Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

download Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

of 39

Transcript of Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    1/39

    0

    CColumn-

    Shortening

    Vertical Shortening &Structural Health

    Monitoring of

    Lotte World Tower 3rd April 2013

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    2/39

    1

    CColumn-

    Shortening

    Contents

    I. Introduction

    II. Vertical Shortening of Lotte World Tower

    III. Structural Health Monitoring of Lotte World Tower

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    3/39

    2

    CColumn-

    Shortening

    Contents

    I. IntroductionII. Vertical Shortening of Lotte World Tower

    III. Structural Health Monitoring of Lotte World Tower

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    4/39

    3

    CColumn-

    Shortening

    Construction Stage Analysis

    Why Construction Stage Analysis

    In general structures are analyzed assuming that the structure is built and loaded in a moment.

    Construction of structures is a time taking process and during this period Material Properties, Loads and

    Boundaries conditions may change.

    Construction Sequence

    Self weight of slab

    Other Dead Loads (Partions, Finishes)

    Completed Structure

    Dead Load + Live Load

    Wind

    Earthquake

    LL,WL,EQActs

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    5/39

    4

    CColumn-

    Shortening

    Construction Stage Analysis

    Why Construction Stage Analysis

    In general structures are analyzed assuming that the structure is built and loaded in a moment.

    Construction of structures is a time taking process and during this period Material Properties, Loads and

    Boundaries conditions may change.

    End Moment of Girder by Stories (Wall Connection)

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    6/39

    5

    CColumn-

    Shortening

    Column Shortening & Related Issues

    The behavior of concrete structures are typically determined using Linear elastic analysis and/or summation of vertical column loads.

    With the increase in building height the actual behavior of the structure increasingly diverges from the results of such conventional analysis.

    Long-term, time-dependent deformations in response to the construction sequence, creep and shrinkage canredistribute the forces and gravity induced side sway that would not be detected by conventional methods.

    When the time dependent effects of construction, creep, shrinkage, variation of concrete stiffness with time,sequential loading are not considered the predicted forces and deflections may be inaccurate.

    With increased height of structures the effect of column shortening (Elastic & Inelastic) take on added significanceand need special consideration in design and construction.

    The strains in the columns of low as well as ultra-high rise buildings are similar if the stress levels are similar;however, the overall column shortening is cumulative and depends upon the height of the structure.

    Elastic Shortening of 80 Storey Steel Structure ~ 180 mm to 255 mm.

    Elastic Shortening of 80 Storey Concrete Structure ~ 65 mm.

    Total Shortening of 80 Storey Concrete Structure ~ 180 to 230 mm.

    Inelastic Shortening ~ 1 to 3 times Elastic shortening.

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    7/39

    6

    CColumn-

    Shortening

    Column Shortening & Related Issues

    Steel Structures

    - Linear elastic Behavior

    Stress StrainStrain is constant for a given Stressduring loading & unloading

    E = ( / )

    L = (PL/A E)

    Concrete Structures- Nonlinear Inelastic Behavior

    - But in general Analysis and design behavior of concrete is treated as linear elastic material

    Neither Stress StrainNor Strain is constant for a given StressDuring loading & unloading

    Elastic Strain + Inelastic Strain

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    8/39

    7

    CColumn-

    Shortening

    Column Shortening & Related Issues

    Concrete Structures

    Elastic Shortening

    Modulus of Elasticity changes with time .

    E i = ( / )

    L = (PL/A E i)

    Inelastic Shortening

    Creep Shortening.Shrinkage Shortening.

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    9/39

    8

    CColumn-

    Shortening

    Effects of Column Shortening

    Absolute shortening is rarely of practical interest.

    Differential shortening between adjacent vertical elements is the most important factor for engineer.

    Axial Shortening of vertical elements will not effect those elements very much, horizontal elements like beams and slabs and non

    structural elements are affected.

    Slabs may not be truly horizontal after some time.

    Beams could be subjected to higher bending moments.Load transfer.

    Structural Effects

    Cracks in Partition Walls.Cracks in StaircasesDeformation of Cladding.

    Mechanical Equipment. Architectural Finishes.Built in Furnishings.

