US Army Corps of Engineers BUILDING STRONG ® Temperature Target and Evaluation Criteria of the...
-
Upload
daniela-stokes -
Category
Documents
-
view
219 -
download
1
Transcript of US Army Corps of Engineers BUILDING STRONG ® Temperature Target and Evaluation Criteria of the...
US Army Corps of Engineers
BUILDING STRONG®
Temperature Target and Evaluation Criteria of the Middle Fork Willamette River
Dan Turner
Environmental Engineer
Portland
January 27, 2015
BUILDING STRONG®
PORTLAND DISTRICT2
Outline
Overview Operational Target update Evaluation Criteria Discussion Preliminary Alternative Analysis
Goal: elicit feedback in time to solidify operational target and evaluation criteria by 60% draft (due in March)
BUILDING STRONG®
PORTLAND DISTRICT3
Middle Fork Willamette
3 dams► Hills Creek► Lookout Point► Dexter
http://www.nwd-wc.usace.army.mil/nwp/teacup/willamette/
Big Cliff
Detroit
BUILDING STRONG®
PORTLAND DISTRICT4
Overview
Middle Fork Willamette Downstream Fish Passage and Water Quality / Temperature Control Alternatives Study
Temperature analysis based on water quality model scenarios
Temperature targets I need:► Operational target (aka model input target)► Alternative evaluation criteria
Continuation of previous meetings …
BUILDING STRONG®
PORTLAND DISTRICT5
Update: Operational Target Used to guide operations (either model or real) on a
specific day. Time variable, instantaneous temperature Sets a goal, like a rule curve Determines how much flow should be passed through
different outlets
BUILDING STRONG®
PORTLAND DISTRICT6
Update: Operational
Target
BUILDING STRONG®
PORTLAND DISTRICT7
Alternative Evaluation Criteria Used to evaluate temperature impacts after the fact. Should highlight important times and places Proposing using the percent of days not achieving (daily
mean temperature).
Use Date RangeImpact Type
criteria (°C)
criteria (°F) Reference
Migration May-01 to Jul-15 delay < 11.1 < 52.0 From sub-group, based on run timing and temperature
Holding May-01 to Sep-15 acute > 19.5 > 67.1 Approx. maximum ‘upstream mix’ calc. d/s Dexter (mean 19.8)
Holding May-01 to Sep-15 chronic > 16.0 > 60.8 ODEQ core cold water criteria
Spawning Sep-01 to Oct-15 acute > 15.6 > 60.1 Same as incubation
Spawning Sep-01 to Oct-15 chronic > 13.0 > 55.4 NFMS comment on 30% report; ODEQ spawning criteria
Incubation Sep-01 to Dec-31 acute > 15.6 > 60.1 From sub-group, based on experimentation (Taylor)
Incubation Sep-01 to Dec-31 chronic > 10.1 > 50.2 NFMS comment on 30%
Emergence Sep-20 plus 1750 ATUs early < ‘no dam’ calc. Standard reporting metric in annual report.
