VG2187-001-A-006_0
-
Upload
elnino-hungba-nguyen -
Category
Documents
-
view
7 -
download
0
description
Transcript of VG2187-001-A-006_0
Total Sheet 17
Vendor’s name : Dong Yang Corrosion Engineering Co., Ltd.
Company’s name : Nghi son Refinery and Petrochemical LLC.
Purchaser : JGCS Consortium
Responsible OC : GS Engineering & Construction Co.,Ltd.
Plant Location : Nghi Son, Vietnam
Project name : NSRP Complex Project
P / Order No. : 0-6495-PG2187-001-A101
Equipment/Material name : Cathodic Protection Materials
Item number : Common
Document title : Installation Procedure
PROJECT (JOB No.: 0-6495-20)
DOCUMENT CLASS: OTHERS
ISSUE PURPOSE: FI
RESULT CODE: A, B, R, F ( )
NEXT STATUS: FA, FR, FI, FC, AB ( )
RESUBMISSION DATE: ( )
RESPONSIBLE DEPT./PERSON: ( )
Review Date: ( )
A: Approved without Comment; B: Approved with Minor CommentR: Not Approved; F: Not Subject to Review
Approval or review hereunder shall not be construed to relieve Vendor/ Subcontractor of hisresponsibilities and liability under the Contract
PurchaserDOC. No.
ORIG. PURCHASE ORDER NO. SERIAL REV.
V G2187-001-A 006 0
0 21/Jan/2015 All For Imformation E.J.Song S.G.Kim D.J.KimRev Date Page Description Prep’d Chk’d App’d
A NA NA ELEC/W.S.Lee 26.Jan.2015
for Onshore Pipeline
INDRA27-JAN-2015
NSRP Complex Project Employer Doc. No.
Rev. 0
Title: Installation Procedure Contractor Doc. No.
VG2187-001-A-006Page 2 of 17
TABLE OF CONTENTS
No. Description Page
1. INTRODUCTION ................................................................................................................................... 3
2. CODES & STANDARDS ...................................................................................................................... 3
3. MATERIAL RECEIVING AND HANDLING .......................................................................................... 4
4. INSTALLATION PROCEDURE ............................................................................................................ 4
4.1. INSTALLATION OF DEEP WELL GROUND BED ............................................................................... 4
4.2. INSTALLATION FOR REFERENCE ELECTRODE(Cu/CuSo4) .......................................................... 5
4.3. INSTALLATION FOR CP COUPON ..................................................................................................... 5
4.4. INSTALLATION OF CABLE LAYING ................................................................................................... 5
4.5. INSTALLATION OF BACKFILLING ..................................................................................................... 5
4.6. CABLE TO PIPE CONNECTION .......................................................................................................... 5
4.7. INSTALLATION OF JUNCTION BOXES ............................................................................................. 6
4.8. INSTALLATION OF BIG FINK TYPE STATIONS ................................................................................ 6
4.9. INSTALLATION OF TRANSFORMER RECTIFIER ............................................................................. 6
5. PRE-COMMISSIONING TESTING & INSPECTION ............................................................................ 8
5.1. CHECK POINT OF TRANSFORMER RECTIFIER .............................................................................. 8
5.2. POTENTIAL TEST AT TEST STATION ................................................................................................ 8
5.3. JUNCTION BOXES .............................................................................................................................. 8
INDRA27-JAN-2015
NSRP Complex Project Employer Doc. No.
Rev. 0
Title: Installation Procedure Contractor Doc. No.
VG2187-001-A-006Page 3 of 17
1. INTRODUCTIONThe purpose of this procedure is to provide minimum requirements of cathodic protection system
installation works in accordance with IFC drawings, standards, codes and related specifications.
2. CODES & STANDARDSThis cathodic protection design shall be in accordance with; but not be limited by the following codes
and standards:
SP0169
National Association of Corrosion Engineers (NACE)
Title : Control of external corrosion on underground or submerged metallic piping systems
SP0286
National Association of Corrosion Engineers Stands (N.A.C.E)
Title : Electrical Isolation of Cathodically Protected Pipelines
SP0193
National Association of Corrosion Engineers Stands (N.A.C.E)
Title : External cathodic protection of on-grade carbon steel storage tank bottoms
RP0196
National Association of Corrosion Engineers Stands (N.A.C.E)
Title : Galvanic Anode Cathodic Protetion of Internal Submerged Surfaces of Carbon Steel Water
Storage Tanks
EN 12954
British Standards Institution (U.K)
Title : Cathodic Protection of Buried or Immersed Metallic Structures - General Principles and
Application for Pipelines
EN 13636
British Standards Institution (U.K)
Title : Cathodic Protection of Buried Metallic Tanks and Related Piping
EN 13509
British Standards Institution (U.K)
Title : Cathodic Protection Measurement Techniques
EN 14505
British Standards Institution (U.K)
Title : Cathodic Protection of Complex Structures
EN 12499
British Standards Institution (U.K)
Title: Internal Cathodic Protection of Metallic Structures
INDRA27-JAN-2015
NSRP Complex Project Employer Doc. No.
