U.S. REGION I - US Environmental Protection Agency · Dorr-Oliver Energy Research Corporation Ferro...
Transcript of U.S. REGION I - US Environmental Protection Agency · Dorr-Oliver Energy Research Corporation Ferro...
-
U.S. ENVIRONMENTAL PROTECTION AGENCY REGION I
J.F.K. FEDERAL BUILDING, Boston, MA 02203
MEMORANDUM SDMS DocID
DATE: February 16, 1994
SUBJ: Final Acceptance of Cost Recovery Settlement Gallup's Quarry Superfund Site, Plainfield, CT
FROM: Margery Adams Miff Assistant Regional Counsel
Leslie McVickar Remedial Project "Manager'
TO: John P. DeVillars Regional Administrator
Attached for your signature is a "responsiveness summary" which relates to a cost recovery agreement under Section 122(h) of CERCLA for response costs incurred by EPA at the Gallup's Quarry Superfund Site, in Plainfield, Connecticut. This document represents the final step in approving this settlement, which was negotiated in the summer of 1993.
Briefly, the site is a former quarry that was used for illegal disposal of hazardous wastes for a nine month period in 19771978. Since that time, the State of Connecticut has undertaken a removal action to remove drums and obviously contaminated soils at the site; EPA performed preliminary studies to support a listing on the National Priorities List, and conducted a search for potentially responsible parties. The site was listed on the NPL in October 1989. EPA has identified 40 potentially responsible parties ("PRPs"), all of whom were customers of the sole transporter known to have disposed of wastes at the site.
Over the past summer, EPA negotiated with the PRPs, resulting in this cost recovery order and a companion agreement to perform the remedial investigation and feasibility study at the site. Twenty-three of the forty PRPs eventually settled, agreeing to pay $345,000 or 80% of EPA's past costs incurred as of February 28, 1993. Copies of the cost recovery settlement, and a September 3, 1993 memorandum containing a complete analysis of the settlement, are attached.
The Department of Justice approved the cost recovery agreement on November 1, 1993, and Acting Regional Administrator Keough signed it on November 18, 1993. Pursuant to Section 122(i) of CERCLA, the settlement was then published in the Federal Register and
-
comments were solicited. No comments were received by the close of the 30-day comment period.
Recommendation
Accordingly, we recommend that you sign the attached Responsiveness Summary, indicating that as EPA has received no comments indicating that the settlement is inappropriate, improper or inadequate, the settlement is accepted by EPA. Payment of the $345,000 amount will then be due from the settling PRPs in 45 days.
Please direct any questions concerning this matter to Margery Adams, Assistant Regional Counsel, at 565-3746.
-
i. /
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION I
In the Matter of:
GALLOP'S QUARRY SUPERFUND SITE
SETTLING PARTIES:
Acco-Bristol Division/Bristol Babcock Inc. American Cyanamid Company Bedoukian Research, Inc. Better Formed Metals/Illinois Tool Works Inc Bryant Electric, Inc. Connecticut Hard Rubber/CHR Industries, Inc. Consolidated Controls Corporation Dorr-Oliver Energy Research Corporation
Ferro Corporation
Instapak Corporation/Sealed Air Corporation Kanthal Corporation
King Industries, Inc. Pitney Bowes, Inc. Polymer Industries, Inc./Colonial Heights
Packaging Inc. Quality Rolling and Deburring, Inc. Reichhold Chemical, Inc. Risdon Manufacturing Company/Risdon Corp. R.T. Vanderbilt Company, Inc. Stamford Wall Paper Company, Inc. Union Carbide Corporation Warner Packaging Waterbury Plating Company
Proceeding Under Section 122(h)(l) of the Comprehensive Environmental Response, Compensation, and Liability Act, as amended, 42 U.S.C. 9622(h)(l)
US EPA Region I CERCLA Docket No. 1-93-1079
COST RECOVERY ADMINISTRATIVE AGREEMENT
It
-
-3
C.F.R. Part 300;
WHEREAS, EPA has provided the Settling Parties with summaries
and other documentation supporting these response costs;
WHEREAS, EPA alleges that the parties who have signed this
Agreement and who are listed in Appendix A ("Settling Parties") are
responsible parties pursuant to Section 107(a) of CERCLA, 42 U.S.C.
9607(a), and are liable for response costs incurred and to be
incurred at or in connection with the Site;
WHEREAS, the Settling Parties do not admit any of EPA's
allegations; and
WHEREAS, EPA and the Settling Parties desire to settle certain
claims arising from the Settling Parties7 alleged involvement with
the Site without litigation and without admission or adjudication
of any issue, of fact or law;
NOW, THEREFORE, EPA and the Settling Parties, in consideration
of the promises and covenants herein, and intending to be legally
bound hereby, agree as follows:
JURISDICTION
1. This Agreement is made and entered into by the United
States Environmental Protection Agency and the Settling Parties
whose names appear in Appendix A and who have executed the attached
signature pages. This Agreement concerns the recovery of costs
incurred by EPA at the Gallup's Quarry Superfund Site as of
February 28, 1993. The authority to enter into such an Agreement
is vested in the President by Section 122(h)(l) of CERCLA, 42
-
-5
with the Site as of February 28, 1993.
REIMBURSEMENT FOR RESPONSE COSTS
5. The Settling Parties shall make payment to EPA by
certified or cashier's check in the amount of $345,000 (the
"Settlement Payment") within forty-five (45) days after the
effective date of this Agreement in full satisfaction of EPA's
claim for response costs incurred at or in connection with the Site
through and including February 28, 1993.
STIPULATED PENALTIES ; "
6. If the Settling Parties fail to tender the ' entire
Settlement Payment within forty-five (45) days after the effective
date of this. Agreement, the Settling Parties shall collectively be
liable to pay the sums set forth below as stipulated penalties:
Period of Failure to Comply Penalty Per Day
1st - 7th day $1,000.00 8th - 14th day $2,000.00 each day thereafter $3,500.00
7. Any such penalty shall be due and payable within ten (10)
days of the receipt of a written demand from EPA. Payment for
.stipulated penalties shall be made as set forth in Paragraph 9
below. Penalties shall accrue regardless of whether EPA has
notified the Settling Parties of their failure to make a timely
payment.
8. In the event that the Settling Parties fail to pay
stipulated penalties as provided in Paragraphs 6 and 7, EPA may
http:3,500.00http:2,000.00http:1,000.00
-
-7
U.S. Environmental Protection Agency John F. Kennedy Federal Building, RCU-23
Boston, Massachusetts 02203
EPA'S COVENANT NOT TO SUE
10. In consideration, and upon payment, of the amounts
specified in Paragraph 5 of this Agreement, EPA agrees that such
payment shall represent full satisfaction of the United States7
claim against the Settling Parties for any and all civil liability
under Section 107(a) of CERCLA, 42 U.S.C. 9607(a), for
reimbursement of response costs incurred at or in connection with
the Site as of February 28, 1993. Nothing in this Agreement shall
'be construed to require EPA to enter into any later agreement with
respect to the Gallup's Quarry Superfund site with any Settling
Party, or to prevent EPA from performing any response actions at
the Site.
COVENANT OF THE SETTLING PARTIES
11. The Settling Parties hereby covenant not to sue the
United States for any claims related to or arising from this
Agreement, including any direct or indirect claim for reimbursement
from the Hazardous Substance Superfund established pursuant to 26
U.S.C. 9507. Nothing in this Agreement shall be deemed to
constitute preauthorization of a claim within the meaning of
Section 111 of CERCLA, 42 U.S.C. 9611.
-
-9
criminal, past or future, in law or in equity, which EPA may have
against any person, firm, corporation or other entity not a
signatory to this Agreement. Except as specifically set forth
herein, this Agreement shall not estop or limit any legal or
equitable claims of the United States against the Settling Parties,
their agents, contractors, or assigns, including but not limited
to, claims related to releases of hazardous substances or other
pollutants or contaminants.
PUBLIC COMMENT PERIOD
15. Final acceptance of this Agreement by EPA shall be
subject to Section 122(i) of CERCLA, 42 U.S.C. 9622(1), which
requires EPA to publish notice of the proposed settlement (the
Agreement) jji the Federal Register, to provide persons who are hot
parties to the proposed settlement an opportunity to comment on the
proposed settlement, and to consider comments filed in determining
whether to consent to the proposed settlement. After consideration
of any comments submitted during the thirty (30) day public comment
period held pursuant to Section 122(i) of CERCLA, EPA may withhold
consent to this Agreement if comments received disclose facts or
considerations which indicate that this Agreement is inappropriate,
improper or inadequate.
SEPARATE DOCUMENTS
16. This Agreement may be executed .in two or more
counterparts, each of which shall be deemed an original, but all of .