    Non Structural Effects

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    10/39

    9

    CColumn-

    Shortening

    Effects of Column Shortening

    Deformation and breakage of Facades, windows &Parapet walls

    Reverse Inclination of Drainage Piping System

    Deformation of Vertical Piping System Deformation and breakage of internal partitions

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    11/39

    10

    CColumn-

    Shortening

    Procedure for Accounting

    Two basic prerequisites for accurately and efficiently predicting these effectsare

    Reliable Data for the creep and shrinkage characteristics of the particular concrete mix Analytical procedures for the inclusion of these time effects in the design of structure.

    Some of the popular predictive methods for predicting creep and shrinkage

    strains are

    ACI 209 -92Bazant Bewaja B3CEB FIP (1978, 1990)PCA Method (Mark Fintel, S.K.Ghosh & Hal Iyengar)

    GL 2000 (Gardner and Lockman)Eurocode

    C

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    12/39

    11

    CColumn-

    Shortening

    Procedure for Accounting

    C

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    13/39

    12

    CColumn-

    Shortening

    Procedure for Accounting

    0.0E+00

    5.0E-05

    1.0E-04

    1.5E-04

    2.0E-04

    2.5E-04

    3.0E-04

    3.5E-04

    4.0E-04

    4.5E-04

    5.0E-04

    0 50 100 150 200 250 300 350 400 450 500 550Date

    S t r a i n

    Back Analysis Output(TA1-20F-02)

    Stain Gauge Output(TA1-20F-02)

    Reflection of physical properties in calculation frommaterial experiment:

    Youngs Modulus, Poissons Ratio, MeanCompressive strength, Volume to Surface ratio,Shapes, sizes etc.

    Reflection of effects of Climate on shortening: Average Temperature , RH etc.

    Construction Sequence:

    Stage duration, Additional Steps, Member Age, Load activation age, Boundary activation age etc.

    Reflection of the above effects on site master-schedule

    Installation of sensors or gages in members for determining the actual shortening.

    Understanding and noting the following:Curing procedure / Temperature,

    Actual Shortening,Change in Ambient Temperature (Important),

    Actual Humidity,Deviation from Defined Construction Stages,

    Manipulation of factors in analytical Calculation,Re- Analysis

    Deferent between analysis v alue and measurement

    Analytical Measurement Experimental Measurement

    Using Software or Manually(Manual calculation is almost impossible) Field Measurements

    C

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    14/39

    13

    CColumn-

    Shortening

    Procedure for Accounting

    Field Measurements

    Determination of Installation location Installation of Gauge After Installation

    After Installation of Gauge After Casting of Concrete Field data collection

    C

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    15/39

    14

    CColumn-

    Shortening

    Compensation at Site

    Pre-slab installation shortenings

    Shortenings taking place up to the time of slab installation

    Post-slab installation shortenings

    Shortenings taking place after the time of slab installation

    :Compensation

    : Design Level

    : Pre-slab Installation shortening

    : Post-slab Installation shortening

    Reinforced Concrete Structure

    Pre-slab installation shortenings has no importance

    Compensation by leveling the forms

    Post-slab installation shortenings due to subsequent loads and creep/shrinkage

    Steel Structure

    Columns are fabricated to exact length.

    Attachments to support the slabs

    Pre-slab installation shortenings need to be known.

    Compensation for the summation of Pre-installation and Post-installation shortenings

    C

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    16/39

    15

    CColumn-

    Shortening

    Compensation at Site

    ColumnColumn

    1 st correction

    2nd correction

    1st correction

    C

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    17/39

    16

    CColumn-Shortening

    Compensation at Site

    SLAB THK.

    B (= Height ofcorrection

    filler

    Height of correction

    Column Rebar

    CON'C Casting face The order of construction

    installation of column forms

    insertion of FILLER

    insertion of correcting FILLER

    Installation of SLAB forms

    securing the thickness of slab.

    C

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    18/39

    17

    CColumn-Shortening Contents

    I. Introduction

    II. Vertical Shortening of Lotte World Tower

    III. Structural Health Monitoring of Lotte World Tower

    C O i

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    19/39

    18

    CColumn-Shortening

    Overview

    C O i

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    20/39

    19

    CColumn-Shortening

    Overview

    Location Jamsil, Seoul, South Korea.

