The Project Schedule Log: Charting the Project Path

Mark DoranPaul Levin, PSPChris Carson, PSP

Page 3: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org3

Author Biography – Mark Doran

Degree:– BS, Building Construction and Contracting Technology

University:– Purdue University

Years of Experience:– 25 years

Professional Field:– Construction Management, Administration and Consulting,

Construction Claims Analysis and Expert Testimony with emphasis on scheduling and schedule analysis

– Founding Partner of Contract Solutions LLC Something you do not know about me:

– Provide scheduling /claims seminars for Federal Publications Seminars.

– Hobbies include golf and scuba diving.– Member: CMAA , ABC and ABA Construction Forum

Page 4: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org4

Author Biography – Paul Levin, PSP

Degree:– BSCE, MEA

University:– BSCE, University of Maryland– Masters in Engineering Administration, The George

Washington University Years of Experience:

– 25 years Professional Field:

– Construction Management, Administration and Consulting. Focus on Project Controls and Scheduling. Primarily heavy construction.

– Senior Schedule Engineer, Washington Metropolitan Area Transit Authority

Something you do not know about me:– Also involved as publisher, editor and writer on various

construction subjects including claims, construction law, BIM, scheduling and project controls.

– Hobbies include bicycles, motorcycles and one week of black diamonds a year

Page 5: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org55

Chris Carson, PSP, CCM, PMP

Corporate Director of Project Controls, Alpha Corporation– Responsible for standards, processes, and procedures for a team of

schedulers, analysts, and project managers in multiple office locations, as well as analysis, work product, and testimony

– Developed and manages the in-house project controls training program at Alpha

Certified as PMI PMP, AACE Planning & Scheduling Professional, CMAA Certified Construction Manager

University: University of Virginia, Mechanical Engineering, 1972 Professional Field: 38 years of experience in Construction Management

Services specializing in Scheduling, Schedule Analysis, Estimating, Claims Active in PMI (Project Management Institute) College of Scheduling

– Vice President of Scheduling Excellence, Managing Director for SEI (Scheduling Excellence Initiative) writing Best Practices and Guidelines for Scheduling and Schedule Impact Analysis

Active in Association for the AACE International, Planning Planet, CMAA

Page 6: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org6

Introduction

Page 7: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org7

Three Topics

Basic Schedule LogDual Tracking Schedule LogSchedule Notebook

Page 8: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org8

Purpose of Schedule Logs

Organizational ToolManagement ToolSchedule Analysis Tool

Page 9: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org9

• Organizational Tool• Keep track of various schedules and baselines• Keep track of submissions and approvals

Page 10: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org10

Purpose of Schedule Logs

• Management Tool• Track project’s progress (and cost) through time• Look for trends and patterns• Forecast where job is headed and make corrections

Page 11: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org11

• Analysis Tool• Overview of project history from scheduler’s

perspective• List of schedules “of record” and approvals• Starting point for schedule-related claims• Identity patterns of changes from month to month

Purpose of Schedule Logs

Page 12: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org12

• Chart – table or spreadsheeto Basic project schedule datao Obtained from schedule software and payment datao Includes data required by contract’s schedule

specifications

Schedule Logs – Basic Format

Page 13: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org13

o Basic Schedule Clauses• Prepared by contractor• Baseline• Approved by owner• Monthly updates

Typical Schedule Specifications

Page 14: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org14

• Basic Schedule Clauses (cont.)• AIA 201• Consensus Docs (formerly AGC200)• EJCDC C-700• Various public agency contract documents

Typical Schedule Specifications

Page 15: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org15

• Advanced Requirements• Cost loading – schedule of values• Resource loading – man-hours

Typical Schedule Specifications

Page 16: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org16

• Advanced Schedule Clauses (cont.)• Unified Facilities Guide Specifications (UFGS) as

used by USACE, NAVFAC, AFCESA and NASA• VA, DOE, FBOP and DOE• Various state DOTs, public transit agencies• Private EPC contracts

Typical Schedule Specifications

Page 17: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org17

o Other Select Requirements

• Narrative – Description of progress, changes, job highlights, etc.