-
-li
the public comment period pursuant to Paragraph 15 has closed and
that comments received, if any, do not require modification of or
EPA withdrawal from this Agreement.
-
-12
IT IS SO AGREED.
U.S. ENVIRONMENTAL PROTECTION AGENCY
y By: _ _ ft
Regional AdministratorEPA Region J
Margery L. Adams Date Senior Assistant Regional Counsel
-
-14
GALLUP'S QUARRY SUPERFDND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT
LIST OF SETTLING PARTIES
Acco-Bristol Division/Bristol Babcock Inc. American Cyanamid Company Bedoukian Research, Inc. Better Formed Metals/Illinois Tool Works Inc, Bryant Electric, Inc. Connecticut Hard Rubber/CHR Industries, Inc. Consolidated Controls Corporation Dorr-Oliver Energy Research Corporation Ferro Corporation Instapak Corporation/Sealed Air Corporation Kanthal Corporation King Industries, Inc. Pitney Bowes, Inc. Polymer Industries, Inc./Colonial Heights
Packaging Inc. Quality Rolling and Deburring, Inc. Reichhold Chemical, Inc. Risdon Manufacturing Company/Risdon Corp. R.T. Vanderbilt Company, Inc. Stamford Wall Paper Company, Inc. Union Carbide Corporation Warner Packaging Waterbury Plating Company
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Name of Settling Party: BRISTOL BABCOCK INC.
By: Title: Secretary
Address: 425 Post Road Fairfield, CT
Date: August 20, 1993
Agent Authorized to Accept Service on Settling Party's Behalf:
Name: Title:
Address:
Telephone:
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Name of Settling Party: C Y T E C INDUSTRY S , a B u s i n e s s Uni t of American Cy a n'ar id Company
By: ^^N^S! -XSjuA f t Title: Vi rp Prp
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Robert H. Bedoukian, President Bedoukian Research, Inc. v_ Name of Settling Party:
By: Title: President
Address: 21 Finance Drive Danburv. CT 06810
Date:
Agent Authorized to Accept Service on Settling Party's Behalf:
Name: Title:
Address :
Telephone:
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Illinois Tool Works Inc. on behalf of its Better Formed Metals division
Name of Settling Party;
By:Title:
Address: 3600 W. Lake Avenue Glenview. IL 60025
Date: 8/20/93
Agent Authorized to Accept Service on Settling Party's Behalf:
Name: Title:
Philip S. Dallosto
Address:
Telephone: 708-657-4199
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Westinghousc Electric Corporation (d.b.a. Bryant Electric, Inc.) Name of Settling Party:
By: Title: Mgr., Corporate Environmental Activities
Address: Environmental Affairs 11 Stanwix Street Pittsburgh, PA 15222
Date: August 18. 1993
Agent Authorized to Accept Service on Settling Party's Behalf:
Name: Prentice Hall Corporation Title:
Address: 30 High Street Hartford. CT 06103
Telephone: 800/221-0770
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Name of Settling Party: CHR industries, inc.
By: Title: President
Address: 407 East street New Haven. fT 0650Q
Date: AM gust 17.
Agent Authorized to Accept Service on Settling Party's Behalf:
Name: Daniel P. Beharrv Title: Counsel
Address: Wiggin & Dana, One CitvPlace Hartford, CT 06103-3403
Telephone: (203) 297-3724
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Of Settling Party: Eaton Corporation ( Con
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Dorr-Oliver (BP America Inc.) Name of Settling Party:
By: Title: __
Address: 200 Public Square: 39-B-5300 Cleveland. Ohio 44114-2375
Date:
Agent Authorized to Accept Service on Settling Party's Behalf:
Name: Charles R. Pinzone Title: Attorney
Address: 200 Public Square. 39-B-5300 Cleveland. Ohio 44114-2375
(216) 586-8298 Telephone:
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Name Of Settling Party: Energy Research Corporation
By: r?j*L*^--z/
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Ferro Corporation Name of Settling Party:
By: Title: R. J.//finch, Vice President. Specialty Plastics
Address: Ferro Corporation JOUU Lakeside Cleveland, Ohio 44114 '
Date: / 1
Agent Authorized to Accept Service on Settling Party's Behalf:
Name: I. Monica Olszevski, Esq. Title: Attorney for Ferro Corporation
Address: 1000 Lakeside Cleveland, Ohio 44114
Telephone: 216-641-8580 x6214
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Name of Settling Party; SEALED AIR CORPORATION
By: Title: Senior Vice President-Firtafice
Address: Park 80 East Saddle Brook/ New Jersey 07662
Date:
Agent Authorized to Accept Service on Settling Party's Behalf;
Name: Robert M. Grace/ Jr. Title: General Counsel and Secretary
Address: Park 80 East Saddle Brook, New Jersey 07662
Telephone: 201-703-4150
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Name of Settling Party: THE KANTHAL CORPORATION
By: Title: President
Address: 119 wooster^Street. Bethel, CT 06801
Date: August 13, 1993
Agent Authorized to Accept Service on Settling Party's Behalf:
Name: Sanford Dean Kaufman, Esq. or Michael R. Kaufman/ Esq. Title: Attorneys
Address: Jones/ Damia/ Kaufffian Wellmaru Borofsky & Stelljes 29 Sugar Hollow Road/ Danbury/ CT 06810
Telephone: f203) 744-1313
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Name of Settling Party: King Industries, Inc.
By: Title:
Address: Science Road Norwalk. CT 06852
Date: August 23. 1993
Agent Authorized to Accept Service on Settling Party's Behalf:
Name: Mark V. Burns Title: Attorney.
Address: 315 Post Road West Westport. CT 06881
Telephone: 203-454-2788
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Name of Settling Party: PITNEY BOWES INC.
By: Title: ASSOCIATE GENERAL COUNSEL & ASSISTANT SE
Address: i FTMranTT prun STAMFQD. CT 06926-0700
Date: '/ 7 7
Agent Authorized to Accept Service on Settling Party's Behalf:
Name: THOMAS HARRISON Title: J>ARTNER
Address: DAY. KFBKY & CITY PLACED HARTFORD, CT 06103-3499
Telephone: 2oy.?7S-(U8n
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Name of Settling Party: Colonial Heights Packaging Inc.
By: Diane M. McAdams Title: Secretary
Address: 120 Par* Avenue New YorK, NY
Date: August 19, 1993
Agent Authorized to Accept Service on Settling Party's Behalf;
Name: Arthur A. Vogel, Jr. Title: Attorney
Address: Quarles & Brady 411 K. Wisconsin Avenue Milwaukee, WI 53202-4497
Telephone: (414) 277-5545
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Name of 'settling Party: Quality Rolling & Deburring. Inc.
By:
Title:
Address: 135 South Main Street Thomaston. CT
Date: August 23. 1993
Agent Authorized to Accept Service on Settling Party's Behalf:
Name: Edward J. Peters, Jr., P.C. Title:
Address: 595 Main Street ~ P. 0. Box 99 Portland, CT06480-0099
Telephone: 203-342-3535
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
/7
Name of settling Party: r{(
Title: Director. Environment, Health & Safety Address : P. 0. Box 13582 _
Durham, NC 27709-3582 _
Date: August 18. 1993 _
Agent Authorized to Accept Service on Settling Party's Behalf:
Name: CT Corporation Systems ___ Title:
Address: 1633 Broadway New York. Nev York 10019
Telephone: (212) 664-1666
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Name of Settling Party: Risdon Corporation
By: Title: Vice President and Corporate Controller
Address: One Risdon Street Nauqatuck, CT 06770
Date: August 17. 1993
Agent Authorized to Accept Service on Settling Party's Behalf:
Name: Daniel P. Beharrv Title: Counsel
Address: Wiooin & Dana '. ri t-vP1 a
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Name of Settling Party:
By: Title:
Address:
Date:
R. ,T. V.
Hugh B. Vanderbilt, Jr. Exec. Vice President, Mining & Manufacturing 30 Winfield Street Norwalk, Connecticut 06855
August 20, 1993
Agent Authorized to Accept Service on Settling Party's Behalf: Howard A. Neuman, Esq.
Name: Satterlee Stephens Burke & Burke Title: Partner .
Address: 230 Park Avenue. Suite 1130 New York. New York 10169
Telephone: (212) 818-9200
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Name of Settling Party:
By: Title:
Address:
Date:
Agent Authorized to Accept
Name: Title:
Address:
Stamford Wall Paper Company, Inc.