    Height Roof 554.6 m; Antenna Spire 556 m

    No. of Floors 123

    Floor Area 304,081 m 2

    Function / Usage Office, Residential, Hotel, Observation Deck

    Structure Type Reinforced Concrete + Steel

    Lateral load resisting system Core Wall + Outrigger Truss + Belt Truss

    Foundation Type Mat Foundation

    Construction Period March 2011 ~ 2015

    Lotte World Tower

    C Overview

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    21/39

    20

    CColumn-Shortening

    Overview

    Location Jamsil, Seoul, South Korea.

    Height Roof 554.6 m; Antenna Spire 556 m

    No. of Floors 123

    Floor Area 304,081 m 2

    Function / Usage Office, Residential, Hotel, Observation Deck

    Structure Type Reinforced Concrete + Steel

    Lateral load resisting system Core Wall + Outrigger Truss + Belt Truss

    Foundation Type Mat Foundation

    Construction Period March 2011 ~ 2015

    Lotte World Tower

    C Overview

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    22/39

    21

    CColumn-Shortening

    Overview

    1 1

    2

    Initial Curing

    Concrete Structures deformation = = Elastic Strain 1 + Inelastic Strain 2

    Inelastic Shortening ~ 1 to 3 times Elastic shortening.

    Conc

    Vertical

    Member

    Pre-slab Installation shortening

    Core wall Column

    CoreShortening Column

    Shortening

    < Deferential Deformation >

    Deferential Shortening

    General Height 555m / 123 floors

    Tower Deformati

    on

    Deformation of the tower is a naturally occurring depending on material, constructionmethod

    Vertical Deformation:Vertical Shortening / Settlement / Construction Errors

    Horizontal Deformation:Differential Shortening / SettlementUneven load due to construction method

    Asymmetric floor plan / Construction errors

    Horizontal Deformation

    VerticalDeformation

    WithTime

    C Vertical Shortening and Related Issue

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    23/39

    22

    CColumn-Shortening

    Vertical Shortening and Related Issue

    High-rise Considerations

    Wind Induced

    acceleration control

    Optimum StructureSystem

    Construction Jointmanagement

    Lateral-Displacement

    control

    Concrete PumpingTechnology

    Health Monitoring

    ShorteningPredictionTechnology

    High performanceConcrete Spalling

    Structural safety aspects Usability aspects

    Cost increase due to Mega columns,outrigger additional stress

    Safety concerns, accordingto the tilt of the tower

    Absence of a connectionbetween tower and parking lotcause safety issue

    Deformation of Material occursdue to Additional stress

    Safety problems of unequal deformationcaused by the slab structure at the hotelarea

    Elevators safety due to towers tilt

    Curtain wall and exterior materialsdeformation and failure occurs

    Deformation of Vertical pipingand breakage problems

    Reverse Inclination of Drainage Piping System

    Inconvenience to residents mayoccurs due to the slope of the slab

    Defection problem due tobreakage of finishes

    Deformation of VerticalPiping System

    Elevators safety due totowers tiltAdditional Stress of Outrigger

    C ShorteningReviewProcess

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    24/39

    23

    CColumn-Shortening

    Shortening Review Process

    Preliminary Analysis

    Material / Section Properties

    Applied Load, Schedule

    Main analysis

    Updating material properties from experiments

    Construction sequence considering the fieldcondition

    1st, 2nd, 3rd Re-Analysis

    Suggestion of compensation and details for non-constructed part of structure

    Final Report

    Shortening, result from test, measurement Review

    Material Experiment

    Compressive strength

    Modulus of elasticity

    Creep & Shrinkage

    Measurement

    Measurement of strain for Column & Wall

    Design with AdditionalForce

    ApplyingCompensation to in-situ

    structure

    Design

    Const-ruction

    0.0E+00

    1.0E-04

    2.0E-04

    3.0E-04

    4.0E-04

    0 5 0 1 00 1 50 2 00 2 50 3 00 3 50

    S t r a

    i n

    Day

    Back Analysis Output (103-1F-01)

    Strain GaugeOutput(103-1F-01)