• Specific reports (Critical Path, ES, EF)• ClaimDigger report• Copy of data file• Support for time extension requests

Typical Schedule Specifications

Page 18: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

o Project Controls Tool

• Tracking

• Analysis• Project Management

18

The Construction Schedule Log

Page 19: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

• Project Controls Tool

o Administrative tracking tool

o Useful for both Owner & Contractoro On-time schedule submittalso Timely approvals

19

Typical Schedule Specifications

Page 20: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

• Project Controls Tool (cont.)

o Three Basic Types

• basic• detailed• dual-tracking

20

Typical Schedule Specifications

Page 21: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Project Controls Tool (cont.)o Basic

21

Typical Schedule Specifications

Page 22: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

o Project Identification Name or IDo Data Date of the Updateo Project’s Planned Completion Date (includes time

extensions)o Current Early Finish Dateo Variance (Total Float)o Slip/Gain (Change in Total Float from prior period)o Number of Activities in the schedule update

22

Schedule Log

Page 23: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

o Location of data fileo Update Identification Number or Versiono Date Submitted to Ownero Date Approved by Owner

23

Schedule Log

Page 24: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Basic Schedule Log (cont.)

o Data from P3 Project Overview Screen:

24

Schedule Log

Page 25: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Project Controls Tool (cont.)o Detailed (Additional project data)

o Percent complete for period and cumulativeo Number of activities on the critical (longest) path

25

Schedule Log

Page 26: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Detailed Schedule Log (cont.)

o Data from P3 Schedule Update (SureTrak similar):

26

Schedule Report

Page 27: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

o Substantial amount of data available to include in report. (Considerations for a Recommended Practice.)

o Data from P3 (for example, cost and resource data)o Data from 3rd party programs (ClaimDigger, Schedule

Analyzer)o Data from Pay Applications, Daily Reports, Certified

Payrolls, etc.o Labor hours plannedo Actual labor hourso Work days plannedo Actual work dayso Earned valueo Lost days due to weather

27

Detailed Schedule Log

Page 28: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

• Use Excel to compute values for further analysis

o Percent completeso Time gained or loss for the periodo Planned vs actual manpower varianceo Earned valueo Schedule data, including added/deleted activities,

durations, relationships and resources

28

Detailed Schedule Log

Page 29: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

• Perform quantitative and qualitative overview of the health and progress of the project.

• Contractor progress versus planned• Identify trends; project performance• Identify and quantify changes and events• Reconcile schedule changes with scope changes

29

Schedule Analysis Tool

Page 30: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Schedule Log Reviews – Examples Example 1

30

Period Data Date Schedule Filename

Update or Revision

Contract SC Date SC Date Total Float Net Time Gain

or Loss (cd) Reason Responsible Party

Baseline 8/20/07 BOAC Baseline 7/22/2010 7/22/2010 0 0 1 7/7/08 B002 Revision 7/22/2010 8/24/2010 -33 33 steel erection & monumental stair shop dwgs Contractor

2 8/1/08 B003 Revision 7/22/2010 9/15/2010 -55 22 steel & SOD Level 1 Contractor

3 9/2/08 B004 Revision 7/22/2010 9/24/2010 -64 9 SOD Level 2 Contractor

o Note the continual trend of delays due to the same issue – Steel.o Notice how delays in shop drawings continued into the 

installation of steel.  o Lost 3 months in 3 months – better get control of this work ASAP!

Schedule Analysis Tool

Page 31: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

• Schedule Log Reviews – Example 2

31

Period Data Date Schedule Filename

Update or Revision

Contract SC Date SC Date Total Float Net Time Gain

or Loss (cd) Reason Responsible Party Notes

3 9/2/08 B004 Revision 7/22/2010 9/24/2010 -64 9 SOD Level 2 Contractor ajdusted for OOS progress4 10/1/08 B005 Revision 7/22/2010 8/31/2010 -40 (24) 1st Floor layout & HVAC rough-in; Fire Alarm Shop Dwgs Contractor Revised forecasted work sequences

5 11/3/08 B006 Revision 7/22/2010 8/30/2010 -39 (1)Electrical Riser Drawings, MEP Coordination Drawings, Structural Steel & Concrete Placement Contractor Revised forecasted work sequences

6 11/3/08 B007 Revision 7/22/2010 7/22/2010 0 (39) Structural Steel fabrication: Elevator Submittals Contractor Revised forecasted work sequences

