UTILITY WORK
WITHIN PUBLIC
RIGHTS-OF WAY
AND
EASEMENTS
PRESENTED BY: Michael McCabe, P.E., CSM
Michael Steele, CPII
![Page 2: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/2.jpg)
![Page 3: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/3.jpg)
City of Palm Bay107,00+ Residents Predominately SFR100+ Sq. Miles 50% built-out800+ Centerline Miles Predominately open
drainage
![Page 4: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/4.jpg)
• FIRST CODE (1974)• REVISION TO CODE TO INCLUDE PERMITTING (1993)
• DEFINITIONS• EXEMPTIONS
• FRANCHISES• PROHIBITED USES• PERMIT
• WHEN REQUIRED• NOT REQUIRED
• LIABILITY• PERMIT PROCEDURES AND REQUIREMENTS• DESIGN, MATERIAL, TESTING AND REPORTS• CONSTRUCTION PROCEDURES• EMERGENCY WORK• PRESERVATION OF MONUMENTS• COSTS INCURRED – PAYMENT• INTERPRETATION OF DISCREPANCIES• PRIMA FACIE EVIDENCE OF VIOLATION• DUTY TO REMOVE UPON NOTICE BY CITY• REMOVAL AND DISPOSAL BY THE CITY UPON FAILURE OF OWNER TO REMOVE;
COSTS• REMOVAL AND DISPOSAL OF UNLAWFUL IMPROVEMENTS WITHOUT NOTICE TO
OWNER• RESTORATION OF DAMAGED AREAS
Right of Way And Easement Use Code
![Page 5: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/5.jpg)
• Existing provisions of other agreements and contracts, i.e franchises, shall prevail over requirements of this code.
• All active franchises exempt from fees. • Current franchise agreements
• Electric• Gas• Solid Waste Collection
• No franchise agreements• Telecommunications, Broadcast, and Cable Services
(Telecommunications Act of 1996)
• Water and Wastewater
EXEMPTIONS
![Page 6: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/6.jpg)
• Fees• Telecommunications and Cable
• Ordinance 2001-40• Communications Services Tax
• Increase Local Tax percentage
PERMIT FEES• General $333
• SFR Irrigation permit $32• Water Service Connection
• No boring required $30• Boring required
$135• Hold Harmless recording (irrigation/docks) $15• Street Cuts
$142• Projects Under Section 179.096(E) (as-built) $254
EXEMPTIONS
![Page 7: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/7.jpg)
• Prior to installing; placing; constructing; or replacing any improvement within the right-of-way and easements. • Includes, but is not limited, to
• all excavations; • jack and bores; • all poles, regardless of its purpose; • all above ground improvements that create an
obstruction; and, • all below ground utilities.
WHEN A RIGHT-OF-WAY PERMIT IS REQUIRED?
![Page 8: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/8.jpg)
• Franchisee when work meets following: • Will not disturb
• Paved areas.• Any other improvement.• Vehicular or pedestrian traffic.• Area larger than 100 square feet.• Exceed a depth below grade of 48 inches,
except utility poles.• Will be restored to a condition as good or better
than existing.• Underground service connection when trench
width less than 12 inches.• Is not a jack-’n-bore of any kind.
WHEN A RIGHT-OF-WAY PERMIT IS NOT REQUIRED?
![Page 9: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/9.jpg)
• Open drainage system
CHALLENGES
• Increased activities due to competition for communications and cable services
![Page 10: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/10.jpg)
• PERMITEE• PUBLIC WORKS DEPARTMENT• CITIZEN/RESIDENT
KEY PLAYERS
![Page 11: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/11.jpg)
COMMERICAL UTILITIES:• Telecommunications• Electric• Cable• Gas
PERMITEE
CITY UTILITIES:• Water (Raw and Distribution Lines)
• Wastewater (Gravity, Forcemain, Reuse)
• Information Technology (Fiberoptic)
![Page 12: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/12.jpg)
CONSTRUCTION ACTIVITIES:• Subcontractors for utility companies• Contractors for private development• City staff (utility and IT)
PERMITEE (CONT)
![Page 13: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/13.jpg)
KEY PLAYERSPublic Works Department:
• Engineering Assistant (Receives, process, routes, issues, final approval)
• Engineering Inspector(s) (Reviews, coordinates, inspects, approves)
• Engineer II (Supervisor)
Citizen:• Service (Availability)
• Aesthetics (Exposed pits and soils, safety fence, vegetation)
• Hazards (Pits, cable, sidewalks, poles)
![Page 14: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/14.jpg)
![Page 15: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/15.jpg)
Permit active for 120 days
![Page 16: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/16.jpg)
Acceptable Site Restoration????
