UST Release Investigation Report · 2009. 11. 1. · The treatment system operated until February...
Transcript of UST Release Investigation Report · 2009. 11. 1. · The treatment system operated until February...
UST Release Investigation Report
ML&P Operations and Dispatch Center 1201 East First Avenue
Anchorage, Alaska
November 2009
UST Release Investigation Report
ML&P Operations and Dispatch Center 1201 East First Avenue
Anchorage, Alaska
November 2009
Prepared by: Hoefler Consulting Group 3401 Minnesota Drive Suite 300 Anchorage, Alaska 99503 (Project Manager: Bret Berglund, Environmental Scientist: Brent Veltkamp)
Prepared for: Anchorage Municipal Light and Power 1200 E. 1st Avenue Anchorage, Alaska 99501
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power i November 2009
TABLE OF CONTENTS
1 INTRODUCTION ............................................................................................................. 1-1
1.1 Site Background...............................................................................................................1-1 1.2 Previous Spills and Investigations ...................................................................................1-2
1.2.1 Gasoline UST Release .....................................................................................................1-2 1.2.2 Used Oil UST Release .....................................................................................................1-2
1.3 Current Regulatory Status................................................................................................1-3 1.4 Site Description and Regional Setting .............................................................................1-3
1.4.1 Geology............................................................................................................................1-3 1.4.2 Hydrogeology ..................................................................................................................1-3 1.4.3 Land Use ..........................................................................................................................1-4
2 UST RELEASE, REMOVAL AND CORRECTIVE ACTIONS...................................... 2-1 2.1 Initial Reported Release and Actions (Water Line Excavation)......................................2-1 2.2 UST Removal...................................................................................................................2-1 2.3 Sampling and Analysis ....................................................................................................2-7 2.4 Data Reporting .................................................................................................................2-8
3 SAMPLE RESULTS ......................................................................................................... 3-1 3.1 Waste Characterization Results .......................................................................................3-1
3.1.1 Product and Water Samples .............................................................................................3-1 3.1.2 Soil Stockpile Results ......................................................................................................3-1
3.2 Site Characterization Results ...........................................................................................3-2 3.2.1 Water Line Excavation Area............................................................................................3-2 3.2.2 UST Excavation Area ......................................................................................................3-2
3.3 Results Discussion ...........................................................................................................3-3 4 SUMMARY AND CONCLUSIONS ................................................................................ 4-1 5 REFERENCES .................................................................................................................. 5-5
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power ii November 2009
LIST OF FIGURES
Figure 1-1 Vicinity Map .............................................................................................................1-5 Figure 1-2 Site Plan ....................................................................................................................1-7 Figure 1-3a Historical Aerial Photographs, 1964 and 1968 .......................................................1-9 Figure 1-3b Historical Aerial Photographs, 1970 and 2002 .....................................................1-11 Figure 2-1 Detailed Site Map with Sample Results....................................................................2-3 Figure 2-2 Cross Section of UST Excavation After Backfilling ................................................2-5
LIST OF TABLES
Table 3-1 Summary of Waste Characterization Samples ...........................................................3-5 Table 3-2 Soil Stockpile Log and Sample Results......................................................................3-7 Table 3-3 Water Line Excavation Laboratory Results, September 4, 2009 ...............................3-9 Table 3-4 UST Excavation Laboratory Results, September 14, 2009......................................3-13
LIST OF APPENDICES
Appendix A 1953 Operations Building Schematic Drawing Appendix B Photograph Log Appendix C ADEC Site Assessment and Release Investigation Summary Form ADEC Underground Storage Tanks Post Closure Notice Appendix D On Compact Disc:
Data Quality Assessment ADEC Laboratory Data Review Checklists
Laboratory Analytical Reports
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power iii November 2009
LIST OF ACRONYMS
AAC Alaska Administrative Code ADEC Alaska Department of Environmental Conservation amsl above mean sea level bgs below ground surface BTEX benzene, toluene, ethylbenzene, and total xylenes COCs contaminants of concern DRO diesel range organics EPA U.S. Environmental Protection Agency GRO gasoline range organics HCG Hoefler Consulting Group mg/Kg milligrams per Kilogram mg/L milligrams per Liter MDL method detection limit ML&P Municipal Light and Power MOA Municipality of Anchorage NA not analyzed/not applicable ND not detected at or above the method reporting limit OBS Oil Burning Specifications PAH polynuclear aromatic hydrocarbons PCB polychlorinated biphenyls PCE tetrachloroethene PID photoionization detector ppm parts per million PQL practical quantitation limit RCRA Resource Conservation and Recovery Act RRO residual range organics TCE trichloroethene TRPH total recoverable petroleum hydrocarbons TSCA Toxic Substances Control Act TSDF Treatment, Storage, and Disposal Facility USCS United Soil Classification System UST underground storage tank VOC volatile organic compound
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power iv November 2009
This page intentionally left blank.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 1-1 November 2009
1 INTRODUCTION
This report describes the results of a limited release investigation and corrective actions performed during the removal of an inactive underground storage tank (UST) located next to the Anchorage Municipal Light and Power (ML&P) Operations and Dispatch Center Building (Operations Building). The Operations Building is located at 1201 E. 1st Avenue, Anchorage, Alaska (Figure 1-1, Vicinity Map). The UST removal and reporting was performed in September 2009, in accordance with Alaska Department of Environmental Conservation’s (ADEC) UST regulations (18 Alaska Administrative Code [AAC] 78), and applicable sections of the UST Procedures Manual (ADEC 2002).
1.1 Site Background The UST site is located on a parcel of land owned by the Municipality of Anchorage and operated by ML&P. The legal description of the property is Lot 5a, Block 39D, East Addition Anchorage Townsite. It encompasses the street addresses of 1201 and 1121 E. 1st Avenue, and is 238,274 square feet (ft2) in size. A small parcel of land adjacent to the north side of the property is leased by ML&P from the Alaska Railroad. The location of the UST, along with the approximate property fence line boundaries are shown on Figure 1-2, Site Plan. The site is located in an industrial area between 1st Avenue and Ship Creek. The property was developed in the 1960s and has been used by ML&P for storage and support facilities. In addition to the Operations Building, the parcel includes the Vehicle Maintenance Building (garage), built around 1984. The site also contains a warehouse annex north of the Operations Building. The parcel formerly contained a Municipality of Anchorage (MOA) Paint and Sign Shop, which was demolished in 1997. The concrete slab and foundation of this building remain. Historical aerial photographs of the site, dating from 1964 until 2002, are shown in Figures 1-3a and 1-3b. The UST north of the Operations Building was inactive in 2009 and there is limited information regarding its history. The buried tank apparently supplied fuel to a boiler previously located in the northwest corner of the Operations Building. The UST is shown on a facility drawing from 1953, included in Appendix A (M.L. Taylor and P.W. Kilpatrick, Architects 1953). Documentation regarding when the tank was taken out of active service has not been located. In 2009, the area above the UST was a parking lot, and was paved over with asphalt. No piping or access points were visible. A concrete pad believed to have been the base of an electrical transformer is located next to the Operations Building, adjacent to the former UST (see Appendix B, Photograph Log). The original dates of service for the transformer in this location are not known. However, there are maintenance records from 1974 indicating that a transformer was replaced at this location (Matthews 2009, pers. com.). The transformer installed in 1974 did not contain oil with polychlorinated biphenyls (PCBs), and was removed in the mid 1980s. On August 31, 2009, during a construction project to install water lines for a fire suppression system, a dark oil-like fluid began flowing into the project excavation next to the Operations
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 1-2 November 2009
Building. Upon review of old facility drawings, the inactive UST was identified as the most likely source of the product. The investigations and removal actions described in this report followed soon thereafter.
1.2 Previous Spills and Investigations There have been no previous investigations directly related to the UST or the immediate area prior to 2009. There have been, however, environmental investigations and cleanup of other portions of the land parcel, primarily focused on UST releases. In addition to the inactive UST next to the Operations Building, there were formerly three other USTs located on the property (see Figure 1-2 for locations). These include the following:
� One 4,000-gallon gasoline and one 4,000-gallon diesel UST located beneath a dispensing island on the southeast corner of the Vehicle Maintenance Building (1121 E. 1st Ave); and
� One 500-gallon used oil UST located on the east side of the Vehicle Maintenance Building approximately 100 feet to the north.
1.2.1 Gasoline UST Release On March 29, 1989, a leak was discovered in the 4,000 gallon unleaded gasoline UST. The UST and adjacent diesel UST were subsequently removed. During the UST removals, approximately 400 yd3 of impacted soil were removed from the excavation. In addition, approximately 167,790 gallons of oily water and 850 gallons of fuel were recovered during and after the initial excavation (Shannon & Wilson 2003). In the fall of 1989, nine groundwater monitoring wells, one product recovery well, a groundwater air stripper, and a soil vapor extraction system were installed. The treatment system operated until February 1996. Groundwater monitoring was continued until 2002, when ADEC granted the site No Further Action status based on decreasing groundwater hydrocarbon concentrations. The groundwater well network was left in place at ADEC’s request for future confirmation and closure sampling.
1.2.2 Used Oil UST Release On October 26, 1990, a used oil UST was removed from the east side of the garage. Soil samples collected during the UST removal indicated significantly elevated petroleum hydrocarbons (5,700 milligrams per Kilogram [mg/Kg] total recoverable petroleum hydrocarbons [TRPH]) and low levels of trichloroethene (TCE) and tetrachloroethene (PCE) at the excavation limits. In 1992, additional sampling showed similar soil contamination and chlorinated solvents in the groundwater at concentrations ranging from 4.7 �g/L to 9.0 �g/L for PCE and 27 �g/L to 48 �g/L for TCE (Shannon & Wilson 2003). In October 1993, three additional monitoring wells (B-1, B-2, and B-3) were installed at locations surrounding the former UST to further define the extent of PCE and TCE in the groundwater (Shannon & Wilson 1993). The highest concentrations were detected in well B-2, located nearest the former UST, with PCE concentrations of 0.025 milligrams per Liter (mg/L) and TCE at 0.043 mg/L. These concentrations exceeded ADEC groundwater cleanup levels. Quarterly sampling and analysis of well B-2 for TCE and PCE was initiated in 2002. Both compounds have continued to exceed the ADEC groundwater cleanup levels (18 AAC 75.345, Table C). There is no clear indication that concentrations are significantly decreasing and
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 1-3 November 2009
approaching cleanup levels. In July 2009 (the most recently reported sampling event), the groundwater sample from well B-3 contained 0.0159 mg/L TCE and 0.0356 mg/L of PCE. The ADEC groundwater cleanup level for these two compounds is 0.005 mg/L. Cis-1,2-dichloroethene (cis-1,2-DCE) was also detected in July 2009, but below the associated cleanup level. Cis-1,2-DCE is a daughter product of the reductive dechlorination of TCE and PCE (Hoefler Consulting Group [HCG] 2009a). In a separate investigation, an Environmental Protection Agency (EPA) contractor installed well points west of the former waste oil tank to evaluate the former tanks contribution to vinyl chloride contamination detected downgradient (west) of the UST site. The results of the investigation indicated the solvent contamination from the waste oil tank degrades rather quickly and the contaminant plume is generally attenuated a short distance from the source area and is not responsible for the chlorinated solvent plume (CH2M HILL 2008). This site is still an active site in the ADEC contaminated sites database (Hazard ID 23606).
1.3 Current Regulatory Status The Operations Building UST site was recently added (9/16/09) as an active site in the ADEC contaminated sites database. The Hazard ID is 25453.
1.4 Site Description and Regional Setting The site lies adjacent to Ship Creek, approximately one mile upstream from its outlet into the Knik Arm of Cook Inlet. The site is relatively flat with an elevation of approximately 35 feet above mean sea level (amsl). Surface drainage at the site is generally to the northwest toward Ship Creek. However, direct runoff to the creek is impeded by an earthen embankment along the north edge of the property (see Figure 1-2, “Pole Yard” area). At its nearest point, Ship Creek is located approximately 300 feet from the northern edge of the UST excavation site; the creek elevation is approximately 10 feet below the average surface elevation of the site. No other surface water bodies are present in the vicinity of the site.
1.4.1 GeologyThe facility is underlain stratigraphically by glacial, glaciofluvial, and glacial lacustrine sediments. Nearest the ground surface, varying thicknesses of fill associated with plant construction are present. Based on the regional geology, underlying the fill is approximately 15 feet of alluvial material deposited by Ship Creek (META 1994). The Bootlegger Cove Formation, made up of predominately silty clays and clayey silts, immediately underlies the alluvial sand and clay. This formation is estimated to be approximately 160 feet thick based on well logs. During excavations for this project, the soils in the immediate excavation areas were observed to be fairly uniform, consisting of well-graded gravels and sand mixtures with little fines. Occasional silt lenses were present. Semi-rounded coarse gravel and small cobbles were common, with a diameter up to 4 inches.
