Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
-
Upload
qatarstructz30 -
Category
Documents
-
view
218 -
download
0
Transcript of Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
1/39
0
CColumn-
Shortening
Vertical Shortening &Structural Health
Monitoring of
Lotte World Tower 3rd April 2013
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
2/39
1
CColumn-
Shortening
Contents
I. Introduction
II. Vertical Shortening of Lotte World Tower
III. Structural Health Monitoring of Lotte World Tower
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
3/39
2
CColumn-
Shortening
Contents
I. IntroductionII. Vertical Shortening of Lotte World Tower
III. Structural Health Monitoring of Lotte World Tower
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
4/39
3
CColumn-
Shortening
Construction Stage Analysis
Why Construction Stage Analysis
In general structures are analyzed assuming that the structure is built and loaded in a moment.
Construction of structures is a time taking process and during this period Material Properties, Loads and
Boundaries conditions may change.
Construction Sequence
Self weight of slab
Other Dead Loads (Partions, Finishes)
Completed Structure
Dead Load + Live Load
Wind
Earthquake
LL,WL,EQActs
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
5/39
4
CColumn-
Shortening
Construction Stage Analysis
Why Construction Stage Analysis
In general structures are analyzed assuming that the structure is built and loaded in a moment.
Construction of structures is a time taking process and during this period Material Properties, Loads and
Boundaries conditions may change.
End Moment of Girder by Stories (Wall Connection)
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
6/39
5
CColumn-
Shortening
Column Shortening & Related Issues
The behavior of concrete structures are typically determined using Linear elastic analysis and/or summation of vertical column loads.
With the increase in building height the actual behavior of the structure increasingly diverges from the results of such conventional analysis.
Long-term, time-dependent deformations in response to the construction sequence, creep and shrinkage canredistribute the forces and gravity induced side sway that would not be detected by conventional methods.
When the time dependent effects of construction, creep, shrinkage, variation of concrete stiffness with time,sequential loading are not considered the predicted forces and deflections may be inaccurate.
With increased height of structures the effect of column shortening (Elastic & Inelastic) take on added significanceand need special consideration in design and construction.
The strains in the columns of low as well as ultra-high rise buildings are similar if the stress levels are similar;however, the overall column shortening is cumulative and depends upon the height of the structure.
Elastic Shortening of 80 Storey Steel Structure ~ 180 mm to 255 mm.
Elastic Shortening of 80 Storey Concrete Structure ~ 65 mm.
Total Shortening of 80 Storey Concrete Structure ~ 180 to 230 mm.
Inelastic Shortening ~ 1 to 3 times Elastic shortening.
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
7/39
6
CColumn-
Shortening
Column Shortening & Related Issues
Steel Structures
- Linear elastic Behavior
Stress StrainStrain is constant for a given Stressduring loading & unloading
E = ( / )
L = (PL/A E)
Concrete Structures- Nonlinear Inelastic Behavior
- But in general Analysis and design behavior of concrete is treated as linear elastic material
Neither Stress StrainNor Strain is constant for a given StressDuring loading & unloading
Elastic Strain + Inelastic Strain
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
8/39
7
CColumn-
Shortening
Column Shortening & Related Issues
Concrete Structures
Elastic Shortening
Modulus of Elasticity changes with time .
E i = ( / )
L = (PL/A E i)
Inelastic Shortening
Creep Shortening.Shrinkage Shortening.
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
9/39
8
CColumn-
Shortening
Effects of Column Shortening
Absolute shortening is rarely of practical interest.
Differential shortening between adjacent vertical elements is the most important factor for engineer.
Axial Shortening of vertical elements will not effect those elements very much, horizontal elements like beams and slabs and non
structural elements are affected.
Slabs may not be truly horizontal after some time.
Beams could be subjected to higher bending moments.Load transfer.
Structural Effects
Cracks in Partition Walls.Cracks in StaircasesDeformation of Cladding.
Mechanical Equipment. Architectural Finishes.Built in Furnishings.
