VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA...

50
VA SIOUX FALLS PHARMACY ADDITION FOR USP COMPLIANCE Sioux Falls, South Dakota VA Project #438-500 SGA # 181906 Project Narratives: 100% Bid Set December 21, 2018

Transcript of VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA...

Page 1: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

VA SIOUX FALLS

PHARMACY ADDITION FOR USP COMPLIANCE

Sioux Falls, South Dakota

VA Project #438-500

SGA # 181906

Project Narratives:

100% Bid Set

December 21, 2018

Page 2: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards
Page 3: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

Architectural Design Narrative VA Project #438-500 P a g e 1 | 1

Architectural Design Narrative

VA Project #438-500

VA Contract #36E77618C0023

December 11, 2018

U.S. Department of Veterans Affairs Royal C. Johnson Veterans Memorial Center Phase II – Sioux Falls Pharmacy Addition for USP 800 Compliance Building #5

Summary of Work:

The current pharmacy at the Sioux Valls VA Medical Center does not meet USP 800 standards and is inadequate in size and

storage for current and future needs. The VA is requiring USP 800 compliance by December 2019. After discussing multiple

options, we determined the best choice to accomplish the goal would be to add a pharmacy adjacent to Oncology and

Occupational Therapy. After completion, the addition will be able to accommodate all compounding needs while the current

pharmacy is remodeled to be compliant with USP 800 standards in a future project. When both pharmacies are USP 800

compliant, this new pharmacy will be solely used for the adjacent Oncology department.

This project was limited to 2,300 SF and the location of the new pharmacy requires moving the Occupational Therapy treatment

rooms and work stations. Care was taken to maintain the current amount of space and storage in Occupational Therapy. Staff in

this department would have liked to maintain their exterior view, but this was impossible due to the existing grade elevation. To

compensate for this loss of exterior view and in an effort to save money and reduce waste, we chose to reuse their existing

windows and added an additional one to provide exceptional amounts of natural daylight into the space.

To connect the pharmacy to Oncology, the Oncology break room needed to be partially relocated into this addition. This was the

best option to interfere as little as possible with the Oncology ward, which was just completed in the spring on 2018. Our

addition also interfered with some windows in Oncology. Many options were discussed and we chose to make them a feature.

Our main determinates here were again, not wanting to interfere with the Oncology infrastructure or operations and not

wanting our alterations to cost a lot of money.

Blast and physical security requirements played a large role early in the design process, but it was later determined that this

addition is designed as an extension of the existing building so we received permission to use the design standards of the

existing building. Designing and building for blast and physical security requirements would have elongated the length of the

project and made it extremely difficult to meet all USP 800 requirements by the due date set by the VA.

This project was an extension of fairly recent additions, so no accommodation for hazardous materials was necessary.

Key Challenges:

The successful timeline of this project required excavation and footings to be completed before harsh winter conditions set in,

which was only 3 months after design began. This project being completed as Design/Build was critical to its success. The project

also required phasing to keep Occupational Therapy and Oncology operational with as little down time as possible.

This project required the relocation and accommodation of multiple mechanical units and a steam line. Three mechanical units

were relocated to the roof of the facility. After the 30% design submission, the location of the steam line was determined. The

cost of relocating the steam line was prohibitive so the addition was modified to accommodate the line as it is.

Interior Narrative:

The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards and Finishes, VA

Interior Design Manual - May 2018 and VA Room Finishes, Door & Hardware Schedule Program Guide, pg 18-14- April 2017 Rev.

5/2017. The colors, patterns and application were coordinated with the existing finishes in Oncology and Occupational Therapy

with assistance and approval from the Interior Designer at the Sioux Falls VA Medical Center.

Page 4: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards
Page 5: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

EHRHART GRIFFIN & ASSOCIATES • 300 N. DAKOTA AVE, SUITE 114 • SIOUX FALLS, SOUTH

DAKOTA 57104 • 605-339-7215

www.ehrhartgriffin.com

memo To: Todd Stone AIA, Stone Group Architects

From: Gregory B. Gerardy EI, Ehrhart Griffin & Associates

cc: Damian Grable PE LS, Ehrhart Griffin & Associates

Date: December 11, 2018

Project: (VA#438-500), (SGA#181906), (EGA#SD181135) Sioux Falls VA – Pharmacy Addition

Re: Civil Narrative for 100% Submittal

Design Overview:

The Sioux Falls VA - Pharmacy Addition civil site plan, is being designed using the most current additions of the

Veterans Affairs, City of Sioux Falls, and state of South Dakota design manuals and specifications. A poured

concrete structural retaining wall was discussed and determined to be utilized to protect ground cover over the

existing steam line, and allow access to the emergency exit. The proposed grading was designed for minimal impact

to the surrounding surface and follow existing drainage patterns.

• Existing Conditions:

The following are all within the foot print of the proposed addition, existing sidewalk, existing area inlet,

existing 8-inch water line, post indicator valve (PIV) with 6-inch water service line, and MRI utility

structures. All of these shall be removed or relocated outside of the footprint of the addition. The

relocation of the MRI utility structures was determined by the mechanical engineer. The rest were

determined by the civil engineer.

• Layout Design:

The existing steam line was potholed, and field located. This caused the location and geometry of the floor

plan and retaining wall to be redesigned and revised after the 30% Design Submittal. The retaining wall

shall be a poured concrete wall designed by a structural engineer. The proposed sidewalk was designed in

accordance with the most current Americans with Disabilities Act (ADA) design standards.

• Grading and Erosion Control Design:

The proposed grading was designed to drain to the east and away from the existing and proposed buildings.

Where it would be captured by the existing storm sewer system. The second design constraint was to keep

sufficient cover over the steam pipe and other existing utilities.

The limits of grading and reseeding areas were initially set at the edge of the match line between the

proposed grading and the existing surface. Following the 60% Review comments these areas were

extended north to the edge of sidewalk. Expanding these areas covers any damage to existing grass that

may occur during construction. Silt fence is to be installed to the east of the project at the edge of grading.

• Utility Design:

The existing sanitary, water and drainage services within the Rehab and Oncology Additions are being

continued and will pick up the internal plumbing for the proposed addition. A new area inlet will be

installed to capture the runoff from the sidewalk between the retaining wall and the addition. This will be

connected to the existing 6-inch drainage pipe. The fire service 8-inch water line and PIV were relocated

north west of the addition and reconnected to the 6-inch service entering the building. This was done to

keep the water lines from running under the addition’s footing. After the 60% Design Submittal and upon

excavation an existing 8-inch city owned water line was located and presumed to run under the proposed

Page 6: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

EHRHART GRIFFIN & ASSOCIATES • 300 N. DAKOTA AVE, SUITE 114 • SIOUX FALLS, SOUTH

DAKOTA 57104 • 605-339-7215

www.ehrhartgriffin.com

footing. It was determined to use bends and reroute the existing water line around the proposed footing if

needed.

VA Review Comments, and Responses:

• 30% Review:

1. No comments regarding civil plans.

• 60% Review:

1. Please detail the temporary egress path from the Oncology exit door once sidewalk is

demo’d.

▪ Keynote number eleven was added to sheet 5.CD101, along with a hatch of the

designated egress pathway that needs to be maintained during construction. GBG

2. Remove concrete cofferdam on area drain and make pipe continuous.

▪ Concrete cofferdam will be removed with the area inlet. The remaining pipe should be

continued by the plumbing plan to connect to any interior drains. No changes made to

civil plans. GBG

3. Show where the three MRI cooling units are moving to.

▪ The new location for the MRI units shall be determined in the field by the mechanical

engineer, and shown on mechanical plans. No changes made to civil plans. GBG

4. PIV needs power and data, please place on electrical plan.

▪ The electrical connection should be shown and designed by the electrical engineer. No

changes made to civil plans. GBG

5. May need to extend the seed/mulch/fertilize line to sidewalk (see dwg).

▪ Limits of grading and seed, mulch, fertilize area was expanded to match the sidewalk to

the north, see sheet 5.CG102. GBG

• 90% Review:

1. No comments regarding civil plans.

Page 7: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

315 N Main Ave Suite 200 Sioux Falls, SD 57104

(605) 343-9606

Page 1 of 4

A l b er t s on En gi n e er i n g I n c .

PROJECT MEMORANDUM 

Date:  December 21, 2018 To:  Todd Stone – Stone Group Architects From:  Aaron Hartwell  Project:  Sioux Falls VA – Pharmacy Addition Project #:  2018‐204  RE:  Structural Narrative for 100% Submittal 

STRUCTURAL NARRATIVE  Design Overview  The pharmacy addition, hereafter referred to as the Facility, is being structurally designed in accordance with the International Building Code (IBC) and applicable Dept. of Veterans Affairs design manuals.  Specifically, the Facility remodel is being designed to meet the requirements of the IBC 2015, ASCE 7‐10 (Minimum Design Loads for Buildings and Other Structures), and the following Dept. of Veterans Affairs design manuals: Physical Security Design Manual Mission Critical Facilities, Jan 2015, Structural Design Manual, Feb. 2014 and the Seismic Design Requirements H‐18‐8, Oct. 2016.  For the most part, all other national design codes and Veterans Affairs documents are referenced from these governing regulations.  Structural System(s) Selection and Overview  The addition to the existing facility is planned to be a steel framed bearing system with exterior non‐load bearing metal stud walls and conventional cast‐in‐place concrete spread foundations.    Addition to the existing structure will be separated to act independently of applied loads:  

Foundations:  Based upon the existing construction, the foundations for the addition are planned to be cast‐in‐place concrete with elevations to match existing where they tie in.  Foundations will be designed to the allowable bearing capacity of the soils that were indicated on the original construction documents and modified by construction documents of additions to the building in the area the planned addition is located. 

Exterior Walls:  Planned to be metal studs supporting brick veneer. Exterior walls will be non‐load bearing with slip connection at the top of wall 

Interstitial Floors:  Planned to be a concrete slab on metal deck supported by steel joists. Interior bearing stud walls to support joists. 

Roofs:  The roof framing for the addition is planned to be steel construction with metal roof deck.  The steel framing will provide an economical solution to support gravity and lateral loading. 

    

Page 8: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

315 N Main Ave Suite 200 Sioux Falls, SD 57104

(605) 343-9606

Page 2 of 4

A l b er t s on En gi n e er i n g I n c .

Analysis Method(s)  The bulk of the design of the facility remodel is being performed using hand calculations and by model software such as Risa 3D when required. New structure to be framed independently of existing building. No analysis of existing framing will be done except where new addition casts a snowdrift load on the existing roof to verify vertical load carrying capacity only.  Design Loads  The facility will be designed for the Dead Load (self weight) of the structure and the following superimposed loads:  

Occupancy Category:  The facility is regarded as an Essential Facility having a Type IV Occupancy in accordance with IBC 2015, ASCE 7‐10, and the VA Structural Design Manual due to the building being a hospital with surgery functions. 

Live Load:  In accordance with IBC 2015, ASCE 7‐10 and the VA Structural Design Manual as follows: 

1. Typical Floor ......................................................................   80 psf + 20 psf Partition 2. Lobbies & Main Corridors ................................................. 100 psf 3. Storage (Light) ................................................................... 150 psf 4. Mechanical Rooms ............................................................ 150 psf 

Snow Load:  In accordance the with IBC 2015 and ASCE 7‐10 and local codes, use the following: 1. Minimum Roof Snow ........................................................   36 psf (includes importance) 2. Ground Snow ....................................................................   40 psf 3. Importance Factor ............................................................  1.2 

Other:  Special case loadings are designed to be supported based on their actual weight and configurations.  In addition, floors shall be designed to accommodate a 2000 Lb. load placed anywhere on the floor in a 2.5 square area based on the VA Structural Design Manual. 