1.4.2 HydrogeologyGroundwater at the site consists of a shallow water table aquifer and a deep confined aquifer. The aquifers are separated by the fine-grained Bootlegger Cove Formation which has a low permeability and acts as an aquitard, or confining unit. The shallow unconfined aquifer underlies the entire site and ranges from 4 to 20 feet below ground surface (bgs). The shallow aquifer is
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 1-4 November 2009
recharged primarily by precipitation and groundwater flow from areas upgradient from the site. Groundwater in this shallow aquifer discharges to Ship Creek and seeps, and also discharges by evapotranspiration. The general groundwater flow direction is west toward Cook Inlet (The RETEC Group 2008). Shallow groundwater measurements from monitoring wells 2A1, B-1 and B-3 (Figure 1-2) by HCG on October 8, 2009 found the depth to groundwater ranged from 4.01 to 5.71 feet bgs (report pending). The groundwater elevation data from this monitoring event and others indicate the groundwater flow direction is to the west, parallel to Ship Creek (see Figure1-2). The estimated hydraulic conductivity is anticipated to be in the range for coarse sand and gravel, 3.29x10-4 to 3.29x10-2 ft/s (Freeze and Cherry 1979). However, the numerous utilities and structures installed in the subsurface at the facility and the associated fill may have local effects on both groundwater flow direction and velocity. A web search was conducted using the Alaska Department of Natural Resources Well Log Tracking System (WELTS) to determine water supply wells located within 0.75 miles of the site. Several deep water supply wells, installed by the MOA and located near Merrill Field, were identified. Merrill Field is approximately 0.75 miles southwest and hydraulically upgradient from the site. No shallow water supply wells were positively identified in the shallow aquifer within 0.75 miles of the site. Several wells on the north side of Ship Creek were identified; however, these wells are on the opposite side of a hydrologic boundary (Ship Creek) and are not hydrologically connected to the site.
1.4.3 Land UseThe area in the vicinity of the Operations Building and the lowland area along Ship Creek have historically been, and will likely continue to be used for commercial and industrial purposes. The area is zoned for heavy or light industry, and the area immediately adjacent to the UST site, and most of the surrounding area, is covered by buildings, concrete, asphalt, and gravel fill. The site is fully developed and there is little remaining natural habitat.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 1-6 November 2009
This page intentionally left blank.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 1-8 November 2009
This page intentionally left blank.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 1-10 November 2009
This page intentionally left blank.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 1-12 November 2009
This page intentionally left blank.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 2-1 November 2009
2 UST RELEASE, REMOVAL AND CORRECTIVE ACTIONS
2.1 Initial Reported Release and Actions (Water Line Excavation) As stated in Section 1.1, on August 31, 2009, a dark fuel oil-like fluid was observed flowing into an excavation on top of the water table next to the Operations Building during a construction project to install water lines. The area is referred to as the Water Line Excavation on Figure 2-1. Photos of the excavation are provided in Appendix A, Photograph Log. The excavation was approximately 6 to 7 feet deep and extended below the water table. The water table had been temporarily lowered by pumping to support the excavation activities, and the oil-like product was not observed until this dewatering occurred. A review of old facility drawings identified the inactive UST as the most likely source of the product. Upon discovery of the suspected fuel release, oily water in the excavation was pumped into a vacuum truck for offsite disposal. Soil suspected of being contaminated was also removed from the lower portion of the excavation and placed on a lined containment. An oil-water separator system was installed to enable dewatering to continue and completion of the construction project. Dewatering was performed by installing a slotted culvert vertically as a sump next to the UST and pumping water to the surface for treatment and discharge. Water was run through an oil-water separator, and discharged to a secondary treatment tank where any remaining sheen was removed with sorbent pads. Treated water was discharged to the municipality’s sewer system in accordance with ML&Ps discharge permit. A Cleanup Plan was submitted by ML&P and approved by ADEC for site characterization and soil management during the remainder of the construction project (HCG 2009b). On September 4, the base of the excavation was expanded slightly to remove soil along the base of the excavation that may have become contaminated from contact with infiltrating product. The excavated soil was stockpiled on a liner. Three stockpiles of potentially contaminated soil were generated during the Water Line excavation, with a total volume of 11 yd3. Based on sample results, the stockpiled soil was either disposed offsite or determined to be suitable for onsite reuse (see Section 3.1.2). After soil removal was complete, soil samples for laboratory analysis were collected along the excavation bottom and sidewalls to characterize the site conditions prior to backfilling. Sample results are discussed in Section 3. Following sampling, the water lines were installed, the excavation was backfilled, and the project was completed. Backfill material consisted of clean fill from offsite; sewer rock was used to backfill the excavation to approximately 4 feet bgs, and gravel was used above the sewer rock.
2.2 UST Removal Following a review of old facility drawings, the likely source of the product was attributed to be the inactive UST. On September 1, 2009, the UST was emptied of approximately 425 gallons of fuel and 1,475 gallons of water. The fluids were sampled for the purpose of waste characterization and sent to an offsite Treatment, Storage and Disposal Facility (TSDF), Emerald Services in Anchorage, AK.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 2-2 November 2009
The UST was subsequently removed on September 14, 2009. A release investigation was conducted concurrently with the removal action, as a release was suspected. The removal action and release investigation were conducted in accordance with a project Work Plan (HCG 2009c) approved by ADEC. Photos of the UST removal and excavation are provided in Appendix A, Photograph Log. For reference, Appendix C includes the ADEC Site Assessment and Release Investigation Summary Form and ADEC UST Post Closure Notice, summarizing information included in this report. During the removal action, ground water dewatering continued because the UST removal required excavation below the water table. Initially, the upper 3 feet of soil, stockpile SP04, was removed from around the UST and placed on the adjacent asphalt (see Table 3-2). A concrete vault and cover, located directly on top of the UST, was removed. Dark staining was evident on the top surface of the concrete, especially in the vault area. The concrete was placed on a liner for eventual cleaning and testing. After the concrete cover was removed, soil around the sides of the UST was excavated. Soil excavated below 3 feet bgs (stockpile SP05) was placed on a liner pending the results of sampling and analysis. An excavation depth of approximately 6 feet bgs was required to remove the UST. The steel tank was approximately 11 feet long and 6 feet 2 inches in diameter with an estimated capacity of approximately 2,500 gallons. There were numerous (40-60) holes up to one inch in diameter along the lower half of the tank, estimated to be at the approximate water table level prior to dewatering. Fluids, primarily water with a small quantity of fuel, were still present in the UST on the date of its removal, and were pumped from the tank prior to the final excavation. Water in the tank was likely ground water that had infiltrated the tank through the numerous holes since the previous pumping on September 1. The oily water (508 gallons total) was sent to an offsite TSDF for disposal (Emerald Services, Anchorage, AK). After the UST was removed, visible product and sheening was present on groundwater at the bottom of the excavation. Product was removed with sorbent boom and pads. The most visibly-contaminated soils around the base and edges of the excavation were removed and combined with SP05 stockpiled soil. Following excavation, soil sampling was conducted along the perimeter of the excavation on all four sidewalls at multiple depth intervals to characterize the site conditions. The sample results are presented in Section 3. The excavation was backfilled after the completion of soil sampling. Backfill material consisted of three types: (1) From the bottom of the excavation to the estimated water table depth (4 feet bgs), backfill material consisted of approximately 40 yd3 of clean sewer rock (coarse gravel with no sand or fines); (2) Stockpile SP04 soil was placed over the sewer rock to a depth of 0.5 to 1 foot bgs. The SP004 soil (approximately 60 yd3) was originally removed from the upper 3 feet of soil within the excavation; (3) Approximately 12 yd3 of surface soil (0-3 bgs) from the Water Line excavation area was used to fill the remainder of the UST excavation. The area was paved approximately one week later. A cross section of the backfilled excavation is shown on Figure 2-2.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 2-4 November 2009
This page intentionally left blank.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 2-6 November 2009
This page intentionally left blank.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 2-7 November 2009
The UST was cleaned to remove any residual product and sent to Alaska Metal Recycling for disposal. The cleaning generated two 55-gallon drums of oily sludge. Nineteen drums of oily sorbent pads and boom were generated during cleanup activities at the Water Line and UST excavation. The drums, including the oily sludge, were sent to an offsite TSDF for disposal (Emerald Services, Anchorage, AK) with ultimate disposal in the lower 48 States. These wastes were characterized based on the product sample recovered from the UST (see Section 3.1). Groundwater pumping and treatment, as described in Section 2.1.1, was continued until September 21 to remove as much residual product as possible from soil and groundwater at the site. At the conclusion of groundwater treatment, no sheening was observed and no product was recovered in the oil-water separator over a 3-day period (Matthews 2009, pers. com.).
2.3 Sampling and Analysis Samples of soil, water and fuel product were collected for the purposes of site and waste characterization throughout the project using standardized methods according to the project Work Plans (HCG 2009b and 2009c) and ADEC guidance documents (ADEC 2002). Sampling was performed by HCG environmental scientists (Brent Veltkamp and Bret Berglund). All site characterization and most waste characterization samples were analyzed by SGS Environmental Services, Inc. in Anchorage, Alaska. Several waste characterization samples were analyzed by Columbia Analytical Services (CAS) in Kelso, Washington. Specific analyses for each sample type are detailed on tables 3-1 through 3-4 in Section 3. Site characterization samples were soil grab samples collected from discrete depth intervals in excavations and from soil stockpiles. Soil samples were collected by hand using clean disposable stainless steel sampling spoons, while wearing disposable nitrile sampling gloves. Soil collected for field duplicates for semi-volatiles analysis was homogenized in a decontaminated stainless steel bowl prior to filling sample jars. To aid in sample location selection, soil stockpiles were screened for volatiles using the headspace method as described in the ADEC UST Procedures Manual, Section 4.4.2 (ADEC 2002). Using this procedure, a photoionization detector (PID) headspace sample was collected and screened at a rate of at least one sample per 10 yd3. Samples were randomly distributed throughout the stockpile and collected at a depth of at least 18 inches below the surface. The screening locations and results were recorded in a field log book, and on stockpile screening logs. For soils contaminated or potentially contaminated, analytical samples were collected from the locations with the highest PID reading at a rate of at least two samples for the first 50 yd3 and 1 per every additional 50 yd3 (or portion thereof). The analyses were focused on the contaminants of concern based on the site history and results of the product sample from the UST (see Table 3-1), and included petroleum hydrocarbons (diesel range organics/residual range organics [DRO/RRO] and gasoline range organics/benzene, toluene, ethylbenzene, and total xylenes [GRO/BTEX]) and PCBs. Petroleum hydrocarbons were not analyzed if it was decided beforehand that stockpiled soil would be sent offsite for disposal based on PID-screening and visual observations. In stockpile SP04, consisting of cover soil from the UST excavation, PID readings were all less than 25 parts per million (ppm) and the soil was classified as clean and reused as excavation backfill without laboratory analysis.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 2-8 November 2009
Soil descriptions, field observations, PID results, and sample information was documented in the field logbook. Soil sample locations were documented by swing tying measurements from fixed reference points (buildings). Soils were classified using the Unified Soil Classification System (USCS) and recording observations of color, odor, and staining. Observations, descriptions, and other pertinent sample information were recorded in the field notebook.
2.4 Data Reporting Analytical data was provided in Level II hardcopy and electronic format. Lab reports are included on CD in Appendix D, along with a Data Quality Assessment and ADEC Laboratory Data Review Checklists. A Data Quality Assessment was performed in accordance with ADEC quality assurance procedures for laboratory data (ADEC 2009) to ensure that the data set met project data quality objectives. An ADEC Laboratory Data Review Checklist was completed for each laboratory work order. The data assessment did not include samples collected for waste characterization. The data review included an evaluation of the following and did not indicate any concerns limiting the usefulness of the data:
� chain-of-custody forms (CoCs), custody seals on coolers, and internal cooler arrival temperatures to ensure that the samples were securely transported and properly preserved;
� hold times (not applicable to PCBs);
� trip blanks;
� continuous calibration verifications;
� instrument and method/extraction and blanks;
� surrogate recoveries;
� laboratory control sample and laboratory control sample duplicate recovery (as percent recovery) and precision (as relative percent difference);
� matrix spike and matrix spike duplicate recovery (as percent recovery) and precision (as relative percent difference); and
� laboratory detection and reporting limits.
