Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

52
www.dot.state.pa.us USE OF POLYURETHANE GROUT FOR CONCRETE PAVEMENT SLAB STABILIZATION Indiana County District 10- 0 Lessons Learned 1

description

Lessons Learned. Indiana County. Use of Polyurethane Grout for Concrete Pavement Slab Stabilization. District 10-0. SR 422 Sec. 6 Indiana By Pass Slab Stabilization Project. Existing Pavement Conditions. Original construction 1995 4 lane Limited Access Highway - PowerPoint PPT Presentation

Transcript of Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

Page 1: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

USE OF POLYURETHANE GROUT FOR CONCRETE PAVEMENT SLAB STABILIZATION

Indiana County

District 10-0

Lessons Learned

1

Page 2: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

SR 422 Sec. 6 Indiana By Pass Slab Stabilization Project

2

Page 3: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Existing Pavement Conditions

– Original construction 1995– 4 lane Limited Access Highway– Two 12 ft lanes each direction– Project length ~3miles– 12 lane miles treated– Shoulders 4 ft left, 10 ft right– 20 ft joint spacing

3

Page 4: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Existing Pavement Conditions cont.

– Pavement section• 10 inch unreinforced PCCP

– Subbase• 4 inch OGS• 4 inch 2A

– Joints are in good condition – Main Problems –

• Mid Bay Slab Cracks• Slab settlement• Rocking• Some pavement distress

4

Page 5: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

SR 422 Sec. 6 Mid-bay Crack Project

• Project traffic and Length

Direction ADT LengthEastbound 4841 3.07 milesWestbound 4920 3.06 miles

7% Trucks Total 12 lane miles

5

Page 6: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Slab Stabilization Scope of Work

– Slab Stabilization using Polyurethane Grout

– Slab Stabilization using Cement Grout(Comparison Section)

– Concrete Pavement Patching full depth– Dowel Bar Retro Fit Repairs– Crack Cleaning and Sealing– Joint Cleaning and Sealing

6

Page 7: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Project Overview

7

Page 8: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

The existing joints are in Good Condition

8

Page 9: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Some Joint Distress but not extensive

9

Page 10: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Mid-Bay Cracks

10

Page 11: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Mid-Bay Cracks

11

Page 12: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Mid-bay slab cracking

10 in PCCP

4” OGS

4” 2A

Subgrade (Stiff to Hard Gravelly Silty Clay)

20 ft Joint Spacing

Mid-bay Crack

12

Page 13: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Slab Curling

10 in PCCP

4” OGS

4” 2A

Subgrade (Stiff to Hard Gravelly Silty Clay)

20 ft Joint Spacing

Mid-bay Crack

13

Page 14: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

OGS Degradation

10 in PCCP

4” OGS

4” 2A

Subgrade (Stiff to Hard Gravelly Silty Clay)

20 ft Joint Spacing

Mid-bay Crack

14

Page 15: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Dowel Bar Retrofit - Grout Stabilization

10 in PCCP

4” OGS

4” 2A

Subgrade (Stiff to Hard Gravelly Silty Clay)

20 ft Joint Spacing

Mid-bay Crack

15

Page 16: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Comparison of distress between Travel Lanes and Passing Lanes

Travel Lanes Passing Lanes

Eastbound Westbound Total Eastbound Westbound Total

DBR* 55 100 155 8 10 18

Full Depth Patchs

48 231 279 3 14 17

Total 103 331 434 11 24 35

Quantities as originally designed

*DBR Dowel Bar Retrofits 16

Page 17: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Grout Hole Spacing

20 ft 20 ft

12 ft

12 ft

Traffic

3ft

6ft6ft

17

Page 18: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Drilling Grout Holes