 Foundations  The new addition will be founded on conventional spread footings designed to meet the allowable soil bearing criteria that was used in original building design and modified by construction documents of existing additions to the building in the area the planned addition is located.  Footing elevations will be stepped as required to match existing foundations and to step with changes in grade around the addition  Subgrade preparation for the footings and floor slabs shall be in accordance with available soils investigations from previous addition projects to the hospital.     

Page 9: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

315 N Main Ave Suite 200 Sioux Falls, SD 57104

(605) 343-9606

Page 3 of 4

A l b er t s on En gi n e er i n g I n c .

Interstitial Floor Framing  Floor framing supporting mechanical load above main floor are planned to be composed of a concrete slab on metal deck. Steel joists spanning from interior bearing walls will support deck.  Roof Framing  The roof framing will be 1.5” metal roof deck supported by steel joist framing. Steel joists are planned to be supported by steel beam and column lines.  Deflection and Drift Limits  Deflection limits criteria for design of structural members are not greater than allowed by the applicable material standard (ACI, AISC, etc.), and IBC 2015 as follows:  

Roof Members:   1. Supporting Plaster (Hard) Ceilings .................................... L/360 Snow, L/240 Total 2. Supporting Ceiling (Hung) ................................................. L/240 Snow, L/180 Total 3. Not Supporting Ceiling ...................................................... L/180 Snow, L/120 Total 

Floor Members ............................................................................... L/360 Live, L/240 Total 

Walls: 1. Wind .................................................................................. L/240 

 Materials  The Facility will be designed for the following materials strengths to be used in construction:  

Concrete (f’c):   1. Foundation Walls & Footings ............................................ 3,000 psi 

Reinforcing Steel:   1. Standard Deformed .......................................................... ASTM A615, Grade 60 

Structural Steel:   1. WF Shapes ......................................................................... ASTM A992 (50 ksi) 2. Misc. Shapes / Plates ........................................................ ASTM A36 (36 ksi) 3. Structural Tubes ................................................................ ASTM A500, Grade B (46 ksi) 4. Structural Pipes ................................................................. ASTM A53, Type E, Grade B (35 ksi) 

 Special Inspections  Structures designed in accordance with IBC 2015 are required to have “special inspections” performed during the construction of the project.  “Special Inspections” are quality control inspections and testing that are performed on a periodic basis to ensure the adequacy of construction.  The Facility will have special inspections performed during the construction of the project meeting the requirements of IBC 2015 at a minimum as follows: 

Page 10: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

315 N Main Ave Suite 200 Sioux Falls, SD 57104

(605) 343-9606

Page 4 of 4

A l b er t s on En gi n e er i n g I n c .

 

Steel Construction .......................................................................... Table 1704.3 

Concrete Construction ................................................................... Table 1704.4 

Open Web Steel Joists ................................................................... Table 1705.2.3   

Page 11: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards
Page 12: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards
Page 13: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards
Page 14: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards
Page 15: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards
Page 16: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

SK -

1

FRAM

ING

Rev

ised

no

blas

t.r3d

HSS6X6X4

HSS6X6X4

HSS6X6X4

HSS6X6X4

HSS6X6X4

HSS6X6X4

HSS6X6X4

W16

X40

W16

X40

W16

X40

W16

X40

W18

X50

W16

X31

.75 Bar.7

5 Ba

r

.75

Bar

.75 Bar

.75 Bar

.75

Bar

HSS6X6X4

HSS6X6X4

W16

X40

W16X40

W16

X40

HSS6X6X4

Y

XZ

aaronh
Text Box
6/13
Page 17: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

Hot

Rol

led

Stee

l Pro

pert

ies

Labe

lE

[ksi

]G

[ksi

]N

uTh

erm

(\1E

5 F)

Den

sity

[k/ft

^3]

Yiel

d[ks

i]R

yFu

[ksi

]R

t1

A992

2900

011

154

.3.6

5.4

950

1.1

651.

12

A36

Gr.3

629

000

1115

4.3

.65

.49

361.

558

1.2

3A5

72 G

r.50

2900

011

154

.3.6

5.4

950

1.1

651.

14

A500

Gr.C

RN

D29

000

1115

4.3

.65

.49

461.

462

1.3

5A5

00 G

r.C R

ect

2900

011

154

.3.6

5.4

950

1.4

621.

36

A53

Gr.B

2900

011

154

.3.6

5.4

935

1.6

601.

27

A108

529

000

1115

4.3

.65

.49

501.

465

1.3

8A3

6 Br

ace

2900

011

154

.3.6

50

361.

558

1.2

Mem

ber P

rimar

y D

ata

Labe

lI J

oint

J Jo

int

K Jo

int

Rot

ate(

deg)

Sect

ion/

Shap

eTy

peD

esig

n Li

stM

ater

ial

Des

ign

Rul

es1

M1

N6

N13

HSS

6X6X

4C

olum

nTu

beA5

00 G

r.C R

ect

Typi

cal

2M

3N

7N

14H

SS6X

6X4

Col

umn

Tube

A500

Gr.C

Rec

tTy

pica

l3

M4

N3

N10

HSS

6X6X

4C

olum

nTu

beA5

00 G

r.C R

ect

Typi

cal

4M

5N

4N

11H

SS6X

6X4

Col

umn

Tube

A500

Gr.C

Rec

tTy

pica

l5

M6

N5

N12

HSS

6X6X

4C

olum

nTu

beA5

00 G

r.C R

ect

Typi

cal

6M

7N

1N

8H

SS6X

6X4

Col

umn

Tube

A500

Gr.C

Rec

tTy

pica

l7

M8

N2

N9

HSS

6X6X

4C

olum

nTu

beA5

00 G

r.C R

ect

Typi

cal

8M

10N

12N

11W

16X4

0Be

amTu

beA9

92Ty

pica

l9

M11

N11

N10

W16

X40

Beam

Tube

A992

Typi

cal

10M

12N

10N

13W

16X4

0Be

amTu

beA9

92Ty

pica

l11

M13

N8

N9

W16

X40

Beam

Tube

A992

Typi

cal

12M

15N

19N

14W

18X5

0Be

amTu

beA9

92Ty

pica

l13

M16

N12

N8

W16

X31

Beam

Tube

A992

Typi

cal

14M

18N

5N

11.7

5 Ba

rH

Brac

eN

one

A36

Brac

eTy

pica

l15

M19

N4

N12

.75

Bar

HBr

ace

Non

eA3

6 Br

ace

Typi

cal

16M

20N

12N

1.7

5 Ba

rH

Brac

eN

one

A36

Brac

eTy

pica

l17

M21

N5

N8

.75

Bar

HBr

ace

Non

eA3

6 Br

ace

Typi

cal

18M

22N

1N

9.7

5 Ba

rH

Brac

eN

one

A36

Brac

eTy

pica

l19

M23

N2

N8

.75

Bar

HBr

ace

Non

eA3

6 Br

ace

Typi

cal

20M

23A

N15

N16

HSS

6X6X

4C

olum

nTu

beA5

00 G

r.C R

ect

Typi

cal

21M

24N

17N

18H

SS6X

6X4

Col

umn

Tube

A500

Gr.C

Rec

tTy

pica

l22

M25

AN

13N

16W

16X4

0Be

amW

ide

Flan

geA9

92Ty

pica

l23

M26

N18

N19

W16

X40

Beam

Wid

e Fl

ange

A992

Typi

cal

24M

28N

9N

18W

16X4

0Be

amW

ide

Flan

geA9

92Ty

pica

l25

M26

AN

187

N18

6H

SS6X

6X4

Col

umn

Tube

A500

Gr.C

Rec

tTy

pica

l

Hot

Rol

led

Stee

l Des

ign

Para

met

ers

Labe

lSh

ape

Leng

th[ft

]Lb

yy[ft

]Lb

zz[ft

]Lc

omp

top[

ft]Lc

omp

bot[f

t]L-

torq

ue[ft

]Ky

yKz

zC

bFu

nctio

n1

M1

HSS

6X6X

419

Late

ral

2M

3H

SS6X

6X4

19La

tera

l3

M4

HSS

6X6X

419

Late

ral

RIS

A-3D

Ver

sion

17.

0.0

Page

1 [Z

:\201

8\20

1820

4\D

-Des

ign

Cal

cula

tions

\RIS

A\FR

AMIN

G R

evis

ed n

o bl

ast.r

3d]

aaronh
Text Box
7/13
Page 18: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

Hot

Rol

led

Stee

l Des

ign

Para

met

ers

(Con

tinue

d)La

bel

Shap

eLe

ngth

[ft]

Lbyy

[ft]

Lbzz

[ft]

Lcom

p to

p[ft]

Lcom

p bo

t[ft]

L-to

rque

[ft]

Kyy

Kzz

Cb

Func

tion

4M

5H

SS6X

6X4

19La

tera

l5

M6

HSS

6X6X

419

Late

ral

6M

7H

SS6X

6X4

19La

tera

l7

M8

HSS

6X6X

419

Late

ral

8M

10W

16X4

020

5Lb

yyLa

tera

l9

M11

W16

X40

205

Lbyy

Late

ral

10M

12W

16X4

024

.997

5Lb

yyLa

tera

l11

M13

W16

X40

265

Lbyy

Late

ral

12M

15W

18X5

035

.85

5Lb

yyLa

tera

l13

M16

W16

X31

405

Lbyy

Late

ral

14M

18.7

5 Ba

r27

.586

Late

ral

15M

19.7

5 Ba

r27

.586

Late

ral

16M

20.7

5 Ba

r44

.283

Late

ral

17M

21.7

5 Ba

r44

.283

Late

ral

18M

22.7

5 Ba

r32

.202

Late

ral

19M

23.7

5 Ba

r32

.202

Late

ral

20M

23A

HSS

6X6X

419

Late

ral

21M

24H

SS6X

6X4

19La

tera

l22

M25

AW

16X4

04

5Lb

yyLa

tera

l23

M26

W16

X40

7.77

85

Lbyy

Late

ral

24M

28W

16X4

07.

071

Lbyy

Late

ral

25M

26A

HSS

6X6X

419

Late

ral

Bas

ic L

oad

Cas

esBL

C D

escr

iptio

nC

ateg

ory

X G

ravi

tyY

Gra

vity

Z G

ravi

tyJo

int

Poin

tD

istri

bute

dAr

ea(M

emb.

..Su

rface

(Pla

t...

1D

ead

DL

-15

2Li

veLL

53

Snow

SL5

4W

ind

XW

LX2

55

Win

d Z

WLZ

15

6Bl

ast N

/SO

L11

57

Blas

t E/W

OL2

25

8BL

C 1

Tra

nsie

nt A

rea

Load

sN

one

979

BLC

2 T

rans

ient

Are

a Lo

ads

Non

e97

10BL

C 3

Tra

nsie

nt A

rea

Load

sN

one

9711

BLC

4 T

rans

ient

Are

a Lo

ads

Non

e97

12BL

C 5

Tra

nsie

nt A

rea

Load

sN

one

97

RIS

A-3D

Ver

sion

17.

0.0

Page

2 [Z

:\201

8\20

1820

4\D

-Des

ign

Cal

cula

tions

\RIS

A\FR

AMIN

G R

evis

ed n

o bl

ast.r

3d]

aaronh
Text Box
8/13
Page 19: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

Load

Com

bina

tions

Des

crip

tion

Solv

ePD

el...

SRSS

BLC

Fact

orBL

CFa

ctor

BLC

Fact

orBL

CFa

ctor

BLC

Fact

orBL

CFa

ctor

BLC

Fact

orBL

CFa

ctor

BLC

Fact

orBL

CFa

ctor

1IB

C 1

6-1

Yes

YD

L1.

42

IBC

16-

2 (a

)Ye

sY

DL

1.2

LL1.

6LL

S1.

63

IBC

16-

2 (b

)Ye

sY

DL

1.2

LL1.

6LL

S1.

6SL

.5SL

N.5

4IB

C 1

6-3

(c)

Yes

YD

L1.

