Validation and Verification Content - NorthernTAG Knight 2015 07 02 EST NTAG... · 1 Validation and...
Transcript of Validation and Verification Content - NorthernTAG Knight 2015 07 02 EST NTAG... · 1 Validation and...
03/07/2015
1
Validation and Verification of
Healthcare Ventilation Systems
Richard Knight CEng, MCIBSE, FIHEEM
Wrightington Hotel & Country Club
3rd July 2015
Content
• Legal requirements
• Designated roles
• Due diligence
• Objectives
• Commissioning
• Validation
• Verification
• Training
Legislation, why do it?
Workplace health, safety and welfare
APPROVED CODE OF PRACTICE L24:1998 now 2013 for the Workplace
(Health, Safety and Welfare) Regulations 1992
Regulation 5 Maintenance of workplace, and of equipment, devices and systems, requires access to be provided to maintain the ventilation and other systems
was
now
Workplace health, safety and welfare
APPROVED CODE OF PRACTICE L24:1998 now 2013 for the Workplace
(Health, Safety and Welfare) Regulations 1992
Regulation 6 Ventilation, requires in (1) Effective and suitable provision shall be made to ensure that every enclosed workplace is ventilated by a sufficient quantity of fresh or purified air.
The Building Regulations 2000 Ventilation approved document
F1:2010 (AMD 2013) • This requires ventilation systems to be
installed to meet HBN and HTM 03-01 and therefore commissioned and validated to these, (6.17)
• Also the approved document requires the systems to be commissioned as req CIBSE commissioning code M
• Not an exhaustive list
03/07/2015
2
The Building Regulations 2000 Ventilation approved document
F1:2010 (AMD 2013) The approved document also requires access
to be provided to maintain
1995 HTM 2023
2010
Part F1 Dig.4
Legislation, Guidance and Standards
Additionally what governs the installation and management of vent systems?
• HSE L8: 2000 now 2013 • Building regulations AD L2A and L2B:2010 AMD 2013 • BSRIA AG3 89.3/2001 Commissioning Air Systems
then BG 47:2013, now BG 47:2015
• CIBSE. Commissioning Code M: Commissioning Management:2003 (ref in AD L2A and L2B)
• CIBSE Commissioning Code A: Air Distribution Systems:1996 (2006)
• Others incl specialist sector such as Health HTM 03
What about other legal requirements?
• The Health and Safety at Work etc Act 1974 (HaSaWA)
• The Management of Health and Safety at Work Regulations 1999
• Control of substances hazardous to health ACOP HS(L)5: 2005 now 2013
• Controlling airborne contaminants at work, A guide to local exhaust ventilation (LEV) HSE HS(G)258:2011
What does DoH say? Comply with the legal requirements
This can be achieved by complying with the following:
• HTM 00: 'Policies and principles':2014
• HTM 03-01 Specialised ventilation for healthcare premises Part A design and installation and part B Operational Management: November 2007
• NHS Model engineering Specification C04 Mechanical ventilation and air conditioning systems 1993 including revisions up to 1997
• HTM 05 Fire Code (parts)
• HBN 00-07 - Resilience planning for the healthcare estates:2014
HTM 00 Policies and principles of healthcare engineering (2014 Edition)
Outlines the requirements, these include:
• Policy and operational policy (or procedures) • Statute and regulation • Professional support • Design and installation • Maintenance • Emergency preparedness • Training, information and communications • Design and safe access to engineering services.
HTM 00, Due diligence
“Any design, installation, commissioning or maintenance work should only be carried out by suitably qualified and authorised contractors.”
So this means: • Designers • Commissioners • Validators • Managers
This additionally “Evidence of current authorisation should be by sight of the correct certificate of
approval”
(HTM 00:2014 3.47)
03/07/2015
3
Designated roles
Recommends the appointment of:
• Designated Persons; (from the Trust Board!)
• Authorising Engineers;
• Authorised Persons;
• Competent Persons.
For each service e.g. water, electricity,
med gas, ventilation systems, etc....
Re affirmed for the fourth time in 7 years By the publication of HTM 00:2014
Commissioning, Validation or Verification?