BUILDING STRONG®
PORTLAND DISTRICT8
Hills Creek Reservoir outflow
baseline data
Use Date Range Impact Type
criteria (deg. C)
criteria (deg. F)
% days not achieving criteria
Migration May-01 to Jul-15 delay < 11.1 < 52.0 100 (100 - 100)Holding May-01 to Sep-15 acute > 19.5 > 67.1 0 (0 - 0)Holding May-01 to Sep-15 chronic > 16.0 > 60.8 0 (0 - 16)Spawning Sep-01 to Oct-15 acute > 15.6 > 60.1 0 (0 - 100)Spawning Sep-01 to Oct-15 chronic > 13.0 > 55.4 67 (24 - 100)Incubation Sep-01 to Dec-31 acute > 15.6 > 60.1 0 (0 - 40)Incubation Sep-01 to Dec-31 chronic > 10.1 > 50.2 66 (49 - 75)Emergence Sep-20 plus 1750 ATUs -- -- -- Dec-08 (Nov-24 - Jan-05)
BUILDING STRONG®
PORTLAND DISTRICT9
Upstream Mix (‘no dam’) Calculation
‘Without Project’ estimate of temperature Function of:
► upstream temperature measurements► ratio of flow between tributaries► 0.11 °C / mile maximum warming► Assumptions that ungaged tributaries are insignificant
or similar to gaged tributaries
Based on Rounds 2010
BUILDING STRONG®
PORTLAND DISTRICT10
Hills Creek Reservoir outflow
upstream mix calculation
Use Date Range Impact Type
criteria (deg. C)
criteria (deg. F)
% days not achieving criteria
Migration May-01 to Jul-15 delay < 11.1 < 52.0 43 (3 - 88)Holding May-01 to Sep-15 acute > 19.5 > 67.1 0 (0 - 4)Holding May-01 to Sep-15 chronic > 16.0 > 60.8 18 (0 - 74)Spawning Sep-01 to Oct-15 acute > 15.6 > 60.1 0 (0 - 53)Spawning Sep-01 to Oct-15 chronic > 13.0 > 55.4 31 (0 - 89)Incubation Sep-01 to Dec-31 acute > 15.6 > 60.1 0 (0 - 20)Incubation Sep-01 to Dec-31 chronic > 10.1 > 50.2 33 (13 - 65)Emergence Sep-20 plus 1750 ATUs -- -- -- Feb-17 (Dec-17 - Apr-30)
BUILDING STRONG®
PORTLAND DISTRICT11
Dexter Reservoir outflow
baseline data
Use Date Range Impact Type
criteria (deg. C)
criteria (deg. F)
% days not achieving criteria
Migration May-01 to Jul-15 delay < 11.1 < 52.0 43 (0 - 74)Holding May-01 to Sep-15 acute > 19.5 > 67.1 0 (0 - 0)Holding May-01 to Sep-15 chronic > 16.0 > 60.8 10 (0 - 47)Spawning Sep-01 to Oct-15 acute > 15.6 > 60.1 91 (0 - 100)Spawning Sep-01 to Oct-15 chronic > 13.0 > 55.4 100 (100 - 100)Incubation Sep-01 to Dec-31 acute > 15.6 > 60.1 34 (0 - 47)Incubation Sep-01 to Dec-31 chronic > 10.1 > 50.2 70 (61 - 83)Emergence Sep-20 plus 1750 ATUs -- -- -- Nov-29 (Nov-19 - Dec-20)
BUILDING STRONG®
PORTLAND DISTRICT12
Dexter Reservoir outflow
upstream mix calculation
Use Date Range Impact Type
criteria (deg. C)
criteria (deg. F)
% days not achieving criteria
Migration May-01 to Jul-15 delay < 11.1 < 52.0 42 (16 - 74)Holding May-01 to Sep-15 acute > 19.5 > 67.1 5 (0 - 38)Holding May-01 to Sep-15 chronic > 16.0 > 60.8 54 (26 - 62)Spawning Sep-01 to Oct-15 acute > 15.6 > 60.1 36 (2 - 53)Spawning Sep-01 to Oct-15 chronic > 13.0 > 55.4 67 (49 - 82)Incubation Sep-01 to Dec-31 acute > 15.6 > 60.1 13 (1 - 20)Incubation Sep-01 to Dec-31 chronic > 10.1 > 50.2 35 (24 - 40)Emergence Sep-20 plus 1750 ATUs -- -- -- Feb-17 (Jan-07 - Apr-02)
BUILDING STRONG®
PORTLAND DISTRICT13
Evaluation locations
Middle Fork Willamette River:► Downstream Hills Creek► Downstream of Salt Creek confluence► Downstream of Salmon Creek confluence► Downstream of the North Fork of the Middle Fork
confluence► Upstream of Lookout Point Reservoir ► Downstream Dexter Dam
BUILDING STRONG®
PORTLAND DISTRICT14
Operational target v.
