VDD

26
MS/051211/132/NF/D, Dismantle Liebherr 132HC Page 2 of 27 CONTENTS 1.0 SEQUENCE OF WORK 2.0 APPENDIX A – CONTACTS & OPERATIVES 3.0 APPENDIX B – RISK ASSESSMENT & COSHH 4.0 APPENDIX C – STANDARD PROCEDURES 5.0 APPENDIX D – RESCUE PROCEDURES 6.0 APPENDIX G – TRANSPORT ACCESS 7.0 APPENDIX H – SKILL MATRIX 8.0 APPENDIX I - INSPECTION CHECKLIST-TOWER CRANE 9.0 APPENDIX K – COSHH ASSESSMENT 10.0 TOWER CRANE BUILD SHEET & DRAWING Van Doorn Tower Crane Consultants

description

TC

Transcript of VDD

Page 1: VDD

MS/051211/132/NF/D, Dismantle Liebherr 132HC Page 2 of 27

CONTENTS 1.0 SEQUENCE OF WORK 2.0 APPENDIX A – CONTACTS & OPERATIVES 3.0 APPENDIX B – RISK ASSESSMENT & COSHH 4.0 APPENDIX C – STANDARD PROCEDURES 5.0 APPENDIX D – RESCUE PROCEDURES 6.0 APPENDIX G – TRANSPORT ACCESS 7.0 APPENDIX H – SKILL MATRIX 8.0 APPENDIX I - INSPECTION CHECKLIST-TOWER CRANE 9.0 APPENDIX K – COSHH ASSESSMENT 10.0 TOWER CRANE BUILD SHEET & DRAWING

Van Doorn Tower Crane Consultants

Page 2: VDD

MS/051211/132/NF /D, Dismantle Liebherr 132HC Page 3 of 27

1.0 SEQUENCE OF WORK INTRODUCTION: The Liebherr 132HC tower crane shall be dismantled using a 250te mobile crane positioned as per drawing supplied by Mobile Crane Supplier. Planned date of Operation: Saturday 17th March 2012 Site Address:

Construction Contractor C/O Project Contractor Glenfield Hospital Leicester

Tower Crane Details:

Liebherr 132HC 25.8 Metres HUH 35 Metre Jib Counter Ballast – 13200Kg Tower Configuration: 1 X 10 Meter Base Tower Section 5 X 2.5 Meter Tower Sections

Mobile Crane Details: Mobile Crane Supplier Terex Demag AC250

57.7 metre main boom 96.6 te counterweight. Outrigger Footprint 8.6m x 8.5m Maximum outrigger point Load 89.025 ton 2 x - 2m x 5m x mats per outrigger Maximum distributed outrigger point load is 4.45t/m2 SWL 9.5 te @ 4 0 m radius.

Expected Duration 1 day

Note; It is the responsibility of Construction Contractor to ensure ground is suitable to handle loads imposed. Details of Transport: All tower crane components will be removed from site as detailed on the attached loading schedule. All transport drivers are to wear full PPE when exiting the vehicle within the confines of the site. There is room on site for 1 lorry at a time. Traffic Management: Please see attached site drawing and traffic management plan. Access and Egress: Access to the tower crane is via site access gate. All loads to be loaded within the exclusion zone.

Van Doorn Tower Crane Consultants

Page 3: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 4 of 27

1.0 SEQUENCE OF WORK

DETAILS OF TRANSPORT:

All tower crane components will be removed from site as detailed on the attached loading schedule. Load collection will be co-ordinated by site logistics. All loads will be timed to avoid any congestion in or around site.

NAMES OF OPERATIONAL PERSONNEL:

Supervisor: Cornelis Van Doorn Operatives‟ names: As per attached Matrix

PERSONNEL PROTECTIVE EQUIPMENT:

P.P.E to be worn at all times and used: Full body harness with Double lanyard.

Work restraint lanyard.

Polycarbonate safety helmet. Safety footwear.

High visibility vest. Gloves.

Overalls.

WEATHER FORECAST

The Maximum Wind speed for this operation is 9.8M/S.

CONTRACTOR’S RESPONSIBILITIES: (a) Access onto site. (b) 110V Supply at the base of the crane for the torque gear

(c) Power supply for the tower crane and access to the switch panel. (d) All permits for Road closure, traffic management & parking suspensions

(e) Exclusion zone and pedestrian barriers (f) Zoning off the working area to all non-essential personnel.

(g) Access, egress for mobile crane and all support vehicles (h) Ground Conditions

(i) 10m x 10m hard standing for mobile crane that can with stand imposed loads

The Site inspection indicated that the following actions were required of site to allow for the successful operation of the crane dismantle. These were discussed and agreed:

After site inspections and discussions with the relevant site management to establish the physical parameters the

dates of the operation are established and a program made to commit labour.

Other contractors working on site will be relocated away from crane operations.

Supply adequate parking for dismantle crew.

Clear area for mobile crane and ensue ground is capable of accepting the loads imposed.

Ensure power to tower crane is on and access available to switch panel available for isolation.

dismantle area to be allocated for the exclusive use of the crew during the whole period required.

Full authority for our supervisor in charge of dismantle to fulfil his obligations relating to BS7121, including

authority to control site personnel where appropriate.

First aid and all emergency services arranged by Client

Page 4: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 5 of 27

Task Method Statement

The dismantle of Liebherr 132HC tower crane will be under the direct control of Van Doorn Supervisor. Following the site induction, control measures to enable the safe dismantle of the tower crane in the exclusion zone which will be

monitored by representatives of Project Coordinator, Constructor Contractor and Van Doorn Supervisor. The dismantle of the Liebherr 132HC will be carried out as per the manufacturer‟s instructions listed in the manual. A

copy of the manual will be on site during the process. Northfield to supply manufactures manual

SEQUENCE OF WORK

Day 1 – Saturday 17th March 2012

Before commencing work introductions must be made to site management and the front page of method

statement completed and signed.