    C Pre-Analysis - Deformations

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    25/39

    24

    CColumn-Shortening

    Pre-Analysis - Deformations

    Vertical deformation

    Deferential Shortening

    Horizontal deformation

    Differential settlement

    Deferential shortening btw Core & Column

    Steel column: Max 18mm

    Mega column: Max 65mm

    Top of tower Steel Frame: 368.7 mm Core wall: 314.0 mm

    Top of mega column

    Mega Col: 297.8 mm Core wall: 241.3 mm

    ABOVEFIRESHUTTER

    ABOVE ABOVEFIRESHUTTER

    ABOVE

    X-Dir

    Y - D i r

    OW1OW2

    OW9OW8

    O W 1 1

    O W 1 2

    OW10

    OW3OW4

    O W 5

    O W 6

    O W 7

    O W 1 0

    O W 1

    O W 4

    OW7

    Pridiction

    X dir: 27.2mmY dir: 115.5mm

    Safety check

    Elevators rails

    Vertical Pipes

    X

    Y

    MEGACOL. CORE WALL

    FOUNDATION

    MEGACOL.

    MEGACOL. CORE WALL

    FOUNDATION

    MEGACOL.

    Core wall settlement: 35mmColumn settlement: 16mm

    Core wall Column

    CoreShortening

    ColumnShortening

    DeferentialShortening

    Lantern & Core

    C Pre-Analysis - Stresses

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    26/39

    25

    CColumn-Shortening

    Pre Analysis Stresses

    Outriggers additional stressSlabs additional stress

    Podiums additional stress

    Differential Deformation btw Slab-Column

    Slab has additional stress

    Additional stress btwtower & podium

    Max 100 ton.m

    Require SettlementJoint & Safety check

    Additional Stress without Delay Joint

    1 st outrigger (L39~L43): 3,600 ton s 2nd outrigger (L72~L75): 4,700 ton s

    required a delay joint installation

    Additional Stress with Delay Joint

    1 st outrigger (L39~L43): 1,700 ton s

    2nd outrigger (L72~L75): 2,000 ton s

    PodiumTower

    connection

    L87~L103

    L72~L75

    L39~L43

    B06~B01

    C Pre-Analysis Compensation

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    27/39

    26

    CColumn-Shortening

    Pre Analysis Compensation- Core wall: Absolute correction for securing design level

    - Column: Relative correction for deferential shortening

    Relative correction between core and column

    correction due to measurement

    pre-Analysis

    Analysis

    Re-analysis1~6 times

    MaterialTest

    Measurement

    1 st correction

    2nd correction

    Additionalcorrection for unconstructed

    L106~L123 + 1m m

    L76~L105 + 2m m

    L72~L75 +3m m +2 5m m 2nd O /R

    L69~L71 + 3m m + 30 m m

    L66~L68 + 3m m + 35 m m

    L63~L65 + 2m m + 40 m m

    L60~L62 + 2m m + 45 m m

    L57~L59 + 2m m + 50 m m

    L54~L56 + 3m m + 55 m m

    L37~L53 +3 m m +6 0m m 1st O /R

    L34~L36 + 3m m + 55 m m

    L31~L33 + 3m m + 50 m m

    L28~L30 + 3m m + 50 m m

    L25~L27 + 3m m + 45 m m

    L22~L24 + 3m m + 40 m m

    L19~L21 + 3m m + 35 m m

    L16~L18 + 3m m + 30 m m

    L13~L15 + 3m m + 25 m m

    L10~L12 + 3m m + 20 m m

    L7~L9 + 3m m + 15 m m

    L4~L6 + 3m m + 10 m m

    B6~L3 + 3m m + 5m mB06

    L01

    L40

    L20

    L10

    L30

    L50

    L60

    L70

    L80

    L90

    L100

    L110

    L120

    TOP

    2nd O/R

    1 st O/R

    Lantern

    1 st B/T

    2nd B/T

    Floor Core Column

    L106-L123 Design level+1mm Steel columns

    L76-L105 Design level+2mm Steel columns

    L72-L75 Design level+2mm Core level+25mm

    L69-L71 Design level+2mm Core level+30mm

    L66-L68 Design level+2mm Core level+35mm

    L63-L65 Design level+2mm Core level+40mm

    L60-L62 Design level+2mm Core level+45mm

    L57-L59 Design level+2mm Core level+50mm

    L37-L56 Design level+3mm Core level+55mmL54-L56 Core level+60mm

    L34-L36 Design level+3mm Core level+55mm

    L31-L33 Design level+3mm Core level+50mm

    L28-L30 Design level+3mm Core level+50mm

    L25-L27 Design level+3mm Core level+45mm

    L22-L24 Design level+3mm Core level+40mm

    L19-L21 Design level+3mm Core level+35mm

    L16-L18 Design level+3mm Core level+30mm

    L13-L15 Design level+3mm Core level+25mm

    L10-L12 Design level+3mm Core level+20mm

    L7-L9 Design level+3mm Core level+15mm

    L4-L6 Design level+3mm Core level+10mm

    B6-L3 Design level+3mm Core level+5mm

    C Material Testing

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    28/39

    27

    CColumn-Shortening

    Loading of Specimens

    Material TestingMatertial Testing ( Construction Materials, Chungnam National University Engineering Laboratory)

