U.S.$Solar$Finance$Update$ - SunSpec Home - SunSpec...

45
U.S. Solar Finance Update Thomas Tansy Solar Energy Finance Associa9on SunSpec Alliance [email protected] June 22, 2016 1

Transcript of U.S.$Solar$Finance$Update$ - SunSpec Home - SunSpec...

U.S.  Solar  Finance  Update  

Thomas  Tansy  Solar  Energy  Finance  Associa9on  

SunSpec  Alliance  [email protected]  June  22,  2016   1  

Agenda  

•  U.S.  solar  finance  framework  (10  min.)  •  Focus  on  unique  aspects  &  risks  (40  min.)  

– Tax  equity  &  ITC  – Developer’s  perspec9ve  –  Investment  diligence  &  risk  management  – Long-­‐term  asset  management  

•  Round  table  discussion  (15  min.)  

2  

U.S.  Market  Sectors  •  Residen9al  

–  Mo9va9ons:  cost  savings,  environmental  concerns  –  Finance  op9ons:  loans,  leases,  frac9onal  ownership  –  Key  factors:  energy  cost,  credit  profile,  state  net  metering  policy  

•  Commercial  &  Industrial  –  Mo9va9ons:  demand  charge  reduc9ons,  tax  relief  –  Finance  op9ons:  loans,  leases,  PPA’s  –  Key  factors:  building  ownership,  credit  profile,  energy  use  profile  

•  U9lity  –  Mo9va9ons:  Renewable  PorZolio  Standard  (RPS)  compliance  –  Finance  op9ons:  rate-­‐base,  bonds,  PPA’s  –  Key  factor:  public  u9lity  commission  posture  

3  

10  Quarters  of  1+  GW  Growth  

4  Source: GTM Research

38 41

47 53

60 67

36

46

56

66

77

88

4 8 12

19 26

2011 '12 '13 '17 '20 '21 '14 '15 '16

No ITC extension

'18 '19

ITC extension

2

+21GW

$35bn

Sustained  by  2015  Investment  Tax  Credit  Extension  

5  

Source: Bloomberg New Energy Finance

Supported  By  Rising  Retail  Energy  Costs,  

6Source: EIA, GTM Research

Decreasing  PV  System  Costs,  

7

Source: GTM Research

And  New  Grid  Support  Services  

8

Source: SolarCity

Industry  Concerns  

•  Affordable  finance  to  scale  growth  – Private  debt  (bank  lines)  – Public  debt  (ABS)  – Equity  (IPO  or  Yieldco)  

•  Lifespan  related  risks  – Asset  management  – O&M  

9  

U.S. Solar ABS Issuance Data (as of April 2016)

  SCTY  I  –  SolarCity  –  LMC  Series  I  LLC  (Series  2013-­‐1)  November  2013

SCTY  II  –  SolarCity  –  LMC  (Series  II  LLC  (Series  2014-­‐1)  April  2014

SCTY  III  –  SolarCity  LMS  (Series  III)  LLC  (Series  2014-­‐2)  July  2014

Sunrun  Callisto  –  Issuer  2015-­‐1,  LLC  (Series  2015-­‐1)  July  2015

SCTY  IV  –  SolarCity  LMC  Series  IV,  LLC  (Series  2015-­‐1)  August  2015

Aurora  Master  Funding,  LLC  Series  2015-­‐15

SCTY  V-­‐  SolarCity  FTE  Series  1,  LLC  (Series  2015-­‐A),  

SCTY-­‐VI-­‐SolarCity  LMC  Series  V,  LLC  (Series  2016-­‐1)

ABS  Coupon/Yield 4.80% 4.59% 4.32%1 4.50%1 4.41%1   5.81%1 5.45%1

Bond  Size $54.4M $70.2M $201.5M $111.0M $123.5M $100.0M $185M $57.45M Collateral Resi  Leases/PPAs  

(71%)/non-­‐resi  (29%)

Resi  Leases/PPAs  (87%)/non-­‐resi  (13%)

Resi  Leases/PPAs  (86%)/non-­‐resi  (14%)

Resi  Leases/PPAs

Resi  Leases/PPAs

CIMU  (70.5%)/  Resi  (29.5%)