Establish an exclusion zone around the base of the tower crane and cordon off the working area of all non-essential

personnel:

All relevant paperwork is required prior to induction:

I. Certificate of conformity for the Mobile Crane II. Test certificates for all lifting accessories

III. Certification for all CPCS trained Banksman

IV. Certification for CPCS qualified appointed person V. CPCS certificate required for mobile crane driver

VI. 12 monthly examination cert for mobile crane

06.00hrs Mobile crane arrives on site and rigs in position as indicated on drawing. All team members to attend site

induction and method statement briefing. Ready for work 07.00am. Project Contractor to carry out site specific induction

1.

Extend outriggers to ½ specified rigging position on outrigger pans and pin. Set crane level and position mat/ballast transport.

Unload rigger mats and position as required. Fully extend outriggers to specified position and pin.

Offload required amount of ballast if required from transport and fit to crane and pin as per

manufacturer‟s specification. Perform 360 degree stability check, if space available.

Extend the boom to operating length as per manufacturer‟s specification. Check safe load indicator is correctly programmed and that all safety devices and limit

switches are operating correctly. Set and check operation of slew restriction

Crane is now ready for work under customer supervision, in accordance with BS7121, safe use of cranes and manufacturers specification.

Please note the rigging procedure for the Terex Demag AC250 will be carried out as per the manufactures manual and Mobile Crane Suppliermethod statement and risk assessment this will be on site during the rigging and de rigging procedures

Visual Creations
Typewritten Text
Visual Creations
Typewritten Text
Visual Creations
Typewritten Text
Visual Creations
Typewritten Text
Visual Creations
Typewritten Text
Visual Creations
Typewritten Text
Visual Creations
Typewritten Text
Visual Creations
Typewritten Text
Visual Creations
Typewritten Text
Page 5: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 6 of 27

As indicated on the attached drawing; the mobile will be placed just outside the entrance to the site. The mobile crane will be working at an approximately 40m radius from the tower crane. The mobile will be positioned in such a way to still allow the 1.2m needed for emergency access to and from the helicopter pad.

Also on the attached drawing it indicates that we plan to re-route the traffic off of the road and through the car park and at all times leaving a 3.1m gap for the vehicles. This new road will be segregated from the works

taking place using road cones and highway tape and there will be a traffic marshal there to police it at all times.

Note: The mobile crane will be fitted with aviation light due to its close proximity to the helicopter landing

pad. In the event of an emergency the hospital is to notify the Van Doorn TCC supervisor immediately so that he may stop work and make the area safe for the helicopter to land that the patient to be manoeuvred along

the designated path to the necessary hospital entrance.

Note: All materials loaded from transport must be supervised at all times by a CPCS Banksman.

All transport drivers are to wear full PPE when exiting the vehicle within the confines of the site;

2. Tower Crane to de-rig and prepare for dismantle. (I.e. remove hoist and trolley ropes).

Tower Crane electrician will remove trolley and hoist limits to enable de-

roping procedure.

The trolley is then travelled to within 2 meters of jib nose.

Using a suitable rope clamp, Clamp the rope just after the final trolley sheath.

Lower the hoist rope to give sufficient “slack rope” under jib.

Trolley out until the hoist rope anchor becomes loose. Unpin anchor from jib nose.

Travel the trolley to the inner most position lower hook block to the ground

Remove the rope clamp and anchor. Hoist the rope back through the trolley

and coil onto hoist drum.

Note: No counter weights should be removed until this procedure has been

completed

3. Using mobile crane lift Scaffpack rescue system onto cab platform and store. Using 4 leg chains slings and

shackle Remove counter ballast in 4 lifts of 2500kg & 1 lift of 1600kg.. Lower to ground and Store.

4. Using mobile crane and 4 leg chains, sling 35 meters front jib on marked points on jib. Raise slightly connect erection rope to the tie bar bracket tension erection rope and remove the tie bar pin, lower the tie bars onto

the jib and secure, disconnect the erection rope lower mobile crane off slightly and remove the bottom pins. Using tag line to control remove, lower to ground split and load (maximum weight 6.6 Tonne). Load 35 metres

of front jib on trailer numbers 1 & 2.

5. Using mobile crane load 5 x counter weights onto trailer number 3.

6. Using mobile crane and 4 leg chain slings remove hoist winch unit. Sling at the correct lifting points remove 4 pins and lower to ground and store. Maximum weight 4.15 tonne.

7. Using mobile crane and 4 leg chains sling counter jib on marked slinging points. Raise counter jib up slightly and remove tie bar pins and secure. Lower mobile crane off slightly and remove bottom pins. Using tag line to

control, lower to ground and load straight onto trailer number 3. Maximum weight 2.5 tonne.

Page 6: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 7 of 27

8. Using mobile crane and 5 tonne 1 metre endless strop remove the A Frame. Sling at the correct lifting point and loosen the 8 locating bolts, remove 4 pins and lower to the ground load straight onto trailer number 3.

9. Using mobile crane and 4 leg chains sling load the front jib tie bars hook block and trolley onto the counter jib

load 3.

10. Trailer Number 4 arrives and is loaded with hoist winch unit.

11. At this stage slew ring “squared up”. Power to tower crane is isolated and mains cable disconnected.

12. Using mobile crane and 4 leg chains sling the slew ring at the correct slinging points and remove In 1 lift of

7.4 te remove 8 tower bolts and lift to ground coil and tie the mains cable to the slewring, position in the loading area lay over and load onto trailer number 4.