John L. Jones, Jr. President 911 Hope Street Stamford, Ct. 06907
August 18, 1993
Service on Settling Party's Behalf:
John L. Jones, Jr. President c/o Stamford Wall Paper Company, Inc. 911 Hope Street. Stamford. Ct. 06907
Telephone: 323-7761
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Name of Settling Party: j L6rt()c
By:
Title:
Address:
Date: '
Agent Authorized to Accept Service on Settling Party's Behalf:
Name: UhrisWiL^' J. ( DLMAJ _ Title: ~~
Address: f.T
o
Telephone: 7fl^ -7^ -$"7
-
GALLUP'S QUARRY SUPERFUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
IT IS SO AGREED:
Name of Settling Party:
By: Title:
Address:
Date:
Agent Authorized to Accept Service on Settling Party's Behalf:
Name: FfafvJ Title:
Address: ST
Telephone:
-
GALLUP'S QUARRY SUPERTUND SITE COST RECOVERY ADMINISTRATIVE AGREEMENT U.S. EPA REGION I CERCLA DOCKET NO. 1-93-1079
ZT IS 60 AGREED:
Name of Settling Party: NARDO2Z1 REALTY COMPANY
X F/K/A WAJERBURY PLATING COMPANY^
By: PRESIDENT
Address: 66 GREEN HILL ROAD MIDDLEBURY. CONNECTICUT 06762
Date: AUGUST i?. 1993
Agent Authorized to Accept Service on Settling Party's Behalf:
Naae: JAMES W. WALSH Title: A T T O R N E Y
Addre: 103MAIN STREET . P.O. BOX OT2 ANSQNIA, CONNECTICUT "
Telephone: 735-332t
-
-1
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION I
IN THE MATTER OF: ) )
GALLUP'8 QUARRY SUPERFUND SITE ) U.S. EPA )
Plainfield, Connecticut ) CERCLA DOCKET ) NO. 1-93-1080 )
SETTLING PARTIES: ) )
Acco-Bristol Division/Bristol Babcock Inc. ) American Cyanamid Company ) Bedoukian Research, Inc. ) Better Formed Metals/Illinois Tool Works Inc.) Bryant Electric, Inc. ) Connecticut Hard Rubber/CHR Industries, Inc. ) Consolidated Controls Corporation ) Dorr-Oliver )
Energy Research Corporation ) Ferro Corporation ) Instapak Corporation/Sealed Air Corporation ) Kanthal Corporation ) King Industries, Inc. ) Pitney Bowes, Inc. ) Polymer Industries, Inc./Colonial Heights )
Packaging Inc. ) Quality Rolling and Debarring, Inc. ) Reichhold Chemical, Inc. )
Risdon Manufacturing Company/Risdon Corp. )
R.T. Vanderbilt Company, Inc. ) Stamford Wall Paper Company, Inc. ) Union Carbide Corporation ) Warner Packaging ) Waterbury Plating Company )
) )
Proceedings relating to a settlement ) agreement under Section 122(d)(3) for action ) under Section 104(b) of the Comprehensive ) Environmental Response, Compensation and ) Liability Act of 1980, as amended, 42 U.S.C. ) Section 9601 et sea. )
-
TABLE OF CONTENTS
JURISDICTION 4
PARTIES BOUND 4'
Engagement of the Settling Parties' Contractor;
Monthly Progress Reports .... 21':
Quality Assurance/Quality Control; Health and Safety
STATEMENT OF PURPOSE 6
EPA'S FINDINGS OF FACT 6
EPA'S DETERMINATIONS 9
ORDER 11
Implementation . 11
Designation of the Settling Parties' Project Coordinator 14
Designation of EPA's Remedial Project Manager 15
Place and Manner of Notice 16
Observation of the Settling Parties' RI/FS Activities .... 17
Necessity of Formal Approval . . . 18
Submissions Requiring EPA Approval . . 18
Availability of RI/FS Data 22
Compliance 22
Split Sampling 23
Record Preservation ... 24
Confidentiality Claims 25
Site Access 25
Endangerment and Emergency Response 27
Use of Resource Conservation and Recovery Act Facilities . . 28
Other Laws 29
Public Review of RI/FS Report 29
-
-3
Community Relations 30
Certification of the Settling Parties'
Appendices
Financial Assurance; Insurance 30
Reimbursement of EPA Response and Oversight Costs 32
Excuses for Delays in Performance 34
Dispute Resolution 36
Stipulated Penalties for Delays in Performance ' 37
Civil Penalties for Noncompliance 40
Performance of the Work Activities 40
Covenant Not to Sue 41
Denial of Liability 41
EPA's Reservation of Rights . . 42
Settling Parties' Reservations of Rights 44
Other Claims 45
Indemnification 46
Waiver of Settlement Conference 47
Notice to the State and Federal Natural Resource Trustee . . 47
Modification of Order . . . 47
Separate Documents 48
Effective Date; Computation of Time . 48
*
Appendix A (Statement of Work)
Appendix B (List of Settling Parties)
-
-4
JURISDICTION
1. This Administrative Order by Consent (Order) is entered into
voluntarily by and between the United States Environmental
Protection Agency (EPA) and all of the Settling Parties listed in
the caption above (hereinafter the Settling Parties). The Order
concerns the preparation of, performance of, and reimbursement of
oversight cost for the Remedial Investigation and Feasibility
Study (RI/FS) for the Superfund Site known as the Gallup's Quarry
Site (the Site) in Plainfield, Connecticut. This Order is issued
pursuant to the authority vested in the President of the United
States by Sections 104 and 122(d)(3) of the Comprehensive
Environmental Response, Compensation, and Liability Act, 42
U.S.C. Sections 9604 and 122(d)(3), which authorize the President
to issue an order setting forth the obligations of the Settling ':
Parties with respect to a settlement agreement for action under
Section 104(b) of CERCLA. This authority was delegated to the
Administrator of EPA on January 23, 1987, by Executive Order
12580, 52 Fed. Reg. 2926 (January 29, 1987), and further
delegated to the Regional Administrator, September 13, 1987, by
EPA delegation No. 14-14-C. The Settling Parties agree not to
contest the authority or jurisdiction of the Regional
Administrator to issue this Order in any subsequent proceeding to
enforce the terms of this Order.
PARTIES BOUND
-
-5
2. This Order shall apply to and be binding upon EPA and the
Settling Parties and their successors and assigns. No change or
changes in the ownership or corporate status of any of the
Settling Parties shall in any way alter the Settling Parties'
responsibilities under this Order. Each Settling Party shall
provide a copy of this Order to any subsequent owners or
successors before ownership rights are transferred. The
Settling Parties shall be jointly and severally liable for the
performance of the activities specified in the Order and for
penalties arising from this Order. The signatories to this Order
certify that they are authorized to execute and legally bind the
parties they represent.
3. The Settling Parties shall provide a copy of this Order to
all contractors, subcontractors, laboratories, and consultants :
retained to conduct any portion of the work performed pursuant to
this Order, within fourteen (14) days after the effective date of
this Order or after the date of such retention.. Notwithstanding
the terms of any contract, the Settling Parties are responsible
for compliance with this Order and for ensuring that their
contractors and agents comply with this Order. Any reference
herein to the Order shall mean the Order, any Appendix thereto
including any future modifications as provided by the terms of'
the Order as may be added-hereafter, including any reports,
plans, specifications, schedules-, and appendices required by this
-
-6
Order which, upon approval of EPA, shall be incorporated into and
enforceable under the Order.
STATEMENT OF PURPOSE
4. In entering into the Order, the mutual objectives of EPA and
the Settling Parties are: (i) to determine the nature and extent
of contamination and any threat to the public health, welfare, or
the environment caused by the release or threatened release of
hazardous substances, pollutants or contaminants from the Site by
conducting a remedial investigation; and (ii) to determine and
evaluate alternatives for .remedial action (if any) to prevent,
mitigate or otherwise respond to or remedy any release or
threatened release of hazardous substances, pollutants, or
contaminants from the Site by conducting a feasibility study.
5. The activities conducted under this Order are subject to
approval by EPA and shall provide all appropriate necessary
information for the Remedial Investigation/Feasibility Study, and
for a Record of Decision that is consistent with CERCLA Sections
104, 121, and 122, and the National Contingency Plan (NCP), 40
CFR Part 300 et sea.
EPA'S FINDINGS OF FACT
6. The Gallup's Quarry Superfund Site (the "Site") is located
on Tarbbx Road in the town of Plainfield, Windham Country,
Connecticut. The Site, approximately twenty-two acres, was used
-
-7
as an unlicensed chemical waste disposal site from approximately
1977 to 1978. The Site is bounded by Mill Brook and its
associated wetlands to the north, Route 12 to the east, Tarbox
Road and residential areas to the south, and Conrail railroad
tracks and wetlands to the west.
8. Land use in the area surrounding the Site is largely
residential. Within three miles from the Site, approximately
6,500 residents rely on groundwater for their sole drinking water
supply. Nearby wooded areas and Mill Brook are used for
recreation, including game fishing.