The data review indicated the reported laboratory data was of good quality. The following tabulated data qualifiers were added to the laboratory-provided data where applicable based on the evaluation.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 2-9 November 2009
Qualifier Description
FThe analyte was positively identified but the associated concentration was estimated above the method detection limit (MDL) and below the practical quantitation limit (PQL).
JThe analyte was positively identified, the quantitation was an estimate. Where applicable a “+” or “-” was appended to indicate positive or negative bias, respectively.
ND The analyte was analyzed for, but not detected. The associated numerical value was at or below the MDL.
M A matrix effect was present. Where applicable a “+” or “-” was appended to indicate positive or negative bias, respectively.
BThe compound was positively identified in the method blank and/or trip blank. The reported concentration was less than 5X that of the blank, or less than 10X for common laboratory contaminants, methylene chloride and acetone.
The rationale for applying qualifiers to specific data sets is described in the Data Quality Assessment. There were several volatile analytes identified where the MDL were higher than migration to groundwater cleanup levels. The MDLs reported with the data are typical for the methodology applied. For those analytes, it is not possible to state with certainty that the affected analytes are not present in the samples above migration to groundwater cleanup levels. The data set was 100% complete with no omissions or rejections with respect to analysis.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 2-10 November 2009
This page intentionally left blank.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 3-1 November 2009
3 SAMPLE RESULTS
3.1 Waste Characterization Results The types and results of waste characterization samples are listed in Table 3-1, with the exception of soil stockpile sample results, listed on Table 3-2. Sample result tables are included at the end of this section. In addition to sample results, the tables also summarize the disposition of the various wastes. A description of the most relevant results is presented below. Analytical data reports are included in Appendix D (on CD).
3.1.1 Product and Water Samples A sample of the product removed from the UST was collected for laboratory analysis of oil burn specifications (total halogens, PCBs, Resource Conservation and Recovery Act [RCRA] metals, and flash point) and volatile organic compounds (VOCs). In addition, a product sample was collected from the Water Line Excavation in the sump area within building. The product results met the RCRA oil burn specification, except for PCBs (Table 3-1). PCBs were detected at 3.4 mg/Kg in the sample from the UST (PS03) and 17 mg/Kg in the product sample from the Water Line excavation (PS02). Based on the oil burn specifications results and visual observations, the product had the characteristics of a light fuel oil or diesel fuel. Chlorinated solvents were not present based on total halogen and VOC analysis. CAS also performed testing on product sample PS03 from the UST in order to provide additional information regarding the nature of the fuel. The testing included a hydrocarbon identification screen, specific gravity (0.85), and viscosity (2.90 centipoise [cP] @ 24.8 ºC). Based on the results, the laboratory concluded that the sample was composed primarily of an unknown slightly weathered diesel, potentially with some lighter fuels (Appendix D, CAS K0909082). A sample of the water recovered from the excavation was also analyzed for VOCs. (Table 3-1, Sample Water 1). No chlorinated solvents were detected, although some fuel components were present in low concentrations (less than 18 AAC 75.345, Table C, Groundwater Cleanup Levels).
3.1.2 Soil Stockpile Results Water Line ExcavationThe soil stockpiles from the Water Line Excavation (SP01, SP02 and SP03) all contained detectable PCBs (Table 3-2). However, no samples exceeded the ADEC Method Two cleanup level of 1 mg/Kg. Based on the petroleum levels, the soil was either classified for onsite reuse or sent offsite for disposal as a non-hazardous waste. The stockpile results were consistent with results for sample ES02, a sample collected from the bottom of the excavation prior to conducting the final soil removal. This composite sample was collected for planning purposes, with the intention of characterizing the contaminated soil prior to its removal. The sample was analyzed for PCBs and VOCs. Chlorinated solvents were not detected in the soil; however, PCBs were detected at 0.165 mg/Kg (Table 3-1). UST Excavation
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 3-2 November 2009
Two stockpiles were generated during the UST removal. The first stockpile, designated SP04, consisted of sandy gravel soil from approximately 0-3 feet bgs, above the top level of the UST. The stockpile was approximately 60 yd³, and was not visibly contaminated. Six PID headspace screening samples were collected from the stockpile; the maximum reading was 7.8 ppm. No analytical samples were collected. The stockpile was designated suitable for reuse based on PID readings and visual observations, and was ultimately used as backfill in the excavation (at the time, PCB contamination was not suspected). Soil removed from the deeper portion of the excavation, designated stockpile SP05, was visibly contaminated with petroleum hydrocarbons. Four PID headspace screening samples were collected, all had elevated readings over the range of the instrument (>15,000). Laboratory analysis detected PCBs up to 114 mg/kg and DRO to 2,550 mg/Kg. The PCB concentration in the stockpile exceeded the Toxic Substances Control Act (TSCA) regulatory level of 50 mg/Kg. This required the soil to be disposed offsite as a TSCA regulated waste in a RCRA hazardous waste landfill.
3.2 Site Characterization Results
3.2.1 Water Line Excavation Area The soil sample results from the completed Water Line Excavation are presented on Table 3-3 and Figure 2-1. Analytical data reports are included in Appendix D (on CD). Samples were collected prior to installation of the water line and backfill of the excavation. Ten samples and one replicate were collected in locations distributed along the bottom of the excavation and sidewalls. The samples were analyzed for GRO/BTEX, DRO/ RRO, and PCBs; two samples from the most likely areas of contamination were analyzed for VOCs. No sample concentrations exceeded the ADEC Method Two cleanup level for the under 40-inch zone. However, DRO and two chlorinated solvents (tetrachloroethene and trichloroethene) exceeded the most stringent ADEC Method Two cleanup level (Migration to Groundwater). DRO exceeded this cleanup level in two locations along the floor of the excavation. The highest concentration (2,140 mg/Kg) was detected within a small excavation within the building (Sample ES07-6.5). This is the same location were the two chlorinated solvents exceeded the Migration to Groundwater cleanup level. PCBs were detected in 5 of 10 samples but no sample concentrations exceeded the ADEC Method Two cleanup level of 1 mg/Kg. Aroclor 1260 was the only PCB detected.
3.2.2 UST Excavation Area After the UST and soil removal was complete, soil samples were collected from the excavation to characterize the remaining soils. Samples were collected from twelve locations on the perimeter sidewalls of the excavation; at the bottom (6.0-6.5 feet bgs) and 4 feet bgs along all four sidewalls, and at 0.5 and 1.5 feet bgs on the southern and western sidewalls (Figure 2-1). Soil samples could not be collected directly below the former tank due to the presence of groundwater in the excavation. The soil samples were analyzed primarily for GRO/BTEX, DRO/RRO and PCBs, with some additional selective analyses for polynuclear aromatic hydrocarbons (PAHs).
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 3-3 November 2009
Soil sample results are presented in Table 3-4 and summarized on Figure 2-1. Analytical data reports are included in Appendix D (on CD). DRO and PCBs exceeded the ADEC Method Two cleanup level for the under 40-inch zone (direct contact or ingestion). DRO exceeded the cleanup standard in two locations with a maximum concentration of 17,700 mg/kg. The more stringent Migration to Groundwater Cleanup standard was exceeded in 6 of 12 locations. PCBs were detected in all 12 sample locations, and exceeded 1 mg/Kg in 8 of 12 locations. The maximum PCB concentration was 112 mg/Kg. Three of the 12 samples were above 50 mg/Kg. Aroclor 1260 was the only PCB detected. Several PAH compounds (1-Methylnaphthalene and 2-methylnaphalene) slightly exceeded the ADEC Method Two Migration to Groundwater cleanup standard. Petroleum contamination was generally highest at the deepest sample point on a given sidewall. Near surface samples (0.5 and 1.5 feet bgs) contained relatively low levels of petroleum contamination. This suggests there may have been minor spills at the surface (perhaps during tank filling), but the primary point of release was in the subsurface near the water table. The highest concentrations of DRO tended to be on the south and west portions of the excavation. This southwest corner is the down gradient edge of the excavation based on the general groundwater flow in the area (Figure 2-1). In addition, alteration of the normal groundwater flow direction during dewatering of the Water Line Excavation may have inadvertently contributed to contaminant migration in this area. With respect to PCBs, the sampling indicated that contamination was generally highest in the surface soil next to the Operations Building. However, there were also some fairly elevated PCB concentrations in the subsurface at 4 to 6 feet bgs. The detected concentrations tended to decrease to the north. It is assumed PCBs are also present in the soil in the 1 to 4 feet bgs depth range within the backfilled excavation. PCBs were detected in all four sidewall samples from 0.5 and 1.5 feet bgs. Therefore, it is probable that the surface soil between these points contained PCBs. This surface soil was originally removed, and then placed back in the UST excavation at a depth of 1 to 4 feet bgs. Clean backfill was used below and above this material to fill the remainder of the excavation (see Section 2.2, and Figure 2-2).
3.3 Results Discussion A review of the data and site history suggests that there were probably two separate sources for the contaminants detected at the site.
� Spills/Leaks of diesel fuel from the UST, and � Spills/leaks of dielectric fluids with PCBs from the adjacent transformer.
The petroleum contamination at the site is attributed to leaks from the UST. The tank had numerous corrosion holes in its lower half indicating that leaks may have been occurring for some time. However, the current information indicates the release was relatively limited with respect to volume and area of impact. If there had been a long-term release consisting of multiple tank volumes, soils in the nearby Water Line excavation would likely have exhibited more extensive and higher concentrations of petroleum in the subsurface. In addition, it is likely the presence of a large, historical release would have been suspected or confirmed in the
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 3-4 November 2009
groundwater sampling conducted as part of the Gasoline and Used Oil UST investigations in the 1990s (see Section 1.2). These sites and associated monitoring wells are located cross- or downgradient of the Operations Building UST. These circumstances suggest the leaks may have developed after the tank became inactive which limited the release to less than one tank volume. Assuming this is the case, the maximum volume of the release would be 1,975 gallons (original tank volume [2,500 gallons], minus recovered product [425 gallons], minus tank sludge [100 gallons]). In addition, there does not appear to have been significant migration in the direction of the Water Line Excavation until the groundwater in the area was artificially lowered by pumping in 2009. The most likely explanation for the presence of PCBs in the soil is a historical release or spill of dielectric fluids containing PCBs from the transformer originally located on the adjacent concrete pad. This release(s) likely occurred prior to 1974, when the transformer was replaced with a non-PCB containing transformer (see Section 1.1). The PCBs were most likely released at the ground surface and initially moved no farther than the immediate dielectric fluid spill area. PCBs have low water solubility, generally bind to fine grained soils, and do not migrate unless the soils are moved through human activity or natural processes (e.g., erosion). The presence of fuel leaking from the UST has probably contributed to the subsequent migration of PCBs from their initial point of release. PCBs are soluble in petroleum products such as fuel and oil, and can therefore be mobilized if light non-aqueous phase liquid (LNAPL) is present and migrating. These conditions were present in the vicinity of the UST and could account for the PCBs being detected in the subsurface at depths of 6 feet bgs. It could also account for the PCBs being detected at low concentrations (3.4 mg/Kg) in the fuel contained in the tank and in the product sampled from the Water Line Excavation. This appears to be more probable than the alternate explanation that fluids containing PCBs were disposed intentionally into the UST. The extent of PCB and petroleum hydrocarbon contamination in the soil or groundwater cannot be quantified with the available data set. However, as discussed above, the limited information available suggests impacts are relatively localized. Furthermore, the extent of PCB contamination should be limited to the extent of migration of the LNAPL phase (fuel or dielectric fluid), unless the PCBs were originally dispersed prior to the area being covered by asphalt. It is likely that petroleum and PCB-contaminated soil extends below the foundation of the Operations Building. On October 10, 2009, three monitoring wells downgradient of the UST excavation were sampled for DRO/RRO and PCBs (Figure 1-2, Wells 2A1, B-1 and B-2). When available, this data set will help define the extent of contaminant migration from the site, particularly dissolved components. A preliminary review of the data set indicates contaminants associated with the UST site have not caused elevated concentrations of contaminants at these locations (HCG 2009d).
Tabl
e 3-
1 Su
mm
ary
of W
aste
Cha
ract
eriz
atio
n Sa
mpl
esM
LP O
pera
tions
and
Dis
patc
h C
ente
r
Oth
er A
naly
ses
Ars
enic
Cad
miu
mC
hrom
ium
Lead
Lim
its:
37.8
°C
4,00
05
210
100
2N
A
PS
029/
1/20
09Li
quid
Pro
duct
col
lect
ed fr
om w
ater
line
ex
cava
tion,
sum
p ar
ea in
side
bu
ildin
g.
