U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

36
U.S. 30 Benton County Public Information Meeting 9/14/11 1 U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

description

U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011. Meeting Purpose & Goals. Project Description Meeting Goals Provide Update Incorporated feedback from last meeting Additional work completed Discuss / Obtain Input On Alignments - PowerPoint PPT Presentation

Transcript of U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

Page 1: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 1

U.S. 30 Corridor - Benton CountyPublic Information Meeting

September 14, 2011

Page 2: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 2

Meeting Purpose & Goals• Project Description• Meeting Goals– Provide Update• Incorporated feedback from last meeting• Additional work completed

– Discuss / Obtain Input On Alignments• Short description during presentation• Opportunity to review displays and ask questions• Intent as last formal public input opportunity prior to

environmental document decision.

Page 3: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 3

Meeting Purpose & Goals, continued• Meeting Goals, continued– Discuss / Obtain Input On Interchange Concepts

• Short description during presentation• Opportunity to review displays and ask questions• Intent as last formal public input opportunity for IA 21• U.S. 218 may require additional review processes

– Present / Obtain Input On Access Layout– Discuss Next Steps and Schedule– Answer YOUR Questions, Address YOUR Concerns

• Please hold questions until end of presentation– Use open house format for additional exhibit displays

and staff available for discussion

Page 4: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 4

Updates• Updates Provided Tonight…….– Includes• Input from previous meeting reviewed and considered• Information requested at previous meeting

– Adjustments to Alternatives 1 & 3– Alternative 2 not carried forward– New U.S. 218 Interchange Alternative– Access points (driveway and roads) now shown

Page 5: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 5

Updates, continued• Adjustments to Alternatives 1 & 3– Slight shift in Alternative 1 alignment east of 19th

Ave / V56

Page 6: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 6

Updates, continued• Alternative 2 not carried forward– Two new lanes added to north where feasible– Shifted to south from west of 19th Ave to east end

of project• Avoid cemetery• Match existing alignment at U.S. 218• Almost 1/3 of project length

– Impacted potential historic property– Construction more complicated / expensive– Fewest public comments in support of

Page 7: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 7

Updates, continued• New U.S. 218 Interchange Alternative– At existing U.S. 218 alignment– Smaller farm ground impacts– Potential impacts to decision processes and

schedule• Access points (driveway and roads) now

shown

Page 8: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 8

Alignment Alternatives• Alignment 1

– Two new lanes on south side– Maintain north right of way line

• Avoid or minimize property takings on north side other than at intersections / interchanges

• Minimize total number of parcels impacted– Avoids impacts to potentially historic properties and Calvary

Cemetery• Alignment 3

– Two new lanes on south side– Reconstructed lanes generally along existing alignment– Requires property takings on both sides– Public perception of smaller farm land impacts – Shift to south near historic property & cemetery

Page 9: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 9

Alignment Alternatives, continuedAlternative Alignment 1

Page 10: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 10

Alignment Alternatives, continuedAlternative Alignment 3

Page 11: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 11

Alignment Comparison• Differences now less than previous proposal– Alternative 1 shifted north (closer to existing roadbed east

of 19th Ave– Alignments for Alternative 1 and 3 now identical for

eastern approximately 3 miles• Total Impacts to farm land nearly the same– Alternative has slightly higher calculated land impacts– Currently estimated at less than 3 acres difference along

the approximately 14 mile corridor– Probably consider as equal impacts

• Alternative 3 impacts properties on both sides (in addition to intersection / interchange requirements)

Page 12: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 12

Alignment Comparison, continued• Costs, traffic characteristics similar• Alternative 1 may provide more flexibility for

construction (more room to build new lanes and maintain old)

• Alternative 3 had higher number of positive comments at last public meeting

• Final design refinements likely to lessen differences– Adjustment to minimize costs and impacts– Potential to become some hybrid of the two

Page 13: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 13

Alignment Alternatives, continued– “Real world” examples• Application of alternatives to specific locations• Illustrative only