MyPower  Loans Resi  Leases/PPAs

Tax  Equity NA NA Master  Lease Inverted  Lease Partnership  Flip/Back  Leverage/Tax  Loss  Insurance

NA NA Master  Lease  (90.8%  of  ADSAB)

ADSAB2  

(PV  of  cash  flows) $87.8M $106.2M $276.0M $146.5M $182.0M $128.0M $249.5M $76.4M

OvercollateralizaYon3 38% 34% 27% 24.23% 32.1% 21.88% 25.9% 24.8% Advance  Rate4   62% 66% 73% 75.77% 67.9% 78.12% 74.1% 75.2% Senior  (Class  A)  Notes  RaYng

$54.4M/  BBB+(sf)

$70.2M/  BBB+(sf)

$160M/  BBB+(sf)

$100M/  A(sf)

$103.5M/  A(sf)

$92.5M/  BBB(sf)

$151.55M/  BBB  (sf)

$52.15M/  BBB(sf)  [S]/  BBB+(sf)  [K]

Subordinated  (Class  B)  Notes  RaYng

NA NA $41.5M/  BB(sf)

$11M/  BBB(sf)

$20M/  BBB(sf)

$7.5M/  B(sf)

$33.45M/  BB(sf)

$5.3M/  BB(sf)  [S]/  BB+(sf)  [K]

RaYng  Agency  UYlized S&P S&P S&P Kroll Kroll Kroll S&P/Kroll S&P/Kroll

1The Yields for these deals are a weighted average based on the size of two tranches offered in each capital structure. 2Aggregate Solar Discount Asset Balance (“ADSAB”) is calculated as the discounted payment streams from leases and PPAs, or notes. 3Calculated as (ADSAB – total Bond Size) ÷  ADSAB. 4Ratio of total Bond Size to ADSAB. 5Not yet priced or closed.

10

U.S.  Solar  Finance  Outlook  •  Con9nued  financial  innova9on  

–  Easy  credit  for  residen9al  roooop  –  Credit  backstop  mechanisms  for  C&I  financing  –  PorZolio  financings  for  substa9on-­‐level  projects  –  Risk  mi9ga9on  and  credit  enhancement  –  Standardiza9on  

•  M&A  and  consolida9on  –  Solar  installa9on  companies  –  Solar  financing  companies  

•  Scale-­‐up  of  issuances  to  public  capital  markets  –  Solar  securi9za9ons  –  Yieldcos  –  Carve-­‐outs,  Newcos,  REITs,  and  maybe  MLPs  –  Green  bonds  

11

The Role of Tax Equity and the ITC

Presented by Dirk Michels [email protected] June 22, 2016

13

Project Financing

•  U.S. style Project Financing requires three types of capital:

-  Tax Equity (±40%)

-  Non-Recourse Debt (±40%)

-  Sponsor Equity (±20%)

14

Tax Equity

•  About 40% of total installation cost

•  Investment Tax Credit (ITC)

•  Depreciable basis is basis less ½ of the ITC/cash grant

15

Investment Tax Credit (ITC)

•  Example: $10M project with ITC -  $3M ITC in Year 1.

-  Depreciation using the Modified Accelerated Cost Recovery System (MACRS) over a 5-year period. Corporate taxation of 40%. •  $8.5M * 40% = $3.4M in tax savings from depreciation over 5

years

16

Sample Project Finance Structures

•  Sale Leaseback

•  (Double) Partnership Flip

•  Lease-Pass Through

17

Thank You Very Much!

For Further Questions:

Dirk Michels Ballard Spahr LLP Los Angeles: 2029 Century Park East, Suite 800

Los Angeles, CA 90067 New York: 919 Third Avenue, 37th Floor

New York, NY 10022 c: 858-254-2260 o: 424-204-4400 e: [email protected]

Prepared for

Ram Akella, CEO - Centrosolar

June 22, 2016

Developer & Investor’s Perspective

Developers & Investors - Share Objectives •  Minimize risk of investment

•  Maximize return on investment

•  Realize returns in the shortest period of time

•  Identify and mitigate each risk

Intersolar Europe 2016

 19

Project Funnel – Basis for Success

Intersolar Europe 2016

 20

OPPORTUNITIES X MWs Projects

PIPELINE X/~2 Projects

BACKLOG  ~20%  of  X  MWs  

Pipeline Probability of being realized is ~50% of all opportunities considered

Backlog Realized projects represent ~20% of assessed opportunities

Project Development Stages

Intersolar Europe 2016

 21

Stage 1 • Identification of potential project site(s)