9324
6N
D (0
.4)
ND
(0.0
3)0.
2 F
ND
(0.4
)17
ND
(7.0
)R
ecov
ered
pro
duct
sen
t offs
ite to
TS
DF
(Em
eral
d S
ervi
ces)
PS
039/
1/20
09Li
quid
Pro
duct
sam
ple
from
US
T pr
ior t
o re
mov
al.
OB
S, V
OC
s61
ND
(100
)N
D (0
.4)
0.03
F0.
2 F
1.1
3.4
ND
(14)
Rec
over
ed p
rodu
ct s
ent o
ffsite
to T
SD
F (E
mer
ald
Ser
vice
s)
Wat
er1
9/1/
2009
Liqu
idO
ily w
ater
col
lect
ed fr
om v
acuu
m
truck
follo
win
g re
mov
al fr
om W
ater
Li
ne E
xcav
atio
n.
VO
Cs
NA
NA
NA
NA
NA
NA
NA
ND
(0.0
062)
3
Som
e fu
el c
ompo
unds
wer
e de
tect
ed
belo
w 1
8 A
AC
75
Tabl
e C
crit
eria
. S
ampl
e w
as ru
n at
a 2
0 fo
ld d
ilutio
n,
som
e M
DLs
are
ele
vate
d.
Oily
wat
er s
ent o
ffsite
to T
SD
F (E
mer
ald
Ser
vice
s)
Con
019/
17/2
009
Sol
id
(con
cret
e ch
ips)
Sam
ple
of c
oncr
ete
cove
r on
the
top
of U
ST.
Sam
ple
colle
cted
usi
ng
ham
mer
dril
l fro
m a
rea
of d
ark
stai
ning
on
conc
rete
insi
de s
urfa
ce o
f pi
ping
vau
lt af
ter t
ank
conc
rete
was
cl
eane
d.
PC
Bs
NA
NA
NA
NA
NA
NA
0.72
5N
A
Sam
ple
dept
h 0-
1.0
inch
es.
Con
cret
e w
as d
ark-
stai
ned
at th
e su
rface
, and
ligh
t gr
ey u
nder
neat
h su
rface
(uns
tain
ed).
Con
cret
e se
nt o
ffsite
for d
ispo
sal
(Anc
hora
ge R
egio
nal L
andf
ill).
Sta
ined
w
ood
arou
nd th
e va
ult w
as d
ispo
sed
with
so
il in
SP
05 (s
ee T
able
3-2
)
ES
029/
2/20
09S
olid
(s
oil)
Soi
l fro
m w
ater
line
exc
avat
ion.
R
epre
sent
ativ
e co
mpo
site
sam
ple
of
soil
that
was
to b
e ex
cava
ted
(col
lect
ed fr
om th
e co
ntam
inat
ed
zone
). P
urpo
se w
as to
exp
edite
w
aste
cha
ract
eriz
atio
n of
the
soil
for
disp
osal
.
PC
Bs,
VO
Cs
NA
NA
NA
NA
NA
NA
0.16
5N
D (0
.072
8)3
No
chlo
rinat
ed s
olve
nts
dete
cted
; som
e fu
el c
ompo
nent
s be
low
Met
hod
2 M
igra
tion
to G
roun
dwat
er.
Soi
l exc
avat
ed o
n 9/
4/20
09.
See
st
ockp
ile S
P03
, Tab
le 3
-2, S
oil S
tock
pile
Lo
g an
d S
ampl
e R
esul
tsN
otes
:1
- PC
B-1
260
was
the
cong
ener
det
ecte
d in
all
sam
ples
.2
- Sam
ples
wer
e an
alyz
ed fo
r Chl
oroe
than
e, V
inyl
Chl
orid
e, 1
-1-D
ichl
oroe
then
e, tr
ans-
1,2-
Dic
hlor
oeth
ene,
cis
-1,2
-Dic
hlor
oeth
ene,
1,2
-Dic
hlor
oeth
ane,
Tric
hlor
oeth
ene,
1,1
,2-T
richl
oroe
than
e,
T
etra
chlo
roet
hene
, 1,1
,2,2
-Tet
rach
loro
etha
ne.
For n
onde
tect
s ("
ND
"), t
he h
ighe
st m
etho
d de
tect
ion
limit
is s
how
n in
par
enth
eses
.3
- The
se s
ampl
es w
ere
anal
yzed
for f
ull l
ist v
olat
ile o
rgan
ic c
ompo
unds
. N
o ch
lorin
ated
sol
vent
s w
ere
dete
cted
. S
cree
ning
Crit
eria
are
18
AA
C 7
5 Ta
ble
C fo
r wat
ers
and
Tabl
es B
1 an
d B
2 fo
r soi
ls.
T
here
fore
, the
se w
aste
s w
ere
assu
med
to h
ave
PC
Bs
< 50
mg/
Kg.
Dat
a Fl
ags
Fre
porte
d va
lue
was
bet
wee
n th
e la
bora
tory
MD
L an
d P
QL
ND
nond
etec
t, m
etho
d de
tect
ion
limit
is p
rese
nted
in b
rack
ets
to th
e le
ft
Abb
revi
atio
nsA
AC
Ala
ska
Adm
inis
trativ
e C
ode
PC
BP
olyc
hlor
inat
ed B
iphe
nyl
MD
LM
etho
d D
etec
tion
Lim
itP
QL
Pra
ctic
al Q
uant
itatio
n Li
mit
mg/
Kg
mill
igra
ms
per k
ilogr
amTS
DF
Trea
tmen
t, S
tora
ge, a
nd D
ispo
sal F
acili
tyN
AN
ot A
naly
zed
VO
CV
olat
ile O
rgan
ic C
ompo
und
OB
SO
il B
urni
ng S
peci
ficat
ion
Bol
d an
d Sh
aded
= S
ampl
e re
sults
exc
eed
the
scre
enin
g cr
iteria
.
4- T
he p
rodu
ct s
ampl
es (P
S02
and
PS
03) w
ere
also
use
d to
cha
ract
eriz
e th
e 2
drum
s of
oil
slud
ge, a
nd 1
9 dr
ums
of o
iled
sorb
ent p
ads,
boo
m, a
nd P
PE
gen
erat
ed d
urin
g th
e cl
eanu
p.
Chl
orin
ated
Solv
ents
2
(mg/
L)
Com
men
ts a
nd D
ispo
sitio
n of
A
pplic
able
Was
te
OB
S, V
OC
s
Ana
lysi
sSa
mpl
e ID
Sam
ple
Dat
eSa
mpl
e Ty
peLo
catio
n/D
escr
iptio
n
Sum
mar
y of
Ana
lytic
al R
esul
tsO
il B
urn
Spec
ifica
tions
(OB
S)
Met
als
(mg/
Kg)
Flas
hPo
int
(°C
)
Tota
lH
alog
ens
(mg/
L)
PCB
s(m
g/K
g)1
3-5
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 3-6 November 2009
This page intentionally left blank.
Tabl
e 3-
2. S
oil S
tock
pile
Log
and
Sam
ple
Res
ults
MLP
Ope
ratio
ns a
nd D
ispa
tch
Cen
ter
PCB
sD
RO
RR
OG
RO
BTE
X
SP
01
Wat
er L
ine
Exc
avat
ion:
Firs
t soi
l fro
m p
oten
tially
-co
ntam
inat
ed s
oil r
emov
ed w
ith
vacu
um tr
uck
39/
1/20
099/
4/20
0995
in
-situ
SP
010.
0696
87.8
36.5
4.04
ND
[0.0
141]
No
cont
amin
ants
det
ecte
d ab
ove
regu
lato
ry c
lean
up le
vels
(AD
EC
or
TSC
A).
Soi
l is
stor
ed o
nsite
in th
e P
ole
Yar
d on
the
grou
nd s
urfa
ce.
In
2010
, soi
l will
be
used
for r
e-gr
adin
g no
rthw
est o
f the
Veh
icle
Mai
nten
ance
B
uild
ing
and
pave
d w
ith a
spha
lt.
AD
EC
not
ified
of p
lan
and
conc
urre
d in
S
ept.
2009
.
SP
025
9/1/
2009
9/4/
2009
1500
0+in
-situ
SP
02A
0.22
3N
AN
AN
AN
A
1500
0+in
-situ
SP
02B
0.38
0N
AN
AN
AN
A
SP
033
9/4/
2009
9/4/
2009
191
in-s
ituS
P03
A0.
121
NA
NA
NA
NA
337
in-s
ituS
P03
B0.
0619
NA
NA
NA
NA
SP
04U
ST
Exc
avat
ion:
su
rface
soi
l 0-3
' bgs
609/
11/2
009
9/14
/200
97.
8he
adsp
ace
Scr
eeni
ng
Onl
yN
AN
AN
AN
AN
AU
sed
to b
ackf
ill U
ST
exca
vatio
n fro
m
appr
oxim
atel
y 4.
0 to
0.7
feet
bgs
.
SP
0512
9/14
/200
99/
14/2
009
1500
0+he
adsp
ace
SP
05A
114
2550
351
NA
NA
1500
0+he
adsp
ace
SP
05B
94.1
2420
350
NA
NA
Not
es:
1) S
oil P
ID-s
cree
ned
from
mul
tiple
loca
tions
; are
a of
hig
hest
PID
read
ing
was
sam
pled
for l
abor
ator
y an
alys
is. P
ID re
adin
gs w
ere
both
in-s
itu, a
nd b
agge
d he
adsp
ace
read
ings
as
show
n.
2) S
oil f
rom
sto
ckpi
les
SP
02, S
P03
, and
SP
05 w
as s
ent o
ffsite
to E
mer
ald
Ser
vice
s (A
ncho
rage
AK
) and
then
to th
e lo
wer
48
Sta
tes
for d
ispo
sal.
S
oil w
ith P
CB
s >
50 m
g/K
g w
as d
ispo
sed
in a
RC
RA
haz
ardo
us w
aste
land
fill (
Sub
title
C la
ndfil
l).
The
othe
r soi
ls w
ere
disp
osed
in a
non
-haz
ardo
us w
aste
land
fill (
RC
RA
Sub
title
D).
3) P
CB
-126
0 w
as th
e co
ngen
er id
entif
ied.
Dat
a Fl
ags
ND
nond
etec
t, m
etho
d de
tect
ion
limit
is p
rese
nted
in b
rack
ets
to th
e le
ft
Abb
revi
atio
nsA
AC
Ala
ska
Adm
inis
trativ
e C
ode
NA
not a
naly
zed
AD
EC
Ala
ska
Dep
artm
ent o
f Env
ironm
enta
l Con
serv
atio
nP
CB
Pol
ychl
orin
ated
Bip
heny
lbg
sbe
low
gro
und
surfa
ceP
IDph
otoi
oniz
atio
n de
tect
orB
TEX
benz
ene,
tolu
ene,
eth
ylbe
nzen
e, a
nd to
tal x
ylen
esP
QL
Pra
ctic
al Q
uant
itatio
n Li
mit
DR
Odi
esel
rang
e or
gani
csR
CR
AR
esou
rce
Con
serv
atio
n an
d R
ecov
ery
Act
GR
Oga
solin
e ra
nge
orga
nics
RR
Ore
sidu
al ra
nge
orga
nics
MD
Lm
etho
d de
tect
ion
limit
TSC
ATo
xic
Sub
stan
ces
Con
trol A
ctm
g/K
gm
illig
ram
s pe
r kilo
gram
TSD
FTr
eatm
ent,
Sto
rage
and
Dis
posa
l Fac
ility
Stoc
kpile
N
umbe
rO
rigin
of S
oil
App
roxi
mat
e Si
ze o
f St
ockp
ile in
C
ubic
Yar
ds
Exca
vatio
n D
ate
US
T E
xcav
atio
n:so
ils 3
-6.5
' bgs
nex
t to
tank
Dis
posi
tion
of S
oil
Sen
t offs
ite fo
r dis
posa
l at T
SD
F2
Sen
t offs
ite fo
r dis
posa
l at T
SD
F2
Sen
t offs
ite fo
r dis
posa
l at T
SD
F
(TS
CA
regu
late
d w
aste
, P
CB
s>50
mg/
Kg)
2
Ana
lytic
al R
esul
ts (m
g/K
g)PI
D
Rea
ding
(p
pm)
Lab
Sam
ple
Num
ber
Wat
er L
ine
Exc
avat
ion:
Rem
oved
with
vac
uum
truc
k du
ring
final
exc
avat
ion
clea
nup
Sam
ple
Dat
e
Wat
er L
ine
Exc
avat
ion:
Sec
ond
batc
h of
soi
l rem
oved
fro
m m
ain
exca
vatio
n w
ith
vacu
um tr
uck
3-7
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 3-8 November 2009
This page intentionally left blank.
