Training Document
MSEDCL
End User Training ManualVer. 1.0
Module: PS
SAP Component: Project System
Budget Process Version: ECC 6.0 R/3
EHP 5.0
![Page 2: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/2.jpg)
Training Document
Table of Contents1. Scheme Creation and Assignment.................................................................................................3
1.1. Creation of Program: T-CODE- IM01..........................................................................................3
1.2. Creation of Scheme – T-code IM11............................................................................................5
1.3. Creation of Sub-Scheme T-code – IM22.....................................................................................8
1.4. Assignment of Plant & Sub-Scheme- T-code –IM22...................................................................9
2. Scheme Budget............................................................................................................................12
2.1. Over all wise budget distribution T-code – IM32.....................................................................12
2.2. Overall Budget –t-code IM32...................................................................................................13
2.3. Yearwise Main scheme & sub-scheme ( Division ) Budget.......................................................13
3. Project Creation...........................................................................................................................15
3.1. Assign scheme to project.........................................................................................................15
3.2. Selection of scheme.................................................................................................................16
4. Cost Planning...............................................................................................................................17
4.1. WBS wise Budget –t-code CJ40................................................................................................17
4.2. Notification :............................................................................................................................18
4.2.1. Notification creation: T-code- Iqs1.......................................................................................18
4.2.2. Notification change: T-code- Iqs2........................................................................................19
4.2.3. Notification check – T-code SBWP.......................................................................................20
5. Budget Allocation........................................................................................................................21
5.1. Creation Project Version- t-code CN72....................................................................................21
5.2. Displaying different version – T-code CN41.............................................................................22
5.3. Budet Distibution T-code IM52................................................................................................23
6. Allocation of Budget....................................................................................................................26
6.1. WBS wise budget allocation t-code CJ30.................................................................................26
6.2. Year wise budget allocation.....................................................................................................27
6.3. Release Budget- T-code – CJ32................................................................................................28
7. Release Project............................................................................................................................29
8. Report..........................................................................................................................................30
8.1. Project wise Actual / Commitment / Planted budget..............................................................30
8.2. Scheme wise budget................................................................................................................32
9. Creation of Purchase order..........................................................................................................34
9.1. Material, civil and centages PO created by Purchase team of respective division...................34
10. Budget commitment Reports..................................................................................................36
![Page 3: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/3.jpg)
Training Document
10.1. Project wise budget............................................................................................................36
10.2. Project wise IM Budget........................................................................................................36
1. Scheme Creation and Assignment
1.1. Creation of Program: T-CODE- IM01User Responsible: Head office finance department
![Page 4: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/4.jpg)
Training Document
As per year the program will be created.
Note: currently program is created for 2014 and 2015 year.
![Page 5: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/5.jpg)
Training Document
1.2. Creation of Scheme – T-code IM11User Responsible: Head office finance department
As per requirement a main scheme will be created in approved year
Input Sceen – Investment program – This is define for whole Maharastra with year of approval.
Position ID- This is Scheme name for current year.
![Page 6: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/6.jpg)
Training Document
Press Enter.
Specify the person responsible of main scheme. By this concern person can only change the main scheme.
![Page 7: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/7.jpg)
Training Document
Selection screen: Controlling area- this is by default as 1000.
Description: enter the description of main Scheme.
Person responsible field.
SAVE the Scheme
![Page 8: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/8.jpg)
Training Document
1.3. Creation of Sub-Scheme T-code – IM22User Responsible: Head office finance department
Select main scheme and click on create position.
Enter all division used in that main scheme as sub-scheme.
Click on check and copy.
Click on copy
![Page 9: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/9.jpg)
Training Document
1.4. Assignment of Plant & Sub-Scheme- T-code –IM22User Responsible: Head office finance department
In Sub-Scheme Finance department assign plant to Sub-Scheme to determine Division.
Selection screen:
1. Select person responsible field(F4)- This will display all division will be assign to main scheme.
2. Select proper no.
3. Check budget distribution : check both year and overall
4. In organization tab – select plant.
Click Save
![Page 10: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/10.jpg)
Training Document
![Page 11: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/11.jpg)
Training Document
![Page 12: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/12.jpg)
Training Document
2. Scheme Budget
User Responsible: Head office finance department
In this budget is distributed both wise i.e. overall and year wise.
2.1.Over all wise budget distribution T-code – IM32
Select main scheme and sub-scheme with correct year.
Here – if we do F4 in position id, system popup all the scheme involving in Investment program.
![Page 13: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/13.jpg)
Training Document
2.2. Overall Budget –t-code IM32
Current budget – This is amount assign to scheme.
Distributed - This is amount given to lower scheme.
Distributable- This is amount left to distribute to lower Scheme.
2.3.Yearwise Main scheme & sub-scheme ( Division ) Budget
Budget can be distributed year wise. Click on period in IN32 screen and select year.
Note: If Overall budget is less than year wise budget, system throws the error of budget exceeding.
Check and save the budget.
![Page 14: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/14.jpg)
Training Document
Year wise distribution
Check and save.
![Page 15: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/15.jpg)
Training Document
3. Project Creation
User Responsible: AE (Division): Project will be created in division, circle or zone by AE estimate of concerned division.
