VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA...
Transcript of VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA...
VA SIOUX FALLS
PHARMACY ADDITION FOR USP COMPLIANCE
Sioux Falls, South Dakota
VA Project #438-500
SGA # 181906
Project Narratives:
100% Bid Set
December 21, 2018
Architectural Design Narrative VA Project #438-500 P a g e 1 | 1
Architectural Design Narrative
VA Project #438-500
VA Contract #36E77618C0023
December 11, 2018
U.S. Department of Veterans Affairs Royal C. Johnson Veterans Memorial Center Phase II – Sioux Falls Pharmacy Addition for USP 800 Compliance Building #5
Summary of Work:
The current pharmacy at the Sioux Valls VA Medical Center does not meet USP 800 standards and is inadequate in size and
storage for current and future needs. The VA is requiring USP 800 compliance by December 2019. After discussing multiple
options, we determined the best choice to accomplish the goal would be to add a pharmacy adjacent to Oncology and
Occupational Therapy. After completion, the addition will be able to accommodate all compounding needs while the current
pharmacy is remodeled to be compliant with USP 800 standards in a future project. When both pharmacies are USP 800
compliant, this new pharmacy will be solely used for the adjacent Oncology department.
This project was limited to 2,300 SF and the location of the new pharmacy requires moving the Occupational Therapy treatment
rooms and work stations. Care was taken to maintain the current amount of space and storage in Occupational Therapy. Staff in
this department would have liked to maintain their exterior view, but this was impossible due to the existing grade elevation. To
compensate for this loss of exterior view and in an effort to save money and reduce waste, we chose to reuse their existing
windows and added an additional one to provide exceptional amounts of natural daylight into the space.
To connect the pharmacy to Oncology, the Oncology break room needed to be partially relocated into this addition. This was the
best option to interfere as little as possible with the Oncology ward, which was just completed in the spring on 2018. Our
addition also interfered with some windows in Oncology. Many options were discussed and we chose to make them a feature.
Our main determinates here were again, not wanting to interfere with the Oncology infrastructure or operations and not
wanting our alterations to cost a lot of money.
Blast and physical security requirements played a large role early in the design process, but it was later determined that this
addition is designed as an extension of the existing building so we received permission to use the design standards of the
existing building. Designing and building for blast and physical security requirements would have elongated the length of the
project and made it extremely difficult to meet all USP 800 requirements by the due date set by the VA.
This project was an extension of fairly recent additions, so no accommodation for hazardous materials was necessary.
Key Challenges:
The successful timeline of this project required excavation and footings to be completed before harsh winter conditions set in,
which was only 3 months after design began. This project being completed as Design/Build was critical to its success. The project
also required phasing to keep Occupational Therapy and Oncology operational with as little down time as possible.
This project required the relocation and accommodation of multiple mechanical units and a steam line. Three mechanical units
were relocated to the roof of the facility. After the 30% design submission, the location of the steam line was determined. The
cost of relocating the steam line was prohibitive so the addition was modified to accommodate the line as it is.
Interior Narrative:
The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards and Finishes, VA
Interior Design Manual - May 2018 and VA Room Finishes, Door & Hardware Schedule Program Guide, pg 18-14- April 2017 Rev.
5/2017. The colors, patterns and application were coordinated with the existing finishes in Oncology and Occupational Therapy
with assistance and approval from the Interior Designer at the Sioux Falls VA Medical Center.
EHRHART GRIFFIN & ASSOCIATES • 300 N. DAKOTA AVE, SUITE 114 • SIOUX FALLS, SOUTH
DAKOTA 57104 • 605-339-7215
www.ehrhartgriffin.com
memo To: Todd Stone AIA, Stone Group Architects
From: Gregory B. Gerardy EI, Ehrhart Griffin & Associates
cc: Damian Grable PE LS, Ehrhart Griffin & Associates
Date: December 11, 2018
Project: (VA#438-500), (SGA#181906), (EGA#SD181135) Sioux Falls VA – Pharmacy Addition
Re: Civil Narrative for 100% Submittal
Design Overview:
The Sioux Falls VA - Pharmacy Addition civil site plan, is being designed using the most current additions of the
Veterans Affairs, City of Sioux Falls, and state of South Dakota design manuals and specifications. A poured
concrete structural retaining wall was discussed and determined to be utilized to protect ground cover over the
existing steam line, and allow access to the emergency exit. The proposed grading was designed for minimal impact
to the surrounding surface and follow existing drainage patterns.
• Existing Conditions:
The following are all within the foot print of the proposed addition, existing sidewalk, existing area inlet,
existing 8-inch water line, post indicator valve (PIV) with 6-inch water service line, and MRI utility
structures. All of these shall be removed or relocated outside of the footprint of the addition. The
relocation of the MRI utility structures was determined by the mechanical engineer. The rest were
determined by the civil engineer.
• Layout Design:
The existing steam line was potholed, and field located. This caused the location and geometry of the floor
plan and retaining wall to be redesigned and revised after the 30% Design Submittal. The retaining wall
shall be a poured concrete wall designed by a structural engineer. The proposed sidewalk was designed in
accordance with the most current Americans with Disabilities Act (ADA) design standards.
• Grading and Erosion Control Design:
The proposed grading was designed to drain to the east and away from the existing and proposed buildings.
Where it would be captured by the existing storm sewer system. The second design constraint was to keep
sufficient cover over the steam pipe and other existing utilities.
The limits of grading and reseeding areas were initially set at the edge of the match line between the
proposed grading and the existing surface. Following the 60% Review comments these areas were
extended north to the edge of sidewalk. Expanding these areas covers any damage to existing grass that
may occur during construction. Silt fence is to be installed to the east of the project at the edge of grading.
• Utility Design:
The existing sanitary, water and drainage services within the Rehab and Oncology Additions are being
continued and will pick up the internal plumbing for the proposed addition. A new area inlet will be
installed to capture the runoff from the sidewalk between the retaining wall and the addition. This will be
connected to the existing 6-inch drainage pipe. The fire service 8-inch water line and PIV were relocated
north west of the addition and reconnected to the 6-inch service entering the building. This was done to
keep the water lines from running under the addition’s footing. After the 60% Design Submittal and upon
excavation an existing 8-inch city owned water line was located and presumed to run under the proposed
EHRHART GRIFFIN & ASSOCIATES • 300 N. DAKOTA AVE, SUITE 114 • SIOUX FALLS, SOUTH
DAKOTA 57104 • 605-339-7215
www.ehrhartgriffin.com
footing. It was determined to use bends and reroute the existing water line around the proposed footing if
needed.
VA Review Comments, and Responses:
• 30% Review:
1. No comments regarding civil plans.
• 60% Review:
1. Please detail the temporary egress path from the Oncology exit door once sidewalk is
demo’d.
▪ Keynote number eleven was added to sheet 5.CD101, along with a hatch of the
designated egress pathway that needs to be maintained during construction. GBG
2. Remove concrete cofferdam on area drain and make pipe continuous.
▪ Concrete cofferdam will be removed with the area inlet. The remaining pipe should be
continued by the plumbing plan to connect to any interior drains. No changes made to
civil plans. GBG
3. Show where the three MRI cooling units are moving to.
▪ The new location for the MRI units shall be determined in the field by the mechanical
engineer, and shown on mechanical plans. No changes made to civil plans. GBG
4. PIV needs power and data, please place on electrical plan.
▪ The electrical connection should be shown and designed by the electrical engineer. No
changes made to civil plans. GBG
5. May need to extend the seed/mulch/fertilize line to sidewalk (see dwg).
▪ Limits of grading and seed, mulch, fertilize area was expanded to match the sidewalk to
the north, see sheet 5.CG102. GBG
• 90% Review:
1. No comments regarding civil plans.
315 N Main Ave Suite 200 Sioux Falls, SD 57104
(605) 343-9606
Page 1 of 4
A l b er t s on En gi n e er i n g I n c .
PROJECT MEMORANDUM
Date: December 21, 2018 To: Todd Stone – Stone Group Architects From: Aaron Hartwell Project: Sioux Falls VA – Pharmacy Addition Project #: 2018‐204 RE: Structural Narrative for 100% Submittal
STRUCTURAL NARRATIVE Design Overview The pharmacy addition, hereafter referred to as the Facility, is being structurally designed in accordance with the International Building Code (IBC) and applicable Dept. of Veterans Affairs design manuals. Specifically, the Facility remodel is being designed to meet the requirements of the IBC 2015, ASCE 7‐10 (Minimum Design Loads for Buildings and Other Structures), and the following Dept. of Veterans Affairs design manuals: Physical Security Design Manual Mission Critical Facilities, Jan 2015, Structural Design Manual, Feb. 2014 and the Seismic Design Requirements H‐18‐8, Oct. 2016. For the most part, all other national design codes and Veterans Affairs documents are referenced from these governing regulations. Structural System(s) Selection and Overview The addition to the existing facility is planned to be a steel framed bearing system with exterior non‐load bearing metal stud walls and conventional cast‐in‐place concrete spread foundations. Addition to the existing structure will be separated to act independently of applied loads:
Foundations: Based upon the existing construction, the foundations for the addition are planned to be cast‐in‐place concrete with elevations to match existing where they tie in. Foundations will be designed to the allowable bearing capacity of the soils that were indicated on the original construction documents and modified by construction documents of additions to the building in the area the planned addition is located.
Exterior Walls: Planned to be metal studs supporting brick veneer. Exterior walls will be non‐load bearing with slip connection at the top of wall
Interstitial Floors: Planned to be a concrete slab on metal deck supported by steel joists. Interior bearing stud walls to support joists.
Roofs: The roof framing for the addition is planned to be steel construction with metal roof deck. The steel framing will provide an economical solution to support gravity and lateral loading.
315 N Main Ave Suite 200 Sioux Falls, SD 57104
(605) 343-9606
Page 2 of 4
A l b er t s on En gi n e er i n g I n c .
Analysis Method(s) The bulk of the design of the facility remodel is being performed using hand calculations and by model software such as Risa 3D when required. New structure to be framed independently of existing building. No analysis of existing framing will be done except where new addition casts a snowdrift load on the existing roof to verify vertical load carrying capacity only. Design Loads The facility will be designed for the Dead Load (self weight) of the structure and the following superimposed loads:
Occupancy Category: The facility is regarded as an Essential Facility having a Type IV Occupancy in accordance with IBC 2015, ASCE 7‐10, and the VA Structural Design Manual due to the building being a hospital with surgery functions.
Live Load: In accordance with IBC 2015, ASCE 7‐10 and the VA Structural Design Manual as follows:
1. Typical Floor ...................................................................... 80 psf + 20 psf Partition 2. Lobbies & Main Corridors ................................................. 100 psf 3. Storage (Light) ................................................................... 150 psf 4. Mechanical Rooms ............................................................ 150 psf
Snow Load: In accordance the with IBC 2015 and ASCE 7‐10 and local codes, use the following: 1. Minimum Roof Snow ........................................................ 36 psf (includes importance) 2. Ground Snow .................................................................... 40 psf 3. Importance Factor ............................................................ 1.2
Other: Special case loadings are designed to be supported based on their actual weight and configurations. In addition, floors shall be designed to accommodate a 2000 Lb. load placed anywhere on the floor in a 2.5 square area based on the VA Structural Design Manual.
Foundations The new addition will be founded on conventional spread footings designed to meet the allowable soil bearing criteria that was used in original building design and modified by construction documents of existing additions to the building in the area the planned addition is located. Footing elevations will be stepped as required to match existing foundations and to step with changes in grade around the addition Subgrade preparation for the footings and floor slabs shall be in accordance with available soils investigations from previous addition projects to the hospital.