Tabl
e 3-
3. W
ater
Lin
e E
xcav
atio
n S
oil S
ampl
e R
esul
ts, S
epte
mbe
r 4, 2
009
(Pos
t Rem
oval
Act
ion)
MLP
Ope
ratio
ns a
nd D
ispa
tch
Cen
ter
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Con
cFl
agSample Dep
th(feet b
gs)
‐‐--
----
----
Fuel
s ( A
K10
2, A
K10
2, a
nd A
K10
3)
Gasoline Ra
nge Organics
1,40
030
0[1.3]
ND
[0.831
]ND
1.35
J[0.889
]ND
0.74
6J
7.06
=[0.873
]ND
[0.675
]ND
[0.832
]ND
[0.762
]ND
[0.803
]ND
[0.743
]N
D7.06
=3/
100/
10N
oDiesel Range Organics
10,2
5025
027
2=
9.85
J[6.96]
ND
[6.83]
ND
8.17
J2,14
0=
[6.76]
ND
15.3
J[6.68]
ND
37.8
J45
.3=
‐‐--
2,14
0=
7/10
0/10
No
Residu
al Range Organics
10,0
0010
,000
175
.2J
37.8
=[6.96]
ND
[6.83]
ND
[6.8]
ND
78.4
J9.55
J12
0=
44.3
=34
7=
7.4
J‐‐
--34
7=
8/10
0/10
No
Ben
zene
, Eth
ylbe
nzen
e, T
olue
ne, a
nd X
ylen
es (S
W80
21B
)Be
nzen
e11
0.02
5[0.006
94]
ND
[0.004
43]
ND
[0.005
47]
ND
[0.004
74]
ND
0.00
608
J[0.003
08]
ND
[0.004
65]
ND
[0.003
6]ND
[0.004
44]
ND
[0.004
07]
ND
[0.004
28]
ND
[0.003
96]
ND
0.00
608
J1/
100/
10N
oEthylben
zene
110
6.9
[0.026
]ND
[0.016
6]ND
[0.020
5]ND
[0.017
8]ND
[0.012
4]ND
0.01
25J
[0.017
5]ND
[0.013
5]ND
[0.016
6]ND
[0.015
2]ND
[0.016
1]ND
[0.014
9]N
D0.01
25J
1/10
0/10
No
Toluen
e22
06.5
[0.026
]ND
[0.016
6]ND
[0.020
5]ND
[0.017
8]ND
[0.012
4]ND
[0.011
5]ND
[0.017
5]ND
[0.013
5]ND
[0.016
6]ND
[0.015
2]ND
[0.016
1]ND
[0.014
9]N
D[0.026
]ND
0/10
0/10
No
o‐Xylene
--‐‐
[0.026
]ND
[0.016
6]ND
[0.020
5]ND
[0.017
8]ND
0.01
92J
0.15
6=
[0.017
5]ND
[0.013
5]ND
[0.016
6]ND
[0.015
2]ND
[0.016
1]ND
[0.014
9]N
D0.15
6=
2/10
0/10
No
P & M
‐Xylen
e--
--[0.026
]ND
[0.016
6]ND
[0.020
5]ND
[0.017
8]ND
0.02
18J
0.2
=[0.017
5]ND
[0.013
5]ND
[0.016
6]ND
[0.015
2]ND
[0.016
1]ND
[0.014
9]N
D0.2
=2/
100/
10N
oTo
tal Xylen
es63
63[0.026
]ND
[0.016
6]ND
[0.020
5]ND
[0.017
8]ND
0.04
1J
0.35
6=
[0.017
5]ND
[0.013
5]ND
[0.016
6]ND
[0.015
2]ND
[0.016
1]ND
[0.014
9]N
D0.35
6=
2/10
0/10
No
1,1,1,2‐Tetrachloroe
thane
----
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
1,1,1‐Trichloroe
thane
360
0.82
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
1,1,2,2‐Tetrachloroe
thane
5.5
0.01
7--
----
----
----
--[0.012
4]ND
[0.011
5]ND
----
----
----
----
----
----
[0.012
4]ND
0/2
0/2
No
1,1,2‐Trichloroe
thane
110.01
8--
----
----
----
--[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
1,1‐Dichloroe
thane
900
25--
----
----
----
--[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
1,1‐Dichloroe
then
e0.85
0.03
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
1,1‐Dichlorop
rope
ne--
----
----
----
----
--[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
1,2,3‐Trichlorob
enzene
----
----
----
----
----
[0.012
4]ND
[0.011
5]ND
----
----
----
----
----
----
[0.012
4]ND
0/2
0/2
No
1,2,3‐Trichlorop
ropane
0.17
0.00
053
----
----
----
----
[0.012
4]ND
[0.011
5]ND
----
----
----
----
----
----
[0.012
4]ND
0/2
0/2
No
1,2,4‐Trichlorob
enzene
410.85
----
----
----
----
[0.012
4]ND
[0.011
5]ND
----
----
----
----
----
----
[0.012
4]ND
0/2
0/2
No
1,2,4‐Trim
ethylben
zene
4923
----
----
----
----
[0.006
47]
ND
0.78
3=
----
----
----
----
----
----
0.78
3=
1/2
0/2
No
1,2‐Dibromo‐3‐chloroprop
ane
----
----
----
----
----
[0.025
7]ND
[0.023
8]ND
----
----
----
----
----
----
[0.025
7]ND
0/2
0/2
No
1,2‐Dibromoe
thane
0.6
0.00
016
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
1,2‐Dichlorob
enzene
455.1
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
1,2‐Dichloroe
thane
4.8
0.01
6--
----
----
----
--[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
1,2‐Dichlorop
ropane
5.3
0.01
8--
----
----
----
--[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
1,3,5‐Trim
ethylben
zene
4223
----
----
----
----
[0.006
47]
ND
0.21
1=
----
----
----
----
----
----
0.21
1=
1/2
0/2
No
1,3‐Dichlorob
enzene
6928
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
1,3‐Dichlorop
ropane
----
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
1,4‐Dichlorob
enzene
300.64
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
2,2‐Dichlorop
ropane
----
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
2‐Bu
tano
ne (M
EK)
23,300
59--
----
----
----
--[0.064
7]ND
[0.06]
ND
----
----
----
----
----
----
[0.064
7]ND
0/2
0/2
No
2‐Ch
lorotoluen
e--
----
----
----
----
--[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
2‐Hexanon
e--
----
----
----
----
--[0.064
7]ND
[0.06]
ND
----
----
----
----
----
----
[0.064
7]ND
0/2
0/2
No
4‐Ch
lorotoluen
e--
----
----
----
----
--[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
4‐Isop
ropylto
luen
e--
----
----
----
----
--[0.006
47]
ND
0.11
4=
----
----
----
----
----
----
0.11
4=
1/2
0/2
No
4‐Methyl‐2
‐pen
tano
ne (M
IBK)
8.1
----
----
----
----
[0.064
7]ND
[0.06]
ND
----
----
----
----
----
----
[0.064
7]ND
0/2
0/2
No
Benzen
e0.02
5--
----
----
----
--[0.004
15]
ND
[0.003
84]
ND
----
----
----
----
----
----
[0.004
15]
ND
0/2
0/2
No
Brom
oben
zene
----
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
Brom
ochlorom
ethane
----
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
Brom
odichlorom
ethane
100.04
4--
----
----
----
--[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
Brom
oform
420
0.34
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
Brom
omethane
140.16
----
----
----
----
[0.051
4]ND
[0.047
7]ND
----
----
----
----
----
----
[0.051
4]ND
0/2
0/2
No
Carbon
disulfid
e25
012
----
----
----
----
[0.025
7]ND
[0.023
8]ND
----
----
----
----
----
----
[0.025
7]ND
0/2
0/2
No
Carbon
tetrachloride
3.1
0.02
3--
----
----
----
--[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
Chlorobe
nzen
e20
00.63
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
Chloroethane
2358
0--
----
----
----
--[0.051
4]ND
[0.047
7]ND
----
----
----
----
----
----
[0.051
4]ND
0/2
0/2
No
Chloroform
3.2
0.46
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
Chloromethane
250.21
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
cis‐1,2‐Dichloroe
then
e13
00.24
----
----
----
----
[0.006
47]
ND
0.04
31=
----
----
----
----
----
----
0.04
31=
1/2
0/2
No
cis‐1,3‐Dichlorop
rope
ne27
0.03
3--
----
----
----
--[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
Dibromochlorom
ethane
140.03
2--
----
----
----
--[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
Dibromom
ethane
370
1.1
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
Dichlorod
ifluo
romethane
380
140
----
----
----
----
[0.012
4]ND
[0.011
5]ND
----
----
----
----
----
----
[0.012
4]ND
0/2
0/2
No
Ethylben
zene
110
6.9
----
----
----
----
[0.006
47]
ND
0.01
5J
----
----
----
----
----
----
0.01
5J
1/2
0/2
No
Hexachlorob
utadiene
3.8
0.12
----
----
----
----
[0.012
4]ND
[0.011
5]ND
----
----
----
----
----
----
[0.012
4]ND
0/2
0/2
No
Freq
uenc
y A
bove
Pr
imar
y Sc
reen
ing
Crit
eria
5,6
Con
tam
inan
t of
Con
cern
(C
OC
)7
ES05
‐2.5
04‐Sep
‐09
1094
6980
11
2.5
ES06
‐204
‐Sep
‐09
1094
6980
12
ES07
‐2.5
04‐Sep
‐09
1094
6980
13
‐‐
Sam
ple
Loca
tions
3
Max
imum
C
once
ntra
tion4
Freq
uenc
y of
D
etec
tion5
2.5
2
ES06
‐5.5
04‐Sep
‐09
1094
6980
06
ES07
‐6.5
04‐Sep
‐09
1094
6980
08
6.5
ES03
‐2.5
04‐Sep
‐09
1094
6980
09
ES04
‐2.5
04‐Sep
‐09
1094
6980
10
2.5
2.5
Trip Blank
04‐Sep
‐09
1094
6980
19
ES03
‐704
‐Sep
‐09
1094
6980
01
ES04
‐6.5
04‐Sep
‐09
1094
6980
02
76.5
6
Prim
ary
ES05
‐604
‐Sep
‐09
1094
6980
03
65.5
Replicate
ES09
5‐6
04‐Sep
‐09
1094
6980
07
Vola
tile
Org
anic
Com
poun
ds (S
W82
60B
)
Met
hod
Two
(und
er 4
0-in
ch
zone
)1
Met
hod
Two
Mig
ratio
n to
G
roun
dwat
er2
Compo
und:
milligrams pe
r kilogram
(mg/Kg
)
3-9
UST
Rel
ease
Inve
stig
atio
n Re
port
M
L&P
Ope
ratio
ns a
nd D
ispa
tch
Cen
ter
Prep
ared
for M
unic
ipal
Lig
ht &
Pow
er
1-
7
N
ovem
ber 2
009
This
pag
e in
tent
iona
lly le
ft bl
ank.