Non Structural Effects
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
10/39
9
CColumn-
Shortening
Effects of Column Shortening
Deformation and breakage of Facades, windows &Parapet walls
Reverse Inclination of Drainage Piping System
Deformation of Vertical Piping System Deformation and breakage of internal partitions
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
11/39
10
CColumn-
Shortening
Procedure for Accounting
Two basic prerequisites for accurately and efficiently predicting these effectsare
Reliable Data for the creep and shrinkage characteristics of the particular concrete mix Analytical procedures for the inclusion of these time effects in the design of structure.
Some of the popular predictive methods for predicting creep and shrinkage
strains are
ACI 209 -92Bazant Bewaja B3CEB FIP (1978, 1990)PCA Method (Mark Fintel, S.K.Ghosh & Hal Iyengar)
GL 2000 (Gardner and Lockman)Eurocode
C
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
12/39
11
CColumn-
Shortening
Procedure for Accounting
C
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
13/39
12
CColumn-
Shortening
Procedure for Accounting
0.0E+00
5.0E-05
1.0E-04
1.5E-04
2.0E-04
2.5E-04
3.0E-04
3.5E-04
4.0E-04
4.5E-04
5.0E-04
0 50 100 150 200 250 300 350 400 450 500 550Date
S t r a i n
Back Analysis Output(TA1-20F-02)
Stain Gauge Output(TA1-20F-02)
Reflection of physical properties in calculation frommaterial experiment:
Youngs Modulus, Poissons Ratio, MeanCompressive strength, Volume to Surface ratio,Shapes, sizes etc.
Reflection of effects of Climate on shortening: Average Temperature , RH etc.
Construction Sequence:
Stage duration, Additional Steps, Member Age, Load activation age, Boundary activation age etc.
Reflection of the above effects on site master-schedule
Installation of sensors or gages in members for determining the actual shortening.
Understanding and noting the following:Curing procedure / Temperature,
Actual Shortening,Change in Ambient Temperature (Important),
Actual Humidity,Deviation from Defined Construction Stages,
Manipulation of factors in analytical Calculation,Re- Analysis
Deferent between analysis v alue and measurement
Analytical Measurement Experimental Measurement
Using Software or Manually(Manual calculation is almost impossible) Field Measurements
C
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
14/39
13
CColumn-
Shortening
Procedure for Accounting
Field Measurements
Determination of Installation location Installation of Gauge After Installation
After Installation of Gauge After Casting of Concrete Field data collection
C
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
15/39
14
CColumn-
Shortening
Compensation at Site
Pre-slab installation shortenings
Shortenings taking place up to the time of slab installation
Post-slab installation shortenings
Shortenings taking place after the time of slab installation
:Compensation
: Design Level
: Pre-slab Installation shortening
: Post-slab Installation shortening
Reinforced Concrete Structure
Pre-slab installation shortenings has no importance
Compensation by leveling the forms
Post-slab installation shortenings due to subsequent loads and creep/shrinkage
Steel Structure
Columns are fabricated to exact length.
Attachments to support the slabs
Pre-slab installation shortenings need to be known.
Compensation for the summation of Pre-installation and Post-installation shortenings
C
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
16/39
15
CColumn-
Shortening
Compensation at Site
ColumnColumn
1 st correction
2nd correction
1st correction
C
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
17/39
16
CColumn-Shortening
Compensation at Site
SLAB THK.
B (= Height ofcorrection
filler
Height of correction
Column Rebar
CON'C Casting face The order of construction
installation of column forms
insertion of FILLER
insertion of correcting FILLER
Installation of SLAB forms
securing the thickness of slab.
C
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
18/39
17
CColumn-Shortening Contents
I. Introduction
II. Vertical Shortening of Lotte World Tower
III. Structural Health Monitoring of Lotte World Tower
C O i
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
19/39
18
CColumn-Shortening
Overview
C O i
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
20/39
19
CColumn-Shortening
Overview
Location Jamsil, Seoul, South Korea.