315 N Main Ave Suite 200 Sioux Falls, SD 57104
(605) 343-9606
Page 3 of 4
A l b er t s on En gi n e er i n g I n c .
Interstitial Floor Framing Floor framing supporting mechanical load above main floor are planned to be composed of a concrete slab on metal deck. Steel joists spanning from interior bearing walls will support deck. Roof Framing The roof framing will be 1.5” metal roof deck supported by steel joist framing. Steel joists are planned to be supported by steel beam and column lines. Deflection and Drift Limits Deflection limits criteria for design of structural members are not greater than allowed by the applicable material standard (ACI, AISC, etc.), and IBC 2015 as follows:
Roof Members: 1. Supporting Plaster (Hard) Ceilings .................................... L/360 Snow, L/240 Total 2. Supporting Ceiling (Hung) ................................................. L/240 Snow, L/180 Total 3. Not Supporting Ceiling ...................................................... L/180 Snow, L/120 Total
Floor Members ............................................................................... L/360 Live, L/240 Total
Walls: 1. Wind .................................................................................. L/240
Materials The Facility will be designed for the following materials strengths to be used in construction:
Concrete (f’c): 1. Foundation Walls & Footings ............................................ 3,000 psi
Reinforcing Steel: 1. Standard Deformed .......................................................... ASTM A615, Grade 60
Structural Steel: 1. WF Shapes ......................................................................... ASTM A992 (50 ksi) 2. Misc. Shapes / Plates ........................................................ ASTM A36 (36 ksi) 3. Structural Tubes ................................................................ ASTM A500, Grade B (46 ksi) 4. Structural Pipes ................................................................. ASTM A53, Type E, Grade B (35 ksi)
Special Inspections Structures designed in accordance with IBC 2015 are required to have “special inspections” performed during the construction of the project. “Special Inspections” are quality control inspections and testing that are performed on a periodic basis to ensure the adequacy of construction. The Facility will have special inspections performed during the construction of the project meeting the requirements of IBC 2015 at a minimum as follows:
315 N Main Ave Suite 200 Sioux Falls, SD 57104
(605) 343-9606
Page 4 of 4
A l b er t s on En gi n e er i n g I n c .
Steel Construction .......................................................................... Table 1704.3
Concrete Construction ................................................................... Table 1704.4
Open Web Steel Joists ................................................................... Table 1705.2.3
SK -
1
FRAM
ING
Rev
ised
no
blas
t.r3d
HSS6X6X4
HSS6X6X4
HSS6X6X4
HSS6X6X4
HSS6X6X4
HSS6X6X4
HSS6X6X4
W16
X40
W16
X40
W16
X40
W16
X40
W18
X50
W16
X31
.75 Bar.7
5 Ba
r
.75
Bar
.75 Bar
.75 Bar
.75
Bar
HSS6X6X4
HSS6X6X4
W16
X40
W16X40
W16
X40
HSS6X6X4
Y
XZ
Hot
Rol
led
Stee
l Pro
pert
ies
Labe
lE
[ksi
]G
[ksi
]N
uTh
erm
(\1E
5 F)
Den
sity
[k/ft
^3]
Yiel
d[ks
i]R
yFu
[ksi
]R
t1
A992
2900
011
154
.3.6
5.4
950
1.1
651.
12
A36
Gr.3
629
000
1115
4.3
.65
.49
361.
558
1.2
3A5
72 G
r.50
2900
011
154
.3.6
5.4
950
1.1
651.
14
A500
Gr.C
RN
D29
000
1115
4.3
.65
.49
461.
462
1.3
5A5
00 G
r.C R
ect
2900
011
154
.3.6
5.4
950
1.4
621.
36
A53
Gr.B
2900
011
154
.3.6
5.4
935
1.6
601.
27
A108
529
000
1115
4.3
.65
.49
501.
465
1.3
8A3
6 Br
ace
2900
011
154
.3.6
50
361.
558
1.2
Mem
ber P
rimar
y D
ata
Labe
lI J
oint
J Jo
int
K Jo
int
Rot
ate(
deg)
Sect
ion/
Shap
eTy
peD
esig
n Li
stM
ater
ial
Des
ign
Rul
es1
M1
N6
N13
HSS
6X6X
4C
olum
nTu
beA5
00 G
r.C R
ect
Typi
cal
2M
3N
7N
14H
SS6X
6X4
Col
umn
Tube
A500
Gr.C
Rec
tTy
pica
l3
M4
N3
N10
HSS
6X6X
4C
olum
nTu
beA5
00 G
r.C R
ect
Typi
cal
4M
5N
4N
11H
SS6X
6X4
Col
umn
Tube
A500
Gr.C
Rec
tTy
pica
l5
M6
N5
N12
HSS
6X6X
4C
olum
nTu
beA5
00 G
r.C R
ect
Typi
cal
6M
7N
1N
8H
SS6X
6X4
Col
umn
Tube
A500
Gr.C
Rec
tTy
pica
l7
M8
N2
N9
HSS
6X6X
4C
olum
nTu
beA5
00 G
r.C R
ect
Typi
cal
8M
10N
12N
11W
16X4
0Be
amTu
beA9
92Ty
pica
l9
M11
N11
N10
W16
X40
Beam
Tube
A992
Typi
cal
10M
12N
10N
13W
16X4
0Be
amTu
beA9
92Ty
pica
l11
M13
N8
N9
W16
X40
Beam
Tube
A992
Typi
cal
12M
15N
19N
14W
18X5
0Be
amTu
beA9
92Ty
pica
l13
M16
N12
N8
W16
X31
Beam
Tube
A992
Typi
cal
14M
18N
5N
11.7
5 Ba
rH
Brac
eN
one
A36
Brac
eTy
pica
l15
M19
N4
N12
.75
Bar
HBr
ace
Non
eA3
6 Br
ace
Typi
cal
16M
20N
12N
1.7
5 Ba
rH
Brac
eN
one
A36
Brac
eTy
pica
l17
M21
N5
N8
.75
Bar
HBr
ace
Non
eA3
6 Br
ace
Typi
cal
18M
22N
1N
9.7
5 Ba
rH
Brac
eN
one
A36
Brac
eTy
pica
l19
M23
N2
N8
.75
Bar
HBr
ace
Non
eA3
6 Br
ace
Typi
cal
20M
23A
N15
N16
HSS
6X6X
4C
olum
nTu
beA5
00 G
r.C R
ect
Typi
cal
21M
24N
17N
18H
SS6X
6X4
Col
umn
Tube
A500
Gr.C
Rec
tTy
pica
l22
M25
AN
13N
16W
16X4
0Be
amW
ide
Flan
geA9
92Ty
pica
l23
M26
N18
N19
W16
X40
Beam
Wid
e Fl
ange
A992
Typi
cal
24M
28N
9N
18W
16X4
0Be
amW
ide
Flan
geA9
92Ty
pica
l25
M26
AN
187
N18
6H
SS6X
6X4
Col
umn
Tube
A500
Gr.C
Rec
tTy
pica
l
Hot
Rol
led
Stee
l Des
ign
Para
met
ers
Labe
lSh
ape
Leng
th[ft
]Lb
yy[ft
]Lb
zz[ft
]Lc
omp
top[
ft]Lc
omp
bot[f
t]L-
torq
ue[ft
]Ky
yKz
zC
bFu
nctio
n1
M1
HSS
6X6X
419
Late
ral
2M
3H
SS6X
6X4
19La
tera
l3
M4
HSS
6X6X
419
Late
ral
RIS
A-3D
Ver
sion
17.
0.0
Page
1 [Z
:\201
8\20
1820
4\D
-Des
ign
Cal
cula
tions
\RIS
A\FR
AMIN
G R
evis
ed n
o bl
ast.r
3d]
Hot
Rol
led
Stee
l Des
ign
Para
met
ers
(Con
tinue
d)La
bel
Shap
eLe
ngth
[ft]
Lbyy
[ft]
Lbzz
[ft]
Lcom
p to
p[ft]
Lcom
p bo
t[ft]
L-to
rque
[ft]
Kyy
Kzz
Cb
Func
tion
4M
5H
SS6X
6X4
19La
tera
l5
M6
HSS
6X6X
419
Late
ral
6M
7H
SS6X
6X4
19La
tera
l7
M8
HSS
6X6X
419
Late
ral
8M
10W
16X4
020
5Lb
yyLa
tera
l9
M11
W16
X40
205
Lbyy
Late
ral
10M
12W
16X4
024
.997
5Lb
yyLa
tera
l11
M13
W16
X40
265
Lbyy
Late
ral
12M
15W
18X5
035
.85
5Lb
yyLa
tera
l13
M16
W16
X31
405
Lbyy
Late
ral
14M
18.7
5 Ba
r27
.586
Late
ral
15M
19.7
5 Ba
r27
.586
Late
ral
16M
20.7
5 Ba
r44
.283
Late
ral
17M
21.7
5 Ba
r44
.283
Late
ral
18M
22.7
5 Ba
r32
.202
Late
ral
19M
23.7
5 Ba
r32
.202
Late
ral
20M
23A
HSS
6X6X
419
Late
ral
21M
24H
SS6X
6X4
19La
tera
l22
M25
AW
16X4
04
5Lb
yyLa
tera
l23
M26
W16
X40
7.77
85
Lbyy
Late
ral
24M
28W
16X4
07.
071
Lbyy
Late
ral
25M
26A
HSS
6X6X
419
Late
ral
Bas
ic L
oad
Cas
esBL
C D
escr
iptio
nC
ateg
ory
X G
ravi
tyY
Gra
vity
Z G
ravi
tyJo
int
Poin
tD
istri
bute
dAr
ea(M
emb.
..Su
rface
(Pla
t...
1D
ead
DL
-15
2Li
veLL
53
Snow
SL5
4W
ind
XW
LX2
55
Win
d Z
WLZ
15
6Bl
ast N
/SO
L11
57
Blas
t E/W
OL2
25
8BL
C 1
Tra
nsie
nt A
rea
Load
sN
one
979
BLC
2 T
rans
ient
Are
a Lo
ads
Non
e97
10BL
C 3
Tra
nsie
nt A
rea
Load
sN
one
9711
BLC
4 T
rans
ient
Are
a Lo
ads
Non
e97
12BL
C 5
Tra
nsie
nt A
rea
Load
sN
one
97
RIS
A-3D
Ver
sion
17.
0.0
Page
2 [Z
:\201
8\20
1820
4\D
-Des
ign
Cal
cula
tions
\RIS
A\FR
AMIN
G R
evis
ed n
o bl
ast.r
3d]
Load
Com
bina
tions
Des
crip
tion
Solv
ePD
el...
SRSS
BLC
Fact
orBL
CFa
ctor
BLC
Fact
orBL
CFa
ctor
BLC
Fact
orBL
CFa
ctor
BLC
Fact
orBL
CFa
ctor
BLC
Fact
orBL
CFa
ctor
1IB
C 1
6-1
Yes
YD
L1.
42
IBC
16-
2 (a
)Ye
sY
DL
1.2
LL1.
6LL
S1.
63
IBC
16-
2 (b
)Ye
sY
DL
1.2
LL1.
6LL
S1.
6SL
.5SL
N.5
4IB
C 1
6-3
(c)
Yes
YD
L1.
2SL
1.6
SLN
1.6
LL.5
LLS
15
IBC
16-
3 (b
) (a)
Yes
YD
L1.
2W
LX.5
6IB
C 1
6-3
(b) (
b)Ye
sY
DL
1.2
WLZ
.57
IBC
16-
3 (d
) (a)
Yes
YD
L1.
2SL
1.6
SLN
1.6
WLX
.58
IBC
16-
3 (d
) (b)
Yes
YD
L1.