18

Page 19: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us19

Page 20: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us20

Page 21: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us21

Page 22: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us22

Page 23: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us23

Page 24: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Mix Ratio

Resin Part Density Pounds/ US Gallon

A Isocyanate FE 800 A-D 10.16B Elastopor FE 663.01 8.95

Mix Ratio 50/50 by volumeB/A=8.95/10.16 = 0.88 by density

24

Page 25: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us25

Page 26: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us26

Page 27: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us27

Page 28: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us28

Page 29: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us29

Page 30: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us30

Page 31: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us31

Page 32: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us32

Page 33: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us33

Page 34: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us34

Page 35: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Grout Application Rate Per Lineal Foot Of 12ft wide Pavement Slab

Pounds per Lineal Foot

Dollars per Lineal Foot

Lowest 9.5 lb/Lf $40.85Highest 15.0 lb/Lf* $64.50Average 13.0 lb/Lf $55.90

*Highest application rate occurred in areas where slab was raised ½ to 1 inch.

Unit Bid Price of Material is $4.30/pound

35

Page 36: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Grout Application Rate Per Hole

Pounds Per Hole Dollars Per HoleLowest 16 lb/Hole $68.80/HoleHighest 35 lb/Hole $150.50/HoleAverage 23 lb/Hole $98.90/Hole

Unit Bid Price of Material is $4.30/pound

36

Page 37: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Application Rate Per Day With 4 Trucks

Pounds Per Day Dollars Per DayGood Day 34,000 $146,000Bad Day* 11,000 $47,300Average 23,000 $98,900

* Equipment break down and or low air temperatures

37

Page 38: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Total Polyurethane Grout Cost

• Original Estimated Quantity380,000 pounds $1.63M

• Actual Quantity627,700 pounds $2.67M

38

Page 39: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Iowa State Mobile Lab

39

Page 40: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Iowa State Mobile Lab

40

Page 41: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Iowa State University- an overview of testing and some very preliminary results

• Tests were done before and after injection at both pavement joints and at mid bay cracks

• Falling Weight Deflectometer (FWD) testing measured both modulus and deflection giving joint efficiency

• Various subgrade density and modulus testing devices were used

• Load transfer efficiency• Pavement Elevation profile• Insitu densities• Subbase gradation• Subgrade Temperature probe

41

Page 42: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

SR-422 WB

Shoulder

Traffic Lane

Passing Lane

Shoulder

ABCD

Elevation Profiles

Easting (m)

650100 650110 650120 650130

Nor

thin

g (m

)

4497980

4497985

4497990

4497995

4498000

4498005

4498010

4498015

4498020

4498025FWD Before and After StabilizationFoam Injection LocationsCracksFWD After Stabilization

SR-422 WB

10 15 20 25 30 35 40 45

Def

lect

ion,

D0 (

mm

)

0.0

0.1

0.2

0.3

0.4

0.5 Sur

face

Mod

ulus

, EFW

D-K

3 (M

Pa)

0

1000

2000

3000

4000

5000

6000

10 15 20 25 30 35 40 45

Def

lect

ion,

D0 (

mm

)

0.0

0.1

0.2

0.3

0.4

0.5 Sur

face

Mod

ulus

, EFW

D-K

3 (M

Pa)

0

1000

2000

3000

4000

5000

6000

D0 Pre-StabilizationD0 Post-StabilizationEFWD Pre-StabilizationEFWD Post-Stabilization

Applied Load (Average) = 37.2 kN

Applied Load (Average) = 56.1 kN

10 15 20 25 30 35 40 45

Def

lect

ion,

D0 (

mm

)

0.0

0.1

0.2

0.3

0.4

0.5 Sur

face

Mod

ulus

, EFW

D-K

3 (M

Pa)

0

1000

2000

3000

4000

5000

6000

Applied Load (Average) = 75.3 kN

Distance (m)

10 15 20 25 30 35 40 45

Def

lect

ion,

D0 (

mm

)0.0

0.1

0.2

0.3

0.4

0.5 Sur

face

Mod

ulus

, EFW

D-K

3 (M

Pa)

0

1000

2000

3000

4000

5000

6000

Applied Load (Average) = 106.5 kN

JointCrack

42

Page 43: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Example of Data presentation