Height Roof 554.6 m; Antenna Spire 556 m
No. of Floors 123
Floor Area 304,081 m 2
Function / Usage Office, Residential, Hotel, Observation Deck
Structure Type Reinforced Concrete + Steel
Lateral load resisting system Core Wall + Outrigger Truss + Belt Truss
Foundation Type Mat Foundation
Construction Period March 2011 ~ 2015
Lotte World Tower
C Overview
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
21/39
20
CColumn-Shortening
Overview
Location Jamsil, Seoul, South Korea.
Height Roof 554.6 m; Antenna Spire 556 m
No. of Floors 123
Floor Area 304,081 m 2
Function / Usage Office, Residential, Hotel, Observation Deck
Structure Type Reinforced Concrete + Steel
Lateral load resisting system Core Wall + Outrigger Truss + Belt Truss
Foundation Type Mat Foundation
Construction Period March 2011 ~ 2015
Lotte World Tower
C Overview
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
22/39
21
CColumn-Shortening
Overview
1 1
2
Initial Curing
Concrete Structures deformation = = Elastic Strain 1 + Inelastic Strain 2
Inelastic Shortening ~ 1 to 3 times Elastic shortening.
Conc
Vertical
Member
Pre-slab Installation shortening
Core wall Column
CoreShortening Column
Shortening
< Deferential Deformation >
Deferential Shortening
General Height 555m / 123 floors
Tower Deformati
on
Deformation of the tower is a naturally occurring depending on material, constructionmethod
Vertical Deformation:Vertical Shortening / Settlement / Construction Errors
Horizontal Deformation:Differential Shortening / SettlementUneven load due to construction method
Asymmetric floor plan / Construction errors
Horizontal Deformation
VerticalDeformation
WithTime
C Vertical Shortening and Related Issue
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
23/39
22
CColumn-Shortening
Vertical Shortening and Related Issue
High-rise Considerations
Wind Induced
acceleration control
Optimum StructureSystem
Construction Jointmanagement
Lateral-Displacement
control
Concrete PumpingTechnology
Health Monitoring
ShorteningPredictionTechnology
High performanceConcrete Spalling
Structural safety aspects Usability aspects
Cost increase due to Mega columns,outrigger additional stress
Safety concerns, accordingto the tilt of the tower
Absence of a connectionbetween tower and parking lotcause safety issue
Deformation of Material occursdue to Additional stress
Safety problems of unequal deformationcaused by the slab structure at the hotelarea
Elevators safety due to towers tilt
Curtain wall and exterior materialsdeformation and failure occurs
Deformation of Vertical pipingand breakage problems
Reverse Inclination of Drainage Piping System
Inconvenience to residents mayoccurs due to the slope of the slab
Defection problem due tobreakage of finishes
Deformation of VerticalPiping System
Elevators safety due totowers tiltAdditional Stress of Outrigger
C ShorteningReviewProcess
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
24/39
23
CColumn-Shortening
Shortening Review Process
Preliminary Analysis
Material / Section Properties
Applied Load, Schedule
Main analysis
Updating material properties from experiments
Construction sequence considering the fieldcondition
1st, 2nd, 3rd Re-Analysis
Suggestion of compensation and details for non-constructed part of structure
Final Report
Shortening, result from test, measurement Review
Material Experiment
Compressive strength
Modulus of elasticity
Creep & Shrinkage
Measurement
Measurement of strain for Column & Wall
Design with AdditionalForce
ApplyingCompensation to in-situ
structure
Design
Const-ruction
0.0E+00
1.0E-04
2.0E-04
3.0E-04
4.0E-04
0 5 0 1 00 1 50 2 00 2 50 3 00 3 50
S t r a
i n
Day
Back Analysis Output (103-1F-01)
Strain GaugeOutput(103-1F-01)
C Pre-Analysis - Deformations
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
25/39
24
CColumn-Shortening
Pre-Analysis - Deformations
Vertical deformation
Deferential Shortening
Horizontal deformation
Differential settlement
Deferential shortening btw Core & Column
Steel column: Max 18mm
Mega column: Max 65mm
Top of tower Steel Frame: 368.7 mm Core wall: 314.0 mm
Top of mega column
Mega Col: 297.8 mm Core wall: 241.3 mm
ABOVEFIRESHUTTER
ABOVE ABOVEFIRESHUTTER
ABOVE
X-Dir
Y - D i r
OW1OW2
OW9OW8
O W 1 1
O W 1 2
OW10
OW3OW4
O W 5
O W 6
O W 7
O W 1 0
O W 1
O W 4
OW7
Pridiction
X dir: 27.2mmY dir: 115.5mm
Safety check
Elevators rails
Vertical Pipes
X
Y
MEGACOL. CORE WALL
FOUNDATION
MEGACOL.