2SL
1.6
SLN
1.6
WLZ
.59
IBC
16-
4 (a
) (a)
Yes
YD
L1.
2W
LX1
LL.5
LLS
110
IBC
16-
4 (a
) (b)
Yes
YD
L1.
2W
LZ1
LL.5
LLS
111
IBC
16-
4 (b
) (a)
Yes
YD
L1.
2W
LX1
LL.5
LLS
1SL
.5SL
N.5
12IB
C 1
6-4
(b) (
b)Ye
sY
DL
1.2
WLZ
1LL
.5LL
S1
SL.5
SLN
.513
IBC
16-
6 (a
)Ye
sY
DL
.9W
LX1
14IB
C 1
6-6
(b)
Yes
YD
L.9
WLZ
115
BLAS
TY
DL
1O
L11
16IB
C 1
6-8
Yes
DL
117
IBC
16-
9Ye
sD
L1
LL1
LLS
118
IBC
16-
10 (b
)Ye
sD
L1
SL1
SLN
119
IBC
16-
11 (b
)Ye
sD
L1
LL.7
5LL
S.7
5SL
.75
SLN
.75
20IB
C 1
6-12
(a) (
a)Ye
sD
L1
WLX
.621
IBC
16-
12 (a
) (b)
Yes
DL
1W
LZ.6
22IB
C 1
6-13
(a) (
a)Ye
sD
L1
WLX
.45
LL.7
5LL
S.7
523
IBC
16-
13 (a
) (b)
Yes
DL
1W
LZ.4
5LL
.75
LLS
.75
24IB
C 1
6-13
(b) (
a)Ye
sD
L1
WLX
.45
LL.7
5LL
S.7
5SL
.75
SLN
.75
25IB
C 1
6-13
(b) (
b)Ye
sD
L1
WLZ
.45
LL.7
5LL
S.7
5SL
.75
SLN
.75
26IB
C 1
6-15
(a)
Yes
DL
.6W
LX.6
27IB
C 1
6-15
(b)
Yes
DL
.6W
LZ.6
28Bl
ast 2
YD
L1
OL2
1
Enve
lope
AIS
C 1
4th(
360-
10):
LRFD
Ste
el C
ode
Che
cks
Mem
ber
Shap
eC
ode
Che
ckLo
c[ft]
LCSh
ear C
heck
Loc[
ft]D
irLC
phi*P
nc [k
]ph
i*Pnt
[k]
phi*M
n y-
y [k
-ft]
phi*M
n z-
z [k
-ft]
Cb
Eqn
1M
1H
SS6X
6X4
.288
194
.004
0z
411
7.51
823
5.8
4242
1.67
4H
1-1b
2M
3H
SS6X
6X4
.164
194
.002
0y
411
7.51
823
5.8
4242
1.67
4H
1-1b
3M
4H
SS6X
6X4
.480
194
.006
0z
411
7.51
823
5.8
4242
1.67
4H
1-1a
4M
5H
SS6X
6X4
.344
04
.002
0y
1311
7.51
823
5.8
4242
2.25
1H
1-1a
5M
6H
SS6X
6X4
.238
194
.006
0y
411
7.51
823
5.8
4242
2.16
5H
1-1b
6M
7H
SS6X
6X4
.466
194
.013
0y
411
7.51
823
5.8
4242
2.17
1H
1-1a
7M
8H
SS6X
6X4
.599
194
.011
0y
411
7.51
823
5.8
4242
2.17
7H
1-1a
8M
10W
16X4
0.2
919.
333
4.1
100
y4
446.
675
531
47.6
2527
3.75
1H
1-1b
9M
11W
16X4
0.2
7710
.222
4.0
8820
y4
446.
675
531
47.6
2527
3.75
1H
1-1b
10M
12W
16X4
0.3
3112
.499
4.0
9724
.997
y4
431.
523
531
47.6
2527
3.75
1H
1-1b
11M
13W
16X4
0.5
3013
4.1
330
y4
427.
202
531
47.6
2527
3.75
1H
1-1b
12M
15W
18X5
0.8
487.
967
4.1
078.
365
y4
497.
8466
1.5
62.2
510
7.57
71.
338
H1-
1b
RIS
A-3D
Ver
sion
17.
0.0
Page
3 [Z
:\201
8\20
1820
4\D
-Des
ign
Cal
cula
tions
\RIS
A\FR
AMIN
G R
evis
ed n
o bl
ast.r
3d]
Enve
lope
AIS
C 1
4th(
360-
10):
LRFD
Ste
el C
ode
Che
cks
(Con
tinue
d)M
embe
rSh
ape
Cod
e C
heck
Loc[
ft]LC
Shea
r Che
ckLo
c[ft]
Dir
LCph
i*Pnc
[k]
phi*P
nt [k
]ph
i*Mn
y-y
[k-ft
]ph
i*Mn
z-z
[k-ft
]C
bEq
n13
M16
W16
X31
.070
4.88
914
.007
40y
1226
1.13
741
0.85
26.3
6327
.215
1.18
8H
1-1b
14M
18.7
5 Ba
r.1
670
14.0
010
12.0
3214
.314
.179
.179
1H
1-1b
*15
M19
.75
Bar
.344
013
.000
09
.032
14.3
14.1
79.1
791
H1-
1a*
16M
20.7
5 Ba
r.4
330
12.0
020
4.0
1214
.314
.179
.179
1H
1-1a
*17
M21
.75
Bar
.003
013
.001
013
.012
14.3
14.1
79.1
791
H1-
1b*
18M
22.7
5 Ba
r.0
120
4.0
040
4.0
2314
.314
.179
.179
1H
1-1b
*19
M23
.75
Bar
.329
011
.001
012
.023
14.3
14.1
79.1
791
H1-
1a*
20M
23A
HSS
6X6X
4.0
5519
4.0
010
y7
117.
518
235.
842
421.
674
H1-
1b21
M24
HSS
6X6X
4.0
670
4.0
030
z12
117.
518
235.
842
421.
674
H1-
1b*
22M
25A
W16
X40
.015
1.95
64
.054
4y
444
6.67
553
147
.625
273.
751
H1-
1b23
M26
W16
X40
.033
4.14
84
.035
7.77
8y
444
6.67
553
147
.625
273.
751
H1-
1b24
M28
W16
X40
.153
04
.058
3.53
6z
440
8.91
531
47.6
2527
3.75
3.04
9H
1-1b
25M
26A
HSS
6X6X
4.3
4619
4.0
030
y12
117.
518
235.
842
421.
674
H1-
1a
RIS
A-3D
Ver
sion
17.
0.0
Page
4 [Z
:\201
8\20
1820
4\D
-Des
ign
Cal
cula
tions
\RIS
A\FR
AMIN
G R
evis
ed n
o bl
ast.r
3d]
SK -
1
BIG
WIN
DO
W O
PTIO
N F
RAM
E.r3
d
N1
N2
N3
N4
N5
N6
N7
N8
HSS6X3X4
HSS6X3X4
HSS8
X6X4
2-60
0S16
2-54
-BB
Y
XZ
Hot
Rol
led
Stee
l Pro
pert
ies
Labe
lE
[ksi
]G
[ksi
]N
uTh
erm
(\1E
5 F)
Den
sity
[k/ft
^3]
Yiel
d[ks
i]R
yFu
[ksi
]R
t1
A992
2900
011
154
.3.6
5.4
950
1.1
651.
12
A36
Gr.3
629
000
1115
4.3
.65
.49
361.
558
1.2
3A5
72 G
r.50
2900
011
154
.3.6
5.4
950
1.1
651.
14
A500
Gr.B
RN
D29
000
1115
4.3
.65
.527
421.
458
1.3
5A5
00 G
r.B R
ect
2900
011
154
.3.6
5.5
2746
1.4
581.
36
A53
Gr.B
2900
011
154
.3.6
5.4
935
1.6
601.
27
A108
529
000
1115
4.3
.65
.49
501.
465
1.3
Mem
ber P
rimar
y D
ata
Labe
lI J
oint
J Jo
int
K Jo
int
Rot
ate(
deg)
Sect
ion/
Shap
eTy
peD
esig
n Li
stM
ater
ial
Des
ign
Rul
es1
M1
N1
N4
HSS
6X3X
4C
olum
nTu
beA5
00 G
r.B R
ect
Typi
cal
2M
2N
2N
3H
SS6X
3X4
Col
umn
Tube
A500
Gr.B
Rec
tTy
pica
l3
M3
N8
N7
HSS
8X6X
4Be
amTu
beA5
00 G
r.B R
ect
Typi
cal
4M
4N
6N
590
2-60
0S16
2-54
-BB
Beam
CS
A653
SS
Gr5
0/1
Typi
cal
5M
5N
4N
3R
IGID
Non
eN
one
RIG
IDTy
pica
l6
M6
N1
N2
RIG
IDN
one
Non
eR
IGID
Typi
cal
Hot
Rol
led
Stee
l Des
ign
Para
met
ers
Labe
lSh
ape
Leng
th[ft
]Lb
yy[ft
]Lb
zz[ft
]Lc
omp
top[
ft]Lc
omp
bot[f
t]L-
torq
ue[ft
]Ky
yKz
zC
bFu
nctio
n1
M1
HSS
6X3X
412
.75
Late
ral
2M
2H
SS6X
3X4
12.7
5La
tera
l3
M3
HSS
8X6X
415
Lbyy
Late
ral
Bas
ic L
oad
Cas
esBL
C D
escr
iptio
nC
ateg
ory
X G
ravi
tyY
Gra
vity
Z G
ravi
tyJo
int
Poin
tD
istri
bute
dAr
ea(M
emb.
..Su
rface
(Pla
t...
1D
ead
DL
-13
2W
ind
WL
13
BLC
2 T
rans
ient
Are
a Lo
ads
Non
e16
Load
Com
bina
tions
Des
crip
tion
Solv
ePD
el...
SRSS
BLC
Fact
orBL
CFa
ctor
BLC
Fact
orBL
CFa
ctor
BLC
Fact
orBL
CFa
ctor
BLC
Fact
orBL
CFa
ctor
BLC
Fact
orBL
CFa
ctor
1IB
C 1
6-3
(b)
Yes
YD
L1.
2W
L.5
2IB
C 1
6-4
(a)
Yes
YD
L1.
2W
L1
LL.5
LLS
13
IBC
16-
6Ye
sY
DL
.9W
L1
4IB
C 1
6-12
(a)
Yes
DL
1W
L.6
5IB
C 1
6-13
(a)
Yes
DL
1W
L.4
5LL
.75
LLS
.75
6IB
C 1
6-15
Yes
DL
.6W
L.6
RIS
A-3D
Ver
sion
17.
0.0
Page
1 [P
:\201
8\20
1820
4\D
-Des
ign
Cal
cula
tions
\RIS
A\BI
G W
IND
OW
OPT
ION
FR
AME.
r3d]
Mem
ber A
ISC
15t
h(36
0-16
): LR
FD S
teel
Cod
e C
heck
sLC
Mem
ber
Shap
eU
C M
axLo
c[ft]
Shea
r UC
Loc[
ft]D
irph
i*Pnc
[k]
phi*P
nt[k
]ph
i*Mny
y[k-
ft]ph
i*Mnz
z[k-
ft]C
bEq
n1
1M
1H
SS6X
3X4
.314
4.25
.075
1.13
3z
55.0
0915
8.97
615
.215
24.8
061.
702
H1-
1b2
1M
2H
SS6X
3X4
.314
4.25
.075
1.13
3z
55.0
0915
8.97
615
.215
24.8
061.
702
H1-
1b3
1M
3H
SS8X
6X4
.222
7.5
.109
15y
176.