• Commissioning is carried out by the contractor to set up the systems and demonstrate they work as the design intended
• Validation is carried out by the client when new or after major alterations or changes in air flow, to confirm the system is operating as designed
• Verification what is done at least annually to verify critical ventilation system are working as validated
Commissioning, Validation or verification? Standards
• CIBSE Commissioning A, W, R • Codes and BSRIA Application Guide Set COMPAK 1
this included AG 3/89.3:2001. then BG 47:2013, now BG 47:2015
• HBNs because they give the specialist advice in addition to HTM
• Other HTMs, other DoH guidance • HSE • British standards • European Standards • Other CIBSE
Commissioning
Who are the major players?
• Designers
• Mechanical and electrical contractors
• Duct installers
• AHU manufacturers
• Commissioner
Chapter 8 Validation of specialised ventilation systems HTM 03-01, Details what is required
Design
• Demonstrate that pipework can be installed
• Show volumes and static pressures for all branches and terminals
• Size of ducts
• Show test points to measure pressure and flow
Setting up for success Drawings
Design But if it cannot be measured it cannot be
delivered
Setting up for success Drawings
03/07/2015
4
Ducts step over to extend length of straight duct to accommodate traverse point, opposed blade damper and >10D between to allow space for air flow to settle down See BSRIA BG 47:2015
Supply diffusers
2500mm
Split supply duct To increase straight branch length
Where D is the distance between the blades of the opposed blade damper and their width
Compliant design leads to correct = delivery
Shown at lower level to illustrate solution
Supply diffuser
Supply diffuser
2500mm
Split supply duct To increase straight branch length
Opposed blade dampers Flexible
Test point
>10D
Where D is the distance between the blades of the opposed blade damper and their width
>100mm
Compliant design leads to correct = delivery
Design
• All terminal flow rates
• All plant design conditions
• All plant winter summer design conditions
• All water/steam flow rates and resistances
• All plant performances e.g. air side resistances
• All plant acoustic performance
Setting up for success Specification
Design
Combined for:
• Controls
• Electrical testing/commissioning
• Water commissioning
• Ventilation commissioning
• Infection prevention
• Validator
• Authored Person......
Setting up for success Commissioning Brief
For the system as it is an Engineering system
As the system has to work not just the individual parts
The HTM details this very well
Design
• The BMS set ups
• The BMS interlocks
• The manual/mechanical interlocks
• The static pressures and volumes throughout the system
• The room pressures
• The electrical protection and VSD setups
• Methods of performance testing etc.
Setting up for success Commissioning Brief Details
Designers Commissioning Brief
• Heaters and coolers perform at design conditions
• Volume exceeds design by amount required by HTM with dirty filters, etc.
• Energy recovery devices perform as design
• Humidifier performs at design conditions
• Etc.
Setting up for success AHU Performance Testing
03/07/2015
5
Design
• Testing of fire and smoke dampers
• Confirming safe access to all
• Fire detection and alarm cause and effect matrix
• Interim and final duct pressure testing (and AHU)
• Interim and final duct cleaning
• Etc.
Setting up for success System performance testing
Designers, Commissioning Brief
A reissue to the engineering sub-contractor of the:
Specification and drawings
or
Saying its already in the specification
Setting up for success What does this NOT mean
Design
The specification/contract documents include:
• A schedule of all interruptions
• The commissioning brief
• Commissioning schedules for all engineering works
• Commissioning programme incl information receipt, comment and sign off
Setting up for success A Recommendation
Mechanical Contractors
• Ensure the commissioning brief is received by the commissioning team
• Ensure any alterations are feed into the designers commissioning brief
• Ensure the commissioning report is complete and forms a conclusion
Basic document and quality control
Communicate
Mechanical Contractors
• Ductwork companies
• AHU manufacturers
• Electrical contractors
• BMS contractors
• Duct cleaning contractors
Coordinate
Duct installer
• Ducts are installed as required by HVCA DW 144:2005 now 2013
• Ducts are delivered clean and kept clean as required by HVCA TR 19:1998 now 2013
• Duct leakage testing passes the requirements of HVCA DW 143:1998 now 2013
Quality control and Performance test
This requires an effective monitoring system On larger works the contractor confirms compliance and is penalised if found not to be
03/07/2015
6
AHU Manufacture
Provide type test certificates for components e.g.
