Urban Transport Develop. Project Greater Beirut Area (GBA)

21
For Greater Beirut Area Workshop on Urban Transport In the Mediterranean Region January 23 rd 2008 By Elie Helou Council for Development & Reconstruction (Beirut – Lebanon)

description

Urban Transport Development Project For Greater Beirut Area Workshop on Urban Transport In the Mediterranean Region January 23 rd 2008 By Elie Helou Council for Development & Reconstruction (Beirut – Lebanon). Urban Transport Develop. Project Greater Beirut Area (GBA). - PowerPoint PPT Presentation

Transcript of Urban Transport Develop. Project Greater Beirut Area (GBA)

Page 1: Urban Transport Develop. Project Greater Beirut Area (GBA)

Urban Transport Development Project For Greater Beirut Area

Workshop on Urban Transport

In the Mediterranean Region

January 23rd 2008

By Elie HelouCouncil for Development & Reconstruction (Beirut – Lebanon)

Page 2: Urban Transport Develop. Project Greater Beirut Area (GBA)

Urban Transport Develop. ProjectGreater Beirut Area (GBA)

Antelias

Mkales

Hayek

Dora

Mucharafieh

Barbir

Khalde

Sayad 1.3 million Inhabitants 1.5 Mil. motorized trips

1.2/pers. in 1970 vs. 0.76/pers. Less than 10% served by Public Transport Low Vehicle occupancy 1.6 pers./car 50% of households own 1 car, 25% own at

least 2 cars

Page 3: Urban Transport Develop. Project Greater Beirut Area (GBA)

27%42%

31% 25% - 50%

15% - 25%

<15%

GBA In Travel timesSpeed / Delay of 27 routes

Intersection operation is the main cause of delay

26%48%

26% 30 Kph - 20 Kph

20 Kph - 10 Kph

<10 Kph

Delay % of travel time

Speed

Page 4: Urban Transport Develop. Project Greater Beirut Area (GBA)

4

GBA Intersection Performance

Page 5: Urban Transport Develop. Project Greater Beirut Area (GBA)

GBA Parking & Pedestrians

Page 6: Urban Transport Develop. Project Greater Beirut Area (GBA)

Urban Transport Development Project

Reducing congestion and streamlining mobility and safety on GBA road network

Re-establishing the 3 E’s (Engineering, Enforcement, Education)

UTDP components: Traffic Management Grade Separations at 19 intersections Parking Management (On-street / Off-street) Public Awareness campaign Traffic police training - enforcement strengthening

Page 7: Urban Transport Develop. Project Greater Beirut Area (GBA)

Urban Transport Development Project Preparation

Preliminary & Final design Economical Analysis Environmental study

Pollution assessment Archeological Assessment Social Assessment Resettlement plan

Public consultations with stakeholders

Page 8: Urban Transport Develop. Project Greater Beirut Area (GBA)

Urban Transport Development ProjectCost & Components

Total Cost 200 MUSD Cost by components:

35 MUSD Traffic Management 148 MUSD Grade Separations at 19 intersections 9 MUSD On-Street Parking Management 3.5 MUSD Public Transport studies 0.4 MUSD Public Awareness campaign 3.6 MUSD Traffic police training - enforcement

strengthening

Page 9: Urban Transport Develop. Project Greater Beirut Area (GBA)

Funds available 150 MUSD as follows: World Bank 65 MUSD AFESD 18 MUSD ADFD 10 MUSD ISDB 10 MUSD KFAED 7 MUSD GOL 25 MUSD Construction + 15 MUSD Expropriation

Funds under request 25 MUSD Gap in funding 25 MUSD

Urban Transport Development Project Funding

Page 10: Urban Transport Develop. Project Greater Beirut Area (GBA)

UTDP - Traffic management Location of Traffic signals

Creation of Traffic Management Organization

Construction started in 2005 Building a traffic control center Installation of approx. 30 surveillance

cameras Installation of 220 signals Paving, striping, signing Due for completion by Dec. 2008

Page 11: Urban Transport Develop. Project Greater Beirut Area (GBA)

Traffic Management OrganizationTMO

HRD and TrainingParking

EnforcementRegulation & Analysis

ESTABLISHING A TRAFFIC MANAGEMENT ORGANIZATION

Minister of Interior and Municipalities

President

Director General

Board of Directors

Legal Advisor

Operation & Maintenance

On-Street Parking Division

Tutelage

Common Services Division

Traffic Engineering

Division

Studies & Design

Accounting MetersInformation

& Public Relations

Violations & Database

Page 12: Urban Transport Develop. Project Greater Beirut Area (GBA)

TMO BuildingTraffic Management Center

Page 13: Urban Transport Develop. Project Greater Beirut Area (GBA)

SIGNAL CONTROL

RAMP METERING

ELECTRONIC TOLL COLLECTION

PUBLIC TRANSPORTATION

ENVIRONMENTAL MONITORING

PARKING GUIDANCE

VARIABLE MESSAGE SIGNING

VIDEO SURVEILLANCE (CCTV)

INITIAL SYSTEM

DRIVER INFORMATION CONTROL CENTER

UTDP TMO Transportation Functions

Page 14: Urban Transport Develop. Project Greater Beirut Area (GBA)

UTDP - Grade Separations Location map

Chiah BlvdNorthernEntrance

Mkales

Hayek

Sodeco

Airport Rd

Mazraa Blvd

Old Saida Rd Construction of 12 overpasses & 8 underpasses at 19 heavily congested intersections in GBA

Construction started in 2005 for 6 years. Environmental monitoring during and after

construction 2 locations completed 7 locations under construction 3 Locations to be launched in 2008

Page 15: Urban Transport Develop. Project Greater Beirut Area (GBA)

UTDP - Grade SeparationsCompleted

LocationHayek

Traffic served 8791 v/ph

Avg. Delay14min

Page 16: Urban Transport Develop. Project Greater Beirut Area (GBA)

UTDP - Grade SeparationsIn Progress

Traffic served 11568 v/phAvg. Delay

11min

Traffic served 6580 v/phAvg. Delay

9min

Page 17: Urban Transport Develop. Project Greater Beirut Area (GBA)

UTDP On-Street Parking Program

Short term goal, Management of On-street parking

Installation of paid parking system for about 6000 curbside parking spaces

Construction started 2006 Development of regulations and policies Long term goal : Encourage private sector

to invest in off-street parking structures

Page 18: Urban Transport Develop. Project Greater Beirut Area (GBA)

UTDP – On-Street Paid Parking ProgramPay & Display Parking Meters

Display Ticket on dashboard

Purchase ticket at the Pay & Display Machine.1hr = 0.66 USD

Page 19: Urban Transport Develop. Project Greater Beirut Area (GBA)

UTDP Public Awareness Campaign

Page 20: Urban Transport Develop. Project Greater Beirut Area (GBA)

UTDP Conclusion

UTDP will solve yesterday’s problems. It will not create substantial corridor

capacity rather streamline mobility Other planned highways such as

Peripherique & its extension to the north are required in the immediate term.

The future is Public Transport

Page 21: Urban Transport Develop. Project Greater Beirut Area (GBA)

Beyond UTDPPublic Transport Network