Value Stream Mapping: Value Stream Mapping: August 2005 Current StateAugust 2005 Current State
Nancy TerranovaNancy Terranova
October 26, 2006October 26, 2006
Regulation 1102 Current StateRegulation 1102 Current State(As of August 2005)(As of August 2005)
Construction permit applicationsConstruction permit applications Processing time – 74.4 hoursProcessing time – 74.4 hours Lead Time – 104.5 daysLead Time – 104.5 days
Construction to Operation Construction to Operation permitspermits Processing time – 15 hoursProcessing time – 15 hours Lead Time – 14 daysLead Time – 14 days
Regulation 1102 Current StateRegulation 1102 Current State(As of August 2005)(As of August 2005)
Less than 1% of incoming Less than 1% of incoming applications issued on first passapplications issued on first pass
18% of applications after being 18% of applications after being determined technically complete determined technically complete issued if first pass set at issued if first pass set at technically completetechnically complete
Construction Permit ProcessConstruction Permit Process
Applications sent to Dover and/or Applications sent to Dover and/or New Castle OfficesNew Castle Offices Applications sent to New Castle Applications sent to New Castle
sometimes didn’t get to Dover in a sometimes didn’t get to Dover in a timely mannertimely manner
About 55% of the applications were About 55% of the applications were administratively complete and accurate administratively complete and accurate (The forms contained information in the (The forms contained information in the blocks, were signed and fees were blocks, were signed and fees were included)included)
Construction Permit ProcessConstruction Permit ProcessCustomer
Receive ApplicationDover
Date Stamped
Processing Time Mins2
Production Lead Time Days0.5
Production Lead Time Days2
Batch Time/Day1
Review, Sort, Copy, Distribute
% Complete & Accurate %55
Processing Time Mins20
Production Lead Time Days0.5
Production Lead Time Days2
Batch Times/Day2-3
Process time for rework is 5 to 10 minutes
Information from New Castle does not always get
to Dover
Opportunity for Standardized Work –
sometimes data goes to ASII, sometimes to EE/ES
Data logged into multiple systems
Multiple Tasks
Dover/New Castle
DEN
I-Steps
Other
Dover
10 %
Dover
New Castle
Dover
New Castle
Mail Log
Application
ASII - 1Rec. - 1
1 Days
2 Mins
1 Days
20 Mins
Skip this
only 10%
Engineers/Scientists spend 16% of total time on Reg. 2 Permitting (Non-Dedicated Resources)
Approximately 3.4 FTEs Support Reg. 2 Permitting
Reg. 2 Current State (8/17/2005)
Construction Permit ProcessConstruction Permit Process
Applications from new facilities Applications from new facilities sent to Program Manager II for sent to Program Manager II for assignment to Eng/Sciassignment to Eng/Sci
Applications sent to Eng/Sci Applications sent to Eng/Sci
Eng/Sci conducts Technical Eng/Sci conducts Technical ReviewReview About 10% of the applications were About 10% of the applications were
technically complete and accurate. technically complete and accurate. (Information in the blocks was missing, (Information in the blocks was missing, incomplete, or inaccurate)incomplete, or inaccurate)
Construction Permit ProcessConstruction Permit Process
Distribute Application for New Facility to
PMI
% Complete & Accurate %100
New Castle
Processing Time Mins1
Production Lead Time Days2
Batch Time/Day1
Eliminate PMII from step
Assigned to Engineer
Dover/New Castle
% Complete & Accurate %100
Processing Time Mins1-2
Production Lead Time Days0.2
Batch Time/Day1
Assignment based upon County and workload
90 %
Review for Technical Completeness
Dover/New Castle
% Complete & Accurate %10
Processing Time Hrs2
Processing Time Hrs12
Processing Time Hrs8
Min
Max
Avg
Production Lead Time Wks2
% Engineer Time %2
Need Technical Checklist
PMII - 1 PMI - 3 EE/ES - 21
Skip this only 10%
1 Days
1 Mins
14 Days
8 Hrs
Production Lead Time Days2
Production Lead Time Days1
Min
Max
Avg
Construction Permit ProcessConstruction Permit Process
Additional information is Additional information is requested, received, and reviewed requested, received, and reviewed by Eng/Sciby Eng/Sci About 85% to 90% of the applications About 85% to 90% of the applications
were then technically completewere then technically complete This means that 9% to 14% of the This means that 9% to 14% of the