2SL

1.6

SLN

1.6

LL.5

LLS

15

IBC

16-

3 (b

) (a)

Yes

YD

L1.

2W

LX.5

6IB

C 1

6-3

(b) (

b)Ye

sY

DL

1.2

WLZ

.57

IBC

16-

3 (d

) (a)

Yes

YD

L1.

2SL

1.6

SLN

1.6

WLX

.58

IBC

16-

3 (d

) (b)

Yes

YD

L1.

2SL

1.6

SLN

1.6

WLZ

.59

IBC

16-

4 (a

) (a)

Yes

YD

L1.

2W

LX1

LL.5

LLS

110

IBC

16-

4 (a

) (b)

Yes

YD

L1.

2W

LZ1

LL.5

LLS

111

IBC

16-

4 (b

) (a)

Yes

YD

L1.

2W

LX1

LL.5

LLS

1SL

.5SL

N.5

12IB

C 1

6-4

(b) (

b)Ye

sY

DL

1.2

WLZ

1LL

.5LL

S1

SL.5

SLN

.513

IBC

16-

6 (a

)Ye

sY

DL

.9W

LX1

14IB

C 1

6-6

(b)

Yes

YD

L.9

WLZ

115

BLAS

TY

DL

1O

L11

16IB

C 1

6-8

Yes

DL

117

IBC

16-

9Ye

sD

L1

LL1

LLS

118

IBC

16-

10 (b

)Ye

sD

L1

SL1

SLN

119

IBC

16-

11 (b

)Ye

sD

L1

LL.7

5LL

S.7

5SL

.75

SLN

.75

20IB

C 1

6-12

(a) (

a)Ye

sD

L1

WLX

.621

IBC

16-

12 (a

) (b)

Yes

DL

1W

LZ.6

22IB

C 1

6-13

(a) (

a)Ye

sD

L1

WLX

.45

LL.7

5LL

S.7

523

IBC

16-

13 (a

) (b)

Yes

DL

1W

LZ.4

5LL

.75

LLS

.75

24IB

C 1

6-13

(b) (

a)Ye

sD

L1

WLX

.45

LL.7

5LL

S.7

5SL

.75

SLN

.75

25IB

C 1

6-13

(b) (

b)Ye

sD

L1

WLZ

.45

LL.7

5LL

S.7

5SL

.75

SLN

.75

26IB

C 1

6-15

(a)

Yes

DL

.6W

LX.6

27IB

C 1

6-15

(b)

Yes

DL

.6W

LZ.6

28Bl

ast 2

YD

L1

OL2

1

Enve

lope

AIS

C 1

4th(

360-

10):

LRFD

Ste

el C

ode

Che

cks

Mem

ber

Shap

eC

ode

Che

ckLo

c[ft]

LCSh

ear C

heck

Loc[

ft]D

irLC

phi*P

nc [k

]ph

i*Pnt

[k]

phi*M

n y-

y [k

-ft]

phi*M

n z-

z [k

-ft]

Cb

Eqn

1M

1H

SS6X

6X4

.288

194

.004

0z

411

7.51

823

5.8

4242

1.67

4H

1-1b

2M

3H

SS6X

6X4

.164

194

.002

0y

411

7.51

823

5.8

4242

1.67

4H

1-1b

3M

4H

SS6X

6X4

.480

194

.006

0z

411

7.51

823

5.8

4242

1.67

4H

1-1a

4M

5H

SS6X

6X4

.344

04

.002

0y

1311

7.51

823

5.8

4242

2.25

1H

1-1a

5M

6H

SS6X

6X4

.238

194

.006

0y

411

7.51

823

5.8

4242

2.16

5H

1-1b

6M

7H

SS6X

6X4

.466

194

.013

0y

411

7.51

823

5.8

4242

2.17

1H

1-1a

7M

8H

SS6X

6X4

.599

194

.011

0y

411

7.51

823

5.8

4242

2.17

7H

1-1a

8M

10W

16X4

0.2

919.

333

4.1

100

y4

446.

675

531

47.6

2527

3.75

1H

1-1b

9M

11W

16X4

0.2

7710

.222

4.0

8820

y4

446.

675

531

47.6

2527

3.75

1H

1-1b

10M

12W

16X4

0.3

3112

.499

4.0

9724

.997

y4

431.

523

531

47.6

2527

3.75

1H

1-1b

11M

13W

16X4

0.5

3013

4.1

330

y4

427.

202

531

47.6

2527

3.75

1H

1-1b

12M

15W

18X5

0.8

487.

967

4.1

078.

365

y4

497.

8466

1.5

62.2

510

7.57

71.

338

H1-

1b

RIS

A-3D

Ver

sion

17.

0.0

Page

3 [Z

:\201

8\20

1820

4\D

-Des

ign

Cal

cula

tions

\RIS

A\FR

AMIN

G R

evis

ed n

o bl

ast.r

3d]

aaronh
Text Box
9/13
Page 20: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

Enve

lope

AIS

C 1

4th(

360-

10):

LRFD

Ste

el C

ode

Che

cks

(Con

tinue

d)M

embe

rSh

ape

Cod

e C

heck

Loc[

ft]LC

Shea

r Che

ckLo

c[ft]

Dir

LCph

i*Pnc

[k]

phi*P

nt [k

]ph

i*Mn

y-y

[k-ft

]ph

i*Mn

z-z

[k-ft

]C

bEq

n13

M16

W16

X31

.070

4.88

914

.007

40y

1226

1.13

741

0.85

26.3

6327

.215

1.18

8H

1-1b

14M

18.7

5 Ba

r.1

670

14.0

010

12.0

3214

.314

.179

.179

1H

1-1b

*15

M19

.75

Bar

.344

013

.000

09

.032

14.3

14.1

79.1

791

H1-

1a*

16M

20.7

5 Ba

r.4

330

12.0

020

4.0

1214

.314

.179

.179

1H

1-1a

*17

M21

.75

Bar

.003

013

.001

013

.012

14.3

14.1

79.1

791

H1-

1b*

18M

22.7

5 Ba

r.0

120

4.0

040

4.0

2314

.314

.179

.179

1H

1-1b

*19

M23

.75

Bar

.329

011

.001

012

.023

14.3

14.1

79.1

791

H1-

1a*

20M

23A

HSS

6X6X

4.0

5519

4.0

010

y7

117.

518

235.

842

421.

674

H1-

1b21

M24

HSS

6X6X

4.0

670

4.0

030

z12

117.

518

235.

842

421.

674

H1-

1b*

22M

25A

W16

X40

.015

1.95

64

.054

4y

444

6.67

553

147

.625

273.

751

H1-

1b23

M26

W16

X40

.033

4.14

84

.035

7.77

8y

444

6.67

553

147

.625

273.

751

H1-

1b24

M28

W16

X40

.153

04

.058

3.53

6z

440

8.91

531

47.6

2527

3.75

3.04

9H

1-1b

25M

26A

HSS

6X6X

4.3

4619

4.0

030

y12

117.

518

235.

842

421.

674

H1-

1a

RIS

A-3D

Ver

sion

17.

0.0

Page

4 [Z

:\201

8\20

1820

4\D

-Des

ign

Cal

cula

tions

\RIS

A\FR

AMIN

G R

evis

ed n

o bl

ast.r

3d]

aaronh
Text Box
10/13
Page 21: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

SK -

1

BIG

WIN

DO

W O

PTIO

N F

RAM

E.r3

d

N1

N2

N3

N4

N5

N6

N7

N8

HSS6X3X4

HSS6X3X4

HSS8

X6X4

2-60

0S16

2-54

-BB

Y

XZ

aaronh
Text Box
11/13
Page 22: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

Hot

Rol

led

Stee

l Pro

pert

ies

Labe

lE

[ksi

]G

[ksi

]N

uTh

erm

(\1E

5 F)

Den

sity

[k/ft

^3]

Yiel

d[ks

i]R

yFu

[ksi

]R

t1

A992

2900

011

154

.3.6

5.4

950

1.1

651.

12

A36

Gr.3

629

000

1115

4.3

.65

.49

361.

558

1.2

3A5

72 G

r.50

2900

011

154

.3.6

5.4

950

1.1

651.

14

A500

Gr.B

RN

D29

000

1115

4.3

.65

.527

421.

458

1.3

5A5

00 G

r.B R

ect

2900

011

154

.3.6

5.5

2746

1.4

581.

36

A53

Gr.B

2900

011

154

.3.6

5.4

935

1.6

601.

27

A108

529

000

1115

4.3

.65

.49

501.

465

1.3

Mem

ber P

rimar

y D

ata

Labe

lI J

oint

J Jo

int

K Jo

int

Rot

ate(

deg)

Sect

ion/

Shap

eTy

peD

esig

n Li

stM

ater

ial

Des

ign

Rul

es1

M1

N1

N4

HSS

6X3X

4C

olum

nTu

beA5

00 G

r.B R

ect

Typi

cal

2M

2N

2N

3H

SS6X

3X4

Col

umn

Tube

A500

Gr.B

Rec

tTy

pica

l3

M3

N8

N7

HSS

8X6X

4Be

amTu

beA5

00 G

r.B R

ect

Typi

cal

4M

4N

6N

590

2-60

0S16

2-54

-BB

Beam

CS

A653

SS

Gr5

0/1

Typi

cal

5M

5N

4N

3R

IGID

Non

eN

one

RIG

IDTy

pica

l6

M6

N1

N2

RIG

IDN

one

Non

eR

IGID

Typi

cal

Hot

Rol

led

Stee

l Des

ign

Para

met

ers

Labe

lSh

ape

Leng

th[ft

]Lb

yy[ft

]Lb

zz[ft

]Lc

omp

top[

ft]Lc

omp

bot[f

t]L-

torq

ue[ft

]Ky

yKz

zC

bFu

nctio

n1

M1

HSS

6X3X

412

.75

Late

ral

2M

2H

SS6X

3X4

12.7

5La

tera

l3

M3

HSS

8X6X

415

Lbyy

Late

ral

Bas

ic L

oad

Cas

esBL

C D

escr

iptio

nC

ateg

ory

X G

ravi

tyY

Gra

vity

Z G

ravi

tyJo

int

Poin

tD

istri

bute

dAr

ea(M

emb.

..Su

rface

(Pla

t...

1D

ead

DL

-13

2W

ind

WL

13

BLC

2 T

rans

ient

Are

a Lo

ads

Non

e16

Load

Com

bina

tions

Des

crip

tion

Solv

ePD

el...

SRSS

BLC

Fact

orBL

CFa

ctor

BLC

Fact

orBL

CFa

ctor

BLC

Fact

orBL

CFa

ctor

BLC

Fact

orBL

CFa

ctor

BLC

Fact

orBL

CFa

ctor

1IB

C 1

6-3

(b)

Yes

YD

L1.

2W

L.5

2IB

C 1

6-4

(a)

Yes

YD

L1.

2W

L1

LL.5

LLS

13

IBC

16-

6Ye

sY

DL

.9W

L1

4IB

C 1

6-12

(a)

Yes

DL

1W

L.6

5IB

C 1

6-13

(a)

Yes

DL

1W

L.4

5LL

.75

LLS

.75

6IB

C 1

6-15

Yes

DL

.6W

L.6

RIS

A-3D

Ver

sion

17.

0.0

Page

1 [P

:\201

8\20

1820

4\D

-Des

ign

Cal

cula

tions

\RIS

A\BI

G W

IND

OW

OPT

ION

FR

AME.

r3d]

aaronh
Text Box
12/13
Page 23: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

Mem

ber A

ISC

15t

h(36

0-16

): LR

FD S

teel

Cod

e C

heck

sLC

Mem

ber

Shap

eU

C M

axLo

c[ft]

Shea

r UC

Loc[

ft]D

irph

i*Pnc

[k]

phi*P

nt[k

]ph

i*Mny

y[k-

ft]ph

i*Mnz

z[k-

ft]C

bEq

n1

1M

1H

SS6X

3X4

.314

4.25

.075

1.13

3z

55.0

0915

8.97

615

.215

24.8

061.