Rev. 0
Title: Installation Procedure Contractor Doc. No.
VG2187-001-A-006Page 4 of 17
3. MATERIAL RECEIVING AND HANDLING Materials and components shall be completely free of water, dry and shall be secured to prevent
damages during transition, lifting and unloading.
Materials and components shall be protected to safeguard against all adverse environmental effect
such as humidity, moisture, rain, dust, dirt, sand, mud, salt and sea water.
Store all materials in a dry and well ventilated place preferably in the original package covering.
All cables shall be handled and stored to avoid damage to the insulation.
During transportation, rubber or wood support/underpinning shall be used to avoid surface
scratching. Gloves shall be worn to avoid smudges from fingerprints.
4. INSTALLATION PROCEDURE
4.1. INSTALLATION OF DEEP WELL GROUND BED Anode location identified as per approved drawing.
The drilling of Deep Well Hole shall be witnessed to ensure the correct depth is achieved and well
casing is installed as per approved drawing.
The well casing shall be bare steel to a depth and elevation as per approved drawing.
The non-active part of the deep ground bed casing shall be insulated from the outer soil as per
approved drawing.
The anode installation will be witnessed to ensure freedom of movement and the correct anode
depth is achieved.
All welding (centralizers, anodes shoe and plate) shall be carried out before the installation of the
anodes to avoid any damages to anodes or the cables.
Weld centralizers to support pipe to ensure that the anode is located vertically and centrally in the
casing. Continue to install anodes, support pipe and vent tubing until all the anodes are in place and
assembly lowered to the bottom of the cased hole.
Carbonaceous backfill shall be fluidized with water to form slurry and pumped into the ground bed.
The procedure will be checked to ensure the bed is pumped from the bottom and no airlocks occur.
The carbonaceous backfill shall be pre-mixed in 50kg batches with 24 to 30 liters of water. The
slurry shall be continuously stirred during pumping operations. Potable water shall be used in the
installation process.
Rough sand or gravel shall complete the fill over the carbonaceous backfill up to 1m below grade
level as per the approved drawing.
Install anode junction box and terminate each anode cable after that each cable shall be labeled
correctly.
The following inspection and tests shall be performed for deep well ground bed and related
accessories as per the approved drawing:
- Location of Deep Ground Bed.
- Depth of borehole to the required length.
- Anode quantity.
- Anode spacing.
- Anode center in steel casing.
- Casing, vent pipe, PVC pipe and support pipe length.
- Coke breeze backfill.
- Anode bed sealed as per approved drawing.
- Visual check of deep well system accessories.
INDRA27-JAN-2015
NSRP Complex Project Employer Doc. No.
Rev. 0
Title: Installation Procedure Contractor Doc. No.
VG2187-001-A-006Page 5 of 17
4.2. INSTALLATION FOR REFERENCE ELECTRODE(Cu/CuSo4) Install the permanent reference electrode at location required as per approved drawings (prior to
installation, polyethylene bag to be removed from the reference electrodes and to be soaked in a
water container for 30 minutes minimum).
Connect to the test station as per the approved drawing.
The following inspection and tests shall be performed for the installation of permanent reference
electrode.
- Installed Electrodes shall be inspected to ensure the functional capability, their location and
level is as per the detail drawing.
- Check the reference cell soaked in water.
- The measured potential of the electrodes to standard electrode (Potable reference electrode)
shall be as follow:
* Cu/CuSO4 Reference electrode : ±50mVThe inspection will be recorded on attached inspection and test sheet.
4.3. INSTALLATION FOR CP COUPON Location of coupons coincides with the location of permanent reference electrodes.
A coupon shall be installed together with permanent type reference electrode as a monitoring facility
and location of the coupon will be the zero to 1/3 diameter of buried piping and the permanent type
reference electrode as per approved drawing.
Coupons shall be backfilled with native soil and wetted with potable water to provide better soil
contact and compaction.
The following inspection and tests shall be performed for the installation of coupons.
- Location of coupons.