    Specimenscreated

    Curing

    Testing

    CREEP

    Strain Gauge Attachment

    Strain Gauge

    2 years

    Drying Shrinkage Elastic Modulus

    Primary Modulus test

    Secondary Modulus test

    Third order Modulustest

    Measure

    DeformationMeasure

    Deformation

    2 Years

    Final Report

    Compressive strength / modulus of elasticity / drying shrinkage / creep experiments.

    Generate formulations based on the test and update the model

    Need on-site materials testing according to the construction progress

    to reflect Site Conditions at a given time

    Compressive strength of 80, 70, 60MPa concrete.

    Chungnam National Laboratory (Period: 2011.01 ~2013.01)

    C Material Testing

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    29/39

    28

    CColumn-Shortening

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    20 30 40 50 60 70 80 90 100 110 120

    ( x 1 0 3

    )

    28

    (PCA)

    Measured vs Analytical

    1) The case of a pre-interpretation(Analysis) is proceed based on assumptions about the

    processes, materials, and environmental.

    Safety review reflected as a result of conservative

    Pre-analysis results reflect only the correction due to usability degradation concerns

    2) Therefore, material test/ measurement / analysis step are suggested to perfome

    shorten process of project

    3) In the step of Construction, compensated during construction and verification neededthrough service company

    ShorteningFactor Property

    Loading

    Environment Elastic Modulus /Concrete Strength Water Cement ratio Aggregate Characteristics Degrees of Compaction

    Schedule change Design load vs Construction load Construction error Differential settlement in foundation

    Temperature Relative humidity

    (30~40%)

    (15~25%)(30~40%)

    Error minimization through material testingperformed

    Measurement/Analysis in the future througherror correction

    C Vertical Shortening Measurement

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    30/39

    29

    CColumn-Shortening

    g

    0.0E+00

    5.0E-05

    1.0E-04

    1.5E-04

    2.0E-04

    2.5E-04

    3.0E-04

    3.5E-04

    4.0E-04

    4.5E-04

    5.0E-04

    0 50 100 150 200 250 300 350 400 450 500 550Date

    S t r a i n

    Back Analysis Output(TA1-20F-02)

    Stain Gauge Output(TA1-20F-02)

    Analysis Measurement

    Reflection of physical properties in calculation frommaterial experiment:

    Youngs Modulus, Poissons Ratio, MeanCompressive strength, Volume to Surface ratio,Shapes, sizes etc.

    Reflection of effects of Climate on shortening: Average Temperature , RH etc.

    Construction Sequence:Stage duration, Additional Steps, Member Age, Load activation age, Boundary activation age etc.

    Reflection of the above effects on site master-schedule

    Installation of sensors or gages in members for determining the actual shortening.

    Understanding and noting the following:Curing procedure / Temperature,

    Actual Shortening,Change in Ambient Temperature (Important),

    Actual Humidity,Deviation from Defined Construction Stages,

    Manipulation of factors in analytical Calculation,Re- Analysis

    Deferent between analysis value and measurement value

    Deferent between analysis value and measurement

    C Vertical Shortening Measurement

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    31/39

    30

    CColumn-Shortening

    g

    B06

    L01

    L38

    L18

    L10

    L28

    L50

    L60

    L70

    L76

    L90

    B03

    Foundation settlement

    400 gauges

    (30~60 per floor)

    ABOVEFIRESHUTTER ABOVE ABOVEFIRESHUTTER ABOVE

    : Mega Column

    : External Core

    : Internal Core

    Gauges Location in Plan

    Gauges Location of settlement

    : Pressure cell

    : Level surveying

    : Strain Gauge

    : B006~L070

    A

    A-A

    : B006~L050

    A

    C Structural Safety Review

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    32/39

    31

    CColumn-Shortening

    y

    additional stress due to differential shorteningbetween core and column

    Reinforcement counter measure by stress exceed

    Provides reinforcement due to stress exceed Provide outrigger delay joint provide optimal days if delay Joint require