5425
5.43
845
.18
58.3
051.
219
H1-
1b4
2M
1H
SS6X
3X4
.386
4.25
.098
1.13
3z
55.0
0915
8.97
615
.215
24.8
061.
583
H1-
1b5
2M
2H
SS6X
3X4
.385
4.25
.098
1.13
3z
55.0
0915
8.97
615
.215
24.8
061.
583
H1-
1b6
2M
3H
SS8X
6X4
.262
7.5
.109
15y
176.
5425
5.43
845
.18
58.3
051.
219
H1-
1b7
3M
1H
SS6X
3X4
.324
4.25
.085
1.13
3z
55.0
0915
8.97
615
.215
24.8
061.
544
H1-
1b8
3M
2H
SS6X
3X4
.324
4.25
.085
1.13
3z
55.0
0915
8.97
615
.215
24.8
061.
544
H1-
1b9
3M
3H
SS8X
6X4
.217
7.5
.081
15y
176.
5425
5.43
845
.18
58.3
051.
219
H1-
1b10
4M
1H
SS6X
3X4
.287
4.25
.071
1.13
3z
55.0
0915
8.97
615
.215
24.8
061.
638
H1-
1b11
4M
2H
SS6X
3X4
.286
4.25
.071
1.13
3z
55.0
0915
8.97
615
.215
24.8
061.
638
H1-
1b12
4M
3H
SS8X
6X4
.200
7.5
.090
15y
176.
5425
5.43
845
.18
58.3
051.
219
H1-
1b13
5M
1H
SS6X
3X4
.265
4.25
.064
1.13
3z
55.0
0915
8.97
615
.215
24.8
061.
691
H1-
1b14
5M
2H
SS6X
3X4
.265
4.25
.064
1.13
3z
55.0
0915
8.97
615
.215
24.8
061.
691
H1-
1b15
5M
3H
SS8X
6X4
.188
7.5
.090
15y
176.
5425
5.43
845
.18
58.3
051.
219
H1-
1b16
6M
1H
SS6X
3X4
.206
4.25
.054
1.13
3z
55.0
0915
8.97
615
.215
24.8
061.
56H
1-1b
176
M2
HSS
6X3X
4.2
064.
25.0
541.
133
z55
.009
158.
976
15.2
1524
.806
1.55
9H
1-1b
186
M3
HSS
8X6X
4.1
397.
5.0
5415
y17
6.54
255.
438
45.1
858
.305
1.21
9H
1-1b
RIS
A-3D
Ver
sion
17.
0.0
Page
2 [P
:\201
8\20
1820
4\D
-Des
ign
Cal
cula
tions
\RIS
A\BI
G W
IND
OW
OPT
ION
FR
AME.
r3d]
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
1
VA Sioux Falls – Pharmacy Addition
Mechanical/Electrical CD Narrative
December 12, 2018
A. HVAC
a. Two new rooftop units will be provided for this project, with one unit being variable air
volume (RTU-2) and one unit being constant volume (RTU-1). Separate units will be
provided to allow the new OT area to operate independently of the Pharmacy area.
Each area will be on different occupancy scheduling, while the Pharmacy area requires
precise pressure control and the OT area does not. In addition, RTU-1 serving the
Pharmacy will be required to be on backup emergency power, while RTU-2 serving the
OT area will not be. For this project, we will look at two strategies for the equipment.
The preferred Option #1 would be to utilize existing campus chilled water and heating
water, along with campus steam for humidification. Option #2 will still utilize campus
heating water and steam for humidification, but will utilize packaged DX cooling at the
equipment, in lieu of chilled water, should it be determined the campus chilled water
system cannot handle the additional capacity of the project. The loads for each system
are indicated in the narrative, and shortly after issue of this report, we will discuss the
capacity requirements with the VA and determine the best course of action for the
cooling system.
1. Final Design: In lieu of providing a variable volume RTU-2 for the OT portion of
the project, it was determined that the existing indoor air handing unit AHU-2
serving the existing OT space had enough spare capacity to serve the new OT
space. The existing AHU-2 is variable air volume and served with campus
chilled and heating water. For the new RTU-43 serving the pharmacy area, we
utilized option #1 which will use campus chilled water for campus, campus
heating water for heating, and campus steam for humidification.
b. (Option #1) RTU-1: 4,525 cfm supply air at 2.0” ESP with VFD; chilled water coil with
88.7F DB / 70.1F WB EAT, target 55F LAT off cooling coil (approximately 19 tons);
heating water preheat coil with 5F EAT, target 60F LAT off heating coil; 1,270 cfm
exhaust fan with VFD; insulated roof curb; Merv 8 pre-filter bank; Merv 14 final filter
bank; modulating outside air damper; modulating return air damper. Provide with
airflow measuring station on outside air opening and inlet airflow measuring station on
the exhaust fan.
1. Final Design: RTU-43: 3,950 cfm supply air at 4.0” ESP with VFD; chilled water
coil with 88.3F DB / 73.7F WB EAT, 23.6 tons; heating water preheat coil with -
5F EAT, 60F LAT off heating coil; insulated roof curb; Merv 8 pre-filter bank;
modulating outside air damper; modulating return air damper. Provide with
airflow measuring station on outside air opening and inlet airflow measuring
station on the exhaust fan. A desiccant dehumidification wheel was added to
the RTU in order to achieve the space temperature and humidity requirements
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
2
in the compounding rooms (68F and 50%). Finally, since the compounding
rooms are served with HEPA filters for each space, the MERV 14 filters were
removed from the RTU and only MERV 8 filters provided.
c. (Option #2) RTU-1: 4,525 cfm supply air at 2.0” ESP with VFD; chilled water coil with
88.7F DB / 70.1F WB EAT, target 55F LAT off cooling coil (approximately 19 tons), 95F
ambient; provide variable capacity scroll compressors on all circuits, heating water
preheat coil with 5F EAT, target 60F LAT off heating coil; 1,270 cfm exhaust fan with
VFD; insulated roof curb; Merv 8 pre-filter bank; Merv 14 final filter bank; modulating
outside air damper; modulating return air damper. Provide with airflow measuring
station on outside air opening and inlet airflow measuring station on the exhaust fan.
1. Final Design: This option was not taken. See Option #1.
d. (Option #1) RTU-2: 1,590 cfm supply air at 2.0” ESP with VFD; chilled water coil with
80.4F DB / 65.5F WB EAT, target 55F LAT off cooling coil (approximately 5 tons); heating
water preheat coil with -3F EAT, target 60F LAT off heating coil; 1,140 cfm exhaust fan
with VFD; insulated roof curb; Merv 8 pre-filter bank; Merv 14 final filter bank;
modulating outside air damper; modulating return air damper. Provide with airflow
measuring station on outside air opening.
1. Final Design: This option was not taken. A new RTU was not provided for the
OT portion of the project.
e. (Option #2) RTU-2: 1,590 cfm supply air at 2.0” ESP with VFD; chilled water coil with
80.4F DB / 65.5F WB EAT, target 55F LAT off cooling coil (approximately 5 tons), 95F
ambient; provide variable capacity scroll compressors on all circuits, heating water
preheat coil with -3F EAT, target 60F LAT off heating coil; 1,140 cfm exhaust fan with
VFD; insulated roof curb; Merv 8 pre-filter bank; Merv 14 final filter bank; modulating
outside air damper; modulating return air damper. Provide with airflow measuring
station on outside air opening.
1. Final Design: This option was not taken. A new RTU was not provided for the
OT portion of the project.
f. In supply air ductwork main from RTU-1, above the ceiling of the Pharmacy space,
provide a duct mounted steam grid humidifier, sized for approximately 75 lb/hr. BAS
Contractor to provide control valve for humidifier and shall be controlled to maintain
humidity at minimum 30% in worst case space served by RTU-1. Ductwork within 3 feet
of humidifier, on both inlet and discharge side, shall be of stainless steel material.
1. Final design: This humidifier H-1 was provided in the supply ductwork from
RTU-43, and sized for 70 lb/hr. Ductwork within 7 feet of humidifier shall be
stainless steel per the VA specs. Finally, direction was given to use building
steam for this humidifier and not clean steam.
g. In supply air ductwork main from RTU-2, above the ceiling of the OT space, provide a
duct mounted steam grid humidifier, sized for approximately 25 lb/hr. BAS Contractor
to provide control valve for humidifier and shall be controlled to maintain humidity at
minimum 30% in worst case space served by RTU-2. Ductwork within 3 feet of
humidifier, on both inlet and discharge side, shall be of stainless steel material.
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
3
1. Final Design: This humidifier was not installed. The OT space is served by the
existing air handling unit that serves the existing OT space.
h. The following rooms will be provided with the HVAC as indicated:
1. OT:
i. Provide (2) shutoff VAV boxes (700 cfm each, variable flow) with supply
ductwork distribution into the space. Terminate with aluminum
louvered diffusers. Provide VAV box with reheat coil. Connect VAV
boxes to supply air main from RTU-2.
1. Final Design: Provide (1) shutoff VAV boxes (900 cfm) with
supply ductwork distribution into the space. Terminate with
aluminum louvered diffusers. Provide VAV box with reheat
coil. Connect VAV box to existing supply air mains from air
handling unit serving the existing OT space.
ii. Provide (1) 24x24 egg crate return air grille in ceiling, connected to
return air main from RTU-2.
1. Final Design: A return grille was not provided in this area.
There is an existing return air grille within the existing building
that will be reused for return air back to the air handling unit.
iii. The BAS system will control the VAV box damper and reheat coil to
maintain space temperature set point. BAS Contractor will provide a
combination space temperature/humidity sensor in this space.
1. Final Design: No change.
iv. The BAS Contractor shall provide a space pressure sensor in this space
to control the speed of the exhaust fan in RTU-2 to maintain space
pressure set point of +0.03”.
1. Final Design: This was not provided. The existing air handling
unit has an exhaust fan which will control the pressure in this
space. The existing pressure sensor was not located in the
remodeled space.
v. Provide approximately (4) heating water radiant ceiling panels above
the perimeter windows in the OT room.
1. Final Design: No change.
vi. Space occupied cooling target: 75F.
1. Final Design: No change.
vii. Space occupied heating target: 70F.
1. Final Design: No change.
viii. Space maximum relative humidity: 60%.
1. Final Design: No change.
ix. Space minimum relative humidity: 30%.
1. Final Design: No change.
2. OT Offices:
i. Provide (1) shutoff VAV box (195 cfm, variable flow) with supply
ductwork distribution into the space. Terminate with aluminum
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
4
louvered diffusers. Provide VAV box with reheat coil. Connect VAV
boxes to supply air main from RTU-2.
1. Final Design: Provide (1) shutoff VAV boxes (300 cfm) with
supply ductwork distribution into the space. Terminate with
aluminum louvered diffusers. Provide VAV box with reheat
coil. Connect VAV box to existing supply air mains from air
handling unit serving the existing OT space.
ii. Provide (1) 24x12 egg crate return air grille in ceiling, connected to
return air main from RTU-2.
1. Final Design: Provide (1) 24x12 egg crate return air grille in
ceiling. Connect to existing return air mains from air handling
unit serving the existing OT space.
iii. The BAS system will control the VAV box damper and reheat coil to
maintain space temperature set point. BAS Contractor will provide a
combination space temperature/humidity sensor in this space.
1. Final Design: No change.
iv. Space occupied cooling target: 75F.
1. Final Design: No change.
v. Space occupied heating target: 70F.
1. Final Design: No change.
vi. Space maximum relative humidity: 60%.
1. Final Design: No change.
vii. Space minimum relative humidity: 30%.