Tabl
e 3-
3. W
ater
Lin
e E
xcav
atio
n S
oil S
ampl
e R
esul
ts, S
epte
mbe
r 4, 2
009
(Pos
t Rem
oval
Act
ion)
MLP
Ope
ratio
ns a
nd D
ispa
tch
Cen
ter
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Conc
Flag
Con
cFl
agSample Dep
th(feet b
gs)
‐‐--
----
----
Freq
uenc
y A
bove
Pr
imar
y Sc
reen
ing
Crit
eria
5,6
Con
tam
inan
t of
Con
cern
(C
OC
)7
ES05
‐2.5
04‐Sep
‐09
1094
6980
11
2.5
ES06
‐204
‐Sep
‐09
1094
6980
12
ES07
‐2.5
04‐Sep
‐09
1094
6980
13
‐‐
Sam
ple
Loca
tions
3
Max
imum
C
once
ntra
tion4
Freq
uenc
y of
D
etec
tion5
2.5
2
ES06
‐5.5
04‐Sep
‐09
1094
6980
06
ES07
‐6.5
04‐Sep
‐09
1094
6980
08
6.5
ES03
‐2.5
04‐Sep
‐09
1094
6980
09
ES04
‐2.5
04‐Sep
‐09
1094
6980
10
2.5
2.5
Trip Blank
04‐Sep
‐09
1094
6980
19
ES03
‐704
‐Sep
‐09
1094
6980
01
ES04
‐6.5
04‐Sep
‐09
1094
6980
02
76.5
6
Prim
ary
ES05
‐604
‐Sep
‐09
1094
6980
03
65.5
Replicate
ES09
5‐6
04‐Sep
‐09
1094
6980
07
Met
hod
Two
(und
er 4
0-in
ch
zone
)1
Met
hod
Two
Mig
ratio
n to
G
roun
dwat
er2
Compo
und:
milligrams pe
r kilogram
(mg/Kg
)
Isop
ropylben
zene
(Cum
ene)
6251
----
----
----
----
[0.006
47]
ND
0.02
56=
----
----
----
----
----
----
0.02
56=
1/2
0/2
No
Methylene
chloride
160
0.01
6--
----
----
----
--[0.025
7]ND
[0.023
8]ND
----
----
----
----
----
----
[0.025
7]ND
0/2
0/2
No
Methyl‐t‐butyl ether
290
1.3
----
----
----
----
[0.009
96]
ND
[0.009
23]
ND
----
----
----
----
----
----
[0.009
96]
ND
0/2
0/2
No
Naphthalene
2820
----
----
----
----
0.02
09J
3.9
=--
----
----
----
----
----
--3.9
=2/
20/
2N
on‐Bu
tylben
zene
4215
----
----
----
----
0.00
726
J0.17
8=
----
----
----
----
----
----
0.17
8=
2/2
0/2
No
n‐Prop
ylbe
nzen
e42
15--
----
----
----
--0.01
04J
0.03
88=
----
----
----
----
----
----
0.03
88=
2/2
0/2
No
o‐Xylene
----
----
----
----
----
[0.012
4]ND
0.12
4=
----
----
----
----
----
----
0.12
4=
1/2
0/2
No
P & M
‐Xylen
e--
----
----
----
----
--[0.012
4]ND
0.22
2=
----
----
----
----
----
----
0.22
2=
1/2
0/2
No
sec‐Bu
tylben
zene
4112
----
----
----
----
[0.006
47]
ND
0.07
27=
----
----
----
----
----
----
0.07
27=
1/2
0/2
No
Styren
e20
00.96
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
tert‐Butylbe
nzen
e70
12--
----
----
----
--[0.006
47]
ND
0.00
673
J--
----
----
----
----
----
--0.00
673
J1/
20/
2N
oTetrachloroe
then
e10
0.02
4--
----
----
----
--[0.006
47]
ND
0.03
09=
----
----
----
----
----
----
0.03
09=
1/2
0/2
No
Toluen
e22
06.5
----
----
----
----
[0.012
4]ND
[0.011
5]ND
----
----
----
----
----
----
[0.012
4]ND
0/2
0/2
No
trans‐1,2‐Dichloroe
then
e16
00.37
----
----
----
----
[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
trans‐1,3‐Dichlorop
rope
ne27
0.03
3--
----
----
----
--[0.006
47]
ND
[0.006
]ND
----
----
----
----
----
----
[0.006
47]
ND
0/2
0/2
No
Trichloroe
then
e0.57
0.02
----
----
----
----
[0.006
47]
ND
0.07
38=
----
----
----
----
----
----
0.07
38=
1/2
0/2
No
Trichlorofluorom
ethane
990
86--
----
----
----
--[0.012
4]ND
[0.011
5]ND
----
----
----
----
----
----
[0.012
4]ND
0/2
0/2
No
Vinyl chloride
4.3
0.00
85--
----
----
----
--[0.009
96]
ND
[0.009
23]
ND
----
----
----
----
----
----
[0.009
96]
ND
0/2
0/2
No
Xylene
s (total)
6363
----
----
----
----
[0.024
9]ND
0.34
6=
----
----
----
----
----
----
0.34
6=
1/2
0/2
No
Aroclor‐101
6--
--[0.016
8]ND
[0.016
3]ND
[0.016
8]ND
[0.016
5]ND
[0.016
5]ND
[0.016
]ND
[0.016
3]ND
[0.016
]ND
[0.016
2]ND
[0.016
]ND
[0.015
3]ND
‐‐--
[0.016
8]ND
0/10
0/10
No
Aroclor‐122
1--
--[0.016
8]ND
[0.016
3]ND
[0.016
8]ND
[0.016
5]ND
[0.016
5]ND
[0.016
]ND
[0.016
3]ND
[0.016
]ND
[0.016
2]ND
[0.016
]ND
[0.015
3]ND
‐‐--
[0.016
8]ND
0/10
0/10
No
Aroclor‐123
2--
--[0.016
8]ND
[0.016
3]ND
[0.016
8]ND
[0.016
5]ND
[0.016
5]ND
[0.016
]ND
[0.016
3]ND
[0.016
]ND
[0.016
2]ND
[0.016
]ND
[0.015
3]ND
‐‐--
[0.016
8]ND
0/10
0/10
No
Aroclor‐124
2--
--[0.016
8]ND
[0.016
3]ND
[0.016
8]ND
[0.016
5]ND
[0.016
5]ND
[0.016
]ND
[0.016
3]ND
[0.016
]ND
[0.016
2]ND
[0.016
]ND
[0.015
3]ND
‐‐--
[0.016
8]ND
0/10
0/10
No
Aroclor‐124
8--
--[0.016
8]ND
[0.016
3]ND
[0.016
8]ND
[0.016
5]ND
[0.016
5]ND
[0.016
]ND
[0.016
3]ND
[0.016
]ND
[0.016
2]ND
[0.016
]ND
[0.015
3]ND
‐‐--
[0.016
8]ND
0/10
0/10
No
Aroclor‐125
4--
--[0.016
8]ND
[0.016
3]ND
[0.016
8]ND
[0.016
5]ND
[0.016
5]ND
[0.016
]ND
[0.016
3]ND
[0.016
]ND
[0.016
2]ND
[0.016
]ND
[0.015
3]ND
‐‐--
[0.016
8]ND
0/10
0/10
No
Aroclor‐126
0--
--0.28
2=
[0.016
3]ND
[0.016
8]ND
[0.016
5]ND
[0.016
5]ND
0.42
7=
[0.016
3]ND
0.49
2=
0.06
96=
0.44
5=
[0.015
3]ND
‐‐--
0.49
2=
5/10
0/10
No
Total PCB
s1.
01.
00.28
2=
[0.016
3]ND
[0.016
8]ND
[0.016
5]ND
[0.016
5]ND
0.42
7=
[0.016
3]ND
0.49
2=
0.06
96=
0.44
5=
[0.015
3]ND
‐‐--
0.49
2=
5/10
0/10
No
Perc
ent S
olid
s (S
M25
40G
)To
tal Solids
----
89=
90.1
=88
.9=
90.4
=90
.9=
92.6
=90
.7=
93.2
=91
.9=
92.2
=96
.8=
‐‐--
----
----
--N
otes
:1
- Prim
ary
Scr
eeni
ng C
riter
ia:
the
clea
nup
leve
l cor
resp
onds
to th
e lo
wes
t val
ue fo
r dire
ct c
onta
ct o
r inh
alat
ion
of s
oil a
s lis
ted
in 1
8 A
AC
75.
341,
Tab
les
B1
and
B2,
(Met
hod
Two
clea
nup
leve
ls) f
or th
e un
der 4
0 in
ch z
one
(Oct
ober
9, 2
008)
. 2
- Sec
onda
ry S
cree
ning
Crit
eria
: th
e va
lue
corr
espo
nds
to th
e va
lue
liste
d in
18
AA
C 7
5.34
1, T
able
s B
1 an
d B
2, M
igra
tion
to G
roun
dwat
er (O
ctob
er 9
, 200
8).
3 - T
he fi
eld
sam
ple
iden
tific
atio
n nu
mbe
r, da
te c
olle
cted
and
labo
rato
ry s
ampl
e id
entif
icat
ion
num
ber a
re p
rovi
ded.
The
sam
ple
dept
h in
feet
is li
sted
afte
r the
hyp
hen
at th
e en
d of
the
sam
ple
iden
tific
atio
n nu
mbe
r.4
- The
max
imum
con
cent
ratio
n of
a d
etec
ted
anal
yte
is s
how
n. I
f an
anal
yte
was
not
det
ecte
d, th
en th
e hi
ghes
t MD
L is
sho
wn.
Trip
bla
nks
are
not i
nclu
ded.
5 - A
par
ent a
nd d
uplic
ate
sam
ple
are
coun
ted
as o
ne s
ampl
e. T
he h
ighe
r of t
he tw
o va
lues
are
use
d fo
r the
pur
pose
of c
ount
ing
dete
ctio
ns a
nd e
xcee
danc
es.
Trip
bla
nks
are
not i
nclu
ded.
6 - S
cree
ning
crit
eria
val
ues
are
from
18
AA
C 7
5.34
1 M
etho
d Tw
o U
nder
40-
inch
Zon
e. T
otal
val
ues
are
the
sum
mat
ion
of d
etec
ted
com
poun
ds o
nly.
If a
ll va
lues
are
non
dete
ctab
le, t
he h
ighe
st M
DL
is s
how
n.7
- A c
ompo
und
is c
onsi
dere
d a
CO
C if
it e
xcee
ds th
e pr
imar
y sc
reen
ing
crite
ria.
8 - T
otal
val
ues
wer
e th
e su
mm
atio
n of
det
ecte
d co
mpo
unds
onl
y. I
f com
poun
ds w
ere
not d
etec
ted,
then
the
high
est M
DL
was
list
ed.
Dat
a Fl
ags
ND
nond
etec
t, m
etho
d de
tect
ion
limit
is p
rese
nted
in b
rack
ets
to th
e le
ftJ
estim
ated
val
ue, a
"+" o
r "-"
indi
cate
s a
posi
tive
or n
egat
ive
bias
Fre
porte
d va
lue
was
bet
wee
n th
e la
bora
tory
MD
L an
d P
QL
=A
det
ecte
d co
mpo
und
(con
cent
ratio
n lis
ted
in c
olum
n to
the
left)
Bco
mpo
und
was
det
ecte
d in
the
met
hod
blan
k or
trip
bla
nk
Abb
revi
atio
ns--
Not
app
licab
le o
r scr
eeni
ng c
riter
ia d
oes
not e
xist
for t
his
com
poun
dm
g/K
gm
illig
ram
s pe
r kilo
gram
AA
CA
lask
a A
dmin
istra
tive
Cod
eP
CB
Pol
ychl
orin
ated
Bip
heny
lbg
sbe
low
gro
und
surfa
ceP
QL
Pra
ctic
al Q
uant
itatio
n Li
mit
CO
CC
onta
min
ant o
f Con
cern
MD
LM
etho
d D
etec
tion
Lim
it
bold
and
sha
ded
- val
ue e
xcee
ds p
rimar
y sc
reen
ing
crite
ria (M
etho
d Tw
o C
lean
up L
evel
s)sh
aded
- va
lue
exce
eds
Met
hod
Two
mig
ratio
n to
gro
undw
ater
cle
anup
leve
ls.
Poly
chlo
rinat
ed B
iphe
nyls
(SW
8082
)
3-9
UST
Rel
ease
Inve
stig
atio
n Re
port
M
L&P
Ope
ratio
ns a
nd D
ispa
tch
Cen
ter
Prep
ared
for M
unic
ipal
Lig
ht &
Pow
er
1-
7
N
ovem
ber 2
009
This
pag
e in
tent
iona
lly le
ft bl
ank.
Tabl
e 3-
4. U
ST
Exc
avat
ion
Soi
l Sam
ple
Res
ults
, Sep
tem
ber 1
4, 2
009
(Pos
t Rem
oval
Act
ion)
MLP
Ope
ratio
ns a
nd D
ispa
tch
Cen
ter
Con
cFl
agC
onc
Flag
Con
cFl
agC
onc
Flag
Con
cFl
agC
onc
Flag
Con
cFl
agC
onc
Fla g
Con
cFl
agC
onc
Flag
Con
cFl
agC
onc
Flag
Con
cFl
agC
onc
Flag
Con
cFl
agC
onc
Flag
Sam
ple
Dep
th (f
eet b
gs)
----
--Fu
els
( AK
102,
AK
102,
and
AK
103)
Gas
olin
e R
ange
Org
anic
s1,
400
300
----
----
[0.7
67]
ND
0.69
2F
----
----
----
----
8.46
J1.