• Development of technical support

• Funding of development costs

Stage 2 • Identify technical options

• Analyze cost/benefits

• Permitting needs

• Market assessment

Stage 3 • Technical & Financial analysis of preferred option

• Financing options

• Start of permitting process

• Preliminary technical concept

Stage 4 • Permitting • Supplier selection & contract negotiation

• Financing of project

Stage 5 • Start of design

• Project scheduling

• Permitting process finalization

Stage 6 • Construction oversight

Stage 7 • Performance testing

Developer’s – Main Activities

Stag

e 1

First contact with project developer St

age

2

Due diligence Financing structures

Stag

e 3

Financing documents St

age

4

Independent review of construction

Stag

e 5

Independent review of commissioning

Financier’s Perspective

Development Timeline – Utility Scale

Intersolar Europe 2016  

22

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

OBTAIN  PERMIT

INTERCONNECTION  AGREEMENT  EXECUTED

           FINALIZE  PROJECT  FINANCING

Procurement  &  Construction  of  InterconnectionSubstation  &  Network  Upgrade

Project  Financing

Site  Preparation Plant  Construction

DEVELOPMENT  PERIOD  =  AT  RISK  $ $  FUNDED  BY  FINANCIER

Negotiate  Site  Control Secure  Land

Interconnection  Agreement

PERMITTING

Year  1 Year  2 Year  3 Year  4

PPA  Bidding  &  Negotiations

Developer's  Involvement

Financier's  Engagement DG projects and residential portfolios require much shorter time to be realized

Each Project Stage Funded by Different Capital Source

Intersolar Europe 2016

 23

I) Development Stage All Equity

II) Construction Stage Equity/Debt

III) Permanent Capital Tax Equity/Equity/Debt

Development Stage = High Risk, High Return •  Venture Capital •  No Debt

Construction Stage = Moderate Risk, Moderate Return •  Private Equity •  Strategic Investors •  Banks •  Specialty Lenders

Operational Stage = Lowest Risk, Lower Return •  Utilities •  Infrastructure Funds •  Engage with Banks,

Institutional Lenders and Tax Equity

Capital Structure – Permanent Capital

Intersolar Europe 2016

 24

Sponsor Equity ~10%

Tax Equity ~35-45%

Senior Debt ~45-55%

Sponsor Equity contribution finalized after Senior Debt &

Tax Equity

Total Equity difficult to bifurcate between

Investment Tax Credit & MACRS

Long Term Debt always in first position

Priority of C

apital Stack

Take Aways for Developers & Investors

•  Priorities §  Power Purchase Agreement

•  Knowledge of cost of power and total cost an imperative §  Long Term Debt

•  Investment grade off takers are requisite •  DSCR of 1.25x + •  Keen focus on interest rates – moving target

§  Tax Equity •  Established institutions with knowledge of the solar industry

•  Target Hurdle Rate §  Unlevered IRR rates of 7-9%

•  Caution & Knowledge §  Keep an on-going thirst for knowledge = costs, brokers, incentives,

valuation, etc. §  Always remain cautious of whom you engage as advisors, brokers,

consutants Intersolar Europe 2016

 25

Are  Low  Cost  Capital  Products  Dead?

Lessons in Diligence from the Yieldco Meltdown

Mercatus Energy Investment Management (EIM) Software Platform

Helping Energy Producers Drive a Step Change Improvement in Organization Productivity and Speed in Decision Making

80 GW of Project Data

6 Technologies Integrated

Projects Managed Across 75 Countries

Solar Wind Storage Energy Efficiency Biomass CHP

Yieldcos:  Dividend  growth-­‐oriented  public  companies,  created  by  a  parent  company,  that  bundle  renewable  and/or  convenBonal  long-­‐term  contracted  operaBng  assets.  