Per Code, restoration of damaged areas shall be restored to condition prior to damages or pay the city the sum of money necessary to restore.
![Page 17: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/17.jpg)
Acceptable Site Restoration????
Flow line maintenance
Per Code, any permittee who has previously failed to restore damages as required shall not be issued further permits
![Page 18: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/18.jpg)
![Page 19: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/19.jpg)
Pit depth of 15”
Pit depth of 12”
![Page 20: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/20.jpg)
![Page 21: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/21.jpg)
![Page 22: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/22.jpg)
Utility Pole Removal
![Page 23: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/23.jpg)
Good work?
![Page 24: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/24.jpg)
PERMITTING PROCESS- Specific zones- Zone 1, Aerial Transmissions- Zone 2, Underground Improvements- Zone 3, Water, Sewer, Gas lines
![Page 25: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/25.jpg)
PERMITTING PROCESS- Specific depths
![Page 26: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/26.jpg)
• Current Flow Chart• Proposed Flow Chart
Improvements
PERMITTING PROCESS
![Page 27: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/27.jpg)
START
APPLICATION SUBMITTAL
PLANS & SPECS
PLAN REVIEW
PERMITREQ’D
REVISIONREQ’D
PROCEED
FILE
ASSIGN INSPECTOR
A B
NO
YES
NO
YES END
Permitting Process Flow Chart
![Page 28: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/28.jpg)
NOTIFYSUBCONTRACTOR
DOCUMENT
A
INSPECTION
CONSTRUCTIONISSUES
DOCUMENT ISSUESRESOLVED
NOTIFYENGINEERING
ASST./ENGINEER
ISSUESRESOLVED
IS WORKCOMPLIANT DOCUMENT
DOCUMENT
WORKDELAY
CONTACTPERMITEE
DOCUMENT
B
DOCUMENTCOMPLIANCE
NO
YES
YES
YES
YES
NO
YES
C
NOINSPECTION
HASWORK
STARTED
NO
YES
NO
C D
DOESWORK
CONTINUENO
YES
24 HRNTP
90 DAYBENCHMARK
DOCUMENT/NOTIFY PERMITEE
PLAN REVISION
![Page 29: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/29.jpg)
C
INSTALLATION
COMPLETE
SUBMIT COMPLETION
& RESTORATION
ISRESTORATION
COMPLETENO
DOCUMENT(NON-
COMPLIANCE)
D
PERMITCOMPLETE
YES
SIGN-OFFPERMIT
CONTACTROW
COORDINATOR
ARCHIVE
END
![Page 30: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/30.jpg)
NOTIFYSUBCONTRACTOR
DOCUMENT
A
INSPECTION
CONSTRUCTIONISSUES
DOCUMENT ISSUESRESOLVED
NOTIFYENGINEERING
ASST./ENGINEER
ISSUESRESOLVED
IS WORKCOMPLIANT DOCUMENT
DOCUMENT
WORKDELAY
CONTACTPERMITEE
DOCUMENT
B
DOCUMENTCOMPLIANCE
NO
YES
YES
YES
YES
NO
YES
C
NOINSPECTION
HASWORK
STARTED
NO
YES
NO
C D
DOESWORK
CONTINUENO
YES
24 HRNTP
90 DAYBENCHMARK
DOCUMENT/NOTIFY PERMITEE
PLAN REVISION
Process Flow Chart
Improvements
![Page 31: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/31.jpg)
NOTIFYSUBCONTRACTOR
DOCUMENT
A
INSPECTION
CONSTRUCTIONISSUES
DOCUMENT ISSUESRESOLVED
NOTIFYENGINEERING
ASST./ENGINEER
ISSUESRESOLVED
IS WORKCOMPLIANT DOCUMENT
DOCUMENT
WORKDELAY
CONTACTPERMITEE
DOCUMENT
B
DOCUMENTCOMPLIANCE
NO
YES
YES
YES
YES
NO
YES
C
NO NOTIFY PERMITEE
HASWORK
STARTED
NO
YES
NO
C D
DOESWORK
CONTINUENO
YES
24 HRNTP
90 DAYBENCHMARK
VOID PERMIT
PLAN REVISION
END
YES
NO
Process Flow Chart
Improvements
![Page 32: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/32.jpg)
PERMITTING PROCESSPermitting Plans and Specifications
![Page 33: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/33.jpg)
Cover Sheet
![Page 34: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/34.jpg)
Cover Sheet
![Page 35: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/35.jpg)