68F,
J10
.4=
----
----
----
[2.5
4]N
D10
.4=
3/4
0/4
No
Die
sel R
ange
Org
anic
s10
,250
250
946
=64
6=
93.5
=13
.1F
12,8
00=
17,7
00=
127
=21
6=
7,74
0=
8,50
0=
183
=41
9J
250
J26
7=
----
17,7
00=
12/1
22/
12Y
esR
esid
ual R
ange
Org
anic
s10
,000
11,0
0045
7=
103
=37
.8=
7.59
F1,
570
=5,
300
=27
8=
654
=60
7=
642
=36
7=
1,24
0J
596
J2,
550
=--
--5,
300
=12
/12
0/12
No
Ben
zene
110.
025
----
----
[0.0
0409
]N
D[0
.003
63]
ND
----
----
----
----
[0.0
057]
ND
[0.0
0494
]N
D[0
.004
64]
ND
----
----
----
[0.0
0406
]N
D[0
.005
7]N
D0/
40/
4N
oE
thyl
benz
ene
110
6.9
----
----
[0.0
153]
ND
[0.0
136]
ND
----
----
----
----
[0.0
214]
ND
[0.0
185]
ND
[0.0
174]
ND
----
----
----
[0.0
152]
ND
[0.0
214]
ND
0/4
0/4
No
Tolu
ene
220
6.5
----
----
0.02
97F
[0.0
136]
ND
----
----
----
----
[0.0
214]
ND
[0.0
185]
ND
[0.0
174]
ND
----
----
----
[0.0
152]
ND
0.02
97F
1/4
0/4
No
o-X
ylen
e--
----
----
--[0
.015
3]N
D[0
.013
6]N
D--
----
----
----
--0.
157
=0.
027
F0.
109
=--
----
----
--[0
.015
2]N
D0.
157
=2/
40/
4N
oP
& M
-Xyl
ene
----
----
----
[0.0
153]
ND
[0.0
136]
ND
----
----
----
----
[0.0
214]
ND
[0.0
185]
ND
0.03
58F
----
----
----
[0.0
152]
ND
0.03
58F
1/4
0/4
No
Tota
l Xyl
ene
6363
----
----
[0.0
153]
ND
[0.0
136]
ND
----
----
----
----
0.15
7=
0.02
7F
0.14
5F
----
----
----
[0.0
152]
ND
0.15
7=
2/4
0/4
No
1-M
ethy
lnap
htha
lene
280
6.2
----
----
0.02
01=
----
7.42
=--
----
----
--9.
56=
9.79
=--
----
----
----
----
--9.
79=
3/3
0/3
No
2-M
ethy
lnap
htha
lene
280
6.1
----
----
0.02
66=
----
9.66
=--
----
----
--[0
.016
4]N
D[0
.016
7]N
D--
----
----
----
----
--9.
66=
2/3
0/3
No
Ace
naph
then
e2,
800
180
----
----
[0.0
0171
]N
D--
--0.
427
=--
----
----
--0.
678
=0.
511
=--
----
----
----
----
--0.
678
=2/
30/
3N
oA
cena
phth
ylen
e2,
800
180
----
----
[0.0
0171
]N
D--
--[0
.016
7]N
D--
----
----
--[0
.016
4]N
D[0
.016
7]N
D--
----
----
----
----
--[0
.016
7]N
D0/
30/
3N
oA
nthr
acen
e20
,600
3,00
0--
----
--[0
.001
71]
ND
----
0.57
4=
----
----
----
0.29
2=
0.26
3=
----
----
----
----
----
0.57
4=
2/3
0/3
No
Ben
zo(a
)Ant
hrac
ene
4.9
3.6
----
----
[0.0
0171
]N
D--
--0.
0674
=--
----
----
--0.
051
F0.
0558
=--
----
----
----
----
--0.
0674
=2/
30/
3N
oB
enzo
[a]p
yren
e0.
492.
1--
----
--[0
.001
71]
ND
----
0.08
44=
----
----
----
0.05
56=
0.06
07=
----
----
----
----
----
0.08
44=
2/3
0/3
No
Ben
zo[b
]Flu
oran
then
e4.
912
----
----
0.00
437
F--
--0.
052
F--
----
----
--0.
0314
F0.
0329
F--
----
----
----
----
--0.
052
F3/
30/
3N
oB
enzo
[g,h
,i]pe
ryle
ne1,
400
38,7
00--
----
--[0
.001
71]
ND
----
0.05
37F
----
----
----
0.04
63F
0.04
15F
----
----
----
----
----
0.05
37F
2/3
0/3
No
Ben
zo[k
]fluo
rant
hene
4912
0--
----
--[0
.001
71]
ND
----
[0.0
167]
ND
----
----
----
[0.0
164]
ND
[0.0
167]
ND
----
----
----
----
----
[0.0
167]
ND
0/3
0/3
No
Chr
ysen
e49
036
0--
----
--[0
.001
71]
ND
----
0.11
8=
----
----
----
0.08
46=
0.09
77=
----
----
----
----
----
0.11
8=
2/3
0/3
No
Dib
enzo
[a,h
]ant
hrac
ene
0.49
4--
----
--[0
.001
71]
ND
----
0.01
77F
----
----
----
[0.0
164]
ND
[0.0
167]
ND
----
----
----
----
----
0.01
77F
1/3
0/3
No
Fluo
rant
hene
1,90
01,
400
----
----
[0.0
0171
]N
D--
--[0
.016
7]N
D--
----
----
--0.
0581
=0.
0468
F--
----
----
----
----
--0.
0581
=2/
30/
3N
oFl
uore
ne2,
300
220
----
----
0.00
312
F--
--2.
11=
----
----
----
1.84
=1.
77=
----
----
----
----
----
2.11
=3/
30/
3N
oIn
deno
[1,2
,3-c
,d] p
yren
e4.
941
----
----
[0.0
0171
]N
D--
--0.
0269
F--
----
----
--[0
.016
4]N
D[0
.016
7]N
D--
----
----
----
----
--0.
0269
F1/
30/
3N
oN
apht
hale
ne28
20--
----
--0.
0072
2=
----
1.99
=--
----
----
--[0
.016
4]N
D[0
.016
7]N
D--
----
----
----
----
--1.
99=
2/3
0/3
No
Phe
nant
hren
e20
,600
3,00
0--
----
--[0
.001
71]
ND
----
0.62
8=
----
----
----
1.74
=1.
8=
----
----
----
----
----
1.8
=2/
30/
3N
oP
yren
e1,
400
1,00
0--
----
--[0
.001
71]
ND
----
0.16
6=
----
----
----
0.18
2=
0.20
4=
----
----
----
----
----
0.20
4=
2/3
0/3
No
Aro
clor
-101
6--
--[0
.016
1]N
D[0
.017
1]N
D[0
.016
8]N
D[0
.015
6]N
D[0
.016
7]N
D[0
.016
2]N
D[0
.015
7]N
D[0
.015
8]N
D[0
.016
5]N
D[0
.167
]N
D[0
.16]
ND
[0.1
6]N
D[0
.079
2]N
D[0
.158
]N
D--
--[0
.167
]N
D0/
120/
12N
oA
rocl
or-1
221
----
[0.0
161]
ND
[0.0
171]
ND
[0.0
168]
ND
[0.0
156]
ND
[0.0
167]
ND
[0.0
162]
ND
[0.0
157]
ND
[0.0
158]
ND
[0.0
165]
ND
[0.1
67]
ND
[0.1
6]N
D[0
.16]
ND
[0.0
792]
ND
[0.1
58]
ND
----
[0.1
67]
ND
0/12
0/12
No
Aro
clor
-123
2--
--[0
.016
1]N
D[0
.017
1]N
D[0
.016
8]N
D[0
.015
6]N
D[0
.016
7]N
D[0
.016
2]N
D[0
.015
7]N
D[0
.015
8]N
D[0
.016
5]N
D[0
.167
]N
D[0
.16]
ND
[0.1
6]N
D[0
.079
2]N
D[0
.158
]N
D--
--[0
.167
]N
D0/
120/
12N
oA
rocl
or-1
242
----
[0.0
161]
ND
[0.0
171]
ND
[0.0
168]
ND
[0.0
156]
ND
[0.0
167]
ND
[0.0
162]
ND
[0.0
157]
ND
[0.0
158]
ND
[0.0
165]
ND
[0.1
67]
ND
[0.1
6]N
D[0
.16]
ND
[0.0
792]
ND
[0.1
58]
ND
----
[0.1
67]
ND
0/12
0/12
No
Aro
clor
-124
8--
--[0
.016
1]N
D[0
.017
1]N
D[0
.016
8]N
D[0
.015
6]N
D[0
.016
7]N
D[0
.016
2]N
D[0
.015
7]N
D[0
.015
8]N
D[0
.016
5]N
D[0
.167
]N
D[0
.16]
ND
[0.1
6]N
D[0
.079
2]N
D[0
.158
]N
D--
--[0
.167
]N
D0/
120/
12N
oA
rocl
or-1
254
----
[0.0
161]
ND
[0.0
171]
ND
[0.0
168]
ND
[0.0
156]
ND
[0.0
167]
ND
[0.0
162]
ND
[0.0
157]
ND
[0.0
158]
ND
[0.0
165]
ND
[0.1
67]
ND
[0.1
6]N
D[0
.16]
ND
[0.0
792]
ND
[0.1
58]
ND
----
[0.1
67]
ND
0/12
0/12
No
Aro
clor
-126
0--
--0.
195
=0.
132
=96
.9=
10.1
=24
.8=
89.1
=0.
153
=11
2=
0.66
1=
0.67
=3.
36=
30.8
=24
.7=
45=
----
112
=12
/12
8/12
Yes
Tota
l PC
Bs8
1.0
1.0
0.19
5=
0.13
2=
96.9
=10
.1=
24.8
=89
.1=
0.15
3=
112
=0.
661
=0.
67=
3.36
=30
.8=
24.7
=45
=--
--11
2=
12/1
28/
12Y
esPe
rcen
t Sol
ids
(SM
2540
G)
Tota
l Sol
ids
--92
.4=
86.2
=87
.5=
95.3
=89
.6=
91.3
=93
.5=
93.9
=89
.9=
88.8
=92
.9=
93.8
=93
.4=
94.1
=--
----
----
Not
es:
1 - P
rimar
y S
cree
ning
Crit
eria
: th
e cl
eanu
p le
vel c
orre
spon
ds to
the
low
est v
alue
for d
irect
con
tact
or i
nhal
atio
n of
soi
l as
liste
d in
18
AA
C 7
5.34
1, T
able
s B
1 an
d B
2, (M
etho
d Tw
o cl
eanu
p le
vels
) for
the
unde
r 40
inch
zon
e (O
ctob
er 9
, 200
8).
3 - T
he fi
eld
sam
ple
iden
tific
atio
n nu
mbe
r, da
te c
olle
cted
and
labo
rato
ry s
ampl
e id
entif
icat
ion
num
ber a
re p
rovi
ded.
The
sam
ple
dept
h in
feet
is li
sted
afte
r the
hyp
hen
at th
e en
d of
the
sam
ple
iden
tific
atio
n nu
mbe
r.
5 - A
par
ent a
nd d
uplic
ate
sam
ple
are
coun
ted
as o
ne s
ampl
e. T
he h
ighe
r of t
he tw
o va
lues
are
use
d fo
r the
pur
pose
of c
ount
ing
dete
ctio
ns a
nd e
xcee
danc
es.
Trip
bla
nks
are
not i
nclu
ded.
6 - S
cree
ning
crit
eria
val
ues
are
from
18
AA
C 7
5.34
1 M
etho
d Tw
o U
nder
40-
inch
Zon
e. T
otal
val
ues
are
the
sum
mat
ion
of d
etec
ted
com
poun
ds o
nly.
If a
ll va
lues
are
non
dete
ctab
le, t
he h
ighe
st M
DL
is s
how
n.
Dat
a Fl
ags
ND
nond
etec
t, m
etho
d de
tect
ion
limit
is p
rese
nted
in b
rack
ets
to th
e le
ftJ
estim
ated
val
ue, a
"+" o
r "-"
indi
cate
s a
posi
tive
or n
egat
ive
bias
Fre
porte
d va
lue
was
bet
wee
n th
e la
bora
tory
MD
L an
d P
QL
=A
det
ecte
d co
mpo
und
(con
cent
ratio
n lis
ted
in c
olum
n to
the
left)
Bco
mpo
und
was
det
ecte
d in
the
met
hod
blan
k or
trip
bla
nk
Abb
revi
atio
ns--
Not
app
licab
le o
r scr
eeni
ng c
riter
ia d
oes
not e
xist
for t
his
com
poun
dm
g/K
gm
illig
ram
s pe
r kilo
gram
AA
CA
lask
a A
dmin
istra
tive
Cod
eP
CB
Pol
ychl
orin
ated
Bip
heny
lbg
sbe
low
gro
und
surfa
ceP
QL
Pra
ctic
al Q
uant
itatio
n Li
mit
CO
CC
onta
min
ant o
f Con
cern
SIM
Sel
ectiv
e Io
n M
onito
ring
MD
LM
etho
d D
etec
tion
Lim
it
bold
and
sha
ded
- val
ue e
xcee
ds p
rimar
y sc
reen
ing
crite
ria (M
etho
d Tw
o C
lean
up L
evel
s)sh
aded
- va
lue
exce
eds
Met
hod
Two
mig
ratio
n to
gro
undw
ater
cle
anup
leve
ls.