9. Prior to 1977, the Site was used for gravel mining
operations. In the spring of 1977, Chemical Waste Removal, Inc.
(CWR) of Bridgeport, Connecticut began to send drummed and bulked '
waste materials to the Site. CWR was the sole transporter of
waste to the Site between approximately May 1977 and January
1978. During that time period, disposal activities occurred in
at least three distinct locations at the site: a buried seepage
system in the elevated central part of the Site, and two separate
pits at the north end of the Site into which barrels of waste
chemicals and free liquid--chemical wastes were dumped.
10. In early January; 1978, in response to citizen complaints,
the Connecticut State Police arid Connecticut Department of
Environmental Protection (CT DEP) investigated activities at the
-
-8
Site.. On January 13, 1978, the CT DEP entered the Site,
discovered half buried drums with markings of "P.F. Etchant" and
"Ferric Chloride", and collected liquid samples in the open pit
area at the Site. The samples confirmed the presence of elevated
levels of numerous hazardous constituents. All operations at the
Site ceased at this time.
11. At the direction of CT DEP and the Connecticut State
Police, investigatory and removal activities, including site
evaluation, and removal of drums and contaminated soil, were
conducted at the site from January through August 1978. Over
1,600 barrels, 5,000 gallons of bulk liquid waste, and 3,500 tons
of contaminated soil were removed by the CT DEP from the ground
during its cleanup effort.
r
12. Wastes disposed of at the Site in drums and as free liquid
waste include, but are not limited to: methyl ethyl ketone,
isopropanol, acetone, methanol, toluene, xylene,
tetrachloroethylene, cyanide, trichloroethylene, 1,1,1
trichloroethyiene, copper, iron, nickel, and chromium. Volatile
organics and metals, including the contaminants listed above,
have been detected in samples from the groundwater, surface
water, sediment and soil by. the CT DEP and Connecticut Department
of Health during their sampling efforts between 1978 and 1981,
and by EPA during 1986, 1987, 1992, and 1993.
-
13. In May 1988, EPA's contractor, the NUS Technical Assistance
Team, initiated a Site Investigation to evaluate the Gallup's
Quarry Site with respect to conditions for Removal Actions under
the National Contingency Plan (NCP), 40 C.F.R. 300.65. Soil
samples collected confirmed the presence of volatile organic
compounds, semi-volatile organic compounds and metals.
14. Pursuant to Section 105(8)(b) of CERCLA, 42 U.S.C.
9605(8)(b), the Site was proposed for inclusion on the National
Priorities List (NPL) published by the Administrator of EPA in
the Federal Register on June 21, 1988 ( 53 Fed. Reg. 23342). The
Site was finally listed on the NPL on October 4, 1989-(54 Fed.
Reg. 41020).
15. The Generator Settling Parties listed in Appendix B
attached hereto are persons who arranged for disposal, or
arranged with a transporter for transport for disposal, of
hazardous substances at the Site, or are successors-in-interest
to persons who arranged for disposal, or arranged with a
transporter for transport for disposal, of hazardous substances
at the Site.
EPA'S DETERMINATIONS
16. On the basis of the Findings of Fact, EPA has determined
that: . - : : - . - . : .
-
-10
a. Each Settling Party is a "person" as that term is
defined in Section 101(21) of CERCLA, 42 U.S.C.
9601(21).
b. Each Settling Party is a liable party within the
meaning of Section 107(a) of CERCLA, 42 U.S.C.
9607(a), and a "potentially responsible party" within
the meaning of Section 122(d)(3) of CERCLA, 42 U.S.C.
9607(a).
c. The Site is a "facility" within the meaning of Section
101(9) of CERCLA, 42 U.S.C. 9601(9).
_d. Substances identified at the S'ite, including those
listed in paragraph 12, are "hazardous substances"
within the meaning of Section 101(14) of CERCLA, 42
U.S.C. 9601(14) .
e. The past, present or potential future migration into
the environment of hazardous substances, pollutants or
contaminants at or from the Site constitutes an actual
."release" or a substantial threat of a release into the
"environment" as those terms are defined in Sections
101(8), 101(22) and 104(a) of CERCLA, 42 U.S.C.
9601(8), 9601(22) and 9604(a).
f. It is necessary, in order to protect the public health
and welfare and the environment, to conduct an RI/FS to
determine the full nature and extent of contamination
that exists at or near the Site and to determine what
remedial actions are or may be necessary to be carried
-
-11
out under Sections 104 and 121 of CERCLA, or secured
g.
through enforcement action under Section 106 of CERCLA.
The RI/FS will be conducted properly and promptly by
the Settling Parties, in accordance with Sections
104(a)(1) and 122(a) of CERCLA, provided that the
Settling Parties perform all activities in accordance
with the terms of this Order, the Statement of Work
h.
(SOW) (Appendix A), and any modifications thereto,
The actions called for in this Order will be consistent
with the NCP to the extent that the NCP is consistent
with CERCLA, provided that the Settling Parties perform
such actions properly in accordance with the terms of
this Order, the Statement of Work, and any
modifications thereto.
h. The Settling Parties are qualified to conduct the
RI/FS, in accordance with Section 104(a)(1) of CERCLA,
'
i.
if the Settling Parties engage a qualified contractor
pursuant to Paragraph 20 of this Order.
EPA will arrange for the oversight and review of the
RI/FS by qualified EPA and qualified contractors, in
accordance with Section 104(a)(1) of CERCLA.
ORDER
BASED ON THE FOREGOING FACTS AND DETERMINATIONS, EPA AND THE SETTLING PARTIES HEREBY AGREE, AND EPA HEREBY ORDERS THAT:
Implementation
-
-12
17. Subject to EPA's rights to implement its own RI/FS pursuant
to Paragraphs 29 and 43, the Settling Parties shall perform the
RI/FS in accordance with the Statement of Work (SOW), which is
attached to this Order as Appendix A, and with any modifications
made or required by EPA to bring documents and/or deliverables
prepared by the Settling Parties under this Order into
conformance with the requirements of CERCLA, the NCP, the SOW,
and modifications to the SOW, and any work plans prepared under
this Order or the SOW, which are incorporated by reference into
this Order. Upon the effective date of this Order, Settling
Parties shall commence implementation of this Order and of work
required by the Statement of Work, and shall conclude-
implementation of such in accordance with the terms and schedules
set forth in this Order, Appendix A, and any approved Work Plans.
The activities conducted pursuant to this Order are subject to
approval by EPA and shall, unless otherwise directed by EPA, be
consistent with the NCP to the extent that the NCP is consistent
with CERCLA. Such activities shall also be consistent with EPA
Interim Guidance on Superfund Selection of Remedy, OSWER
Directive No. 9355.0-19; Guidance for Conducting Remedial
Investigation and Feasibility Studies under CERCLA, OSWER
Directive Number 9355.3-01; and guidances referenced in the
Statement of Work.
18. If any inconsistencies between any of the above laws,
regulations or guidance exist, CERCLA shall govern. Furthermore,
-
-1-3
if any of the above laws, regulations or guidance are amended
prior to the signing of a Record of Decision for final remedial
action at the Site, EPA may modify or require modification to the
SOW and to any approved Work Plan or other deliverable
accordingly. EPA may also may require Settling Parties to
develop a new Work Plan or other deliverable accordingly, and the
Settling Parties shall conduct all activities required by the new
or modified Work Plan or other deliverable. To the extent
permitted in Paragraphs 57 and 58, the provisions of this
paragraph are subject to Dispute Resolution.
19. EPA may determine that additional tasks not inconsistent
with the NCP, including remedial investigatory work and/or
engineering evaluations, other than those specified in the
Statement of Work and modifications thereto, are part of the
RI/FS. The Settling Parties shall implement any additional tasks
which EPA determines are necessary as part of performing the
activities required under this Order, provided that such tasks
are consistent with the objectives of this Order. The additional
tasks shall be completed in accordance with the standards,
specifications, and schedule determined or approved by EPA, after
EPA has notified the Settling Parties in writing of the need to
perform the additional work and has provided the Settling Parties
with a schedule and an explanation of the additional work. To
the extent permitted by Paragraphs 57 and 58, EPA's decision to
require additional work shall be subject to Dispute Resolution.
-
-14
Enaaaement of the Settling Parties' Contractor
Designation of the Settling Parties' Project Coordinator
20. Within forty-five (45) days of the effective date of this
Order, the Settling Parties shall engage a qualified Contractor
to perform the technical activities required under this Order.