1. Final Design: No change.
3. Pharmacy:
i. Provide (1) shutoff VAV box (1,100 cfm, constant flow) with supply
ductwork distribution into the space. Terminate with (6) aluminum
louvered diffusers. Provide VAV box with reheat coil. Connect VAV
boxes to supply air main from RTU-1.
1. Final Design: Provide (1) shutoff VAV box (1,035 cfm, constant
flow) with supply ductwork distribution into the space.
Terminate with (5) aluminum louvered diffusers. Provide VAV
box with reheat coil. Connect VAV boxes to supply air main
from RTU-1.
ii. The BAS system will control the VAV box damper and reheat coil to
maintain space temperature set point. BAS Contractor will provide a
combination space temperature/humidity sensor in this space.
1. Final Design: No change.
iii. Provide (1) 24x24 egg crate return air grille in ceiling, connected to
return air main from RTU-1.
1. Final Design: No change.
iv. Provide master central monitoring station by the pharmacy
workstations that displays the pressure differentials between the
following spaces:
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
5
1. Pharmacy to Ante (+)
2. Ante (+) to IV Prep (++)
3. Ante (+) to HD Buffer (-)
4. Pharmacy to HD Storage (-)
5. Pharmacy to CSCA (-)
6. Pharmacy to Receiving (-)
Final Design: No change. The monitoring station is located by the
pharmacy workstation. See note M454 on sheet 5.HV101.
v. At door from Pharmacy into Ante (+), on Pharmacy side of door, provide
pressure controller that displays the pressure differential between
Pharmacy and Ante (+).
Final Design: No change.
vi. Space occupied cooling target: 75F.
Final Design: No change.
vii. Space occupied heating target: 70F.
Final Design: No change.
viii. Space maximum relative humidity: 60%.
Final Design: No change.
ix. Space minimum relative humidity: 30%.
Final Design: No change.
4. Pharmacy Office:
i. Provide (1) shutoff VAV box (120 cfm, constant flow) with supply
ductwork distribution into the space. Terminate with aluminum
louvered diffusers. Provide VAV box with reheat coil. Connect VAV
boxes to supply air main from RTU-1.
Final Design: A VAV box was not provided for this office. This office is
a total interior space like the open pharmacy area, and as such, supply
air from the Pharmacy work area VAV box was used for the office.
ii. The BAS system will control the VAV box damper and reheat coil to
maintain space temperature set point. BAS Contractor will provide a
combination space temperature/humidity sensor in this space.
Final Design: A space temperature and humidity sensor is installed in
both the Office and Pharmacy area. Each device will be used to control
the single VAV box to maintain work case in each space. The
conditions between spaces is not anticipated to very much at all.
iii. Provide (1) 24x12 egg crate return air grille in ceiling, connected to
return air main from RTU-1.
Final Design: The grille was not provided. The air supplied to the
Office will transfer out/under the door and into the Pharmacy area,
where it is returned to RTU-43.
iv. Space occupied cooling target: 75F.
Final Design: No change.
v. Space occupied heating target: 70F.
Final Design: No change.
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
6
vi. Space maximum relative humidity: 60%.
Final Design: No change.
vii. Space minimum relative humidity: 30%.
Final Design: No change.
5. Pharmacy Breakroom:
i. Provide (1) shutoff VAV box (150 cfm, constant flow) with supply
ductwork distribution into the space. Terminate with aluminum
louvered diffusers. Provide VAV box with reheat coil. Connect VAV
boxes to supply air main from RTU-1.
Final Design: Provide (1) shutoff VAV box (210 cfm, constant flow)
with supply ductwork distribution into the space. Terminate with
aluminum louvered diffusers. Provide VAV box with reheat coil.
Connect VAV boxes to supply air main from RTU-43.
ii. The BAS system will control the VAV box damper and reheat coil to
maintain space temperature set point. BAS Contractor will provide a
combination space temperature/humidity sensor in this space.
Final Design: No change.
iii. Provide (1) roof mounted exhaust fan (285 cfm, constant flow) with
exhaust ductwork distribution into the space. Terminate at (1) 24x12
egg crate exhaust air grille in ceiling. Provide motorized damper at
ductwork connection to fan. The BAS will control the damper to be
open whenever the fan is operating.
Final Design: Provide (1) roof mounted exhaust fan (400 cfm, constant
flow) with exhaust ductwork distribution into the space. Terminate at
(1) 24x12 egg crate exhaust air grille in ceiling. The fan is provided
with a gravity backdraft damper.
iv. Space occupied cooling target: 75F.
Final Design: No change.
v. Space occupied heating target: 70F.
Final Design: No change.
vi. Space maximum relative humidity: 60%.
Final Design: No change.
vii. Space minimum relative humidity: 30%.
Final Design: No change.
6. Lockers:
i. Provide (1) shutoff VAV box (290 cfm, constant flow) with supply
ductwork distribution into the space. Terminate with aluminum
louvered diffusers. Provide VAV box with reheat coil. Connect VAV
boxes to supply air main from RTU-1.
Final Design: A VAV box was not provided for this space. This space is
a total interior space like the open pharmacy area, and as such, supply
air from the Pharmacy work area VAV box was used for the lockers.
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
7
ii. The BAS system will control the VAV box damper and reheat coil to
maintain space temperature set point. BAS Contractor will provide a
combination space temperature/humidity sensor in this space.
Final Design: A temperature and humidity sensor was not installed for
this space.
iii. Provide (1) roof mounted exhaust fan (140 cfm, constant flow) with
exhaust ductwork distribution into the space. Terminate at (1) 24x12
egg crate exhaust air grille in ceiling. Provide motorized damper at
ductwork connection to fan. The BAS will control the damper to be
open whenever the fan is operating.
Final Design: Provide (1) roof mounted exhaust fan (150 cfm, constant
flow) with exhaust ductwork distribution into the space. Terminate at
(1) 24x12 egg crate exhaust air grille in ceiling. The fan is provided
with a gravity backdraft damper.
iv. Space occupied cooling target: 75F.
Final Design: No change.
v. Space occupied heating target: 70F.
Final Design: No change.
vi. Space maximum relative humidity: 60%.
Final Design: No change.
vii. Space minimum relative humidity: 30%.
Final Design: No change.
7. IV Compounding (++):
i. This room is required to be positive to the adjacent Ante Room (+). USP
800 requires minimum 30 ACH of HEPA filtered supply air to the space,
which equates to approximately 370 cfm of filtered supply air. One
hood will be installed in the room at approximately 390 cfm of exhaust.
To maintain a (++) pressure differential in the room, a +300 cfm supply
air to exhaust air will be required. Therefore, 690 cfm of HEPA filtered
supply air will be delivered to the space from RTU-1. This supply air will
be ducted to (2) laminar flow diffusers in the ceiling of this space. The
HEPA filters for the supply air will be installed in an approximately 4’-0”
high interstitial space above the room. A housing will be provided for
the filters that allows testing and certification of the filters. Merv 8
filters will also be installed inside the housing and upstream of the HEPA
filters.
Final Design: This room is required to be positive to the adjacent Ante
Room (+). USP 800 requires minimum 30 ACH of HEPA filtered supply
air to the space, which equates to approximately 395 cfm of filtered
supply air. One hood will be installed in the room which will be a 100%
recirculation hood with HEPA filtration. To maintain a (++) +270 cfm
pressure differential in the room, a 395 cfm of HEPA supply air will be
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
8
delivered to the space, while 125 cfm of exhaust air will be exhausted
from the space. The exhaust air from the space will be HEPA filtered
before discharging to the exterior. The HEPA filters for the supply and
exhaust air will be installed in an approximately 6’-0” high interstitial
space above the room. A housing will be provided for the filters that
allows testing and certification of the filters. Merv 8 filters will also be
installed inside the housing and upstream of the HEPA filters.
ii. Provide (1) shutoff VAV box (690 cfm, constant flow) with supply
ductwork distribution into the space. Provide VAV box with reheat coil.
Connect VAV boxes to supply air main from RTU-1. Ductwork from VAV
box to HEPA filter housing in interstitial space will be galvanized steel.
Ductwork from the HEPA filter housing to the space shall be stainless
steel.
Final Design: Provide (1) shutoff VAV box (395 cfm, constant flow)
with supply ductwork distribution into the space. Provide VAV box
with reheat coil. Connect VAV boxes to supply air main from RTU-43.
Ductwork from VAV box to HEPA filter housing in interstitial space will
be galvanized steel. Ductwork from the HEPA filter housing to the
space shall be stainless steel.
iii. The BAS system will control the VAV box damper to maintain a constant
690 cfm of air and will control the reheat coil to maintain space
temperature set point. BAS Contractor will provide a combination
space temperature/humidity sensor in this space.
Final Design: The BAS system will control the VAV box damper to
maintain a constant 395 cfm of air and will control the reheat coil to
maintain space temperature set point. BAS Contractor will provide a
combination space temperature/humidity sensor in this space.
iv. Provide (1) roof mounted exhaust fan (390 cfm, constant flow) with
exhaust ductwork distribution into the space and to the hood. The
hood shall operate continuously. All exhaust ductwork shall be stainless
steel material.
Final Design: (2) High Plume discharge exhaust fans (EF-3 and EF-4)
will be provided for all the compounding rooms. The 125 cfm of
exhaust air for this space will be through a wall mounted grille located
12” above finished floor. The exhaust shall operate continuously. All
exhaust ductwork shall be stainless steel material.
v. At door from Ante (+) into IV Compounding (++), on Ante (+) side of
door, provide pressure controller that displays the pressure differential
between Ante (+) and IV Compounding (++).
Final Design: No change.
vi. Space occupied cooling target: 68F.
Final Design: No change.
vii. Space occupied heating target: 68F.
Final Design: No change.
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
9
viii. Space maximum relative humidity: 60%.
Final Design: No change.
ix. Space minimum relative humidity: 30%.
Final Design: No change.
8. Ante Room (+):
i. This room is required to be positive to the adjacent Pharmacy and HD
Buffer (-), but negative to the adjacent IV Compounding (++). USP 800
requires minimum 30 ACH of HEPA filtered supply air to the space,
which equates to approximately 535 cfm of filtered supply air. To
maintain a (+) pressure differential in the room, a +150 cfm supply air to
exhaust air will be required. Therefore, 535 cfm of HEPA filtered supply
air will be delivered to the space from RTU-1, and 385 cfm of exhaust air
will be extracted from this space. This supply air will be ducted to (2)
laminar flow diffusers in the ceiling of this space. The HEPA filters for
the supply air will be installed in an approximately 4’-0” high interstitial
space above the room. A housing will be provided for the filters that
allows testing and certification of the filters. Merv 8 filters will also be
installed inside the housing and upstream of the HEPA filters.
Final Design: This room is required to be positive to the adjacent
Pharmacy and HD Buffer (-), but negative to the adjacent IV
Compounding (++). USP 800 requires minimum 30 ACH of HEPA
filtered supply air to the space, which equates to approximately 495
cfm of filtered supply air. No hoods will be installed in this space. To
maintain a (+) +150 cfm pressure differential in the room, 395 cfm of
HEPA supply air will be delivered to the space, while 345 cfm of
exhaust air will be exhausted from the space. The exhaust air from
the space will be HEPA filtered before discharging to the exterior. The
HEPA filters for the supply and exhaust air will be installed in an
approximately 6’-0” high interstitial space above the room. A housing
will be provided for the filters that allows testing and certification of
the filters. Merv 8 filters will also be installed inside the housing and
upstream of the HEPA filters.
ii. Provide (1) shutoff VAV box (535 cfm, constant flow) with supply
ductwork distribution into the space. Provide VAV box with reheat coil.
Connect VAV boxes to supply air main from RTU-1. Ductwork from VAV
box to HEPA filter housing in interstitial space will be galvanized steel.