Page 14: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 14

Alignment Alternatives, continued

Illustrative Example

Not intended as final acquisition lines

Page 15: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 15

Alignment Alternatives, continued

Illustrative Example

Not intended as final acquisition lines

Page 16: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 16

Alignment Alternatives, continued

Illustrative Example

Not intended as final acquisition lines

Page 17: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 17

Alignment Alternatives, continued

Illustrative Example

Not intended as final acquisition lines

Page 18: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 18

Alignment Alternatives, continued

Illustrative Example

Not intended as final acquisition lines

Page 19: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 19

Alignment Alternatives, continued

Illustrative Example

Not intended as final acquisition lines

Page 20: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 20

Alignment Alternatives, continued

Illustrative Example

Not intended as final acquisition lines

Page 21: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 21

Alignment Alternatives, continued

Illustrative Example

Not intended as final acquisition lines

Page 22: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 22

Alignment Alternatives, continued

Illustrative Example

Not intended as final acquisition lines

Page 23: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 23

Interchange Concepts• U.S. 30 / IA 21– Both Diamond Interchanges– Option 1 – U.S. 30 over IA 21– Option 2 – IA 21 over U.S. 30– Same as last meeting

Page 24: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 24

Interchange Concepts, continued• U.S. 30 / IA 21 – Options 1 & 2

Page 25: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 25

Interchange Concepts, continued• U.S. 30 / U.S. 218– Option 1 – Folded Diamond, U.S. 218 relocated to

west– Option 2 – Diamond, U.S. 218 relocated to west– Option 3 – Single loop, , U.S. 218 relocated to west– Option 4 – “Parclo B” (2 exit loops), U.S. 218 on

existing alignment

Page 26: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 26

Interchange Concepts, continued• U.S. 30 / U.S. 218 – Option 1

Page 27: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 27

Interchange Concepts, continued• U.S. 30 / U.S. 218 – Option 2

Page 28: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 28

Interchange Concepts, continued• U.S. 30 / U.S. 218 – Option 3

Page 29: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 29

Interchange Concepts, continued• U.S. 30 / U.S. 218 – Option 4

Page 30: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 30

Access• Specific drives not previously shown at public

input meetings• Previous approach slightly modified– Previously proposed full access points to be

allowed every ½ mile and limited (right in / right out) access allowed approximately every ¼ mile

– Full Versus Limited

Page 31: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 31

Access, continuedRight In / Right out Access

Page 32: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 32

Access, continued• Reviewed Access Control– Goal = Full Access every ½ mile, right in / right out allowed

at ¼ spacing– Very few locations with right in / right out– Safety impacts of allowing full access not significant

• NOW – Proposing to allow some exceptions– A couple locations with FULL access at less than ½ mile

spacing– Existing Residential/Commercial Drives– Not intending to allow exceptions for field entrances– Exceptions not planned for new access points at less than

½ spacing

Page 33: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 33

Next Steps• Review input received from public input meeting• Presentation to DOT management

– Selection of recommended alignment and IA 21 alternative– Initial discussion on U.S. 218 alternatives

• Field studies & report for additional study area near US 218• State Historical Preservation Office concurrence• Selection of recommended U.S. 218 alternative• Public Hearing on Preferred Alternative• Approval of Environmental Document• Preliminary / Final Design• Right of Way Acquisition• Construction Funding• Construction

Page 34: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 34

Schedule• Field Studies – Fall 2011• SHPO Concurrence – Spring 2012• Public Hearing – Spring / Summer 2012– Unable to share recommendations prior to meeting– Present preferred alternative– Potential spring planting conflict versus schedule

• Environmental Document Approval – Summer 2012

• Right of Way Acquisition start – 2014 / 2015• Construction start – dependant on funding

Page 35: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 35

U.S. 30 Corridor – Benton CountyPublic Information Meeting

Questions?Website http://www.iowadot.gov/pim/index.html

Catherine [email protected] 319-364-0235

Page 36: U.S. 30 Corridor - Benton County Public Information Meeting September 14, 2011

U.S. 30 Benton County Public Information Meeting9/14/11 36

Reconstruction of Existing Roadbed• Existing underlying pavement is in poor shape. • Provides an opportunity to correct vertical

alignment / sight distance• Ability to reconstruct bridges to current standards

and provide full shoulders• Allows adjustments to the horizontal alignments

and slopes adjacent to the pavement.• Improved snow storage / reduced drifting• Old roadbed will be reused in project.