1 USAF Utah Test and Training Range (UTTR) Hard-Case Bomb and Bomb Dummy Unit Recycling Project 2006 Performed by: CH2M HILL Inc. & Bering Sea Eccotech, Inc.

Transcript of USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility,...

Page 1: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

1

USAF Utah Test and Training Range (UTTR)

Hard-Case Bomb and Bomb Dummy Unit Recycling Project

2006Performed by:

CH2M HILL Inc.&

Bering Sea Eccotech, Inc.

Page 2: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

2

North Gate Recycle Facility,Utah Test & Training Range -SouthHill Air Force Base, Utah

75 CEG/CEVREnvironmental Management DivisionCivil Engineer Group Contract No: F42650-03-D-0002

Delivery Order 0013

Page 3: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

3

Page 4: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

4

Project Objectives• Demilitarization of 2,545 hard case MK-80 series

Bombs to allow metal to be recycled

• Demilitarization of approximately 300 tons of Bomb Dummy Units (BDU) – 33’s

• Inspection, certification and verification of demilitarized metals for recycling

• Classification and Segregation of other Munitions and Munitions Related Items for disposition by USAF

Page 5: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

5

Page 6: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

6

Page 7: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

7

MK 80 Series Hard Case Bomb Operational Processes

1. Confirm explosive counter charge to tail and thermal cut to nose

2. Sheer Hard Case MK 80 series bombs3. Separate internal fill and plumbing form

casings 4. Perform I00% visual inspection of casing5. Segregate and Secure Casings for Smelting

Page 8: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

8

Page 9: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

9

Page 10: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

10

Page 11: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

11

Page 12: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

12

Page 13: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

13

Page 14: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

14

Mk 80 Series Total Salvable Metal

• 2,545 MK 80 Series Hard Case Bomb metals = 515.81 tons in salvage weight

• 20 yard roll-offs averaged 16 tons per load

• 33 transportation loads

Page 15: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

15

Bomb Dummy Unit (BDU) 33’s Preparation for Recycling

1. Segregate BDU 33’s from other Munitions and Munitions' related items and target debris

2. Process BDU 33’s cast iron bodies to 4-inch minus

3. Separate pot metals (tails) lugs, cartridge cases, and plungers from cast iron

4. Process separately MK106 and other Munitions and Munitions related debris for crushing/shredding for recycling

5. Stage cast iron for reuse by USAF

Page 16: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

16

Page 17: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

17

Page 18: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

18

Page 19: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

19

Page 20: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

20

Page 21: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

21

Page 22: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

22

Page 23: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

23

Page 24: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

24

Page 25: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

25

Page 26: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

26

Page 27: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

27

Page 28: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

28

BDU 33’s Demilitarized Weights

BDU-piles and Containers 372.19 Tons– 323. 75 tons cast-iron– 1. 13 tons aluminum parts (carts)– 38. 30 tons tail fins (pot metal)

363. 18 tons

Other pile munitions & munitions related Items 9. 01 tons

– 372.19 Tons

Page 29: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

29

Qualified Scrap Recycler

Page 30: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

30

Summary

• Demilitarization efforts = 1, 775,620 lbs of metals

Demilitarize 2,545, Mk 80 series bombs– 515.81 tons of recyclable steel

Demilitarize 300 tons of BDU 33’s– 363 tons (actual)– 9 tons of other munitions/related items– 372 tons total

Page 31: USAF Utah Test and Training Range (UTTR) Hard-Case Bomb ...€¦ · 2 North Gate Recycle Facility, Utah Test & Training Range -South Hill Air Force Base, Utah 75 CEG/CEVR Environmental

31

QUESTIONS