Ductwork from the HEPA filter housing to the space shall be stainless
steel.
Final Design: Provide (1) shutoff VAV box (495 cfm, constant flow)
with supply ductwork distribution into the space. Provide VAV box
with reheat coil. Connect VAV boxes to supply air main from RTU-43.
Ductwork from VAV box to HEPA filter housing in interstitial space will
be galvanized steel. Ductwork from the HEPA filter housing to the
space shall be stainless steel.
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
10
iii. The BAS system will control the VAV box damper to maintain a constant
535 cfm of air and will control the reheat coil to maintain space
temperature set point. BAS Contractor will provide a combination
space temperature/humidity sensor in this space.
Final Design: The BAS system will control the VAV box damper to
maintain a constant 495 cfm of air and will control the reheat coil to
maintain space temperature set point. BAS Contractor will provide a
combination space temperature/humidity sensor in this space.
iv. Provide (1) roof mounted exhaust fan (385 cfm, constant flow) with
exhaust ductwork distribution into the space and terminate at a grille
on the wall approximately 18” above floor. The exhaust shall operate
continuously. All exhaust ductwork shall be stainless steel material.
Final Design: (2) High Plume discharge exhaust fans (EF-3 and EF-4)
will be provided for all the compounding rooms. The 345 cfm of
exhaust air for this space will be through a wall mounted grille located
12” above finished floor. The exhaust shall operate continuously. All
exhaust ductwork shall be stainless steel material.
v. At door from Ante (+) into HD Buffer (-), on Ante (+) side of door,
provide pressure controller that displays the pressure differential
between Ante (+) and HD Buffer (-).
Final Design: No change.
vi. Space occupied cooling target: 68F.
Final Design: No change.
vii. Space occupied heating target: 68F.
Final Design: No change.
viii. Space maximum relative humidity: 60%.
Final Design: No change.
ix. Space minimum relative humidity: 30%.
Final Design: No change.
9. HD Buffer (-):
i. This room is required to be negative to the adjacent Ante Room (+).
USP 800 requires minimum 30 ACH of HEPA filtered supply air to the
space, which equates to approximately 485 cfm of filtered supply air.
One hood will be installed in the room at approximately 390 cfm of
exhaust. To maintain a (-) pressure differential in the room, a -150 cfm
supply air to exhaust air will be required. Since 485 cfm minimum
supply air is required, an additional 245 cfm of exhaust is required in the
space for a total exhaust volume of 635 cfm. 485 cfm of HEPA filtered
supply air will be delivered to the space from RTU-1. This supply air will
be ducted to (2) laminar flow diffusers in the ceiling of this space. The
HEPA filters for the supply air will be installed in an approximately 4’-0”
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
11
high interstitial space above the room. A housing will be provided for
the filters that allows testing and certification of the filters. Merv 8
filters will also be installed inside the housing and upstream of the HEPA
filters.
Final Design: This room is required to be negative to the adjacent Ante
Room (+). USP 800 requires minimum 30 ACH of HEPA filtered supply
air to the space, which equates to approximately 410 cfm of filtered
supply air. One hood will be installed in the room at approximately
530 cfm of exhaust. To maintain a (-) -120 cfm pressure differential in
the room, a -120 cfm supply air to exhaust air will be required. Since
the 530 cfm exhaust hood operates continuously per the VA staff,
secondary exhaust will not be required inside the space. 410 cfm of
HEPA filtered supply air will be delivered to the space from RTU-43.
This supply air will be ducted to (2) laminar flow diffusers in the ceiling
of this space. The exhaust air from the hood will be HEPA filtered
before discharging to the exterior. The HEPA filters for the supply and
exhaust air will be installed in an approximately 6’-0” high interstitial
space above the room. A housing will be provided for the filters that
allows testing and certification of the filters. Merv 8 filters will also be
installed inside the housing and upstream of the HEPA filters.
ii. Provide (1) shutoff VAV box (485 cfm, constant flow) with supply
ductwork distribution into the space. Provide VAV box with reheat coil.
Connect VAV boxes to supply air main from RTU-1. Ductwork from VAV
box to HEPA filter housing in interstitial space will be galvanized steel.
Ductwork from the HEPA filter housing to the space shall be stainless
steel.
Final Design: Provide (1) shutoff VAV box (410 cfm, constant flow)
with supply ductwork distribution into the space. Provide VAV box
with reheat coil. Connect VAV boxes to supply air main from RTU-43.
Ductwork from VAV box to HEPA filter housing in interstitial space will
be galvanized steel. Ductwork from the HEPA filter housing to the
space shall be stainless steel.
iii. The BAS system will control the VAV box damper to maintain a constant
485 cfm of air and will control the reheat coil to maintain space
temperature set point. BAS Contractor will provide a combination
space temperature/humidity sensor in this space.
Final Design: The BAS system will control the VAV box damper to
maintain a constant 410 cfm of air and will control the reheat coil to
maintain space temperature set point. BAS Contractor will provide a
combination space temperature/humidity sensor in this space.
iv. Provide (1) roof mounted exhaust fan (245 cfm, constant flow) with
exhaust ductwork distribution into the space and terminate at a grille
on the wall approximately 18” above floor. The exhaust shall operate
continuously. All exhaust ductwork shall be stainless steel material.
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
12
Final Design: (2) High Plume discharge exhaust fans (EF-3 and EF-4)
will be provided for all the compounding rooms. The exhaust shall
operate continuously. All exhaust ductwork shall be stainless steel
material.
Provide (1) roof mounted exhaust fan (390 cfm, constant flow) with
exhaust ductwork distribution into the space and to the hood. The
hood shall operate continuously. All exhaust ductwork shall be stainless
steel material.
Final Design: (2) High Plume discharge exhaust fans (EF-3 and EF-4)
will be provided for all the compounding rooms. The exhaust shall
operate continuously. All exhaust ductwork shall be stainless steel
material.
v. Space occupied cooling target: 68F.
Final Design: No change.
vi. Space occupied heating target: 68F.
Final Design: No change.
vii. Space maximum relative humidity: 60%.
Final Design: No change.
viii. Space minimum relative humidity: 30%.
Final Design: No change.
10. HD Storage (-):
i. This room is required to be negative to the adjacent Pharmacy. USP 800
requires 12 ACH of exhaust air from the space, which equates to
approximately 315 cfm. One hood will be installed in the room at
approximately 390 cfm of exhaust. To maintain a (-) pressure
differential in the room, a -150 cfm supply air to exhaust air will be
required. Therefore, 240 cfm of HEPA filtered supply air will be
delivered to the space from RTU-1. This supply air will be ducted to (1)
laminar flow diffuser in the ceiling of this space. The HEPA filters for the
supply air will be installed in an approximately 4’-0” high interstitial
space above the room. A housing will be provided for the filters that
allows testing and certification of the filters. Merv 8 filters will also be
installed inside the housing and upstream of the HEPA filters.
Final Design: This room is required to be negative to the adjacent
Pharmacy. USP 800 requires 12 ACH of supply air to the space, which
equates to approximately 265 cfm. One hood will be installed in the
room at approximately 260 cfm of exhaust. 370 cfm of supply air is
required to cool the room, so this amount of air will be delivered to the
space. To maintain a (-) -150 cfm pressure differential in the room, a
+150 cfm exhaust air to supply air will be required. Since the hood is
providing 260 cfm of constant exhaust, 260 cfm of supplemental
exhaust will be provided for the space. Only the exhaust air from the
space will be HEPA filtered. This space is not required to be a ISO clean
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
13
environment, so the supply air will not be HEPA filters. The supply air
will be ducted to (1) perforated aluminum diffuser in the ceiling of this
space. The HEPA filters for the exhaust air will be installed in an
approximately 6’-0” high interstitial space above the room. A housing
will be provided for the filters that allows testing and certification of
the filters. Merv 8 filters will also be installed inside the housing and
upstream of the HEPA filters.
ii. Provide (1) shutoff VAV box (240 cfm, constant flow) with supply
ductwork distribution into the space. Provide VAV box with reheat coil.
Connect VAV boxes to supply air main from RTU-1. Ductwork from VAV
box to HEPA filter housing in interstitial space will be galvanized steel.
Ductwork from the HEPA filter housing to the space shall be stainless
steel.
Final Design: Provide (1) shutoff VAV box (370 cfm, constant flow)
with supply ductwork distribution into the space. Provide VAV box
with reheat coil. Connect VAV boxes to supply air main from RTU-43.
Ductwork from VAV box to the space shall be galvanized steel.
iii. The BAS system will control the VAV box damper to maintain a constant
240 cfm of air and will control the reheat coil to maintain space
temperature set point. BAS Contractor will provide a combination
space temperature/humidity sensor in this space.
Final Design: The BAS system will control the VAV box damper to
maintain a constant 370 cfm of air and will control the reheat coil to
maintain space temperature set point. BAS Contractor will provide a
combination space temperature/humidity sensor in this space.
iv. Provide (1) roof mounted exhaust fan (390 cfm, constant flow) with
exhaust ductwork distribution into the space and to the hood. The
hood shall operate continuously. All exhaust ductwork shall be stainless
steel material.
Final Design: (2) High Plume discharge exhaust fans (EF-3 and EF-4)
will be provided for all the compounding rooms. The exhaust shall
operate continuously. All exhaust ductwork shall be stainless steel
material. Secondary exhaust in the room will terminate with a wall
grille installed 12” above finished floor.
v. Space occupied cooling target: 68F.
Final Design: No change.
vi. Space occupied heating target: 68F.
Final Design: No change.
vii. Space maximum relative humidity: 60%.
Final Design: No change.
viii. Space minimum relative humidity: 30%.
Final Design: No change.
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
14
ix. At door from Pharmacy into HD Storage (-), on Pharmacy side of door,
provide pressure controller that displays the pressure differential
between Pharmacy and HD Storage (-).
Final Design: No change.
11. CSCA (-):
i. This room is required to be negative to the adjacent Pharmacy. USP 800
requires minimum 15 ACH of HEPA filtered supply air to the space,
which equates to approximately 280 cfm of filtered supply air. Two
hoods will be installed in the room at approximately 390 cfm of exhaust
each, for a total of 780 cfm of exhaust. To maintain a (-) pressure
differential in the room, a -150 cfm supply air to exhaust air will be
required. Therefore, 630 cfm of HEPA filtered supply air will be
delivered to the space from RTU-1. This supply air will be ducted to (2)
laminar flow diffusers in the ceiling of this space. The HEPA filters for
the supply air will be installed in an approximately 4’-0” high interstitial
space above the room. A housing will be provided for the filters that
allows testing and certification of the filters. Merv 8 filters will also be
installed inside the housing and upstream of the HEPA filters.
Final Design: This room is required to be negative to the adjacent
Pharmacy. USP 800 requires 12 ACH of supply air to the space, which
equates to approximately 460 cfm. Two hoods will be installed in the
room at approximately 530 cfm each (1060 cfm total) of exhaust. To
maintain a (-) -150 cfm pressure differential in the room, a +150 cfm
exhaust air to supply air will be required. Since the hood is providing
1060 cfm of constant exhaust, 910 cfm of constant supply air will be
required. Only the exhaust air from the space will be HEPA filtered.
This space is not required to be a ISO clean environment, so the supply
air will not be HEPA filters. The supply air will be ducted to (2)
perforated aluminum diffusers in the ceiling of this space. The HEPA
filters for the exhaust air will be installed in an approximately 6’-0”
high interstitial space above the room. A housing will be provided for
the filters that allows testing and certification of the filters. Merv 8
filters will also be installed inside the housing and upstream of the
HEPA filters.
ii. Provide (1) shutoff VAV box (630 cfm, constant flow) with supply
ductwork distribution into the space. Provide VAV box with reheat coil.