MEGACOL. CORE WALL
FOUNDATION
MEGACOL.
Core wall settlement: 35mmColumn settlement: 16mm
Core wall Column
CoreShortening
ColumnShortening
DeferentialShortening
Lantern & Core
C Pre-Analysis - Stresses
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
26/39
25
CColumn-Shortening
Pre Analysis Stresses
Outriggers additional stressSlabs additional stress
Podiums additional stress
Differential Deformation btw Slab-Column
Slab has additional stress
Additional stress btwtower & podium
Max 100 ton.m
Require SettlementJoint & Safety check
Additional Stress without Delay Joint
1 st outrigger (L39~L43): 3,600 ton s 2nd outrigger (L72~L75): 4,700 ton s
required a delay joint installation
Additional Stress with Delay Joint
1 st outrigger (L39~L43): 1,700 ton s
2nd outrigger (L72~L75): 2,000 ton s
PodiumTower
connection
L87~L103
L72~L75
L39~L43
B06~B01
C Pre-Analysis Compensation
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
27/39
26
CColumn-Shortening
Pre Analysis Compensation- Core wall: Absolute correction for securing design level
- Column: Relative correction for deferential shortening
Relative correction between core and column
correction due to measurement
pre-Analysis
Analysis
Re-analysis1~6 times
MaterialTest
Measurement
1 st correction
2nd correction
Additionalcorrection for unconstructed
L106~L123 + 1m m
L76~L105 + 2m m
L72~L75 +3m m +2 5m m 2nd O /R
L69~L71 + 3m m + 30 m m
L66~L68 + 3m m + 35 m m
L63~L65 + 2m m + 40 m m
L60~L62 + 2m m + 45 m m
L57~L59 + 2m m + 50 m m
L54~L56 + 3m m + 55 m m
L37~L53 +3 m m +6 0m m 1st O /R
L34~L36 + 3m m + 55 m m
L31~L33 + 3m m + 50 m m
L28~L30 + 3m m + 50 m m
L25~L27 + 3m m + 45 m m
L22~L24 + 3m m + 40 m m
L19~L21 + 3m m + 35 m m
L16~L18 + 3m m + 30 m m
L13~L15 + 3m m + 25 m m
L10~L12 + 3m m + 20 m m
L7~L9 + 3m m + 15 m m
L4~L6 + 3m m + 10 m m
B6~L3 + 3m m + 5m mB06
L01
L40
L20
L10
L30
L50
L60
L70
L80
L90
L100
L110
L120
TOP
2nd O/R
1 st O/R
Lantern
1 st B/T
2nd B/T
Floor Core Column
L106-L123 Design level+1mm Steel columns
L76-L105 Design level+2mm Steel columns
L72-L75 Design level+2mm Core level+25mm
L69-L71 Design level+2mm Core level+30mm
L66-L68 Design level+2mm Core level+35mm
L63-L65 Design level+2mm Core level+40mm
L60-L62 Design level+2mm Core level+45mm
L57-L59 Design level+2mm Core level+50mm
L37-L56 Design level+3mm Core level+55mmL54-L56 Core level+60mm
L34-L36 Design level+3mm Core level+55mm
L31-L33 Design level+3mm Core level+50mm
L28-L30 Design level+3mm Core level+50mm
L25-L27 Design level+3mm Core level+45mm
L22-L24 Design level+3mm Core level+40mm
L19-L21 Design level+3mm Core level+35mm
L16-L18 Design level+3mm Core level+30mm
L13-L15 Design level+3mm Core level+25mm
L10-L12 Design level+3mm Core level+20mm
L7-L9 Design level+3mm Core level+15mm
L4-L6 Design level+3mm Core level+10mm
B6-L3 Design level+3mm Core level+5mm
C Material Testing
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
28/39
27
CColumn-Shortening
Loading of Specimens
Material TestingMatertial Testing ( Construction Materials, Chungnam National University Engineering Laboratory)
Specimenscreated
Curing
Testing
CREEP
Strain Gauge Attachment
Strain Gauge
2 years
Drying Shrinkage Elastic Modulus
Primary Modulus test
Secondary Modulus test
Third order Modulustest
Measure
DeformationMeasure
Deformation
2 Years
Final Report
Compressive strength / modulus of elasticity / drying shrinkage / creep experiments.