• Attenuators, fans, batteries, filters
• Provides pressure testing certificates for all coils, plate recuperators, AHU, etc.
• Fan curves are essential.......
Quality control and Installation
This requires an effective monitoring system On larger works the contractor confirms compliance and is penalised if found not to be
Filters If they do not have BS EN 779
They are not compliant
Commissioner(s)
• Commissions the electrical, wet and ventilation systems,
• To the designers commissioning brief
• To the HTM 03-01A chapter 8 and other clauses
• To CIBSE Comm Codes A, W, R.....
• To BSRIA Comm Codes air water etc.
Standards
Commissioner
• The commissioning report should refer to the brief and commissioning schedules
• Should form a conclusion
• Record the testing methodology (hopefully as defined in the brief )
• Record the performance
• Record the completeness of the installation
• Provide for record calibration certificates
Content Compliant or not?
Turning vanes needed
Blast Plate needed
Dampers not needed Drip tray far too shallow
Partial replacement of AHU, to increase cooling
Replacement Existing remaining
Water eliminator needed coils copper/copper
Poor traverse point
Outside wall with louvre
Setting up for success Including for refurbishments
Common Problems
All to often what the controls are doing!
-5
0
5
10
15
20
25
30
35
40
08:
15:0
0
08:
30:0
0
08:
45:0
0
09:
00:0
0
09:
15:0
0
09:
30:0
0
09:
45:0
0
10:
00:0
0
10:
15:0
0
10:
30:0
0
10:
45:0
0
11:
00:0
0
11:
15:0
0
11:
30:0
0
11:
45:0
0
12:
00:0
0
12:
15:0
0
12:
30:0
0
12:
45:0
0
13:
00:0
0
13:
15:0
0
13:
30:0
0
13:
45:0
0
14:
00:0
0
14:
15:0
0
14:
30:0
0
14:
45:0
0
15:
00:0
0
15:
15:0
0
15:
30:0
0
15:
45:0
0
16:
00:0
0
16:
15:0
0
16:
30:0
0
16:
45:0
0
17:
00:0
0
17:
15:0
0
17:
30:0
0
17:
45:0
0
18:
00:0
0
18:
15:0
0
18:
30:0
0
18:
45:0
0
19:
00:0
0
Outside Air Temp
Off Frost Coil Temp
Off Cooler Temp
Reheat Valve Pos
Supply Temp
Theatre Temp
Supply Humidity
Theatre Humidity
Controls
03/07/2015
7
Incorrectly located test point
Measuring air flows
Validation
So as earlier
• Validation is carried out by the client when new or after major alterations or changes in air flow, to confirm the system is operating as designed
Validation
So as earlier
This does include, the:
• Air flows
• Air velocities
• Plant performance
• Controls
• Water flow rates....... Not just the air flow rates or the air side performance
Advantages
Can commissioning and validation of ventilation systems be an advantage to:
reduced risk during delivery and especially in use • Clients,
• Designers,
• Installers,
• Main Contractors,
• Commissioners.
reduced total time to implement “prepare for success”
reduced time to install and commission
reduced time pressures at end of job
reduced time to commission and having to manage fails
Personal risk to all reduced
Verification
Verification
Compares:
• The condition of the system
• The operation of controls
• The operation of fire precautions
• The performance of the system
All with respect to the validation Report
Objectives
Just the same as when carrying out electrical periodic inspection tests
Must form a conclusion, is it compliant, is it safe to use?
03/07/2015
8
What did the order say? For a verification of a healthcare ventilation
system
You would hope, it would say something like?
Please carry out verification of xxxxx at yyyy in accordance with HTM 03-01 for the sum of......
Output: Getting the report the HTM requires
What did the order say?
For a verification of a healthcare ventilation system
You would hope, it would say something like? Please carry out verification of xxxxx at yyyy in
accordance with HTM 03-01 for the sum of...... Watch out for order confirmations Confirming works carried out to their quotation
of.......perhaps limiting the works
What did the order say?