702

H1-

1b2

1M

2H

SS6X

3X4

.314

4.25

.075

1.13

3z

55.0

0915

8.97

615

.215

24.8

061.

702

H1-

1b3

1M

3H

SS8X

6X4

.222

7.5

.109

15y

176.

5425

5.43

845

.18

58.3

051.

219

H1-

1b4

2M

1H

SS6X

3X4

.386

4.25

.098

1.13

3z

55.0

0915

8.97

615

.215

24.8

061.

583

H1-

1b5

2M

2H

SS6X

3X4

.385

4.25

.098

1.13

3z

55.0

0915

8.97

615

.215

24.8

061.

583

H1-

1b6

2M

3H

SS8X

6X4

.262

7.5

.109

15y

176.

5425

5.43

845

.18

58.3

051.

219

H1-

1b7

3M

1H

SS6X

3X4

.324

4.25

.085

1.13

3z

55.0

0915

8.97

615

.215

24.8

061.

544

H1-

1b8

3M

2H

SS6X

3X4

.324

4.25

.085

1.13

3z

55.0

0915

8.97

615

.215

24.8

061.

544

H1-

1b9

3M

3H

SS8X

6X4

.217

7.5

.081

15y

176.

5425

5.43

845

.18

58.3

051.

219

H1-

1b10

4M

1H

SS6X

3X4

.287

4.25

.071

1.13

3z

55.0

0915

8.97

615

.215

24.8

061.

638

H1-

1b11

4M

2H

SS6X

3X4

.286

4.25

.071

1.13

3z

55.0

0915

8.97

615

.215

24.8

061.

638

H1-

1b12

4M

3H

SS8X

6X4

.200

7.5

.090

15y

176.

5425

5.43

845

.18

58.3

051.

219

H1-

1b13

5M

1H

SS6X

3X4

.265

4.25

.064

1.13

3z

55.0

0915

8.97

615

.215

24.8

061.

691

H1-

1b14

5M

2H

SS6X

3X4

.265

4.25

.064

1.13

3z

55.0

0915

8.97

615

.215

24.8

061.

691

H1-

1b15

5M

3H

SS8X

6X4

.188

7.5

.090

15y

176.

5425

5.43

845

.18

58.3

051.

219

H1-

1b16

6M

1H

SS6X

3X4

.206

4.25

.054

1.13

3z

55.0

0915

8.97

615

.215

24.8

061.

56H

1-1b

176

M2

HSS

6X3X

4.2

064.

25.0

541.

133

z55

.009

158.

976

15.2

1524

.806

1.55

9H

1-1b

186

M3

HSS

8X6X

4.1

397.

5.0

5415

y17

6.54

255.

438

45.1

858

.305

1.21

9H

1-1b

RIS

A-3D

Ver

sion

17.

0.0

Page

2 [P

:\201

8\20

1820

4\D

-Des

ign

Cal

cula

tions

\RIS

A\BI

G W

IND

OW

OPT

ION

FR

AME.

r3d]

aaronh
Text Box
13/13
Page 24: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards
Page 25: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

1

VA Sioux Falls – Pharmacy Addition

Mechanical/Electrical CD Narrative

December 12, 2018

A. HVAC

a. Two new rooftop units will be provided for this project, with one unit being variable air

volume (RTU-2) and one unit being constant volume (RTU-1). Separate units will be

provided to allow the new OT area to operate independently of the Pharmacy area.

Each area will be on different occupancy scheduling, while the Pharmacy area requires

precise pressure control and the OT area does not. In addition, RTU-1 serving the

Pharmacy will be required to be on backup emergency power, while RTU-2 serving the

OT area will not be. For this project, we will look at two strategies for the equipment.

The preferred Option #1 would be to utilize existing campus chilled water and heating

water, along with campus steam for humidification. Option #2 will still utilize campus

heating water and steam for humidification, but will utilize packaged DX cooling at the

equipment, in lieu of chilled water, should it be determined the campus chilled water

system cannot handle the additional capacity of the project. The loads for each system

are indicated in the narrative, and shortly after issue of this report, we will discuss the

capacity requirements with the VA and determine the best course of action for the

cooling system.

1. Final Design: In lieu of providing a variable volume RTU-2 for the OT portion of

the project, it was determined that the existing indoor air handing unit AHU-2

serving the existing OT space had enough spare capacity to serve the new OT

space. The existing AHU-2 is variable air volume and served with campus

chilled and heating water. For the new RTU-43 serving the pharmacy area, we

utilized option #1 which will use campus chilled water for campus, campus

heating water for heating, and campus steam for humidification.

b. (Option #1) RTU-1: 4,525 cfm supply air at 2.0” ESP with VFD; chilled water coil with

88.7F DB / 70.1F WB EAT, target 55F LAT off cooling coil (approximately 19 tons);

heating water preheat coil with 5F EAT, target 60F LAT off heating coil; 1,270 cfm

exhaust fan with VFD; insulated roof curb; Merv 8 pre-filter bank; Merv 14 final filter

bank; modulating outside air damper; modulating return air damper. Provide with

airflow measuring station on outside air opening and inlet airflow measuring station on

the exhaust fan.

1. Final Design: RTU-43: 3,950 cfm supply air at 4.0” ESP with VFD; chilled water

coil with 88.3F DB / 73.7F WB EAT, 23.6 tons; heating water preheat coil with -

5F EAT, 60F LAT off heating coil; insulated roof curb; Merv 8 pre-filter bank;

modulating outside air damper; modulating return air damper. Provide with

airflow measuring station on outside air opening and inlet airflow measuring

station on the exhaust fan. A desiccant dehumidification wheel was added to

the RTU in order to achieve the space temperature and humidity requirements

Page 26: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

2

in the compounding rooms (68F and 50%). Finally, since the compounding

rooms are served with HEPA filters for each space, the MERV 14 filters were

removed from the RTU and only MERV 8 filters provided.

c. (Option #2) RTU-1: 4,525 cfm supply air at 2.0” ESP with VFD; chilled water coil with

88.7F DB / 70.1F WB EAT, target 55F LAT off cooling coil (approximately 19 tons), 95F

ambient; provide variable capacity scroll compressors on all circuits, heating water

preheat coil with 5F EAT, target 60F LAT off heating coil; 1,270 cfm exhaust fan with

VFD; insulated roof curb; Merv 8 pre-filter bank; Merv 14 final filter bank; modulating

outside air damper; modulating return air damper. Provide with airflow measuring

station on outside air opening and inlet airflow measuring station on the exhaust fan.

1. Final Design: This option was not taken. See Option #1.

d. (Option #1) RTU-2: 1,590 cfm supply air at 2.0” ESP with VFD; chilled water coil with

80.4F DB / 65.5F WB EAT, target 55F LAT off cooling coil (approximately 5 tons); heating

water preheat coil with -3F EAT, target 60F LAT off heating coil; 1,140 cfm exhaust fan

with VFD; insulated roof curb; Merv 8 pre-filter bank; Merv 14 final filter bank;

modulating outside air damper; modulating return air damper. Provide with airflow

measuring station on outside air opening.

1. Final Design: This option was not taken. A new RTU was not provided for the

OT portion of the project.

e. (Option #2) RTU-2: 1,590 cfm supply air at 2.0” ESP with VFD; chilled water coil with

80.4F DB / 65.5F WB EAT, target 55F LAT off cooling coil (approximately 5 tons), 95F

ambient; provide variable capacity scroll compressors on all circuits, heating water

preheat coil with -3F EAT, target 60F LAT off heating coil; 1,140 cfm exhaust fan with

VFD; insulated roof curb; Merv 8 pre-filter bank; Merv 14 final filter bank; modulating

outside air damper; modulating return air damper. Provide with airflow measuring

station on outside air opening.

1. Final Design: This option was not taken. A new RTU was not provided for the

OT portion of the project.

f. In supply air ductwork main from RTU-1, above the ceiling of the Pharmacy space,

provide a duct mounted steam grid humidifier, sized for approximately 75 lb/hr. BAS

Contractor to provide control valve for humidifier and shall be controlled to maintain

humidity at minimum 30% in worst case space served by RTU-1. Ductwork within 3 feet

of humidifier, on both inlet and discharge side, shall be of stainless steel material.

1. Final design: This humidifier H-1 was provided in the supply ductwork from

RTU-43, and sized for 70 lb/hr. Ductwork within 7 feet of humidifier shall be

stainless steel per the VA specs. Finally, direction was given to use building

steam for this humidifier and not clean steam.

g. In supply air ductwork main from RTU-2, above the ceiling of the OT space, provide a

duct mounted steam grid humidifier, sized for approximately 25 lb/hr. BAS Contractor

to provide control valve for humidifier and shall be controlled to maintain humidity at

minimum 30% in worst case space served by RTU-2. Ductwork within 3 feet of

humidifier, on both inlet and discharge side, shall be of stainless steel material.

Page 27: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

3

1. Final Design: This humidifier was not installed. The OT space is served by the

existing air handling unit that serves the existing OT space.

h. The following rooms will be provided with the HVAC as indicated:

1. OT:

i. Provide (2) shutoff VAV boxes (700 cfm each, variable flow) with supply

ductwork distribution into the space. Terminate with aluminum

louvered diffusers. Provide VAV box with reheat coil. Connect VAV

boxes to supply air main from RTU-2.

1. Final Design: Provide (1) shutoff VAV boxes (900 cfm) with

supply ductwork distribution into the space. Terminate with

aluminum louvered diffusers. Provide VAV box with reheat

coil. Connect VAV box to existing supply air mains from air

handling unit serving the existing OT space.

ii. Provide (1) 24x24 egg crate return air grille in ceiling, connected to

return air main from RTU-2.

1. Final Design: A return grille was not provided in this area.

There is an existing return air grille within the existing building

that will be reused for return air back to the air handling unit.

iii. The BAS system will control the VAV box damper and reheat coil to

maintain space temperature set point. BAS Contractor will provide a

combination space temperature/humidity sensor in this space.

1. Final Design: No change.

iv. The BAS Contractor shall provide a space pressure sensor in this space

to control the speed of the exhaust fan in RTU-2 to maintain space

pressure set point of +0.03”.

1. Final Design: This was not provided. The existing air handling

unit has an exhaust fan which will control the pressure in this

space. The existing pressure sensor was not located in the

remodeled space.

v. Provide approximately (4) heating water radiant ceiling panels above

the perimeter windows in the OT room.

1. Final Design: No change.

vi. Space occupied cooling target: 75F.

1. Final Design: No change.

vii. Space occupied heating target: 70F.

1. Final Design: No change.

viii. Space maximum relative humidity: 60%.

1. Final Design: No change.

ix. Space minimum relative humidity: 30%.

1. Final Design: No change.

2. OT Offices:

i. Provide (1) shutoff VAV box (195 cfm, variable flow) with supply

ductwork distribution into the space. Terminate with aluminum

Page 28: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

4

louvered diffusers. Provide VAV box with reheat coil. Connect VAV

boxes to supply air main from RTU-2.

1. Final Design: Provide (1) shutoff VAV boxes (300 cfm) with

supply ductwork distribution into the space. Terminate with

aluminum louvered diffusers. Provide VAV box with reheat

coil. Connect VAV box to existing supply air mains from air

handling unit serving the existing OT space.

ii. Provide (1) 24x12 egg crate return air grille in ceiling, connected to

return air main from RTU-2.

1. Final Design: Provide (1) 24x12 egg crate return air grille in

ceiling. Connect to existing return air mains from air handling

unit serving the existing OT space.

iii. The BAS system will control the VAV box damper and reheat coil to

maintain space temperature set point. BAS Contractor will provide a

combination space temperature/humidity sensor in this space.

1. Final Design: No change.

iv. Space occupied cooling target: 75F.