applications still could not be processed applications still could not be processed without additional technical informationwithout additional technical information
Public Notice (ad) prepared by Public Notice (ad) prepared by Eng/Sci Eng/Sci
Construction Permit ProcessConstruction Permit Process
Contact Customer For Additional Information
Dover/New Castle
Processing Time Mins15
Processing Time Hrs4
Processing Time Hrs2
Min
Max
Avg
Production Lead Time Days30
Production Lead Time Days60
Production Lead Time Days30
Min
Max
Avg
Obtain Information Technical and Engineer/Scientist
Review 1
Phone
Meeting
Dover/New Castle
% Incorrect %10-15
Processing Time Hrs2
Processing Time Days5
Processing Time Hrs18
Min
Max
Avg
Production Lead Time Days1
Production Lead Time Days30
Production Lead Time Days15
Min
Max
Avg
5 % of Engineer/Scientist Time
Ability to obtain information drives lead time
Proper information is required to conduct
emission calculations and determine applicable
regulations
It is important that the customer recognize
applicable requirements during this step
Opportunity to standardize work (checklist of items to
be reviewed)
This step depends on the quality of information from
the customer
Create forms for calculations
Clearly identify experts, formalize Subject Matter
Experts
Minor New Source Review will not require a control
technology review
E-MailPhoneLetter
EE/ES - 21 EE/ES - 21EE/ES - 21
2 Hrs
15 Days
18 Hrs
Apr 05 7May 05 9Jun 05 11Jul 05 3
Apr 05 5May 05 1Jun 05 1Jul 05 1
Construction Permit ProcessConstruction Permit Process
Program Manager I reviews the adProgram Manager I reviews the ad 95% of the ads were complete and 95% of the ads were complete and
accurate accurate
Public Notice (ad) is placed for 15 Public Notice (ad) is placed for 15 day comment periodday comment period Requests for public hearing are not Requests for public hearing are not
addressed in this processaddressed in this process
Technical Memorandum and Technical Memorandum and Permit prepared by Eng/Sci Permit prepared by Eng/Sci
Construction Permit ProcessConstruction Permit Process
Draft Legal Notice
Dover/New Castle
% Complete & Accurate %100
Processing Time Mins30
Production Lead Time Mins30
Already have a template – may need to be improved
the language in the template based upon
requests from the public (more details)
PMI Approval of Legal Notice
% Complete & Accurate %95
Processing Time Mins5
Production Lead Time Hrs2
Production Lead Time Days1
Production Lead Time Days0.5
Min
Max
Avg
Place Public Notice
Dover
Processing Time Mins30
Production Lead Time Days3
Production Lead Time Days11
Production Lead Time Days7
Min
Max
Avg
Batch Time/Week1
EE/ES - 21 PMI - 3 ASII - 1
30 Mins
0.5 Days
2 Mins
7 Days
30 Mins
3020201
Construction Permit ProcessConstruction Permit Process
Develop Permit and Technical Memo
Word
Excel
Screen3
Dover/New Castle
% Complete & Accurate %80
Processing Time Days2
Processing Time Wks2
Processing Time Wks1
Min
Max
Avg
Production Lead Time Wks1
Production Lead Time Days60
Production Lead Time Days30
Min
Max
Avg
7% of Engineer/Scientist Time
Customer familiarization with requirements
Standardized permits and memos for certain types of
equipment
Customer
EE/ES - 21
40 Hrs
Construction Permit ProcessConstruction Permit Process
Program Manager I reviews the Program Manager I reviews the technical memo and permittechnical memo and permit 20% to 25% of the documents were 20% to 25% of the documents were
complete and accuratecomplete and accurate Program Manager II reviews the Program Manager II reviews the
technical memo and permit. If technical memo and permit. If ready, the permit is also signed.ready, the permit is also signed. 90% to 95% of the documents were 90% to 95% of the documents were
complete and accuratecomplete and accurate
Construction Permit ProcessConstruction Permit Process
PMI Review
Dover/New Castle
% Complete & Accurage %20-25
Processing Time Mins30
Processing Time Days1
Processing Time Hrs4
Production Lead Time Days1
Production Lead Time Wks1
Production Lead Time Days2
Min
Max
Avg
Min
Max
Avg
Standardize PMI review
Need better technical memos
PMII Review and Sign
New Castle
% Complete & Accurage %90-95
Processing Time Mins15
Processing Time Hrs2
Processing Time Mins30
Production Lead Time Days1
Production Lead Time Days7
Production Lead Time Days2
Min
Max
Avg
Min
Max
Avg
Use electronic means to transport between New
Castle and Dover
Rework
PMI - 3 PMII - 1