For a verification of a healthcare ventilation system
You would hope, it would say something like? Please carry out verification of xxxxx at yyyy in
accordance with HTM 03-01 for the sum of...... Watch out for reports Stating or recording the works carried out,
thereby limiting the scope of the report
For the report
• As with commissioning reports and validation reports they should be unconditional
• Just confirming at the beginning of the report in accordance with HTM 03-01
Annual inspection and verification requirements
Should be inspected annually
The inspection shall establish:
a. the system is still required;
b. the AHU conforms to the minimum standard (see Chapter 3);
c. the fire containment has not been breached;
d. the general condition of the system is adequate for purpose;
e. the system overall is operating in a satisfactory manner. (4.2)
Recommends use of check sheets
in appendices 1 and 2 (4.3)
Annual inspection and verification requirements
Critical ventilation systems
All ventilation systems shall be inspected quarterly and verified
annually (4.4)
the quarterly inspection should be as 4.1-4.3 (4.5)
the annual inspection shall be to ensure the system:
a. achieves the minimum standards specific to the application
b. is operating to an acceptable performance level
c. remains fit for the purpose
03/07/2015
9
Annual inspection and verification requirements
Definition of a critical system
a. operating theatres of any type, including rooms used for interventional
investigations (for example catheter laboratories);
b. patient isolation facility of any type;
c. critical care, intensive treatment or high dependency unit;
d. neonatal unit;
e. Category 3 or 4 laboratory or room;
f. pharmacy aseptic suite;
g. inspection and packing room in a sterile services department;
h. MRI, CAT and other types of emerging imaging technologies that require particularly stable environmental conditions to remain within calibration;
j. any system classified as an LEV system under the COSHH Regulations;
k. any other system that clearly meets the definition. (4.7)
Annual inspection and verification requirements
Annual verification
a. the system is still required;
b. the AHU conforms to the minimum standard (see Chapter 3);
c. the fire containment has not been breached;
d. the general condition of the ventilation system is adequate;
e. the fabric of the area served is satisfactory;
f. the system performance is adequate with respect to the functional requirement – this will require:
(i) a full measure of the supply and extract air-flow rates;
(ii) the calculation of room air-change rates if applicable;
(iii) the measurement of room differential pressures if applicable;
(iv) the measurement of room noise levels;
(v) air-quality checks if appropriate;
(vi) a check on the control functions.(HTM 03-01B 4.9)
Annual inspection and verification requirements
Fabric condition a. the ceiling should be complete and, if tiled, all tiles should be
clipped down and sealed; (note HTM 60 banned the use of tiles as fire barriers, clinical rooms are often required to be fire rated see HTM 05-02)
b. the walls and floors should be free from significant construction and finish defects;
c. windows and their trickle vents should be sealed and locked shut; d. the doors should close completely and the door closers should be
correctly adjusted to hold them against the room pressure; e. all service penetrations and access panels should be sealed to
prevent uncontrolled air flow between rooms and service voids; f. steps should have been taken (if necessary) to prevent portable
equipment and stock items from obstructing low-level supply, transfer or extract air-flow paths..(4.11)
70
Annual inspection and verification requirements
Critical ventilation systems-verification standards All ventilation systems should achieve not less than 75% of the air change rates given in appendix 2,
or its design (4.16) (would not recommend this for LEV and other legislation)
All ventilation systems should achieve not less than 75% of the pressure values given in appendix 2,
or its design (4.17)
All ventilation systems should achieve the sound levels in table 2 (4.18)
There is absolutely no interest in anything less than 100% for the European healthcare ventilation standard
Annual inspection and verification requirements
Critical ventilation systems-verification standards
UCV theatres Generally as part A, note velocities remain at 100%, filter challenge only needed if the HEPAs are damaged, disturbed or replaced (Note after 4.20)
Category 3 and 4 labs and rooms
Refer to current guidance from “advisory committee on dangerous pathogens” and HSE (4.25) would suggest this is 100% of design and guidance
Pharmacy aseptic suites
Refer to current guidance from ”European guide to good manufacturing practice” (4.26) link given should read http://ec.europa.eu/health/documents/eudralex/index_en.htm would suggest this is 100% of design and guidance
Critical system verification failure
Should a system fail it should be taken out of service
If for medical reasons the system has to remain in use, the senior manager of the department should be informed in writing is “suboptimal”. A copy of the notice should be sent to the infection control committee (4.29)
03/07/2015
10
Appendix 1 –
Annual inspection of critical
ventilation systems
Appendix 2 – Operating suite annual verification
03/07/2015
11
• The appendices do not cover all the verification requirements of HTM 03-01B
• The HTM has many, many more requirements for Verification see chapters 3, 4 and 5 of Part B, and Part A
What should be verified
The appendices do not cover all the verification requirements of HTM 03-01B
What should be verified
Sadly most commissioning reports and validation reports do not cover all the validation requirements of HTM 03-01A
What should be validated
Some common problems
Theatre X
Report Content
Good Headings
This looks a bit odd?