13. Using mobile crane and 2 leg chains lower erection platforms to top of next section and fit.

14. Using mobile crane and 4 leg chains remove 5 x 2.5 meter tower sections in 1 x lift of 7.6te. Remove tower

bolts, lower to ground and lay over. Load straight onto trailer number 5.

15. Using mobile crane and 2 leg chain slings remove erection platforms in 2 lifts of 250kg and load straight onto trailer number 6.

16. Using mobile crane and 4 leg chains remove 10 meter base tower section in 1 x lift of 5.5te. Remove tower

bolts and, Lower to ground and lay over. Load straight onto trailer number 6.

17. Mobile crane to de-rig and leave site. Tower crane crew to clear working area and leave site.

Page 7: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 8 of 27

Specific to 250 Tonne Terex Demag AC250 Mobile Crane with 96.6 te counter ballast 57.7m main boom, outriggers Centres 8.6m x 8.5m

No. Item to be Lifted Weight Size of Load Max. radius of

load

Capacity of

crane

Method of Slinging loading and distribution of

load

Comments

1 5 x 2.5 Metre

Tower Sections

7.6te

12m x 1.7m x 1.7m

40m

9.5te

4 Leg Chain

Lay down in loading area,

Use timber to protect road

2 Slew ring

7.4te

5.7m x 2.4m x 2.4m 40m 9.5te 4 Leg Chain Lay down in loading area, Use timber to protect road

3

Hoist Winch

4.15te

3.6m x 1.9m x 1.7m

34m

11.1te

4 Leg Chain

Store in site area,

4 Counter Jib 2.5te 11m x 2.4m x 1.2m 36m 10.5te 4 Leg Chain Load Straight onto trailer Control lift with tag lines

5 Counter weights 2.5te

3m x 1.6m x 0.4m 34m 11.1te 4 Leg Chains & shackle

Store in site area,

6

Front Jib 6.6te 35m x 1.7m

24m 16.7te 4 Leg Chain & Collar Chains

Land and split in exclusion zone

Control lift with tag lines

Page 8: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 9 of 27

Lifting Plans

LOLER 1998 Regulations refer to lifting plans for lifting operations but do not detail the criteria except for tandem lifts. For our lifting operations we pre-empted this with our Slingers and Signallers Guide, which sets out the rules for basic or common lifts.

(See BS7121 Paragraph 3.3). The crane driver and singer/signaller form a partnership of mutual trust in the others ability and

communication by hand or radio is paramount to the success of the task as each is remote from the load at any one time.

Spare Equipment

No operational critical spares required,

PPE

Full harness, hard hats, Safety boots, Hi-viz vest, rigger gloves, and overalls

Time Restrictions

No time restrictions

Welfare

Construction Contractor to provide welfare on site this includes toilets and rest room.

Risk assessment

See attachment.

Page 9: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 10 of 27

2.0A Method Statement – Site Amendments

Page 10: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 11 of 27

3.0 APPENDIX B – RISK ASSESSMENT

SUB ACTIVITY RISK / HAZARD

(i.e. Problems that may or will arise and need controlling)

INITIAL RISK CONTROL (i.e. How are you going to stop a hazard from becoming an accident)

RESIDUAL RISK

Who ensures?

Transport of loads Road traffic accident MEDIUM

Vehicle maintained, MOT'd, Driver competent, within hours LOW HAULIER

Pedestrians HIGH Driver to remain alert to pedestrians taking risks MEDIUM HAULIER

Exceeding drivers hours MEDIUM

Driver to check tachograph and log break times. Advise site if return journey critical

If necessary leave trailer and return to base LOW

HAULIER

Reversing HIGH Reversing bleeper to be working and banksman to be in attendance LOW HAULIER/Van Doorn

Late delivery MEDIUM

Deliveries to be planned to arrive in good time deliveries to be coordinated so they arrive in correct order

Holding area to be located LOW HAULIER/Van Doorn

Loosening of load MEDIUM

Load to be checked on leaving yard and at each break

Good strops / chains to be used LOW HAULIER

Objects falling off wagon MEDIUM

Large objects to be well secured with good strops and chains, small objects to be put in boxes or secured to large sections LOW

HAULIER/Van Doorn

Over width loads HIGH Warning triangles and flashing lights to be fitted, Police escort if required LOW HAULIER/Van Doorn Over length loads HIGH Warning triangles and flashing lights to be fitted, Police escort if required LOW HAULIER/Van Doorn

Mobile crane Reversing into position HIGH Reversing bleeper to be working and banksman to be in attendance LOW Van Doorn/SITE Capacity MEDIUM Check crane vs. order. Bigger crane may have access problem LOW Van Doorn/SITE Lifting gear MEDIUM Check certificates and condition LOW Van Doorn

Overturning HIGH

Set up correctly on good ground, double check on driver's set up LOW MOBILE CRANE COMPANY / Van

Doorn /SITE

Public interest HIGH

Keep public at bay with Herras fencing, hoarding or barriers. Respond politely if questioned LOW Van Doorn /SITE

Page 11: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 12 of 27

SUB ACTIVITY RISK / HAZARD

(i.e. Problems that may or will arise and need controlling)

INITIAL RISK CONTROL (i.e. How are you going to stop a hazard from becoming an accident)

RESIDUAL RISK

Who ensures?