Generate formulations based on the test and update the model
Need on-site materials testing according to the construction progress
to reflect Site Conditions at a given time
Compressive strength of 80, 70, 60MPa concrete.
Chungnam National Laboratory (Period: 2011.01 ~2013.01)
C Material Testing
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
29/39
28
CColumn-Shortening
0
2
4
6
8
10
12
14
16
18
20 30 40 50 60 70 80 90 100 110 120
( x 1 0 3
)
28
(PCA)
Measured vs Analytical
1) The case of a pre-interpretation(Analysis) is proceed based on assumptions about the
processes, materials, and environmental.
Safety review reflected as a result of conservative
Pre-analysis results reflect only the correction due to usability degradation concerns
2) Therefore, material test/ measurement / analysis step are suggested to perfome
shorten process of project
3) In the step of Construction, compensated during construction and verification neededthrough service company
ShorteningFactor Property
Loading
Environment Elastic Modulus /Concrete Strength Water Cement ratio Aggregate Characteristics Degrees of Compaction
Schedule change Design load vs Construction load Construction error Differential settlement in foundation
Temperature Relative humidity
(30~40%)
(15~25%)(30~40%)
Error minimization through material testingperformed
Measurement/Analysis in the future througherror correction
C Vertical Shortening Measurement
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
30/39
29
CColumn-Shortening
g
0.0E+00
5.0E-05
1.0E-04
1.5E-04
2.0E-04
2.5E-04
3.0E-04
3.5E-04
4.0E-04
4.5E-04
5.0E-04
0 50 100 150 200 250 300 350 400 450 500 550Date
S t r a i n
Back Analysis Output(TA1-20F-02)
Stain Gauge Output(TA1-20F-02)
Analysis Measurement
Reflection of physical properties in calculation frommaterial experiment:
Youngs Modulus, Poissons Ratio, MeanCompressive strength, Volume to Surface ratio,Shapes, sizes etc.
Reflection of effects of Climate on shortening: Average Temperature , RH etc.
Construction Sequence:Stage duration, Additional Steps, Member Age, Load activation age, Boundary activation age etc.
Reflection of the above effects on site master-schedule
Installation of sensors or gages in members for determining the actual shortening.