evaluation criteria
BUILDING STRONG®
PORTLAND DISTRICT15
Questions and Discussion
BUILDING STRONG®
PORTLAND DISTRICT16
Operations StructuresMinimum Power (%)
Max Lake Elevation (ft)
Scenario HCL LOP HCL LOP HCL LOP NotesnoBlend 100% 100% 1541 926 existing existing
base_lopSpillOnly 40% 40% 1541 926 existing no RO base rule curve; base with LOP spill, no RO usage
hclSpillwayWs1510 40% 40% 1510 926 Spillway existing HCL WS at max of 1510 to use spillway more effectively; LOP-DEX base rule curve; Spillway at HCL; 40% minimum power at HCL/LOP
hclFloat_pow1300_noHCLppmin
0% 40% 1541 926 float/lower outlet
existing Floating outlet at HCL; no HCL minimum power constraint; Lower outlet at 1300
hclFloat_pow1300_LopFloat_noppmin
0% 0% 1541 926 float/lower outlet
float Floating outlet at HCL; no HCL minimum power constraint; Lower outlet at 1300
Preliminary Alternatives
Each model scenario consists of three years: cool-wet, normal and hot-dry
BUILDING STRONG®
PORTLAND DISTRICT17
Hills Creek outflow:
noBlend current conditionspowerhouse outlet prioritized
Use Date Range Impact Type
criteria (deg. C)
criteria (deg. F)
% days not achieving criteria
Migration May-01 to Jul-15 delay < 11.1 < 52.0 100 (100 - 100)Holding May-01 to Sep-15 acute > 19.5 > 67.1 0 (0 - 0)Holding May-01 to Sep-15 chronic > 16.0 > 60.8 0 (0 - 0)Spawning Sep-01 to Oct-15 acute > 15.6 > 60.1 0 (0 - 0)Spawning Sep-01 to Oct-15 chronic > 13.0 > 55.4 69 (0 - 98)Incubation Sep-01 to Dec-31 acute > 15.6 > 60.1 0 (0 - 0)Incubation Sep-01 to Dec-31 chronic > 10.1 > 50.2 73 (65 - 78)Emergence Sep-20 plus 1750 ATUs -- -- -- Dec-05 (Dec-01 - Dec-12)
BUILDING STRONG®
PORTLAND DISTRICT18
Hills Creek outflow:
base_lopSpillOnly powerhouse and RO flow optimized to achieve operational target (minimum 40% RO flow)
Use Date Range Impact Type
criteria (deg. C)
criteria (deg. F)
% days not achieving criteria
Migration May-01 to Jul-15 delay < 11.1 < 52.0 100 (100 - 100)Holding May-01 to Sep-15 acute > 19.5 > 67.1 0 (0 - 0)Holding May-01 to Sep-15 chronic > 16.0 > 60.8 0 (0 - 0)Spawning Sep-01 to Oct-15 acute > 15.6 > 60.1 0 (0 - 0)Spawning Sep-01 to Oct-15 chronic > 13.0 > 55.4 60 (0 - 87)Incubation Sep-01 to Dec-31 acute > 15.6 > 60.1 0 (0 - 0)Incubation Sep-01 to Dec-31 chronic > 10.1 > 50.2 73 (65 - 78)Emergence Sep-20 plus 1750 ATUs -- -- -- Dec-05 (Dec-01 - Dec-12)
BUILDING STRONG®
PORTLAND DISTRICT19
Hills Creek outflow:
hclSpillwayWs1510Operate the spillway in additional the powerhouse and RO.
