.12.4 Package A4

May 08, 2014

May 20, 2014

Location: Ngoi Gianh bridge

Site visit: May 8, 16, 20, 29; Jun 23

Date first observed: 08-May-2014

Problems description and cause: The

workers did not use fully PPEs while working on

site.

Recommendation and Action taken by

Engineer: The Consultant has orally requested

the Contractor to force his workers using fully

PPEs when working on site in order to ensure

safety. Refer to the letters GET-MISC-410,

GET2-KEA-A4-1558, GET-KEA-A4-153, GET-

MISC-412…

Responsible Party: KEANGNAM

Deadline: Immediate

Current status: The Contractor has not yet

implemented the Engineer‘s instructions

June 23, 2014

4.12.5 Package A5

Location: Package A5

Page 80: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 72

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

April 1, 2014 (Km136)

April 1, 2014 (Km111)

April 9, 2014 (Km111)

Site visit: Apr 01, 09; May 07, 30; Jun 9, 18

Date first observed: 01-Apr-2014

Problems description and cause: Workers

are not provided enough PPE at work

Recommendation and Action taken by

Engineer: The Contractor must implement the

tasks as follows:

1. Ensure that all workers are provided with

PPE and they use PPE adequately at work,

2. Install scaffoldings that are stable and has

fall prevention provisions

Responsible Party: Keangnam Contractor

Deadline: Immediate

Current status: Mitigation measures have not

been implemented

May 30, 2014 (Km137)

Page 81: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 73

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

June 18, 2014 (Km138)

4.12.6 Package A6

April 7, 2014 (Km 174)

April 15, 2014 (Km 182)

Location: Km174, Km182, Km156, Km170

Site visit: Apr 4, 15, 25; May 5, 19, 23; Jun 05

Description: The workers use fully PPE during work.

April 26, 2014 (Km 156)

Page 82: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 74

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 23, 2014 (Tunnel’s construction site)

June 05, 2014 (Km 162)

4.12.7 Package A7

April 24, 2014 (Km205+800)

May 16, 2014 (Km195+500)

Location: Package A7

Site visit: Apr 24; May 16; Jun 03, 12, 16, 30

First observed: 24-Apr-2014

Problems description and cause: The

workers are not provided PPE at work

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to immediately provide enough PPE

for workers and ensure that they use

adequately PPE at work

Deadline: Immediate

Current status: The Contractor still has not

provided PPE for workers

Page 83: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 75

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

June 03, 2014 (Km195+230)

4.12.8 Package A8

Apr 25, 2014 (Km 222+800)

May 20, 2014 (Km224+369)

Location: Package A8

Site visit: Apr 25; May 20, 29; June 12, 16, 30

Date first observed: 25-Apr-2014

Problems description and cause: Workers

are not provide PPE at work due to

irresponsibility of the Contractor

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to stop the work and provide enough

PPE for workers and ensure that they use

adequately PPE at work

Deadline: Immediate

Current status: The Contractor has not

implemented the requirement of the Engineer

Page 84: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 76

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

June 30, 2014 (Km231+800)

4.13 TRAFFIC CONDITIONS AND SIGNPOSTING IN ROADS

4.13.1 Package A1

At the present, at package A1, the Contractor has finished all construction works.

4.13.2 Package A2

The main construction work of package A2 has been finished, miscellaneous works which

have been carrying out during this period didn’t affect the traffic.

4.13.3 Package A3

April 03, 2014 (right site)

Location: TL325B bridge

Site visit: Apr 03, 10, 24; May 09, Jun 23

Date first observed: 05-Mar-2014

Problems description and cause: There is

not any sign board.

Recommendation and Action taken by

Engineer: The Contractor is also requested to

install signboard system in this area in order to

ensure safety for public traffic.

Responsible Party: Posco

Page 85: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 77

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 9, 2014

Deadline: immediately

Current status: The Contractor has finished

the construction work in this area and installed

the signboard to warn the road user about the

height of the bridge; however, the surface of

existing road in this section is destroyed

June 23, 2014

4.13.4 Package A4

During the site inspections in this period, we didn’t detect any serious problem of traffic

maintenance and protection in package A4.

4.13.5 Package A5

Location: Public road Km129

Site visit: Apr 25; Jun 04

Date first observed: 25th April, 2014

Problems description and cause: Quality of

public road was impacted by the Contractor’s

construction activities.

Recommendation and Action taken by

Engineer: The Contractor must implement the

tasks as follows:

Page 86: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 78

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

April 25, 2014 (Km129)

June 4, 2014 (Km129)

1. Undertake repair of damaged sections to

ensure that these are in passable condition.

2. Undertake full restoration of damaged road

sections.

Responsible Party: Keangnam Contractor

Deadline: 10-May-2014

Current status: The Contractor is reparing

damaged public road in orde to ensure the

region’s traffic.

May 7, 2014

May 30, 2014

Location: Public road - Km143+000

Site visit: May 07, 30

Date first observed: 07-May-2014

Problems description and cause: Certain

sections of Provincial Road 166 from km 141 to

143 as well as a section of the local road along

km 149, which is used by Project vehicles, are

damaged/in bad condition

Recommendation and Action taken by

Engineer: The Contractor must implement the

tasks as follows:

1. Undertake repair of damaged sections to

ensure that these are in passable condition.

2. Undertake full restoration of damaged road

sections.

(Referring to the letter No. GET-KEA-A5-145

dated on 15th May, 2014)

Responsible Party: Keangnam Contractor

Deadline: Immediate

Page 87: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 79

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

Current status: The Contractor is combining

with Local authorities and Yen Bai province

people’s committee in order to repair damaged

Province road No.166

4.13.6 Package A6

April 2, 2014 (Km180)

April 7, 2014 (Km165)

Location: Package A6

Site visit: Apr 2, 7; May 14, 19

Description: The Contractor installed safety signboard in roads.

May 14, 2014 (Km165)

4.13.7 Package A7

Location: Underpass culvert Km 211+565

Site visit: Apr 24; May 29; Jun 03

Date first observed: 20-Feb-2014

Problems description and cause: The

Page 88: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 80

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

April 24, 2014

May 29, 2014

frontage road is dirty and slippery causing

difficulty for road users

Recommendation and Action taken by

Engineer: The Contractor has been requested

to speed up the construciton work here to

ensure the traffic condition for road users as

designed. Refer to letters Get4-GRBCC-1042

and 1056

Deadline: 28-Feb-2014 (Immediate)

Current status: The Contractor is carrying out

the work; surface of frontage road has been

covered with subbase

June 03, 2014

4.13.8 Package A8

Apr 10, 2014

Location: Underpass box culvert Km235+800

Site visit: Apr 10, 23; May 06; June 24

Date first observed: 19-Feb-2014

Problems description and cause: Frontage

road is dirty and slippery causing difficulty for

road users

Recommendation and Action taken by

Engineer: The Engineer has requested the

Contractor to speed up the work in this area to

Page 89: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 81

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

May 06, 2014

June 24, 2014

ensure the traffic condition for road users. Refer

to letters Get4-Vinaconex-912 and 230 EPMU-

NBLC-A8

Deadline: 28-Feb-2014

Current status: The Contractor is carrying out

the work here to improve the traffic condition as

designed; however, the progress of work is

slow

4.14 SIGNPOSTING IN DANGEROUS SURFACES

4.14.1 Package A1

At the present, at package A1, the Contractor has finished all construction works.

4.14.2 Package A2

Up to now, the main construction work of package A1 has been finished.

4.14.3 Package A3

Location: Box Culvert - Km 60+570

Site visit: Apr 03, 10, 24; May 20

Page 90: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 82

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

April 10, 2014

May 20, 2014

Current status: Safety fence has installed

surrounding dangerous deep hole. Up to now,

the package A3 has been finished the main

construction work and exploited from June 28,

2014

4.14.4 Package A4

Having inspected the construction sites, there is no serious problem noted during the site

inspections. However, the Engineer also recommended the Contractor to pay attention to this

issue if it happens and the necessary countermeasures must be applied to prevent accident

happening.

4.14.5 Package A5

In the site inspections, we didn’t detect the problem on the sites. However, the Engineer also

recommended the Contractor to pay attention to this issue if it happens and the necessary

countermeasures must be applied to prevent accident happening.

Page 91: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 83

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4.14.6 Package A6

April 7, 2014 (Km165)

April 7, 2014 (Ngoi Chac bridge)

April 15, 2014 (Km179)

Location: Package A6

Site visit: Apr 7, 15; May 14, 28; June 5, 16

Description: The Contractor installed

signposting in dangerous surfaces in order to

keep the Project’s safety. Package A6 has been

opened for traffic in June 14, 2014.

May 14, 2014 (Tunnel’s construction site)

June 5, 2014 (Km174)

Page 92: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 84

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4.14.7 Package A7

At the present, the main construction work of package A7 has been finished and it has come to

operation.

4.14.8 Package A8

At the present, the main construction work of package A8 has been finished and it has come to

operation.

4.15 RESTORATION AND LANDSCAPING WORKS

4.15.1 Package A1

The Contractor has finished the planting anti-flare and landscaping trees in median and toll

plazas. Planting grass on slopes of embankment to protect slopes from erosion also has been

completed.

4.15.2 Package A2

Up to now, the Contractor has completed planting anti-flare and landscaping trees in median.

Twenty kilometers of embankment slopes has been planted with grass to protect slopes from

erosion. Remaining slope is being prepared in order to carry out sodding work.

4.15.3 Package A3

The Contractor has already planted the anti-flare and landscaping tree in median. It’s about

40% of slope protected with grass and the Contractor is finishing the remaining slope to carry

out the sodding work.

4.15.4 Package A4

The Contractor is preparing to plant the anti-glare trees in median in compliance with the

requirements of the Project‘s Technical Specification.

4.15.5 Package A5

Up to now, the Contractor has grassed about 80% of the slopes and the Contractor is trying to

finish the remaining slope on schedule to complete the sodding work.

Page 93: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 85

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4.15.6 Package A6

The Contractor already finshed the sodding work and anti-flare trees in the median of package

A6. Package A6 has come to operation in June 14, 2014.

4.15.7 Package A7

The Contractor has already submitted Restoration plant for Unauthorized disposals at

Km190+420; Km208+890; Km209+800 and Km195+350- Km195+500 on March 28th 2014.

Engineer reviewed and proposed to VEC and ADB to checking and approval. So now the

contractor was waiting opinion of ADB mission and will carry out according to ADB mission

mentions.

Till the present, the Contractor has grassed about 70% of the slopes and all the surfaces that

are prepared for second stage and the Contractor is trying to finish the remaining slope on

schedule to complete the sodding work.

4.15.8 Package A8

Up to the date, the Contractor has grassed about 70% of the slopes and the surface that is

prepared for second stage and the Contractor is carrying out the remaining work.

4.16 ACCIDENTS DUE TO THE LACK OF SAFETY MEASURES. RESPONSIBLES

During this period, the second quarter in 2014, by the site inspection, Consultant did not notice

about any serious accident happened due to lack of safety measures. Also, Consultant did not

receive any report regarding significant accidents in any package.

However, the Consultant has often required the Contractors to comply with the Methods

Statement as well as the project’s Safety Plan and to improve the management and control of

safety issues to ensure the project’s safety during construction process and prevent

unfortunate accidents in the future.

Page 94: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 86

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4.17 CONTRACTORS’ ENVIRONMENTAL AND SAFETY SPECIALISTS MOBILIZATION

As this issue is one of the most important ones for the right implementation of the contractors’ ECP and ECAP, here is presented a summary

table of the currently situation, updated until September 2013, in each package about the mobilization of contractors’ environmental and safety

managers. Some remarks are also considered inside the table.

PACKAGECURRENT STATUS

POSITION PROPOSED APPROVED MOBILIZED NAME REMARKS

A1 Environment Specialist Yes Yes Yes Jeon Young Sub

Safety manager Yes Yes Yes Le Dinh Quyen

A2

Safety manager Yes Yes Yes Le Dinh Quyen

A3 Environmental manager

Safety manager Yes Yes Yes Nguyen Thanh Cong

Demobilzied

A4 Environmental manager Yes No No Phan Manh Ha

Contractor proposed Mr Ha as Environment manager according to the letter KNEA4-GET-2014-192

Safety manager Yes Yes Yes Nguyen Danh Nam

Demobilized

A5 Environmental manager Yes Yes Yes Cho, Han Sun

Safety manager Yes Yes Yes Nguyen Van Phuc

A6 Environmental manager Yes Yes Yes Hee Duk Kim

Page 95: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 87

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

PACKAGECURRENT STATUS

POSITION PROPOSED APPROVED MOBILIZED NAME REMARKS

Safety manager Yes Yes Yes Kwon, Oh Lin

A7

Environmental manager Yes Yes No Li Sheng Guang EPMU approved by letter No: 1562 /EPMU-NBLC-KH

These managers, after have been approved, were never mobilized,

Safety manager Yes Yes No Lai Jian Hong

A8 Environmental manager Yes Yes Yes Tran Van Dinh Package already opened to traffic

Safety manager Yes Yes Yes Mai Xuan Lap Package already opened to traffic

Page 96: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 88

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

5. REFERENCE DOCUMENTS RELATIVE TO ENVIRONMENT, HEALTH AND SAFETY

ISSUES

5.1 PACKAGE A1

5.2 PACKAGE A2

5.3 PACKAGE A3

Nº Document reference Date Remark

1 GET2-POS-A3-2330 Apr 12, 2014

Request to ensure safety Km64+100

regarding collapse high voltage power

line).

2 GET2-POS-A3-2341 April 22, 2014

Request the Contractor to provide related

documents of landslide compensation-

Package A3

3 GET2-POS-A3-2342 April 22, 2014

Request the Contractor to solve landslide

in Phu Ninh- Hung Lo-Kim Duc- Viet Tri

City.

4 GET2-POS-A3-2343 April 22, 2014

Request the Contractor to remove spoil

and submit document of disposal area

section Km55+300- Package A3

5 GET2-POS-A3-2360 May 5, 2014 Environment and safety issues at

Package A3.

6 GET-MISC-410 May 6, 2014 Safety issue under NBLC Highway

Project

7 GET2-POS-A3-2360 May 13, 2014 Environment and safety issues at

Package A3.

8 GET-POS-A3-264 May 15, 2014 ADB Inspection Mission, May 2014 -

Package A3

9 GET2-POS-A3-2369 May 21, 2014 Warning the Project Manager about delay

to improve the safety issues at National

Page 97: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 89

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

Railway Flyover, Package A3.

10 GET2-POS-A3-2375 May 30, 2014 Decorative plants at IC8 bridge.

11 GET2-POS-A3-2378 June 06, 2014

Remind the Contractor POSCO to

cooperate with local authorities to solve

the landslides and vibration issues at

Package A3

12 GET2-POS-A3-2383 June 13, 2014

Approve Environmental monitoring and

Observation services report in April 2014

- Package A3

13 GET-MISC-416 June 20, 2014 To ensure traffic safety on expressway

5.4 PACKAGE A4

Nº Document reference Date Remark

1 GET2-KEA-A4-1539 April 08, 2014 Request the Contractor to ensure safety

at construction area of Ngoi lao bridge

2 GET2-KEA-A4-1545 April 22, 2014

Request the Contractor to provide related

douments of landslide compensation-

package A4

3 GET2-KEA-A4-1546 April 22, 2014

Request the Contractor to solve landslide

in Sai Nga and Son Nga commune – Cam

Khe district, Phu Tho province.

4 GET2-KEA-A4-1547 April 22, 2014

Request the Contractor to submit disposal

area document for soft soil treatment from

Km82+810 - Km83+360 - Package A4.

5 GET-MISC-410 May 6, 2014 Safety issue under NBLC Highway

Project

6 GET2-KEA-A4-1558 May 13, 2014

Request the Contractor KEANGNAM to

ensure the environment & safety issues

and mobilize the environment and safety

Page 98: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 90

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

managers

8 GET-KEA-A4-153 May 15, 2014 ADB Inspection Mission, May 2014 -

Package A4

9 GET-MISC-412 May 16, 2014

Second Reminder. Ensure traffic safety

for works carried out in open to traffic

areas

10 GET2-KEA-A4-1580 June 13, 2014

Ensure environment and safety issues at

package A4 and submit the document for

unauthorized disposal at Km96

11 GET2-KEA-A4-1581 June 13, 2014

Approve Environmental monitoring and

Observation services report in March

2014 - Package A4.

12 GET2-KEA-A4-1582 June 13, 2014

Approve Environmental monitoring and

Observation services report in April 2014

- Package A4

13 GET-MISC-416 June 20, 2014 To ensure traffic safety on expressway

14 GET2-KEA-A4-1588 June 26, 2014 Ensure safety at package A4

5.5 PACKAGE A5

No Document reference Date Remark

1 GET3-KEANGNAM-14-A5-107

April 7, 2014 Requires the Contractor to submit documents related to compensate local people 

2 GET3-KEANGNAM-14-A5-117

April 17, 2014 Requires the Contractor to improve fuel control on the site

3 GET3-KEANGNAM-14-A5-125

April 23, 2014 Approval of Report on Environmental Monitoring for March 2014

4 GET3-KEANGNAM-14-A5-129

April 24, 2014 Comment on the documents of Asphalt Concrete Batching Plant Km126

Page 99: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 91

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

5 GET3-KEANGNAM-14-A5-132

April 28, 2014 Inspection at Asphalt Concrete Batching Plants at Km117, Km126, Km135

6 GET3-KEANGNAM-14-A5-148

May 14, 2014 Approval of Report on Environmental Monitoring for April 2014

7 GET3-KEANGNAM-14-A5-153

May 15, 2014

Approval with comments on Asphalt Concrete Batching Plant at Dong Quyet Hamlet, Bao Hung commune, Tran Yen district, Yen Bai province

8 GET3-KEANGNAM-14-A5-157

May 16, 2014 Approval with comments on Asphalt Concrete Batching Plant at Km135+700, package A5

9 GET3-KEANGNAM-14-A5-183

June 10, 2014Request the Contractor to apply measures in order to minimize dust  

10 GET3-KEANGNAM-14-A5-192

June 20, 2014.Approval of Report on Environmental Monitoring for May 2014

11 GET3-KEANGNAM-14-A5-193

June 20, 2014Comment on Method Statement of tree and shrub planting on package A5

12 GET3-KEANGNAM-14-A5-202

June 24, 2014Requires the Contractor to submit documents

13 GET3-KEANGNAM-14-A5-203

June 25, 2014Approval with comments on Asphalt Concrete Batching Plant

5.6 PACKAGE A6

No Document reference Date Remark

1 GET3-DOOSAN-14-A6-079

April 7, 2014 Require the Contractor to apply measures in order to ensure the Project’s environmental and safety issues 