10 15 20 25 30 35 40 450

20

40

60

80

100

Pre-StabilizationPost-Stabilization

10 15 20 25 30 35 40 45

Load

Tra

nsfe

r Effe

cien

cy, L

TE (%

)

0

20

40

60

80

100

Pre-StabilizationPost-Stabilization

Applied Load (Average) = 56.3 kN

Joint

Crack

Applied Load (Average) = 37.4 kN

Joint

Crack

Distance (m)

10 15 20 25 30 35 40 450

20

40

60

80

100

Pre-StabilizationPost-Stabilization

Applied Load (Average) = 106.2 kN

Joint

Crack

10 15 20 25 30 35 40 450

20

40

60

80

100

Pre-StabilizationPost-Stabilization

Applied Load (Average) = 75.6 kN

Joint

Crack

PennDOT SpecificationTarget LTE = 65%

PennDOT SpecificationTarget LTE = 65%

PennDOT SpecificationTarget LTE = 65%

PennDOT SpecificationTarget LTE = 65%

43

Page 44: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

10 15 20 25 30 35 40 450

20

40

60

80

100

Pre-StabilizationPost-Stabilization

10 15 20 25 30 35 40 45

Load

Tra

nsfe

r Effe

cien

cy, L

TE (%

)

0

20

40

60

80

100

Pre-StabilizationPost-Stabilization

Applied Load (Average) = 56.3 kN

Joint

Crack

Applied Load (Average) = 37.4 kN

Joint

Crack

Distance (m)

10 15 20 25 30 35 40 450

20

40

60

80

100

Pre-StabilizationPost-Stabilization

Applied Load (Average) = 106.2 kN

Joint

Crack

10 15 20 25 30 35 40 450

20

40

60

80

100

Pre-StabilizationPost-Stabilization

Applied Load (Average) = 75.6 kN

Joint

Crack

PennDOT SpecificationTarget LTE = 65%

PennDOT SpecificationTarget LTE = 65%

PennDOT SpecificationTarget LTE = 65%

PennDOT SpecificationTarget LTE = 65%

44

Page 45: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Some key findings are as follows:

• Load transfer efficiency for the joints is about 79% before and after stabilization

• Load transfer efficiency for the mid-panel cracks is about 43% before stabilization and 88% after stabilization

• Corner slab deflections post-stabilization are less than 0.5 mm

45

Page 46: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Slab elevation changes

• There was an elevation change of about 0.25in. on average in test section 6

• There was an elevation change of about 0.8in on average in test section 7. This section also took twice as much material

46

Page 47: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Comparison with Portland Cement Grout

• The polyurethane performance will be compared to a 1,300 foot (~67 slabs) test section which will be grouted using portland cement grout during the construction season of 2010.

47

Page 48: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Summary and observations

• The OGS showed signs of particle degradation allowing for some slab rocking

• The 2A appeared to be stable

• The subgrade was stiff to hard

• The mid-bay cracks appear to be due to slab curling.

• The polyurethane grout is effective in stabilizing slab movements

48

Page 49: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Summary and Observations Cont.

• The Grout was effective at penetrating the clean OGS layer but it did not penetrate the 2A layer

• The grout is effective at lifting the slabs but it appeared difficult to accurately control the movement

• The grout coated the bottom of the slab with ¼ to 1 inch thick layer

• The grout did not block the drainage system

49

Page 50: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Based on the observations and information collected the following contract changes have been made

• We increased the polyurethane quantity to include total grouting of the passing lane

• We reduced the quantity of full depth patches and increased the quantity of DBRs. – The DBRs cost about ½ the amount of a patch and

reduces the number of pavement joints.

• We are considering the elimination of the diamond grinding

50

Page 51: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Based on the observations and information collected the following contract changes have been made

• The District has modified the special provision base on information from this project. Major changes include adding more quality control procedures

• Iowa State will monitor the grout performance over next three years

51

Page 52: Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

www.dot.state.pa.us

Use of Polyurethane Grout for Concrete Pavement Slab Stabilization

• Thank You

• Questions?

52