1. Final Design: No change.

v. Space occupied heating target: 70F.

1. Final Design: No change.

vi. Space maximum relative humidity: 60%.

1. Final Design: No change.

vii. Space minimum relative humidity: 30%.

1. Final Design: No change.

3. Pharmacy:

i. Provide (1) shutoff VAV box (1,100 cfm, constant flow) with supply

ductwork distribution into the space. Terminate with (6) aluminum

louvered diffusers. Provide VAV box with reheat coil. Connect VAV

boxes to supply air main from RTU-1.

1. Final Design: Provide (1) shutoff VAV box (1,035 cfm, constant

flow) with supply ductwork distribution into the space.

Terminate with (5) aluminum louvered diffusers. Provide VAV

box with reheat coil. Connect VAV boxes to supply air main

from RTU-1.

ii. The BAS system will control the VAV box damper and reheat coil to

maintain space temperature set point. BAS Contractor will provide a

combination space temperature/humidity sensor in this space.

1. Final Design: No change.

iii. Provide (1) 24x24 egg crate return air grille in ceiling, connected to

return air main from RTU-1.

1. Final Design: No change.

iv. Provide master central monitoring station by the pharmacy

workstations that displays the pressure differentials between the

following spaces:

Page 29: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

5

1. Pharmacy to Ante (+)

2. Ante (+) to IV Prep (++)

3. Ante (+) to HD Buffer (-)

4. Pharmacy to HD Storage (-)

5. Pharmacy to CSCA (-)

6. Pharmacy to Receiving (-)

Final Design: No change. The monitoring station is located by the

pharmacy workstation. See note M454 on sheet 5.HV101.

v. At door from Pharmacy into Ante (+), on Pharmacy side of door, provide

pressure controller that displays the pressure differential between

Pharmacy and Ante (+).

Final Design: No change.

vi. Space occupied cooling target: 75F.

Final Design: No change.

vii. Space occupied heating target: 70F.

Final Design: No change.

viii. Space maximum relative humidity: 60%.

Final Design: No change.

ix. Space minimum relative humidity: 30%.

Final Design: No change.

4. Pharmacy Office:

i. Provide (1) shutoff VAV box (120 cfm, constant flow) with supply

ductwork distribution into the space. Terminate with aluminum

louvered diffusers. Provide VAV box with reheat coil. Connect VAV

boxes to supply air main from RTU-1.

Final Design: A VAV box was not provided for this office. This office is

a total interior space like the open pharmacy area, and as such, supply

air from the Pharmacy work area VAV box was used for the office.

ii. The BAS system will control the VAV box damper and reheat coil to

maintain space temperature set point. BAS Contractor will provide a

combination space temperature/humidity sensor in this space.

Final Design: A space temperature and humidity sensor is installed in

both the Office and Pharmacy area. Each device will be used to control

the single VAV box to maintain work case in each space. The

conditions between spaces is not anticipated to very much at all.

iii. Provide (1) 24x12 egg crate return air grille in ceiling, connected to

return air main from RTU-1.

Final Design: The grille was not provided. The air supplied to the

Office will transfer out/under the door and into the Pharmacy area,

where it is returned to RTU-43.

iv. Space occupied cooling target: 75F.

Final Design: No change.

v. Space occupied heating target: 70F.

Final Design: No change.

Page 30: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

6

vi. Space maximum relative humidity: 60%.

Final Design: No change.

vii. Space minimum relative humidity: 30%.

Final Design: No change.

5. Pharmacy Breakroom:

i. Provide (1) shutoff VAV box (150 cfm, constant flow) with supply

ductwork distribution into the space. Terminate with aluminum

louvered diffusers. Provide VAV box with reheat coil. Connect VAV

boxes to supply air main from RTU-1.

Final Design: Provide (1) shutoff VAV box (210 cfm, constant flow)

with supply ductwork distribution into the space. Terminate with

aluminum louvered diffusers. Provide VAV box with reheat coil.

Connect VAV boxes to supply air main from RTU-43.

ii. The BAS system will control the VAV box damper and reheat coil to

maintain space temperature set point. BAS Contractor will provide a

combination space temperature/humidity sensor in this space.

Final Design: No change.

iii. Provide (1) roof mounted exhaust fan (285 cfm, constant flow) with

exhaust ductwork distribution into the space. Terminate at (1) 24x12

egg crate exhaust air grille in ceiling. Provide motorized damper at

ductwork connection to fan. The BAS will control the damper to be

open whenever the fan is operating.

Final Design: Provide (1) roof mounted exhaust fan (400 cfm, constant

flow) with exhaust ductwork distribution into the space. Terminate at

(1) 24x12 egg crate exhaust air grille in ceiling. The fan is provided

with a gravity backdraft damper.

iv. Space occupied cooling target: 75F.

Final Design: No change.

v. Space occupied heating target: 70F.

Final Design: No change.

vi. Space maximum relative humidity: 60%.

Final Design: No change.

vii. Space minimum relative humidity: 30%.

Final Design: No change.

6. Lockers:

i. Provide (1) shutoff VAV box (290 cfm, constant flow) with supply

ductwork distribution into the space. Terminate with aluminum

louvered diffusers. Provide VAV box with reheat coil. Connect VAV

boxes to supply air main from RTU-1.

Final Design: A VAV box was not provided for this space. This space is

a total interior space like the open pharmacy area, and as such, supply

air from the Pharmacy work area VAV box was used for the lockers.

Page 31: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

7

ii. The BAS system will control the VAV box damper and reheat coil to

maintain space temperature set point. BAS Contractor will provide a

combination space temperature/humidity sensor in this space.

Final Design: A temperature and humidity sensor was not installed for

this space.

iii. Provide (1) roof mounted exhaust fan (140 cfm, constant flow) with

exhaust ductwork distribution into the space. Terminate at (1) 24x12

egg crate exhaust air grille in ceiling. Provide motorized damper at

ductwork connection to fan. The BAS will control the damper to be

open whenever the fan is operating.

Final Design: Provide (1) roof mounted exhaust fan (150 cfm, constant

flow) with exhaust ductwork distribution into the space. Terminate at

(1) 24x12 egg crate exhaust air grille in ceiling. The fan is provided

with a gravity backdraft damper.

iv. Space occupied cooling target: 75F.

Final Design: No change.

v. Space occupied heating target: 70F.

Final Design: No change.

vi. Space maximum relative humidity: 60%.

Final Design: No change.

vii. Space minimum relative humidity: 30%.

Final Design: No change.

7. IV Compounding (++):

i. This room is required to be positive to the adjacent Ante Room (+). USP

800 requires minimum 30 ACH of HEPA filtered supply air to the space,

which equates to approximately 370 cfm of filtered supply air. One

hood will be installed in the room at approximately 390 cfm of exhaust.

To maintain a (++) pressure differential in the room, a +300 cfm supply

air to exhaust air will be required. Therefore, 690 cfm of HEPA filtered

supply air will be delivered to the space from RTU-1. This supply air will

be ducted to (2) laminar flow diffusers in the ceiling of this space. The

HEPA filters for the supply air will be installed in an approximately 4’-0”

high interstitial space above the room. A housing will be provided for

the filters that allows testing and certification of the filters. Merv 8

filters will also be installed inside the housing and upstream of the HEPA

filters.

Final Design: This room is required to be positive to the adjacent Ante

Room (+). USP 800 requires minimum 30 ACH of HEPA filtered supply

air to the space, which equates to approximately 395 cfm of filtered

supply air. One hood will be installed in the room which will be a 100%

recirculation hood with HEPA filtration. To maintain a (++) +270 cfm

pressure differential in the room, a 395 cfm of HEPA supply air will be

Page 32: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

8

delivered to the space, while 125 cfm of exhaust air will be exhausted

from the space. The exhaust air from the space will be HEPA filtered

before discharging to the exterior. The HEPA filters for the supply and

exhaust air will be installed in an approximately 6’-0” high interstitial

space above the room. A housing will be provided for the filters that

allows testing and certification of the filters. Merv 8 filters will also be

installed inside the housing and upstream of the HEPA filters.

ii. Provide (1) shutoff VAV box (690 cfm, constant flow) with supply

ductwork distribution into the space. Provide VAV box with reheat coil.

Connect VAV boxes to supply air main from RTU-1. Ductwork from VAV

box to HEPA filter housing in interstitial space will be galvanized steel.

Ductwork from the HEPA filter housing to the space shall be stainless

steel.

Final Design: Provide (1) shutoff VAV box (395 cfm, constant flow)

with supply ductwork distribution into the space. Provide VAV box

with reheat coil. Connect VAV boxes to supply air main from RTU-43.

Ductwork from VAV box to HEPA filter housing in interstitial space will

be galvanized steel. Ductwork from the HEPA filter housing to the

space shall be stainless steel.

iii. The BAS system will control the VAV box damper to maintain a constant

690 cfm of air and will control the reheat coil to maintain space

temperature set point. BAS Contractor will provide a combination

space temperature/humidity sensor in this space.

Final Design: The BAS system will control the VAV box damper to

maintain a constant 395 cfm of air and will control the reheat coil to

maintain space temperature set point. BAS Contractor will provide a

combination space temperature/humidity sensor in this space.

iv. Provide (1) roof mounted exhaust fan (390 cfm, constant flow) with

exhaust ductwork distribution into the space and to the hood. The

hood shall operate continuously. All exhaust ductwork shall be stainless

steel material.

Final Design: (2) High Plume discharge exhaust fans (EF-3 and EF-4)

will be provided for all the compounding rooms. The 125 cfm of

exhaust air for this space will be through a wall mounted grille located

12” above finished floor. The exhaust shall operate continuously. All

exhaust ductwork shall be stainless steel material.

v. At door from Ante (+) into IV Compounding (++), on Ante (+) side of

door, provide pressure controller that displays the pressure differential

between Ante (+) and IV Compounding (++).

Final Design: No change.

vi. Space occupied cooling target: 68F.

Final Design: No change.

vii. Space occupied heating target: 68F.

Final Design: No change.

Page 33: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

9

viii. Space maximum relative humidity: 60%.

Final Design: No change.

ix. Space minimum relative humidity: 30%.

Final Design: No change.

8. Ante Room (+):

i. This room is required to be positive to the adjacent Pharmacy and HD

Buffer (-), but negative to the adjacent IV Compounding (++). USP 800

requires minimum 30 ACH of HEPA filtered supply air to the space,

which equates to approximately 535 cfm of filtered supply air. To

maintain a (+) pressure differential in the room, a +150 cfm supply air to

exhaust air will be required. Therefore, 535 cfm of HEPA filtered supply

air will be delivered to the space from RTU-1, and 385 cfm of exhaust air

will be extracted from this space. This supply air will be ducted to (2)

laminar flow diffusers in the ceiling of this space. The HEPA filters for

the supply air will be installed in an approximately 4’-0” high interstitial

space above the room. A housing will be provided for the filters that

allows testing and certification of the filters. Merv 8 filters will also be

installed inside the housing and upstream of the HEPA filters.

Final Design: This room is required to be positive to the adjacent

Pharmacy and HD Buffer (-), but negative to the adjacent IV

Compounding (++). USP 800 requires minimum 30 ACH of HEPA

filtered supply air to the space, which equates to approximately 495

cfm of filtered supply air. No hoods will be installed in this space. To

maintain a (+) +150 cfm pressure differential in the room, 395 cfm of

HEPA supply air will be delivered to the space, while 345 cfm of

exhaust air will be exhausted from the space. The exhaust air from

the space will be HEPA filtered before discharging to the exterior. The

HEPA filters for the supply and exhaust air will be installed in an

approximately 6’-0” high interstitial space above the room. A housing

will be provided for the filters that allows testing and certification of

the filters. Merv 8 filters will also be installed inside the housing and

upstream of the HEPA filters.

ii. Provide (1) shutoff VAV box (535 cfm, constant flow) with supply

ductwork distribution into the space. Provide VAV box with reheat coil.