2 GET3-DOOSAN-14-A6-077

April 7, 2014

Approval of Report on Environmental Monitoring for January and February 2014

3 GET3-DOOSAN-14-A6-080

April 7, 2014 Approval of Report on Environmental Monitoring for March 2014

Page 100: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 92

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

4 GET3-DOOSAN-14-A6-076

April 7, 2014 Approval with comments on Disposal area

5 GET3-DOOSAN-14-A6-078

April 7, 2014

Requires the Contractor to submit documents related to compensate local people

6 GET3-DOOSAN-14-A6-084

April 10, 2014 Approval with comments on Disposal areas

7 GET3-DOOSAN-14-A6-090

April 20, 2014 Approval of Report on Environmental Monitoring for April 2014

8 GET3-DOOSAN-14-A6-106

May 14, 2014 Approval of Method statement for Landscaping works, package A6

9 GET3-DOOSAN-14-A6-114

May 23, 2014 Require to survey and design additional living road , package A6

10 GET3-DOOSAN-14-A6-130

June 11, 2014Approval of Report on Environmental Monitoring for May 2014 

11 GET3-DOOSAN-14-A6-142

June 24, 2014Requires the Contractor to submit documents

5.7 PACKAGE A7

Nº Document reference Date Remark

1 GET4-GRBCC-1103 April 02, 2014 Ensure safety and clean on site after

technical open - Package A7

2 GET4-GRBCC-1115 April 22, 2014

Ensure safety and clean on site after

technical open - Package A7- Second

time

3 GET4-GRBCC-1120 April 25, 2014 Ensure safety and clean on site - Package

A7

4 GET-MIS-406 April 29, 2014 ADB’s fact finding mission in May 2014

5 GET-MIS-407 April 29, 2014 Ensure safety during national holidays

Page 101: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 93

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

6 GET-MIS-408 April 30, 2014 Ensure safety for works carried out in

areas already opened for traffic

7 GET-GUA-162 May 15, 2014 Actions to be taken regarding the disposal

along Package A7

8 GET4-GRBCC-1128 May 19, 2014 Request to submit the CMS for assuring

traffic safety during construction

9 GET4-GRBCC-1129 May 20, 2014

Retuning the Proposal drawing, addition

items design gabion baskets 151

provincial road (side MSE wall:

Km195+262.65- Km195+411.80)

10 GET4-GRBCC-1133 May 27, 2014 Request to implement the instruction of

ADB mission on May, 2014

11 GET4-GRBCC-1134 June 04, 2104

Require to clearance for under Bridges,

inside box culverts and pile culverts-

Package A7

12 GET4-GRBCC-1137 June 16, 2014Request to remove the bushes have dead

out of Package A7

13 572/EPMUNBLC-KT June 16, 2014

Construction and exploitation of Package

A7 and A8 (Lao Cai province) of Noi Bai-

Lao Cai expressway Project

14 588/EPMUNBLC-KT June 19, 2014To ensure traffic safety on expressway of

Package A7 and A8

5.8 PACKAGE A8

Nº Document reference Date Remark

1 GET4-Vinaconex-982 April 02, 2014 Ensure safety and clean on site after

technical open - Package A8- third time

2 GET4-Vinaconex- 987A April 16, 2104

Returning the Capacity document of Duc

Minh International Joint Stock company-

Grass supplier for slope of cutting section

Page 102: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

Hanoi office: 12th floor, Ocean Park Building, Dao Duy Anh Street, Dong Da Distric 94

VinhPhuc office: Huu Thu Hamlet, Kim Long Ward, Tam Duong Distric, VinhPhuc Province

Madrid head office: Calle Ramón de Aguinaga 8, 28028 Madrid, Spain

(Vetiver grass)

3 GET4-Vinaconex-993 April 25, 2104 Ensure safety and clean on site -

Package A8

4 GET-MIS-406 April 29, 2104 ADB’s fact finding mission in May 2014

5 GET-MIS-407 April 29, 2104 Ensure safety during national holidays

6 GET-MIS-408 April 30, 2104 Ensure safety for works carried out in

areas already opened for traffic

7 GET4-Vinaconex-995 May 05, 2014

Approval the Capacity document of Duc

Minh International Joint Stock company-

Grass supplier for slope of cutting section

(Vetiver grass)- version A2

8 GET4-Vinaconex-997 May 06, 2014 Returning the construction methods for

planting grasses of Package A8

9 GET4-Vinaconex-1000 May 14, 2014 Approval the Method statement for

planting grasses for works (Version A2)

10 GET-Vinaconex-155 May 15, 2014 ADB inspection mission, May 2014-

Package A8

11 355/EPMU NBLC A8 June 04, 2014

The contractor is requested to removing

the unsuitable material out of Unauthority

disposal

12 GET4- Vinaconex-1028 June 26, 2014Require to clearance for Drainage box

culverts Km233+506- Package A8

Page 103: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

95

6. GRIEVANCE INTAKES. PUBLIC CONSULTATION

As Annex 1 we include a summary table with references about complaints which were

expressed by local people affected by the construction works, to the environmental or social

impact specialists.

It’s supposed that these are not the only existing complaints, but the only ones received or

collected by Consultant.

On the other hand, after being implemented in some packages the system to collect

complaints by the contractors, the Consultant has not received any information from

contractors.

Page 104: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

96

Page 105: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

97

7. ANNEX 1: COMPLAINTS OF LOCAL PEOPLE. SUMMARY TABLE

Page 106: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

98

Page 107: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

99

PACK. LOCATION COMPLAINT DESCRIPTION DATE EXECUTED ACTIONS CURRENT STATUS DOCUMENT.

A2 Km 42+300 ~ Km 44+180

Erosion leads the soil into croplands and cause the lost for 35 households. Local authority (Song Lo’s DPC) has finished calculating the damaged and requested the Contractor to compensate

15-Mar-2014

The EPMU, together with the Engineer and the Contractor, worked with local authorities and make a schedule for compensation from July 14, 2014 till August 04, 2014

Compensation shall be implemented as scheduled

A2

Tam Duong district,

Lap Thach district,

Song Lo district

There are houses that are near the construction sites affected by vibration during carrying out the embankement work; request the Contractor to verify the quo status of these houses and submit a compensation method basing on the calculation of the independent audit companies, then compensate affected households for the damaged assets

27-Mar-2014

The Contractor has hired the independent audit companies to verify the sphere of influence and impact level to compensate affected households for the damaged assets

The Contractor is carrying out the compensation work. Up to now, there were 90% of affected households already compensated. The remaining households don’t agree with compensation level and the Contractor is cooperating with local authority and these owners to deal with this matter

Consultant’s report

A2 Song Lo district

Request the Contractor to compensate impacted household for damaged assets due to flooding which was caused by construction work of the project

25-Mar-2014

The EPMU, together with the Engineer and the Contractor, worked with local authorities and make a schedule for compensation from July 14, 2014 till August 04, 2014

Compensation shall be implemented as scheduled

A3 IC10, TL325B, National raiway flyover

The Contractor’s construction activities and material transportation were caused dustiness at this location

16/04/2014

The Contractor is spraying water at this location in order to minimize the spread of dust during project implementation

The construction work has been finished

Page 108: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

100

PACK. LOCATION COMPLAINT DESCRIPTION DATE EXECUTED ACTIONS CURRENT STATUS DOCUMENT.

A3 TL325B, National raiway flyover

The Contractor is constructing earth works with high vibration level, this situation is causing impact to structure of local people’s house

14/05/2014

The Contractor is combining with local people and local authorities in order to solve this problem

Construction work has been finished so this area was no longer impacted by construction activity

A4

Ngoi Gianh, Ngoi Lao, TL321C, Ngoi Van

The Contractor’s construction activities and material transportation were caused dustiness at this location

22/04/2014

The Contractor is spraying water at this location in order to minimize the spread of dust during project implementation

The Contractor is maintaining the mitigation measure

A5 Km133+700

After completion of embankment works in this area in January 2014, about 3,000 m2 of rice field, which is on higher elevation than the rest of the surrounding land, has not received irrigation. Prior to construction, water flows from higher fields that are now on the other side of the road. As the road now acts like a dam and the current irrigation system is lower than the affected rice field, the land owner can no longer grow rice in the area and prefers that his land is acquired by the Project. The area is also affected by erosion of the road embankment slope

15/04/2014

The Contractor is planting grass at embankment slope and installing side ditch at this location in order to prevent erosion. Besides, the Contractor also is combining with local authorities and EPMU in order to determine feasible options to resolve the issue on irrigation

The work is being carried out

Consultant´s reports

Page 109: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

101

PACK. LOCATION COMPLAINT DESCRIPTION DATE EXECUTED ACTIONS CURRENT STATUS DOCUMENT. The Contractor must: 1-undertake consultations with the District People’s Committee and the affected HH to determine feasible options to resolve the issue on irrigation; 2-Implement slope stabilization measures and adequate drainage to avoid erosion to the rice field.

A5 Km 141+000 Km 143+000 Km 149+000

Certain sections of provincial road 166 from Km141 to Km143 as well as a section of the local road along Km149, which is used by Project vehicles, are damaged/in bad condition The Contractor must: 1-Undertake repair of damaged section to ensure that these are in passable conditionr; 2-Undertake full restoration of damaged road sections.

02/5/2014

The Contractor is combining with District People’s Committee in order to repair these damaged roads.

The work is being carried out

Consultant´s reports

A6 Km 165+000

The Contractor’s construction activities and transportation material are causing impact to quality of public roads, difficultly to vehicles travel through this location The Contractor must:

04/4/2014

The Contractor is combining with District People’s Committee in order to repair these damaged roads.

The work is under implementation

Consultant´s reports

Page 110: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

102

PACK. LOCATION COMPLAINT DESCRIPTION DATE EXECUTED ACTIONS CURRENT STATUS DOCUMENT. 1-Repair damaged roads in order to ensure the region’s traffic; 2-Implement the Engineer’s requirements and instructionsr; 3-Comply with Traffic Control Plan during construction.

A6 Km 159+000

At Km159, this section of provincial road used to have asphalt pavement but it is now in muddy condition due to damage that is caused by Project vehicles The Contractor must: 1-Undertake repair of damaged section to ensure that these are in passable conditionr; 2-Undertake full restoration of damaged road sections.

02/5/2014

The Contractor is combining with District People’s Committee in order to repair these damaged roads.

The work is under implementation

Consultant's reports

A6

Ngoi Rom bride, Ngoi Cong bridge, Ngoi Hut bridge, Suoi Nau bridge

River obstruction due to temporary access road at bridge sites. Although the temporary access road across the river is no longer needed for the remaining bridge works, the Contrctor has yet to remove the said obstruction causing high velocity flow downstream. This condition will cause scouring/erosion of the river

02/5/2014

The Contractor is combining with District People’s Committee in order to solve this problem

The work is under implementation

Consultant's reports

Page 111: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

103

PACK. LOCATION COMPLAINT DESCRIPTION DATE EXECUTED ACTIONS CURRENT STATUS DOCUMENT. embankment. The Contractor must undertake complete removal of the temporary access road and restoration of affected riverbed

A7 Km 210+200

Erosion leaded the soil from pipe culvert to the cropland; request the Contractor to restore the affected area and compensate land owner for damaged asset; countermeasure must be implemented to avoid this problem happening in the future

09/4/2014

The contractor had coordinate with Local Authorities and EPMU to compensate for household

Consultant´s reports

A7 Km 215+000

Erosion leaded the soil from pipe culvert to the adjacent pond; request the Contractor to restore the affected area and compensate land owner for damaged asset; countermeasure must be implemented to avoid this problem happening in the future

06/5/2014

The Contractor is cooperating with local authority and affected household to deal with this matter

The problem is being resolved

Consultant´s reports

A7 Km199+100 While construction the earth overflow in fields

13/2/2012; 14/8/2012

Request the contractor to dredging or compensation

The contractor had coordinate with Local Authorities and EPMU to compensate for household

Consultant´s reports

A8 Km 237+700 There is a house that was 09/4/2014 Compensation has been Consultant´s reports

Page 112: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

104

PACK. LOCATION COMPLAINT DESCRIPTION DATE EXECUTED ACTIONS CURRENT STATUS DOCUMENT. impacted by vibration during carrying out embankement work and househole owner requested the Contractor to compensate her for damaged asset

implmented on 25/4/2014

A8 Km 220+900

Local people complained for the dirtiness and difficulty during traveling through the underpass box culvert in this area; request the Contractor to repair this section to ensure the traffic condition for the people

06/5/2014

The Contractor has carried out the work to repair the road in this section and ensure the traffic condition here

Consultant´s reports

A8 Km222+000 ~ Km222+500

Local people complained that it’s lack of frontage road to access their fields and forest; request the Contractor to construct a road to connect with production area

13/6/2014 The Contractor is carrying out the work

The work is under construction

Consultant´s reports

Page 113: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

105

8. ANNEX 2: DATA OF ENVIRONMENTAL QUALITY PARAMETERS ANALYSIS

Page 114: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

106

Page 115: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

107

8.1 ANNEX 2.1: AIR QUALITY PARAMETERS

Page 116: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

108

Page 117: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

109

PACKAGE A3

Station Sensitive Receptors

Sampling Date & Time,

weather condition

PARAMETERS, µg/m3 SO2 CO NOx TSP PM10

Apr May June Apr May June Apr May June Apr May June Apr May June

Km 48+500 Residential area

14/1/2014 14/2/2014

Km 55+500 Residential area

14/1/2014 14/2/2014

050 3,302 31 128 108

Km 67+700 Residential area

14/1/2014 14/2/2014

65 3,472 29 199 79

Km 78+900 Street 14/1/2014 14/2/2014

58 3,205 62 231 102

QCVN 05:2009/BTNMT 350 (1-hr) 30,000 (1-hr) 200 (1-hr) 300 (1-hr) 150 (24-hr)

PACKAGE A4

Station Sensitive Receptors

Sampling Date & Time,

weather condition

PARAMETERS, µg/m3

SO2 CO NOx TSP PM10

Apr May June Apr May June Apr May June Apr May June Apr May June

Km 91+150 School 20/5/2014 172 3,162 39 235 146

Km 95+100 Residential area

20/5/2014 126 3,264 62 146 112

Page 118: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

110

CPB TanThanh

Residential area

20/5/2014 215 3,169 85 262 124

Km 88+300 Residential area

21/5/2014 151 3,658 69 243 138

Km 104+900 Residential area

21/5/2014 119 3,056 71 124 88

Km 106+500 Residential area

21/5/2014 127 3,231 42 203 113

Km 106+800 School 21/5/2014 148 3,266 62 168 136

QCVN 05:2009/BTNMT 350 (1-hr) 30,000 (1-hr) 200 (1-hr) 300 (1-hr) 150 (24-hr)

PACKAGE A5

Station Sensitive Receptors

Date

PARAMETERS, µg/m3

SO2 CO NOx TSP HC

Apr May June Apr May June Apr May June Apr May June Apr May June

Km 117+050 A1 174 1620 162 178 - - -

Km 117+050 A1 159 1910 149 172 - - -

Km 117+050 A1 141 1540 157 195 - - -

Km 118+820 A2 292 3830 175 248 - - -

Km 118+820 A2 241 3270 162 231 - - -

Km 118+820 A2 247 3480 179 240 - - -

Page 119: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

111

Station Sensitive Receptors

Date

PARAMETERS, µg/m3

SO2 CO NOx TSP HC

Apr May June Apr May June Apr May June Apr May June Apr May June

Km 121+433 A3 293 4710 188 257 - - -

Km 121+433 A3 322 4530 182 242 - - -

Km 121+433 A3 278 4490 174 239 - - -

QCVN 05:2009/BTNMT 350 (1-hr) 30,000 (1-hr) 200 (1-hr) 300 (1-hr) 5000 (1-hr)

Notes:

A1, A2, A3: Sampling points are close to Bao Long Church area (Km117+050): (GPS: N 21.40.269; E 104.53.057)

A4, A5, A6: Sampling points are close to Hop Minh My bridge construction site (Km118+820): (GPS: N 21.40.801; E 104.52.259)

A7, A8, A9: Sampling points are close to National Road bridge construction site (Km121+433): (GPS: N 21.41.609; E 104.51.171)

PACKAGE A6

Due to the main construction works of package A6 has been finished in the last quarter and miscellaneous works such as fencing, installing

signboard, cleaning, grassing don’t affect the air quality so the air mornitoring work has been terminated.

Page 120: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

112

Page 121: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

113

8.2 ANNEX 2.2: WATER QUALITY PARAMETERS

Page 122: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

114

Page 123: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

115

PACKAGE A3

May

Sensitive Receptors

Date pH DO TSS COD

BOD5 (20oC)

Surf. Oil and Grease

Fecal Coliform

Total Coliform

- mg/l mg/l mg/l mg/l mg/l mg/l MPN/100mlMPN/100ml

Km 67+000 21/05/2014 6,52 - 22 18 10 - - 20 5.600 Km 78+000 21/05/2014 6,62 - 21 15 09 - - 24 5.720

QCVN08:08 5,5-9 ≥ 4 50 30 15 0,4 0,1 100 7500

Weather condition: Cloudy, average temperature 28.5 C, windy speed 0.33 m/s. South-East windy direction

PACKAGE A4

May

Sensitive Receptors

Date pH DO TSS COD

BOD5 (20oC)

Surf. Oil and Grease

Fecal Coliform

Total Coliform

- mg/l mg/l mg/l mg/l mg/l mg/l MPN/100mlMPN/100ml

Km 88+700 22/05/2014 6,52 - 32 14 7,5 - - 13 4.000 Km 97+500 22/05/2014 6,33 - 36 13,1 6,9 - - 10 4.820

Km 101+000 22/05/2014 6,52 - 30 11,8 6,6 - - 8 3.800 Km 109+000 22/05/2014 6,66 - 32 12,2 7,2 - - 6 3.740 Km 108+227 22/05/2014 6,48 - 33 12,6 7,6 - - 11 4.080

QCVN08:08 5,5-9 ≥ 4 50 30 15 0,4 0,1 100 7500

Weather condition: Cloudy, average temperature 28 C, windy speed 0.38 m/s. South-East windy direction

PACKAGE A5

According to Environmental Monitoring Plan approved by the Engineer through the letter Ref.

GET3-KEANGNAM-11-A5-037 dated 28th March, 2011, the contractor carryied out the

Environment monitoring with frequency: 1 time / 1 month. Include some indications: pH, DO,

TSS, COD, BOD5, Surfactant, Oil and grease, Fecal coliform, total coliform.

May

Page 124: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

116

Sensitive Receptors

Date pH DO TSS COD

BOD5 (20oC)

Surf. Oil and Grease

Fecal Coliform

Total Coliform

- mg/l mg/l mg/l mg/l mg/l mg/l MPN/100mlMPN/100ml

W1 28/05/2014 7.1 5.7 32 7 < 5 < 0,1 < 0,1 50 960

W2 28/05/2014 6.9 5.5 34 9 < 5 < 0,1 < 0,1 60 930

W3 28/05/2014 7.0 5.4 36 5 < 5 < 0,1 < 0,1 75 880

W4 28/05/2014 6.6 5.9 40 6 < 5 < 0,1 < 0,1 65 780

W5 28/05/2014 7.1 6.4 37 6 < 5 < 0,1 < 0,1 64 690

W6 28/05/2014 7.3 6.1 33 7 < 5 < 0,1 < 0,1 70 710

W7 28/05/2014 7.5 5.6 30 8 < 5 < 0,1 < 0,1 65 680

W8 28/05/2014 6.7 6.2 32 9 < 5 < 0,1 < 0,1 72 610

W9 28/05/2014 6.6 6.0 31 19 11 0.24 0.05 420 4700

W10 28/05/2014 6.5 6.3 36 20 14 0.26 0.03 470 5900

W11 28/05/2014 6.3 5.7 39 18 12 0.30 0.07 510 5700

W12 28/05/2014 6.2 5.6 44 23 15 0.32 0.09 570 6100

QCVN08:08 5,5-9 ≥ 4 50 30 15 0,4 0,1 100 7500

Weather condition: Cloudy, average temperature 29.1 C, windy speed 0.37 m/s. South-East windy direction

Notes:

W1: Ngoi Thia river (Km145+500) – The bridge pier (N21050’961’’; E104042’500’’)

W2: Ngoi Thia river (Km145+500) – 50m from the bridge pier (toward upstream)

(N21050’960’’; E104042’483’’)

W3: Ngoi Thia river (Km145+500 – 200 m from the bridge pier (toward downstream)

(N21050’982’’; E104042’521’’)

W4: Ngoi Thia river (Km145+500 – 400 m from the bridge pier (toward downstream)

(N21050’998’’; E104042’539’’)

W5: Y Can lake (Km126+000) – Surface water sample at position No. 1 (N21044’038’’;

E104049’496’’)

W6: Y Can lake (Km126+000) – Surface water sample at position No. 2 (N21044’046’’;

E104049’503’’)

W7: Y Can lake (Km126+000) – Surface water sample at position No. 3 (N21044’067’’;

E104045’553’’)

W8: Y Can lake (Km126+000) – Surface water sample at position No. 4 (N21044’079’’;

E104045’571’’)

Page 125: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

117

W9: Nuoc Mat lake (Km122+000) – Surface water sample at position No. 1 (N21044’741’’;

E104050’492’’)

W10: Nuoc Mat lake (Km122+000) – Surface water sample at position No. 2

(N21044’711’’; E104050’935’’)

W11: Nuoc Mat lake (Km122+000) – Surface water sample at position No. 3

(N21044’726’’; E104050’955’’)

W12: Nuoc Mat lake (Km122+000) – Surface water sample at position No. 4

(N21044’725’’; E104050’965’’)

* Nuoc Mat lake (W9, W10, W11 and W12) has a small area and locates in the residential area

with dense population density. The area of lake tends to be smaller because of site clearance

as well as encroachment by inhabitants. Because domestic wastewater from residential areas

discharges into Nuoc Mat lake, water quality of the lake in polluted partly although the

measured values are within acceptable limits in QCVN 08:2008 – column B1.