3.1. Assign scheme to project
User Responsible: AE (Division)
AE estimate of concerned division will assign scheme to project.In assignment tab.
![Page 16: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/16.jpg)
Training Document
3.2. Selection of scheme
![Page 17: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/17.jpg)
Training Document
4. Cost Planning
User Responsible: AE (Division)
AE Esmiate of concerned division will do cost palnning which include all types of Tax, Overhead Cost
4.1. WBS wise Budget –t-code CJ40
Note: This t-code is only use to plan Tax and overhead cost. Primary cost is calculated in cj20n through network planning.
![Page 18: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/18.jpg)
Training Document
4.2. Notification :
User Responsible: AE (Division)
Once Cost Planning is done AE estimate sends notification to finance department of respective division for further action of budget
4.2.1. Notification creation: T-code- Iqs1.
Select Notification type – P1.
Click on save.
Note user can check tender documents,pdf,etc.. through Project in document overiew . As AE estimate attched project releated document in Top WBS.
![Page 19: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/19.jpg)
Training Document
4.2.2. Notification change: T-code- Iqs2
Enter notification no.
Click on send for sending to applicant
![Page 20: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/20.jpg)
Training Document
Click on send button.
4.2.3. Notification check – T-code SBWP
Enter the recipient to whom notification should be send
![Page 21: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/21.jpg)
Training Document
5. Budget Allocation
5.1. Creation Project Version- t-code CN72
User Responsible: DYM FINANCE (Division)
DYM of respective division will check the notification and project cost plan.DYM finance will create a version of the project before providng budget, to monitor changes.Selection screen input: 1. Provide current project in which budget to be allocated.2. Enter version key as project no.3. Version group: as audit version.
Click on execute.
![Page 22: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/22.jpg)
Training Document
5.2. Displaying different version – T-code CN41.
NOTE : for displaying different version,1st select DB profile, activate version .
![Page 23: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/23.jpg)
Training Document
Note:
1. For Full turn key project material : Order cost plan- This cost is project plan including centages and excluding Taxes.
Project cost sch - cost is cumalative cost , which is sum of plan cost in project and Tax included in CJ40.
2. For partial turn key project – Order cost plan - This cost is project cost plan excluding centages for MSEDCL procure material and Taxes.
Project cost sch - cost is cumalative cost , which is sum of plan cost in project and Tax included in CJ40 including centages for MSEDCL procure materials..
5.3. Budet Distibution T-code IM52
User Responsible: DYM FINANCE (Division)
DYM Finance of respective division will proivde budget to the concerned scheme and year
Input screen:
1. Investment program : main investment scheme name.
2. Position ID- sub-scheme name.(if wroung scheme is selected which is not assign to project, system doesnot process further)
3. Approval year: year.
4. Select current-year measure and orginal.
![Page 24: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/24.jpg)
Training Document
5. TOP wbs of project which is assign with investment program.
Here Select Original button.
Note:
Current budget – This is amount assign to scheme.
Distributed - This is amount given to lower scheme.
Distributable- This is amount left to distribute to lower Scheme.
Caution: First check if the Current scheme has budget for current year by clicking on individual scheme.
![Page 25: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/25.jpg)
Training Document
Distribute year wise:
![Page 26: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/26.jpg)
Training Document
6. Allocation of Budget
User Responsible: DYM FINANCE (Division)
Budget will be distributed / allocated to each WBS
6.1. WBS wise budget allocation t-code CJ30.
This amount is same as IM assigned amount through T-Code IM52
![Page 27: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/27.jpg)
Training Document
Click on select all , then go to Edit tab
Select copy view –‘planned total’.
Select 100 percentages. Check and save.
6.2. Year wise budget allocation
Open project from CJ30 and for each WBS maintain budget in year wise.
![Page 28: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/28.jpg)
Training Document
6.3. Release Budget- T-code – CJ32
User Responsible: DYM FINANCE (Division)
Click on select all , then go to Edit tab
Select copy view ‘’current budget’’.
Select 100 percentage and copy.
Check and released budget year wise also, by selecting each wbs.
![Page 29: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/29.jpg)
Training Document
7. Release Project
User Responsible: If the project is of division level then EE of division will released the project.
![Page 30: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/30.jpg)
Training Document
8. Report
User can have different kind of standard reports
8.1.Project wise Actual / Commitment / Planted budget
![Page 31: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/31.jpg)
Training Document
![Page 32: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/32.jpg)
Training Document
8.2.Scheme wise budget
![Page 33: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/33.jpg)
Training Document
![Page 34: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/34.jpg)
Training Document
9. Creation of Purchase order.
User Responsible: AE Purchase (Division)
9.1. Material, civil and centages PO created by Purchase team of respective division.
Note: IF project PO is created above the quoted price, then overall cost will be increase and system will asked for budget supplement.
Material Po.
![Page 35: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/35.jpg)
Training Document
![Page 36: User Manual Budget Process Document V01](https://reader031.fdocuments.us/reader031/viewer/2022020718/5695d18f1a28ab9b029707d6/html5/thumbnails/36.jpg)
Training Document
10. Budget commitment Reports
10.1. Project wise budget
Report - S_ALR_87013558 - Budget/Actual/Commitment/Rem Plan/Assigned
10.2. Project wise IM Budget