Connect VAV boxes to supply air main from RTU-1. Ductwork from VAV

box to HEPA filter housing in interstitial space will be galvanized steel.

Ductwork from the HEPA filter housing to the space shall be stainless

steel.

Final Design: Provide (1) shutoff VAV box (495 cfm, constant flow)

with supply ductwork distribution into the space. Provide VAV box

with reheat coil. Connect VAV boxes to supply air main from RTU-43.

Ductwork from VAV box to HEPA filter housing in interstitial space will

be galvanized steel. Ductwork from the HEPA filter housing to the

space shall be stainless steel.

Page 34: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

10

iii. The BAS system will control the VAV box damper to maintain a constant

535 cfm of air and will control the reheat coil to maintain space

temperature set point. BAS Contractor will provide a combination

space temperature/humidity sensor in this space.

Final Design: The BAS system will control the VAV box damper to

maintain a constant 495 cfm of air and will control the reheat coil to

maintain space temperature set point. BAS Contractor will provide a

combination space temperature/humidity sensor in this space.

iv. Provide (1) roof mounted exhaust fan (385 cfm, constant flow) with

exhaust ductwork distribution into the space and terminate at a grille

on the wall approximately 18” above floor. The exhaust shall operate

continuously. All exhaust ductwork shall be stainless steel material.

Final Design: (2) High Plume discharge exhaust fans (EF-3 and EF-4)

will be provided for all the compounding rooms. The 345 cfm of

exhaust air for this space will be through a wall mounted grille located

12” above finished floor. The exhaust shall operate continuously. All

exhaust ductwork shall be stainless steel material.

v. At door from Ante (+) into HD Buffer (-), on Ante (+) side of door,

provide pressure controller that displays the pressure differential

between Ante (+) and HD Buffer (-).

Final Design: No change.

vi. Space occupied cooling target: 68F.

Final Design: No change.

vii. Space occupied heating target: 68F.

Final Design: No change.

viii. Space maximum relative humidity: 60%.

Final Design: No change.

ix. Space minimum relative humidity: 30%.

Final Design: No change.

9. HD Buffer (-):

i. This room is required to be negative to the adjacent Ante Room (+).

USP 800 requires minimum 30 ACH of HEPA filtered supply air to the

space, which equates to approximately 485 cfm of filtered supply air.

One hood will be installed in the room at approximately 390 cfm of

exhaust. To maintain a (-) pressure differential in the room, a -150 cfm

supply air to exhaust air will be required. Since 485 cfm minimum

supply air is required, an additional 245 cfm of exhaust is required in the

space for a total exhaust volume of 635 cfm. 485 cfm of HEPA filtered

supply air will be delivered to the space from RTU-1. This supply air will

be ducted to (2) laminar flow diffusers in the ceiling of this space. The

HEPA filters for the supply air will be installed in an approximately 4’-0”

Page 35: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

11

high interstitial space above the room. A housing will be provided for

the filters that allows testing and certification of the filters. Merv 8

filters will also be installed inside the housing and upstream of the HEPA

filters.

Final Design: This room is required to be negative to the adjacent Ante

Room (+). USP 800 requires minimum 30 ACH of HEPA filtered supply

air to the space, which equates to approximately 410 cfm of filtered

supply air. One hood will be installed in the room at approximately

530 cfm of exhaust. To maintain a (-) -120 cfm pressure differential in

the room, a -120 cfm supply air to exhaust air will be required. Since

the 530 cfm exhaust hood operates continuously per the VA staff,

secondary exhaust will not be required inside the space. 410 cfm of

HEPA filtered supply air will be delivered to the space from RTU-43.

This supply air will be ducted to (2) laminar flow diffusers in the ceiling

of this space. The exhaust air from the hood will be HEPA filtered

before discharging to the exterior. The HEPA filters for the supply and

exhaust air will be installed in an approximately 6’-0” high interstitial

space above the room. A housing will be provided for the filters that

allows testing and certification of the filters. Merv 8 filters will also be

installed inside the housing and upstream of the HEPA filters.

ii. Provide (1) shutoff VAV box (485 cfm, constant flow) with supply

ductwork distribution into the space. Provide VAV box with reheat coil.

Connect VAV boxes to supply air main from RTU-1. Ductwork from VAV

box to HEPA filter housing in interstitial space will be galvanized steel.

Ductwork from the HEPA filter housing to the space shall be stainless

steel.

Final Design: Provide (1) shutoff VAV box (410 cfm, constant flow)

with supply ductwork distribution into the space. Provide VAV box

with reheat coil. Connect VAV boxes to supply air main from RTU-43.

Ductwork from VAV box to HEPA filter housing in interstitial space will

be galvanized steel. Ductwork from the HEPA filter housing to the

space shall be stainless steel.

iii. The BAS system will control the VAV box damper to maintain a constant

485 cfm of air and will control the reheat coil to maintain space

temperature set point. BAS Contractor will provide a combination

space temperature/humidity sensor in this space.

Final Design: The BAS system will control the VAV box damper to

maintain a constant 410 cfm of air and will control the reheat coil to

maintain space temperature set point. BAS Contractor will provide a

combination space temperature/humidity sensor in this space.

iv. Provide (1) roof mounted exhaust fan (245 cfm, constant flow) with

exhaust ductwork distribution into the space and terminate at a grille

on the wall approximately 18” above floor. The exhaust shall operate

continuously. All exhaust ductwork shall be stainless steel material.

Page 36: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

12

Final Design: (2) High Plume discharge exhaust fans (EF-3 and EF-4)

will be provided for all the compounding rooms. The exhaust shall

operate continuously. All exhaust ductwork shall be stainless steel

material.

Provide (1) roof mounted exhaust fan (390 cfm, constant flow) with

exhaust ductwork distribution into the space and to the hood. The

hood shall operate continuously. All exhaust ductwork shall be stainless

steel material.

Final Design: (2) High Plume discharge exhaust fans (EF-3 and EF-4)

will be provided for all the compounding rooms. The exhaust shall

operate continuously. All exhaust ductwork shall be stainless steel

material.

v. Space occupied cooling target: 68F.

Final Design: No change.

vi. Space occupied heating target: 68F.

Final Design: No change.

vii. Space maximum relative humidity: 60%.

Final Design: No change.

viii. Space minimum relative humidity: 30%.

Final Design: No change.

10. HD Storage (-):

i. This room is required to be negative to the adjacent Pharmacy. USP 800

requires 12 ACH of exhaust air from the space, which equates to

approximately 315 cfm. One hood will be installed in the room at

approximately 390 cfm of exhaust. To maintain a (-) pressure

differential in the room, a -150 cfm supply air to exhaust air will be

required. Therefore, 240 cfm of HEPA filtered supply air will be

delivered to the space from RTU-1. This supply air will be ducted to (1)

laminar flow diffuser in the ceiling of this space. The HEPA filters for the

supply air will be installed in an approximately 4’-0” high interstitial

space above the room. A housing will be provided for the filters that

allows testing and certification of the filters. Merv 8 filters will also be

installed inside the housing and upstream of the HEPA filters.

Final Design: This room is required to be negative to the adjacent

Pharmacy. USP 800 requires 12 ACH of supply air to the space, which

equates to approximately 265 cfm. One hood will be installed in the

room at approximately 260 cfm of exhaust. 370 cfm of supply air is

required to cool the room, so this amount of air will be delivered to the

space. To maintain a (-) -150 cfm pressure differential in the room, a

+150 cfm exhaust air to supply air will be required. Since the hood is

providing 260 cfm of constant exhaust, 260 cfm of supplemental

exhaust will be provided for the space. Only the exhaust air from the

space will be HEPA filtered. This space is not required to be a ISO clean

Page 37: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

13

environment, so the supply air will not be HEPA filters. The supply air

will be ducted to (1) perforated aluminum diffuser in the ceiling of this

space. The HEPA filters for the exhaust air will be installed in an

approximately 6’-0” high interstitial space above the room. A housing

will be provided for the filters that allows testing and certification of

the filters. Merv 8 filters will also be installed inside the housing and

upstream of the HEPA filters.

ii. Provide (1) shutoff VAV box (240 cfm, constant flow) with supply

ductwork distribution into the space. Provide VAV box with reheat coil.

Connect VAV boxes to supply air main from RTU-1. Ductwork from VAV

box to HEPA filter housing in interstitial space will be galvanized steel.

Ductwork from the HEPA filter housing to the space shall be stainless

steel.

Final Design: Provide (1) shutoff VAV box (370 cfm, constant flow)

with supply ductwork distribution into the space. Provide VAV box

with reheat coil. Connect VAV boxes to supply air main from RTU-43.

Ductwork from VAV box to the space shall be galvanized steel.

iii. The BAS system will control the VAV box damper to maintain a constant

240 cfm of air and will control the reheat coil to maintain space

temperature set point. BAS Contractor will provide a combination

space temperature/humidity sensor in this space.

Final Design: The BAS system will control the VAV box damper to

maintain a constant 370 cfm of air and will control the reheat coil to

maintain space temperature set point. BAS Contractor will provide a

combination space temperature/humidity sensor in this space.

iv. Provide (1) roof mounted exhaust fan (390 cfm, constant flow) with

exhaust ductwork distribution into the space and to the hood. The

hood shall operate continuously. All exhaust ductwork shall be stainless

steel material.

Final Design: (2) High Plume discharge exhaust fans (EF-3 and EF-4)

will be provided for all the compounding rooms. The exhaust shall

operate continuously. All exhaust ductwork shall be stainless steel

material. Secondary exhaust in the room will terminate with a wall

grille installed 12” above finished floor.

v. Space occupied cooling target: 68F.

Final Design: No change.

vi. Space occupied heating target: 68F.

Final Design: No change.

vii. Space maximum relative humidity: 60%.

Final Design: No change.

viii. Space minimum relative humidity: 30%.

Final Design: No change.

Page 38: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

14

ix. At door from Pharmacy into HD Storage (-), on Pharmacy side of door,

provide pressure controller that displays the pressure differential

between Pharmacy and HD Storage (-).

Final Design: No change.

11. CSCA (-):

i. This room is required to be negative to the adjacent Pharmacy. USP 800

requires minimum 15 ACH of HEPA filtered supply air to the space,

which equates to approximately 280 cfm of filtered supply air. Two

hoods will be installed in the room at approximately 390 cfm of exhaust

each, for a total of 780 cfm of exhaust. To maintain a (-) pressure

differential in the room, a -150 cfm supply air to exhaust air will be

required. Therefore, 630 cfm of HEPA filtered supply air will be

delivered to the space from RTU-1. This supply air will be ducted to (2)

laminar flow diffusers in the ceiling of this space. The HEPA filters for

the supply air will be installed in an approximately 4’-0” high interstitial

space above the room. A housing will be provided for the filters that

allows testing and certification of the filters. Merv 8 filters will also be

installed inside the housing and upstream of the HEPA filters.

Final Design: This room is required to be negative to the adjacent

Pharmacy. USP 800 requires 12 ACH of supply air to the space, which

equates to approximately 460 cfm. Two hoods will be installed in the

room at approximately 530 cfm each (1060 cfm total) of exhaust. To

maintain a (-) -150 cfm pressure differential in the room, a +150 cfm

exhaust air to supply air will be required. Since the hood is providing

1060 cfm of constant exhaust, 910 cfm of constant supply air will be

required. Only the exhaust air from the space will be HEPA filtered.

This space is not required to be a ISO clean environment, so the supply

air will not be HEPA filters. The supply air will be ducted to (2)

perforated aluminum diffusers in the ceiling of this space. The HEPA

filters for the exhaust air will be installed in an approximately 6’-0”

high interstitial space above the room. A housing will be provided for

the filters that allows testing and certification of the filters. Merv 8

filters will also be installed inside the housing and upstream of the

HEPA filters.

ii. Provide (1) shutoff VAV box (630 cfm, constant flow) with supply

ductwork distribution into the space. Provide VAV box with reheat coil.

