Using Two-Stage Tendering Effectively
-
Upload
francis-ho -
Category
Real Estate
-
view
276 -
download
0
Transcript of Using Two-Stage Tendering Effectively
![Page 1: Using Two-Stage Tendering Effectively](https://reader034.fdocuments.us/reader034/viewer/2022051318/588859491a28ab951c8b72bd/html5/thumbnails/1.jpg)
Kate Kennedy
Olswang Masterclass –6 October 2015
Using Two Stage Tendering Effectively
![Page 2: Using Two-Stage Tendering Effectively](https://reader034.fdocuments.us/reader034/viewer/2022051318/588859491a28ab951c8b72bd/html5/thumbnails/2.jpg)
|
Why use two stage tendering?
6 October 2015Using Two Stage Tendering Effectively2
• Generally more used in large or complex tendering
• Current market is contractor friendly
• Inability to get sufficient numbers of contractors serious about tendering for projects has meant two stage tendering has become a necessity on some projects
• A way of establishing whether a project is feasible without having to start works
• Greater cost certainty
• Early appointment of the contractor can lead to an earlier start on site
![Page 3: Using Two-Stage Tendering Effectively](https://reader034.fdocuments.us/reader034/viewer/2022051318/588859491a28ab951c8b72bd/html5/thumbnails/3.jpg)
|
What is two stage tendering? First Stage
Using Two Stage Tendering Effectively3
• Tendering contractors are invited to provide a quote on the basis of an incomplete design, price and programme.
• The employer then choses a preferred contractor to work with during second stage of the tender (the pre-construction period)
• The first stage then ends with the appointment of the preferred contractor on the terms of a PCSA. The PCSA governs the relationship between the employer and the contractor in the period leading up to the contractor’s submission of its construction stage tender.
6 October 2015
![Page 4: Using Two-Stage Tendering Effectively](https://reader034.fdocuments.us/reader034/viewer/2022051318/588859491a28ab951c8b72bd/html5/thumbnails/4.jpg)
|
Second Stage
Using Two Stage Tendering Effectively4
• During the pre-construction period, the contractor advises the employer on the buildability of the design, tenders long-lead subcontracts and builds up a fixed price, programme and cost plans
• In order for this second stage to be a successful springboard to the works, the contractor has to be proactive in its engagement.
6 October 2015
![Page 5: Using Two-Stage Tendering Effectively](https://reader034.fdocuments.us/reader034/viewer/2022051318/588859491a28ab951c8b72bd/html5/thumbnails/5.jpg)
|
Advantages of two stage tendering
Using Two Stage Tendering Effectively5
• Employer has pre-existing relationship with the contractor and consulting team before the works commence
• Contractor’s knowledge of previous, similar schemes is made available earlier
• Value engineering facilitated at an earlier stage
• Allows a more collaborative approach
• Greater client control over pre-selection and appointment of subcontractors
• Reduction of abortive tender costs
• Can avoid buildability issues once the project has commenced
6 October 2015
![Page 6: Using Two-Stage Tendering Effectively](https://reader034.fdocuments.us/reader034/viewer/2022051318/588859491a28ab951c8b72bd/html5/thumbnails/6.jpg)
|
Disadvantages of two stage tendering
Using Two Stage Tendering Effectively6
• Potentially could compromise a client’s commercial position
• Can lead to an abuse of negotiating position, which leads to damaged relations from the start of the build
• More complicated and can be more expensive and has higher initial costs than single stage procurement methods
• Needs a sophisticated client
• Can be difficult to replace the contractor
6 October 2015
![Page 7: Using Two-Stage Tendering Effectively](https://reader034.fdocuments.us/reader034/viewer/2022051318/588859491a28ab951c8b72bd/html5/thumbnails/7.jpg)
|
Practical points for employers to try and maintain a strong bargaining position
Using Two Stage Tendering Effectively7
• If the client has a bargaining chip of future work, that can help
• Don’t start on site prior to the agreement of the second stage tender
• Try to make sure you maintain high quality design information throughout
• If you can, try to include works packages in the first stage tender in order to ensure that they can be priced on the basis of a competitive rather than negotiated tender
• Keep client involvement in the second stage procurement of subcontractors. This gives the client greater cost certainty for the works
6 October 2015
![Page 8: Using Two-Stage Tendering Effectively](https://reader034.fdocuments.us/reader034/viewer/2022051318/588859491a28ab951c8b72bd/html5/thumbnails/8.jpg)
|
Points to note for the PCSA
Using Two Stage Tendering Effectively8
• Ensure there is a ‘get out’ route for the client without suffering significant delay or extra costs
• Try to ensure as many t’s and c’s of the schedule of amendments as are possible are agreed.
• Obligation on the contractor to liaise with the employer to agree proposed sub-contractors for works packages.
• Ensure there is no obligation on the employer to enter into the building contract.
• Ensure that all work carried out under the PCSA is subsumed within the building contract when executed
• Query whether any collateral warranties might be needed during the PCSA period
6 October 2015
![Page 9: Using Two-Stage Tendering Effectively](https://reader034.fdocuments.us/reader034/viewer/2022051318/588859491a28ab951c8b72bd/html5/thumbnails/9.jpg)
|
•For more information•please contact:
Brussels+32 2 647 4772
London+44 20 7067 3000
Madrid+34 91 187 1920
Munich+49 89 203 031 300
Paris+33 17 091 8720
Singapore+65 6720 8278
Thames Valley+44 20 7067 3000
Kate Kennedy
+44 20 7067 [email protected]
@hardhatlawyer