The Contractor shall employ key personnel dedicated to the RI/FS
that shall have a minimum of five (5) years of direct experience
in performing investigations and studies at hazardous waste
sites. Subcontractors retained by the Contractor shall
contribute no more than twenty-five percent (25%) of the total
work to be conducted under the agreement between the Respondent
and the Contractor, not including .the costs of laboratory
analysis, well drilling and geophysical techniques. All work
performed by said Contractor pursuant to this Order shall be
under the general direction and supervision of a qualified
individual with expertise in hazardous waste site investigation
and cleanup. The Contractor shall employ such professional staff
sufficient to perform the RI/FS prior to engagement by the
Settling Parties.
21. The Settling Parties shall provide written notice of the
engagement of the Contractor to EPA within seven (7) days after
engaging a contractor. The notice shall include a copy of the
Settling Parties' contract with the Contractor, including a
statement of qualifications, identification of project personnel,
and language dedicating the specific professional staff for
-
-15
specific hours devoted to the project. The Settling Parties
shall notify EPA regarding the identity and qualifications of all
subcontractors as soon as each subcontractor is engaged or at
least fourteen (14) days prior to the subcontractor's
commencement of site work, whichever occurs first. EPA shall
have the right to disapprove, based on professional
qualifications, conflicts of interest and/or deficiencies in
previous similar work, any Contractor or subcontractor or other
person engaged directly or indirectly by the Settling Parties to
conduct work activities under this Order. Any disapproval shall
be in writing.
22. Within fourteen (14) calendar days after the effective date
of this Order, the Settling Parties shall designate a Project
Coordinator who shall be responsible for the administration of
all actions called for by this Order and shall submit the
coordinator's name, address and telephone number to EPA. Any
subsequent change in the Settling Parties' Project Coordinator
shall be accomplished by notifying EPA in writing at least
fourteen (14) calendar days prior to the change.
Designation of EPA's Remedial Project Manager
23. EPA will designate a Remedial Project Manager (RPM) for
administration of its responsibilities, for oversight of the day
to-day activities conducted under the Order, and for receipt of
all written matter required by the Order. In addition, EPA will
5
-
-19
those of the authors and not those of the U.S. Environmental
Protection Agency."
29. EPA will review the deliverables required by this Order to
determine whether they are consistent with the requirements of
Appendix A and the Order and, after opportunity for review and
comment by the State, EPA will respond in writing to Settling
Parties with one of four findings:
A. Approval means that Settling Parties shall proceed
with the next scheduled RI/FS activity consistent with
the deliverable.
B. Approval with Conditions means that Settling Parties
shall proceed with the next scheduled RI/FS activity,
subject to certain required modifications or conditions
set forth in EPA comments. EPA will specify a schedule
for resubmitting the deliverable with the required
modifications or conditions as set forth in the EPA
comments. If the Settling Parties fail to resubmit the
deliverable within the specified time, EPA may order
the Settling Parties to cease work on the RI/FS
activity until such time as the modification is made or
the condition is met.
C. Disapproval with Modification Required means that
the Settling Parties shall not proceed until they
modify the deliverable to correct the noted
deficiencies delineated in EPA's comments, and resubmit
-
-20
the deliverable for further EPA review. Modifications
may be required in any original-submitted deliverable,
any portions of a deliverable, or any deliverable or
portion of deliverable resubmitted to EPA. EPA will
specify a schedule for resubraitting deliverables
requiring modifications.
D. Disapproval with EPA Modification means that EPA has
determined that it will modify the submission to cure
any deficiencies and/or undertake the RI/FS or any
portion of the RI/FS. The EPA response shall include
the reasons for the determination and a general
explanation as to why the Settling Parties will not be
allowed the opportunity to cure the deficiencies or to
perform the RI/FS or any portion thereof. In either
case the Settling Parties agree to reimburse EPA for :
the costs of such modification or work as an oversight
cost, as provided in Paragraph 52, Reimbursement of EPA
Response and Oversight Costs.
A finding of Approval or Approval with Conditions shall not be
construed to mean that EPA concurs with all conclusions, methods
or statements in the deliverables.
30. Any reports, plans, specifications, schedules, and
attachments or other deliverables required by this Order are
incorporated in and shall be an enforceable part of this Order.
-
-21
Any delay or non-compliance with such reports, plans
specifications, schedules, and attachments or other deliverables
shall be considered delay or non-compliance with requirements of
this Order and shall subject the Settling Parties to penalties
pursuant to Paragraph 60 or 64, subject to the provisions of
Paragraph 55, Excuses for Delays in Performance.
Monthly Progress Reports
31. The Settling Parties shall provide monthly written progress
reports (Progress Reports) to EPA and the State of Connecticut.
At a minimum, these Progress Reports shall describe the progress
made during the preceding month by: (1) describing the actions
which have been taken toward achieving compliance with this
Order; (2) summarizing all the results of-.sampling and tests and
all other data received by the Settling Parties; (3) summarizing ':
all costs incurred by Settling Parties in performing work under
this Order (provide only on a semi-annual basis); and (4)
describing actions, data, plans, and procedures which are
scheduled for the next month. Progress Reports shall be
submitted to the EPA RPM and the State of Connecticut by the
fifteenth (15th) day of each month following the last day of the
reporting period, beginning after the effective date of this
Order. Meetings between the the RPM, the Settling Parties'
Project Coordinator, and the Contractor shall be held at least
once per month at the EPA office in Boston, unless EPA designates
another location or determines that a monthly meeting is not
-
-2-2
required for a particular month. The Settling Parties and the
Contractor engaged to perform work under this Order shall also
meet with and make formal presentations to EPA at the completion
of major components of the RI/FS, as specified by the EPA RPM.
Availability of RI/FS Data
32. The Settling Parties shall submit in their monthly Progress
Reports, as described in Paragraph 31 of this Order, a summary of
results of all sampling and/or tests and all other data generated
by the Settling Parties, by their Contractor, or on the Settling
Parties' behalf, in.the course of implementation of the Order.
The full results and any underlying documentation shall be
furnished to EPA upon request.
Quality Assurance/Quality Control; Health and Safety Compliance
33. While conducting all sample collection and analysis
activities required by this-Order, the Settling Parties shall use
quality assurance, quality control, and chain of custody
procedures in accordance with the SOW, and with EPA's: "Interim
Guidelines and Specifications for Preparing Quality Assurance
Project Plan," December 1980, QAMS-005/80, "Data Quality
Objective Guidance" (EPA/540/G87/003 and 004); "EPA NEIC Policies
and Procedures Manual" (revised November 1984, EPA 330/9-78-001
R); and subsequent amendments to such guidelines. To provide
quality assurance and maintain quality control, the Settling
Parties shall submit a Quality Assurance Project Plan ("QAPP") to
-
-23
EPA consistent with the requirements, guidance, and schedule
contained in the Statement of Work. Upon EPA approval pursuant
to Paragraph 29, Settling Parties shall comply with the approved
Quality Assurance Project Plan.
34. The Settling Parties also shall prepare a Health and Safety
Plan as required and described in the Statement of Work. The
accepted Health and Safety Plan shall be consistent with and
implement standards promulgated by the Secretary of Labor
pursuant to Section 126 of CERCLA and Section 6 of the
Occupational Health and Safety Act of 1970.
Split Sampling
35. At the request of EPA, the Settling Parties shall provide
split or duplicate samples to EPA and/or its authorized
representatives, of any samples collected by the Settling Parties
pursuant to the implementation of this Order. Similarly, the
Settling Parties shall allow such split or duplicate samples to
be taken by EPA and/or its authorized representatives. The
"Settling Parties shall notify EPA not less than thirty (30) days
in advance of any sample collection activity. Not less than
twenty-one (21) days in advance of sample collection, or such
lesser time as approved by the RPM, the Settling Parties shall
notify EPA of the sampling date, sampling media, the number of
samples from each media, unless EPA specifies a different time
period. EPA's RPM or its contractors shall notify the Settling
-
-24
Parties of the opportunity to take split or duplicate samples,
and will provide the validated analytical results from their
samples to the Settling Parties when they become available.
Record Preservation
36. During the pendency of this Order and for a-period of not
less than six (6) years after EPA certification pursuant to
paragraph 65 of this Order, the Settling Parties shall preserve
all records and documents in their possession or in the
possession of their employees, agents, officials, authorized
representatives, accountants, contractors, attorneys, successors
or assigns, and parent companies, which relate in any-way to the
Site or to implementation of this Order, notwithstanding any
document retention policy to the contrary. At the conclusion of
this document retention period, the Settling Parties shall notify
EPA at least ninety (90) days prior to the destruction of-any
such records or documents.
The Settling Parties shall send such notice, accompanied by a
copy of this Order, to:
Office of Regional Counsel U.S. Environmental Protection Agency JFK Federal Building Boston, MA 02203 Attention: Gallup's Quarry Superfund Site
Upon request by EPA, Settling Parties shall deliver to EPA any or
all such records and documents or copies of any such records
and documents.
