2
Program Office Updates• In July, the CTO organization, including the FDsys
program office was combined with the CIO organization.
Program Management
Technology Management
ITOperations
Project Management
Security
Former CTO group Former CIO group
New CIO group
Strategic Programs like FDsys are now tightly aligned with IT Infrastructure and Operations.
3
GPO Strategic System Initiatives
Business Information
Systems
Content Management
Systems
Digital Production
Systems
(FDsys, Composition System, ILS)
(Financial, HR) (Manufacturing Systems, Print on Demand)
IT Infrastructure and Operations
The CIO Organization is well positioned to support GPO’s Strategic System Initiatives.
4
Presentation Outline
• Project Overview and Status • FDsys Communications Update• Release 1C Development Update• Proof of Concept Demonstration• Questions and Answers
5
FDsys Communication Update
Working Groups• Office of the Clerk of the House• Office of the Secretary of the Senate• Interagency Council on Digital Content
Submission (ICDCS)
Presentations were given to over 30 federal agencies in 8 cities
6
FDsys Communication Update
Proof of Concept Demonstrations• Joint Committee on Printing• Office of the Clerk of the House• Office of the Secretary of the Senate• DC area librarians• Congressional Research Service• Office of the Federal Register• Interagency Council on Digital Content
Submission
7
Release 1B Beta Testing
9/26 – 10/10
Federal Depository Library Community
11/30 – 12/7
GPO Internal – Submission
12/10 – 12/17
Federal Agencies - Submission
8
Release 1C Development Update
• 1C is the first public release of FDsys
• Builds on the foundation established for 1B
9
Release 1C Development Update
• Will be rolled out in stages, or “increments”
• Each increment will introduce additional system functionality
10
Release 1C Development Update
• Release 1.C planning milestones accomplished
√ System Requirements Review (SRR)√ Initial requirements document – RD 3.1√ System Design Review (SDR)√ Feature sets approach√ Requirements fine tuning
11
Release 1C Development Update
• Future 1.C planning milestones
Delta SRR
Baseline for requirements – RD 3.2
Delta SDR
Baseline for system architecture
12
Release 1C Development Update
• So cut to the chase!
• What’s in the feature sets?
• What is the schedule?
13
Release 1C Development Update
• What’s in the feature sets?– Infrastructure– Package management/OAIS– GPO Access replacement– Metadata management (ILS)
14
Release 1C Development Update
• What else?– Congressional content submission– Persistent name– Agency content submission– Access and delivery
15
Release 1C Development Update
• First public release – late 2008
• Additional releases – 2009
• R1.B demo system will remain available
16
Release 1.B
• Proof of concept demonstration
• Content submission
• Access
17
Questions and Answers
• Contact us by email [email protected]