PACKAGE A6

Due to the main construction works of package A6 has been finished in the last quarter and

miscellaneous works such as fencing, installing signboard, cleaning, grassing don’t affect the

water quality so the water quality mornitoring work has been terminated.

Page 126: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

118

Page 127: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

119

8.3 ANNEX 2.3: NOISE LEVELS

Page 128: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

120

Page 129: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

121

PACKAGE A3

Package A3 has been opened for exploitation so there is no construction work that causes the

noise and vibration affecting sensitive areas.

PACKAGE A4

May

Noise measuring

Vibration measuring

MonitoringValue (dBA) Standard Value (dBA)

Station 6h-10h 10h-14h 14h -18h 6h - 21h

Km 91+150 55 53 55

70

Km 95+100 65 59 62

Tan ThanhCBP 67 60 64

Km 88+400 65 60 62

Km 105+100 62 55 61

Km 107+000 65 54 63

Km 106+800 62 53 60

Station Min. Value Max. Value Average

Value Standard Value

(mg/m3)

Km 91+150 0,33 0,29 0,31

0,055

Km 95+100 0,32 0,28 0,30

Tan ThanhCBP 0,34 0,30 0,32

Km88+300 to Km88+500 0,28 0,26 0,28

Km104+900 to Km105+350 0,28 0,24 0,26

Km106+500 to Km107+600 0,29 0,25 0,27

Km106+800 0,33 0,29 0,31

Page 130: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

122

PACKAGE A5

January

Station Sensitive Receptors

Date

Result (dB) (average)

QCVN 26:2010 Exceeding

value

Working shift

6 h – 21h

21h – 6h

6 h – 21h

21h – 6h

6 h – 21h

21h – 6h

Km 117+050

N 1 23 / 04 / 2014 48.3 38.7 55 45 - -

- The value of noise level referred to standards applied for extremely quiet areas (QCVN 26:2010/BTNMT) - Noise primarily generated from the vehicle the vehicles or motorbike but constructional equipment

Weather condition: Cloudy, average temperature 28.2 C, windy speed 0.26 m/s. South-East windy direction

Station Sensitive Receptors

Date

Result (dB) (average)

QCVN 26:2010 Exceeding

value

Working shift

6 h – 21h

21h – 6h

6 h – 21h

21h – 6h

6 h – 21h

21h – 6h

Km118+820 N 2 23 / 04 / 2014 61.9 49.2 70 55

Km121+433 N 3 23 / 04 / 2014 68.2 51.9 70 55 - -

- The value of noise level referred to standards applied for commerce, office, industry area. - Noise primarily generated

Weather condition: Cloudy, average temperature 28.2 C, windy speed 0.26 m/s. South-East windy direction

Notes:

According to Environmental Monitoring Plan approved by the Engineer through the letter Ref.

GET3-KEANGNAM-11-A5-037 dated 28th March, 2011, the contractor carries out the

Environment monitoring with frequency: 1 time / 1 month.

N1: Sampling points are close to Bao Long Church area (Km117+050): (GPS: N 21.40.269;

E 104.53.057)

N2: Sampling points are close to Hop Minh My bridge construction site (Km118+820):

(GPS: N 21.40.801; E 104.52.259)

Page 131: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

123

N3: Sampling points are close to National Road bridge construction site (Km121+433):

(GPS: N 21.41.609; E 104.51.171)

PACKAGE A6

Package A3 has been opened for exploitation so there is no construction work that causes the

noise and vibration affecting sensitive areas.

Page 132: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

124

Page 133: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

125

9. ANNEX 3: DOCUMENTATION RECEIVED FROM CONTRACTORS DURING THE

PERIOD

Page 134: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

126

DOCUMENTS RECEIVED FROM CONTRACTORS DURING THE FOURTH QUARTER 2013

PACKAGE CONTRACTOR REFERENCE DESIGNATION REV APPROVED

A5 KEANGNAM KNE-NBLC5-

VEC&GET-14-142

Submission for approval of Asphalt plant at location Hamlet

4, Minh Tien commune, Tran Yen district, Yen Bai province

1 Yes

A5 KEANGNAM

KNE-NBLC5-

VEC&GET-14-003

Submission for approval of asphalt concrete batching plant

at Dong Quyet Hamlet, Bao Hung commune, Tran Yen

district, Yen Bai province – package A5

1

Yes

A5 KEANGNAM KNE-NBLC5-

VEC&GET-14-163A

Submission for approval of Asphalt Concrete Batching Plant

at Km135+700 - package A5

1 Yes

A5 KEANGNAM KNE-NBLC5-

VEC&GET-14-334

Report on Environmental Monitoring for May 2014 0 Yes

A5 KEANGNAM KNE-NBLC5-

VEC&GET-14-330

Method Statement of tree and shrub planting on package

A5

0 No

A5 KEANGNAM KNE-NBLC5-

VEC&GET-14-277

Submission for approval of Asphalt plant to be used for

section Km143+000 – Km150+900, package A5

1 Yes

A6 DOOSAN DHIC-14-SET-008 Request for approval of new disposal areas (package A6) 0 Yes

A6 DOOSAN DHIC-14-SET-011 Request for approval of new disposal areas (package A6) 0 Yes

A6 DOOSAN DHIC-14-SET-012 Environmental monitoring plan in May 2014 0 Yes

Page 135: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

127

DOCUMENTS RECEIVED FROM CONTRACTORS DURING THE FOURTH QUARTER 2013

PACKAGE CONTRACTOR REFERENCE DESIGNATION REV APPROVED

A6 DOOSAN DHIC-14-SET-016 Submission of environmental monitoring report in May 2014 0 Yes

A6 DOOSAN DHIC-14-CT-039 Method Statement for landscaping work, package A6 1 Yes

A7 GRBCC

Ref.

GRBCC/GETINSA/

A7/2040

Shop drawing, plan to process and slope protection of

disposal site Km195+500

A1

A7 GRBCC

Ref.

GRBCC/GETINSA/

A7/2054

Proposal drawing, addition items design gabion baskets 151

provincial road (side MSE wall: Km195+262.65-

Km195+411.80)

A1 Returned the

contractor

A8 VINACONEX A8/LC/140411-04

Submit the Capacity document of Duc Minh International

Joint Stock company- Grass supplier for slope of cutting

section (Vetiver grass)

A1 Returned the

contractor

A8 VINACONEX A8/LC/140415-03 Submit the Method statement for planting grasses for works

(Version A2)

A1 Returned the

contractor

A8 VINACONEX A8/LC/140421-01

Submit the Capacity document of Duc Minh International

Joint Stock company- Grass supplier for slope of cutting

section (Vetiver grass)- version A2

A2

Approved

Page 136: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

128

DOCUMENTS RECEIVED FROM CONTRACTORS DURING THE FOURTH QUARTER 2013

PACKAGE CONTRACTOR REFERENCE DESIGNATION REV APPROVED

A8 VINACONEX A8/LC/140508-09 Submit the Method statement for planting grasses for works

(Version A2)

A2 Approved

A8 VINACONEX A8/LC/140218-04 Submit the Method statement for planting anti-glare tree for

works of package A8

A1 Approved

Page 137: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

129

10. ANNEX 4: STATUS OF THE DOCUMENTATION RELATED TO BORROW PITS,

QUARRIES, SOIL DISPOSALS AND CONCRETE BATCHING PLANTS

Page 138: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

130

Page 139: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

131

Note:

a – For public lands, indicate whether it is the property of the commune, district, province, etc.

b – Indicate the beneficial use of the property before it was acquired for the project (e.g., rice field, acacia plantation, etc.). If none, provide a short description, e.g., grassland, abandoned/idle farm lot, etc.

c – Specify which government agency (e.g., District People’s Committee) issued the approval, including any written agreement between the contractor and the land owner

Package A1

BORROW PITS

Package /Borrow Pit

No. Location

Approved Area (m2)

ApprovedVolume

(m3)

Ownershipa Prior Land

Useb

Approval Operation Schedule

Name Contact Info Local

AuthoritiesPSC Start

Estimated Completion

Actual Completion

A1/BP6

Minh Tri and Minh Phu Commune, Soc Son District,

Hanoi city

832,862 Industrial crop land

31-Aug-09 31-Aug-09 Closed 2013

A1/BP16

La Mai Hill, Huong Son Commune,

Binh Xuyen District, Vinh Phuc Province

606,590 Industrial crop land

27-Apr-10 06-May-10 06-May-10 27-May-13 Closed 2013

A1/BP17

Go De Hill, Huong Son Commune,

Binh Xuyen District, Vinh Phuc Province

263,290 Industrial crop land

27-Apr-10 06-May-10 06-May-10 27-May-13 Closed 2013

A1/BP21

Dong Mo Hill, Nam Son Commune, Soc Son District,

Hanoi City

492,800 Industrial crop land

01-Nov-10 25-Mar-11 25-Mar-11 30-Nov-15 Closed 2013

A1/SG1

Go De Hill, Huong Son Commune,

Binh Xuyen District, Vinh Phuc Province

100,000 Industrial crop land

27-Apr-10 13-Jan-11 13-Jan-11 27-May-13 Closed 2013

Page 140: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

132

BORROW PITS

Package /Borrow Pit

No. Location

Approved Area (m2)

ApprovedVolume

(m3)

Ownershipa Prior Land

Useb

Approval Operation Schedule

Name Contact Info Local

AuthoritiesPSC Start

Estimated Completion

Actual Completion

A1/SG4

Dong Giang Hill, Trung My

Commune, Binh Xuyen District, Vinh

Phuc Province

90,000 Industrial crop land

27-Apr-10 22-Mar-12 22-Mar-12 27-May-13 Closed 2013

QUARRIES

Package /Quarry No.

Location Approved Area (m2)

ApprovedVolume

(m3)

Ownershipa Prior Land

Useb

Approval Operation Schedule

Name Contact Info Local

Authorities PSC Start

Estimated Completion

Actual Completion

A1/Q1

Quang Son commune, Lap

Thach dist, Vinh Phuc

123,000 2,611,729 Rock-mine

08-Apr-10 13-Dec-11 13-Dec-11 17-Apr-13 Closed 2013

A1/Q2

Trung Mau commune, Binh Xuyen dist, Vinh

Phuc

640,000 75,187,00

0

Rock-mine

21-Jul-04 13-Dec-11 13-Dec-11 30-Jun-14 Closed 2013

BATCHING PLANTS

Package/ CBP No.

Location Appropriate

settling pond

Noise and dust

measures

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Local

AuthoritiesPSC Start Est. End

Actual End

A1/CBP1 Underpass NH2 Yes Yes Evernew Holding.,

JSC

A24-BT4, My Dinh commune,

Tu Liem dist, Hanoi

Unidentified Unidentified 10-May-11 10-May-11 Dec 2013

A1/CBP2 Underpass NH2 Yes Yes Ngoc Mai Construct.

Tho Dan village, Kim No

Unidentified Unidentified 29-Jun-11 29-Jun-11 Dec 2013

Page 141: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

133

BATCHING PLANTS

Package/ CBP No.

Location Appropriate

settling pond

Noise and dust

measures

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Local

AuthoritiesPSC Start Est. End

Actual End

JSC commune, Dong Anh dist,

Hanoi

A1/CBP3 Km 13+500 Yes Yes POSCO

POSCO E&C – Noi Bai – Lao Cai Highway project – Huu

thu village, Kim Long commune,

Tam Duong dist, Vinh Phuc

Pond 05-May-08 27-Jan-10 27-Jan-10 Dec 2013

A1/CBP4 Km 25+000 Yes Yes POSCO

POSCO E&C – Noi Bai – Lao Cai Highway project – Huu

thu village, Kim Long commune,

Tam Duong dist, Vinh Phuc

Long term cropland

05-May-08 27-Jan-10 27-Jan-10 Dec 2013

SPOILS DISPOSAL AREAS

Package / SD No.

Location Approved

Area (m2)

Approved Capacity

(m3)

Ownershipa Approval Operation

Name Contact Info Local

Authorities PSC

A1/SD1

Trung Mau village, Trung My commune, Binh Xuyen district, Vinh Phuc province

200,000 m2 200,000 m3

Hoang Chi Thanh

Hoang Van Ngoc

Dong Ich Hamlet, Trung My commune,

Binh Xuyen dist, Vinh

Phucs

06-Dec-10 20-Dec-10

Page 142: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

134

Package A2

BORROW PITS

Package /Borrow Pit No.

Location ApprovedArea (m2)

ApprovedVolume

(m3)

Ownershipa Prior Land

Useb

Approval Operation Schedule

Name Contact Info Local

AuthoritiesPSC Start

Estimated Completion

Actual Completion

A2/BP4

Chay Hill, Vinh Phu village, Hop Hoa

town, Tam Duong District, Vinh Phuc

Province

327,167 Industrial crop land

29-Dec-09 01-Apr-10 01-Apr-10 29-Dec-12 March 2014

A2/BP5

Rung Nen hill, Thanh Van-Dao Tu

Commune, Tam Duong District, Vinh

Phuc Province

508,467 Industrial crop land

23-Mar-10 01-Apr-10 01-Apr-10 30-Apr-13 March 2014

A2/BP7

Nhon Huc & Go Bep Hill, Tu Yen

Commune, Song Lo District, Vinh Phuc

Province

941,590 Industrial crop land

01-Oct-10 15-Nov-10 15-Nov-10 01-Oct-13 March 2014

A2/BP11

Quan Hill, Phu Ninh Commune, Phu Ninh

District, Phu Tho Province

297,000 Industrial crop land

19-May-10 01-Jun-12 01-Jun-12 19-May-12 March 2014

A2/BPSG1

Rung Nen hill, Thanh Van-Dao Tu

Commune, Tam Duong District, Vinh

Phuc Province

508,467 Industrial crop land

23-Mar-10 19-May-12 19-May-

12 30-Apr-13 March 2014

A2/BPSG5

Dinh Chua Hill, Tien Lu Commune, Lap Thach District, Vinh

Phuc Province

623,837 Industrial crop land

18-Oct-10 09-Jul-12 09-Jul-12 18-Oct-12 March 2014

Page 143: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

135

QUARRIES

Package /Quarry No.

Location Approved Area (m2)

Approved Volume

(m3)

Ownershipa Prior Land

Useb

Approval Operation Schedule

Name Contact

Info Local

AuthoritiesPSC Start

Estimated Completion

Actual Completion

A2/Q1

Quang Son commune, Lap

Thach dist, Vinh Phuc

123,000 2,611,729 Rock-mine 13-Dec-11 08-Apr-10 13-Dec-11 17-Apr-25 March 2014

A2/Q2

Trung Mau commune, Binh Xuyen dist, Vinh

Phuc

640,000 75,187,000 Rock-mine 13-Dec-11 21-Jul-04 13-Dec-11 30-Jun-14 March 2014

SPOILS DISPOSAL AREAS

Package / SD No.

Location Approved

Area (m2)

Approved Capacity

(m3)

Ownershipa Approval Operation

Name Contact Info Local

AuthoritiesPSC

A2/SD1

Fields 99 and 99(1), map No. 21, Cau hamlet, Hoang Dan commune, Tam Duong district, Vinh Phuc province

9,110 m2 30,000 m3 Hoa Hung Co.,Ltd

Hoang Dan commune, Tam

Duong dist, Vinh Phuc

09-Jul-10 12-Jul-10

A2/SD2 Tu Du commune, Lap Thach district, Vinh Phuc province

60,000 m2 60,000 m3 Tu Du

commune

Tu Du CPC, Lap Thach dist,

Vinh Phuc March-10 04-Jun-10

A2/SD3

Dong Go area, map No. 07, Tien Lu commune, Lap Thach district, Vinh Phuc province

2,000 m2 4,000 m3 Tien Lu

commune

Tien Lu CPC, Lap Thach dist,

Vinh Phuc 28-May-10 04-Jun-10

A2/SD4 Dong Ai area, map No. 19, Tien Lu

12,000 m2 24,000 m3 Tien Lu

commune Tien Lu CPC,

Lap Thach dist, 28-May-10 04-Jun-10

Page 144: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

136

SPOILS DISPOSAL AREAS

Package / SD No.

Location Approved

Area (m2)

Approved Capacity

(m3)

Ownershipa Approval Operation

Name Contact Info Local

AuthoritiesPSC

commune, Lap Thach district, Vinh Phuc province

Vinh Phuc

A2/SD5

Field No. 155, map No. 12, Phu Thinh village, Tu Yen commune, Song Lo district, Vinh Phuc province

5,566 m2 11,132 m3 Tu Yen

commune

Tu Yen CPC, Song Lo dist,

Vinh Phuc 11-May-10 20-May-10

A2/SD6

Map No. 38, Khan Tat hill, Dao Tu commune, Tam Duong district, Vinh Phuc province

10,300 m2 10,300 m3 Ly Van Hung

Dao Tu commune, Tam

Duong, Vinh Phuc

25-Mar-10 31-Mar-10

A2/SD7

Field No. 1, map No. 3, Bo U hill, Dao Tu commune, Tam Duong district, Vinh Phuc province

9,400 m2 9,400 m3 Nguyen Anh

Chien

Dao Tu commune, Tam

Duong, Vinh Phuc

25-Mar-10 31-Mar-10

A2/SD8

Field No. 185, Dong Ich commune, Lap Thach district, Vinh Phuc province

30,560 m2 30.560 m3 Dong Ich commune

Dong Ich CPC, Lap Thach dist,

Vinh Phuc 08-Mar-10 17-Mar-10

A2/SD9

Field No. 613, Dong Ich commune, Lap Thach district, Vinh Phuc province

10,345 m2 10,345 m3 Dong Ich commune

Dong Ich CPC, Lap Thach dist,

Vinh Phuc 08-Mar-10 17-Mar-10

A2/SD10

Field No. 78, Gian village, Cao Phong commune, Song Lo district, Vinh

3,268 m2 6,536 m3 Nguyen Van

Luu

Cap Phong commune, Song

Lo dist, Vinh Phuc

20-Mar-10 25-Mar-10

Page 145: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

137

SPOILS DISPOSAL AREAS

Package / SD No.

Location Approved

Area (m2)

Approved Capacity

(m3)

Ownershipa Approval Operation

Name Contact Info Local

AuthoritiesPSC

Phuc province

A2/SD11

Fields No. 337, 475, 481, Dong Hang Phien village, Dong Thinh commune, Song Lo district, Vinh Phuc province

13,863 m2 100,000 m3 Dong Thinh commune

Dong Thich CPC, Dong

Thinh commune, Song

Lo dist, Vinh Phuc

Mar-10 18-Mar-10

A2/SD12

Long Son village, Dao Tu commune, Tam Duong district, Vinh Phuc province

2,250 m2 5,500 m3 Lai Xuan Diem

Long Son village, Dao Tu commune, Tam Duong district,

Vinh Phuc province

07-Mar-13 30-May-13

BATCHING PLANTS

Package/ CBP No.