- Termination status of lead cables
4.4. INSTALLATION OF CABLE LAYING Buried cables should laid at a depth that will protect them from disturbance by plough or other
excavations.
Cable tiles or cable warning tape should be used to warn of the presence of the cable during any
subsequent excavation.(Cable tiles and warning tape shall be supplied by contractor)
The cable shall immediately be tagged with its unique ID as per approved drawing.
The cable lengths shall be checked against the cable schedule lengths or approved drawing in order
that wastage is minimized.
The inspection will be recorded on attached inspection and test sheet.
4.5. INSTALLATION OF BACKFILLING Before Backfilling, Be attention to avoid damages to anode, cables & etc.
If any damage to C.P materials is detected (cable cutting, welding damage etc), backfilling shall be
stopped and promptly repaired or replacement actions shall undertaken.
The inspection will be recorded on attached inspection and test sheet.
4.6. CABLE TO PIPE CONNECTION Cable to pipe connections shall be performed by the welding plate for bolt fastened method, the
welding plate shall be welded directly to the pipe as detailed below:
The pipe coating shall be removed over an area of approximately 50 x 50 mm either using a scraper
or hot knife.
The area shall be thoroughly cleaned to bright metal using a coarse file. If necessary, the exposed
area is then pre-heated using a flame torch to relieve area of moisture.
INDRA27-JAN-2015
NSRP Complex Project Employer Doc. No.
Rev. 0
Title: Installation Procedure Contractor Doc. No.
VG2187-001-A-006Page 6 of 17
The completed welding shall be checked visually and mechanically tested with a 1 KG copper
headed hammer. Negative & test cable shall be connected to welding plate by bolt fastened method
with double nut.
The completed connection point and pipe shall be cleanly washed. The cable connection and the
exposed pipe shall be coated with approved coating material (Epoxy, AR-16). The repair material
shall overlap existing coating at least by 20mm.
- Welding plate for cable connection shall be as same material as cooling water piping to
avoid galvanic corrosion and shall not be coated for electrical continuity.
The inspection will be recorded on attached inspection and test sheet.
4.7. INSTALLATION OF JUNCTION BOXES Install the junction box at location as per approved drawing.
It is highly recommended to install the anodes cables first and then select the anode terminal box
location where all associated anode cables tails can reach, because cable joint in anode cable is not
allowed. Therefore, select the anode terminal box location very carefully to avoid any problem
related to short cable length one more time.
Install the pre-cast foundation with frame for mounting of the box. Mount the box on the frame.
Identification the box with Tag No plate.
A minimum suitable length of cable shall be left in the trench at points of termination/connection to
above ground boxes.
The following inspection and tests shall be performed for the installation of boxes.
- Equipment supports will be inspected to ensure they are fabricated as per the approved
detail drawing.
- Base plates, fixings, concrete foundations etc. will be checked for locations and level and
the fixings.
- Cables to boxes will be checked against the approved drawing for correct routing and
termination.
- Visual and connection check.
The inspection will be recorded on attached inspection and test sheet.
4.8. INSTALLATION OF BIG FINK TYPE STATIONS Install Flush Fink Type Stations as per approved drawing.
A minimum suitable length of slack cable shall be left in the trench at points of
termination/connection to above ground apparatus.
The following inspection and tests shall be performed for the installation of Flush Fink Type Stations.
- Equipment supports shall be inspected to ensure they are fabricated as per the approved
detail drawing.
- Concrete pit, etc. shall be checked for locations and level and the fixings.
- Cables to the stations shall be checked in accordance with the approved drawing for correct
routing and termination.
4.9. INSTALLATION OF TRANSFORMER RECTIFIER Location of TR/Rectifier shall be decided at site as per approval drawings.
Prior to the installation, the foundations will be checked for level and civil clearance.
Fix transformer rectifier on a concrete foundation by utilizing anchors and the fixing holes provided.
Great care shall be taken in identification of polarity of all cables ensuring they match the polarity of
the marked terminals.
The installation of TR/Rectifier will be witnessed to ensure correct orientation alignment for cabling
in accordance with approved drawings. Secure fasten of termination.
Final check of cable termination with approved drawings.
INDRA27-JAN-2015
NSRP Complex Project Employer Doc. No.
Rev. 0
Title: Installation Procedure Contractor Doc. No.
VG2187-001-A-006Page 7 of 17
On completion of the cable connections, all glands shall be tightened with sufficient slack in the
cables to permit cables to be removed from the terminals. The opening where the cables exit the
duct for buried cables shall be sealed properly.
Earthing shall be provided according to electrical specification. (Earthing shall be supplied by
contractor)
The following inspection and tests shall be performed for the installation of TR/Rectifier.