Connect VAV boxes to supply air main from RTU-1. Ductwork from VAV

box to HEPA filter housing in interstitial space will be galvanized steel.

Ductwork from the HEPA filter housing to the space shall be stainless

steel.

Final Design: Provide (1) shutoff VAV box (910 cfm, constant flow)

with supply ductwork distribution into the space. Provide VAV box

with reheat coil. Connect VAV boxes to supply air main from RTU-43.

Ductwork from VAV box to the space shall be galvanized steel.

Page 39: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

15

iii. The BAS system will control the VAV box damper to maintain a constant

630 cfm of air and will control the reheat coil to maintain space

temperature set point. BAS Contractor will provide a combination

space temperature/humidity sensor in this space.

Final Design: The BAS system will control the VAV box damper to

maintain a constant 910 cfm of air and will control the reheat coil to

maintain space temperature set point. BAS Contractor will provide a

combination space temperature/humidity sensor in this space.

iv. Provide (2) roof mounted exhaust fan (390 cfm each, constant flow)

with exhaust ductwork distribution into the space and to each hood.

The hoods shall operate continuously. All exhaust ductwork shall be

stainless steel material.

Final Design: (2) High Plume discharge exhaust fans (EF-3 and EF-4)

will be provided for all the compounding rooms. The exhaust shall

operate continuously. All exhaust ductwork shall be stainless steel

material.

v. Space occupied cooling target: 68F.

Final Design: No change.

vi. Space occupied heating target: 68F.

Final Design: No change.

vii. Space maximum relative humidity: 60%.

Final Design: No change.

viii. Space minimum relative humidity: 30%.

Final Design: No change.

ix. At door from Pharmacy into CSCA (-), on Pharmacy side of door, provide

pressure controller that displays the pressure differential between

Pharmacy and CSCA (-).

Final Design: No change.

12. HD Receiving (-):

i. This room is required to be negative to the adjacent Pharmacy, OT, and

Lockers. USP 800 requires 12 ACH of exhaust air from the space, which

equates to approximately 185 cfm. To maintain a (-) pressure

differential in the room, a -450 cfm supply air to exhaust air will be

required. To cool the space, 100 cfm of supply air will be delivered to

the space, 550 cfm of exhaust air will be extracted from the space. The

supply air will be ducted to (1) laminar flow diffuser in the ceiling of this

space.

Final Design: This room is required to be negative to the adjacent

Pharmacy, OT, and Lockers. USP 800 requires 12 ACH of suppy air to

the space, which equates to approximately 125 cfm. To maintain a (-)

-150 cfm pressure differential in the room, a +150 cfm exhaust air to

supply air will be required. 275 cfm of exhaust will be provided for the

space. The supply air will be ducted to one aluminum louver diffuser in

the ceiling. This space is not required to be ISO clean, so the supply air

Page 40: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

16

will not be HEPA filtered. Likewise, since drugs will not be unpacked in

this room, the exhaust for the space will also not be HEPA filtered.

ii. Connect VAV boxes to supply air main from RTU-1. Ductwork from VAV

box space will be galvanized steel.

Final Design: Provide (1) shutoff VAV box (125 cfm, constant flow)

with supply ductwork distribution into the space. Provide VAV box

with reheat coil. Connect VAV boxes to supply air main from RTU-43.

Ductwork from VAV box to the space shall be galvanized steel.

iii. The BAS system will control the VAV box damper to maintain a constant

100 cfm of air and will control the reheat coil to maintain space

temperature set point. BAS Contractor will provide a combination

space temperature/humidity sensor in this space.

Final Design: The BAS system will control the VAV box damper to

maintain a constant 125 cfm of air and will control the reheat coil to

maintain space temperature set point. BAS Contractor will provide a

combination space temperature/humidity sensor in this space.

iv. Provide (1) roof mounted exhaust fan (550 cfm, constant flow) with

exhaust ductwork distribution into the space and terminate at a grille

on the wall approximately 18” above floor. The exhaust shall operate

continuously. All exhaust ductwork shall be stainless steel material.

Final Design: (2) High Plume discharge exhaust fans (EF-3 and EF-4)

will be provided for all the compounding rooms. The exhaust shall

operate continuously. All exhaust ductwork shall be stainless steel

material.

v. Space occupied cooling target: 68F.

Final Design: No change.

vi. Space occupied heating target: 68F.

Final Design: No change.

vii. Space maximum relative humidity: 60%.

Final Design: No change.

viii. Space minimum relative humidity: 30%.

Final Design: No change.

ix. At door from Pharmacy into HD Receiving (-), on Pharmacy side of door,

provide pressure controller that displays the pressure differential

between Pharmacy and HD Receiving (-).

Final Design: No change.

B. Medical Gas

a. As there is no requirement for medical gas in the renovated space as well as no existing

lines in the space no medical gas design is planned.

Final Design: No change.

Page 41: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

17

C. Domestic Plumbing

a. All plumbing fixtures in the renovation area of the project will be removed. All water,

waste, and vent piping serving the fixtures will also be removed. Remove vent and

water piping to mains above ceiling and cap air and watertight. Remove waste to below

floor and cap below floor.

Final Design: No change.

b. Provide SCW and HW to the following plumbing fixtures:

i. (1) Sink faucet (laminar flow) in CSCA (-) (1/2” SCW, 1/2” HW). Provide point of

use thermostatic mixing valve.

Final Design: No change.

ii. (1) Sink faucet (laminar flow) in HD Storage (-) (1/2” SCW, 1/2” HW). Provide

point of use thermostatic mixing valve.

Final Design: No change.

iii. (1) Sink faucet (laminar flow) in Ante (+) (1/2” SCW, 1/2” HW). Provide point of

use thermostatic mixing valve.

Final Design: No change.

iv. (1) Sink faucet (laminar flow) in HD Receiving (-) (1/2” SCW, 1/2” HW). Provide

point of use thermostatic mixing valve.

Final Design: No change.

v. (1) Emergency eyewash by sink in CSCA (-) (1/2” SCW, 1/2” HW). Provide point

of use thermostatic mixing valve.

Final Design: No change.

vi. (1) Emergency eyewash by sink in HD Storage (-) (1/2” SCW, 1/2” HW). Provide

point of use thermostatic mixing valve.

Final Design: No change.

vii. (1) Emergency eyewash by sink in Ante (+) (1/2” SCW, 1/2” HW). Provide point

of use thermostatic mixing valve.

Final Design: No change.

viii. (1) Emergency eyewash by sink in HD Receiving (-) (1/2” SCW, 1/2” HW).

Provide point of use thermostatic mixing valve.

Final Design: No change.

ix. Final Design: (1) Sink faucet in EMS for floor mounted mop sink (3/4” SCW,

3/4” HW).

x. Final Design: (1) Sink faucet (laminar flow) in OT. Provide point of use

thermostatic mixing valve

c. Provide sanitary waste and vent to the following plumbing fixtures:

i. (1) Sink in CSCA (-) (2”W, 1-1/2”V).

Final Design: No change.

ii. (1) Sink in HD Storage (-) (2”W, 1-1/2”V).

Final Design: No change.

iii. (1) Sink in Ante (+) (2”W, 1-1/2”V).

Final Design: No change.

Page 42: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

18

iv. (1) Sink in HD Receiving (-) (2”W, 1-1/2”V).

Final Design: No change.

v. Final Design: (1) Sink in OT (2”W, 1-1/2”V).

vi. Final Design: (1) Mop Sink in EMS (3”W, 2”V).

d. There is an existing 6” sanitary waste service for the existing building that will be

covered with the proposed addition. WPE does not know the condition of this piping,

however, would recommend replacing the piping that will be below the building with

new Schedule 40 PVC piping.

Final Design: This was not correct. There was not a 6” sanitary service on the exterior

that was covered with the new addition.

e. The new 6” piping main below the building addition will be utilized to connect the waste

from the plumbing fixtures listed above.

Final Design: From the plans on the Oncology project, there was a 4” sanitary stubbed

through the west wall of that addition for future connection. During design, it was

discovered that this stub was not installed. New sanitary for this project will be

connected to an existing 4” underground main about 6 feet east of the existing west

Oncology exterior wall.

f. Route vent piping from plumbing fixtures listed above to a single 4” vent through roof.

Final Design: To save piping lengths, (3) 4” vents through roof were utilized.

g. Route 1” HW from fixtures listed above to existing HW mains in existing building.

Provide shutoff isolation valve at connection to main. All HW piping shall be Type L

copper with 1” fiberglass insulation.

Final Design: No change.

h. Route 1” SCW from fixtures listed above to existing SCW mains inside existing building.

Provide shutoff isolation valve at connection to main. All SCW piping shall be Type L

copper with 1” fiberglass insulation.

Final Design: No change.

i. Route 3/4” recirculating hot water (RHW) from furthest fixture to existing RHW main

inside existing building. Provide shutoff isolation valve at connection to main. All RHW

piping shall be Type L copper with 1” fiberglass insulation. On recirculating system, at

connection to furthest fixture, provide 0.5 gpm automatic flow balancing valve.

Final Design: No change.

j. Floor drains shall not installed in any of the following rooms: IV Compounding (++),

Ante (+), HD Buffer (-), HD Storage (-), CSCA (-), HD Receiving (-).

Final Design: No change. However, (2) floor drains were added on the interstitial floor

to capture water in the event of a water leak in that space.

k. No water or vent piping shall be routed above the ceilings in any of the following rooms:

IV Compounding (++), Ante (+), HD Buffer (-), HD Storage (-), CSCA (-), HD Receiving (-).

Piping to sinks shall be routed inside walls of these spaces and out to walls in spaces not

requiring a clean space certification.

Final Design: No change.

Page 43: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

19

D. Fire Protection

a. The existing fire sprinkler system serving the area will need to be modified as required in

order to meet the needs of the new floor plan arrangement.

Final Design: No change.

E. Temperature Controls

a. The control system will be a direct digital control BACNET system for the new HVAC

systems. All system graphics and points will be contained on the existing front end

workstation. The BAS shall control the following systems:

i. RTU-1 (Final Design: RTU-43):

1. Supply fan on/off.

2. Supply fan status and alarm.

3. Supply fan speed based on ductwork differential pressure.

4. Pre-filter pressure drop.

5. Final filter pressure drop.

Final Design: Omitted. Final filters are not installed in RTU.

6. Exhaust fan on/off.

Final Design: Omitted. Exhaust fan not included with RTU.

7. Exhaust fan status and alarm.

Final Design: Omitted. Exhaust fan not included with RTU.

8. Exhaust fan speed based on fan airflow (calculated differential between

outside air flow measurement and minimum outside air quantity

(economizer mode only)).

Final Design: Omitted. Exhaust fan not included with RTU.

9. Outside air damper modulation.

10. Return air damper modulation.

11. Mixed air temperature.

12. Discharge air temperature.

13. Heating coil discharge air temperature.

14. Heating coil control valve modulation.

15. Chilled water coil control valve modulation.

16. Final Design: Return air humidity.

17. Final Design: Return air temperature.

18. Final Design: Heating coil discharge humidity.

19. Final Design: Desiccant wheel supply bypass damper.

20. Final Design: Desiccant wheel mixed air bypass damper.

21. Final Design: Discharge air dewpoint.

22. Final Design: Discharge air humidity.

23. Final Design: Desiccant wheel on/off.

ii. RTU-2:

1. Supply fan on/off.

Page 44: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

20

2. Supply fan status and alarm.

3. Supply fan speed based on ductwork differential pressure.

4. Pre-filter pressure drop.

5. Final filter pressure drop.

6. Exhaust fan on/off.

7. Exhaust fan status and alarm.

8. Exhaust fan speed based on space pressure sensor.

9. Outside air damper modulation.

10. Return air damper modulation.

11. Mixed air temperature.

12. Discharge air temperature.

13. Heating coil discharge air temperature.

14. Heating coil control valve modulation.

15. Chilled water coil control valve modulation.

Final Design: RTU-2 was omitted. Existing AHU-2 was used for the new OT

portion of the project.

iii. VAV boxes (13) (Final Design: Quantity of (10)):

1. Box airflow and alarm.

2. Reheat coil control valve modulation.

3. Damper modulation.

4. Discharge air temperature.

iv. Radiant Ceiling Panels (4) (Final Design: No change):

1. Reheat control valve modulation.

v. Exhaust Fans (10) (Final Design: Quanity of (2)):

1. Exhaust fan on/off.

2. Exhaust fan status and alarm.

vi. Induct Humidifiers (2) (Final Design: Quantity of (1)):

1. Steam control valve modulation.

vii. Combination space humidity/temperature sensors (12) (Final Design: Quantity

of (11)).

viii. Space pressure sensors (1).