Location Appropriate

settling pond

Noise and dust

measures

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Local

AuthoritiesPSC Start Est. End

Actual End

A2/CBP1 Km 39+118 Yes Yes Vinh Sinh Co.,Ltd

160 – Dinh Dong – Le Chan dist, Hai Phong

City

Agricultural land

Unidentified 17-Nov-10 17-Nov-10 March 2014

A2/CBP2 Lo River Bridge Yes Yes POSCO

POSCO E&C – Noi Bai – Lao Cai Highway project – Huu

thu village, Kim Long commune,

Tam Duong dist, Vinh Phuc

Agricultural land

05-May-08 15-Jun-11 15-Jun-11 March 2014

Page 146: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

138

BATCHING PLANTS

Package/ CBP No.

Location Appropriate

settling pond

Noise and dust

measures

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Local

AuthoritiesPSC Start Est. End

Actual End

A2/CBP3 Lo River Bridge Yes Yes POSCO

POSCO E&C – Noi Bai – Lao Cai Highway project – Huu

thu village, Kim Long commune,

Tam Duong dist, Vinh Phuc

Wild land 05-May-08 25-Jun-11 25-Jun-11 March 2014

Package A3

BORROW PITS

Package / Borrow Pit No.

Location

Approved

Area (m2)

Approved

Volume (m3)

Ownershipa Prior Land

Useb

Approval Operation Schedule

Name Contact Info Date Agencyc Start Estimated

Completion

Actual Completio

n

1 Km 52+500 (Section 1) 90,000m3

/ 1 year TGT Group Hill land

Phu Tho Province

02-Jul-12

30-Aug-13 Not yet

2 Km 53+700 (Section 1) 90,000m3

/ 1 year TGT Group Hill land

Phu Tho Province

02-Jul-12

30-Aug-13 Not yet

3 Km 54+000 (Section 1) 90,000m3

/ 1 year TGT Group Hill land

Phu Tho Province

02-Jul-12

30-Aug-13 Not yet

4 Km 54 + 000 (Section 3)

328,295 Long Vuong Hill land Phu Tho Province

15-Aug-11

14-Jun-13 Not yet

5 Km 76 +400 (Section 6) 264,527 VINASHIN Hill land Phu Tho Province

10-Feb-12

31-Aug-13 Not yet

Page 147: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

139

BORROW PITS

Package / Borrow Pit No.

Location

Approved

Area (m2)

Approved

Volume (m3)

Ownershipa Prior Land

Useb

Approval Operation Schedule

Name Contact Info Date Agencyc Start Estimated

Completion

Actual Completio

n

6 Km 81 +000 (Section 7) 805,000 Posco E&C Hill land Phu Tho Province

Not yet

QUARRIES

Package / Quarry No.

Location ApprovedArea (m2)

Approved

Volume (m3)

Ownershipa Prior Land

Useb

Approval Operation Schedule

Name Contact Info Date Agencyc Start Estimated

Completion Actual

Completion

1 Phu Man comm.

Quoc Oai dist. Ha Noi Capital

Sunway-

Hataco JSC

2 Phu Man comm.

Quoc Oai dist. Ha Noi Capital

Vimeco

JSC 1-Oct-13 30-Jan-14

3 Ngoc Lap comm. Yen

Lap dist. Phu Tho pro.

Phu Tho forest & mineral product

JSC

4 Phuc Ung comm. Son duong dist.,

Tuyen Quang pro.

Tuyen Quang forest & mineral product

JSC

23-Nov-

12 31-Mar-13

5 Huong Can comm.

Thanh Son dist., Phu Tho pro.

ThanhCong limited Co.,

16-Jan-

13 20-Nov-13

6 Thuong Am comm.,

Son Duong dist. Tuyen Quang pro.

Duy Thinh

Co.,

Page 148: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

140

QUARRIES

Package / Quarry No.

Location ApprovedArea (m2)

Approved

Volume (m3)

Ownershipa Prior Land

Useb

Approval Operation Schedule

Name Contact Info Date Agencyc Start Estimated

Completion Actual

Completion

7 Nhu Khe comm.

Thanh Liem dist., Ha Nam pro.

Thang Loi

cooperative

8 Dan Ha comm., Ky Son dist., Hoa Binh

pro. N/A

9 Doi Can comm. Yen

Son dist. Tuyen Quang pro.

Ha Nam

lime stone Co., - Mrs

10 Ngoc Lap comm. Yen

Lap dist. Phu Tho pro.

Tu Lap Co.,

11 Ngoc Lap comm. Yen

Lap dist. Phu Tho pro.

Truong An

JSC 6-Feb-13 10-Nov-13

12 Quang Son comm.

Lap Thach dist. Vinh Phuc pro.

Hung Vi

Co.,

13 Cao Duong comm.

Luong Son dist. Hoa Binh pro..

Ngoc Thao

Co., 1-Apr-13 3-Nov-13

14 Cao Duong comm.

Luong Son dist. Hoa Binh pro..

Valine Co.,

(Hung Long)

SPOILS DISPOSAL AREAS

Package SD No.

Location

Approved

Area (m2)

Approved

Capacity

(m3)

Ownershipa

Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

1 Km53+360 3,200 14,400 Nguyen van 3-Jun-10 The

Page 149: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

141

QUARRIES

Package / Quarry No.

Location ApprovedArea (m2)

Approved

Volume (m3)

Ownershipa Prior Land

Useb

Approval Operation Schedule

Name Contact Info Date Agencyc Start Estimated

Completion Actual

Completion

Hoa, Nguyen Van

Chung

Consultant

2 Km49+500 2,350 46,000 Le Van Ngu Rice field & Vegetable

field

16-Feb-11

The Consultant

3 Km49+600 1,954 37,000 Nguyen

Tien Dung

Rice field & Vegetable

field

16-Feb-11

The Consultant

4 Km50+900 2,146 29,000 Le Dinh

Chat

Rice field & Vegetable

field

16-Feb-11

The Consultant

5 Km51+400 1,940 35,000 Nguyen Thi

Ly

Rice field & Vegetable

field

16-Feb-11

The Consultant

6 Km52+800 5,690 34,000 Nguyen Thi

Tuat

Rice field & Vegetable

field

16-Feb-11

The Consultant

7 Area No. 8 - Hung Lo 53,489 500,000

Nguyen Xuan

Thuong, Nguyen Van Sang, Cao Van Chinh, Cao Van

Duong, Cao Van Minh

22-Mar-

11 The

Consultant

8 Km52+740 4,114 30,000 Nguyen

Xuan Hai

Area No.2 - Phu Ninh Commune

24-Apr-13The

Consultant

9 Km52+840 6,021 60,000 Nguyen Van

The

Area No.2 - Phu Ninh Commune

24-Apr-13The

Consultant

Page 150: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

142

QUARRIES

Package / Quarry No.

Location ApprovedArea (m2)

Approved

Volume (m3)

Ownershipa Prior Land

Useb

Approval Operation Schedule

Name Contact Info Date Agencyc Start Estimated

Completion Actual

Completion

10 Km54+020 6,084 50,000 Nguyen Van

Bay

Area No.5 - Phu Ninh Commune

11 Hop Quan - Phu Ninh Commune

21,000 378,000 Phu Ninh Commune

Area No. 10 near Nha Xe

hill 13-Oct-10

The Consultant

12 Tien Kien Commune 15,724 283,032 Nguyen

Cong Chuc

Area No. 8 &No.9

4-Nov-11 The

Consultant

13 Km56+100 - Phu Ninh Commune

5,070 40,000 Nguyen Truong Giang

Area No.10 -

Phu Ninh Commune

22-Apr-11The

Consultant

14 Km55+900 - Phu Ninh Commune

2,880 15,500 Nguyen Van

Tai

Area No.10 - Phu Ninh Commune

24-Apr-13The

Consultant

15 Ram A1-2 Km00+100 - Phu Ninh Commune

5,736 50,000 Nguyen Van

Chi

Area No.8 - Phu Ninh Commune

24-Apr-13The

Consultant

16 Ram A1-2 Km00+200 - Phu Ninh Commune

4,072 35,000 Nguyen Thi

Nhuan

Area No.4 - Phu Ninh Commune

24-Apr-13The

Consultant

17 Km53+800 - Phu Ninh Commune

8,172 70,000 Phu Ninh Commune

Area No.7 - Phu Ninh Commune

24-Apr-13The

Consultant

18 Km56+300 - Phu Ninh Commune

6,163 50,000 Phu Ninh Commune

Area No.10 -

Phu Ninh Commune

24-Apr-13The

Consultant

19 Phu Ho Commune 25,000 150,000 Nguyen Van

Thai

Area No.5 - Phu Ho

Commune

25-Feb-11

The Consultant

20 Van Lung Commune 11,508 69,500 Van Lung Commune

Dui forest 13-Oct-10The

Consultant

21 Vo Lao Commune 12,850 89,950 Dinh Tien

Minh

06-Sep-10

The Consultant

Page 151: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

143

QUARRIES

Package / Quarry No.

Location ApprovedArea (m2)

Approved

Volume (m3)

Ownershipa Prior Land

Useb

Approval Operation Schedule

Name Contact Info Date Agencyc Start Estimated

Completion Actual

Completion

22 Chi Tien & Hoang Cuong Commune

15,170 106,190 Tran Quy

Cuong 19-Oct-10

The Consultant

23 Yen Lap Commune 4,517 90,340

Truong Xuan

Company.,LTD

27-Jul-12 The

Consultant

BATCHING PLANTS

Package / SD No.

Location Appropriate settling

pond

Noise and dust measure

s

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual

End

1 Section 2 – Concrete batching plant D

Yes Yes HEUNG WOO

VINA CO., LTD

10-Aug-

10 31-Dec-13

2 Section 7 – Concrete batching plan t

Yes Yes Evernew 8-Dec-12 30-Jul-13

3 IC No.10 bridge - Concrete batching plant

Yes Yes

Duong Chau Construction and Trading

company

10-Jan-

13 9-Jul-13

4 Phu Ninh – Phu Tho Yes Yes Song Lo

construction &tradinG, JSC

14-Sep-

11 31-Dec-13

5 Section 3 – Asphalt concrete batching plant

N/A Yes SEAHAN 31-Dec-

12 3-May-13

6 Section 7 – Asphalt concrete batching plant

N/A Yes Cienco 116 12-Jul-13

Page 152: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

144

Package A4

BORROW PITSPackage /Borrow Pit No.

Location Approved

Area (m2)

Approved

Volume (m3)

Ownershipa Prior Land Useb

Approval Operation Schedule

Name Contact Info Date Agencyc Start Estimated Completio

n

Actual Completio

n A4/BP1 Hill Thờ, zone 10,

Xuan Ang commune, Ha Hoa district, Phu Tho province.

39,000 473,277.7

Xuan Ang Commune

Mr Tuan. Xuan Ang President

Artificial forest land, farm land…

27 June 2012

Phu Tho Provincial People’s Committee

27 June 2012

4th Quarter 2013

A4/BP2 Hill Sặt, zone 1, Quan Khe commune, Ha Hoa district, Phu Tho province.

34,000 93,180 Quan Khe Commune

Mr Tuoc. Quan Khe president

Artificial forest land, farm land…

26 June 2012

Phu Tho Provincial People’s Committee

26 June 2012

4th Quarter 2013

A4/BP3 Hill Bóng Đa, zone 3, Quan Khe commune, Ha Hoa district, Phu Tho province.

36,000 193,909 Quan Khe Commune

Mr Tuoc. Quan Khe president

Artificial forest land, farm land…

26 June 2012

Phu Tho Provincial People’s Committee

26 June 2012

4th Quarter 2013

A4/BP4 Quyet Tien commune, Ha Hoa district, Phu Tho province.

45,400 292,012 Hien Luong Commune

Mr Nguyen. Hien Luong president.

Artificial forest land, farm land…

26 June 2012

Phu Tho Provincial People’s Committee

26 June 2012

4th Quarter 2013

A4/BP5 Hill Lau, zone 5, Vo Tranh commune, Ha Hoa district, Phu Tho province.

16,800 156,423 Vo Tranh Commune

Mr Thinh. Vo Tranh President

Artificial forest land, farm land…

23 Apr 2012

Phu Tho Provincial People’s Committee

23 Apr 2012

4th Quarter 2013

A4/BP6 Hill Trường, zone 1, Hien Luong commune, Ha Hoa district, Phu Tho province.

55,000 864,270 Hien Luong Commune

Mr Nguyen. Hien Luong president.

Artificial forest land, farm land…

23 Apr 2012

Phu Tho Provincial People’s Committee

23 Apr 2012

4th Quarter 2013

A4/BP7 Km80+000-Km82+500

118.500 805.098 Thanh Nga

Thanh Nga commune, Cam

Hill land of forestry tree

24 Aug 2012

Phu Tho Provincial

Aug 2012

Aug 2014

Page 153: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

145

Hills of Ong Duoc, Nuong Phe, Nuong Dieu, Nuong Son, Nha Vam Go Ca

commune, Cam Khe, district.

Khe, district, Phu Tho province

People’s Committee

A4/BP8 Hill Reo, Dong Cam commune, Cam Khe district

239.443 Dong Cam commune, Cam Khe, district.

Dong Cam commune, Cam Khe, district.

Artificial forest land, farm land…

02 Oct 2012

Phu Tho Provincial People’s Committee

02 Oct 2012

02 Oct 2014

A4/BP9 Hill Gieng Chuoi, Tuy Loc commune, Cam Khe district

1.600 195.872 Tuy Loc commune, Cam Khe, district.

Tuy Loc commune, Cam Khe, district.

Artificial forest land, farm land…

02 Oct 2012

Phu Tho Provincial People’s Committee

02 Oct 2012

02 Oct 2014

A4/BP10

Hill Gia Gia and Hill Nuong Trong Phung Xa commune, Cam Khe district

2.500 99.000 Phung Xa commune, Cam Khe, district.

Phung Xa commune, Cam Khe, district.

Artificial forest land, farm land…

05 Oct 2012

Phu Tho Provincial People’s Committee

02 Oct 2012

05 Oct 2014

QUARRIESPackage /Quarry No.

Location Approved

Area (m2)

Approved

Volume (m3)

Ownershipa Prior Land Useb

Approval Operation Schedule

Name Contact Info Date Agencyc Start Estimated Completio

n

Actual Completio

n Not Applicable

SPOILS DISPOSAL AREAS Package / SD No.

Location Approved

Area (m2)

Approved

Capacity (m3)

Ownershipa Prior Land Useb Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

Xa Minh Coi, Ha Hoa 1 Km 90+080 1266.2 16400 Nguyen Thi

Rang Zone 7, Minh Coi Communce, Ha

Low elevation, flood area, can not

20 Oct. 2010

Minh Coi Communce

20 Oct. 2010

4th Quarter 2013

4th Quarter 2013

Page 154: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

146

Hoa cultivation 2 Km 90+220 111.02 2500 Bui Van Nhu Zone 7, Minh Coi

Communce, Ha Hoa

Low elevation, flood area, can not cultivation

20 Oct. 2010

Minh Coi Communce

20 Oct. 2010

4th Quarter 2013

4th Quarter 2013

3 Km 90+220 637.6 12250 Nguyen Y Nguyen

Zone 7, Minh Coi Communce, Ha Hoa

Low elevation, flood area, can not cultivation

20 Oct. 2010

Minh Coi Communce

20 Oct. 2010

4th Quarter 2013

4th Quarter 2013

4 Km 90+280 453.6 8200 Nguyen Viet Hung

Zone 7, Minh Coi Communce, Ha Hoa

Low elevation, flood area, can not cultivation

20 Oct. 2010

Minh Coi Communce

20 Oct. 2010

4th Quarter 2013

4th Quarter 2013

5 Km 91+200 172.8 12000 Le Quang Thang Zone 5, Minh Coi Communce, Ha Hoa

Low elevation, flood area, can not cultivation

20 Oct. 2010

Minh Coi Communce

20 Oct. 2010

4th Quarter 2013

4th Quarter 2013

6 Km 92+000 850 16369 Phung Thi Khoa Zone 5, Minh Coi Communce, Ha Hoa

Low elevation, flood area, can not cultivation

20 Oct. 2010

Minh Coi Communce

20 Oct. 2010

4th Quarter 2013

4th Quarter 2013

7 Km 92+100 702.1 11200 Nguyen Van Giao

Zone 1, Minh Coi Communce, Ha Hoa

Low elevation, flood area, can not cultivation

20 Oct. 2010

Minh Coi Communce

20 Oct. 2010

4th Quarter 2013

4th Quarter 2013

8 Km 92+510 504.2 6000 Nguyen Van Cuong

Zone 2, Minh Coi Communce, Ha Hoa

Low elevation, flood area, can not cultivation

20 Oct. 2010

Minh Coi Communce

20 Oct. 2010

4th Quarter 2013

4th Quarter 2013

9 Km 92+600 522.2 6500 Nguyen Van Cuong

Zone 2, Minh Coi Communce, Ha Hoa

Low elevation, flood area, can not cultivation

20 Oct. 2010

Minh Coi Communce

20 Oct. 2010

4th Quarter 2013

4th Quarter 2013

10 Km 92+850 822.73 14300 Do Thi Nu Zone 2, Minh Coi Communce, Ha Hoa

Low elevation, flood area, can not cultivation

20 Oct. 2010

Minh Coi Communce

20 Oct. 2010

4th Quarter 2013

4th Quarter 2013

11 Km 93+050 376.2 6100 Nguyen Van Thoa

Zone 2, Minh Coi Communce, Ha Hoa

Low elevation, flood area, can not cultivation

20 Oct. 2010

Minh Coi Communce

20 Oct. 2010

4th Quarter 2013

4th Quarter 2013

12 Km 93+160 687.6 13400 Nguyen Van Thoa

Zone 2, Minh Coi Communce, Ha Hoa

Low elevation, flood area, can not cultivation

20 Oct. 2010

Minh Coi Communce

20 Oct. 2010

4th Quarter 2013

4th Quarter 2013

13 Km 93+100 326.3 5800 Le Thi Loan Zone 2, Minh Coi Communce, Ha Hoa

Fish pond, but not efficient

20 Oct. 2010

Minh Coi Communce

20 Oct. 2010

4th Quarter 2013

4th Quarter 2013

14 Km 93+600 1354.8 18200 Ly Minh Tam Zone 2, Minh Coi Low elevation, 20 Oct. Minh Coi 20 Oct. 4th Quarter 4th Quarter

Page 155: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

147

Communce, Ha Hoa

flood area, can not cultivation

2010 Communce 2010 2013 2013

15 Km 93+700 650 5350 Nguyen Ba Ngoc

Zone 2, Minh Coi Communce, Ha Hoa

Low elevation, flood area, can not cultivation

20 Oct. 2010

Minh Coi Communce

20 Oct. 2010

4th Quarter 2013

4th Quarter 2013

16 Km 93+820 3880 85360 Nguyen Thanh Binh

Zone 2, Minh Coi Communce, Ha Hoa

Steep slope, unable to make farming

05 Oct. 2013

Ha Hoa District

05 Oct. 2013

18th June 2013

17 Km 92+300 900 15300 Nguyen Van Tai Zone 2, Minh Coi Communce, Ha Hoa

Not suitable for farming.