-
-25
Confidentialitv Claims
37. The Settling Parties may assert a confidentiality claim, if
appropriate, covering all or part of the information requested by
this Order pursuant to 40 C.F.R. 2.203(b). Such an assertion
shall be adequately substantiated when it is made. Neither
analytical data nor any information specified in Section
104(e)(7)(F) of CERCLA, shall be claimed as confidential by the
Settling Parties. Information determined to be confidential by
EPA shall be afforded the protection specified by 40 C.F.R. Part
2, Subpart B, and Section 104(e)(7) of CERCLA. If no such claim
accompanies the information when it is submitted to EPA, it may
be made available to the public by EPA without further notice to
the Settling Parties.
Site Access
38. All Settling Parties who own, occupy, or control property at
the Site, or property adjacent to the Site to which access is
required in order to properly carry out the terms of this Order,
shall grant access to the other Settling Parties, the Settling
Parties' authorized representatives, and EPA and their officers,
employees, agents, contractors, consultants and other authorized
representatives for purposes of implementing this Order.
39. To the extent that access to, use or ownership of, or
easements over the Site or property other than the Site is
required for proper and complete implementation of this Order,
-
-26
the Settling Parties shall use their best efforts to obtain
access agreements or other interests in such property within
thirty (30) days of the effective date of this Order. For
purposes of this Paragraph "best efforts," include, but are not
limited to, providing payment of money in consideration of access
to property.
40. Such agreements or other interests obtained pursuant to the
preceding paragraph shall, at a minimum, allow the Settling
Parties and their authorized representatives, EPA and its
designated coordinators, agents, employees, contractors,
consultants, and other authorized representatives to enter freely
and move about the Site at all times for the purpose of
implementing this Order or overseeing the implementation of Work
under this Order. In the event that Settling Parties fail to
obtain any necessary access agreements within the time period
specified above, the Settling Parties shall notify EPA and the
State in writing within five (5) days thereafter. Such
notification shall include a description of the efforts made by
the Settling Parties to obtain the necessary access and the
reason for their lack of success. The Settling Parties shall
reimburse EPA for any costs EPA may incur in exercising their
statutory authority to gain access to the Site; reimbursement
shall be provided as in Paragraph 52, Reimbursement of EPA
Response and Oversight Costs.
-
-27
Endanaerment and Emergency Response
41. Upon the occurrence of any event during the RI/FS that
causes or threatens any release of hazardous substances,
pollutants or contaminants from the Site into the environment or
that endangers the public health, welfare, or the environment,
the Settling Parties shall immediately take all appropriate
action to prevent, abate or minimize such release or
endangerment. The Settling Parties shall also orally notify the
EPA RPM within twenty-four (24) hours, or in the event of the EPA
RPM's unavailability, the Settling Parties shall notify within
the same time period the Regional Duty Officer of the Emergency
Planning and Response Branch, EPA Region I, telephone-(617) 223
7265. In addition, the Settling Parties shall comply with the
notification requirements of Connecticut law. The Settling
Parties shall act in accordance with all applicable provisions of =
the Health and Safety Plan prepared pursuant to the Statement of
Work.
42. The Settling Parties shall submit a written report to EPA
within five (5) days after each such event setting forth: (i)
the events that have occurred; (ii) the measures taken and to be
taken to mitigate any harm caused or threatened by the event; and
(iii) the measures taken and to be taken to prevent the
reoccurrence of such an event.
-
-2-8
43. Regardless of whether or not such a report is made to EPA,
if EPA determines- that activities in compliance or noncompliance
with this Order have caused or may cause a release of a hazardous
substance, pollutant or contaminant or a threat to the public
health or welfare or to the environment, EPA may: (i) order the
Settling Parties to stop further implementation of this Order for
such period of time as may be needed to abate such release or
threat; and/or (ii) undertake any action which EPA determines is
necessary to abate such a release or threat.
Use of Resource Conservation and Recovery Act Facilities
44. All facilities used by the Settling Parties for the off-site
transfer, treatment, storage or disposal of hazardous substances
removed from the Site must be in compliance with the applicable
requirements of the Resource Conservation and Recovery Act
(RCRA), as amended, and relevant state law. The Settling Parties
are responsible for complying with these requirements, including
fulfilling the standards applicable to generators of hazardous
waste, found at 40 C.F.R. Part 262. In particular, this
responsibility includes using and signing manifest forms for
hazardous waste leaving the Site. Further, the Settling Parties
must designate, in a report to EPA, any facilities that the
Settling Parties propose to use for such off-site transfer,
storage, treatment or disposal, and EPA must approve the use of
such proposed facilities prior to the shipment of hazardous
substances from the Site.
-
-29
Other Lavs
45. All actions required to be taken pursuant to this Orc".er
shall be undertaken in accordance with the requirements of all .
applicable or relevant and appropriate state and federal laws and
regulations (ARARs), including: CERCLA; laws relating to
occupational safety and health; and other federal and State
environmental laws as defined in EPA and State policy in effect
at the time of the signing of the ROD. Pursuant to Section
121(e)(l) of CERCLA, no federal, state or local permits are
required for work conducted under this Order which is on the Site
or on suitable areas in very close proximity to the Site
necessary for implementation of such work.
46. Other agencies, including the Occupational Safety and Health
Administration (OSHA) and the Fish and Wildlife Service (F&WS),
may be called upon to review the conduct of work under this
Order. In the event that two or more federal or state laws or
regulations are applicable, the more stringent of the conflicting
provisions shall apply; provided, however, that this provision
shall not limit EPA's authority under Section 121(d) of CERCLA.
Public Review of RI/FS Report
47. When EPA determines the RI/FS required under this Order is
acceptable for public review, the RI/FS shall be made available
by EPA for public comment for a period of not less than thirty
(30) days. The dates and length of the public comment period
-
-30
shall be established by EPA. Following the public review and
comment period, EPA may refer the FS Report back to the Settling
Parties for revision pursuant to public comments, and EPA and the
State comments. In addition, the Settling Parties shall provide
information for the Responsiveness Summary as requested by EPA,
pursuant to all applicable EPA guidance documents. The Settling "*
Parties shall prepare all portions of a Draft Responsiveness
Summary specified by EPA. EPA will prepare the final
Responsiveness Summary for the RI/FS.
Community Relations
48. EPA shall be responsible for preparing a Community
Relations Plan and conducting a community relations program. The
Settling Parties and the Contractor engaged to conduct the RI/FS
under this Order shall, consistent with the Community Relations
Plan: (i) attend and participate in public meetings regarding the
Site, including in the development of graphic materials, to the
extent specified by the RPM; (ii) prepare fact sheets concerning
the Site and activities conducted under this Order for submission
to the RPM; and (iii) provide timely and appropriate responses to
inquiries from the public at the request of the RPM.
Financial Assurance; Insurance
49. Within thirty (30) days after the effective date of this
Order and annually thereafter until certification of the work
under Paragraph 65 of this Order, one or more of the Settling
-
-31
Parties shall demonstrate to EPA that they meet one of the
financial assurance mechanisms specified in 40 CFR 264.143 for
the estimated costs of work to be performed by Settling Parties
under this Order. This assurance may be provided in the form of
the most recent certified financial statement available for any
of the Settling Parties showing the information specified in 40
CFR 264.143(f).
50. At least seven (7) days prior to commencing any on-site work
under this Order, the Settling Parties shall secure, and shall
maintain for the.duration of this Order, comprehensive general
liability and automobile insurance with aggregate limits of
$5,000,000 (five million dollars). The United States shall be
named as an insured for all such insurance policies. Within the
same time period, the Settling Parties shall provide EPA with '
certificates of such insurance and a copy of each insurance
policy. If the Settling Parties demonstrate to EPA that any
contractor or subcontractor maintains insurance equivalent to
that described above or insurance covering the same risks but in
a lesser amount, then the Settling Parties need provide only that
portion of the insurance described above which is not maintained
by the contractor or subcontractor.
51. For the duration of this Order-, the Settling Parties shall
satisfy, or shall ensure that their contractors and
subcontractors satisfy, all applicable laws and regulations
-
-32
regarding worker's compensation insurance for all persons
performing the work on behalf of the Settling Parties in
furtherance of this Order.
Reimbursement of EPA Response and Oversight Costs
52. The Settling Parties shall reimburse the Hazardous
Substances Superfund for all response costs, including oversight
costs and interest, incurred after the effective date of this
Order by the United States in connection with the RI/FS and this
Order, including without limitation costs incurred by EPA under
or in connection with a contract or arrangement between EPA and a
qualified person to assist EPA in overseeing and reviewing the
conduct of activities required under this Order. Reimbursable
response costs shall include all direct costs related to the
RI/FS and this Order and all indirect costs calculated in
accordance .with EPA policy, including without limitation: time
and travel costs of EPA personnel regarding RI/FS activities
(including access and community relations); contractor costs;
costs under a cooperative agreement; costs related to discussing
the interpretation of Order provisions or reviewing any report
delivered pursuant to this Order; costs related to resolving
disputes which arise under this Order; the costs of doing and/or
redoing any of the Settling Parties' obligations under this
Order; EPA, contractor, and cooperative* agreement costs related
to the preparation of a Baseline Risk Assessment; and any
-
-3-3
interest that accrues from the date on which payment becomes due
pursuant to Paragraphs 53 and 54.
