Velo Ontario’s Ontario Bicycling Route Development of Regional Cycling Networks Discussion Panel...

21
Velo Ontario’s Ontario Bicycling Route Development of Regional Cycling Networks Discussion Panel Pro-Walk/Pro-Bike Conference, Victoria, British Columbia September, 7-10, 2004 Presenter: David Hunt, President Velo Ontario Alternates: Norma Moores, John van der Mark

Transcript of Velo Ontario’s Ontario Bicycling Route Development of Regional Cycling Networks Discussion Panel...

Velo Ontario’s Ontario Bicycling Route

Development of Regional Cycling NetworksDiscussion Panel

Pro-Walk/Pro-Bike Conference, Victoria, British Columbia

September, 7-10, 2004

Presenter: David Hunt, President Velo Ontario

Alternates: Norma Moores, John van der Mark

Contents

Velo Ontario

Ontario Bicycling Route

Project Rationale

Background and Approach

Activities Completed

Next Steps

Conclusion

Velo Ontario

A new voice for Ontario cyclists

Volunteer, non-profit organization

Advocating more and better cycling

Objectives:• Advocacy and lobbying• Promoting cycling education • Monitor policies and practices of government• Forum for communication and discussion• Promote cycling programs, facilities and benefits

Velo Ontario

Nine member Board

About 100 members

Key Projects:– OBR

– safe cycling improvements

– advocacy

– partnerships

– award recognition

– administration

Ontario Bicycling RouteA vision to implement an on-road cycling network across Ontario, connecting all regions, many municipalities and key points of interest

Ontario Bicycling Route

OBR Layering/Phasing - Draft

Project Rationale

– Fills cycling route gap– Encourages local cycling connections – Focus for route preservation/improvement– Interconnects with trails– Benefits safety, economy, environment, health– Supports provincial policies – Follows successful models elsewhere

Background/Approach

Initiated by Ontario Cycling Association– Route Selection Criteria– Compendium Report & Working Map– Initial Contacts

Supported by Velo Ontario in 2001– project manager – formed project teams, – work plans

Route Selection Criteria

Avoid high traffic and truck volumesOn road networkDirect as possibleAll regions connectedViable trans-provincial routesAccess:

• major geographic features • key parks• major urban centres • international boundaries

OBR on the Back Roads of Niagara

Route Selection CriteriaAvoid high traffic and truck volumesOn road networkDirect as possibleAll regions connectedViable trans-provincial routesAccess:

• major geographic features • key parks• major urban centres • international boundaries

OBR in the Niagara Peninsula

Niagara Parkway & Niagara River Recreation Trail

Niagara River at Queenston

Velo-Ontario Work Group - Provincial Cycling Route Network - Schedule

Step/Activities2001 2002

Mar. Apr. May June July Aug. Sept. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May

Management &Co-ordination

Network Verification

Mapping

Bicycle FacilityGuidelines

Signage & Name

Network Recognition& Support

Implementation &Finance

Monitor Progress

General Meetings M M M M

Velo Ontario OBR Work Group - Activity Schedule

Activities Completed– 7,500 km on-road network mapped– verification with 400 contacts– New name – Network maps – Web site www.veloontario.ca– Bicycle design guidelines – OBR route signs designed– Project profiled e.g. Toronto Bike Show

Issues

• Vast majority of respondents positive

• Municipal (4)– Safety on busy roads– Costs to pave shoulders– Low demand for cycling route facilities– Questioned benefits

• Cycling Tour Operator (1)– gettoization of cyclists on designated routes

OBR Route Sign Design

Next StepsPhase I: Marketing/Funding Package– Develop in winter 2004/05– Target road stakeholders – Other agencies

Phase II: Re-contact Stakeholders – Spring 2005– Updated information package – Request support

Next Steps

Phase III: Focus on Lake Erie– Windsor to Fort Erie (500 km)

– Higher demand and manageable route

– Great Connections

– Special effort to involve municipalities

Next Steps

Phase IV: Lake Erie Tour– Bicycle tour 2005– Promotional effort– Increase route knowledge (i.e. road test)– Build momentum for OBR

Conclusion

• Long term project

• Recognition and approvals required

• Financial and resource issues

• Dedicated Velo Ontario membership,work groups, and partners