Final Design: No pressure sensors.

ix. HEPA Filter Fan Modules (5):

1. Fan status and alarm.

Final Design: Omitted. Fan filter modules not used.

F. HVAC Piping

a. This addition will require the relocation of (1) air cooled chiller located on grade along

the north of the existing building. This equipment will be relocated to the roof of the

new addition and chilled water re-piped from their new locations on the roof down to

existing piping connection points in the new addition. All new piping shall be Schedule

40 black steel.

Page 45: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

21

Final Design: This addition will require the relocation of (2) air cooled chillers and (1)

condensing unit located on grade along the north of the existing building. This

equipment will be relocated to the roof of the new addition and chilled/refrigerant

piping routed from their new locations on the roof down to existing piping connection

points on the exterior grade. All new piping shall be Schedule 40 black steel.

b. Route Low Pressure Steam piping to the following listed devices. Connect new 1-1/4”

LPS piping main to existing steam piping main inside existing building. Provide shutoff

isolation valve at connection to main. All LPS piping shall be Schedule 40 steel with 1”

fiberglass insulation.

i. RTU-1 Induct Humidifier Distributor: 1-1/4” LPS.

ii. RTU-2 Induct Humidifier Distributor: 3/4” LPS.

Final Design: Route Low Pressure Steam piping to the following listed devices.

Connect new 1” LPS piping main to existing steam piping main inside existing building.

Provide shutoff isolation valve at connection to main. All LPS piping shall be Schedule

40 steel with 1” fiberglass insulation.

i. H-1 Induct Humidifier Distributor: 1” LPS.

c. Route Low Pressure Steam condensate piping to the following listed devices. Connect

new 1” LPCR piping main to existing main inside existing building. Provide shutoff

isolation valve at connection to main. All LPS piping shall be Schedule 40 steel with 1”

fiberglass insulation.

i. RTU-1 Induct Humidifier Distributor: 3/4” LPCR.

ii. RTU-2 Induct Humidifier Distributor: 3/4” LPCR.

Provide F&T trap and accessories at each distributor.

Final Design: Route Low Pressure Steam condensate piping to the following listed

devices. Connect new 3/4” LPR piping main to existing main inside existing building.

Provide shutoff isolation valve at connection to main. All LPS piping shall be Schedule

40 steel with 1” fiberglass insulation.

i. H-1 Induct Humidifier Distributor: 3/4” LPR.

Provide F&T trap and accessories at each distributor.

d. Route reheat heating water supply and return piping to the following listed devices.

Connect new 1-1/4” reheat HWS and HWR piping main to existing piping mains inside

existing building. Provide shutoff isolation valve at connection to main. All reheat HWS

and HWR piping shall be Schedule 40 steel with 1” fiberglass insulation.

i. Radiant Ceiling Panels in OT area: 3/4" (0.5 gpm).

ii. (13) VAV boxes: 3/4” each (1 gpm each).

At each device, provide a coil kit complete with shutoff valves, strainer, and automatic

flow balancing valve.

Page 46: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

22

Final Design: Route reheat heating water supply and return piping (HWS/R) to the

following listed devices. Connect new 1-1/4” HWS and HWR piping main to existing

piping mains inside existing building. Provide shutoff isolation valve at connection to

main. All reheat HWS and HWR piping shall be Schedule 40 steel with 1” fiberglass

insulation.

iii. Radiant Ceiling Panels in OT area: 3/4" (0.5 gpm).

iv. (10) VAV boxes: 3/4” each (1 gpm each).

v. Hydronic unit heater UH-1: 3/4" (1 gpm).

At each device, provide a coil kit complete with shutoff valves, strainer, and automatic

flow balancing valve.

e. (Option #1 RTUs) Route chilled water supply and return piping to the following listed

devices. Connect new 2-1/2” CWS and CWR piping existing piping mains inside existing

building. Provide shutoff isolation valve at connection to main. All CWS and CWR piping

shall be Schedule 40 steel with 1” fiberglass insulation.

i. RTU-1: 2" (48 gpm).

ii. RTU-2: 1-1/4" (12 gpm).

At each device, provide a coil kit complete with shutoff valves, strainer, and automatic

flow balancing valve.

Final Design: (Option #1 RTUs) Route chilled water supply and return piping to the

following listed devices. Connect new 2-1/2” GCS and GCR piping existing piping

mains inside existing building. Provide shutoff isolation valve at connection to main.

All GCS and GCR piping shall be Schedule 40 steel with 1” fiberglass insulation.

iii. RTU-43: 2-1/2" (63 gpm).

iv. FC-1: 1" (3 gpm).

At each device, provide a coil kit complete with shutoff valves, strainer, and automatic

flow balancing valve.

f. Route heating water supply and return piping to the following listed devices. Connect

new 2” HWS and HWR piping main to existing mains inside existing building. Provide

shutoff isolation valve at connection to main. All HWS and HWR piping shall be

Schedule 40 steel with 1” fiberglass insulation.

i. RTU-1: 2” (28 gpm).

ii. RTU-2: 1” (5 gpm).

At each device, provide a coil kit complete with shutoff valves, strainer, and automatic

flow balancing valve.

Final Design: Route heating water supply and return piping (GHS and GHR) to the

following listed devices. Connect new 1-1/2” GHS and GHR piping main to existing

mains inside existing building. Provide shutoff isolation valve at connection to main.

All HWS and HWR piping shall be Schedule 40 steel with 1” fiberglass insulation.

iii. RTU-43: 1-1/2” (20 gpm).

At each device, provide a coil kit complete with shutoff valves, strainer, and automatic

flow balancing valve.

Page 47: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

23

g. The approximate total loads imposed by the project on the existing campus systems are

as follows:

i. Steam (Humidification): 100 #/hr.

ii. Chilled Water: 23.6 Tons (63 gpm).

iii. Reheat Heating Water: 116,000 BTUH (14 gpm).

iv. Heating Water: 293,000 BTUH (33 gpm).

Final Design: The approximate total loads imposed by the project on the existing

campus systems are as follows:

v. Steam (Humidification): 73 #/hr.

vi. Chilled Water: 24 Tons (60 gpm).

vii. Reheat Heating Water: 150,400 BTUH (12.5 gpm).

viii. Heating Water: 280,000 BTUH (20 gpm).

G. Electrical Distribution

a. The hospital is served by both normal and emergency electrical sources. Electrical

panels for both normal-power and emergency-power systems are installed in most

instances in electrical and mechanical rooms.

b. Lighting, receptacle, and equipment loads in the constructed pharmacy space will be fed

from new panels. New panel location(s) will be reviewed with the architect and VA for

optimal placement in compliance with VA standards and design guidelines. Where

existing spaces are remodeled the electrical loads will be fed from existing panels.

Where new space is added for other departments the electrical loads will be connected

to existing panels wherever possible. The need for new panels for other departments

will be analyzed by the design team and addressed on a case-by-case basis.

c. Electrical loads will primarily be fed from the normal power source. Emergency power

will be utilized as directed by the VA design guidelines and review by the local VA

engineer/project manager.

d. Life safety, critical branch, and equipment branch loads will be circuited as determined

by the VA design Guidelines and in conjunction with the National Electrical Code.

Emergency power connection shall be provided for equipment that needs to operate

continuously and cannot be interrupted. Equipment such as refrigerators/freezers,

safes, etc., shall be connected to the building emergency power system.

H. Lighting Systems

a. All lighting in the pharmacy space will be new.

b. Light fixtures will utilize energy-efficient LED sources.

c. Light fixtures will be connected to emergency sources (i.e. life safety and critical

branches) as required by the VA design guidelines.

Page 48: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

24

d. It is anticipated that new light fixtures will be lay-in style, compatible with 2’x2’

acoustical tile ceilings. Suspended light fixtures will be utilized in

mechanical/electrical/storage type spaces without ceilings.

e. Lighting performance (lighting levels and lighting power densities) will be designed in

accordance with the Illuminating Engineering Society (IES) guidelines and VA design

guidelines, which includes design standard ASHRAE 90.1.

f. Lighting controls will be designed in accordance with VA design guidelines, which

includes automatic lighting control components such as occupancy and vacancy sensors.

Dimming will be utilized where multi-level lighting scenes are required.

I. Power Systems

a. Receptacle layouts will be designed in accordance with VA design guidelines.

b. Motors will be controlled by motor starters and VFD’s (variable frequency drives), as

determined by the mechanical design.

c. Connections to systems furniture will be either a) from adjacent walls, or b) via power

poles. This shall be determined during design by the architect and VA.

d. All wiring shall be concealed in stud-wall construction and above accessible suspended

ceilings. Surface-mounted raceways shall be utilized in spaces such as mechanical,

electrical, and information-technology rooms, and in remodel spaces where concealing

raceways is cost-prohibitive.

e. Floor boxes will be provided as directed by the VA design guidelines.

J. Telecommunications Systems

a. Intercom, telephone, and computer systems will all be provided in the pharmacy

construction project.

b. Voice, Data, and Intercom Systems will be designed in accordance with the VA design

guidelines. The design team will review available capacity of the existing IT

infrastructure and connect new voice and data drops to existing racks wherever

possible. Where existing voice and data infrastructure does not have sufficient capacity

to accommodate new outlets, the design team will work closely with the VA to provide

means to serve new outlets.

c. Any voice and data required for remodeled spaces shall connect to voice/data

infrastructure previously serving those spaces.

d. Wireless Access System: existing wireless access points will be reused. The existing

WAP’s (wireless access points) will be removed prior to demolition; existing WAP data

cables can be coiled and reused; WAP’s may be installed in the same locations where

they were removed.

e. Nurse Call System:

i. The existing nurse call system will be extended to the remodeled OT space.

f. Clock System: not anticipated in this project.

g. Television System: not anticipated in this project.

Page 49: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards

4609 Techlink Circle Sioux Falls, SD 57106 Ph: (605) 362-3753 Fax (605) 362-3759

SIOUX FALLS

25

h. Audio/Visual System: is not anticipated in this project.

i. Overhead Paging System: will be provided in accordance with the VA design guidelines.

K. Fire Alarm System

a. An extension to the existing fire alarm layout will be designed in accordance with

current Codes and VA design guidelines. Existing devices removed during any

demolition may be reused provided they are in good working order. New devices will be

provided as required.

L. Access Control System (card access)

a. Access control shall be provided in compliance with VA design guidelines.

M. Video Surveillance System

a. Video surveillance shall be provided in compliance with VA design guidelines.

i. Final Design: A stand-alone video surveillance system shall be provided in

compliance with local Sioux Falls VA site-specific requirements.

N. Security/Intrusion Detection System

a. Not anticipated in this project.

i. Final Design: Intrusion detection shall be provided in compliance with local

Sioux Falls VA site-specific requirements.

Page 50: VA SIOUX FALLS - MDM Construction · 2019-02-12 · Interior Narrative: The project follows VA standards for material selection and placement as outlined in Sioux Falls VA Standards