Construction Permit ProcessConstruction Permit Process
Construction permit issuedConstruction permit issued Copied and sortedCopied and sorted Mailed to CompanyMailed to Company Logged in mail logLogged in mail log Distributed Distributed Logged into DENLogged into DEN
Construction Permit ProcessConstruction Permit Process
Copy, Log, and Distribute
DEN
Dover/New Castle
% Complete & Accurate %100
Processing Time Mins30
Production Lead Time Days1-2
Batch Time/Day1
Construction Permit
Customer
AS - 4
1 Days
30 Mins
Lead Time to Issue Construction Permit: 104.5 Days
Process Time to Issue Construction Permit: 74.4 Hours or 10 Days
% Complete & Accurate from “Receive Application” to “Copy, Log, and Distribute”: <1%
% Complete % Accurate from “Technical and Engineer/Scientist Review 1” to “Copy, Log, and Distribute: 18%
Operation Permit ProcessOperation Permit Process
Company contacts Eng/Sci to request a Company contacts Eng/Sci to request a Construction to Operation InspectionConstruction to Operation Inspection
About 98% of the inspections showed About 98% of the inspections showed compliance with the construction permit. So an compliance with the construction permit. So an operation permit could be preparedoperation permit could be prepared
Note, Regulation 1102, Section 11.4.2, dated June 6, 2006 states:Upon satisfactory demonstration that the equipment, facility or air contaminant control device complies with all of the terms and conditions of the construction permit, the Department shall grant approval to operate by issuing an operation permit.
Operation Permit ProcessOperation Permit Process
Construction to Operation Inspection
Request for Operating Inspection (Informal)
DEN
Dover/New Castle
% Complete & Accurate %98
Processing Time Hrs2
Processing Time Days1
Processing Time Hrs4
Production Lead Time Days1
Production Lead Time Wks1
Production Lead Time Days2
Make a form to sign and hand out at the inspection
to provide operating permission
Min
Max
Avg
Min
Max
Avg
EE/ES - 21
2 Days
4 Hrs
Operation Permit ProcessOperation Permit Process
Technical Memorandum and Technical Memorandum and Operation Permit prepared by Operation Permit prepared by Eng/Sci Eng/Sci
Program Manager I reviews Program Manager I reviews the technical memo and the technical memo and Operation PermitOperation Permit 80% of the documents were 80% of the documents were
complete and accuratecomplete and accurate
Operation Permit ProcessOperation Permit Process
Develop Operating Permit and Inspection
Report Memo
Dover/New Castle
% Complete & Accurate %100
Processing Time Hrs1
Processing Time Days2
Processing Time Days1
Production Lead Time Days1
Production Lead Time Wks2
Production Lead Time Wks1
Have good templates for operating permits and
memos
Min
Max
Avg
Min
Max
Avg
PMI Review
Dover/New Castle
% Complete & Accurate %80
Processing Time Hrs1
Processing Time Hrs4
Processing Time Hrs2
Production Lead Time Days1
Production Lead Time Days5
Production Lead Time Days2
EE/ES - 21 PMI - 3
8 Hrs
2 Days
2 Hrs
Operation Permit ProcessOperation Permit Process
Program Manager II reviews Program Manager II reviews the Technical Memorandum the Technical Memorandum and Operation Permit. If and Operation Permit. If ready, the permit is also ready, the permit is also signedsigned 95% of the documents were 95% of the documents were
complete and accuratecomplete and accurate
Operation Permit ProcessOperation Permit ProcessPMII Review and Sign
New Castle
% Complete & Accurate %95
Processing Time Mins15
Processing Time Hrs1
Processing Time Mins30
Production Lead Time Days1
Production Lead Time Days5
Production Lead Time Days2
Date change causes quality problems
PMII - 1
30 Mins
1 Days
Operation Permit ProcessOperation Permit Process
Operation permit issuedOperation permit issued Copied and sortedCopied and sorted Mailed to CompanyMailed to Company Logged in mail logLogged in mail log Distributed Distributed Logged into DENLogged into DEN
Operation Permit ProcessOperation Permit Process
Operating Permit
Customer
Copy, Log, and Distribute
DEN
New Castle
% Complete & Accurate %100
Processing Time Mins30
Production Lead Time Days1-2
Batch Time/Day1
Admin. Specialist for Dover group is in New Castle
AS - 4
1 Days
30 Mins
Lead Time to Issue Operating Permit: 14 Days
Process Time to Issue Operating Permit: 15 Hours
% Complete & Accurate from “Construction to Operation Inspection” to “Copy, Log, and Distribute”: 74%