Positioning & setting up MEDIUM

Tell driver where you want him to go. Check this is feasible. Check outrigger positions LOW Van Doorn

Ground conditions MEDIUM Client to advise on sub surface problems LOW SITE

Positioning MEDIUM Mark on ground where king pin to be set and orientation LOW Van Doorn Counterweight swing HIGH Ensure 600mm clearance to hard points or barrier off LOW Van Doorn

Collision with Helicopter MEDIUM Ensure aviation light fitted to mobile crane cat head. And communication between both parties for correct procedures LOW

MOBILE CRANE COMPANY / Van Doorn /SITE

Unloading & Loading of

wagons Climbing up onto arctic MEDIUM Use step and hand holds, clear mud off before climbing. Ladder should/be available LOW

Van Doorn

Climbing up crane section MEDIUM Use ladder if obvious step and hand holds are not valid LOW Van Doorn Attaching strops MEDIUM Ensure secure position before releasing hands to work with strops LOW Van Doorn

Manual handling of small loads MEDIUM Individual loads will be assessed before lifting. Use of proper manual handling techniques will be adopted. Mechanical lifting will be employed were possible. LOW

Van Doorn

Lifting of sections Load falling HIGH

Use certificated strops. Certified slinger to attach. Lift 6" off ground to check

balance. Mark lifting points for disassembly. Ensure strops cannot slip LOW Van Doorn

Public interest HIGH

Keep public at bay with Herras fencing, hoarding or barriers. Respond politely if

questioned LOW Van Doorn /SITE

Load judder on lifting MEDIUM Check strops cannot slip. Check chains are not twisted or snagged LOW Van Doorn Pinched fingers MEDIUM Wear gloves and keep fingers clear as load goes onto crane LOW Van Doorn

Assembly &

Disassembly of

sections on Ground

Van Doorn

Pinched fingers MEDIUM Wear gloves and keep fingers clear as load comes off crane. Set up timbers to rest

sections LOW

Van Doorn

Tools slipping MEDIUM Use good correct tools LOW Van Doorn

Page 12: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 13 of 27

SUB ACTIVITY RISK / HAZARD

(i.e. Problems that may or will arise and need controlling)

INITIAL RISK CONTROL (i.e. How are you going to stop a hazard from becoming an accident)

RESIDUAL RISK

Who ensures?

Re-arrangement of strops MEDIUM Ensure load is stable on ground before altering strops. If held on one strop, ensure restraint against unplanned movement LOW

Van Doorn

Sledge hammer work MEDIUM

Check head is secure and use remote drift. Check hands will not hit steel work if drift

missed or shifts LOW Van Doorn

Working platforms HIGH

Ensure stable base to work off. Use scaffold boards and ladders where practical,

adequate guardrails, barriers to prevent falls. MEDIUM Van Doorn

Van Doorn

Lifting at height Alignment of base MEDIUM Check with site for line and level LOW Van Doorn Concrete strength MEDIUM Check with site that erection strength attained LOW Van Doorn Attaching strops MEDIUM Ensure secure position before releasing hands to work with strops LOW Van Doorn Releasing strops MEDIUM Ensure secure position before releasing hands to work with strops LOW Van Doorn

Loose fittings HIGH Minimise loose fittings at height. Keep in sacks or boxes, use catch nets or tie to

structure MEDIUM Van Doorn

Sledge hammer work MEDIUM

Check head is secure and use remote drift. Check hands will not hit steel work if drift

missed or shifts LOW Van Doorn

Men falling HIGH

All men at height to wear full harnesses and clip on when outside handrails MEDIUM Van Doorn

Tools falling HIGH

Toe boards provided on all access equipment. Tool belts to be used to store tools

when at height. Exclusion zone to be placed around the base of the tower crane. MEDIUM SITE/ Van Doorn

Public interest HIGH

Keep public at bay with Heras fencing, hoarding or barriers. Respond politely if

questioned LOW Van Doorn /SITE

Vertical alignment MEDIUM

Check with site for line and level LOW SITE

Load falling HIGH

All loads to be well secured with appropriate strops/chains. Certified slinger to

attach, lift 6" to check balance, ensure strops cannot slip. LOW Van Doorn

Falling Items HIGH

Use certificated strops. Certified slinger to attach. Lift 6" off ground to check balance. Mark lifting points for disassembly. Ensure strops cannot slip MEDIUM

Van Doorn

Page 13: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 14 of 27

SUB ACTIVITY RISK / HAZARD

(i.e. Problems that may or will arise and need controlling)

INITIAL RISK CONTROL (i.e. How are you going to stop a hazard from becoming an accident)

RESIDUAL RISK

Who ensures?

Working at height Fall from height HIGH

Edge protection with intermediate guardrail as the preferred control. If this is not possible then harnesses must be worn and clipped on where practicable at all times. MEDIUM

Van Doorn

Recovery of Personnel MEDIUM A Heightec recue kit will be available on site at all times. The erection crew will

include at least 2 members trained in its use. LOW

Van Doorn

Fall of tools from height HIGH

Toe boards provided on all access equipment. Tool belts to be used to store tools

when at height. Exclusion zone to be placed around the base of the tower crane. MEDIUM Van Doorn

Fall from ladder HIGH

Work on ladder for short duration work only, ladder must be lashed and/or footed.

Tool belt to be used to carry tools up or down ladder. MEDIUM Van Doorn

Injury to others HIGH

Area below to be secured. No work to be carried out above other operators, to liaise with operators of possible interfaces. MEDIUM

Van Doorn

Confined Areas MEDIUM

Operators to be made aware of obstructions that could be in the way, sprinkler heads, or other services. Hardhat to be worn at all times along with any other PPE

that may be required. LOW

Van Doorn

Use of Hand Tools (cuts bruises abrasions)

MEDIUM Gloves to be worn at all times. Tools to be checked for suitability. Only trained operatives to be used. LOW

Van Doorn

Van Doorn Assembly &

disassembly of sub

items

Falling items HIGH Use certificated strops. Certified slinger to attach. Lift 6" off ground to check

balance. Mark lifting points for disassembly. Ensure strops cannot slip. Ensure No-Go zone established under work area with sentries. MEDIUM

Van Doorn

Falling men HIGH All men at height to wear full harnesses and clip on when outside handrails MEDIUM Van Doorn

Falling tools HIGH Toe boards provided on all access equipment. Tool belts to be used to store tools

when at height. Exclusion zone to be placed around the base of the tower crane. MEDIUM SITE/ Van Doorn

Misalignment MEDIUM

Check fit, and adjust before final tightening. Major errors to be investigated and

referred back to Van Doorn. LOW Van Doorn

Incompatibility MEDIUM

Site assessment over criticality and ability to continue. Note to be made and reported back to Van Doorn to prevent next time LOW

Van Doorn

Page 14: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 15 of 27

SUB ACTIVITY RISK / HAZARD

(i.e. Problems that may or will arise and need controlling)

INITIAL RISK CONTROL (i.e. How are you going to stop a hazard from becoming an accident)

RESIDUAL RISK

Who ensures?