Hold pool elevation at 1510 ft (normal summer pool at 1541 ft)
Use Date Range Impact Type
criteria (deg. C)
criteria (deg. F)
% days not achieving criteria
Migration May-01 to Jul-15 delay < 11.1 < 52.0 64 (43 - 78)Holding May-01 to Sep-15 acute > 19.5 > 67.1 0 (0 - 0)Holding May-01 to Sep-15 chronic > 16.0 > 60.8 0 (0 - 7)Spawning Sep-01 to Oct-15 acute > 15.6 > 60.1 0 (0 - 0)Spawning Sep-01 to Oct-15 chronic > 13.0 > 55.4 33 (33 - 47)Incubation Sep-01 to Dec-31 acute > 15.6 > 60.1 0 (0 - 0)Incubation Sep-01 to Dec-31 chronic > 10.1 > 50.2 72 (69 - 75)Emergence Sep-20 plus 1750 ATUs -- -- -- Dec-15 (Dec-08 - Dec-25)
BUILDING STRONG®
PORTLAND DISTRICT20
Hills Creek outflow:
hclFloat_pow1300_LopFloat_noppmin
Hypothetical new structures that allow a ‘floating’ outlet and a new deep outlet at 1300 ft (1384 currently deepest)
Use Date Range Impact Type
criteria (deg. C)
criteria (deg. F)
% days not achieving criteria
Migration May-01 to Jul-15 delay < 11.1 < 52.0 50 (29 - 70)Holding May-01 to Sep-15 acute > 19.5 > 67.1 0 (0 - 0)Holding May-01 to Sep-15 chronic > 16.0 > 60.8 38 (31 - 43)Spawning Sep-01 to Oct-15 acute > 15.6 > 60.1 0 (0 - 0)Spawning Sep-01 to Oct-15 chronic > 13.0 > 55.4 33 (33 - 33)Incubation Sep-01 to Dec-31 acute > 15.6 > 60.1 0 (0 - 0)Incubation Sep-01 to Dec-31 chronic > 10.1 > 50.2 32 (32 - 45)Emergence Sep-20 plus 1750 ATUs -- -- -- Jan-08 (Dec-31 - Jan-16)
BUILDING STRONG®
PORTLAND DISTRICT21
Thermal blocks downstream of Hills Creek Dam
BUILDING STRONG®
PORTLAND DISTRICT22
0
2
4
6
8
10
12
14
16
18
0 2 4 6 8 10 12 14
Tem
pera
ture
(deg
C)
Distance upstream of LOP pool (miles)
May 23Current Condition
Temp Control Structure
Without Project
LOP Pool NF MF Willamette Salmon Cr. Salt Cr. HCR out
Thermal Block (<52 deg F)
BUILDING STRONG®
PORTLAND DISTRICT23
0
2
4
6
8
10
12
14
16
18
0 2 4 6 8 10 12 14
Tem
pera
ture
(deg
C)
Distance upstream of LOP pool (miles)
June 8Current Condition
Temp Control Structure
Without Project
LOP Pool NF MF Willamette Salmon Cr. Salt Cr. HCR out
Thermal Block (<52 deg F)
BUILDING STRONG®
PORTLAND DISTRICT24
0
2
4
6
8
10
12
14
16
18
0 2 4 6 8 10 12 14
Tem
pera
ture
(deg
C)
Distance upstream of LOP pool (miles)
June 23Current Condition
Temp Control Structure
Without Project
LOP Pool NF MF Willamette Salmon Cr. Salt Cr. HCR out
Thermal Block (<52 deg F)
BUILDING STRONG®
PORTLAND DISTRICT25
0
2
4
6
8
10
12
14
16
18
0 2 4 6 8 10 12 14
Tem
pera
ture
(deg
C)
Distance upstream of LOP pool (miles)
July 8Current Condition
Temp Control Structure
Without Project
LOP Pool NF MF Willamette Salmon Cr. Salt Cr. HCR out
Thermal Block (<52 deg F)
BUILDING STRONG®
PORTLAND DISTRICT26
0
2
4
6
8
10
12
14
16
18
0 2 4 6 8 10 12 14
Tem
pera
ture
(deg
C)
Distance upstream of LOP pool (miles)
Aug 23Current Condition
Temp Control Structure
Without Project
LOP Pool NF MF Willamette Salmon Cr. Salt Cr. HCR out
Thermal Block (<52 deg F)
BUILDING STRONG®
PORTLAND DISTRICT27
Mid Fork ds Salmon Cr:
noBlendcurrent conditionspowerhouse outlet prioritized
Use Date Range Impact Type
criteria (deg. C)
criteria (deg. F)
% days not achieving criteria
Migration May-01 to Jul-15 delay < 11.1 < 52.0 88 (71 - 100)Holding May-01 to Sep-15 acute > 19.5 > 67.1 0 (0 - 0)Holding May-01 to Sep-15 chronic > 16.0 > 60.8 0 (0 - 0)Spawning Sep-01 to Oct-15 acute > 15.6 > 60.1 0 (0 - 0)Spawning Sep-01 to Oct-15 chronic > 13.0 > 55.4 2 (0 - 98)Incubation Sep-01 to Dec-31 acute > 15.6 > 60.1 0 (0 - 0)Incubation Sep-01 to Dec-31 chronic > 10.1 > 50.2 71 (68 - 74)Emergence Sep-20 plus 1750 ATUs -- -- -- Dec-14 (Dec-09 - Dec-25)
BUILDING STRONG®
PORTLAND DISTRICT28
Mid Fork ds Salmon Cr:
hclSpillwayWs1510Operate the spillway in additional the powerhouse and RO.
