Watershed Protection Land Trust Partnerships to Meet Your Goals.
Using the Design-Build Approach to Meet Energy Reduction Goals March 2012.
-
Upload
alexis-berry -
Category
Documents
-
view
212 -
download
0
Transcript of Using the Design-Build Approach to Meet Energy Reduction Goals March 2012.
Using the Design-Build Approach to Meet Energy
Reduction Goals
March 2012
University of California, Irvine
457 Buildings comprising 5,480,000 ASF1,478 acres main campus
$16M annual utilities budgetLab buildings consume 2/3 of campus energy
March 2, 2012 2
Statewide Energy Partnership
3-year agreement between CPUC, IOU’s, UC, CSU Annual reduction and incentive goals $40M project cost over 3-years Year one goal – 16,097,345 kWh & 434,844
Therms Organization couldn’t meet year one goals Utilize ESCO-like best value design-build contract Performance guarantee
Annual kWh and therm reduction Maximum acceptance cost (MAC)
March 2, 2012 3
Design – Build ContractingDesign – Build Contracting
Design-Build performanceDesign-Build performance GoalGoal Actual Actual
kWhkWh 11,087,62311,087,623 11,857,97511,857,975 ThermsTherms 236,055 236,055 371,361 371,361 MACMAC $7,800,000$7,800,000 $8,292,910$8,292,910
Types of projects completedTypes of projects completedkWh/yr.kWh/yr.
therms/yr.therms/yr. LightingLighting 5,719,306 (48%)5,719,306 (48%) 00 MBCXMBCX 2,774,175 (23%)2,774,175 (23%) 323,449 (87%)323,449 (87%) AC ControlsAC Controls 1,804,871 (15%)1,804,871 (15%) 47,912 (13%) 47,912 (13%) ESDVRESDVR 1,559,623 (13%)1,559,623 (13%)
March 2, 2012 4
Design-Build Best Value Design-Build Best Value ContractingContracting
ProPro’’ss Large quantity of projects completed quickly; Large quantity of projects completed quickly;
achieved year-1 goalsachieved year-1 goals Contractor managed numerous groupsContractor managed numerous groups Performance guaranteePerformance guarantee
ConCon’’ss Owner accepts risk that cost savings will be Owner accepts risk that cost savings will be
achievedachieved Need in house expertise to verify and monitorNeed in house expertise to verify and monitor
Lessons LearnedLessons Learned Contractor not used to dealing with Owner technical Contractor not used to dealing with Owner technical
expertise & involvementexpertise & involvement Contractor not familiar with SEP approval processContractor not familiar with SEP approval process Separate contracts by type of workSeparate contracts by type of work
March 2, 2012 5
Energy Projects Going Energy Projects Going ForwardForward
Evaluate your organization Evaluate your organization Design-build with specialized contractorsDesign-build with specialized contractors
Less control over designLess control over design Constant Air Volume to Variable Air VolumeConstant Air Volume to Variable Air Volume
Unit price contractUnit price contract LightingLighting
Design – bid – buildDesign – bid – build Retain engineering and design controlRetain engineering and design control Exhaust Stack Discharge Velocity Reduction / Exhaust Stack Discharge Velocity Reduction /
Wind ResponseWind Response Heavy interaction with end-usersHeavy interaction with end-users
CDCV in VivariaCDCV in Vivaria MBCxMBCxMarch 2, 2012 6
Statewide Energy Statewide Energy PartnershipPartnership
March 2, 2012 7
SEP Program Year 2009 2010 2011 Total 2012
Electric Savings (kWh/Yr.)
16,741,000
7,209,000
10,214,000
34,614,000
15,500,000
Natural Gas (Therms/Yr.)
469,000 869,000 425,0001,763,0
00477,000
GHG (CO2e Tones/Yr.)
7,700 6,800 5,400 19,900 7,300
Incentive Received$4,284,0
00$2,586,
000$2,835,0
00$9,705,
000$4,355,0
00
Energy Cost Savings/Yr.
$2,016,000
$1,294,000
$1,271,000
$4,581,000
$1,890,000
kWh % Reduction vs. 2008
12% 5% 7% 24% 11%
Questions?Questions?
March 2, 2012 8