    Effect & Countermeasure due to shortening

    1 st Outrigger (L39~L43)

    Steel Outrigger Delay Joint

    Steel Outrigger Adjustment Joint

    (Securing safety under construction)

    Outrigger Structural Safety issues and alternatives proposed

    2nd

    Outrigger (L72~L75)

    Additional Stress4700 kN

    Additional Stress3660 kN

    C Structural Safety Review

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    33/39

    32

    CColumn-Shortening

    additional stress due to differential shorteningbetween core and column

    Reinforcement countermeasure by stress exceed

    provide Detail of reinforcement in each area

    Effect & Countermeasure due to shortening

    L

    Additional Force induced by differential shortening

    Slabs additional stress check

    STORY 26F~35F

    2-HD19

    2-HD19

    2-HD19

    1-HD19

    3-HD19

    2-HD19

    Reinforcement

    Example of reinforcement due to additional force

    Tower Slab Structural Safety issues and alternatives proposed

    Connecting member

    Core WallColumn

    DifferentialShortening

    C Structural Safety Review

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    34/39

    33

    CColumn-Shortening

    Lower Levels Structural Safety issues and alternatives proposed

    Moment & Shear force due to phase difference

    Phase difference=Diff. shortening + Foundation Dif. settlements- Diff. shortening : difference between columns & podium

    - Dif. settlements : difference between podium & foundation

    Additional force due to phase difference

    Alternative- Structural reinforcement & Control Joint- Settlement Joint

    Effect & Countermeasure due to shortening

    a

    b

    t

    Control Joint

    a + b 1/5 to 1/4 t

    BEAM &

    GIRDER

    Jack Support

    Settlement Joint

    Detail of Control Joint

    Detail of reinforcement

    Reinforcement for moment

    The Side of Podium The Side of Tower

    The Side of Podium

    The Side of Tower

    C Structural Safety Review

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    35/39

    34

    CColumn-Shortening

    Curtain Wall Correction

    To prevent damage / elimination of curtain wall due to

    differential shortening among columns

    To prevent damage / elimination of curtain wall due to Stack

    Joint

    Effect & Countermeasure due to shortening

    JointControl

    Thermalexpansion

    ElasticShortening

    InelasticShortening

    HORIZONTAL SECTION DETAIL HORIZONTAL SECTION DETAIL(STACK JOINT)

    Curtain Wall Stack Joint Plan

    Required Stack Joint plan considering vertical shortening value

    C Structural Safety Review

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    36/39

    35

    CColumn-Shortening

    Partition Wall Correction

    1.0B SOLID BRICK

    1.0B SOLID BRICK

    T18 MORTAR

    T18 MORTAR

    THK10 VIBRATIONPROF RUBBER

    FIRE SEALANT

    Masonry Type Partition Panel Type

    : Location of target partition

    Column Core

    PARTITION

    Crack

    Column Core

    PARTITION

    timeelapsed

    C Structural Safety Review

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    37/39

    36

    CColumn-Shortening

    Correction for Vertical Piping

    Review vertical piping deformation Appropriate deformation absorbing joint details and location

    suggests

    Review Reverse Inclination due to deferential settlement

    Shortening impact and solutions

    Expansion Joint

    v1

    : v = ( v1 + v2 + v3 )

    h

    v2

    v3

    Joint: h

    vertical pipings joint

    < Alternative against deformation >

    C Structural Safety Review

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    38/39

    37

    CColumn-Shortening

    Elevator Equipment calibration

    Drop of clip position due to Core collapse

    Deformation of the elevator rails due to Core collapse

    Rails the lower part of the bumper beam

    Review in Buffer section require for the lower bumper beam

    of rails

    Shortening impact and solutions

    Derail rail clips due to shortening

    Decrease supporting capacity of guide rail

    Sliding Clip derailed

    Securing 5mm free spacein every floor

    Cl

  • 7/28/2019 Vertical Shortening and Health Monitoring of Lotte World TowerCase Study

    39/39

    38

    CColumn-Shortening

    +82 -31 -789 -4206

    Email : [email protected]

    ContactUs