Verona Road (US 18/151) Project - 511 WI Projects · 17.05.2012 · Project Area Stage 3 - When...
Transcript of Verona Road (US 18/151) Project - 511 WI Projects · 17.05.2012 · Project Area Stage 3 - When...
-
Verona Road (US 18/151) Project
Public Informational Meeting May 17, 2012
-
US 18/151 (Verona Road) Project
County PD to Seminole Highway Dane County
-
Project Area
Stage 2 • Verona Road from County
PD to Raymond Road • County PD between
Hardrock Road and Commerce Park Drive
Raymond Rd
County PD
Williamsburg Way
Beltline
Stage 1 • Verona Road between
Raymond Road and Nakoma Road
• Beltline between Whitney Way and Seminole Highway
NORTH
-
Project Area
Stage 3 - When Needed (2031 or Later) • Freeflow interchange with directional
ramps to the east • Freeway conversion of US 151 • One-way pair local road system • Freeway will travel within the median
and below the frontage roads
Williamsburg Way Grade Separated
County PD
Raymond Road
Frontage Road Associated with Stage 3
One‐way Pair Local Frontage Roads
Ramps
Ramps
-
Why Improve Verona Road? Congestion: Significant traffic backups and delay on the Beltline and Verona Road occur daily.
•
•I 39/90 ‐
The number of vehicles that want to use the Verona Road interchange is comparable to the highest interchanges in the Madison Area – Even the interstate interchanges.
The existing interchange was not designed to handle these volumes.
-
Why Improve Verona Road? Safety
2005 to 2009 Data The Beltline Section east of Verona Road has: • Total crash rate that is 2.5 to 3.3 times the state average (depending on direction).
• Injury crash rate of 2.3 to 4.1 times the state average (depending on direction).
-
Why Improve Verona Road? Pavement and Bridge Needs
Substandard Height
Deteriorating Pavement
• Bridge Constructed in 1957 • Only Bridge on West Beltline Not Reconstructed/Widened
-
Stage 1 Features Third Lane Westbound Will drop at Gammon Road Exit
Third Lane Eastbound Will Start at Whitney Way
Noise Wall
Noise Walls
Noise Walls
New Beltline Bridge 6 feet Higher to Improve Clearance
Seminole Highway Bridge Replaced with Improved Clearance
-
Single Point Urban Interchange (SPUI)
NORTH
SE Noise Wall
NE Noise Wall to Seminole HighwayNew Pedestrian
Underpass
Stage 1 Features
-
Single Point Urban Interchange (SPUI) 3 Major Movements
NORTH
-
Single Point Urban Interchange (SPUI) Left Turns From Beltline to Verona Road
NORTH
-
Single Point Urban Interchange (SPUI) Left Turns From Verona Road to Beltline
NORTH
-
Single Point Urban Interchange (SPUI) Verona Road Through Movements
NORTH
-
Stage 1 Features Single Point Urban Interchange (SPUI)
Looking East
EB On‐RampNB Verona Rd.
-
Stage 1 Features
Summit Road/Roundabout Jug‐Handle
NORTH
Sidewalks (Typ.)
Bike Lanes (Typ.)
Verona Road bridges over Roundabout
Avalon Village
Walgreens
U-Haul
Harbor Freight
Proposed Storm Water Basin
-
Stage 1 Features
Summit Road/Roundabout Jug‐Handle
-
Stage 1 Features
Summit Road/Roundabout Jug‐Handle
-
Stage 1 Features Pedestrian Overpass near Whenona Way
• Replaces Existing Pedestrian Overpass
WB Beltline EB Beltline Frontage Road
14 Feet Structure East of the Interchange
• Coordinated with Cannonball Trail Crossing of the Beltline
-
Stage 2 Features
• County PD converted to a diamond interchange. US 151 will travel
over County PD • US 151 expanded to
three lanes in each direction from County PD to just south of Raymond Road
Evaluate Intersection Alternatives
-
Stage 2 Features
County PD
NORTH
Possible ped/bike overpass/ underpass
Existing Trail Connection to Remain
US 151 Over County PD
County PD Interchange
-
FEISFEIS
Option 3
Jug HandleJug Handle
Texas UTexas U
Stage 2 Features Williamsburg Way Alternatives
FEIS
Option 1
Option 3Option 3
Jug Handle
Option 2
Texas U
This imag e canno t currently be displayed.
Option 4Option 4
Grade Separated Interchange
-
Stage 3 Features Depressed Freeway
Note: Stage 1 Single Point instead of Diamond
-
Eligible Noise Walls
• 5 Noise Walls Eligible for the Project
• Decision to implement a noise wall at a location is determined by a vote of support from benefited receptors
• Benefited receptor receives an 8 decibel reduction in sound level
• Total of 87 benefited receptors
32 Receptors
8 Receptors
22 Receptors
22 Receptors
3 Receptors
-
Maintaining Traffic Flow • Traffic Diversion Routes – 8 outlying intersections being reviewed for improvements ‐ High Priority to Success of Project
• Official Alternate Route established – potentially permanent • Incident Management Plan (Increased Enforcement and Assistance in Work Zone) • ITS features (Digital Message Signs and Interchange Cameras) installed early in
project to communicate real time information to users • Public Outreach
Alternate Route
(Press Releases and Web Site)
-
Alternate
Route
Anticipated Diversion Routes To ease congestion during construction, the following intersections will receive improvements in 2013.
1. County M and County PB: Signal and turn lane extensions proposed.
2. County M and County D (Fish Hatchery Road): Signal and turn lanes proposed.
3. County D and Whalen Road: Turn lane and bike accommodations proposed.
4. Seminole Highway and Lacy Road: Turn lane additions.
5. County PD and Seminole Highway: Eastbound left turn lane extension.
6. Seminole Highway and Sentinel Pass: Signal and turn lane extensions.
7. Whitney Way and Gilbert: Southbound left‐turn lane extension.
8. Seminole Highway, Yuma and Nakoma Drive: Signal and revised pavement marking.
-
Stakeholder Involvement WisDOT Verona Road Team coordination with: Municipalities & Advisory Committees MPO for Madison General Public Property Owners Businesses & Organizations Neighborhood Groups Dane County Stakeholders Group discussing labor opportunities
Bi‐Weekly Open Houses near corridor for continuous communication with Public
Extensive Public Communication Plan during construction focusing on: Continuous updates of traffic lane and ramp changes Tourism/Madison Events (Badger Sporting Events) Freight Local Community access Alternate routes
-
Anticipated Project Schedule
Stage 1 (2011 to 2016) Design 2011 to 2013 Right of Way Acquisition 2011 to 2013 Construction 2014 to 2016
Stage 2 (2013 to 2019) Design 2013 to 2015 Right of Way Acquisition 2015 to 2016 Construction 2017 to 2019
-
Project Contacts Verona Road Project Team
John Vesperman Mark Vesperman WisDOT Verona Road Project Chief WisDOT Verona Road Project Manager
(608) 246‐3850 (608) 246‐7548 [email protected] [email protected]
John Steiner Joe Bunker WisDOT Verona Road Project Supervisor Strand Associates ‐ Design Consultant
(608) 246‐3862 (608) 251‐4843 [email protected] [email protected]
Mary Heiser WisDOT Real Estate Specialist
(608) 242‐8037 [email protected]
For more project information visit: www.veronaroadproject.wi.gov
http:www.veronaroadproject.wi.govmailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]