Understanding and noting the following:Curing procedure / Temperature,
Actual Shortening,Change in Ambient Temperature (Important),
Actual Humidity,Deviation from Defined Construction Stages,
Manipulation of factors in analytical Calculation,Re- Analysis
Deferent between analysis value and measurement value
Deferent between analysis value and measurement
C Vertical Shortening Measurement
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
31/39
30
CColumn-Shortening
g
B06
L01
L38
L18
L10
L28
L50
L60
L70
L76
L90
B03
Foundation settlement
400 gauges
(30~60 per floor)
ABOVEFIRESHUTTER ABOVE ABOVEFIRESHUTTER ABOVE
: Mega Column
: External Core
: Internal Core
Gauges Location in Plan
Gauges Location of settlement
: Pressure cell
: Level surveying
: Strain Gauge
: B006~L070
A
A-A
: B006~L050
A
C Structural Safety Review
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
32/39
31
CColumn-Shortening
y
additional stress due to differential shorteningbetween core and column
Reinforcement counter measure by stress exceed
Provides reinforcement due to stress exceed Provide outrigger delay joint provide optimal days if delay Joint require
Effect & Countermeasure due to shortening
1 st Outrigger (L39~L43)
Steel Outrigger Delay Joint
Steel Outrigger Adjustment Joint
(Securing safety under construction)
Outrigger Structural Safety issues and alternatives proposed
2nd
Outrigger (L72~L75)
Additional Stress4700 kN
Additional Stress3660 kN
C Structural Safety Review
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
33/39
32
CColumn-Shortening
additional stress due to differential shorteningbetween core and column
Reinforcement countermeasure by stress exceed
provide Detail of reinforcement in each area
Effect & Countermeasure due to shortening
L
Additional Force induced by differential shortening
Slabs additional stress check
STORY 26F~35F
2-HD19
2-HD19
2-HD19
1-HD19
3-HD19
2-HD19
Reinforcement
Example of reinforcement due to additional force
Tower Slab Structural Safety issues and alternatives proposed
Connecting member
Core WallColumn
DifferentialShortening
C Structural Safety Review
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
34/39
33
CColumn-Shortening
Lower Levels Structural Safety issues and alternatives proposed
Moment & Shear force due to phase difference
Phase difference=Diff. shortening + Foundation Dif. settlements- Diff. shortening : difference between columns & podium
- Dif. settlements : difference between podium & foundation
Additional force due to phase difference
Alternative- Structural reinforcement & Control Joint- Settlement Joint
Effect & Countermeasure due to shortening
a
b
t
Control Joint
a + b 1/5 to 1/4 t
BEAM &
GIRDER
Jack Support
Settlement Joint
Detail of Control Joint
Detail of reinforcement
Reinforcement for moment
The Side of Podium The Side of Tower
The Side of Podium
The Side of Tower
C Structural Safety Review
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
35/39
34
CColumn-Shortening
Curtain Wall Correction
To prevent damage / elimination of curtain wall due to
differential shortening among columns
To prevent damage / elimination of curtain wall due to Stack
Joint
Effect & Countermeasure due to shortening
JointControl
Thermalexpansion
ElasticShortening
InelasticShortening
HORIZONTAL SECTION DETAIL HORIZONTAL SECTION DETAIL(STACK JOINT)
Curtain Wall Stack Joint Plan
Required Stack Joint plan considering vertical shortening value
C Structural Safety Review
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
36/39
35
CColumn-Shortening
Partition Wall Correction
1.0B SOLID BRICK
1.0B SOLID BRICK
T18 MORTAR
T18 MORTAR
THK10 VIBRATIONPROF RUBBER
FIRE SEALANT
Masonry Type Partition Panel Type
: Location of target partition
Column Core
PARTITION
Crack
Column Core
PARTITION
timeelapsed
C Structural Safety Review
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
37/39
36
CColumn-Shortening
Correction for Vertical Piping
Review vertical piping deformation Appropriate deformation absorbing joint details and location
suggests
Review Reverse Inclination due to deferential settlement
Shortening impact and solutions
Expansion Joint
v1
: v = ( v1 + v2 + v3 )
h
v2
v3
Joint: h
vertical pipings joint
< Alternative against deformation >
C Structural Safety Review
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
38/39
37
CColumn-Shortening
Elevator Equipment calibration
Drop of clip position due to Core collapse
Deformation of the elevator rails due to Core collapse
Rails the lower part of the bumper beam
Review in Buffer section require for the lower bumper beam
of rails
Shortening impact and solutions
Derail rail clips due to shortening
Decrease supporting capacity of guide rail
Sliding Clip derailed
Securing 5mm free spacein every floor
Cl
-
7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study
39/39
38
CColumn-Shortening
+82 -31 -789 -4206
Email : [email protected]
ContactUs