Connect VAV boxes to supply air main from RTU-1. Ductwork from VAV
box to HEPA filter housing in interstitial space will be galvanized steel.
Ductwork from the HEPA filter housing to the space shall be stainless
steel.
Final Design: Provide (1) shutoff VAV box (910 cfm, constant flow)
with supply ductwork distribution into the space. Provide VAV box
with reheat coil. Connect VAV boxes to supply air main from RTU-43.
Ductwork from VAV box to the space shall be galvanized steel.
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
15
iii. The BAS system will control the VAV box damper to maintain a constant
630 cfm of air and will control the reheat coil to maintain space
temperature set point. BAS Contractor will provide a combination
space temperature/humidity sensor in this space.
Final Design: The BAS system will control the VAV box damper to
maintain a constant 910 cfm of air and will control the reheat coil to
maintain space temperature set point. BAS Contractor will provide a
combination space temperature/humidity sensor in this space.
iv. Provide (2) roof mounted exhaust fan (390 cfm each, constant flow)
with exhaust ductwork distribution into the space and to each hood.
The hoods shall operate continuously. All exhaust ductwork shall be
stainless steel material.
Final Design: (2) High Plume discharge exhaust fans (EF-3 and EF-4)
will be provided for all the compounding rooms. The exhaust shall
operate continuously. All exhaust ductwork shall be stainless steel
material.
v. Space occupied cooling target: 68F.
Final Design: No change.
vi. Space occupied heating target: 68F.
Final Design: No change.
vii. Space maximum relative humidity: 60%.
Final Design: No change.
viii. Space minimum relative humidity: 30%.
Final Design: No change.
ix. At door from Pharmacy into CSCA (-), on Pharmacy side of door, provide
pressure controller that displays the pressure differential between
Pharmacy and CSCA (-).
Final Design: No change.
12. HD Receiving (-):
i. This room is required to be negative to the adjacent Pharmacy, OT, and
Lockers. USP 800 requires 12 ACH of exhaust air from the space, which
equates to approximately 185 cfm. To maintain a (-) pressure
differential in the room, a -450 cfm supply air to exhaust air will be
required. To cool the space, 100 cfm of supply air will be delivered to
the space, 550 cfm of exhaust air will be extracted from the space. The
supply air will be ducted to (1) laminar flow diffuser in the ceiling of this
space.
Final Design: This room is required to be negative to the adjacent
Pharmacy, OT, and Lockers. USP 800 requires 12 ACH of suppy air to
the space, which equates to approximately 125 cfm. To maintain a (-)
-150 cfm pressure differential in the room, a +150 cfm exhaust air to
supply air will be required. 275 cfm of exhaust will be provided for the
space. The supply air will be ducted to one aluminum louver diffuser in
the ceiling. This space is not required to be ISO clean, so the supply air
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
16
will not be HEPA filtered. Likewise, since drugs will not be unpacked in
this room, the exhaust for the space will also not be HEPA filtered.
ii. Connect VAV boxes to supply air main from RTU-1. Ductwork from VAV
box space will be galvanized steel.
Final Design: Provide (1) shutoff VAV box (125 cfm, constant flow)
with supply ductwork distribution into the space. Provide VAV box
with reheat coil. Connect VAV boxes to supply air main from RTU-43.
Ductwork from VAV box to the space shall be galvanized steel.
iii. The BAS system will control the VAV box damper to maintain a constant
100 cfm of air and will control the reheat coil to maintain space
temperature set point. BAS Contractor will provide a combination
space temperature/humidity sensor in this space.
Final Design: The BAS system will control the VAV box damper to
maintain a constant 125 cfm of air and will control the reheat coil to
maintain space temperature set point. BAS Contractor will provide a
combination space temperature/humidity sensor in this space.
iv. Provide (1) roof mounted exhaust fan (550 cfm, constant flow) with
exhaust ductwork distribution into the space and terminate at a grille
on the wall approximately 18” above floor. The exhaust shall operate
continuously. All exhaust ductwork shall be stainless steel material.
Final Design: (2) High Plume discharge exhaust fans (EF-3 and EF-4)
will be provided for all the compounding rooms. The exhaust shall
operate continuously. All exhaust ductwork shall be stainless steel
material.
v. Space occupied cooling target: 68F.
Final Design: No change.
vi. Space occupied heating target: 68F.
Final Design: No change.
vii. Space maximum relative humidity: 60%.
Final Design: No change.
viii. Space minimum relative humidity: 30%.
Final Design: No change.
ix. At door from Pharmacy into HD Receiving (-), on Pharmacy side of door,
provide pressure controller that displays the pressure differential
between Pharmacy and HD Receiving (-).
Final Design: No change.
B. Medical Gas
a. As there is no requirement for medical gas in the renovated space as well as no existing
lines in the space no medical gas design is planned.
Final Design: No change.
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
17
C. Domestic Plumbing
a. All plumbing fixtures in the renovation area of the project will be removed. All water,
waste, and vent piping serving the fixtures will also be removed. Remove vent and
water piping to mains above ceiling and cap air and watertight. Remove waste to below
floor and cap below floor.
Final Design: No change.
b. Provide SCW and HW to the following plumbing fixtures:
i. (1) Sink faucet (laminar flow) in CSCA (-) (1/2” SCW, 1/2” HW). Provide point of
use thermostatic mixing valve.
Final Design: No change.
ii. (1) Sink faucet (laminar flow) in HD Storage (-) (1/2” SCW, 1/2” HW). Provide
point of use thermostatic mixing valve.
Final Design: No change.
iii. (1) Sink faucet (laminar flow) in Ante (+) (1/2” SCW, 1/2” HW). Provide point of
use thermostatic mixing valve.
Final Design: No change.
iv. (1) Sink faucet (laminar flow) in HD Receiving (-) (1/2” SCW, 1/2” HW). Provide
point of use thermostatic mixing valve.
Final Design: No change.
v. (1) Emergency eyewash by sink in CSCA (-) (1/2” SCW, 1/2” HW). Provide point
of use thermostatic mixing valve.
Final Design: No change.
vi. (1) Emergency eyewash by sink in HD Storage (-) (1/2” SCW, 1/2” HW). Provide
point of use thermostatic mixing valve.
Final Design: No change.
vii. (1) Emergency eyewash by sink in Ante (+) (1/2” SCW, 1/2” HW). Provide point
of use thermostatic mixing valve.
Final Design: No change.
viii. (1) Emergency eyewash by sink in HD Receiving (-) (1/2” SCW, 1/2” HW).
Provide point of use thermostatic mixing valve.
Final Design: No change.
ix. Final Design: (1) Sink faucet in EMS for floor mounted mop sink (3/4” SCW,
3/4” HW).
x. Final Design: (1) Sink faucet (laminar flow) in OT. Provide point of use
thermostatic mixing valve
c. Provide sanitary waste and vent to the following plumbing fixtures:
i. (1) Sink in CSCA (-) (2”W, 1-1/2”V).
Final Design: No change.
ii. (1) Sink in HD Storage (-) (2”W, 1-1/2”V).
Final Design: No change.
iii. (1) Sink in Ante (+) (2”W, 1-1/2”V).
Final Design: No change.
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
18
iv. (1) Sink in HD Receiving (-) (2”W, 1-1/2”V).
Final Design: No change.
v. Final Design: (1) Sink in OT (2”W, 1-1/2”V).
vi. Final Design: (1) Mop Sink in EMS (3”W, 2”V).
d. There is an existing 6” sanitary waste service for the existing building that will be
covered with the proposed addition. WPE does not know the condition of this piping,
however, would recommend replacing the piping that will be below the building with
new Schedule 40 PVC piping.
Final Design: This was not correct. There was not a 6” sanitary service on the exterior
that was covered with the new addition.
e. The new 6” piping main below the building addition will be utilized to connect the waste
from the plumbing fixtures listed above.
Final Design: From the plans on the Oncology project, there was a 4” sanitary stubbed
through the west wall of that addition for future connection. During design, it was
discovered that this stub was not installed. New sanitary for this project will be
connected to an existing 4” underground main about 6 feet east of the existing west
Oncology exterior wall.
f. Route vent piping from plumbing fixtures listed above to a single 4” vent through roof.
Final Design: To save piping lengths, (3) 4” vents through roof were utilized.
g. Route 1” HW from fixtures listed above to existing HW mains in existing building.
Provide shutoff isolation valve at connection to main. All HW piping shall be Type L
copper with 1” fiberglass insulation.
Final Design: No change.
h. Route 1” SCW from fixtures listed above to existing SCW mains inside existing building.
Provide shutoff isolation valve at connection to main. All SCW piping shall be Type L
copper with 1” fiberglass insulation.
Final Design: No change.
i. Route 3/4” recirculating hot water (RHW) from furthest fixture to existing RHW main
inside existing building. Provide shutoff isolation valve at connection to main. All RHW
piping shall be Type L copper with 1” fiberglass insulation. On recirculating system, at
connection to furthest fixture, provide 0.5 gpm automatic flow balancing valve.
Final Design: No change.
j. Floor drains shall not installed in any of the following rooms: IV Compounding (++),
Ante (+), HD Buffer (-), HD Storage (-), CSCA (-), HD Receiving (-).
Final Design: No change. However, (2) floor drains were added on the interstitial floor
to capture water in the event of a water leak in that space.
k. No water or vent piping shall be routed above the ceilings in any of the following rooms:
IV Compounding (++), Ante (+), HD Buffer (-), HD Storage (-), CSCA (-), HD Receiving (-).
Piping to sinks shall be routed inside walls of these spaces and out to walls in spaces not
requiring a clean space certification.
Final Design: No change.
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
19
D. Fire Protection
a. The existing fire sprinkler system serving the area will need to be modified as required in
order to meet the needs of the new floor plan arrangement.
Final Design: No change.
E. Temperature Controls
a. The control system will be a direct digital control BACNET system for the new HVAC
systems. All system graphics and points will be contained on the existing front end
workstation. The BAS shall control the following systems:
i. RTU-1 (Final Design: RTU-43):
1. Supply fan on/off.
2. Supply fan status and alarm.
3. Supply fan speed based on ductwork differential pressure.
4. Pre-filter pressure drop.
5. Final filter pressure drop.
Final Design: Omitted. Final filters are not installed in RTU.
6. Exhaust fan on/off.
Final Design: Omitted. Exhaust fan not included with RTU.
7. Exhaust fan status and alarm.
Final Design: Omitted. Exhaust fan not included with RTU.
8. Exhaust fan speed based on fan airflow (calculated differential between
outside air flow measurement and minimum outside air quantity
(economizer mode only)).
Final Design: Omitted. Exhaust fan not included with RTU.
