Van Allen Probes Spacecraft Operations July 29, 2015 Kristin Fretz...
-
Upload
annabella-sparks -
Category
Documents
-
view
214 -
download
0
Transcript of Van Allen Probes Spacecraft Operations July 29, 2015 Kristin Fretz...
Van Allen ProbesSpacecraft Operations
July 29, 2015
Kristin Fretz
JHU/APL
240-228-5386
2
Van Allen Probes Summary Both observatories continue to operate
nominally Spacecraft, ground system, and
instruments are continually monitored and anomalies are tracked
Trending reviews held every 6 months with subsystems and instruments reporting on:
GS
/SC
F
GS
/US
N
MO
C S
/W
INS
T
SC
GS
/SC
F
GS
/US
N
MO
C S
/W
INS
T
SC
GS
/SC
F
GS
/US
N
MO
C S
/W
INS
T
SC
GS
/SC
F
GS
/US
N
MO
C S
/W
INS
T
SC
2012 2013 2014 2015
0
1
2
3
4
5
Age of Open ARs by Distribution and Status Type
Open
Monitor
Dispositioned
Diagnosed
Nu
mb
er o
f A
Rs
Last review held on June 9, 2015; no new concerns indicated by a review of current trending data
Engineering team continues to support project science in evaluating changes to orbits and spacecraft operations
Subsystem or instrument performance Overview of major subsystem/instrument
activities Anomalous behaviors (address any open
ARs) Changes in nominal operating conditions Trends that could impact future operations
3
Ground & Operations Highlights
Average Daily Data Return Average daily return for the
past year SCA: 13.9Gbits SCB: 13.9Gbits
Consistently exceeding 5.9Gb data per day requirement from each spacecraft
Regular Activities Decouple operations allows independent operation of the spacecraft and
instruments Non-critical real time contacts unattended; ground system executes Contact Plan Critical event contacts are staffed (e.g., precession maneuvers every 3 weeks) Monitor spacecraft, instruments, and ground system for anomalies Ground HW replacement plan in place; moved to new RAID system in Dec. 2014 Currently no full GSW updated scheduled
4
Spacecraft Highlights (1 of 3)
G&C/Propulsion All trended parameters
are behaving within limits
Both spacecraft require a spin down maneuver; targeting August 20
Monitor propellant usage and provide estimates of predicted end of life
Spacecraft Predicted Life SCA SCB
Remaining useable propellant – June 2015 (kg) 39.4 ± 0.82 39.5 ± 0.81
Holdout for disposal (kg)* 16.10 16.49
Available for extended mission (kg) 23.27 23.05
Avg. prop usage per maneuver (kg)** 0.308 0.287
Nominal SC life expected in orbit (years)*** 3.98 4.23
Uncertainty in predicted life estimate (+/-years) 0.25 0.26
Estimated nominal EOM May-19 June-19
Current Estimate (June 2015)
* Based on 20.9 yr, 2-burn disposal maneuver; passivation waiver required** Average propellant usage per maneuver between 2015 and 2019*** Assumes 19 E-W precession maneuvers/year
Mission Design/Navigation Routinely perform 1-week and 2-week comparisons of prediction
accuracy All trajectory requirements are currently being satisfied Monitor for potential conjunctions (0 high interest events in the last 6
months) Designing science related orbit changes as needed
5
Spacecraft Highlights (2 of 3)
Telecommunications All data (except SSPA supply
current) are within expected limits
SSPA trend shows excessive decrease in DC current draw
Assuming trend continues, the mission meets requirements (2.8-dB margin at end of 8 yrs)
Thermal All trended parameters behaving within expected limits Temperatures not expected to increase since material properties not
expected to degrade IEM/FSW
All trended parameters behaving within expected limits Monitor and track SBC corrected error counts, SSR total error counts,
single event upsets, etc.
6
Spacecraft Highlights (3 of 3)
PDU/PGS All trended parameters
behaving within expected limits Completed extended mission
analysis of power systems operations through Nov. 2020
Adequate power system margins through the extended mission
Solar Array has sufficient capabilities to complete the extended mission (solar array degradation less than predicted)
Battery cycle and calendar life are predicted to meet the extended mission
Autonomy/FM All key parameters are within expected limits Continually monitor LVS, Software LVS, and LBSOC thresholds
Adjusted in accordance with eclipse seasons Work with PGS Subsystem to determine when degradation of battery or SA
will require fine adjustments of thresholds
7
On-Going Work
As understood by the engineering team, the #1 science goal is to maximize mission lifetime
GOAL: Operate through early 2019
Any changes to the orbit are evaluated by engineering team Propellant is the limiting item for mission life EOL power analysis shows sufficient power through Nov. 2020 Radiation analysis on worst case part predicts total dose of 20krad in Feb. 2022
Evaluated various orbit changes for science team: Lapping Events
Continue to evaluated on a case-by-case basis
Typically use 40-70g propellant
N-S Maneuver Science team decided to eliminate N-S maneuvers after December 2014
Decreases mission life by 1-2 months/maneuver
Lower Sun Offset Angle / Widen E-W Component Science team decided remain at 19°north sun offset angle component
Lowering N-S component would result in shadowing of EFW booms
Apogee Maneuver Science team decided to adjust apogees of both spacecraft by 70km
Decreases mission life by 1-2 months
8
Deorbit Maneuver
Looking at adjusting de-orbit strategy to conserve propellant for a longer life and possibly adjust orbit of one spacecraft
Requirements Must deorbit within 25 years
Passivate battery and propulsion system
Multiple maneuver strategy Next to last burn would meet 25 year requirement
Last burn would use ‘Propellant Uncertainty’ to shorten orbit lifetime
Working with Scott Hull (GSFC) to revise plan Would require a waiver to NASA-STD-8719.14A Process for Limiting
Orbital Debris
9
Summary
Both observatories continue to operate nominally
No new concerns indicated by a review of current trending data
Engineering team continues to support project science in evaluating changes to orbits and spacecraft operations for extended mission
Radiation effects analyzed; less severe than predicted EOL power analysis completed; sufficient power exists Rework end of mission plan; possible changes to deorbit strategy
to extend propellant life
Questions?