53. On a periodic basis, EPA will submit to the Settling
Parties a bill for response costs incurred by EPA with respect to
the RI/FS and this Order. This bill will consist of a line-item
summary of costs incurred during the preceding year; the summary
will include a breakdown of costs by category, including without
limitation payroll, travel, indirect costs, and contracts, and a
brief narrative of work related to such costs (generally one to
two paragraphs in length). The Settling Parties shall, within
forty-five (45) days after receipt of each annual bill, remit a
certified check payable to the Hazardous Substances Superfund for
the amount of such bill. The Settling Parties shall include the
name of the Site, the Site identification number 01B7, and the '
docket number for this Order on the check and mail the check with
a cover letter to:
U.S. Environmental Protection Agency Region I
Attn: Superfund Accounting P.O. Box 360197 M
Pittsburgh, PA 15251
A copy of the transmittal letter and the check shall be provided
simultaneously to the EPA Remedial Project Manager.
54. If the Settling Parties dispute a bill or any portion of a
bill submitted by EPA, the Settling Parties may initiate dispute
resolution pursuant to the procedures of Paragraph 57, provided,
-
-34
however, that the Settling Parties notify EPA in writing within
twenty-one (21) days after receipt of the disputed bill and that
the Settling Parties pay all undisputed portions of the bill in-
accordance with the provisions of this reimbursement section. If
EPA determines that the Settling Parties acted in good faith in
invoking dispute resolution concerning a response or oversight "*
cost, the time for payment of the disputed portion of the bill
will be extended until the dispute is resolved; interest,
however, shall accrue on the disputed response or oversight cost
as if no extension of the time for payment had been granted. If
the Settling Parties fail to raise a dispute within twenty-one
(21) days of their receipt of the bill, the Settling Parties
remain obligated for payment of the entire amount of the bill on
the original payment due date, interest shall accrue on any
unpaid portion of the bill from the original payment due date,
and EPA may seek stipulated penalties or otherwise act to enforce
the Settling Parties' compliance with this section and the Order.
Excuses for Delays in Performance
55. With respect to the Settling Parties' compliance with any
interim or final time deadline set forth in this Order, no
stipulated penalties or other sanctions will be imposed for delay
directly caused by the following which could not have been
overcome by the Settling Parties' due diligence: (i) an act of
God; (ii) any delay caused by the public review and comment
process as provided in the Work Plan and this Order; (iii) any
-
-35
other cause beyond the control of the Settling Parties; provided,
however, that increases in the cost of performance of the RI/FS
shall not excuse such performance nor affect the applicability 'of
the penalty provisions or other sanctions which are provided for
under this Order. Such penalties and sanctions shall be avoided
only if, and only to the extent that, delays directly caused by
conditions specified in (i) through (iii) above materially
interfered with or prevented the Settling Parties' execution of
their responsibilities during the period of such delay. The
Settling Parties further agree to use their best efforts to
minimize any delay which may result. The Settling Parties
acknowledge that they will have the burden of justifying excuses
for delay in performance under this Paragraph..
56. The Settling Parties shall orally notify the EPA RPM within '
forty-eight (48) hours in the event that circumstances occur
which the Settling Parties assert should trigger the excuse
provisions of this section, and shall identify with specificity
the cause of such delay and the estimated duration of such delay.
Within five (5) days after the Settling Parties first become
aware of such circumstances4 the Settling Parties shall supply to
EPA in writing an explanation of the cause(s) of any actual or
expected delay or noncompliance, the anticipated duration of any
delay, the measures taken and to be taken by the Settling Parties
to prevent or minimize the delay or correct the noncompliance,
and the timetable for implementation of such measures. Failure
-
-36
to notify EPA, in writing, shall result in a waiver of the
Settling Parties' right to assert that the delay should be
excused under the terms of this section.
Dispute Resolution
57. If the Settling Parties object to any EPA notice of
disapproval or decision made pursuant to this Order, including
any decision which has resulted in the assessment of stipulated
penalties, the Settling Parties shall notify EPA in writing of
their objections within fourteen (14) days of receipt of the
notice. EPA shall communicate with the Settling Parties on the
disputed matter and shall have fourteen (14) days from the
receipt by EPA of the notification of objection to reach
agreement. If agreement cannot be reached on any issue within
this fourteen (14) day period, EPA shall provide a written
statement of its decision and the basis therefor to the Settling
Parties, and the Settling Parties shall implement the activities
required by the EPA decision beginning no later than five (5)
days after receipt of the EPA statement. Except as specifically
provided herein, engagement of a dispute resolution among the
parties shall not be cause for the delay of any work.
58. If the Settling Parties object, in writing, to an EPA
decision involving a substantial modification to the Statement of
Work or a major deliverable, an EPA manager above the level of
the Geographic Section Chief within EPA Region I shall mediate
-
-37
and resolve the dispute. The designated EPA manager shall
determine, in his or her sole discretion, whether the decision in
fact involves a substantial modification to the Statement of Work
or major deliverable. During the pendency of a dispute under
this paragraph, the accrual of stipulated penalties which relate
to nonperformance of the work required by the disputed EPA
decision shall be suspended. Disputes under this Paragraph shall
in all other respects be governed by Paragraph 57 of this Order.
59. In the event that the Settling Parties do not implement the
activities required by the EPA decision, the EPA Regional
Administrator may take such civil enforcement actions-against the
Settling Parties as may be provided by statutory or equitable
authorities, including, but not limited to, the assessment of
such civil penalties or damages as are authorized by Sections 122 ':
and 109 of CERCLA. In such an event, EPA retains the right to
perform additional studies and to conduct a partial or complete
RI/FS pursuant to its authority under CERCLA and to recover the
costs thereof from the Settling Parties.
Stipulated Penalties for Delays in Performance
60. For each day that the Settling Parties fail to complete a
major deliverable identified in Table 1 of the SOW or to comply
with any time deadline for such major deliverable established
pursuant to this Order, the Settling Parties shall pay to EPA and
the State the sums set forth below as stipulated penalties:
-
-38
Period of Failure to Comply Penalty Per Day
1st - 7th day $ 1,000
8th - 14th day $ 2,000
each day thereafter $ 3,500
Penalties shall begin to accrue on the day after performance is
due or the day a violation occurs, and shall continue to accrue
through the final day of the correction of the noncompliance or
completion of the activity.
61. For each day that the Settling Parties fail to comply with
any deadline established pursuant to this Order other than
deadlines governed by Paragraph 60 hereto, stipulated-penalties
to EPA in the amount of five hundred dollars ($500) per day shall
accrue on the day after performance is due and shall continue to
accrue through the final day of the correction of the
noncompliance or completion of the activity.
62. Any penalty, accruing under Paragraphs 60 or 61 shall be due
and payable within fourteen (14) days of the receipt of a written
demand by EPA. Payment of such penalty shall be made by
certified check payable to the Hazardous Substances Superfund,
shall reference the Gallup's Quarry Site, and the EPA Region and
Site/Spill ID# 01B7, and shall be mailed to the following address
with a notation of the docket number of this Order:
-
-39
Region I U.S. Environmental Protection Agency
Attn: Superfund Accounting P.O. Box 360197 M
Pittsburgh, PA 15251
A copy of the certified check shall be sent to the Remedial
Project Manager within five (5) days of payment. The stipulated
penalties set forth in this section do not preclude EPA from
electing to pursue any other remedies or sanctions which may be
available to EPA by reason of the Settling Parties' violation of
this Order or the Settling Parties' failure or refusal to comply
with any of the requirements of this Order, except that EPA
agrees that any amount of stipulated penalties recovered by EPA
for a particular violation of this Order shall be deducted from
any amount of civil penalties recoverable by EPA for the same
violation of the Order. Such remedies and sanctions include
injunctive relief, the assessment of such civil penalties or
damages as are authorized by Sections 122 and 109 of CERCLA, or
the performance of a federally-funded response action, and a
corresponding suit for reimbursement of costs incurred by the
United States and the State.