7 1/1/09 B008 Revision 7/22/2010 7/22/2010 0 0 Elec/FA OHRI Lvel 1 & 2 ContractorRevised Dur activitiy 9910167; delete Preds for 3015200

8 2/2/09 B009 Revision 7/22/2010 7/22/2010 0 0 Masonry Walls at Mech Spaces levels 1-4. Contractor Revised forecasted work sequences

o Note the continual trend of schedule recovery.. Or is it?o Notice that the schedule recovery is actually “forecasted recovery” in the future 

based on revised, planned work sequences.o Be aware of “masking” of delays by revising future durations or work sequences 

that have not been proven, yet!o This type of schedule “recovery” can shift the critical path without actually 

resolving the issues that has/is delaying the Project, this can also shift the perceived critical path (and delays) to a different party (ie. Owner/,designer, etc.) 

Schedule Analysis Tool

Page 32: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

• Schedule Log Reviews – Example 3

32

8 2/2/09 B009 Revision 7/22/2010 7/22/2010 0 0 Masonry Walls at Mech Spaces levels 1-4. Contractor

9 3/2/09 B010 Revision 7/22/2010 10/27/2010 -97 97 negative progress on South CW Shop dwgs; lack of progress OHRI on lvl 4; lack of Progress on Pavilion CW fab

Contractor

o Note the delay of more than 30 days in one montho Negative progress can be for items of failed work that needs to be 

removed and re‐installed; disapproved shop drawings that had been assigned progress in previous updates, etc.

Schedule Analysis Tool

Page 33: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

• Schedule Log Reviews – Example 4

33

Contract SC Date

SC Date Total Float Net Time Gain or Loss (cd)

Reason Responsible Party

7/22/2010 9/15/2010 -55 (82)Submittal/Rev/approve South CW Shops sooner; 10th floor floating slab slipped 1 wk. Contractor

7/22/2010 10/8/2010 -78 23 Lack of progress on Fab/Del Initial Del South CW; Lack of progress Int & perim CMU Flr 10. Contractor

7/22/2010 10/11/2010 -81 3 One day slippage on Fab & Del South CW resulted in 3cd schedule slippage. Contractor

7/22/2010 1/6/2011 -168 87 Lack of Progress South Curtainwall Contractor

7/22/2010 2/3/2011 -196 28 Lack of progress prep & Build Chamber ATI S Curtainwall; Lack of progress on Fab/Del Initial Del South CW.

Contractor

7/22/2010 3/3/2011 -224 28 3 wek slippage to prep & Build Chamber ATI S Curtainwall; 3 week slippag on Fab/Del Initial Del South CW.

Contractor

7/22/2010 3/8/2011 -229 5 Prep & Build ATI S CW; South CW Fab Contractor

o Note the pervasive delays to the same issue – South Curtainwall design and mock‐up/testing at ATI.  How could you prevent this on your project?

Schedule Analysis Tool

Page 34: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org34

Delay Analysis Organization with the Schedule Log

Review Project and Case Background– Example

• General Contractor client – DBB delivery• Construction of new high school• Disputed issues summary

– Foundation problems– Slow shop drawing submittals– Pre-engineered building problems– Contractor production problems– IT re-design issues– Utility changes

Page 35: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org35

• Review Project and Case Background– Availability & legitimacy of baseline & updates

• Baseline approved• Monthly updates produced, no response about

approvals– Availability & legitimacy of documents

• Daily field reports reasonably detailed• Meeting minutes haphazard• Correspondence file light• RFI, Change Estimate and Change Order logs

available• Monthly invoices available• Several TIAs submitted contemporaneously

Delay Analysis Organization with the Schedule Log

Page 36: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

• Schedule Log

36

Chron Order File Name Start Date Data Date Early Finish Activity

CountCritical

Activities Cum Delay Update Window Size (cd)

Project Duration (cd)

Remain. Time (cd) Notes

6-Jul-09 15-Apr-09 15-Apr-09 26-Jul-10 578 29 0 N/A 467 467 baseline DC 2003

6-Jul-09 15-Apr-09 15-Apr-09 26-Jul-10 580 83 0 N/A 467 467 revised baseline DC Hodges 03

16-Jul-08 15-Apr-09 16-Jul-09 10-Aug-10 578 61 10 92 482 390 Revised baseline (Zero Progress)9-Mar-09 15-Apr-09 15-Apr-09 26-Jul-10 571 50 0 N/A 467 467 Baseline Revisions DC 03