Roping & De-Roping Sock parting MEDIUM Ensure free running of ropes and sock in good condition LOW Van Doorn Wrong rope MEDIUM Check diameter, configuration, pre use, strength and length before starting LOW Van Doorn Drum collapsing MEDIUM Check condition and set up on secure stand LOW Van Doorn Falling pear MEDIUM Pull ropes tight and hammer into wedge. Tail to be clipped to drum LOW Van Doorn Broken wires MEDIUM Wear gloves and check along length on pre used rope LOW Van Doorn Working on jib / falling HIGH All men at height to wear full harnesses and clip on when outside handrails MEDIUM Van Doorn 2 fall / 4 fall hook retention MEDIUM Inner hook to be lashed to jib until reeving complete LOW Van Doorn Van Doorn Commissioning &

Decommission Electric shock MEDIUM

Do not energise until OK'd by electrician LOW Van Doorn

Mis-wiring MEDIUM

Competent electrician to be present LOW

Van Doorn

Setting limits MEDIUM

All men at height to wear full harnesses and clip on when outside handrails. Check

several times to ensure no creep of pawls. Ensure settings match manual practice if

too fine. LOW

Van Doorn

Public Interest HIGH Keep public at bay with Heras fencing, hoarding or barriers. Respond politely if

questioned LOW SITE

Testing Crane collapse MEDIUM

Follow procedures for torque and sequence. Check wind strength and completeness

of preceding work LOW Van Doorn

Load falling HIGH

Use certificated strops. Certified slinger to attach. Lift 6" off ground to check

balance. Mark lifting points for disassembly. Ensure strops cannot slip LOW Van Doorn

Setting limits MEDIUM

All men at height to wear full harnesses and clip on when outside handrails. Check several times to ensure no creep of pawls. Ensure settings match manual practice if

too fine. LOW

Van Doorn

Page 15: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 16 of 27

4.0 APPENDIX C – STANDARD PROCEDURES

DISMANTLE METHOD STATEMENT PROCEDURES

(1) All personal protective equipment will be supplied and must be maintained properly and worn at all times

when “on site”.

(2) When erecting or dismantling a safety harness must be worn at all times and used when not protected from falling by handrails or the crane structure.

(3) Generally, Van Doorn are responsible for making sure that both the working area needed and the area around the mobile crane is kept clear at all times. The supervisor must make sure that this is carried out to

his satisfaction.

(4) All procedures to be in accordance with the manufacturer‟s manual. The stated wind speed limitations in the manual must be strictly adhered to, and in case of same restriction being exceeded, or indeed forecast to be

exceeded, all work should be stopped, assuming the work is in a safe condition.

(5) Lines of adequate strength and length to be used to control loads.

(6) Both before and during the operation, all the crew and also the mobile driver, must be kept informed of the procedures to be carried out, and in particular individual duties such as signals and radio controls etc. for

example.

(7) Anything arising to obviate the work being carried out as planned, such as substitution of mobile etc., may be

allowed at the discretion of the supervisor provided that: (a) All Lifts to be assess for safety in both height and weight.

(b) No change allowed in actual planned erection unless allowed for in the manual. (c) Both site and the office to be notified, especially if such change extends the working period.

Changes to be written on the method statement.

If the supervisor considers it is not practicable to carry out the work, both site and the office must be told

immediately

Page 16: VDD

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 17 of 27

5.0 APPENDIX E – RESCUE PROCEDURES

Each Supervisor will carry a Heightec “Scaffpack” rescue kit and when erecting the crane the rescue kit will be craned

to the top of the crane during the slew ring erection and lowered off to the ground level with the use of a hand line after the final inspection of the crane has been completed. During dismantle operations the rescue kit will be lifted to the top

of the crane on first lift.

During a operation the “Scaffpack” rescue kit will be the first lift to take place, and rescue kit placed in the cab for safe keeping.

The “Scaffpack” kit is designed so that one man can rescue another if they are suspended from the jib by their safety harness. The “Scaffpack” rescue kit uses a three line pulley system that can either lower the person down or lift the

person up into the jib.

All equipment meets the requirements of the PPE Directive – 89/686/EEC

Page 17: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 18 of 27

7.0 APPENDIX F - TRANSPORT

Plant No:

D No:

Crane Specification: Liebherr 132HC

Address:

Glenfield Hospital

Leicester

Date: Saturday 17th March 2012

Day 1 – Saturday 7th January 2012

Load No: Time: Description

1 10.00 20 metre Front jib.

2 11.00 15 metre Front jib.

3 12.00 Counter Jib, 4 x 2500kg & 1 x 1600kg Counter Weights, A Frame, Hook & Trolley

4 13.30 Hoist Winch, Slewring & Slewring Baskets.

5

6

14.30

15.00

5 x 2.5 Metre Tower Sections.