Theatre X
Its a clean room!
03/07/2015
12
Any one for a swim
The verification (or validation) report should ask and answer Is there a statement regards Legionella risk? (3.1)
- Fan
Air Flow Direction
If the trap dries out the flood can occur
-ve -ve
Demonstration fire barriers
Are fire precautions in accordance with Firecode? (3.7)
Also as last years EFA Exactly as when we test electrical circuits
Does the report record all the extracts including those in the corridors?
Some one nicked the extract grille We seem to be seriously short of extract for this theatre Has some on stolen others?
How were the measurements made?
• For example are the air volumes measured correctly as required by for example CIBSE, BSRIA (these named in HTM)
• So this would mean recording where duct measurements
taken, grille correction factors
• If these could not be done, then the figures obtained can not be relied on
• In all cases the report should be clear • Not just say “not possible.....”
Motorised damper fitted Honeywell N2024-SW2
The diagram from Honeywell installation manual for this actuator Confirms this not fitted with spring return as required by HTM 03-01A 6.29
Did the dampers close?
Could the filters
support combustion?
Much evidence the insect screen fitted as required by HTM, does not stop feathers
The filter correctly asserts it has been manufactured to meet BS 779 But would “support combustion” not permitted by HTM Do Verifications pick these up? (3.12)
03/07/2015
13
Can the AHU be accessed?
(3.13.....et al)
AHU intakes and discharges
Verifications should ask and answer are Intake and discharge points situated where they
will cause vitiated air to be drawn into a System? (3.21)
Fresh Air Intake
Exhaust air discharge
If no diagram not easy to say in report, same for all AHU components
Fire dampers
Have all fire dampers been tested as part of the annual verification (4.13)
They are often not installed correctly often easy to inspect, if not say they cannot be seen, and recommend an access door
Controls
a check on the control functions is required in the verification. (4.9f vi)
The objective to protect the patient These should be checked, these were not working correctly see staining
The objective to keep systems available And this closed a NICU for a week all because the controls were not setup correctly
Water carry over from the chiller battery
One of the many uses of inco pads
Pressure stabiliser damaged and unstable in operation generating noise the blade also appears to be installed the wrong way around
UCV Grids These were greater than 6% out of tolerance In this case the verifier did not measure the supply ventilation rate.
In other cases the verifier has reported over 100 air changes....
Because the verification was not carried out correctly the closed fire dampers were missed for years
03/07/2015
14
And what about the extracts in the corridors
Training
• Qualification
• Competency
• Assessment
• Appointment
HTM 00:2014 (and the earlier versions) has a chapter on this and so does HTM 03-01 This includes the AE, AP, CP, Verifier etc.
Training
General
All personnel employed in the design, operation and maintenance of engineering services, including maintenance personnel and operators, should receive adequate, documented training. Personnel should not commence their duties until this training has been completed, competency has been validated and detailed operating instructions have been provided. (6.1)
Those required to monitor and/or maintain ventilation equipment will need to show that they are competent to do so.
From HTM03-01B:2007 1.19
What is this guy on!!
PDF and Slides Richard Knight
Thank you
• Richard Knight
• Mobile 077 949 14 211
• Email [email protected]