05 Oct. 2013

Ha Hoa District

18 June. 2013

27 June. 2013

18 Km 91+240 2718.7 46218 Minh Coi Commune

Minh Coi Commune

Valley, slopes areas

05 Oct. 2013

Ha Hoa District

18 June. 2013

30 August. 2013

Xa Bang Gia, Ha Hoa 1 Bai ui 3600 28800 Bang Gia

Communce Mr. Thinh Chairman of Bang Gia Communce

Fish pond 12 Dec. 2010

Bang Gia Communce

12 Dec. 2010

4th Quarter 2013

2 Zone 11 3800 11400 Nguyen Van Quan

Zone 11, Bang Gia Communce

Fish pond 19 Nov. 2010

Bang Gia Communce

19 Nov. 2010

4th Quarter 2013

Xa Vo Tranh, Ha Hoa 1 Cap Tien,

Zone 6, Vo Tranh

1200 3600 Tran Thien Le Zone 6, Cap Tien, Vo Tranh Communce

Fish pond 10 January, 2011

Vo Tranh Communce

10 January, 2011

1st Quarter 2014

2 Dong Mai, Zone 5

1500 6000 Vo Tranh Communce

Zone 5, Vo Tranh Communce

Fish pond 10 January, 2011

Vo Tranh Communce

10 January, 2011

4th Quarter 2013

Xa Hien Luong, Ha Hoa 1 Cutural

house 1620 3240 Mr Nguyen,

Chairman of Hien Luong Communce

Hien Luong Communce

Low elevation, flood area need to raise level

17 Dec. 2010

Hien Luong Communce

17 Dec. 2010

4th Quarter 2013

4th Quarter 2013

2 Zone 2 1200 1800 Mr Nguyen, Chairman of Hien Luong Communce

Hien Luong Communce

Low elevation, flood area need to raise level

17 Dec. 2010

Hien Luong Communce

17 Dec. 2010

4th Quarter 2013

4th Quarter 2013

3 Pond of 1200 2400 Mrs Hoan Zone 2, Hien Fish pond 17 Dec. Hien Luong 17 Dec. 4th Quarter 4th Quarter

Page 156: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

148

Mrs Hoan, Zone 2

Luong Communce 2010 Communce 2010 2013 2013

4 Old brick production area

4000 6000 Dong Trua Au Co Cooperative

Excavated area for brick production needs to be recovered

17 Dec. 2010

Hien Luong Communce

17 Dec. 2010

4th Quarter 2013

4th Quarter 2013

Xa Quan Khe, Ha Hoa

1 Fish pond of Mr. Cuong’s house

690 1244 Nguyen Van Cuong

Zone 1, Quan Khe Communce, Ha Hoa

Fish pond, but not efficient

7 Oct. 2010

Quan Khe Communce

7 Oct. 2010

4th Quarter 2013

4th Quarter 2013

2 Fish pond of Mrs. Oanh’s house, Zone 1

900 2160 Do Thi Oanh Zone 1, Quan Khe Communce, Ha Hoa

Fish pond, but not efficient

7 Oct. 2010

Quan Khe Communce

7 Oct. 2010

4th Quarter 2013

4th Quarter 2013

3 Fish pond of Mr. Chau’s house

624 1560 Do Ngoc Chau Zone 3, Quan Khe Communce, Ha Hoa

Fish pond, but not efficient

7 Oct. 2010

Quan Khe Communce

7 Oct. 2010

4th Quarter 2013

4th Quarter 2013

4 Pond, Zone 1

5788 36000 Mr Doanh, Chairman of Quan Khe Communce

Quan Khe Communce

Fish pond, but not efficient

7 Oct. 2010

Quan Khe Communce

7 Oct. 2010

4th Quarter 2013

4th Quarter 2013

5 Dyke, Zone 1

400 23152 Mr Doanh, Chairman of Quan Khe Communce

Quan Khe Communce

Low elevation, flood area, can not cultivation

7 Oct. 2010

Quan Khe Communce

7 Oct. 2010

4th Quarter 2013

4th Quarter 2013

Xa Son Nga, huyen Cam Khe 1 Km 81+020 800 8000 Nguyen Van

Yen Zone 3, Son Nga Communce

Low elevation, need to raise level for cultivation

29 Dec. 2010

Son Nga Communce

29 Dec. 2010

4th Quarter 2013

4th Quarter 2013

2 Km 81+020 400 2400 Nguyen Minh Duc

Zone 3, Son Nga Communce

Low elevation, need to raise level for cultivation

29 Dec. 2010

Son Nga Communce

29 Dec. 2010

4th Quarter 2013

4th Quarter 2013

3 Km 81+080 240 960 Hoangf Van Ba Zone 3, Son Nga Low elevation, 29 Dec. Son Nga 29 Dec. 4th Quarter 4th Quarter

Page 157: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

149

Communce need to raise level for cultivation

2010 Communce 2010 2013 2013

4 Km 80+800 2000 20000 Hoa Mai Company

Son Nga Communce

Backfill for brick production area

29 Dec. 2010

Son Nga Communce

29 Dec. 2010

4th Quarter 2013

4th Quarter 2013

Xa Phung Xa, huyen Cam Khe

1 Km 82+080 300 600 Nguyen Thi Thung

Zone 2, Phung Xa Communce

Pond, and low area, need to

28 Dec. 2010

Phung Xa Communce

28 Dec. 2010

4th Quarter 2013

4th Quarter 2013

2 Km 82+100 2200 8800 M. Toa, Vice Chairman of Phung Xa Communce

Phung Xa Communce

Fill for stadium of the communce

28 Dec. 2010

Phung Xa Communce

28 Dec. 2010

4th Quarter 2013

4th Quarter 2013

Xa Tuy Loc, huyen Cam Khe

1 Km 85+500 2,424 9,396 Nguyen Van Hong

Zone 4, Du Ba Village, Tuy Loc commune, Cam Khe district

Pond 19 Dec. 2012

Tuy Loc Communce

1 Nov 2012

5 Feb 2013

2 Km 85+600 404

1,568 Nguyen Van Hong

Zone 4, Du Ba Village, Tuy Loc commune, Cam Khe district

Houses’s garden 19 Dec. 2012

Tuy Loc Communce

20 Dec 2012

5 Feb 2013

3 Km 85+550 1934

7500 Nguyen Van Hong

Zone 4, Du Ba Village, Tuy Loc commune, Cam Khe district

Pond 19 Dec. 2012

Tuy Loc Communce

20 Dec 2012

5 Feb 2013

4 Km 85+480 3112

12064 Nguyen Van Hong

Zone 4, Du Ba Village, Tuy Loc commune, Cam Khe district

Pond 19 Dec. 2012

Tuy Loc Communce

1 Nov 2012

5 Feb 2013

5 Km 85+460 851

3300 Nguyen Van Hong

Zone 4, Du Ba Village, Tuy Loc commune, Cam Khe district

Houses’s garden 19 Dec. 2012

Tuy Loc Communce

20 Dec 2012

5 Feb 2013

Xa Tuy Loc, huyen Cam Khe

1 Km80+000-Km82+500

4.517 100.000 Truong Xuan Co., Ltd.

Yen Lap commune, Cam

Emty land for storing of brick.

12/04/2013

Cam Khe district

April 2013

Dec 2013 Dec 2013

Page 158: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

150

Khe district, Phu Tho province

BATCHING PLANTS

Package / SD No.

Location Appropriatesettling pond

Noise and dust measure

s

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

A4/CBP1

Ha Hoa Bridge Yes Yes Bang Gia Communce

Mr. Long Chairman of Bang Gia Communce

Pending 1 Jan. 2012

Bang Gia Communce

1 Jan. 2012

1 Jan. 2016

A4/CBP2

Zone 4, Minh Coi commune, Ha Hoa district

Yes Yes Ho Van Thai 01696.643.932 farm land 14 Dec 2012

Minh Coi commune certified

1st Quarter 2012

4th Quarter 2013

4th Quarter 2013

Nguyen Tien Loi

01686.352.890 farm land 14 Dec 2012

Minh Coi commune certified

1st Quarter 2012

4th Quarter 2013

4th Quarter 2013

Nguyen Tuan Hong

0975.247.493 farm land 14 Dec 2012

Minh Coi commune certified

1st Quarter 2012

4th Quarter 2013

4th Quarter 2013

Nguyen Xuan Liem

01689.338.258 farm land 14 Dec 2012

Minh Coi commune certified

1st Quarter 2012

4th Quarter 2013

4th Quarter 2013

Phung Duc Thu

01275.168.096 farm land 14 Dec 2012

Minh Coi commune certified

1st Quarter 2012

4th Quarter 2013

4th Quarter 2013

Tran Van Nhan

0210.6291.937 farm land 14 Dec 2012

Minh Coi commune certified

1st Quarter 2012

4th Quarter 2013

4th Quarter 2013

Nguyen Hong Phuong

01678.814.448 farm land 14 Dec 2012

Minh Coi commune certified

1st Quarter 2012

4th Quarter 2013

4th Quarter 2013

Nguyen Van Sy

01687.147.867 farm land 14 Dec 2012

Minh Coi commune certified

1st Quarter 2012

4th Quarter 2013

4th Quarter 2013

Page 159: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

151

Package A5

BATCHING PLANTS

Package / SD No.

Location Appropriate

settling pond

Noise and dust

measures

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

A5/CBP1 Km 124+000 Yes No Song Hong Concrete JSC

Tran Yen district, Yen Bai province

Side Cut of idled land

31/10/201 Tran Yen GOV

17/9/2011

A5/CBP2 Km 136+000 Yes No Licogi 15 Van Yen

district, Yen Bai province

grass land 31/10/201

1 Van Yen GOV

4/12/2011

A5/CBP3 Km 145+200 Yes No Thanh Thu-Bao Tin

Van Yen district, Yen Bai province

idled grass land

27/6/2011 Van Yen GOV

10/12/2011

A5/CBP dtx KCN Dam Hong Yes No

Dong Tam Xanh Investment and Construction JSC

Van Yen district, Yen Bai province

commercial lot

26/1/2011 Van Yen GOV

30/7/2011

A5/CBP 4 Km145+100 Yes No Trancosin Van Yen

district, Yen Bai province

commercial lot

6/10/2012 Van Yen GOV

12/11/2012

A5/CBP 5 Km122+000 Yes No Licogi 13 Tran Yen

district, Yen Bai province

commercial lot

10/6/2013 Tran Yen GOV

6/5/2013

A5/ACBP1 Km142 Yes No 123 company

Van Yen district, Yen Bai province

Private land 1/10/2013 Van Yen GOV

6/11/2013

A5/ACBP2 Km119 Yes No

Asphalt concrete batching plant Km119

Tran Yen district, Yen Bai province

Private land 11/12/201

3 Tran Yen GOV

14/1/2014

Page 160: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

152

BATCHING PLANTS

Package / SD No.

Location Appropriate

settling pond

Noise and dust

measures

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

A5/ACBP3 Km135+700 Yes No

Asphalt concrete batching plant Km135

Tran Yen district, Yen Bai province

Disposal areas Km135

3/1/2014 Tran Yen GOV

15/2/2014

A5/ACBP4 Km117 No No

Asphalt concrete batching plant Km117

Tran Yen district, Yen Bai province

Service area Km117

10/1/2014 Tran Yen GOV

2/2/2014

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

A5/SD1

Km111+740, Minh Quan commune, Tran Yen district, Yen Bai province

4094 14201 Song Da Co., Ltd

Minh Quan commune, Tran Yen district, Yen

Bai province

Private land

17-Sep-2012 3-Oct-2012 3-Oct-2012

A5/SD2

Km111+680, Minh Quan commune, Tran Yen district, Yen Bai province

16580 59245 Song Da Co., Ltd

Minh Quan commune, Tran Yen district, Yen

Bai province

Private land

17-Sep-2012 3-Oct-2012 3-Oct-2012

A5/SD3

Km113+100, Minh Quan commune, Tran Yen district, Yen Bai province

4427 29358 Song Da Co., Ltd

Minh Quan commune, Tran Yen district, Yen

Bai province

Private land

17-Sep-2012 3-Oct-2012 3-Oct-2012

A5/SD4

Km112+200, Minh Quan commune, Tran Yen district, Yen Bai province

9600 43790 Song Da Co., Ltd

Minh Quan commune, Tran Yen district, Yen

Bai province

Private land

17-Sep-2012 3-Oct-2012 3-Oct-2012

A5/SD5 Km112+600, Bao 19370 60750 Song Da Bao Hung Wild land 17-Sep-2012 3-Oct-2012 3-Oct-2012

Page 161: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

153

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

Hung commune, Tran Yen district, Yen Bai province

Co., Ltd commune, Tran Yen district, Yen

Bai province

A5/SD6

Km116+480, Bao Hung commune, Tran Yen district, Yen Bai province

1940 12731 Song Da Co., Ltd

Bao Hung commune, Tran Yen district, Yen

Bai province

Private land

17-Sep-2012 3-Oct-2012 3-Oct-2012

A5/SD7

Km125+300, Minh Tien commune, Tran Yen district, Yen Bai province

3566 8273 Licogi 15 Co., Ltd

Minh Tien commune, Tran Yen district, Yen

Bai province

Private land

17-Sep-2012 3-Oct-2012 3-Oct-2012

A5/SD8

Km118+755, Bao Hung commune, Tran Yen district, Yen Bai province

560 28528 Licogi 13 Co., Ltd

Bao Hung commune, Tran Yen district, Yen

Bai province

Wild land 9-Oct-2012 27-Oct-2012

27-Oct-2012

A5/SD9

Km119+6800, Hop Minh commune, Tran Yen district, Yen Bai province

1560 43759 Licogi 13 Co., Ltd

Bao Hung commune, Tran Yen district, Yen

Bai province

Wild land 9-Oct-2012 27-Oct-2012

27-Oct-2012

A5/SD10

Km120+180, Hop Minh commune, Tran Yen district, Yen Bai province

64699 Licogi 13 Co., Ltd

Bao Hung commune, Tran Yen district, Yen

Bai province

Wild land 9-Oct-2012 27-Oct-2012

27-Oct-2012

A5/SD11

Km126+620, Y Kan commune, Tran Yen district, Yen Bai province,

4721 Licogi 15 Co. Ltd

Y Kan commune, Tran Yen district, Yen

Bai province,

Private land

17-Sep-2012 15-Oct-2012

15-Oct-2012

A5/SD12

Km126+750, Y Kan commune, Tran Yen district, Yen Bai province

2448 Licogi 15 Co. Ltd

Y Kan commune, Tran Yen district, Yen

Bai province,

Private land

17-Sep-2012 15-Oct-2012

15-Oct-2012

A5/SD13 Km129+300, Y Kan commune, Tran Yen district, Yen Bai

2427 Licogi 15 Co. Ltd

Y Kan commune, Tran Yen district, Yen

Private land

17-Sep-2012 15-Oct-2012

15-Oct-2012

Page 162: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

154

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

province Bai province,

A5/SD14

Km130+620, Y Kan commune, Tran Yen district, Yen Bai province

2238 11700 Licogi 15 Co. Ltd

Y Kan commune, Tran Yen district, Yen

Bai province,

Private land

17-Sep-2012 15-Oct-2012

15-Oct-2012

A5/SD15

Km131+840, Quy Mong commune, Tran Yen district, Yen Bai province

2158 28167 Licogi 15 Co. Ltd

Quy Mong commune, Tran Yen district, Yen

Bai province

Private land

17-Sep-2012 24-Oct-2012

24-Oct-2012

A5/SD16

Km132+440, Quy Mong commune, Tran Yen district, Yen Bai province

2465 19720 Licogi 15 Co. Ltd

Quy Mong commune, Tran Yen district, Yen

Bai province

Private land

17-Sep-2012 2-Nov-2012

2-Nov-2012

A5/SD17

Km133+680, Quy Mong commune, Tran Yen district, Yen Bai province

1875 18750 Licogi 15 Co. Ltd

Quy Mong commune, Tran Yen district, Yen

Bai province

Private land

17-Sep-2012 2-Nov-2012

2-Nov-2012

A5/SD18

Km136+320, Quy Mong commune, Tran Yen district, Yen Bai province

2175 32190 Licogi 15 Co. Ltd

Quy Mong commune, Tran Yen district, Yen

Bai province

Wild land 27-Aug-2012 9-Sep-2012

9-Sep-2012

A5/SD19

Km138+000, Hoang Thang commune, Tran Yen district, Yen Bai province

6003 Licogi 15 Co. Ltd

Quy Mong commune, Tran Yen district, Yen

Bai province

Wild land 27-Aug-2012 9-Sep-2012

9-Sep-2012

A5/SD20

Km136+750, Quy Mong commune, Tran Yen district, Yen Bai province

1980 8329 Licogi 15 Co. Ltd

Quy Mong commune, Tran Yen district, Yen

Bai province

Wild land 27-Aug-2012 9-Sep-2012

9-Sep-2012

A5/SD21

Km137+420, Hoang Thang commune, Tran Yen district, Yen Bai province

5437 45891 Licogi 15 Co. Ltd

Hoang Thang commune, Tran Yen district, Yen

Bai province

Private land

27-Aug-2012 9-Sep-2012

9-Sep-2012

A5/SD22 Km137+980, Hoang 1244 5980 Trancosin Hoang Thang Private 27-Aug-2012 9-Sep- 9-Sep-

Page 163: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

155

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

Thang commune, Tran Yen district, Yen Bai province

Co. Ltd commune, Tran Yen district, Yen

Bai province

land 2012 2012

A5/SD23

Km140+140, Xuan Ai commune, Tran Yen district, Yen Bai province

13940 Trancosin

Co. Ltd

Xuan Ai commune, Tran Yen district, Yen

Bai province

Private land

27-Aug-2012 9-Sep-2012

9-Sep-2012

A5/SD24

Km141+160, Xuan Ai commune, Tran Yen district, Yen Bai province

11681 Trancosin

Co. Ltd

Xuan Ai commune, Tran Yen district, Yen

Bai province

Private land

27-Aug-2012 20-Sep-

2012 20-Sep-

2012

A5/SD25

Km141+240, Xuan Ai commune, Tran Yen district, Yen Bai province

3599 Trancosin

Co. Ltd

Xuan Ai commune, Tran Yen district, Yen

Bai province

Private land

27-Aug-2012 20-Sep-

2012 20-Sep-

2012

A5/SD26

Km140+520, Xuan Ai commune, Tran Yen district, Yen Bai province

6015 Trancosin

Co. Ltd

Xuan Ai commune, Tran Yen district, Yen

Bai province

Private land

27-Aug-2012 20-Sep-

2012 20-Sep-

2012

A5/SD27

Km140+860, Xuan Ai commune, Tran Yen district, Yen Bai province

15826 Trancosin

Co. Ltd

Xuan Ai commune, Tran Yen district, Yen

Bai province

Private land

27-Aug-2012 20-Sep-

2012 20-Sep-

2012

A5/SD28

Km145+000, Yen Hop Commune, Van Yen district, Yen Bai province

4500 26286 Trancosin

Co. Ltd

Yen Hop Commune, Van

Yen district, Yen Bai province

Private land

27-Aug-2012 20-Sep-

2012 20-Sep-

2012

A5/SD29

Km146+250, Yen Hop Commune, Van Yen district, Yen Bai province

3500 11584 Trancosin

Co. Ltd

Yen Hop Commune, Van

Yen district, Yen Bai province

Private land

27-Aug-2012 20-Sep-

2012 20-Sep-

2012

A5/SD30 Km146+720, Yen 1734 6937 Trancosin Yen Hop Private 27-Aug-2012 17-Sep- 17-Sep-