Hold pool elevation at 1510 ft (normal summer pool at 1541 ft)
Use Date Range Impact Type
criteria (deg. C)
criteria (deg. F)
% days not achieving criteria
Migration May-01 to Jul-15 delay < 11.1 < 52.0 64 (43 - 76)Holding May-01 to Sep-15 acute > 19.5 > 67.1 0 (0 - 0)Holding May-01 to Sep-15 chronic > 16.0 > 60.8 0 (0 - 7)Spawning Sep-01 to Oct-15 acute > 15.6 > 60.1 0 (0 - 0)Spawning Sep-01 to Oct-15 chronic > 13.0 > 55.4 27 (11 - 31)Incubation Sep-01 to Dec-31 acute > 15.6 > 60.1 0 (0 - 0)Incubation Sep-01 to Dec-31 chronic > 10.1 > 50.2 69 (58 - 72)Emergence Sep-20 plus 1750 ATUs -- -- -- Dec-28 (Dec-18 - Jan-09)
BUILDING STRONG®
PORTLAND DISTRICT29
Mid Fork ds Salmon Cr:
hclFloat_pow1300_LopFloat_noppmin
Hypothetical new structures that allow a ‘floating’ outlet and a new deep outlet at 1300 ft (1384 currently deepest)
Use Date Range Impact Type
criteria (deg. C)
criteria (deg. F)
% days not achieving criteria
Migration May-01 to Jul-15 delay < 11.1 < 52.0 55 (41 - 72)Holding May-01 to Sep-15 acute > 19.5 > 67.1 0 (0 - 0)Holding May-01 to Sep-15 chronic > 16.0 > 60.8 28 (17 - 36)Spawning Sep-01 to Oct-15 acute > 15.6 > 60.1 0 (0 - 0)Spawning Sep-01 to Oct-15 chronic > 13.0 > 55.4 29 (22 - 31)Incubation Sep-01 to Dec-31 acute > 15.6 > 60.1 0 (0 - 0)Incubation Sep-01 to Dec-31 chronic > 10.1 > 50.2 32 (31 - 33)Emergence Sep-20 plus 1750 ATUs -- -- -- Jan-18 (Jan-10 - Jan-27)
BUILDING STRONG®
PORTLAND DISTRICT30
Middle Fork Willamette downstream of Dexter Dam
BUILDING STRONG®
PORTLAND DISTRICT31
Mid Fork ds Dexter Dam:
noBlendcurrent conditionspowerhouse outlet prioritized
Use Date Range Impact Type
criteria (deg. C)
criteria (deg. F)
% days not achieving criteria
Migration May-01 to Jul-15 delay < 11.1 < 52.0 58 (46 - 79)Holding May-01 to Sep-15 acute > 19.5 > 67.1 0 (0 - 0)Holding May-01 to Sep-15 chronic > 16.0 > 60.8 0 (0 - 9)Spawning Sep-01 to Oct-15 acute > 15.6 > 60.1 67 (18 - 100)Spawning Sep-01 to Oct-15 chronic > 13.0 > 55.4 100 (100 - 100)Incubation Sep-01 to Dec-31 acute > 15.6 > 60.1 25 (7 - 38)Incubation Sep-01 to Dec-31 chronic > 10.1 > 50.2 72 (69 - 76)Emergence Sep-20 plus 1750 ATUs -- -- -- Nov-29 (Nov-26 - Dec-03)
BUILDING STRONG®
PORTLAND DISTRICT32
Mid Fork ds Dexter Dam:
base_lopSpillOnly powerhouse and RO flow optimized to achieve operational target (minimum 40% RO flow)
Use Date Range Impact Type
criteria (deg. C)
criteria (deg. F)
% days not achieving criteria
Migration May-01 to Jul-15 delay < 11.1 < 52.0 51 (4 - 70)Holding May-01 to Sep-15 acute > 19.5 > 67.1 0 (0 - 0)Holding May-01 to Sep-15 chronic > 16.0 > 60.8 40 (31 - 44)Spawning Sep-01 to Oct-15 acute > 15.6 > 60.1 40 (38 - 42)Spawning Sep-01 to Oct-15 chronic > 13.0 > 55.4 98 (84 - 100)Incubation Sep-01 to Dec-31 acute > 15.6 > 60.1 15 (14 - 16)Incubation Sep-01 to Dec-31 chronic > 10.1 > 50.2 71 (68 - 74)Emergence Sep-20 plus 1750 ATUs -- -- -- Dec-07 (Dec-02 - Dec-12)
BUILDING STRONG®
PORTLAND DISTRICT33
Mid Fork ds Dexter Dam:
hclSpillwayWs1510HCR: operate the spillway in additional the powerhouse and RO. Hold pool elevation at 1510 ft.