1 15-Apr-09 15-Apr-09 15-Apr-09 26-Jul-10 571 50 0 N/A 467 467 Baseline Final

DESIGN 15-Apr-09 1-May-09 N/A 8 8#VALUE! 16 #VALUE! Design Issues Schedule

2 19-Oct-09 15-Apr-09 19-Oct-09 29-Sep-10 571 112 65 171 532 345 Update October 19, 2009

3 4-Dec-09 15-Apr-09 4-Dec-0925-Oct-10 571 133

91 46 558 325 Update December 04, 2009

34-Dec-09 15-Apr-09 4-Dec-09 9-Dec-10 571 221 136 0 603 370 Update December 04, 2009, with

Glenwood

4 21-Jan-10 15-Apr-09 21-Jan-10 15-Dec-10 571 212 142 48 609 328 January Update 2010

5 3-Mar-10 15-Apr-09 3-Mar-10 27-Dec-10 571 213154 41 621 299 February Update 2010

6 19-May-10 15-Apr-09 19-May-10 27-Dec-10 571 127154 77 621 222 May update 2010

7 2-Jul-10 15-Apr-09 2-Jul-10 6-Dec-10 571 134133 44 600 157 June Update 2010

8 28-Jul-10 15-Apr-09 28-Jul-10 17-Dec-10 571 185144 26 611 142 July Update 2010

IT 15-Apr-09 28-Jul-10 14-Jan-11 577 185172 0 639 170 IT Claim with July Update

9 1-Oct-10 15-Apr-09 1-Oct-10 10-Feb-11 571 113199 65 534 266 September Update 2010

TANK 15-Apr-09 3-Oct-10 10-Mar-11 576 114227 2 694 158 Day Tank Claim with Sept Update

10 3-Nov-10 15-Apr-09 3-Nov-10 24-Feb-11 571 82213 31 680 113 October Update 2010

11 10-Dec-10 15-Apr-09 10-Dec-10 2-Mar-11 571 62219 37 686 82 November Update 2010

12 15-Feb-11 15-Apr-09 15-Feb-11 21-Feb-11 571 18210 67 677 6 January Update 2011

13 18-Mar-11 15-Apr-09 18-Mar-11 8-Apr-11 571 6256 31 723 21 February Update 2011

14 26-Apr-11 15-Apr-09 26-Apr-11 17-May-11 571 6295 39 762 21 March/April Update 2011

Delay Analysis Organization with the Schedule Log

Page 37: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

• Schedule Log

37

ChronOrder File Name Start Date Data Date Early Finish Activity

CountCritical

Activities Cum Delay Update Window Size (cd)

Project Duration (cd)

Remain. Time (cd) Notes

6-Jul-09 15-Apr-09 15-Apr-09 26-Jul-10 578 29 0 N/A 467 467 baseline DC 2003

6-Jul-09 15-Apr-09 15-Apr-09 26-Jul-10 580 83 0 N/A 467 467 revised baseline DC Hodges 03

16-Jul-08 15-Apr-09 16-Jul-09 10-Aug-10 578 61 10 92 482 390 Revised baseline (Zero Progress)

9-Mar-09 15-Apr-09 15-Apr-09 26-Jul-10 571 50 0 N/A 467 467 Baseline Revisions DC 03

1 15-Apr-09 15-Apr-09 15-Apr-09 26-Jul-10 571 50 0 N/A 467 467 Baseline Final

DESIGN 15-Apr-09 1-May-09 N/A 8 8#VALUE! 16 #VALUE! Design Issues Schedule

219-Oct-09 15-Apr-09 19-Oct-09 29-Sep-10 571 112 65 171 532 345 Update October 19, 2009

34-Dec-09 15-Apr-09 4-Dec-09

25-Oct-10 571 13391 46 558 325 Update December 04, 2009

34-Dec-09 15-Apr-09 4-Dec-09 9-Dec-10 571 221 136 0 603 370 Update December 04, 2009, with Glenwood

421-Jan-10 15-Apr-09 21-Jan-10 15-Dec-10 571 212 142 48 609 328 January Update 2010

5 3-Mar-10 15-Apr-09 3-Mar-10 27-Dec-10 571 213154 41 621 299 February Update 2010