- Prior to removal to site the TR/rectifier will be inspected for mechanical damage at enclosure
of TR/Rectifier.
- Particular attention for safety risk will be paid to control panel measuring instruments and
control devices.
- Oil filling will be completed in vendor ’s factory before delivery at site.
- Prior to installation, the foundations will be checked for level and civil clearance will be
obtained.
- The installation of TR/Rectifier will be witnessed to ensure correct orientation and alignment
for cabling, including termination and earthing as per approved drawing.
The inspection will be recorded on attached inspection and test sheet.
INDRA27-JAN-2015
NSRP Complex Project Employer Doc. No.
Rev. 0
Title: Installation Procedure Contractor Doc. No.
VG2187-001-A-006Page 8 of 17
5. PRE-COMMISSIONING TESTING & INSPECTION
5.1. CHECK POINT OF TRANSFORMER RECTIFIER Check the input/output switch (MCCB) position. It should be at "Off" position.
Check the input voltage. It should be fit to rating of rectifier.
Before energizing the TR/rectifier, adjust output volume to minimum position. And then check the
potential at test station (Natural potential).
Energizing the rectifier step by step as follows.
- Input MCCB “ON”
- Output MCCB “ON”
Check the polarity at output terminal by multi-tester
- The cable to anode terminal box or positive junction box shall be connected on positive (+)
terminal of TR/Rectifier. Cable tag & continuity shall be checked before termination.
- The cable to structure or negative junction box shall be connected on negative (-) terminal of
TR/Rectifier. Cable tag & continuity shall be checked before termination.
- Check the polarity at output terminal by multi-tester
Check the value of DC ampere, DC voltage and record it on the form.
- Adjust the volume for control with slowly until it reaches the protective potential
The inspection will be recorded on attached inspection and test sheet.
5.2. POTENTIAL TEST AT TEST STATION At test station, the potentials of structure to electrolyte should be recorded with respect to a
reference electrode(Cu/CuSO4).
The structure lead wire shall be connected to the (+) terminal of a multi-meter(DC Volts mode)
The reference electrode lead wire shall be connected to the (-) terminal of the multi-meter and the
electrode placed upon moist soil immediately above the structure under test station.
Check the natural potential before TR/Rectifier energizing.
Check the protective potential after TR/Rectifier energizing.
This potential shall be measured with respect to a Cu/CuSO4 reference electrode contacting the
electrolyte.
- The protective (Instant off) potential of pipe for this project should be more negative than
(-)0.85V vs Cu/CuSO4 Reference cell.
- A minimum of 100mV of cathodic polarization between the structure surface and a stable
reference electrode contacting the electrolyte. The formation or decay of polarization can be
measured to satisfy this criterion.
All potential measurements shall be taken with meters having a minimum input impedance of 100m
ohm.
The inspection will be recorded on attached inspection and test sheet.
5.3. JUNCTION BOXES Check the internal connection with approved drawing.
Check the anode current of feed cable.
The inspection will be recorded on attached inspection and test sheet.
INDRA27-JAN-2015
NSRP Complex Project Employer Doc. No.
Rev. 0
Title: Installation Procedure Contractor Doc. No.
VG2187-001-A-006Page 9 of 17
Appendix
INS -01 Inspection and Test Sheet : MMO-Ti Tubular Anode
INS -02 Inspection and Test Sheet : Mg Anode
INS -03 Inspection and Test Sheet : Reference Electrode Function Test
INS -04 Inspection and Test Sheet : Boxes
INS -05 Inspection and Test Sheet : Coating
INS -06 Inspection and Test Sheet : Cable Installation
INS -07 Inspection and Test Sheet : TR/Rectifier
INS -08 Pre-commissioning check list : TR/Rectifier
INDRA27-JAN-2015
NSRP Complex Project Employer Doc. No.
Rev. 0
Title: Installation Procedure Contractor Doc. No.
VG2187-001-A-006Page 10 of 17
INSPECTION AND TEST SHEET (For Construction)MMO-Ti Tubular Anode(For U/G Onshore Pipeline)
PIPE No: Date:
No Description Results Remark
1 Location and length of anode as per drawing
2 Cable identification
3 Depth of excavation to the required length
Results
Acceptance :
Rejection : X
Note :
Title
Name
Signature
Date
Form no. INS-01
INDRA27-JAN-2015
NSRP Complex Project Employer Doc. No.
Rev. 0
Title: Installation Procedure Contractor Doc. No.