Standard Detail (City’s)
![Page 36: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/36.jpg)
Plan and Cross-Sections
![Page 37: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/37.jpg)
Plan and Cross-Sections
![Page 38: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/38.jpg)
Plan and Cross-Sections
![Page 39: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/39.jpg)
Plan and Details
![Page 40: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/40.jpg)
Plan (aerial view)
![Page 41: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/41.jpg)
Plan (street view)
![Page 42: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/42.jpg)
Plan (color code other utilities)
![Page 43: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/43.jpg)
Traffic Control Plan
![Page 44: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/44.jpg)
General Notes
![Page 45: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/45.jpg)
PERMITTING PROCESS CHALLENGES
- Number of Open Permits (312)• 1 utility company has 72 open permits
![Page 46: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/46.jpg)
![Page 47: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/47.jpg)
Permitted splice pits
![Page 48: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/48.jpg)
Permitted splice pits in one neighborhood
![Page 49: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/49.jpg)
INSPECTION OF WORK
EXISTINGUTILITIES
SWALE
PROPOSED BORE
![Page 50: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/50.jpg)
INSPECTION OF WORK
EXISTINGUTILITIES
SWALE
PROPOSED BORE
EXISTINGUTILITIES???
![Page 51: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/51.jpg)
INSPECTION CONSTRAINTSManpower
• 6 Inspectors
Inspector Responsibilities
![Page 52: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/52.jpg)
Permits per Inspector
![Page 53: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/53.jpg)
![Page 54: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/54.jpg)
- Training- Meetings- Work Reports- Plan Reviews- Construction Inspections- Capital Improvement Projects- Commercial Projects
INSPECTION CONSTRAINTS
![Page 55: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/55.jpg)
- Infrastructure Inventory• Failed Culvert Pipes (+/- 1400)• Sidewalk Inspections (Annually)• Guardrail & Handrail (2 year
Inspections)• Roadway Inspections (5 year
Inspections)
INSPECTION CONSTRAINTS
![Page 56: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/56.jpg)
- Citizen Requests• (245 Last Quarter)
- ROW Permits Inspections- NPDES Permit Requirements (MS4)
• Illicit discharge investigations• Dry weather outfall monitoring• Storm event inspections
INSPECTION CONSTRAINTS
![Page 57: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/57.jpg)
INSPECTOR DUTIES
![Page 58: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/58.jpg)
PERMITTING PROCESS SUMMARY
OF CHALLENGES• Number of open permits• Lack of required start-up notification• Timeliness of completion (335 Days)• Infrastructure maintenance after
installation• Manpower• Time management
![Page 59: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/59.jpg)
POSSIBLE IMPROVEMENTS
• Streamline the flow chart• Restrict open permits to 20-30• 10 working day stop work delay• GPS conflicts to import to GIS• Additional inspection staff or dedicate
one inspector for permits• Communication
• Quarterly meetings with utilities• Monthly meetings with Inspectors• Monthly meetings with staff
![Page 60: Utility Work within Public Right of Way](https://reader036.fdocuments.us/reader036/viewer/2022062514/557e6fffd8b42a03668b4851/html5/thumbnails/60.jpg)
QUESTIONS
? ??
?