10 Metre Base Tower Section & Erection Platforms.

Visual Creations
Typewritten Text
Construction Contractor
Visual Creations
Typewritten Text
C/O Project Coordinator
Page 18: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 19 of 27

8.0 APPENDIX G – TRANSPORT ACCESS

FIELD OPERATIONS DIRECTORATE Construction Division Technology Unit

ENGINEERING PLANT GROUP

Please find below photograph taken by the HSE, showing our men using a step ladder to gain access to the back of the trailer, which because of the short time our men spend slinging the load, usually from the safety of the inside of the load and stepping off the trailer before the load is lifted, and the fact that our men use their safety harnesses and clip on if slinging the load from the outside i.e. jib sections on the smaller cranes, the HSE have concluded that the system we use is perfectly acceptable.

Page 19: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 20 of 27

5.0 APPENDIX D – SKILL MATRIX

C.P.C.S.No C.P.C.S.No Slinger Heightec/ Gotcha Torque & C.I.T.B. Appointed NVQ CSM Remote P.P.E

Expiry Signaller Safety Rescue Tooling Touch Persons Training First Inspection

Awareness Kit Pass Course Aid C.P

Surname Forename Status Number Date Date Date Training Training Date Training Level Date Date

Page 20: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 21 of 27

10.0 APPENDIX I - Inspection Checklist-Tower Crane

1 Pre-Inspection -Confirm Crane Identification 41 Hoist Gearbox

2 Pre-Inspection - Review Crane Inspection Register 42 Hoist Motor

3 Track, Rails, Sleepers, etc 43 Hoist Brake

4 Earth Rods and Continuity Strips 44 Hoist Brake, Hydraulic Pump / Tanks / Pipes

5 Trailing Cable and Drum 45 Hoist Drum

6 Travel Motors and Audible Warnings 46 Hoist Limit Switches

7 Travel Gearboxes 47 Hoist Rope

8 Travel Wheels and Bearings 48 Saddle Jib Heel Section and Sheave

9 Travel Limit Switches and Ramps 49 Trolley Motor and Brake

10 Chassis / Pads / Grillage 50 Trolley Gearbox

11 Central Ballast and Markings 51 Trolley Limit Switches

12 Central Ballast Chart 52 Trolley Ropes and Terminal Fittings

13 Radius Board 53 Trolley Carriage Assembly and Platform

14 Expendable Base 54 Trolley Rollers

15 Base Access 55 Trolley Sheaves and Pins

16 Mast Towers / Bolts / Ladders and Rest Platforms 56 Main Jib Tie Bars and Pins

17 Tie–ins to Building 57 Intermediate Jib Sections and Sheaves

18 Slewing Ring and Bolts 58 Jib Nose Section and Sheave

19 Slewing Pinions 59 Hoist Rope Anchor or Terminal Fittings

20 Slew Motors and Gearboxes 60 Derricking Jib Assembly Complete, Heel,

Intermediate and Nose Sections and all

Associated Pins and Sheaves

21 Slew Brake Assembly 61 Derricking Jib Tie Bars on Pendant Ropes and Fittings

22 Brake Solenoid and Master Cylinder 62 Derricking Rope and Sheaves

23 Audible Warning 63 Derricking Rope Anchor Points

24 Cabin and Controls 64 Derricking Drum and Limit Switches

25 Visual Display Unit 65 Derricking Motor and Brake Assembly

26 Cab Access, Ladders and Platforms 66 Anemometer

27 Platforms Surrounding Machinery Deck on

Derricking Cranes

67 Maintenance Chart

28 Electrical Panels and Doors 68 Lubricants and Tools

29 Cab Sheave and Guard 69 Hook Block Assembly

30 „A‟ Frame Foot Pins 70 Rising Mains Cable and Mast Clamps

31 „A‟ Frame 71 Climbing Frame Structure

32 „A‟ Frame Limit Switches 72 Hydraulic Tank, Pump, Ram, Hoses and Fittings

33 „A‟ Frame Platform and Ladder 73 Guide Rollers and Fittings

34 „A‟ Frame Tie Bar Anchor Positions 74 Ladders, Platforms and Fitting Positions

35 Counter Jib and Handrails 75 Folding Platform Support System

36 Illuminating Signs 76 Section Guide Rail and Tie Bar

37 Counter Jib Tie Bars and Pins 77 Section Support Rollers and Brackets

38 Counter Jib Electrical Panel and Doors 78 Climbing Support Shoe

39 Counter Jib Ballast Weights 79 All Pins and Bolts

40 Machinery Deck 80

Plant No: Location:

Inspection by (Engineer Surveyor): Date:

Any Observations or Defects will be Entered into the appropriate section of the Examination Report.

Page 21: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 22 of 27

12.0 APPENDIX K – COSHH ASSESSMENT (COSHH Data Sheet link)

Product:

EXOL EP GREASE RANGE

INCLUDING 000/EP, 00/EP, 0/EP(T), EP1, EP2(T), EPC, EP3, LT1/EP, and LT2/EP

Not classified as dangerous for supply in the UK

Health Risks:

EYES: Wash area thoroughly with water for at least 15mins. If irritation persists seek medical attention. SKIN: Wash area with large amounts of soap and water. If irritation persists seek medical.

INHALATION: Vapour pressure of this material is low; inhalation under normal conditions is not usually a problem INGESTION: Not expected to be a problem. If swallowed do not induce vomiting. Seek medical help if uncomfortable.

PRESSURE INJECTION: Obtain immediate medical attention even injury may appear minor. Copy of Safety Data Sheet must accompany injured person to hospital.

PPE: GLOVES: Nitron Lite or better.

GOGGLES: SAFETY GLASSES: Yes if risk of eye contact.

VISOR: N/R COVER SKIN: Yes if risk of splash/contact

MASK: N/R

RESPIRATOR: N/R SAFETY FOOTWEAR: Yes

Exposure Controls: (OES: Occupational Exposure Standard) N/A

LEV: N/A

Ecological Information:

Prevent entry into drains, sewers and water courses.