VG2187-001-A-006Page 11 of 17
INSPECTION AND TEST SHEET (For Construction)Mg Anode (For Temporary)
PIPE No: Date:
No Description Results Remark
1 Location of anode
2 Termination of anode lead cables
3 Cable tags
Results
Acceptance :
Rejection : X
Note :
Title
Name
Signature
Date
Form no. INS-02
INDRA27-JAN-2015
NSRP Complex Project Employer Doc. No.
Rev. 0
Title: Installation Procedure Contractor Doc. No.
VG2187-001-A-006Page 12 of 17
INSPECTION AND TEST SHEET (For Construction)Reference Electrode Function Test (For U/G Onshore Pipeline)
Item No: Date:
No Reference Electrode
No.
Potential
(Portable Reference
Electrode)
(△mV)
Results Remark
1
2
3
4
5
6
7
8
9
10
Results
Acceptance :
Rejection : X
Criteria : ±50mV
Note :
Title
Name
Signature
Date
Form no. INS-03
INDRA27-JAN-2015
NSRP Complex Project Employer Doc. No.
Rev. 0
Title: Installation Procedure Contractor Doc. No.
VG2187-001-A-006Page 13 of 17
INSPECTION AND TEST SHEET (For Construction)Boxes(For U/G Onshore Pipeline)
Box No : Date :
No Description Results Remark
1 Support as per approved drawings
2 Foundation location and direction
3Cable connections as per connectiondiagram.
4 All cable clearly identified with tags.
Results
Acceptance :
Rejection : X
Note :
Title
Name
Signature
Date
Form no. INS-04
INDRA27-JAN-2015
NSRP Complex Project Employer Doc. No.
Rev. 0
Title: Installation Procedure Contractor Doc. No.
VG2187-001-A-006Page 14 of 17
INSPECTION AND TEST SHEET (For Construction)Coating(For U/G Onshore Pipeline)
Pipe No: Date:
No Description Results Location Remark
1 Check the welding condition
2 Check the cable connection to welding plate
3 Check the coating condition
Results
Acceptance :
Rejection : X
Note :
Title
Name
Signature
Date
Form no. INS-05
INDRA27-JAN-2015
NSRP Complex Project Employer Doc. No.
Rev. 0
Title: Installation Procedure Contractor Doc. No.
VG2187-001-A-006Page 15 of 17
INSPECTION AND TEST SHEET (For Construction)Cable Installation(For U/G Onshore Pipeline)
Item No: Date:
No Description Results Remark
1 Sufficient slack
2 Buried depth
3 Backfilling
Results
Acceptance :
Rejection : X
Note :
Title
Name
Signature
Date
Form no. INS-06
INDRA27-JAN-2015
NSRP Complex Project Employer Doc. No.
Rev. 0
Title: Installation Procedure Contractor Doc. No.
VG2187-001-A-006Page 16 of 17
INSPECTION AND TEST SHEET (For Construction)TR/Rectifier(For U/G Onshore Pipeline)
TR/Rectifier No : Date :
No Description Results Remark
1 Equipment Undamaged
2 Orientation and Alignment Correct
3 Accessories Installing
4 Earth as per detail drawing
5 Oil filling complete and no leakage
Results
Acceptance :
Rejection : X
Note :
Title
Name
Signature
Date
Form no. INS-07
INDRA27-JAN-2015
NSRP Complex Project Employer Doc. No.
Rev. 0
Title: Installation Procedure Contractor Doc. No.
VG2187-001-A-006Page 17 of 17
INSPECTION AND TEST SHEET (For Pre-commissioning)TR/Rectifier(For U/G Onshore Pipeline)
Item No: Date:
No Description Results Remark
1 Before energizing the TR/Rectifier
ACheck if all anodes cable are terminated and labeledin the junction box.
BCheck if the negative cable (from structure) isterminated in the junction box.
C Check if all JBs and test boxes are labeled outside.
D Check if all shunt and resistor in the box are installedas per drawing.
E Check if all TR/Rectifier capacity, location, labeling,oil level, silica gel are installed as per specification.
F Check if all the TR/Rectifier’s positive cable is
connected to PJB and negative cable is connected toNJB
G Check if all reference electrode are installed as perdrawings.
H Witness potential natural reading for all test boxes before energizing the TR/Rectifiers.
2 After energizing the TR/Rectifiers
A Verify if TR/Rectifiers meters are functioning.
B Witness if potential “On/Off” readings are meetingthe protection criterion for all test boxes.
Results
Acceptance :
Rejection : X
Note :
Title
Name
Signature
Date
Form no. INS-08
INDRA27-JAN-2015