Having  grown  too  big  and  too  fast,  Yieldcos  suffered  declines  in  revenue  and  loss  of  investment  funds  due  to:

»  Risky  financial  engineering »  The  relentless  acquisiBons  of  assets  and  poor  

project  pipeline  

»  Deficient  project  data »  Compliance    and  diligence  failure  

The Downfall of YieldCos – Lack of Diligence

•  Every  asset  class;  data  integrity,  transparency,  compliance  and  accurate  reporBng  are  key  to  aOract  and  retain  investors. »  It’s  also  mandated  by  

regulaBons  post  2008  economic  meltdown

•  Without  these  aOributes,  the  Renewable  Energy  sector  will  not  aOract  investment.  

•  In  order  for  Yieldcos  and  solar  financing  vehicles  to  regain  credibility:

»  Structure  needs  to  be  simplified

»  Assets    need  to  be  closely  managed

»  Cash  flows  need  to  be  tracked »  Models  need  to  be  accurate

»  Data  needs  to  be  validated  systemaBcally

•  For  now  the  standards  will  be  higher  

Lessons Learned

•  In  the  world  of  distributed  generaBon,  technology  is  key,  investor  confidence  is  necessary  and  financial  games  lead  to  trouble.  

•  Low-­‐cost  capital  is  necessary  in  gaining  a  compeBBve  advantage  in  the  clean  energy  market.  

•  If  renewable  companies  have  the  process  and  technology  to  maintain  a  robust  pipeline,  to  responsibly  feed  financial  instruments  and  to  make  consistent  dividend  payments,  they  can  gain  a  substanBal  advantage  when  it  comes  to  raising  capital.  

Key Takeaways

The  most  successful  energy  companies  of  the  future  will  gain  a  compe55ve  advantage  by  digi5zing  their  business  processes.  

ü AutomaBng  manual  processes  and  eliminaBon  of  clumsy  unnecessary,  Bme-­‐wasBng,  confusing,  and  expensive  overhead  

ü   Taking  “grunge”  out  of  the  asset  investment  management  process

ü The  Impact ü  Stay  compliant  with  investor  criteria  and  guidelines

ü  Assess  project  eligibility  and  clarify  risk  factors  faster   ü  Speed  Accuracy  and  Agility  in  Decision-­‐making

ü  Increase  producBvity,  efficiency  and  reduce  costs  across  your  enBre  organisaBon

What it Means to be Digital/Digitally Diligent

Intersolar Europe Conference 2016 | München

ABOUT 3MEGAWATT

8 GW

2,000 Sites

20 Countries

3megawatt provides BluePoint the world’s leading

solar asset management software platform for solar asset owners and operators

ASSET MANAGEMENT - DIFFERENCES EUROPE | US

THE US MARKET IS MORE COMPLEX FOR ASSET MANAGEMENT

Europe US Asset Management Service 3rd party asset managers Developers

Investors Minority institutional Majority institutional

Monitoring Systems Very fragmented A few big players

EPC Plays big role post COD Plays little role post COD

Separation AM and O&M Little separation Segregated functions

Compliance Requirments Light More complex

Energy Sales Settlements Mostly easy Very complex

Certificate Settlement Mostly easy Complex

Reporting Requirements Mostly easy Complex

Integration with Storage Little traction w. C&I/utility Market developing faster

Pricing pressures High Medium/High

WHAT CHALLENGES ARE SPECIFIC TO THE US?

ü  Portfolio Aggregation

ü  1603 Cash Grant Compliance/ Tax Equity Reporting

ü  Credit Risk PPA Off-takers

ü Net Metering Credits/ Renewable Energy Certificates

ü  FERC/NERC Compliance

ü  PPA Invoicing

REPORTING, COMPLIANCE AND REVENUE SETTLEMENTS

WHAT IS NEW?

ü  Community solar or distributed energy 2.0

ü  Storage O&M

ü  Demand charge reduction

ü  Backup servicing

ü NERC CIP compliance

ü  Spare part management systems

ü  Solar Asset Management Software

THE CURRENT BUZZWORDS

THANK YOU

BLUEPOINT THE LEADING SOLAR ASSET MANAGEMENT PLATFORM

U.S.  Solar  Finance  Update    

Q&A    

Thomas  Tansy  Solar  Energy  Finance  Associa9on  

SunSpec  Alliance  [email protected]  June  22,  2016   41  

Thank  You  

42  

Thomas [email protected]+1-831-227-1073

Appendix I Sale Leaseback Structure

Appendix II (Double) Partnership Flip Structure

Appendix III Lease Pass-Through Structure