Fire Precautions: Non flammable.

Use CO2, Powder or Foam extinguishers.

Disposal: Dispose of as COSHH Waste by licenced carrier

1.IDENTIFICATION OF THE SUBSTANCE/PREPARATION AND COMPANY NAME

NAME OF MANUFACTURER/SUPPLIER:-

EXOL Lubricants Ltd

All Saints Road

Wednesbury

West Midlands, WS10 9TS

BUSINESS TELEPHONE No : 0121 568 6800 FAX No : 0121-568 6720

HEALTH AND SAFETY EMERGENCY TELEPHONE No. (out of hours only): 0121 568 6800

Page 22: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 23 of 27

PRODUCT NAME: LIBRA EP RANGE INCLUDING 000/EP, 00/EP, 0/EP(T), EP1, EP2(T), EPC, EP3, LT1/EP and LT2/EP

APPLICATION: LUBRICATION PRODUCT SUPPLIED FOR USE IN LUBRICATING SYSTEMS ONLY

2. COMPOSITION/INFORMATION ON INGREDIENTS

GENERAL: MINERAL OIL THICKENED WITH LITHIUM SOAP, AND CONTAINING EP, ANTI-WEAR, ANTI-0XIDANT, AND

CORROSION INHIBITOR ADDITIVES (PLUS POLYMER ADDITIVE FOR TACKY GRADES).

HAZARDOUS INGREDIENTS:- R & S PHRASES:- CONCENTRATION:-

NONE NOT APPLICABLE NOT APPLICABLE

3. HAZARDS IDENTIFICATION

THIS PRODUCT IS NOT CLASSIFIED AS HAZARDOUS UNDER CURRENT UK HEALTH AND SAFETY, AND ENVIRONMENTAL LEGISLATION WHEN USED IN THE APPLICATION FOR WHICH IT IS INTENDED.

PRESSURE INJECTION: INJECTION OF ALL PRODUCTS WILL CAUSE SEVERE INTERNAL DAMAGE IF NOT PROMPTLY TREATED.

SPECIAL HAZARDS OF PRODUCT AFTER USE : NO POTENTIALLY HAZARDOUS COMPONENTS TO CONSIDER.

4. FIRST AID MEASURES

EYES : FLUSH EYES THOROUGHLY WITH COPIOUS AMOUNTS OF WATER, UNTIL IRRITATION SUBSIDES.

IF IRRITATION PERSISTS, OBTAIN MEDICAL ATTENTION.

SKIN : WASH WITH LARGE AMOUNTS OF WATER, USING SOAP IF AVAILABLE.

INHALATION: VAPOUR PRESSURE OF THIS MATERIAL IS LOW. INHALATION UNDER NORMAL CONDITIONS IS NOT

USUALLY A PROBLEM.

INGESTION : NOT EXPECTED TO BE A PROBLEM. IF SWALLOWED, DO NOT INDUCE VOMITING IF UNCOMFORTABLE,

SEEK MEDICAL ADVICE.

PRESSURE INJECTION: ALWAYS OBTAIN IMMEDIATE MEDICAL ATTENTION EVEN THOUGH THE INJURY MAY APPEAR

MINOR!

Page 23: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 24 of 27

5. FIRE FIGHTING MEASURES

FLAMMABILITY : NON-FLAMMABLE FLASH POINT (oC PMCC) : > 150

EXTINGUISHING MEDIA : FOAM, DRY POWDER, & CO2

PRODUCTS OF COMBUSTION: CARBON, OXIDES OF CARBON, AND ZINC.

6. ACCIDENTAL RELEASE MEASURES

PERSONAL PRECAUTIONS : SPILT PRODUCT PRESENTS A SIGNIFICANT SLIP HAZARD

AVOID EXPOSURE OF THE PRODUCT TO SOURCES OF IGNITION.

ENVIRONMENTAL PRECAUTIONS : PREVENT ENTRY INTO DRAINS, SEWERS AND WATER COURSES

DECONTAMINATION PROCEDURES : SOAK UP WITH INERT ABSORBENT, OR CONTAIN AND REMOVE BY BEST AVAILABLE

MEANS.

7. HANDLING AND STORAGE

KEEP CONTAINERS CLOSED WHEN NOT IN USE

PREVENT SLIP HAZARDS

STORAGE TEMPERATURE 0 > 40oC

8. EXPOSURE CONTROLS/PERSONAL PROTECTION

EYES : WEAR SAFETY GLASSES IF THERE IS A RISK OF POSSIBLE EYE CONTACT.

SKIN : USE BARRIER CREAM, WEAR GLOVES, AND OVERALLS IF THERE IS A POSSIBILITY OF PROLONGED SKIN CONTACT.

INHALATION : NO SPECIAL RESPIRATORY PROTECTION IS REQUIRED UNDER NOR MAL CONDITIONS OF USE.

INDUSTRIAL HYGIENE : GOOD PERSONAL HYGIENE PRACTICES SHOULD BE FOLLOWED.

Page 24: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 25 of 27

9. PHYSICAL AND CHEMICAL PROPERTIES

APPEARANCE : BOTTLE GREEN GREASE ODOUR : NONE

SPECIFIC GRAVITY @ 20oC : 0.96 pH : N/A

SOLUBILITY : INSOLUBLE IN WATER FLASH POINT (closed cup) oC : ABOVE 150

FLAMMABILITY LIMIT(in air % by volume) LEL : N/E UEL: N/E

VAPOUR PRESSURE @ 20oC : BELOW 0.1mm Hg. VAPOUR DENSITY (air = 1) : N/E

BOILING POINT (oC) : 310 min. POUR/MELTING POINT (oC) : ABOVE 160

KINEMATIC VISCOSITY @ 40oC (mm2 S-1) : N/A

THESE PROPERTIES DO NOT CONSTITUTE A SPECIFICATION

10. STABILITY AND REACTIVITY

THERMAL - STABLE

LIGHT - STABLE

AVOID EXTREME HEAT

INCOMPATIBLE WITH STRONG OXIDISING AGENTS

11. TOXICOLOGICAL INFORMATION

THE FOLLOWING TOXICOLOGICAL ASSESSMENT IS BASED ON A KNOWLEDGE OF THE TOXICITY OF THE PRODUCT'S COMPONENTS.