Page 164: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

156

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

Hop Commune, Van Yen district, Yen Bai province

Co. Ltd Commune, Van Yen district,

Yen Bai province

land 2012 2012

A5/SD31

Km147+200, Yen Hop Commune, Van Yen district, Yen Bai province

1488 11583 Trancosin

Co. Ltd

Yen Hop Commune, Van

Yen district, Yen Bai province

Private land

27-Aug-2012 17-Sep-

2012 17-Sep-

2012

A5/SD32

Km148+300, Yen Hop commune, Tran Yen district, Yen Bai province

1023 15000 Trancosin

Co. Ltd

Yen Hop commune, Tran Yen district, Yen

Bai province

Private land

27-Aug-2012 17-Sep-

2012 17-Sep-

2012

A5/SD33

Km111+740, Minh Quan commune, Tran Yen district, Yen Bai province

2184 6282 Song Da 9 Co. Ltd

Minh Quan commune, Tran Yen district, Yen

Bai province

Private land

28-Nov-2012 15-Dec-

2012 15-Dec-

2012

A5/SD34

Km111+740, Minh Quan commune, Tran Yen district, Yen Bai province

1280 7919 Song Da 9 Co. Ltd

Minh Quan commune, Tran Yen district, Yen

Bai province

Wild land 28-Nov-2012 15-Dec-

2012 15-Dec-

2012

A5/SD35

Km111+680, Minh Quan commune, Tran Yen district, Yen Bai province

2677 6150 Song Da 9 Co. Ltd

Minh Quan commune, Tran Yen district, Yen

Bai province

Private land

28-Nov-2012 15-Dec-

2012 15-Dec-

2012

A5/SD36

Km111+680, Minh Quan commune, Tran Yen district, Yen Bai province

4603 5000 Song Da 9 Co. Ltd

Minh Quan commune, Tran Yen district, Yen

Bai province

Wild land 28-Nov-2012 15-Dec-

2012 15-Dec-

2012

A5/SD37

Km111+800, Minh Quan commune, Tran Yen district, Yen Bai province

9300 48095 Song Da 9 Co. Ltd

Minh Quan commune, Tran Yen district, Yen

Bai province

Private land

28-Nov-2012 22-Dec-

2012 22-Dec-

2012

A5/SD38 Km110+100, Minh 9600 43790 Song Da Minh Quan Private 28-Nov-2012 22-Dec- 22-Dec-

Page 165: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

157

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

Quan commune, Tran Yen district, Yen Bai province

9 Co. Ltd commune, Tran Yen district, Yen

Bai province

land 2012 2012

A5/SD39

Km110+340, Minh Quan commune, Tran Yen district, Yen Bai province

330 1650 Song Da 9 Co. Ltd

Minh Quan commune, Tran Yen district, Yen

Bai province

Private land

28-Nov-2012 22-Dec-

2012 22-Dec-

2012

A5/SD40

Km110+360, Minh Quan commune, Tran Yen district, Yen Bai province

7070 29100 Song Da 9 Co. Ltd

Minh Quan commune, Tran Yen district, Yen

Bai province

Private land

28-Nov-2012 22-Dec-

2012 22-Dec-

2012

A5/SD41

Km111+670, Minh Quan commune, Tran Yen district, Yen Bai province

12000 30000 Song Da 9 Co. Ltd

Minh Quan commune, Tran Yen district, Yen

Bai province

Private land

28-Nov-2012 22-Dec-

2012 22-Dec-

2012

A5/SD42

Km148+300, Yen Hop Commune, Van Yen district, Yen Bai province

150000 Trancosin

Co. Ltd

Yen Hop Commune, Van

Yen district, Yen Bai province

Private land

17-Dec-2012 15-Jan-

2013 15-Jan-

2013

A5/SD43

Km146+250, Yen Hop Commune, Van Yen district, Yen Bai province

11584 Trancosin

Co. Ltd

Yen Hop Commune, Van

Yen district, Yen Bai province

Private land

17-Dec-2012 15-Jan-

2013 15-Jan-

2013

A5/SD44

Km145+000, Yen Hop Commune, Van Yen district, Yen Bai province

26286 Trancosin

Co. Ltd

Yen Hop Commune, Van

Yen district, Yen Bai province

Private land

17-Dec-2012 15-Jan-

2013 15-Jan-

2013

A5/SD45

Km126+900, Y Kan commune, Tran Yen district, Yen Bai province

16084 Trancosin

Co. Ltd

Y Kan commune, Tran Yen district, Yen

Bai province

Private land

17-Dec-2012 15-Jan-

2013 15-Jan-

2013

Page 166: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

158

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

A5/SD46

Km127+000, Y Kan commune, Tran Yen district, Yen Bai province

4224

Keangnam

Contractor

Y Kan commune, Tran Yen district, Yen

Bai province

Wild land 4-Feb-2013 28-Mar-

2013 28-Mar-

2013

A5/SD47

Km127+000, Y Kan commune, Tran Yen district, Yen Bai province

5779

Keangnam

Contractor

Y Kan commune, Tran Yen district, Yen

Bai province

Wild land 4-Feb-2013 28-Mar-

2013 28-Mar-

2013

A5/SD48

Km120+200, Hop Minh commune, Tran Yen district, Yen Bai province

7067

Keangnam

Contractor

Hop Minh commune, Tran Yen district, Yen

Bai province

Private land

4-Feb-2013 28-Mar-

2013 28-Mar-

2013

A5/SD49

Km122+100, Hop Minh commune, Tran Yen district, Yen Bai province

37515 Hoang An

Co. Ltd

Hop Minh commune, Tran Yen district, Yen

Bai province

Wild land 4-Feb-2013 28-Mar-

2013 28-Mar-

2013

A5/SD50

Km128+800, Y Kan commune, Tran Yen district, Yen Bai province

2558 Hoang An

Co. Ltd

Y Kan commune, Tran Yen district, Yen

Bai province

Private land

17-Sep-2012 3-Nov-2012

3-Nov-2012

A5/SD51

Km129+590, Y Kan commune, Tran Yen district, Yen Bai province

2784 Hoang An

Co. Ltd

Y Kan commune, Tran Yen district, Yen

Bai province

Private land

17-Sep-2012 3-Nov-2012

3-Nov-2012

A5/SD52

Km126+000, Y Kan commune, Tran Yen district, Yen Bai province

392

Keangnam

Contractor

Y Kan commune, Tran Yen district, Yen

Bai province

Private land

5-Feb-2013 29-Mar-

2013 29-Mar-

2013

A5/SD53

Km125+950, Y Kan commune, Tran Yen district, Yen Bai province

880

Keangnam

Contractor

Y Kan commune, Tran Yen district, Yen

Bai province

Private land

5-Feb-2013 26-Feb-

2013 26-Feb-

2013

A5/SD54 Km125+600, Y Kan commune, Tran Yen

2919 Keangna

m Y Kan

commune, Tran Private

land 5-Feb-2013

26-Feb-2013

26-Feb-2013

Page 167: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

159

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

district, Yen Bai province

Contractor

Yen district, Yen Bai province

A5/SD55

Km125+500, Y Kan commune, Tran Yen district, Yen Bai province

987

Keangnam

Contractor

Y Kan commune, Tran Yen district, Yen

Bai province

Private land

5-Feb-2013 26-Feb-

2013 26-Feb-

2013

A5/SD56

Km125+780. Y Kan commune, Tran Yen district, Yen Bai province

2095

Keangnam

Contractor

Y Kan commune, Tran Yen district, Yen

Bai province

Private land

5-Feb-2013 26-Feb-

2013 26-Feb-

2013

A5/SD57

Km125+700, Y Kan commune, Tran Yen district, Yen Bai province

378

Keangnam

Contractor

Y Kan commune, Tran Yen district, Yen

Bai province

Private land

5-Feb-2013 26-Feb-

2013 26-Feb-

2013

A5/SD58

Km125+700, Y Kan commune, Tran Yen district, Yen Bai province

622

Keangnam

Contractor

Y Kan commune, Tran Yen district, Yen

Bai province

Private land

5-Feb-2013 26-Feb-

2013 26-Feb-

2013

A5/SD59

Km145+500, Yen Hop Commune, Van Yen district, Yen Bai province

809 2000 Song Da 9 Co. Ltd

Yen Hop Commune, Van

Yen district, Yen Bai province

Private land

18-Apr-2013 5-May-2013

5-May-2013

A5/SD60

Km147+680, Yen Hop Commune, Van Yen district, Yen Bai province

2000 6000 Trancosin

Co. Ltd

Yen Hop Commune, Van

Yen district, Yen Bai province

Private land

18-Apr-2013 5-May-2013

5-May-2013

A5/SD61

Km148+200, Yen Hop Commune, Van Yen district, Yen Bai province

20000 106000 Trancosin

Co. Ltd

Yen Hop Commune, Van

Yen district, Yen Bai province

Wild land 18-Apr-2013 5-May-2013

5-May-2013

A5/SD62 Km149+030, Yen 1800 4000 Trancosin Yen Hop Private 18-Apr-2013 5-May- 5-May-

Page 168: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

160

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

Hop Commune, Van Yen district, Yen Bai province

Co. Ltd Commune, Van Yen district,

Yen Bai province

land 2013 2013

A5/SD63

Km146+700, Yen Hop Commune, Van Yen district, Yen Bai province

1992 50000 Trancosin

Co. Ltd

Yen Hop Commune, Van

Yen district, Yen Bai province

Wild land 2-Nov-2013 18-Dec-

2013 18-Dec-

2013

A5/SD64

Km148+000, Yen Hop Commune, Van Yen district, Yen Bai province

2650 105000 Trancosin

Co. Ltd

Yen Hop Commune, Van

Yen district, Yen Bai province

Private land

2-Nov-2013 18-Dec-

2013 18-Dec-

2013

A5/SD65

Km148+500, Yen Hop Commune, Van Yen district, Yen Bai province

2929 45000 Trancosin

Co. Ltd

Yen Hop Commune, Van

Yen district, Yen Bai province

Wild land 2-Nov-2013 18-Dec-

2013 18-Dec-

2013

A5/SD66

Km148+900, Yen Hop Commune, Van Yen district, Yen Bai province

2930 12000 Trancosin

Co. Ltd

Yen Hop Commune, Van

Yen district, Yen Bai province

Wild land 2-Nov-2013 18-Dec-

2013 18-Dec-

2013

A5/SD67

Km149+675, Yen Hop Commune, Van Yen district, Yen Bai province

991 10000 Trancosin

Co. Ltd

Yen Hop Commune, Van

Yen district, Yen Bai province

Private land

2-Nov-2013 18-Dec-

2013 18-Dec-

2013

BORROW PITS

Package / Location Approved Approved Ownershipa Prior Land Approval Operation Schedule

Page 169: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

161

Borrow Pit No.

Area (m2) Volume(m3)

Name Contact Info Useb

Date Agencyc Start Estimated

Completion Actual

Completion A5/BP1 Km111+170 120,000 Song Da 9

sub-contractor

Tran Yen district, Yen Bai province

Mountain Tran Yen GOV

A5/BP2 Km111+540 130,000 Song Da 9 sub-contractor

Tran Yen district, Yen Bai province

Mountain Tran Yen GOV

A5/BP3 Km116+600 33,000 Song Da 9 sub-contractor

Tran Yen district, Yen Bai province

Mountain Tran Yen GOV

A5/BP4 Km117+120 37,000 Licogi 13 sub-contractor

Tran Yen district, Yen Bai province

Mountain Tran Yen GOV

A5/BP5 Km117+400 15,000 Licogi 13 sub-contractor

Tran Yen district, Yen Bai province

Mountain Tran Yen GOV

A5/BP6 Km118+100 20,000 Licogi 13 sub-contractor

Tran Yen district, Yen Bai province

Mountain Tran Yen GOV

A5/BP7 Km120+340 10,000 Keangnam Contractor

Tran Yen district, Yen Bai province

Mountain Tran Yen GOV

A5/BP8 Km120+860 30,000 Keangnam Contractor

Tran Yen district, Yen Bai province

Mountain Tran Yen GOV

A5/BP9 Km121+180 40,000 Keangnam Contractor

Tran Yen district, Yen Bai province

Mountain Tran Yen GOV

A5/BP10 Km123+760 20,000 Keangnam Contractor

Tran Yen district, Yen Bai province

Mountain Tran Yen GOV

A5/BP11 Km124+600 80,000 Keangnam Contractor

Tran Yen district, Yen Bai province

Mountain Tran Yen GOV

A5/BP12 Km125+460 35,000 Keangnam Contractor

Tran Yen district, Yen Bai province

Mountain Tran Yen GOV

Page 170: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

162

BORROW PITS

Package / Borrow Pit No.

Location Approved Area (m2)

Approved Volume

(m3)

Ownershipa Prior Land

Useb

Approval Operation Schedule

Name Contact Info Date Agencyc Start Estimated

Completion Actual

Completion A5/BP13 Km125+700 25,025 Keangnam

Contractor Tran Yen

district, Yen Bai province

Mountain Tran Yen GOV

A5/BP14 Km125+720 30,000 Keangnam Contractor

Tran Yen district, Yen Bai province

Mountain Tran Yen GOV

A5/BP15 Km125+880 100,000 Keangnam Contractor

Tran Yen district, Yen Bai province

Mountain Tran Yen GOV

A5/BP16 Km129+440 130,000 Keangnam Contractor

Tran Yen district, Yen Bai province

Mountain Tran Yen GOV

A5/BP17 Km129+240 70,000 Keangnam Contractor

Tran Yen district, Yen Bai province

Mountain Tran Yen GOV

A5/BP18 Km129+160 50,000 Keangnam Contractor

Tran Yen district, Yen Bai province

Mountain Tran Yen GOV

Package A6

BATCHING PLANTS

Package A6 / SD No.

Location Appropriate

settling pond

Noise and dust

measures

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

A6/CBP1 Km 163 Yes No Vinasan Van Yen

district, Yen Bai province

idled grass land

10-Jun-2010

Van Yen GOV

Page 171: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

163

BATCHING PLANTS

Package A6 / SD No.

Location Appropriate

settling pond

Noise and dust

measures

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

A6/CBP2 Km 165 Yes No Whitestone Vina

Van Yen district, Yen Bai province

idled grass land

Van Yen GOV

A6/CBP3 Km 180 Yes No Whitestone Vina

Van Yen district, Yen Bai province

idled grass land

29-Sep-2010

Van Yen GOV

A6/CBP4 Km 185 Yes No Whitestone Vina

Van Yen district, Yen Bai province

Side Cut of idled land

26-Aug-2011

Van Yen GOV

A6/ACBP1 Km 171 Yes No

Asphalt Concrete Batching Plant Km171

Van Yen district, Yen Bai province

Service area of Package A6

2-Oct-2011

Van Yen GOV

A6/ACBP2 Km 180 Yes No

Asphalt Concrete Batching Plant Km180

Van Yen district, Yen Bai province

idled grass land 15-Oct-

2011 Van Yen GOV

A6/ACBP3 Km 163 Yes No

Asphalt Concrete Batching Plant Km163

Van Yen district, Yen Bai province

idled grass land 1-Jan-

2014 Van Yen GOV

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual

End

A6/SD1

Km152+600, Tan Hop commune, Van Yen district, Yen Bai province

2,838 54,528 Quang

Trung., Ltd

Tan Hop commune, Van Yen

district, Yen

Private land 27-Mar-

2012 11-April-

2012 16-April-

2012

Page 172: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

164

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual

End Bai province

A6/SD2

Km152+900, Tan Hop commune, Van Yen district, Yen Bai province

985 17971 Quang Trung., Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Private land 27-Mar-

12 11-April-

2012 16-April-

2012

A6/SD3

Km155, Tan Hop commune, Van Yen district, Yen Bai province

1500 6000 Truong Loc.,

Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Garden of Mr. Hoa

19-April-2012

26-April-2012

26-April-2012

A6/SD4

Km155, Tan Hop commune, Van Yen district, Yen Bai province

3000 12000 Truong Loc.,

Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Garden of Mr. Dung

19-April-2012

26-April-2012

26-April-2012

A6/SD5

Km155, Tan Hop commune, Van Yen district, Yen Bai province

3000 12000 Truong Loc.,

Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Garden of Mr. Thang

19-April-2012

26-April-2012

26-April-2012

A6/SD6

Km155+700, Tan Hop commune, Van Yen district, Yen Bai province

1200 4800 Truong Loc.,

Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Garden of Mr. Thuc

19-April-2012

26-April-2012

26-April-2012

A6/SD7

Km153+700, Tan Hop commune, Van Yen district, Yen Bai province

3000 12000 Truong Loc.,

Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Private land 19-April-

2012 26-April-

2012 26-April-

2012

Page 173: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

165

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual

End

A6/SD8

Km153+300, Tan Hop commune, Van Yen district, Yen Bai province

28766 Truong Loc.,

Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Private land 24-May-

2012 12-Jun-

2012 12-Jun-

2012

A6/SD9

Km154+000, Tan Hop commune, Van Yen district, Yen Bai province

3018 15303 Truong Loc.,

Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Private land 27-Dec-

2012 18-Jan-

2013 18-Jan-

2013

A6/SD10

Km153+520, Tan Hop commune, Van Yen district, Yen Bai province

3380 20785 Truong Loc.,

Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Private land 27-Dec-

2012 18-Jan-

2013 18-Jan-

2013

A6/SD11

Km155+400, Tan Hop commune, Van Yen district, Yen Bai province

480 3638 Truong Loc.,

Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Private land 9-Oct-2012

16-Oct-2012

16-Oct-2012

A6/SD12

Km155+600, Tan Hop commune, Van Yen district, Yen Bai province

3161 18644 Truong Loc.,

Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Wild land 28-Jan-

2013 5-Feb-2013

5-Feb-2013

A6/SD13

Km155+500, Tan Hop commune, Van Yen district, Yen Bai province

448 1413 Truong Loc.,

Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Wild land 28-Jan-

2013 5-Feb-2013

5-Feb-2013

A6/SD14 Km155+700, Tan 5063 100848 Truong Loc., Tan Hop Private land 28-May- 11-Jun- 11-Jun-

Page 174: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

166

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual

End Hop commune, Van Yen district, Yen Bai province

Ltd commune, Van Yen

district, Yen Bai province

2013 2013 2013

A6/SD15

Km155+500, Tan Hop commune, Van Yen district, Yen Bai province

2077 9347 Licogi., Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Garden of Mr. Hieu

19-Apr-2012

26-Apr-2012

26-Apr-2012

A6/SD16 Tan Hop commune, Van Yen district, Yen Bai province

2171 9770 Licogi., Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Private land of Tan Hop’s

primary school

19-Apr-2012

26-Apr-2012

26-Apr-2012

A6/SD17 Tan Hop commune, Van Yen district, Yen Bai province

6466 29097 Licogi., Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Private land of Tan Hop’s

children school

19-Apr-2012

26-Apr-2012

26-Apr-2012

A6/SD18 Tan Hop commune, Van Yen district, Yen Bai province

7526 33867 Licogi., Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Garden of Mr. Hien

19-Apr-2012

26-Apr-2012

26-Apr-2012

A6/SD19 Tan Hop commune, Van Yen district, Yen Bai province

3422 15399 Licogi., Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Garden of Mr. Thong

19-Apr-2012

26-Apr-2012

26-Apr-2012

A6/SD20 Tan Hop commune, Van Yen district,

6877 60947 Licogi., Ltd Tan Hop

commune, Van Yen

Garden of Mr. Huong

19-Apr-2012

26-Apr-2012

26-Apr-2012

Page 175: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

167

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual

End Yen Bai province district, Yen

Bai province

A6/SD21 Tan Hop commune, Van Yen district, Yen Bai province

3752 18193 Licogi., Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Private land 5-Jun-2012

16-Jun-2012

16-Jun-2012

A6/SD22 Tan Hop commune, Van Yen district, Yen Bai province

4163 30572 Licogi., Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Private land 5-Jun-2012

16-Jun-2012

16-Jun-2012

A6/SD23 Tan Hop commune, Van Yen district, Yen Bai province

2383 22253 Licogi., Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Private land 11-Jul-2012