6 19-May-10 15-Apr-09 19-May-10 27-Dec-10 571 127154 77 621 222 May update 2010

7 2-Jul-10 15-Apr-09 2-Jul-10 6-Dec-10 571 134133 44 600 157 June Update 2010

8 28-Jul-10 15-Apr-09 28-Jul-10 17-Dec-10 571 185144 26 611 142 July Update 2010

IT 15-Apr-09 28-Jul-10 14-Jan-11 577 185172 0 639 170 IT Claim with July Update

9 1-Oct-10 15-Apr-09 1-Oct-10 10-Feb-11 571 113199 65 534 266 September Update 2010

TANK 15-Apr-09 3-Oct-10 10-Mar-11 576 114227 2 694 158 Day Tank Claim with Sept Update

10 3-Nov-10 15-Apr-09 3-Nov-10 24-Feb-11 571 82213 31 680 113 October Update 2010

11 10-Dec-10 15-Apr-09 10-Dec-10 2-Mar-11 571 62219 37 686 82 November Update 2010

12 15-Feb-11 15-Apr-09 15-Feb-11 21-Feb-11 571 18210 67 677 6 January Update 2011

13 18-Mar-11 15-Apr-09 18-Mar-11 8-Apr-11 571 6256 31 723 21 February Update 2011

14 26-Apr-11 15-Apr-09 26-Apr-11 17-May-11 571 6295 39 762 21 March/April Update 2011

Note – Activity Count does not change within updates

Schedule generates a Cumulative Delay Chart

Delay Analysis Organization with the Schedule Log

Page 38: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

• Add Columns to Schedule Log for Delays

38

Delay Analysis Organization with the Schedule Log

Page 39: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

• Chart Cumulative Delays directly from Schedule Log

39

Delay Analysis Organization with the Schedule Log

Page 40: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Chart Cumulative Delays – Overlay known delay event timeframes

40

Delay Analysis Organization with the Schedule Log

Page 41: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Chart Cumulative Delays – Label known delay timeframes

41

Delay Analysis Organization with the Schedule Log

Page 42: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Annotate Cumulative Delays

42

Period of possible concurrent submittal problems

Delay Analysis Organization with the Schedule Log

Page 43: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Chart Cumulative Delays – Note any general issues/concerns

43

Shows two schedules with same data date & different EF dates

Could be acceleration or mistake, but worthy of investigation?

Delay Analysis Organization with the Schedule Log

Page 44: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Chart Cumulative Delays – Identify specific delay/acceleration concerns

44

No overall delay due to IT design

Delay Analysis Organization with the Schedule Log

Page 45: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Chart Cumulative Delays – Identify specific delay/acceleration concerns

45

Period of possible concurrent production problems

Delay Analysis Organization with the Schedule Log

Page 46: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Delay Analysis Organization with the Schedule Log

Chart Cumulative Delays

46

Shows two schedules with same data date & different EF dates

No overall delay due to IT design

Period of possible concurrent submittal problems

Period of possible concurrent production problems

Delay Analysis Organization with the Schedule Log

Page 47: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Chart Cumulative Delays– Only provides simplified overview for discussion

• Shows schedule results with no research– Can show if analysis will be dealing with simple delay– Helps expose more complicated analysis needs

• Acceleration/mitigation• Concurrency • Disruption?

– Also helps quickly point out “normal” production for use in Measured Mile analysis of disruption

47

Delay Analysis Organization with the Schedule Log

Page 48: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Another Example of Annotated Cumulative Delay Chart

48

Delay Analysis Organization with the Schedule Log

Page 49: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Another Example of Annotated Cumulative Delay Chart

49

Delay Analysis Organization with the Schedule Log

Page 50: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org50

Dual-Tracking Schedule Update

Page 51: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Dual-Tracking Schedule Logo Background – Shortcomings of traditional update specs.

o Do not require pure updateo Do not require comparison of actual progress to

planned progresso Do not promote accountability to meet the reported

plano Do not promote accountability report actual

sequencing

51

Page 52: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Dual-Tracking Schedule Logo Background – Idea of dual-tracking, or dual-update

o Engaged to help develop and implement a scheduling and monitoring specification tool by the Federal Bureau of Prisons (FBOP) in ~ 2001 and the GSA in ~ 2002

o Experience from the “Big Dig” provided basis

52

Page 53: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Dual-Tracking Schedule Log (Cont.)

