US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District.

7
US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District

Transcript of US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District.

Page 1: US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District.

US Army Corps of Engineers Budgeting Process

Sherry L. Adams

Project Manager, Huntington District

Page 2: US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District.

“High Priority” Missions: Flood Damage Reduction Commercial Navigation Ecosystem Restoration

Beach Erosion/Hurricane ProtectionFlooding

Navigation

Environmental Infrastructure Needs

Water Supply

Lock / Dam Replacement - Inland Waterways System

Salmon Mitigation

Ecosystem Restoration

Port / Harbor Deepenings

Waterfront Development

Environmental Infrastructure Needs

Environ. Restoration

Wetland Losses

Letter to Corps District OfficeLetter to Corps District Office

Inform Congressional RepresentativeInform Congressional Representative

Page 3: US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District.

Senate Resolution House Resolution

Authority - Congress! Study Resolutions WRDA Bills Standing Authorities Appropriations Bills

OR

- Signed by President

Transportation & Infrastructure

Committee

Environment & Public Works

Committee

MemberMember( Step 1 )

Passage ~ 2-yr. Intervals

Have we studied

the problem before?

Page 4: US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District.

President’s Budget ( G I )

HQUSACE

DIVISION

(Step 2 )

“High Priority” Missions

Flood Damage Reduction Navigation Ecosystem Restoration

WRDA

HR/SR

Coordination

Budget Cycle 1/

Page 5: US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District.

HQ Provides Budget Guidance ( Mar )

HQ Review & Approval

( May -Jun )

Budget Presented to Sec. Army(Jul - Aug )

OMB Passback( Nov )

Budget Submitted to OMB ( Sep )

President’s Budgetto Congress ( Feb )

Field Offices DevelopProgram Requirements

( Apr - May )

Appropriations Bills( Jul - Sep )

Cong. Hearings ( Mar - Apr )

President Signs Approp. Bill ( Sep - Oct )

OMB Provides Budget Guidance ( Jan )

Funding Alloc. To Field Offices

( Oct - Dec )

Page 6: US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District.

• Projects with smaller scope, cost and complexity

• Delegated authority to design and construct without specific Congressional authorization

Continuing Authority Program (CAP)

Page 7: US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District.

Existing CAP Funding Policies

• Complete existing construction projects

• No new project cooperation agreements

• Congressional authorization for start or continuation of study (Naming or earmark)