16-Jul-2012

16-Jul-2012

A6/SD24 Tan Hop commune, Van Yen district, Yen Bai province

18412 Licogi., Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Private land 24-Aug-

2012 7-Sep-2012

7-Sep-2012

A6/SD25 Tan Hop commune, Van Yen district, Yen Bai province

5502 104470 Licogi., Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Private land 24-Aug-

2012 7-Sep-2012

7-Sep-2012

A6/SD26 Tan Hop commune, Van Yen district, Yen Bai province

23043 Licogi., Ltd

Tan Hop commune, Van Yen

district, Yen

Private land 24-May-

2012 21-Jun-

2012 21-Jun-

2012

Page 176: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

168

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual

End Bai province

A6/SD27 Tan Hop commune, Van Yen district, Yen Bai province

22675 Licogi., Ltd

Tan Hop commune, Van Yen

district, Yen Bai province

Private land 24-May-

2012 21-Jun-

2012 21-Jun-

2012

A6/SD28

Km166+600, Dong An commune, Van Yen district, Yen Bai province

3258 An Sinh., Ltd

Dong An commune, Van Yen

district, Yen Bai province

Wild land 13-Aug-

2010 16-Aug-

2010 16-Aug-

2010

A6/SD29

Km167+300, Dong An commune, Van Yen district, Yen Bai province

5380 An Sinh., Ltd

Dong An commune, Van Yen

district, Yen Bai province

Wild land 13-Aug-

2010 16-Aug-

2010 16-Aug-

2010

A6/SD30

Km168+700, Dong An commune, Van Yen district, Yen Bai province

24318 An Sinh., Ltd

Dong An commune, Van Yen

district, Yen Bai province

Private land 13-Aug-

2010 16-Aug-

2010 16-Aug-

2010

A6/SD31

Km168+000, Dong An commune, Van Yen district, Yen Bai province

11882 An Sinh., Ltd

Dong An commune, Van Yen

district, Yen Bai province

Wild land 13-Aug-

2010 16-Aug-

2010 16-Aug-

2010

A6/SD32

Km166+050, Dong An commune, Van Yen district, Yen Bai province

2819 An Sinh., Ltd

Dong An commune, Van Yen

district, Yen Bai province

Wild land 13-Aug-

2010 16-Aug-

2010 16-Aug-

2010

Page 177: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

169

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual

End

A6/SD33

Km165+400, Dong An commune, Van Yen district, Yen Bai province

1317 6959 An Sinh., Ltd

Dong An commune, Van Yen

district, Yen Bai province

Private land 1-Jun-2012

12-Jun-2012

12-Jun-2012

A6/SD34

Km165+400, Dong An commune, Van Yen district, Yen Bai province

51127 An Sinh., Ltd

Dong An commune, Van Yen

district, Yen Bai province

Private land 1-Jun-2012

12-Jun-2012

12-Jun-2012

A6/SD35

Km166+487, Dong An commune, Van Yen district, Yen Bai province

20083 An Sinh., Ltd

Dong An commune, Van Yen

district, Yen Bai province

Private land 1-Jun-2012

12-Jun-2012

12-Jun-2012

A6/SD36

Km166+688, Dong An commune, Van Yen district, Yen Bai province

1594 7680 An Sinh., Ltd

Dong An commune, Van Yen

district, Yen Bai province

Private land 1-Jun-2012

12-Jun-2012

12-Jun-2012

A6/SD37

Km166+520, Dong An commune, Van Yen district, Yen Bai province

2571 15058 An Sinh., Ltd

Dong An commune, Van Yen

district, Yen Bai province

Private land 2-Sep-2013

17-Sep-2013

17-Sep-2013

A6/SD38

Km165+360, Dong An commune, Van Yen district, Yen Bai province

2155 3597 An Sinh., Ltd

Dong An commune, Van Yen

district, Yen Bai province

Private land 2-Sep-2013

17-Sep-2013

17-Sep-2013

A6/SD39 Km175+240, Chau 965 3859 Weicovina., Chau Que Ha Private land 13-Aug- 16-Aug- 16-Aug-

Page 178: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

170

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual

End Que Ha commune, Van Yen district, Yen Bai province

Ltd commune, Van Yen

district, Yen Bai province

2010 2010 2010

A6/SD40

Km175+460, Chau Que Ha commune, Van Yen district, Yen Bai province

1090 4361 Weicovina.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Private land 13-Aug-

2010 16-Aug-

2010 16-Aug-

2010

A6/SD41

Km175+720, Chau Que Ha commune, Van Yen district, Yen Bai province

2515 10059 Weicovina.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Private land 13-Aug-

2010 16-Aug-

2010 16-Aug-

2010

A6/SD42

Km176+200, Chau Que Ha commune, Van Yen district, Yen Bai province

2383 9534 Weicovina.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Private land 13-Aug-

2010 16-Aug-

2010 16-Aug-

2010

A6/SD43

Km176+560, Chau Que Ha commune, Van Yen district, Yen Bai province

6939 27756 Anh Cuong.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Private land 13-Aug-

2010 16-Aug-

2010 16-Aug-

2010

A6/SD44

Km176+500, Chau Que Ha commune, Van Yen district, Yen Bai province

3333 29105 Anh Cuong.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Private land 19-Mar-

2012 24-Mar-

2012 24-Mar-

2012

A6/SD45 Km177+500, Chau Que Ha commune, Van Yen district,

1054 9329 Anh Cuong.,

Ltd

Chau Que Ha commune, Van Yen

Private land 19-Mar-

2012 24-Mar-

2012 24-Mar-

2012

Page 179: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

171

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual

End Yen Bai province district, Yen

Bai province

A6/SD46

Km177+200, Chau Que Ha commune, Van Yen district, Yen Bai province

2422 44043 Anh Cuong.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Private land 19-Mar-

2012 24-Mar-

2012 24-Mar-

2012

A6/SD47

Km177+210, Chau Que Ha commune, Van Yen district, Yen Bai province

1071 17617 Anh Cuong.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Private land 19-Mar-

2012 24-Mar-

2012 24-Mar-

2012

A6/SD48

Km171+200, Chau Que Ha commune, Van Yen district, Yen Bai province

932 16888 Weicovina.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Private land 19-Mar-

2012 24-Mar-

2012 24-Mar-

2012

A6/SD49

Chau Que Ha commune, Van Yen district, Yen Bai province

1211 Weicovina.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Private land 20-Oct-2012

31-Oct-2012

31-Oct-2012

A6/SD50

Chau Que Ha commune, Van Yen district, Yen Bai province

9781 Weicovina.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Private land 20-Oct-2012

31-Oct-2012

31-Oct-2012

A6/SD51

Chau Que Ha commune, Van Yen district, Yen Bai province

17769 Weicovina.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen

Private land 20-Oct-2012

31-Oct-2012

31-Oct-2012

Page 180: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

172

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual

End Bai province

A6/SD52

Km173+540, Chau Que Ha commune, Van Yen district, Yen Bai province

51276 Doosan

Contractor

Chau Que Ha commune, Van Yen

district, Yen Bai province

Private land 20-Oct-2012

31-Oct-2012

31-Oct-2012

A6/SD53

Km173+540, Chau Que Ha commune, Van Yen district, Yen Bai province

121442 Doosan

Contractor

Chau Que Ha commune, Van Yen

district, Yen Bai province

Private land 20-Oct-2012

31-Oct-2012

31-Oct-2012

A6/SD54

Km178+920, Chau Que Ha commune, Van Yen district, Yen Bai province

488 1220 Weicovina.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Garden of Mrs. Vach

20-Apr-2012

5-May-2012

5-May-2012

A6/SD55

Km179+040, Chau Que Ha commune, Van Yen district, Yen Bai province

1980 4950 Weicovina.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Garden of Mr. Khoa

20-Apr-2012

5-May-2012

5-May-2012

A6/SD56

Km179+040, Chau Que Ha commune, Van Yen district, Yen Bai province

2660 6650 Weicovina.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Garden of Mr. Thang

20-Apr-2012

5-May-2012

5-May-2012

A6/SD57

Km179+700, Chau Que Ha commune, Van Yen district, Yen Bai province

380 950 Weicovina.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Garden of Mr. Viet

20-Apr-2012

5-May-2012

5-May-2012

Page 181: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

173

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual

End

A6/SD58

Km179+600, Chau Que Ha commune, Van Yen district, Yen Bai province

1275 3188 Weicovina.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Garden of Mr. Vien

20-Apr-2012

5-May-2012

5-May-2012

A6/SD59

Km181+500, Chau Que Ha commune, Van Yen district, Yen Bai province

7785 19463 Quang

Trung., Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Garden of Mr. Hanh

20-Apr-2012

5-May-2012

5-May-2012

A6/SD60

Km179+520, Chau Que Ha commune, Van Yen district, Yen Bai province

2922 7305 Weicovina.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Garden of Mr. Binh

20-Apr-2012

5-May-2012

5-May-2012

A6/SD61

Km177+200, Chau Que Ha commune, Van Yen district, Yen Bai province

6700 66997 Weicovina.,

Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Wild land 25-Oct-2012

12-Nov-2012

12-Nov-2012

A6/SD62

Chau Que Ha commune, Van Yen district, Yen Bai province

14941 Quang

Trung., Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Private land 27-Feb-

2013 2-Apr-2013

2-Apr-2013

A6/SD63

Chau Que Ha commune, Van Yen district, Yen Bai province

29846 Quang

Trung., Ltd

Chau Que Ha commune, Van Yen

district, Yen Bai province

Private land 27-Feb-

2013 2-Apr-2013

2-Apr-2013

A6/SD64 Chau Que Ha 42528 Quang Chau Que Ha Private land 27-Feb- 2-Apr-2013 2-Apr-

Page 182: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

174

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual

End commune, Van Yen district, Yen Bai province

Trung., Ltd commune, Van Yen

district, Yen Bai province

2013 2013

A6/SD65

Km182+620, Chau Que Thuong commune, Van Yen district, Yen Bai province

3200 4000 Quang

Trung., Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Private land 27-Feb-

2013 2-Apr-2013

2-Apr-2013

A6/SD66

Km184+900, Chau Que Thuong commune, Van Yen district, Yen Bai

27000 Nghe An.,

Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Private land 8-Sep-2010

16-Sep-2010

16-Sep-2010

A6/SD67

Km185+300, Chau Que Thuong commune, Van Yen district, Yen Bai

2700 39286 Nghe An.,

Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Private land 13-Mar-

2013 20-Mar-

2013 20-Mar-

2013

A6/SD68

Km185+300, Chau Que Thuong commune, Van Yen district, Yen Bai

5350 97066 Nghe An.,

Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Private land 24-Mar-

2013 3-May-2013

3-May-2013

A6/SD69

Km188+200, Chau Que Thuong commune, Van Yen district, Yen Bai

46690 162582 Nghe An.,

Ltd

Chau Que Thuong

commune, Van Yen

Private land 29-Dec-

2010 13-Jan-

2011 13-Jan-

2011

Page 183: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

175

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual

End district, Yen Bai province

A6/SD70

Km190+110, Chau Que Thuong commune, Van Yen district, Yen Bai province

6910 17032 Nghe An.,

Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Wild land 29-Dec-

2010 13-Jan-

2011 13-Jan-

2011

A6/SD71

Km187+300, Chau Que Thuong commune, Van Yen district, Yen Bai province

1102 15780 Nghe An.,

Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Wild land 29-Dec-

2010 13-Jan-

2011 13-Jan-

2011

A6/SD72

Km187+900, Chau Que Thuong commune, Van Yen district, Yen Bai province

691 5404 Nghe An.,

Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Private land 29-Dec-

2010 13-Jan-

2011 13-Jan-

2011

A6/SD73

Km189+600, Chau Que Thuong commune, Van Yen district, Yen Bai province

1146 19898 Nghe An.,

Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Private land 29-Dec-

2010 13-Jan-

2011 13-Jan-

2011

A6/SD74

Km187+660, Chau Que Thuong commune, Van Yen district, Yen Bai province

2446 13684 Nghe An.,

Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Private land 14-Oct-2011

28-Nov-2011

28-Nov-2011

Page 184: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

176

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual

End

A6/SD75

Km188+400, Chau Que Thuong commune, Van Yen district, Yen Bai province

995 5396 Nghe An.,

Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Private land 14-Oct-2011

28-Nov-2011

28-Nov-2011

A6/SD76

Km188+600, Chau Que Thuong commune, Van Yen district, Yen Bai province

1185 4387 Nghe An.,

Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Private land 14-Oct-2011

28-Nov-2011

28-Nov-2011

A6/SD77

Km189+600, Chau Que Thuong commune, Van Yen district, Yen Bai province

3586 14962 Nghe An.,

Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Private land 14-Oct-2011

28-Nov-2011

28-Nov-2011

A6/SD78

Km190+140, Chau Que Thuong commune, Van Yen district, Yen Bai province

1075 18519 Nghe An.,

Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Wild land 14-Oct-2011

28-Nov-2011

28-Nov-2011

A6/SD79

Km188+400, Chau Que Thuong commune, Van Yen district, Yen Bai province

2439 14962 Nghe An.,

Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Wild land 14-Oct-2011

28-Nov-2011

28-Nov-2011

A6/SD80 Km188+500, Chau Que Thuong

1945 12833 Nghe An.,

Ltd Chau Que

Thuong Wild land

14-Oct-2011

28-Nov-2011

28-Nov-2011

Page 185: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

177

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual

End commune, Van Yen district, Yen Bai province

commune, Van Yen

district, Yen Bai province

A6/SD81

Km189+200, Chau Que Thuong commune, Van Yen district, Yen Bai province

2148 18714 Nghe An.,

Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Wild land 14-Oct-2011

28-Nov-2011

28-Nov-2011

A6/SD82

Km188+720, Chau Que Thuong commune, Van Yen district, Yen Bai province

58384 Nghe An.,

Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Wild land 11-Jan-

2013 20-Jan-

2013 20-Jan-

2013

A6/SD83

Km186+145, Chau Que Thuong commune, Van Yen district, Yen Bai province

7231 96970 Cavico., Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Wild land 26-Nov-

2010 15-Dec-

2010 15-Dec-

2010

A6/SD84

Km186, Chau Que Thuong commune, Van Yen district, Yen Bai province

19993 Cavico., Ltd

Chau Que Thuong

commune, Van Yen

district, Yen Bai province

Wild land 26-Nov-

2010 15-Dec-

2010 15-Dec-

2010

A6/SD85

Km173+300, Chau Que Ha commune, Van Yen district, Yen Bai province

65350 Doosan Contractor

Chau Que Ha commune, Van Yen

district, Yen

Wild land 25-Sep-2013

10-Oct-2013

25-Sep-2013

Page 186: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

178

SPOILS DISPOSAL AREAS

Package SD No.

Location Approved

Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land

Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual

End Bai province

A6/SD86

Km156+100 – Km156+300, Tan Hop commune, Van Yen district, Yen Bai province

9506 Doosan Contractor

Tan Hop commune, Van Yen

district, Yen Bai province

Private land 25-Sep-2013

10-Oct-2013

25-Sep-2013

A6/SD87

Km185+060, Chau Que Thuong commune, Van Yen district,

5400 32900 Doosan Contractor

Chau Que Thuong

commune, Van Yen district,

Wild land 22-Oct-13

25-Oct-2013

25-Sep-2013

A6/SD88

Km152+500 – Km152+700, Tan Hop commune, Van Yen district, Yen Bai province

6800 29240 Doosan Contractor

Tan Hop commune, Van Yen

district, Yen Bai province

Private land 29-Oct-13

22-Nov-2013

22-Nov-2013

A6/SD89

Km152+830, Tan Hop commune, Van Yen district, Yen Bai province

15000 Doosan Contractor

Tan Hop commune, Van Yen

district, Yen Bai province

Private land 2-Nov-13 29-Nov-2013

29-Nov-2013

A6/SD90

Km173+540, Chau Que Ha commune, Van Yen district, Yen Bai province

21442 Van Phuc sub-contractor

Chau Que Ha commune, Van Yen

district, Yen Bai province

Private land 29-Oct-13

22-Nov-2013

22-Nov-2013

A6/SD91

Km173+800, Chau Que Ha commune, Van Yen district, Yen Bai province

28043 Doosan Contractor

Chau Que Ha commune, Van Yen

district, Yen Bai province

Wild land 22-Jan-14

14-Mar-2014

14-Mar-2014

Page 187: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

179

Packages A7

BORROW PITS

Package /Borrow Pit No.

Location Approved Area (m2)

Approved Volume

(m3)

Ownershipa Prior Land Useb

Approval Operation Schedule

Name Contact Info Date Agencyc Start Estimated Completion

Actual Completion

A7/BP1 Km207- Km218+040

30.000 300.000m3 Cam4- Cam Con committee- Bao Yen district- Lao Cai Provice

Hill land 11/5/2011 DONRE OF Lao Cai Provice

30/5/2011 11/10/2011 30/10/2011

QUARRIES

Package /Quarry No.

Location Approved Area (m2)

Approved Volume

(m3)

Ownershipa Prior Land Useb

Approval Operation Schedule

Name Contact Info Date Agencyc Start Estimated Completion

Actual Completion

A7/Q1 No information has been provided

SPOILS DISPOSAL AREAS Package / SD No.

Location Approved Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

A7/SD1 Km191+600 106.000 1.060.000 Tan An committee

Tan An- Van Ban- Lao Cai

idle farm lot

19/4/2010 Contact between the contractor and land owner with confirm of commune

30/4/2010 15/12/2010 30/11/2010

A7/SD2 Km195+800 103.000 1.030.000 Tan An committee

Tan An- Van Ban- Lao Cai

idle farm lot

19/4/2010 30/4/2010 15/12/2010 30/11/2010

A7/SD3 Km197+200 65.000 260.000 Tan An committee

Tan An- Van Ban- Lao Cai

idle farm lot

19/4/2010 30/4/2010 15/12/2010 30/11/2010

A7/SD4 Km198+400 8.000 120.000 Tan An Tan An- Van rice field 19/4/2010 30/4/2010 15/12/2010 30/11/2010

Page 188: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

180

SPOILS DISPOSAL AREAS Package / SD No.

Location Approved Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

committee Ban- Lao Cai people’s committee

A7/SD5 Km203+440 10.000 70.000 Tran Van Bang

Khe U- Tan Thuong- Van Ban- Lao Cai

rice field 7/5/2010 30/5/2010 31/12/2011 20/10/2011

A7/SD6 Km203+440 30.000 210.000 Tran Van Ngoi

Khe U- Tan Thuong- Van Ban- Lao Cai

rice field 7/5/2010 30/5/2010 31/12/2011 25/11/2011

A7/SD7 Km206+500 8.000 40.000 Do Van Hanh

Ban Ly- Cam Con- Bao Yen- Lao Cai

acacia plantation

10/5/2010 25/5/2010 31/12/2011 20/8/2011

A7/SD8 Km205+000 10897.6 54488 Nguyen Van Dong

Ban Ly2- Cam Con- Bao Yen- Lao Cai

idle farm lot

19/5/2010 15/5/2010 31/12/2011 29/9/2011

A7/SD9 Km206+200 3772.3 18861.5 Ly Van Tu Ban Ly1- Cam Con- Bao Yen- Lao Cai

idle farm lot

19/5/2010 15/5/2010 31/12/2011 29/9/2011

A7/SD10 Km209+280 2.848.5 14.242.5 Nguyen Thi Linh

Bong 1- Cam Con- Bao Yen- Lao Cai

rice field 1/2/2012 15/2/2012

A7/SD11 Km210+360 3.044.6 21.312.2 Tran Van Su

Tan Tien- Cam Con- Bao Yen- LC

rice field 1/2/2012 15/2/2012 5/2012

A7/SD12 Km210+360 5.281.9 36.973.3 Hoang Van Chuc

rice field 1/2/2012 15/2/2012 5/2012

A7/SD13 Km210+360 2.703.8 18.926.6 Nguyen Thi Tam

rice field 1/2/2012 15/2/2012 5/2012

A7/SD14 Km210+380 3.735 26.145 Hoang Van Thong

rice field 1/2/2012 15/2/2012 5/2012

A7/SD15 Km210+380 1.592.1 11.144.7 Nguyen Van Hai

rice field 1/2/2012 15/2/2012 5/2012

Page 189: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

181

SPOILS DISPOSAL AREAS Package / SD No.