o Background – First started using on United States Federal Courthouse in Youngstown, OH.

o Utilized by GSA Region 5 starting in ~ 2002 o Generally required by the GSA national

scheduling specifications for major capital projects since ~ 2003

53

Page 54: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Dual-Tracking Schedule Log (Cont.)

o Background – Key factors for successo Provides timely, accurate, relevant

information to make informed business decisions regarding time, money, and claims

o Provides focus and accountability on the responsible parties to solve issues quickly and timely, and provides a historical record of critical paths and near critical paths

54

Page 55: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Dual-Tracking Schedule Log (Cont.)o Result is a schedule log with two lines per

update that highlights differences between two and provides a more accurate representation of project schedule status.

o Provides focus on the results of revisions incorporated into schedule updates.

55

Period Data Date Schedule Filename

Update or Revision

Contract SC Date SC Date Time Gain or

Loss (cd)Net Time Gain

or Loss (cd)

Cumulative Time Gain or

LossReason Responsible

Party Notes

Baseline 8/20/07 BOAC Baseline 7/22/2010 7/22/2010 0 0 0 1 7/7/08 CS02 Update 7/22/2010 12/22/2010 153 steel erection & monumental stair shop dwgs Contractor1 7/7/08 B002 Revision 7/22/2010 8/24/2010 (120) 33 33 logic revision for Mon Stair SDs Contractor forecasted recovery2 8/1/08 CS03 Update 7/22/2010 9/10/2010 17 steel & SOD Level 1 Contractor

2 8/1/08 B003 Revision 7/22/2010 9/15/2010 5 22 55 added a crew restraint for Electrical SOD Rough in Floor 2 Part A to be dependant on Floor 1 Part B Contractor

this crew restraint was not in the baseline schedule BOAC

3 9/2/08 CS04 Update 7/22/2010 9/29/2010 14 SOD Level 2 Contractor3 9/2/08 B004 Revision 7/22/2010 9/24/2010 (5) 9 64 Logic revision Contractor ajdusted for OOS progress4 10/1/08 CS05 Update 7/22/2010 11/12/2010 49 1st Floor layout & HVAC rough-in; Fire Alarm Shop Dwgs Contractor4 10/1/08 B005 Revision 7/22/2010 8/31/2010 (73) (24) 40 Logic revision Contractor Revised forecasted work sequences

5 11/3/08 CS06 Update 7/22/2010 9/22/2010 22 Electrical Riser Drawings, MEP Coordination Drawings, Structural Steel & Concrete Placement

Contractor

5 11/3/08 B006 Revision 7/22/2010 8/30/2010 (23) (1) 39 Logic revision to Coordination Dwg Submittals Contractor Revised forecasted work sequences6 11/3/08 P007 Update 7/22/2010 9/27/2010 28 Structural Steel fabrication: Elevator Submittals Contractor

6 11/3/08 B007 Revision 7/22/2010 7/22/2010 (67) (39) 0 Recovery schedule revised work sequences HVAC; OHRI; Elevators Contractor Revised forecasted work sequences

7 1/1/09 CS08 Update 7/22/2010 7/28/2010 6 Elec/FA OHRI Lvel 1 & 2 Contractor

7 1/1/09 B008 Revision 7/22/2010 7/22/2010 (6) 0 0 Logic revision ContractorRevised Dur activitiy 9910167; delete Preds for 3015200

8 2/2/09 CS09 Update 7/22/2010 8/11/2010 20 Masonry Walls at Mech Spaces levels 1-4. Contractor8 2/2/09 B009 Revision 7/22/2010 7/22/2010 (20) 0 0 Logic revisions for OOS & Mech OHRI. Contractor Revised forecasted work sequences

Page 56: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org56

There is a simple way for schedulers to create a pure update at the end of the month.

Export progress (actual starts, actual finishes, percent completes) from the new updated/revised schedule into a spreadsheet.

Copy the previous update and rename the file. Import progress from the spreadsheet into the new file. Change the data date to reflect the new update data date. Calculate the schedule. Run a compare program (Digger) to ensure no other revisions are included in the

pure update except for actual starts, actual finishes and percent complete.

Page 57: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org57

Export progress (actual starts, actual finishes, percent completes) from the new updated/revised schedule into a spreadsheet.