9. Outside air damper modulation.
10. Return air damper modulation.
11. Mixed air temperature.
12. Discharge air temperature.
13. Heating coil discharge air temperature.
14. Heating coil control valve modulation.
15. Chilled water coil control valve modulation.
16. Final Design: Return air humidity.
17. Final Design: Return air temperature.
18. Final Design: Heating coil discharge humidity.
19. Final Design: Desiccant wheel supply bypass damper.
20. Final Design: Desiccant wheel mixed air bypass damper.
21. Final Design: Discharge air dewpoint.
22. Final Design: Discharge air humidity.
23. Final Design: Desiccant wheel on/off.
ii. RTU-2:
1. Supply fan on/off.
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
20
2. Supply fan status and alarm.
3. Supply fan speed based on ductwork differential pressure.
4. Pre-filter pressure drop.
5. Final filter pressure drop.
6. Exhaust fan on/off.
7. Exhaust fan status and alarm.
8. Exhaust fan speed based on space pressure sensor.
9. Outside air damper modulation.
10. Return air damper modulation.
11. Mixed air temperature.
12. Discharge air temperature.
13. Heating coil discharge air temperature.
14. Heating coil control valve modulation.
15. Chilled water coil control valve modulation.
Final Design: RTU-2 was omitted. Existing AHU-2 was used for the new OT
portion of the project.
iii. VAV boxes (13) (Final Design: Quantity of (10)):
1. Box airflow and alarm.
2. Reheat coil control valve modulation.
3. Damper modulation.
4. Discharge air temperature.
iv. Radiant Ceiling Panels (4) (Final Design: No change):
1. Reheat control valve modulation.
v. Exhaust Fans (10) (Final Design: Quanity of (2)):
1. Exhaust fan on/off.
2. Exhaust fan status and alarm.
vi. Induct Humidifiers (2) (Final Design: Quantity of (1)):
1. Steam control valve modulation.
vii. Combination space humidity/temperature sensors (12) (Final Design: Quantity
of (11)).
viii. Space pressure sensors (1).
Final Design: No pressure sensors.
ix. HEPA Filter Fan Modules (5):
1. Fan status and alarm.
Final Design: Omitted. Fan filter modules not used.
F. HVAC Piping
a. This addition will require the relocation of (1) air cooled chiller located on grade along
the north of the existing building. This equipment will be relocated to the roof of the
new addition and chilled water re-piped from their new locations on the roof down to
existing piping connection points in the new addition. All new piping shall be Schedule
40 black steel.
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
21
Final Design: This addition will require the relocation of (2) air cooled chillers and (1)
condensing unit located on grade along the north of the existing building. This
equipment will be relocated to the roof of the new addition and chilled/refrigerant
piping routed from their new locations on the roof down to existing piping connection
points on the exterior grade. All new piping shall be Schedule 40 black steel.
b. Route Low Pressure Steam piping to the following listed devices. Connect new 1-1/4”
LPS piping main to existing steam piping main inside existing building. Provide shutoff
isolation valve at connection to main. All LPS piping shall be Schedule 40 steel with 1”
fiberglass insulation.
i. RTU-1 Induct Humidifier Distributor: 1-1/4” LPS.
ii. RTU-2 Induct Humidifier Distributor: 3/4” LPS.
Final Design: Route Low Pressure Steam piping to the following listed devices.
Connect new 1” LPS piping main to existing steam piping main inside existing building.
Provide shutoff isolation valve at connection to main. All LPS piping shall be Schedule
40 steel with 1” fiberglass insulation.
i. H-1 Induct Humidifier Distributor: 1” LPS.
c. Route Low Pressure Steam condensate piping to the following listed devices. Connect
new 1” LPCR piping main to existing main inside existing building. Provide shutoff
isolation valve at connection to main. All LPS piping shall be Schedule 40 steel with 1”
fiberglass insulation.
i. RTU-1 Induct Humidifier Distributor: 3/4” LPCR.
ii. RTU-2 Induct Humidifier Distributor: 3/4” LPCR.
Provide F&T trap and accessories at each distributor.
Final Design: Route Low Pressure Steam condensate piping to the following listed
devices. Connect new 3/4” LPR piping main to existing main inside existing building.
Provide shutoff isolation valve at connection to main. All LPS piping shall be Schedule
40 steel with 1” fiberglass insulation.
i. H-1 Induct Humidifier Distributor: 3/4” LPR.
Provide F&T trap and accessories at each distributor.
d. Route reheat heating water supply and return piping to the following listed devices.
Connect new 1-1/4” reheat HWS and HWR piping main to existing piping mains inside
existing building. Provide shutoff isolation valve at connection to main. All reheat HWS
and HWR piping shall be Schedule 40 steel with 1” fiberglass insulation.
i. Radiant Ceiling Panels in OT area: 3/4" (0.5 gpm).
ii. (13) VAV boxes: 3/4” each (1 gpm each).
At each device, provide a coil kit complete with shutoff valves, strainer, and automatic
flow balancing valve.
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
22
Final Design: Route reheat heating water supply and return piping (HWS/R) to the
following listed devices. Connect new 1-1/4” HWS and HWR piping main to existing
piping mains inside existing building. Provide shutoff isolation valve at connection to
main. All reheat HWS and HWR piping shall be Schedule 40 steel with 1” fiberglass
insulation.
iii. Radiant Ceiling Panels in OT area: 3/4" (0.5 gpm).
iv. (10) VAV boxes: 3/4” each (1 gpm each).
v. Hydronic unit heater UH-1: 3/4" (1 gpm).
At each device, provide a coil kit complete with shutoff valves, strainer, and automatic
flow balancing valve.
e. (Option #1 RTUs) Route chilled water supply and return piping to the following listed
devices. Connect new 2-1/2” CWS and CWR piping existing piping mains inside existing
building. Provide shutoff isolation valve at connection to main. All CWS and CWR piping
shall be Schedule 40 steel with 1” fiberglass insulation.
i. RTU-1: 2" (48 gpm).
ii. RTU-2: 1-1/4" (12 gpm).
At each device, provide a coil kit complete with shutoff valves, strainer, and automatic
flow balancing valve.
Final Design: (Option #1 RTUs) Route chilled water supply and return piping to the
following listed devices. Connect new 2-1/2” GCS and GCR piping existing piping
mains inside existing building. Provide shutoff isolation valve at connection to main.
All GCS and GCR piping shall be Schedule 40 steel with 1” fiberglass insulation.
iii. RTU-43: 2-1/2" (63 gpm).
iv. FC-1: 1" (3 gpm).
At each device, provide a coil kit complete with shutoff valves, strainer, and automatic
flow balancing valve.
f. Route heating water supply and return piping to the following listed devices. Connect
new 2” HWS and HWR piping main to existing mains inside existing building. Provide
shutoff isolation valve at connection to main. All HWS and HWR piping shall be
Schedule 40 steel with 1” fiberglass insulation.
i. RTU-1: 2” (28 gpm).
ii. RTU-2: 1” (5 gpm).
At each device, provide a coil kit complete with shutoff valves, strainer, and automatic
flow balancing valve.
Final Design: Route heating water supply and return piping (GHS and GHR) to the
following listed devices. Connect new 1-1/2” GHS and GHR piping main to existing
mains inside existing building. Provide shutoff isolation valve at connection to main.
All HWS and HWR piping shall be Schedule 40 steel with 1” fiberglass insulation.
iii. RTU-43: 1-1/2” (20 gpm).
At each device, provide a coil kit complete with shutoff valves, strainer, and automatic
flow balancing valve.
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
23
g. The approximate total loads imposed by the project on the existing campus systems are
as follows:
i. Steam (Humidification): 100 #/hr.
ii. Chilled Water: 23.6 Tons (63 gpm).
iii. Reheat Heating Water: 116,000 BTUH (14 gpm).
iv. Heating Water: 293,000 BTUH (33 gpm).
Final Design: The approximate total loads imposed by the project on the existing
campus systems are as follows:
v. Steam (Humidification): 73 #/hr.
vi. Chilled Water: 24 Tons (60 gpm).
vii. Reheat Heating Water: 150,400 BTUH (12.5 gpm).
viii. Heating Water: 280,000 BTUH (20 gpm).
G. Electrical Distribution
a. The hospital is served by both normal and emergency electrical sources. Electrical
panels for both normal-power and emergency-power systems are installed in most
instances in electrical and mechanical rooms.
b. Lighting, receptacle, and equipment loads in the constructed pharmacy space will be fed
from new panels. New panel location(s) will be reviewed with the architect and VA for
optimal placement in compliance with VA standards and design guidelines. Where
existing spaces are remodeled the electrical loads will be fed from existing panels.
Where new space is added for other departments the electrical loads will be connected
to existing panels wherever possible. The need for new panels for other departments
will be analyzed by the design team and addressed on a case-by-case basis.
c. Electrical loads will primarily be fed from the normal power source. Emergency power
will be utilized as directed by the VA design guidelines and review by the local VA
engineer/project manager.
d. Life safety, critical branch, and equipment branch loads will be circuited as determined
by the VA design Guidelines and in conjunction with the National Electrical Code.
Emergency power connection shall be provided for equipment that needs to operate
continuously and cannot be interrupted. Equipment such as refrigerators/freezers,
safes, etc., shall be connected to the building emergency power system.
H. Lighting Systems
a. All lighting in the pharmacy space will be new.
b. Light fixtures will utilize energy-efficient LED sources.
c. Light fixtures will be connected to emergency sources (i.e. life safety and critical
branches) as required by the VA design guidelines.
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
24
d. It is anticipated that new light fixtures will be lay-in style, compatible with 2’x2’
acoustical tile ceilings. Suspended light fixtures will be utilized in
mechanical/electrical/storage type spaces without ceilings.
e. Lighting performance (lighting levels and lighting power densities) will be designed in
accordance with the Illuminating Engineering Society (IES) guidelines and VA design
guidelines, which includes design standard ASHRAE 90.1.
f. Lighting controls will be designed in accordance with VA design guidelines, which
includes automatic lighting control components such as occupancy and vacancy sensors.
Dimming will be utilized where multi-level lighting scenes are required.
I. Power Systems
a. Receptacle layouts will be designed in accordance with VA design guidelines.
b. Motors will be controlled by motor starters and VFD’s (variable frequency drives), as
determined by the mechanical design.
c. Connections to systems furniture will be either a) from adjacent walls, or b) via power
poles. This shall be determined during design by the architect and VA.
d. All wiring shall be concealed in stud-wall construction and above accessible suspended
ceilings. Surface-mounted raceways shall be utilized in spaces such as mechanical,
electrical, and information-technology rooms, and in remodel spaces where concealing
raceways is cost-prohibitive.
e. Floor boxes will be provided as directed by the VA design guidelines.
J. Telecommunications Systems
a. Intercom, telephone, and computer systems will all be provided in the pharmacy
construction project.
b. Voice, Data, and Intercom Systems will be designed in accordance with the VA design
guidelines. The design team will review available capacity of the existing IT
infrastructure and connect new voice and data drops to existing racks wherever
possible. Where existing voice and data infrastructure does not have sufficient capacity
to accommodate new outlets, the design team will work closely with the VA to provide
means to serve new outlets.
c. Any voice and data required for remodeled spaces shall connect to voice/data
infrastructure previously serving those spaces.
d. Wireless Access System: existing wireless access points will be reused. The existing
WAP’s (wireless access points) will be removed prior to demolition; existing WAP data
cables can be coiled and reused; WAP’s may be installed in the same locations where
they were removed.
e. Nurse Call System:
i. The existing nurse call system will be extended to the remodeled OT space.
f. Clock System: not anticipated in this project.
g. Television System: not anticipated in this project.
4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759
SIOUX FALLS
25
h. Audio/Visual System: is not anticipated in this project.
i. Overhead Paging System: will be provided in accordance with the VA design guidelines.
K. Fire Alarm System
a. An extension to the existing fire alarm layout will be designed in accordance with
current Codes and VA design guidelines. Existing devices removed during any
demolition may be reused provided they are in good working order. New devices will be
provided as required.
L. Access Control System (card access)
a. Access control shall be provided in compliance with VA design guidelines.
M. Video Surveillance System
a. Video surveillance shall be provided in compliance with VA design guidelines.
i. Final Design: A stand-alone video surveillance system shall be provided in
compliance with local Sioux Falls VA site-specific requirements.
N. Security/Intrusion Detection System
a. Not anticipated in this project.
i. Final Design: Intrusion detection shall be provided in compliance with local
Sioux Falls VA site-specific requirements.