Location Approved Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

A7/SD16 Km210+400 1.800 10.800 Tran Van Be

rice field 1/2/2012 15/2/2012 5/2012

A7/SD17 Km216+260 2.010.3 12.061.8 Pham Van Thuy

Hong Cam- Cam Con- Bao Yen- LC

rice field 1/2/2012 15/2/2012 5/2012

A7/SD18 Km216+840 5.760.5 34.563 Vuong Thanh Hung

rice field 1/2/2012 15/2/2012 5/2012

A7/SD19 Km216+980 3.470.7 22.559.55 Pham Van Truong

rice field 1/2/2012 15/2/2012 5/2012

A7/SD20 Km217+960 1.549 10.068.5 Pham Van Minh

rice field 1/2/2012 15/2/2012 5/2012

A7/SD21 Km207+000 5.887.3 41.211.1 Vu Van Khac

Tan Thanh- Cam Con- Bao Yen- LC

rice field 1/2/2012 20/5/2012 6/2012

A7/SD22 Km209+820 2.282.5 15.977.5 Le Van Hung

Tan Tien- Cam Con- Bao Yen- LC

rice field 1/2/2012 20/5/2012 6/2012

A7/SD23 Km210+740 151.5 1.090.8 Trinh Thi Hien

Tan Tien- Cam Con- Bao Yen- LC

rice field 7/5/2012 20/5/2012 6/2012

A7/SD24 Km210+760 1.500 14.250 Cam Con committee

rice field 7/5/2012 20/5/2012 6/2012

A7/SD25 Km210+780 145.3 1.191.46 Dinh Thi Mui

rice field 7/5/2012 20/5/2012 6/2012

A7/SD26 Km210+800 1.390 8.618 Le Nguyen Hong

rice field 7/5/2012 20/5/2012 6/2012

A7/SD27 Km210+820 1.141 8.215.2 Tran Cu rice field 7/5/2012 20/5/2012 6/2012

A7/SD28 Km211+200 1.490 11.026 Lam Xuan Truong

Con2- Cam Con- Bao Yen-

rice field 7/5/2012 20/5/2012 6/2012

Page 190: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

182

SPOILS DISPOSAL AREAS Package / SD No.

Location Approved Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

LC

A7/SD29 Km216+520 9.127 86.706.5 Pham Thi Cuong

Hong Cam- Cam Con- Bao Yen- LC

rice field 7/5/2012 20/5/2012 6/2012

A7/SD30 Km216+520 7.385 66.465 Vu Thi Huong

rice field 7/5/2012 20/5/2012 6/2012

A7/SD31 Km216+640 11.075 110.750 Pham Thi Lan

rice field 7/5/2012 20/5/2012 6/2012

A7/SD32 Km217+080 14.655 131.895 Le Van Hien

rice field 7/5/2012 20/5/2012 6/2012

A7/SD33 Km217+280 7.865 86.515 Tran Van Theo

rice field 7/5/2012 20/5/2012 6/2012

A7/SD34 Km189+700 15.555.56 140.000 Tran Van Thanh

Hamlet1- Que Thuong- Van Yen- Yen Bai

idle farm lot

20/10/2011 1/11/2011 25/3/2012

A7/SD35 Km191+350 15.000 120.000 Ta Dinh Hai

Xuan Sang1-Tan An- Van Ban- Lao Cai

idle farm lot

22/10/2011 15/11/2011 3/2012

A7/SD36 Km199+100 10.769.23 70.000 Ly Xuan Hinh

Cau Thin- Tan Thuong- Van Ban- Lao Cai

idle farm lot

21/10/2011 12/11/2011 3/2012

A7/SD37 Km189+700 15,555.56 140,000.00 Tran Van Thanh

Tan An- Van Ban- Lao Cai

abandoned 11/4/2013 These waste disposal have approved by Resource and Environme

15/6/2012 20/12/2012 31/12/2012

A7/SD38 Km191+350 8,000.00 60,000.00 Tran Van Nhi

Tan An- Van Ban- Lao Cai

idle farm lot

11/4/2013 15/6/2012 20/12/2012 31/12/2012

A7/SD39 Km191+350 6,875.00 55,000.00 Pham Van Thong

Tan An- Van Ban- Lao Cai

idle farm lot

11/4/2013 15/6/2012 20/12/2012 31/12/2012

A7/SD40 Km191+350 15,000.00 120,000.00 Ta Dinh Hai

Tan An- Van Ban- Lao Cai

idle farm lot

11/4/2013 15/6/2012 20/12/2012 31/12/2012

Page 191: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

183

SPOILS DISPOSAL AREAS Package / SD No.

Location Approved Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

A7/SD41 Km194+790 9,333.33 70,000.00 Dang Van Thong

Tan An- Van Ban- Lao Cai

abandoned 11/4/2013 nt Bureau of Van Ban district

15/6/2012 20/12/2012 31/12/2012

A7/SD42 Km195+700 70,000.00 490,000.00 Some ownership

Tan An- Van Ban- Lao Cai

abandoned 11/4/2013 15/6/2012 20/12/2012 31/12/2012

A7/SD43 Km199+100 10,769.23 70,000.00 Ly Xuan Hinh

Tan Thuong- Van Ban- Lao Cai

abandoned 11/4/2013 15/6/2012 20/12/2012 31/12/2012

A7/SD44 Km199-Km200 7,500.00 60,000.00 Nguyen Thi Bac

Tan Thuong- Van Ban- Lao Cai

abandoned 11/4/2013 15/6/2012 20/12/2012 31/12/2012

BATCHING PLANTS Package / SD No.

Location Appropriate settling pond

Noise and dust

measures

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

A7/CBP1 Km191+353 Settling pond had provided

Noise and dust measures had support with plant

Khe Sang BCP

Xuan Sang2- Tan An commune - Van Ban District- Lao Cai

Abandoned 7/9/2012 Van Ban District people’s committee

18/3/2011 25/3/2013 December 2013

A7/CBP2 Km199+860 Settling pond had provided

Noise and dust measures had support with plant

Tan Thuong BCP

Khe Quat- Tan An commune- Van Ban District- Lao Cai

Abandoned 7/9/2012 Van Ban District people’s committee

14/11/2011 25/3/2013 March 2014

A7/CBP3 Km198+400 Settling pond had provided

Noise and dust measures

Xom Danh BCP

Ngam Thin- Tan Thuong commune - Van

rice field Van Ban District people’s

15/1/2011 25/3/2013 March 2014

Page 192: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

184

BATCHING PLANTS Package / SD No.

Location Appropriate settling pond

Noise and dust

measures

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

had support with plant

Ban District- Lao Cai

committee

A7/CBP4 Km209+329 Settling pond had provided

Noise and dust measures had support with plant

Tan Tien BCP

Bong1- Cam Con commune - Bao Yen District- Lao Cai

Hill land Bao Yen District people’s committee

25/3/2011 25/3/2013 July 2013

A7/ABP1 Km195+800 Settling pond had provided

Noise and dust measures had support with plant

Trancosin ABP

Tan Son- Tan An- Van Ban- Lao Cai

Hill land 7/11/2012 Van Ban District people’s committee

15/11/2012 25/3/2013 March 2014

A7/ABP2 Km203+100 Settling pond had provided

Noise and dust measures had support with plant

Trico ABP Tan Thuong- Van Ban- Lao Cai

Hill land 11/10/2012 Van Ban District people’s committee

14/12/2012 25/3/2013 March 2014

Packages A8

BORROW PITSPackage /Borrow Pit No.

Location Approved Area (m2)

ApprovedVolume

(m3)

Ownershipa Prior Land Useb

Approval Operation Schedule

Name Contact Info Date Agencyc Start Estimated Completion

Actual Completion

A8/BP1 Km234- Km235 10,5ha= 500.000m3/y Hùng Thắng Hill land 10/01/2011 Lao Cai 31/01/2011 31/01/2012 12/2011

Page 193: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

185

105.000 ear and Dong Cam- Gia Phu Committee- Bao Thang District- Lao Cai Provice

Province people’s committee

QUARRIESPackage /Quarry No.

Location Approved Area (m2)

ApprovedVolume

(m3)

Ownershipa Prior Land Useb

Approval Operation Schedule

Name Contact Info Date Agencyc Start Estimated Completion

Actual Completion

A8/Q1 38800 45.000m3/year Ban Cam quarry

Ban Cam committee- Bao Thang District- Lao Cai Provice

Hill land 7/4/2011 Lao Cai Province people’s committee

April-2011 December- 2015

March-2014

SPOILS DISPOSAL AREAS Package / SD No.

Location Approved Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

A8/SD1 Km218+500 2.612 11.754 Tran Van Chac

An Thang- Son Ha- Bao Thang- Lao Cai

rice field 20/7/2010

Contact between the contractor and land owner with confirm of commune people’s committee

8/2010 11/2010

A8/SD2 Km222+500 952 1.904 Tran Hai Cuong

An Hong- Son Ha- Bao Thang- Lao Cai

rice field 20/7/2010 8/2010 11/2010

A8/SD3 Km223+050 1.386 3.465 Nguyen Thi Quy

rice field 20/7/2010 8/2010 11/2010

A8/SD4 Km234+860 10.000 120.000 Nguyen Van Duong

Tien Loi2- Xuan Giao- Bao Thang- Lao Cai

rice field 10/8/2010 8/2010 11/2010

A8/SD5 Km234+860 2.680 8.000 Pham Van Su

rice field 10/8/2010 8/2010 11/2010

A8/SD6 Km234+840 10.000 120.000 Nguyen Van Duong

rice field 10/8/2010 8/2010 11/2010

Page 194: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

186

SPOILS DISPOSAL AREAS Package / SD No.

Location Approved Area (m2)

ApprovedCapacity

(m3)

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

A8/SD7 Km237+580 730 1.900 Nguyen Thanh Luot

Phu Xuan- Gia Phu- Bao Thang- Lao Cai

rice field 20/6/2012 1/7/2010 11/2010

A8/SD8 Km237+195 652 2.000 Do The Huy

Son Ca- Gia Phu- Bao Thang- Lao Cai

rice field 20/6/2012 1/7/2010 11/2010

A8/SD9 Km237+160 360 1.200 Hoang Van Uyen

rice field 3/8/2010 15/8/2010 11/2010

A8/SD10 Km237+060 350 1.255 Pham Van Tho

rice field 20/7/2010 15/8/2010 11/2010

A8/SD11 Km237+060 488 1.200 Nguyen Ngoc Dinh

rice field 28/7/2010 15/8/2010 11/2010

A8/SD12 Km238+500 4.900 7.350 Tran Van Sinh

Ben Den- Gia Phu- Bao Thang- Lao Cai

rice field 10/8/2010 15/8/2010 11/2010

A8/SD13 Km238+500 300 450 Nguyen Thi Vi

rice field 10/8/2010 15/8/2010 11/2010

A8/SD14 Km238+500 2.400 3.600 Dao Van Nghia

rice field 10/8/2010 15/8/2010 11/2010

A8/SD15 Km238+500 3.000 7.500 Nguyen Duc Loi

rice field 10/8/2010 15/8/2010 11/2010

A8/SD16 Km238+500 9.600 19.200 Pham Van Thi

rice field 10/8/2010 15/8/2010 11/2010

A8/SD17 Km238+500 3.000 6.000 Dao Thi Muoi

rice field 10/8/2010 15/8/2010 11/2010

A8/SD18 Km238+500 3.000 6.000 Pham Van Thu

rice field 10/8/2010 15/8/2010 11/2010

A8/SD19 Km238+500 4.00 8.00 Pham Van Vien

rice field 10/8/2010 15/8/2010 11/2010

Page 195: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

187

BATCHING PLANTSPackage / SD No.

Location Appropriate settling pond

Noise and dust

measures

Ownershipa Prior Land Useb

Approval Operation

Name Contact Info Date Agencyc Start Est. End Actual End

A8/CBP1 Km218+040 Settling pond had provided

Noise and dust measures had support with plant

Suoi Nhu BCp

An Thang hamlet, Son Ha commune, Bao Thang, Lao Cai

Abandoned 16/7/2012 Bao Thang District people’s committee

1/4/2011 1/8/2013 July 2013

A8/CBP2 Km231+889 Settling pond had provided

Noise and dust measures had support with plant

Suoi Trat BCP

Giao Binh hamlet, Xuan Giao commune, Bao Thang, Lao Cai

Hill land 16/7/2012 Bao Thang District people’s committee

11/1/2011

1/8/2013 February 2014

A8/CBP3 Km238+265 Settling pond had provided

Noise and dust measures had support with plant

Ngoi Bo BCP

Ben Pha hamlet, Gia Phu commune, Bao Thang, Lao Cai

Abandoned 16/7/2012 Bao Thang District people’s committee

24/1/2011

1/8/2013 May 2013

A8/ABP1 Km238+265 Settling pond had provided

Noise and dust measures had support with plant

Ngoi Bo ABP

Ben Pha hamlet, Gia Phu commune, Bao Thang, Lao Cai

Abandoned 25/6/2013 Bao Thang District people’s committee

29/3/2013

1/8/2013 March 2014

A8/ABP2 Km230+800 Settling pond had provided

Noise and dust measures had support with plant

Son Hai ABP

Son Hai commune, Bao Thang, Lao Cai

Abandoned Not yet Not yet 20.9.2013

31.12.2013

March 2014

Page 196: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

188

Page 197: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

189

11. ANNEX 5: SUMMARY TABLE OF IMPOSED PENALTIES

Page 198: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

190

Page 199: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

191

PACKAGE A1

DATE/ LETTER REFERENCE

ISSUE PENALTY IMPOSED EXECUTION (Y/N)

22-Nov-2013/GET1-POS-A1-2317

Construction work caused landslide on riversides at Tan Loi (Km 10+695) and Xuan Phuong (Km 7+660) Bridges but restoration works have not been carried out

Due to the Contractor didn’t take any action to implement the requirement of the Engineer in order to restore the affected areas so the Engineer temporarily retained VND ten billion (approximate USD 476,000) from IPC no 38 until the Contractor finishes restoration work

Yes

PACKAGE A2

DATE/ LETTER REFERENCE

ISSUE PENALTY IMPOSED EXECUTION (Y/N)

No penaltyimposed

PACKAGE A3

DATE/ LETTER REFERENCE

ISSUE PENALTY IMPOSED EXECUTION (Y/N)

No penalty imposed

PACKAGE A4

DATE/ LETTER REFERENCE

ISSUE PENALTY IMPOSED EXECUTION (Y/N)

No penalty imposed

PACKAGE A5

DATE/ LETTER REFERENCE

ISSUE PENALTY IMPOSED EXECUTION (Y/N)

Ref. GET3-KEANGNAM-14-A5-117 dated on 17th April, 2014

At Km123+860, Km130+800, Asphalt Concrete Batching Plant Km135, Ngoi Thu: incompliance in fuel management

The Engineer required the Contractor to improve fuel control at these locations. If the situation is not improved, we will consider suspending payments of the works

No

Page 200: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

192

DATE/ LETTER REFERENCE

ISSUE PENALTY IMPOSED EXECUTION (Y/N)

which relates to the non compliance item

GET-KEA-A5-154 dated to on 14th May, 2014

Damaged local road (certain sections from km 141 to km 143, km 149), certain sections of Provincial Road 166 from km 141 to 143 as well as a section of the local road along km 149, which is used by Project vehicles, are damaged/in bad condition

The Engineer required the Contractor to apply measures in order to solve this problem. If the situation is not improved, clause 2.1 (h) in the section 01600- Maintenance and protection of traffic (referring to the Project’s technical specification) will be immediately applied, as suspending payments the works related with the non compliance.

No

PACKAGE A6

DATE/ LETTER REFERENCE

ISSUE PENALTY IMPOSED EXECUTION (Y/N)

No penalty imposed

PACKAGE A7

DATE/ LETTER REFERENCE

ISSUE PENALTY IMPOSED EXECUTION (Y/N)

25/04/2014 - Ref. GET4-GRBCC-1120

Ensure safety and clean on site after technical open - Package A7- Third time

Engineer will not sign next IPC until the contractor completed according to the Engineer’s instructions

No

19/05/2014 - Ref. GET4-GRBCC-1128

Request to submit the CMS for assuring traffic safety during construction

Engineer will not sign next IPC until the contractor completed according to the Engineer’s instructions

No

27/05/2014 - Ref. GET4- GRBCC - 1133

Request to implement the instruction of ADB mission on May, 2014

Engineer will not sign next IPC until the contractor completed according to the Engineer’s instructions

No

04/06/2014 - Ref. GET4- GRBCC - 1134

Request to remove the bushes have dead out of

Engineer will not sign next IPC until the contractor completed

No

Page 201: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

193

DATE/ LETTER REFERENCE

ISSUE PENALTY IMPOSED EXECUTION (Y/N)

Package A7 according to the Engineer’s instructions.

16/6/2014 - Ref. GET4- GRBCC - 1137

Require to clearance for under Bridges, inside box culverts and pile culverts- Package A7

Engineer will not sign as-build and payment for remain items of these Bridges and culverts

No

PACKAGE A8

DATE/ LETTER REFERENCE

ISSUE PENALTY IMPOSED EXECUTION (Y/N)

25/04/2014- Ref. Get4- Vinocanex- 993

Ensure safety and clean on site - Package A8

Engineer will not sign next IPC until the contractor completed according to the Engineer’s instructions.

No

27/05/2014- Ref. Get4- Vinocanex- 1005

Require to clearance An Tien lake at construction place of Son Hai Bridge Km227+065- Package A8

Engineer will retaining payment next IPC for this Bridge

No

26/6/2014- Ref. Get4- Vinocanex- 1028

Require to clearance for Drainage box culverts Km233+506- Package A8

Engineer will not sign as-build and payment for remain items of these Bridges and culverts

No

Page 202: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

194

Page 203: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

195

12. ANNEX 9: DOCUMENTATION RELATED TO COMPLAINTS AND

COMPENSATION ACTIVITIES DUE TO SOCIAL IMPACTS

Page 204: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

196

Page 205: VIE: Greater Mekong Subregion Kunming Hai Lao Cai Highway ... · VIE: Greater Mekong Subregion Kunming–Hai . Phong Transport Corridor Noi Bai– Lao Cai Highway Project . Prepared

Loan 2391/2392 – VIE: GMS Kunming – Hai Phong Transport Corridor

Noi Bai – Lao Cai Highway Project

197

Package A2: Compensation status for cracking houses which were impacted by construction activity

Location No. of

complained households

Influence Zone Checking Status

Compensated

Amount (VND)

Within influence zone

Ouf of influence zone

Compensated Estimated

Kim Long – Tam Duong 5 2 3 5 58,917,432 58,917,432

Dao Tu – Tam Duong 43 40 3 42 661,834853 814,072308

An Hoa – Tam Duong 8 7 1 7 97,386,487 102,386,487

Hoang Dan – Tam Duong

70 70 0 70 1,036,213,575 1,038,408,386

Tien Lu – Lap Thach 55 47 8 52 195,000,000 380,009,646

Van Quan – Lap Thach 46 44 2 34 254,307,164 295,117,096

Dinh Chu – Lap Thach 7 7 0 1 12,334,891 69,606,578

Dong Ich – Lap Thach 51 49 2 49 515,726,908 539,444,817

Tu Yen – Song Lo 19 16 3 13 65,068,490 105,489,439

Duc Bac – Song Lo 3 3 0 3 55,247,453 55,247,453