LOP: 40% min. power (base)
Use Date Range Impact Type
criteria (deg. C)
criteria (deg. F)
% days not achieving criteria
Migration May-01 to Jul-15 delay < 11.1 < 52.0 50 (25 - 72)Holding May-01 to Sep-15 acute > 19.5 > 67.1 0 (0 - 0)Holding May-01 to Sep-15 chronic > 16.0 > 60.8 39 (25 - 53)Spawning Sep-01 to Oct-15 acute > 15.6 > 60.1 36 (24 - 49)Spawning Sep-01 to Oct-15 chronic > 13.0 > 55.4 71 (69 - 71)Incubation Sep-01 to Dec-31 acute > 15.6 > 60.1 13 (9 - 18)Incubation Sep-01 to Dec-31 chronic > 10.1 > 50.2 72 (68 - 75)Emergence Sep-20 plus 1750 ATUs -- -- -- Dec-11 (Dec-05 - Dec-18)
BUILDING STRONG®
PORTLAND DISTRICT34
Mid Fork ds Dexter Dam: hclFloat_pow1300_LopFloat_noppminHCR: Hypothetical new structures that allow a ‘floating’ outlet and a new deep outlet at 1300 ft (1384 currently deepest) LOP: base
Use Date Range Impact Type
criteria (deg. C)
criteria (deg. F)
% days not achieving criteria
Migration May-01 to Jul-15 delay < 11.1 < 52.0 46 (1 - 66)Holding May-01 to Sep-15 acute > 19.5 > 67.1 0 (0 - 0)Holding May-01 to Sep-15 chronic > 16.0 > 60.8 43 (38 - 55)Spawning Sep-01 to Oct-15 acute > 15.6 > 60.1 40 (38 - 44)Spawning Sep-01 to Oct-15 chronic > 13.0 > 55.4 71 (69 - 100)Incubation Sep-01 to Dec-31 acute > 15.6 > 60.1 15 (14 - 17)Incubation Sep-01 to Dec-31 chronic > 10.1 > 50.2 68 (64 - 70)Emergence Sep-20 plus 1750 ATUs -- -- -- Dec-12 (Dec-06 - Dec-18)
BUILDING STRONG®
PORTLAND DISTRICT35
Mid Fork ds Dexter Dam: hclFloat_pow1300_LopFloat_noppmin
HCR and LOP:temperature control structures.
Use Date Range Impact Type
criteria (deg. C)
criteria (deg. F)
% days not achieving criteria
Migration May-01 to Jul-15 delay < 11.1 < 52.0 12 (0 - 53)Holding May-01 to Sep-15 acute > 19.5 > 67.1 30 (24 - 42)Holding May-01 to Sep-15 chronic > 16.0 > 60.8 60 (54 - 65)Spawning Sep-01 to Oct-15 acute > 15.6 > 60.1 40 (40 - 44)Spawning Sep-01 to Oct-15 chronic > 13.0 > 55.4 69 (67 - 69)Incubation Sep-01 to Dec-31 acute > 15.6 > 60.1 15 (15 - 17)Incubation Sep-01 to Dec-31 chronic > 10.1 > 50.2 63 (47 - 68)Emergence Sep-20 plus 1750 ATUs -- -- -- Dec-23 (Dec-14 - Dec-31)
BUILDING STRONG®
PORTLAND DISTRICT36
Discussion