63. If the Settling Parties invoke dispute resolution regarding
any decision which has resulted in the assessment of stipulated
penalties, the Settling Parties shall pay all stipulated
penalties for which EPA has made a written demand into an
interest-bearing escrow account within fourteen (14) days of
receipt of the EPA demand. The Settling Parties shall pay
-
-40
penalties into this account as they continue to accrue, at least
every seven (7) days. Within seven (7) days after receipt of the
EPA decision regarding the disputed matter, the escrow agent
shall pay the balance of the account to the prevailing party
identified in the EPA decision.
""
Civil Penalties for Noncompliance
64. The Settling Parties are advised that violations of this
Order or any portion thereof may subject them to civil penalties
of up to $25,000 per violation and $25,000 for each day in which
such violation continues, as provided in Sections 109 and 122 of
CERCLA, 42 U.S.C. 9609, 9622. The Settling Parties are
further advised that they may also be subject to penalties of up
to $75,000 for each day during which a second or subsequent
violation continues.
Certification of the Settling Parties'
Performance of the Work Activities
65. Upon EPA's issuance of the Record of Decision, EPA shall
determine if the Settling Parties have met all of their
responsibilities under Appendix A (the Statement of Work), and
under the provisions of the Order, including payment of oversight
costs and any stipulated penalties or other penalties or damages
that the Settling Parties may have incurred during the course of
their activities under the Order. If EPA determines that such
responsibilities have been satisfied, EPA will, after issuance of
-
-41
the Record of Decision for the Site, certify to the Settling
Parties that their responsibilities under the Statement of Work,
the Work Plan and this Order have been completely and
successfully discharged.
Covenant Not to Sue
66. Upon certification by EPA that the Settling Parties have
completed the RI/FS in accordance with this Order, EPA covenants
not to sue or initiate an administrative proceeding or civil
action against the Settling Parties for completion of the RI/FS
for any operable units covered by the signed Record of Decision,
or for any other activities performed or costs incurred pursuant
to the Order, including oversight costs incurred while performing
the acitivities covered under the Statement of Work and this
Order. This covenant not to sue shall not take effect and shall
be rendered null and void in the event that the Settling Parties
fail to make all of the payments required of them by this Order.
Settling Parties are not released from liability, if any, for any
actions taken beyond the terms of this Order regarding removals,
other operable units, remedial design/remedial action of this
operable unit, or activities arising pursuant to Section 121(c)
Of CERCLA, 42 U.S.C. 9621(C).
Denial of Liability
67. By entering into this Order, or by taking any action in
accordance with it, the Settling Parties agree to be bound by all
-
-42
of the terms hereunder. However, the Settling Parties do not
admit any of the factual allegations, findings or legal
determinations contained in this Order or in the Statement of
Work. The Settling Parties do not admit any liability for any
purpose, nor do they admit or assume any liability for the
alleged release or threat of release of any hazardous substance,
pollutant or contaminant into the environment from the Site or
anywhere else.
68. The participation of any Settling Party in this Order shall
not be admissible in or used against any Settling Party in any
judicial or administrative proceeding or action, or used against
the Settling Parties as a collateral estoppel, except in an
action by EPA to enforce the terms of this Order, or in any
action to which EPA is a party which alleges an injury based on
the acts or omissions of the Settling Parties in connection with
this Order. However, the terms of this Order and the
participation of the Settling Parties shall be admissible in any
action or proceeeding brought by any Settling Parties to enforce
any contractual obligations imposed by any agremeent among the
Settling Parties.
EPA's Reservations of Rights
69. EPA reserves the right to bring an action against the
Settling Parties under Section 107 of CERCLA for recovery of: (i)
all past response costs incurred by the United States at the Site
-
-43
not reimbursed by the Settling Parties; (ii) any costs incurred
in the event that EPA performs all or a portion of the Ri/FS; and
(iii) any future costs incurred by the United States in
connection with response activities conducted under CERCLA at
this Site. EPA expressly reserves any and all rights and
defenses that it may have to enforce this Order against the
Settling Parties, including EPA's right under this Order both to
disapprove of work performed by the Settling Parties and to.
require that the Settling Parties perform tasks in addition to
those detailed in this Order. In addition, EPA reserves the
right to undertake actions under Section 104 of CERCLA, including
removal and/or remedial actions, at any time and to perform any
and all portions of the RI/FS which the Settling Parties fail to
perform to EPA's satisfaction. Except as expressly provided
herein, issuance of this Order shall not affect or limit in any
way any rights which EPA may have in relation to any liabilities
or obligations which the Settling Parties or other persons may be
subject to under CERCLA or other laws by virtue of any
connections that the Settling Parties or those other persons have
or may have had with the Site. EPA reserves any and all rights
to take any enforcement actio'n pursuant to CERCLA and/or any
other available legal authority, including the right to seek
injunctive relief, response costs, monetary penalties, and
punitive damages for any violation of law or this Order.
-
-44
70. EPA agrees not to file an action for recovery of $430,D47.75
in past direct and indirect costs covered by the Cost Recovery
Administrative Agreement, EPA CERCLA Docket 1-93-1079, provided
that the Settling Parties have fulfilled all of their obligations
under that Agreement.
71. Notwithstanding any other provision of this Order, EPA shall
retain all of its information, gathering, entry, inspection, and
enforcement authorities and rights under CERCLA and other any
.other applicable law, regulation, or permit.
?
Settling Parties/ Reservation of Rights
72. Except as otherwise provided in this Order, the Settling
Parties expressly reserve all rights, claims, demands and causes
of action they may have against any and all other persons and
entities who are not parties to this Order and as to each other
for matters not covered hereby. EPA recognizes that the Settling
Parties may have the right to seek contribution, indemnification,
or any other available remedy against any persons who may be
found responsible for or liable for contribution or indemnity or
otherwise for any amounts which have been or will be expended by
the Settling Parties in connection with the Site.
73. Notwithstanding any obligation in this Order requiring the
Settling Parties to make any records, documents or other
materials available to EPA, nothing herein shall be construed to
http:430,D47.75
-
-45
be a waiver of any rights a Settling Party may have to assert the
attorney-client or attorney work product privileges as to those
materials. However, no analytical information or information
specified in Section 104(e)(7)(F) of CERCLA shall be subject to
any such privilege.
Other Claims
74. Except as expressly provided herein, nothing in this Order
shall constitute or be construed as a release or covenant not to
sue regarding any claim, cause of action, or demand in law or
equity against any person, firm, trust, trustee, joint venture,
partnership, corporation, or other entity for any liability it
may have arising out of or relating in any way to the generation,
storage, treatment, handling, transportation, release/ or
disposal of any hazardous substances, hazardous wastes,
pollutants, or contaminants found at, taken to, or taken from the
Site. Except as expressly provided herein, this Order shall not
estop or limit any legal or equitable claims of the United States
against the Settling Parties, their agents, contractors, or
assigns, including, but not limited to, claims related to
releases of hazardous substances or other pollutants or
contaminants.
75. In consideration of the entry of this Order, the Settling
Parties agree not to assert any causes of action, claims, or
demands against the United States, including the Hazardous
-
-46
Substances Superfund or EPA (whether directly or as the United
States) for the costs of the RI/FS or any other costs incurred
pursuant to this Order. This Order does not constitute any
decision on preauthorization of funds under Section 111(a)(2) of
CERCLA. The Settling Parties further agree not to assert any
causes of action, claims, or demands against any "Hepartment or
agency of the United States for costs incurred by such department
or agency in performing oversight functions pursuant to a
cooperative agreement with EPA.
Indemnification
76. The United States does not assume any liability by entering
into this Order or by virtue of any designation of the Settling
Parties as EPA's authorized representatives. The Settling
Parties agree to indemnify and save and hold harmless the United
States Government and its agencies, departments, agents, offices,
employees, and representatives from any and all. claims or causes
of action arising from or on account of acts or omissions of the
Settling Parties, their officers, employees, agents, servants,
receivers, successors, trustees, assignees, or contractors in
carrying out the activities pursuant to this Order. The United
States shall not be held out as a party to, or in any other way
be held liable under, any contract entered into by the Settling
Parties or by the Contractor in carrying out the activities
pursuant to this Order.
-
-47
Waiyer of Settlement Conference
77. In consideration of the communications between the Settling
Parties and EPA, prior to the issuance of this Order concerning
its terms, Settling Parties hereby agree that there is no need
for a settlement conference prior to the effective date of this
Order.
Notice to the State and the Federal Natural Resource Trustees
78. Pursuant to the requirements of Sections 121 (f) and
104 (b) (2) of CERCLA, EPA has notified the State of Connecticut of
the scope of the response action, the negotiations with the
potentially responsible parties, and of the issuance of this
Order.
79. Pursuant to Section 122(j) of CERCLA, EPA has notified the
Federal Natural Resource Trustees of the scope of the response
action, the negotiations with the potentially responsible
parties, and of the issuance of this Order.
Modification of Order
80. This Order, with the exc