Rep
licat
eTE
W-9
.814
-Sep
-09
1094
8730
10
--
Trip
Bla
nk
--6.
04.
01.
50.
51.
5--
TEW
-4.0
14-S
ep-0
910
9487
3011
4.0
6.0
6.5
4.0
1.5
0.5
6.0
TES
-6.5
14-S
ep-0
910
9487
3005
TES
-4.0
14-S
ep-0
910
9487
3006
TES
-1.5
14-S
ep-0
910
9487
3007
TES
-0.5
14-S
ep-0
910
9487
3008
Prim
ary
TEW
-6.0
14-S
ep-0
910
9487
3009
6.5
TEN
-6.0
14-S
ep-0
910
9487
3002
TEE
-6.5
14-S
ep-0
910
9487
3003
TEE
-4.0
14-S
ep-0
910
9487
3004
4.0
Con
tam
inan
t of
Con
cern
(C
OC
)7
Com
poun
d m
illig
ram
s pe
r kilo
gram
(m
g/K
g)
Met
hod
Two
(und
er 4
0-in
ch
zone
)1
Met
hod
Two
Mig
ratio
n to
G
roun
dwat
er2
Sam
ple
Loca
tions
3
Max
imum
C
once
ntra
tion4
Freq
uenc
y of
Det
ectio
n5
Rep
licat
eTE
W-9
.914
-Sep
-09
1094
8730
13
TEW
-0.5
14-S
ep-0
910
9487
3014
Trip
Bla
nk14
-Sep
-09
1094
8730
17
4 - T
he m
axim
um c
once
ntra
tion
of a
det
ecte
d an
alyt
e is
sho
wn.
If a
n an
alyt
e w
as n
ot d
etec
ted,
then
the
high
est M
DL
is s
how
n. T
rip b
lank
s ar
e no
t inc
lude
d.
7 - A
com
poun
d is
con
side
red
a C
OC
if it
exc
eeds
the
prim
ary
scre
enin
g cr
iteria
.8
- Tot
al v
alue
s w
ere
the
sum
mat
ion
of d
etec
ted
com
poun
ds o
nly.
If c
ompo
unds
wer
e no
t det
ecte
d, th
en th
e hi
ghes
t MD
L w
as li
sted
.
Freq
uenc
y A
bove
Pr
imar
y Sc
reen
ing
Crit
eria
5,6
Ben
zene
, Eth
ylbe
nzen
e, T
olue
ne, a
nd X
ylen
es (S
W80
21B
)
Poly
nucl
ear A
rom
atic
Hyd
roca
rbon
s (S
W82
70D
SIM
)
Poly
chlo
rinat
ed B
iphe
nyls
(SW
8082
)
2 - S
econ
dary
Scr
eeni
ng C
riter
ia:
the
valu
e co
rres
pond
s to
the
valu
e lis
ted
in 1
8 A
AC
75.
341,
Tab
les
B1
and
B2,
Mig
ratio
n to
Gro
undw
ater
(Oct
ober
9, 2
008)
.
Prim
ary
TEW
-1.5
14-S
ep-0
910
9487
3012
TEN
-4.0
14-S
ep-0
910
9487
3001
3-1
3
UST
Rel
ease
Inve
stig
atio
n Re
port
M
L&P
Ope
ratio
ns a
nd D
ispa
tch
Cen
ter
Prep
ared
for M
unic
ipal
Lig
ht &
Pow
er
1-
7
N
ovem
ber 2
009
This
pag
e in
tent
iona
lly le
ft bl
ank.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 4-1 November 2009
4 SUMMARY AND CONCLUSIONS
Visual observations and sampling and analysis have confirmed a release of diesel fuel occurred from an inactive UST next to the ML&P Operations Building (1121 E. 1st Ave, Anchorage, AK). The duration of the release(s) or the total quantity of fuel released is unknown. However, the site history and sample results (both current and past) suggest the release was less than 2,000 gallons and the impacts are localized. The UST was emptied of product and removed from the ground in September of 2009, stopping the potential for future releases. Sampling indicated that there was also a PCB spill located in the same approximate location as the UST. The source of the PCBs is assumed to be spills or leaks of dielectric fluids from a transformer that was located a few feet from the UST prior to 1974. The fuel release appears to have enabled the PCBs to migrate within the fuel-saturated zone and in some areas the contaminants are commingled. Limited soil removal was performed in combination with the UST removal and the associated water line installation project. After the removal action was complete, soil sampling and analysis detected contaminants above ADEC regulatory cleanup levels (18 AAC 75.341) along the edges of the excavation. Based on these results, the primary contaminants of concern (COCs) at the site are DRO and PCBs. PAHs are also potential COCs. Along the edges of the UST excavation, DRO and PCBs exceeded the ADEC Method Two cleanup level for the under 40-inch zone (direct contact or ingestion). The maximum detected DRO concentration was 17,700 mg/Kg, and the maximum detected PCB concentration was 112 mg/Kg. Two PAH compounds (1-methylnaphthalene and 2-methylnaphalene) slightly exceeded the Method Two Migration to Groundwater cleanup standard. It is also suspected that a portion of the soil used to backfill the excavation contained PCBs above 1 mg/Kg, and possibly above 50 mg/Kg, as soil from the excavation was used for backfill before it was known PCBs were present. The soil removed from the UST excavation for disposal (12 yd3) had a maximum detected PCB concentration of 114 mg/Kg and DRO of 2,550 mg/Kg. At the nearby Water Line Excavation, no sample concentrations exceeded the ADEC Method Two cleanup level for the under 40-inch zone after the removal action was complete. However, DRO and two chlorinated solvents (tetrachloroethene and trichloroethene) exceeded the most stringent ADEC Method Two cleanup level (Migration to Groundwater). The highest DRO concentration detected was 2,140 mg/Kg. This sample was located at a depth of 6.5 feet bgs in the small excavation within the Operations Building. The two chlorinated solvents exceeded the Migration to Groundwater Cleanup Level at this location as well. PCBs were detected but no sample concentrations exceeded 1 mg/Kg. The contaminated soil detected at the Water Line Excavation is attributed to migration from adjacent sources areas, the dominant source being the UST area. Product (fuel) was observed flowing into the excavation from the UST area in September 2009. It is also possible some of the detected petroleum hydrocarbons on the west side of the Water Line Excavation originated from the Gasoline UST site to the west. The low levels of chlorinated solvents detected in the soils
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 4-2 November 2009
are likely the result of transport from offsite locations. There is documented contamination of chlorinated solvents in the ground water in the region (e.g., The RETEC Group 2008; BGES 2007; CH2MHill 2008). Groundwater sampling was not performed as part of this investigation. However, based on visual observations and soil sampling results, impacts to ground water are likely, at least in the immediate area. Potentially, some free product is still present. However, given the dewatering and product recovery efforts conducted for several weeks during and after UST removal, it is likely most if not all residual product is relatively immobile and localized. Current information, albeit limited, does not indicate there are current exposure pathways between the COCs and human or ecological receptors. Contamination appears to be localized and confined within the subsurface of the facility boundaries. The contaminated soil is covered by concrete or asphalt, preventing contact between potential receptors and the soil. Volatile components are low, indicating vapors are unlikely to pose a significant risk. There are no drinking water wells on the property or adjacent properties, and surface water bodies are not present. These circumstances suggest the site poses a low risk to human health or the environment given the current site conditions. As a result of this release investigation, several recommendations are offered for consideration:
• Appropriate institutional controls should be put in place and maintained to prevent the exposure to contaminants at adverse concentrations.
• Additional site characterization should be performed to define the extent of contamination, evaluate the potential for offsite migration, and determine the appropriate management strategy for the site. At a minimum, groundwater monitoring of existing groundwater wells should be performed to confirm that contaminants are not migrating beyond the immediate area and potentially reaching downgradient receptors. This sampling was initiated in October 2009 and results are pending. Soil sampling for PCBs and DRO beyond the boundaries of the UST excavation is also advisable.
• PCB concentrations in excess of 50 mg/Kg were detected and remain in the soil at the site. Therefore, the cleanup and disposal of the PCB-contaminated soil must comply with applicable TSCA regulations (40 CFR 761.61) unless the EPA approves alternative requirements as part of a risk-based disposal under 40 CFR 761.61(c). Under 40 CFR 761.61(a), self-implementing onsite cleanup and disposal of PCB remediation waste, the EPA has established cleanup levels and associated institutional controls for PCB remediation waste (contaminated soil). Under these regulations, the PCB cleanup level for soil varies from 1 to 100 mg/Kg depending upon the site use (occupancy). The cleanup levels and institutional controls applicable to a “low occupancy area” are probably appropriate for the site and could be implemented fairly readily. Under these regulations, soil with PCBs greater than 100 mg/Kg must be removed unless risk-based disposal is approved in accordance with 40 CFR 761.61(c). The site management strategy should consider whether removal of the PCB-contaminated soil to some threshold level (e.g., 100, 50 or 25 mg/Kg) is preferred over the implementation of more restrictive institutional controls. Removal actions will be complicated by the existing infrastructure (utilities and buildings) and shallow water table. Therefore, the most
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 4-3 November 2009
practical approach may be a combination of removal actions and institutional controls, contingent upon regulator approval.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 4-4 November 2009
This page intentionally left blank.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 5-5 November 2009
5 REFERENCES
Alaska Department of Environmental Conservation (ADEC). 2002. Underground Storage
Tanks Procedures Manual. November 7. ADEC. 2009. Environmental Laboratory Data and Quality Assurance Requirements. Technical
Memorandum. March. BGES, Inc. (BGES). 2007. Forth Avenue and Gambell Street, Anchorage Alaska. Additional Site
Assesment. December. CH2M HILL. 2008. Area GW 2/3 Supplemental Groundwater Investigation in the Vicinity of
the Alaska Railroad Corporation, Anchorage Terminal Reserve. Prepared for the U.S. EPA. November.
Freeze, Allan R. and Cherry, John A. 1979. Groundwater, Prentice-Hall Englewood Cliffs,
New Jersey. 604 pp. Hoefler Consulting Group (HCG). 2009a. Letter to ML&P entitled: Re: July 2009 Groundwater
Monitoring at 1121 E. 1st Avenue, Anchorage, Alaska, File #2100.26.301, Fac. ID #73, Event ID #78, Reckey #1989210008601. August 25.
HCG. 2009b. Cleanup Plan for Petroleum Contaminated Soil in the “Water Line Excavation,”
ML&P Operations and Dispatch Center, 1201 E. 1st Ave, Anchorage, Alaska. September.
HCG. 2009c. Work Plan for Limited Release Investigation and Soil Removal Action During UST
Removal at ML&P Operations and Dispatch Center, 1201 E. 1st Ave, Anchorage, Alaska. September.
HCG. 2009d. Data Report for October 2009 Groundwater Sample Results, ML&P Operations
and Dispatch Center, 1201 E. 1st Ave, Anchorage, Alaska. (In Progress). Anticipated November.
META Environmental. 1994. Site Characterization and Remediation Alternatives Study at
ML&P Power Plant No. 1. November. M.L. Taylor and P.W. Kilpatrick, Architects. 1953. Schematic drawing: Floor Plan, Sheet 16 of
18, Heating. June 4. Matthews, Jerry. 2009. Personal communication between Mr. Mathews, ML&P Distribution
Transformer Shop/Facility Maintenance, and HCG staff, September through November.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power 5-6 November 2009
Shannon & Wilson. 1993. Document Review and Groundwater Monitoring Results. 1121 East First Avenue, Anchorage, Alaska. September.
Shannon & Wilson. 2003. ML&P Property Review and Status, East First and Third Avenues,
Anchorage, Alaska. Jul The RETEC Group, Inc. 2008. Remedial Investigation, Alaska Railroad Corporation,
Anchorage Terminal Reserve, U.S. EPA Docket No. CERCLA 10-2004-0065. May 12.
UST Release Investigation Report ML&P Operations and Dispatch Center
Prepared for Municipal Light & Power November 2009
Appendix A
1953 Operations Building Schematic Drawing