Page 58: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org58

Title goes here

Page 59: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org59

Page 60: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org60

Copy the previous update and rename the file.

Import progress from the spreadsheet into the new file.

Page 61: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org61

Page 62: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org62

Page 63: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org63

Change the data date to reflect the new update data date.

Calculate the schedule.

Run a compare program (Digger) to ensure no other revisions are included in the pure update except for actual starts, actual finishes and percent complete.

Page 64: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org64

Page 65: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org65

Page 66: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Comments

Progress should be analyzed first, leaving all other non-progress changes for the bifurcation

Non-progress revisions include:– Addition or deletion of activities.– Split or combined activities, using new activity IDs.– Addition or deletion of logic links.– Changes to lag value or logic links.– Addition, deletion or changes to constraints.– Changes to OD.– Increase in RD such that RD becomes greater than OD.– Changes to calendar assignments.– Changes to holiday assignments within a pre-existing

calendar.

Page 67: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

When Excel Export Fails

Sometimes the export fails repeatedly, especially with large schedules– If so, use Global Changes to import data

• Actual Start dates• Actual Finish dates• Remaining Duration

Page 68: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Using Global Changes

Actualized activities in the future will skew results– Use Global Changes to correct any RDs made to activities not

actualized (done by mistake fairly often)– Don’t forget to change the Data Date for the next update

Page 69: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Analysis Using P6

Primavera Project Management is more difficult to use with analysis bifurcating the update– May still be done using User Defined Fields (UDF)

Page 70: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Analysis Using P6

Requires storing data in the UDF using the Update Options

Page 71: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Forensic Schedule Analysis RP

This technique is covered in the AACE International Recommended Practice No. 29R-03, Forensic Schedule Analysis– Separates progress in each update– Relies upon validity of both as-built and as-planned

portions of schedule– Initial conclusions are drawn from the schedule,

which can be misleading• Critical that research is done to verify schedule

conclusions

Page 72: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Basic Methods: Observational, Dynamic

3.4. Dynamic – Contemporaneous “Split” (Bifurcated Contemporaneous Period)– Applicable on complicated projects– Uses contemporaneous updates as new baselines– The “split” separates Logic changes from Actual

Progress

Page 73: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Update Schedule Validation

Recommendations– Assemble all officially submitted updates (or updates used to

manage project)– Review consistency of as-built actual dates on an activity basis

from update to update, verify with documentation– Review validity of as-planned portion of schedule– Verify consistency of calculation mode from update to update

(RL/PO)– Document & provide basis for all schedule changes affecting

the Longest Path or CP– If possible, check RD & %C for accuracy

Page 74: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Basic Methods: Observational, Dynamic

5.3 Source Data Reliability– How much is available?

3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8

Baseline Schedule Need Need Need Need

Schedule Updates Need Need

As-Built Record Need Need Need Need

Source Schedules or Data

M E T H O D

Page 75: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

Basic Methods: Observational, Dynamic

3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8

Non-Compensable Time Extension OK OK OK OK OK OK OK OK

Compensable Delay OK OK OK OK OK OK

Right to Finish Early Compensable Delay OK

Entitlement to Early Completion Bonus OK OK OK OK OK OK OK OK

Disruption Without Project Delay OK OK OK OK OK OK OK

Constructive Acceleration OK OK OK

Forensic Use of Analysis

M E T H O D

• 5.3 Use of analysis– What can this type of analysis conclude?

Page 76: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org76

The Schedule Notebook

Page 77: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

The Schedule Notebook

o Old School Organizational Toolo For the project scheduler, engineer or

project managero Solely a reference to:

o Look up schedule statuso Have specs and other authoritative data

handyo Place to keep schedule logo Place to keep current schedule(s)

77

Page 78: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org

The Schedule Notebook (cont.)

o Schedule Notebook Organizationo Three ring bindero Tabs:

o Award/NTP (official documents)o Contract Milestones (from specs and drawings)o Schedule Specificationo Schedule Logo Baseline (Original + any recovery schedule

baselines)o Updates (As room allows; including narratives.

Include at least a longest path report.)o Project Control Reports o Other/Notes

78

Page 79: Use Of Schedule Logs   2012 Pmi Scop Conference

scheduling.vc.pmi.org79

Questions?