ESTIMATED ORAL LD50 RAT > 2g/kg.

HEALTH EFFECTS ON EYES : MAY CAUSE TRANSIENT IRRITATION

ON SKIN : UNLIKELY TO CAUSE HARM ON BRIEF OR OCCASIONAL CONTACT

BY INHALATION : LOW VOLATILITY MAKES INHALATION UNLIKELY AT AMBIENT TEMPS.

BY INGESTION : MAY CAUSE NAUSEA, VOMITING, AND DIARRHOEA

CHRONIC : REPEATED AND PROLONGED SKIN CONTACT MAY LEAD TO SKIN DISORDERS

OTHER : PRODUCTS WHICH HAVE BECOME CONTAMINATED IN USE OR FROM EXTERNAL SOURCES MAY PRESENT MORE SERIOUS HEALTH EFFECTS

12 ECOLOGICAL INFORMATION

Page 25: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 26 of 27

BIODEGRADABILITY: N/E CHEMICAL OXYGEN DEMAND (mg. O2/litre): N/E

LUBRICATING GREASES ARE INHERENTLY, BUT NOT READILY, BIODEGRADABLE.

13. DISPOSAL RECOMMENDATIONS

PLACE USED AND CONTAMINATED MATERIALS/PACKAGING IN SUITABLE CONTAINERS. DISPOSE OF THE CONTROLLED WASTE

IN ACCORDANCE WITH DUTY OF CARE (ENVIRONMENTAL PROTECTION ACT 1990 - SECTION 34 (7)) USING A LICENSED WASTE DISPOSAL COMPANY.

14. TRANSPORT INFORMATION

CLASSIFICATION FOR TRANSPORT:- NOT CLASSIFIED AS HAZARDOUS FOR TRANSPORT

UN NUMBER : NONE PACKAGING GROUP: NOT APPLICABLE

SHIPPING NAME : NOT APPLICABLE

IMO CLASS : NOT APPLICABLE MARINE POLLUTANT : NO

ADR/RID : NOT APPLICABLE ICAO/IATA: NOT APPLICABLE

. 15 REGULATORY INFORMATION

HAZARD LABEL DATA : THIS PRODUCT IS NOT CLASSIFIED AS DANGEROUS FOR SUPPLY IN THE UK.

EC DIRECTIVES : FRAMEWORK WASTE DIRECTIVE, 91/156/EEC

WASTE OIL DIRECTIVE, 87/101/EEC

STATUTORY INSTRUMENTS : THE HEALTH AND SAFETY AT WORK etc.ACT 1974

CONSUMER PROTECTION ACT 1987

ENVIRONMENTAL PROTECTION ACT 1990

CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH REGS.1988

THE CHEMICALS (HAZARD INFORMATION AND PACKAGING FOR SUPPLY) REGS. 1996

16. OTHER INFORMATION

Page 26: VDD

Van Doorn Tower Crane Consultants

MS/051211/132/NF/D, Dismantle Liebherr 132HC

Page 27 of 27

THE DATA AND ADVISE GIVEN APPLY WHEN THE PRODUCT IS SOLD FOR THE STATED APPLICATION OR APPLICATIONS. THE PRODUCT IS NOT SOLD AS SUITABLE FOR ANY OTHER APPLICATIO

N. USE OF THE PRODUCT FOR APPLICATIONS OTHER THAN AS STATED IN THIS SHEET MAY GIVE RISE TO RISKS NOT

MENTIONED IN THIS SHEET. YOU SHOULD NOT USE THE PRODUCT OTHER THAN FOR THE STATED APPLICATION OR APPLICATIONS WITHOUT

SEEKING ADVICE FROM US.

IF YOU HAVE PURCHASED THE PRODUCT FOR SUPPLY TO A THIRD PARTY FOR USE AT WORK, IT IS YOUR DUTY TO TAKE ALL

NECESSARY STEPS TO SECURE THAT ANY PERSON HANDLING OR USING THE PRODUCT IS PROVIDED WITH THE INFORMATION IN THIS SHEET.

IF YOU ARE AN EMPLOYER, IT IS YOUR DUTY TO TELL YOUR EMPLOYEES AND OTHERS WHO MAY BE AFFECTED OF THE

HAZARDS DESCRIBED IN THIS SHEET AND OF ANY PRECAUTIONS WHICH SHOULD BE TAKEN.

APPROVED CODES OF PRACTICE : WASTE MANAGEMENT. THE DUTY OF CARE.

GUIDANCE NOTES : OCCUPATIONAL SKIN DISEASES: HEALTH AND SAFETY PRECAUTIONS (EH26)

OCCUPATIONAL EXPOSURE LIMITS (EH40)

THE CARCINOGENICITY OF MINERAL OILS (EH58)

SKIN CANCER CAUSED BY OIL [MS(B)5]

SAVE YOUR SKIN! - OCCUPATIONAL CONTACT DERMATITIS {MS(B)6]

DERMATITIS - CAUTIONARY NOTICE [SHW367]

EFFECTS OF MINERAL OIL ON THE SKIN [SHW397]

THE ABOVE PUBLICATIONS ARE AVAILABLE FROM HSE.